Environmental Impact Assessment
Executive Summary
Proposed Low-rise and Low-density Residential
Development
At Various Lots and their Adjoining
Government Land
in D.D. 104, East of Kam Pok Road,
Mai Po, Yuen Long, N.T.
Prepared by
Ramboll Environ
Hong Kong Limited
in association with
ADI
Limited
AECOM
China
Point Consultants Ltd.
CKM Asia Limited
Ecosystems
Ltd.
MCAAL
Vision
Planning Consultants Ltd.
Westwood
Hong and Associates Ltd.
Date:
August 2016
Reference Number:
R2057_V6.F
Environmental Impact
Assessment
Executive Summary
Proposed Low-rise and Low-density Residential
Development
At Various Lots and their Adjoining
Government Land
in D.D. 104, East of Kam Pok Road,
Mai Po, Yuen Long, N.T.
Prepared by: |
|
Approved by: |
Henry
Ng |
|
David
Yeung |
Ramboll Environ
Hong Kong Limited
Room 2403,
Jubilee Centre,
18 Fenwick
Street,
Wanchai,
Hong Kong
Tel: 3465 2888
Fax: 3465 2899
E-mail: hkinfo@ramboll.com
Q:\Projects\HENKPRRDEI01\Report\EIA\FORMAL Submission_public
inspection Aug16\CD_Report to EPD\Exe Summary_ENG\html
format\Executive Summary R2057 V6.F Eng_160815_clean.htm
Table of Contents
1.3 EIAO and Designated
Projects
2. KEY Findings of ENVIRONmental Impact Assessment (“EIA”)
2.5 Sewerage and Sewage
Treatment
3. ENVIRONMENTAL MONITORING AND AUDIT
List of Figures
Figure 1 Location &
Environs of the Project
Figure 3 Conceptual Layout of the Project
Figure 4 Proposed Landscape Buffer along the Boundary of the Project Site
Figure 5 Illustrative Section of Noise Barrier
Buffered & Visually Enhanced by Peripheral Planting
Figure 6 Recommended Landscape Mitigation Measures –
Design of Landscape Berms
Figure 7 Recommended Landscape Enhancement –
Provision of Landscape Pond
List of Appendix
Appendix A Environmental Impact Assessment
Non-Technical Summary
Figure 1 Location
of the Project Site
Figure
2 Outline Zoning Plan
Figure
3 Conceptual Layout of the Project
|
TSP (1-hour average)
|
RSP (24-hour average)
|
RSP (Annual average)
|
PM2.5 (24-hour average)
|
PM2.5 (Annual average)
|
Predicted Range, μg/m3
|
164 – 316 **
|
78-80 *
|
43.3 – 43.7 **
|
59-59 *
|
30.7 – 30.8 **
|
No. of Exceedance
|
n/a
|
1 ***
|
n/a
|
1 ***
|
n/a
|
Compliance with Air Quality Criteria?
|
Yes
|
Yes #
|
Yes
|
Yes #
|
Yes
|
|
|
|
|
|
|
Air Quality Criteria, μg/m3
|
500
|
100
|
50
|
75
|
35
|
No. of Exceedance Allowed
|
n/a
|
9
|
n/a
|
9
|
n/a
|
Unmitigated
Noise Level, dB(A)
|
Mitigated
Noise Level, dB(A) *
|
Noise
Criteria, dB(A)
|
Mitigation
Measures
|
>75
(for dwellings)
|
58 - 74
|
75dB(A)
for residential uses; and 70dB(A) for educational institutions (65B(A) during school examination period)
|
Quiet type construction
equipment; scheduling of construction programme to avoid concurrent works; best
practices; and provision of movable noise barriers and fixed temporary noise
barriers.
|
>70
(for educational institutions)
|
61-62
|
|
Calculated Noise Level, dB(A)
|
Noise Criteria, dB(A)
|
Road Traffic Noise
|
46 – 70 *
|
70
|
Industrial Noise
|
52 / 45 (day-time/ night-time)
**
|
55 (day-time); and 45 (night-time)
|
|
Recommended
Mitigation Measures
|
Construction Phase
|
·
A peripheral site drainage system comprising
precast concrete u-channels along site boundary and works area;
·
Equipped with sand/silt removal facilities in
accordance with the requirements stipulated in Professional Persons on Environmental
Consultative Committee Practice Notes on the Site Drainage (ProPECC
PN 1/94);
·
Surface runoff to be collected and directed for
treatment before discharge into Ngau Tam Mei Drainage Channel;
·
A construction phase drainage management plan with
details of design of the temporary site drainage system to be prepared, implemented,
and audited;
·
Regular environmental audits, as part of the proposed Environmental Monitoring
and Audit (EM&A), including regular water quality monitoring and site
inspections to ensure there is no uncontrolled discharge of surface runoff
and that the recommended mitigation measures are properly implemented;
·
Pursuant to the “Water Pollution Control
Ordinance”, applications to the EPD for Discharge Licences prior to the commencement
of the construction works and occupation of the development; and
·
An
Emergency Response Plan during inclement weather and emergencies.
