3. Air Quality Impact Assessment
3.2 Statutory Requirements and Evaluation Criteria
3.4 Identification of Air Sensitive Receivers
3.6 Evaluation of Impacts during Construction Phase
3.7 Evaluation of Impacts during Operation Phase
3.9 Potential for Cumulative Impacts
3.11 Monitoring and Audit
Requirements
3.1.1
This Section
presents a qualitative assessment of the potential air quality impacts that
could arise from the construction and operation of the Project. Representative
Air Sensitive Receivers (ASRs) have been identified and an assessment of air
quality impacts has been conducted.
Mitigation measures and Environmental Monitoring and Audit (EM&A)
programme have been proposed if deemed necessary.
3.2.1
The criteria for evaluating air quality impacts and
the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of
the TM-EIAO. The principal legislation for the
management of air quality in Hong Kong is the Air Pollution Control Ordinance
(APCO) (Cap. 311). The Air Quality
Objectives (AQOs) stipulating statutory ambient limits for air pollutants and
the maximum allowable number of exceedances over specific averaging periods are
presented in Table 3.1.
Table 3. 1
¡V Hong Kong Air Quality Objectives
Air
Pollutant |
Averaging Time |
|
No. of Exceedances Allowed per Year |
Sulphur Dioxide (SO2) |
10 minutes |
500 |
3 |
|
24-hours |
125 |
3 |
Respirable Suspended Particulates
(RSP) (b) |
24-hours |
100 |
9 |
Annual |
50 |
- |
|
Fine Suspended Particulates
(FSP) (c) |
24-hours |
75 |
9 |
Annual |
35 |
- |
|
Nitrogen Dioxide (NO2) |
1-hour |
200 |
18 |
|
Annual |
40 |
- |
Ozone (O3) |
8-hours |
160 |
9 |
Carbon Monoxide (CO) |
1-hour |
30,000 |
- |
|
8-hours |
10,000 |
- |
Lead |
Annual |
0.5 |
- |
Notes: (a)
Measured at
298K and 101.325 kPa. (b)
Suspended
particles in air with a nominal aerodynamic diameter of 10 £gm or less (c)
Suspended
particles in air with a nominal aerodynamic diameter of 2.5 £gm or less |
3.2.2
A maximum hourly TSP level of 500 mg m-3
at Air Sensitive Receivers (ASRs) is also stipulated in Section 1, Annex 4 of the EIAO-TM
to assess potential construction dust impacts. The measures stipulated in the Air Pollution Control (Construction Dust)
Regulation should also be followed
whenever possible to ensure that any dust impacts are reduced.
3.2.3
Annex 4
of the EIAO-TM has also stipulated that the odour
level at a sensitive receiver should not exceed 5 odour
units based on an averaging time of 5 seconds for odour
prediction assessment.
3.3.1
Clause
3.4.4.2 of the EIA
Study Brief prescribes the Study Area which is generally defined by a distance of 500 m from boundary of the Project, or to
include other project locations as identified in the EIA. Figures 3.1 ¡V 3.6 shows the
Study Area within the 500 m envelope of the Project (including the works areas)
and the identified representative ASRs which have been described in the next
section in details. The Study Area is the same for both the construction and
operation phases.
3.4.1
Air Sensitive Receivers (ASRs) have been identified in
accordance with Annex 12 of EIAO-TM and are summarised in Table
3.2 and shown in Figures 3.2 ¡V 3.6.
Table
3. 2 ¡V Identified Representative Air
Sensitive Receivers
ASR |
Description |
Minimum Distance away from the Project (m) |
Type of Use |
FPCL1 |
Fortune
Pharmacal Co. Ltd. |
77 |
Industrial |
HKSM1 |
Hong
Kong School of Motoring ¡V Yuen Long School Driving Test Centre |
118 |
Office |
TSSP1 |
Temporary
Shelter at Shan Pui |
273 |
Residential |
SPCH1 |
Shan
Pui Chung Hau Tsuen |
11 |
Residential |
TTWS1 |
Tung
Tau Wai San Tsuen |
39 |
Residential |
SPCH2 |
Shan
Pui Chung Hau Tsuen |
15 |
Residential |
WCTT1 |
Wang
Chau Tung Tau Wai |
89 |
Residential |
TNRG1 |
Twin
Regency |
30 |
Residential |
WCLU1 |
Wang
Chau Lam Uk Tsuen |
65 |
Residential |
YYGD1 |
Yuk Yat Garden |
50 |
Residential |
WFCT1 |
Wang
Fu Court |
16 |
Residential |
YUST1 |
Yeung
Uk San Tseun |
58 |
Residential |
YLLP1 |
Yuen
Long Long Ping Estate Wai Chow School |
66 |
Educational |
LSTS1 |
A.D.
