1.
INTRODUCTION
1.1
Background
1.2
Purpose of this Manual
1.3
Environmental Monitoring and Audit
Requirements
1.4
Project Organization
1.5
Construction Programme
2.
AIR QUALITY
2.1
Air Quality Monitoring Parameters
2.2
Monitoring Equipment
2.3
Laboratory Measurement/Analysis
2.4
Monitoring Locations
2.5
Baseline Monitoring
2.6
Impact Monitoring
2.7
Event and Action Plan for Air Quality
2.8
Mitigation Measures for Construction Dust
3.
NOISE
3.1
Noise Monitoring Parameters
3.2
Monitoring Equipment
3.3
Monitoring Locations for Airborne
Construction Noise
3.4
Baseline Monitoring
3.5
Impact Monitoring
3.6
Event and Action Plan for Construction
Noise
3.7
Residual Impact
3.8
Mitigation Measures for Construction Noise
3.9
Ground Borne Construction Noise Monitoring
3.10 Monitoring
Locations for Groundborne Construction Noise
4.1
Water Quality Parameters
4.2
Monitoring Equipment
4.3
Monitoring Locations
4.4
Baseline Monitoring
4.5
Impact Monitoring
4.6
Event and Action Plan for Water Quality
4.7
Mitigation measures for Water Quality
5.1
General
5.2
Mitigation Measures for Waste Management
6.1
General
6.2
Mitigation Measures for Terrestrial Ecology
6.3
Mitigation Measures for Marine Ecology
7.
FISHERIES
7.1
General
7.2
Mitigation Measures
8.
LANDSCAPE AND VISUAL IMPACTS
8.1
General
8.2
Mitigation Measures for Landscape and
Visual during Construction
8.3
Mitigation Measures for Landscape and
Visual during Operation
9.1
General
9.2
Mitigation Measures for Cultural Heritage
10.1 Site
Inspections/Audits
10.2 Compliance
with Legal and Contractual Requirements
10.3 Environmental
Complaints
11.
REPORTING
11.1 General
11.2 Baseline
Monitoring Report
11.3 Monthly
EM&A Reports
11.4 Quarterly
EM&A Summary Reports
11.5 Final
EM&A Summary Report
11.6 Data
Keeping
11.7 Interim
Notifications of Environmental Quality Limit Exceedances
11.8 Electronic
Reporting of EM&A Information
lIST OF TABLES
Table
2.1 Locations for
Air Quality Monitoring Stations
Table
2.2 Action and
Limit Levels for Air Quality
Table
2.3 Event/Action
Plan for Air Quality
Table
3.1 Locations for
Airborne Construction Noise Monitoring Stations
Table
3.2 Action and
Limit Levels for Airborne Construction Noise
Table
3.3 Event/Action
Plan for Airborne Construction Noise
Table
3.4 Locations for
Groundborne Construction Noise Monitoring Stations
Table
3.5 Construction
Ground Borne Noise Standards
Table
3.6a TBM Working Hours -
Sensitive Receiver (Domestic Premise)
Table
3.6b TBM
Working Hours - Sensitive Receiver (Education Institution)
Table
4.1 Water Quality
Parameters
Table
4.2 Methods for
Laboratory Analysis for Water Samples
Table
4.3 Action /Limit
Levels for Water Quality
Table
4.4 Event and
Action Plan for Water Quality
Table
5.1a Estimated Spoil
Generated Breakdown from Eastern Portal for 24 hours TBM operation regime
Table
5.1b Estimated Spoil
Generated Breakdown from Western Portal for 24 hours TBM operation regime
lIST OF FIGUREs
Figure
1.1 Tunnel Layout
Plan and Intake Shaft Locations
Figure
1.2 Project
Organization Chart
Figure
2.1 Locations of
Monitoring Stations
Figure
2.2 Locations of
Monitoring Stations
Figures
3.1 Locations of
Construction Noise Monitoring Stations
Figures
3.2 Locations
of Construction Noise Monitoring Stations
Figures
3.3 Locations
of Construction Noise Monitoring Stations
Figures
3.4 Locations
of Construction Noise Monitoring Stations
Figures
3.5 Locations
of Construction Noise Monitoring Stations
Figures
3.6 Locations
of Construction Noise Monitoring Stations
Figures
3.7 Locations
of Construction Noise Monitoring Stations
Figures
3.8 Locations
of Construction Noise Monitoring Stations
Figures
3.9 Locations
of Construction Noise Monitoring Stations
Figures
3.10 Locations
of Construction Noise Monitoring Stations
Figures
3.11 Locations
of Construction Noise Monitoring Stations
Figures
3.12 Locations
of Construction Noise Monitoring Stations
Figures
3.13 Locations
of Construction Noise Monitoring Stations
Figures
3.14 Locations
of Construction Noise Monitoring Stations
Figures
3.15 Locations
of Construction Noise Monitoring Stations
Figures
3.16 Locations
of Construction Noise Monitoring Stations
Figures
3.17 Locations
of Construction Noise Monitoring Stations
Figures
3.18 Locations
of Construction Noise Monitoring Stations
Figure
4.1 Locations of
Water Quality Monitoring Stations
Figure
10.1 Flow
Chart of the Complaint Response Procedures
lIST OF APPENDIces
A
Environmental Mitigation Implementation Schedule
B
Sample
Air Quality Monitoring Field Data Sheet
C
Sample
Construction Noise Monitoring Field Data Sheet
D
Sample
of the Interim Notifications of Exceedances
F
Tentative
Construction Programme
1.1.1
Surface
water falling within the northern catchments of Hong Kong Island is intercepted
by a series of existing drainage pipes and culverts running through the urban
area that ultimately discharge at several locations into Victoria Harbour. The
existing system is overloaded and flooding and hazardous overland water flows can
occur in extreme conditions. However, much of the catchment[1] is outside the urban area and the
objective of the drainage improvement scheme studied here is to intercept
surface water before it enters the urban area and direct it to a discharge
outlet
on the west-side of Hong Kong Island. This will reduce the flows entering into lower catchment and reduce flooding
frequency in the urban area.
1.1.2
The
study under Agreement No. CE91/95 identified a tunnel alignment to intercept
flows and direct them to the tunnel. Due to the proximity of the tunnel
alignment to Country Parks it was determined that the project would be
classified as a Designated Project (DP) falling under the requirements of the Environmental Impact Assessment Ordinance (EIAO). It has included the Environmental Impact
Assessment (EIA) Study.
1.1.3
Black
& Veatch Hong Kong Ltd. (B&V) was commissioned by the Drainage Services
Department (DSD) in October 2002 under Agreement No. CE 25/2002 (DS) to
undertake the Drainage Improvement in Northern Hong Kong Island - Hong Kong
West and Lower Catchment Improvement - Investigation Study. The investigation
includes a review of the extent and alignments of the drainage tunnels together
with its associated drainage structures (e.g. the intake shafts and connecting adits
between the shafts and tunnels). An Environmental Impact Assessment (EIA) Study
has been undertaken to provide information on the nature and extent of
environmental impacts arising from the construction and operation of the
proposed DP project and related activities.
From the EIA, the recommendations for monitoring contained herein, are
made. Figure 1.1 shows the layout of the Project.
