16                         conclusions

16.1                   General

16.1.1             An EIA report has been prepared for the proposed Kai Tak Multi-purpose Sports Complex. This report has provided an in-depth assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the best available information at this stage of the EIA.

16.1.2             The assessment has been conducted, in accordance with the EIA Study Brief (No. ESB-274/2014) under the EIAO for the Project, covering the following environmental issues: -

·           Air quality impact

·           Hazard to life

·           Noise impact

·           Water quality impact

·           Sewerage and sewage treatment implications

·           Waste management implications

·           Land contamination

·           Terrestrial ecological impact

·           Landscape and visual impact

·           Impact on cultural heritage

16.1.3             A summary of environmental impacts identified in this EIA and the proposed mitigation measures, if any, are described in the following sections.

16.2                   Air Quality Impact Assessment

Construction Phase

16.2.1             Potential air quality impacts from the construction works of the Project would mainly be related to construction dust from site clearance, excavation, foundation and site formation works. Construction dust impact arising from this Project with consideration of concurrent projects has been assessed for both the unmitigated and mitigated scenarios. With proper implementation of the recommended mitigation measures in Sections 3.7.19 to 3.7.22, it has been concluded that all dust concentrations at ASRs would comply with the TSP criterion as well as the relevant AQO for RSP and FSP. Hence, no adverse residual air quality impacts are anticipated during the construction phase.

Operation Phase

16.2.2             Air emission sources during the operational phase include open road traffic emissions, marine emissions from the Kai Tak Cruise Terminal, emissions from To Kwa Wan Typhoon Shelter, industrial emissions from nearby chimneys within 1km of the Project site, and the background pollutant concentration predicted by PATH.

16.2.3             The Project itself is not an air pollution source. The only air emission source due to the Project is the induced traffic along the traffic routes. Based on the modelling results, it is predicted that the cumulative 10-min. SO2, hourly SO2, daily average RSP, annual average RSP, daily average FSP, annual average FSP, and hourly NO2 at all the identified ASRs would comply with the AQOs for both “Without Project” and “With Project” Scenarios.

16.2.4             Exceedance of the annual average NO2 criterion was identified at some selected ASRs in localized areas along major roads such as Prince Edward Road East and Kowloon City Road (near the Kai Tak Tunnel West Portal). The AQO exceedance of the annual NO2 under the “With Project” scenario is dominated by the background air pollution level.

16.2.5             Various options of mitigation measures have been explored and practical measures have been recommended to be implemented and are shown in Section 3.8.47.

16.2.6             Residual environmental impacts have been evaluated in accordance with Section 4.4.3 of EIAO-TM. Assessment results show that the exceedance of annual average NO2 is mainly caused by the relatively high concentrations of background air pollution in Kowloon City and To Kwa Wan Districts, and the impact magnitude for changes in ambient pollutant concentrations due to the Project is considered minimal in the assessment area. With the implementation of the air quality improvement schemes currently being undertaken by the Government, continuous air quality improvement in the territory is expected. The small affected population in Year 2023 will further be reduced to a limited size in Year 2036. Based on the assessment results, similar population would be affected even without the Project.

16.2.7             Through the evaluation of the residual environmental impacts in Sections 3.8.50 to 3.8.58, it is considered that the Project will not cause long term serious environmental implications.

16.2.8             In conclusion, the Project would not impose adverse air quality impact on the assessment area and the residual impacts are insignificant.

16.3                   Hazard to Life Assessment

16.3.1             Hazard to Life Assessment in KTD area was fully addressed in the approved Kai Tak Development EIA Report (Register No.: AEIAR-130/2009). Based on the latest available information, no new PHI is proposed in KTD area and all existing/planned hazardous sources within or in vicinity of KTD were considered in the approved KTD EIA report. The Project site is outside all the Consultation Zones / study areas of the identified hazardous sources. Hence the finding of the hazard to life assessment related to the Project in the approved EIA report for the KTD remain valid, i.e. adverse potential hazard to life impact arising from the construction and operation on the Project is not anticipated.

