CONTENTS

13       ConclusionS. 13-1

13.1  General. 13-1

13.2  Benefits of Project.. 13-1

13.3  Air Quality Impact.. 13-1

13.4  Noise Impact. 13-2

13.5  Water Quality Impact.. 13-2

13.6  Waste Management Implications. 13-2

13.7  Land Contamination.. 13-3

13.8  Ecological Impact.. 13-3

13.9  Landscape and Visual Impacts. 13-3

13.10   Hazard to Life.. 13-4

13.11   Overall Conclusion.. 13-4

 

 

 

 

 

 

 


13                     ConclusionS

13.1                General

13.1.1            This EIA report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project based on the preliminary engineering design information available.  The assessment has been conducted, in accordance with the Study Brief No.  ESB-317/2019 under the EIAO for the Project, covering the following environmental issues:

·        Air Quality Impact;

·        Noise Impact;

·        Water Quality Impact;

·        Waste Management Implications;

·        Land Contamination;

·        Ecological Impact;

·        Landscape and Visual Impact; and

·        Hazard to Life.

 

13.1.2            The findings of this EIA Study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project.  During the EIA process, specific environmental control and mitigation measures have been identified and incorporated into the planning and design of the Project in order to achieve compliance with environmental legislation and standards during both the construction and operation phases.  An EM&A programme has also been developed.  The Implementation Schedules listing the recommended mitigation measures are presented in the Appendix 11A.  A summary of the environmental impacts identified in this EIA and key assessment and limitation of assessment methodologies are provided in Appendix 13A and Appendix 13B respectively. The conclusions of technical chapters are presented in the sections below.

13.2                Benefits of Project

13.2.1            The existing DHSRs site will be released for housing and/or other compatible and beneficial uses after implementation of the Project.

13.2.2            Subject to subsequent planning, the released DHSRs and DHPS will provide opportunities for enhancing the community with ample open spaces, a better connectivity to existing housing estates and G/IC facilities and easy access to the natural environment (e.g. Maclehose Trail Section 5, Lion Rock Country Park).

13.2.3            The project location is rich in granite.  Excavation of caverns will produce a large amount of hard granitic rocks, which are valuable natural resources for construction use.  Rocks produced under this Project would become a local source to support the construction industry.

13.3                Air Quality Impact

Construction Phase

13.3.1            The potential sources of air quality impacts associated with the construction of the Project have been identified and the potential impacts were evaluated. Fugitive dust may arise from the construction activities such as site clearance, rock drilling, blasting operation, breaking works, excavation works, handling and transportation of C&D materials, stockpiling and wind erosion. With the implementation of mitigation measures recommended, no unacceptable fugitive dust impact is expected during construction phase.

Operation Phase

13.3.2            As the DHSRs and DHPS are mainly for the storage and pumping of fresh water and flushing water, air quality impact during the operation of the Project is not envisaged.

13.4                Noise Impact

Construction Phase

13.4.1            The use of powered mechanical equipment during the construction phase of the Project is expected to create noise impact to the nearby NSRs. Assessment indicates that the construction noise impact can be largely mitigated to the criteria in the EIAO-TM by use of quiet construction equipment, erecting noise barriers / enclosures; implementing good site practices and use of quieter construction method. With the implementation of the recommended mitigation measures, no exceedance of the daytime construction noise criteria is expected.

Operation Phase

13.4.2            The maximum permissible sound power levels for the ancillary facilities have been derived as noise design target. With implementation of recommended mitigation measures, fixed noise from operation of the Project will comply with the relevant noise criteria.

13.5                Water Quality Impact

Construction Phase

13.5.1            The potential sources of water quality impacts associated with the construction of the Project have been identified and the potential impacts were evaluated. Water quality impact may arise from construction site run-off, general construction activities, sewage from construction workforce, potential accidental chemical spillage, construction works in close proximity of inland watercourses, cleansing effluent generated from washing of interior of structures and potential groundwater filtration. With proper implementation of mitigation measures recommended, no unacceptable water quality impact is expected during construction phase. Regular site inspection should be conducted during the construction phase to ensure the recommended mitigation measures are properly implemented.

Operation Phase

13.5.2            The DHSRs and associated pumping stations are mainly for the storage and pumping of fresh water and flushing water, potential sources of water quality impact include effluents from cleaning of service reservoir, non-point source surface run-off from new impervious area and minimal sewage from the development. With proper implementation of mitigation measures recommended, no adverse waste quality impact is envisaged during operation of the Project..

13.6                Waste Management Implications

Construction Phase

13.6.1            C&D materials will inevitably be produced during the construction phase of the Project. Waste generated during construction works include inert C&D materials, non-inert C&D materials, chemical waste and general refuse. Provided that there is strict control of C&D materials generated from construction works and that all arisings are stored, handled, transported and disposed of in accordance with the recommended mitigation measures, no unacceptable impact due to waste management is expected during construction phase. The recommended mitigation measures can be enforced by incorporating them into the waste management requirements as part of the Environmental Management Plan. Environmental audit would be necessary to ensure the implementation of proper waste management practices during construction.

Operation Phase

13.6.2            With the implementation of the mitigation measures during the operation phases of the Project, no significant impact on waste management is anticipated.

13.7                Land Contamination

13.7.1            A review of past and present land uses of the project site was conducted. Based on desk-top review and site walkover, the presence of contaminated land is not expected.

13.8                Ecological Impact

13.8.1            Ecological impact assessment for the relocation of DHSR has been conducted following the guidelines of the EIAO-TM Annex 8 and Annex 16.

13.8.2            All total of 5 types of habitat were identified within the study area, of which 2 types of habitats, including plantation and developed area were located within the Project Area, where the construction of ancillary building and associated water main laying works. The ecological value of the identified habitats within the Project Area is rated low.

