TABLE OF CONTENTS
14. IMPLEMENTATION SCHEDULE OF THE PROPOSED MITIGATION
MEASURES
Table 14.1 Implementation Schedule of the
Measures for Air Quality
Table 14.2 Implementation Schedule of the
Measures for Noise
Table 14.3 Implementation Schedule of the
Measures for Water Quality
Table 14.4 Implementation Schedule of the
Measures for Waste Management
Table 14.5 Implementation Schedule of the
Measures for Land Contamination Issue
Table 14.6 Implementation Schedule of the
Measures for Sewerage and Sewage Treatment Issue
Table 14.7 Implementation Schedule of the
Measures for Ecological Aspect
Table 14.8 Implementation Schedule of the
Measures for Fisheries
Table 14.9 Implementation Schedule of the
Measures for Cultural Heritage
Table 14.10 Implementation Schedule of the
Measures for Landscape and Visual Aspect
Table 14.1 Implementation Schedule of the Measures for Air Quality
EM&A Manual Ref. |
Environmental
Protection Measures |
Objectives of the
Measures |
Location / Duration
of Measures/ Timing of Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation
and Guidelines |
Tools/ Mechanism for
Implementation |
|||
Des |
C |
O |
||||||||
2.2 |
Implement
the following dust suppression measures as stipulated under the Air Pollution
Control (Construction Dust) Regulation (Cap. 311R), good site practices and
good housekeeping of the site: ·
Use
of regular watering, to reduce dust emissions from exposed site surfaces and
unpaved roads particularly during dry weather; ·
Use
of frequent watering in particularly dusty construction areas close to ASRs; ·
Use
of frequent watering or water sprinklers for major haul roads, material
stockpiling areas and other dusty activities within the construction site; ·
Side
enclosure and covering of any aggregate or dusty material storage piles to
reduce emissions. Where this is not
practicable owing to frequent usage, watering should be applied to aggregate
fines; ·
For
the work sites close to the ASR with a separation distance less than 5m,
provide hoardings of not less than 5m high from ground level along the site
boundary; for the work sites close to the ASRs with a separation distance
between 5m and 10 m, provide hoardings of not less than 3.5 m high from
ground level along the site boundary; for other work sites, provide hoardings
of not less than 2.4 m high from ground level along the site boundary except
for site entrance or exit; ·
Open
temporary stockpiles should be avoided or covered. Prevent placing dusty material storage
plies near ASRs; ·
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations; ·
Establishment
and use of vehicle wheel and body washing facilities at the exit point of the
site; ·
Imposition
of speed control for vehicles on unpaved site roads. 8 km/hr is the recommended limit; ·
Routing
of vehicles and positioning of construction plants should be at the maximum
possible distance from ASRs; ·
Avoid
position of material stockpiling areas, major haul roads and dusty works
within the construction site close to concerned ASRs; ·
Avoid
unnecessary exposed earth; and ·
During
or after the de-bagging process, the use of cement or dry pulverised fuel ash
should be conducted in a totally enclosed system or facility and effective
air pollution control measures should be placed at any exits or exhaust to
avoid potential air quality influence. |
To minimise construction dust nuisance |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- Air
Pollution Control Ordinance (APCO) (Cap. 311) - Air
Pollution Control (Construction Dust) Regulation (Cap. 311R) |
- Pollution
control regulations - EM&A |
|
3.7.1.2 |
2.2 |
Incorporate the below guidelines on
construction control from EPD’s Recommended Pollution Control Clauses for
Construction Contracts in the contract documents: ·
The
Contractor shall observe and comply with the APCO and its subsidiary
regulations, particularly the Air Pollution Control (Construction Dust)
Regulation. ·
The
Contractor shall undertake at all times to prevent dust nuisance as a result
of the construction activities. ·
The
Contractor shall ensure that there will be adequate water supply / storage
for dust suppression. ·
The
Contractor shall devise and arrange methods of working and carrying out the
works in such a manner so as to minimise dust impacts on the surrounding
environment, and shall provide experienced personnel with suitable training
to ensure that these methods are implemented. ·
Before
the commencement of any work, the Contractor may be required to submit the
methods of working, plant, equipment and air pollution control system to be
used on the site for the Engineer inspection and approval. |
To minimise
construction dust nuisance |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- APCO - Air
Pollution Control (Construction Dust) Regulation - EPD’s
Recommended Pollution Control Clauses for Construction Contracts |
- Pollution
control regulations - EM&A |
3.7.1.3 |
2.2 |
Follow the requirements as stipulated in Air
Pollution Control (Non-road Mobile Machinery) (Emission) Regulation and
implement the below measures: · Connect construction
plant and equipment to mains electricity supply and avoid use of diesel
generators and diesel-powered equipment; · Deploy
electrified NRMMs as far as practicable; and · Use of
exempted NRMMs not allowed. |
To minimise exhaust emission
from non-road mobile machinery |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- Air
Pollution Control (Non-road Mobile Machinery) (Emission) Regulation |
- Pollution
control regulations - EM&A |
3.7.1.4 |
2.2 |
· The
odorous materials from desilting works and excavation at nullah bed should be
well covered on site with tarpaulin and placed as far away from the ASRs as
possible. · These
odorous materials should be removed off-site for disposal as soon as possible
within 24 hours. · During
transportation, these odorous materials on the trucks should be properly
covered by tarpaulin. |
To minimise odour
nuisance from desilting / excavated materials |
All construction sites
/ construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
Table 14.2 Implementation Schedule of the Measures for Noise
EIA Ref. |
EM&A Manual Ref. |
Environmental
Protection Measures |
Objectives of the
Measures |
Location / Duration
of Measures/ Timing of Completion of Measures |
Implementation Agent |
Implementation
Stages** |
Relevant Legislation
and Guidelines |
Tools/ Mechanism for
Implementation |
||
Des |
C |
O |
||||||||
For Construction Phase |
||||||||||
4.8.1.2 |
3.2 |
Good
Site Practices
The
site practices listed below should be followed during construction works:
· Only well-maintained
PME to be operated on site and should be serviced regularly during
construction · Silencers
or mufflers on construction equipment should be utilised (if appropriate) and
should be properly maintained during the construction; · Mobile
plant, if any, should be sited as far away from NSRs as possible · Machines
and plant (such as trucks) that may be in intermittent use should be shut
down between work periods or should be throttled down to a minimum · Plant
known to emit noise strongly in one direction should, wherever possible, be
orientated to direct noise away from the nearby NSRs ·
Material
stockpiles and other structures should be effectively utilised, wherever
practicable, in screening noise from on-site construction activities |
To minimise construction noise nuisance arising from the
Project |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
4.8.1.3 –
4.8.1.5 |
3.2 |
Use
of Quality PME / Quieter Construction Method
· Use Quality PME
(QPME) for Hand-held Percussive Breaker, Excavator/loader, wheeled/tracked,
Roller, vibratory, Crane, mobile/barge mounted (diesel), and Crane,
mobile/barge mounted (diesel) and quieter construction methods such as silent
piling by press-in method using Giken Piler and
Power-pack is adopted as an alternative of traditional sheet piling, use of
hydraulic crusher is adopted for demolition of footbridge, and use of road
ripper is adopted for concrete breaking.
