CONTENTS
12.2 Environmentally Friendly Options Considered and Incorporated
to Avoid Environmental Impacts
12.3 Environmental
Designs Recommended to Minimise and Mitigate Environmental Impacts
12.5 Estimated
Population Protected from Various Environmental Impacts
12.6 Environmental
Benefits of Environmental Protection Measures Recommended
TABLES
Table 12.1 Key
Environmental Problems Avoided and Sensitive Areas Protected
Table 12.2 Key Recommended Mitigation Measures and
Associated Benefits
·
Avoidance of the recognised site of conservation importance;
·
Avoidance of the encroachment of semi-natural watercourse;
·
Avoidance of the encroachment of secondary woodland;
and
·
Avoidance of direct impacts on species of conservation
interest.
Avoidance of the Encroachment of Secondary Woodland
Avoidance
of Direct Impacts on Species of Conservation Interest
·
Reinstatement and enhancement of temporarily
affected habitats;
·
Relocation of tunnel portal;
·
Elimination of emergency exit tunnel and
alternative of cavern interior design; and
·
Elimination of ventilation shaft.
Reinstatement and Enhancement of Temporarily
Affected Habitats
Elimination of Emergency Exit Tunnel and Alternative
of Cavern Interior Design
·
to integrate the MOE inside the access tunnel (i.e. emergency exit
tunnel can be eliminated);
·
to shorten the length of the access tunnel by 250 metre, where the
length of tunnel is about 1,000m under original caverns location and about 750m
under preferred cavern location;
·
to utilise the space of roof arch of access tunnel
to accommodate the ventilation ducts in order to minimise the excavation volume
of access tunnel; and
·
to adopt drained cavern and tunnel lining so as to
reduce the thickness of the structural lining.
Elimination of Ventilation Shaft
Table 12.1 Key Environmental Problems
Avoided and Sensitive Areas Protected
Designed Approaches |
Key Environmental Problems Avoided and Sensitive
Areas Protected |
Avoidance of works in Country Park |
·
Adverse
impacts on natural resources would be avoided. |
Avoidance of the encroachment of semi-natural
watercourses, woodland and species of conservation interests |
·
Adverse
impacts on natural resources would be avoided. |
Reinstatement and enhancement of temporarily affected
habitats |
·
Adverse
impacts on natural resources would be minimised. |
Relocation of Tunnel Portal |
·
Adverse
impacts on air quality and noise to the local residents would be minimised
and avoided. ·
Indirect
disturbance impacts to habitats and associated fauna and flora which arise
from construction works could be minimised. |
Elimination of Emergency Exit Tunnel and
Alternative of Cavern Interior Design |
·
Generation
of waste during construction phase would be minimised. |
Elimination of Ventilation Shaft |
·
Adverse
visual impact would be minimised. |
·
Existing air and noise sensitive receivers at Tin
Ma Court, Tin Wang Court, Tsui Chuk Garden, Chuk Yuen North Estate, Tsz Lok Estate, Chuk Yuen South Estate, Pang Ching
Court, schools, hospital and institutional uses in the vicinity of Project Site would be protected from air quality and noise
impact assessment by the implementation of good site practices during
construction phase of the Project.
Table 12.2 Key
Recommended Mitigation Measures and Associated Benefits
EIA Aspects |
Key
Recommended Mitigation Measures |
Associated
Benefits |
Air
Quality |
Construction
Dust ·
Dust
suppression measures stipulated in the Air Pollution Control (Construction
Dust) Regulation. ·
Implement
specific dust mitigation measures for excavation, drilling and blasting
activities during the construction of tunnel portal. These include the use of
blast nets / canvas covers and ensure portal door is properly closed. |
To minimise the dust nuisance
on ASRs during construction phase. |
Noise
Impact |
Design Phase ·
The
location and setting of the access portal are taken into account of the
design, which is away from the local residents and façade with angle of view
facing the main carriageways (Lung Cheung Road). Construction Phase ·
The NSRs,
which are in close proximity of project site, will be protected by limiting
the pipe section to be constructed by open cut method in a length of no more
than 30 m at any one time. ·
A majority
of the residential NSRs and educational NSRs are protected with
implementation of quiet PME, moveable noise barriers & noise enclosure,
except occasional exceedance of noise criterion at the following NSRs: o Grace Methodist Church Kindergarten,
Our Lady’s College, and St. Bonaventure College and High School, Ho Lap Primary School; and o Our Lady of Maryknoll Hospital, Wu
York Yu Health Centre, and Proposed Departmental Quarters for Customs &
Excise Department ·
Those
educational NSRs could comply the required noise criteria by carrying out the
works during school holidays; and placing the concrete lorry mixer 10m away
from Our Lady of Maryknoll Hospital, Wu York Yu Health Centre, and Proposed
Departmental Quarters for Customs & Excise Department. Operation Phase ·
With the
fixed plant properly designed to meet the maximum permissible SWLs, no
adverse operational noise impact is envisaged. |
To minimise the
construction noise on NSRs during construction phase. During the operation
phase, the fixed noise impact to the nearby NSRs could be protected. |
Water
Quality |
Construction Phase ·
The key
issue from the land-based construction activities would be the potential
release of construction site run-off and wastewater from general construction
activities, accidental spillage, sewage from on-site construction workers, construction works in close proximity of
inland watercourses, cleansing effluent generated from washing of interior of
structures and groundwater infiltration. Impacts could be controlled by
implementing the site practices as outlined in the ProPECC PN 1/94
“Construction Site Drainage” and the ETWB TC(W) No. 5/2005 “Protection of
natural streams/rivers from adverse impacts arising from construction works”
and the mitigation measures such as provision of drainage system and
sand/silt removal facilities, groundwater control measures, and proper
treatment and discharge of cleansing effluent etc. ·
The
Contractor shall apply for a discharge licence to discharge the effluent from
the construction site under the WPCO. The discharge quality must meet the
requirements specified in the discharge licence. All the runoff and wastewater
generated from the works areas should be treated so that it satisfies all the
standards listed in the Technical Memorandum on Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
(TM-DSS). Operation Phase ·
The main
operation impact from the Project would come from the treatment and disposal
of cleansing water during cleaning and maintenance of the service reservoirs.
