Slope Stabilisation Works in Ship Street, Hong Kong
The
project was a slope stabilisation works at Ship Street, Hong Kong
Environmental
Concern
The site was surrounded by domestic and commercial premises. In the absence of any dust emission control measures, e.g. mixing dry cement powder without enclosure, the slope stabilisation works, would cause serious dust disturbance to the pedestrians as well as the nearby domestic and commercial premises.
Measures
Adopted
Administration
- Pre-blended concrete mix plus pre-dampening control was used.
Dust
Cover - Barriers were erected between work sites and sensitive
receptors.
Watering
- Correct pressure and water setting were applied in the event of shotcreting
works.
Messy
works environment without proper measures
Orderly environment upon works completion
Observations
& Achievements
Since the implementation of the dust abatement measures, the dust nuisance to the pedestrian was stopped.