· The Contractors may
adopt alternative quiet PME / construction method as long as it can be
demonstrated that they would not result in construction noise impacts worse
than those predicted in this EIA Report.
|
To mitigate the adverse construction noise impact arising
from the Project at the affected NSRs |
All active construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
4.8.1.6 –
4.8.1.7 |
3.2 |
Use
of Movable Noise Barriers / noise insulation fabric / noise enclosure
· A typical design
which has been used locally is a wooden framed barrier with a cantilevered
upper portion of superficial density no less than 14 kg/m² on a skid footing
with 25mm thick internal sound absorptive lining. · Acoustic mat with
surface mass of not less than 7kg/m2 would be used for plant items such as
piler. · A longer cantilevered
top cover would be required to achieve screening benefits at upper floors of
NSRs. The direct line-of-sight between
the PME and the NSRs should be totally screened by a substantial barrier such
that the PME will not be visible when viewed from any window, door or other
opening in any façade of the NSR. · The Contractor shall
be responsible for the design and actual position of the movable noise
barriers with due consideration given to the position and size of the PME,
and the requirement of intercepting the line-of-sight from the NSRs to the
PME, as well as ensuring that the barriers should have no opening and
gap. · Use movable noise
barriers for PMEs as listed in Appendix 4.6 of EIA Report. |
To mitigate the adverse construction noise impact arising
from the Project at the affected NSRs |
All active construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
4.8.1.10
& 4.8.1.16 |
3.2 |
Construction
Restrictions during Examination Period
·
construction of dry weather flow intercepting channel and
pipe laying along the nullah (Work Section 3, Group C-2) should not be
undertaken within 30m from TWGHs Tsoi Wing Sing Primary School (NAP11) during
examination period; and ·
construction of staircases and ramps (Work Section 1,
Group B-2) and (connection work to the existing sewerage system (Work Section
1, Group C-1) should not be undertaken concurrently within 30m from TWGHs Sin
Chu Wan Primary School (NAP16) during examination period. ·
Concurrent construction of this Project with Revised
Trunk Road T4 should avoid examination period of Buddhist Wong Wan Tin
College (NAP12) between December 2025 and February 2026. ·
Concurrent construction of this Project with Joint-user
Complex at Tsuen Nam Road, Tai Wai should avoid examination period of TWGHs
Sin Chu Wan Primary School (NAP16) from January 2024 to April 2024 and July
2024 to October 2024. |
To mitigate the adverse construction noise impact arising
from the Project at the affected NSRs |
All active construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
For Operational Phase (to be
provided and established during the construction phase) |
||||||||||
4.8.2.1 |
3.2 |
The
fixed plants of the proposed UV disinfection system should be properly
designed to meet the maximum permissible SWL in Appendix 4.5. The following
best practices should be implemented for the proposed underground water pumps
and disinfection system as far as practicable to further minimise any
potential impacts: · Quieter plant should
be chosen as far as practicable; · Include noise levels
specification when ordering new plant items; · Locate fixed plant /
louvres away from any NSRs as far as practicable; · Locate fixed plant in
walled plant rooms or in specially designed enclosures; ·
Install direct noise mitigation measures including
silencers, acoustic louvres and acoustic enclosure where necessary. |
Avoid adverse fixed plant noise impact |
Design phase |
Project Proponent / Contractor |
P |
|
P |
- EIAO-TM - NCO |
- Pollution
control regulations - EM&A |
Table 14.3 Implementation Schedule of the Measures for Water Quality
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
For
Construction Phase |
||||||||||
5.8.1.1 |
4.2 |
All effluent discharged from the
construction site should comply with the standards stipulated in the
Technical Memorandum on Standards for Effluents Discharged into Drainage and
Sewerage Systems, Inland and Coastal Waters (TM-DSS). There is a need to apply to EPD for a discharge licence for discharge of effluent from the construction site under the WPCO. The discharge quality must meet the requirements specified in the discharge licence. All the runoff and wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS. If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring should be carried out in accordance with the relevant WPCO licence. |
To avoid
water quality impacts from polluted site discharges. |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- Water
Pollution Control Ordinance (WPCO) - TM-DSS |
- Pollution
control regulations - EM&A |
5.8.1.1 –
5.8.1.14 |
4.2 |
Wastewater from General Construction
Activities and Construction Site Run-off Implement
Best Management Practices (BMPs) of mitigation measures in controlling water
pollution to achieve control of potential pollution of nearby water bodies
during the construction phase of the Project.
