Table of Contents

 

4    Noise Impact. 4-1

4.1     Introduction. 4-1

4.2     Environmental Guidelines, Standards and Criteria. 4-1

4.3     Description of the Environment. 4-2

4.4     Noise Sensitive Receivers. 4-2

4.5     Identification of Potential Impacts. 4-4

4.6     Assessment Methodology. 4-5

4.7     Prediction and Evaluation of Environmental Impacts. 4-6

4.8     Mitigation of Adverse Environmental Impacts. 4-6

4.9     Evaluation of Residual Impacts. 4-12

4.10   Environmental Monitoring and Audit. 4-12

4.11   Conclusion. 4-12

 

List of Tables

Table 4.1   Noise Criteria for Daytime Construction Noise. 4-1

Table 4.2   Identified NSRs within 300m from the Boundary of the Project. 4-2

Table 4.3   Identified Representative Noise Assessment Points. 4-3

Table 4.4   Summary of Unmitigated Construction Noise Levels. 4-6

Table 4.5   SWL of QPME Adopted for Construction Noise Mitigation. 4-7

Table 4.6   Mitigated Construction Noise Level. 4-9

Table 4.7   Mitigated Cumulative Construction Noise Level. 4-10

 

Figures

Figure 4.1          Location of Study Area and NSRs

Figure 4.2          Location of Noise Assessment Points (Key plan)

Figure 4.3          Location of Noise Assessment Points

Figure 4.4          Location of Noise Assessment Points

Figure 4.5          Location of Noise Assessment Points

Appendices

Appendix 4.1    Photographs of Existing NSRs

Appendix 4.2    Plant inventory (Unmitigated Scenario)

Appendix 4.3    Construction Programme, Locations of Works areas and Distance to Notional Sources

Appendix 4.4    SWL of PME

Appendix 4.5    Construction Noise Assessment (Unmitigated Scenario)

Appendix 4.6    Typical Configuration of Noise Barrier and Portable Noise Enclosure

Appendix 4.7    Plant Inventory (Mitigated Scenario)

appendix 4.8    Construction Noise Assessment (Mitigated Scenario)

 

 

 


4              Noise Impact

4.1                  Introduction

4.1.1.1          This section presents an assessment on the potential noise impacts arising from the construction of the Project.  The noise impact assessment is conducted in accordance with the requirements of Annex 5 and Annex 13 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO -TM) as well as the requirements set out under Clause 3.4.4 and Appendix B of the EIA Study Brief (ESB-287/2015).

4.2                  Environmental Guidelines, Standards and Criteria

4.2.1               General

4.2.1.1          Construction noise impact has been assessed in accordance with the criteria and methodology given in the Technical Memoranda (TM) under the Noise Control Ordinance (NCO), and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

4.2.1.2          Assessment procedures and standards are set out in the following TM:

·               Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM); and

·               Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM).

4.2.2               Construction Noise

4.2.2.1          The NCO provides the statutory framework for the control of noise from construction works, other than percussive piling, using powered mechanical equipment (PME) between the hours of 1900 and 0700 hours or at any time on Sundays and general holidays (i.e. restricted hours).  Noise from construction activities taking place at other times is subject to the Noise Standards for Daytime Construction Activities in Table 1B of Annex 5 of the EIAO-TM.  The criteria are summarized in Table 4.1.

Table 4.1         Noise Criteria for Daytime Construction Noise

Uses

Daytime Noise Criteria in Leq (30min), dB(A)

Domestic premises

75

Educational Institution

70

Educational Institution (during examination)

65

Note: The above standards apply to uses which rely on opened windows for ventilation.

4.2.3               Operation Noise

4.2.3.1         The Project is not a noise pollution source and therefore noise impact arising from the project during operation phase is not anticipated.

 

4.3                  Description of the Environment

4.3.1.1          The Project is located at the waterfront of Lei Yue Mun as shown in Figure 2.1.  The land uses in the Study Area, i.e. the area within a distance of 300m from the boundary of the Project, are mainly residential uses and restaurants in village houses and squatters. The existing noise climate is dominated by noise from business activities and passing marine vessels.