|
Operational Phase
|
·
Domestic
sewage to be discharged into planned public sewers under
the permanent disposal scheme;
·
A
sewage treatment plant to treat generated sewage in interim;
·
Treated
effluent is to comply with relevant discharge limits in
the licence and the conditions in the EP, and there is no net increase in
pollution loading to Deep Bay areas;
·
Best Management Practices have
been proposed to abate first flush pollution in stormwater runoff, which
covers design measures; provision of devices/
facilities to remove pollutants; and administrative measures;
·
Proper
drainage system to collect surface runoff from the development with
appropriate facilities and sand traps.
Road gullies with sand traps and oil interceptor and car park and similar facilities to be
installed with oil interceptors; and
·
An
Emergency Response Plan during inclement weather and emergencies.
|
Item |
Target Effluent Quality of STP
* |
Group
C Inland Discharge Standards in WPCO (for flow of ≤100 m3/d) * |
Annual Pollution Loads from 200 m3 channel
water (before Development), ** |
Annual Pollution Loads (after Development with co-treatment) ** |
Annual Reduction of Pollution Loads at Deep Bay WCZ ** |
BOD5
|
3 |
<20 |
292 |
274 |
18 |
TN-N |
4 |
Not Specified |
398 |
365 |
33 |
TP |
0.5 |
<10 |
58 |
47 |
11 |
TSS |
10 |
<20 |
4,453 |
916 |
3,537 |
NH3-N
|
2 |
<2 |
197 |
183 |
15 |
E.coli. (no.) |
1000 |
<1,000 |
2.2 x1013 |
9.1
x1011 |
2.1
x1013 |
Remark: * All units in mg/L except E. coli which is in no./100ml.
|
Recommended
Measures
|
Sewage
from construction workforce
(Construction Phase)
|
·
Chemical toilets will be provided
on-site; and
·
The facility will be serviced and
cleaned by a specialist contractor at regular intervals.
|
Domestic Sewage
(Operational Phase)
|
·
A peak flow of 4.4 L/s sewage to be
generated;
·
Sewage
to be discharged to planned public sewer under permanent disposal scheme;
·
An
interim sewage treatment plant (STP) will be in operation before the
completion of San Tin and Ngau Tam Mei Trunk Sewerage;
·
The
interim STP to be designed to facilitate future connection to the planned San
Tin and Ngau Tam Mei Trunk Sewerage;
·
Maintenance
and emergency measures recommended to ensure effective operation of the STP;
·
Discharge
from interim STP will NOT result
in net increase in pollution loads to Deep Bay by abstracting 200 m3
of water per day from Ngau Tam Mei Drainage Channel for co-treatment at
interim STP;
·
Equalization
tank (with capacity of ~3 days of sewage storage) will be provided in case of
entire outage of the STP. Tank away
will be provided for prolonged outage of STP;
·
The discharge of treated
effluent from
the interim STP is to comply with the terms and conditions in the discharge licence
under the WPCO as well as the conditions specified in the EP of this Project.
