7.                       WASTE management AND LAND CONTAMINATION

 

7.1                   Introduction

 

7.1.1              This Section identifies the potential waste arising from the construction and operation of the Project and assesses the potential environmental impacts associated with waste handling and disposal.  The main issues include the following:

 

·         Handling and disposal of construction and demolition (C&D) materials arising from nullah modification, excavation and construction works; and

·         Management of chemical waste, general refuse and floating refuse.

 

7.1.2              Waste avoidance, minimisation, reuse and recycling, storage, collection, transport and disposal schemes have been examined and appropriate measures for waste reduction and management have been proposed.

 

7.1.3              This Section also identifies and assesses any potential land contamination issues arising from the Project and to propose remediation measures if necessary.

 

7.2                   Relevant Legislation, Policies, Standards and Criteria

 

7.2.1              The following discussion on legislative requirements and evaluation criteria applies to both the construction and operation phases of the Project.  The criteria and guidelines for evaluating potential waste management implications are laid out in Annexes 7 and 15 of the EIAO-TM under the EIAO (Cap 499).  The following legislation covers, or has some bearing upon the handling, treatment and disposal of the wastes generated from the construction and operation of the Project.

 

·         Waste Disposal Ordinance (Cap.354);

·         Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C);

·         Land (Miscellaneous Provisions) Ordinance (Cap.28); and

·         Public Health and Municipal Services Ordinance (Cap.132) – Public Cleansing and Prevention of Nuisances Regulation.

 

Waste Disposal Ordinance (Cap 354)

 

7.2.2              The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes, with waste defined as any substance or article, which is abandoned.  Construction waste is not directly defined in the WDO but is considered to fall within the category of ‘trade waste’.  Trade waste is defined as waste from any trade, manufacturer or business, wasted building, civil engineering materials, but does not include animal waste.

 

7.2.3              Under the WDO, wastes can only be disposed of at a licensed site.  The WDO provides for the issuing of licences for the collection and transport of general wastes.  Licences are, however, not currently issued for the collection and transport of construction waste or trade waste.  For general waste there is no charge and this will need to be disposed of in a licensed facility.

 

7.2.4              The Waste Disposal (Charges for Disposal of Construction Waste) Regulation defined construction waste as any substance, matters or things that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned.  It does not include any sludge, screening or matter removed in or generated from any desludging, desilting or dredging works.

 

7.2.5              The Construction Waste Disposal Charging Scheme entered into operation on 1 December 2005.  Starting from 1 December 2005, the main contractor who undertakes construction work under a contract with value of HK$1 million or above is required to open a billing account solely for the contract for waste disposal.  Application shall be made within 21 days after the contract is awarded.  

 

7.2.6              Depending on the percentage of inert materials in the construction waste, inert construction waste can be disposed of at public fill reception facilities.  However, mixed construction waste can be disposed of at construction waste sorting facilities, landfills and Outlying Islands Transfer Facilities which have different disposal costs.  The scheme encourages reducing, reusing and sorting of construction waste such that the waste producer can reduce their disposal fee.  Table 7.1 summarises the government construction waste disposal facilities, types of waste accepted and disposal cost.

 

Table 7.1        Government Facilities for Disposal of C&D Materials

Government Waste Disposal Facilities

Type of Construction Waste Accepted

Charge (HK$/Tonne)

Public fill reception facilities

Consisting entirely of
inert construction waste++

$71

Sorting facilities

Containing more than 50% by weight of inert construction waste++

$175

Landfills@

Containing not more than 50% by weight of inert construction waste++

$200

Transfer Facilities@

Containing any percentage of
inert construction waste++

$200

# Except for the Outlying Islands Transfer Facilities, the minimum charge load is 1 tonne, i.e. if a load of waste weighs 1 tonne or less, it will be charged as 1 tonne. A load of waste weighing more than 1 tonne will be charged at 0.1 tonne increment. For Outlying Islands Transfer Facilities, the charge is $20 per 0.1 tonne and the minimum charge load is 0.1 tonne.

++ Inert construction waste means rock, rubble, boulder, earth, soil, sand, concrete, asphalt, brick, tile, masonry or used bentonite.

@ If a load of waste contains construction waste and other waste, that load will be regarded as consisting entirely of construction waste for the purpose of calculating the applicable charge. 

 


Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C)

 

7.2.7              Chemical waste as defined under the Waste Disposal (Chemical Waste) (General) Regulation includes any substance being scrap material, or unwanted substances specified under Schedule 1 of the Regulation, if the specified substance or chemical occurs in such a form, quantity or concentration so as to cause pollution or constitute a danger to health or risk of pollution to the environment.

