TABLE OF CONTENTs
5.......... Water Quality Impacts
5.2 Environmental Legislation, Policies, Plans,
Standards and Criteria
5.3 Water Sensitive Receivers for the Project
5.4 Water Sensitive Receivers for Sewage
Pumping Stations (DP9)
5.5 Baseline Conditions ¡V River Water Quality
in Deep Bay WCZ
5.6 Baseline Conditions ¡V River Water Quality
in North Western WCZ
5.7 Baseline Conditions ¡V Marine Water Quality
in Deep Bay WCZ
5.8 Baseline Conditions ¡V Marine Water Quality
in North Western Water
5.9 Assessment Approach and Methodology
5.10 Identification and Evaluation of
Environmental Impacts ¡V Construction Phase
5.11 Identification and Evaluation of
Environmental Impacts ¡V Operational Phase
5.12 Cumulative Impacts from Concurrent Projects
5.13 Mitigation Measures ¡V Construction Phase
5.14 Mitigation Measures ¡V Operational Phase
5.15 Evaluation of Residual Environmental
Impacts
5.17 Environmental
Acceptability of Schedule 2 Designated Projects
APPENDICES
Appendix 5.1 Key Assumptions for
Quantification of Construction Site Run-off
Appendix 5.4 Key Assumptions for Compiling
Non-Point Source Pollution from Surface Run-off
FIGURES
Figure 5.1 Key
Water Bodies Within Study Area and Water Quality Monitoring Stations
Figure 5.2 Locations
of Inland Water Bodies ¡V Key Plan
Figure 5.2.1 Locations of
Inland Water Bodies ¡V Sheet 1 of 14
Figure 5.2.2 Locations of
Inland Water Bodies ¡V Sheet 2 of 14
Figure 5.2.3 Locations of
Inland Water Bodies ¡V Sheet 3 of 14
Figure 5.2.4 Locations of
Inland Water Bodies ¡V Sheet 4 of 14
Figure 5.2.5 Locations of
Inland Water Bodies ¡V Sheet 5 of 14
Figure 5.2.6 Locations of
Inland Water Bodies ¡V Sheet 6 of 14
Figure 5.2.7 Locations of
Inland Water Bodies ¡V Sheet 7 of 14
Figure 5.2.8 Locations of
Inland Water Bodies ¡V Sheet 8 of 14
Figure 5.2.9 Locations of
Inland Water Bodies ¡V Sheet 9 of 14
Figure
5.2.10 Locations of
Inland Water Bodies ¡V Sheet 10 of 14
Figure
5.2.11 Locations of
Inland Water Bodies ¡V Sheet 11 of 14
Figure 5.2.12 Locations of Inland Water
Bodies ¡V Sheet 12 of 14
Figure
5.2.13 Locations of
Inland Water Bodies ¡V Sheet 13 of 14
Figure
5.2.14 Locations of
Inland Water Bodies ¡V Sheet 14 of 14
Figure 5.3 Proposed
Locations of Flood Retention Facilities
Figure 5.4 Indicative
Locations of Marine Water Sensitive Receivers and Observation Points
Figure 5.6 Locations
of Footbridges and Cycle Bridges
Figure 5.7 Locations
of Foundations for the Proposed Viaduct of DP12
¡P Construction of new primary distributor road (Road P1) (DP1)
¡P Construction of eight new distributor roads (Roads D1 to D8) (DP2)
¡P Construction of slip roads between: Road D8 Junction and existing Castle Peak Road; Junction of D8/P1 and Junction of D7/P1; and KSWH connection to Road D3 (DP5)
¡P Construction of partly depressed and partly decked-over roads located at Road D2, Road D4 and Road D6 (DP6)
¡P Construction of four new SPSs (Sites 2-34, 3-41, 3-48 and 4-35) (DP9)
¡P Construction of Road P1 and slip-road from KSWH to Road D3 partly located within the ¡§CA¡¨ of Yuen Tau Shan (DP12)
Environmental Impact Assessment Ordinance (EIAO)
¡P Annex 6 ¡V Criteria for Evaluating Water Pollution; and
¡P Annex 14 ¡V Guidelines for Assessment of Water Pollution.
