Contents

13.         CONCLUSION   13-2

13.1       Introduction  13-2

13.2       Air Quality Impact 13-3

13.3       Noise Impact 13-3

13.4       Water Quality Impact 13-3

13.5       Waste Management and Land Contamination  13-4

13.6       Ecological Impact 13-5

13.7       Fisheries Impact 13-7

13.8       Cultural Heritage Impact 13-7

13.9       Landscape and Visual Impact 13-8

13.10         Environmental Monitoring and Audit (EM&A) 13-8

13.11         Overall Conclusion  13-9

 

 

13.                    CONCLUSION

 

13.1                Introduction

 

13.1.1           The YLBS is proposed to enhance the flood protection level of the existing Yuen Long Nullah (YLN) and Kam Tin River (KTR) and minimise the flooding risk in accordance with DSD¡¦s Stormwater Drainage Manual (SDM), accounting for future development and climate change. The construction works under YLBS is anticipated to commence in Q4 of 2022 for completion by Q3 of 2029.

 

13.1.2           The proposed revitalisation works under the Project would enhance the social connectivity of YLN and its surroundings into an aesthetically-pleasing environment. The aim is to promote water-friendliness, ecological enhancements, biodiversity and beautification of YLN, taking into consideration of their effects on hydraulic performance.

 

13.1.3           This Environmental Impact Assessment (EIA) Report has been prepared for the proposed Yuen Long Barrage Scheme (the Project) in accordance with the requirements set out in the EIA Study Brief (ESB-307/2018) and the Technical Memorandum on EIA Process (EIAO-TM). Aspects that have been considered in this EIA Report include:

¡P               Air Quality;

¡P               Noise;

¡P               Water Quality;

¡P               Waste Management and Land Contamination;

¡P               Ecology;

¡P               Fisheries;

¡P               Cultural Heritage; and

¡P               Landscape and Visual.

 

13.1.4           A summary of environmental impacts identified in this EIA is provided in Appendix 13.1. The conclusion of the technical chapters of this EIA is described in the following sections.

 

13.1.5           The key assessment assumptions, limitation of assessment methodologies and related prior agreements with EPD / other authorities on assessment of different environmental aspects are given in Appendix 13.2.

 

13.2                Air Quality Impact

 

13.2.1           The potential sources of air quality impacts associated with the construction and operation of the Project have been identified and the potential impacts were evaluated.

 

13.2.2           Potential impacts of dust, gaseous and odour emissions from construction activities have been considered.  With implementation of standard construction practices and mitigation measures, no unacceptable impact on air sensitive receivers (ASR) is anticipated. Potential odour nuisance from screened debris/materials will be removed on demand basis to maintain the function of the pumping station as well as to preclude any potential odour impact during operation. As such no unacceptable residual air quality impacts are envisaged from the construction and operation of the Project.

 

13.2.3           Cumulative air quality impacts associated with concurrent projects within the Study Area have been considered, no unacceptable impacts are anticipated. 

 

13.3                Noise Impact

 

13.3.1           A construction noise assessment has been undertaken to predict the noise levels at the representative noise sensitive receivers (NSRs) due to the construction of the Project.  Practicable mitigation measures, including good construction site practices, use of quiet construction plant, movable noise barriers, noise insulation sheet and scheduling of construction activities, have been recommended.  With the implementation of the recommended mitigation measures, the predicted construction noise levels at all NSRs comply with the noise criteria during the daytime period.  Therefore, no unacceptable noise impact is expected to arise from the construction activities.  Also, no unacceptable cumulative impact or residual impact is anticipated.

 

13.3.2           Potential noise impact from the operation of the proposed pumping stations has been assessed.  The predicted fixed plant noise levels at the representative NSRs due to the operation of the proposed Barrage Scheme comply with the day-time and night-time noise criteria.  No unacceptable residual impact is anticipated.  Attenuation measures, if required, will be provided to the fixed plant items for achieving the compliance of EIAO-TM noise criteria during the detailed design stage.

 

13.4                Water Quality Impact

 

13.4.1           The potential sources of water quality impacts associated with the construction and operation of the Project have been identified and the potential impacts were evaluated.