The guidelines for handling and disposal of the following types of
construction site discharges as detailed in the ProPECC
PN 1/94 "Construction Site Drainage" should be followed, where
applicable: ·
Construction Site Run-off ·
Boring and Drilling Water ·
Wheel Washing Water ·
Rubbish and Litter · Acid
Cleaning, Etching and Pickling Wastewater |
To
prevent water pollution from uncontrolled wastewater discharge / construction
site runoff so as to avoid / minimise water quality impacts |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM - The
Practice Note for Professional Persons on Construction Site Drainage (ProPECC PN 1/94) |
- Pollution
control regulations - EM&A |
5.8.1.15 |
4.2 |
Construction
Works in Close Proximity of Inland Waters Adopt the precautionary measures / practices outlined in ETWB TC
(Works) No. 5/2005 “Protection of
natural streams/rivers from adverse impacts arising from construction works”
where applicable, such as the followings: ·
The
use of less or smaller construction plants may be specified in areas close to
the watercourses ·
Temporary
storage of materials (e.g. equipment, chemicals and fuel) and temporary
stockpile of construction materials should be located well away from any
watercourses when carrying out of the construction works. ·
Stockpiling
of construction materials and dusty materials should be covered and located
away from any watercourses. ·
Construction
debris and spoil should be covered up and / or disposed of as soon as
possible. ·
Proper
shoring may need to be erected. |
To prevent / minimise
water pollution from construction works in close proximity to inland water |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- ETWB TC
(Works) No. 5/2005 |
- EM&A |
5.5.1.1 |
4.2 |
The Contractor should communicate and coordinate
with DSD and CEDD to avoid overlapping of the proposed desilting works at
downstream tidal zone with their routine maintenance desilting works as far
as practicable. |
To minimise the
potential water quality impact |
Desilting works at
downstream tidal zone / construction phase |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
5.8.1.16
– 5.8.1.18 |
4.2 |
Construction
Works at Tai
Wai Nullah Construction works within the nullah should
be scheduled in dry season when the flow is low. Precautionary / pollution control measures
listed below for site demarcation and flow diversion with physical barriers /
temporary drainage should be implemented prior to the construction works
within channel to ensure that all the construction works would be undertaken
in dry conditions and physically separated from downstream. ·
Physical
barriers with impermeable liners will be deployed to confine the works area
to maintain a dry condition within and to prevent pollutants running into the
downstream waters ·
Depending
on the site conditions, physical barriers or temporary drainage would be
established to intercept and divert the upstream flow ·
Dewatering
of the construction works area shall be conducted prior to the construction
works. Silt removal facilities should
be adopted to treat the wastewater from dewatering operations prior to
discharge. Details of the containment structures, flow diversion pathway and
water treatment method should be provided by the Contractor to the Engineer
for approval before commencement of construction works for the Project. After completion of the construction works,
the works area shall be cleaned up before receiving any water flow or
connecting to any existing watercourse. ·
All
excavated materials generated from construction works in watercourses and wet
areas should be collected and handled in compliance with the WDO. No direct disposal of the construction
wastes or excavated materials into the stormwater drainage system and inland
water should be allowed. ·
The
precautionary measures in Appendix D of ETWB TC No. 5/2005 shall be applied
and pollution control measures for construction works in close proximity to
inland water and mitigation measures for general construction activities
should also be implemented. |
To prevent / minimise
water pollution from construction works at TWN |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WPCO - EIAO-TM - ETWB TC (Works)
No. 5/2005 |
- Pollution
control regulations - EM&A |
5.8.1.19
– 5.8.1.20 |
4.2 |
Sewage
from Construction Workforce ·
No discharge of sewage to the stormwater drains
and inland water will be allowed. ·
Adequate and sufficient portable chemical toilets
should be provided in the works areas to handle sewage from construction
workforce. A licensed collector should
be employed to clean and maintain the chemical toilets on a regular basis. ·
Notices should be posted at conspicuous locations
to remind the workers not to discharge any sewage or wastewater into the
surrounding environment |
To avoid water
quality impact from sewage effluent from construction workforce |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WPCO - EIAO-TM - ProPECC PN 1/94 |
- Pollution
control regulations - EM&A |
5.8.1.21
– 5.8.1.23 |
4.2 |
Accidental
Spillage of Chemicals ·
Contractor must register as a chemical waste producer
if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354) and
its subsidiary regulations in particular the Waste Disposal (Chemical Waste)
(General) Regulation, should be observed and complied with for control of
chemical wastes. ·
The Contractor is also recommended to develop
management procedures for chemicals used and prepare an emergency spillage
handling procedure to deal with chemical spillage in case of accident occurs. ·
Any service shop and maintenance facilities
should be located on hard standings within a bunded area, and sumps and oil
interceptors should be provided.
Maintenance of vehicles and equipment involving activities with
potential for leakage and spillage should only be undertaken within the areas
appropriately equipped to control these discharges. ·
Disposal of chemical wastes should be carried out
in compliance with the WDO and requirements in its subsidiary Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes. |
To avoid water
quality impact from accidental spillage of chemicals |
All construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WPCO - EIAO-TM - WDO |
- Pollution
control regulations - EM&A |
For Operational
Phase (to be provided and established during
the construction phase) |
||||||||||
5.8.2.1 –
5.8.2.5 |
4.2 |
Surface
Run-off / Runoff from Riparian Public Open Space Follow the guidelines
in ProPECC PN 5/93 “Drainage Plans subject to
Comments by Environmental Protection Department” in design of site drainage: Design
Measures ·
Exposed
surface shall be avoided within the Site to minimise soil erosion. The Site shall be either hard paved or
covered by landscaping area and plantation where appropriate. ·
The
drainage system within the
Site should be designed to cater for the runoff from 50 year-return-period
rainstorm. Devices / Facilities to Control
Pollution ·
Screening
facilities such as standard gully grating and trash grille, with spacing which is capable of
screening large substances such as fallen leaves and rubbish should be
provided at the inlet of drainage system. ·
Road
gullies with standard design and silt traps and oil interceptors should be
incorporated during the detailed design to remove particles present in
stormwater runoff. |
Avoid or minimise
water quality impact from surface run-off |
Design phase |
Project
Proponent / Contractor |
P |
|
P |
- EIAO-TM - WPCO - TM-DSS - ProPECC PN 5/93 |
- Pollution
control and other regulations |
Table 14.4 Implementation Schedule of the Measures for Waste Management
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
6.5.1.3 |
5.2 |
Implement
the following good site practices on waste management: ·
Nomination
of approved personnel, such as a site manager, to be responsible for
implementation of good site practices, arrangements for waste collection and
effective disposal to an appropriate facility; ·
Training
of site personnel in site cleanliness, concepts of waste reduction, reuse and
recycling, proper waste management and chemical waste handling procedures; ·
Provision
of sufficient waste reception / disposal points, and regular collection of
waste; ·
Adoption
of appropriate measures to minimise windblown litter and dust during
transportation of waste by either covering trucks or by transporting wastes
in enclosed containers; ·
Provision
of regular cleaning and maintenance programme for drainage systems, sumps and
oil interceptors; ·
Adoption
of a recording system for the amount of wastes generated, recycled and
disposed (including the disposal sites); and ·
Preparation
of Waste Management Plan (WMP), as part of the Environmental Management Plan
(EMP) for submission to the Architect/Engineer for
approval. |
To ensure proper
waste management |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor |
|
P |
|
- Waste
Disposal Ordinance (WDO) - ETWB
TC(W) No. 19/2005 - Waste
Disposal (Chemical Waste) (General) Regulation - Project
Administration Handbook (PAH) for Civil Engineering Works, Section 4.1.3 of
Chapter 4 |
- Pollution
control regulations |
6.5.1.4 |
5.2 |
Waste
Reduction Measures ·
Segregate
and store different types of construction related waste in different
containers, skips or stockpiles to enhance reuse or recycling of materials
and their proper disposal; ·
Provide
separate labelled bins to segregate recyclable waste such as aluminium cans from
other general refuse generated by the work force, and to encourage collection
by individual collectors; ·
Recycle
any unused chemicals or those with remaining functional capacity; ·
Maximise
the use of reusable steel formwork to reduce the amount of C&D materials; ·
Adopt
proper storage and site practices to minimise the potential for damage to, or
contamination of construction materials; ·
Plan
the delivery and stock of construction materials carefully to minimise the
amount of waste generated; and ·
Minimise
over ordering and wastage through careful planning during purchasing of
construction materials. |
Good site practices
to achieve avoidance / minimisation of waste
generation |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WDO |
- Pollution
control regulations - EM&A |
6.5.1.6 –
6.5.1.7 |
5.2
|
Reducing
and Reuse of C&D Materials ·
Careful
design, planning together with good site management to reduce over-ordering
and generation of C&D materials. ·
Formwork
should be designed to minimise the use of standard wooden panels, so that
high reuse levels can be achieved.