Water Quality
Objectives
Table 5.1 Summary
of Water Quality Objectives for Deep Bay WCZ
Criteria |
Subzone |
|
Aesthetic appearance |
(a) Waste discharges shall cause no objectionable
odours or discolouration of the water. |
Whole Zone |
(b) Tarry residues, floating wood, articles made
of glass, plastic, rubber or of any other substances should be absent. |
Whole Zone |
|
(c) Mineral oil should not be visible on the
surface. Surfactants should not give rise to a lasting foam. |
Whole Zone |
|
(d) There should be no recognisable sewage-derived
debris. |
Whole Zone |
|
(e) Floating, submerged and semi-submerged
objects of a size likely to interfere with the free movement of vessels, or
cause damage to vessels, should be absent. |
Whole Zone |
|
(f) Waste discharges shall not cause the water to
contain substances which settle to form objectionable deposits. |
Whole Zone |
|
Bacteria |
(a) The level of Escherichia coli should not exceed 610 per 100 mL, calculated as
the geometric mean of all samples collected in one calendar year. |
Secondary Contact Recreation Subzone and
Mariculture Subzone (L.N. 455 of 1991) |
(b) The level of Escherichia coli should be zero per 100 ml, calculated as the
running median of the most recent 5 consecutive samples taken at intervals of
between 7 and 21 days. |
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
(c) The level of Escherichia coli should not exceed 1000 per 100 ml, calculated as
the running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
(d) The level of Escherichia coli should not exceed 180 per 100 mL, calculated as
the geometric mean of all samples collected from March to October inclusive
in one calendar year. Samples should be taken at least 3 times in a calendar
month at intervals of between 3 and 14 days. |
Yuen Long Bathing Beach Subzone (L.N. 455 of
1991) |
|
Colour |
(a) Waste discharges shall not cause the colour
of water to exceed 30 Hazen units. |
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the colour
of water to exceed 50 Hazen units. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
Dissolved
oxygen (DO) |
(a) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling
occasions during the year; values should be taken at 1 metre below surface. |
Inner Marine Subzone excepting Mariculture
Subzone |
(b) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling
occasions during the year; values should be calculated as water column
average (arithmetic mean of at least 2 measurements at 1 metre below surface
and 1 metre above seabed). In addition, the concentration of dissolved oxygen
should not be less than 2 milligrams per litre within 2 metres of the seabed
for 90% of the sampling occasions during the year. |
Outer Marine Subzone excepting Mariculture
Subzone |
|
(c) The dissolved oxygen level should not be less
than 5 milligrams per litre for 90% of the sampling occasions during the
year; values should be taken at 1 metre below surface. |
Mariculture Subzone |
|
(d) Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 milligrams per litre. |
Yuen Long & Kam Tin (Upper and Lower)
Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground
Subzones and other inland waters of the Zone |
|
pH |
(a) The pH of the water should be within the
range of 6.5-8.5 units. In addition, waste discharges shall not cause the natural
pH range to be extended by more than 0.2 units. |
Marine waters excepting Yung Long Bathing Beach
Subzone |
(b) Waste discharges shall not cause the pH of
the water to exceed the range of 6.5-8.5 units. |
Yuen Long & Kam Tin (Upper and Lower)
Subzones, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering
Ground Subzones |
|
(c) The pH
of the water should be within the range of 6.0-9.0 units. |
Other inland waters |
|
(d) The pH of the water should be within the
range of 6.0-9.0 units for 95% of samples. In addition, waste discharges
shall not cause the natural pH range to be extended by more than 0.5 units. |
Yung Long
Bathing Beach Subzone |
|
Temperature |
Waste discharges shall not cause the natural
daily temperature range to change by more than 2.0 degrees Celsius. |
Whole Zone |
Salinity |
Waste discharges shall not cause the natural
ambient salinity level to change by more than 10% |
Whole Zone |
Suspended
solids (SS) |