4.4                  Noise Sensitive Receivers

4.4.1.1          In accordance with Annex 13 of the EIAO-TM, domestic premises including temporary housing, educational institutions (including kindergartens and nurseries), hospitals, medical clinics, homes for the aged, convalescent homes, places of worship, libraries, courts of law, performing arts centres, auditoria and amphitheatres are NSRs. 

4.4.1.2         According to the observations from site visits and review of relevant land use plans including the Outline Zoning Plans (OZP), NSRs within 300 m of the Project boundary have been reviewed.  Locations of the study area and NSRs are shown in Figure 4.1.  In accordance with the OZP (S/K15/25 - Cha Kwo Ling, Yau Tong, Lei Yue Mun), the study area mainly comprises zoning of village development, Green Belt, Coastal Protection Area and Other Specifies Uses.  No planned NSR is identified within the study area.  Identified NSRs within 300 m study boundary from the Project are shown in Table 4.2 below. Photographs of existing NSRs are shown in Appendix 4.1.

Table 4.2         Identified NSRs within 300m from the Boundary of the Project

NSR

Land Use

NSR Status

Lei Yue Mun Village

Residential

Existing

Jockey Club Lei Yue Mun Plus

Performing Arts Centre  & Educational institution (1)&(2)

Existing

Ma Wan Tsuen

Residential

Existing

Tin Hau Temple

Place of Worship (1)

Existing

Ma Pui Tsuen

Residential

Existing

Che Ting Tsuen

Residential

Existing

Canaryside

Residential

Existing

Notes:

(1)      Places of worship and performing arts centres are NSRs under the EIAO-TM but there are no specific daytime construction noise standards for these types of NSRs.

(2)      Jockey Club Lei Yue Mun Plus provides multi-purpose facilities, including rooms for performing arts and a ceramic workshop. Courses, workshops and talks are held occasionally in the Jockey Club Lei Yue Mun Plus for educational purpose,

4.4.1.3          The first layer of NSRs would provide acoustic shielding to those receivers at further distance behind.  The predicted noise levels at the first layer of NSRs represent the worst-case scenario, and therefore representative Noise Assessment Points (NAPs) at these NSRs are selected for construction noise impact assessment.  In accordance with Annex 13 of the EIAO-TM, places of worship and performing arts centres are NSRs. The EIAO-TM however does not stipulate specific noise limits for these types of NSRs.  A summary of identified representative NAPs, is presented in Table 4.3 with their locations shown in Figure 4.2 to Figure 4.5.


 

Table 4.3         Identified Representative Noise Assessment Points

NAP ID

Description

Land Use

Number of Storeys

Daytime Noise Criterion, Leq (30mins), dB(A)

Distance from The Nearest Boundary of The Works,

m

HPRC43

No. 43, Lei Yue Mun Hoi Pong Road Central

Residential

2

75

11

LYMP

Jockey Club Lei Yue Mun Plus

Performing Arts Centre & Educational institution

2

70

65 during examination

(1)&(2)

<1

HPRC53A

No. 53A, Lei Yue Mun Hoi Pong Road Central

Residential

2

75

5

HPRCV1

Village house in Lei Yue Mun Hoi Pong Road Central

Residential

1

75

<1

HPRCV2

Village house in Lei Yue Mun Hoi Pong Road Central

Residential

1

75

24

HPRE21C

No. 21C, Lei Yue Mun Hoi Pong Road East

Residential

1

75

12

HPRE79A

No. 79A, Lei Yue Mun Hoi Pong Road East

Residential

2

75

8

HPRE75B

No. 75B, Lei Yue Mun Hoi Pong Road East

Residential

2

75

1

HPRE81

No. 81, Lei Yue Mun Hoi Pong Road East

Residential

2

75

<1

MWT145

No. 145, Ma Wan Tsuen

Residential

1

75

<1

THT

Tin Hau Temple

Place of Worship

1

75(1)&(3)

24

Note:

(1)      Places of worship and performing arts centres are NSRs under the EIAO-TM but there are no specific daytime construction noise standards for these types of NSRs.

(2)      Considering that courses, workshops and talks would be held occasionally in the Jockey Club Lei Yue Mun Plus (LYMP) for education purpose, noise criteria of 70 dB(A) and 65 dB(A) during examination are proposed for the construction noise impact assessment.  Based on observations on site, only spilt-type air-conditioners (A/C) are installed at LYMP, and therefore it is still considered possible for the NSR at LYMP to rely on opened window for ventilation.  As such, LYMP is identified as an NSR for the construction noise impact assessment.

