Hoarding at West Rail Site Formation Works in Yuen Long
The
project involved site formation works carried out at Yuen Long for KCRC
West Rail Construction.
Environmental Concern
Dust and mud arising from site formation or transportation of construction materials were the major concern affecting the users of Pat Heung Road and Kam Tin Road.
No
hoarding was erected at the site boundary and the public road was very dusty
Vehicle
washing facilities not provided at a vehicle exit point and dusty deposits
were brought to public road.
Vehicle was not washed to remove dusty materials before leaving the construction site
Measures
Adopted
Hoarding
- Hoarding along Pat Heung Road and Kam Tin Road was erected.
Treatment
- In addition, vehicle-washing facilities were provided at every discernible
or designated vehicle exit points.
Vehicle
washing facilities provided and in use at a vehicle exit point
Hoarding
erected along site boundary
The vehicle exit of the construction site was cleaned
Observations
& Achievements
Through installation of the vehicle washing facilities and erection of handing, the dust level along Pat Heung Road and Kam Tin Road were greatly reduced.