1.1.4
The
proposed tunnel starts from a tunnel portal close to the site of the Haw Par
Mansion in Tai Hang and follows a sinuous route beneath urban areas in Jardines
Lookout and Mid Levels. A discharge portal at the west end of Hong Kong Island
at Pokfulam, north of the Cyberport site is proposed. The tunnel is designed to convey the intercepted
flood flows for a 200-year storm event occurring across the complete
catchment. The internal diameter of the
initial section of the tunnel, before the Aberdeen Vehicular Tunnel, is 6.25m,
while the remaining tunnel section has an internal diameter of 7.25m. Thirty five intake locations have been
identified within the project areas that are suitable for intercepting flood
flows. The intakes structures are interconnected with the main tunnel by
connecting adits which are 2.3m in diameter.
Figure 1.1 shows the alignment of the proposed tunnel, adits and the
locations of the intake structures.
1.2.1
The
purpose of this Environmental Monitoring and Audit (EM&A) Manual is to
guide the setup of
an EM&A programme to ensure compliance with the recommendations in the EIA study, to assess the effectiveness of the
recommended mitigation measures and to identify any further need for additional
mitigation measures or remedial action.
1.2.2
This
Manual outlines the monitoring and audit programme to be undertaken for the
construction and operational phases of the proposed DP. It aims to provide
systematic procedures for monitoring, auditing and minimising of the
environmental impacts associated with the project.
1.2.3
Hong
Kong environmental regulations for noise, air quality, water quality and waste,
the Hong Kong Planning Standards and
Guidelines (HKPSG), and recommendations in the EIA Report have served as environmental
standards and guidelines in the preparation of this Manual.
1.2.4
For
the purpose of this Manual, the "Engineer" should refer to the
Engineer as defined in the Contract and the Engineer's Representative (ER), in
cases where the Engineer's powers have been delegated to the ER, in accordance
with the Contract. The Environmental Team (ET) leader, who should be responsible for and in
charge of the ET, should refer to the person delegated
the role of executing the environmental monitoring and audit requirements.
1.2.5
This
Manual contains the following:
·
Duties
of the ET with respect to the environmental monitoring and audit requirements
during construction;
·
Duties
of the Independent Environmental Checker (IEC) with respect to the
environmental monitoring and audit requirements during construction;
·
Information
on project organisation and programming of construction activities for the project;
·
Requirements
with respect to the construction schedule and the necessary environmental
monitoring and audit programme to track the varying environmental impacts;
·
Definition
of Action and Limit Levels;
·
Establishment
of event and action plans;
·
Requirements
of reviewing pollution sources and working procedures required in the event of
non-compliance of the environmental criteria; and
·
Requirements
of presentation of environmental monitoring and audit data and appropriate
reporting procedures.
1.3
Environmental Monitoring and Audit
Requirements
1.3.1
The
construction and operation phase impacts of the DP have been assessed and
presented in the EIA Report. The EIA Report has specified the recommended
environmental mitigation measures to minimise the potential adverse
environmental impacts identified. An implementation schedule of the recommended
environmental mitigation measures is prepared as part of the EIA study and is contained in Appendix A of this
Manual.
1.3.2
In
order to ensure that the mitigation measures recommended in EIA Report are
fully implemented and resulted in the expected effectiveness, this Manual
defines the scope of EM&A requirements for the construction and operation
of the DP to achieve satisfactory environmental performance. The EM&A
requirements are prepared in accordance with the requirements stipulated in Annex 21 of the Technical Memorandum
on Environmental Impact Assessment
Process (EIA-TM).
The environmental monitoring to be undertaken for the DP are as
follows:-
·
Baseline Monitoring refers to the measurement of prevailing
environmental parameters, including existing air quality and noise level, to
determine the nature and ranges of natural variation and to establish, where
appropriate, the nature of change. This
information is useful for assessing the short and long term environmental
impacts of the Project activities.
·
Impact Monitoring involves the measurement of environmental
parameters during the Project activities in order to determine the impacts of
the activities and the effectiveness of the proposed mitigation measures, and
any further remedial measures which are needed.
·
Compliance Monitoring involves periodic sampling and/or
continuous measurement of environmental parameters and the determination of
their compliance with regulatory requirements and standards.
1.3.3
The
environmental monitoring programme shall also be subject to environmental
audit. The aim is to determine whether
satisfactory compliance with the legislative requirements has been met, and to
ensure that no annoyance is caused to sensitive receivers or else the remedial
action plan will be initiated, if required.
This will require information on the standards for parameters of concern
and monitoring data. Each audit will
consist of a review of the monitoring data and comparison with the relevant
legislative requirements and environmental performance standards specified in
the Contract Document.
1.3.4
In
order to ensure that the mitigation measures recommended in the EIA study are implemented fully and resulted in the
expected effectiveness, this Manual defines the scope of EM&A requirements
for the construction of the proposed DP to achieve satisfactory environmental
performance. The EM&A requirements
for the DP shall be as follows:-
·
Pre-Construction
Phase – including all baseline monitoring prior to any
project activity occurring on site.
·
Construction
Phase – including impact/compliance monitoring and audit during all
construction activities.
·
Operation
Phase – including ground water level monitoring and audit at selected intakes/drop
shafts locations.
1.4
Project
Organization
1.4.1
The
proposed EM&A organization is shown in Figure 1.2 of this Manual. The
responsibilities of respective parties for the EM&A programme during the
pre-construction and construction are listed in forthcoming Clauses.
Environmental
Team
1.4.2
The ET
Leader and the ET should not be in any way an
associated body of the Contractor. The ET should be led and managed by the ET Leader. The ET Leader shall be the person who has at least
7 years' experience in EM&A or environmental management.
1.4.3
Suitably
qualified staff should be included in the ET, and resources for the
implementation of the EM&A programme should be allocated in time under the
Contract, to enable fulfillment of the project's EM&A requirements as
specified in the EM&A Manual during construction. The project proponent should be responsible
for the EM&A requirements as specified in this EM&A manual during
operation phase of the proposed project.
1.4.4
The ET
Leader and the ET are employed to implement the EM&A programme and ensure the
Contractor's compliance with the project's environmental performance
requirements during construction. The duties are:
(a) sampling, analysis and statistical evaluation of
monitoring parameters as required in the EM&A Manual;
(b) carry out environmental site surveillance;
(c) audit of compliance with environmental protection,
and pollution prevention and control regulations;
(d) monitor the implementation of environmental
mitigation measures;
(e) monitor the compliance with Conditions in the
relevant Environmental Permit (EP) and compliance with Specifications in the
Contract;
(f) review the construction programme and comment as
necessary;
(g) review the construction methodology and comment as
necessary;
preparation and updating of EM&A works schedule with reference to the best
available detailed construction programme;
(h) investigation of non-compliant events, evaluation
and identification of corrective measures;
(i) liaison with IEC on all environmental performance
matters, and timely submission of all relevant EM&A proforma for the
approval by IEC;
(j) advice to the Contractor on environment improvement,
awareness, enhancement matters, etc., on site and
(k) timely submission of the EM&A report to the project
proponent and the DEP.
1.4.5
Site
inspections should be carried out by the ET at least once per week during
construction. Ad hoc site inspections should also be carried out if significant
environmental problems are identified.
Independent
Environmental Checker
1.4.6
The
IEC should advise the ER on environmental issues related to the project. The
role of the IEC should be independent from the management of construction
works, but the IEC should be empowered to audit the environmental performance
of construction.
1.4.7
The
IEC should be employed prior to commencement of construction of the project.
