CONTENTS

6.                    WASTE  MANAGEMENT AND LAND CONTAMINATION   6-2

6.1                 Introduction  6-2

6.2                 Relevant Legislation, Policies, Standards and Criteria  6-2

6.3                 Assessment Methodology  6-6

6.4                 Expected Waste Sources  6-6

6.5                 Waste Management Assessment 6-7

6.6                 Mitigation Measures  6-13

6.7                 Land Contamination  6-18

6.8                 Residual Environmental Impacts  6-21

6.9                 Environmental Monitoring and Audit Requirements  6-21

6.10               Conclusion  6-22

 

6.                       WASTE  MANAGEMENT AND LAND CONTAMINATION

6.1                   Introduction

 

6.1.1             This Section identifies the potential waste arising from the construction and operation of the Project and assesses the potential environmental impacts associated with waste handling and disposal.  The main issues include the following:

 

·            Handling and disposal of construction and demolition (C&D) materials arising from nullah revitalisation, excavation and construction works; and

·            Management of chemical waste, general refuse and floating refuse.

 

6.1.2             Waste avoidance, minimisation, reuse and recycling, storage, collection, transport and disposal schemes have been examined and appropriate measures for waste reduction and management have been proposed.

 

6.1.3             This Section also identifies and assesses any potential land contamination issues arising from the Project and to propose remediation measures if necessary.

 

6.2                   Relevant Legislation, Policies, Standards and Criteria

 

6.2.1             The following discussion on legislative requirements and evaluation criteria applies to both the construction and operation phases of the Project.  The criteria and guidelines for evaluating potential waste management implications are laid out in Annexes 7 and 15 of the EIAO-TM under the EIAO (Cap 499).  The following legislation covers, or has some bearing upon the handling, treatment and disposal of the wastes generated from the construction and operation of the Project.

 

·            Waste Disposal Ordinance (Cap 354);

·            Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C);

·            Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N);

·            Land (Miscellaneous Provisions) Ordinance (Cap 28);

·            Public Health and Municipal Services Ordinance (Cap.132) – Public Cleansing and Prevention of Nuisances Regulation; and

·            Dumping at Sea Ordinance (Cap 466).

 

Waste Disposal Ordinance (Cap 354)

 

6.2.2             The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes, with waste defined as any substance or article, which is abandoned. Construction waste is defined as any substance, matter or thing that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works.

 

6.2.3             Under the WDO, wastes can only be disposed of at a licensed site. It should be noted that under the WDO, the authority may by license permit any person to provide services for the collection or removal of chemical waste or clinical waste but not for general refuse. In addition, the Land (Miscellaneous Provisions) Ordinance (Cap 28) requires that individuals or company who deliver public fill to the public fill reception facilities to obtain Dumping Licenses. For general waste there is no charge and this will need to be disposed of in a licensed facility.

 

Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C)

 

6.2.4             Chemical waste as defined under the Waste Disposal (Chemical Waste) (General) Regulation includes any substance being scrap material, or unwanted substances specified under Schedule 1 of the Regulation, if the specified substance or chemical occurs in such a form, quantity or concentration so as to cause pollution or constitute a danger to health or risk of pollution to the environment.

 

6.2.5             A person should not produce, or cause to be produced, chemical wastes without registration with the Environmental Protection Department (EPD).  Chemical wastes must either be treated using on-site facility licensed by EPD or be collected by a licensed collector for off-site treatment at a licensed facility.  Under EPD Regulation, the waste producer, collector and disposal facility must sign all relevant parts of a computerised trip ticket for each consignment of waste.  The computerized system is designed to allow the transfer of wastes to be traced from cradle-to-grave.

 

6.2.6             The EPD Regulation prescribes storage facilities to be provided on-site which include labelling and warning signs.  To reduce the risks of pollution and danger to human health or life, the waste producer is required to prepare and make available written emergency procedures for spillage, leakage or accidents arising from the storage of chemical wastes.  They must also provide their employees with training on such procedures.

 

Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N)

 

6.2.7             The Waste Disposal (Charges for Disposal of Construction Waste) Regulation defined construction waste as any substance, matters or things that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned.  It does not include any sludge, screening or matter removed in or generated from any desludging, desilting or dredging works.

 

6.2.8             The Construction Waste Disposal Charging Scheme entered into operation on 1 December 2005.  Starting from 1 December 2005, the main contractor who undertakes construction work under a contract with value of HK$1 million or above is required to open a billing account solely for the contract for waste disposal.  Application shall be made within 21 days after the contract is awarded.  

 

6.2.9             Depending on the percentage of inert materials in the construction waste, inert construction waste can be disposed of at public fill reception facilities.  However, mixed construction waste can be disposed of at construction waste sorting facilities, landfills and Outlying Islands Transfer Facilities which have different disposal costs.  The scheme encourages reducing, reusing and sorting of construction waste such that the waste producer can reduce their disposal fee.  Table 6.1 summarises the government construction waste disposal facilities, types of waste accepted and disposal cost.

 

Table 6.1       Government Facilities for Disposal of C&D Materials

Government Waste Disposal Facilities

Type of Construction Waste Accepted

Charge (HK$/Tonne)

Public fill reception facilities

Consisting entirely of
inert construction waste++

$71

Sorting facilities

Containing more than 50% by weight of inert construction waste++

$175

Landfills@

Containing not more than 50% by weight of inert construction waste++

$200

Transfer Facilities@

Containing any percentage of
inert construction waste++

$200

# Except for the Outlying Islands Transfer Facilities, the minimum charge load is 1 tonne, i.e. if a load of waste weighs 1 tonne or less, it will be charged as 1 tonne. A load of waste weighing more than 1 tonne will be charged at 0.1 tonne increment. For Outlying Islands Transfer Facilities, the charge is $20 per 0.1 tonne and the minimum charge load is 0.1 tonne.

++ Inert construction waste means rock, rubble, boulder, earth, soil, sand, concrete, asphalt, brick, tile, masonry or used bentonite.

