6.1.1
This Section presents the water quality impact assessment
for the construction and operational phases of the Project. Potential impacts have been identified and
their significance on the Water Sensitive Receivers (WSRs) evaluated. Mitigation measures are recommended,
where necessary, to reduce the potential water quality impacts in order to
control residual impacts to acceptable levels.
6.2.1
The following legislation and relevant guidance or
non-statutory guidelines are applicable to the evaluation of water quality
impacts associated with the construction and operation of the Project:
¡P
Water Pollution Control Ordinance (WPCO);
¡P
Technical Memorandum for Effluents Discharged
into Drainage and Sewerage Systems, Inland and Coastal Waters (TM- DSS);
¡P
Environmental Impact Assessment Ordinance
(Cap. 499. S.16) and the Technical Memorandum on EIA Process (EIAO-TM), Annexes
6 and 14; and
¡P
Practice Note for Professional Persons,
Construction Site Drainage (ProPECC PN1/94);
¡P
Drainage Services Department Practice Note
No. 1/2015: Guidelines on Environmental and Ecological Considerations for River
Channel Design.
¡P
Town Planning Board Guideline No. 12C (TPB
PG-No. 12C) Requirement on No Net Increase in Pollution Load to Deep Bay
Water Pollution Control Ordinance (WPCO)
6.2.2
The Water Pollution
Control Ordinance (WPCO) is the primary legislation for the control of
water pollution and water quality in Hong Kong. Under the WPCO, Hong Kong waters are
divided into 10 Water Control Zones (WCZs). Each WCZ has a designated set of
statutory Water Quality Objectives (WQOs). The proposed Project is located within
the Deep Bay WCZ. The WQOs
designated for this zone are thus relevant for assessing the water quality
impacts from the construction and operation of the Project (Table 6.1).
Table 6.1 Key Water Quality
Objectives of the Deep Bay WCZ for Yuen Long & Kam Tin (Upper) Subzone and Yuen
Long & Kam Tin (Lower) Subzone
Water
Course within the Study Area |
pH Range |
Maximum
5-day Biochemical Oxygen Demand (BOD5) |
Maximum
Chemical Oxygen Demand (COD) |
Maximum
Annual Median Suspended Solids (SS) |
Minimum
Dissolved Oxygen (DO) |
Maximum
Annual Mean Unionised Ammoniacal Nitrogen |
Yuen Long & Kam Tin (Upper) Subzone |
6.5
¡V 8.5 |
3
mg/L |
15
mg/L |
20
mg/L |
4
mg/L |
0.021
mg/L |
Yuen Long & Kam Tin (Lower) Subzone |
6.5
¡V 8.5 |
5
mg/L |
30
mg/L |
20
mg/L |
4
mg/L |
0.021
mg/L |
Technical
Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Waters (TM- DSS)
6.2.3
All discharges during both the construction and operation
phases of a proposed development are required to comply with the Technical Memorandum for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS)
issued under Section 21 of the WPCO. The TM-ICW
defines acceptable discharge limits to different types of receiving
waters. Under the TM-ICW, effluents discharged into the
drainage and sewerage systems, inland and coastal waters of the WCZs are
subject to pollutant concentration standards for specified discharge
volumes. These are defined by the
Environmental Protection Department (EPD) and are specified in licence conditions
for any new discharge within a WCZ.
Technical
Memorandum on EIA Process (EIAO-TM)
6.2.4 Annexes 6 and 14 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) provide general guidelines and criteria to be used in assessing water quality issues.
Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94)
6.2.5 Apart from the above statutory requirements, the Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) issued by EPD in 1994, also provide useful non-statutory guidelines on the management of construction site drainage and prevention of water pollution associated with the construction activities.
Drainage
Services Department Practice Note No. 1/2015: Guidelines on Environmental and Ecological Considerations
for River Channel Design
6.2.6 The Practice Note presents the essential environmental and ecological considerations that should be taken into account in the design of river channels.
Town
Planning Board Guideline No. 12C (TPB PG-No. 12C) Requirement on No Net
Increase in Pollution Load to Deep Bay
6.2.7 The Project Site will partly fall within the Wetland Buffer Area. According to the TPB PG-No. 12C, the development within the Wetland Buffer Area shall not cause net increase in pollution load to Deep Bay.
Hydrology
and Hydrodynamics
6.3.1
YLTN has a total length of about 12 km and is made of
concrete lining at the bottom and side walls. The nullahs are divided into five sections,
namely East, West, Town Centre, Upstream (including Main and San Hui) and
Downstream sections, according to their location (Figure 6.1). The proposed
Project involves the Town Centre Section which aligns from north to south in
the middle of Yuen Long Town area and separates the town into western and
eastern parts. The Town Centre
Section is approximately 30 m wide and 4 m deep. It is a rectangular concrete channel
collecting flows from western and eastern areas of the town centre. The DWF in the Town Centre Section has an
estimated average flow rate of 600 m3/day.
6.3.2
YLTN can currently provide flood protection standard
of 1 in 50 years return period. Its
hydraulic performance has been assessed using the InfoWorks
ICM model (1). The
performance assessment was carried out by comparing the peak water-levels with
bank levels for open channels to quantify the level of protection at each
section of the channel. The results
identified some minor flooding blackspots, including Ting Fook Villas, Wang
Chau Public School, Tai Kiu Tsuen, Shui Pin Tsuen and
Tai Kei Leng, in Yuen Long Town area.
6.3.3
It is anticipated that the flooding problem in YLTN could
be worsened subsequent to the increasing population and the development of
residential, commercial and industrial buildings.
Baseline River Water Quality
6.3.4
The proposed Project is located between Shap Pat Heung Road and Tung Tau Wai San Tsuen (Figure
1.1). Water courses
identified within the Study Area (defined as 500 m from the boundary of the
Project Site) include the YLTN, Main Nullah (MN), San Hui Nullah (SHN), East
Nullah, West Nullah and Kam Tin River.
The Study Area falls within the Deep Bay WCZ and the WQOs designated for
the whole zone are thus relevant to this Project and are summarized on Table 6.1 above.
Water Quality of YLTN, MN and
SHN
6.3.5
River water quality has been regularly monitored by the EPD
since 1986. Measurements and
laboratory tests of over 40 physic-chemical and biological parameters,
including organics, nutrients, metals and E. coli levels are recorded on
a monthly basis. In 2018, a total
of 6 stations in the Yuen Long District were monitored, four of them were relevant
to the monitoring of YLTN (stations YL3-4), MN (YL1) and SHN (station YL2) (Figure
6.2).
6.3.6
Data of key water quality parameters measured in 2018 at the four
monitoring stations as reported in the Annual
River Water Quality in Hong Kong (2) are presented in Table 6.2.