16.3.2             No further hazard to life assessment is required.

16.4                   Noise Impact Assessment

Construction Phase

16.4.1             Construction noise would be generated from the use of powered mechanical equipment (PME). With the implementation of mitigation measures such as adoption of good site practice and use of quieter PME and mobile noise barriers, the mitigated construction noise from the Project at all the representative noise sensitive receivers (NSR) would comply with the criterion.

Operation Phase

16.4.2             During the operational phase of the Project, potential traffic noise impact on surrounding NSRs caused by the traffic induced has been predicted and evaluated. The assessment results indicated that insignificant additional traffic noise impact would be caused by the traffic induced by the Project or the overall traffic noise levels would comply with the noise criterion, except for some planned NSRs. For the planned NSRs where a significant additional traffic noise impact caused by the Project is anticipated, it has been shown that the potential traffic noise impact caused by the Project would not create unacceptable constraints to the proposed development, whilst the future developers of these developments sites would carry out environmental assessments (EA) for the proposed developments at the detailed designed stage. The EA would include the required mitigation measures for traffic noise impact in order to ensure that all NSRs at the subject sites would not be exposed to road traffic noise levels above criteria as stipulated in the Hong Kong Planning Standards and Guidelines (HKPSG).

16.4.3             The potential noise impact arising from the operation of the Main Stadium, including sports and musical events, as well as the potential noise impact from human activities in public places has been assessed and found to comply with the noise criterion in the daytime/evening period with the acoustic design in place. Also, the potential noise impact for sports events in the Public Sports Ground has been evaluated and similarly found to comply with the noise criterion in the daytime/evening period with the acoustic design in place. Fixed plant noise would exceed the noise criterion; however, with noise mitigation the mitigated fixed plant noise levels would comply with the noise criterion at the worst-affected receivers.

16.4.4             Based on the mode of operation for the Project, no organized event shall be conducted simultaneously in the Main Stadium and the Public Sports Ground. The mitigated cumulative noise levels due to sports events in the Main Stadium and all the fixed plant, and the mitigated cumulative noise levels due to sports events in the Public Sports Ground and all the fixed plant would comply with the noise criteria at all NSRs. No adverse cumulative operation noise impact is anticipated.

16.4.5             Music events held in the Main Stadium would generate noise. With the implementation of the recommended mitigation measures in Sections 5.6.1 to 5.6.4, the potential noise impact arising from the musical events at the Main Stadium during daytime/evening period (i.e. 7 a.m. to 11 p.m.) would comply with the noise criteria in Noise Control Guidelines for Music, Singing and Instrument Performing Activities.  Should the future operator plan to implement any music events at the Main Stadium during night-time period (i.e. 11 p.m. to 7 a.m.), the operator is obliged to comply with the requirements under the NCO.

16.4.6             Noise from human activities in public places would arise mainly from crowd dispersal after events. In general, crowd dispersion is not a source of annoyance especially during daytime/evening. The crowd from the Main Stadium may disperse on the podium level during daytime/evening. It is recommended that for dispersion after 10:30 p.m. the crowd after leaving the Main Stadium should be directed immediately to the ground level of MPSC instead of on the podium level for minimizing the exposed sections of the dispersal routes. The future operator should arrange its staff to marshal the dispersion of crowds after 10:30 p.m. in an orderly manner from the exits of the Main Stadium all the way to the two nearby MTR stations. No adverse potential noise impact arising from crowd dispersion within the Project site is expected.

16.5                   Water Quality Impact Assessment

Construction Phase

16.5.1             During the construction phase, potential water quality impact may arise from site run-off, sewage from workforce, accidental spillage of chemicals, and discharge of wastewater from various construction activities. With the implementation of the recommended mitigation measures including those stipulated in the EPD’s Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN1/94), no adverse water quality impact on the water sensitive receivers from the construction works for the Project is anticipated.