@ If a load of waste contains construction waste and other waste, that load will be regarded as consisting entirely of construction waste for the purpose of calculating the applicable charge. 

 

Land (Miscellaneous Provisions) Ordinance (Cap 28)

 

6.2.10         The inert portion of C&D materials (also called public fill) may be taken to public fill reception facilities.  Public fill reception facilities usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the public fill reception facilities to obtain Dumping Licences.  The licences are issued by CEDD under delegated authority from the Director of Lands.

 

6.2.11         Individual licences and windscreen stickers are issued for each vehicle involved.  Under the licence conditions, public fill reception facilities will only accept earth, soil, sand, rubble, brick, tile, rock, boulder, concrete, asphalt, masonry or used bentonite.  In addition, in accordance with paragraph 11 of DEVB TC(W) No. 6/2010 “Trip Ticket System for Disposal of Construction and Demolition Materials”, the Public Fill Committee will advise on the acceptance criteria (e.g. no mixing of construction waste, nominal size of the materials less than 250mm, etc).  The material will, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable by the public fill reception facility supervisor.

 

Public Health and Municipal Services Ordinance (Cap 132) – Public Cleansing and Prevention of Nuisances Regulation

 

6.2.12         This Regulation provides a further control on the illegal dumping of wastes on unauthorised (unlicensed) sites.

 

Dumping at Sea Ordinance (Cap 466)

 

6.2.13         The Dumping at Sea Ordinance (DASO) is to control the disposal of substances and articles at sea and the dumping of substances and articles in the sea and under the sea-bed, and for connected purposes. All these operations would require a permit to be issued by the Director of Environmental Protection (DEP) as the Authority under the DASO.  Before an application of a marine dumping permit is made, requirements stipulated in ETWB TC(W) No. 34/2002 regarding the sampling, testing and disposal arrangement of dredged/excavated sediments must be fulfilled.

 

Other Relevant Guidance

 

6.2.14         Other guideline documents which detail how the Contractor will comply with the WDO and its associated regulations include:

 

·            Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat, Hong Kong Government;

·            Chapter 9 - Environment (1999), Hong Kong Planning Standards and Guidelines, Hong Kong Government;

·            New Disposal Arrangements for Construction Waste (1992), EPD & CED, Hong Kong SAR Government;

·            Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), EPD, Hong Kong Government;

·            Works Branch Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site, Works Branch, Hong Kong Government;

·            WBTC No. 2/93, Public Dumps, Works Branch, Hong Kong Government;

·            WBTC No. 2/93B, Public Filling Facilities, Works Branch, Hong Kong Government;

·            WBTC No. 16/96, Wet Soil in Public Dumps, Works Branch, Hong Kong Government;

·            WBTC Nos. 4/98 and 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects, Works Bureau, Hong Kong SAR Government;

·            WBTC Nos. 25/99, 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Sub-committee Papers; Works Bureau, Hong Kong SAR Government;

·            WBTC No. 12/2000, Fill Management; Works Bureau, Hong Kong SAR Government;

·            WBTC No. 19/2001, Metallic Site Hoardings and Signboards, Works Bureau, Hong Kong SAR Government;

·            WBTC No. 11/2002, Control of Site Crusher, Works Bureau, Hong Kong SAR Government;

·            WBTC No. 12/2002, Specification Facilitating the Use of Recycled Aggregates. Works Bureau, Hong Kong SAR Government;

·            ETWB TC(W) No. 34/2002, Management of Dredged/Excavated Sediment;

·            ETWB TC(W) No. 19/2005 Environmental Management on Construction Site; Environment, Transport and Works Bureau, Hong Kong SAR Government.

·            DEVB TC(W) No. 6/2010, Trip Ticket for Disposal of Construction and Demolition Materials;

·            DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness;

·            DEVB TC(W) No.2/2011, Encouraging the Use of Recycled and Other Green Materials in Public Works Projects;

·            DEVB TC(W) No. 9/2011, Enhanced Control Measures for Management of Public Fill; and

·            Hong Kong Blueprint for Sustainable Use of Resources 2013-2022, Environment Bureau, May 2013;

·            Project Administration Handbook for Civil Engineering Works (2014 Edition) – Section 4.1.3 relating to construction and demolition materials.

 

6.3                   Assessment Methodology

 

6.3.1             The potential environmental impacts associated with the handling and disposal of waste arising from the construction and operation of the Project were assessed in accordance with the criteria presented in Annexes 7 and 15 of EIAO-TM and summarised as follows:

·            Estimation of the types and quantities of the wastes to be generated based on information provided by the Engineering Design Team and the relevant research and studies on waste arisings;

·            Assessment of the secondary environmental impacts due to the management of waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges and traffic; and

·            Assessment of the potential impacts on the capacity of waste collection, transfer and disposal facilities.

 

6.4                   Expected Waste Sources

 

Construction Phase

 

6.4.1             The proposed works include the following construction activities:

·            Construction of tidal barrier;

·            Construction of pumping stations;

·            Refinements to the existing intersection of YLN and Yuen Long Bypass Floodway (YLBF);

·            Excavation at the downstream of YLN; and

·            Construction and modification of flood walls

 

6.4.2             Construction activities will result in the generation of a variety of C&D materials.  The C&D materials are usually mixed consisting of inert components (public fill) such as soil, rock, concrete, brick, and asphalt etc. and non-inert components (C&D waste) comprising metal, timber, paper, plastic and general refuse.  Sediment accumulated on the concrete lined section of YLN will need to be removed to facilitate channel widening and deepening works. Chemical waste may also arise as a result of construction activities.  Floating refuse may arise from litter at upstream and floating refuse from Shan Pui River through tidal water during heavy rain. The likely waste generated from the proposed construction works can be classified into the following categories:

·            C&D materials;

·            Excavated sediments;

·            Chemical waste;

·            General refuse; and

·            Floating refuse

 

6.4.3             The construction and modification of flood walls involves minor works at the existing parapet wall. The generation of C&D materials for such works would be minimal.

