DP9 ¡V SEWAGE PUMPING STATIONS
TABLE OF CONTENTs
11B...... Landscape and visual Impacts
11.2B Designated Projects under Schedule 2 within NDA
Project
11.4B Baseline Landscape Conditions
11.5B Landscape Impact Assessment
11.6B Landscape and Visual Mitigation Measures in
Construction and Operation Phases
11.7B Prediction of Significance of Landscape Impacts
11.8B Visual Impact Assessment
11.9B Cumulative Impacts from Concurrent Projects
FIGURES
Figure 11.47 Landscape
Resources (LRs)
Figure 11.47a-f Landscape
Resource Enlargement Plans
Figure 11.48 Landscape
Character Areas (LCAs)
Figure 11.49 Landscape
Resource Impacts
Figure 11.49a-d Landscape
Resource Impact Enlargement Plans
Figure 11.50 Landscape
Character Area Impacts
Figure 11.50a-d Landscape
Character Area Impact Enlargement Plans
Figure 11.51a-f Mitigation
Measures Site Plan and Section
Figure 11.52a-b Locations
of Viewpoints in Construction and Operation Phase
Figure 11.53a-b Residential VSRs in Construction and
Operation Phase
Figure 11.54a-b Recreational VSRs in Construction and
Operation Phase
Figure 11.55a-b Occupational VSRs in Construction and
Operation Phase
Figure 11.56a-b Travelling VSRs in Construction and
Operation Phase
Figure 11.57a-b Photomontage
01 ¡V View from Proposed Heritage Trail
Figure 11.58a-b Photomontage
02 ¡V View from San Lee Uk Tsuen Nullah
Figure 11.59a-b Photomontage 03 ¡V View from Yuen Tau Shan
Hiking Trail
Figure 11.60a-b Photomontage 04 ¡V View from San Sang San
Tsuen
Figure 11.61a-b Photomontage 05 ¡V View from Tsing Chuen Wai
Nullah
Figure 11.62 Broad
Brush Tree Survey
Figure 11.63 Tree
Impact and Mitigation Plan
TABLES
Table 11.1B Schedule
2 DPs Associated with HSK NDA (DP 9)
Table 11.2B Broad
Brush Tree Survey (DP 9)
Table 11.3B Baseline
Landscape Resources (LRs) (DP 9)
Table 11.4B Baseline
Landscape Character Areas (LCAs) (DP 9)
Table 11.5B Magnitude
of Landscape Change During the Construction and Operation Phases Before
Mitigation (DP 9)
Table 11.6B Proposed Construction Phase
Landscape and Visual Mitigation Measures (DP 9)
Table 11.7B Proposed
Operation Phase Landscape and Visual Mitigation Measures (DP 9)
Table 11.8B Significance
of Landscape Impacts in Construction and Operation Phases (DP 9)
Table 11.9B Sensitivity
of VSRs (DP 9)
Table 11.10B Magnitude
of Visual Change during the Construction and Operation Phases Before Mitigation
(DP 9)
Table 11.11B Significance
of Visual Impacts in the Construction and Operation Phases (DP 9)
Construction of four new sewage pumping stations (SPSs) (Sites 2-34, 3-41, 3-48 and 4-35) (DP9)
Table 11.1B Schedule 2 DPs
Associated with HSK NDA (DP 9)
Designated Project Reference No. |
Schedule 2 Designated Project |
Work Component/ Reference in RODP |
|
DP9 1 |
Part I, F.3(b) |
A sewage pumping station ¡V (b) with an installed capacity of more than 2,000 m3 per day and a boundary of which is less than 150 m from an existing or planned receiver |
Construction of four new SPSs (Sites 2-34, 3-41, 3-48 and 4-35) |
Note:
Outline Zoning Plans (OZPs)
Landscape Features
Landscape Resources (LRs)
¡P trees of 100 years old or above;
¡P trees of cultural, historical or memorable significance e.g. Fung Shui tree, tree as landmark of monastery or heritage monument, and trees in memory of an important person or event;
¡P trees of precious or rare species;
¡P trees of outstanding form (taking account of overall tree size, shape and any special features) e.g. trees with curtain like aerial roots, trees growing in unusual habitat; or
¡P trees with trunk diameter equal or exceeding 1.0 m (measured at 1.3 m above ground level), or with height/canopy spread equal or exceeding 25 m.
Broad Brush Tree Survey
Table
11.2B Broad Brush Tree Survey (DP9) |
||||||||||
Tree no. |
Species |
Chinese Name |
Est. Tree Size
(m) |
Form |
Health |
Amenity Value |
Survival Rate after Transplanting |
Remarks |
||
Overall Height |
Trunk Diameter |
Crown Spread |
||||||||
278-T1 |
Bombax ceiba |
¤ì´Ö |
35 |
1.50 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
278-T2 |
Bombax ceiba |
¤ì´Ö |
20 |
1.00 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
278D-T1 |
Ficus
microcarpa |
²Ó¸º_ |
16 |
1.00 |
20 |
Good |
Fair |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
743-T1 |
Bombax ceiba |
¤ì´Ö |
16 |
1.10 |
14 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good form
and size among its own tree species. |
785A-T1 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
18 |
0.90 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T2 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
18 |
0.80 |
12 |
Fair |
Fair |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T3 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
25 |
1.00 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T4 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
18 |
1.00 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T5 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
22 |
0.80 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
787A-T1 |
Ficus
microcarpa |
²Ó¸º_ |
8 |
1.56 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
995-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
13 |
1.50 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1071A-T1 |
Melaleuca
cajuputi subsp. Cumingiana |
¥Õ¤d¼h |
12 |
1.00 |
7 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
1077-T1 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.00 |
18 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
1213A-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
15 |
1.50 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good form
and size among its own tree species. |
A0017-T1 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.50 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1213-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
15 |
1.50 |
17 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1213-T2 |
Ficus elastica |
¦L«×¾ó¾ð |
16 |
3.00 |
25 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
207-T1 |
Ficus
microcarpa |
²Ó¸º_ |
15 |
1.50 |
20 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
207-T2 |
Ficus
microcarpa |
²Ó¸º_ |
15 |
1.50 |
20 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
207-T3 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.20 |
15 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
633-T1 |
Bombax ceiba |
¤ì´Ö |
20 |
1.00 |
14 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
633-T2 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.20 |
16 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
756-T1 |
Ficus benjamina |
««¸º_ |
16 |
1.00 |
18 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
962-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
13 |
1.50 |
16 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
Table
11.2B Broad Brush Tree Survey (DP9) (cont.) |
||||||||||
Tree no. |
Species |
Chinese Name |
Est. Tree Size
(m) |
Form |
Health |
Amenity Value |
Survival Rate after Transplanting |
Remarks |
||
Overall Height |
Trunk Diameter |
Crown Spread |
||||||||
1213-T3 |
Ailanthus
fordii |
±`ºñ¯äÝÏ |
10 |
0.16 |
3 |
Fair |
Good |
High |
Low |
The
tree species is scheduled under the Forests And Countryside Ordinance (Cap.
96). |
1213-T4 |
Ailanthus
fordii |
±`ºñ¯äÝÏ |
10 |
0.22 |
3 |
Fair |
Good |
High |
Low |
The
tree species is scheduled under the Forests And Countryside Ordinance (Cap.
96). |
Table
11.2B Broad Brush Tree Survey (DP9) (cont.) |
||||||||||
Tree no. |
Species |
Chinese Name |
Est. Tree Size (m) |
Form |
Health |
Amenity Value |
Survival Rate after Transplanting |
Remarks |
||
Overall Height |
Trunk Diameter |
Crown Spread |
||||||||
181-T1 |
Celtis sinensis |
¦µ¾ð |
12 |
0.70 |
10 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
224-T1 |
Bombax ceiba |
¤ì´Ö |
15 |
0.65 |
10 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
278D-T2 |
Bombax ceiba |
¤ì´Ö |
20 |
0.60 |
12 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
640A-T1 |
Bombax ceiba |
¤ì´Ö |
13 |
0.50 |
10 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
640A-T2 |
Bombax ceiba |
¤ì´Ö |
15 |
0.60 |
12 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
688D-T1 |
Michelia x alba |
¥ÕÄõ |
20 |
0.55 |
10 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
688D-T2 |
Michelia x alba |
¥ÕÄõ |
20 |
0.30 |
7 |
Fair |
Good |
High |
Low |
This particular
tree has very large size among its own tree species. |
688G-T1 |
Ficus religiosa |
µÐ´£¾ð |
12 |
0.80 |
10 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
914-T1 |
Homalium hainanensis |
¬õªá¤Ñ®Æ¤ì |
13 |
0.45 |
8 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
914-T2 |
Homalium hainanensis |
¬õªá¤Ñ®Æ¤ì |
12 |
0.35 |
6 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
1064-T1 |
Michelia x alba |
¥ÕÄõ |
13 |
0.60 |
8 |
Good |
Good |
High |
Low |
This particular
tree has very good form and size among its own tree species. |
Baseline Visual Conditions
SPS Site 2-34
SPS Site 3-41
SPS Site 3-48
SPS Site 4-35
Sensitivity of LRs and LCAs
¡P Quality of the LRs;
¡P Maturity of the LRs;
¡P Rarity of special landscape elements;
¡P Importance of the Landscape Resource in local and regional context; and
¡P Ability of the landscape to accommodate change
Table 11.3B Baseline Landscape Resources (LRs) (DP 9)
Id. No. |
Landscape
Resource (LR) |
Baseline Area |
Description |
||||
Quality &
Maturity (High, Medium, Low) |
Rarity (High, Medium, Low) |
Importance (Local, Regional, National, Global) |
Ability to Accommodate Change (Low, Medium, High) |
Sensitivity (Low, Medium, High) |
|||
LR
2 ¡V Hillside Woodland |
46.9 ha |
|
|||||
2.4 |
Ngau
Hom Shek |
8.8 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises the contiguous
wooded hillsides located to the east of the Shenzhen Bay Bridge and KSWH that
effectively form the northern green backdrop of the NDA. Numerous graves are found scattered
about the hillsides.
Vegetation is comprised of mature and semi-mature tree canopies of
various species forming an interconnected tree canopy. One Important Tree,
181-T1, is located in this LR. A
total of approx. 491 trees have been identified within this LR; the dominant
species includes Macaranga
tanarius var. tomentosa, Lophostemon
confertus, and Celtis sinensis. |
|||||||
Zoning: The majority of the LR
lies within area zoned GB under the Ha Tsuen OZP S/YL-HT/10, with smaller
patches located at the base of the northerly and westerly slopes zoned
¡§Agriculture¡¨ (AGR). |
|||||||
2.6 |
Tung Tau Tsuen |
1.3 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises two
contiguous wooded hillsides rising to 28.3 m and 24.2 m located north of Hong
Mei Tsuen and Tung Tau Tsuen. The
hillsides lie immediately adjacent to Yeung Hau Temple, a Declared
Monument. Numerous graves are
found scattered about the hillsides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy. A
total of approx. 132 trees have been identified within this LR; the dominant
species includes Macaranga
tanarius var. tomentosa, Dimocarpus
longan, Clausena lansium, Litchi chinensis, and Artocarpus heterophyllus. |
|||||||
Zoning: The north facing slopes
of the hillsides are zoned ¡§Comprehensive Development Area¡¨ (CDA) and the
south-facing hillsides are zoned V, both under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.7 |
Ha Tsuen Road |
0.3 ha |
High |
Medium |
Local |
Medium |
High |
This LR comprises a
lone, isolated wooded hillside rising to 13.2 m located north of Ha Tsuen
Road and surrounded by open storage land-uses on all sides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy. A total
of approx. 43 trees have been identified within this LR; the dominant species
includes Litchi chinensis. |
|||||||
Zoning: The hillside is zoned
GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.8 |
Ha Tsuen |
1.2 ha |
Medium |
Medium |
Local |
Low |
Medium |
This LR comprises a
lone, isolated wooded hillside rising to 35.9 m located north of the Sewage
Treatment Plant and disconnected from the northern wooded hillside ridgeline
of Ngau Hom Shek by open storage land-uses on all sides. The top of the hillside has been
de-vegetated and levelled to make room for industrial land uses. Vegetation is comprised of mature and
semi-mature tree canopies of various species forming an interconnected tree
canopy. A total of approx. 108
trees have been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The hillside is zoned
GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.9 |
Yuen Tau Shan |
29.4 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises the
contiguous wooded hillsides located to the west of the Shenzhen Bay Bridge
and KSWH that effectively form the western ridgeline of the NDA. Numerous graves are found scattered
about the hillsides.
Vegetation is comprised of mature and semi-mature tree canopies of various
species forming an interconnected tree canopy. A total of approx. 1,389 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Eucalyptus sp., Acacia confusa, Leucaena leucocephala,
Dimocarpus longan. |
|||||||
Zoning: The majority of the LR
lies within area zoned ¡§CA" under the Ha Tsuen OZP S/YL-HT/10, Ping Shan OZP S/YL-PS/16, &
Lam Tei & Yick Yuen OZP S/TM-LTYY/8.
Additional areas lie within areas zoned GB under the aforementioned
OZPs, and a small patch located at the foothills facing Deep Bay is zoned AGR
under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.11 |
Kau Lee Uk Tsuen |
2.9 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises of a
hillside area located to the west of Kau Lee Uk Tsuen and rises 38.1 m in
elevation. Numerous graves are
found scattered about the hillsides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy. A
total of approx. 139 trees have been identified within this LR; the dominant
species includes Litchi
chinensis, Macaranga tanarius var. tomentosa, Clausena lansium, Dimocarpus longan, and Celtis sinensis. |
|||||||
Zoning: The hillside lie within
areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.12 |
San Sang Tsuen |
2.9 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises
three discontinuous hillside areas located to the west and northwest of San
Sang Tsuen, rising to elevations of 18 m, 24.5 m, 28.3 m. Numerous graves are found
scattered about the hillsides.
Vegetation is comprised of mature and semi-mature tree canopies of
various species forming an interconnected tree canopy. One Important Tree, 633-T2,
is located within the LR; it is identified as Ficus macrocarpa. A total of approx. 156 trees have been
identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, and Aleurites moluccana. |
|||||||
Zoning: The easternmost
hillsides lies within area zoned G/IC, and the two westerly hillsides lie
within areas zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
LR 3 ¡V Hillside Shrub & Grassland |
25.5 ha |
||||||
3.3 |
Ngau Hom Shek |
2.4 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises
various hillside meadows located within the extents of LR2.3 - Ngau Hom Shek
Woodland. Here, there are few
trees and the dominant vegetation consists of successional herbaceous plants
and grassland species. Numerous graves are found scattered about the
areas. One Important Tree,
237C-T1 is located within this LR.
The identified tree species is Cinnamomum
camphora and is identified as having very good form for trees of this species.
A total of approx. 56 trees have been identified within this LR; the dominant
species includes Lophostemon
confertus, Acacia auriculiformis, and Tetradium glabrifolium . |
|||||||
Zoning: The LR lies within
area zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
3.4 |
Yuen Tau Shan |
22.9 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises
various hillsides located scattered amongst the extents of LR2.9 ¡V Yuen Tau
Shan Woodland. These hillsides comprise
part of the western ridgeline of the Project area, and comprise dense
woodland stands and more open, hillside shrub land. In this LR, there are few trees and
the dominant vegetation consists of successional herbaceous plants and
grassland. Numerous graves are
found scattered about the various hillsides. A total of approx. 149 trees
have been identified within this LR; the dominant species includes Leucaena leucocephala, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The majority of the LR
lies within area zoned CA under the Ha Tsuen OZP S/YL-HT/10, Ping Shan OZP S/YL-PS/16, &
Lam Tei & Yick Yuen OZP S/TM-LTYY/8.
