3.                            CONSIDERATION OF ALTERNATIVES

3.1                        Need of the Project

3.1.1                  Yuen Long Town Nullah (YLTN) was constructed in the 1960s for alleviation of flooding problem. With the increasing aspirations for a better living environment, the local residents of Yuen Long are requesting the Government to improve the early design of the YLTN, which is an old concrete-lined nullah and considered no longer in line with the modern with greenery changing townscape of Yuen Long. Moreover, odour from expedient connection / illegal discharge / dry-weather contaminated water (e.g. from street cleansing) discharging into the nullah would cause nuisance to nearby residents. To improve the environment, this Project is proposed to resolve the odour problem and prevent the DWF flowing into the nullah in the first stage of improvement works. Later the landscaping and beautification works will be constructed in Barrage Scheme soon after the completion of DWFI system.

3.1.2                  Some drainage projects including building fabric dam at the downstream section, the Yuen Long Bypass Floodway and other drainage improvement works were carried out in 1990s to improve the flooding problem at Yuen Long Town Centre. Upon completion of the drainage projects, part of the flow from upper catchment has been diverted away from Yuen Long Town.  The flow in Yuen Long Town has been greatly reduced and some of the nullahs become polluted open channels with minimal base flow. 

3.1.3                  In view of the requests from the District Council and members of the public to look for opportunities to improve the drainage system and enhance the environment, the Drainage Services Department (DSD) commissioned the Agreement No. CE 39/2006 (DS) “Rehabilitation of Yuen Long Town Nullahs - Feasibility Study” to investigate different options for improving the environmental conditions of the YLTN.  The Study identified that rehabilitation of the Town Centre Section is the top priority as high pedestrian flow compounded with severe water quality problem in this area have created an undesirable environment.  The findings of the Study provide the basis of scope of improvements for YLTN for the current Project.

3.1.4                  Under this Project, the polluted DWF to the nullah will be intercepted and treated in the YLEPP (upgraded from existing YLSTW). Upon completion of the DWFI system under the Project, the residents living along the Town Centre Section of YLTN will be immediately benefited from the elimination of odour problem due to polluted DWF. In addition, by intercepting the polluted DWF for proper treatment, the downstream ecologically sensitive Shan Pui River and Inner Deep Bay will be benefited by the improved water quality.

3.1.5                  Regulation enforcement (e.g. Water Pollution Control Ordinance) is one of the strategies to resolve the expedient connection / illegal discharge and subsequent water pollution and odour problems at sources. The whole Yuen Long catchment consists of 5 main streams with an approximate area over 13 km2. The expedient connection/illegal discharge may come from various activities and buildings in this large area. Although identification of expedient connections is being carried out for subsequent enforcement works, the pollution sources could not be completely eliminated due to difficulties in finding sources and existence of some non-point sources. To control the polluted flow entering the nullah, DWFI system is considered the most direct and effective measures. Given there would be some constraints of the expedient connection identification and execution, downstream control measures (i.e. DWF interception and treatment) are also required. DSD and EPD will work together to improve the water quality and minimize odour problem of YLTN with this two-pronged approach.   

3.2                        Environmental Benefits

 

Alleviation of Odour Nuisance

 

3.2.1                  Odour have been a problem of YLTN due to the polluted water in recent decades. With the interception of partial DWF in YLTN under this Project, the odour nuisance to the residents nearby will be alleviated. 

 

Water Quality Improvement of Downstream Watercourse

3.2.2                  The polluted DWF in the YLTN is originally towards Shan Pui River and subsequently to Inner Deep Bay without any treatment that may deteriorate the water quality of these ecological sensitive water bodies. By intercepting the polluted DWF for proper treatment, the water quality of ecologically sensitive Shan Pui River and Inner Deep Bay can be improved.

 

Greening Enhancement

 

3.2.3                  Green roof, vertical greening and shrub / tree planting will be provided for the DWF pumping station. The maintenance access and footpaths of the pumping station will be paved with soft paving materials (i.e. Grasscrete).

 

Blue-green Infrastructure

 

3.2.4                  Less polluted upstream DWF (i.e. from Kung Um Road Nullah) is selected to maintain water flow in YLTN which will be integrated with the landscaping and beautification works conducted in a separated DSD’s project “Yuen Long Barrage Scheme – Investigation, Design and Construction” as blue-green elements for YLTN revitalization. The revitalized YLTN would be a blue-green infrastructure and promoted as a scenic and water-friendly place for leisure for the residents and public.  

3.3                        Consideration of “Without Project” Alternative

3.3.1                  The “Without-Project” scenario considers not implementing the recommended improvement of YLTN.      

3.3.2                  More polluted DWF generation is expected due to population growth and development in Yuen Long.  If the proposed Project is not implemented, more polluted DWF will be discharged to the nullah resulting in further worsening of water quality and odour problems as well as deterioration of the nullah appearance.   