 

Operation Phase

 

6.4.4             During operation period, only a small amount of silt material and debris will be generated from the routine maintenance of the revitalised YLN. Similarly, small amount of screenings and chemical waste will be generated from the routine operation and maintenance of the pumping stations and tidal barrier.

 

6.4.5             Despite the small amount of wastes expected, handling and disposal of the above-mentioned wastes may cause environmental impacts and nuisance if it is not properly managed.

 

6.5                   Waste Management Assessment

 

Construction Phase

 

C&D Materials

 

6.5.1             The majority of C&D materials generated from the Project will arise during the construction of the pumping stations, tidal barrier and revitalisation of YLN.  It is expected that most of this material will be broken pieces of concrete, soil and rock from ground breaking and excavation works.  A preliminary estimate of the C&D materials and other wastes generated, reused and disposed during construction is shown in Table 6.2.

 

6.5.2             Most of the C&D materials are inert and approximately 5.7% of the materials can potentially be reused on-site.  For example, the generated soil can be stockpiled for later reuse for backfilling.  

 

6.5.3             However, there is limited potential to reuse the excavated concrete.   Nevertheless, the project team would explore reusing the inert C&D materials in other concurrent projects at later stage. For those inert C&D materials that cannot be reused, it is proposed to dispose the materials at Tuen Mun Area 38 Fill Bank via Yuen Long Highway, Tuen Mun Road, Wong Chu Road, Lung Fu Road and Lung Mun Road or other approved public fill reception facility.  It is estimated that an average of about 12 truck trips per day will be required to dispose these materials off-site ([1]). In addition, it is estimated that approximately 5,360 m3 of C&D wastes will be generated and disposed of at WENT Landfill via Yuen Long Highway, Tuen Mun Road, Wong Chu Road, Lung Fu Road, Lung Mun Road and Nim Wan Road. An average of about one truck trip every other day will be required to dispose the C&D wastes to landfill.

 

6.5.4             With proper implementation of good site practices and mitigation measures, no unacceptable environmental impacts are anticipated from management of the C&D materials generated.

 

Table 6.2  Estimated Quantities of C&D Materials and Other Wastes during Construction


Scope of Works

C&D Material Arisings (m3)

Reuse On-site (m3) (see Note 1)

Surplus C&D Materials (m3) for Off-site Disposal

C&D Waste (m3)

(see Note 5)

Chemical Wastes

General Refuse

Floating Refuse

Tidal Barrier

2,449

0

2,449

50

50 litres per month

(See Note 2)

32.5 kg per day (See Note 3)

(See Note 4)

Pumping Stations

34,719

0

34,719

1,500

Deepened Pump Sump

10,961

0

10,961

500

E&M Control

4,564

0

4,564

200

Channel Widening (Inlet)

2,126

0

2,126

50

Channel Widening (Outlet)

3,624

0

3,624

60

Revitalisation of YLN

77,438

7,744

69,694

3,000

Total

135,881

7,744

128,137

5,360

Notes:

1         Suitable rock should be reused as backfilling materials.

2         The amount of chemical waste will be dependent on the contractor’s on-site maintenance programme and the number of equipment and vehicles used on-site. Chemical waste should be collected by licensed contractor and properly disposed of at approved chemical waste treatment facilities.  Chemical waste will be generated throughout the construction period.

3         The amount of general refuse will dependent on the contractor’s operating procedures and housekeeping practices as well as the size of the workforce on-site. All such wastes should be sorted, reused and recycled before disposal at designated outlets. General refuse will be generated throughout the construction period.

4         With proper waste management and education, floating refuse arising from the construction activities is not anticipated. For floating refuse not generated from the Project (i.e. litter at upstream and floating refuse from Shan Pui River through tidal water), the quantity is not estimated under this EIA. However, any floating refuse trapped within the Project Area will be collected by contractor and disposed to landfill.

5         All C&D waste should be sorted, reused and recycled as far as possible before disposal at designated landfill.

 

Excavated Sediments

 

6.5.5             YLN was constructed in the 1960s into a concrete lined channel. An inflatable dam was constructed to prevent tidal water of Deep Bay from entering into Yuen Long Town. Over the years, a thin layer of sediment has accumulated on the YLN bed section from the inflatable dam to the confluence of old Kam Tin River. To facilitate the widening and deepening works of the Barrage, the sediment above the concrete section of YLN will need to be excavated for marine disposal according to prevailing guidelines. No marine disposal is proposed for the excavated materials generated from other works under the Project.

 

6.5.6             Based on site observation and preliminary estimation, the sediment is expected to be generally about 0.5 m in depth. Since the length and width of the YLN section requiring sediment excavation is about 500 m and 70 m, the volume of sediment is conservatively estimated at approximately 17,500 m3. Reusing the sediment as fill material within the Project will be further considered in the detailed design stage subject to the sediment quality and engineering design. The feasibility of reusing the sediment in other projects would be limited. If on-site reuse of sediment is not feasible, then marine disposal of sediment in accordance with ETWB TC(W) No. 34/2002 should be followed.

 

6.5.7             Pursuant to Appendix G, 3(i) of ESB-307/2018, a Sediment Sampling and Testing Plan (SSTP) with reference to ETWB TC(W) No. 34/2002 was prepared and submitted to EPD for approval. This Plan details the ranges of parameters to be analysed; the number, type and methods of sampling; sample preservation; chemical and biological laboratory test methods to be used. A total of twenty-two (22) sampling locations were proposed. EPD expressed no further comment on 11 June 2020. MFC/CEDD expressed no comment in principle on the rationale for sediment removal on 30 October 2020. Copy of the relevant correspondences and SSTP are enclosed in Appendix 6.1a and Appendix 6.1b. The sampling location plan is shown in Figure 6.1.