Additional areas lie within areas zoned GB under the aforementioned
OZPs, and a small patch located at the foothills facing Deep Bay is zoned AGR
under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
3.5 |
Kau Lee Uk Tsuen |
0.2 ha |
Medium |
Medium |
Local |
Low |
High |
This LR comprises
hillside meadows located within the extents of LR2.10 - Hung Uk Tsuen
Woodland. Here, there are few trees
and the dominant vegetation consists of successional herbaceous plants and
grassland species. Numerous
graves are found scattered about the area. A total of approx. 4 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa and Celtis sinensis. |
|||||||
Zoning: The hillsides lie
within areas zoned GB under the Ping Shan OZP S/YL-PS/16. |
|||||||
LR 4 ¡V Low-lying Woodland/Plantation |
16.1 ha |
||||||
4.8 |
San Sang San Tsuen |
15.8 ha |
High |
Medium |
Regional |
Low |
High |
This LR consists of
two extremely large, woodland and scrubland areas located adjacent to a
similar sized area of land used for agriculture. This LR is located between the Kong
Sam Western Highway (KSWH) and the West Rail Line (WRL) alignment, and south
of San Sang San Tsuen and San Sang Tsuen villages. It primarily consists of two
continuous, large areas. The
northern area is immediately south of the aforementioned village areas, and
consists of stands of mature and semi-mature trees and open scrubland and
grassland areas. All the
vegetation is of relatively high quality. The southern area is located south of
the large agricultural zone LR 6.9 and is bisected by a small drainage
channel. Vegetation here is similar
to the above. These two areas are
generally continuous, open, unspoiled, and generally of high quality. Five numbers of Important Trees,
688D-T1, 688-T2, 688G-T1, 914-T1, & 914-T2 are located within this
LR. Identified as Michelia x alba, Ficus religiosa, and Homalium
hainanensis, the tree species are recognized for their very good form and
large size among their own tree species. A total of approx. 626 trees have
been identified within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, Leucaena
leucocephala, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The northern area of
this LR largely resides within areas zoned R(D), with a very small area
residing within area zoned V, both under the under the Ha Tsuen OZP S/YL-HT/10. The majority of the LR, both north and
south areas, reside within areas zoned GB under the Ping Shan OZP
S/YL-PS/16. A small portion of
the southern LR area falls within land zoned U under the Ping Shan OZP
S/YL-PS/16. |
|||||||
4.12 |
Powerline Pylon |
0.3 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of
the area surrounding an electrical transmission wire pylon. Vegetation has grown to include
scrubland and herbaceous species around the base of the pylon supports. It is located south of Yick Yuen Tsuen
and lies adjacent to a drainage nullah. A total of approx. 22 trees have been
identified within this LR; the dominant species includes Bauhinia purpurea and Leucaena leucocephala. |
|||||||
Zoning: This LR resides within
areas zoned R(C) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 5 ¡V Low-lying Shrub & Grassland |
23.7 ha |
||||||
5.3 |
Fung Kong Tsuen |
7.0 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR primarily consists
of scattered scrubland areas with open grassland or bare patches of dirt
interspersed between. It
presently serves as a transition between LR 2.4 - Ngau Hom Shek Woodland to
the west and large, contiguous industrial and open-air storage areas serviced
by Ping Ha Road to the east. Vegetation is generally of good quality and the
grassland forms the base of the hillside in this area. A total of approx. 145
trees have been identified within this LR; the dominant species includes Leucaena leucocephala and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This LR resides
primarily within areas zoned GB, but also within CDA, V, and ¡§Recreation¡¨
(REC) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.5 |
San Wai |
1.4 ha |
High |
Medium |
Local |
Medium |
High |
This LR consists of
four grassland patches located within the vicinity of San Wai, Sik Kong
Tsuen, and Tseung Kong Wai villages.
Vegetation is generally of good quality and the grassland forms green
backdrops set against rural village housing. Three Important Trees, 278-T1, 278-T2
and 278D-T1 are located in this LR.
The identified tree species include Bombax ceiba and Ficus
microcarpa and are potentially registrable as OVTs due to large tree size
and very good form among trees of these species. A total of approx. 60 trees
have been identified within this LR; the dominant species includes Dimocarpus longan, Macaranga tanarius var. tomentosa, and Clausena lansium. |
|||||||
Zoning: This LR resides within
areas zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.6 |
San Lee Uk Tsuen |
0.7 ha |
High |
Medium |
Local |
Low |
High |
This LR consists of a
large woodland stand and scrubland located south of Sha Chau Lei Road and the
nullah, and north of the WRL alignment.
The vegetation consists of mature and semi-mature trees forming an
interlocking tree canopy with dense understory, or more open areas of
scrubland with herbaceous and grassland species. This LR is continuous, open,
unspoiled, and generally of high quality. A total of approx. 25 trees have
been identified within this LR; the dominant species includes Leucaena leucocephala, Dimocarpus longan,
Ficus microcarpa, and Celtis sinensis. |
|||||||
Zoning: This LR resides within
areas zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.7 |
San Sang Tsuen |
0.5 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of a
small grassland interspersed between rural residential developments in San
Sang Tsuen. As continual expansion
of village housing occurs, it is likely that this area will be subsumed by
development in short time. |
|||||||
Zoning: This LR resides within
areas zoned V and R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.8 |
Chung Uk Tsuen |
1.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR primarily
consists of an open area of scrubland vegetation and several stands of mature
woodlands and individual trees.
The LR is circumscribed on three sides by rural village housing and is
bound to the east by a nullah drainage channel. This LR is located south of Castle
Peak Road and south of Chung Uk Tsuen.
The character of vegetation is generally of good quality in that the
trees are mature and semi-mature species. As continual expansion of village
housing occurs, it is likely that this area will be subsumed by development.
A total of approx. 86 trees have been identified within this LR; the dominant
species includes Leucaena
leucocephala, Celtis sinensis, Artocarpus heterophyllus, and Clausena lansium. |
|||||||
Zoning: This LR resides within
areas zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
5.9 |
Yick Yuen Tsuen |
12.4 ha |
High |
Medium |
Regional |
Medium |
High |
This LR consists of an
extremely large, woodland and scrubland area. This LR is located west of Yick Yuen
Tsuen and east of the KSWH. It
consists of continuous, large areas vegetation including stands of mature and
semi-mature trees and open scrubland and grassland areas. All the vegetation is of relatively
high quality. This LR is
generally continuous, open, and of high quality. A total of approx. 503 trees
have been identified within this LR; the dominant species includes Leucaena leucocephala, Dimocarpus longan, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This LR resides within
areas zoned GB and R(D) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
5.11 |
Tsing Chuen Wai |
0.4 ha |
Low |
Low |
Local |
High |
Low |
This LR primarily
consists of low-quality scrubland interspersed between rural residential developments
and the KSWH. As continual
expansion of village housing occurs, it is likely that this area will be
subsumed by development in short time. A total of approx.27 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala. |
|||||||
Zoning: This LR resides within
areas zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 6 ¡V Vegetation on Agricultural Land |
28.0 ha |
||||||
6.3 |
Ha Tsuen |
3.7 ha |
Low |
Low |
Local |
High |
Low |
This LR comprises five
individual, non-congruous plots of land actively being used in agricultural
production. They are located near
Tseung Kong Wai, Ski Kong Wai, San Wai, and Ha Tsuen Shi and generally are
bordered by rural village housing and vegetation. As this LR is essentially located in
leftover spots around village housing, as continual expansion of village
housing occurs it is likely that this area will be subsumed by development. A
total of approx. 66 trees have been identified within this LR; the dominant
species includes Eucalyptus
torelliana, Dimocarpus longan, and Melaleuca cajuputi subsp.
Cumingiana. |
|||||||
Zoning: This LR largely
resides within land zoned V under the Ha Tsuen OZP S/YL-HT/10, with very
small areas falling under REC or GB designation. |
|||||||
6.5 |
Shek Po Tsuen |
1.2 ha |
Low |
Low |
Local |
High |
Low |
This LR comprises five
individual, non-congruous plots of land actively used in agricultural
production. They are located in
the vicinity of Shek Po Tsuen to the north, west and south, as well as two larger
sized plots located to the west on either side of the WRL alignment. The plots surrounding Shek Po Tsuen
occupy leftover spaces around village housing, and as continual expansion of
village housing occurs, it is likely that this area will be subsumed by
development. The two plots
located to the west are located adjacent to the large Low-lying
Woodland/Plantation LR4.12. A total of approx. 41 trees have been identified
within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, and Roystonea regia. |
|||||||
Zoning: This LR resides wholly
within land zoned V and R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
6.6 |
San Sang San Tsuen |
19.3 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises three
individual, non-congruous plots of land actively used in agricultural
production. They are located to
the south of San Sang San Tsuen and are bounded by the KSWH to the west and
the WRL to the east. The north is
bound by LR4.13 ¡V San Sang San Tsuen Low-lying Woodland/Plantation, a
high-amenity scrubland. This LR
is the largest contiguous area of land being actively used for agriculture
within the Project area. It
consists of agricultural plots of various sizes growing a variety of crops,
numerous stands of trees varying in age, rural housing and buildings of
varying quality and functions, areas of woodland and scrubland between plots
and buildings. It is regarded to
have a high amenity value due to its intensive use and large size. Six Important Trees, 785A-T1, 785A-T2,
785A-T3, 785A-T4, 785A-T5, & 787A-T1 are located within this LR. A total
of approx. 651 trees have been identified within this LR; the dominant
species includes Dimocarpus longan, Mangifera indica,
Artocarpus heterophyllus, and Macaranga tanarius var.
tomentosa. |
|||||||
Zoning: This LR resides mostly
within areas zoned GB under the Ping Shan OZP S/YL-PS/16. A small corner of the southeastern LR
falls within area zoned U under the Ping Shan OZP, and a very miniscule area
of the LR falls within land zoned R(D) under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
6.10 |
Tin Sam |
1.8 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of
continuous agricultural plots located to the southwest of Tin Sam
village. Interspersed throughout this
agricultural area are numerous trees as well as sheds and rural buildings of
varying functions. This LR is
located to the east of the WRL alignment across from a small drainage
channel. The vegetation is
generally of good quality. A total of approx. 189 trees have been identified
within this LR; the dominant species includes Dimocarpus longan and Clausena lansium. |
|||||||
Zoning: This LR resides within
area under R(C) under the Ping Shan OZP S/YL-PS/16. |
|||||||
6.11 |
Yick Yuen Tsuen |
2.1 ha |
Medium |
Low |
Local |
High |
Low |
This LR consists of
two small, non-congruous areas of agricultural land adjacent to LR4.19; a
large, open scrub and woodland area.
This LR is located west of Yick Yuen Tsuen and the WRL alignment, and
east of the KSWH. It also
includes a small, marginalized area of agricultural land adjacent to the KSWH
located just north of Tsing Chuen Wai.
Interspersed throughout these agricultural areas are numerous trees as
well as sheds and rural buildings of varying functions. The vegetation is generally of good
quality. A total of approx. 82 trees have been identified within this LR; the
dominant species includes Dimocarpus
longan, Litchi chinensis, and Clausena lansium. |
|||||||
Zoning: This LR resides within
areas zoned GB and R(D) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 7 ¡V Vegetation within Residential
Developments |
0.3 ha |
||||||
7.2 |
Developments along
Castle Peak Road |
0.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR comprises residential
developments along Castle Peak Road including: Uptown & The Woodside;
Symphony Garden & Treasure Court; Lai Hung Garden; Bauhinia Garden. Vegetation includes amenity planting
around residential developments.
This LR is located along Castle Peak Road. The vegetation is newly established
and provides garden and recreation spaces for residents. A total of approx.
37 trees have been identified within this LR; the dominant species includes Spathodea campanulata, Bauhinia variegata,
Ficus microcarpa, Michelia x alba, Melaleuca cajuputi subsp. cumingiana, Ficus benjamina, and Cinnamomum burmannii. |
|||||||
Zoning: This LR resides within
areas zoned CDA and R(B) under the Tong Yan San Tsuen OZP S/YL-TYST/10. |
|||||||
LR 8 ¡V Vegetation within Rural Village |
41.4 ha |
||||||
8.5 |
Sik Kong Tsuen/ Hong
Mei Tsuen/ Tseung Kong Wai |
3.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
The LR is of multiple
areas in Sik Kong Tsuen, Hong Mei Tsuen and Tseung Kong Wai. The village areas
are along San Sik Road. The vegetation is within and around the rural housing
and the open storage areas. Four Important Trees, 201-T1, 202-T1, 207-T1 and
207-T2, are located in this LR. Identified species include Ficus macrocarpa. A total of approx.
176 trees have been identified within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, Litchi
chinensis, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR resides in land
zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
8.6 |
Sik Kong Wai / San Uk
Tsuen / Ha Tsuen Shi |
0.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
The LR is part of the Sik Kong Wai, San Uk
Tsuen and Ha Tsuen Shi village housing areas. The village areas are north of a
large container yard across from Tin Ha Road. Vegetation is mixed and
self-seeded trees within and around the populated areas. A total of approx.
18 trees have been identified within this LR; the dominant species includes Melaleuca cajuputi subsp. cumingiana, Eucalyptus torelliana, and Acacia confuse. |
|||||||
Zoning: The LR resides in land zoned V under the Ha
Tsuen OZP S/YL-HT/10. |
|||||||
8.11 |
San Sang Tsuen |
3.4 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of two large medium-sized areas
trees scattered about village housing. It is located west of Tin Ha
Road. Vegetation is a mixture of self-seeded and cultivated trees within and
around the village area. A total of approx. 191 trees have been identified
within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, Macaranga tanarius var. tomentosa, and Litchi chinensis. |
|||||||
Zoning: The majority of the LR resides in land zoned V
under the Ha Tsuen OZP S/YL-HT/10. A small portion of the LR is under land
zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. In addition, a trivial area of
the LR resides in land zoned U under the Ping Shan OZP S/YL-PS/16. |
|||||||
8.12 |
San Lee Uk Tsuen / Tin
Sam |
2.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of several small,
non-congruous vegetation patches scattered about the San Lee Uk Tsuen Village
area, and one vegetation patch north of Tin Sam. The LR is located west of Hung Shui Kiu Main Street.
General vegetation is of self-seeded semi-mature and mature trees. One Important Tree, 706-T1 is located
within this LR. The identified
tree species is Ficus elastica and
is potentially registrable as an OVT due to its large size and good form
among trees of this species. A total of approx. 125 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala, Dimocarpus longan,
Bauhinia purpurea, and Clausena lansium. |
|||||||
Zoning: The LR mostly resides in land zoned V under the
Ping Shan OZP S/YL-PS/16. Other areas are in land zoned R(C) and G/IC also
under the Ping Shan OZP S/YL-PS/16. |
|||||||
8.13 |
Hung Shui Kiu |
0.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of three small sized village housing
areas located in the vicinity of Hung Shui Kiu Tin Sam Road and Hung Kei
Road. General vegetation is
of self-seeded semi-mature and mature trees. A total of approx. 13 trees have
been identified within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, Macaranga tanarius var. tomentosa, and Artocarpus heterophyllus. |
|||||||
Zoning: The LR resides in land zoned R(B) under the
Ping Shan OZP S/YL-PS/16. |
|||||||
8.14 |
Tin Sam |
6.8 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is located about the large village
housing area of Tin Sam; it is located south and west of Tin Ha Road along
Tin Sam. Area is west of residential developments Casa De Oro and Parkview
Garden. Vegetation is a mixture of self-seeded and cultivated trees within
and around the village area. A total of approx. 321 trees have been
identified within this LR; the dominant species includes Dimocarpus longan, Macaranga tanarius var. tomentosa, and Clausena lansium. |
|||||||
Zoning: The LR resides in land zoned V and R(C) under
the Ping Shan OZP S/YL-PS/16. This LR also resides in land zoned R(B)2 under
the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
8.17 |
Tan Kwai Tsuen |
0.8 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of a
large continuous canopy of trees and vegetation throughout Tan Kwei Tsuen.