3.3.3                  Based upon the above, the “Without-Project” option is not preferred due to the consideration of potential worsening of odour and water quality problems.

3.4                        Consideration of Alternative Design and Layout

 

Selection of DWF for Interception and Treatment

3.4.1                  The proposed discharge standard of Yuen Long Effluent Polishing Plant (YLEPP) was reviewed as reference to examine the necessity for DWF interception, as extracted in Table 3.1:

 

Table 3.1         Proposed Discharge Standard of Yuen Long Effluent Polishing Plant

 

Parameter

Unit

Concentration

Remarks

5-day Biochemical Oxygen Demand (BOD5)

mg/L

10

95 Percentile

Total Suspedned Solid (TSS)

mg/L

10

95 Percentile

Ammonia Nitrogen (NH3-H)

mg/L

2

Annual average

Total Nitrogen (TN)

mg/L

10

Annual average

Total Phosphorus (TP)

mg/L

1

Annual average

E. coli

Count/100mL

100

Monthly Geometric Mean

 

 

3.4.2                  In accordance with the River Water Quality in Hong Kong published by the Environment Protection Department (EPD), the Water Quality Index (WQI) is based on the assessment level of dissolved oxygen, ammonia-nitrogen content and the Biochemical Oxygen Demand. The water quality is classified in the range from “Very Bad” to “Excellent”. The water sampling of DWF in YLTN has been conducted in 2017. The results and the corresponding WQI at each monitoring location is summarized in
Table
3.2.


Table 3.2         Water Sampling Results

 

Kung Um Road Nullah

San Hui Nullah

End of Town Centre Section

Western Nullah

Eastern Nullah

WQI (Water Quality)

9 (Fair)

11 (bad)

13 (bad)

11 (bad)

15 (very bad)

DO(mg/l)

5.46

3.80

1.86

2.38

1.28

SS (mg/l)

14.70

7.45

14.60

4.39

31.1*

Ammonia as N (mg/l)

3.55

12.77*

3.79

1.79

8.80*

Total Kjeldahl Nitrogen (mg/l)

4.41

13.90

5.01

2.94

11.33

Total Phosphorus (mg/l)

0.53

2.59*

0.64

0.32

1.15

BOD (mg/l)

8.47

7.15

14.20

6.20

64.4*

Note: *Water quality exceed the proposed discharge standard of YLEPP

3.4.3                  As illustrated, the water quality of DWF in San Hui Nullah, Town Centre Section and Eastern Nullah is relatively poor. They are recommended to be intercepted and treated at YLEPP. The water quality of DWF in West Nullah is better than the proposed treatment standards of YLEPP. Therefore, it is recommended to be intercepted but not to be treated in YLEPP. The water quality of DWF in Kung Um Road Nullah is the best among the branches. It is recommended as flowing water remained in YLTN.

 

Alternative Location of Discharge Points of the Proposed DWFI System

3.4.4                  According to the recommendations during the feasibility study stage, the DWF intercepted by the proposed DWFI system will be discharged into YLEPP for treatment. The feasibility of different discharge options taking into consideration of the increase in DWF to be intercepted is investigated.  Four proposed options are described below:

 

(a)                Option 1   Discharge all DWF to YLEPP (original scheme)

 

(b)                Option 2  Discharge 11,000 m3/day DWF to YLEPP and 7,000 m3/day to San Wai Sewage Treatment Works (SWSTW)

 

(c)                Option 3   Discharge all DWF to SWSTW with upgrading of existing sewage pumping station (SPS)

 

(d)                  Option 4   Discharge all DWF to SWSTW via a proposed pumping station

3.4.5                  Options 2, 3 and 4 are proposed to convey part or all DWF to SWSTW. However, these options would impose significant cost impact and interface issues with the existing sewerage facilities due to the extensive upgrading works required and are thus not recommended.  The potential impacts on existing sewerage system due the proposed options are summarized in Table 3.3 below:

Table 3.3         Impacts on Existing Sewerage System

Impact on

Option 1

Option 2

Option 3

Option 4

YLEPP

·      Additional operation cost (18,000 m3/d)

·      Additional  operation cost (11,000 m3/d)

N/A

N/A

SWSTW

N/A

·      Upgrade  treatment capacity by 7,000 m3/d

·      Additional operation cost

·      Upgrade  treatment capacity by 18,000 m3/d

·      Additional operation cost

·      Upgrade  treatment capacity by 18,000 m3/d

·      Additional operation cost

Yuen Long South SPS (YLS SPS)

N/A

·      Upgrade  pumping capacity by 7,000 m3/d

·      Additional operation cost

N/A

N/A

Ping Shun Street SPS (PSS SPS)

N/A

N/A

·      Interface with MTR Development

·      Upgrade  pumping capacity by 18,000 m3/d

·      Additional operation cost

N/A

Ha Tsuen SPS (HT SPS)