 

13.4.2           Potential impacts arising from the proposed construction works are predicted to be largely confined to the specific works areas.  With proper implementation of the recommended mitigation measures, in particular the establishment of dry condition for excavation works within the existing nullah and adoption of good construction site practices as recommended in relevant regulatory guidelines, unacceptable water quality impacts are not expected at the identified water sensitive receivers (WSRs) including the Deep Bay Wetland Conservation Area and Mai Po Inner Deep Bay Ramsar Site. 

 

13.4.3           During the operation phase, the existing tidal condition will be shifted downstream from the existing inflatable dam to the proposed barrage. The water quality at the upstream of the barrage is expected to be improved.  Practicable designs including energy dissipators or refinements of the orientations of the pump outlets will be optimised in the detailed design stage to dissipate excess energy of flowing water downstream such that the hydraulic performance of the downstream will be as similar to the existing condition as possible. Therefore, the potential sediment erosion impact or increases in suspended solids to nearby waters, mangroves, ponds and ultimately Deep Bay, due to the operation of the barrage are not anticipated. With regular maintenance works to remove excessive sediments, it is anticipated that the Project will not lead to any unacceptable water quality impacts. Unacceptable water quality impacts are also not expected to occur at any identified WSRs due to the small-scale and infrequent maintenance works. 

 

13.4.4           With proper implementation of the recommended mitigation measures, no unacceptable residual water quality impacts are envisaged from the construction and operation of the Project. Nevertheless, a monitoring programme is recommended during the construction phase to verify the predictions of the EIA and ensure compliance with the assessment criteria.

 

13.4.5           Cumulative water quality impacts associated with concurrent projects within the Study Area have been considered with no unacceptable impact anticipated. 

 

13.5                Waste Management and Land Contamination

 

13.5.1           Wastes generated by the construction activities are likely to include construction and demolition (C&D) materials, excavated sediment and floating refuse from the construction works, general refuse from the workforce and chemical waste from any maintenance of construction plant and equipment.  Provided that these identified wastes arisen are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed in terms of the avoidance-minimisation-reuse-recycling-disposal hierarchy, unacceptable environmental impacts are not anticipated during construction of the Project.

 

13.5.2           The recommended measures can be enforced by incorporating them into the waste management requirements in the Waste Management Plan (WMP) as part of the Environmental Management Plan (EMP).  Environmental site audit would be necessary to ensure the implementation of proper waste management practices during construction.

 

13.5.3           For the operation phase, trash and sediment are expected to be produced by maintenance works of the tidal barrier. Such waste will be removed by manual means and disposed of to landfill immediately after the clearance works.  Small amount of screenings and chemical waste will be generated and collected during operation and routine maintenance of the pumping stations. No unacceptable environmental impacts are anticipated with proper waste management practices.

 

13.5.4           A review of past and present land uses of the project site was conducted. Based on desk-top review and site walkover, the presence of contaminated land is not expected.

 

13.6                Ecological Impact

 

13.6.1           A literature review and ecological field surveys have been conducted. A total of 14 habitat types, including channelised watercourse, semi-natural watercourse, pond, abandoned wet agricultural land/freshwater marsh, tidal marsh, mangrove, reedbed, mitigation wetland, shrubland, agricultural land, mixed woodland, plantation and wasteland and developed area, were recorded within the 500m assessment area, with channelised watercourse, plantation and developed area being the habitats recorded within the Project Site. The ecological values of the wetland associated habitats including channelised watercourse (only YLTN Section 4, SPR, KTR), semi-natural watercourse, pond, abandoned wet agricultural land/freshwater marsh, tidal marsh, mangrove, reedbed and mitigation wetland are at least low to middle, middle or middle to high. The other habitats, except shrubland, plantation in NSW, which are of low to middle ecological value, are considered of low or very low ecological value. Species of conservation importance recorded within the 500m assessment area included 2 flora, 3 mammals, 51 avifauna, 5 herpetofauna, 9 butterflies, 3 odonates, 1 aquatic fauna and the endemic Bent-winged Firefly. Only 14 avifauna of very low abundance and 1 fish species of conservation importance were recorded within the Project Site.