This LR is located northeast and south of two residential developments, The
Verdancy and the Meadowlands. Vegetation within this LR primarily consists of
self-seeded and planted mature and semi-mature trees with various understory
and shrub planting. Two Important Trees, 1064-T1 & 1064-T2 are located
within this LR. The identified
tree species are Michelia x alba &
Ficus virens and are potentially
registrable as an OVT due to their large size and good form. A total of
approx. 28 trees have been identified within this LR; the dominant species
includes Dimocarpus longan,
Bauhinia purpurea, Cinnamomum burmannii, and Ficus microcarpa. |
|||||||
Zoning: The majority of LR
resides in land zoned R(D) under the Tong Yan San Tsuen OZP S/YL/-TYST/10. A
smaller are of LR resides in land zoned R(B)3 under the Tong Yan San Tsuen
OZP S/YL/-TYST/10. |
|||||||
8.18 |
Wo Ping San Tsuen /
Cheung Uk Tsuen / Arkadia |
11.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of
two village housing areas; these are Wo Ping San Tsuen and Cheung Uk Tsuen.
Southern portion of area is a housing development Arkadia. The LR is located
southeast of Castle Peak Road Hung Shui Kiu. Vegetation in the LR is generally
self-seeded semi-mature to mature trees. A total of approx. 213 trees have
been identified within this LR; the dominant species includes Leucaena leucocephala, Clausena lansium, and Dimocarpus longan. |
|||||||
Zoning: The LR resides mostly
in land zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. A small
portion of LR resides in land zoned R(D) under the Lam Tei & Yick Yuen
OZP S/TM-LTYY/8. In addition, trivial areas of the LR reside in land zoned O
and R(B)2R(B)2 under the Lam Tei
& Yick Yuen OZP S/TM-LTYY/8. |
|||||||
8.19 |
Yick Yuen Tsuen |
11.9 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of
one village housing area, called Yick Yuen Tsuen. The site is adjacent to an open
air storage area to the north and woodland area to the west. There are
pockets of vegetation scattered around the village area between and around
the housing. Vegetation is generally self-seeded semi-mature to mature trees.
A total of approx. 447 trees have been identified within this LR; the
dominant species includes Dimocarpus
longan and Litchi chinensis. |
|||||||
Zoning: The majority of LR
resides in land zoned R(C) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8.
A portion of LR resides in land zoned V under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
8.20 |
Tsing Cheun Wai / Tuen
Tsz Wai |
1.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is adjacent to
two village housing areas: Tsing Cheun Wai and Tuen Tsz Wai. Village area is southwest
of the KSWH and northwest of Castle Peak Road. The vegetation is mostly
scattered around housing areas; and are generally self-seeded semi-mature to
mature trees. A total of approx. 38 trees have been identified within this
LR; the dominant species includes Leucaena
leucocephala, Dimocarpus longan, and Clausena lansium. |
|||||||
Zoning: The LR resides mostly
in land zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. Smaller
areas of LR reside in land zoned GB and CA under the Lam Tei & Yick Yuen
OZP S/TM-LTYY/8. |
|||||||
8.21 |
Lam Tei / Tuen Mun San
Tsuen |
0.05 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR comprises scattered stands of trees
and vegetation located amongst the village areas of Fuk Hang Tsuen, Lam Tei, and
Tuen Mun San Tsuen. This LR is located east of Castle Peak Road, near to the
residential developments, The Sherwood and Lingrade Garden. Vegetation is
generally self-seeded semi-mature to mature trees. A total of approx. 3 trees
have been identified within this LR; the dominant species includes Dimocarpus longan, Leucaena leucocephala, Clausena lansium, and Archontophoenix alexandrae. |
|||||||
Zoning: The LR reside in land zoned R(B), R(C), G/IC,
CDA, O and V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 9 ¡V Vegetation within Industrial Land /
Open Storage |
28.9 ha |
||||||
9.3 |
Ping Ha Road |
0.3 ha |
Low |
Low |
Local |
High |
Low |
LR is scattered
amongst a large container yard and an open storage along Ping Ha Road. Vegetation
is generally around the perimeter of the open space yards providing a minor
partition between the road and storage yards. Vegetation is generally
self-seeded semi-mature trees with some understory and shrub planting. A
total of approx. 22 trees have been identified within this LR; the dominant
species includes Ficus
benjamina, Ficus microcarpa, and Macaranga tanarius var.
tomentosa. |
|||||||
Zoning: The LR resides in land
zoned CDA under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.7 |
Tseung Kong Wai |
9.6 ha |
Low |
Low |
Local |
High |
Low |
The LR is south of an
open container yard and north of Tseung Kong Wai rural housing area.
Vegetation is within and around the boundary of the industrial buildings and
open-air yards. Vegetation is generally self-seeded semi-mature trees with
understory and shrubs plants. One Important Tree, 207-T3, is located in this
LR. A total of approx. 321 trees have been identified within this LR; the
dominant species includes Ficus
microcarpa, Macaranga tanarius var. tomentosa, and Ficus
virens. |
|||||||
Zoning: The LR is over
multiple zoned areas under the Ha Tsuen OZP S/YL-HT/10; zoned CDA,GB and REC. |
|||||||
9.9 |
Ha Tsuen Road |
5.6 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR consists of several
large open spaces used for container storage and parking lots. The area is
north of Ha Tsuen Road and a sewage treatment plant. Vegetation is generally
around the perimeter of the open space yards providing a minor partition
between the road and storage yard. Vegetation is mostly self-seeded
semi-mature trees with some wild understory planting. One Important Tree,
224-T1, is located in this LR.
A total of approx. 468 trees have been identified within this LR; the
dominant species includes Ficus benjamina,
Ficus microcarpa, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR resides mostly
in land zoned REC under the Ha Tsuen OZP S/YL-HT/10. Small areas of the LR
also reside in land zoned G/IC and GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.11 |
Sik Kong Wai Road / Ha
Tsuen Road |
1.11 ha |
Low |
Low |
Local |
High |
Low |
LR is bordering a
large container yard and a smaller open-air storage area. Area is located
along Sik Kong Wai Road and north of Ha Tsuen Road. Vegetation is generally
along the perimeters of the sites flanking the roads. Vegetation is mostly self-seeded
semi-mature trees with some wild understory planting. A total of approx. 116
trees have been identified within this LR; the dominant species includes Ficus microcarpa, Ficus benjamina, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR is over
multiple zoned areas under the Ha Tsuen OZP S/YL-HT/10; zoned OS, REC, GB and
V. |
|||||||
9.16 |
San Lee Uk Tsuen |
0.7 ha |
Low |
Low |
Local |
High |
Low |
The LR is northwest of San Lee Uk Tsuen, also
located along the southeast of the WRL and southeast of San Sang Tsuen.
Vegetation is mostly around the perimeter of the open storage yard. It is
generally self-seeded semi-mature trees with some wild understory planting. A
total of approx. 12 trees have been identified within this LR; the dominant
species includes Sterculia
nobilis, Macaranga tanarius var. tomentosa, Ficus benjamina, Clausena lansium, Morus alba,
Dimocarpus longan, and Ficus
microcarpa. |
|||||||
Zoning: The LR resides in land zoned R(D) under the Ha
Tsuen OZP S/YL-HT/10; and in land zoned V under the Ping Shan OZP S/YL-PS/16. |
|||||||
9.17 |
Kau Lee Uk Tsuen / San Sang Tsuen |
9.7 ha |
Low |
Low |
Local |
High |
Low |
The LR is located between Kau Lee Uk Tsuen and
San Sang Tsuen, and east of KSWH. General area consists of industrial
buildings and open storage yards with planting scattered throughout the
buildings and open storage yards. Vegetation is generally self-seeded
semi-mature to mature planting. Two identified Important Trees, 640A-T1 &
640A-T2, are located within this LR adjacent to Sha Chau Lei village. The identified tree species is Bombax ceiba and both have very good
form and size among trees of this species. A total of approx. 247 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Clausena lansium, Litchi
chinensis, and Dimocarpus longan. |
|||||||
Zoning: Majority of LR resides
in land zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. Other areas of LR are
in land zoned V, GB and OS(1) under the Ha Tsuen OZP S/YL-HT/10. In addition,
a small area of the LR resides in land zoned GB under the Ping Shan OZP
S/YL-PS/16. |
|||||||
9.18 |
Yick Yuen Road |
1.2 ha |
Low |
Low |
Local |
High |
Low |
The LR consists of one
large container storage area, located north of Yick Yuen Road and west of the
WRL. Vegetation is generally around the perimeter of the open space yards
providing a minor partition between the road and storage yards. Vegetation is
generally self-seeded semi-mature trees with some understory and shrub
planting. A total of approx. 102 trees have been identified within this LR;
the dominant species includes Leucaena
leucocephala, Ficus benjamina, and Macaranga tanarius var.
tomentosa. |
|||||||
Zoning: The LR resides mostly
in land zoned U under the Ping Shan OZP S/YL-PS/16. A small portion of LR is
in land zoned G/IC and R(B)2 under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
9.19 |
KSWH South |
0.7 ha |
Low |
Low |
Local |
High |
Low |
The LR consists of 2
separate open storage areas. Both are located along the KSWH: one at Yick
Yuen Road and other at Tsing Yick Road. Vegetation is generally at the
perimeter of the open space yards with self-seeded semi-mature trees with
some understorey and shrub planting. A total of approx. 53 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala, Eucalyptus
tereticornis, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR resides in land
zoned GB under both the Ping Shan OZP S/YL-PS/16 and the Lam Tei & Yick
Yuen OZP S/TM-LTYY/8. |
|||||||
LR 10 ¡V Water Course |
4.1 ha |
|
|||||
10.5 |
Sik Kong Tsuen &
Tseung Kong Wai Nullah |
0.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a
channelised watercourse with vertical concrete banks running in west to east
direction eventually turning northeast and draining into LR10.4 - Ping Ha
Road Nullah. This LR stretches
from west of Tseung Kong Wai and passes through the village areas of San Wai
and Sik Kong Tsuen. This LR has
an abundance of tree stands lining the riverbanks in the vicinity of Sik Kong
Wai and gradually becomes more open and sparse of vegetation as one moves
upstream. |
|||||||
Zoning: This LR lies within
areas zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
10.6 |
Sik Kong Wai &
Ling To Nullah |
0.2ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a
channelised watercourse with vertical concrete banks running in a southwest to
northeast direction eventually joining LR10.5 and draining into Ping Ha Road
Nullah. This LR stretches from
Ling To where it passes under the KSWH, meanders between numerous industrial
and open storage yards, and, at flowing between Sik Kong Wai and Ha Tsuen
Shi, turns north to drain into LR10.4 ¡V Ping Ha Road Nullah. This LR has an abundance of tree
stands lining the riverbanks in the vicinity of the villages as well as
continuous tree cover as it meanders through the open storage areas. It gradually becomes more open in the
vicinity of Ling To Temple. A total of approx. 3 trees have been identified
within this LR; the dominant species includes Macaranga tanarius var. tomentosa and Acacia
auriculiformis. |
|||||||
Zoning: This LR lies within
areas zoned V, GB, and ¡§Open Storage¡¨ (OS) under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
10.7 |
Yuen Tau Shan Streams
& Nullah |
0.1 ha (nullah) |
Medium |
Medium |
Regional |
Medium |
Medium |
This LR consists of
the three natural watercourses that exist within the NDA. These three natural streams are all
located along the western ridgeline of the NDA. The northernmost stream drains
northwards and eventually is channelised before emptying into Deep Bay. The other two streams are located
across the KSWH from LR6.6 - San
Sang San Tsuen. They both become
channelised and culverted before passing under the highway and eventually
emptying into LR10.11 ¡V Tin Sam Channel. A total of approx. 61 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Pinus massoniana, Leucaena
leucocephala, and Ficus hispida. |
|||||||
Zoning: The northern stream
lies within areas zoned GB and CA under the Ha Tsuen OZP S/YL-HT/10. The two southern streams lie within areas
zoned GB and CA under the Ping Shan OZP S/YL-PS/16. |
|||||||
10.10 |
Shek Po Channel |
0.7 ha |
High |
Medium |
Local |
Low |
High |
This LR is a concrete
channel running through the south of the NDA and eventually draining into
LR10.1 Tin Shui Wai (TSW) River Channel. It consists of a sloping concrete
bank channel north of Castle Peak Road and, south of Castle Peak Road, the
concrete sloping banks are lined with grasscrete for a short section before
returning to bare concrete banks.
This LR has an abundance of high quality tree stands lining the
riverbanks for nearly the entire length. |
|||||||
Zoning: The extents of this LR
north of Castle Peak Road does not fall within any OZP, whereas the extents
south of this road falls within area zoned R(D) under the Tong Yan San Tsuen
OZP S/YL-TYST/10. |
|||||||
10.11 |
Tin Sam Channel |
1.9 ha |
High |
Medium |
Local |
Low |
High |
This LR is a concrete
channel running through the south of the NDA and eventually draining into LR10.1
TSW River Channel. It consists of a sloping concrete bank channel north of
Tin Ha Road and, south of Tin Ha Road, becomes a vertical bank channel. This LR has an abundance of high
quality tree stands lining the riverbanks for nearly the entire length. A
total of approx. 1 tree have been identified within this LR, the dominant
species includes Dimocarpus
longan. |
|||||||
Zoning: The extents of this LR
north of Tin Ha Road does not fall within any OZP, whereas the extents south
of this road falls within area zoned V and R(C) under the Ping Shan OZP
S/YL-PS/16 and GB under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
10.12 |
San Sang San Tsuen
Channel |
0.5 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of
three very small tributaries traversing the area south of San Sang San Tsuen
through LR6.6 - San Sang San Tsuen Vegetation on Agricultural Land as well as
LR4.13 ¡V San Sang San Tsuen Low-lying Woodland/Plantation. These drainage channels consist of
vertical concrete embankments with an abundance of trees along their length. |
|||||||
Zoning: This LR falls within
numerous zoning designations under the GB, U, R(C) and R(D) all under the
Ping Shan OZP S/YL-PS/16. |
|||||||
10.13 |
Yick Yuen Tsuen &
Tsing Chuen Wai Nullah |
0.4 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a concrete
channel running through the south of the NDA and eventually draining into the
Tuen Mun River. The main nullah consists of a sloping concrete bank channel
extending from Castle Peak Road and the KSWH and draining southwest. A smaller tributary drains from Yick
Yuen Tsuen in a southwardly direction.
This smaller tributary has an abundance of tree stands along the
riverbanks whereas the main channel is bare, concrete sloped embankment. A
total of approx. 1 tree have been identified within this LR. |
|||||||
Zoning: The southern extents
of this LR does not fall within any OZP, whereas the northern extents fall
within area zoned V and R(D) under the Ping Shan OZP S/YL-PS/16 and GB under
the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 11 ¡V Vegetation in Urban Parks |
0.9 ha |
|
|||||
11.4 |
Tin Ha Road Playground |
0.4 ha |
High |
Medium |
Local |
Medium |
Medium |
The Tin Ha Road
Playground is a medium-sized open space adjacent to rural residential housing
and located along Castle Peak Road.