(a) Waste discharges shall neither cause the natural
ambient level to be raised by 30% nor give rise to accumulation of suspended
solids which may adversely affect aquatic communities. |
Marine waters |
(b) Waste discharges shall not cause the annual
median of suspended solids to exceed 20 milligrams per litre. |
Yuen Long & Kam Tin (Upper and Lower)
Subzones, Beas Subzone, Ganges Subzone, Indus Subzone, Water Gathering Ground
Subzones and other inland waters |
|
Ammonia |
The un-ionised ammoniacal nitrogen level should
not be more than 0.021 milligram per litre, calculated as the annual average
(arithmetic mean). |
Whole Zone |
Nutrients |
(a) Nutrients shall not be present in quantities
sufficient to cause excessive or nuisance growth of algae or other aquatic
plants. |
Inner and
Other Marine Subzone |
(b) Without limiting the generality of objective
(a) above, the level of inorganic nitrogen should not exceed 0.7 milligram
per litre, expressed as annual mean. |
Inner Marine Subzone |
|
(c) Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.5 milligram per
litre, expressed as annual water column average (arithmetic mean of at least
2 measurements at 1 metre below surface and 1 metre above seabed). |
Outer Marine Subzones |
|
5-day biochemical
oxygen demand (BOD) |
(a) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 3 milligrams per litre. |
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5 milligrams per litre. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
Chemical
oxygen demand (COD) |
(a) Waste discharges shall not cause the chemical
oxygen demand to exceed 15 milligrams per litre. |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges
Subzone and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the chemical
oxygen demand to exceed 30 milligrams per litre. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
Toxins |
(a) Waste discharges shall not cause the toxins
in water to attain such levels as to produce significant toxic carcinogenic,
mutagenic or teratogenic effects in humans, fish or any other aquatic
organisms, with due regard to biologically cumulative effects in food chains
and to toxicant interactions with each other. |
Whole Zone |
(b) Waste discharges shall not cause a risk to
any beneficial uses of the aquatic environment. |
Whole Zone |
|
Phenol |
Phenols shall not be present in such quantities
as to produce a specific odour, or in concentration greater than 0.05
milligrams per litre as C6H5OH. |
Yung Long Bathing Beach Subzone |
Turbidity |
Waste discharges shall not reduce light
transmission substantially from the normal level. |
Yung Long Bathing Beach Subzone |
Table 5.2 Summary
of Water Quality Objectives for North Western WCZ
Parameters |
Criteria |
Subzone |
Aesthetic appearance |
(a) Waste discharges shall cause no objectionable
odours or discolouration of the water. |
Whole Zone |
(b) Tarry residues, floating wood, articles made
of glass, plastic, rubber or of any other substances should be absent. |
Whole Zone |
|
(c) Mineral oil should not be visible on the
surface. Surfactants should not give rise to a lasting foam. |
Whole Zone |
|
(d) There should be no recognisable
sewage-derived debris. |
Whole Zone |
|
(e) Floating, submerged and semi-submerged objects
of a size likely to interfere with the free movement of vessels, or cause
damage to vessels, should be absent. |
Whole Zone |
|
(f) Waste discharges shall not cause the water to
contain substances which settle to form objectionable deposits. |
Whole Zone |
|
Bacteria |
(a) The level of Escherichia coli should not exceed 610 per 100 mL, calculated as
the geometric mean of all samples collected in one calendar year. |
Secondary Contact Recreation Subzones |
(b) The level of Escherichia coli should be less than 1 per 100 mL, calculated as
the running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days. |
Tuen Mun (A) and Tuen Mun (B) Subzones and Water
Gathering Ground Subzones |
|
(c) The level of Escherichia coli should not exceed 1000 per 100 mL, calculated as
the running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days. |
Tuen Mun (C) Subzone and other inland waters |
|
(d) The level of Escherichia coli should not exceed 180 per 100 mL, calculated as
the geometric mean of all samples collected from March to October inclusive.
