Content


Chapter    Title                                                                                                                           Page

1.1              Background_________________________________________________________________ 1

1.2              Project Organisation___________________________________________________________ 2

1.3              Works Undertaken in the Reporting Month__________________________________________ 2

2.1              Summary of EM&A Requirements________________________________________________ 5

2.2              Implementation of Environmental Mitigation Measures_________________________________ 5

3.1              Monitoring Parameters, Frequency and Duration_____________________________________ 6

3.2              Monitoring Location___________________________________________________________ 6

3.3              Monitoring Equipment__________________________________________________________ 6

3.4              Equipment Calibration_________________________________________________________ 7

3.5              Monitoring Methodology________________________________________________________ 7

3.5.1           Field Monitoring______________________________________________________________ 7

3.5.2           Maintenance and Calibration____________________________________________________ 7

3.6              Results of Impact Monitoring_____________________________________________________ 7

4.1              Site Inspections_______________________________________________________________ 9

4.2              Environmental Meetings_______________________________________________________ 10

4.3              Status of Environmental Submissions, Permits and Licences___________________________ 10

4.4              Advice on the Solid and Liquid Waste Management Status_____________________________ 10

4.5              Review of Environmental Monitoring Procedures____________________________________ 10

4.6              Implementation Status of Environmental Mitigation Measures__________________________ 10

5.1              Non-compliance of Action and Limit Levels________________________________________ 12

5.2              Environmental Complaints_____________________________________________________ 12

5.3              Notifications of Summons and Successful Prosecutions_______________________________ 12

6.1              Construction Programme for the Next Reporting Month_______________________________ 13

6.2              Key Issues for the Next Reporting Month___________________________________________ 13

6.2.1           Air________________________________________________________________________ 13

6.2.2           Noise_____________________________________________________________________ 13

6.2.3           Water Quality_______________________________________________________________ 13

6.2.4           Waste_____________________________________________________________________ 14

6.2.5           Ecology____________________________________________________________________ 14

6.2.6           Landscape and Visual________________________________________________________ 14

6.3              Monitoring Schedule for the Next Reporting Month___________________________________ 14

7.1              Conclusions________________________________________________________________ 15

7.2              Recommendations___________________________________________________________ 15

Appendices                                                                                                                              16

Appendix A.  Construction Works Programme_________________________________________________ 17

Appendix B.  Project Organisation Chart for Section 4___________________________________________ 18

Appendix C. Environmental Quality Performance Limits_________________________________________ 19

Appendix D. Event and Action Plans________________________________________________________ 20

Appendix E.  Schedule of Mitigation Measures from the EIA Report and EM&A Manual__________________ 22

Appendix F.  EM&A Schedule_____________________________________________________________ 34

Appendix G. Calibration Certificates________________________________________________________ 35

Appendix H. Noise Monitoring Results and Graphical Presentation_________________________________ 36

Appendix I.   Monthly Waste Flow Table_____________________________________________________ 37

Appendix J.  Complaint Log______________________________________________________________ 38

Appendix K.  Weather Information from Hong Kong Observatory___________________________________ 39

 

Figures

Figure 1.1:_ General Layout Plan_ 3

Figure 1.2:_ Location of Secondary Boundary Fence and Noise Monitoring Station at Section 4_ 4

 

Tables

Table 2.1:__ Summary of EM&A Impact Requirements 5

Table 3.1:__ Noise Monitoring Parameters, Frequency and Duration_ 6

Table 3.2:__ Noise Impact Monitoring Location_ 6

Table 3.3:__ Noise Monitoring Equipment 7

Table 3.4:__ Noise Monitoring Equipment Calibration Frequencies 7

Table 3.5:__ Results of Noise Impact Monitoring_ 8

Table 4.1:__ Summary of Environmental Site Inspections 9

Table 4.2:__ Status of Environmental Submissions, Permits and Licences 10

Table 4.3:__ Environmental Submissions Made under the Valid EP & FEP(s) during the Reporting Month_ 10