It primarily consists of a soccer pitch and smaller sports pitch, with
various amenity planting and paved activity spaces around the pitch. The vegetation consists of semi-mature
amenity trees and shrub planting. A total of approx. 24 trees have been
identified within this LR; the dominant species includes Callistemon
viminalis and Eucalyptus torelliana.
|
|||||||
Zoning: This LR falls within
areas zoned O under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
11.5 |
Nai Wai Soccer Pitch /
Fuk Hang Tsuen Road Garden |
0.5 ha |
High |
Medium |
Local |
Medium |
Medium |
Nai Wai Soccer Pitch
is a small open space adjacent to Nai Wai. It primarily consists of a soccer
pitch with various amenity planting and paving around the pitch. The vegetation consists of semi-mature
amenity trees and shrub planting.
The Fuk Hang Tsuen Road Garden is a medium-sized open space adjacent
to residential units in The Sherwood, and located off Castle Peak Road behind
the Miu Fat Buddhist Monastery.
It primarily consists of numerous spaces, activity areas, walking
trails and planting areas. The
vegetation consists of semi-mature amenity trees and shrub planting. There is also a large paved square on
top of a carpark entrance located to the south off Lam Tei Main Street. One
Important Tree, 1213-T2, is located in this LR. A total of approx. 45 trees
have been identified within this LR; the dominant species includes Araucaria heterophylla, Aleurites moluccana,
Ficus virens, Leucaena leucocephala, and Archontophoenix alexandrae. |
|||||||
Zoning: This LR falls within
areas zoned O under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 12 ¡V Vegetation on Modified Slopes |
1.2 ha |
|
|||||
12.1 |
Hang Hau Tsuen |
0.08 ha |
Medium |
Low |
Local |
High |
Low |
This LR comprises several
modified slopes along Deep Bay Road and Fung Kong Tsuen Road near LR6.2 -
Hang Hau Tsuen Nullah, in the north of the NDA. It also includes several vegetated
slopes circumscribing a large open storage yard in the vicinity of LR2.2 ¡V
Ngau Hom Hillside Woodland. These
slopes comprise hillsides with semi-mature vegetation and with various
scattered, self-seeded shrubs and trees growing on slopes. A total of approx.
16 trees have been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Celtis sinensis, Dimocarpus
longan, Ficus benjamina, Melia azedarach. |
|||||||
Zoning: This LR falls within
areas zoned CDA, V, and CPA under Ha Tsuen OZP S/YL-HT/10, areas zoned R(D),
R(E), and GB under Lau Fau Shan & Tsim Bei Tsui OZP S/YL-LFS/7. |
|||||||
12.2 |
Ha Tsuen |
0.2 ha |
Medium |
Low |
Local |
High |
Low |
This LR comprises
numerous modified slopes in the vicinity of KSWH where it crosses the
northern hills and connects to Deep Bay Bridge. It also includes several small slopes
in the vicinity of the San Wai Sewage Treatment Works (SW STW) and Ha Tsuen
Road. A total of approx. 27 trees have been identified within this LR; the
dominant species includes Leucaena
leucocephala, Acacia auriculiformis, Ficus microcarpa, Eucalyptus sp., Macaranga tanarius var. tomentosa, and Acacia confusa. |
|||||||
Zoning: This LR falls within
areas zoned AGR, GB, G/IC, and OS Ha Tsuen OZP S/YL-HT/10. |
|||||||
12.3 |
Yick Yuen Tsuen |
0.9 ha |
Medium |
Low |
Local |
High |
Low |
This LR comprises several
modified slopes in the vicinity of KSWH to the west of Yick Yuen Tsuen. The slopes cut into the
hillsides to make way for the highway and smaller roads branching off. A
total of approx. 94 trees have been identified within this LR; the dominant species
includes Leucaena leucocephala,
Eucalyptus citriodora, and
Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This LR falls within
areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
LR 14 ¡V Roadside Vegetation |
2.5 ha |
||||||
14.6 |
Ping Ha Road |
0.02 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises intermittent stands of trees
located along Ping Ha Road. While
not continuous along the entire roadway, this LR extends from Tin Wah Road in
the north to TSW Station in the south.
Vegetation consists of mature and semi-mature trees of various
species, some planted and others naturally colonised. A total of approx. 3
trees have been identified within this LR; the dominant species includes Ficus microcarpa, Ficus benjamina, Leucaena
leucocephala, Melaleuca cajuputi subsp. cumingiana, and Hibiscus tiliaceus. |
|||||||
Zoning: This LR falls within areas zoned R(A) and OU
under the TSW OZP S/TSW/12; areas zoned U under the Ping Shan OZP S/YL-PS/16;
and areas zoned V, U, G/IC, O, and CDA under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
14.8 |
Tin Ha Road |
0.4 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
intermittent stands of trees located along Tin Ha Road. While not continuous along the entire
roadway, this LR extends from Ping Ha Road to the north to Castle Peak Road
to the south. Vegetation consists
of mature and semi-mature trees of various species, some planted and others
naturally colonised. A total of approx. 45 trees have been identified within
this LR; the dominant species includes Ficus microcarpa, Macaranga tanarius var. tomentosa, Khaya senegalensis, and Dimocarpus longan. |
|||||||
Zoning: This LR falls within
areas zoned V and U under the Ha Tsuen OZP S/YL-HT/10; and areas zoned V and
R(C) under the Ping Shan OZP S/YL-PS/16. |
|||||||
14.10 |
Castle Peak Road |
1.5 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
intermittent stands of trees located along Castle Peak Road. While not continuous along the entire
roadway, this LR extends from Ping Shan to the east to Lam Tei to the west. Vegetation consists of mature and
semi-mature trees of various species, some planted and others naturally
colonised. Five identified
Important Trees, 1077-T1, 962-T1, 1202-T1, 1202-T2 & 1213A-T1, are located
within this LR adjacent to Castle Peak Road. The identified tree species are Ficus microcarpa, Melaleuca cajuputi subsp. Cumingiana, & Ficus elastica and all have very good
form and large size among trees of this species. A total of approx. 215 trees
have been identified within this LR; the dominant species includes Celtis sinensis, Melaleuca cajuputi subsp. cumingiana, Ficus microcarpa, Dimocarpus
longan, Albizia lebbeck, Leucaena leucocephala, Cinnamomum camphora. |
|||||||
Zoning: This LR falls within
areas zoned V, R(A), R(B), GB, CDA,
and I under the Ping Shan OZP S/YL-PS/16; areas zoned I, V, and G/IC
under the Tong Yan San Tsuen OZP S/YL-TYST/10; and areas zoned V, G/IC, and
R(C) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
14.12 |
Hung Shui Kiu Tin Sam
Road / Hung Yuen Road / |
0.1 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
intermittent stands of trees located along Hung Shui Kiu Tin Sam Road, Hung
Chi Road, Hung Kei Road, Hung Tai Road, and Hung Yuen Road. While not continuous along the roadways,
this LR covers roadways in the general San Lee Uk Tsuen area and extends
towards Castle Peak Road to the south.
Vegetation consists of mature and semi-mature trees of various
species, some planted and others naturally colonised A total of approx. 24
trees have been identified within this LR; the dominant species includes Livistona chinensis, Bauhinia purpurea, and Spathodea campanulata. |
|||||||
Zoning: This LR falls within
areas zoned V, R(A), R(B), and CDA under the Ping Shan OZP S/YL-PS/16. |
|||||||
14.13 |
Yick Yuen Road |
0.2 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
three intermittent stands of trees located along Yick Yuen Road. While not continuous along the
roadway, this LR extends from Castle Peak Road to the east to the alignment
to the west. Vegetation consists
of mature and semi-mature trees of various species, some planted and others
naturally colonised. One
identified Important Tree, 995-T1, is located within this LR adjacent to Yick
Yuen Road. The identified tree
species is Ficus elastica and is
potentially registrable as an OVT due it¡¦s large size and that this
particular tree has very good form and size among its own tree species. A
total of approx. 19 trees have been identified within this LR; the dominant
species includes Ficus
benjamina. |
|||||||
Zoning: This LR falls within
areas zoned U under the Ping Shan OZP S/YL-PS/16; and areas zoned G/IC, R(C),
and R(D) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
14.14 |
KSWH |
0.2 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
stands of trees located along KSWH and centred around the traffic islands
around the interchange with the Yuen Long Highway. While not continuous along the entire
roadway, this LR comprises several significant stands of trees located along
the roadway. Vegetation consists
of mature and semi-mature trees of various species, some planted and others
naturally colonised. One Important Tree, 1213-T1, is located in this LR. A
total of approx. 5 trees have been identified within this LR; the dominant
species includes Leucaena leucocephala,
Archontophoenix alexandrae, Clausena lansium, Bauhinia sp. |
|||||||
Zoning: This LR falls within
areas zoned GB, V, G/IC, and R(C) under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
LR 15 ¡V Water Bodies |
0.5 ha |
||||||
15.5 |
Sik Kong Tsuen |
0.3 ha |
High |
High |
Local |
Low |
High |
This LR comprises four
stormwater ponds located in the vicinity of Sik Kong Wai, Sik Kong Tsuen, and
Lo Uk Tsuen villages. The ponds are
located along the proposed heritage trail that runs through numerous villages
in San Wai and therefore have strong cultural ties to the villagers. Vegetation lines the banks and
primarily comprises shrubs and grasses and numerous stands of mature and semi-mature
trees. |
|||||||
Zoning: This LR falls within
areas zoned V under the Ha Tsuen OZP S/YL-HT/10 |
|||||||
15.6 |
Tseung Kong Wai |
0.2 ha |
Low |
Medium |
Local |
High |
Low |
This LR comprises one fishpond
located amongst various industrial storage/open air storage land uses at the
base of the northern hills of the NDA.
It is situated north of Ha Tsuen Road and has limited vegetation
around the perimeter. |
|||||||
Zoning: This LR falls within
areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
15.12 |
San Sang San Tseun |
0.32 ha |
Low |
Medium |
Local |
High |
Low |
This LR comprises of
one inactive fish pond located in the vicinity of San Sang San Tsuen and amongst
low-lying woodland/plantation land LR4.8 ¡V San Sang San Tsuen. It is located
west of Tin Ha Road and Tin Sam Channel. The fishpond is overgrown with
herbaceous species of vegetation. |
|||||||
Zoning: |
|||||||
This LR resides within
areas zoned GB under the Ping Shan OZP S/YL-PS/16 |
|||||||
LR 17 ¡V Marsh |
0.6 ha |
|
|||||
17.2 |
Fung Kong Tsuen |
0.6 ha |
High |
High |
Regional |
Low |
High |
This LR comprises a
moderate-sized marsh located adjacent LR5.3-Fung Kong Tsuen Low-lying Shrub
and Grassland. The marsh is
heavily influenced by development and likely evolved from abandoned
agriculture. A total of approx. 26 trees have been identified within this LR;
the dominant species includes Dimocarpus
longan, Litchi chinensis, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This LR resides
primarily within areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
LR 18 ¡V Important Trees |
N/A |
|
|||||
18 |
|
|
High |
High |
Regional |
Low |
High |
There are approximately
37 trees that are classified as ¡§Important Trees¡¨. Species include Ficus microcarpa, Ficus elastic, Bombax
ceiba, and Artocarpus nitidus subsp. lingnanensis, among others. Important trees are
located throughout the Project assessment area and identified within the
corresponding LR¡¦s above, contributing to the sensitivity rating of each LR
where present. Due to the ¡§Important
Trees¡¨ quality and natural status, its regional importance, and low tolerance
to change, the sensitivity given is High. |
Landscape Character Areas (LCAs)
¡P Scattered villages: predominately concentrated along the major traffic corridors (e.g. Castle Peak Road and Yuen Long Highway) at the south of the assessment area, consisting largely of low-rise buildings.
¡P Agricultural land: of approximately 50.57 ha within the Assessment area. This land is intended for the retention of fallow arable land with potential for rehabilitation for cultivation and other agricultural purposes. The agricultural land is located in the north of the assessment area directly south of Deep Bay Road, and in the south-southeast located between KSWH and Castle Peak Road.
¡P Open storage plots: are one of the largest current constituent land uses within the NDA planning area. Open storage is predominantly located in the northern portion of the NDA and it is estimated that over 200 ha of land is committed to this category of land use. The existence of open storage uses has significant implications for the assessment area as they contribute to the degradation of the rural living environment of the assessment area and its surrounding environs and creates is a general sense of transience and change about the landscape even though the traditional rural character predominates.
Table 11.4B Baseline
Landscape Character Areas (LCAs) (DP 9)
Landscape Character Area |
Description |
Sensitivity |
Baseline Area |
|
||||||
Quality &
Maturity (High, Medium,
Low) |
Rarity (High, Medium,
Low) |
Importance (Local, Regional,
National, Global) |
Ability to
Accommodate Change (Low, Medium, High) |
|
||||||
LCA1 |
Miscellaneous Rural Fringe Landscape |
|
||||||||
Medium |
Medium |
Local |
Medium |
Medium |
328 ha |
|||||
LCA2 |
Miscellaneous Urban Fringe Landscape |
|
||||||||
Medium |
Low |
Local |
Medium |
Medium |
0.04 ha |
|||||
LCA4 |
Upland and Hillside Landscape |
|
||||||||
High |
Medium |
Regional |
Low |
High |
71.2 ha |
|||||
Potential Sources of Landscape and Visual Impacts
¡P Site clearance works involving the removal of the existing Storage Containers and recreational facilities, as well as the removal of existing trees and shrub planting;
¡P Site formation works including cutting and filling
¡P Excavation works and haulage off-site of excavated materials;
¡P Storage of existing topsoil for reinstatement works;
¡P Importation and storage of construction equipment and plant;
¡P Materials stockpiling;
¡P Construction of site access;
¡P Temporary Traffic Management activities;
¡P Construction of the temporary parking areas, on-site accommodation offices & structures and working areas, importation and storage of equipment and materials;
¡P Construction of four nos. of SPS at 15 m height;
¡P Re-alignment of streams and watercourses
¡P Dust and construction debris;
¡P The laying down of utilities, including water, drainage and power; and
¡P Night lighting.
¡P Operation of four nos. of SPS at 15 m height; and
¡P Residual impacts from loss of trees and vegetation during the construction phase.