Alternatives such as steel formwork or plastic facing should be
considered to increase the potential for reuse. ·
Excavated
inert materials with suitable characteristics / size should be reused on-site
as fill material as far as practicable. ·
Surplus inert C&D materials would be transported and
delivered to public filing area for beneficial reuse as fill material by
other projects. ·
Prior
to disposal of non-inert C&D materials, wood, steel and other metals
should also be separated for reuse and / or recycle where practicable. |
Good site practices
on reducing and reuse of C&D materials |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WDO - ETWB
TC(W) No. 19/2005 - Project
Administration Handbook (PAH) for Civil Engineering Works, Section 4.1.3 of
Chapter 4 |
- Pollution
control regulations - EM&A |
6.5.1.8 |
5.2
|
Storage of
C&D Materials
Suitable
areas should be designated within the works site boundaries for temporary
stockpiling of C&D material. The temporary storage
of C&D materials on-site should be limited to no more than 1,000m3. Within stockpile areas, the
following measures should be taken to control potential environmental impacts
or nuisance: ·
cover
material during heavy rainfall; ·
locate
stockpiles to minimise potential visual impacts; ·
minimise
land intake of stockpile areas as far as possible. |
To ensure proper
waste management to control associated environmental nuisance |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WDO - ETWB
TC(W) No. 19/2005 - PAH for
Civil Engineering Works, Section 4.1.3 of Chapter 4 |
- Pollution
control regulations - EM&A |
6.5.1.9 |
5.2 |
Delivering
of C&D Materials ·
A
trip-ticket system and a recording system for the amount of waste generated,
recycled and disposed, including the disposal sites, should also be set up to
monitor the disposal of C&D materials and to control fly-tipping. ·
Warning
signs should be put up to remind the designated disposal sites. CCTV should also be installed at the
vehicular entrance and exit of the site as additional measures to prevent
fly-tipping. ·
When
delivering inert C&D materials at a public fill reception facility, the
material shall not contain material considered to be unsuitable by the
Filling Supervisor. |
To ensure proper
waste management to control associated environmental nuisance |
All construction
sites and Transportation Route of Waste / Construction Phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WDO - DEVB
TC(W) No.06/2010 - Land
(Miscellaneous Provisions) Ordinance (Cap. 28) |
- Pollution
control regulations - EM&A |
6.5.1.10 |
5.2 |
Chemical
Waste ·
If
chemical waste is produced at the construction site, the contractor would be
required to register with the EPD as a Chemical Waste Producer. ·
Good
quality containers compatible with the chemical wastes should be used, and
incompatible chemicals should be stored separately. ·
Appropriate
labels should be securely attached on each chemical waste container
indicating the corresponding chemical characteristics of the chemical waste. ·
The
contractor shall use a licensed collector to transport and dispose of the chemical
wastes at the CWTC or other licensed facility. |
To ensure proper
waste management |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor
|
|
P |
|
- WDO - Waste
Disposal (Chemical Waste) (General) Regulation - Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes |
- Pollution
control regulations - EM&A |
6.5.1.11 |
5.2 |
General
Refuse ·
A
reputable waste collector should be employed by the contractor to remove
general refuse from the site on a regular basis for disposal of at designated
landfill. ·
Clearly
labelled recycling bins should be provided on site. ·
The
contractor should carry out an education programme for workers in avoiding,
reducing, reusing and recycling of materials generation. Posters and leaflets advising on the use of
the bins should also be provided in the site as reminders. The recyclable waste materials should then
be collected by reliable waste recycling agents on a regular basis. |
To ensure proper
waste management to control associated environmental nuisance |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor
|
|
P |
|
- WDO -
Public Health and Municipal Services
Ordinance (Cap.132) |
- Pollution
control regulations - EM&A |
6.5.1.12
– 6.5.1.13 |
5.2 |
Desilted
Materials ·
The
desilted materials should be contained in watertight container on-site and be
transported off-site by trucks for disposal of at strategic landfill. ·
The
excavated silts shall be wetted during excavation / material handling and
shall be properly covered when placed on trucks. Loading of the materials to the truck shall
be controlled to avoid splashing and overflowing of the slurry to the
surrounding water. ·
Requirements
of the Air Pollution Control (Construction Dust) Regulation and Water Pollution
Control Ordinance (WPCO), where relevant, shall be adhered to during
excavation, transportation and disposal of the desilted materials. |
To ensure proper
waste management to control associated environmental nuisance |
Section 1 of the
Construction site / Construction Phase / upon completion of all construction
activities |
Contractor
|
|
P |
|
- Air
Pollution Control (Construction Dust) Regulation - WDO - Public
Health and Municipal Services Ordinance (Cap.132) - WPCO |
- Pollution
control regulations - EM&A |
Table 14.5 Implementation Schedule of the Measures for Land Contamination Issue
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
7.6 |
6.1.1.2 |
Since
land contamination issue would not be anticipated, no mitigation measure is
considered necessary for the Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 14.6 Implementation Schedule of the Measures for Sewerage and Sewage Treatment Issue
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
8.5.1.1 |
7.2.1.1 |
Since no adverse
impacts on sewerage and sewage treatment would be anticipated, no mitigation
measure is considered necessary for the Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 14.7 Implementation Schedule of the Measures for Ecological Aspect
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
For
Construction Phase |
||||||||||
9.8.2.1 |
8.2 |
Avoidance of Ardeid
Roosting Site Avoid encroachment of
the night roosting sites for ardeids |
To avoid direct
impacts on ardeid night roosting sites |
Design and
Construction Phase |
Project
Proponent / Contractor |
P |
P |
|
N/A |
- EM&A |
9.8.2.2 |
8.2 |
Protection of Mature
Vegetation along Nullah Retain existing mature
trees along TWN on pedestrian road within the Project site. |
To protect mature
vegetation along the nullah |
Design and
Construction Phase |
Project
Proponent / Contractor |
P |
P |
|
N/A |
- EM&A |
9.8.2.3 |
8.2 |
Restriction of
Construction Hours No construction works
within the nullah in Section 1 (channel bed modification and desilting at
downstream tidal zone) should be undertaken from 16:30 to 07:30 during dry
season (October to March) and from 17:00 to 07:00 during wet season (April to
September). A pre-construction
ardeid survey should be conducted no earlier than 3 months before the
commencement of construction works for each sections of TWN, for areas within
100m from the Project site to confirm the location and status of the night
roost. The surveys should be conducted
covering the ardeid pre-roosting and night roosting sites to record the
location of ardeid roosting trees, the ardeid species and abundance utilizing
the pre-roosting and night roosting sites.