(3)   A construction noise assessment criterion of 75 dB(A) is proposed for Tin Hau Temple. Reference has been made to the approved EIA report for Tseung Kwan O - Lam Tin Tunnel and Associated Works (EIAO Register No.: AEIAR-173/2013).

4.5                  Identification of Potential Impacts

4.5.1.1          The potential source of noise impact during the construction of the Project would be the use of PME for various construction activities. The key construction works would include the following:

·               construction of a public landing facility, a promenade and a breakwater which involves dredging of seabed;

·               Improvement works of four existing lookout points (i.e. Lookout points 1,3, 4 & 5) and an existing viewing platform ;

·               construction of a carp-shaped platform and a pavilion with children play area;

·               beautification works for the promenade, lookout points and viewing platform by installing green/planter walls, planting areas, railings and sitting benches, etc.; and

·               streetscape improvement works (i.e. installation of decorative mosaic tiles along Hoi Pong Road Central and Hoi Pong Road East).

4.5.1.2          The existing structure of lookout point 2 will be retained, therefore no improvement works will be required.

4.5.1.3          Excavation works in the lookout points will be carried out manually due to the insufficient spaces for the use of construction plant. All excavated materials will be transported to the viewing platform and will be removed off site by marine vessels.  

4.5.1.4          The plant inventory provided by the Project Engineer for the construction noise impact assessment is presented in Appendix 4.2.  Appendix 4.3 presents the currently envisaged work programme, locations of the work sites and distances between the notional sources and the NSRs.   The feasibility and practicability for the plant inventory and associated plant utilisation rates adopted for the assessment have been confirmed by the Project Engineer.  The Project Proponent has also confirmed the validity of the plant inventory.  The currently envisaged construction programme would not require any work using PME during restricted hours (i.e. the hours from 1900 to 0700 hours or at any time on a general holiday) or percussive piling works.  Therefore, only the impacts from daytime general construction activities are assessed in this EIA Report.

Streetscape Improvement Works

4.5.1.5          One of the noisy activities would be the streetscape improvement works (i.e. installation of decorative mosaic tiles) that require the use of handheld breaker along Hoi Pong Road Central and Hoi Pong Road East at a very short distance from certain NSRs.  Based on the preliminary design, however, the works would only involve an area that measures approximately 1m x 1m in size.  With the very small scale of breaking works, each of the NSRs is expected to be impacted by the noise from the streetscape improvement works for the duration of less than an hour per day over a period of approximately one week only.

Concurrent Project

4.5.1.6         Based on the available information, Lei Yue Mun Village Sewerage project would be the only concurrent project within the Study Area. The description and the construction programme of the Lei Yue Mun Village Sewerage project are presented in Section 2.12.1.1.

4.6                  Assessment Methodology

4.6.1.1          The methodology for the construction noise impact assessment follows the procedures outlined in the GW-TM. The general approach is summarized as follows:

·               Locate the NSRs which would most likely be affected by noise from the construction work;

·               Determine the items of PME for each discrete construction activity, based on available information or agreed plant inventories;

·               Assign sound power levels (SWLs) to the proposed PME according to the GW-TM or other sources;

·               Calculate distance attenuation to NSRs from notional noise source;

·               Apply corrections in the calculations such as potential screening effects and acoustic reflection, if any;

·               Predict construction noise levels at NSRs in the absence of any mitigation measures;

·               Consider cumulative impact from concurrent projects within 300 m of the NSRs, if any; and

·               Compare the cumulative construction noise level against the corresponding noise criterion and propose suitable mitigation measures where necessary.

4.6.1.2          For the SWLs of the PME, reference is made to Table 3 of the GW-TM and "Sound power levels of other commonly used PME" (Other PME) published by EPD.  Where no relevant SWL can be found in the GW-TM and other PME, reference is made to the information relating to Quality Powered Mechanical Equipment (QPME) available at EPD’s web site[1] or PME specification published by equipment manufacturer.  SWLs of the equipment adopted in this noise assessment and sources of the reference are presented in Appendix 4.4.    