Nature and Magnitude of Landscape change Before Mitigation in Construction Phase
Nature and Magnitude of Landscape change Before Mitigation in Operation Phase
Table 11.5B Magnitude of Landscape Change during the Construction and Operation Phases before Mitigation (DP 9)
ID No. |
LRs/ LCAs |
Source of Impact |
Description of Impacts |
Compatibility of the Project with the
Surrounding Landscape (High, Medium, Low) |
Duration of Impact (None, Temporary (Short,
Medium, Long-term); Permanent, Reversible; Permanent, Irreversible) |
Magnitude of Change (None, Negligible, Small, Intermediate, Large) |
|||
LR2 Natural Hillside Woodland |
|||||||||
LR2.4 |
Ngau
Hom Shek |
None |
None -
Baseline vegetation
coverage is approx. 8.8 ha |
N/A |
None |
None |
|||
LR2.6 |
Tung
Tau Tsuen |
None |
None -
Baseline vegetation coverage
is approx. 1.3 ha |
N/A |
None |
None |
|||
LR2.7 |
Ha
Tsuen Road |
None |
None -
Baseline vegetation
coverage is approx. 0.3 ha |
N/A |
None |
None |
|||
LR2.8 |
Ha
Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 1.2 ha |
N/A |
None |
None |
|||
LR2.9 |
Yuen
Tau Tsuen |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.13 ha -
Baseline vegetation coverage
is approx. 29.4 ha -
Change of landscape
quality -
A total of approx. 6
trees are impacted |
Medium |
Permanent, Irreversible |
Small |
|||
Operation -
New sewage pumping
station and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from
loss of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
LR2.11 |
Kau
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx.2.9 ha |
N/A |
None |
None |
|||
LR2.12 |
San
Sang Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 2.9 ha |
N/A |
None |
None |
|||
LR3 Natural Hillside Shrub & Grassland |
|||||||||
LR3.3 |
Ngau
Hom Shek |
None |
None -
Baseline vegetation
coverage is approx. 2.4 ha |
N/A |
None |
None |
|||
LR3.4 |
Yuen
Tau Shan |
None |
None -
Baseline vegetation
coverage is approx. 22.9 ha |
N/A |
None |
None |
|||
LR3.5 |
Kau
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.2 ha |
N/A |
None |
None |
|||
LR3.6 |
Hung
Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.2 ha |
N/A |
None |
None |
|||
LR4 Low-lying Woodland/Plantation |
|||||||||
LR4.8 |
San
Sang San |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.25 ha. -
Baseline vegetation
coverage is approx. 15.8 ha -
Change of landscape
quality -
A total of approx. 10
trees are impacted |
Medium |
Permanent, Irreversible |
Small |
|||
Operation -
New sewage pumping
station and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from
loss of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
LR4.12 |
Powerline
Pylon |
None |
None -
Baseline vegetation coverage
is approx. 0.3 ha |
N/A |
None |
None |
|||
LR5 Grassland |
|||||||||
LR5.3 |
Fung
Kong Tsuen |
None |
None -
Baseline vegetation
coverage is approx.7.0 ha |
N/A |
None |
None |
|||
LR5.5 |
San
Wai |
None |
None -
Baseline vegetation
coverage is approx. 1.4 ha |
N/A |
None |
None |
|||
LR5.6 |
San
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.7 ha |
N/A |
None |
None |
|||
LR5.7 |
San
Sang Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.5 ha |
N/A |
None |
None |
|||
LR5.8 |
Chung
Uk Tsuen |
None |
None -
Baseline vegetation coverage
is approx. 1.2 ha |
N/A |
None |
None |
|||
LR5.9 |
Yick
Yuen Tsuen |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.002 ha. -
Baseline vegetation
coverage is approx. 12.4 ha -
Change of landscape
quality |
Medium |
Permanent, Irreversible |
Negligible |
|||
Operation -
New sewage pumping station
and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from
loss of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
LR5.11 |
Tsing
Chuen Wai |
None |
None -
Baseline vegetation
coverage is approx. 0.4 ha |
N/A |
None |
None |
|||
LR6 Vegetation on Agricultural Land |
|||||||||
LR6.3 |
Ha
Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 3.7 ha |
N/A |
None |
None |
|||
LR6.5 |
Shek
Po Tsuen |
None |
None -
Baseline vegetation coverage
is approx. 1.2 ha |
N/A |
None |
None |
|||
LR6.6 |
San
Sang San Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 19.3 ha |
N/A |
None |
None |
|||
LR6.10 |
Tin
Sam |
None |
None -
Baseline vegetation
coverage is approx. 1.8 ha |
N/A |
None |
None |
|||
LR6.11 |
Yick
Yuen Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 2.1 ha |
N/A |
None |
None |
|||
LR7 Vegetation within Residential Developments |
|||||||||
LR7.2 |
Developments
along Castle Peak Road |
None |
None -
Baseline vegetation
coverage is approx. 0.3 ha |
N/A |
None |
None |
|||
LR8 Vegetation within Rural Residential |
|||||||||
LR8.5 |
Sik
Kong Tsuen / Hong Mei Tsuen /
Tsueng Kong Wai |
None |
None -
Baseline vegetation
coverage is approx. 3.2 ha |
N/A |
None |
None |
|||
LR8.6 |
Sik
Kong Wai / San Uk Tsuen / Ha Tsuen Shi |
None |
None -
Baseline vegetation
coverage is approx. 0.3 ha |
N/A |
None |
None |
|||
LR8.11 |
San
Sang Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 3.4 ha |
N/A |
None |
None |
|||
LR8.12 |
San
Lee Uk Tsuen / Tim Sam |
None |
None -
Baseline vegetation
coverage is approx. 2.2 ha |
N/A |
None |
None |
|||
LR8.13 |
Hung
Shui Kiu |
None |
None -
Baseline vegetation
coverage is approx. 0.2 ha |
N/A |
None |
None |
|||
LR8.14 |
Tim
Sam |
None |
None -
Baseline vegetation
coverage is approx. 6.8 ha |
N/A |
None |
None |
|||
LR8.17 |
Tan
Kwei Tsuen |
None |
None -
Baseline vegetation coverage
is approx. 0.8 ha |
N/A |
None |
None |
|||
LR8.18 |
Wo
Ping San Tsuen / Cheung Uk Tsuen / Arkadia |
None |
None -
Baseline vegetation
coverage is approx. 11.2 ha |
N/A |
None |
None |
|||
LR8.19 |
Yick
Yuen Tsuen |
Construction -
Site clearance works -
Presence of construction
equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.04 ha -
Baseline vegetation
coverage is approx. 11.9 ha -
Change of landscape quality -
A total of approx. 2
trees are impacted |
Medium |
Permanent, Irreversible |
Small |
|||
Operation -
New sewage pumping
station and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from loss
of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
LR8.20 |
Tsing
Chuen Wai / Tuen Tsz Wai |
None |
None -
Baseline vegetation
coverage is approx. 1.3 ha |
N/A |
None |
None |
|||
LR8.21 |
Lam Tei
/ Tuen Mun San Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.05 ha |
N/A |
None |
None |
|||
LR9 Vegetation within Industrial Land / Open
Storage |
|||||||||
LR9.3 |
Ping
Ha Road |
None |
None -
Baseline vegetation
coverage is approx. 0.3 ha |
N/A |
None |
None |
|||
LR9.7 |
Tseung
Kong Wai |
None |
None -
Baseline vegetation
coverage is approx. 9.6 ha |
N/A |
None |
None |
|||
LR9.9 |
Ha
Tsuen Road |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.001 ha. -
Baseline vegetation
coverage is approx. 9.6 ha. -
Change of landscape
quality |
Medium |
Permanent, Irreversible |
Negligible |
|||
Operation -
New sewage pumping
station and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from
loss of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
LR9.11 |
Sik Kong
Wai Road / Ha Tsuen Road |
None |
None -
Baseline vegetation
coverage is approx. 1.1 ha |
N/A |
None |
None |
|||
LR9.16 |
San
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.7 ha |
N/A |
None |
None |
|||
LR9.17 |
Kau Lee Uk Tsuen / San Sang Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 9.7 ha |
N/A |
None |
None |
|||
LR9.18 |
Yick
Yuen Road |
None |
None -
Baseline vegetation
coverage is approx. 1.2 ha |
N/A |
None |
None |
|||
LR10 Water Course |
|||||||||
LR10.5 |
Sik
Kong Tsuen / Tsueng Kong Wai Nullah |
None |
None -
Baseline nullah area is
approx. 0.3 ha |
N/A |
None |
None |
|||
LR10.6 |
Sik
Kong Wai / Ling To Nullah |
None |
None -
Baseline nullah area is
approx. 0.2 ha |
N/A |
None |
None |
|||
LR10.7 |
Yuen
Tau Shan Streams & Nullah |
None |
None -
Baseline nullah area is
approx. 0.1 ha |
N/A |
None |
None |
|||
LR10.10 |
Shek
Po Channel |
None |
None -
Baseline water area is
approx. 0.7 ha |
N/A |
None |
None |
|||
LR10.11 |
Tin
Sam Channel |
None |
None -
Baseline water area is
approx. 1.9 ha |
N/A |
None |
None |
|||
LR10.12 |
San
Sang San Tsuen Channel |
None |
None -
Baseline water area is
approx. 0.5 ha |
N/A |
None |
None |
|||
LR10.13 |
Yick
Yuen Tsuen / Tsign Chuen Wai Nullah |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no. SPS
developments -
Night lighting |
Construction -
Loss of nullah area of
approx. 0.02 ha. -
Baseline nullah area is
approx. 0.4 ha -
Change of landscape
quality |
Medium |
Permanent, Irreversible |
Small |
|||
Operation -
New sewage pumping station
and associated infrastructure replacing existing vegetation |
Operation -
Loss of nullah area -
Residual impacts from
loss of nullah area due to the replacement with new sewage pumping station
and associated infrastructure |
||||||||
LR11 Vegetation with Urban Park |
|||||||||
LR11.4 |
Tin Ha Road Playground |
None |
None -
Baseline vegetation
coverage is approx. 0.4 ha |
N/A |
None |
None |
|||
LR11.5 |
Nai Wai Soccer Pitch / Fuk Hang Tsuen Road Garden |
None |
None -
Baseline vegetation
coverage is approx. 0.5 ha |
N/A |
None |
None |
|||
LR12 Vegetation on Modified Slopes |
|||||||||
LR12.1 |
Hang
Hau Tsuen |
None |
Construction -
Baseline vegetation
coverage is approx. 0.08 ha |
N/A |
None |
None |
|||
LR12.2 |
Ha
Tsuen |
None |
Construction -
Baseline vegetation
coverage is approx. 0.2 ha |
N/A |
None |
None |
|||
LR12.3 |
Yick
Yuen Tsuen |
None |
Construction -
Baseline vegetation
coverage is approx. 0.9 ha |
N/A |
None |
None |
|||
LR14 Roadside Vegetation |
|||||||||
LR14.6 |
Ping
Ha Road |
None |
None -
Baseline vegetation
coverage is approx. 0.02 ha |
N/A |
None |
None |
|||
LR14.8 |
Tin
Ha Road |
None |
None -
Baseline vegetation
coverage is approx. 0.4 ha |
N/A |
None |
None |
|||
LR14.10 |
Castle
Peak Road |
None |
None -
Baseline vegetation
coverage is approx. 1.5 ha |
N/A |
None |
None |
|||
LR14.12 |
Hung
Shui Kiu Tin Sam Road / Hung Yuen Road |
None |
None -
Baseline vegetation
coverage is approx. 0.1 ha |
N/A |
None |
None |
|||
LR14.13 |
Yick
Yuen Road |
None |
None -
Baseline vegetation
coverage is approx. 0.2 ha |
N/A |
None |
None |
|||
LR14.14 |
KSWH |
None |
None -
Baseline vegetation
coverage is approx. 0.2 ha |
N/A |
None |
None |
|||
LR15 Water Bodies |
|||||||||
LR15.5 |
Sik
Kong Tsuen |
None |
None -
Baseline water area is
approx. 0.3 ha |
N/A |
None |
None |
|||
LR15.6 |
Tseung
Kong Wai |
None |
None -
Baseline water area is
approx. 0.2 ha |
N/A |
None |
None |
|||
LR 15.12 |
San
Sang San Tseun |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Sewage Pumping Station Site 3-41 |
Construction -
Loss of water area
ofapprox. 0.3ha -
Baseline water area
isapprox. 0.3ha |
Low |
Permanent, Irreversible |
Large |
|||
Operation New sewage pumping station and associated
infrastructure replacing existing water body |
Operation Residual impacts from loss of water area due to
the replacement with new sewage pumping station and associated infrastructure |
||||||||
LR17 Marsh |
|||||||||
LR 17.2 |
Fung Kong Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.6ha |
N/A |
None |
None |
|||
Landscape Character Areas |
|||||||||
LCA1 |
Miscellaneous Rural Fringe Landscape |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.68 ha. -
Baseline vegetation
coverage is approx. 328.00 ha -
Change of landscape
quality |
Medium |
Permanent, Irreversible |
Small |
|||
Operation -
New sewage pumping
station and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from
loss of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
LCA2 |
Miscellaneous
Urban Fringe Landscape |
None |
Construction -
No physical change to
the LCA2 -
Baseline vegetation
coverage is approx. 0.04 ha |
N/A |
None |
None |
|||
LCA4 |
|
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of 4 no.
SPS developments -
Night lighting |
Construction. -
Loss of vegetation of
approx. 0.2 ha. -
Baseline vegetation
coverage is approx. 71.15 ha -
Change of landscape
quality |
Low |
Permanent, Irreversible |
Small |
|||
Operation -
New sewage pumping
station and associated infrastructure replacing existing vegetation |
Operation -
Residual impacts from
loss of vegetation due to the replacement with new sewage pumping station and
associated infrastructure |
||||||||
Table 11.6B Proposed Construction Phase Landscape and Visual Mitigation Measures (DP 9)
ID No. |
Landscape and Visual Mitigation Measures |
Capital Funding Agency |
Implementation Agency** |
CM1 |
Minimised construction
area and contractor¡¦s temporary works areas The
construction area and contractor¡¦s temporary works areas should be minimised. General Good Practice Measures - For areas unavoidably disturbed by the Project on a short-term basis e.g. works areas, the general principle to try and restore these to their former state to suit future land use, should be adhered to. |
DSD |
DSD |
CM3 |
Protection
of existing trees Tree
Protection & Preservation ¡V Exiting trees to be retained within the
Project Site should be carefully protected during construction. Detailed Tree
Protection Specification shall be provided in the Contract Specification.
Under this specification, the Contractor shall be required to submit, for
approval, a detailed working method statement for the protection of trees
prior to undertaking any works adjacent to all retained trees, including
trees in Contractor¡¦s works areas. A detailed tree survey will be carried out for the Tree Removal Application (TRA) process which will be carried out at the later detailed design stage of the Project. The detailed tree survey will propose which trees should be retained, transplanted or felled and will include details of tree protection measures for those trees to be retained. |
DSD |
DSD |
CM4 |
Transplantation
of existing trees where practical Trees unavoidably affected by the Project works should be transplanted where practical. Trees should be transplanted straight to their final receptor site and not held in a temporary nursery as far as possible. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, where applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the Project programme. A detailed
transplanting proposal will be submitted to relevant Government departments
for approval in accordance with DEVB TCW Nos 6/2015 and 7/2015 and final
locations of transplanted trees should be agreed prior to commencement of the
work. For trees associated with highways e.g. roadside planting along highways, that are unavoidably affected and should be transplanted, HyD HQ/GN/13 ¡¥Interim Guidelines for Tree Transplanting Works under Highways Department's Vegetation Maintenance Ambit¡¦ should be referred to. |
DSD |
DSD |
CM5 |
Control of night-time lighting Control of night-time lighting and glare by hooding all lights. Construction day and night time lighting should be controlled to
minimise glare impact to adjacent VSRs during the construction phase. |
DSD |
DSD |
CM6 |
Construction of decorative hoarding around construction works Erection of decorative mesh screens or construction hoardings around
works areas in visually unobtrusive colours. Screen hoarding shall be erected along areas of the construction works
site boundary where the works site borders publically accessible routes
and/or is close to visually sensitive receivers (VSRs). It is proposed that
the screening be compatible with the surrounding environment and where
possible, non-reflective, recessive colours be used. |
DSD |
DSD |
CM7 |
Reduction of construction period to practical minimum Options to reduce the construction period to practical minimum to be
provided. |
DSD |
DSD |
CM10 |
Advance screen planting Advance screen planting of fast growing tree and shrub species to
noise barriers and hoardings. Trees shall be capable of reaching a height
>10m within 10 years. |
DSD |
DSD |
CM11 |
Minimise disturbance footprints To minimise landscape and visual impacts, the footprint and elevation
of such elements should be optimised to reduce topographical/ landform
changes, as well as reduce land take and interference with natural terrain.
Where there is a need to significantly cut into the existing landform,
retaining walls should be considered as well as cut slopes, to minimise
landform changes and land resumption, while also considering visual amenity.
Earthworks and engineered slopes should be designed to be a visually
interesting landform, compatible with the surrounding landscape and to mimic
the natural contouring and terrain e.g. introduction and continuation of
natural features such as spurs and ridges where appropriate, to support
assimilation with the hillside setting. |
DSD |
DSD |
*Management and
Maintenance Agencies are identified as per DEVB TCW No. 6/2015. Agreement from individual
agent shall be sought at the detailed design stage before commencement of the
contract.
