7. ECOLOGICAL Impact Assessment
7.2 Statutory Requirements and Evaluation Criteria
7.4 Methodology for Baseline Establishment
7.6 Identification of Ecological Impacts
7.7 Potential for Cumulative Impacts
7.11 Monitoring and Audit Requirements
7.1.1
The EIA Study Brief (SB)
No. ESB-307/2018 for the Project issued on 9 March 2018 has stipulated the
technical requirements for ecological impact assessment (EcoIA), in Section
3.4.6 and Appendix D of EIA SB. The aim of the EcoIA is to protect, maintain or
rehabilitate the natural environment, in particular to avoid or minimize
impacts on recognized sites of conservation importance and other ecologically
sensitive areas such as the Mai Po Inner Deep Bay Ramsar Site, Wetland
Conservation Area (WCA) and Wetland Buffer Area (WBA), and mudflats / mangrove
at Kam Tin River (KTR) and Shan Pui River (SPR). The assessment is intended to
identify and quantify as far as possible the potential ecological impacts
arising from the Project including its construction and operation phases as
well as subsequent management and maintenance of the Project.
Key ecological
issues stipulated in EIA Study Brief
7.1.2
Key ecological issues stated
in the EIA Study Brief included but not limited to the following:
(a)
Natural and man-made
wetland habitats including mudflats, mangrove, streams, drainage channels,
fishponds, freshwater ponds, reedbeds, marshes and others, in particular the
mudflats at Shan Pui River and Kam Tin River exposed during low tide, as well
as roosting areas of Black-faced Spoonbill and Great Cormorant;
(b)
Migratory and overwintering
waterbirds roosting and/or feeding in the wetland habitats above;
(c)
The active egretry at Tung
Shing Lei (TSL) and the egrets and herons breeding there;
(d)
Intertidal/benthic
communities;
(e)
Mammals, in particular
Eurasian Otter;
(f)
Fireflies in particular
Bent-winged Firefly; and
(g)
Any other habitats and
species identified as having special conservation importance by this study.
7.1.3
This Section
presents the findings of an assessment of the potential ecological impacts
associated with the construction and operation of the proposed Project for Yuen
Long Barrage Scheme. It summarizes baseline information gathered from the
literature review and baseline ecological surveys on the ecological resources
in the assessment area, and describes the ecological importance of this area.
General
7.2.1
The relevant ordinances and regulations that are
applicable to this EcoIA include the followings:
¡P
Forests
and Countryside Ordinance (Cap. 96) and its subsidiary legislation, the
Forestry Regulations;
¡P
Wild
Animals Protection Ordinance (Cap. 170);
¡P
Environmental
Impact Assessment Ordinance (Cap. 499) and the associated Technical Memorandum
(EIAO-TM); and
¡P
Protection
of Endangered Species of Animals and Plants Ordinance (Cap. 586) and its
subsidiary legislation.
7.2.2
This EcoIA makes reference
to the following guidelines and standards:
¡P
Hong
Kong Planning Standards and Guidelines (HKPSG) Chapter 10, ¡§Conservation¡¨;
¡P
PELB
Technical Circular 1/97 Works Branch Technical Circular 4/97, ¡§Guidelines for
Implementing the Policy on Off-site Ecological Mitigation Measures¡¨;
¡P
EIAO Guidance Note No. 3/2010 ¡V Flexibility and Enforceability of
Mitigation Measures Proposed in an EIA Report;
¡P
EIAO
Guidance Note No. 6/2010 ¡V Some Observations on Ecological Assessment from the
Environmental Impact Assessment Ordinance Perspective;
¡P
EIAO
Guidance Note No. 7/2010 ¡V Ecological Baseline Survey for Ecological
Assessment;
¡P
EIAO
Guidance Note No. 10/2010 ¡V Methodologies for Terrestrial and Freshwater
Ecological Baseline Surveys; and
¡P
EIAO
Guidance Note No. 11/2010 ¡V Methodologies for Marine Ecological Baseline
Surveys.
