Contents

Executive Summary                                                                                     

1                      introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   Marine Construction Works Undertaken during Reporting Week      

2.3                   Status of Environmental Approval Documents

3                      Water Quality Monitoring Requirements                

3.1                   Monitoring Locations                                                        

3.2                   Monitoring Parameters and Frequency                 

3.3                   Monitoring Equipment and Methodology               

4                      Impact Monitoring Results                                             

4.1                   Data Collected During Mid-Ebb and Mid-Flood Tidal Conditions  

4.2                   Continuous In-Situ Measurement Data                     

5                      Environmental Non-CONFORMANCES                          

5.1                   Summary of Environmental Exceedance                

5.2                   Summary of Environmental Complaint                    

5.3                   Summary of Environmental Summons and Prosecution

6                      Future Key Issues                                                                 

6.1                   Key Issues For The Coming Month                                

6.2                   Monitoring Schedule For The Coming Months     

7                      Conclusions                                                                           

 


LIST OF TABLES

Table 2.1        Summary of Marine Works Undertaken During the Reporting Week

Table 2.2        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Table 3.1        Co-ordinates of Starting Points and Ending Points for Zones A and E (HK Grid)

Table 3.2        Co-ordinates of Baseline Monitoring Stations (HK Grid)

Table 3.3        Monitoring Frequency and Parameters for Impact Monitoring at Zone A

Table 3.4        Proposed Action and Limit Levels of Water Quality for Zones A and E

Table 4.1        Exceedances of Action and Limit Levels for Suspended Solids during Mid-flood Tide on 20 May 2009

Table 6.1        Construction Works to be Undertaken in the Coming Monitoring Period

 

 

LIST OF ANNEXES

Annex A

Impact Monitoring Schedule

Annex B

QA/QC Results of Laboratory Testing for Suspended Solids

Annex C

Impact Water Quality Monitoring Results

Annex D

Continuous In-situ Measurement Data

 

LIST OF FigureS

Figure 2.1

The Route of the Proposed Cable System

Figure 3.1

Location of Water Quality Monitoring Stations (Zone A)

 

 

Executive Summary

The construction works for the VSNL Intra Asia Submarine Cable System – Deep Water Bay commenced on 16 March 2009.  This is the third Weekly Impact Monitoring Report presenting the impact water quality monitoring conducted during the period from 15 May to 21 May 2009 in accordance with the EM&A Manual.

Summary of Construction Works undertaken during the Reporting Period

During the reporting week, route clearance and pre-lay trial run of the burial tool the “Injector” was undertaken outside Zones A to E on 16 May and 17 May 2009.  Following this, the working vessel was mobilised to Deep Water Bay on 18 May 2009.  The working vessel entered Zone A at around 14:47 hrs on 19 May 2009 and preparation works including deployment of marker buoys and setup for cable joint operations were undertaken afterwards.  On 20 May and 21 May 2009, onboard activities were carried out to join the Pre-laid shore end to the cable on board the barge. 

Water Quality

Three monitoring events were scheduled between 15 May and 21 May 2009 at Deep Water Bay (ie Zone A).  All monitoring events at all designated monitoring stations were performed on schedule, ie on 19 May, 20 May and 21 May 2009.

All measured Dissolved Oxygen and Turbidity levels complied with the Action and Limit (AL) Levels. 

Environmental Non-conformance

Three exceedances of Action and Limit Levels for Suspended Solids (SS) were noted on 20 May 2009.  Results of the detailed investigation indicated that none of the recorded exceedances were attributed to the Project construction works.

No complaints were received during the reporting week.

No environmental summons/prosecution were received during the reporting week.

Future Key Issues

Works to be undertaken in the coming monitoring period (ie 22 May to 28 May 2009) include onboard construction activities for cable joint operations prior to the Phase III cable installation works.

 


1                                  introduction

ERM-Hong Kong, Limited (ERM) was appointed by Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) as the Monitoring Team (MT) to implement the Environmental Monitoring and Audit (EM&A) programme for the VSNL Intra Asia Submarine Cable System – Deep Water Bay (thereinafter called the (‘Project’)).