13.8.3            The proposed works would not encroach into the boundary of Lion Rock Country Park, hence no direct impact on wildlife and habitats within the country park is anticipated. Direct and indirect ecological impacts that would arise from the Project during the construction and operation phase have been identified and evaluated. Direct impacts arising from the proposed works for the preferred tunnel portal and cavern option include permanent loss of plantation (approx. 0.252 ha) and developed area (0.032 ha), and temporary loss of plantation (approx. 0.760 ha) and developed area (approx. 3.114 ha) are anticipated.

13.8.4            Construction site runoff and other disturbance impacts resulting from the proposed aboveground works may potentially have indirect impact on wildlife and species of conservation interest. Standard mitigation measures such as good site practice, control of lighting and minimization of groundwater infiltration are proposed.

13.8.5            Most impacts are considered to be negligible in nature. Overall, no significant ecological impacts were anticipated in this assessment. With effective implementation of recommended mitigation measures, no adverse residual ecological impacts are expected from the Project.

13.9                Landscape and Visual Impacts

13.9.1            The Project will inevitably result in some landscape and visual impacts during construction and operation phases.  These impacts have been minimised through careful consideration of alternatives, minimisation of works areas, and incorporation of aesthetic external designs and landscape treatments of proposed aboveground structures. 

Broad Bush Tree Survey

13.9.2            Based on a broad-brush estimate, approximately 260-300 nos. of existing trees is directly overlapped with the proposed tunnel portal and ancillary building, so trees would be unavoidably removed. The dominant tree species are Acacia confusa, Sterculia lanceolate and Mallotus paniculatus, No tree of particular interest was identified within the Project site. 

Landscape Impact for Tunnel Portal, Ancillary Building and Access Road

13.9.3            The affected LRs and LCAs include LR1.2 Engineered Slope (Vegetated), LR1.5 Lion Rock Park Transit Nursery and LCA2 Upland Hillside Landscape at Lion Rock which falls within the footprints of the proposed tunnel portal, the access road leading to the portal, and the ancillary buildings. The landscape impacts of LRs and LCAs within the footprint of the tunnel portal, ancillary facilities and temporary construction storage are considered to be Moderately Adverse without implementation of mitigation measures during construction and operation phases.

Landscape Impact for Water Mains Works

13.9.4            The overall landscape impacts of LRs and LCAs along the footprint of the proposed water mains (i.e. LR1.1 Roadside vegetation, LR2.1 Urban development, LR3.1 Tsz Wan Shan Road Sitting Out Area and LCA4 Wong Tai Sin Residential Urban Landscape) are considered to be Slightly Adverse without implementation of mitigation measures during construction phase and Slightly Adverse to Insubstantial during operation phase. The remaining LRs and LCAs are far away from the Project Site and are estimated to encounter Insubstantial landscape impacts.  

Visual Impact for Tunnel Portal, Ancillary Building and Access Road

13.9.5            During the construction phase of the Project, the overall visual impacts on the VSRs who can partially see the construction site of the proposed portal and the ancillary buildings (i.e. residents of Tin Ma Court (R01) and the Palace (R02)) are considered to be Moderately Adverse, and Slightly Adverse visual impact on the another three VSRs (the recreational users in Lion Rock Park (L03), Occupants in Lion Rock Park Transit Nursery (F07) and travellers along Lion Rock Road (T02)) who can have a glimpse view of the construction site of the proposed portal/ ancillary buildings without implementation of mitigation measures. 

13.9.6            During the operation, the Project will result in Moderately Adverse visual impacts on the residents of Tin Ma Court (R01) and the Palace (R02), and Slightly Adverse impacts on the other three VSRs (L03,  F07 and T02) who can glimpse the portal site and the ancillary buildings. 

Visual Impact for Water Mains Works

13.9.7            The proposed water mains laying works will only result in Slightly Adverse visual impacts on the local VSRs during the construction phase. The rest of the VSRs who can see the temporary road works for water mains laying works will only experience Insubstantial visual impacts during the Project operation phase as the water mains are located in the underground and invisible to the VSRs. 

Overall Landscape and Visual Impacts

13.9.8            Tree compensation according to DEVB TCW No.4/2020 will be carried out. Trees will be compensated at a ratio of not less than 1:1 in terms of quantity of removed trees. Tree species selected shall be compatible with surrounding existing vegetation. It is considered that there is no net loss of landscape resources in terms of trees upon full implementation of compensatory planting. Given the above-ground works extent is rather small in scale, the landscape resources in terms of areas might even encompass a potential gain with full implementation of mitigation measures.

13.9.9            With full implementation of all proposed mitigation measures, the residual impacts on all VSRs are anticipated to be Slight to Moderate to Slight during construction phase and Slightly Adverse to Insubstantial during operation phase. All the residual landscape and visual impacts arising from the project are considered Acceptable.

13.9.10         As a whole, the residual landscape and visual impacts of the proposed Project is considered acceptable with the proposed mitigation measures implemented during construction and operation phases. 

13.10            Hazard to Life

13.10.1         There will be no overnight storage of explosives for this Project. Transportation of explosives to site for cavern and tunnel construction will be undertaken on a daily basis. The contractor is required to destroy any unused explosives before nightfall.


 

13.11            Overall Conclusion

13.11.1         The EIA has identified and assessed the potential environmental impacts during the construction and operation of the Project in accordance with the requirements set out in the EIA Study Brief (ESB-317/2019), EIAO-TM and all environmental legislation and standards. The EIA has concluded that with the implementation of the recommended mitigation measures, no unacceptable environmental impacts are envisaged as a result of the construction and operation of the Project and the Project would be in compliance with the applicable environmental legislation and standards.

END OF TEXT