7.2.3
This EcoIA also makes
reference to the following Mainland legislation:
¡P
List of
State Protected Wild Animals, promulgated by the State Council °ê®a«ÂI«OÅ@³¥¥Í°Êª«¦W¿ư; and
¡P
List of
Wild Plants under State Protection°ê®a«ÂI«OÅ@³¥¥Í´Óª«¦W¿ư(²Ä¤@§å).
7.2.4
Other international conventions and guidelines that
are relevant to this EcoIA include the following:
¡P
Convention on International Trade in Endangered
Species of Wild Fauna and Flora ("CITES"). This Convention regulates international
trade in animal and plant species considered to be at risk from such trade.
Depending on the degree of threat posed by international trade, CITES
classifies endangered species of animals and plants into three Appendices.
Appendix I includes highly endangered species threatened with extinction.
Commercial trade in these species is prohibited. Appendix II includes species
which are not presently threatened with extinction but may become so unless
trade is controlled. Trade of these
species is allowed but is subject to licensing controls. Appendix III species
are species identified by any Party to CITES as requiring cooperation in
controlling their trade. Their trade is subject to permits or certificates of
origin. Hong Kong's obligations under this Convention are enforced via the
Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586). The CITES authority for Hong Kong SAR is
the Department of Agriculture, Fisheries and Conservation (AFCD).
¡P
IUCN.
The World Conservation Union maintains, through its Species Survival
Commission, a ¡§Red List¡¨ of globally threatened species of wild plants and
animals (see http://www.iucnredlist.org).
The Red List is considered the authoritative publication to classify species
into nine groups as Extinct (EX) - No individuals remaining; Extinct in the
Wild (EW) - Known only to survive in captivity, or as a naturalized population
outside its historic range; Critically Endangered (CR) - Extremely high risk of
extinction in the wild; Endangered (EN) - Very high risk of extinction in the
wild; Vulnerable (VU) - High risk of extinction in the wild; Near Threatened
(NT) - Likely to become endangered in the near future; Least Concern (LC) -
Lowest risk. Does not qualify for a higher risk category. Widespread and
abundant taxa are included in these two categories: Data Deficient (DD) ¡V
Knowledge of the species is inadequate to enable assessment its risk of
extinction; and Not Evaluated (NE) ¡V Species not yet evaluated against the
criteria.
¡P
United Nations Convention on Biological
Diversity. This convention requires parties to regulate or manage biological
resources important for the conservation of biological diversity whether within
or outside protected areas, with a view to ensuring their conservation and
sustainable use. It also requires parties to promote the protection of
ecosystems, natural habitats and the maintenance of viable populations of
species in natural surroundings. The People¡¦s Republic of China (PRC) ratified
the Convention on Biological Diversity on 5 January 1993. The HKSAR Government
has stated that it is "committed to meeting the environmental
objectives" of the Convention (PELB 1996).
¡P
Convention on Wetlands of International
Importance Especially as Waterfowl Habitat (the "Ramsar Convention"),
which requires parties to conserve and make wise use of wetlands, particularly
those supporting waterfowl populations. The PRC ratified the Ramsar Convention
on 31 July 1992, and various wetlands have since been listed as wetlands of
international importance (i.e. Ramsar sites). One of these, Mai Po Marshes and
Inner Deep Bay Ramsar site in Hong Kong SAR, was listed on 4 September 1995.
¡P
Convention on the Conservation of Migratory
Species of Wild Animals (the Bonn Convention), which requires parties to
protect listed threatened or endangered migratory species occurring within
their boundaries.
Criteria of evaluating species of conservation
importance
7.2.5
Species of flora and fauna with conservation importance were
given special attention. In accordance with Table 3, Annex 8 of the EIAO-TM, the ecological value of
species was assessed in terms of protection status, distribution, and rarity. For
faunal species, the protection status (e.g. fauna protected under Cap.