N/A

·      Interface with HT SPS expansion works

·      Upgrade  pumping capacity by 7,000 m3/d

·      Additional operation cost

·      Interface with HT SPS expansion works

·      Upgrade  pumping capacity by 18,000 m3/d

·      Additional operation cost

·      Interface with HT SPS expansion works

·      Upgrade  pumping capacity by 18,000 m3/d

·      Additional operation cost

Existing rising main and sewer

N/A

·      Between YLS SPS and HT SPS (34 km)

·      Between HT SPS and SWSTW (1.9 km)

·      Between PSS SPS and HT SPS (34 km)

·      Between HT SPS and SWSTW (1.9 km)

·      Between HT SPS and SWSTW (1.9 km)

 

3.4.6                  In addition, it is anticipated that the quantity of the DWF, particularly from the upstream of YLTN (at the junction of Kiu Hing Road and Tai Shu Ha Road West), would be subsequently improved after completion of the sewerage works at the area.  Eventually, the DWF at upstream (i.e. Kung Um Road Nullah and San Hui Nullah) is expected to be cleaner and probably less DWF is required to be treated.  In view of this, upgrading of substantial existing sewerage facilities to handle the DWF might not be a cost-effective option.

 

Conclusion and Recommendation for Location of Discharge Point

3.4.7                  It is considered that conveying all DWF from YLTN to YLEPP, i.e. Option 1, would be the most appropriate choice as the final scheme in this Project.

3.5                        Construction Related Aspects

 

Construction Activities

3.5.1                  Construction of the rising mains, DWFI system and pumping station generally involves construction activities such as site clearance, excavation, erection of formwork, steel fixing, concreting and backfilling. 

3.6                        Consideration of Alternative Construction Methods and Sequences of Works

 

Comparison of the Environmental Benefits and Dis-benefits of Alternative Construction Methods

 

Pumping Station

3.6.1                  Potential alternative construction method includes offsite precast structures for pumping station.  The benefit of offsite precast structures is that there will be less environmental nuisance to nearby sensitive receivers during construction. 

3.6.2                  Offsite precast method will be proposed to most part of the pumping station structure to minimize the environmental impacts. The remaining small parts will be cast in-situ where environmental impacts to air quality, noise and water quality, the duration and extent of the impacts are generally temporary and localised.  It is anticipated that the environmental impacts can be mitigated by appropriate measures.

 

Dry Weather Flow Interception (DWFI) System

3.6.3                  Major parts of the DWFI system are u-channel cast-in together with concrete mass for nullah wall stabilization. Since the concrete mass is 5m in width and about 1.5m in depth, the size of the precast concrete mass will be too large for transportation through the limited and narrow access into the nullah. Off-site precast units are considered not practical and cost effective.  Although in-situ construction could pose environmental nuisance such as constructional noise, dust and water quality impacts, it is expected that the duration and extent of the impacts are temporary and localized given the limited section to be constructed.  It is anticipated that the potential environmental impacts can be alleviated by proper implementation of appropriate mitigation measures.  Therefore, conventional construction method of in-situ construction of DWFI system is considered more suitable and practical and will be adopted.

 

Rising Main

3.6.4                  The use of ‘no-dig’ trenchless technique such as pipe jacking was considered necessary below existing box culverts and central divider because open trench techniques would require major modification works of the structures on top (Figure 2.1). 

3.6.5                  Outside existing structures, the use of ‘no-dig’ trenchless technique was considered not necessary/practicable as the Project Site is highly developed and is in close proximity to various types of high risk underground utilities. Open cut construction method is considered for the sections outside existing structures and the associated potential environmental impacts can be mitigated by adopting standard mitigation measures.

 

Consideration of Alternative Construction Sequence

3.6.6                  The construction works of DWFI system, including u-channel and DWF interceptors, will not be undertaken simultaneously in adjoining sections to reduce the construction impacts to nearby sensitive receivers.  This approach aims to avoid heavy construction concentrated in one area in order to strike a balance between the need to control the magnitude of environmental impact while not hindering the overall programme of the Project. 

3.6.7                  It will be necessary to carry out careful phasing of the works to re-connect the proposed DWFI system with existing pipes to ensure satisfactory diversion of flows without the risk of backing up of drain.  It is thus recommended that the connection with existing pipes should be carried out during dry season to reduce the risk.

3.6.8                  With regard to nullah excavation, instead of directly excavating the nullah bed which will generate sediment plumes in river water and lead to water quality impacts, the excavation of nullah bed for this Project will be carried out within an enclosed area surrounded by concrete blocks, sandbag barriers or other appropriate measures.  By adopting this method, sediments generated from the excavation works will be confined within the enclosed area, thus reducing the potential water quality impacts due to dispersal of suspended sediments.  Temporary diversion works of flow will be carried out before the commencement of excavation works within the nullah.  To further reduce the potential water quality impacts, excavation works in the nullah will only be undertaken in dry condition.