 

13.6.2           Potential direct impacts on natural habitats and recognised sites of conservation importance within the assessment area except Wetland Buffer Area (WBA) inside Project Site have been avoided through confinement of construction works within the proposed works area. Only 0.29 ha of plantation of low ecological value will be lost permanently, while net wetland loss will not occur due to the decommissioning of the existing inflatable dam to release some space and the deepening of the bed of the watercourse together with the operation of tidal barrier can allow waters from Deep Bay flush in 50m beyond the location of the existing inflatable dam to offset the wetland loss (i.e. 0.26ha watercourse) due to the permanent structures at the channelised watercourse.

 

13.6.3           Major indirect impacts due to construction noise disturbances from demolition works using excavator mounted breakers and piling works on key wetland habitats within the assessment area and in close proximity to the Project Site as well as migratory/overwintering waterbirds have been avoided through scheduling of such noisy construction works outside dry season (i.e. November to March, which is the peak overwintering period of waterbirds).

 

13.6.4           As the YLN S4 will be enhanced ecologically, with the design of the tidal barrier to allow brackish waters flushing in the YLN, no negative ecological impacts due to habitat loss are predicted. On the other hand, the flight-line of waterbirds to-and-fro the YLN S4 and SPR were limited, with the manoeuvrability of waterbirds and the unlikely feeding and roosting grounds in the upstream of YLN, potential impacts to flight-line of waterbirds due to the barrage is considered minor.

 

13.6.5           Hydrodynamics at the Old Kam Tin River as well as SPR will not be changed significantly due to the large waterbody of Deep Bay. While the scouring effects to the exposed mudflat during low tide can be minimised by good discharging design. As there will be no strong artificial lighting, with the proposed mitigation measure in place, potential impacts from light to nocturnal life including Mai Po Bent-winged Firefly are considered minor.

 

13.6.6          Mitigation measures have been proposed during construction stage. According to the ecological survey data from present study, Shan Pui River recorded a relatively higher abundance of waterbirds in dry season. In order to minimise the construction noise disturbance on the nearby wetland habitats and the associated disturbance-sensitive overwintering/migratory waterbirds, which are most abundant during the dry season months, the comparatively disturbing construction works i.e. percussive piling works and demolition using breakers mounted on excavators, would therefore be scheduled outside the dry season (i.e. November to March, which is the peak overwintering period of waterbirds). In addition, a pre-construction survey is recommended for areas within 100m from the Project boundary to confirm the location and status of the night roost. Ardeid night roost was recorded at a site along Kam Tin River. No construction works should be undertaken within 100m from any night roost confirmed by the pre-construction survey after 17:00 from February to September and 16:30 from October to January to avoid disturbance to ardeid night roost. Within YLTN Section 4 of the Project Site, fish species of conservation importance i.e. Gobiopterus macrolepis was recorded. Direct impact to this species is likely in the works area of the tidal barrier during construction phase, and translocation of this species is recommended. Capture-and-translocation of this fish species will be implemented in the works area of the tidal barrier and pumping station prior to construction works to minimise the impacts on this species of conservation importance.

 

13.6.7           With the implementation of the recommended mitigation measures (e.g. avoidance of noisy construction works and use of alternative quieter construction method during peak overwintering period within dry season; provision of noise barriers around Project Sit, provision of movable noise barrier/acoustic mat for piling plants and breaker; use of enclosure for construction plant, use of QPME; restriction of construction hours of construction activities within specified months, etc.), no unacceptable adverse residual impacts would be expected during construction and operational phases.

 

13.7                Fisheries Impact

 

13.7.1           A study based on existing information on pond culture fisheries resources and activities within the assessment area has been undertaken, following the criteria and guidelines for evaluating and assessing fisheries impact as stated in Annexes 9 and 17 of the EIAO-TM.

 

13.7.2           The proposed construction works will be conducted within the proposed project boundary. No loss of active or inactive fishponds are anticipated within the assessment area. There would be no loss of oyster culture area or fishing ground near Deep Bay.  With the implementation of mitigation measures recommended for controlling water quality impact, the Project would not cause any unacceptable water quality impact to adjacent fishponds or oyster culture area and fishing ground near Deep Bay during construction and operational phases. 