1.1                            Purpose of the Report

This is the third Weekly Impact Monitoring Report, which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from 15 May to 21 May 2009.

1.2                            Structure of the Report

The structure of the report is as follows:

Section 1 :  Introduction

Details the background, purpose and structure of the report.

 

Section 2 :  Project Information

Summarises background and scope of the project, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting period.

 

Section 3 :  Water Quality Monitoring Requirements

Summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, and Event / Action Plans.

 

Section 4 :  Monitoring Results

Summarises the monitoring results obtained in the reporting period.

 

Section 5 :  Environmental Non-conformance

Summarises any monitoring exceedance, environmental complaints and environmental summons within the reporting period.

 

Section 6 :  Future Key Issues

Summarises the monitoring schedule for the next week.

 

Section 7 :  Conclusions

Presents the key findings of the impact monitoring results.

 

 

2                                  Project Information

2.1                            Background

Tata Communications (Bermuda) Ltd (formerly Videsh Sanchar Nigam Limited (VSNL)) proposes to install a submarine telecommunications cable, which will run from Deep Water Bay and through southeast Hong Kong offshore waters.  The cable landing site will be at the western edge of Deep Water Bay beach at an existing cable landing manhole location.  From Deep Water Bay, the cable will extend southwards towards the East Lamma Channel.  Near to Round Island, the cable will turn approximately parallel to the East Lamma Channel passing to the south of Po Toi Island.  The cable will then run eastward close to the boundary of HKSAR waters and then out beyond Hong Kong territorial waters into the South China Sea.  At the southeast offshore waters, it will be necessary to install a grout mattress to protect the cable where it crosses Hong Kong Electric Co., Ltd’s (HKE) gas pipeline.  A map of the proposed cable route is presented in Figure 2.1.

In August 2007, a Project Profile (PP) included an assessment of the potential environmental impacts associated with the installation of the submarine cable circuit was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for application for Permission to apply directly for an Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP-294/2007) and Further Environmental Permit (FEP-01/294/2007).  Amendments to the permitting requirements were incorporated into the Environmental Permit to address potential environmental impacts associated with cable crossings over the HKE’s gas pipeline in southeast Hong Kong waters.  Under the requirements of Condition 3 of the EP, an EM&A programme as set out in the Environmental Monitoring and Audit Manual (EM&A Manual) is required to be implemented.  In accordance with the EM&A Manual, impact monitoring of water quality is required for the Project.

Baseline Monitoring was conducted near Deep Water Bay (ie Zones A and E) between 27 February 2009 and 9 March 2009 and the results were presented in the Baseline Water Quality Monitoring Report Part A.  Baseline monitoring for the Po Toi section of works was undertaken from 27 February 2009 to 13 March 2009 and the Baseline Water Quality Monitoring Report Part B presented the results of the monitoring data for Zones B to D near Po Toi Island.

Impact Monitoring has been carried out at Deep Water Bay (ie Zone A) since 25 March 2009.  This report presents results of the data from monitoring stations within Zone A during the cable installation works in the reporting week.  Results of the impact monitoring data will therefore be compared against the results of the Baseline Environmental Monitoring Part A.

2.2                            Marine Construction Works Undertaken during Reporting Week

The cable installation barge “CB Networker” installs the cable in three phases:

·           Phase I – Locate in-service cables by divers (ie completed);

·           Phase II – Conduct route clearance and pre-lay trial run of burial tool “Injector” (completed); and

·           Phase III – Install cable along the proposed route using the burial tool “Injector”.

A summary of the major works undertaken during the reporting week is shown in Table 2.1.

Table 2.1        Summary of Marine Works Undertaken During the Reporting Week

Date

Works Area

Activity

15 May 2009

Outside Zones A to E

Weather Downtime

16 May 2009

Outside Zones A to E

Route clearance and pre-lay trail run of burial tool “Injector”

17 May 2009

Outside Zones A to E

Route clearance and pre-lay trail run of burial tool “Injector”

18 May 2009

Outside Zones A to E

Mobilisation of the working vessel to Deep Water Bay

19May 2009

Zone A

(the working vessel entered Zone A at around 14:47 hrs)

Mobilisation of the working vessel to Deep Water Bay.  Preparation works including deployment of marker buoys and setup for jointing operations stock cable to mini shore end

20 May 2009

Zone A

Onboard activities to join the Pre-laid shore end to the cable on board the barge

21 May 2009

Zone A

Onboard activities to join the Pre-laid shore end to the cable on board the barge

 

2.3                            Status of Environmental Approval Documents

A summary of the relevant permits, licences, notifications and/or reports on environmental protection for this Project is presented in Table 2.2.