4.6.1.3         It is assumed that all PME items required for a particular construction activity would be located at the notional or probable source position of work fronts where such activity is to be performed.  The locations of work fronts are shown in Appendix 4.3.  To predict the noise level, PME has been organised into groups required for each discrete task of the construction works. The sound pressure level (SPL) of each construction task has been calculated, depending on the number of plant items involved and the distance from the NSR. A positive 3 dB façade correction has been added to the predicted noise levels to account for the façade effect at each assessment point. The noise levels at the NSRs have then been predicted by adding up the SPLs of all concurrent construction tasks from the Project and other concurrent projects identified during the course of the EIA study within the study area.  Notional sources that are at distances greater than 300 m from the NSRs have been excluded from the assessment.

4.6.1.4          The unmitigated construction noise impacts at the identified NSRs have been predicted accordingly. Practicable direct mitigation measures including the use of quieter equipment, movable noise barriers, noise barrier, enclosures and quieter alternative methods have been considered if exceedance of relevant criteria is predicted.  Appropriate correction factors for barrier effect have been adopted in accordance with Section 2.10 of the GW-TM.  In cases where the mitigated noise levels still exceeded the relevant criteria, the duration of the noise exceedance would be estimated.

4.7                  Prediction and Evaluation of Environmental Impacts

4.7.1.1          For normal daytime working hours, exceedances of the construction noise criteria for residential uses and educational institution were predicted at all of the residential NAPs with no mitigation measures in place.  Details of the unmitigated construction noise assessment are presented in Appendix 4.5 with the results summarized in Table 4.4. With noise exceedance predicted, direct noise mitigation measures are required to alleviate the construction noise impact on the affected NSRs.

Table 4.4         Summary of Unmitigated Construction Noise Levels

NAP ID

Daytime Noise Criterion

Leq (30mins), dB(A)

Predicted Unmitigated Construction Noise Levels, Leq (30mins), dB(A)

Max. Noise Exceedance, dB(A)

HPRC43

75

69 - 80

5

LYMP

70

(65 during examination)

(1)&(2)

75 - 95

25

(30 during examination)

HPRC53A

75

87 - 89

14

HPRCV1

75

74 – 85

10

HPRCV2

75

67 - 80

5

HPRE21C

75

68 - 83

8

HPRE79A

75

66 - 84

9

HPRE75B

75

70 - 91

16

HPRE81

75

69 - 96

21

MWT145

75

60 - 94

19

THT

75(1)&(3)

55 - 72

-

Notes:

(1)      Places of worship and performing arts centres are NSRs under the EIAO-TM but there are no specific daytime construction noise standards for these types of NSRs.

(2)      Considering that courses, workshops and talks would be held occasionally in the Jockey Club Lei Yue Mun Plus for education purpose, noise criteria of 70 dB(A) and 65 dB(A) during examination are proposed for the construction noise impact assessment. 

(3)   A construction noise assessment criterion of 75 dB(A) is proposed for Tin Hau Temple. Reference has been made to the approved EIA report for Tseung Kwan O - Lam Tin Tunnel and Associated Works (EIAO Register No.: AEIAR-173/2013).

4.8                  Mitigation of Adverse Environmental Impacts

4.8.1               Mitigation Measures

4.8.1.1          The results of the construction noise assessment indicate that, there would be exceedance of the construction noise criteria at some of the NSRs in the absence of any mitigation measures.  The various mitigation options listed below have thus been considered:

·               Good site practices to limit noise emissions at the sources;

·               Use of quiet powered mechanical equipment;

·               Use of construction noise barriers to screen noise from construction plant; and

·               Scheduling of Noisy Activities.

4.8.1.2          The above mitigation measures would be implemented on work sites as good practices where appropriate.  Detailed descriptions of these mitigation measures are given in the following sections.

Good Site Practice

4.8.1.3          Although the noise mitigation effects are not easily quantifiable and the benefits may vary with site conditions and operating conditions, good site practices are easy to implement and do not impact upon the works schedule.  The site practices listed below should be followed during each phase of construction:

·               Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program;

·               Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction program;

·               Mobile plant, if any, should be sited as far from NSRs as possible;

·               Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum; and

·               Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs;

4.8.1.4          In addition, the “Recommended Pollution Control Clauses for Construction Contracts” published by the EPD should be adopted in the Contract Specification for the Contractors to follow and implement relevant measures and good site practices in minimising noise impact.