Samples should be taken at least 3 times in one calendar month at intervals
of between 3 and 14 days. |
Bathing Beach Subzones |
|
Colour |
(a) Waste discharges shall not cause the colour
of water to exceed 30 Hazen units. |
Tuen Mun (A) and Tuen Mun (B) Subzones and Water
Gathering Ground Subzones |
(b) Waste discharges shall not cause the colour
of water to exceed 50 Hazen units. |
Tuen Mun (C) Subzone and other inland waters |
|
Dissolved
oxygen (DO) |
(a) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 mg per litre for 90% of the sampling
occasions during the whole year; values should be calculated as water column
average (arithmetic mean of at least 3 measurements at 1 m below surface,
mid-depth and 1 m above seabed). In addition, the concentration of dissolved
oxygen should not be less than 2 mg per litre within 2 m of the seabed for
90% of the sampling occasions during the whole year |
Marine waters |
(b) Waste
discharges shall not cause the level of dissolved oxygen to be less than 4
milligrams per litre. |
Tuen Mun
(A), Tuen Mun (B) and Tuen Mun (C) Subzones, Water Gathering Ground Subzones
and other inland waters |
|
pH |
(a) The pH of the water should be within the
range of 6.5-8.5 units. In addition, waste discharges shall not cause the
natural pH range to be extended by more than 0.2 units. |
Marine waters excepting Bathing Beach Subzones |
(b) Waste discharges shall not cause the pH of
the water to exceed the range of 6.5-8.5 units. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
|
(c) The pH
of the water should be within the range of 6.0-9.0 units. |
Other inland waters |
|
(d) The pH of the water should be within the
range of 6.0-9.0 units for 95% of samples. In addition, waste discharges
shall not cause the natural pH range to be extended by more than 0.5 units. |
Bathing
Beach Subzones |
|
Temperature |
Waste discharges shall not cause the natural
daily temperature range to change by more than 2.0 degrees Celsius. |
Whole Zone |
Salinity |
Waste discharges shall not cause the natural
ambient salinity level to change by more than 10% |
Whole Zone |
Suspended solids
(SS) |
(a) Waste discharges shall neither cause the
natural ambient level to be raised by 30% nor give rise to accumulation of
suspended solids which may adversely affect aquatic communities. |
Marine waters¡¦ |
(b) Waste discharges shall not cause the annual
median of suspended solids to exceed 20 milligrams per litre. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
|
(c) Waste discharges shall not cause the annual
median of suspended solids to exceed 25 mg per litre. |
Other inland waters |
|
Ammonia |
The un-ionised ammoniacal nitrogen level should
not be more than 0.021 milligram per litre, calculated as the annual average
(arithmetic mean). |
Whole Zone |
Nutrients |
(a) Nutrients shall not be present in quantities
sufficient to cause excessive or nuisance growth of algae or other aquatic
plants. |
Marine waters |
(b) Without limiting the generality of objective
(a) above, the level of inorganic nitrogen should not exceed 0.3 mg per
litre, expressed as annual water column average (arithmetic mean of at least
3 measurements at 1 m below surface, mid-depth and 1 m above seabed). |
Castle Peak Bay Subzone |
|
(c) Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.5 mg per litre,
expressed as annual water column average (arithmetic mean of at least 3
measurements at 1 m below surface, mid-depth and 1 m above seabed). |
Marine waters excepting Castle Peak Bay Subzone |
|
5-day
biochemical oxygen demand (BOD) |
(a) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 3 milligrams per litre. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5 milligrams per litre. |
Other inland waters |
|
Chemical
oxygen demand (COD) |
(a) Waste discharges shall not cause the chemical
oxygen demand to exceed 15 milligrams per litre. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the chemical
