Measures
Adopted
Quiet
Method - A purposely-built acoustic enclosure was built to screen
the operation of concrete pump and the concrete lorry mixer. The mixer
is a Specified Powered Mechanical Equipment which demands a more stringent
Acceptable Noise Level.
CNP
- No concreting work was allowed beyond 11 p.m.
Administration
- To ensure good communication, the contractor was required to submit
a 48-hour-advance notification before commencement of concreting work
of those identified bore piles and diaphragm walls necessitating major