**CEDD will only be responsible for
construction of the site formation and essential infrastructure
Note: The Contractor shall be responsible for the
maintenance of the soft landscape works during the establishment period at
operation phase. The project proponent shall then be responsible for the
management and maintenance of the soft landscape work until such time those are
successfully handed over to the designated agent/department.
Table 11.7B Proposed Operation Phase Landscape and Visual Mitigation Measures
ID No. |
Landscape and Visual Mitigation Measures |
Capital Funding Agency |
Implementation Agency |
Management Agency* |
Maintenance Agency* |
OM1 |
Compensatory tree planting where practical Compensatory Planting ¡V Compensatory tree planting for felled trees
shall be provided to the satisfaction of relevant Government departments.
Required numbers and locations of compensatory trees shall be determined and
agreed separately with Government during the Tree Removal Application process
under ETWBTC 7/2015. Compensatory planting is proposed at the potential open areas such as
open spaces, amenity areas, open areas of the streetscapes, as well as the
open areas within development lots. Tree compensation within the HSK NDA will be provided at a 1:1 ratio.
This means that for every tree that is removed, a new one will be planted.
Furthermore, trees affected by DPs will be compensated within their
respective DP areas. |
DSD |
DSD |
DSD |
DSD |
OM2 |
Sensitive design of above-ground structures All above-ground structures, including Sewage Pumping Stations,
Electrical Sub-Stations, EFLS Stations, Emergency and Firemen¡¦s¡¦ Accesses,
etc. shall be sensitively designed in a manner that responds to the existing
and planned urban context. The footprint and massing of development components and the works area
should also be kept to a practical minimum and the detailed design of
development components for construction phase should follow the Sustainable
Building Design Guidelines. The form, textures, finishes and colours of the
proposed development components should aim to be compatible with the existing
surroundings. To improve visual amenity designs should be aesthetically pleasing
and treatment of structures also improve visual amenity. |
DSD |
DSD |
DSD |
DSD |
OM5 |
Visual softening via soft landscape elements Attractive soft landscape in areas adjoining Sewage Pumping Stations, Electrical Sub-Stations, EFTS Stations, Emergency and Firemen¡¦s¡¦ Accesses, etc. (taking into account the necessary setbacks) so as to provide a visual softening and greening effect (e.g. provision of tree / shrub / climber planting). |
DSD |
DSD |
DSD |
DSD |
OM8 |
Sensitive and chromatic treatment of architectural
facades Elegant architectural and engineering design, sensitive architectural and chromatic treatment for building facades. The form, textures, finishes and colours of the proposed development components should aim to be compatible with the existing surroundings. To improve visual amenity designs should be aesthetically pleasing and treatment of structures also improve visual amenity. For example, natural building materials such as stone and timber, should be considered for architectural features, and light earthy tone colours such as shades of green, shades of grey, shades of brown and off-white should also be considered to reduce the visibility of the development components. |
DSD |
DSD |
DSD |
DSD |
OM11 |
Tree planting to site boundaries Tree planting screens along appropriate site boundaries |
DSD |
DSD |
DSD |
DSD |
OM12 |
Night time lighting Control of lighting glare. A balance between lighting for safety, and avoiding excessive lighting can be achieved through consideration of the following: the type of lamp (light source) used; use of directional lighting to avoid light spill into sensitive areas; height of the lighting column can affect the amount/extent of glare; and control/timing of lighting periods of some facilities, particularly those close to sites of conservation importance. |
DSD |
DSD |
DSD |
DSD |
OM13 |
Green roofs and vertical greening Green roofs and vertical greening provision of green roofs and vertical greening where feasible and appropriate to mitigate visual impacts of buildings and structures |
DSD |
DSD |
DSD |
DSD |
*Management and
Maintenance Agencies are identified as per DEVB TCW No. 6/2015. Agreement from individual
agent shall be sought at the detailed design stage before commencement of the
contract.
Note: The Contractor shall be responsible for the
maintenance of the soft landscape works during the establishment period at
operation phase. The project proponent shall then be responsible for the management
and maintenance of the soft landscape work until such time those are
successfully handed over to the designated agent/department.
Programme of Implementation of Landscape and Visual Mitigation Measures
Table 11.8B Significance of Landscape Impacts in Construction and Operation Phases (DP 9)
ID No. |
Landscape
Resources / Landscape Character |
Sensitivity (Low, Medium, High) |
Magnitude of Change (None,
Negligible, Small, Intermediate, Large)* |
Impact Significance BEFORE Mitigation (None,
Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance AFTER Mitigation (None,
Insubstantial, Slight, Moderate, Substantial) |
|
|||||||
|
Construction |
Operation |
|
|||||||||||
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
|
||||||||
LR2
Hillside Woodland |
|
|||||||||||||
2.4 |
Ngau
Hom Shek |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
2.6 |
Tung
Tau Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
2.7 |
Ha
Tsuen Road |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
2.8 |
Ha
Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
2.9 |
Yuen
Tau Tsuen |
High |
Small |
Small |
Slight |
Slight |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Slight |
Slight |
Insubstantial |
|
|||
2.11 |
Kau
Lee Uk Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
2.12 |
San
Sang Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR3
Hillside Shrub & Grassland |
|
|||||||||||||
3.3 |
Ngau
Hom Shek |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
3.4 |
San
Sang Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
3.5 |
Kau
Lee Uk Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
3.6 |
Hung
Uk Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR4
Low-lying Woodland/Plantation |
|
|||||||||||||
4.8 |
San
Sang San |
High |
Small |
Small |
Moderate |
Moderate |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Moderate |
Moderate |
Slight |
|
|||
4.12 |
Powerline
Pylon |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR5
Grassland |
|
|||||||||||||
5.3 |
Fung
Kong Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
5.5 |
San
Wai |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
5.6 |
San
Lee Uk Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
5.7 |
San
Sang Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
5.8 |
Chung
Uk |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
5.9 |
Yick
Yuen Tsuen |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
|
|||
5.11 |
Tsing
Chuen Wai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR6
Vegetation on Agricultural Land |
|
|||||||||||||
6.3 |
Ha
Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
6.5 |
Shek
Po Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
6.6 |
San
Sang San Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
6.10 |
Tin
Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
6.11 |
Yick
Yuen Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
LR7
Vegetation within Residential Developments |
|
|||||||||||||
7.2 |
Developments
along Castle Peak Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR8
Vegetation within Rural Village |
|
|||||||||||||
8.5 |
Sik
Kong Tsuen/ Hong Mei Tsuen/ Tseung Kong Wai |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.6 |
Sik
Kong Wai / San Uk Tsuen / Ha Tsuen Shi |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.11 |
San
Sang Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.12 |
San
Lee Uk Tsuen / Tim Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.13 |
Hung
Shui Kiu |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.14 |
Tim
Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.17 |
Tan
Kwei Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.18 |
Wo
Ping San Tsuen / Cheung Uk Tsuen / Arkadia |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.19 |
Yick
Yuen Tsuen |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Slight |
Slight |
Insubstantial |
|
|||
8.20 |
Tsing
Cheun Wai / Tuen Tsz Wai |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
8.21 |
Fuk
Hang Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR9
Vegetation within Industrial Land / Open Storage |
|
|||||||||||||
9.3 |
Ping
Ha Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
9.7 |
Tseung
Kong Wai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
9.9 |
Ha
Tsuen Road |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
|
|||
9.11 |
Sik
Kong Wai Road / Ha Tsuen Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
9.16 |
San
Lee Uk Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
9.17 |
Kau Lee Uk Tsuen / San Sang Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
9.18 |
Yick
Yuen Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
9.19 |
KSWH
South |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR10
Water Course |
|
|||||||||||||
10.5 |
Sik
Kong Tsuen / Tsueng Kong Wai Nullah |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
10.6 |
Sik
Kong Wai / Ling To Nullah |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
10.7 |
Yuen
Tau Shan Streams |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
10.10 |
Shek
Po Channel |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
10.11 |
Tin
Sam Channel |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
10.12 |
San
Sang San Tsuen Channel |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
10.13 |
Yick
Yuen Tsuen / Tsing Chuen Wai Nullah |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Slight |
Slight |
Insubstantial |
|
|||
LR11
Vegetation within Urban Park |
|
|||||||||||||
11.4 |
Tin
Ha Road Playground |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
11.5 |
Nai
Wai Soccer Pitch / Fuk Hang Tsuen Road Garden |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||
LR12
Vegetation on Modified Slopes |
|
|||||||||||||
12.1 |
Hang
Hau Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
12.2 |
Ha
Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
12.3 |
Yick
Yuen Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR14
Roadside Vegetation |
|
|||||||||||||
14.6 |
Ping
Ha road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
14.8 |
Tin
Ha Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
14.10 |
Castle
Peak Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
14.12 |
Hung
Shui Kiu Tin Sam Road / Hung Yuen Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
14.13 |
Yick
Yuen Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
14.14 |
KSWH |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LR15
Water Bodies |
|
|||||||||||||
15.5 |
Sik Kong
Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
15.6 |
Tseung
Kong Wai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
15.12 |
San Sang San Tsuen |
Low |
Large |
Large |
Moderate |
Moderate |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Moderate |
Moderate |
Slight |
|
|||
LR17
Marsh |
|
|||||||||||||
17.2 |
Fung Kong Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
Landscape
Character Areas |
|
|||||||||||||
LCA1 |
Miscellaneous Rural Fringe Landscape |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Slight |
Slight |
Insubstantial |
|
|||
LCA2 |
Miscellaneous
Urban Fringe Landscape |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
|
|||
LCA4 |
|
High |
Small |
Small |
Slight |
Slight |
CM1, 3, 4, 7,
8, 10, 11, 12, 13 OM1, 5, 11, 13 |
Slight |
Slight |
Insubstantial |
|
|||
Zone of Visual Influence (ZVI)
¡P TSW River Channel, Tim Sam Channel, and Shek Po Channel
¡P Ridgelines of Yuen Tau Shan, along the northern boundary of the Project, and to the south of the Project
¡P Several scattered vegetated woodland hillsides rising above the valley bottom
¡P TSW Promenade and associated vegetation
¡P Vegetation associated with rural agriculture and village areas
¡P Ling To Temple and nearby valley environment
¡P Scattered, haphazard areas of light industrial sheds, buildings, and storage yards
¡P Haphazard placement of port back up storage yards
¡P Presence of and traffic along the KSWH, Yuen Long Highway, and Castle Peak Road
Visually Sensitive Receivers (VSRs)
¡P Type of VSR. VSRs are categorised according to whether the viewer is at home, at work or school, at play or leisure, or travelling. (Ranked by the major VSR types, as described below)
- Residential VSRs ¡V These VSRs are people living in the area and who view the proposed NDA from their homes. They are considered the most sensitive VSRs due to the character of the view from their homes having a substantial effect on their perception of quality and acceptability of their home environment and general quality of life.
- Occupational VSRs ¡V These VSRs are people working or in education in the area, who view the proposed NDA from their workplace or education centre. Visual amenity is in general not considered a top priority within the average workplace and these VSRs are considered to be relatively less sensitive than residential VSRs as their view will have a less important, although still material, effect on their perception of quality of life. The degree to which this applies to workers depends on whether their location is industrial, retail or commercial. The VSRs in industrial areas, such as factories, are generally considered to be the least sensitive, due to the relatively low quality of their existing view in an industrial area.
- Recreational VSRs ¡V These VSRs are people engaging in recreational activities such as hikers on established trails and footpaths, people participating in team sports at recreation grounds or at leisure. Sensitivity of these VSRs depends on duration of stay, nature of the activity and how enclosed the location is.
- Travelling VSRs ¡V These VSRs are people travelling on public roads and railways, both in public and private vehicles and on foot. They have varying sensitivity depending on the speed, nature and frequency of travel, but are generally considered to be transitory to the area with less regard for the surrounding views and with low sensitivity.
¡P Number of Individuals (Ranked as very many, many, few or very few)
¡P Higher number of individuals within a VSR contributes to an increase in the level of sensitivity for that VSR
¡P Quality of Existing View (Ranked as good, fair or poor)
¡P Good quality existing views contribute to an increase in the levels of sensitivity for that VSR, while poor quality views contribute to a decrease
¡P Availability of Alternative Views (Ranked as yes or no)
¡P The absence of alternative views contributes to an increase in sensitivity for the respective VSR as the importance of the existing view is heightened
¡P Degree of visibility / distance between VSR & nearest source(s) of impact (Ranked as full, partial or obscured)
¡P VSRs with full views have a greater exposure than partial and obscured views, and this contributes to an increased level of sensitivity, as does the VSR¡¦s proximity to the nearest source of impact
¡P Duration of View (Ranked temporary or permanent)
¡P VSRs with permanent duration of views have a longer exposure than those with a temporary duration, contributing to an increased level of sensitivity
¡P Frequency of View (Ranked intermittent or continuous)
¡P VSRs with a continuous frequency of views have a higher awareness than those with an intermittent duration, contributing to an increased level of sensitivity.
High:
The VSR is highly sensitive to any change in the viewing experience (e.g.
residential, recreational and travelling VSRs where the principle view is of
the development site, formalised public viewpoints or the landscape);
Medium:
The VSR is moderately sensitive to any change in the viewing experience (e.g.
residential, recreational, occupational and travelling VSRs where the secondary
view is of the development); and
Low: The VSR is slightly sensitive to
any change in the viewing experience (e.g. VSRs travelling through the
landscape, residential and recreational VSRs who are far away, and occupational
VSRs for whom the view does not significantly impact the experience of place).
Table 11.9B Sensitivity of VSRs (DP9)
VSR ID |
Key VSR |
Number
of Individuals (Very Few, Few, Many, Very Many) |
Quality of Existing View (Good,
Fair, Poor) |
Availability of
Alternative Views (Yes / No) |
Duration and Frequency of Views to Source(s) of
Impact (Temporary/Permanent
& Intermittent/Continuous) |
Degree of Visibility of Source(s) of Visual Impact (Full, Partial,
Obscured) & Distance
Between VSR & Nearest Source(s) of Impact |
Sensitivity of the VSR (High/
Medium/Low) |
|||||
Construction |
Operation |
Construction |
Operation |
|||||||||
RES-3 |
Residents in Fung Kong Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured,
550 m |
Obscured,
550 m |
Medium |
|||
RES-4 |
Residents in Lo Uk Tsuen, Hong Mei Tsuen, San Wai, Sik Kong Tsuen, and
Tung Tau Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured,
300 m |
Obscured,
300 m |
High |
|||
RES-9 |
Residents in Sun Fung Wai |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured,
200 m |
Obscured,
200 m |
Medium |
|||
RES-11 |
Residents in Shek Po Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured,
600 m |
Obscured,
600 m |
Medium |
|||
RES-12 |
Residents in San Sang Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial,
130 m |
Obscured,
130 m |
High |
|||
RES-47 |
Residents in Sunny Villas, Tseung Kong Wai, Sik Kong Wai, Ha Tsuen Shi, and San Uk Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Full,
100 m |
Full,
100 m |
High |
|||
REC-1 |
Hikers along Castle Peak Trails |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial,
~0-6150 m |
Partial,
~0-6150 m |
High |
|||
REC-8 |
Hikers along the Hillside north of the NDA |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial,
500-1500 m |
Obscured,
500-1500 m |
Medium |
|||
T-1 |
Motorists along KSWH |
Many |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Full,
0 m |
Full,
0 m |
Medium |
|||
T-2 |
Users of the MTR between TSW and Siu Hong Station |
Many |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Full,
0 m |
Full,
0 m |
Medium |
|||
T-5 |
Motorists along Castle Peak Road |
Many |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured,
180 m |
Obscured,
180 m |
Medium |
|||
T-6 |
Motorists along Ping Ha Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured,
650 m |
Obscured,
650 m |
Low |
|||
T-7 |
Motorists along Tin Ha Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial,
120 m |
Full,
120 m |
Medium |
|||
T-8 |
Motorists along Shek Po Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured,
180 m |
Obscured,
180 m |
Low |
|||
T-17 |
Cyclists along Castle Peak Road |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured,
120 m |
Obscured,
120 m |
High |
|||
T-18 |
Cyclists along Tin Ha Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial,
120 m |
Full,
120 m |
High |
|||
T-19 |
Cyclists along Shek Po Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured,
530 m |
Obscured,
530 m |
Medium |
|||
T-20 |
Cyclists along Ping Ha Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured,
650 m |
Obscured,
650 m |
Medium |
|||
O-22 |
Workers in Industrial Area of Ha Tsuen |
Few |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured,
530 m |
Obscured,
530 m |
Low |
|||
|
|
|
|
|||||||||
|
|
|
|
|||||||||
Potential Sources of Visual Impacts
¡P Compatibility of the Project with the Visual Backdrop: A ranking of High, Medium or Low is assigned according to the compatibility of the Project with the Visual Backdrop. Compatibility is determined by the visual consistency, proportion, scale, colour, texture, form of the Project in relation to what is presently available in forming the Visual Backdrop for the VSR. The Visual Backdrop may be made up of the surrounding landscape, geological features, waterways, and urban skyline that is viewable from the VSR;
¡P Duration and Frequency of Impact: A ranking of Temporary or Permanent define the duration of impact, while Intermittent and Continuous define the frequency. These are assigned according to the amount of time during which the VSR experiences the impact of the project;
Temporary: The impacts of the Project on the VSR are experienced for a finite duration; the Project will not always be visible;
Permanent: The impacts of the Project on the VSR are to remain constant; the Project will always be visible;
Intermittent: The impacts of the Project on the VSR are interrupted at times, occurring within discreet events; the Project will not be continually visible;
Continuous: The impacts of the Project on the VSR are experienced over an ongoing frequency; the Project will be continually visible.