A plan detailing the survey methodology should be submitted to and
approved by AFCD prior to the pre-construction ardeid survey. The findings should also be submitted and
approved by AFCD. No noisy construction
works with power mechanical equipment (PME) in areas within 100m away from
any night roost confirmed by the survey should be undertaken from 16:30 to
07:30 during dry season (October to March) and from 17:00 to 07:00 during wet
season (April to September) for all work sections 1 – 6 of TWN. |
To avoid construction
works with PME interfacing with ardeids pre-roosting/roosting hours. |
Construction Phase |
Project
Proponent / Contractor |
P |
P |
|
N/A |
- EM&A |
9.8.3.1 |
8.2 |
Careful Phasing of
Construction Activities The construction works
will be divided into six sections. Construction will
start from the downstream and will not be undertaken at the entire section at
the same time to reduce the construction impacts on nearby sensitive
receivers comparing construction in the entire section. All works within the
nullah would be undertaken during dry season while works outside the nullah
(such as walkway improvement) would be scheduled to avoid overlapping with
works within the nullah to avoid heavy construction activities concentrating
in a certain area over any period. |
To minimise
construction disturbances to surrounding habitats and associated wildlife |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor
|
P |
P |
|
N/A |
- EM&A |
9.8.3.2 |
8.2 |
Careful Phasing of
Construction Activities within Stilling Basin Regarding to
reconstruction of wetland habitat in the stilling basin at Section 6,
construction will be divided into parts depending on the site constraints
(i.e. reconstruct half of the basin at a time) to minimise disturbance and
mortality of existing freshwater community within the basin. |
To minimise
disturbance and mortality of existing freshwater community within stilling
basin. |
Construction site at
Section 6 / Construction Phase / upon completion of all construction
activities |
Contractor
|
P |
P |
|
N/A |
- EM&A |
9.8.3.3 –
9.8.3.5 |
8.2 |
Good site practices
on air quality and noise control to further minimise construction
disturbances to surrounding habitats and associated wildlife. |
To minimise
construction disturbances to surrounding habitats and associated wildlife |
Construction Phase |
Contractor |
|
P |
|
- EIAO-TM |
-
EM&A |
9.8.3.7 |
8.2 |
Minimising Impacts on
Water Quality during Construction Phase Precautionary /
pollution control measures and good site practices for construction works in
close proximity and within as detailed in Table 14.3. |
To prevent pollution
of waterbodies and to minimise indirect water quality impacts on ecology |
All construction
sites / Construction Phase / upon completion of all construction activities |
Contractor |
P |
P |
|
- EIAO-TM -
ProPECC PN 1/94 -
ETWB TC (Works) No. 5/2005 - WPCO - TM-DSS |
-
Pollution control regulations - EM&A |
9.8.4.1 |
8.2 |
Compensation of
Temporary Loss of Pre-roosting Site Under the
revitalisation design, ardeids pre-roosting habitat at downstream Section 1
would be reinstated into a mix of stepped terrace and slope at water edge to
enhance foraging / pre-roosting habitats for waterbirds (e.g. ardeids). To compensate for the
temporary loss of pre-roosting site for ardeids during reconstruction of the
concrete platforms at Section 1 in dry seasons, floating pontoons of similar
areas could be provided at downstream of the works area as far as
practicable, along southern bank out of Project site, as an alternative
assembly point for ardeids. These floating
pontoons should be installed by October before the start of every dry season
within the construction programme and disassemble in April upon end of dry
season. Installation of the floating
pontoons in early dry season can help in maximising usage of ardeids, by
allowing them to get familiar with these floating platforms earlier and
thereby increase the percentage of usage.
The proposed extend and location of the floating pontoon should be
submitted and approved by AFCD together with the pre-construction survey
methodology. Ardeid’s usage of the
temporary floating pontoon should be monitored in in the monthly ecological
monitoring. |
To compensate for the
temporary loss of pre-roosting site for ardeids |
Construction site at
Section 1 / Installed before and disassemble after Dry seasons (November to
March) during Construction Phase / upon completion of all construction
activities |
Contractor |
P |
P |
|
- EIAO-TM |
- EM&A |
For Both
Construction and Operational Phases |
||||||||||
9.8.3.8 |
8.2 |
Lighting
installed along TWN under the revitalisation plan shall be minimised or
incorporate wildlife-friendly lighting to avoid light spill.
Intensity of light should be controlled to the lowest level possible
and long wavelength lights such as amber lamps, which is visible to human but
invisible to most animals, are recommended. The
lights should be installed with a shield and at level as close to the ground
as possible to prevent extensive light casting up into the sky. Lights with motion sensors can also be considered to
further minimise disturbance to surrounding habitats as lights that are not
in use would be automatically turn off. |
To minimise
disturbance to surrounding habitats and associated wildlife |
Design, Construction
& Operation Phase |
Contractor
for construction phase / Project Proponent for operational phase |
P |
P |
P |
-
Charter of External Lighting issued by EEB -
Guidelines on Industry Best Practices for External
Lighting Installations issued by EEB |
-
EM&A (for construction phase) |
For
Operational Phase (to be provided and
established during the construction phase) |
||||||||||
9.8.3.6 |
8.2 |
Minimising Impacts on
Hydrodynamics Properties Design of
ecological-friendly riverbed lining should be considered with reference to
DSD PN No. 3/2021 “Guidelines on Design for Revitalisation of River Channel’. For instance, the original bed substrates within the
nullah in the stilling basin at Section 6 could be stockpiled and preserved
off-site temporarily during construction phase for reuse in wetland
vegetation planting in the nullah as far as practicable. |
To minimise impact on
hydrological properties of watercourse habitat |
Design / Construction
Phase |
Contractor |
P |
P |
|
- DSD PN No. 3/2021 |
-
EM&A |
9.8.3.9 |
8.2 |
Design
of site drainage and Best Management Practices (BMPs) for storm water
discharge should follow the relevant guidelines and practices as given in the
ProPECC PN 5/93 to minimise surface runoff from the
Project. |
To prevent / minimise
the indirect water quality impacts from surface run-off on ecology |
Design phase |
Project
Proponent / Contractor |
P |
P |
P |
-
ProPECC PN 5/93 |
-
EM&A |
Table 14.8 Implementation Schedule of the Measures for Fisheries
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
10.6.2 |
9.2 |
Since no adverse impacts
on fisheries would be anticipated, no specific fisheries mitigation measure
is considered necessary for the Project. Nonetheless,
water pollution control measures (Table 14.3
refers) should be strictly followed as these measures also serve to further
protect fisheries resources. |
N/A (Measures are under
water quality section) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 14.9 Implementation Schedule of the Measures for Cultural Heritage
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
11.7.1.1 |
10.1.1.2 |
Pre and post condition survey of
Gatehouse of Pok Ngar
Villa (new item pending for grading assessment), Li Cottage (Grade 1), Nos.