The IEC should have at least 7 years experience in EM&A or environmental
management. The appointment of the IEC is subject to the approval of the
Engineer.
1.4.8
The
IEC should audit the overall EM&A programme including the implementation of
all environmental mitigation measures, submissions relating to EM&A, and
any other submission required under this Manual. In addition, the IEC should be responsible
for verifying the environmental acceptability of permanent and temporary works,
and relevant design plans and submissions under this Manual.
1.4.9
The
IEC should arrange and conduct at least monthly general site inspections of the
project during the construction periods. Ad hoc site inspection should also be
carried out if significant environmental problems are identified.
1.4.10
The
IEC should ensure the impact monitoring is conducted according to the
prescribed schedule at the correct locations.
1.4.11
The
IEC should report the findings of the site inspections and other environmental
performance reviews to DSD and Engineer/ER.
1.4.12
Appropriate
resources should also be allocated under the Contract for the IEC to fulfill their duties specified in this
Manual.
1.4.13
The
main duty of the IEC is to carry out environmental audit of the construction of
the project; this should include, inter alias, the followings:
(a) review and audit all aspects of the EM&A
programme;
(b) advise on proactive actions;
(c) validate and confirm the accuracy of monitoring
results, monitoring equipment, monitoring locations, monitoring procedures and
locations of sensitive receivers;
(d) carry out random sample check and audit on
monitoring data and sampling procedures, etc.;
(e) conduct random site inspection;
(f) audit the recommendations and requirements in EIA
Report against the status of implementation of environmental protection
measures on site;
(g) review the effectiveness of environmental mitigation
measures and project environmental performance;
(h) on a needs basis, audit the Contractor's
construction methodology and agree the least impact alternative in consultation
with the ET Leader and the Contractor;
(i) investigate complaint cases and check the
effectiveness of corrective measures;
(j) review accuracy of environmental monitoring section
of EM&A reports;
(k) verify EM&A report submitted by the ET Leader;
(l) feedback audit results to ET by signing off relevant
EM&A proformas.
Contractors
1.4.14
The
term "Contractors" should be taken to mean all construction
contractors and sub-contractors, working on site at any one time. Besides
reporting to the Engineer, the Contractors should:
(a) provide assistance to ET in carrying out monitoring;
(b) work within the scope of the relevant contract
and conditions;
(c) participate in the site inspections undertaken by
the ET, as required, and undertake any correction actions instructed by the
Engineer;
(d) provide information/advice to the ET regarding works
activities which may contribute, or be continuing to the generation of adverse
environmental conditions;
(e) implement measures to reduce impact whenever Action
and Limit Levels are exceeded;
(f) take responsibility and strictly adhere to the
guidelines of the EM&A programme and complementary protocols developed by
their project staff; and
(g) adhere to the procedures for carrying out complaint
investigation in accordance with EM&A manual
Engineer or Engineer's Representative (ER)
1.4.15
The
term Engineer, or Engineer's Representative, refers to the organization
responsible for overseeing the construction works of the project and
'monitoring' the works undertaken by the various Contractors, and for ensuring
that they are undertaken by the Contractors in accordance with the
specification and contractual requirements. The ER should:
(a) monitor the Contractors' compliance with contract
specifications, including the implementation and operation of environmental
mitigation measures and ensure their effectiveness, and other aspects of the
EM&A programme;
(b) inform the Contractor when action is required to
reduce impacts in accordance with the
Event and Action Plan;
(c) provide assistance to the ET as necessary in the
implementation of the environmental monitoring and auditing programme;
(d) adhere to the procedures for carrying out complaint
investigation in accordance with EM&A manual; and
(e) instruct the Contractors to follow the agreed
protocols or those in the Contract Specifications in the event of exceedances
of Action and Limit levels;
1.5.1
The
major construction activities of the Project are tunneling works,
drilling & blasting works, excavation and concreting works for the intakes
structure, stilling basins and tunnel portals.
1.5.2
During
the operation stage, the major site activities are the maintenance work of
the main drainage tunnel, adits, intake structures and the ancillary
facilities.
1.5.3
The
construction of the Project is scheduled for commencement in mid 2007 for completion in end 2011. A tentative construction programme is
provided in Appendix F. The ET and IEC
shall make reference to the Contractor’s actual works progress and works
programme during the construction stage to schedule the EM&A works, and the
Contractor shall provide the respective information to the ET Leader and the
IEC for formulating the EM&A schedule.
2.1
Air
Quality Monitoring Parameters
2.1.1
The
construction of the Project is scheduled for commencement in mid 2007 for completion in end 2011. A tentative construction programme is provided
in Appendix F. The ET and IEC shall make
reference to the Contractor’s actual works progress and works programme during
the construction stage to schedule the EM&A works, and the Contractor shall
provide the respective information to the ET Leader and the IEC for formulating
the EM&A schedule.
2.1.2
Monitoring
and audit of the Total Suspended
Particulates (
2.1.3
1-hour
and 24-hour
2.1.4
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and other special phenomena and work progress of the
concerned site etc. shall be recorded down in details. A sample field log sheet is shown in Appendix
B to this Manual.
2.2.1
High
Volume Sampler (HVS) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour
·
0.6-1.7m3/min
(20-60 SCFM) adjustable flow range;
·
equipped
with a timing/control device with +/- 5 minutes accuracy for 24 hours
operation;
·
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable
of providing a minimum exposed area of 406 cm2 (63in2);
·
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped
with a shelter to protect the filter and sampler;
·
incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
equipped
with a flow recorder for continuous monitoring;
·
provided
with a peaked roof inlet;
·
incorporated
with a manometer;
·
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
easy
to change the filter; and
·
capable of operating continuously for 24-hour
period.
2.2.2
The ET
Leader shall be responsible for provision of the monitoring equipment and
associated accessories and power supply.
He shall ensure that sufficient numbers of HVSs with an appropriate
calibration kit are available for carrying out the regular impact monitoring
and ad hoc monitoring. The HVSs shall be
equipped with an electronic mass flow controller and be calibrated against a
traceable standard at regular intervals.
All the equipment, calibration kit, filter papers, etc. shall be clearly
labeled. The ET Leader shall also liaise
with the concerned parties for gaining access to the monitoring stations for
the installation of the monitoring equipment and carrying out monitoring.
2.2.3
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The calibration data shall be properly
documented for future reference by the
concerned parties such as IEC.
All the data should be converted into standard temperature and pressure
condition.
2.2.4
The
flow-rate of the sampler before and after the sampling exercise with the filter
in position shall be verified to be constant and be recorded in the field log
sheet mentioned in Section 2.3.
2.2.5
If the
ET Leader proposes to use a direct reading dust meter to
measure 1-hour
2.2.6
Wind
data monitoring equipment shall also be provided and set up at conspicuous
locations for logging wind speed and wind direction near to the dust monitoring
locations. The equipment installation
location shall be proposed by the ET Leader and agreed with the ER in consultation
with the IEC. For installation and operation of wind data
monitoring equipment, the following points shall be observed:-
·
the wind sensors should be installed on
masts at an elevated level 10m above ground so that they are clear of
obstructions of turbulence caused by the buildings;
·
the wind data should be captured by a data
logger and to be downloaded for processing at least once a month;
·
the wind data monitoring equipment should be
re-calibrated at least once every six months; and
·
wind direction should be divided into 16
sectors of 22.5 degrees each.