 

7.2.8              A person should not produce, or cause to be produced, chemical wastes without registration with the Environmental Protection Department (EPD).  Chemical wastes must either be treated using on-site facility licensed by EPD or be collected by a licensed collector for off-site treatment at a licensed facility.  Under EPD Regulation, the waste producer, collector and disposal facility must sign all relevant parts of a computerised trip ticket for each consignment of waste.  The computerized system is designed to allow the transfer of wastes to be traced from cradle-to-grave.

 

7.2.9              The EPD Regulation prescribes storage facilities to be provided on-site which include labelling and warning signs.  To reduce the risks of pollution and danger to human health or life, the waste producer is required to prepare and make available written emergency procedures for spillage, leakage or accidents arising from the storage of chemical wastes.  They must also provide their employees with training on such procedures.

 

Land (Miscellaneous Provisions) Ordinance (Cap 28)

 

7.2.10          The inert portion of C&D materials (also called public fill) may be taken to public fill reception facilities.  Public fill reception facilities usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the public fill reception facilities to obtain Dumping Licences.  The licences are issued by CEDD under delegated authority from the Director of Lands.

 

7.2.11          Individual licences and windscreen stickers are issued for each vehicle involved.  Under the licence conditions, public fill reception facilities will only accept earth, soil, sand, rubble, brick, tile, rock, boulder, concrete, asphalt, masonry or used bentonite.  In addition, in accordance with paragraph 11 of DEVB TC(W) No. 6/2010 “Trip Ticket System for Disposal of Construction and Demolition Materials”, the Public Fill Committee will advise on the acceptance criteria (e.g. no mixing of construction waste, nominal size of the materials less than 250mm, etc).  The material will, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable by the public fill reception facility supervisor.

 


Public Health and Municipal Services Ordinance (Cap 132) – Public Cleansing and Prevention of Nuisances Regulation

 

7.2.12          This Regulation provides a further control on the illegal dumping of wastes on unauthorised (unlicensed) sites.

 

Other Relevant Guidance

 

7.2.13          Other guideline documents which detail how the Contractor will comply with the WDO and its associated regulations include:

 

·         Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat, Hong Kong Government;

·         Chapter 9 - Environment (1999), Hong Kong Planning Standards and Guidelines, Hong Kong Government;

·         New Disposal Arrangements for Construction Waste (1992), EPD & CED, Hong Kong SAR Government;

·         Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), EPD, Hong Kong Government;

·         Works Branch Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site, Works Branch, Hong Kong Government;

·         WBTC No. 2/93, Public Dumps, Works Branch, Hong Kong Government;

·         WBTC No. 2/93B, Public Filling Facilities, Works Branch, Hong Kong Government;

·         WBTC No. 16/96, Wet Soil in Public Dumps, Works Branch, Hong Kong Government;

·         WBTC Nos. 4/98 and 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects, Works Bureau, Hong Kong SAR Government;

·         WBTC Nos. 25/99, 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Sub-committee Papers; Works Bureau, Hong Kong SAR Government;

·         WBTC No. 12/2000, Fill Management; Works Bureau, Hong Kong SAR Government;

·         WBTC No. 19/2001, Metallic Site Hoardings and Signboards, Works Bureau, Hong Kong SAR Government;

·         WBTC No. 11/2002, Control of Site Crusher, Works Bureau, Hong Kong SAR Government;

·         WBTC No. 12/2002, Specification Facilitating the Use of Recycled Aggregates. Works Bureau, Hong Kong SAR Government;

·         ETWB TC(W) No. 19/2005 Environmental Management on Construction Site; Environment, Transport and Works Bureau, Hong Kong SAR Government.

·         DEVB TC(W) No. 6/2010, Trip Ticket for Disposal of Construction and Demolition Materials;

·         DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness;

·         DEVB TC(W) No.2/2011, Encouraging the Use of Recycled and Other Green Materials in Public Works Projects;

·         DEVB TC(W) No. 9/2011, Enhanced Control Measures for Management of Public Fill; and

·         Hong Kong Blueprint for Sustainable Use of Resources 2013-2022, Environment Bureau, May 2013;

·         Project Administration Handbook for Civil Engineering Works (2014 Edition) – Section 4.1.3 relating to construction and demolition materials.