1-3 First Street, Tai Wai (Grade 3) and Entrance Gate, Chik
Chuen Wai (Grade 2) should be conducted to inspect
the buildings’ structural integrity and record the buildings’
conditions by professional qualified building surveyor or engineer
before and after the construction works, respectively. The
survey results shall be submitted to AMO for record. Protective measures shall be provided to the
built heritage subject to the results of the pre-condition survey. Post-condition survey should be conducted
after the construction works to identify any damages that have occurred or
caused by the construction. If damages
to these built heritage resources are identified, AMO shall be informed
immediately. |
To avoid
and minimise potential indirect impacts of ground-borne vibration to built heritage |
During construction
phase in Work Sections 2 & 3 of TWN / upon completion of all construction
activities in Work Sections 2 & 3 |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
11.7.1.2 |
10.1.1.2 |
A buffer zone of 5 m from Gatehouse of Pok
Ngar Villa (new item pending for grading
assessment) should be set up, in which no construction machineries and
construction storage should trespass the buffer zone. Fencing should also be set up to clearly
demarcate the buffer zone to avoid potential damage due to site negligence. |
To avoid
potential direct damage to built heritage |
During construction
phase in Work Section 3 of TWN / upon completion of all construction
activities in Work Section 3 |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
11.1.7.3 |
10.1.1.2 |
Monitoring of vibration, settlement and tilting incorporated
with a set of Alert, Alarm and Action (AAA) system shall be employed for
Gatehouse of Pok Ngar
Villa (new item pending for grading assessment), Li Cottage (Grade 1), Nos.
1-3 First Street, Tai Wai (Grade 3) and Entrance Gate, Chik
Chuen Wai (Grade 2) during the construction
phase. If the alert level is exceeded,
the monitoring frequency should be increased.
If the alarm level is exceeded, the design of the construction may
need to be amended. If the action
level is exceeded, all works should be stopped. The actual limiting criteria should be further agreed with the
AMO. A monitoring proposal, including
type of monitoring, checkpoint locations, distribution of monitoring points,
installation details, frequency of monitoring and proposed actions to be
taken when reaching respective monitoring limits, should be submitted to AMO
for comments before commencement of the works. Prior agreement and consent should be
sought from the owner(s), stakeholder(s) and relevant Government
department(s) for the installation of monitoring points before commencement
of the works. Record of monitoring
should be submitted regularly to AMO during the construction. AMO should be alerted in case any
irregularities are observed. |
To avoid
and minimise potential indirect impacts of ground-borne vibration to built heritage |
During construction
phase in Work Sections 2& 3 of TWN / upon completion of all construction
activities in Work Sections 2 & 3 |
Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
Table 14.10 Implementation Schedule of the Measures for Landscape and Visual Aspect
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||
Des |
C |
O |
||||||||
For Construction Phase |
||||||||||
Table 12.10 |
11.2. |
CM1
– Tree Preservation during Construction All existing trees to
be retained shall be carefully protected during construction. Tree protection works shall be in accordance with DEVB
TC(W) No. 4/2020 – Tree Preservation and Tree Management Practice Note No. 1
– Tree Preservation during Construction. For the 3 nos. of
identified OVTs within 100m assessment boundary, though they are not affected
by proposed works, tree maintenance departments/ their agents are required to
follow the respective requirements as stipulated in Para.16 - 32 of DEVB
TC(W) No. 5/2020 to preserve the OVTs in the Register. |
To protect the existing trees to be retained |
All
active construction sites / construction phase / upon completion of all
construction activities |
DSD
/ LCSD / Contractor |
P |
P |
|
-
DEVB TCW No. 4/2020 and the latest Guidelines on Tree
Preservation during Development issued by GLTM Section of DEVB |
-
EM&A |
Table 12.10 |
11.2. |
CM2
– Erection of Decorative Screen Hoarding Decorative
Hoarding, which is compatible with the surrounding settings, shall be erected
during construction to minimise the potential landscape and visual impacts
due to the construction works and activities.
|
Proper
site management / setting to minimise potential landscape and visual impacts |
All
active construction sites / construction phase / upon completion of all
construction activities |
DSD
/ Contractor |
|
P |
|
-
EIAO-TM |
-
EM&A |
Table 12.10 |
11.2. |
CM3
– Control of Night-time Lighting Glare Any lighting
provision of the construction works at night shall be carefully control to
prevent light overspill to the nearby VSRs and into the sky. |
To
minimise potential impact to nearby VSRs by proper site settings |
All
active construction sites / construction phase / upon completion of all
construction activities |
DSD
/ Contractor |
|
P |
|
-
Charter of External Lighting issued by EEB -
Guidelines on Industry Best Practices for External
Lighting Installations issued by EEB |
-
EM&A |
Table 12.10 |
11.2. |
CM4
– Management of Construction Activities and Facilities The facilities and
activities at works sites and areas, which include site office, temporary storage
areas, temporary works etc., shall be carefully managed and controlled on the
height, deposition and arrangement to minimise any potential adverse
landscape and visual impacts. |
Proper
site management / setting to minimise potential landscape and visual impacts |
All
active construction sites / construction phase / upon completion of all
construction activities |
DSD
/ Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
Table 12.10 |
11.2. |
CM5
– Reinstatement of Temporarily Disturbed Landscape Areas All hard and soft
landscape areas disturbed temporarily during construction due to temporary
excavations, temporary works sites and works areas shall be reinstated to
equal or better quality, to the satisfaction of the relevant Government
Departments. |
To
reinstate disturbed hard and soft landscape areas |
All
active construction sites / construction phase / upon completion of all
construction activities |
DSD
/ Contractor |
|
P |
|
- EIAO-TM |
- EM&A |
Table 12.10 |
11.2. |
CM6
– Reinstatement of Temporarily Disturbed Watercourses Temporarily disturbed
watercourses shall be reinstated to the satisfaction of relevant Government