170 (except birds as all wild birds
are protected under the ordinance but their conservation importance is not
equal), Cap. 586, and/or regional/global laws/conventions), the species
distribution (e.g. endemic), and the rarity
(e.g. rare or restricted, or level of concern highlighted in
Fellowes et al. (2002)) were considered. Similarly, floral species of conservation importance
are considered from protection status
(e.g. listed under Forestry Regulations and Cap.586 in Hong Kong,
listed by IUCN or CITES, or listed as Category I or II
protected species in mainland China);
species distribution (e.g. endemic);
and rarity (e.g. considered rare or very rare by Corlett et al.
(2000) and regarded as rare by Yip et al. (2010)).
However, exotic invasive
species, escaped cultivars or captive species, vagrants and introduced
species are excluded.
7.2.6
The
following laws/regulations and conventions
for conservation were relevant with
evaluation of the conservation importance of flora and fauna
species.
¡P
Forestry Regulations (Cap. 96A) which are
subsidiary legislation of the Forests and Countryside Ordinance (Cap. 96);
¡P
Category I/II/III in List of Wild Plants under
State Protection;
¡P
Considered ¡¥Rare¡¦ or ¡¥Very Rare¡¦ plant species
listed by Corlett et al. (2000) and regarded as ¡¥Rare¡¦ plant
species by Yip et al. (2010);
¡P
China Plant Red Data Book;
¡P
Threatened Species List of China¡¦s Higher Plants
(Qin et al., 2017);
¡P
Wild Animals Protection Ordinance (Cap 170);
¡P
Protection of Endangered Species of Animals and
Plants Ordinance (Cap 586);
¡P
Category I or II State Protected Wild Animals;
¡P
PRC Wild Animal Protection Law;
¡P
China Red Data Book of Endangered Animals;
¡P
China Species Red List;
¡P
Red List of China¡¦s Vertebrates;
¡P
The International Union for Conservation of
Nature and Natural Resources (IUCN) Red
List of Threatened Species (Species which are classified by IUCN as Near
Threatened (NT), Least Concern (LC), Data Deficient (DD), or Not Evaluated
(NE), and not covered by any other laws/regulations/conventions are not
considered of conservation importance in the present EcoIA);
¡P
The Convention on International Trade in
Endangered Species of Wild Fauna and Flora (CITES); and
¡P
Fauna species considered of concern in Fellowes et al. (2002).
7.2.7 The species identified from both literature review and the ecological surveys as having conservation importance were further categorized in accordance with their relevance to potential impacts, which were assessed in accordance with the EIAO-TM criteria.
7.3.1
As stated in Section 3.4.6.1 of EIA SB, the assessment
area for the purpose of EcoIA includes all areas within 500m distance from the
site boundary of the Project and other areas likely to be impacted by the
Project. For aquatic ecology, the assessment area is the same as the water
quality impact assessment i.e. include areas within 500m from the site boundary
of the Project and cover the Deep Bay Water Control Zone as designated under
the Water Pollution Control Ordinance and the water sensitive receivers in the
vicinity of the Project.
Literature review methodology
7.4.1
A literature review was conducted to
characterize the existing conditions within the assessment area and to identify
habitats and species of potential importance in the area. The literature
review covers Government and private sector reports, independent and Government
published literature, academic studies, vegetation maps and land use maps.
7.4.2
Reviewed information includes, but is not
limited to the following:
¡P
EIA reports in the area including but not
limited to AEIAR-220/2019 Yuen Long Effluent Polishing Plant; AEIAR-223/2020 Improvement
of Yuen Long Town Nullah (Town Centre Section);
¡P
Hong Kong Biodiversity ¡V Newsletter of
Agriculture, Fisheries and Conservation Department (AFCD);
¡P
Publications of AFCD;
¡P
Development Permission Areas Plan, Draft Outline
Zoning Plans and Outline Zoning Plans of Town Planning Board;
¡P
Annual report and other publications of The Hong
Kong Bird Watching Society;
¡P
Memoirs of Hong Kong Natural History Society;
and
¡P
Porcupine! Newsletter of Ecology &
Biodiversity, The School of Biological Sciences, The University of Hong Kong.
