Table of contents

 

4      Noise Impact Assessment.. 4-1

4.1         Introduction. 4-1

4.2         Environmental Legislation, Standards and Guidelines. 4-1

4.3         Descriptions of Environment 4-6

4.4         Identification of Potential Noise Impact 4-6

4.5         Noise Sensitive Receivers. 4-6

4.6         Assessment Methodology, Prediction and Evaluation of Environmental Impacts. 4-7

4.7         Evaluation and Recommendation of Noise Mitigation Measures. 4-16

4.8         Evaluation of Residual Impacts. 4-20

4.9         Environmental Monitoring and Audit Requirements. 4-21

4.10       Conclusion. 4-21

 

 

 

4               NOISE IMPACT ASSESSMENT

4.1               Introduction

4.1.1        This Chapter presents an assessment of the potential noise impact arising from the construction and operation of the Project. Mitigation measures have been identified to alleviate the impact and their effectiveness has been evaluated.  

4.2              Environmental Legislation, Standards and Guidelines

    Construction Noise

4.2.1        The Noise Control Ordinance (NCO) (Cap. 400) provides the statutory framework for noise control in Hong Kong. Assessment procedures and standards are set out in the respective Technical Memoranda (TM) promulgated under the NCO.  The following TMs are applicable to the assessment and control of construction noise.

·            Technical Memorandum on Noise from Construction Work other than Percussive Piling (TM-GW);

·             Technical Memorandum on Noise from Percussive Piling (TM-PP); and

·             Technical Memorandum on Noise on Construction Work in Designated Areas (TM-DA)

·            Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites (TM-IND)

4.2.2        Both the percussive piling and construction work under restricted hours require a construction noise permit (CNP) in order to carry out such work. As the issuance of a CNP by the Noise Control Authority would depend on the compliance of percussive piling noise impact or construction noise impact with the limits set out within the TM-PP and TM-GW/TM-DA, the assessment of this type of noise would not be covered in the EIA report.

4.2.3        For construction, there is no statutory limit on daytime construction noise under the NCO and related TMs.  Nevertheless, the Technical Memorandum on Environmental Impact Assessment Process” (EIAO-TM) stipulates noise standards for daytime construction activities, as shown Table 4-1.  

Table 4-1: Construction Noise Standards during Non-Restricted Hours

Uses

Noise Standards [1] , Leq (30 mins) dB(A)

0700 to 1900 hours

on any day not being a Sunday or general holiday

1900 to 0700 hours

or any time on Sundays or general holiday

All domestic premises including temporary housing accommodation

75

(See Note 2)

Hotels and hostels

75

Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required

70

65 (During examinations)

Notes:

[1]     The above standards apply to uses that rely on opened windows for ventilation.

[2]     The criteria laid down in the relevant technical memoranda under the NCO for designated areas and construction works other than percussive piling may be used for planning purpose. A Construction Noise Permit (CNP) shall be required for the carrying out construction work during the period.


    Construction Noise during Restricted Hours

4.2.4        The NCO provides statutory control on general construction works (excluding percussive piling) conducted during restricted hours (i.e. 1900 to 0700 hours (of the next day) from Monday to Saturday and at any time on Sundays or in public holidays). A Construction Noise Permit (CNP) is required for carrying out of any general construction activities involving the use of any Powered Mechanical Equipment (PME) within restricted hours from the Authority under the NCO. The noise criteria and the assessment procedures for issuing a CNP are specified in the TM-GW under the NCO.

4.2.5        The use of Specified PME (SPME) and/or the undertaking of Prescribed Construction Work (PCW) within a Designated Area (DA) under the NCO during the restricted hours are controlled by the TM-DA. The relevant technical details in Technical Memorandum on Noise from Construction Work in Designated Areas (TM-DA) under NCO can be referred. The acceptable noise levels for construction during the restricted hours are summarized in Table 4-2 below.

Table 4-2:  Construction Noise Standards during Restricted Hours

Uses

Acceptable Noise Level for Area Sensitive Ratings, dB(A)

A

B

C

All weekdays during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the day and evening (0700 to 2300 hours)

60

65

70

All days during the night-time (2300 to 0700 hours)

45

50

55

4.2.6        The Area Sensitive Rating depends on the type of area and the degree of impact that Influencing Factors (IFs) have on the NSRs and is determined from Table 4-3 below. Industrial area, major road or the area within the boundary of Hong Kong International Airport shall be considered to be an IF.

Table 4-3: Area Sensitivity Ratings (ASRs)

Type of Area containing NSR

Degree to which NSR is affected by IF

Not Affected

Indirectly Affected

Directly Affected

(i) Rural area, including country parks or village type developments

A

B

B

(ii) Low density residential area consisting of low-rise or isolated high-rise developments

A

B

C

(iii) Urban area

B

C

C

(iv) Area other than those above

B

B

C

4.2.7        According to the preliminary construction programme, it is very likely that the proposed construction works would be carried out during non-restricted hours only. For carrying out any general construction activity involving the use of any Powered Mechanical Equipment (PME) within restricted hours, a Construction Noise Permit (CNP) is required from the authority under the NCO. The noise criteria and the assessment procedures for issuing the CNP are specified in the TM-GW under the NCO. There is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a well justified CNP application, once filed, for construction work within restricted hours as guided by the relevant TMs issued under the NCO. It is the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs in case of any construction activities during restricted hours.