& F.D.P.O.H. Ltd. Leung Shing Tak School |
70 |
Educational |
TSPE1 |
The
Spectra |
21 |
Residential |
HPHO1 |
Hor
Ping House, Long Ping Estate |
92 |
Residential |
VHTK1 |
Village
house at Tai Kui |
13 |
Residential |
PFBD1 |
Po
Fai Building |
6 |
Residential |
MYBD1 |
Man Yip
Building |
6 |
Residential |
FYBD1 |
Fuk Yip
Building |
6 |
Residential |
FOHE1 |
Fook
On House |
13 |
Residential |
YFHE1 |
Yuen
Fat House |
6 |
Residential |
KSBD1 |
Kin
Shing Building |
6 |
Residential |
HLBD1 |
Healey
Building |
8 |
Residential |
WCMS1 |
Wah
Cheung Mansion |
6 |
Residential |
WSMS1 |
Wah
Shing Mansion |
6 |
Residential |
YLBD1 |
Yuen
Long Building |
6 |
Residential |
TPTG1 |
Tai
Pei Tau Rest Garden |
28 |
Residential |
CSPP1 |
Chung
Sing Path Playground |
30 |
Recreational |
YTHE1 |
Yuen
Tong House |
6 |
Residential |
FYBD2 |
Fung
Yue Building |
6 |
Residential |
SFBD1 |
Siu
Fung Building |
6 |
Residential |
HPHE1 |
Happy
House |
6 |
Residential |
KHHE1 |
Kam
Hei House |
6 |
Residential |
CKHE1 |
Chi
King House |
19 |
Residential |
YCHE1 |
Yuen
Cheung House |
19 |
Residential |
HWBD1 |
Ho
Wang Building |
10 |
Residential |
WKBD1 |
Wah
Kin Building |
11 |
Residential |
CCHS1 |
Caritas
Yuen Long Chan Chun Ha Secondary School |
10 |
Educational |
YFGD1 |
Yee
Fung Garden |
39 |
Residential |
YLVA1 |
Yuen
Long Villa |
20 |
Residential |
SFCT1 |
Sun
Fai Court |
10 |
Residential |
MTTN1 |
Ma
Tin Tsuen |
11 |
Residential |
MTTN2 |
Ma
Tin Tsuen |
11 |
Residential |
LTTN1 |
Lung
Tin Tsuen |
11 |
Residential |
LAGR1 |
La
Grove |
30 |
Residential |
MTPK1 |
Ma
Tin Pok Village House |
30 |
Residential |
MTPK2 |
Ma
Tin Pok Village House |
90 |
Residential |
PKSN1 |
Park
Signature |
172 |
Residential |
TLTN1 |
Tin
Liu Tsuen |
11 |
Residential |
TLTN2 |
Tin
Liu Tsuen |
18 |
Residential |
TLTN3 |
Tin
Liu Tsuen |
7 |
Residential |
SCTN1 |
Sham
Chung Tsuen |
16 |
Residential |
PYVA1 |
Park
Yoho Venezia |
121 |
Residential |
CCST1 |
Cheung
Chun San Tsuen |
258 |
Residential |
RIVA1 |
Riva |
51 |
Residential |
KPTN1 |
Ko
Po Tsuen |
13 |
Residential |
KHWA1 |
Kam
Hing Wai |
141 |
Residential |
3.5.1 Data collected by EPD air quality monitoring programme during the period of 2015 to 2019 were examined with the average period value presented in Table 3.3. It is noted that the 5-year averaged annual and 1-hour concentrations of NO2, 24-hour concentrations of FSP and RSP and 8-hour concentration of O3 exceeded the relevant AQO. The concentrations of SO2 and CO were in relatively low level and well within the AQOs during 2015-2019.
3.5.2
The traffic emissions from Castle Peak Road,
Long Yip Road,Yuen Long Highway and other local
roads, as well as emissions from the Yuen Long Industrial Estate (YLIE) and
Tung Tau Industrial Area (TTIA), are considered likely to be the key local
sources affecting the ambient air quality within the Study Area.