2.2.7
In
exceptional situations, the ET Leader may propose alternative methods to obtain
representative wind data. The
alternative methods shall be agreed by ER in consultation with the IEC.
2.3
Laboratory
Measurement/Analysis
2.3.1
The ET
Leader shall carry out laboratory measurements/analyses for the dust samples
collected.
2.3.2
A
clean laboratory with constant temperature and humidity control, and equipped
with necessary measuring and conditioning instruments, to handle the dust
samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The
laboratory shall be Hong Kong Laboratory
Accreditation Scheme (HOKLAS) accredited.
2.3.3
If a
site laboratory is set up or a non-HOKLAS accredited laboratory is hired for
carrying out the laboratory analysis, the laboratory equipment shall be
approved by the ER and the measurement procedures shall be witnessed by the
ER. The ET Leader shall provide the ER
with one copy of the Title 40 of the Code
of Federal Regulations, Chapter 1 (Part 50), Appendix B for his
reference.
2.3.4
Filter
paper of size 8”´10” shall be labeled before sampling. It shall be a clean filter paper with no pin
holes, and shall be conditioned in a humidity controlled chamber for over
24-hour and be pre-weighed before use for the sampling.
2.3.5
After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter
paper is then returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with a readout
down to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
2.3.6
All
the collected samples shall be kept in a good condition for 6 months before
disposal.
2.4.1
Two
designated monitoring stations, AQ1 and AQ2 are selected for dust impact monitoring as they are the
representative air sensitive receivers very close to the construction works
areas. Table 2.1 describes the air quality
monitoring locations, which are also depicted in Figures 2.1 and 2.2.
Table 2.1 Locations for Air Quality Monitoring
Stations
Monitoring
Stations |
Figure
no. |
Location |
AQ1 |
2.1 |
True Light Middle School of Hong Kong |
AQ2 |
2.2 |
Aegean Terrace |
2.4.2
The
status and locations of dust sensitive receivers may change after issuing this
Manual. If such cases exist, the ET
Leader shall propose updated monitoring locations, which shall be approved by
the ER and agreed with IEC.
2.4.3
When
alternative monitoring locations are proposed, the following criteria, as far
as practicable, shall be followed:-
·
at the site boundary or such locations close to the
major dust emission source;
·
close to the sensitive receptors; and
·
take into account the prevailing meteorological
conditions.
2.4.4
The ET
Leader shall agree with the ER on the position of the High Volume Sampler for
installation of the monitoring equipment.
When positioning the samplers, the following points shall be noted:
·
a horizontal platform should be provided with
appropriate support to secure the samplers against gusty wind;
·
no two samplers should be placed less than 2 meters
apart;
·
the distance between the sampler and an obstacle, such
as buildings, should be at least twice the height that the obstacle protrudes
above the sampler;
·
a minimum of 2 meters separation from walls, parapets
and penthouses is required for rooftop samples;
·
a minimum of 2 meters separation from any supporting
structure, measured horizontally is required;
·
no furnaces or incineration flues or building
vents are nearby;
·
airflow around the sampler is unrestricted;
·
the sampler is more than 20 meters from the drip line;
·
any wire fence and gate, to protect the sampler, should
not cause any obstruction during monitoring;
·
permission must be obtained to set up the samplers and
to obtain access to the monitoring stations; and
·
a secured supply
of electricity is needed to operate the samplers.
2.5.1
Baseline
monitoring shall be carried out at all the designated monitoring locations for
at least 14 consecutive days prior to the commissioning of the construction
works to obtain daily 24-hour
2.5.2
During the baseline monitoring, there should not be any
construction or dust generation activities in the vicinity of the monitoring
stations.
2.5.3
In
case the baseline monitoring cannot be carried out at the designated monitoring
locations during the baseline monitoring period, monitoring shall be carried
out at alternative locations which can effectively represent the baseline
conditions at the impact monitoring locations.
The alternative baseline monitoring locations shall be approved by the
ER and agreed with IEC.
2.5.4
In
exceptional case, when insufficient baseline monitoring data or questionable
results are obtained, the ET Leader shall liaise with IEC to agree on an appropriate set of data to
be used as a baseline reference and submit to ER for approval.
2.5.5
Ambient
conditions may vary seasonally and shall be reviewed at three monthly
intervals. If the ET Leader considers
that the ambient conditions have been changed and repeat of the baseline
monitoring is required to be carried out for obtaining the updated baseline
levels, the monitoring should be conducted at times when the Contractor’s
activities are not generating dust, at least in the proximity of the monitoring
stations. Should changes in ambient conditions be determined, the baseline
levels and, in turn, the air quality criteria, should be revised. The revised
baseline levels and air quality criteria should be agreed with IEC and
2.6.1
The ET Leader shall carry out impact monitoring during the
course of the Project activities under the Contract. For regular impact monitoring, the sampling
frequency of at least once in every six-day, shall be strictly observed at all
the monitoring stations for 24-hour
2.6.2
The
specific time to start and stop the 24-hr
2.6.3
In
case of non-compliance with the air quality criteria, more frequent monitoring
exercise, as specified in the Event/Action Plan in Section 2.7 shall be conducted within 24 hours after
the result is obtained. This additional monitoring shall be continued until the
excessive dust emission or the deterioration in air quality is rectified.
2.7
Event
and Action Plan for Air Quality
2.7.1
The baseline monitoring results form the basis for
determining the air quality criteria for the impact monitoring. The ET Leader shall compare the impact
monitoring results with air quality criteria set up for 24-hour
Table 2.2 Action
and Limit Levels for Air Quality
Parameters |
Action |
Limit |
24
Hour |
For baseline level
≤ 200 µg/m³, Action level = (Baseline
level *1.3 + Limit level)/2 For baseline level >
200 µg/m³, Action level = Limit
level |
260 |
1
Hour |
For
baseline level ≤ 384 µg/m³,
Action
level = (Baseline level * 1.3 + Limit level)/2 For
baseline level > 384 µg/m³,
Action
level = Limit level |
500 |
Table 2.3 Event/Action
Plan for Air Quality
|
ACTION |
|||
EVENT |
ET |
IEC |
ER |
CONTRACTOR |
ACTION LEVEL |
|
|
|
|
1.Exceedance
for one sample |
1. Identify the source and investigate the causes and propose remedial
measures 2. Inform ER & IEC 3. Repeat measurement to confirm finding 4. Increase monitoring frequency to daily |
1.
Check monitoring data submitted by ET 2.Check
Contractor's working methods |
1.Notify
Contractor |
1.Rectify any unacceptable practice 2.Amend working methods if appropriate |
2.Exceedance
for two or more consecutive samples |
1. Identify the source 2. Inform ER & IEC 3. Repeat measurements to confirm findings 4. Increase monitoring frequency to daily 5. Discuss with ER & IEC for remedial actions
required 6. If exceedance continues, arrange meeting with
ER & IEC 7. If exceedance stops, cease additional
monitoring |
1.Checking
monitoring data submitted by ET 2.