Table 6.2 Summary of River
Water Quality Monitoring Data collected by EPD River Water Quality Monitoring
Programme for Stations in YLTN, MN and SHN (2018)
Parameter |
Unit |
River WQOs (Yuen Long and Kam Tin Upper Subzone) |
River WQOs (Yuen Long and
Kam Tin Lower Subzone) |
YL1 (MN) |
YL2 (SHN) |
YL3 (YLTN) |
YL4 (YLTN) |
Dissolved oxygen (DO) |
mg/L |
≥ 4 |
≥ 4 |
4.3 |
3.5 |
2.8 |
2.9 |
pH |
- |
6.5 ¡V 8.5 |
6.5 ¡V 8.5 |
7.1 |
7.3 |
7.3 |
6.9 |
Suspended solids (SS) |
mg/L |
≤20 |
≤20 |
15.5 |
7.3 |
25.5 |
61.0 |
5-Day Biochemical Oxygen
Demand (BOD5) |
mg/L |
≤3 |
≤5 |
18.0 |
10.1 |
68 |
140 |
Chemical Oxygen Demand (COD) |
mg/L |
≤15 |
≤30 |
31 |
35 |
92 |
165 |
Escherichia coli (E.coli) |
cfu/100mL |
0 |
1,000 |
120,000 |
87,000 |
1,000,000 |
1,700,000 |
Ammonia-nitrogen (NH3-N) |
mg/L |
n.a. |
n.a. |
6.300 |
17.000 |
9.250 |
6.850 |
Total Kjeldahl
nitrogen (TKN) |
mg/L |
n.a. |
n.a. |
7.80 |
19.50 |
13.50 |
11.00 |
Total phosphorus |
mg/L |
n.a. |
n.a. |
0.97 |
2.65 |
1.45 |
1.10 |
Flow rate |
m3/s |
n.a. |
n.a. |
0.125 |
0.023 |
0.400 |
0.135 |
Notes:
¡P
Data source: EPD River Water
Quality in Hong Kong in 2018
¡P
Data presented are in annual medians of monthly samples; except those
for E. coli which are in annual geometric means.
¡P
cfu - colony forming unit.
¡P
n.a. indicated the absence of applicable WQOs
¡P
Underlined figures = non-compliance of WQO
¡P
The WQO for Nitrogen under the WPCO refers to level of Un-ionized
Ammoniacal Nitrogen. As such, there
is no applicable WQO to Ammonia-Nitrogen.
6.3.7
The 2018 monitoring data indicate that river water quality at
the upstream area (i.e. YL1 and YL2) of MN and SHN is generally better than
that at the downstream area (i.e. YL3 and YL4) of the YLTN. The levels of Suspended Solids (SS), Chemical
Oxygen Demand (COD), 5-day Biochemical Oxygen Demand (BOD5) and E.
coli were higher at the downstream than the upstream stations.
6.3.8
It is also noted that generally high levels of E. coli were recorded at all
stations. For Dissolved Oxygen (DO),
the values were higher at the upstream stations (MN station YL1 and SHN station
YL2). BOD5,
COD and E. coli levels exceeded the
WQO at all stations.
6.3.9
In terms of WQO compliance rate, overall compliance rate of
the four monitoring stations in 2018 was 38%. In 2018, the Water Quality Index
(WQI) was graded as ¡§bad¡¨ at MN station YL1 and SHN station YL2 and as ¡§very bad¡¨
at YLTN stations YL3 and YL4.
Water Quality of Kam Tin River
6.3.10
In 2018, water quality of Kam Tin River was monitored at two
stations (please refer to Figure 6.2 for locations of the
monitoring stations). Data of key water quality parameters measured in 2018 at
the two monitoring stations as reported in the Annual River Water Quality in Hong Kong are presented in Table 6.3.
Table 6.3 Summary of River
Water Quality Monitoring Data collected by EPD River Water Quality Monitoring
Programme for Stations in Kam Tin River (2018)
Parameter |
Unit |
River WQOs (Yuen Long and
Kam Tin Upper Subzone) |
River WQOs (Yuen Long and
Kam Tin Lower Subzone) |
Stations
in Kam Tin River |
|
KT1 |
KT2 |
||||
Dissolved oxygen (DO) |
mg/L |
≥ 4 |
≥ 4 |
5.1 |
3.1 |
pH |
- |
6.5 ¡V 8.5 |
6.5 ¡V 8.5 |
7.1 |
7.3 |
Suspended solids (SS) |
mg/L |
≤20 |
≤20 |
8.5 |
31.5 |
5-Day Biochemical Oxygen
Demand (BOD5) |
mg/L |
≤3 |
≤5 |
8.5 |
26.5 |
Chemical Oxygen Demand
(COD) |
mg/L |
≤15 |
≤30 |
20 |
50 |
Escherichia coli (E.coli) |
cfu/100mL |
0 |
1000 |
71,000 |
82,000 |
Ammonia-nitrogen (NH3-N) |
mg/L |
n.a. |
n.a. |
4.850 |
9.000 |
Total Kjeldahl
nitrogen (TKN) |
mg/L |
n.a. |
n.a. |
6.60 |
12.00 |
Total phosphorus |
mg/L |
n.a. |
n.a. |
0.91 |
2.10 |
Flow rate |
m3/s |
n.a. |
n.a. |
0.333 |
0.229 |
Notes:
¡P
Data source: EPD River Water
Quality in Hong Kong in 2018
¡P
Data presented are in annual medians of monthly samples; except those
for E. coli which are in annual geometric means.
¡P
cfu - colony forming unit.
¡P
n.a. indicated the absence of applicable WQOs
¡P
Underlined figures = non-compliance of WQO
¡P
The WQO for Nitrogen under the WPCO refers to level of Un-ionized
Ammoniacal Nitrogen. As such, there
is no applicable WQO to Ammonia-Nitrogen.
6.3.11
In 2018, BOD5, COD and E. coli levels exceeded the WQO at both stations. The overall
compliance rate of the two monitoring stations in 2018 was 47%. The WQI at KT1 and KT2 was graded as ¡§fair¡¨
and ¡§bad¡¨ respectively in 2018.
Water Quality of DWF in YLTN
6.3.12
Water sampling and the discrete flow measurement were
conducted in four consecutive non-rainy days between 5 August and 8 August
2017. On each of the four sampling days, five grab samples were collected at
the sampling locations at five specific times including (1) 9:00am, (2)
11:00am, (3) 6:00pm, (4) 9:00pm and (5) 11:30pm. The grab samples were sent to HOKLAS
accredited laboratory for chemical analysis immediately after sampling. According
to the results of water sampling of DWF as presented in Table 6.4, the
upstream DWF coming from Kung Um Road Nullah (Southwest branch at the junction
of Kung Um Road and Tai Shu Ha Road East) has better water quality when
compared with DWF from San Hui Nullah / Town Centre Section / East Nullah and
West Nullah.