Table 2.2        Summary of Environmental Licensing, Notification, Permit and Reporting Status

Permit / Licence / Notification / Report

Reference

Validity Period

Remarks

Environmental Permit

(EP-294/2007)

Throughout the construction period

 

Granted on 23 November 2008

Further Environmental Permit

(FEP-01/294/2007)

Throughout the construction period

 

Granted on 9 July 2008

EM&A Manual

-

Throughout the construction period

 

Approved by EPD on 12 March 2009

Baseline Water Quality Monitoring Report (Part A)

-

Throughout the construction period for Zones A and E

Approved by EPD on 1 April 2009

Baseline Water Quality Monitoring Report (Part B)

-

Throughout the construction period for Zones B to D

Approved by EPD on 30 April 2009


3                                  Water Quality Monitoring Requirements

3.1                            Monitoring Locations

In accordance with the EM&A Manual, during the installation of the cable in Zone A, water quality sampling was undertaken at stations situated around the cable laying works at Deep Water Bay (ie Zone A).  The locations of the sampling stations within Zone A are shown in Figure 3.1. 

·           S1 and S2 are situated at the two Seawater Intake Points in Deep Water Bay.  They are within 500 m west/northwest of the cable alignment at Deep Water Bay for monitoring the effect of cable laying works in the area.  The monitoring works started when the cable installation works were carried out in Zone A;

·           S3 is a Sensitive Receiver used to monitor the water quality condition of the Coastal Protection Areas at Middle Island.  The monitoring works took place when the cable installation works were conducted in Zone A;

·           B1 is an Impact Station used to monitor the effect of the construction activities on Deep Water Bay Beach when the cable installation works were undertaken in Zone A; and

·           R1 is a Control Station for S1, S2, S3 and B1 at Deep Water Bay which is not supposed to be influenced by the cable laying works due to its remoteness from the construction works.

The co-ordinates of Zone A and the above monitoring stations are listed in Table 3.1 and Table 3.2, respectively.

Table 3.1        Co-ordinates of Starting Points and Ending Points for Zone A (HK Grid)

Zone

Starting Point

Ending Point

Easting

Northing

Easting

Northing

A

837029.763

811601.699

836367.572

810545.975

Table 3.2        Co-ordinates of Baseline Monitoring Stations (HK Grid)

Station

Nature

Corresponding Control Station

Easting

Northing

S1

Seawater Intakes

R1

836538.669

811528.535

S2

Seawater Intakes

R1

836195.047

810956.409

S3

Coastal Protection Areas

R1

836677.103

810666.744

B1

Gazetted Beach

R1

837241.114

811498.400

R1

Control Station

-

835951.109

809052.535

3.2                            Monitoring Parameters and Frequency

The impact water quality monitoring was conducted in accordance with the requirements stated in the EM&A Manual.  These are presented below.

3.2.1                      Monitoring Parameters

Parameters measured in situ were:

·           dissolved oxygen (DO) (% saturation and mg L-1);

·           temperature (°C);

·           turbidity (NTU); and

·           salinity (‰).

The only parameter measured in the laboratory was:

·           suspended solids (SS) (mgL-1).

In addition to the water quality parameters, other relevant data were measured and recorded in field logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal state, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

3.2.2                      Monitoring Frequency

Impact Monitoring at S1, S2, S3, B1 and R1 took place when the cable installation works were undertaken within 500 m (Zone A) of monitoring stations S1, S2, S3 and B1.  The sampling works ceased when no cable installation works were conducted inside Zone A.

Impact monitoring was carried out during the barge operating hours, normally covering both mid-flood and mid-ebb tidal conditions, until water quality monitoring was not required.

