Contents

11.         ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS  11-2

11.1       Introduction  11-2

11.2       EM&A Manual 11-2

11.3       Air Quality  11-3

11.4       Noise  11-3

11.5       Water Quality  11-4

11.6       Waste Management 11-4

11.7       Ecology  11-5

11.8       Fisheries  11-6

11.9       Cultural Heritage  11-6

11.10         Landscape and Visual 11-6

11.11         Implementation Schedule  11-7

 

11.                    ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

 

11.1                Introduction

 

11.1.1           This section provides a summary of the requirements of Environmental Monitoring and Audit (EM&A) for the construction and operation phases of the Project based on the assessment results of the various environmental issues in the preceding sections. Details of the EM&A requirements are provided in a stand-alone EM&A Manual.

 

11.2                EM&A Manual

 

11.2.1           A stand-alone EM&A Manual has been prepared for this Project as part of the EIA study. The EM&A Manual defines the mechanisms for implementing the EM&A requirements specific to each phase of the work.  The EM&A Manual provides a description of the organisational arrangements and resources required for the EM&A programme based on the conclusions and recommendations of this EIA.  It stipulates details of the construction monitoring required and actions that shall be taken in the event of exceedances of the environmental criteria.  In effect, the EM&A Manual forms a handbook for the on-going environmental management during construction.

 

11.2.2           The EM&A Manual comprises descriptions of the key elements of the EM&A programme including:

 

¡P               Appropriate background information on the construction of the Project with reference to relevant technical reports;

 

¡P               Organisational arrangements, hierarchy and responsibilities with regard to the management of environmental performance during the construction phase.  The EM&A team, the Engineering team, the Contractor(s) team and the project proponent¡¦s representatives are included;

 

¡P               A broad construction programme indicating those activities for which specific mitigation is required and providing a schedule for their timely implementation;

 

¡P               Descriptions of the parameters to be monitored and criteria through which performance will be assessed including: monitoring frequency and methodology, monitoring locations (typically, the location of sensitive receivers as listed in the EIA), monitoring equipment lists, event contingency plans for exceedances of established criteria and schedule of mitigation and best practice methods for reduced adverse environmental impacts;

 

¡P               Procedures for undertaking on-site environmental performance audits as a means of ensuring compliance with environmental criteria; and

¡P               Reporting procedures.

 

11.2.3           The EM&A Manual will be a dynamic document which will undergo a series of revisions, as needed, to accommodate the progression of the construction programme.

 

11.2.4           The objectives of carrying out EM&A for the Project include:

 

¡P               Providing baseline information against which any short- or long-term environmental impacts of the Project can be determined;

 

¡P               Providing an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

 

¡P               Monitoring the performance of the Project and the effectiveness of mitigation measures;

 

¡P               Verifying the environmental impacts identified in the EIA;

 

¡P               Determining Project compliance with regulatory requirements, standards and government policies;

 

¡P               Taking remedial action if unexpected results or unacceptable impacts arise; and

 

¡P               Providing data to enable an environmental audit to be undertaken at regular intervals.

 

11.2.5           The following sections summarise the recommended EM&A requirements and further details are provided in the EM&A Manual.

 

11.3                Air Quality

 

11.3.1          Regular site audits at the frequency of once a week should be conducted during the construction phase to ensure that the recommended mitigation measures are properly implemented to reduce the air quality impacts from the Project.

 

11.4                Noise

 

11.4.1           Noise monitoring is recommended during the construction phase to ensure compliance with the noise criterion at the noise sensitive receivers (NSRs).  Baseline monitoring should be undertaken for a period of 2 weeks before commencement of any construction works. Weekly noise monitoring will be undertaken between 0700-1900 hours during working days at the representative NSRs.  The noise monitoring locations are presented in the EM&A Manual.

 

11.4.2           Weekly site audits will be conducted to ensure that the recommended mitigation measures are properly implemented during the construction stage. 

 

11.4.3          Details of the EM&A programme for noise are presented in the EM&A Manual.

 

11.5                Water Quality

 

11.5.1          A water quality monitoring programme is proposed during the construction of the Project.

 

Construction Phase

 

11.5.2          Baseline monitoring should be undertaken three times per week for a period of four weeks before commencement of the construction works to establish baseline water quality conditions of the area.  Impact monitoring should be undertaken three times per week during the construction period to obtain water quality data of the area throughout the construction period for comparison with the baseline water quality data and hence determine any water quality impacts from the construction activities.  Post Project monitoring should also be undertaken three times per week for four weeks after the completion of construction works.

 

11.5.3          Weekly site inspections and audits will be conducted to ensure that the recommended mitigation measures are properly implemented during the construction stage.

 

               Operation Phase

 

11.5.4       Unacceptable water quality impacts are not expected during the operation of the Project.  Therefore, environmental monitoring and audit for water quality is not recommended for the operation phase of the Project. 

