The Project
Outcomes
3D model
Links
 
 
 
     Sai Kung Drainage Improvement     西貢雨水排放改善工程

 
The following amendments have been made after taking into consideration the local Villager Representatives's comments
 
(a)  the scope of works at Pak Kong River reduced from full scale training to removal of two bottleneck;
(b)  re-provide the overflow weir at Ho Chung Channel
 
Key Outcomes:
 
Environmental Friendly Design
 
(a)  The masonry and grasscrete lining was revised to gabion lining with planting pits to retain the river ecology, and to improve the aesthetic, vision and environmental aspect of the river widening works.
(b)  Natural substrates, pools and riffles will be provided at the riverbed so as to restore and enhance the ecological habitat in the originally river channel.
(c)  Fish-ladder will be provided at the downstream side of the weirs.
(d)  Since there were many village houses adjacent to the concerned river section, the structural stability of these houses is the major concern. As such, a remaining wall would be provided behind the gabion walls.
 
Dredging at Seabed of Peng Chau, Tung Wan Gas-fired Power Station Extension at Lamma Kam Tin Secondary Drainage Channels KT13 Hong Kong Wetland Park Sheung Shui to Lok Ma Chau Spurline Sai Kung Drainage Improvement Repositioning and Long Term Operation Plan of Ocean Park KCRC East Rail Extension New Boundary Bridge between Lok Ma Chau and Huanggang Sheung Shui to Lok Ma Chau Spurline (Habitat Creation and Management Plan) background