4.2.8        The Noise Control Ordinance (NCO) and Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) were followed for assessing the noise from powered mechanical equipment (PME) for different sensitive uses.

 

Construction Ground-Borne Noise

4.2.9        According to the TM-GW, the Area Sensitivity Rate of the area in which the identified NSRs are located is “A”. Moreover, the TM-IND under NCO mentioned that where the noise under investigation is transmitted primarily through the structural elements of the building or if the assessment point is at an internal location of a building, an adjustment of -10 dB(A) should be made to relevant acceptable noise levels (ANLs). The relevant noise limits for ground-borne noise are tabulated in Table 4-4.

Table 4-4 Ground-borne Construction Noise Limits

Time Period

Uses

Noise Standard

(Leq, 30 min dB(A))

(1)Day-time

Domestic Premises

65

Educational institutions (normal periods)

60

Educational institutions (during examination periods)

55

(1)Evening-time

All Noise Sensitive Uses

50

(1)Night-time

All Noise Sensitive Uses

35

(1)      assessment point is at a particular internal location

 

Operational Noise

4.2.10    Noise from the proposed sewage treatment plant (STP) is considered as the only fixed noise source during the operation phase of the Project. Operational noise is controlled under the Noise Control Ordinance (NCO)’s Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites (TM-IND).

4.2.11    According to the TM-IND, appropriate Area Sensitivity Ratings should be determined for the NSRs under consideration from Table 1 of the TM-IND. Then, the appropriate Acceptable Noise Level (ANL) for a given NSR and the time period under consideration could be read from Table 3 of TM-IND. According to the TM-IND, the ANLs for different Area Sensitivity Ratings (ASRs) of noise sensitive receivers (NSRs) are given in Table 4-5.

Table 4-5 Acceptable Noise Levels

Time Period

ASR A

ASR B

ASR C

All days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the day-time and evening (0700 to 2300 hours)

60

65

70

All days during the night-time (2300 to 0700 hours)

50

55

65

4.2.12    More stringent criteria for fixed plant noise impacts recommended in Table 1A of the EIAO-TM for planning purposes are as follow:

·         5 dB(A) below the appropriate ANL set out in the TM-IND (the ANL–5 dB(A) criterion), or

·         The prevailing background noise level where the prevailing background noise level is 5 dB(A) below the appropriate ANL (although during the operation the NCO will be the controlling legislation).

4.2.13    In this Project, the study area covering 300m from the proposed works boundary (as shown in Figure 4-1) is identified as rural area consisting village type developments without being affected by IF thus the NSRs are assigned an Area Sensitive Rating of “A”.

4.2.14    In order to determine the appropriate criteria for noise assessment, background noise survey was carried out during the course of the EIA process at two locations to determine the baseline noise levels. Noise monitoring was conducted for 14 consecutive days in November 2014. Locations of the monitoring stations are summarised in Table 4-6 and shown on Figure 4-1. For those sensitive receivers which were found to experience prevailing noise levels lower than the ANL-5dB(A) criterion, fixed plant noise impact were assessed against the prevailing background noise levels.

Table 4-6  Background Noise Monitoring Results at Selected NSRs in Po Toi O

Time Period

Measurement Parameter

Noise Level (dB(A))

NM1 - Near Local Resident

NM2 - Near Fairway Vista

Max.

Min.

Average

Max.

Min.

Average

Daytime

0700 -1900

Leq30min

62

52

57

66

51

58

Evening Time

1900 - 2300

Leq5min

62

53

57

59

49

53

Night Time

2300 - 0700 of next day

Leq5min

56

46

51

53

47

50

4.2.15    The lowest recorded background noise level during daytime/evening period was 49 dB(A). Since the background noise level was 6 dB(A) lower than the ANL -5 dB(A), the noise criteria for daytime/evening time periods will adopt the prevailing background noise level of 49 dB(A). As the lowest nighttime background noise level was 1 dB(A) higher than the ANL-5dB(A), noise criterion of 45 dB(A) is adopted for nighttime period. The operational phase noise criteria are summarized in Table 4-7.

Table 4-7 Acceptable Noise Levels (ANLs) during Operational Period

Time Period

Acceptable Noise Levels (ANLs), dB(A)

(ANL -5)

dB(A)

Prevailing

Background

dB(A)

*Noise Criteria

dB(A)

Day (0700 to 1900 hours)

60

55

49

49

Evening (1900 to 2300 hours)

Night (2300 to 0700 hours)

50

45

46

45

* ANL – 5dB(A) or the prevailing background noise levels (for quiet areas with level 5dB(A) below the ANL). 

4.3              Descriptions of Environment

4.3.1         The village to be sewered is situated within a quiet rural area, with some of the surrounding open land used as a golf course, recreational areas and seafood restaurants. Noise levels in this village are generally very low with little noise influence from outside of the village.

4.4              Identification of Potential Noise Impact

4.4.1         During the construction phase, use of powered mechanical equipment (PME) will inevitably generate construction noise and hence may cause noise nuisance to the nearby residences. During the operational phase, equipment noise from the proposed sewage treatment plant will be the main noise source with potential noise impact on the NSR.