 

7.3                   Assessment Methodology

 

7.3.1              The potential environmental impacts associated with the handling and disposal of waste arising from the construction and operation of the Project were assessed in accordance with the criteria presented in Annexes 7 and 15 of EIAO-TM and summarised as follows:

 

·         Estimation of the types and quantities of the wastes to be generated based on information provided by the Engineering Design Team and the relevant research and studies on waste arisings;

·         Assessment of the secondary environmental impacts due to the management of waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges and traffic; and

·         Assessment of the potential impacts on the capacity of waste collection, transfer and disposal facilities.

 

7.4                   Expected Waste Sources

 

Introduction

 

7.4.1              The proposed improvement works include the following construction activities:

 

·         Excavation of the nullah;

·         Construction of DWFI system;

·         Laying of rising mains; and

·         Construction of DWF pumping station

 

7.4.2              Construction activities will result in the generation of a variety of C&D materials.  The C&D materials are usually mixed consisting of inert components (public fill) such as soil, rock, concrete, brick, and asphalt etc and non-inert components (C&D waste) comprising metal, timber, paper, plastic and general refuse.  Chemical waste may also arise as a result of construction activities.  Floating refuse may arise from litter at upstream and floating refuse from Shan Pui River through tidal water during heavy rain. The likely waste generated from the proposed construction works can be classified into the following categories:

 

·         C&D materials;

·         Chemical waste;

·         General refuse; and

·         Floating refuse

 

7.4.3              River sediment will not be excavated for the construction of the Project as excavation works will be confined to the level above the river sediment layer (i.e. only concrete, soil and rock which were used as filled materials for the YLTN will be excavated).

 

7.4.4              During operation period, only a small amount of silt material and debris will be generated from the maintenance of the DWFI and nullah, while small amount of screenings and chemical waste will be generated from the routine operation and maintenance of the DWF pumping station.

 

7.4.5              Handling and disposal of the above mentioned wastes may cause environmental impacts and nuisance if it is not properly managed.

 

7.5                   Waste Management Assessment

 

Construction Phase
 
Excavated Waste Materials

 

7.5.1              The majority of C&D materials generated from the Project will arise during the construction of the DWFI system, rising mains and DWF pumping station.  It is expected that most of this material will be broken pieces of concrete, soil and rock from ground breaking and excavation works.  A preliminary estimate of the C&D materials generated, reused and disposed during construction is shown in Table 7.2.

 

7.5.2              Most of the C&D materials are inert and approximately 29% of the materials can potentially be reused on-site.  For example, the generated soil can be stockpiled for later reuse for backfilling.   

 

7.5.3              However, there is limited potential to reuse the excavated concrete.  The surplus inert C&D materials will be disposed at Tuen Mun Area 38 Fill Bank via New Territories Circular Road.  It is estimated that a total of 2 truck trips per day will be required to dispose these materials off-site ([1]).   In addition, it is estimated that approximately 700 m3 of C&D wastes will be generated and disposed of at WENT Landfill via Nim Wan Road.

 

7.5.4              With proper implementation of good site practices and mitigation measures, no unacceptable environmental impacts are anticipated from management of the C&D materials generated.

 


Table 7.2        Estimated Quantities of C&D Materials generated, reused and disposed during Construction

 


Scope of Works

C&D Material (Excavated Materials) Arisings (m3)

Reuse On-site (m3) (see Note 1)

Surplus C&D Materials (m3) for Off-site Disposal

C&D Waste (m3)

Chemical Wastes

General Refuse

Floating Refuse

Construction of DWFI System

11,550

2,310

9,240

500

50 litres per month

(See Note 2)

32.5 kg per day (See Note 3)

(See Note 4)

Construction of Rising Mains

2,000

1,774

226

100

Construction of DWF Pumping Station

1,702

340

1,362

100

Total

15,252

4,424

10,828

700

Notes:

1                           Suitable rock should be reused as backfilling materials.

2                           The amount of chemical waste will be dependent on the contractor’s on-site maintenance programme and the number of equipment and vehicles used on-site. Chemical waste should be collected by licensed contractor and properly disposed of at approved chemical waste treatment facilities.  Chemical waste will be generated throughout the construction period.

3                           The amount of general refuse will dependent on the contractor’s operating procedures and housekeeping practices as well as the size of the workforce on-site. All such wastes should be sorted, reused and recycled before disposal at designated outlets. General refuse will be generated throughout the construction period.

4                           With proper waste management and education, floating refuse arising from the construction activities is not anticipated. For floating refuse not generated from the Project (i.e. litter at upstream and floating refuse from Shan Pui River through tidal water), the quantity is not estimated under this EIA. However, any floating refuse trapped within the Project Area will be collected by contractor and disposed to landfill.