¡P Scale of Development: A ranking of Large, Medium or Small is assigned according to the relative size, height and span of the Project;
¡P Reversibility of Change: A ranking of Yes or No is assigned according to whether the Project is Permanent or Temporary;
¡P Degree of Visibility of Sources of Visual Impact: A ranking of Full, Partial or Obscured is assigned according to the visibility of the Project, as a function of distance from the VSR and/or the absence/presence of any obstructions, such as existing structures or landscape elements, which may inhibit visibility. (For example, the Project may be located immediately adjacent to a VSR, but its visibility may be inhibited by the presence of existing tall buildings located between the VSR and the Project.):
Full: The Project is fully visible to the
VSR as a function of distance and/or the absence of any obstructions;
Partial: The Project is only partially visible
to the VSR as a function of distance and/or the presence of obstructions;
Obscured: The Project is mostly hidden or
concealed from the VSR as a function of distance and/or the presence of
obstructions.
¡P Distance Between VSR & Nearest Sources of Impact: The approximate distance between the VSR and the nearest source of impact as part of the Project (for example, a building or noise barrier) is indicated in metres;
¡P
Potential
Blockage of Existing View: A ranking of Full, Partial, Slight, Negligible
or None is assigned in an effort to anticipate the impact of the Project on the
VSR¡¦s existing view, as a function of changes to existing views or view
corridors resulting from construction of the new built form.
Full:
The existing view is fully blocked by the Project as a function of an increase
or decrease in the blockage;
Partial: The existing view is partially blocked by the Project as a function of an increase or decrease in the blockage;
Slight: The existing
view is only slightly blocked by the Project as a function of an increase or
decrease in the blockage;
Negligible: The blockage of the existing view by the Project is negligible as a function of an increase or decrease in the blockage;
None:
The existing view is not blocked as a result of the Project.
Large: |
The VSRs would suffer a major change in their viewing experience; |
Intermediate: |
The VSRs would suffer a moderate change in their viewing experience; |
Small: |
The VSRs would suffer a small change in their viewing experience; |
Negligible: |
The VSRs would suffer no discernible change in their viewing experience. |
None |
The VSRs would suffer no change in their viewing |
Landscape and Visual Mitigation Measures
Table 11.10B Magnitude of Visual Change during the Construction and Operation Phases before Mitigation (DP9)
VSR
ID |
Key
VSR |
Compatibility
of the Project with the Visual Backdrop (High/Medium/Low) |
Duration
and Frequency of Impacts (Temporary/Permanent & Intermittent/Continuous) |
Scale of Development (Large/Medium/Small) & Reversibility of Change (Yes/No) |
Degree of
Visibility of Source(s) of Visual Impact (Full, Partial, Obscured) & Distance Between VSR & Nearest Source(s) of Impact |
Potential
Blockage of Existing View (Full/Partial/Slight/Negligible/None) |
Magnitude
of Visual Change BEFORE Mitigation (None,
Negligible, Small, Intermediate, Large) |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
||||
Residential VSRs |
|||||||||||
RES-3 |
Residents in Fung Kong Tsuen |
High |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Obscured, 550 m |
Obscured, 550 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the south towards the DP9
site 2-34. Due to the distance from the DP9 site 2-34, the degree of
visibility of sources of impact during construction and operation would be
obscured by existing buildings and landscape features. In terms of the source
of visual impacts, views during construction may include site clearance, site
formation and development of the SPS, while views during operation may
include the new SPS building at site 2-34. Due to the small scale of the
development in the view combined with a ¡§High¡¨ compatibility with the visual
backdrop, the magnitude of change during construction and operation is
considered to be ¡§None¡¨. |
|||||||||||
RES-4 |
Residents in Lo Uk Tsuen, Hong Mei Tsuen, San Wai, Sik Kong Tsuen, and
Tung Tau Tsuen |
High |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Obscured, 300 m |
Obscured, 300 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the DP9 site
2-34. Due to the distance from the DP9 site 2-34, obscured views of the
Project during construction and operation would be permanent and continuous.
There would be negligible blockage of existing views during construction due
to existing features obscuring views to the DP9 site, while blockage during
operation would also be negligible. In terms of the source of visual impacts,
views during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 2-34. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨.
Refer to Figures 11.57a and 11.57b as representative examples of possible visual impacts. |
|||||||||||
RES-9 |
Residents in Sun Fung Wai |
High |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Obscured, 200 m |
Obscured, 200 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the northwest towards the
DP9 site 4-35. Due to the distance from the DP9 site 4-35, obscured views of
the Project during construction and operation would be permanent and
continuous. In terms of the source of visual impacts, views during
construction may include site clearance, site formation and development of
the SPS, while views during operation may include the new SPS building at
site 4-35. Due to the small scale of the development in the view combined
with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude of change
during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
RES-11 |
Residents in Shek Po Tsuen |
High |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Obscured, 600 m |
Obscured, 600 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the southwest towards the DP9
site 3-41. Due to the distance from the DP9 site 3-41, obscured views of the
Project during construction and operation would be permanent and continuous.
In terms of the source of visual impacts, views during construction may
include site clearance, site formation and development of the SPS, while
views during operation may include the new SPS building at site 3-41. Due to
the small scale of the development in the view combined with a ¡§High¡¨
compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
RES-12 |
Residents in San Sang Tsuen |
High |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Partial, 130 m |
Obscured, 130 m |
Partial |
Slight |
Intermediate |
Small |
This VSR would mainly experience views to the south towards the DP9
site 3-41. Due to the distance from the DP9 site 3-41, partial views of the
Project during construction and obscured views during operation would be
permanent and continuous. There would be partial blockage of existing views
during construction, while blockage during operation would be slight as the
alignment of structures associated with the development of the NDA would
decrease the view shed. In terms of the source of visual impacts, views
during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 3-41. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction is considered to be ¡§Intermediate¡¨ and in
operation is considered to be ¡§Small¡¨. Refer to Figures 11.58a and 11.58b as representative examples of possible visual impacts. |
|||||||||||
RES-47 |
Residents in Sunny Villas, Tseung Kong Wai, Sik Kong Wai, Ha Tsuen Shi, and San Uk Tsuen |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Full, 100 m |
Full, 100 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would mainly experience views to the northwest towards the
DP9 site 2-34. Due to the proximity from the DP9 site 2-34, full views of the
Project for residents to the northwest edge of this group during construction
and operation would be permanent and continuous. There would be partial
blockage of existing views during construction and operation. In terms of the
source of visual impacts, views during construction may include site
clearance, site formation and development of the SPS, while views during
operation may include the new SPS building at site 2-34. Due to the small
scale of the development in the view combined with a ¡§High¡¨ compatibility
with the visual backdrop, the magnitude of change during construction and
operation is considered to be ¡§Intermediate¡¨. Refer to Figures 11.57a and 11.57b as representative examples of possible visual impacts. |
|||||||||||
Recreational VSRs |
|||||||||||
REC-1 |
Hikers along Castle Peak Trails |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Partial, ~0-6150 m |
Partial, ~0-6150 m |
Slight |
Slight |
Small |
Small |
This VSR would mainly experience views to the west towards the DP9
sites. Due to the distance from the DP9 sites, partial views of the Project
for hikers during construction and operation would be permanent and
intermittent as this VSR are in motion. There would be slight blockage of
existing views during construction and operation as the scale of the
development and distance from hikers would make a minor impact. In terms of
the source of visual impacts, views during construction may include site
clearance, site formation and development of the SPS, while views during
operation may include the new SPS buildings. Due to the small scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Small¡¨. Refer to Figures 11.59a and 11.59b as representative examples of possible visual impacts. |
|||||||||||
REC-8 |
Hikers along the
Hillside north of the NDA |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Partial, 500-1500 m |
Obscured, 500-1500 m |
Slight |
Negligible |
Small |
Negligible |
This VSR would mainly experience views to the south towards the DP9 site
2-34. Due to the distance from the DP9 site 2-34, partial views of the
Project for hikers during construction and obscured in operation would be
permanent and intermittent as this VSR is in motion. There would be slight
blockage of existing views during construction, becoming negligible in
operation as the new buildings associated with the NDA would further obscure
views of the SPS. In terms of the source of visual impacts, views during
construction may include site clearance, site formation and development of
the SPS, while views during operation may include the new SPS building at
site 2-34. Due to the small scale of the development in the view combined
with a ¡§Medium¡¨ compatibility with the visual backdrop, the magnitude of
change during construction is considered to be ¡§Small¡¨ and in operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
Travelling VSRs |
|||||||||||
T-1 |
Motorists along KSWH |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Full, 0 m |
Full, 0 m |
Slight |
Slight |
Small |
Small |
This VSR would mainly experience direct views to the west towards the
DP9 site 3-48. Due to the immediate proximity to the DP9 site 3-48, full
views of the SPS during construction and operation would be permanent and
intermittent as this VSR are in motion. There would be slight blockage of
existing views during construction and operation as the scale of the
development would make a minor impact. In terms of the source of visual
impacts, views during construction may include site clearance, site formation
and development of the SPS, while views during operation may include the new
SPS building at site 3-48. Due to the small scale of the development in the
view combined with a ¡§Medium¡¨ compatibility with the visual backdrop, the
magnitude of change during construction and operation is considered to be
¡§Small¡¨. |
|||||||||||
T-2 |
Users of the MTR
between TSW and Siu Hong Station |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Full, 0 m |
Full, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would mainly experience direct views to the east towards the
DP9 site 4-35. Due to the immediate proximity to the DP9 site 4-35, full
views of the SPS during construction and operation would be permanent and
intermittent as this VSR are in motion. In terms of the source of visual
impacts, views during construction may include site clearance, site formation
and development of the SPS, while views during operation may include the new
SPS building at site 3-48 and site 4-35. Due to the small scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Intermediate¡¨. Refer to Figures 11.58a and
11.58b as representative examples of possible visual impacts. |
|||||||||||
T-5 |
Motorists along Castle
Peak Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Obscured, 180 m |
Obscured, 180 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the DP9
site 4-35. Due to the distance from the DP9 site 4-35, obscured views of the
SPS during construction and operation would be permanent and intermittent as
this VSR are in motion. In terms of the source of visual impacts, views
during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 4-35. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
T-6 |
Motorists along Ping Ha
Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Obscured, 650 m |
Obscured, 650 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the southwest towards the DP9
site 2-34. Due to the distance from the DP9 site 2-34, obscured views of the
SPS during construction and operation would be permanent and intermittent as
this VSR are in motion. In terms of the source of visual impacts, views
during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 2-34. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
T-7 |
Motorists along Tin Ha
Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Full, 120 m |
Full, 120 m |
Slight |
Slight |
Small |
Small |
This VSR would mainly experience views to the west towards the DP9
site 3-41. Due to the proximity to the DP9 site 3-41, full views of the SPS
during construction and operation would be permanent and intermittent as this
VSR are in motion. There would be slight blockage of existing views during
construction and operation as the scale of the development would make a minor
impact. In terms of the source of visual impacts, views during construction
may include site clearance, site formation and development of the SPS, while
views during operation may include the new SPS building at site 3-41. Due to
the small scale of the development in the view combined with a ¡§Medium¡¨
compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Small¡¨. Refer to Figures 11.58a and 11.58b as representative examples of possible visual impacts. |
|||||||||||
T-8 |
Motorists along Shek Po
Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Obscured, 180 m |
Obscured, 180 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the DP9
site 3-41. Due to the distance from the DP9 site 3-41, obscured views of the
SPS during construction and operation would be permanent and intermittent as
this VSR are in motion. In terms of the source of visual impacts, views
during construction may include site clearance, site formation and development
of the SPS, while views during operation may include the new SPS building at
site 3-41. Due to the small scale of the development in the view combined
with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude of change
during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
T-17 |
Cyclists along Castle Peak Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Obscured, 120 m |
Obscured, 120 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the DP9
site 4-35. Due to the distance from the DP9 site 4-35, obscured views of the
SPS during construction and operation would be permanent and intermittent as
this VSR are in motion. This VSR experiences views at a slower pace than
motorists along the same road. In terms of the source of visual impacts,
views during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 4-35. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
T-18 |
Cyclists along Tin Ha Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Full, 120 m |
Full, 120 m |
Slight |
Slight |
Small |
Small |
This VSR would mainly experience views to the west towards the DP9
site 3-41. Due to the proximity to the DP9 site 3-41, full views of the SPS
during construction and operation would be permanent and intermittent as this
VSR are in motion. This VSR experiences views at a slower pace than motorists
along the same road. There would be slight blockage of existing views during
construction and operation as the scale of the development would make a minor
impact. In terms of the source of visual impacts, views during construction
may include site clearance, site formation and development of the SPS, while
views during operation may include the new SPS building at site 3-41. Due to
the small scale of the development in the view combined with a ¡§Medium¡¨
compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Small¡¨. Refer to Figures 11.58a and 11.58b as representative examples of possible visual impacts. |
|||||||||||
T-19 |
Cyclists along Shek Po Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Obscured, 530 m |
Obscured, 530 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the DP9 site
3-41. Due to the distance from the DP9 site 3-41, obscured views of the SPS
during construction and operation would be permanent and intermittent as this
VSR are in motion. This VSR experiences views at a slower pace than motorists
along the same road. In terms of the source of visual impacts, views during
construction may include site clearance, site formation and development of
the SPS, while views during operation may include the new SPS building at
site 3-41. Due to the small scale of the development in the view combined
with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude of change
during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
T-20 |
Cyclists along Ping Ha Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Small, No |
Obscured, 650 m |
Obscured, 650 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the southwest towards the
DP9 site 2-34. Due to the distance from the DP9 site 2-34, obscured views of
the SPS during construction and operation would be permanent and intermittent
as this VSR are in motion. This VSR experiences views at a slower pace than
motorists along the same road. In terms of the source of visual impacts,
views during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 2-34. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
Occupational VSRs |
|||||||||||
O-22 |
Workers in Industrial Area of Ha Tsuen |
High |
Permanent, Continuous |
Permanent, Continuous |
Small, No |
Obscured, 530 m |
Obscured, 530 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the DP9
site 2-34. Due to the distance from the DP9 site 2-34, obscured views of the
Project during construction and operation would be permanent and continuous.