 

11.5.5          Details of the EM&A programme for water quality are presented in the EM&A Manual.

 

11.6                Waste Management

 

Construction Phase

 

11.6.1          To facilitate monitoring and control over the contractors¡¦ performance on waste management, regular waste audit will be implemented throughout the construction phase and a Waste Management Plan (WMP) will be prepared and implemented by the contractor in accordance with ETWB TC(W) No. 19/2005.  The aims of the waste audit are:

¡P               To review the WMP, which will form part of the Environmental Management Plan (EMP) in accordance with ETWB TC(W) No. 19/2005, including the quantities and types of construction and demolition (C&D) materials generated, reused and disposed of off-site; the amount of fill materials exported from/imported to the site and the quantity of timber used in temporary works construction for each process/activity;

¡P               To monitor the implementation and achievement of the WMP on site to assess its effectiveness; and

¡P               To monitor the follow-up actions on deficiencies identified.

 

11.6.2          Site inspections will be undertaken every week.  Particular attention will be given to the contractor¡¦s provision of sufficient spaces, adequacy of resources and facilities for on-site sorting and temporary storage of C&D materials.  The C&D materials to be disposed of from the site will be visually inspected to ensure the absence of non-inert materials (e.g. general refuse, timber, etc).  The waste to be disposed of at landfills will as practicable contains no observable inert or reusable/recyclable C&D materials (e.g. soil, broken rock, metal, and paper/cardboard packaging, etc).  Any irregularities observed during the site inspections will be raised promptly to the contractor for rectification.

 

Operation Phase

 

11.6.3          No monitoring and audit is required during operation of the Project. 

 

11.7                Ecology

 

Construction Phase

 

Ecological Monitoring of Birds

 

11.7.1          Monthly ecological monitoring, focusing on avifauna species of conservation importance and overwintering waterbirds utilising wetland habitats along Shan Pui River and Kam Tin River within 500m from the Project boundary should be conducted during construction phase. The result of the ecological field surveys conducted for the EIA study should be adopted as the baseline for the evaluation of utilization of the wetland habitats by birds. A review on the applicability of the results of baseline surveys during the EIA should be conducted and verification surveys should be undertaken as necessary.

 

Ardeids Night Roost Monitoring

 

11.7.2          The area within 100m from the Project boundary should be monitored monthly during the construction phase to check the location and status of any active ardeid night roost. A pre-construction survey should be conducted before commencement of construction.

 

11.7.3          Site audits should be undertaken on weekly basis to check the proper implementation and maintenance of recommended mitigation measures during construction phase of the Project.

 

Operation Phase

 

11.7.4          As the potential impacts to ecology during operational phase are all considered minor or insignificant, operational phase monitoring and audit are not required. Monitoring of the effectiveness of the revitalisation will be formulated during the Detailed Design Stage.

 

11.7.5          Details of the EM&A programme for ecology are presented in the EM&A Manual. 

 

11.8                Fisheries

 

11.8.1          As no unacceptable adverse fisheries impacts are anticipated during construction or operational phases, no specific monitoring programme for fisheries is required. Regular audits should be undertaken to ensure the effectiveness of the mitigation measures and good site practices recommended during construction phase for further controlling the water quality impacts, as these measures also serve to protect fisheries resources. Details of the EM&A programme are presented in the EM&A Manual. 

 

11.9                Cultural Heritage

 

11.9.1          Measures have been recommended for the protection, and secure and safe public access during the construction phase of four, indirectly affected by the works, built heritage sites. The recommended vibration monitoring, relevant buffer zone requirements and access conditions should be audited during the construction phase at least once a month.  Details of the EM&A programme are presented in the EM&A Manual. 

 

11.10            Landscape and Visual

 

Construction Phase

 

Monitoring of Design, Construction and Establishment Works

 

11.10.1      The design, implementation and maintenance of landscape and visual mitigation measures should be checked to ensure that they are fully realised and that any potential conflicts between the proposed landscape measures and any other Project works and operational requirements are resolved at the earliest possible date and without compromise to the intention of the mitigation measures.

 

Design of Landscape and Visual Mitigation Measures

 

11.10.2      The detailed design of the landscape and visual mitigation measures should be undertaken so as to ensure compliance with the proposed measures in EIA report.

 

Site Supervision of Landscape Works

 

11.10.3      The implementation of the landscape works during the construction phase and establishment works should be inspected through the site audit program.

 

Operation Phase

 

Monitoring of Landscape Establishment

 

11.10.4      All landscape and visual mitigation measures should be monitored during the landscape establishment period to check that intended mitigation effects are realized.

 

11.10.5      Details of the EM&A programme for landscape and visual are presented in the EM&A Manual.

 

11.11            Implementation Schedule

 

11.11.1      An Implementation Schedule of the environmental mitigation measures recommended in the EIA study has been prepared in form of a checklist.  The Implementation Schedule is presented in Appendix 11.1 and also attached to the EM&A Manual.