 

6.5.8             Sediment sampling was undertaken on 7 September 2020 in the excavation area in accordance with the agreed SSTP. Sampling and laboratory testing were conducted by Wellab Limited (HOKLAS Registration No. 083). As the depth of the sediment is only about 0.5 m, surface grab sample was taken using Van Veen Grab Sampler lowered from a boat. A total of eleven (11) surface grab samples were collected at locations S10, S11, S14 to S22. Sediment samples were not collected at locations S01 to S09, S12 and S13 after several attempts including relocations within the sampling grid. It was considered that no sediment is deposited at these locations. Results of chemical test are presented in Appendix 6.2. From the chemical testing results, Category H sediment was identified. No further biological screening is required for the collected sediment samples as the samples are classified as Category H with no contaminant levels exceeding 10 times Lower Chemical Exceedance Level (LCEL). In accordance with ETWB TC(W) No. 34/2002, Type 2 – Confined Marine Disposal should be adopted for Category H sediment with no contaminant levels exceeding 10 times LCEL.

 

6.5.9             The SSTP, testing results and disposal option presented above are only to fulfill the EIA Study under the EIAO. A separate SSTP/Sediment Quality Report in accordance with ETWB TC(W) No. 34/2002 would be prepared when applying for the dumping permit under DASO.  Additional SI works, based on the SSTP, should then be carried out by the contractor in order to confirm the disposal arrangements of the excavated sediment.  Sediment Quality Report (SQR), reporting the chemical and biological screening results and the estimated quantities of sediment under different disposal options, should then be submitted to EPD for agreement under DASO.

 

Sediment Disposal Options and Quantities

 

6.5.10         Based on the screening results, the disposal options for each of the sediment samples were determined in accordance with the ETWB TC(W) No. 34/2002. Referring to the construction programme, the proposed works of the Project comprises 3 primary construction phases. At phase 1, excavation works will be carried out at the sections of YLN for channel deepening and widening works, tidal barrier and pumping stations. At phase 2, excavation works will be conducted underground for piling works and other related woks. As the sediment in YLN is above +0.2 mPD, no sediment will be generated from this phase. At phase 3, no excavation works will be carried out. Therefore, excavated sediment will only be generated in phase 1. Estimated quantities of sediment under the disposal option is presented in Table 6.3.

 

Table 6.3    Estimated Quantities of Sediment under Disposal Option

Disposal Option+

Corresponding Category

Estimated In-situ Quantity* (m3)

Phase 1

Phase 2

Phase 3

Total
(Phase 1, 2 & 3)

Confined Marine Disposal at disposal site(s) allocated by MFC

Category H Sediment

17,500

0

0

17,500

Total:

17,500

0

0

17,500

Notes:
* The quantities shown in the table are estimates only and will be subject to further review during the detailed design and construction stage.

+ The disposal option is proposed base on the sediment sampling and testing results under this EIA study and is for this EIA study purpose only. The final disposal option should be subject to the results of separate SSTP and SQR submitted under the DASO and allocated by relevant authority.

6.5.11         The Project would seek to minimise the quantity of sediment to be excavated and explore the opportunity to reuse the excavated sediment during the detailed design stage. Sediment to be disposed at designated marine disposal areas would be carried out in accordance with ETWB TC(W) No. 34/2002 and the disposal options for the excavated sediment shall follow the procedures in ETWB TC(W) No. 34/2002. The recommended mitigation measures for marine disposal are discussed in Section 6.6 below. No adverse waste management implications are anticipated if the recommended mitigation measures are implemented.

Chemical Waste

 

6.5.12         Wastes classified as chemical waste are listed in the Waste Disposal (Chemical Waste) (General) Regulation.  Where the construction processes produce chemical waste, the contractor must register with EPD as a chemical waste producer.  Chemical waste should be collected by licensed contractor and properly disposed of at approved chemical waste treatment facilities. 

 

6.5.13         Variety of chemicals would be used for carrying out construction activities.  These chemicals may include paints, petroleum products, spent lubricants, grease, mineral oil, solvent and other chemicals used during construction activities.  Accidental spillages of chemicals in the works area may contaminate the top soils on exposed ground/earth.  The contaminated soil particles may be washed away by construction site runoff causes water pollution.

 

6.5.14         Chemical wastes pose serious environmental and health and safety hazards if not stored and disposed of in an appropriate manner as outlined in the Chemical Waste Regulation.  These hazards include:

·            Toxic effects to workers;

·            Adverse effects on water quality from spills; and

·            Fire hazards.

 

6.5.15         The amount of chemical waste cannot be accurately predicted at this stage since it largely depends on the contractor’s housekeeping measure. The amount is anticipated to be small (about 50 litres per month) and it is recommended that good housekeeping measures should be implemented to reduce the amount of chemical waste generated. The chemical wastes will be collected by licensed collector for the disposal of at licensed treatment facilities (e.g. Chemical Waste Treatment Centre (CWTC) at Tsing Yi) in accordance with relevant regulation and guideline.

 

6.5.16         With the incorporation of suitable arrangements for the storage, handling, transportation and disposal of chemical wastes under the requirements stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Waste, no unacceptable environmental impacts and hazards will result from the handling, transportation and disposal of chemical waste arising from the Project.

 

General Refuse

 

6.5.17         The presence of a construction site with workers and associated site office will result in the generation of general refuse (mainly consist of food waste, aluminium cans and waste paper) which requires off-site disposal.  The storage of general refuse has the potential to give rise to adverse environmental impacts.  These include odour if the waste is not collected frequently, windblown litter, water quality impacts if waste enters water bodies, and visual impact. 

6.5.18         Assuming up to 50 construction workers will be working on site at any one time, with a general refuse generation rate of 0.65 kg per worker per day ([2]), the amount of general refuse to be generated will be about 32.5 kg per day.  An adequate number of waste containers will be provided to avoid spillage of waste. 

 

6.5.19         Recyclable materials such as paper and aluminium cans will be separated and delivered to the local recyclers.  An adequate number of waste containers will be provided to avoid spillage of waste.  The non-recyclable waste will be collected and disposed of at the landfill on a regular basis.  With respect to the small quantity of general refuse to be transferred, it is not anticipated that it will cause unacceptable operational impacts to these facilities. 