Table 4.4:__ Implementation Schedule of Mitigation Measures 11

Table C.1:__ Action and Limit Levels for Construction Noise_ 19

Table D.1:__ Event and Action Plan for Construction Noise_ 20

Table E.1:__ Recommended Mitigation Measures – Air Quality 22

Table E.2:__ Recommended Mitigation Measures – Noise_ 24

Table E.3:__ Recommended Mitigation Measures – Water Quality 25

Table E.4:__ Recommended Mitigation Measures – Waste Management 27

Table E.5:__ Recommended Mitigation Measures – Ecology 29

Table E.6:__ Recommended Mitigation Measures – Landscape and Visual 30

Table I.1:__ Monthly Summary Waste Flow Table for 2010_ 37

Table J.1:__ Complaint Log for the Reporting Month (December 2010) 38

 


Executive Summary


Mott MacDonald Hong Kong Limited (MMHK) has been commissioned by the Architectural Services Department (ArchSD) as the Environmental Team (ET) to carry out Environmental Monitoring and Audit (EM&A) services for the construction of a secondary boundary fence (SBF) at Section 4 along the boundary in the Frontier Closed Area (FCA).

This is the 7th Monthly EM&A Report for the works carried out during the reporting month from 1 to 31 December 2010, and presents a summary of the environmental monitoring and audit works, list of activities, and mitigation measures implemented during the abovementioned reporting month.

Site Activities

The following major construction activities took place during the reporting month:

Works Order No. 1 (ASD 010962):

¡  No major works. (Substantial completion was certified on 12 October 2010.)

Works Order No. 2 (ASD 010969):

¡  Tree pruning work;

¡  Installation of transparent panel for the new boundary fence;

¡  Construction of footing of the new boundary fence;

¡  Construction of steel frame and mesh for the new boundary fence; and

¡  Excavation works for footing of steel fence.

Works Order No. 3 (ASD 010974):

¡  Erection of hoarding for the new check point;

¡  Excavation at the new check point site; and

¡  Formation of blinding layer for the new check point.

Breach of Action and Level Limits

There was no breach of Action or Limit levels for noise level (measured as Leq) in the reporting month.

Complaints

There was no record of complaints received in the reporting month.

Notification of Summons and Successful Prosecutions

There was no record of Notification of summons and successful prosecution in the reporting month.

Reporting Changes

There are no reporting changes in the reporting month.

Future Key Issues

Future key issues to be considered in the forthcoming month include:

Air

¡  Regular maintenance of all plant and equipment;

¡  Handling of any excavated dusty materials or stockpile of dusty materials;

¡  Spraying of water prior to any loading, unloading or transfer of dusty materials; and

¡  Washing of vehicles before leaving the construction sites.

Noise

¡  Location of noisy equipment and noisy activities relative to the Noise Sensitive Receivers (NSRs);

¡  Avoiding the operation of unused equipment, and minimising the use of Powered Mechanical Equipment (PME) and parallel use of noisy equipment / machinery;

¡  Adoption of Level 1 site-specific direction mitigation measures (use of quiet plant and movable noise barrier) for construction/demolition work undertaken at a distance of 60m or less to the NSRs; and

¡  Regular maintenance of all plant and equipment.

Water Quality

¡  No discharge of silty water into the storm drain and drainage channel within and the vicinity of the site;

¡  Removal off-site of construction plant causing pollution to water system due to leakage of oil or fuel; and

¡  Temporary stockpiling of excavated soil in a specially designated area with provision of tarpaulin cover.

Waste

¡  Control measures at the stockpiling area to prevent the generation of dust and pollution of stormwater channels, fish ponds or river channels;

¡  Segregation, storage, transportation and disposal of different types of waste; and

¡  Keeping of records of quantities of wastes generated, recycled and disposal (with locations).

Ecology

¡  Good site practices for controlling the dust and water quality; and

¡  Clear definition of works limit to avoid impact on adjacent habitats.

Landscape and Visual

¡  Retain tree with high amenity or ecology value and contributing most to landscape and amenity of site;

¡  Precautionary area around trees to be retained equal to half of the tree canopy diameter;

¡  Prohibition of the storage of materials including fuel, the movement of construction vehicles, and the refuelling and washing of equipment including concrete mixers within the precautionary area;

¡  Pruning of the branches of existing trees identified for transplantation and retention;

¡  Rectification and repair of damaged vegetation following the construction phase to its original condition;

¡  Careful monitoring of all works affecting the trees identified for retention and transplantation; and

¡  Enforcement of construction site controls including storage of materials, location and appearance of site accommodation and the careful design of site lighting to prevent light spillage.