Table 6.4 Water Sampling Results
|
Kung
Um Road Nullah |
San
Hui Nullah |
End of Town Centre Section |
YLTN ¡V
West Nullah |
YLTN ¡V
East Nullah |
WQI
(Water Quality) |
9 (Fair) |
11 (bad) |
13
(bad) |
11 (bad) |
15 (very bad) |
DO
(mg/L) |
5.46 |
3.80 |
1.86 |
2.38 |
1.28 |
SS
(mg/L) |
14.70 |
7.45 |
14.60 |
4.39 |
31.1 |
Ammonia
as N (mg/L) |
3.55 |
12.77 |
3.79 |
1.79 |
8.80 |
Total Kjeldahl Nitrogen (mg/L) |
4.41 |
13.90 |
5.01 |
2.94 |
11.33 |
Total
Phosphorus (mg/L) |
0.53 |
2.59 |
0.64 |
0.32 |
1.15 |
BOD
(mg/L) |
8.47 |
7.15 |
14.20 |
6.20 |
64.4 |
Note: Underlined figures = non-compliance of WQO The presented results are
the average measured value |
Discharges into the Yuen Long Town
Nullah
6.3.13
Discharges of sewage from unsewered villages and livestock
farms are the main source of pollution to the YLTN. As reported in the Feasibility Study for
the Project, a total of six livestock farms, including three pig farms and
three poultry farms, are located within the catchment of YLTN (1)(3). As discussed in Section 6.3.9 above, the WQI in 2018 was graded as ¡§very bad¡¨ at
YL3 and YL4 and ¡§bad¡¨ at YL1 and YL2.
6.3.14
An Expedient Connection Survey was carried out in early 2005
under Agreement No. 99/2002 (DS) ¡V Provision of Sewerage to Unsewered
Areas/Villages in Northwest New Territories ¡V Feasibility Study. The results of the survey indicated that
there were a number of expedient connections along the
Yuen Long Nullah (e.g. due to the unsewered areas in Yuen Long). Under the Project, it is estimated that
about 60 numbers of stormwater outfalls will be intercepted to the DWFI
system.
6.3.15
According to the existing sewage treatment process of the
YLSTW, treated effluent from the YLSTW has undergone preliminary, primary and
secondary treatment before being discharged to the Shan Pui River (refer to the
Figure
6.3 for the Sewage Treatment Process Flowchart). In general, the raw sewage will firstly
undergo preliminary screening, degritting and
subsequently primary sedimentation.
The sewage will then be purified by means of a secondary biological
treatment process, during which the organic matter in the settled sewage will
be decomposed by micro-organisms.
Eventually, treated effluent for discharge to Shan Pui River should meet
the discharge license standard of not more than 30 mg/L for SS and 20 mg/L for
BOD5.
6.3.16
Monthly mean BOD5 and SS levels recorded for the
treated effluent from YLSTW are shown in Table 6.5. Review of the treated effluent quality
from YLSTW in the period of January 2009 to December 2018 revealed that the
water quality of the treated effluent was well within the discharge license
standard, with a range of monthly means from less than 5 mg/L to less than 10
mg/L (recorded in Dec 2018) for BOD5 and from less than 5 mg/L to 19
mg/L (recorded in March 2018) for SS, respectively (4).
Table 6.5 Monthly Mean BOD5
and SS Levels recorded for the Treated Effluent from YLSTW from January 2009 to
December 2018
BOD5
(mg O2/L) |
||||||||||||
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
|
2009 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
2010 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
2011 |
<5 |
<6 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
2012 |
<5 |
<6 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<6 |
2013 |
<5 |
<5 |
<7 |
<6 |
<5 |
<5 |
<6 |
<5 |
<5 |
<5 |
<6 |
<5 |
2014 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<7 |
<6 |
<9 |
2015 |
<9 |
<7 |
<6 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<6 |
<5 |
<5 |
2016 |
<6 |
<6 |
<5 |
<6 |
<5 |
<5 |
<5 |
<5 |
<6 |
<6 |
<5 |
<6 |
2017 |
<5 |
<5 |
<5 |
<5 |
<7 |
<5 |
<5 |
<5 |
<5 |
<6 |
<5 |
<7 |
2018 |
<7 |
<7 |
<9 |
<6 |
<6 |
<8 |
<6 |
<6 |
<5 |
<6 |
<5 |
<10 |
SS
(mg/L) |
||||||||||||
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
|
2009 |
<10 |
11 |
<12 |
<10 |
<7 |
<7 |
<7 |
<8 |
<6 |
<7 |
<6 |
<7 |
2010 |
<8 |
<5 |
<8 |
<7 |
<7 |
10 |
<9 |
<9 |
<6 |
<8 |
<8 |
<6 |
2011 |
<6 |
<8 |
<6 |
<6 |
<6 |
<7 |
<6 |
<5 |
<6 |
<5 |
<5 |
<5 |
2012 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
2013 |
<6 |
<7 |
<6 |
<7 |
<5 |
<5 |
<5 |
<5 |
<5 |
<6 |
<9 |
<6 |
2014 |
<9 |
<8 |
<8 |
<8 |
<9 |
<6 |
<6 |
<6 |
<8 |
13 |
<8 |
12 |
2015 |
15 |
<8 |
<11 |
<8 |
<9 |
<7 |
<8 |
<7 |
<7 |
<7 |
<7 |
8 |
2016 |
<9 |
<8 |
<9 |
<10 |
<7 |
<7 |
<8 |
<9 |
<7 |
<8 |
<6 |
<8 |
2017 |
<6 |
<6 |
<9 |
<8 |
<7 |
8 |
<9 |
<11 |
11 |
<12 |
<15 |
14 |
2018 |
18 |
18 |
19 |
15 |
<12 |
14 |
16 |
<11 |
<9 |
<8 |
<8 |
<18 |
6.4.1
The Water Quality Sensitive Receivers (WSRs) that may be
affected by changes in water quality arising from the Project are identified in
accordance with the EIAO-TM. The identified WSRs include the sections
of YLTN, Deep Bay Wetland Buffer Area, Shan Pui River, Deep Bay Wetland
Conservation Area, Kam Tin River, mangrove and Mai Po Inner Deep Bay Ramsar
Site. The approximate distance from
the identified WSRs to the Project Site is detailed in Table 6.6.
Table 6.6 Identified
Water Quality Sensitive Receivers (WSRs)
WSR |
Minimum Distance away from the Project Site
Boundary |
Minimum Distance away from the 500m Study
Area Boundary |
Yuen Long Town Nullah |
Within the Project Site |
Within the 500m Boundary |
Deep Bay Wetland Buffer Area |
Within the Project Site |
Within the 500m Boundary |
Shan Pui River |
Within the Project Site |
Within the 500m Boundary |
Deep Bay Wetland Conservation Area |
~80m |
Within the 500m Boundary |
Kam Tin River |
~80 m |
Within the 500m Boundary |
Mangrove |
~100m |
Within the 500m Boundary |
Mai Po Inner Deep Bay Ramsar Site |
~1300m |
~800m |
6.4.2
Locations of the identified WSRs are shown in Figure
6.2.
All the fish ponds within the 500-m study area are currently
inactive. Based on our desk-top
review, these inactive ponds are enclosed waterbody and there is currently no
water intake point where water can be abstracted from Yuen Long Town Nullah/Shan
Pui River into the ponds. These ponds are therefore not considered as a
potential WSR.