4.5              Noise Sensitive Receivers

4.5.1        The Study Area covered 300m from the proposed works boundary as shown in Figure 4-2. Given the proximity of the STP and associated sewerage works to the Po Toi O village, noise sensitive receivers in the village are likely to be affected by the Project during its construction and operation. Noise sensitive receivers have been identified from the Approved Clear Water Bay Peninsula South Outline Zoning Plan, S/SK-CWBS/2, and 1:1000 survey plans of the area. In addition, site visits have been carried out to identify the NSR and representative worst impact points of the identified NSR. In general, the sewers are laid 2m away from and in parallel to NSRs. A list of the identified NSR and their locations are depicted in Figure 4-2 and listed in Table 4-8 below. Photographic record can be found in Appendix 4.4.

Table 4-8 Representative Noise Sensitive Receivers

NSR

Description

Land Use

Ground mPD

Notional Noise Distance (m) from NSR

No. of Storey

Pipes

Po Toi O Chuen Road Sewer Pipe

Sewage Treatment Plant

PTO_N1

Village House in PTOCR 28

Village

6

4

37.8

77.5

2

PTO_N2

Village House in PTOCR 7A

Village

4.1

4.2

167.4

203.4

*3

PTO_N3

Temporary Structure for living

Village

4.5

5.9

332.6

356.8

1

FV_N1

Fairway Vista House 12

Village

7.5

2

331.5

352.6

3

SC_N1

Seacrest Villas in PTOCR No. 64

Village

25.1

10.2

195.8

213.3

3

Noted: PTOCR = Po Toi O Chuen Road

             * Ground floor of PTO_N2 is a seafood restaurant. Only first and second floors are considered as NSR.

4.5.2        The village zone within or near the proposed sewerage works covers the Po Toi O Village, Seacrest Villas and Fairway Vista. The land on both sides of the proposed pipe alignment has already been fully occupied by houses. No future addition of NSR is expected. Even if a house will be squeezed into the already crowded land, it will only be of similar distance or further away from the sewerage works when compared with the existing houses. This noise assessment will be sufficient in assessing and evaluating the potential noise impact.

4.6              Assessment Methodology, Prediction and Evaluation of Environmental Impacts

4.6.1        Noise impact assessment was conducted in accordance with the requirements in EIAO-TM Annex 5 and 13.

Construction Noise

4.6.2        The Project comprises three main works including the construction of sewage treatment plant (STP), underground sewers and rising mains, and the submarine outfall.

4.6.3        Detailed construction method, sequence of works and the plant inventory in different work stages were proposed at the time of this EIA. Until a contractor is appointed, full details of the types and utilization of construction plants will not be known exactly. Typical types and number of powered mechanical equipment (PME) needed for various construction activities for the construction of STP and pipes installation have been assigned as shown in Tables 4-9 to 4-13 below. PME that will likely be used concurrently have been grouped within the same works stage. The project engineer has reviewed the currently proposed construction programme and methodology including list of PME items, percentage on-time assumptions, etc. such that they are considered practicable and appropriate for this project.

4.6.4        As not every item of PME would be operated all the time when it is on site, a typical percentage on time was assumed for each PME based on experience in actual site practice so that the noise prediction exercise would be a more realistic one. Accordingly, the effective sound power levels for each construction activity were quantified and are listed in the same table.

Construction of Sewage Treatment Plant

4.6.5        The construction of STP will include earthworks, trench support and ground compaction works, general concrete building works, backfilling and surfacing works. Common construction plant including hydraulic breaker, excavator/loader, concrete lorry mixer, vibratory poker, lorry and the like will be used. Typical plant list for STP construction is shown in Table 4-9.

Table 4-9: Typical PME to be used for Construction of Sewage Treatment Plant

Activity

Noise Source

TM-GW Reference Number

Nos. used

SWL, dB(A)

% on time

Effective SWL in a 30 min period

Overall SWL

Stage I

Earth Works

1.1

Hydraulic breaker

CNP 028

2

122

50%

122

123

Excavator / loader

CNP 081

2

112

80%

114

Lorry

CNP 141

2

112

30%

110

 

 

 

 

 

 

 

 

Stage II

Trench Support & Ground Compaction

2.1

Vibrating hammer (piling)

CNP 172

2

115

80%

117

118

Roller, vibratory

CNP 186

2

108

80%

110

 

 

 

 

 

 

 

 

Stage III

Concrete Building Works

3.1

Vibratory poker

CNP 170

2

113

80%

115

117

Concrete Lorry Mixer

CNP 044

2

109

100%

112

 

 

 

 

 

 

 

 

Stage IV

Backfilling

4.1

Backhoe

CNP 081

1

112

80%

111

112

Roller, vibratory

CNP 186

1

108

60%

106

 

 

 

 

 

 

 

 

Stage V

Surfacing

5.1

Vibratory poker

CNP 170

1

113

80%

112

114

Concrete Lorry Mixer

CNP 044

1

109

100%

109

 

 

 

 

 

 

 

 

 

Installation of Gravity Sewers and Rising Mains

4.6.6        Trenchless method is proposed for the laying of rising mains from the STP to the footpath between village house no.23 and no.28 of Po Toi O Village, which will be deep down to 10m underground. Since the launching site is located at the STP, no additional power mechanical equipment is required for excavation and backfilling work for the launching site. Pipe jacking machine (e.g. hydraulic jack) would be applied underground. Therefore, the noise generated for pipe laying under trenchless method is relatively small when compared to other concurrent works and hence was not considered in the quantitative construction noise assessment. The generator for powering the pipe jacking machine will be located at the sewage treatment plant site over 77.5m away from the nearest NSR. The noise from generator at NSR will be reduced to low level that will have no major contribution to the overall construction noise level at the NSR. This construction method is commonly applied in pipe laying in village area. The ground compositions in the first few meters are soil and sand. No significant groundborne noise impact is expected.