In-situ and SS data of the control and impact stations within Zone A were collected daily during mid-flood and mid-ebb tidal states (Table 3.3).  In addition, continuous in-situ measurements were taken at the impact monitoring stations, ie B1, S1, S2 and S3, at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) within Zone A.  The monitoring frequency and parameters for Impact Monitoring are summarised in Table 3.3.

Table 3.3        Monitoring Frequency and Parameters for Impact Monitoring at Zone A

Zone

Station Type

Monitoring Station

Monitoring Frequency

Monitoring Parameter

Mid-ebb Tide / Mid-flood Tide

30- to 60- Minute Interval

A

Control

R1

Daily when cable installation works undertaken in Zone A

Temperature, Turbidity, Salinity, DO, SS

-

Impact

S1, S2, S3 and B1

Temperature, Turbidity, Salinity, DO

3.3                            Monitoring Equipment and Methodology

3.3.1                      Monitoring Equipment

Dissolved Oxygen, Temperature, Salinity, Turbidity Measuring Equipment

The instrument was a portable, weatherproof multi-parameter measuring instrument (YSI 6820) complete with cables, multi-probe sensor, comprehensive operation manuals, and was operable from a DC power source.  It was capable of measuring:

·           dissolved oxygen levels in the range of 0 – 50 mg L-1; and 0-500% saturation;

·           temperature of -5 to 50 °C;

·           turbidity levels between 0-1000 NTU (response of the sensor was checked with certified standard turbidity solutions before the start of measurement); and,

·           salinity in the range of 0-40 ppt (checked with 30 ppt Salinity solutions before the start of the measurement).

Water Depth Gauge

The water depth gauge affixed to the bottom of the water quality monitoring vessel was used.

Current Velocity and Direction

Current velocity and direction was estimated by conducting float tracking.

Positioning Device

A Global Positioning System (GPS) was used (C-Navigator World DGPS, GPS 72A) during monitoring to ensure the accurate recording of the position of the monitoring vessel before taking measurements.  The use of DGPS was used for positioning device, which was well calibrated at an appropriate checkpoint.

Water Sampling Equipment

Water samples for suspended solids measurement were collected by the use of a multi-bottle water sampling system (General Oceanics Inc., Rosette Sampler ROS02), consisting of PVC bottles of more than two litres, which could be effectively sealed with cups at both ends.  The water sampler had a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler was at the selected water depth.

3.3.2                      Monitoring Methodology

Timing & Frequency

In-situ and SS data were collected daily at both control and impact stations within Zone A if the monitoring period covered the mid-flood tide and/or mid-ebb tide.  The water quality sampling was undertaken within a 3 hour window of 1.5 hours before and 1.5 hours after mid-flood and mid-ebb tides.  Tidal range for flood and ebb tides was not less than 0.5m for capturing representative tides.  Continuous In-situ measurements were taken at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) for each impact station within Zone A.

Reference was made to the predicted tides at Waglan Island, which is the tidal station nearest to the Project site, published on the website of Hong Kong Observatory([1]).  Based on the predicted water levels at Waglan Island, the impact water quality monitoring was conducted following the schedule presented in Annex A.

Duplicate samples were collected from each of the monitoring events for in situ measurements and laboratory analysis.

Depths

Each station was sampled and measurements were taken at three depths, 1 m below the sea surface, mid depth and 1m above the sea bed.

Protocols

The multi-parameter measuring instrument (YSI 6820) was checked and calibrated by an HOKLAS accredited laboratory before use.  Onsite calibration was also carried out to check the responses of sensors and electrodes using certified standard solutions before each use.  Sufficient stocks of spare parts were maintained for replacements when necessary, and backup monitoring equipment was made available.

Water samples for SS measurements were collected in high density polythene bottles, packed in ice (cooled to 4° C without being frozen), and delivered to an HOKLAS accredited laboratory as soon as possible after collection.

Laboratory Analysis

All laboratory work was carried out by a HOKLAS accredited laboratory.  Water samples of about 1,000 mL were collected at the monitoring and control stations for carrying out the laboratory determinations.  The determination work started within the next working day after collection of the water samples.  The analyses followed the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS).

The QA/QC details were in accordance with requirements of HOKLAS or another internationally accredited scheme (for details refer to Annex B).