Check Contractor's working methods 3. Discuss with ET, IEC and Contractor on
proposed remedial actions 4. Advise the ER & ET on the
effectiveness of the proposed remedial measures 5.Supervise
the implementation of the remedial measures |
1.Confirm
receipt of notification of failure in writing 2.Notify
Contractor 3.Ensure
remedial actions properly implemented |
1.Submit proposals for remedial actions to
ER within 3 working days of notification 2.Implement the agreed proposals 3.Amend proposal if appropriate |
LIMIT
LEVEL |
|
|
|
|
1.Exceedance
for one sample |
1. Identify source,,investigate the causes and propose remedial
measures 2. Inform ER & IEC and 3. Repeat measurement to confirm finding 4. Increase monitoring frequency to daily 5. Assess effectiveness of Contractor's remedial
actions and keep |
1.Check
monitoring data submitted by ET 2.
Check Contractor's working methods 3.
Discuss with ET and Contractor on proposed remedial actions 4.
Advise the ER on the effectiveness of the proposed remedial measures 5.Supervise
the implementation of the remedial measures |
1.Confirm
receipt of notification of failure in writing 2.Notify
Contractor 3.Ensure
remedial actions properly implemented |
1.Take
immediate action to avoid further exceedance 2.Submit
proposals for remedial actions to ER within 3 working days of notification 3.Implement
the agreed proposals 4.Amend
proposal if appropriate |
2.Exceedance
for two or more consecutive samples |
1. Identify source 2. Inform ER, IEC and 3. Repeat measurement to confirm findings 4. Increase monitoring frequency to daily 5. Investigate the causes of exceedance 6. Arrange meeting with & IEC and ER to
discuss the remedial actions to be taken 7. Assess effectiveness of Contractor's remedial
actions and keep ER, IEC and 8. If exceedance stops, cease additional
monitoring |
1.Discuss
amongst ER, ET and Contractor on the potential remedial actions 2.Review
Contractor’s remedial actions to assure their effectiveness and advise the ER
accordingly 3.Supervise
the implementation of the remedial measures |
1.Confirm
receipt of notification of failure in writing 2.Notify
Contractor 3.In
consultation with the IEC, agree with the Contractor on the remedial measures
to be implemented 4.Ensure
remedial measure are properly implemented 5.If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated |
1. Take immediate action to avoid further
exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Resubmit proposals if problem still not under
control 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated |
3.1
Noise
Monitoring Parameters
3.1.1
The construction
noise levels shall be measured in terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq(30 min) shall be used as the monitoring parameter for
the time period between 0700-1900 hours on normal weekdays. A supplementary information for data auditing, statistical
results such as L10 and L90 shall also be obtained for
reference. For
all other time periods, Leq(5 min) shall be employed
for comparison with the Noise Control
Ordinance (NCO) criteria.
3.2.1
As
referred to in the Technical Memorandum
(TM) issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804:
1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if
the calibration levels from before and after the noise measurement agree to
within 1.0dB.
3.2.2
Noise
measurements shall not be made in the presence of fog, rain, wind with a steady
speed exceeding 5ms-1 or wind with gusts exceeding 10ms-1. The wind speed shall be checked with a
portable wind speed meter capable of measuring the wind speed in m/s. Sample noise field data sheet is shown in Appendix C to this Manual
for reference.
3.2.3
The ET
Leader shall be responsible for the provision of the monitoring equipment and
associated accessories and power supply.
He shall ensure that sufficient noise measuring equipment and associated
instrumentation are available for carrying out the regular impact monitoring
and ad hoc monitoring. All the equipment
and associated instrumentation shall be clearly labelled. The ET Leader shall also liaise with the
concerned parties for gaining access to the monitoring stations for the
installation of the monitoring equipment and carrying out monitoring.
3.3
Monitoring
Locations for Airborne Construction Noise
3.3.1
Twenty-one
designated monitoring stations, NC1 to NC21 are selected for construction noise
monitoring. Table 3.1 describes the construction noise monitoring locations,
which are also depicted in Figures 2.1, 2.2 and 3.1-3.16. The status and
locations of noise sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall
propose updated monitoring locations and seek approval from ER and agreement
from the IEC of the proposal.
Table 3.1 Locations for Airborne Construction
Noise Monitoring Stations
Location |
Fig. no. |
Monitoring Stations |
Descriptions |
Status |
Eastern Portal |
2.1 |
NC1 |
True Light Middle School of Hong Kong |
School |
Eastern Portal |
2.1 |
NC2 |
The Legend (Future development) |
Domestic Premises |
Western Portal |
2.2 |
NC3 |
Aegean Terrance |
Domestic Premises |
Intakes BR6(P) |
3.1 |
NC4 |
Man Yuen Garden |
Domestic Premises |
Intakes BR7(P) |
3.1 |
NC5 |
16 Caronia |
Domestic Premises |
Intake DG1(P) |
3.2 |
NC6 |
Blk C Villa Monte Rosa |
Domestic Premises |
Intake DG1 |
3.3 |
NC7 |
Rosaryhill School |
School |
Intake E5(A)(P) |
3.3 |
NC8 |
Buddist Li Ka Shing Care & Attention Home for the Elderly |
Domestic Premises |
Intake E7(P) |
3.4 |
NC9 |
Marymount Secondary School |
School |
Intake E7(P) |
3.4 |
NC10 |
117 Blue Pool Road |
Domestic Premises |
Intakes MA13(P) & MA14(P) |
3.5 |
NC11 |
The Harbour View |
Domestic Premises |
Intake P5(P) |
3.6 |
NC12 |
24 Po Shan Road |
Domestic Premises |
Intake PFLR1(P) |
3.7 |
NC13 |
Honey Court |
Domestic Premises |
Intake RR1(P) |
3.8 |
NC14 |
Ying Wa Girl’s School |
School |
Intake RR1(P) |
3.8 |
NC15 |
Peaksville Court |
Domestic Premises |
Intake THR2(P) |
3.9 |
NC16 |
Hong Kong Japanese School |
School |
Intake W0(P) |
3.12 |
NC17 |
Sir Ellis Kadoorie Secondary School |
School |
Intake W5(P) |
3.13 |
NC18 |
Raimondi College |
School |
Intake W8 |
3.14 |
NC19 |
Hong Kong Institute of Technology |
School |
Intake W8 |
3.14 |
NC20 |
Blk A, 80 Robinson Road |
Domestic Premises |
Intake W12(P) |
3.15 |
NC21 |
92A-92C Sylvanbrook |
Domestic Premises |
3.3.2
When
alternative monitoring locations are proposed, the monitoring locations should
be chosen based on the following criteria:-
(a) at locations close to the major site activities
which are likely to have noise impacts;
(b) close to the noise sensitive receivers. For the purposes of this section, any
domestic premises, hotel, hostel, temporary housing accommodation, hospital,
medical clinic, educational institution, place of public worship, library,
court of law, performing art centre should be considered as noise sensitive
receiver; and
(c) for monitoring locations located in the vicinity of the
sensitive receivers, care should be taken to cause minimal disturbance to the
occupants during monitoring.
3.3.3
The
monitoring station shall normally be at a point 1m from the exterior of the
sensitive receivers building facade and be at a position 1.2m above the
ground. If there is problem with access
to the normal monitoring position, an alternative position may be chosen, and a
correction to the measurements shall be made.
For reference, a correction of +3dB(A) shall be
made to the free field measurements. The
ET Leader shall agree with the IEC on the monitoring position and the
corrections adopted. Once the positions
for the monitoring stations are chosen, the baseline monitoring and the impact
monitoring shall be carried out at the same positions.