Ecological
survey methodology
7.4.3
In accordance with the requirements of the EIA Study
Brief, necessary field surveys of at least 12 months covering both dry and wet season
were required. Under the present EIA study, a 13-month ecological survey
programme was completed to verify the information from the desktop review, fill
the information gap in particular the Project Site and nearby habitats, and
fulfil the objectives of this EIA.
The survey was carried out by qualified personnel and the detailed
methodology and findings of the ecological review is presented in Appendix
7.1.
7.4.4
Ecological survey items included the followings:
¡P
Habitat and vegetation;
¡P
Terrestrial mammal including night survey and
camera trapping;
¡P
Avifauna including night survey and flight
behavior of waterbirds;
¡P
Egretry;
¡P
Herpetofauna;
¡P
Butterfly and odonate;
¡P
Firefly and;
¡P
Aquatic assemblage; and
¡P
Intertidal/benthic.
7.4.5
The ecological survey programme is listed in Table
7.1.
Table 7.1. Ecological Survey Programme from July 2019 to July 2020
Ecological Field Surveys |
2019 |
2020 |
|||||||||||
Wet Season |
Dry Season |
Wet Season |
|||||||||||
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
|
Habitat and
Vegetation Survey |
|
✓ |
✓ |
|
|
|
|
|
✓ |
|
|
|
|
Terrestrial
Mammal Survey |
✓ |
|
✓ |
|
✓ |
|
✓ |
|
✓ |
|
✓ |
|
|
Terrestrial
Mammal Survey (Nighttime) |
✓ |
|
✓ |
|
✓ |
|
✓ |
|
✓ |
|
✓ |
|
|
Infra-red Camera
Surveys for Eurasian Otters |
Carried out continuously throughout the 12-month survey
period |
|
|||||||||||
Avifauna
Transect Survey |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|
Avifauna
Transect Survey (Nighttime) |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|
Survey of Ardeid
Night Roost at KTR |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|
Survey of
flight behaviour of waterbirds |
✓# |
✓# |
✓ |
✓ |
✓* |
✓* |
✓* |
✓* |
✓ |
✓# |
✓# |
✓ |
|
Egretry
Survey |
|
|
|
|
|
|
|
|
|
✓ |
✓ |
✓ |
✓ |
Herpetofauna
Survey |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|||||||
Herpetofauna
Survey (Nighttime) |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|||||||
Butterflies
and Odonates Survey |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|||||||
Fireflies |
✓ |
✓ |
✓ |
✓ |
✓ |
✓ |
|||||||
Aquatic
Assemblages Survey^ |
|
|
✓ |
|
|
|
|
|
✓ |
|
|
|
|
Intertidal
/ Benthic Survey |
|
|
✓ |
|
|
|
|
|
✓ |
|
|
|
|
* Additional survey of flight behaviour of roosting waterbirds in winter
# Additional
survey of flight behaviour of ardeids during breeding season
^ As a fish
species Gobiopterus macrolepis of conservation importance
was recorded during the survey, additional sampling locations were added
7.5.1
The baseline conditions of the ecological resources of
the habitats in the assessment area are reviewed by desktop literature review
and dedicated field surveys.
7.5.3
Findings of the literature review (Appendix
7.1) identified a number of habitats and species of conservation
importance recorded within and surrounding of the Project Site. Detailed
findings of the field surveys are presented in Appendix 7.1.
7.5.4
The field surveys confirmed that the Project Site
(components of proposed barrage, parapet walls and the revitalized section)
lies mainly on channelized watercourse, plantation and developed area, with low
to middle, low and very low ecological value, respectively. The ecological
values of the wetland associated habitats within the 500m assessment area
including channelized watercourse (only YLN Section 4, SPR, KTR),
semi-natural watercourse, pond, abandoned wet agricultural land/freshwater
marsh, tidal marsh, mangrove, reedbed and mitigation wetland are at least low
to middle, middle or middle to high.