Table 4-10: Typical PME to be used for Installation of Rising Mains (Trenchless Method)

Activity

Noise Source

TM-GW Reference Number

Nos. used

SWL, dB(A)

% on time

Effective SWL in a 30 min period

Overall SWL

-

Generator, portable

CNP 107

1

100

100%

100

100

 

 

 

 

 

 

 

 

 

4.6.7        Gravity sewers and rising mains will be laid within the first 3m below ground in the village area. As there are different existing underground utilities located along footpath in Po Toi O, trenchless method is considered risky for pipe laying in shallow ground layer. Open trench method (cut and cover) will be adopted, in which construction works generally take place in successive sequences as excavation, trench support and ground compaction, pipe laying, backfilling, and surfacing. Construction of pipelines in areas with restricted access in narrow alleys and pathways will mainly use manual method or semi-PME method in order to reduce noise impact on the quiet village. A typical plant list for construction of gravity sewers and rising mains in the village area is provided in Table 4-11.

Table 4-11: Typical PME to be used for Installation of Gravity Sewers and Rising Mains (Open Cut Method)

Activity

Noise Source

TM-GW Reference Number

Nos. used

SWL, dB(A)

% on time

Effective SWL in a 30 min period

Overall SWL

Stage I

Excavation

1.1

Breaker, hand held

CNP 026

1

114

60%

112

112

Generator, portable

CNP 107

1

100

60%

98

 

 

 

 

 

 

 

 

Stage II

Trench Support & Ground Compaction

No PME would be needed. Manual working for construction would be adopted.

 

 

 

 

 

 

 

 

Stage III

Pipe-laying

No PME would be needed. Manual working for construction would be adopted.

 

 

 

 

 

 

 

 

Stage IV

Backfilling

No PME would be needed. Manual working for construction would be adopted.

 

 

 

 

 

 

 

 

Stage V

Surfacing

5.1

Vibratory poker

CNP 170

1

113

80%

112

112

 

 

 

 

 

 

 

 

 

4.6.8        For the laying of gravity sewer on Po Toi O Chuen Road, larger scale of PMEs are required for excavation and surfacing work. The plant list for open trench method for pipe laying on Po Toi O Chuen is shown in Table 4-12. 

Table 4-12: Typical PME to be used for Installation of Gravity Sewers on Po Toi O Chuen Road (Open Cut Method)

Activity

Noise Source

TM-GW Reference Number

Nos. used

SWL, dB(A)

% on time

Effective SWL in a 30 min period

Overall SWL

Stage I

Earth Works

1.1

Hydraulic breaker

CNP 028

1

122

50%

119

120

Excavator / loader

CNP 081

1

112

80%

111

Lorry

CNP 141

1

112

30%

107

 

 

 

 

 

 

 

 

Stage II

Trench Support & Ground Compaction

2.1

Vibrating hammer (piling)

CNP 172

1

115

80%

114

115

Roller, vibratory

CNP 186

1

108

80%

107

 

 

 

 

 

 

 

 

Stage III

Pipe-laying

No PME would be needed. Manual working for construction would be adopted.

Stage IV

Backfilling

4.1

Backhoe

CNP 081

1

112

80%

111

112

Roller, vibratory

CNP 186

1

108

60%

106

 

 

 

 

 

 

 

 

Stage V

Surfacing

5.1

Vibratory poker

CNP 170

1

113

80%

112

114

Concrete Lorry Mixer

CNP 044

1

109

100%

109

 

 

 

 

 

 

 

 

 

Construction of Submarine Outfall

4.6.9        The submarine outfall will be constructed by horizontal directional drilling (HDD). An entry pit will be excavated within sheet piles at the rocky shore for insertion of the drill head. The drill head will drill into the rock layer below seabed and the tunnel will be enlarged by pre-reaming. After that, the rising mains will be pulled from the diffuser installation point back to the entry site. The plant equipment for HDD will be placed on the rocky shore, which is about 13.2m from the nearest sensitive receiver (a house). The plant list for HDD method for construction of submarine outfall is shown in Table 4-13.  According to the Ground Investigation results, the rock layer is 10m below ground. As drilling depth at the launching site is shallower where soft marine deposits and alluvium are located, no significant groundborne noise is expected from HDD works.