Environmental mitigation measures will be implemented on site as recommended and weekly site audits will be carried out to ensure that the environmental conditions are acceptable.



1.1          Background

The Frontier Closed Area (FCA) is an integral part of the package of measures aimed at maintaining the integrity of the boundary of the Hong Kong Special Administrative Region (HKSAR) with mainland China, and combating illegal immigration and other cross-boundary criminal activities.  Following a recent review, the HKSAR Government has concluded that with the erection of a secondary boundary fence (SBF) along the boundary patrol road (BPR) and construction of new sections of the BPR and primary boundary fence (PBF) at certain sections along the boundary, the FCA coverage can be substantially reduced without affecting the objective of maintaining the integrity of the boundary. 

The PBF and SBF (hereafter referred to as ‘The Project’) will be erected along the northern and southern curbs of the realigned BPR respectively to facilitate the Hong Kong Police Force (HKPF) in combating cross-boundary criminal activities.  The reduced FCA will comprise a narrow strip of land covering the realigned BPR and areas to its north, together with the points of crossing the boundary (i.e. the Boundary Control Points and Sha Tau Kok town).  Areas south of the SBF will generally be excised from the FCA.

An Environmental Impact Assessment (EIA) for the proposed works was carried out under the Environmental Impact Assessment Ordinance (EIAO, Cap 499). An EIA Report and an Environmental Monitoring and Audit (EM&A) Manual were completed in January 2009 and approved by the Environmental Protection Department (EPD) in April 2009 (Register No. AEIAR-136/2009). The entire length of the proposed works is about 21.7 km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into four sections. A general layout plan of the Project site is presented in Figure 1.1, while the location of the SBF at Section 4 in Sha Tau Kok is presented in Figure 1.2.

An Environmental Permit (EP) covering the overall proposed works was issued in June 2009 (Permit No. EP-347/2009). An application for Variation of the Environmental Permit (VEP) (Application No. VEP-314/2010) was subsequently submitted on 24 May 2010 and the amended Environmental Permit (Permit No. EP-347/2009/A) was issued by EPD on 9 June 2010.

With regard to Section 4, an application for a Further Environmental Permit (FEP) covering the works under Works Order No. ASD 010962 (also known as Works Order No. 1) was submitted to EPD on 2 March 2010 (Application No. FEP-104/2010) and this was granted on 29 March 2010 (Permit No. FEP-03/347/2009). Furthermore, another application for an FEP covering the works under Works Order Nos. ASD 010969 and ASD 010974 (also known as Works Order Nos. 2 and 3 respectively) – including a new section of SBF consisting of transparent panel, a new checkpoint and kiosk – was submitted to EPD on 13 August 2010 (Application No. FEP-112/2010) and was granted on 7 September 2010 (Permit No. FEP-04/347/2009/A).

The Architectural Services Department (ArchSD) has been entrusted with the management of the Project by the Project Proponent – the Secretary for Security of the HKSAR Government. Mott MacDonald Hong Kong Limited (MMHK) has in turn been commissioned by ArchSD as the consulting engineer for the entire Project under Consultancy Agreement No. 9SN005, and is the Engineer’s Representative (ER) for construction of the Project.

For Section 4 of the Project, MMHK and ENVIRON Hong Kong Limited (ENVIRON) have been commissioned as the Environmental Team (ET) and Independent Environmental Checker (IEC) respectively to undertake the Environmental Monitoring and Audit (EM&A) programme as described in the approved EM&A Manual of the Project. Also, the Contract to undertake and perform the construction works for Section 4 was awarded to Chun Wo Construction & Engineering Company Limited (‘The Contractor’) and is scheduled to last for approximately 18 months. It formally commenced on 28 May 2010, and the construction works and EM&A programme under the above-mentioned EP and FEP(s) also commenced on this date. The construction works programme is presented in Appendix A.