 

Floating Refuse

 

6.5.20         The litter from the upstream may come down along the nullah to the Project Area. During heavy rain, the inflatable rubber dam may be deflated and floating refuse in Shan Pui River may be subsequently washed up onto the Project Area through tidal water. During construction phase, the construction workforce may also generate floating refuse (e.g. waste paper and empty containers) while working along the nullah. With proper waste management and training to workers, floating refuse arising from the construction activities is not anticipated. Any floating refuse trapped within the Project Area will be collected by contractor and disposed of to landfill. 

 

Operational Phase

 

6.5.21         During the operation phase, trash and sediment from the upstream of YLN will be stored behind the tidal barrier. Therefore, maintenance works will be carried out to remove trash and sediment regularly. Such waste will be removed by manual means and disposed of to landfill after the clearance works.  No unacceptable environmental impacts are thus anticipated.

 

6.5.22         Mechanical screens will be installed at the inlet chamber of the pumping stations. Small amount of screenings will be generated. The screenings will be properly packed and handled within the pumping station structure to avoid odour and hygiene nuisance. The screenings will then be transported to landfill for disposal. If the operation of the pumping stations would produce chemical waste, the operator / authority will register with EPD as a chemical waste producer. Routine maintenance of the pumping stations will generate a very small amount of chemical waste. The chemical wastes will be collected by licensed collector for the disposal of at licensed treatment facilities (e.g. Chemical Waste Treatment Centre (CWTC) at Tsing Yi) in accordance with relevant regulation and guideline. No unacceptable environmental impacts are thus anticipated.

 

6.6                   Mitigation Measures

 

Construction Phase

 

C&D Materials

 

6.6.1             The HKSAR Government's construction and demolition waste management policy follows the same hierarchy as for other wastes i.e. in order of desirability: avoidance, minimisation, recycling, treatment and safe disposal of waste. As the Project will generate more than 50,000 m3 of C&D materials, a Construction and Demolition Material Management Plan (C&DMMP) should be prepared and submit to the Public Fill Committee of CEDD in accordance with the Project Administration Handbook for Civil Engineering Works."

 

6.6.2             Training of construction staff should be undertaken by the contractor about the concept of site cleanliness and appropriate waste management procedures.  The contractor should develop and provide toolbox talk for on-site sorting of C&D materials to enhance workers’ awareness in handling, sorting, reuse and recycling of C&D materials.  Requirements for staff training should be included in the contractor’s Environmental Management Plan (EMP).

 

6.6.3             Good planning and site management practice should be employed to eliminate over ordering or mixing of construction materials to reduce wastage.  Proper storage and site practices will minimise the damage or contamination of construction materials.

 

6.6.4             Where waste generation is unavoidable, the potential for recycling or reuse should be rigorously explored.  If waste cannot be recycled, disposal routes described in the EMP should be followed.  A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be implemented.  In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills and to control fly-tipping, a trip-ticket system should be included.  One may make reference to DEVB TC(W) No. 6/2010 for details.

 

6.6.5             Regular cleaning and maintenance of the waste storage area should be provided.

 

6.6.6             Control measures for temporary stockpiles on-site should be taken in order to minimize the noise, generation of dust, pollution of water and visual impact.  These measures include:

·            Surface of stockpiled soil should be regularly wetted with water especially during dry season;

·            Disturbance of stockpiled soil should be minimized;

·            Stockpiled soil should be properly covered with tarpaulin especially when heavy rain storms are predicted;

·            Stockpiling areas should be enclosed where space is available;

·            Stockpiling areas should be located away from the water bodies; and

·            An independent surface water drainage system equipped with silt traps should be installed at the stockpiling area.

6.6.7             The identification of final disposal sites for C&D materials generated by the construction works will be considered during the detailed design stage of the Project when the volume and types of C&D materials can be more accurately estimated.  The Public Fill Committee of CEDD should be consulted on designated outlets (e.g. public filling area) for public fill, whilst EPD should be consulted on landfills for C&D waste.  Disposal of C&D waste to landfill must not have more than 50% (by weight) inert material.  The C&D waste delivered for landfill disposal should contain no free water and the liquid content should not exceed 70% by weight.

 

6.6.8             In order to avoid dust or odour impacts, any vehicle leaving a works area carrying C&D waste or public fill should have their load covered up before leaving the construction site.

 

6.6.9             C&D materials should be disposed of at designated public fill reception facilities or landfills.  Disposal of these materials for the use at other construction projects is subject to the approval of the Engineer and/or other relevant reception authorities.  Furthermore, unauthorized disposal of C&D materials in particular on private agricultural land is prohibited and may be subject to relevant enforcement and regulating actions.  The disposal of public fill and C&D waste will be controlled through trip-ticket system in accordance with DEVB TC(W) No. 6/2010.

 

Concrete Waste

 

6.6.10         Dry concrete waste (considered as public fill) should be sorted out from the other wastes and recycled for reuse or sorted out for disposal at designated public filling facilities.

 

Wooden Materials

 

6.6.11         All wooden materials used on-site should be kept separately from other wastes to avoid damage and to facilitate reuse.  Timber which cannot be reused should be sorted out from other wastes and stored separately from all inert wastes before being disposed of to landfill.

 

6.6.12         Reusable steel or concrete panel shutters, fencing and hoarding and signboard should be used as a preferred alternative to items made of wood, to minimise wastage of wood.  Attention should be paid to WBTC No. 19/2001 - Metallic Site Hoardings and Signboards to reduce the amount of timber used on construction sites.  Metallic alternatives to timber are readily available and should be used rather than new timber.  Precast concrete units should be adopted wherever feasible to minimize the use of timber formwork.

 

6.6.13         Only waste material is needed to be taken to a landfill.  It should be separated from recyclable wood and steel materials.  As for all waste types, these materials should be reused on-site or other approved sites before disposal is considered as an option.  Disposal to landfill should only be considered as a final option.  Contractors are responsible for storage of re-useable materials on-site.