3.4.1
The ET Leader shall
carry out baseline monitoring prior to the commencement of the construction
works. The baseline monitoring shall be
carried out daily for a period of at least 14 consecutive days. A schedule on the baseline monitoring for construction noise prior to
the commencement of the construction works shall be submitted to the
ER for approval and IEC agreement before the monitoring starts.
3.4.2
Before
commencing the baseline monitoring, the ET leader
shall inform the IEC of the baseline monitoring programme such that the IEC can
conduct on-site audit to ensure accuracy of the baseline monitoring
results.
3.4.3
There shall not be any construction activities in
the vicinity during the baseline monitoring.
In exceptional cases, when insufficient baseline monitoring data or
questionable results are obtained, the ET Leader shall liaise with IEC to agree
on an appropriate set of data to be used as a baseline reference.
3.4.4
Noise monitoring shall be carried out at all the designated monitoring
stations. The monitoring frequency shall depend on the scale of the
construction activities. The following
is an initial guide on the regular monitoring frequency for each station on a
per week basis when noise generating activities are underway:-
(a) one set of measurements between 0700-1900 hours on
normal weekdays;
(b) one set of measurements between 1900-2300 hours;
(c) one set of measurements between 2300-0700 hours of
next day; and
(d) one set of measurements between 0700-1900 hours on
holidays.
3.4.5
For
the measurements (b), (c) and (d) above, one set of measurements shall at least
include 3 consecutive Leq (5 min) results.
3.5.1
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction
activities. The following is an initial
guide on the regular monitoring frequency for each station once every week in accordance
with the methodology in the TM when noise generating activities are underway:-
·
one set of measurements between 0700-1900 hours on
normal weekdays;
3.5.2
If a
school exists near the construction activity, noise monitoring shall be carried
out at the monitoring stations for the school during the school examination
periods. The ET Leader shall liaise with the school's personnel and the
Examination Authority to ascertain the exact dates and times of all examination
periods during the course of the construction.
3.5.3
In
case of non-compliance with the construction noise criteria, more frequent
monitoring as specified in the Event/Action Plan in Section 3.6 of this Manual shall be carried out. This additional monitoring shall be continued
until the recorded noise levels are rectified or proved to be irrelevant to the
construction activities.
3.6
Event
and Action Plan for Construction Noise
3.6.1
The
Action and Limit levels for construction noise are defined in Table 3.2. Should
non-compliance of the criteria occur, action in accordance with the
Event/Action Plan in Table 3.3, shall be carried
out. As residual impacts are predicted
at some NSRs according to the air borne noise construction noise assessment
presented in the EIA report, the Event/Action Plan and the construction stage
noise EM&A work shall be strictly implemented to facilitate identification
of practicable measures to minimize the residual noise impacts.
Table 3.2 Action and Limit Levels for
Construction Noise
Time
Period |
Action |
Limit |
0700-1900 hrs on normal weekdays |
When one
documented complaint is received |
75* dB(A) |
0700-2300 hrs on holidays; and 1900-2300 hrs on all
other days |
60/65/70** dB(A) |
|
2300-0700 hrs of next day |
45/50/55** dB(A) |
* reduce to 70 dB(A)
for schools and 65 dB(A) during school examination periods.
**
to be selected based on Area Sensitivity Rating.
Public
Relationship Strategy
3.7.1
Having
a good public relation with the local communities during the construction stage
of the works is indispensable for smooth implementation of the Project. Prior
to commencement of the construction, visits to the possibly affected local
communities including the District Councils, nearby residents, schools and property
owners will be carried out. The purpose
of the visits is to advise the public the following information in relation to
the Project:
·
the
implementation programme of the works;
·
the
planned construction activities that will be involved;
·
the
possible impacts to the affected communities;
·
the
measures to avoid or mitigate any adverse impacts;
·
the
monitoring programme to check the efficiency of the measures; and
·
the communication channels between the local communities
and the project office for better understanding the efficiency of the measures
taken and the necessity for enhancement of the measures.
3.7.2
To maintain
a better communication link with the local communities, it will specify under
the contract to establish a 24-hour hot line manned by the Contractor such that all the received enquiries or
complaints could be logged immediately and forwarded to the relevant project
officers to follow up. Under the
establishment of the project site office, liaison officers will also be
nominated who are responsible for regular contacts with the local communities
advising them the current progress of works, the efficiency of the
environmental mitigation measures and any follow-up action that have been taken
in responses to any non-compliances or complaints received from the local
communities. It is considered that such
a close relation between the local communities and the project site office
could ensure speedy resolution of any environmental non-compliance and maintain
an environmental standard acceptable to the communities during construction.
Table 3.3 Event/Action Plan for Construction Noise
EVENT |
ACTION |
|||
|
ET
|
IEC |
ER |
Contractor |
Action
Level |
1. Notify IEC, ER and Contractor 2. carry our
investigation by reviewing all the relevant monitoring
data and the corresponding construction activities. Exceedances should also be
confirmed by immediate verification in the field as far as practical. 3. Report the results of investigation to
the IEC, ER and Contractor 4. Discuss with the Contractor and
formulate remedial measures 5. increase monitoring frequency to check
mitigation effectiveness |
1.Review
the analysed results submitted by the ET 2. Review
the proposed remedial measures by the Contractor and advise the ER & ET
accordingly 3.Supervise
the implementation of remedial measures |
1.
Confirm receipt of notification of complaint in writing 2. Notify Contractor 3. require Contractor
to proposed remedial measures for analyzed noise problem 4. Ensure remedial
measures are properly implemented |
1. Identify practicable measures to
minimize the noise impact. Submit
noise mitigation proposals to ET, IEC and ET.
2. Implement noise mitigation proposals |
Limit
Level |
1. Notify IEC, ER, 2. Identify the source(s) of impact by
reviewing all the relevant monitoring data and the
corresponding construction activities. Exceedances should also be confirmed
by immediate verification in the field as far as practical. 3. Repeat measurement to confirm findings 4. Increase monitoring frequency 5. Carry out analysis of Contractor’s
working procedures to determine possible mitigation to be implemented. 6. inform IEC, ER and 7. Assess effectiveness of Contractor’s
remedial actions and keep IEC, 8. If exceedance stops, cease additional
monitoring. |
1. Discuss amongst ER, ET, and Contractor
on the potential remedial actions 2. Review Contractor’s remedial actions to
assure their effectiveness and advise the ER &ET accordingly 3.Supervise the implementation of the
remedial measures |
1. Confirm receipt of notification of exceedance
in writing 2. Notify Contractor 3. Require Contractor to propose remedial measures
for the analyzed noise problem 4. Ensure remedial measures are properly
implemented 5. If exceedance continuous, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is aborted |
1. Take immediate action to avoid further
exceedance 2. Identify practicable measures to
minimize the noise impact. Submit
proposals for remedial actions to ER within three working days of
notification 3. Implement the agreed proposals 4. Resubmit proposal if problem still not
under control 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated |
3.8
Ground
Borne Construction Noise Monitoring
3.8.1
Based
on the recommendations of the EIA study, it is required to carry out ground
borne noise monitoring to ensure that proper control of groundborne noise is executed by the contractor. The monitoring frequency shall be the same as stated in Section 3.5.
3.9
Monitoring
Locations for Groundborne
Construction Noise
3.9.1
Prediction of construction groundborne noise indicates the criteria will be
achieved at all NSRs during day-time.