Quiet Powered Mechanical Equipment

4.8.1.5          To reduce the noise impacts at the affected NSRs during normal daytime working hours, mitigation measure such as the use of quiet PME is recommended.  The type of quiet PME adopted in this assessment is for reference only.  The contractors may adopt alternative quiet PME as long as it can be demonstrated that they would not result in construction noise impacts worse than those predicted in this assessment.

4.8.1.6          For the use of quiet plant associated with the construction works, reference has been made to QPME list available on the EPD website, which provides the SWLs for specific quiet PME or PME specification published by equipment manufacturer.   The items of QPME and the associated SWLs adopted for the assessment are listed in Table 4.5. 

Table 4.5         SWL of QPME Adopted for Construction Noise Mitigation

Works Area

Construction Activity

QPME/Quiet PME

QPME Reference Number

Model number

SWL, dB(A)

LF (Landing Facility)

Install pipe pile wall retain existing shore

Crane, mobile/barge mounted (diesel)

EPD-05690

KOBELCO CKS900

101

Grouting behind the pipe pile wall

Crane, mobile/barge mounted (diesel)

EPD-05690

KOBELCO CKS900

101

Construction of the breakwater, deck structure, wave absorption chamber and deck furniture

Crane, mobile/barge mounted (diesel)

EPD-05690

KOBELCO CKS900

101

Surface rock excavation

Breaker, excavator mounted (hydraulic)

-

Atlas Copco

MB1000

119 (1)

LP1

(Lookout Point 1)

Demolition of existing structure

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

Backfill

Compactor, vibratory

EPD-00054

Dynapac

LF 62

102

Beautification Works

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

LP2

(Lookout Point 2)

Beautification Works

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

LP4

(Lookout Point 4)

Demolition of existing structure

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

Beautification Works

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

LP5

(Lookout Point 5)

Demolition of existing structure

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

Backfill

Compactor, vibratory

EPD-00054

Dynapac

LF 62

102

Beautification Works

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

VP

(Viewing Platform)

Excavation

Excavator/loader, wheeled/tracked

EPD-05477

KOBELCO

SK30SR-6

91

CP

(Carp Platform)

Construction of Carp Platform

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

PA

(Pavilion)

Provision of Pavilion

Crane, mobile/barge mounted (diesel)

EPD-05690

KOBELCO CKS900

101

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

ST

(Streetscape Improvement)

Streetscape Improvement Works

Hand-held Percussive Breaker

EPD-04329

HILTI

TE 1000-AVR

99

Note:

(1)      Detail of noise emission and guaranteed SWL is available on the supplier’s website:

https://www.atlascopco.com/en-uk/mrba/products/excavator-attachments/Hydraulic-breaker/hydraulic-breakers/hydraulic-breaker-MB-1000

Temporary Noise Barriers

4.8.1.7          To alleviate the construction noise impact on the affected NSRs, temporary noise barriers would be erected to provide screening from the construction plant. 

4.8.1.8         Noise barriers will become more effective when located immediately adjacent to the working area, and can reduce the noise level by up to 5 dB(A) and 10 dB(A) for mobile and stationary plants, respectively.  Portable noise enclosure should be used, as far as practicable, to mitigate the noise impacts arising from the use of handheld breaker, air compressor, compactor (vibratory) and drill/grinder, hand-held electric at some work areas (i.e. works areas LP3, LP4, LP5 and ST) where locate very close to the NSRs. Use of noise enclosure can reduce the noise level by up to 15 dB(A). The Contractor will be responsible for design of the noise barrier and noise enclosure with due consideration given to the size of the PME and the requirement of intercepting the line of sight between the NSRs and PME.  The construction material of the noise barrier and the portable noise enclosure should have a minimum surface density of 10 kg/m2 and it should have no openings or gaps.  The typical configuration of noise barrier and portable noise enclosure is shown in Appendix 4.6. 

4.8.1.9          The plant inventory for the assessment of the mitigated scenario is presented in Appendix 4.7.

Scheduling of Noisy Activities to Avoid Noise Impact to LYMP

4.8.1.10    To minimise the construction noise impact on LYMP, the streetscape improvement works would not be carried out within 10 m from LYMP during the time when LYMP is used for any noise sensitive purposes, such as holding courses or workshops.  In addition, the beautification works at work areas LP1 would not be conducted during examination period. The Contractor should liaise with the operator of LYMP to obtain the updated schedule of courses, workshops and examination at the time conducting the relevant construction works.