5                           All C&D waste should be sorted, reused and recycled as far as possible before disposal at designated landfill.

 

Chemical Waste

 

7.5.5              Wastes classified as chemical waste are listed in the Waste Disposal (Chemical Waste) (General) Regulation.  Where the construction processes produce chemical waste, the contractor must register with EPD as a chemical waste producer.  Chemical waste should be collected by licensed contractor and properly disposed of at approved chemical waste treatment facilities. 

 

7.5.6              Variety of chemicals would be used for carrying out construction activities.  These chemicals may include paints, petroleum products, spent lubricants, grease, mineral oil, solvent and other chemicals used during construction activities.  Accidental spillages of chemicals in the works area may contaminate the top soils on exposed ground/earth.  The contaminated soil particles may be washed away by construction site runoff causes water pollution.

 

7.5.7              Chemical wastes pose serious environmental and health and safety hazards if not stored and disposed of in an appropriate manner as outlined in the Chemical Waste Regulation.  These hazards include:

 

·         Toxic effects to workers;

·         Adverse effects on water quality from spills; and

·         Fire hazards.

 

7.5.8              The amount of chemical waste cannot be accurately predicted at this stage since it largely depends on the contractor’s housekeeping measure.  The amount is anticipated to be small (about 50 litres per month) and it is recommended that good housekeeping measures should be implemented to reduce the amount of chemical waste generated. The chemical wastes will be collected by licensed collector for the disposal of at licensed treatment facilities (e.g. Chemical Waste Treatment Centre (CWTC) at Tsing Yi) in accordance with relevant regulation and guideline.

 

7.5.9              With the incorporation of suitable arrangements for the storage, handling, transportation and disposal of chemical wastes under the requirements stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Waste, no unacceptable environmental impacts and hazards will result from the handling, transportation and disposal of chemical waste arising from the Project.

 

General Refuse

 

7.5.10          The presence of a construction site with workers and associated site office will result in the generation of general refuse (mainly consist of food waste, aluminium cans and waste paper) which requires off-site disposal.  The storage of general refuse has the potential to give rise to adverse environmental impacts.  These include odour if the waste is not collected frequently, windblown litter, water quality impacts if waste enters water bodies, and visual impact. 

 

7.5.11          Assuming up to 50 construction workers will be working on site at any one time, with a general refuse generation rate of 0.65 kg per worker per day ([2]), the amount of general refuse to be generated will be about 32.5 kg per day.  An adequate number of waste containers will be provided to avoid spillage of waste. 

 

7.5.12          Recyclable materials such as paper and aluminium cans will be separated and delivered to the local recyclers.  An adequate number of waste containers will be provided to avoid spillage of waste.  The non-recyclable waste will be collected and disposed of at the landfill on a regular basis.  With respect to the small quantity of general refuse to be transferred, it is not anticipated that it will cause unacceptable operational impacts to these facilities. 

 

Floating Refuse

 

7.5.13          The litter from the upstream may come down along the nullah to the Project Area. During heavy rain, the inflatable rubber dam may be deflated and floating refuse in Shan Pui River may be subsequently washed up onto the Project Area through tidal water. During construction phase, the construction workforce may also generate floating refuse (e.g. waste paper and empty containers) while working along the nullah. With proper waste management and training to workers, floating refuse arising from the construction activities is not anticipated. Any floating refuse trapped within the Project Area will be collected by contractor and disposed of to landfill.  

 

Operational Phase

 

7.5.14          During the operation phase, catch pits will be provided to collect the silt material and debris in order to avoid blockage of the drainage system and minimize the amount of silt material and debris flowing to the YLTN.  In addition, maintenance works will be carried out to remove the silt material and debris inside the drainage channels/pipes and the broken pieces of the damaged part of the drainage channels/pipes.  Such waste will be removed by manual means and disposed of to landfill after the clearance works.  No unacceptable environmental impacts are thus anticipated.

 

7.5.15          Mechanical screens will be installed at the inlet chamber of the DWF pumping station. Small amount of screenings will be generated. The screenings will be properly packed and handled within the pumping station structure to avoid odour and hygiene nuisance. The screenings will then be transported to landfill for disposal. Routine maintenance of the pumping station will generate a very small amount of chemical waste. The chemical wastes will be collected by licensed collector for the disposal of at licensed treatment facilities (e.g. Chemical Waste Treatment Centre (CWTC) at Tsing Yi) in accordance with relevant regulation and guideline. No unacceptable environmental impacts are thus anticipated.