 

13.8                Cultural Heritage Impact

 

13.8.1          It is recommended that the moderate archaeological potential of this area as mentioned in Agreement No. CB20120293 Planning and Engineering Study for the Public Housing Site and Yuen Long Industrial Estate Extension at Wang Chau Final Technical Report No. 3G (TR-3G) Preferred Option and Technical Assessment ¡V Environmental Impact Assessment Report (Arup 2014) should be reviewed if this area is affected by any proposed works under this Project in future.

 

13.8.2          The desk-based review and Built Heritage Survey recorded five Graded historic buildings, a Nil-Grade and thirty-two not-graded buildings, three villages with Fung Shui Woodlands alongside five major festivals.  The assessment concluded the Graded Historic buildings will not be affected by the Project."

 

13.8.3          Assessment also concluded four not-graded built heritage items may be affected during the construction phase:  HB-17 and HB-18, village houses in Ma Tin Tsuen, and HB-30, a Village God Shrine and HB-31, a Buddhist Stone Tablet.  Mitigation measures such as condition survey (prior to construction phase) with vibration monitoring during construction is recommended for the village houses (HB-17-18) and shrine (HB-30). In addition, buffer zones to safeguard the physical safety of the heritage structures and measures to ensure safe public access during construction phase is recommended for the four heritage structures (HB-17, HB-18, HB-30 and HB-31).

 

13.9                Landscape and Visual Impact

 

Yuen Long Barrage Scheme

 

13.9.1          Temporary adverse visual impacts will be observed during the construction phase, however beneficial landscape and visual impacts will be observed during the operation phase due to the enhancement of the nullah channel and the integration of the nullah barrage with the landscape.

 

13.9.2          In accordance with Annex 10 of the EIAO-TM, it is considered that, with the landscape and visual enhancement brought by this project such as revitalisation works proposed in this project and the mitigation measures proposed,, the proposed development will result in overall beneficial landscape and visual impacts as it will complement the landscapes and visual character of its setting, follow the planning objectives and will improve the overall landscape and visual quality.

 

Kam Tin River Parapet Modification

 

13.9.3          In accordance with Annex 10 of the EIAO-TM, it is considered that the parapet modification works will in overall terms be acceptable, that is there will be no significant effects on the landscape and no significant visual effects or interference with key views.

 

Modification of Parapet Walls along Yuen Long Nullah, Yuen Long Bypass Floodway, and Sham Chung River

 

13.9.4          In accordance with Annex 10 of the EIAO-TM, it is considered that the parapet modification works will in overall terms be acceptable, that is there will be no significant effects on the landscape and no significant visual effects or interference with key views.

 

13.10            Environmental Monitoring and Audit (EM&A)

 

13.10.1      Monitoring of noise, water quality, ecology, cultural heritage, and landscape and visual impact has been recommended during the construction phase and where appropriate operational phase of the Project.  Environmental site audit should be conducted weekly throughout the construction phase to ensure that the proposed mitigation measures are implemented.

 

13.10.2      The detailed EM&A programme is presented in a standalone EM&A Manual.

 

13.11            Overall Conclusion

 

13.11.1          The YLBS is proposed to enhance the flood protection level of the existing YLN and Kam Tin River (KTR) and minimise the flooding risk in accordance with DSD¡¦s Stormwater Drainage Manual (SDM), accounting for future development and climate change. The construction works under YLBS is anticipated to commence in Q4 of 2022 for completion by Q3 of 2029.

 

13.11.2          The proposed revitalisation works under the Project would enhance the social connectivity of YLN and its surroundings into an aesthetically-pleasing environment. The aim is to promote water-friendliness, ecological enhancements, biodiversity and beautification of YLN, taking into consideration of their effects on hydraulic performance.

 

13.11.3      The EIA has identified and assessed the potential environmental impacts during the construction and operation of the Project in accordance with the requirements set out in the EIA Study Brief (ESB-307/2018) and EIAO-TM. The EIA has concluded that with the implementation of the recommended mitigation measures, no unacceptable environmental impacts are envisaged as a result of the construction and operation of the Project and the Project would be in compliance with the applicable environmental legislation and standards.

 

END OF TEXT