6.5.1
The main construction activities associated with the
Project that have the potential to cause water quality impacts involve the following:
¡P
Construction activities
on the nullah bed, including ground breaking, excavation, pipeline laying,
backfilling and reinstatement works associated with
construction of DWFI system and the section of rising main inside the YLTN;
¡P
Sewage discharges from
the construction work force;
¡P
Construction runoff and drainage;
and
¡P
Pollutants entering the
receiving waters due to accidental spillage /uncontrolled discharge from the general
construction activities.
6.5.2
Potential water quality impacts that may arise during the
operation phase of the Project are identified as follows:
¡P
Changes in water quality
of the YLTN due to interception of YLTN DWF;
¡P
Release of excess DWF;
¡P
Maintenance works for the
pipes of the DWFI system to remove excessive silt, vegetation, debris and
obstructions within the drainage channel which may lead to disturbance and
re-suspension of river sediments and thereby affecting water quality;
¡P
Emergency discharge of
the collected DWF in case of pumping station breakdown;
¡P
Changes in hydrodynamic
conditions; and
¡P
Change in sediment deposition
and erosion pattern.
6.5.3
As the treated effluent from YLEPP will not be reused for
maintaining water flow, there will be no biocide discharge upon the latest
project scope.
6.6.1
Ground breaking, excavation, pipeline laying and backfilling
works for construction of DWFI system and rising main section inside the YLTN may
lead to elevated SS levels and dispersal of SS to the downstream section of the
YLTN if in contact with river water.
River water will be required to be diverted from the works area as far
as practicable before works commence (i.e. working in dry condition) which will
limit the potential of release of SS into river water and subsequent dispersal
to downstream area (please refer to Section
3.6.8 for details). Water
quality impacts due to release and dispersal of SS from construction activities
on the nullah bed are thus not expected to be unacceptable.
6.6.2
Overall, no unacceptable adverse impacts to water quality are
anticipated to occur as a result of the construction works on the nullah bed
with proper implementation of the mitigation measures as proposed in Section 6.7.
6.6.3
Sewage will be generated from the construction workforce,
site office¡¦s sanitary facilities and from portable toilets. If not properly managed, these
wastewaters could cause adverse water quality impacts, odour and potential
health risks to the workforce by attracting pests and other disease vectors.
6.6.4
According to the latest construction programme and estimate,
there will be a maximum of 50 construction workers on-site during the peak
construction period of the Project.
With an estimated sewage generation rate of 0.15 m3/worker/day (5),
about 7.5 m3 of sewage will be generated per day. Adequate number of portable toilets will
be provided at the Project Site to ensure that sewage from site staff is
properly collected and managed. No unacceptable
environmental impacts are envisaged provided that the portable toilets are
properly maintained by the contractor and the collected sewage is disposed at
the designated sewage treatment works.
6.6.5
During construction of DWFI system, rising main and DWF
pumping station, runoff from the construction site, particularly during
excavation, pipeline laying and backfilling, will contain high SS level which could
be a source of water pollution.
Wastewater with high pH value may be generated by in-situ concreting works for reinstatement of the nullah. Potential adverse water quality impacts
may thus arise at the WSRs if construction site runoff is
allowed to spill outside the construction site area and drain into the
nearby streams, storm drain or natural drainage without treatment. However, with proper implementation of
general good construction site practices as described in Section 6.7 below, it is anticipated that the land
based construction works will not cause unacceptable water quality
impact through site runoff and drainage.
6.6.6
The following pathways of uncontrolled discharge and spillage
of contaminants from general construction activities may lead to adverse water
quality impacts to nearby WSRs:
¡P
Uncontrolled discharge of
wastewater generated from concrete and vehicle washing;
¡P
Uncontrolled discharge of
debris and rubbish such as packaging, construction waste and refuse etc; and
¡P
Spillages of liquid and
chemicals stored on-site, such as oil, diesel and solvents etc.
6.6.7
Wastewater generated from concrete and vehicle washing may
contain elevated levels of SS. Wastewater
from concrete washing is also noted with high pH value. Debris and rubbish generated by the
construction activities, if allowed to enter nearby streams, storm drain or
natural drainage, may cause blockages.
The spillage of liquids and chemicals stored on-site may also result in
water quality impacts by leading to increase in levels of contaminants (e.g.
oil and grease) when they enter nearby water bodies.
6.6.8
The effects on water quality from the construction activities
are, however, likely to be acceptable, provided that the site is well
maintained and that good construction practices and well-designed temporary
drainage system and mitigation measures, as described in Section 6.7, are implemented properly.
6.6.9
During operation of the Project, the DWFI system will collect
the polluted DWF which is originally discharged to the Town Centre Section of
YLTN and causing the odour nuisance in the area. The system will then convey the DWF to
the future YLEPP (upgraded from the existing YLSTW) for tertiary
treatment. Eventually,
treated effluent from YLEPP will be discharged to Shan Pui River and it is
expected that the treated effluent will meet the proposed discharge license
standard of not more than 10 mg/L for SS, 10 mg/L for BOD5, 10 mg/L
for TN, 1 mg/L for TP and 100 counts/100mL for E.coli.
6.6.10
With interception of YLTN DWF and subsequent released of
treated effluent at Shan Pui River, it is expected that pollutant loading to
Shan Pui River will change as a result of the operation of the Project.
6.6.11
As the residual pollution loading from YLEPP has been
accounted for in their approved EIA Report, the pollution loading reduction due
to this Project is assumed to be same as the original pollution loading of the 18,000
m3/day DWF before operation. To calculate the pollution loading reduction,
average water quality data of stations YL3 and YL4 as recorded from 2014-2018
by EPD are used. Water quality data
of YL3 are used to represent pollution loading from the San Hui Nullah and Town
Centre Section of the YLTN, whereas water quality data of YL4 are used to
represent loading from the East Nullah. Using the above data and flow rates of
the nullahs, the pollution loading reduction to Shan Pui River due to
interception of YLTN DWF is calculated and presented in Table 6.7.
6.6.12
As shown in the results, it is anticipated that the pollution
loads to the Shan Pui River will be reduced by 742 kg/day for SS, 1,906 kg/day BOD5,
197 kg/day for TN, 22 kg/day for TP and 2.8¡Ñ1014 counts/day for E.coli due to operation of the Project. The reduction in pollution load caused
by the operation of the Project will thus leading to beneficial impacts of
improvement of water quality and alleviation of odour nuisance. The Project
would not generate a net increase in pollution loading to the receiving water
in the Deep Bay WCZ.
6.6.13
It is anticipated that the quantity of the DWF, particularly
from the upstream of YLTN (at the junction of Kiu
Hing Road and Tai Shu Ha Road West), would be subsequently reduced after
completion of the sewerage works at the area. Eventually, the DWF at upstream (i.e.
Kung Um Road Nullah and San Hui Nullah) is supposed to be cleaner and may lead
to improvement of water quality in the YLTN. In order to ensure that the Project will
not retard recovery of the water body if level of pollution from other sources
decrease (e.g. from upstream of YLTN as presented above), water quality of the
sources of DWF to the YLTN should be regularly reviewed.