 

7.6                   Mitigation Measures

 

Construction Phase

 

General

 

7.6.1              The HKSAR Government's construction and demolition waste management policy follows the same hierarchy as for other wastes i.e. in order of desirability: avoidance, minimisation, recycling, treatment and safe disposal of waste.

 

7.6.2              Training of construction staff should be undertaken by the contractor about the concept of site cleanliness and appropriate waste management procedures.  The contractor should develop and provide toolbox talk for on-site sorting of C&D materials to enhance workers’ awareness in handling, sorting, reuse and recycling of C&D materials.  Requirements for staff training should be included in the contractor’s Environmental Management Plan (EMP).

 

7.6.3              Good planning and site management practice should be employed to eliminate over ordering or mixing of construction materials to reduce wastage.  Proper storage and site practices will minimise the damage or contamination of construction materials.

 

7.6.4              Where waste generation is unavoidable, the potential for recycling or reuse should be rigorously explored.  If waste cannot be recycled, disposal routes described in the EMP should be followed.  A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be implemented.  In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills and to control fly-tipping, a trip-ticket system should be included.  One may make reference to DEVB TC(W) No. 6/2010 for details.

 

7.6.5              Regular cleaning and maintenance of the waste storage area should be provided.

 

On-site Sorting, Reuse and Recycling

 

7.6.6              All waste materials should be segregated into categories covering:

 

·         Inert C&D materials suitable for reuse on-site;

·         Inert C&D materials suitable for public fill reception facilities;

·         Recyclable C&D waste for recycling;

·         Remaining C&D waste for landfill;

·         Chemical waste; and

·         General refuse for landfill.

 

7.6.7              Proper segregation and disposal of construction waste should be implemented. Separate containers should be provided for inert and non-inert wastes.

 

7.6.8              Sorting is important to recover materials for reuse and recycling.  Specific area should be allocated for on-site sorting of C&D materials and to provide a temporary storage area for those sorted materials.  If area is limited, all C&D materials should at least be sorted on-site into inert and non-inert components. Non-inert materials (C&D waste) such as bamboo, timber, vegetation, packaging waste and other organic materials should be reused and recycled wherever possible and disposed of to the designated landfill only as a last resort.  Inert materials (public fill) such as concrete, stone, clay, brick, soil, asphalt and the like should be separated and reused in this or other projects (subject to approval by the relevant parties in accordance with the DEVB TC(W) No. 6/2010) before disposed of at a public filling facility operated by CEDD.  Steel and other metals should be recovered from demolition waste stream and recycled.

 

7.6.9              The reuse of inert materials such as soil, rock and broken concrete should be maximised.  Waste should be separated into fine, soft and hard materials.  With the use of a crusher. coarse materials can be crushed to make it suitable for use as fill materials where fill is required in the works.  This minimises the use of imported materials and maximizes the use of the C&D materials produced.

 

Excavated Materials

 

7.6.10          Control measures for temporary stockpiles on-site should be taken in order to minimize the noise, generation of dust, pollution of water and visual impact.  These measures include:

 

·         Surface of stockpiled soil should be regularly wetted with water especially during dry season;

·         Disturbance of stockpiled soil should be minimized;

·         Stockpiled soil should be properly covered with tarpaulin especially when heavy rain storms are predicted;

·         Stockpiling areas should be enclosed where space is available;

·         Stockpiling location should be away from the water bodies; and

·         An independent surface water drainage system equipped with silt traps should be installed at the stockpiling area.

 

7.6.11          The identification of final disposal sites for C&D materials generated by the construction works will be considered during the detailed design stage of the Project when the volume and types of C&D materials can be more accurately estimated.  The Public Fill Committee of CEDD should be consulted on designated outlets (e.g. public filling area) for public fill, whilst EPD should be consulted on landfills for C&D waste.  Disposal of C&D waste to landfill must not have more than 50% (by weight) inert material.  The C&D waste delivered for landfill disposal should contain no free water and the liquid content should not exceed 70% by weight.

 

7.6.12          In order to avoid dust or odour impacts, any vehicle leaving a works area carrying C&D waste or public fill should have their load covered up before leaving the construction site.