There would be negligible blockage of existing views during construction due
to existing features obscuring views to the DP9 site, while blockage during
operation would also be negligible. In terms of the source of visual impacts,
views during construction may include site clearance, site formation and
development of the SPS, while views during operation may include the new SPS
building at site 2-34. Due to the small scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨.
Refer to Figures 11.57a and 11.57b as representative examples of possible visual impacts. |
|||||||||||
Note: (1) 0* denotes VSR within Project Site Boundary |
|||||||||||
(2) The closet viewing
distance has been used to rate the worst case scenario |
(3) ¡¥Permanent¡¦ duration
measurement refers to entire construction/operational phase
Prediction of Significance of Visual Impacts
Impacts during the Construction and Operational Phase before Mitigation
Residential VSRs
¡P
RES3: This
VSR will have permanent and continuous obscured views towards the source of
visual impact (DP9 site 2-35) during construction and operation at a distance
of 550 m. In the construction phases, the resultant magnitude of visual change
is negligible, and this combined with their Medium sensitivity results in an
impact considered to be of Insubstantial
significance. In the operation
phase, the predicted magnitude of visual change is anticipated to be
negligible, with the predicted impact significance anticipated to be Insubstantial.
¡P
RES4: This
VSR will have permanent and continuous obstructed views towards the source of
visual impact at a distance of 300 m. In the constructionpPhase, the resultant
magnitude of visual change is negligible, and this combined with their High
sensitivity results in an impact considered to be of Insubstantial significance.
In the operation phase, the predicted impact significance is anticipated
to remain the same as in the construction phase, as the unmitigated development
would render similar impacts as the construction phase.
¡P
RES9,
RES11: These VSRs will have permanent and continuous obstructed views
towards the source of visual impact at distances of 200 m to 600 m. In the
construction phase, the resultant magnitude of visual change is negligible, and
this combined with their Medium sensitivity results in an impact considered to
be of Insubstantial
significance. In the operation
phase, the predicted magnitude of visual change is anticipated to be
negligible, with the predicted impact significance anticipated to change to Insubstantial.
¡P
RES12: This
VSR will have permanent and continuous partial views towards the source of
visual impact during construction and obstructed views during operation at a
distance of 130 m. In the construction phase, the resultant magnitude of visual
change is Intermediate, and this combined with their High sensitivity results
in an impact considered to be of Substantial
significance. In the operation
phase, the predicted magnitude of visual change is anticipated to change to
Small as a result of the adjacent developments, with the predicted impact
significance anticipated to change to Moderate.
¡P
RES47: This
VSR will have permanent and continuous full views towards the source of visual
impact at a distance of 100 m. In the construction phase, the resultant
magnitude of visual change is Intermediate, and this combined with their High
sensitivity results in an impact considered to be of Substantial significance.
In the operation phase, the predicted impact significance is anticipated
to remain the same as in the construction phase, as the unmitigated development
would render similar impacts as the construction phase.
Recreational VSRs
¡P
REC1:
This VSR will have permanent and intermittent partial views towards the source
of visual impact at distances of 0 - 6,150 m as this VSR intersects with the
Project area. In the construction phase, the resultant magnitude of visual
change is Small, and this combined with their High sensitivity results in an
impact considered to be of Moderate
significance. In the operation
phase, the predicted impact significance is anticipated to remain the same as
in the construction phase, as the unmitigated development would render similar
impacts as the construction phase.
¡P
REC8:
This VSR will have permanent and intermittent partial views towards the source
of visual impact during construction and obstructed views during operation at
distances of 500 -1500 m. In the construction phase, the resultant magnitude of
visual change is Small, and this combined with their Medium sensitivity results
in an impact considered to be of Moderate
significance. In the operation
phase, the predicted magnitude of visual change is anticipated to change to
negligible as a result of the adjacent developments, with the predicted impact
significance anticipated to change to Insubstantial.
Traveling VSRs
¡P
T1:
This VSRs will have permanent and intermittent full views towards the source of
visual impact at a distance of 0-50 m as the VSRs intersect with the Project
boundaries (DP sites 3-41, 3-48, and 3-45). In the construction phase, the
resultant magnitude of visual change is Small, and this combined with the
Medium sensitivity results in an impact considered to be of Moderate significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P
T2:
This VSR will have permanent and intermittent full views towards the source of
visual impact at a distances of 0 m as this VSR intersects with the Project
boundaries. In the construction phase, the resultant magnitude of visual change
is Intermediate, and this combined with the Medium sensitivity results in an
impact considered to be of Moderate
significance. In the operation
phase, the predicted impact significance is anticipated to remain the same as
in the construction phase, as the unmitigated development would render similar
impacts as the construction phase.
¡P
T5:
This VSR will have permanent and intermittent obscured views towards the source
of visual impact at a distance of 180 m. In the construction phase, the
resultant magnitude of visual change is negligible, and this combined with
their Medium sensitivity results in an impact considered to be of Insubstantial significance. In the operation phase, the predicted
magnitude of visual change is anticipated to be negligible, with the predicted
impact significance anticipated to change to Insubstantial.
¡P
T7:
This VSR will have permanent and intermittent full views towards the source of
visual impact during construction and operation at a distance of 120 m. In the
construction phase, the resultant magnitude of visual change is Small, and this
combined with their Medium sensitivity results in an impact considered to be of
Moderate significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P
T6, T8:
These VSRs will have permanent and intermittent obscured views towards the
source of visual impact at distances of 180 m to 650 m. In the construction
phase, the resultant magnitude of visual change is negligible, and this
combined with their Low sensitivity results in an impact considered to be of Insubstantial significance. In the operation phase, the predicted
magnitude of visual change is anticipated to be negligible, with the predicted
impact significance anticipated to change to Insubstantial.
¡P
T18:
This VSR will have permanent and intermittent full views towards the source of
visual impact during construction and operation at a distance of 120 m. In the
construction phase, the resultant magnitude of visual change is Small, and this
combined with their High sensitivity results in an impact considered to be of Moderate significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P
T17:
This VSR will have permanent and intermittent obstructed views towards the
source of visual impact at a distance of 120 m. In the construction phase, the
resultant magnitude of visual change is negligible, and this combined with the
High sensitivity results in an impact considered to be of Insubstantial significance. In the operation phase, the predicted
magnitude of visual change is anticipated to be negligible, with the predicted
impact significance anticipated to change to Insubstantial.
¡P
T19, and
T20: These VSRs will have permanent and intermittent obstructed views
towards the source of visual impact at a distances ranging from 180 to
650 m. In the construction phase, the resultant magnitude of visual change is
negligible, and this combined with their Medium sensitivity results in an
impact considered to be of Insubstantial
significance. In the operation phase, the predicted magnitude of visual change
is anticipated to change to negligible as a result of the adjacent
developments, with the predicted impact significance anticipated to change to Insubstantial.
Occupational VSRs
¡P
O22:
This VSR will have permanent and continuous obstructed views towards the source
of visual impact at a distance of 530 m. In the construction phase, the
resultant magnitude of visual change is negligible, and this combined with
their Low sensitivity results in an impact considered to be of Insubstantial significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
Residual Impacts during the Construction & Operation Phases after Mitigation
Preliminary Land Use Study for Lam Tei Quarry and the Adjoining Areas
¡P This is a preliminary land use study to identify and examine the development potential and suitable types of possible future land uses of the Lam Tei Quarry (LTQ) and its adjoining areas, including two proposed Strategic Cavern Areas (SCVAs) identified under the Feasibility Study on Long-Term Strategy for Cavern Development. Although no cumulative impacts are predicted with the implementation of mitigation measures at this stage, it is advised that a coordinated approach be undertaken between these projects.
Tuen Mun Western Bypass
¡P TMWB together with the Tuen Mun ¡V Chek Lap Kok Link, will provide a north-south highway corridor linking the NWNT with the Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities, the Hong Kong International Airport and North Lantau. Although no cumulative impacts are predicted with the implementation of mitigation measures at this stage, it is advised that a coordinated approach be undertaken between these projects to reduce potential impacts in terms of both magnitude and the period of disturbance during construction.
Proposed Development Under the Study on the Enhancement of the Lan Fau Shan Rural Township and Surrounding Areas
¡P The objective of the study is to realise the tourism and recreational potential of Lau Fau Shan and its surrounding areas. The assessment area with a total site area of about 565 ha, mainly covers Lan Fau Shan and the coastal areas of Deep Bay, stretching from the KSWH in the south to Tsim Bei Tsui in the north. Although no cumulative impacts are predicted with the implementation of mitigation measures at this stage, it is advised that a coordinated approach be undertaken between these projects to reduce potential impacts in terms of both magnitude and the period of disturbance during construction.
Proposed Development Under the Study on the Enhancement of Yuen Long South
¡P The overall objective of the Study is to examine and optimise the development potential of the degraded brownfield land in Yuen Long South for housing purpose and other uses with supporting infrastructure and community facilities, and to improve the existing environment. Although no cumulative impacts are predicted with the implementation of mitigation measures at this stage, it is advised that a coordinated approach be undertaken between these projects to reduce potential impacts.
Table
11.11B Significance of Visual Impacts in the Construction and Operation Phases
(DP9)
VSR ID. |
Key Visually Sensitive Receiver (VSR) |
Magnitude of Change before Mitigation (None, Negligible, Small, Intermediate, Large) |
Receptor Sensitivity & Number
(Low, Medium, High) (Very Few, Few, Many, Very Many) |
Impact Significance BEFORE Mitigation (None, Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance AFTER Mitigation (None, Insubstantial, Slight, Moderate, Substantial) |
|||||
Construction |
Operation |
||||||||||
|
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
|
DAY 1 |
YEAR 10 |
|
RES-3 |
Residents in Fung Kong Tsuen |
Negligible |
Negligible |
Medium, Many |
Medium, Many |
Negligible |
Negligible |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-4 |
Residents in Lo Uk Tsuen, Hong Mei Tsuen, San Wai, Sik Kong Tsuen, and
Tung Tau Tsuen |
Negligible |
Negligible |
High, Many |
High, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-9 |
Residents in Sun Fung Wai |
Negligible |
Negligible |
Medium, Many |
Medium, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-11 |
Residents in Shek Po Tsuen |
Negligible |
Negligible |
Medium, Many |
Medium, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-12 |
Residents in San Sang Tsuen |
Intermediate |
Small |
High, Many |
High, Many |
Substantial |
Moderate |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Moderate |
Slight |
Insubstantial |
RES-47 |
Residents in Sunny Villas, Tseung Kong Wai, Sik Kong Wai, Ha Tsuen Shi, and San Uk Tsuen |
Intermediate |
Intermediate |
High, Many |
High, Many |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Moderate |
Moderate |
Slight |
REC-1 |
Hikers along Castle Peak Trails |
Small |
Small |
High, Few |
High, Few |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Slight |
Slight |
Insubstantial |
REC-8 |
Hikers along the Hillside north of the NDA |
Small |
Negligible |
Medium, Few |
Medium, Few |
Moderate |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Slight |
Insubstantial |
Insubstantial |
T-1 |
Motorists along KSWH |
Small |
Small |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Slight |
Slight |
Insubstantial |
T-2 |
Users of the MTR between TSW and Siu Hong Station |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Slight |
Slight |
Insubstantial |
T-5 |
Motorists along Castle Peak Road |
Negligible |
Negligible |
Medium, Many |
Medium, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
T-6 |
Motorists along Ping Ha Road |
Negligible |
Negligible |
Low, Many |
Low, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
T-7 |
Motorists along Tin Ha Road |
Small |
Small |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Slight |
Slight |
Insubstantial |
T-8 |
Motorists along Shek Po Road |
Negligible |
Negligible |
Low, Many |
Low, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
T-17 |
Cyclists along Castle Peak Road |
Negligible |
Negligible |
High, Few |
High,
Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
T-18 |
Cyclists along Tin Ha Road |
Small |
Small |
High, Few |
High, Few |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Slight |
Slight |
Insubstantial |
T-19 |
Cyclists along Shek Po Road |
Negligible |
Negligible |
Medium, Few |
Medium, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
T-20 |
Cyclists along Ping Ha Road |
Negligible |
Negligible |
Medium, Few |
Medium, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
O-22 |
Workers in Industrial Area of Ha Tsuen |
Negligible |
Negligible |
Low, Few |
Low, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7,10, 11, OM1, 2, 5, 8,
11, 12, 13 |
Insubstantial |
Insubstantial |
Insubstantial |
¡P Existing Baseline Conditions in March 2016 ¡V This photo illustrates the ¡¥before scenario¡¦ - the existing landscape conditions before construction of the proposed Project development (including DP9 sites) for the purpose to assess the magnitude of visual change.
¡P
Proposed
Project development without mitigation at Day 1 (Operational Phase) ¡V This
photomontage illustrates the proposed HSK development at Day 1 (including DP9
sites) without mitigation (i.e. no screen planting, no chromatic treatment to
the buildings, no landscape greening etc.). This photomontage is used to
demonstrate impacts / changes caused by the DP9 sites and assess the
effectiveness of implementing mitigation measures in reducing the landscape and
visual impacts.
¡P Proposed Project development with mitigation at Day 1 (Operational Phase) ¡V This photomontage illustrates the proposed HSK development at Day 1 (including DP9 sites) with mitigation (i.e. with screen planting, with chromatic treatment to the buildings, with landscape greening etc.). This photomontage is used to illustrate the implementation of mitigation measures at Day 1 and reduction of the landscape and visual impacts imposed by the proposed DP9 sites at Day 1.
¡P Proposed Project development with mitigation at Year 10 (Operational Phase) - This photomontage illustrates the proposed HSK development at Year 10 (including DP9 sites) with mitigation (i.e. with screen planting, with chromatic treatment to the buildings, with landscape greening etc.). This photomontage is used to illustrate the implementation of mitigation measures matured at Year 10 further reducing the landscape and visual impacts imposed by the proposed DP9 sites.
Summary of Landscape and Visual Mitigation Measures
¡P CM1 ¡V Minimised construction area and contractor¡¦s temporary works areas
¡P CM3 ¡V Protection of existing trees
¡P CM4 ¡V Transplantation of existing trees where practical
¡P CM5 ¡V Control of night time lighting
¡P CM6 ¡V Construction of decorative hoarding around construction works
¡P CM7 ¡V Reduction of construction period to a practical minimum
¡P CM10 ¡V Advanced screen planting
¡P CM11 ¡V Minimise disturbance footprints
¡P OM1 ¡V Compensatory tree planting where practical
¡P OM2 ¡V Sensitive design of above-ground structures
¡P OM5 ¡V Visual softening via soft landscape elements
¡P OM8 ¡V Sensitive and chromatic treatment of architectural facades
¡P OM11 ¡V Tree planting to site boundaries
¡P OM12 ¡V Night time lighting
¡P OM13 ¡V Green roofs and vertical greening
Summary of Predicted Landscape Impacts in the Construction & Operation Phase
Insubstantial (LR2.9, 5.9, 8.19, 9.9,
& 10.13; and LCA1, LCA4)
Slight (LR4.8 & 15.12)
Overall Summary: Landscape Impacts
Summary of Predicted Visual Impacts in the Construction & Operation Phase
Overall Summary: Visual Impacts
Overall Conclusion