Table 3. 3 ¡V 5-year Averaged Annual
Background Concentration of Air Pollutants recorded at Yuen Long Station by EPD
for the Period of 2015-2019
Air Pollutant |
Averaging Time |
AQO (a) |
Data Description |
Unit |
Year (b) (c) |
5-year mean |
||||
2015 |
2016 |
2017 |
2018 |
2019 |
||||||
Fine
Suspended Particulates (FSP) (PM
2.5) |
24-hour |
75 (9) |
Max. |
£gg m-3 |
127 |
76 |
77 |
80 |
81 |
88 |
10th Max. |
£gg m-3 |
78 |
63 |
52 |
46 |
45 |
57 |
|||
No. of
Exceedance(s) |
- |
12 |
1 |
2 |
1 |
2 |
4 |
|||
Annual |
35 |
- |
£gg m-3 |
30 |
23 |
22 |
20 |
20 |
23 |
|
Respirable Suspended Particulates (RSP) (PM10) |
24-hour |
100 (9) |
Max. |
£gg m-3 |
176 |
128 |
111 |
121 |
125 |
132 |
10th Max. |
£gg m-3 |
102 |
86 |
87 |
75 |
83 |
87 |
|||
No. of
Exceedance(s) |
- |
12 |
4 |
2 |
4 |
1 |
5 |
|||
Annual |
50 |
- |
£gg m-3 |
44 |
37 |
40 |
37 |
37 |
39 |
|
Sulphur Dioxide (SO2) |
10-minute |
500 (3) |
Max. |
£gg m-3 |
67 |
77 |
105 |
70 |
53 |
74 |
4th Max. |
£gg m-3 |
51 |
58 |
80 |
52 |
42 |
57 |
|||
24-hour |
125 (3) |
Max. |
£gg m-3 |
20 |
18 |
24 |
20 |
12 |
19 |
|
4th Max. |
£gg m-3 |
17 |
17 |
20 |
17 |
11 |
16 |
|||
Nitrogen Dioxide (NO2) |
1-hour |
200 (18) |
Max |
£gg m-3 |
339 |
202 |
214 |
231 |
193 |
236 |
19th Max. |
£gg m-3 |
162 |
149 |
156 |
150 |
161 |
156 |
|||
No. of
Exceedance(s) |
- |
5 |
1 |
2 |
3 |
0 |
2 |
|||
Annual |
40 |
- |
£gg m-3 |
45 |
46 |
41 |
43 |
44 |
44 |
|
Carbon Monoxide (CO) |
1-hour |
30,000 |
Max. |
£gg m-3 |
2460 |
2080 |
1450 |
1720 |
2150 |
1972 |
8-hour |
10,000 |
Max. |
£gg m-3 |
2143 |
1474 |
1324 |
1574 |
1903 |
1684 |
|
Ozone (O3) |
8-hour |
160 (9) |
Max. |
£gg m-3 |
261 |
269 |
272 |
249 |
310 |
272 |
10th Max. |
£gg m-3 |
164 |
143 |
175 |
162 |
200 |
169 |
|||
No. of
Exceedance(s) |
- |
11 |
5 |
13 |
10 |
25 |
13 |
Notes: (a) Values in ( ) indicate the number of
exceedances allowed per year
(b) Data
extracted from EPD Website (http://www.aqhi.gov.hk/en/download/air-quality-reportse469.html?showall=&start=1)
(c) Bolded values represent exceedances of the AQOs.
3.5.3
The future year background concentrations are made reference to the EPD¡¦s PATH-2016 modelling results. The
