Cycle Track between Tsuen Wan and Tuen Mun (Tuen Mun to So Kwun Wat)

Environmental Monitoring and Audit Manual

Civil Engineering and Development Department

April 2022

 

 

 


 

 

 

 

 

 

 


 

Contents

Chapter                                                                                                    

1.         Introduction  1-1

1.1.      Background  1-1

1.2.      Project Implementation Programme  1-1

1.3.      Purpose of EM&A Manual 1-1

1.4.      Contents in this EM&A Manual 1-1

2.         Project Organisation  2-1

2.1.      Key Parties and Organisation Chart 2-1

3.         Air Quality  3-1

3.1.      Introduction  3-1

3.2.      EM&A Requirements During Construction Phase  3-1

3.3.      EM&A Requirements During Operational Phase  3-1

4.         Noise  4-1

4.1.      Introduction  4-1

4.2.      EM&A Requirements During Construction Phase  4-1

4.3.      Noise Mitigation Measures  4-4

4.4.      EM&A Requirements During Operational Phase  4-6

5.         Water Quality  5-1

5.1.      Introduction  5-1

5.2.      Water Quality Parameters  5-1

5.3.      Monitoring Equipment 5-1

5.4.      Measurement and Laboratory Analysis  5-3

5.5.      Monitoring Locations  5-3

5.6.      Baseline Water Quality Monitoring  5-4

5.7.      Impact Water Quality Monitoring  5-4

5.8.      Action and Limit Levels  5-5

5.9.      Event and Action Plan  5-5

5.10.    Construction Site Audit and Inspection  5-8

5.11.    Mitigation Measures  5-8

6.         Waste Management 6-1

6.1.      Introduction  6-1

6.2.      Site Inspection  6-1

6.3.      Mitigation Measures  6-1

7.         Land Contamination  7-1

7.1.      Introduction  7-1

7.2.      EM&A Requirements  7-1

8.         Ecology  8-1

8.1.      Introduction  8-1

8.2.      Mitigation Measures  8-1

9.         Fisheries  9-1

9.1.      Introduction  9-1

9.2.      EM&A for Fisheries  9-1

9.3.      Mitigation Measures  9-1

10.       Landscape and Visual 10-1

10.1.    Introduction  10-1

10.2.    EM&A Requirements  10-1

10.3.    Mitigation Measures  10-1

11.       Cultural Heritage  11-1

11.1.    Introduction  11-1

11.2.    Mitigation Measures  11-1

12.       Site Environmental Audit 12-1

12.1.    Site Inspection  12-1

12.2.    Environmental Compliance  12-1

12.3.    Environmental Complaints  12-2

12.4.    Documentation  12-3

13.       Reporting  13-1

13.1.    General 13-1

13.2.    Baseline Monitoring Report 13-1

13.3.    Monthly EM&A Report 13-1

13.4.    Quarterly EM&A Summary Reports  13-4

13.5.    Final EM&A Summary Report 13-5

13.6.    Termination of EM&A Programme  13-6

13.7.    Data Keeping  13-6

13.8.    Electronic Reporting of EM&A Information  13-6

13.9.    Interim Notifications of Environmental Quality Limit Exceedances  13-7

14.       Implementation Schedule of Mitigation Measures  14-1

14.1.    Introduction  14-1

 

Figures

Figure 1.1

Project Location

Figure 4.1

Locations of Noise Monitoring Stations

 

Appendices

Appendix A

Construction Noise Monitoring Field Record Sheet

Appendix B

Sample Template for Interim Notifications of Environmental Quality Limits Exceedances

 

 


1.              Introduction

1.1.            Background

1.1.1.            The EIA Study Brief (No: ESB-295/2016) for “Cycle Track between Tsuen Wan and Tuen Mun (Tuen Mun to So Kwun Wat)” (the Project) includes the requirement to prepare an Environmental Monitoring and Audit (EM&A) programme.

1.1.2.            The scope of the Project comprises the following:

i.      Construction of new cycle tracks of about 3.6 km long from Hin Fat Lane and Hoi Wing Road at Tuen Mun to Kwun Tsing Road at So Kwun Wat with associated footpaths

ii.     Construction of a marine cycle bridge with footpath of about 200 m long between Cafeteria Old Beach and Kadoorie Beach.

iii.    Provision of cycle parking areas near Hin Fat Lane, Cafeteria Old Beach and Kwun Tsing Road.

1.1.3.            The alignment of cycle track is shown in Figure 1.1.

1.2.            Project Implementation Programme

1.2.1.            The construction is scheduled to commence in the 1st quarter of 2023 and will be completed by the 3rd quarter of 2026 tentatively. 

1.3.            Purpose of EM&A Manual

1.3.1.            The purpose of this EM&A Manual (hereafter refer to as the “Manual”) is to guide the setup of an EM&A programme to ensure compliance with the EIA study recommendations, to assess the effectiveness of the recommended mitigation measures and to identify any further need for additional mitigation measures or remedial action.  This Manual outlines the monitoring and audit programme for both the construction and operational phase of the Project.  It aims to provide systematic procedures for monitoring, auditing and minimising environmental impacts associated with the construction and operational phases.

1.3.2.            This Manual specifies the EM&A requirements to ensure that the mitigation measures recommended in the EIA are effectively implemented and the whole EM&A programme properly managed.

1.4.            Contents in this EM&A Manual

1.4.1.            This EM&A Manual is prepared in accordance with Annex 21 of the Technical Memorandum on EIA Process (EIAO-TM) and the EIA Study Brief for the Project and follows the approach recommended in the EM&A Guidelines for Development Projects in Hong Kong.

1.4.2.            The EM&A Manual contains the following information:

§  project organization for the Project;

§  responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER) and Environmental Team (ET) with respect to the environmental monitoring and audit requirements during the course of the Project;

§  requirements with respect to the construction programme schedule and the necessary environmental monitoring and audit programme to track the varying environmental impact;

§  details of the methodologies to be adopted, including all field laboratories and analytical procedures, and details on quality assurance and quality control programme;

§  definition of Action and Limit Levels;

§  establishment of Event and Action Plans;

§  requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints;

§  requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures.

1.4.3.            An implementation schedule of the environmental mitigation measures has been developed and presented in Section 14 in accordance with the requirements of Clause 3.5.3 of the EIA Study Brief.

 

 


2.              Project Organisation