4.8.1.11     With the use of QPME and noise barriers and scheduling noisy activities outside the time when LYMP is used for any noise sensitive purposes, such as holding courses or workshops, the mitigated construction noise levels at the representative NAPs would be in the range of 45 to 75 dB(A).  The predicted noise impacts at different NAPs are summarized in Table 4.6 with details of the calculations given in Appendix 4.8.  The results revealed that the construction noise levels at all NSRs would comply with the EIAO-TM daytime noise criterion after the implementation of the proposed noise mitigation measures.

Table 4.6         Mitigated Construction Noise Level

NAP ID

Daytime Noise Criterion

Leq (30mins), dB(A)

Predicted Mitigated Construction Noise Levels

Leq (30mins), dB(A)

Max. Noise Exceedance, dB(A)

HPRC43

75

55 - 62

-

LYMP

70

(65 during examination)

60 – 67

60 – 65 (during examination period)

-

HPRC53A

75

66 - 71

-

HPRCV1

75

66 - 75

-

HPRCV2

75

61 - 72

-

HPRE21C

75

65 - 75

-

HPRE79A

75

52 – 69

-

HPRE75B

75

55 - 75

-

HPRE81

75

59 - 75

-

MWT145

75

50 - 75

-

THT

75

45 - 54

-

 

4.8.2               Cumulative Mitigated Construction Noise Level

4.8.2.1          As discussed in Section 4.5, the only concurrent project that may pose cumulative construction noise impacts would be the Lei Yue Mun Village Sewerage project. Based on the information available for the LYM Waterfront Enhancement Project and the preliminary information provided by DSD at the time of preparing this EIA report, the only works that would have an interface with the LYM Waterfront Enhancement Project are the construction of underground sewers to LYM Village along Lei Yue Mun Hoi Pong Road Central and Lei Yue Mun Hoi Pong Road East. 

4.8.2.2          Notwithstanding the above, a preliminary environmental review (PER) for the Lei Yue Mun Village Sewerage project has been undertaken by DSD. Based on the construction noise impact assessment conducted for the PER, construction activities, including breaking of pavement and reinstatement (concrete) would involve the use of PME. Excavation, pipe laying and backfilling would be carried out manually and no PME will be required for these activities.

4.8.2.3         Based on the plant inventory and the associated noise mitigation measures recommended in the PER for the Lei Yue Mun Village Sewerage project, cumulative construction noise impacts have been assessed and the predicted cumulative construction noise levels at the representative NAPs are summarized in Table 4.7.

Table 4.7         Mitigated Cumulative Construction Noise Level

NAP ID

Daytime Noise Criterion

Leq (30mins), dB(A)

Predicted Mitigated Construction  Noise Levels, Leq (30mins) , dB(A)

Max. Noise Exceedance, dB(A)

LYM Waterfront Enhancement

LYM Village Sewerage

Cumulative

HPRC43

75

55 - 62

56

56 - 63

-

LYMP

70

(65 during examination)

60 – 67

60 – 65 (during examination period)

71

71 – 72

 

2

(7  dB(A) during examination)

HPRC53A

75

66 - 71

65

65 - 72

-

HPRCV1

75

66 - 75

77

77 - 79

4

HPRCV2

75

61 - 72

49

49 - 72

-

HPRE21C

75

65 - 75

60

60 - 75

-

HPRE79A

75

52– 69

65

65 - 70

-

HPRE75B

75

55 - 75

71

71 - 76

1

HPRE81

75

59 - 75

77

77 - 79

4

MWT145

75

50 - 75

77

77 - 79

4

THT

75

45 - 54

43

43 - 54

-

4.8.2.4          Owing to the close proximity of the representative NAPs to the works areas of both Projects, the cumulative noise levels would exceed the EIAO daytime construction noise criteria at LYMP, HPRCV1, HPRE75B, HPRE81 and MWT145.