Impacts could be minimised by following the WSD’s current standard practice and complying with Water Pollution Control
Ordinance (WPCO). Best Management
Practices (BMPs) including design measures and administration measures are
proposed to reduce non-point source surface water pollution. No adverse
residual water quality impact is anticipated during the operation of the
Project. |
To minimise the
potential water pollution to the nearby water sensitive receivers (WSRs),
thus, the WSRs could be protected in construction and operation phases. |
Waste
Management Implications |
·
Implementation
of the proposed waste control and mitigation measures would avoid the
potential water quality, dust and noise impacts associated with handling,
transportation and disposal of the identified wastes arising from the
construction phase of the Project. ·
Implementation
of a trip-ticket system promulgated under DEVB TC(W) No. 6/2010 to monitor
off-site delivery of surplus inert and non-inert construction and demolition
(C&D) materials. ·
Handling
of chemical wastes in accordance with the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes, and disposal of chemical wastes at
licensed chemical waste recycling/ treatment facilities. ·
Employ
reputable waste collectors for disposal of general refuse. ·
A
C&DMMP will be prepared and submitted to Public Fill Committee for
approval in accordance with Project Administration Handbook for Civil
Engineering Works. ·
EMP shall
be submitted to the Architect/Engineer for approval before construction works
in accordance with ETWB TC(W) No. 19/2005. |
Implementation of good
waste management to avoid, reuse and recycle the waste materials as far as
practical and fully utilise the waste resources during the construction and
operation. |
Ecology |
·
The
preferred option could minimise encroachment into adjacent woodland and
watercourse habitats, as well as avoid the direct impacts on floral species
of conservation interest (Aquilaria sinensis). ·
Shorten the access tunnel could
eliminate the emergency exit portal, which avoid the direct impact of
Herpetofauna species of conservation interest, Lesser Spiny Frog, as well as
butterfly species of conservation interest, Common Archduke. ·
Replanting
would be implemented upon the completion of the construction works to
reinstate the temporarily affected areas to condition similar to original
status. ·
The
indirect disturbance impacts to habitat and associated fauna and flora could
be minimised by the use of quieter piling machinery and construction plants,
hoarding and standard good site practices during construction, as well as
screen planting around the portal during operation. |
To avoid the
disturbance of ecologically sensitive areas, floral and faunal species of
conservation interest. |
Landscape
and Visual Impacts |
·
Site
layout and works area including temporary access road(s), stockpiling
area(s), temporary construction storage shall be carefully planned to
preserve existing landscape resources and trees as far as practicable. ·
Existing
vegetation shall be retained on site as far as practicable. Trees unavoidably
affected by the Project shall be transplanted as far as practicable. Affected
trees that are not suitable for transplantation and to be felled shall be
compensated in not less than 1:1 in quantity and in accordance with DEVB TC
(W) No.4/2020 – Tree Preservation or its latest version. ·
Landscape
planting shall be provided in accordance with DEVB TCW No.3/2012. Planting
species shall be compatible with the nearby existing vegetation cover as far
as practicable. ·
Rooftop
greening and vertical greening shall be implemented. The orientation and
location of the ancillary facilities shall be carefully designed. Its finish
shall be non-reflective and dull in colour. |
To provide a disguising
effect that merge proposed building to surrounding context visually; while
the overall greenery coverage shall be increased. |
Hazard
to Life |
·
No
overnight storage of explosive on site. The delivery of the explosive will be
once per day. |
To minimise the risk to
the sensitive receivers (i.e. residents and wildlife, etc.) nearby during
construction phase. |
END OF TEXT