1.2 Requirements under the Environmental Impact
Assessment Ordinance
1.4 Objectives of the EIA Study
1.1.1
The Drainage Master Plan Studies for the Yuen
Long, Kam Tin, Ngau Tam Mei and Tin Shui Wai Drainage Basin (YLDMP) were
completed in 1998 respectively. The majority of the
improvement works in Yuen Long and Kam Tin recommended under the YLDMP Study
have been completed. Since completion of the DMP Studies, there were changes in
developments within the areas and new development proposals and town planning
studies were commissioned. In addition, some new flooding complaints were
received on the upstream areas of the drainage basins, indicating that further
improvement to the drainage systems were required.
1.1.2
Drainage Services Department (DSD) commissioned
the “Review of Drainage Master Plans in Yuen Long and North Districts –
Feasibility Study” (the DMP Review Study) in 2008 so that the new development
scenarios could be incorporated and the effectiveness of the previously
recommended works could also be assessed.
1.1.3
The Review Study completed in end 2011
identified that some areas in Yuen Long District could not meet the required
flood protection level according to the latest land use changes and future
developments taking into account various factors, including sedimentation at
the downstream main channels, mangrove growth at river estuaries, updated
extreme sea level statistics at Tsim Bei Tsui and projected Climate Change
impacts, in the hydraulics analysis. To account for the severity and extent of
possible flooding and the works implementation time, the Review Study proposed
drainage improvement works in Yuen Long District.
1.1.4
In August 2016, the Development Bureau signed
out a Project Definition Statement (PDS) to justify and define the scope of the
“Yuen Long Barrage Scheme” (YLBS). The Technical Feasibility Study (TFS)
completed by DSD that confirms the feasibility of the Project and was approved
by DEVB in September 2016 and the Project was subsequently included in Cat B
under PWP Item No. 4178D in October 2017.
1.1.5 Black & Veatch (B&V) was commissioned by DSD to carry out the Investigation, Design and Construction of the Project “Yuen Long Barrage Scheme” in September 2018. The general location plan of the Project is shown in Drawing No. 400171/B&V/LAY/001.
1.2.1 A Project Profile (No. PP-564/2018) was submitted to the Environmental Protection Department (EPD) on 25 January 2018 for application of an Environmental Impact Assessment (EIA) Study Brief under section 5(1)(a) of the Environmental Impact Assessment Ordinance (EIAO) and the EIA Study Brief No. ESB-307/2018 for the Project was issued on 9 March 2018 under the EIAO.
1.2.2 The Project consists of the following designated projects under the following items of Part I, Schedule 2 of the EIAO:
1.2.3 The location plan of the proposed work and conservation area and environmental sensitive area is shown in Figure 1.1.
1.3.1 The purpose of the EIA Study is to provide information on the nature and extent of the environmental impacts arising from construction and operation of the Project and related activities that take place concurrently. This information will contribute to decisions on:
1.4.1
The objectives of the EIA Study described in the EIA Study
Brief (No. ESB-307/2018) are listed below:
(i)
to describe the Project and associated works together with
the requirements and environmental benefits for carrying out the Project;
(ii)
to identify & describe elements of community and environment
likely to be affected by the Project and/or likely to cause adverse impacts to
the Project, including both the natural and man-made environment and the
associated environmental constraints;
(iii)
to identify & quantify emission sources and determine the
significance of impacts on sensitive receivers and potential affected uses;
(iv)
to identify & quantify contaminated land within any
project area for development works, and to propose measures to avoid disposal
in the first instance;
(v)
to identify & quantify any potential losses or damage to
flora, fauna and wildlife habitats;
(vi)
to identify any negative impacts on sites of cultural
heritage and to propose measures to mitigate these impacts;
(vii)
to identify & evaluate any potential landscape and visual
impacts and to propose measures to mitigate these impacts;
(viii)
to propose the provision of infrastructure or mitigation
measures to minimize pollution, environmental disturbance and nuisance during
the construction and operation of the Project;
(ix)
to investigate the feasibility, effectiveness and implication
of the proposed mitigation measures;
(x)
to identify, predict and evaluate the residual (i.e. after
practicable mitigation) environmental impacts and the cumulative effects
expected to arise during the construction and operation phases of the Project
in relation to the sensitive receivers and potentially affected uses;
(xi)
to identify, assess and specify methods, measures and standards,
to be included in the detailed design, construction and operation of the
Project which are necessary to mitigate these residual environmental impacts
and cumulative effects and reduce them to acceptable levels;
(xii)
to design & specify environmental monitoring & audit
requirements; and
(xiii)
to identify any additional studies necessary to implement the
mitigation measures or monitoring and proposals recommended in the EIA report.
1.5.1
The remainder of this EIA report are organised as follows:
·
Section 2 describes
the Project including the alternatives considered;
·
Section 3 presents
the air quality impact assessment;
·
Section 4 presents
the noise impact assessment;
·
Section 5 presents
the water quality impact assessment;
·
Section 6 presents
the waste management implication and land contamination assessment;
·
Section 7 presents
the ecological impact assessment;
·
Section 8 presents
the fisheries impact assessment;
·
Section 9 presents
the cultural heritage impact assessment;
·
Section 10 presents
the landscape and visual impact assessment;
·
Section 11 describes
the requirements for environmental monitoring and audit;
·
Section 12 summarizes
the environmental outcomes associated with the Project; and
·
Section 13 summarizes
the conclusions of this EIA Study.