 

7.6.13          C&D materials should be disposed of at designated public fill reception facilities or landfills.  Disposal of these materials for the use at other construction projects is subject to the approval of the Engineer and/or other relevant reception authorities.  Furthermore, unauthorized disposal of C&D materials in particular on private agricultural land is prohibited and may be subject to relevant enforcement and regulating actions.  The disposal of public fill and C&D waste will be controlled through trip-ticket system in accordance with DEVB TC(W) No. 6/2010.

 

Chemical Waste

 

7.6.14          Where the construction processes produce chemical waste, the contractor must register with EPD as a chemical waste producer.  Wastes classified as chemical wastes are listed in the Waste Disposal (Chemical Waste) (General) Regulation. These wastes are subject to stringent disposal routes.  EPD requires information on the particulars of the waste generation processes including the types of waste produced, their location, quantities and generation rates.  A nominated contact person must be registered with EPD.  An updated list of licensed chemical waste collector can be obtained from EPD.

 

7.6.15          Storage, handling, transport and disposal of chemical waste should be arranged in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published by EPD, and should be collected by a licensed chemical waste collector.

 

7.6.16          Suitable containers should be used for specific types of chemical wastes. The containers should be properly labelled (in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations), resistance to corrosion, stored safely and closely secured.  Stored volume should not be kept more than 450 liters unless the specification has been approved by the EPD.  Storage area should be enclosed by three sides by a wall, partition of fence that is at least 2 m height or height of tallest container with adequate ventilation and space.

 

7.6.17          Hard standing, impermeable surfaces draining via oil interceptors should be provided in works area compounds.  Interceptors should be regularly emptied to prevent release of oils and grease into the surface water drainage system after accidental spillages.  The interceptor should have a bypass to prevent flushing during periods of heavy rain.  Oil and fuel bunkers should be bunded and/or enclosed on three sides to prevent discharge due to accidental spillages or breaches of tanks.  Bunding should be of sufficient capacity to accommodate 110% of the volume of the largest container or 20% of the total volume of waste, whichever is largest.  Waste collected from any grease traps should be collected and disposed of by a licensed contractor.

 

7.6.18          Lubricants, waste oils and other chemical wastes are likely to be generated during the maintenance of vehicles and mechanical equipment.  Used lubricants should be collected and stored in individual containers which are fully labelled in English and Chinese and stored in a designated secure place.  If possible, such waste should be sent to oil recycling companies, and the empty oil drums collected by appropriate companies for reuse or refill.

 

7.6.19          The registered chemical waste producer (i.e. the contractor) has to arrange for the chemical waste to be collected by licensed collectors.  The licensed collector should regularly take chemical waste to a licensed chemical waste treatment facility (such as the Chemical Waste Treatment Centre in Tsing Yi).  A trip ticket system operates to control the movement of chemical wastes.

 

7.6.20          No lubricants, oils, solvents or paint products should be allowed to discharge into water courses, either by direct discharge, or as contaminants carried in surface water runoff from the construction site.

 

General Works Waste

 

Concrete Waste

 

7.6.21          Dry concrete waste (considered as public fill) should be sorted out from the other wastes and recycled for reuse or sorted out for disposal at designated public filling facilities.

 

Wooden Materials

 

7.6.22          All wooden materials used on-site should be kept separately from other wastes to avoid damage and to facilitate reuse.  Timber which cannot be reused should be sorted out from other wastes and stored separately from all inert wastes before being disposed of to landfill.

 

7.6.23          Reusable steel or concrete panel shutters, fencing and hoarding and signboard should be used as a preferred alternative to items made of wood, to minimise wastage of wood.  Attention should be paid to WBTC No. 19/2001 - Metallic Site Hoardings and Signboards to reduce the amount of timber used on construction sites.  Metallic alternatives to timber are readily available and should be used rather than new timber.  Precast concrete units should be adopted wherever feasible to minimize the use of timber formwork.

 

7.6.24          Only waste material is needed to be taken to a landfill.  It should be separated from recyclable wood and steel materials.  As for all waste types, these materials should be reused on-site or other approved sites before disposal is considered as an option.  Disposal to landfill should only be considered as a final option.  Contractors are responsible for storage of re-useable materials on-site.

 

General Refuse

 

7.6.25          General refuse generated on-site should be stored in enclosed bins or skips and collected separately from other construction and chemical wastes and disposed of at designated landfill.  A temporary refuse collection point should be set up by the contractor to facilitate the collection of refuse by licensed contractors.  The chemical wastes will be collected by licensed collector for the disposal of at licensed treatment facilities (e.g. Chemical Waste Treatment Centre (CWTC) at Tsing Yi) in accordance with relevant regulation and guideline. The removal of waste from the site should be arranged on a daily or at least on every second day by the contractor to minimise any potential odour impacts, minimise the presence of pests, vermin and other scavengers and prevent unsightly accumulation of waste.