oxygen demand to exceed 30 milligrams per litre. |
Other inland waters |
|
Toxins |
(a) Waste discharges shall not cause the toxins
in water to attain such levels as to produce significant toxic, carcinogenic,
mutagenic or teratogenic effects in humans, fish or any other aquatic
organisms, with due regard to biologically cumulative effects in food chains
and to toxicant interactions with each other. |
Whole Zone |
(b) Waste discharges shall not cause a risk to
any beneficial uses of the aquatic environment. |
Whole Zone |
|
Phenol |
Phenols shall not be present in such quantities
as to produce a specific odour, or in concentration greater than 0.05
milligrams per litre as C6H5OH. |
Bathing Beach Subzones |
Turbidity |
Waste discharges shall not reduce light
transmission substantially from the normal level. |
Bathing Beach Subzones |
Technical Memorandum
Practice Note
Technical Circular
Existing Inland Watercourses
¡P Tin Shui Wai Main Channel and its tributaries (TSW);
¡P Hang Hau Tsuen Channel and its tributaries (HTT);
¡P Small watercourses along Deep Bay (DB);
¡P Upstream / tributaries of Shan Pui River (SPR); and
¡P Upstream / tributaries of Tuen Mun River (TMR).
Tin Shui Wai Main Channel and its Tributaries (TSW)
Hang Hau Tsuen Channel and its Tributaries (HTT)
Table 5.3 Summary
of Major Watercourses at or Near the Project Area
ID (See Figure 5.1) |
Existing Fresh Water System |
Description |
Water Sections to be Removed or
Realigned |
||||||
General |
Major Sub-sections of the Fresh
Water System |
Figure Reference (Fig. Ref.) |
Name |
Description |
Fig. Ref. |
||||
Name |
Description |
||||||||
Watercourses Discharging to Deep Bay WCZ |
|||||||||
TSW |
TSW Main Channel and its tributaries |
A large fresh water system, which spreads across the majority of the
Project area and generally runs from south to north and finally enters the
marine water of Deep Bay WCZ |
TSW Main Channel |
Core channel of the fresh water system, which generally runs along the
north-eastern boundary of the Project area from south to north and eventually
joins the marine water of Deep Bay WCZ in the north. |
Overview: Figure 5.1 Close up maps: Figure 5.2.6, Figure 5.2.7 (see upper right) and Figure 5.2.11 (see bottom left) |
N/A - The whole section of the Tin Shui Wan Main Channel will be
retained under the Project |
|||
Lo Uk Tsuen tributaries |
Upstream tributaries of the fresh water system, which generally run
across the middle portion of the Project area from west to east and
eventually enters the TSW Main Channel; Some small watercourses (originate
from the hill side in the west) also enter these Lo Uk Tsuen tributaries. |
Overview: Figure 5.1 Close up maps: Figure 5.2.7 (see bottom right) and Figure 5.2.8 (see upper part) |
TSW3 |
A small upstream section of Lo Uk Tsuen Tributaries to be removed
under the Project |
|||||
Hung Shiu Kiu (HSK) Main Street Channel |
An upstream tributary of the fresh water system, which originates from
a water channel near Wo Ping San Tsuen in the south and then runs towards the
north and eventually enters the TSW Main Channel |
Overview: Figure 5.1 Close up maps: Figure 5.2.8 (see bottom right) and Figure 5.2.9 (see right hand side) |
N/A -The whole section of HSK Main Street Channel will be retained
under the Project |
||||||
Tin Sam Channel tributaries |
Upstream tributaries of the fresh water system, which originates from
a watercourse in the south and then runs near Tin Sam towards the north and
eventually joins the HSK Main Street Channel. Some small watercourses (originate
from the hillside in the west) also run across the Project area towards the
east and then enter Tin Sam Channel |
Overview: Figure 5.1 Close up maps: Figure 5.2.4, Figure 5.2.8 (see bottom right) and Figure 5.2.9 (see left hand side) |
TSW1A, TSW1B, TSW1C, TSW1D |
4 minor sections that finally drain into Tin Sam Channel to be removed