 

On-site Sorting, Reuse and Recycling

 

6.6.14         All waste materials should be segregated into categories covering:

·            Inert C&D materials suitable for reuse on-site;

·            Inert C&D materials suitable for public fill reception facilities;

·            Recyclable C&D waste for recycling;

·            Remaining C&D waste for landfill;

·            Chemical waste; and

·            General refuse for landfill.

 

6.6.15         Proper segregation and disposal of construction waste should be implemented. Separate containers should be provided for inert and non-inert wastes.

 

6.6.16         Sorting is important to recover materials for reuse and recycling.  Specific area should be allocated for on-site sorting of C&D materials and to provide a temporary storage area for those sorted materials.  If area is limited, all C&D materials should at least be sorted on-site into inert and non-inert components. Non-inert materials (C&D waste) such as bamboo, timber, vegetation, packaging waste and other organic materials should be reused and recycled wherever possible and disposed of to the designated landfill only as a last resort.  Inert materials (public fill) such as concrete, stone, clay, brick, soil, asphalt and the like should be separated and reused in this or other projects (subject to approval by the relevant parties in accordance with the DEVB TC(W) No. 6/2010) before disposed of at a public filling facility operated by CEDD.  Steel and other metals should be recovered from demolition waste stream and recycled.

 

6.6.17         The reuse of inert materials such as soil, rock and broken concrete should be maximised.  Waste should be separated into fine, soft and hard materials.  With the use of a crusher, coarse materials can be crushed to make it suitable for use as fill materials where fill is required in the works.  This minimises the use of imported materials and maximizes the use of the C&D materials produced.

 

Excavated Sediments

 

6.6.18         The sediment should be excavated, handled, transported and disposed of in a manner that would minimize adverse environmental impacts.  

 

6.6.19         Requirements of the Air Pollution Control (Construction Dust) Regulation, where relevant, shall be adhered to during excavation, transportation and disposal of the sediment.

 

6.6.20         In order to minimize the exposure to contaminated materials, workers shall, if necessary, wear appropriate personal protective equipment (PPE) when handling contaminated sediments.  Adequate washing and cleaning facilities shall also be provided on site.

 

6.6.21         For off-site disposal, the basic requirements and procedures specified under ETWB TC(W) No. 34/2002 shall be followed. Marine Fill Committee (MFC) of CEDD is managing the disposal facilities in Hong Kong for the excavated sediment, while EPD is the authority of issuing marine dumping permit under the Dumping at Sea Ordinance (DASO).

 

6.6.22         To ensure disposal space is allocated for the Project, the Project Proponent should be responsible for obtaining agreement from MFC on the rationale for sediment removal and the allocation of the disposal site. The contractor(s), on the other hand, should be responsible for the application of the marine dumping permit under DASO from EPD for the sediment disposal.

 

6.6.23         The excavated sediments are expected to be loaded onto the barge at public barging point of which the exact location will be determined by the contractor(s) and agreed by EPD/CEDD and transported to the designated disposal sites allocated by MFC.  The excavated sediment would be disposed of according to its determined disposal options and ETWB TC(W) No. 34/2002.

 

6.6.24         Stockpiling of contaminated sediments should be avoided as far as possible.  If temporary stockpiling of contaminated sediments is necessary, the excavated sediment should be covered by tarpaulin and the area should be placed within earth bunds or sand bags to prevent leachate from entering the ground, nearby drains and surrounding water bodies.  The stockpiling areas for contaminated sediments should be paved with impermeable linings to avoid contamination to underlying soil or groundwater.  Separate and clearly defined areas should be provided for stockpiling of contaminated and uncontaminated materials.  Leachate, if any, should be collected and discharged according to the Water Pollution Control Ordinance (WPCO).

 

6.6.25         In order to minimize the potential odour / dust emissions during excavation and transportation of the sediment, the excavated sediments shall be wetted during excavation / material handling and shall be properly covered when placed on trucks or barges.  Loading of the excavated sediment to the barge shall be controlled to avoid splashing and overflowing of the sediment slurry to the surrounding water.

 

6.6.26         The barge transporting the sediments to the designated disposal sites shall be equipped with tight fitting seals to prevent leakage and shall not be filled to a level that would cause overflow of materials or laden water during loading or transportation.  In addition, monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by the DEP.

 

Chemical Waste

 

6.6.27         Where the construction processes produce chemical waste, the contractor must register with EPD as a chemical waste producer.  Wastes classified as chemical wastes are listed in the Waste Disposal (Chemical Waste) (General) Regulation. These wastes are subject to stringent disposal routes.  EPD requires information on the particulars of the waste generation processes including the types of waste produced, their location, quantities and generation rates.  A nominated contact person must be registered with EPD.  An updated list of licensed chemical waste collector can be obtained from EPD.

 

6.6.28         Storage, handling, transport and disposal of chemical waste should be arranged in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published by EPD, and should be collected by a licensed chemical waste collector.

 

6.6.29         Chemical waste should be stored away from channels or water bodies.

 

6.6.30         Suitable containers should be used for specific types of chemical wastes. The containers should be properly labelled (in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations), resistance to corrosion, stored safely and closely secured.  Stored volume should not be kept more than 450 liters unless the specification has been approved by the EPD.  Storage area should be enclosed by three sides by a wall, partition of fence that is at least 2 m height or height of tallest container with adequate ventilation and space.

 

6.6.31         Hard standing, impermeable surfaces draining via oil interceptors should be provided in works area compounds.  Interceptors should be regularly emptied to prevent release of oils and grease into the surface water drainage system after accidental spillages.  The interceptor should have a bypass to prevent flushing during periods of heavy rain.  Oil and fuel bunkers should be bunded and/or enclosed on three sides to prevent discharge due to accidental spillages or breaches of tanks.  Bunding should be of sufficient capacity to accommodate 110% of the volume of the largest container or 20% of the total volume of waste, whichever is largest.  Waste collected from any grease traps should be collected and disposed of by a licensed contractor.

