| Activities
which involve the use or handling of Asbestos Containing Materials
Under
the Air
Pollution Control Ordinance, before an owner of premises
carries out any intended asbestos abatement work or work involving
the use or handling of any asbestos containing material, he
is required to submit an Asbestos Investigation Report and
an Asbestos Abatement Plan. He is also required to give written
notice to the Authority of the date on which the work is to
commence.
How
to submit Asbestos Investigation Report and Asbestos Abatement
Plan
1. The
owner of premises shall first engage a registered asbestos
consultant to carry out an investigation and to devise an
abatement plan.
2. The
original copy of the Asbestos Investigation Report and the
Asbestos Abatement Plan can be submitted to any one of the
EPD Customer Service Counters.
3. The
Asbestos Investigation Report and the Asbestos Abatement Plan
is required to reach EPD at least 28 days before the work
is to be commenced.
How
to submit notification of commencement of asbestos abatement
work
1. The
owner of premises shall give notification
in writing the date on which the work is to be commenced.
2. The
notification can be submitted to any one of the EPD Customer Service Counters.
3. The
notification is required to reach EPD at least 28 days before
the work is to be commenced.
Please
also refer to the EPD leaflet "Environmental Asbestos Control".
|