|
|
Recommendations
|
Construction Waste
|
· A waste management plan to be prepared and implemented by
contractor(s) through-out construction;
· Implementation of proper trip
ticket system;
· Proper training on waste
management to workers;
·
Avoidance and minimization to reduce the
potential quantity of C&D materials generated; ·
Reuse of materials as practical as possible; ·
Recovery and Recycling as practical as possible; ·
Proper treatment and disposal in respect to
relevant laws, guidelines and good practice; ·
Landfill disposal as the last resort; and ·
Regular environmental audit and monitoring to ensure
effective implementation; ·
On-site re-use of excavated materials/ sediment
will be required. |
ID |
Sensitivity |
Magnitude of Change |
Significance Threshold (Unmitigated) |
Mitigation Measures* |
Significance Threshold (Mitigated) |
|||
Construction Phrase |
Operation Phrase |
Construction Phrase |
Operation Phrase |
Construction Phrase/ Operation Phase Day
1 (Mitigated) |
Operation Phrase |
|||
Year 10 (Residual) |
||||||||
1.0 Key Landscape Resources (LRs) – Insubstantial to Slight
residual impact
significance |
||||||||
LR3.5 Fung Chuk Road Roadside Amenity |
Medium |
Intermediate |
Intermediate |
Moderate Adverse |
Moderate Adverse |
CP1, CP3, CP4,
OP1, OP2, OP6 |
Slight Adverse |
Insubstantial |
LR3.8 Kam Pok Road Roadside Amenity |
Small |
Small |
CP1, CP3, CP4,
OP1, OP2, OP6 |
|||||
LR6.1 Ha San Wai Road North Fish Pond (Abandoned) |
Low |
Large |
Large |
CP3,OP2, OP7 |
Moderate Adverse |
Slight Adverse |
||
LR10.3 Ha Chuk Yuen Road Open Yards |
Intermediate |
Intermediate |
CP3,OP1, OP2 |
Slight Adverse |
Insubstantial |
|||
2.0 Key Landscape Character Areas (LCAs) – Insubstantial residual impact
significance |
||||||||
LCA5 Kam
Pok Road Low-rise Residential Landscape |
Low |
Intermediate |
Intermediate |
Moderate Adverse |
Moderate Adverse |
CP1, CP3, CP4, OP1, OP2, OP5, OP6, OP7 |
Slight Adverse |
Insubstantial |
3.1 Visually Sensitive Receivers (VSRs) - slight
residual impact significance |
||||||||
VSR 3 Vehicular Travellers and Pedestrians along Fung Chuk
Road |
Medium |
Large |
Large |
Significant Adverse |
Significant Adverse |
CP1, CP2, CP5, OP3, OP4, OP5, OP6 |
Moderate Adverse |
Slight Adverse Further to the establishment of tree preservation and
transplanting proposals and new tree planting proposals in the landscape
buffer, the proposed development will be largely screened as in their
original visual context. |
VSR 5 Vehicular
Travellers and Pedestrians along Ha Chuk Yuen Road |
CP1, CP2, CP5, OP3, OP4, OP5, OP6 |
Slight Adverse Further to the establishment of tree preservation
proposals and new tree planting proposals in the landscape buffer, the
proposed development will be largely screened as in their original visual
context. |
||||||
VSR 7 Residents of Low-rise House Development along Ha San
Wai Road |
CP1, CP2, OP3, OP4, OP5, OP6 |
Slight Adverse Responsive design of the building height profile and
massing and innovative design of noise barrier. Upon full establishment of transplanting proposals in
landscape area of Ha San Wai Road, visual impact will be alleviated |
||||||
VSR 11 Vehicular
Travellers and Pedestrians alongside of Ngau Tam Mei Drainage Channel |
CP2, OP3, OP4, OP5 |
|||||||
3.2 Visually Sensitive Receivers (VSRs) – Insubstantial impact
significance |
||||||||
PVSR 1 Residents of Planned Low-rise House Development at
Fung Chuk Road North |
High |
Intermediate |
Intermediate |
Moderate Adverse |
Moderate Adverse |
CP1, CP2, CP5, OP3, OP6 |
Slight Adverse |
Insubstantial |
VSR 4 Villagers of
Chuk Yuen Tsuen and Hang Fook Gardens |
CP2, OP3,OP4, |
|||||||
VSR 8 Residents of
Low-rise House Development along Fairview Park Boulevard |
Medium |
Small |
Small |
Moderate Adverse |
Moderate Adverse |
CP2, OP3, OP4, OP5 |
Slight Adverse |
Insubstantial |
VSR 10 Residents of
Low-rise House Development at Fairview Park |
Intermediate |
Intermediate |
CP1, OP6 |
|||||
VSR 2 Workers at Chuk Yuen Floodwater Pumping Station and
Storage Pond |
Low |
Intermediate |
Intermediate |
Moderate Adverse |
Moderate Adverse |
CP1, CP2, CP5, OP3,OP6 |
Slight Adverse |
Insubstantial |
VSR 6.1 Workers of
Warehouses and Open Container Storage at Ha San Wai Tsuen |
CP1, CP2, CP5, OP3,OP4, OP5, OP6 |
|||||||
VSR 6.2 Villagers
of Ha San Wai |
CP2, OP3, OP4, OP5, OP6 |
|||||||
VSR 9 Vehicular
Travellers and Pedestrians along Fairview Park Road South |