3.3.3                      Action and Limit Levels

The Action and Limit levels for Zones A and E, which were established based on the results of Baseline Environmental Monitoring Part A, are presented in Tables 3.4.

Table 3.4        Proposed Action and Limit Levels of Water Quality for Zones A and E

Parameter

Action Level

Limit Level

Dissolved Oxygen (DO) (1)

Surface and Mid-depth (2)

Surface and Mid-depth (2)

 

5%-ile of baseline data for surface and middle layer = 6.59 mg L-1

1%-ile of baseline data for bottom layer = 6.42 mg L-1

 

 

 

 

Bottom

Bottom

 

5%-ile of baseline data for bottom layers = 6.58 mg L-1

1%-ile of baseline for bottom layer = 6.42 mg L-1

 

 

 

Depth-averaged Suspended Solids (SS) (3) (4)

95%-ile of baseline data = 7.91 mg L-1

99%-ile of baseline data = 8.96 mg L-1

 

or 120% of control station's SS at the same tide of the same day

or 130% of control station's SS at the same tide of the same day

 

 

 

Depth-averaged Turbidity (Tby) (3) (4)

95%-ile of baseline data = 5.17 NTU

99%-ile of baseline data = 5.72 NTU

 

or 120% of control station's Tby at the same tide of the same day

or 130% of control station's Tby at the same tide of the same day

 

 

 

Notes:

(1)    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(2)    The Action and Limit Levels for DO for Surface & Middle layer were calculated from the combined pool of baseline surface layer data and baseline middle layer data.

(3)    “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths.

(4)    For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

 

3.3.4                      Event and Action Plan

The Event and Action Plan for water quality monitoring which was stipulated in the EM&A Manual is presented in Table 3.5.

Table 3.5       Event Action Plan for Water Quality

Event

Contractor

Action Level Exceedance

Step 1 - repeat sampling event.

Step 2 – identify source(s) of impact and confirm whether exceedance was due to the construction works;

Step 3 – inform EPD, AFCD and LCSD and confirm notification of the non-compliance in writing;

Step 4 - discuss with cable installation contractor the most appropriate method of reducing suspended solids during cable installation (e.g. reduce cable laying speed/volume of water used during installation).

Step 5 - repeat measurements after implementation of mitigation for confirmation of compliance.

Step 6 - if non compliance continues - increase measures in Step 4 and repeat measurements in Step 5.  If non compliance occurs a third time, suspend cable laying operations.

Limit Level Exceedance

Undertake Steps 1-5 immediately, if further non compliance continues at the Limit Level, suspend cable laying operations until an effective solution is identified.


4                                  Impact Monitoring Results

A total of three monitoring events were scheduled between 15 May and 21 May 2009 at Deep Water Bay (ie Zone A).  All monitoring events at all designated monitoring stations within Zone A were performed on schedule, ie on 19 May, 20 May and 21 May 2009.

4.1                            Data Collected During Mid-Ebb and Mid-Flood Tidal Conditions

The monitoring data taken during the mid-ebb and mid-flood tidal conditions for Zone A are presented in Annex C and compared against the baseline monitoring results in Figures C1 - C4.  The impact monitoring results obtained during this week were mostly comparable to the results recorded during the baseline monitoring except that relatively high DO concentrations were measured on 20 and 21 May 2009.

Results of the monitoring showed that all measured dissolved oxygen and turbidity levels complied with the Action and Limit (AL) Levels specified in the EM&A Manual.  Suspended Solids (SS) levels were generally compliant with the Action and Limit Levels, however, exceedances were noted at stations B1, S2 and S3 on 20 May 2009.  A review of the above exceedance is discussed in the following section.

4.1.1                      Exceedance on 20 May 2009

Exceedances of the Action and Limit Levels for Suspended Solids (SS) were recorded at Stations B1, S2 and S3 during the mid-flood tide on 20 May 2009 (Table 4.1).

The Contractor confirmed that the Networker was on a four point mooring in Zone A throughout the day of 20 May 2009.  Onboard activities were undertaken to join the Pre-laid shore end to the cable on board the barge.  Neither the injector nor the thrusters were in operation.