Table 6.7 Anticipated
Improvement to Water Quality in YLTN
For SS |
||||
Source of DWF |
Flow Rate of DWF (m3/day) |
SS conc. in DWF (mg/L) (1) |
Estimated SS conc. in merged DWFs at downstream
section of YLTN (mg/L) |
Predicted Reduction in Pollution Load for SS during
Operation (kg/day) |
San Hui Nullah, Town Centre Section of YLTN |
1,600 |
23.1 |
41.22 |
742 |
East Nullah |
16,300 |
43.0 |
||
For BOD5 |
||||
Source of DWF |
Flow Rate of DWF (m3/day) |
BOD5 conc. in DWF (mg/L) (1) |
Estimated BOD5 conc. in merged DWFs at
downstream section of YLTN (mg/L)
|
Predicted Reduction in Pollution Load for BOD5
during Operation (kg/day) |
San Hui Nullah, Town Centre Section of YLTN |
1,600 |
43.4 |
105.87 |
1,906 |
East Nullah |
16,300 |
112.0 |
||
For TN |
||||
Source of DWF |
Flow Rate of DWF (m3/day) |
TN conc. in DWF (mg/L) (1)(2) |
Estimated TN conc. in merged DWFs at downstream section
of YLTN (mg/L) |
Predicted Reduction in Pollution Load for TN during
Operation (kg/day) |
San Hui Nullah, Town Centre Section of YLTN |
1,600 |
9.26 |
10.92 |
197 |
East Nullah |
16,300 |
11.09 |
||
For TP |
||||
Source of DWF |
Flow Rate of DWF (m3/day) |
TP conc. in DWF (mg/L) (1) |
Estimated TP conc. in merged DWFs at downstream
section of YLTN (mg/L) |
Predicted Reduction in Pollution Load for TP during
Operation (kg/day) |
San Hui Nullah, Town Centre Section of YLTN |
1,600 |
1.14 |
1.19 |
22 |
East Nullah |
16,300 |
1.20 |
||
For E.coli |
||||
Source of DWF |
Flow Rate of DWF (m3/day) |
E.coli conc.
in DWF (counts/100mL) (1) |
Estimated E.coli conc.
in merged DWFs at downstream section of YLTN (counts/100mL) |
Predicted Reduction in Pollution Load for E.coli during Operation (counts/day) |
San Hui Nullah, Town Centre Section of YLTN |
1,600 |
715,165 |
1,565,686 |
2.8 ¡Ñ 1014 |
East Nullah |
16,300 |
1,649,173 |
Note
(1): Average water quality data of
stations YL3 and YL4 as recorded from 2014-2018 by EPD are used.
(2): TN data is not
available. The sum of nitrate-nitrogen and TKN concentrations has been used for
conservation estimation of TN.
6.6.14
During operation of the Project, the DWFI system will collect
the polluted DWF currently being discharged to the Town Centre Section of YLTN
and causing the odour nuisance in the area. The system will then convey the DWF to
the YLEPP for tertiary treatment. The DWFI system will convey up to 18,000 m3/day of the intercepted DWF to the YLEPP for treatment. When the above
limit is reached, the exceeded DWF will be overflown directly or as close as
possible to the desilting basin of the existing low flow pumping station (LFPS)
and mixed with the DWF of Kung Um Road Nullah and West
Nullah before being discharged to Shan Pui River
through the existing LFPS. The discharge point of
the existing LFPS is indicated in Figure 6.4. It is anticipated that
such release of excess DWF will not lead to deterioration of water quality when
compared to the existing baseline conditions under which the DWF with the same
water quality is not being collected and thus flowing in the YLTN.
6.6.15
Maintenance works will be undertaken for the DWFI
system. Diversion of the DWF to the
nearby sewerage system can be adopted during maintenance of the pipe so that
the water quality at YLTN would not be adversely affected. It is expected that maintenance will
only be undertaken on an as-needed basis and frequent maintenance (i.e. monthly)
will not be required. Such small-scale
maintenance would require only light mechanical equipment such as a small
loader and/or a small crane truck. Hand-held
equipment will be used for vegetation removal. Given the infrequent maintenance
requirements and the collected solid wastes will be collected and disposed
off-site properly, unacceptable water quality impact is not expected.
6.6.16
Whilst possible changes to water quality may be expected
during the removal works, such as increases in SS due to disturbance of nullah bed
material and subsequently increased sedimentation onto the nullah bed, it is
expected that these changes will be short-term and occur only within the area
of maintenance works and for a short distance downstream due to rapid settling
out of any disturbed nullah bed material.
Changes in SS concentrations and sedimentation rate would be expected to
be within the typical ranges experienced under ambient conditions following
heavy storms and increased sediment run-off. Therefore, no unacceptable water quality
impacts are anticipated to occur as a result of the small-scale maintenance
works. Water quality impacts to the
ecological sensitive receivers located downstream of the proposed drainage
channel (Wetland Conservation Area and Mai Po and Inner Deep Bay Ramsar Site near
the Shenzhen River estuary) are also not expected to occur due to the small-scale
and temporary nature of the maintenance works. Please refer to Section 8 for more detail on ecological impacts.
6.6.17
An emergency bypass system will be provided for the DWF pumping
station. In case of pumping station
breakdown, the collected DWF will be discharged directly or as close as
possible to the desilting basin of the existing low flow pumping station (LFPS)
and mixed with the DWF of Kung Um Road Nullah and West Nullah before being
discharged to Shan Pui River through the existing LFPS. As such, unacceptable adverse water
quality impacts are not expected during emergency discharge. In addition, the u-channels/pipes of the
DWFI system will be designed to accommodate the designed flow rate of the DWF and
with adequate structural strength to withstand the loading during normal
circumstances and maintenance works.
It is thus highly unlikely that the pipes will burst causing adverse
water quality impacts to the receiving waters.
As added protection, the following measures will be provided
in the DWF pumping station to avoid breakdown of the pumping station:-
¡P
One standby pump will be installed in the pumping station for
emergency.
¡P
Dual power supply to the DWF pumping station is agreed with
CLP Power.
6.6.18
The current flood-protection capacity of the YLTN (i.e. 1 in
50 years) will not be altered by the Project. In addition, according to the Drainage
Impact Assessment conducted for this Project(1), adequate freeboard could be
maintained after the implementation of DWFI system and mitigation works in
hydraulic aspect.
6.6.19
A maximum of 18,000m3 of DWF to the YLTN will be
intercepted and conveyed to YLEPP for treatment, and the treated effluent will
be released to the Shan Pui River. According
to the Engineer¡¦s estimation, interception of the DWF to the YLTN would only
lead to a reduction of 3-4% of total volume of water to the section of Shan Pui
River near the confluence with Kam Tin River, where key ecological habitat is
identified (please refer to Section 8 for
details on habitats identified). It should, however, be noted that the
concerned river section is joined to Deep Bay and is thus expected to be
affected by its tidal influence. For
instance, the Inner Deep Bay station DM1, which is the closest station to the
Study Area, had salinity varies from 0.2 ¡V 29.5 psu
when measured over the past years (i.e. 1986-2017 (6)). This would indicate the tidal influence
from Deep Bay within the Study Area.