CP2, OP3, OP4, OP5 |
|||||||
3.3 Visually Sensitive Receivers (VSRs) – beneficial impact
significance |
||||||||
PVSR 12A Future Residents of Planned Recreation Zone to the east of
Fairview Park |
Medium |
Intermediate |
Intermediate |
Moderate Adverse |
Moderate Adverse |
CP1, CP2, CP5, OP3, OP5, OP6 |
Slight Adverse |
Slight Beneficial Responsive design of the building height profile and
massing. Upon full establishment of tree preservation,
transplanting and new planting proposals in the roadside landscape area of
Kam Pok Road, visual impact will be alleviated |
PVSR 12B Future Recreational Users of Planned Recreation Zone to
the east of Fairview Park |
* Proposed Landscape and/or Visual Mitigation
Measures
|
Mitigation Code |
Mitigation Measures |
Landscape/Visual |
Construction Phase |
CP1 |
Preservation of Existing Vegetation |
L/V |
CP2 |
Works Area and Temporary Works Areas |
V |
|
CP3 |
Implementation of Mitigation Planting and Planting Species Selection |
L |
|
CP4 |
Transplantation of Existing Trees |
L |
|
CP5 |
Coordination with Concurrent Projects
- Coordinated implementation programme with concurrent projects to minimise
potential impacts and where possible reduce the period of
disturbance. |
V |
|
Operational Phase |
OP1 |
Roadside and Amenity Planting |
L |
OP2 |
Compensatory Planting Proposals |
L |
|
OP3 |
Responsive Design
of Buildings |
V |
|
OP4 |
Noise Mitigation
Structures |
V |
|
OP5 |
Design of Engineering Structure |
L/V |
|
OP6 |
Creation of Landscape Buffer |
L/V |
|
OP7 |
Provision of Landscape Pond |
L |
Figure 7 Recommended
Landscape Enhancement – Provision of Landscape Pond
Environmental
Aspects
|
Monitoring Requirements
|
General
|
Construction Phase:
· Site Surveillance – once per week during construction
phase by ET;
· Environmental complaints investigation – upon receipt of
complaints by ET and IEC;
· Reporting – baseline monitoring report; monthly EM&A
reports; quarterly EM&A summary reports; and final EM&A reports by ET.
|
Noise
|
Construction Phase:
Monitoring noise level at nearby sensitive receivers.
·
Baseline
Monitoring:
Monitoring for 14 days prior to commencement of
construction works by ET.
·
Impact
Monitoring:
Weekly monitoring throughout the construction phase by ET.
Operational Phase:
Nil
|
Air Quality
|
Construction Phase:
Monitoring dust level at nearby sensitive receivers.
·
Baseline
monitoring by ET:
Monitoring for 14 days prior to commencement of
construction works by ET.
·
Impact
monitoring:
Monitoring every six days and throughout the construction
phase by ET.
Operational Phase:
Nil
|
Water Quality
|
Construction Phase:
Monitoring water quality at nearby drainage channel and Ngau Tam
Mei Drainage Channel by ET.
· Baseline Monitoring:
3 days a week and for 4 weeks prior to commencement of
construction works by ET.
·
Impact
Monitoring:
3 days a week throughout the construction phase by ET.
Operational Phase:
Nil
|
Sewerage and Sewage Treatment
|
Construction Phase:
Nil.
Operational Phase:
Regular
sampling and testing of treated effluent in accordance with discharge licence
requirements as well as conditions specified in the EP during operation of
the interim sewage treatment plant by ET. The water
quality at Ngau Tam Mei Drainage Channel will also be monitored
regularly.
|
Waste Management
|
Construction Phase:
Monitoring
on waste generation, disposal and minimisation by ET and Engineer. Auditing on contractor(s) waste management
performance.
Operational Phase:
Nil
|
Landscape and Visual
|
Construction Phase:
· Baseline Review:
Undertaken a tree survey 1 month prior to commencement of
construction work by Certified Arborist or who has tree survey relevant experiences not
less than 1 year.
·
Impact
Monitoring:
Monitoring and auditing of the protection of preserved
trees quarterly from Day 1 of construction phase to the end of planting establishment
period.
Operational Phase:
Nil.
|
Ecology
|
Construction Phase (by qualified ecologist):
· Regular site auditing for checking the
implementation of good site practice;
·
Utilisation
of the Ngau Tam Mei Drainage Channel by birds between October and March will
be monitored during the construction phase.
A baseline survey will be conducted before commencement of construction
works to record bird uses of the Ngau Tam Mei Drainage Channel and
identification of any site condition changes.
Operational Phase:
· Nil
|
Fisheries
|
Construction Phase:
· Nil;
Operational Phase:
· Nil
|