Table 4-13: Typical PME to be used for Construction of Submarine Outfall (Land-based Works)

Activity

Noise Source

TM-GW Reference Number

Nos. used

SWL, dB(A)

% on time

Overall SWL

Stage I

Plant Setup and Entry Pit Setup

1.1

Vibrating hammer (piling)

CNP165

1

115

60%

112.8

Excavator / loader

CNP081

1

112

60%

109.8

Concrete Mixer (petrol)

CNP046

1

96

50%

93.0

Generator, silenced

CNP102

1

100

100%

100.0

Welding and cuting set

--

1

89

30%

83.8

Stage II

Pilot Drilling

2.1

Generator, silenced

CNP102

1

100

100%

100.0

HDD Drill Rig

--

1

88

80%

87.0

Crane

CNP049

1

95

40%

91.0

Mud pump

CNP106

1

105

80%

104.0

Agitator

CNP005

1

90

80%

89.0

Drilling fluid mixer

CNP105

1

90

80%

89.0

Drilling Fluid pump

CNP106

1

105

80%

104.0

Bentonite filtering plant

CNP162

1

105

100%

105.0

Mud Tanks and recycling unit (pump)

--

1

104

70%

102.5

Water / mud pump (electric)

CNP281

1

88

80%

87.0

Generator (for drilling rig)

CNP102

1

100

100%

100.0

Air compressor

CNP001

1

100

70%

98.5

Hydraulic power pack

CNP174

1

100

100%

100.0

Stage III

Pre-Reaming & Cofferdam at Diffuser

3.1

Generator, silenced

CNP102

2

100

100%

103.0

HDD Drill Rig

--

1

88

80%

87.0

Crane

CNP049

2

95

40%

94.0

Mud pump

CNP106

1

105

80%

104.0

Agitator

CNP005

1

90

80%

89.0

Drilling fluid mixer

CNP105

1

90

80%

89.0

Drilling Fluid pump

CNP106

1

105

80%

104.0

Bentonite filtering plant

CNP162

1

105

100%

105.0

Mud Tanks and recycling unit (pump)

--

1

104

70%

102.5

Water / mud pump (electric)

CNP281

1

88

80%

87.0

Generator (for drilling rig)

CNP102

1

100

100%

100.0

Air compressor

CNP001

1

100

70%

98.5

Hydraulic power pack

CNP174

1

100

100%

100.0

Welding and cuting set

--

1

89

30%

83.8

Stage IV

Pipe Installation & Installation of Diffuser & Removal of Cofferdam

4.1

Generator, silenced

CNP102

2

100

100%

103.0

HDD Drill Rig

--

1

88

80%

87.0

Crane

CNP049

2

95

40%

94.0

Mud pump

CNP106

1

105

80%

104.0

Agitator

CNP005

1

90

80%

89.0

Drilling fluid mixer

CNP105

1

90

80%

89.0

Drilling Fluid pump

CNP106

1

105

80%

104.0

Bentonite filtering plant

CNP162

1

105

100%

105.0

Mud Tanks and recycling unit (pump)

--

1

104

70%

102.5

Water / mud pump (electric)

CNP281

1

88

80%

87.0

Generator (for drilling rig)

CNP102

1

100

100%

100.0

Air compressor

CNP001

1

100

70%

98.5

Hydraulic power pack

CNP174

1

100

100%

100.0

 

4.6.10    Phases of construction of the works were identified and unmitigated and mitigated scenarios were assessed for noise impact at the identified NSR.

Prediction of Unmitigated Construction Noise Impact

4.6.11    The impact of construction noise on the identified NSRs was assessed in accordance with the procedures laid down in Technical Memorandum on Noise from Construction Work Other Than Percussive Piling. A +3 dB (A) façade correction was added to the predicted noise levels to account for the façade effect at each NSR. In general, the noise impact will be the highest when works are being carried out close to the NSRs and, as the works areas gradually shift away, the noise would tend to diminish.

4.6.12    As a conservative approach to assessing the worst-case construction noise impacts, it was assumed that all the proposed PMEs for each construction work stage were operating concurrently.  The predicted cumulative worst-case construction noise levels at the NSRs due to construction of STP, laying of gravity sewer and rising mains on Po Toi O Chuen Road and in the village, and construction of submarine outfall are summarized in Table 4-14. Detailed calculations are provided in Appendix 4.1.

Table 4-14: Predicted Worst-case Cumulative Construction Noise Levels at
Representative NSRs - Unmitigated Scenario

NSR

Description of NSR

Predicted Worst-case Construction Noise Level dB(A)

Unmitigated Results

Noise Criteria

Exceedance

PTO1_N1

Village House in PTOCR 28

95

75

20

PTO_N2

Village House in PTOCR 7A

95

75

20

PTO_N3

Temporary Structure for Living

92

75

17

FV_N1

Fairway Vista House 12

101

75

26

SC_N1

Seacrest Villas in PTOCR No. 64

90

75

15

4.6.13    Based on the effective sound power level of the PMEs and the distance of work site to the noise sensitive receivers, unmitigated construction noise level for some work stages were predicted to exceed the EIAO-TM of 75dB(A) guideline level by 15 to 26 dB(A). About 130 residential dwellings and 1 temple will be affected. Various mitigation options have been considered in accordance with the guidelines laid down in the Environmental Impact Assessment Ordinance, Guidance Note No. 9/2010 “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2010) as discussed in Section 4.7.

 

Operational Noise

4.6.14    During the operational phase, equipment noise from the proposed sewage treatment plant will be the main noise source with potential noise impact on the NSRs.