dust (RSP and FSP) concentrations of the assessment year extracted from Year
2020 PATH results are presented in Table 3.4.
Table 3. 4 ¡V Background Concentrations
extracted from PATH-2016 Model
Grid |
Respirable Suspended Particulates (RSP) (PM10) |
Fine Suspended
Particulates (FSP) (PM 2.5) |
Sulphur Dioxide (SO2) |
Nitrogen Dioxide |
||||
24-hour average 10th Max. |
Annual average |
24-hour average 10th Max. |
Annual average |
10-minute average 4th Max. |
24-hour average 4th Max. |
1-hour average 10th Max. |
Annual average |
|
24,45 |
83.9 |
35.6 |
62.9 |
25.3 |
109.8 |
25.7 |
94.6 |
19.6 |
24,46 |
82.3 |
35.1 |
61.7 |
24.9 |
113.9 |
26.0 |
101.1 |
23.5 |
24,49 |
81.2 |
34.4 |
60.9 |
24.4 |
109.2 |
26.2 |
100.0 |
18.6 |
25,45 |
81.6 |
35.2 |
61.2 |
25.0 |
111.3 |
25.6 |
99.6 |
19.5 |
25,46 |
81.7 |
35.2 |
61.3 |
25.0 |
111.5 |
26.0 |
111.5 |
26.1 |
25,47 |
82.2 |
35.4 |
61.6 |
25.2 |
111.5 |
26.1 |
114.3 |
27.7 |
25,48 |
82.3 |
35.2 |
61.7 |
25.0 |
111.3 |
26.2 |
114.4 |
25.6 |
26,45 |
81.4 |
34.9 |
61.1 |
24.8 |
112.1 |
25.3 |
103.3 |
16.6 |
26,46 |
81.2 |
34.9 |
60.9 |
24.8 |
111.3 |
25.5 |
100.9 |
19.2 |
26,47 |
81.7 |
34.9 |
61.3 |
24.8 |
111.6 |
25.8 |
103.8 |
19.8 |
26,48 |
82.8 |
35.2 |
62.1 |
25.0 |
110.7 |
25.9 |
101.2 |
19.3 |
26,49 |
82.0 |
35.0 |
61.5 |
24.8 |
110.2 |
26.0 |
95.5 |
16.9 |
27,47 |
81.6 |
34.7 |
61.2 |
24.6 |
111.6 |
25.7 |
95.1 |
16.7 |
27,48 |
82.3 |
35.4 |
61.8 |
25.1 |
110.6 |
25.8 |
96.6 |
17.4 |
28,46 |
81.9 |
35.1 |
61.4 |
24.9 |
112.4 |
25.2 |
84.0 |
14.2 |
28,47 |
81.0 |
34.4 |
60.8 |
24.4 |
111.7 |
25.5 |
88.6 |
14.6 |
28,48 |
81.0 |
34.8 |
60.7 |
24.7 |
111.3 |
25.8 |
87.2 |
14.9 |
29,46 |
80.7 |
33.9 |
60.5 |
24.1 |
112.7 |
25.1 |
79.6 |
13.0 |
29,47 |
81.7 |
34.3 |
61.3 |
24.4 |
111.2 |
25.2 |
78.1 |
12.4 |
Notes:
[1] For 24-hr average PM10, the
concentration is adjusted by adding 26.5 £gg/m3, extracted from EPD¡¦s Guidelines on
Choice of Models and Model Parameters.
[2] For annual average PM10, the
concentration is adjusted by adding 15.6 £gg/m3, extracted from EPD¡¦s Guidelines on
Choice of Models and Model Parameters.
[3] For 24-hr average PM2.5, as there is
no information from the PATH-2016 model, a conversion factor of 0.75 is
multiplied to the 24-hr average PM10, extracted from EPD¡¦s
Guidelines on the Estimation of PM2.5 for Air Quality Assessment in Hong Kong.
[4] For annual average PM2.5, as there
is no information from the PATH-2016 model, a conversion factor of 0.71 is
multiplied to the annual average PM10, extracted from EPD¡¦s
Guidelines on the Estimation of PM2.5 for Air Quality Assessment in Hong Kong.
[5] For 10-min average SO2, as there is
no information from the PATH-2016 model, the most conservative conversion
factor 2.45 (Stability Class A) was applied to the 1-hour SO2 concentration to
estimate the 10-minute SO2 concentrations, extracted from EPD¡¦s
Guidelines on the Estimation of 10-minute Average SO2 Concentration
for Air Quality Assessment in Hong Kong.
3.6.1
The following sources of air pollution are expected
during the construction phase of the Project:
¡P
Fugitive dust during construction of the Barrage Scheme
including site clearance, site formation, excavation, foundation and piling,
building works, etc;
¡P
Fugitive dust caused by earthworks at YLN during revitalisation
works including surface breaking, excavation, materials handling, loading,
unloading and backfilling, etc;
¡P
Fugitive dust from construction and modification of
parapet walls;
¡P
Gaseous
emissions from diesel-powered construction equipment and vehicle associated
with construction of the Project; and
¡P
Odour
from the excavated channel bed materials.