4.8.2.5          For the sewer laying works, the construction would normally be carried out section by section and the road breaking works would normally last for a short period of time only. It is anticipated that the duration of exceedance would at most be less than two hours per day over a period of approximately one week for each NSR, depending on the exact construction method to be adopted by the sewerage works contractor.

4.8.2.6        The construction works of the Lei Yue Mun Village Sewerage project are still being planned and only a preliminary construction programme is available for reference at the time of this assessment.  Based on the information of Lei Yue Mun Village Sewerage project provided by DSD, some of the sewerage construction works would be carried out within the works area of streetscape improvement works (i.e. along Hoi Pong Road Central and Hoi Pong Road East).  Since conducting sewerage construction works and streetscape improvement works may involve repeated construction works at the same location, the ArchSD would closely liaise with DSD and their contractors in planning the interfacing works to minimise duplicated/concurrent construction works, including exploring the possibility of entrusting the streetscape improvement works to DSD, so as to minimise nuisance to nearby sensitive receivers such as residents, shops, restaurants and educational institution as far as practicable.  Before commencing noisy construction works, such as road breaking works, in the vicinity of the NSRs, the Contractor would closely liaise with the affected NSRs to keep them informed of the works and should strive to complete the works in the shortest time possible.  To minimise nuisance to nearby educational institution and seafood restaurants, noisy construction works would not be carried out during the examination period of the educational institution and the peak business hour of the restaurant.

4.9                  Evaluation of Residual Impacts

4.9.1.1         With the implementation of all feasible noise mitigation measures, there would be no exceedance of the construction noise criteria due to the Project.  However, cumulative construction noise levels are found to exceed the EIAO daytime construction noise criteria at LYMP, HPRCV1, HPRE75B, HPRE81 and MWT145. The predicted exceedance from cumulative impacts is mainly due to the limited separation between the NSRs and the proposed works areas of the Project and the concurrent project.  All practicable direct mitigation measures have been exhausted to minimise the impacts. 

4.9.1.2         It is recommended that the Contractor liaise closely with the contractor of the Lei Yue Mun Village Sewerage project to avoid duplicated/concurrent works near the concerned NSRs as far as practicable.

4.10             Environmental Monitoring and Audit

4.10.1.1     Noise monitoring is recommended as part of the environmental monitoring and audit (EM&A) programme for the construction phase of the Project to check compliance with the daytime construction noise criterion at a frequency of once a week.  The implementation of the recommended mitigation measures for daytime construction activities should also be audited as part of the EM&A programme.  Details of the EM&A requirements are provided in the EM&A Manual. Given that residual cumulative noise impacts were predicted at some NSRs, it is also recommended that the Contractor make necessary provisions for responding to potential complaints from nearby NSRs, such as setting up a hotline and/or community liaison group. 

4.11             Conclusion

4.11.1.1     This assessment has presented the construction noise impacts of the Project during normal daytime working hours.  The assessment results indicate that the mitigated noise levels at all NSRs would comply with the noise criteria set out in the EIAO-TM with the implementation of the proposed noise mitigation measures, including the use of QPME, deployment of construction noise barriers and portable noise enclosure and scheduling of noisy activities outside the time when LYMP is used for any noise sensitive purposes, such as holding course or workshop.  Adverse noise impact during construction phase is not anticipated.

4.11.1.2     Before commencing noisy construction works, such as road breaking works, in the vicinity of the NSRs, the Contractor should closely liaise with the occupants of the affected NSRs to keep them informed of the works and should strive to complete the works in the shortest time possible.  To minimise nuisance to operators of nearby seafood restaurants, noisy construction works should not be carried out during the peak business hour of the restaurant as a precautionary measure. The streetscape improvement works should not be carried out within 10 m from LYMP during the the time when LYMP is used for any noise sensitive purposes, such as holding course and workshop. The Contractor should also liaise with the operator of LYMP to obtain the examination schedule and should not carry out the Beautification Works at Look out Point 1 during examination period. 

4.11.1.3     Weekly noise monitoring to check compliance with the daytime noise criterion and auditing of the implementation of noise mitigation measures are recommended as part of the EM&A programme for the construction phase of the Project.

4.11.1.4     The Project is not a noise pollution source and therefore noise impact arising from the project during operation phase is not anticipated.

 



[1] http://www.epd.gov.hk/epd/english/environmentinhk/noise/qpme/index.html