Due to the predominant tidal influence, the reduction in volume due to
the DWF interception is not expected to be significant. It should also be noted
that the reduction of flow volume in the nullah is due to interception of some
of the polluted flow which should not have been drained into the nullah.
6.6.20
On the other hand, the flow rate reduction within the section
of YLTN between the Project Site and the YLEPP due to the DWF interception
would reduce the amount of freshwater input to and cause the increase of salinity
at downstream where ecological receiver (i.e. mangroves) is identified. The
associated ecological impact assessment is provided in Section 8.8.
6.6.21
In addition, as presented in Section 6.6.13 above, the DWF interception is expected to lead to reduction in pollution load
to Shan Pui River which is considered as a beneficial water quality
impact. Considering the above, unacceptable
impact to hydrodynamic conditions that would lead to adverse water quality
impacts is not expected to occur.
6.6.22
As discussed in Section
6.6.13, it is anticipated that pollution loads to Shan Pui River will be
reduced by 742 kg/day for SS, 1,906 kg/day BOD5, 197 kg/day for TN,
22 kg/day for TP and 2.8¡Ñ1014 counts/day for E.coli due to operation of the Project which are being considered
as beneficial water quality impacts.
As such, although reduction in SS loading may change the pattern of sediment
deposition and erosion within the drainage channel and along the downstream section
of YLTN leading to improvement of water quality, no unacceptable water quality
impacts are anticipated to occur due to the alteration.
6.6.23
In addition, regular maintenance works will be undertaken within
the proposed drainage channel and at the downstream sections to remove
excessive sediments and thus reduce sediment pollution to the Deep
Bay (regular maintenance works will be undertaken by DSD at these downstream sections
which are not within the scope of the Project). As such, it is not anticipated that the
Project will lead to any unacceptable water quality impacts within the Project
Site and along the downstream section of YLTN by altering sediment deposition
and erosion patterns.
6.7.1
Potential impacts on water quality as a result of
construction activities of the Project, including ground breaking, excavation, pipeline
laying, backfilling and restatement works on the nullah bed associated with
construction of DWFI system have been assessed in Section 6.6 above. The
following section describes the mitigation measures proposed to alleviate water
quality impacts during construction of the Project.
6.7.2
The Contractor should observe and comply with the Water
Pollution Control Ordinance and its subsidiary regulations and obtain a
discharge license under the Ordinance.
The Contractor should carry out the Project works in such a manner as to
minimize adverse impacts on the water quality during execution of the works. In particular, the Contractor should arrange
the working method to minimize the effects on the water quality within and
outside the Project Site and on the transport routes. In addition, the management of
construction site drainage from the Project will follow guidelines provided in ProPECC PN 1/94.
6.7.3
Proper site management measures should be implemented to
control site runoff and drainage, and thereby prevent high sediment loadings
from reaching downstream sections of the river/stream. The Contractor should follow the
practices, and be responsible for the design, construction, operation and
maintenance of all the mitigation measures. The design of the mitigation measures should
be submitted by the Contractor to the Engineer for approval. These mitigation measures shall include
the following practices to minimize site surface runoff and the chance of
erosion, and also to retain and reduce any suspended
solids prior to discharge:
¡P
Before commencing any
work, all sewer and drainage connections should be sealed to prevent debris,
soil, sand etc. from entering public sewers/drains.
¡P
Provision of perimeter
channels to intercept storm-runoff from outside the site. These should be constructed in advance
of the construction works.
¡P
Temporary ditches such as
channels, earth bunds or sand bag barriers should be included to facilitate
runoff discharge into the stormwater drain, via a sand/silt basin/trap.
¡P
Works programme should be
designed to minimize works areas at any one time, thus minimizing exposed soil
areas and reducing the potential for increased siltation and runoff.
¡P
Sand/silt removal
facilities such as sand traps, silt traps and sediment basins should be
provided to remove the sand/silt particles from run-off where necessary. These facilities should be properly and
regularly cleaned and maintained.
These facilities should be carefully planned to ensure that they would
be installed at appropriate locations to capture all surface water generated on
site.
¡P
Careful programming of
the works to avoid excavation works during the rainy season.
¡P
Temporary access roads
(if any) should be protected by crushed gravel and exposed slope surfaces shall
be protected when rainstorms are likely; and
¡P
Open stockpiles of
construction materials on-site should be covered with tarpaulin or similar
fabric during rainstorms to prevent erosion.
6.7.4
The use of containment structures and diversion channels is
recommended wherever practicable to facilitate a dry or at least confined excavation
within the nullah (please refer to Section
3.6.8 for details). For
example, nullah water should be contained within the works area before the commencement
of excavation by the use of concrete blocks or sandbag
barriers. Water within the
contained area should be discharged to the nullah before excavation commences
to create the dry conditions. Nullah
water should also be diverted from the works area through the
use of diversion channel constructed by materials such as concrete
blocks (please refer to Section 3.6.8 for
details). Details of the
containment structures and diversion channels should be provided by the
Contractor to the Engineer for approval before commencement of construction
works for the Project. By limiting
or confining the works areas the extent of disturbance to the surrounding water
bodies will be significantly reduced, and thus resulting impacts on water
quality from sediment re-suspension will be reduced. Furthermore, excavation works in the
nullah should be carried out during periods of low flow (dry season from
November to March) as far as practicably to reduce impacts on downstream water
quality and sensitive receivers. These measures will be implemented to ensure
compliance with the Water Pollution Control Ordinance and its subsidiary
regulations.
6.7.5
All discharges during the construction phase of the Project
are required to comply with the Technical
Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Waters (TM-ICW) issued under Section 21 of the WPCO. Domestic sewage/wastewater generated by
workforce on-site should be collected in a suitable storage facility such as
portable chemical toilets. An
adequate number of portable toilets will be provided during the construction
phase. These toilets should be
maintained in a state that will not deter the workers from using them. The collected sewage/wastewater will be
discharged into the foul sewer or transferred to the Government sewage
treatment works by a licensed collector.
6.7.6 The following mitigation measures should be implemented for the storage and handling of oil, other petroleum products and chemicals:
¡P
Waste streams
classifiable as chemical wastes should be properly stored, collected and
treated for compliance with Waste
Disposal Ordinance or Disposal
(Chemical Waste) (General) Regulation requirements.
¡P
All fuel tanks and
chemical storage areas should be provided with locks and be sited on paved
areas.
¡P
The storage areas should
be surrounded by bunds with a capacity equal to 110% of the storage capacity of
the largest tank to prevent spilled oil, fuel and chemicals from reaching the
receiving waters.
¡P
Waste oil should be
collected and stored for recycling or disposal, in accordance with the Waste Disposal Ordinance.