(a) Barrage
Scheme
3.6.2
Site
clearance, site formation, excavation, backfilling, construction of
substructure and superstructure are the major construction activities for the
Barrage Scheme. Construction of the Barrage Scheme would last for about 54
months. Site clearance, site formation, excavation and backfilling works would
take about 30 months within the 54 months period.
3.6.3
Vegetation
if appropriate and debris will be removed during site clearance and fugitive
dust emission is considered to be limited. Excavation and backfilling works may
have the potential to generate fugitive dust. About 60,803 m3 of excavated
materials will be generated in association with the construction of the Barrage
Scheme. On-site storage of
excavated materials will be minimised as far as practicable and surplus
excavated materials will be transported off-site for disposal so that potential
dust emissions can be minimised. It
is estimated that a maximum of 8 trucks per day will be required to dispose of
the C&D materials/construction waste off-site. The size of the works area
for the Barrage Scheme is about 7,300
m2, in which about 900 m2 is the E&M Control Centre,
about 3,400 m2 for the two pumping stations, about 500 m2 for
the tidal barriers, about 1,150 m2 for the link bridge and some of the works areas are for
storage use and occupied by the construction plant or equipment. Active works
area in which excavation and filling will be undertaken is smaller than the
works area. With proper implementation of good site practices and mitigation
measures stipulated in the Air Pollution
Control (Construction Dust) Regulation, potential unacceptable dust impacts
associated with on-site handling and transportation of the public fill and
construction waste to disposal sites are not expected to occur. Also the nearest
ASR FPCL1 is located at more than 77m from the works area of the Barrage
Scheme. As the dust impact is
localized and with implementation of the dust suppression works, no
unacceptable dust impact on this ASR and those beyond is anticipated during
site formation and excavation works.
3.6.4
Negligible
fugitive dust emission is expected from construction of substructure and
superstructure as they will involve mainly concreting and steel-reinforcement works and these works are not dust generating.
(b) Revitalisation concepts for YLN
3.6.5
The
construction duration for the revitalisation works is expected to last for about
2 years within the tentative construction programme. The most affected air
sensitive receivers will be those along the two sides of the YLN. Only minor
impacts will be expected due to construction works because the scale of
demolition of the existing nullah and excavation is expected to be relatively
small.
3.6.6
As
the construction works will be constructed section by section, construction
dust nuisance is not expected to cause any significant dust impacts to the
nearby sensitive receivers. The quantity of C&D materials from site
clearance and excavation is unlikely to be large enough to cause a significant
dust nuisance. It is anticipated that excavated material will only be
stockpiled on each local works area and the duration of the stockpiling will be
as short as possible.
3.6.7
Based
on the engineering design, it is estimated that about 77,438 m3 of
construction and demolition (C&D) materials and channel bed material will
be excavated from the Project for the whole construction period. About 7,744 m3 of the
excavated materials will be reused on-site and the rest (about 69,694 m3)
will be temporarily stored in stockpiling areas for subsequent disposal off-site. Since the construction works will be
conducted section by section, It is estimated that a
maximum of 2 trucks per day from a single work site will be required to dispose
of the C&D materials/construction waste off-site. Dust generated from
construction vehicle movements to and from the stockpiling areas and works
areas will generally be limited within the work areas. The feasibility of reusing some of the
excavated materials as backfilling materials will be rigorously examined during
the detailed design stage. As some materials may be used back in the
construction processes, the quantity of material need
to be disposed of or imported can be reduced. Hence construction dust nuisance
at nearby representative sensitive receivers will expect to be insignificant.
3.6.8
In
addition, the construction dust nuisance can be alleviated by implementation of proper
construction dust mitigation measures as required by the Air Pollution Control (Construction Dust) Regulation. Moreover, as
the proposed channels are close to existing roads, purpose-built haul road is
not expected for the transportation of excavated material and filling material.
3.6.9
Limited excavation and backfilling works are
required during the construction of parapet walls, flap valves and the
associated drainage works. It is understood that the construction of the
parapet walls would be carried out section by section, with each section about
20m long a maximum, thus construction dust nuisance is not expected to cause
any significant dust impacts to the nearby sensitive receivers. Any dust
emissions during excavation activities is expected to be localized and dust
impact to nearby ASRs is not anticipated with implementation of dust mitigation
measures. For backfilling works, fugitive
dust emissions will be reduced by compacting the filled area immediately after
backfilling and covered by impervious sheet when it is not in use.