Departments. Good site practices as described in
ETWB TCW No. 5/2005 “Protection of natural streams/rivers from adverse
impacts arising from construction works” shall also be adopted to avoid any
pollution entering the watercourses nearby where applicable. |
To
reinstate disturbed watercourse |
All
active construction sites / construction phase / upon completion of all
construction activities |
DSD
/ Contractor |
|
P |
|
- ETWB TCW No. 5/2005 |
-
EM&A |
For Operational Phase (to be provided and established during the
construction phase) |
||||||||||
Table 12.11 |
11.2. |
OM1
– Greening Enhancement along Channel
Bed and Embankment The existing concrete riverbed and embankment will be
resurfaced by a layer of vegetation, which will enhance the aesthetic value
of the nullah. The riverbed will be planted with
various types of riparian and wetland plants while the river embankment will
be covered by various types of climbers or trailing plants along the parapet
planters. |
To
enhance aesthetic value of TWN |
Design,
Construction and Operational Phases |
DSD / Contractor Long-term Maintenance
Party: DSD |
P |
P |
P |
- EIAO-TM |
- EM&A (for construction
phase) |
Table 12.11 |
11.2. |
OM2
– Provision of Recreational Opportunity along Nullah The provision and
improvement of recreational facilities including but not limited to
sitting-out areas, thematic planting, play elements, viewing decks, gathering
points, proposed 3km walkways, improvement/ modification of planters, water
play features etc. along the nullah aim to enhance the ecological, landscape
and visual value of the nullah, provide a greener environment, promote water friendliness
and improve the community environment. |
To
enhance landscape and visual value of TWN |
Design,
Construction and Operational Phases |
DSD / Contractor Long-term Maintenance
Party[1]: DSD
/ LCSD |
P |
P |
P |
- EIAO-TM |
- EM&A (for construction
phase) |
Table 12.11 |
11.2. |
OM3
– Compensatory Tree Planting Any trees to be felled under the Project shall be
compensated in accordance with DEVB TC(W) No. 4/2020 - Tree
Preservation. A Tree Preservation and
Removal Proposal (TPRP) shall be prepared and submitted under the DEVB TC(W)
No. 4/2020 by Contractor. As
stipulated in DEVB TC(W) No. 4/2020, “…the number of compensatory trees
onsite and offsite shall not be lower than that of number of trees removed
including dead trees, but excluding trees of undesirable species...”. The compensatory plantings shall be
realistic, practicable and sustainable with a holistic consideration to
balance the quantity and quality of tree planting, and follow the “right tree
for the right place” principles.
The proposed planting species shall be made reference to the
Greening Master Plan issued by CEDD and the Street Tree Selection Guide
issued by DEVB. To compensate the
loss of existing trees, heavy standard compensatory trees are proposed in
available planting area to enhance the amenity value to vicinity of site,
subject to detailed design. |
To compensate trees
to be felled under the Project |
Design, Construction
and Operational Phases |
DSD / Contractor Long-term Maintenance
Party[1]: DSD
/ LCSD |
P |
P |
P |
- DEVB TC(W) No. 4/2020 |
-
EM&A (for construction
phase) |
Table 12.11 |
11.2. |
OM4 – Sensitive and Aesthetically Pleasing
Design Sensitive and aesthetically pleasing design as regard to the
form, material and finishes shall be incorporated to the proposed
above-ground structures e.g. pavilions, seating areas, viewing decks,
railings along the nullah etc so as to minimise any potential adverse
landscape and visual impact. |
To enhance aesthetic
value of the proposed aboveground structures |
Design and
Operational Phases |
DSD / Contractor Long-term Maintenance
Party[1]: DSD
/ LCSD |
P |
|
|
- EIAO-TM |
- EM&A (for construction
phase) |
Table 12.11 |
11.2. |
OM5
– Tree Transplanting According
to latest tree treatment proposal, 1 no. of tree that is unavoidably affected
by proposed works is suggested to be transplanted where practical. A TPRP will be submitted to relevant government
departments for approval in accordance with DEVB TC(W) No. 6/2015 - Maintenance of Vegetation and Hard
Landscape Features and DEVB TC(W) No. 4/2020 - Tree Preservation, and
Guidelines on Tree Transplanting by DEVB and final locations of transplanted
trees should be agreed prior to commencement of the work. A
cost-effective transplanting strategy should be established at the Design
Phase of the Project. Transplanted
trees are recommended to be relocated to final locations without the use of
Holding Nursery under single handling where possible subject to the sequence of
construction of the works. This will minimize the
cost and ensure the better survival of the trees after transplanting. However, if single transplanting handling
is not possible, the transplanted trees shall be translocated to a holding
nursery before the commencement of the engineering works; and will be
replanted back to the receptor sites once the engineering works are
completed. |
To transplant trees
which are affected by proposed works |
Design, Construction
and Operational Phases |
DSD / Contractor Long-term Maintenance
Agent[1]: DSD
/ LCSD |
P |
P |
P |
-
DEVB TC(W) Nos. 6/2015 and 4/2020 -
Guidelines on Tree Transplanting by DEVB |
-
EM&A (for construction phase) |
Note:
[1] In case of interface issues between DSD
(Project Proponent) and LCSD facilities, the arrangement of long-term
maintenance/management agencies are subject to agreement of with corresponding
departments in accordance with DEVB TCW No. 6/2015 - Maintenance of
Vegetation and Hard Landscape Features.
Table 14.11 Implementation Schedule of the Best Management Practices on Pollution Control during Operational Phase
EIA Ref. |
EM&A Manual Ref. |
Environmental Protection Measures |
Objectives of the Measures |
Location / Duration of Measures/ Timing of
Completion of Measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
Tools/ Mechanism for Implementation |
||||
Des |
C |
O |
||||||||||
Air
Quality |
||||||||||||
3.7.2 |
N/A |
The temporary stockpile materials from maintenance desilting will
be located as far away from the ASRs as possible. These materials will be properly covered
with tarpaulin and should be removed off-site within 24 hours to avoid any
odour nuisance arising. |
To avoid odour from
desilting materials from maintenance works |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
-EIAO-TM |
- Maintenance
practices of future management government departments |
||
Noise |
||||||||||||
4.8.2.1 |
N/A |
Develop
and implement a regularly scheduled plant maintenance programme so that plant
items are properly operated and serviced.