 

6.6.32         Lubricants, waste oils and other chemical wastes are likely to be generated during construction.  Used lubricants should be collected and stored in individual containers which are fully labelled in English and Chinese and stored in a designated secure place.  If possible, such waste should be sent to oil recycling companies, and the empty oil drums collected by appropriate companies for reuse or refill.

6.6.33         The registered chemical waste producer (i.e. the contractor) has to arrange for the chemical waste to be collected by licensed collectors.  The licensed collector should regularly take chemical waste to a licensed chemical waste treatment facility (such as the Chemical Waste Treatment Centre in Tsing Yi).  A trip ticket system operates to control the movement of chemical wastes.

 

6.6.34         No lubricants, oils, solvents or paint products should be allowed to discharge into water courses, either by direct discharge, or as contaminants carried in surface water runoff from the construction site.

 

General Refuse

 

6.6.35         General refuse generated on-site should be stored in enclosed bins or skips and collected separately from other construction and chemical wastes and disposed of at designated landfill.  A temporary refuse collection point should be set up by the contractor to facilitate the collection of refuse by reputable contractors.  The chemical wastes will be collected by licensed collector for the disposal of at licensed treatment facilities (e.g. Chemical Waste Treatment Centre (CWTC) at Tsing Yi) in accordance with relevant regulation and guideline. The removal of waste from the site should be arranged on a daily or at least on every second day by the contractor to minimise any potential odour impacts, minimise the presence of pests, vermin and other scavengers and prevent unsightly accumulation of waste.

 

6.6.36         The recyclable components of the general waste generated by the workforce, such as aluminium cans, paper and cleansed plastic containers should be separated from other waste.  Provision and collection of recycling bins for different types of recyclable waste should be set up by the contractor.  The contractor should also be responsible for arranging recycling companies to collect these materials.

 

Floating Refuse

 

6.6.37         Any floating refuse trapped within the Project Area should be collected by contractor and disposed of to landfill.

 

Operation Phase

 

6.6.38         The screenings, silt materials and debris collected during operation and maintenance should be properly packed and transported to the designated landfill for disposal as soon as possible. All chemical waste should be properly stored, labelled and removed by licensed waste collectors in accordance with Waste Disposal (Chemical Waste) (General) Regulation.

 

6.7                   Land Contamination

 

Introduction

 

6.7.1             This Section identifies and assesses land lots and sites within the Project boundary which, due to their past or present land uses, are potentially contaminated sites.

 

Relevant Legislation, Policies, Standards and Criteria

 

6.7.2             The following requirements and guidelines are relevant to assessment of land contamination.

·            Section 3.1 of Annex 19 of EIAO-TM under the EIAO;

·            Guidance Note for Contaminated Land Assessment and Remediation (August 2007);

·            Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land Management (December 2007); and

·            Practice Guide for Investigation and Remediation of Contaminated Land (August 2011).

 

 

Assessment Methodology

 

6.7.3             According to the Practice Guide, site appraisal shall precede to determine the need for site investigation, and to provide the information to support a contamination assessment, which the findings will subsequently determine if site remediation is required.

 

6.7.4             The site appraisal consists of the following:

·            desk-top review of existing and historical survey maps;

·            interpretation of existing and historical aerial photographs;

·            review of land use record, permitted uses of existing private lots;

·            site walkover to verify the collected information; and

·            review the relevant government records (i.e. Dangerous Goods storage, spillage / leakage of chemicals, chemical wastes producers) of the Project Site.

 

6.7.5             The site walkover was undertaken to identify any physical clues of contamination, such as presence of industrial related building structures, chemical drums, chemical or oil stains, unnatural colours / odours and abandoned piping / mechanical components.

 

Site Appraisal Findings

 

Past Land Uses

 

6.7.6             A review of historical aerial photos (from 1963 – 2018) was undertaken to identify the past land uses within the project area in Yuen Long (Appendix 6.3). Based on the historic photos, the land use in the area was cultivation land and squatters. The proposed works along YLN only comprise works within the nullah itself, where adjacent private lots would not be affected. And as for the works along Kam Tin River, there would be no land excavation as only minor modifications to the existing parapet walls are anticipated. Thus, land contamination is not envisaged for either Yuen Long Nullah or Kam Tin River. According to the aerial photos, there was no presence of building structures that would indicate possible industrial activities in the proposed works area. A summary of the review is provided in Table 6.4.

 

Table 6.4     Review of Historical Aerial Photographs

 

Aerial Photo Reference

Year

Observed Land Use

Barrage

Fig No. 6.3_1

1963

The YLN had not been constructed yet. The surrounding was mainly cultivation land.

Fig No. 6.3_2

1967

The width of the river had been enlarged and the flow path of the river had been straightened. The YLN had been constructed. Some squatters were observed along the riverbank.

Fig No. 6.3_3

1972

Part of the river bed are observed, possibly related to low water level.

Fig No. 6.3_4

1981

The cultivation land located in the north-west direction of the site was removed and filling work are observed. The squatters were still occupying the riverbank.

Fig No. 6.3_5

1987

The land located in the north-west direction of the site was covered with medium dense vegetation. An area of vegetation clearance was observed in there, possibly related to site formation work.

Fig No. 6.3_6

1990

A car park and the Leeman Hydraulic Technology Company Limited were constructed in the north-west direction of the site.

Fig No. 6.3_7

1993

The Fortune Pharmacal was constructed in the east site direction of the site. The pond in the south-east of the site was filled and the covered by medium dense vegetation.

Fig No. 6.3_8

1996

Construction works are observed along the riverbank and a fibre dam was constructed upstream, not far away from the proposed location of the Barrage. The Hong Kong School of Motoring was constructed in the east direction of the site.

Fig No. 6.3_9

1999

The construction work observed in previous year was still in process.

Fig No. 6.3_10

2018

The land along the sides of the riverbank were covered by light dense vegetation.

 

Aerial Photo Reference

Year

Observed Land Use

Modifications to existing intersection of YLN and YLBF and Parapet Walls

Fig No. 6.3_11

1963

The site for the proposed modifications was cultivation land at that time.  The YLN and YLBF had not been constructed yet.