3.9.2
Eight designated monitoring stations (GNC1 to GNC8) are selected for construction groundborne noise monitoring to check for compliance.
Table 3.4 describes the construction groundborne noise monitoring locations, which are also
depicted in Figures 2.1, 2.2 and 3.16-3.18. The status and locations of noise
sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall
propose updated monitoring locations and seek approval from ER and agreement
from the IEC of the proposal.
3.9.3
The
monitoring locations are selected at sensitive receivers (e.g. schools or
domestic premises). The Legend (GNC2)
near Eastern Portal, Aegean Terrance (GNC3) near
Western Portal, Carriana Sasson (
Table 3.4 Locations for Ground borne
Construction Noise Monitoring Stations
Location |
Fig. no. |
Monitoring
Stations |
Descriptions |
Status |
Near Eastern Portal |
2.1 |
GNC1 |
True Night
Middle School |
School |
Near Eastern Portal |
2.1 |
GNC2 |
The Legend (Future development) |
Domestic Premises |
Near Western Portal |
2.2 |
GNC3 |
Aegean Terrace |
Domestic Premises |
Near Western Portal |
2.2 |
GNC4 |
Carriana Sasson |
Domestic Premises |
Near Western Portal |
2.2 |
GNC5 |
Hong Kong University Educational Institute |
School |
Tunnel chainage CH+ 1950 |
3.16 |
GNC6 |
French
International School |
School |
Near Intake W3(P) |
3.17 |
GNC7 |
Hong Villa |
Domestic Premises |
Near Intake W5(P) |
3.18 |
GNC8 |
Raimondi
College |
School |
3.9.4
The criterion include TM for
the Assessment of Noise from Places other than Domestic Premises, Public Places
or Construction Sites (TM-Places) under the NCO stipulates that noise
transmitted primarily through the structural elements of building, or buildings
shall be 10dB(A) less than the relevant ANLs.
3.9.5
Table
3.5 indicates the noise criteria which apply for the groundborne noise
assessment. The ground borne noise
criteria during restricted hours (daytime during holidays, all evening and
nighttime) presented in Tables 3.5, 3.6a and 3.6b which only refer to areas
with
Table 3.5 Construction Ground
Borne Noise Standards
|
Ground
Borne Noise Criteria, dB(A) (Leq, 30 mins) |
||
Uses |
Daytime (except
General Holidays and Sundays)* |
Daytime
during general holidays and Sundays and all days during Evening (1900
to 2300 hrs)** |
Night
time (2300
to 0700 hrs)** |
Domestic
Premises |
65 |
55 |
40 |
Educational Institutions (normal periods) |
60 |
55 |
[1] |
Educational Institutions (during examination
periods) |
55 |
55 |
[1] |
* 10 dB(A)
below the noise criteria stipulated in EIAO-TM
** 10 dB(A)
below the noise criteria stipulated in GW-TM
[1] No sensitive uses
usually present during these periods
3.9.6
If the ground borne level exceeds in the defined limit
measured during TBM operation, TBM construction work and the associated works
should be restricted during the all days evening / all days night-time / day
time including general holidays and Sundays.
Tables 3.6a and 3.6b show the follow up actions for ground borne noise
monitoring if exceedance is found at representative monitoring locations. The
noise level should be
measured on the ground floor inside the nearest building during the TBM
construction work in the evening and early morning.
Table 3.6a TBM
Working Hours - Sensitive Receiver (Domestic Premise)
Scenario |
Monitoring Time |
Monitoring Result |
Working hours of
TBM or associated work operation |
A |
Day time |
55 dB(A) < x <
65 dB(A) |
Day time (Except
general holidays and Sundays) (0700 – 1900 hrs) only |
B§ |
Day time |
40 dB(A) < x <
55 dB(A) |
Day time
including general holidays and Sundays and all days during evening (0700-2300
hrs) only |
C§ |
Day time |
< 40 dB (A) |
No restriction |
Table
3.6b TBM Working Hours - Sensitive Receiver (Education Institution)
Scenario |
Monitoring Time |
Monitoring Result |
Working hours of
TBM or associated work operation |
D |
Day time |
55 dB(A) < x <
60 dB(A) |
Day time (Except
general holidays and Sundays) (0700 – 1900 hrs) only |
E§ |
Day time |
x < 55
dB(A) |
No restriction |
Remarks:
§ - For scenarios
B, C and E, they reflect the working hours are subject to CNP application.
4.1.1
An assessment of potential impacts to water
quality due to the construction and operation of Drainage Improvement in
Northern Hong Kong Island – Hong Kong West Drainage Tunnel has been carried out
and identified in the EIA Report. The water quality assessment in the EIA
identified that the key impacts may arise from the intakes and tunnel
excavation works, construction of temporary berthing point, outlet structure
and stilling basin at western portal. To
minimise the potential impacts arising from the construction on the water
quality in the vicinity of water sensitive receivers, proper construction
methods with good site practices are required. The measures include
installation of proper drainage system to collect site runoff and silt curtain
in the waters around the temporary berthing point to prevent dispersion of
suspended particle. Groundwater level monitoring would also be carried out at
those construction works areas near to the natural streams during the first
year of operation phase (maintenance period) to assess effect of tunnel
construction to the existing ground water regime.
4.1.2
Water
quality monitoring and audit for the project are required to ensure compliance
with the water quality criteria and the effectiveness of the proposed
mitigation measures. Marine water
quality monitoring and audit shall be carried out during the construction
period for the works at the Western Portal. The related construction activities includes construction of temporary berthing
facility, outlet structure, stilling basin, tunnel boring at western
portal. If proper measures are not
taken, it may have short term impacts on the marine water quality.
4.1.3
It was
considered that site inspections should also be required to ensure that the
recommended water pollution mitigation measures would be properly implemented,
functioned and maintained during construction phase of the DP. The requirements
of site inspections are detailed in Section 10.
4.2
Water
Quality Parameters
4.2.1
The
following water quality parameters will be included in the monitoring programme
during construction phase.
Table 4.1 Water
Quality Parameters
Phase |
Water
Quality Parameters |
Construction |
· Temperature (°C) · pH (pH unit) · turbidity (NTU) · water depth (m) · salinity (mg/L) · dissolved oxygen (DO) (mg/L and % of
saturation) · suspended solids (SS) (mg/L) |
4.3.1
For
water quality monitoring, the following equipments will be supplied by the ET
and approved by the ER.
Dissolved Oxygen (DO) and Temperature Measuring
Equipment
4.3.2
The
instrument for measuring dissolved oxygen and temperature will be portable and
weatherproof completed with cable, sensor, comprehensive operation manuals and
use DC power source. It will be capable of measuring:
· a dissolved oxygen level in the range of 0-20 mg/L and
0-200% saturation; and
· a temperature of 0-45 degree Celsius.
4.3.3
It
will have a membrane electrode with automatic compensation completed with a
cable. Sufficient stocks of spare
electrodes and cables will be available for replacement where necessary (e.g.
YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and
cable or an approved similar instrument).
4.3.4
In
situ salinity will be measured to calibrate the DO equipment prior to each DO
measurement if salinity compensation is not built-in in the DO equipment.
Turbidity
4.3.5
Turbidity
will be measured in situ by the nephelometric method. The instrument will be
portable and weatherproof using a DC power source complete with cable, sensor
and comprehensive operation manuals. The equipment will be capable of measuring
turbidity between 0-1000 NTU. The probe cable will not be less than 25m in
length. The meter will be calibrated in order to establish the relationship
between NTU units and the levels of SS.
