CONTENTS

1          INTRODUCTION.. 1-2

1.1        Background.. 1-2

1.2        Designated Project.. 1-2

1.3        Purpose of the EIA Study.. 1-2

1.4        Objectives of the EIA Study.. 1-3

1.5        Structure of this EIA Report.. 1-3

 

 

 


1                             INTRODUCTION

1.1                       Background

1.1.1                  The 2011-12 Policy Address announced that the Government would adopt a multi-pronged approach, including Rock Cavern Development (RCD), for expanding land resources. Civil Engineering and Development Department (CEDD) took initiative to commission a study on “Enhancing Land Supply Strategy: Reclamation outside Victoria Harbour and Rock Cavern Development”.

1.1.2                  The Study has identified three Government facilities (viz. the Diamond Hill Fresh Water and Salt Water Service Reservoirs (DHSRs), Sham Tseng Sewage Treatment Works and Sai Kung Sewage Treatment Works) for relocating to caverns and recommended further detailed feasibility study to identify and address the issues associated with the relocation proposal.

1.1.3                  Water Supplies Department (WSD) commenced a detailed feasibility study under Agreement No. CE 33/2014 (WS) “Relocation of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Caverns – Feasibility Study” in December 2014. The result of the Feasibility Study (FS) affirmed that relocating the DHSRs and associated facilities to caverns is technically feasible.

1.1.4                  The relocation of DHSRs to caverns (the Project) would generate social benefits from the release of about 4 hectares of land to address the territorial housing needs and the local community needs.

1.1.5                  Binnies Hong Kong Limited was commissioned by WSD in December 2018 to undertake the investigation, design and construction supervision on relocating the DHSRs into caverns. The project site is shown in Figure 1.1.

1.1.6                  In accordance with the requirements of Section 5(1) of the Environmental Impact Assessment (EIA) Ordinance, a Project Profile (No. PP-582/2019) for the Project was submitted to the Director of Environmental Protection (DEP) for application for an EIA Study Brief on 23 May 2019. Pursuant to Section 5(7)(a) of the EIA Ordinance, the DEP issued a Study Brief (No.:ESB-317/2019) on 28 June 2019 for the EIA study.

1.2                       Designated Project

1.2.1                  The Project is a Designated Project under Item Q.2, Part I of Schedule 2 of the Environmental Impact Assessment Ordinance, "Underground Rock Caverns", which requires an environmental permit for its construction and operation.

1.3                       Purpose of the EIA Study

1.3.1                  The purpose of the EIA Study is to provide information on the nature and extent of the environmental impacts arising from construction and operation of the Project and related activities that take place concurrently.  This information will contribute to decisions on:

·         the acceptability of potential environmental consequences that are likely to arise as a result of the Project;

·         the conditions and requirements for the design, construction and operation of the Project and related activities to mitigate against potential environmental consequences; and

·         the acceptability of residual impacts after the proposed mitigation measures are implemented.

1.4                       Objectives of the EIA Study

1.4.1                  The objectives of the EIA study as stated in the EIA Study Brief are as follows:

a)               to describe the Project and associated works together with the requirements and environmental benefits for carrying out the Project;

b)              to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including both the natural and man-made environment and the associated environmental constraints;

c)               to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;

d)              to identify, assess and quantify any potential ecological impacts arising from the Project including potential losses or damage to flora, fauna and natural habitats; and to propose measures to mitigate these impacts;

e)               to identify and quantify waste management requirements and to propose measures to mitigate these impacts;

f)                to identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;

g)               to propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project;

h)              to investigate the feasibility, effectiveness and implications of the proposed mitigation measures;

i)                to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the project in relation to the sensitive receivers and potential affected uses;

j)                to identify, assesses and specify methods, measures and standards, to be included in the detailed design, construction and operation phases of the Project which are necessary to mitigate these residual environmental impacts and cumulative effects and reduce them to acceptable levels;

k)               to design and specify the environmental monitoring and audit requirements;

l)                to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and

m)            to identify any additional studies necessary to implement the mitigation measures of monitoring and proposals recommended in the EIA report.

1.5                       Structure of this EIA Report

1.5.1                  The background of the Project, purpose and objectives of this EIA Report are introduced in this section. A description of the Project and details of considerations of alternative options and the construction methodologies are provided in Section 2. Sections 3 to 10 detail the results of the environmental assessment of each key subject area, covering relevant legislation, environmental conditions, assessment criteria, methodology, and assessment findings.

1.5.2                  Sections 3 to 10 include:

·         Section 3: Air Quality Impact

·         Section 4: Noise Impact

·         Section 5: Water Quality Impact

·         Section 6: Waste Management Implications

·         Section 7: Land Contamination

·         Section 8: Ecological Impact

·         Section 9: Landscape and Visual Impact

·         Section 10: Hazard to Life

1.5.3                  The outline of the requirements for the Environmental Monitoring & Audit (EM&A) programme is presented in Section 11. The EM&A programme and a detailed implementation schedule of the recommended mitigation measures are presented in a separate EM&A Manual. A summary of environmental outcomes and conclusion of the whole assessment is given in Sections 12 and 13, respectively.

1.5.4                  An Executive Summary (ES) has been prepared as a separate document in both Chinese and English which contains summaries of main issues, findings, conclusions and recommendations.

END OF TEXT