under the Project |
|||||
TSW4 |
A section of Tin Sam Channel to be realigned under the Project |
||||||||
Others small tributaries |
Small watercourses near Tin Wah Road in the northern Project area,
which finally discharge to the TSW Main Channel |
Figure 5.2.7 (see upper right) |
TSW2, TSW2A, TSW2B |
Minor watercourses near Tin Wah Road to be removed under the Project |
Figure 5.2.7 (see upper right) |
||||
Small watercourse near Hung Uk Tsuen in the eastern portion of the
Project area, which finally discharges to the TSW Main Channel |
TSW5 |
A water section (west of Hung Uk Tsuen) to be removed under the
Project |
|||||||
HHT |
Hang Hau Tsuen Channel and its tributaries |
A relatively small stormwater system at the northern tip of the
Project area, which generally runs from south to north and finally discharges
to the marine water of Deep Bay WCZ. |
Overview: Figure 5.1 Close up maps: Figure 5.2.1 and Figure 5.2.7 (see upper middle) |
HHT1 |
A side branch of the Channel to be removed |
||||
HHT2 |
An upstream section of the Channel to be removed |
||||||||
DB |
Small water-courses along Deep Bay |
These small watercourses are located at the north-western boundary of
the Project area, generally running from south to north and finally enters
the marine water of Deep Bay WCZ. |
Overview: Figure 5.1 Close up map: Figure 5.2.2 |
N/A ¡V All of these minor watercourses will be retained under the
Project |
|||||
SBR |
Upstream tributaries of Shan Pui River |
These small watercourses are located around the proposed combined flushing
water service reservoir (FLWSR) and fresh water service reservoir (FWSR) in
the south, within the catchment of Shan Pui River, which would eventually
discharge to the marine water of Deep Bay WCZ. |
Overview: Figure 5.1 Close up map: Figure 5.2.14 |
N/A ¡V All these minor watercourses will be retained under the Project |
|||||
Watercourses discharging to North Western WCZ |
|||||||||
TMR |
Upstream tributaries of Tuen Mun River |
These watercourses are the upstream tributaries of Tuen Mun River
found at the southern tip of the Project area. They are running generally from north
to south and eventually enters the marine water of North Western WCZ |
Overview: Figure 5.1 Close up map: Figure 5.2.5 |
TMR1 |
An upstream section of this tributary to be removed under the Project |
||||
Small Watercourses Along Deep Bay (DB)
Upstream Tributaries of Shan Pui River (SMR)
Upstream Tributaries of Tuen Mun River (TMR)
Planned Inland Watercourses
Existing Ponds and Wet Agricultural Areas
Table 5.4 Ponds
and Agricultural Wet Areas within Assessment Area
ID |
Description |
Location |
Within Project Area? (Yes/No) |
Figure Reference |
Remarks |
P1A |
Inactive fish pond |
North of Project Area to the south of Hang Hau Tsuen Channel |
No |
|
|
P1B |
Inactive fish pond |
North of Project Area to the south of Hang Hau Tsuen Channel |
No |
|
|
P1C |
Inactive fish pond |
North of Project Area to the south of Hang Hau Tsuen Channel |
No |
|
|
P3A |
Active fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P3B |
Active fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P3C |
Inactive fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P3D |
Active fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P6A |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P6B |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P6C |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P6D |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P7 |
Inactive fish pond |
North of Project Area to the west of TSW Main Channel |
No |
|
|
P7A |
Recreational pond |
North of Project Area to the west of TSW Main Channel |
No |
|
|
P8A |
Flood protection pond |
At the ¡§Village Type Development¡¨ (¡§V¡¨) near Sik Kong Tsuen |
Yes |
|
|
P8B |
Inactive fish pond |
At the northern part of Project area near San
Wai |
Yes |
P8B will be removed under the Project |
|
P8C |