Suspended Solids (SS)
4.3.6
A
water sampler, consisting of a transparent PVC or glass cylinder of a capacity
of not less that two litres which can be effectively sealed with cups at both
ends will be used (Kahlsico Water Sampler 13SWB203 or an approved similar
instrument). The water sampler will have a positive latching system to keep it
open and prevent premature closure until released by a messenger when the
sampler is the selected water depth.
4.3.7
Water
samples for SS will be collected in high density polythene bottles, packed in
ice and delivered to HOKLAS accredited laboratory for analysis as soon as
possible after collection.
Water Depth Detector
4.3.8
A
portable, battery-operated echo sounder (Seafarer 700 or a similar approved
instrument) will be used for the determination of water depth at each
designated monitoring station. This unit can either be hand held or affixed to
the underside of the survey boat, if the same vessel is to be used throughout
the monitoring programme.
Salinity
4.3.9
A
portable salinometer capable of recording within the range of 0-40 ppt will be
used for salinity measurements.
Water Sampling for Laboratory Analysis
4.3.10
A
water sampler as detailed in Section 4.3.6 will be used to collect samples for
laboratory analysis.
Position System
4.3.11
A
portable salinometer capable of recording within the range of 0-40 ppt will be
used for salinity measurements.
4.3.12
A hand
held or boat fixed type Digital Global Positioning System (DGPS) will be used
to ensure that the correction location has been selected prior to sample
collection. Coordinates checking should
be carried out with a DGPS. The DGPS
should be calibrated at appropriate checkpoint (e.g. Quarry Bay Survey Nail at
Easting 840683.49, Northing 816709.55) to ensure the monitoring station is at
the correct position before taking measurement and water samples.
Sample Container and Storage
4.3.13
Following
collection, water samples for SS analysis will be stored in high density
polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen), delivered to the laboratory
and analysed as soon as possible.
Calibration of In Situ Instruments
4.3.14
All in
situ monitoring instruments will be checked, calibrated and certified by a
laboratory accredited under HOKLAS or other international accreditation scheme
before use, and subsequently re-calibrated at 3 monthly intervals throughout
all stages of the water quality monitoring.
4.3.15
For
the on site calibration of field equipment, the BS 1427:1993, "Guide to
Field and on-site test methods for the analysis of waters" will be
observed.
4.3.16
Sufficient
stocks of spare parts will be maintained for replacements when necessary.
Backup monitoring equipment will also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
Laboratory Analytical Methods
4.3.17
Analysis
of SS will be carried out in a HOKLAS or other international accredited
laboratory. The following table shows the standard test methods of the proposed
determinants for laboratory analysis.
Table
4.2 Methods for Laboratory Analysis
for Water Samples
Parameters
(Unit) |
Suggested
Method |
Detection
Limit |
SS (mg/L) |
APHA 2540 D |
< 0.1 mg/L |
Notes:
APHA= American Public Health Association:
Standard Methods for the Examination of Water and Wastewater Ed 19
4.3.18
The
testing laboratory will be HOKLAS accredited (or if not, approved by the ER)
and comprehensive quality assurance and control procedures in place in order to
ensure quality and consistency in results.
4.3.19
If a
site laboratory is set up or a non-HOKLAS and non-international accredited
laboratory is hired for carrying out the laboratory analysis, the laboratory
equipment, analytical procedures, and quality control will be approved by ER.
All the analysis will be witnessed by the ER.
4.3.20
The ET
will provide the ER with one copy of the relevant chapters of the
"Standard Methods for the Examination of Water and Wastewater"
updated edition and any other relevant document for his reference.
4.3.21
For the
testing methods of other parameters as recommended by
4.4.1
The marine water quality monitoring locations are shown
in Figure 4.1 and ground water level (borehole with piezometer) monitoring
locations are shown in Figures 2.1, 3.7, 3.9, 3.10, 3.11 and 3.15. Prior to the
commencement of the EM&A programme, the ET leader shall agree with ER and
Table 4.3 Methods for Laboratory Analysis for Water Samples
Monitoring station |
Fig. no. |
Description |
Easting |
Northing |
Monitoring Parameters |
Underground water |
|
||||
UC1 |
2.1 |
Eastern Portal |
(i) |
(i) |
Underground
water level is the monitoring parameter to be measured at each ground water
monitoring stations. Marine
water quality parameters to be monitored include temperature, pH, turbidity,
water depth, salinity, dissolved oxygen (DO) and suspended solids (SS). |
UC2 |
3.7 |
PFLR1(P) |
(i) |
(i) |
|
UC3 |
3.9 |
THR2(P) |
(i) |
(i) |
|
UC4 |
3.10 |
TP5(P) |
(i) |
(i) |
|
UC5 |
3.11 |
TP789(P) |
(i) |
(i) |
|
UC6 |
3.15 |
W12(P) |
(i) |
(i) |
|
Marine Water |
|||||
CE |
4.1 |
Control station (Ebb) |
830026 |
814956 |
|
CF |
4.1 |
Control station (Flood) |
831778 |
812420 |
|
I1 |
4.1 |
Impact Station |
831088 |
813654 |
|
I2 |
4.1 |
Impact Station |
831105 |
813582 |
|
Intake A |
4.1 |
Impact Station (Cyberport intake) |
831603 |
813044 |
|
Intake B |
4.1 |
Impact Station
(Queen Mary Hospital/Sha Wan Drive intake) |
830606 |
814583 |
Note : (i) The location of
ground water monitoring stations shall be determined on site to suit the actual
conditions
4.4.2
The final locations and number of the monitoring points
shall be agreed with
4.4.3
When alternative monitoring locations are proposed, they
shall be chosen based on the following criteria:
(a) at locations close to and preferably at
the boundary of the mixing zone of the major site activities as indicated in
the EIA final report, which are likely to have water quality impacts;
(b) close to the
sensitive receptors which are directly or likely to be affected;
(c) for monitoring
locations located in the vicinity of the sensitive receptors, care shall be
taken to cause minimal disturbance during monitoring;
4.4.4
Control stations are necessary to compare the water
quality from potentially impacted sites with the ambient water quality. Control stations shall be located within the
same body of water as the impact monitoring stations but shall be outside the
area of influence of the works and, as far as practicable, not affected by any
other works. For underground water
monitoring, the measured ground water levels should be compared with the
pre-construction monitoring data carried out by the project office.
4.4.5
Replicates in-situ measurements and sample (except
ground water monitoring) collected from each independent sampling event are
required for all parameters to ensure a robust statistically interpretable
dataset.
Marine Water
4.5.1
Baseline conditions for water quality will be established
and agreed upon with ER and
4.5.2
The baseline conditions will normally be established by
measuring all the water quality parameters for the construction phase
monitoring as illustrated in Figure 4.1. The measurements will be taken at all
designated monitoring stations 3 days per week, at mid-flood and mid-ebb tides,
at three depth locations (i.e. 1 m below surface, mid-depth and 1m from bed),
for a period of 4 weeks prior to the commencement of marine works. The interval between two sets of monitoring will
not be less than 36 hours and the baseline monitoring schedule will be
submitted to ER and
4.5.3 Measurements will be taken at 3 water depths, namely, 1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6 m, the mid-depth station may be omitted.