Fig No. 6.3_12

1967

The cultivation land had been converted into a nullah and has formed an integral part of YLN.

Fig No. 6.3_13

1972

No significant changes are observed.

Fig No. 6.3_14

1981

No significant changes are observed.

 

Fig No. 6.3_15

1987

No significant changes are observed.

 

Fig No. 6.3_16

1990

No significant changes are observed.

 

Fig No. 6.3_17

1993

Construction of the Yuen Long Highway had been started in north-east direction of the Site.

 

Fig No. 6.3_18

1996

The construction of Yuen Long Highway had been finished. No other significant changes are observed.

 

Fig No. 6.3_19

1999

No significant changes are observed.

 

Fig No. 6.3_20

2018

No significant changes are observed.

 

Present Land Uses

 

6.7.7             Site walkover was undertaken in March 2020 to verify existing land uses and to identify potential sources and signs of contamination, such as presence of industrial activities, chemicals, oil and hazardous waste handling and storage locations, bulk storage tanks, sumps, pipelines, staining, decolouration, abnormal odours, distressed vegetation, etc.

 

6.7.8             The walkover confirmed the area for constructing the pumping stations and tidal barrier. The proposed pumping stations and tidal barrier are currently vacant. No polluting activities / sources were observed within the project site areas during the walkover. The proposed works will not encroach upon any petrol filling stations, car repair / dismantling workshops, industrial premises or other major polluting areas.

 

6.7.9             According to the Land Requirement Study Report, the proposed construction works for the Project are all currently located within Government Land. Representative photos showing the existing site conditions are presented in Appendix 6.4.

 

Spillage / Leakage Records

 

6.7.10         Fire Services Department (FSD) and EPD have been enquired on any dangerous goods license and possible incident on spillage, leakage of chemicals or dangerous goods and chemical waste producers at the Project Area. Reply from FSD and EPD indicated that there have been no records of dangerous goods license since Year 1990 and no records of any incidents of spillage/leakage of chemical or dangerous goods with the Project Area in the past 5 years. The relevant correspondences are provided in Appendix 6.5. 

 

6.7.11         The EPD’s Chemical Waste Producer Register was inspected in September 2020 and no record of chemical producer was identified within the Works Area.

 

Summary of Findings

 

6.7.12         The proposed works will be constructed on existing vacant lands, carriageways, footpaths and the YLTN.  No signs of suspected land contamination due to past and present land uses were identified from review of historical aerial photos and during site walkover.

 

6.7.13         Based on the findings of the land contamination appraisal, no signs of suspected land contamination due to past and present land uses were identified from review of historical aerial photos and during site walkover. As such, submission of a Contamination Assessment Plan (CAP) as stated in Appendix G, 4.2 (i) of ESB-307/2018 for further soil sampling and analysis is considered not necessary.

 

6.8                   Residual Environmental Impacts

 

6.8.1             With the implementation of the recommended mitigation measures, no unacceptable residual impacts are anticipated from the construction and operation of the Project.

 

6.9                   Environmental Monitoring and Audit Requirements

 

Construction Phase

 

6.9.1             To facilitate monitoring and control over the contractors’ performance on waste management, a waste monitoring and audit programme will be implemented throughout the construction phase and a Waste Management Plan (WMP) will be prepared and implemented by the contractor in accordance with ETWB TC(W) No. 19/2005.  The aims of the monitoring and audit programme are:

 

·            To review the WMP, which will form part of the EMP in accordance with ETWB TC(W) No. 19/2005, including the quantities and types of C&D materials generated, reused and disposed of off-site; the amount of fill materials exported from/imported to the site and the quantity of timber used in temporary works construction for each process/activity;

·            To monitor the implementation and achievement of the WMP on site to assess its effectiveness; and

·            To monitor the follow-up actions on deficiencies identified.

 

6.9.2             Site inspections will be undertaken each week.  Particular attention will be given to the contractor’s provision of sufficient spaces, adequacy of resources and facilities for on-site sorting and temporary storage of C&D materials.  The C&D materials to be disposed of from the site will be visually inspected to ensure the absence of non-inert materials (e.g. general refuse, timber, etc.).  The waste to be disposed of at landfills will as practicable contain no observable inert or reusable/recyclable C&D materials (e.g. soil, broken rock, metal, and paper/cardboard packaging, etc.).  Any irregularities observed during the site inspections will be raised promptly to the contractor for rectification.

 

6.9.3             The findings of the waste inspections will be reported in the monthly Environmental Monitoring and Audit Report.

 

Operation Phase

 

6.9.4             No monitoring and audit are required during operation of the Project.

 

6.10               Conclusion

 

6.10.1         Wastes generated by the construction activities are likely to include C&D materials, excavated sediment and floating refuse from the construction works, general refuse from the workforce and chemical waste from any maintenance of construction plant and equipment.  Provided that these identified wastes arisen are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed in terms of the avoidance-minimisation-reuse-recycling-disposal hierarchy, unacceptable environmental impacts are not anticipated during construction of the Project.

 

6.10.2         The recommended measures can be enforced by incorporating them into the waste management requirements in the WMP as part of the EMP.  Environmental site audit would be necessary to ensure the implementation of proper waste management practices during construction.

 

6.10.3         For the operation phase, trash and sediment are expected to be produced by maintenance works of the tidal barrier. Such waste will be removed by manual means and disposed of to landfill after the clearance works.  Small amount of screenings and chemical waste will be generated and collected during operation and routine maintenance of the pumping stations. No unacceptable environmental impacts are anticipated with proper waste management practices.

 

6.10.4         A review of past and present land uses of the project site was conducted. Based on desk-top review and site walkover, the presence of contaminated land is not expected.



([1])  Assuming a capacity of 7 m3 per truck, bulk factor of 1.4 and 25 working days a month.  The duration of work is 83 months.

([2])  This is considered as a conservative estimate based on the number reported in a number of EIA reports approved under the EIAO.