Operation Phase

16.5.2             During the operational phase, surface runoff from the Main Stadium and the Public Sports Ground may be contaminated by the residual fertilizers and pesticides from the maintenance of the natural turf. Mitigation measures have been proposed such as the adoption of artificial turf or hard surface as the default playing surface, which involve no pesticides nor fertilizers. If natural turf is used as the default playing surface, the use and application of fertilizers and pesticides will follow the normal practices. A staged intercepting system will be developed for storage of surface water for reuse and a Stormwater Re-use Management Plan will be prepared and implemented, so as to ensure no residual fertilizers and pesticides from the turf surface run-off are discharged. Hence, with the implementation of the recommended mitigation measures, the operation of the Project will unlikely result in unacceptable stormwater discharge problem.

16.6                   Sewerage and Sewage Treatment Implications

Construction Phase

16.6.1             During the construction phase, the Project will not impact on the existing sewerage system.

Operation Phase

16.6.2             Sewage generated from the Project will be collected at the To Kwa Wan Preliminary Treatment Works (TKWPTW) and subsequently delivered to Stonecutters Island Sewage Treatment Works via deep tunnels for further treatment and disposal. The amount of sewage generated by visitors, spectators, permanent and temporary employee of all facilities in MPSC was estimated as per EPD Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning (GESF) (2005). Since the capacity of the current design capacity of the TKWPTW will be adequate to cater for the increased flow due to the Project, no additional sewerage treatment facilities are required.

16.6.3             Two new sewerages will be built to collect sewage generated from the Project and discharge into the downstream sewers, which will be subsequently discharged into the nearby sewage pumping stations for further disposal.

16.7                   Waste Management Implications

Construction Phase

16.7.1             Potential waste management implications from the generation of waste during the construction phase have been evaluated. Mitigation measures are proposed for minimizing waste generation and off-site disposal. Precast and prefabricated construction shall be adopted as far as practicable. Reuse and recycle of construction waste should be implemented as much as possible and construction and operation waste should be minimized during the design, construction and operation phases.

16.7.2             It is estimated that totally 657,519 m3 C&D material, including inert and non-inert would be generated from the Project. About 21% of C&D material would be re-used on site, 69% would be disposed of off site to public fill and 10% of construction waste would be disposed of to landfill. The inert materials that can be reused/recycled on site amounting to 141,945 m3. 447,464m3of the inert C&D materials would be transported to the public fill area by barge through trucks to the nearby barging point. The non-inert waste materials would be disposed of at the designated landfills. The waste materials accounting to 68,110 m3 would be transported by barge similar to C&D materials.

Operation Phase

16.7.3             The types of waste that would be generated during the operational phase have been assessed. Recommendations have been made to ensure proper treatment and disposal of these wastes. The daily waste generation after full house events in the Project is about 35 tonnes per day (tpd) consisting of 27 tpd of domestic solid waste and 8 tpd of commercial solid waste.

16.8                   Land Contamination Assessment

16.8.1             The land contamination issues in the Project have been reviewed and assessed. Basically, land contamination in the former Kai Tak Airport has been fully assessed in the approved EIA ReportKai Tak Airport North Apron Decommissioning (NAKTA) (Register No.: AEIAR-002/1998). Land contamination identified in the North Apron had been cleaned up and the site is considered clean for the intended use for this Project. No update of the land contamination assessment is considered necessary. Furthermore, no use of the land in the Project with potential for land contamination is anticipated.

16.9                   Terrestrial Ecological Impact Assessment

16.9.1             No site of conservation importance was identified in the Study Area. About 16.1 ha of construction sites, 5.0 ha of developed area and 6.9 ha of abandoned area in the project site will be lost. These habitats have only very low ecological value. Although 2 nos. of avifauna species of conservation importance and 1 uncommon avifauna species were recorded in the project footprint, only minor impact is expected as no nursery ground, breeding, foraging or roosting behavior was recorded in the Project footprint. Nevertheless, no site, flora or other fauna species of conservation importance would be impacted directly

16.9.2             Surrounding habitats and their communities may be subject to indirect impacts such as water contamination, noise, dust, and/or glare induced by construction and operation activities. Nevertheless, with proper implementation of water quality, noise, dust and glare mitigation measures, all indirect impacts in construction and operational phases would be acceptable as they would be insignificant or minor.