¡P
Vehicle and plant
servicing areas, vehicle wash bays and lubrication bays should, as far as
possible, be located within roofed areas.
The drainage in these covered areas should be connected to foul sewers
via a petrol interceptor.
6.7.7
In the event that accidental spillage or leakages
of hazardous substances / chemical wastes occur, the response procedures as listed
below should be followed. It should
be noted that the procedures below are not exhaustive
and the contractor should propose other response procedures in the emergency
contingency plan based on the particular types and quantities of chemicals or
hazardous substances used, handled and stored on-site.
¡P
Oil leakage or spillage
should be contained and cleaned up immediately. Waste oil should be collected
and stored for recycling or disposal in accordance with the Waste Disposal Ordinance.
¡P
Instruct untrained
personnel to keep at a safe distance well away from the spillage area.
¡P
If the spillage / leakage
involve highly toxic, volatile or hazardous waste,
initiate emergency evacuation and call the emergency service.
¡P
Only trained persons
equipped with suitable protective clothing and equipment should be allowed to
enter and clean up the waste spillage / leakage area.
¡P
Where the spillage/
leakage is contained in the enclosed storage area, the waste can be transferred
back into suitable containers by suitable handheld equipment, such as hand operated
pumps, scoops or shovels. If the
spillage / leakage quantity is small, it can be covered and mixed with suitable
absorbing materials such as tissue paper, dry soft sand or vermiculite. The resultant slurry should be treated
as chemical waste and transferred to suitable containers for disposal.
¡P
For spillage / leakage in
other areas, immediate action is required to contain the spillage /
leakage. Suitable liquid absorbing
materials such as tissue paper, dry soft sand or vermiculite should be used to
cover the spill. The resultant
slurry should be treated as chemical waste and transferred to suitable
containers for disposal.
¡P
Areas that have been contaminated
by chemical waste spillage / leakage should be cleaned. While water is a soluble solvent for aqueous
chemical wastes and water soluble organic waste,
kerosene or turpentine should be used for organic chemical wastes that are not
soluble in water. The waste from
the cleanup operation should be treated and disposed
of as chemical waste.
¡P
In incidents where the
spillage / leakage may result in significant contamination of an area or risk
of pollution, the EPD should be informed immediately.
6.7.8
Maintenance may be necessary for the proposed YLTN at regular
intervals to remove excessive silts, vegetation, debris and obstruction.
6.7.9
The following considerations should be included in planning
for the maintenance works:
(a)
Maintenance of the channels should be restricted to annual
silt removal when the accumulated silt will adversely affect the hydraulic
capacity of the channel, except during emergency situations where flooding risk
is imminent. Desilting should be
carried out by hand or light machinery during the dry season (October to March)
when water flow is low.
(b)
Phasing of the works should be considered to better control
and reduce any impacts caused. Where
possible, works should be carried out along half width of the drainage channel
in short sections. A free passage along the drainage channel is necessary to
avoid forming stagnant water in any phase of the works.
(c)
Containment structures (such as sand bags barrier) should be
provided for the desilting works area to facilitate a dry or at least confined
working area within the drainage channel.
(d)
The locations for the disposal of the removed materials
should be identified and agreement sought with the relevant departments before
commencement of the maintenance works.
Temporary stockpile of waste materials should be located away from the
channel and properly covered. These waste materials should be disposed of in a
timely and appropriate manner.
(e)
Effective temporary flow diversion scheme should be implemented and the generated wastes should be collected and
disposed off-site properly to avoid adversely affecting the water quality of
the drainage system.
6.7.10
An Emergency Response Plan should be developed before the
commencement of the Project¡¦s operation in order to provide details on the
emergency arrangement in case of breakdown of the DWFI system.
6.7.11
The proposed system includes overflowing pipes with outlets
on both sides of the nullah. When water rises to a certain level,
stormwater within the underground system will be released and directly
discharged into the nullah. This prevents further back-up into the
upstream system and the side branches. The discharge of stormwater
directly into the nullah is consistent with the existing drainage pattern.
6.8.1
According to publicly available information at time of
writing, the following major developments in north western part of New
Territories in Hong Kong and are downstream of the Project will be constructed
and/or operated concurrently with the construction and operation of the
Project.
¡P
Yuen Long Barrage Scheme
(YLBS);
¡P
Elevated Pedestrian
Corridor in Yuen Long Town Connecting with Long Ping Station (EPC);
¡P
Housing Sites in
Yuen Long South (HSYLS); and
¡P
Yuen Long Effluent
Polishing Plant (YLEPP)
6.8.2
The construction period of YLBS will overlap with that of the
Project during 2021 to 2026. According to the Project Profile, construction
site runoff and increase suspended solids due to removal of river sediment
would cause impact on water quality. With proper adoption of mitigation
measures and good site practices, no unacceptable water quality impact is
expected.
6.8.3
The construction period of EPC will overlap with that of the
Project during 2021 to 2025. According to the EIA Report, the main water pollution
sources of EPC is construction activities, construction surface runoff and
sewage from site workforce. No unacceptable water quality impact is expected
with implementation of the mitigation measures.
6.8.4
The project area of HSYLS will not encroach but in close
vicinity to the Project Site of the YLTN Project. The construction period of HSYLS will overlap with that of
the Project during 2021 to 2026. Most of the works are at least 400m away from the
YLTN Project except decking over sections of YLTN along Kung Um Road and Kiu Hing Road which is about 100m away from the Project
Site. Site runoff during decking works may flow into the nullah. According to
the EIA Report, mitigation measures such as providing toe boards or bunds along
the works platform over the nullah shall be implemented. No unacceptable water
quality impact is expected with implementation of the mitigation measures.
6.8.5
The construction period of YLEPP will overlap with that of
the Project during 2021 to 2026. According to the EIA Report, the major water
pollution sources of YLEPP is construction activities, sewage from site
workforce, accidental spillage and surface run-off. No unacceptable water
quality impact is expected with implementation of the mitigation measures.
6.8.6
In consideration of the YLTN Project and the concurrent
projects will not generate significant water quality impact during construction
phase. Adverse cumulative water quality impacts during construction phase are
not anticipated.
6.8.7
The operation of YLBS will occur concurrently with the
Project. According to the Project Profile, the proposed barrage conveys stormwater
from YLTN to Shan Pui River for discharge, no adverse impact on water quality
is expected. Based on the latest preliminary design of YLBS, excess flow from
DWF pumping station will enter the closed interception pipe from current
discharge point to the future LFPS. The proposed DWF interception arrangement
under the YLTN Project will be affected due to the decommissioning of the
existing low flow pumping station and inflatable dam under the YLBS. Potential
changes in DWF interception arrangement, hydrology and sedimentation rate will
be assessed during the EIA study of YLBS.
6.8.8
The operation of EPC will occur concurrently with the
Project. According to the EIA Report, surface runoff from the elevated
pedestrian corridor would be the source of water pollution from EPC and no
adverse water quality impact is anticipated with the provision of the drainage
system. There would be no increase of the amount of surface runoff and velocity.