4.6.15    The equipment inventory of the Po Toi O STP will be similar to those for small sewage treatment plants in Hong Kong, and this would include sewage pumps, ventilation fans, deodourizing fans, mechanically raked fine screen and blower.  A typical equipment inventory based on the design at the time of preparation of this EIA, is provided in Table 4-15. The inventory and operation modes were confirmed with the project engineer. The typical Sound Power Levels (SWL) associated with these equipment items are also provided.

Table 4-15: Typical Noisy Equipment for the Proposed Po Toi O Sewage Treatment Plant

Location

Equipment

No. of Units

Typical SWL, dB(A)

Sub-total SWL, dB(A)

Preliminary Treatment Units

Submersible pump (Ref. 1)

2

85

88.0

Mechanically raked fine screen (Ref. 3)

2

89

92.0

Deodourizing fan (Ref. 4)

2

85

88.0

Exhaust fan (Ref. 2)

1

79

79.0

MBR Equipment Unit

Mechanically pump (Ref. 5)

3

92

96.8

Deodourizing fan (Ref. 4)

2

85

88.0

Exhaust fan (Ref. 2)

1

79

79.0

Sludge Treatment Unit

 

Submersible pump (Ref. 1)

2

85

88.0

Deodourizing fan (Ref. 4)

2

85

88.0

Exhaust fan (Ref. 2)

1

79

79.0

Air Blower Room

Blower (Ref. 6)

1

85

85.0

Exhaust fan (Ref. 2)

1

79

79.0

Outfall Pumping Station and Header Tank

Mechanical pump (Ref. 5)

4

92

98.0

Deodourizing fan (Ref. 4)

2

85

88.0

Exhaust fan (Ref. 2)

2

79

82.0

Remark: -

SWL – Sound Power Level

Only noisy equipment is included in the table.  Other equipment which do not have significant noise emissions are excluded.

(Ref. 1) SWL referenced to CNP283.

(Ref. 2) SWL referenced to approved EIA of Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-148/2008) and Good Practices on Ventilation System Noise Control based on the flow rate of 1,300m3/hr.

(Ref. 3) SWL referenced to the approved EIA Report on Tai Po Sewage Treatment Works Stage V (EIA-097/2004).

(Ref 4) SWL of plant refers to Good Practices on Ventilation System Noise Control based on the flow rate of 17,000 m3/hr and 125 Pa.

(Ref 5) SWL of plant refer to Good Practices on Pumping System Noise Control based on the horsepower of pumpset 20 hp at 1800 rpm.

(Ref 6) SWL of plant refers to the tender specification for Shatin STW Stage 3 Upgrading and approved EIA of Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-148/2008).

4.6.16    Standby equipment would only be used in case of failure or maintenance of duty units. Therefore, concurrent operation of both duty and standby equipment will not occur under the normal operation.  As a reasonable worst case scenario assessment, the maximum sound power levels during operation would be under the full operation of all duty equipment which is given in Table 4-15.

4.6.17    The impact of operational noise on the identified NSRs was assessed in accordance with the procedures laid down in Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites. A +3 dB (A) façade correction was added to the predicted noise levels to account for the façade effect at each NSR.

4.6.18    All identified noisy equipment items of the STP would be confined inside the building structure except exhaustion fans. A reduction of 20 dB(A) can be achieved if the building enclosure is built using suitable material such as concrete with surface density of 25 kg/m2. Equipment items to be confined within the building structure of PTOSTW with noise reduction consideration are summarized in Table 4-16.

Table 4-16: Proposed Design Measures For Operation of  Po Toi O Sewage Treatment Plant

Location

Equipment

Mitigation Measures

Noise Reduction dB(A)

Preliminary Treatment Units

Submersible pump

Enclosed Inside Building Structure

-20

Mechanically raked fine screen

-20

Deodourizing fan

-20

Exhaust fan

--

0

MBR Equipment Unit

Mechanically pump (Ref. 5)

Enclosed Inside Building Structure

-20

Deodourizing fan (Ref. 4)

-20

Exhaust fan (Ref. 2)

--

0

Sludge Treatment Unit

 

Submersible pump (Ref. 1)

Enclosed Inside Building Structure

-20

Deodourizing fan (Ref. 4)

-20

Exhaust fan (Ref. 2)

--

0

Air Blower Room

Blower (Ref. 6)

Enclosed Inside Building Structure

-20

Exhaust fan (Ref. 2)

--

0

Existing Outfall Pumping Station and Header Tank

Mechanical pump (Ref. 5)

Enclosed Inside Building Structure

-20

Deodourizing fan (Ref. 4)

-20

Exhaust fan (Ref. 2)

--

0

4.6.19    The predicted worst-case noise levels at identified NSRs due to the operation of STP would comply with the noise criteria at all time.  The predicted noise levels at representative NSRs are summarized in Table 4-17 and detailed in Appendix 4.2.