Inactive fish pond |
At the northern part of Project area near San
Wai |
Yes |
P8C will be removed under the Project |
|
P9A |
Flood protection pond |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
P9B |
Flood protection pond |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
P9C |
Flood protection pond |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
P9D |
Wetland mitigation pond |
Near the western boundary of Project area underneath KSWH |
Yes |
|
|
P9E |
Wetland mitigation pond |
Near the western boundary of Project area underneath KSWH |
Yes |
|
|
P9F |
Wetland mitigation pond |
West of Project area underneath KSWH |
Yes |
|
|
P9G |
Wetland mitigation pond |
West of Project area underneath KSWH |
Yes |
|
|
P9H |
Inactive fish pond |
West of Project area and to the west of KSWH |
No |
|
|
P9I |
Inactive fish pond |
West of Project area and to the west of KSWH |
No |
|
|
P9J |
Inactive fish pond |
West of Project area and to the west of KSWH |
No |
|
|
P10 |
Inactive fish pond |
At the southern portion of Project area near
San Sang San Tsuen |
Yes |
P10 will be removed under the Project |
|
P10A |
Recreational pond |
At ¡§V¡¨ east of Project area |
No |
|
|
P10B |
Recreational pond |
At ¡§V¡¨ east of Project area |
No |
|
|
P10C |
Flood protection pond |
At the ¡§V¡¨ in the eastern portion of the Project area |
Yes |
|
|
P11A |
Inactive fish pond |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
P11B |
Inactive fish pond |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
P12 |
Reinforced concrete flood storage pond |
To the immediate west of KSWH |
Yes |
|
|
A1 |
Wet agricultural area |
West of Project area and to the west of KSWH |
No |
|
|
A2A |
Wet agricultural area |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
A2B |
Wet agricultural area |
At the border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
Part of A2B, A3C, A3D (located outside the ¡§V¡¨ area) will be removed |
|
A2C |
Wet agricultural area |
At the border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
||
A2D |
Wet agricultural area |
At the border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
||
A3 |
Wet agricultural area |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
A3A |
Wet agricultural area |
At the southern part of the Project area near the upstream tributaries
of Tuen Mun River |
Yes |
A3A will be removed under the Project |
|
A3C |
Wet agricultural area |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
A4A |
Wet agricultural area |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
A4B |
Wet agricultural area |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
A4C |
Wet agricultural area |
North of Yuen Long Highway and to the south of Project area |
No |
|
Shaded cell: Ponds
/ wet agricultural areas to be completed or partially removed under the Project
Planned Ponds and Agricultural Wet Areas
Planned Flood Retention Facilities
Marine Water Sensitive Receivers
¡P Existing and planned cooling water intakes along the coastlines of outer Deep Bay, Tuen Mun District and North Lantau;
¡P Existing and planned flushing water intakes along the coastlines of Tuen Mun District and North Lantau;
¡P Existing bathing beaches in Tuen Mun District;
¡P Existing Tuen Mun typhoon shelter;
¡P Existing Gold Coast marina;
¡P Planned marina at Tung Chung East;
¡P Existing Tai O estuary;
¡P Existing Sha Chau and Lung Kwu Chau Marine Park;
¡P Planned The Brothers Marine Park;
¡P Existing Mai Po Inner Deep Bay Ramsar Site;
¡P Existing oyster culture area at inner Deep Bay;
¡P Existing fish spawning ground north of Lantau;
¡P Existing artificial reefs near airport and Sha Chau;
¡P Other existing ecological resources along the coastlines of Deep Bay, Sha Chau, Lung Kwu Chau, The Brothers and north Lantau including coral habitats, horseshoe crab habitats, seagrass habitats, mangrove habitats and Sites of Special Scientific Interest (SSSIs).