Increase of the water level of nullah may occur due to the decrease of cross-section
area as a result of the permanent structures of the EPC. The flood risk can be
mitigated to acceptable level and adverse water quality impact is not
anticipated with the implementation of the mitigation measures recommended in
the EIA Report.
6.8.9
During the operation of HSYLS, water quality impact may mainly
arise from sewage disposal, surface run-off from the PDA, emergency discharge
from sewage treatment works and pumping stations, maintenance flushing for
reclaimed water service reservoir and wastewater from industrial and commercial
activities. On the other hand, water quality of watercourse nearby (including
YLTN) and Deep Bay WCZ would be improved due to the decommissioning of 3 pig
farms and 2 chicken farms as well as the construction of new sewerage and
sewage treatment works for the unsewered area. No significant water quality
impact is anticipated with the implementation of mitigation measures.
6.8.10
During the operation of YLEPP, the overall water quality in
the inner Deep Bay would be improved for the upgrading treatment level from
secondary treatment to tertiary treatment. Adverse water impact may arise from
the emergency discharge. With implementation of appropriate mitigation measures
such as dual power supply, the occurrence of emergency discharge from the YLEPP
and the subsequent water quality impact will be minimized. According to the
tentative schedules, the YLTN Project will be completed one year before the
commissioning of Phase 1 of YLEPP. During the gap year, the collected DWF will
be conveyed directly or as close as possible to the desilting basin of the
existing LFPS and mixed with the DWF of Kung Um Road Nullah and West Nullah before
being discharged to Shan Pui River through the existing LFPS. After the
commissioning of Phase 1 of YLEPP, up to 18,000 m3/day of DWF from
the YLTN Project will be intercepted and released to the YLEPP for treatment. Based
on the findings in Section 6.6.13 and the EIA Report of YLEPP, no net increase
in pollution loads to the Deep Bay is anticipated for both projects.
6.8.11
In consideration of both the Project and the concurrent
projects will not generate significant water quality impact during operation phase.
Adverse cumulative water quality impacts during operational phase are not
anticipated.
6.9.1
With the proper implementation of the recommended mitigation
measures described in Section 6.7
above, no unacceptable residual water quality impacts are envisaged from the
construction and operation of the Project.
6.10.1
With proper implementation of the recommended mitigation
measures, unacceptable water quality impacts at the identified WSRs are not
expected to occur. However, a water
quality monitoring programme is recommended to verify the predictions of the
EIA and ensure compliance with the assessment criteria.
6.10.2
Detailed approach and methodology of the water quality
monitoring programme are presented in the Environmental Monitoring and Audit
Manual (EM&A Manual) under a separate cover and are briefly described
below.
6.10.3
Baseline monitoring should be undertaken for three times per
week for a period of four weeks before commencement of the construction works
to establish baseline water quality conditions of the area. Impact monitoring should be undertaken for
three times per week during the construction period to obtain water quality
data of the area throughout the construction period for comparison with the
baseline water quality data and hence determine any water quality impacts from
the construction activities. Post
Project monitoring should also be undertaken three times per week for four
weeks after the completion of construction works.
6.10.4
The following parameters will be monitored under the water
quality monitoring programme:
¡P
pH (in situ measurement);
¡P
Water temperature (oC) (in
situ measurement);
¡P
Salinity (ppt) (in situ measurement);
¡P
Dissolved Oxygen (DO) (%
saturation and mg L-1) (in
situ measurement);
¡P
Turbidity (NTU) (in situ measurement); and
¡P
Suspended Solids (SS) (mg
L-1) (laboratory analysis).
6.10.5
Weekly site inspections and audits will be conducted
to ensure that the recommended mitigation measures are properly implemented
during the construction stage.
6.10.6
Unacceptable water quality impacts are not expected
during the operation of the Project.
It is anticipated that the pollution loads to the Shan Pui
River will be reduced by 742 kg/day for SS, 1,906 kg/day BOD5, 197
kg/day for TN, 22 kg/day for TP and 2.8¡Ñ1014 counts/day for E.coli due to
operation of the Project. The
reduction in pollution load caused by the operation of the Project will thus
leading to beneficial impacts of improvement of water quality and alleviation
of odour nuisance.
6.10.7
Therefore, environmental monitoring and audit for
water quality is not recommended for the operation phase of the Project. On the other hand, the water quality of
the branches of YLTN will be regularly reviewed. When the water quality has
reached the prevailing acceptable standards, EPD will be consulted and the DWF
interception system would be reviewed and modified, e.g. re-connect the
branches with better water quality to the existing DWF channel.
6.11.1
The potential sources of water quality impacts associated
with the construction and operation of the Project have been identified and the
potential impacts were evaluated.
6.11.2
Potential impacts arising from the proposed construction
works are predicted to be largely confined to the specific works areas. With proper implementation of the
recommended mitigation measures, in particular the
establishment of dry condition for excavation works within the existing nullah and
adoption of good construction site practices as recommended in relevant
regulatory guidelines, unacceptable water quality impacts are not expected at
the identified WSRs including the Deep Bay Wetland Conservation Area and Mai Po
Inner Deep Bay Ramsar Site.
6.11.3
During the operation phase, the interception of polluted DWF
by the Project is expected to lead to improvement of water quality within the
YLTN and at Shan Pui River and is thus considered to be beneficial. With regular maintenance works to remove
excessive sediments, it is anticipated that the Project will not lead to any unacceptable
water quality impacts by altering the sediment deposition and erosion pattern
of the Project Site and its downstream area. Unacceptable water quality impacts are
also not expected to occur at any identified WSRs due to the small-scale and
infrequent maintenance works.
6.11.4
During emergency discharge of the collected DWF to the YLTN
(e.g. due to breakdown of the DWF pumping station), water quality of the nullah
is predicted to be similar to the existing condition
before operation of the Project. In
addition, given the low likelihood of the emergency discharge and proper
Emergency Response Plan will be in place and implemented, no unacceptable water
quality impact is expected to be associated with such discharge.
6.11.5
With proper implementation of the recommended mitigation
measures, no unacceptable residual water quality impacts are envisaged from the
construction and operation of the Project.
Nevertheless, a monitoring programme is recommended during the construction
phase to verify the predictions of the EIA and ensure compliance with the
assessment criteria.
6.11.6
Cumulative water quality impacts associated with concurrent
projects within the Study Area have been considered with no unacceptable impact
anticipated.
1)
B&V
(2019) Improvement of Yuen Long Town Nullah (Town Centre Section) ¡V
Investigation, Draft Drainage Impact Assessment Report (Issue 2)
2)
EPD
(2018) River Water Quality Report in Hong Kong 2018
3)
http://www.epd.gov.hk/epd/english/laws_regulations/enforcement/lw_map.html
- Accessed on 25 March 2019
5)
Table
2 of the Drainage Services Department's Sewerage Manual
6) Environmental Protection Department Website: Marine Water Quality Data (1986-2017) Available at http://epic.epd.gov.hk/EPICRIVER/marine/history [Accessed March 2019]