The programme should be implemented by properly trained personnel. |
To further minimise
any fixed plant noise nuisance |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
-EIAO-TM |
- Maintenance
practices of future management government departments |
||
Water
Quality |
||||||||||||
5.8.2.1 –
5.8.2.9 |
N/A |
Surface Run-off / Irrigation Run-off /
Runoff from Riparian Public Open Space ·
BMPs
for storm water discharge and management, as well as good administrative and management
measures for riparian public open spaces
as detailed below are recommended for the Project to mitigate potential
adverse water quality impacts. DSD PN
No. 3/2021 “Guidelines on Design for Revitalisation of River Channel”
guidelines on the essential environmental considerations and maintenance and
management requirements for a revitalised river channel should also be
followed. ·
Good
management measures such as regular cleaning and sweeping of road surface /
open areas is suggested. The road surface
/ open area cleaning should also be carried out prior to occurrence of
rainstorm. Sufficient
garbage collection unit /
system should be established / maintained and litters in amenity areas or
river should be regularly removed. ·
Good
management practices should be adopted to properly manage the water
application rate and time during irrigation to minimise chance of
run-off. Use of fertilisers and
pesticides, if required, should be properly controlled, e.g. applications
prior to forecasted heavy rain event should also be avoided to minimise the
potential for run-off of residual fertiliser. In
addition, use of more specific, systemic and biodegradable pesticide in low
dosage is more preferred. Priority would be given to
remove infected/sick plantings over the use of pesticides. The use and handling of fertilisers and
pesticides should follow the Pesticide Ordinance and Code of Practice for the
Safe and Proper Use of Pesticides in Public Areas by AFCD, Food and Health
Bureau (FEHD) and Leisure and Cultural Services Department (LCSD). ·
Manholes,
as well as storm water gullies, ditches provided among the development areas
should be regularly inspected and cleaned (e.g. monthly). Additional inspection and cleansing should
be carried out before forecast heavy rainfall. ·
Channel
that allows activities close to the water should deploy a patrol team to
identify unsafe behaviours and to safeguard the public’s safety. The leisure facilities should also be provided with
instructions and safety warnings in conspicuous places. ·
The
following management and maintenance requirements on water quality control
recommended in DSD PN No. 3/2021: o Regular sample and test water quality; o Facilities that allow primary contact
recreation (e.g. water play zone) should develop its standard operating
procedure in case of not meeting the Water Quality Goals (Mitigation measures
during operation phase for water play zone); o Regularly maintain the treatment unit
to meet its design treatment effectiveness; o Develop emergency response plan on how
primary/secondary contact recreation activities; and shall be suspended when
water quality fails to achieve the water quality goals i.e. mitigation
measures during operation phase for water play zone. |
To prevent / minimise
water pollution from surface / irrigation run-off |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
- WPCO - TM-DSS - ProPECC PN 5/93 - Pesticide
Ordinance (Cap. 133) - Code of Practice
for the Safe and Proper Use of Pesticides in Public Areas |
- Pollution
control and other regulations - Maintenance
practices of future management government departments |
||
5.8.2.10
– 5.8.2.11 |
N/A |
Routine Maintenance Works The maintenance practices would be
similar to the existing maintenance works undertaken by the DSD. The following considerations would be
included in planning for the maintenance works: ·
Maintenance
desilting of the nullah should be carried out on an annual basis during dry
season (November to March) when the water flow is low, with the exception of
during emergency situations where the accumulated silt would adversely affect
the hydraulic capacity of the nullah or where flooding risk is imminent, or
when complaints on environmental nuisance associated with the accumulated
silt are received. Desilting should be
carried out by hand-held or light machinery at low tide. ·
Phasing
of the works should be considered to better control and reduce any impacts
caused. Where possible, works should
be carried out along half width of the drainage channel in short
sections. A free passage along the
drainage channel is necessary to avoid forming stagnant water in any phase of
the works. ·
Containment
structures (such as sandbags barrier) should be provided for the desilting
works area to facilitate a dry or at least confined working area within the
drainage channel. ·
The
locations for the disposal of the removed materials should be identified and
agreement sought with the relevant departments before commencement of the
maintenance works. Temporary stockpile
of waste materials should be located away from the channel and properly
covered. These waste materials should
be disposed of in a timely and appropriate manner. ·
Effective
temporary flow diversion scheme should be implemented and the generated
wastes should be collected and disposed off-site properly to avoid adversely
affecting the water quality of the drainage system. |
To avoid or minimise
water quality impact from routine maintenance works |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
- EIAO-TM - WPCO - WDO |
- Pollution
control regulations - Maintenance
practices of future management government departments |
||
Waste
Management |
||||||||||||
6.5.2.1 |
N/A |
·
The
silt materials, debris and screenings from the DWFI system / nullah during routine
maintenance, as well as from maintenance desilting, should be properly stored
in enclosed bins or compaction units and
transported to the designated landfill for disposal as soon as possible. |
To ensure proper
waste management to control associated environmental nuisance |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
- Air
Pollution Control (Construction Dust) Regulation - WDO - Public
Health and Municipal Services Ordinance (Cap.132) - WPCO |
- Pollution
control regulations - Maintenance
practices of future management government departments |
||
6.5.2.2 |
N/A |
·
All
chemical waste generated from the maintenance works should be properly
stored, labelled and removed by licensed waste collectors in accordance with
Waste Disposal (Chemical Waste) (General) Regulation. |
To ensure proper
waste management |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
- WDO - Public
Health and Municipal Services Ordinance (Cap.132) - Waste
Disposal (Chemical Waste) (General) Regulation - Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes |
- Pollution
control regulations - Maintenance
practices of future management government departments |
||
6.5.2.3 |
N/A |
General
Refuse from Visitors ·
Sufficient
number of trash bins and recycling bins have already been provided and would
be retained for the collection of general refuse generated by visitors along
TWN. ·
Same
as the existing practice, the general refuse would be removed by reputable
waste collector on a daily basis. |
To ensure proper
waste management to control associated environmental nuisance |
Along TWN /
Throughout operational phase |
Project
Proponent |
|
|
P |
- WDO - Public
Health and Municipal Services Ordinance (Cap.132) |
- Pollution
control regulations |
||
Ecology |
||||||||||||
9.8.3.8 |
N/A |
Best
Management Practices (BMPs) for storm water discharge should follow the
relevant guidelines and practices as given in the ProPECC
PN 5/93 to minimise surface runoff from the Project, whilst good site
practices in planning maintenance works should be followed to minimise the
potential impacts on water quality to the nearby waterbodies from surface
run-off / maintenance works and the associated ecological impacts. |
Minimise the
potential impacts on water quality to the nearby waterbodies from surface
run-off / maintenance works and the associated ecological impacts |
Maintenance period /
Throughout operational phase |
Project
Proponent |
|
|
P |
- ProPECC PN 5/93 |
- Pollution
control regulations - Maintenance
practices of future management government departments |
||
Fisheries |
||||||||||||
10.6.3 |
N/A |
Since no adverse
fisheries impacts would be anticipated under normal operation of the TWN, no
specific fisheries mitigation measure during operational phase is considered
necessary for the Project.
Nonetheless, water pollution control measures should be strictly
followed as these measures also serve to further protect fisheries resources. |
N/A (Measures are under
water quality section) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
||