Table 4-17: Predicted Worst-case Operation Noise Levels at Representative NSRs - Unmitigated Scenario

NSR

NSR Description

Predicted Unmitigated Noise Level, dB(A)

Day-time Noise Criterion, dB(A)

Night-time Noise Criterion, dB(A)

PTO_N1

Village House in PTOCR 28

45

49

45

PTO_N2

Village House in PTOCR 7A

37

49

45

PTO_N3

Temporary Structure for living

32

49

45

FV_N1

Fairway Vista House 12

32

49

45

SC_N1

Seacrest Villas in PTOCR No. 64

37

49

45

4.6.20    In fact, typical concrete wall has better noise insulation performance. The assumption of 20 dB(A) reduction has been conservative. Also, with some of the equipment stored underground, the noise impact will be further reduced. Furthermore, the acoustic louvres are designed to face the slope but not the village, avoiding direct view of the noise source from NSR. The maximum allowable sound power levels of equipment items would be specified in the tender specification to ensure the operational noise impact complying with relevant noise criteria.

4.6.21    Most of the noisy equipment items in the sewage treatment plant are fully enclosed underground or enclosed by concrete structure. With noise reduction due to distance between the STP and the nearest NSR, no operational noise impact is anticipated and therefore no mitigation is required.

4.7              Evaluation and Recommendation of Noise Mitigation Measures

Construction Noise

4.7.1        Mitigation at source or path should be the most effective way to reduce the impact. There are 4 ways in doing that viz. : -

·             by use of quiet plants and working methods to mitigate at source;

·             by use of mobile noise barriers/enclosures along the path of noise propagation;

·             by adopting good site practice to limit noise emissions at source;

·             by scheduling of work to minimize work scale and duration of impact.

Use of Quiet Plants and Working Methods

4.7.2        Silenced plants or quality powered mechanical equipment (QPME) are quieter than those noise levels given in TM-GW for the equivalent type of equipment. These silenced equipment items are known to be available in Hong Kong and hence should be adopted as far as practical. Table 4-18 shows the possible alternative quieter PME which are taken from BS:5228: Part 1:2009 or available noise label.  These quieter PMEs are available in the market and have been successfully applied to other projects and have achieved noticeable noise reductions.  The quieter PMEs to be used for the works shall meet the following SWLs, or lower:

Table 4-18 Quiet PME and Associated Sound Power Level Proposed for the Project

Description of PME

Equivalent Quiet PME

SWL, dB(A)

Hydraulic breaker

BS5228 Tab. D8-12

106

Excavator / loader

EPD-00081

99

Lorry

BS5228 Tab. D8-25

96

Vibrating hammer (piling)

BS5228 Tab. D4-12

94

Roller, vibratory

BS5228 Tab. D3-115

102

Vibratory poker

BS5228 Tab. D6-40

98

Backhoe

BS5228 Tab. D3-108

97

Breaker, hand held

Noise Label NB-0022-13-001

100

Ref:

·       BS 5228-1:2009. BSI British Standards. Code of practice for noise and vibration control on construction and open sites – Part 1: Noise

·       EPD Issued Noise Emission Label: https://epic.epd.gov.hk/eForm/lic_epd119/lrrf031_list.jsp?epic_lic_no=002030606&a119_or_119_ind=A&lang=eng

 

4.7.3        In addition to use of breaker for breaking up road surface in the village area, drilling with chemical agent will be considered as far as practicable in the construction phase according to local situation.

Use of Mobile Noise Barriers/Enclosures

4.7.4        Mobile noise barriers can be effective in screening noise from reaching sensitive receivers, particularly for the low-rise houses in this case. 3m high mobile barriers with skid footing and a small cantilevered upper portion can be located within a few metres of stationary plants and within about 5m of more mobile plant such as hydraulic breaker. All these PMEs are slow moving or usually stationary when they are operating and hence the position of the mobile barriers will not need to be frequently adjusted.

4.7.5        Some sections of gravity sewers and rising mains construction would be aligned close to the village houses. As the handheld breaker is the noisy PME for excavation work, it shall be fitted with mufflers to minimize noise emission. A movable enclosure made up of plywood is proposed to surround both worker and breaker during breaking process. The internal wall of the enclosure should be laid with sound absorbent such as mineral wool. Without direct view of the noisy part of the breaker from NSR, this design can achieve 15dB(A) reduction, which has already taken into account sound leakage through the gaps. A typical drawing of the enclosure can be found in Appendix 4-5.

4.7.6        For construction of submarine outfall using HDD, the work area is large enough to accommodate semi-enclosure. It should enclose the stationary plant equipment on three sides with cover. Only the side facing the sea shall be opened for heat exhaustion.

 

Schedule of Work

4.7.7        As the footpath between village houses is very narrow, pipe laying in close proximity of the NSRs cannot be avoided. Construction work will be divided into short sections (10m) to reduce the duration of localized work (about one month per workfront). Three workfronts will progress at the same time. Each workfront should be separated from each other by at least 100m to minimize cumulative effect.

4.7.8        During laying of gravity sewers and rising mains near NSRs PTO_N1 and PTO_N3, major concurrent noisy activities are laying of Po Toi O Chuen Road sewer and horizontal directional drilling (HDD) respectively. The 10m workfront of gravity sewers and rising mains installation near the two NSRs shall be scheduled at different times from these noisy activities to minimize cumulative noise impact.

4.7.9        As the prevailing noise level in restricted hours is lower than daytime (averaged 50 – 51 dB(A) vs 57 - 59 dB(A) based on baseline monitoring), construction works will be carried out in daytime to avoid nuisance during evening and night time.