Table 5.5 Tentative Discharge
Points of Emergency Overflow from SPS and Downstream Receiving Water
SPS (see Figure 5.5) |
Discharge Point of Emergency Overflow and Downstream Receiving Water (refer to Table 5.3 for detailed description of Receiving Water) |
SPS No. 1 |
Tin Sam Channel, which would then discharge
to the TSW Main Channel and finally to the marine water of Deep Bay WCZ. |
SPS No. 2 |
A side branch of Tin Sam Channel,
which would firstly drain into Tin Sam Channel and then discharge to the TSW
Main Channel and finally to the marine water of Deep Bay WCZ. |
SPS No. 3 |
Tin Sam Channel, which would then
discharge to the TSW Main Channel and finally to the marine water of Deep Bay
WCZ. |
SPS No. 4 |
Lo Uk Tsuen Tributaries, which
would then enter the TSW Main Channel and finally to the marine water of Deep
bay WCZ. |
Tin Shui Wai Main Channel and Its Tributaries (TSW)
Table 5.6 Summary Statistics of River Water
Quality Data at Tin Shui Wai Catchment Collected by EPD in 2014
Parameters |
EPD Stations (Figure 5.1) |
WPCO
WQO |
|
TSR1 |
TSR2 |
||
Dissolved
oxygen (DO) (mg/L) |
5.8 |
9.4 |
Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 mg/L |
(3.1 ¡V 9.3) |
(8.2 ¡V 12.0) |
||
pH |
7.6 |
8.2 |
The pH of the water should be within the
range of 6.0-9.0 |
(7.2 ¡V 8.0) |
(7.4 ¡V 8.7) |
||
Suspended
solids (mg/L) |
5 |
5 |
Waste discharges shall not cause the annual median
of suspended solids to exceed 20mg/L |
(2 - 23) |
(2 -8) |
||
5-day
Biochemical Oxygen Demand (BOD) (mg/L) |
6 |
2 |
Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5mg/L |
(4 - 40) |
(<1 - 7) |
||
Chemical
Oxygen Demand (COD) (mg/L) |
15 |
6 |
Waste discharges shall not cause the chemical
oxygen demand to exceed 30mg/L |
(6 - 48) |
(<2 - 12) |
||
Oil
& grease (mg/L) |
<0.5 |
<0.5 |
Not available |
(<0.5 ¡V 2.8) |
(<0.5 - <0.5) |
||
Faecal
coliforms (cfu/100mL) |
650,000 |
47,000 |
Not available |
(75,000 - 7,000,000) |
(5,300 - 200,000) |
||
E. coli (cfu/100mL) |
210,000 |
20,000 |
Not exceed 1000 per 100 ml,
calculated as the running median of the most recent 5 consecutive samples
taken at intervals of between 7 and 21 days |
(15,000 ¡V 2,500,000) |
(2,800 - 88,000) |
||
Ammonia-nitrogen
(mg/L) |
2.20 |
0.34 |
Not available |
(0.40 ¡V 4.30) |
(0.10 ¡V 1.50) |
||
Nitrate-nitrogen
(mg/L) |
0.51 |
0.77 |
Not available |
(<0.01 - 1.00) |
(0.54 - 0.96) |
||
Total
Kjeldahl nitrogen (mg/L) |
3.85 |
0.69 |
Not available |
(0.83 - 7.20) |
(0.19 ¡V 2.20) |
||
Ortho-phosphate
(mg/L) |
0.17 |
0.05 |
Not available |
(0.06 - 0.38) |
(<0.01 - 0.19) |
||
Total
phosphorus (mg/L) |
0.34 |
0.08 |
Not available |