 

7.6.26          The recyclable components of the general waste generated by the workforce, such as aluminium cans, paper and cleansed plastic containers should be separated from other waste.  Provision and collection of recycling bins for different types of recyclable waste should be set up by the contractor.  The contractor should also be responsible for arranging recycling companies to collect these materials.

 

Floating Refuse

 

7.6.27          Any floating refuse trapped within the Project Area shall be collected by contractor and disposed of to landfill.

 

               Operation Phase

 

7.6.28          The silt materials and debris collected during maintenance should be properly packed and transported to the designated landfill for disposal as soon as possible. All chemical waste should be properly stored, labelled and removed by licensed waste collectors in accordance with Waste Disposal (Chemical Waste) (General) Regulation.

 


7.7                   Land Contamination

 

Introduction

 

7.7.1              This Section identifies and assesses land lots and sites within the Project boundary which, due to their past or present land uses, are potentially contaminated sites.

 

Relevant Legislation, Policies, Standards and Criteria

 

7.7.2              The following requirements and guidelines are relevant to assessment of land contamination.

 

·               Section 3.1 of Annex 19 of EIAO-TM under the EIAO;

·               Guidance Note for Contaminated Land Assessment and Remediation (August 2007);

·               Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land Management (December 2007); and

·               Practice Guide for Investigation and Remediation of Contaminated Land (August 2011).

 

Assessment Methodology

 

7.7.3              According to the Practice Guide, site appraisal shall precede to determine the need for site investigation, and to provide the information to support a contamination assessment, which the findings will subsequently determine if site remediation is required.

 

7.7.4              The site appraisal consists of the following:

 

·               desk-top review of existing and historical survey maps;

·               interpretation of existing and historical aerial photographs;

·               review of land use record, permitted uses of existing private lots;

·               site walkover to verify the collected information; and

·               review the relevant government records (i.e. Dangerous Goods storage, spillage / leakage of chemicals, chemical wastes producers) of the Project Site.

 

7.7.5              The site walkover was undertaken to identify any physical clues of contamination, such as presence of industrial related building structures, chemical drums, chemical or oil stains, unnatural colours / odours and abandoned piping / mechanical components.

 

Site Appraisal Findings

 

Past Land Uses

 

7.7.6              A review of historical aerial photos (from 1964 – 2011) was undertaken to identify the past land uses within the project area (Annex 7A).  Based on the historic photos, the land use in the area was formerly fishponds, agricultural lands, roads and village areas. With the development of Yuen Long New Town, the works areas were developed in stages into roads, footpaths and the Yuen Long Nullah.  Some sites were not developed and were left vacant most of the time.  Although the proposed DWF pumping station is located at Tung Tau Industrial Area, it is located in a small strip of land between a road and the nullah and was not developed into industrial uses. According to the aerial photos, there was no presence of building structures that would indicate possible industrial activities in the proposed works area. A summary of the review is provided in

7.7.7              Table 7.3.

 

Table 7.3        Review of Historical Aerial Photographs

Aerial Photo Reference

Year

Observed Land Use

DWFI & Rising Main

DWF pumping station at Tung Tau Industrial Area

Annex 7A_1

1963

YL Industrial Estate not yet developed, YLTN under construction, upstream of nullah mainly agricultural land, downstream portion mainly fishponds

Vacant land next to Yuen Long creek with fishponds nearby

Annex 7A_2

1973

YL Industrial Estate not yet developed, YLTN largely formed

Vacant land and road with fishponds nearby, Tung Tau Industrial Area not yet developed

Annex 7A_3

1982

Works in progress at YL Industrial Estate, road, footpath, channel bed

Vacant land, works in progress at Tung Tau Industrial Area

Annex 7A_4

1993

Road, footpath, channel bed, YL Industrial Estate largely in operation

Vacant land

Annex 7A_5

2003

Road, footpath, channel bed

Vacant land

Annex 7A_6

2012

Road, footpath, channel bed

Vacant land

Annex 7A_7

2018

Road, footpath, channel bed

Vacant land

 

Present Land Uses

 

7.7.8              Site walkover was undertaken in December 2018 to verify existing land uses and to identify potential sources and signs of contamination, such as presence of industrial activities, chemicals, oil and hazardous waste handling and storage locations, bulk storage tanks, sumps, pipelines, staining, decolouration, abnormal odours, distressed vegetation, etc.