 

Adoption of Good Site Practice

4.7.10    Good site practice and noise management can significantly reduce the impact of a construction site’s activities on nearby NSRs. Although the reduction in noise level is not readily predictable and quantified, the following measures should be useful during each phase of construction:

·             Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme;

·             Machines that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·             Silencer and mufflers on construction equipment should be utilised and should be properly maintained during the construction programme;

·             Noisy activities can be scheduled to minimise exposure of nearby NSRs to high levels of construction noise. For example, noisy activities can be scheduled for midday. Avoid carrying out noisy activities at the same time;

·             For the installation of gravity sewers and rising mains near residence, hand-held breaker may be used to break the hard concrete layer. The manual equipment should be used as far as practicable to avoid using the PME. If found necessary, the percentage on time should be limited to reduce continuous contributions; 

·             Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs;

·             Mobile plant should be sited as far away from NSRs as possible; and

·             Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

4.7.11    During excavation works for gravity sewers and rising mains installation, generator and breaker will be operated at the same time. Generator should be placed at a fixed location and screened by noise barrier. It should be at least 5-6m away from the NSRs whenever excavation work has to be carried out at their front doors (calculations in Appendix 4.3 refers). These measures can minimize the noise contribution from the generator and the total sound power level at NSRs.

4.7.12    Only one vibratory poker is proposed for surfacing work after pipe laying. To further minimize noise nuisance, vibratory poker will only be operated 4m away from NSR and with noise barrier properly erected. This can reduce the construction noise level at the NSR to 75B(A) as shown in Appendix 4.3 (NSRs PTO_N1 & FV_N1). Surfacing work within 4m from NSR will be carried out by manual method.

4.7.13     “Recommended Pollution Control Clauses for Construction Contracts” is available on EPD website. It contains the recommended noise pollution control measures to be implemented by the contractor during the construction stage. The predicted noise levels are summarized in Table 4-19. Detailed calculations are provided in Appendix 4.3.

Table 4-19: Predicted Cumulative Construction Noise Levels at Representative NSRs - Mitigated Scenario

NSR

Description of NSR

Predicted Worst-case Construction Noise Level dB(A)

Mitigated Results

Noise Criteria

Exceedance

PTO1_N1

Village House in PTOCR 28

75

75

-

PTO_N2

Village House in PTOCR 7A

75

75

-

PTO_N3

Temporary Structure for living

74

75

-

FV_N1

Fairway Vista House 12

75

75

-

SC_N1

Seacrest Villas in PTOCR No. 64

71

75

-

 

4.7.14    With the adoption of quiet PMEs and temporary barrier/enclosure/semi-enclosure, no construction noise exceedance is expected. When the works areas gradually shifted away, the noise would tend to diminish.

Cumulative Noise Impact Due to Concurrent Project

4.7.15    The following discusses the potential cumulative interface issues between concurrent projects as indicated in Chapter 2 – Project Description. There may be two potential concurrent projects in the area, i.e.

·             Roundabout near the minibus stop

·             Fish culture zone (FCZ) dredging and relocation

4.7.16    During the course of the study, CEDD has confirmed that there was no programme for the fish culture zone dredging and relocation. There was also no information on when the roundabout would be constructed. Therefore, no cumulative noise impact is expected.

4.7.17    Should there be concurrent project in the vicinity, continuous discussion between contractors shall be conducted to plan the location and programme of construction work to minimize cumulative impact.

4.8              Evaluation of Residual Impacts

4.8.1        After implementation of mitigation measures as mentioned in Section 4.7, construction noise impact on NSRs would comply with the daytime noise guideline 75dB(A). Upon completion of the sewage treatment plant, noisy plant equipment will be operated within the building structure or underground. The fixed equipment noise will comply with the daytime/evening time and nighttime noise criteria. Therefore, no residual noise impact is expected in both construction and operational phases.

4.9              Environmental Monitoring and Audit Requirements

4.9.1        With the implementation of proposed construction noise mitigation measures such as use of quality powered mechanical equipment (QPME), use of mobile noise barriers, enclosure and semi-enclosure, good site practice and management, and construction noise monitoring and audit programme, construction noise impact could be reduced down to acceptable levels. Regular monitoring of noise level should be carried out at noise monitoring stations near representative sensitive receivers before and throughout construction work to ensure that relevant noise standard can be met.

4.9.2        Since the noisy equipment items in the sewage treatment plant are fully enclosed underground or enclosed by concrete structure, operational noise impact is expected to be acceptable. Operational noise monitoring is considered unnecessary.

4.9.3        General EM&A requirements were presented in Chapter 12.

4.10          Conclusion

4.10.1    Construction noise arising from typical types and numbers of powered mechanical equipment items (PME) for the construction of sewage treatment plant, rising mains/sewer installation and submarine outfall have been assessed. Based on the effective sound power levels of the PMEs and the notional noise distances to the noise sensitive receivers, unmitigated construction noise levels would exceed the 75dB(A) guideline level for the non-restricted hours for all NSRs. At source mitigation measures have been proposed including the use of quality plants, use of mobile noise barriers, semi-enclosure, enclosure, strategic work scheduling and good site practice. With the proposed mitigation measures, no construction noise exceedance is expected.

4.10.2    Most of the noisy equipment items in the sewage treatment plant would be fully underground or enclosed by concrete structure. With noise reduction due to distance between the STP and the nearest NSR, operational noise impact is anticipated to be acceptable.