3.6.10 In view of the relatively small
scale of the construction works, the quantity of excavated materials generated,
the potential fugitive dust nuisance during the construction phase should be
limited. With the implementation of
dust suppression measures and good site practices stipulated in the Air
Pollution Control (Construction Dust) Regulation, no unacceptable adverse air quality impacts on the identified
representative ASRs are anticipated during the construction phase.
3.6.11 The potential air quality impacts
associated with the gaseous emissions from diesel-powered construction
equipment are expected to be relatively low as only a small number of
generators and vehicles are expected to be deployed on site. Requirements as stipulated in the
Air Pollution Control (Non-road Mobile
Machinery) (Emission) Regulation will be followed to control potential
emissions from non-road mobile machinery.
In addition, all
construction plant is required to use ultra-low-sulphur diesel (ULSD) (defined
as diesel fuel containing not more than 0.005% sulphur by weight) as stipulated
in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W))
No. 19/2005 on Environmental Management on Construction Sites. With reference to DEVB TC(W) No. 13/2020, public works contracts
will be required to observe the requirements of timely application of temporary
electricity to minimize the use of diesel generators. Therefore, no adverse air
quality impacts are expected from gaseous emissions.
3.6.12 Excavation
of the nullah bed material will be required for the construction of the
Project. Depending on the quality
of the nullah bed material, the excavation and handling of nullah bed material
may cause odour impacts during construction. Hydrogen sulphide
(H2S) is the key odour constituent of the
excavated material.
Excavation works should be conducted in the shortest time span possible.
Programming of the works should be carried out to ensure that the time for such
works can be minimised. If necessary, the contractors
should also liaise with local resident to inform them of the duration of
potential odour nuisance, and that efforts are made
to minimise and mitigate such nuisance. Odorous
excavated material should be placed as far away from ASRs as possible. Temporary
stockpiles of odorous excavated material should be removed off-site as soon as
practically possible within 24 hours to avoid odour
nuisance arising. With the implementation of good site practice recommended in Section 3.8, unacceptable odour nuisance is not anticipated.
3.7.1
Potential odour may arise from the screened debris/materials
collected as a result of the screening operation conducted at the inlet chamber
of the pumping facilities. The screened debris/materials will be removed on
demand basis to maintain the function of the pumping station as well as to
preclude any potential odour impact during operation. Considered the separation
of inlet screens and nearest ASR is over 80m, potential odour impact from
screening operation during operation phase is not anticipated.
3.7.2
Maintenance would be necessary for the revitalised YLN
to remove excessive silts, vegetation, debris and obstructions in order to
maintain its hydraulic performance and structural integrity. Moderate siltation will generally be
allowed to accumulate, and removal of excess silt would be carried out at
locations where it would impede water flow. Such small-scale maintenance
would require only light mechanical equipment such as a small loader and/or a
small crane truck. Hand-held
equipment will be used for vegetation removal. Therefore, unacceptable impacts from
dust and gaseous emission are not expected to occur.
3.8.1
Relevant dust control measures stipulated in the Air Pollution Control (Construction Dust)
Regulation, and good site practices will be incorporated as the Contract
Specifications for implementation throughout the construction period. These
include:
¡P
The works area for site clearance and excavation
should be sprayed with water before, during and after the operation so as to maintain the entire surface wet.
¡P
Where a vehicle leaving a construction site is carrying a load of dusty materials,
the load should be covered entirely by clean impervious sheeting to ensure that
the dusty materials will not leak from the vehicle.
¡P
Erection of hoarding along the site boundary, where
appropriate.
¡P
All dusty materials should be sprayed with water
immediately prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
¡P
Reduce the traffic induced dust dispersion and
re-suspension, the travelling speed of vehicles within the site should be
controlled.
¡P
Regular maintenance of construction equipment deployed
on-site should be conducted to prevent black smoke emission.