 

7.7.9              The walkover confirmed the area for constructing the DWFI and rising mains consist mainly of concrete channel bed, roads and footpaths. The proposed DWF pumping station is currently vacant. No polluting activities / sources were observed within the project site areas during the walkover. The proposed works will not encroach upon any petrol filling stations, car repair / dismantling workshops, industrial premises or other major polluting areas. All the project site areas are currently located in government land. Representative photos showing the existing site conditions are presented in Annex 7B.

 

               Spillage / Leakage Records

7.7.10          Fire Services Department (FSD) and EPD have been enquired on any dangerous goods license and possible incident on spillage, leakage of chemicals or dangerous goods at the Project Area. Reply from FSD and EPD indicate that there has been no dangerous goods license since Year 1990 and no records of any incidents of spillage/leakage of chemical waste or dangerous goods with the Project Area in the past 3 years. The relevant correspondences are provided in Annex 7C. 

 

7.7.11          The EPD’s Chemical Waste Producer Register was inspected in June 2019 and no record of chemical producer was identified within the Works Area.

 

Summary of Findings

 

7.7.12          The proposed works will be constructed on existing vacant lands, carriageways, footpaths and the YLTN channel bed.  No signs of suspected land contamination due to past and present land uses were identified from review of historical aerial photos and during site walkover.

 

7.8                   Residual Environmental Impacts

 

7.8.1              With the implementation of the recommended mitigation measures, no unacceptable residual impacts are anticipated from the construction and operation of the Project.

 

7.9                   Environmental Monitoring and Audit Requirements

 

Construction Phase

 

7.9.1              To facilitate monitoring and control over the contractors’ performance on waste management, a waste monitoring and audit programme will be implemented throughout the construction phase and a Waste Management Plan (WMP) will be prepared and implemented by the contractor in accordance with ETWB TC(W) No. 19/2005.  The aims of the monitoring and audit programme are:

 

·         To review the WMP, which will form part of the EMP in accordance with ETWB TC(W) No. 19/2005, including the quantities and types of C&D materials generated, reused and disposed of off-site; the amount of fill materials exported from/imported to the site and the quantity of timber used in temporary works construction for each process/activity;

·         To monitor the implementation and achievement of the WMP on site to assess its effectiveness; and

·         To monitor the follow-up actions on deficiencies identified.

 

7.9.2              Site inspections will be undertaken each week.  Particular attention will be given to the contractor’s provision of sufficient spaces, adequacy of resources and facilities for on-site sorting and temporary storage of C&D materials.  The C&D materials to be disposed of from the site will be visually inspected to ensure the absence of non-inert materials (e.g. general refuse, timber, etc).  The waste to be disposed of at landfills will as practicable contain no observable inert or reusable/recyclable C&D materials (e.g. soil, broken rock, metal, and paper/cardboard packaging, etc).  Any irregularities observed during the site inspections will be raised promptly to the contractor for rectification.

 

7.9.3              The findings of the waste inspections will be reported in the monthly Environmental Monitoring and Audit Report.

 

Operation Phase

 

7.9.4              No monitoring and audit is required during operation of the Project. 

 

7.10               Conclusion

 

7.10.1          Wastes generated by the construction activities are likely to include C&D materials from the construction works, general refuse from the workforce and chemical waste from any maintenance of construction plant and equipment.  Provided that these identified wastes arisen are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed in terms of the avoidance-minimisation-reuse-recycling-disposal hierarchy, unacceptable environmental impacts are not anticipated during construction of the Project.

 

7.10.2          The recommended measures can be enforced by incorporating them into the waste management requirements in the WMP as part of the EMP.  Environmental site audit would be necessary to ensure the implementation of proper waste management practices during construction.

 

7.10.3          For the operation phase, only silt material and debris are expected to be produced by maintenance works of the DWFI system.  Such waste will be removed by manual means and disposed of immediately after the clearance works.  Small amount of screenings and chemical waste will be generated during operation and routine maintenance of the DWF pumping station. No unacceptable environmental impacts are anticipated with proper waste management practices.

 

7.10.4          A review of past and present land uses of the project site was conducted. Based on desk-top review and site walkover, the presence of contaminated land is not expected.



([1])  Assuming a capacity of 7 m3 per truck, bulk factor of 1.4 and 25 working days a month.  The duration of work is 49 months.

([2])    This is considered as a conservative estimate based on the number reported in a number of EIA reports approved under the EIAO.