8.             Environmental Monitoring and Audit

8.1         Introduction

This EIA study has focused on the assessment and mitigation of the potential impacts associated with the phased decommissioning/ demolition/ construction and operation of the Project.  One of the key outputs has been the identification of mitigation measures to be undertaken so that residual impacts comply with regulatory requirements including the EIAO-TM.  To confirm effective and timely implementation of the mitigation measures, it is considered necessary to develop Environmental Monitoring and Audit (EM&A) procedures and mechanisms by which the Implementation Schedule (Appendix 8A) may be tracked and its effectiveness assessed.

8.2         Objectives of EM&A

The objectives of carrying out EM&A for the Project include:

§  Providing baseline information against which any short or long term environmental impacts of the Project can be determined;

§  Providing an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

§  Monitoring the environmental performance of the Project and the effectiveness of the recommended mitigation measures;

§  Verifying the environmental impacts identified in the EIA;

§  Determining Project compliance with regulatory requirements, standards and government policies;

§  Taking remedial action(s) if unexpected results or unacceptable impacts arise; and

§  Providing data to enable an environmental audit to be undertaken at regular intervals.

The following Sections summarise the recommended EM&A requirements for the Project.  Further details are provided in the EM&A Manual.

8.3         Air Quality

8.3.1    Decommissioning/ Demolition and Construction Phases

The EIA study concluded that no adverse fugitive dust impact is anticipated during the decommissioning/ demolition and construction of Project, and dust monitoring is considered not necessary.  However, it is recommended to conduct regular environmental site inspections, i.e. on weekly basis, to confirm the implementation of the dust control measures and good site practices as recommended in Section 3.9.1 throughout the decommissioning/ demolition and construction phases.  These measures are also summarised in the Implementation Schedule provided in Appendix 8A.

8.3.2    Operation Phase

Based on the prediction of the air quality modelling exercise conducted under this EIA study, no adverse air quality impact is anticipated during the operation of the new OCGTs.  Regular environmental site inspections or air quality monitoring during the operation phase is considered not necessary.

8.4         Noise

8.4.1    Decommissioning/ Demolition and Construction Phases

The EIA study concluded that no adverse noise impact is anticipated during the decommissioning/ demolition and construction of the Project, and noise monitoring is considered not necessary.  However, it is recommended to conduct regular environmental site inspections, i.e. on weekly basis, to confirm the implementation of the good site practices as recommended in Section 4.7.1 throughout the decommissioning/ demolition and construction phases.  These good site practices are also summarised in the Implementation Schedule provided in Appendix 8A. 

8.4.2    Operation Phase

Based on the prediction of quantitative noise assessment conducted under this EIA study, no adverse noise impact is anticipated during the operation phase of the Project.  Regular environmental site inspection or noise monitoring during the operation phase is considered not necessary.

8.5         Water Quality

8.5.1    Decommissioning/ Demolition and Construction Phases

The EIA study concluded that no adverse water quality impact is anticipated during the decommissioning/ demolition and construction of the Project, and water quality monitoring is considered not necessary.  However, it is recommended to conduct regular environmental site inspections, i.e. on a weekly basis, to confirm the implementation of the water pollution control measures and good site practices as recommended in Section 5.5 throughout the decommissioning/ demolition and construction phases.  These measures are summarised in the Implementation Schedule provided in Appendix 8A.

8.5.2    Operation Phase

Similar to the operation of the existing units, there will be no cooling water discharge during the operation of the new OCGTs.  Regular environmental site inspection or water quality monitoring during the operation phase is considered not necessary.

8.6         Waste Management

8.6.1    Decommissioning/ Demolition and Construction Phases

The EIA study concluded that no adverse environmental impacts or other hazards arising from waste management is anticipated during decommissioning/ demolition and construction of the Project with the implementation of good site practices.  It is recommended to conduct regular environmental site inspections, i.e. on a weekly basis, to audit the waste management practices and to determine if wastes are being managed in accordance with the recommended good site practices and WMP throughout the decommissioning/ demolition and construction phases.  The audits will investigate all aspects of waste management including waste generation, storage, handling, recycling, transportation and disposal.  The recommended waste management measures are summarised in the Implementation Schedule provided in Appendix 8A. 

8.6.2    Operation Phase

As the operation of the new units and associated equipment will generate minimal quantity of waste and no adverse environmental impacts will arise with the implementation of standard waste management practices at LPS, regular environmental site inspection or waste monitoring during the operation phase is considered not necessary.

8.7         Land Contamination

8.7.1    Decommissioning/ Demolition and Construction Phases

A Land Contamination Specialist shall be engaged to oversee the removal/ demolition process of the Project and review the need to include additional sampling locations, as per recommendations in the CAP.  SI and sampling works at the proposed sampling locations shall be undertaken under the supervision of the Land Contamination Specialist once the proposed sampling locations are made available during the course of the decommissioning/ demolition phase. 

During the decommissioning/ demolition and construction phases, good housekeeping practices shall be maintained by the contractor(s) to minimise the risk of land contamination associated with the decommissioning, demolition and construction activities.  With good housekeeping practices in place, adverse land contamination impact during the decommissioning/ demolition and construction phases is not expected.  To ensure that the recommendations as described in Section 7.9 have been properly implemented by the contractor(s), regular environmental site inspections, i.e. on a weekly basis, during decommissioning/ demolition and construction phases of Project shall be conducted.  The visual inspections/audits will look at all aspects of construction activities that disturb soil.  The recommended good housekeeping practices for decommissioning/ demolition and construction phases are summarised in the Implementation Schedule provided in Appendix 8A.

8.7.2    Operation Phase

There would be no land contamination issue associated with the operation of the Project with the current good housekeeping practices at LPS in place.  Regular environmental site inspection or monitoring related to land contamination during the operation phase is considered not necessary.