It should be noted that the levels of suspended solids at Stations B1, S2 and S3 exceeded the Action and Limit Levels but were within 120% of the Control Stations R1’s SS level.  This indicates the ambient SS levels were relatively higher.  In addition, SS levels of all impact stations did not show-non-compliance during the preceding mid-edd tide.  The dissolved oxygen concentrations maintained at high levels whilst turbidity levels were generally low throughout the day.  This suggests the water quality in Deep Water Bay was stable and acceptable on 20 May 2009.

It was considered that the exceedances were more likely due to an increase in the natural input of SS when water entered into Deep Water Bay toward the beach during the flood tide.

No spatial trend could be drawn from the monitoring results and hence there were no indications of pollution sources coming from the Project works area.  The exceedances were, therefore, considered unlikely related to the Project works.

Table 4.1        Exceedances of Action and Limit Levels for Suspended Solids during Mid-flood Tide on 20 May 2009

Exceedance Log No.

0096120_20 May 09_SS_F_Station B1

0096120_20 May 09_SS_F_Station S2

0096120_20 May 09_SS_F_Station S3

Sampling date

20 May 2009

Monitoring station

B1, S2 and S3

Parameter

Depth-averaged Suspended Solids (mg/L)

Action Levels

Mid-Flood

120% of R1 = 11.4

or 7.91 (baseline data)

Limit Levels

Mid-Flood

130% of R1 = 12.4

or 8.96 (baseline data)

Measured Levels at Station B1

Mid-Flood

9.67

(exceeds Limit Level)

Measured Levels at Station S2

Mid-Flood

9.33

(exceeds Limit Level)

Measured Levels at Station S3

Mid-Flood

8.17

(exceeds Action Level)

 

4.2                            Continuous In-Situ Measurement Data

Continuous in-situ measurements were taken at the impact monitoring stations, ie B1, S1, S2 and S3, at 30- to 60- minute intervals (subject to the weather conditions and travelling time between stations) for Zone A and the results and the graphical presentations were included in Annex D.

In general, the water quality of Zone A was stable throughout each sampling day (ie 19 May, 20 May or 21 May 2009) with the exception of some fluctuations in bottom DO during the first two days. 

 

5                                  Environmental Non-CONFORMANCES

5.1                            Summary of Environmental Exceedance

Three Notification of Exceedances (NOEs) with detailed investigation reports were issued to EPD and AFCD during the reporting period for recording water quality monitoring exceedances on suspended solids of the monitoring stations.  The exceedances were examined against the Project works.  Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction works.

5.2                            Summary of Environmental Complaint

No complaints were received during the reporting period.

5.3                            Summary of Environmental Summons and Prosecution

No summons or prosecution on environmental matters were received during the reporting period.

 

6                                  Future Key Issues

6.1                            Key Issues For The Coming Month

Works to be taken for the coming monitoring period are summarised in Table 6.1.

Table 6.1        Construction Works to be Undertaken in the Coming Monitoring Period

Zone

Works to be taken

A

Onboard Construction Activities

A

Phase III Cable Installation

E

Phase III Cable Installation

B

Phase III Cable Installation

C

Phase III Cable Installation

D

Phase III Cable Installation

6.2                            Monitoring Schedule For The Coming Months

The tentative schedule of water quality monitoring for the coming week (ie 22 May to 28 May 2009) is presented in Annex B.  The water sampling will be conducted at the same monitoring location as in this reporting week.  However, the tentative schedule of the water quality monitoring is subject to continued operational progress and weather constraints.

 

7                                  Conclusions

This Weekly Impact Monitoring Report presents the EM&A work undertaken during the period from 15 May to 21 May 2009 in accordance with the EM&A Manual and the requirements under FEP-01/294/2007.

Three exceedances of Action and Limit Levels were noted on 20 May 2009 in the reporting week.  Results of the detailed investigation indicated that none of the exceedances were attributed to the Project construction works.

No complaints and summons/prosecution were received during the reporting week.

The MT will keep track of the EM&A programme to verify compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 



([1])         Hong Kong Observatory (2009) http://www.hko.gov.hk/tide/eWLtide.htm