This monthly EM&A report summarises the environmental monitoring and audit works, list of activities and mitigation measures implemented at Section 4 during the period of 1 to 31 December 2010 inclusive (‘reporting month’).

The scope of works for Section 4 consists of:

¡  Erection of an SBF from the entrance of the Sha Tau Kok town (i.e. the location of ‘Gate One’) to the Sha Tau Kok Control Point (approximately 0.5 km);

¡  Use of transparent panel for a section of an SBF;

¡  Provision of a two-storey high checkpoint at ‘Gate One’;

¡  Addition of a kiosk/guard house on an existing footpath of Sha Tau Kok Road; and

¡  Removal of the existing checkpoint at Shek Chung Au.

1.2          Project Organisation

The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix B.

1.3          Works Undertaken in the Reporting Month

The following activities have taken place during the reporting month:

Works Order No. 1 (ASD 010962):

¡  No major works. (Substantial completion was certified on 12 October 2010.)

Works Order No. 2 (ASD 010969):

¡  Tree pruning work;

¡  Installation of transparent panel for the new boundary fence;

¡  Construction of footing of the new boundary fence;

¡  Construction of steel frame and mesh for the new boundary fence; and

¡  Excavation works for footing of steel fence.

Works Order No. 3 (ASD 010974):

¡  Erection of hoarding for the new check point;

¡  Excavation at the new check point site; and

¡  Formation of blinding layer for the new check point.

 


 

Figure 1.1:     General Layout Plan

 


 

Figure 1.2:     Location of Secondary Boundary Fence and Noise Monitoring Station at Section 4

 

 

 

 


2.1          Summary of EM&A Requirements

The EM&A programme requires environmental monitoring of construction noise as well as environmental site inspections for air quality, noise, water quality, waste management, ecology, landscape and visual, as specified in the approved EM&A Manual.

Originally, the EM&A Manual designated two locations as noise monitoring stations during the construction phase. However, currently noise levels at only one of these monitoring stations (as shown in Figure 1.2) are monitored. The reasons for this arrangement are detailed in Section 3.2.

A summary of impact EM&A requirements is presented in Table 2.1. The Environmental Quality Performance Limits and the Event and Action Plans (for construction noise only) are shown in Appendix C and Appendix D respectively.

Table 2.1:      Summary of EM&A Impact Requirements

Parameters

Description

Location(s)

Frequency

Duration

Air

On-site Inspection

Active Works Sites

Weekly

During Construction

Noise

Leq, 30min

STK-DBD

Weekly

During Construction

Waste management

On-site Waste Audit

Active Works Sites

Weekly

During Construction

On-site Waste Inspection

Wastewater

On-site Wastewater Audit

Active Works Sites

Weekly

During Construction

Ecology

On-site Audit of Recommended Ecological Mitigation Measures

Active Works Sites

Periodically (by Contractor)

As specified in EM&A Manual (see Table E.5)

Landscape and Visual

On-site Audit of Recommended Landscape and Visual Mitigation Measures

Active Works Areas

Regular intervals (by Contractor/ Landscape Sub-Contractor)

As specified in EM&A Manual (see Table E.6)

General Site Conditions

Environmental Site Inspection

Works areas and areas affected by works

Weekly

During Construction

2.2          Implementation of Environmental Mitigation Measures

The Contractor is required to implement mitigation measures listed in the latest valid EP and FEP(s) (where applicable), EIA Report and EM&A Manual. During routine site inspections, the Contractor's implementation of mitigation measures, if any, are to be inspected and reviewed. A schedule of the implementation of mitigation measures identified at the EIA stage is given in Appendix E.

 

 

 


3.1          Monitoring Parameters, Frequency and Duration

Following the requirements in the EM&A Manual for noise, noise monitoring has to be carried out during the construction phase. Continuous noise monitoring for the A-weighted levels Leq, L10 and L90 is undertaken once per every week during daytime hours (between 07:00 and 19:00) on normal weekdays.

Table 3.1 summarizes the monitoring parameters, frequency and duration of air quality monitoring. The noise monitoring schedule during the reporting month is presented in Appendix F.

Table 3.1:      Noise Monitoring Parameters, Frequency and Duration