16.9.3             With proper implementation of the proposed mitigation measures, residual impact is considered acceptable. The overall impact on terrestrial ecology is considered as acceptable.

16.10               Landscape and Visual Impact Assessment

16.10.1         Under the proposed MPSC development, the cultural and historical features surrounding the project will be preserved and a new landscape design within the MPSC study area implemented that is considered appropriate to the planned context of the area and should produce long term landscape and visual benefits.

16.10.2         The current landscape resources and character within the site are of limited quality and value. The project provides a clear opportunity for enhancement by undertaking significant tree planting and public space creation. Approximately 160 trees will be lost during the construction of the project, but none of them are of any importance or with high amenity value. It is anticipated that the project will carry out planting of about 340 new trees.

16.10.3         With suitable mitigation measures taken to enhance the visual compatibility such as extensive greening and superstructure designs that respond to the existing and planned urban context in terms of scale, height and bulk (visual weight), the different facilities within the Project will have an overall enhanced visual effect on the area. The landscape deck will contribute as an attractive open space and integrating all the buildings within MPSC development. The landscape deck provides seamless linkage from the MTR stations to the Metro Park and surrounding development within the KTD. It offers people a visually stimulating environment and help to create a sense of place.

16.10.4         Glare impact on Visual Sensitive Receivers (VSRs) located near the MPSC and associated above ground structure have been reviewed. The predicted glare rating for all of the VSRs within the study boundary are below the Glare Rating Limit adopted. No significant discomfort glare condition is anticipated.

16.10.5         It is not anticipated that there will be any adverse residual impacts generated by the Project, whilst significant greening of the site, coupled with careful visual integration into the urban context through control of scale, massing and building disposition will provide a long term beneficial visual outlook.

16.11               Cultural Heritage Impact Assessment

16.11.1         Relevant cultural heritage impact assessments in previously approved EIA reports have been reviewed (Kai Tak Development (Register No.: AEIAR-130/2009) and Shatin to Central Link (SCL) – Tai Wai to Hung Hom Section (Register No.: AEIAR-167/2012)). Based on the site location and the survey plan in Year 1904, the Project site was formerly a sea area. It is unlikely ancestors have congregated at the Project Site. Hence, the project site has no archaeological value. Built Heritage Impact Assessment is not required as there is no built heritage within the Study Area of the Project and associated works.

16.11.2         The Project will not interfere with Lung Tsun Stone Bridge Site of Archaeological Interest. The southern portion of the former Sacred Hill and the southern portion of the archaeological survey-cum-excavation area of SCL – Tai Wai to Hung Hom Section for Sacred Hill (North) fall within the CHIA Study Area. Since no archaeological deposit was discovered from the southern portion of the archaeological survey-cum-excavation at Sacred Hill (North) and these two areas fall outside the project site, there is no cultural heritage impact arising from this Project and no mitigation measure is required.

16.12               Environmental Monitoring and Audit Requirement

16.12.1         It is recommended that an EM&A programme should be implemented during the construction and operation phases (i.e. regarding musical event noise, stormwater reuse, and landscaping) to monitor the environmental impacts on the neighboring sensitive receivers. A standalone EM&A Manual has been prepared to specify the monitoring requirements for the implementation of the environmental mitigation measures identified in the EIA process.

16.12.2         The Environmental Mitigation Implementation Schedule (EMIS) in Chapter 14 has also been included in the Appendix A of the EM&A Manual detailing the proposed mitigation measures, the implementation locations, timeframe, and implementation agent.