¡P
At locations when ASR is located within short distance
from the site boundary (about 5m), solid screen or barriers should be erected
around dusty activities to minimise potential dust impact
¡P
Connect construction plant and equipment to mains
electricity supply and avoid use of diesel generators and diesel-powered
equipment as far as practicable to minimize the emission impact from these
machineries on nearby residents
3.8.2
Excavated nullah bed
materials that are placed on trucks for disposal should be properly covered
with tarpaulin sheets during transportation to minimise the release of any
potential odour. The odorous
excavated material should be placed as far away from the sensitive receivers as
possible. Odorous channel bed
material excavated during construction phase should be removed off-site as soon
as practicable within 24 hours to avoid any odour nuisance.
3.8.3
During operation phase, mitigation measures are
considered necessary when materials generated from the maintenance works are
found to be odorous, and the following measures should be implemented by DSD.
¡P
Odorous materials should be placed in covered
containers or properly covered with tarpaulin as far as possible;
¡P
Temporarily store odorous material as far away from
ASRs as possible;
¡P
Odorous materials should be removed off-site as soon
as practically possible within 24 hours to avoid any odour nuisance arising;
and
¡P
Regular inspection at inlet chamber of existing pumping
facilities to prevent accumulation of debris/materials at the inlet screens
causing odour nuisance.
3.9.1
The potential for cumulative air quality impact during
the construction and operation phase of the Project has been checked against
the following concurrent projects identified in Section 2:
¡P
Yuen Long Town Nullah (YLTN) Improvement Works;
¡P
Elevated Pedestrian Corridor (EPC) in Yuen Long Town
Connecting with Long Ping Station;
¡P
Housing Sites in Yuen Long South;
3.9.2
For YLTN
improvement works, the construction period will overlap with that of the
Project (Barrage Scheme) during 2022 to 2026. For
the revitalisation works, no overlap of construction
works is expected as the DWFI for the YLTN improvement works will need to be
completed before revitalisation works can commence.
According to its EIA report, dust impact is anticipated during construction but it would be minimal if dust
suppression measures stipulated in the Air Pollution Control (Construction Dust)
Regulation is implemented.
3.9.3
For EPC in Yuen Long Town Connecting with Long Ping
Station, the construction period will overlap with that of the Project during
2022 to 2026. The EPC works is over 1 km from the Barrage Scheme, cumulative
impact is not envisaged. Only the revitalisation
works of YLN may overlap with the EPC project. According
to its EIA report, no adverse dust, gaseous emissions and odour
impacts are anticipated during construction with proper implementation of
mitigation measures.
3.9.4
For Housing Sites in Yuen Long South, the Project
(Barrage Scheme) is located well over 2 km from the project. Cumulative impact
is not expected. Only the proposed revitalisation of YLN and modification of
parapet wall at SCR may potentially overlap with that of this housing
development project. According to its EIA report, dust impact would arise from
the construction activities such as soil excavation, site formation and wind
erosion. No adverse residual air quality impact is anticipated with
implementation of mitigation measures during construction.
3.9.5
In
consideration of both the Project and concurrent projects will not generate
significant dust and odour impact, unacceptable adverse
cumulative dust and odour impact is not anticipated.
3.9.6
Operation of the Project will only involve limited scope of
maintenance works to remove excessive silts, vegetation, debris and
obstructions. As such, unacceptable
cumulative impact to air quality is not anticipated during concurrent operation
with other projects.
3.10.1 No
unacceptable residual impact is anticipated from the construction and operation
of the Project with the implementation of the recommended mitigation measures
and good site practices.
3.11.1 Weekly site inspections during construction stage will be carried out in order to confirm that the mitigation and control measures are properly implemented and are working effectively to ensure construction dust, gaseous/odour emissions will be reduced/controlled to acceptable level.
3.11.2 No adverse impact would be generated during the operation phase of this Project. Therefore, no monitoring is required during operational phase.
3.12.1 The
potential sources of air quality impacts associated with the construction and
operation of the Project have been identified and the potential impacts were
evaluated.
3.12.2 Potential
impacts of dust, gaseous and odour emissions from construction activities have been
considered. With implementation of
standard construction practices and mitigation measures, no unacceptable impact
on ASRs is anticipated. As such no unacceptable residual air quality
impacts are envisaged from the construction and operation of the Project.
3.12.3 Cumulative
air quality impacts associated with concurrent projects within the Study Area
have been considered, no unacceptable impacts are anticipated.
3.12.4 In order to ensure and demonstrate
that mitigation measures are properly implemented during the construction stage
for reducing the air quality impacts from the Project, weekly site inspections
and audits will be conducted as part of the EM&A Programme of the Project.