7.5.5
The ecological values of the habitats recorded within
the 500m assessment area have been evaluated in accordance with the criteria
stipulated in Table 2 of Annex 8 of EIAO-TM. Details of the evaluation are
provided in Appendix 7.1. the overall ecological
values of the habitats recorded in the 500m assessment area are summarized in Table 7.2.
Table 7.2 Habitat
Evaluation
Habitat |
Overall
Ecological Value |
Habitat found
in Project Site? |
Channelized watercourse |
Very low: YLN Sections 1,2,3 and other minor
channelized watercourses; Low:
upper section of Yuen Long Bypass Floodway (YLBF) and Sham Chung River
(SCR); Low to Middle: YLN Section 4, lower section
of YLBF; Middle: SPR and KTR |
Yes, revitalization will be conducted in YLN
Sections 1-4, the proposed barrage will be in YLN Section 4 |
Semi-natural watercourse |
Middle |
No |
Pond |
Low to Middle: other ponds within the 500m
assessment area; Middle: abandoned ponds within Nam Sang Wai
(NSW) |
No |
Tidal marsh |
Middle |
No |
Mangrove |
Middle |
No |
Reedbed |
Middle to High |
No |
Abandoned wet agricultural land / freshwater
marsh |
Low to Middle |
No |
Mitigation wetland |
Middle |
No |
Shrubland |
Low to middle |
No |
Agricultural land |
Very low |
No |
Mixed woodland |
Low |
No |
Plantation |
Low: Remaining plantation within the 500m
assessment area; Low to middle: plantation in NSW; Middle: for the locations that hold TSL
egretry and night roost of ardeids |
Yes, the pumping station and E&M room will be on the remaining plantation within the 500m
assessment area, but no impact and far away from egretry or night roost. |
Wasteland |
Very low |
No |
Developed area |
Very low |
Yes, most of the proposed parapet walls will
be on developed area |
7.5.6
Species of flora and fauna with conservation
importance were given special attention. A total of 2 flora, 3 mammals, 51
avifauna, 5 herpetofauna, 9 butterflies, 3 odonates, 1 aquatic fauna and the
endemic Bent-winged Firefly, of conservation importance were recorded in the
500m assessment area. Among the species of conservation importance, a total of
14 species of birds of very low abundance and a fish species of conservation
importance were recorded inside the Project Site. Detailed evaluation of the
species of conservation importance is shown in Appendix 7.1.
Identification of Key Works
7.6.1
The proposed works of the present
Project will include three major components (1. proposed barrage, 2.
parapet walls, and 3. revitalization): provision of a
barrage at the northern end of Yuen Long Nullah, the modification of parapet
wall along a section of Kam Tin River, and the provision of parapet wall along a section of Yuen Long Nullah to the south of Yuen Long Highway, and a
section of Sham Chung River (the existing railing (~1m) in the section of YLN
and Sham Chung River will be replaced by parapet walls of ~1m high). The location plan of the three
major components is shown in Drawing No.
400171/B&V/LAY/001 in Appendix
1.1.
7.6.2
Construction of the barrage
generally involves common civil engineering construction activities such as
site clearance, excavation, formwork, substructure and superstructure
construction, concreting, landscaping and E&M installation. The proposed
works for the barrage shall comprise of 3 phases: Phase 1 ¡V channel deepening,
widening and stabilization works (cofferdam for temporary diversion, excavation
works by open cut, slope stabilizing (concreting works)); Phase 2 ¡V
construction of pumping stations, E&M control room and link bridge
(cofferdam for temporary diversion, foundation works (percussive piling /
concreting works), superstructure and E&M installation works); Phase 3 ¡V
tidal barrier assembly and installation (cofferdam for temporary diversion,
flow optimising walls in YLN, superstructure and E&M installation works).
7.6.3
Additional concrete parapet
walls would be constructed along YLN
and Sham Chung River along sections that are vulnerable to flooding. The
existing parapet walls along Kam Tin River would be heightened with opaque
panels.
7.6.4
Upon completion of the
barrage, revitalization works along YLN will be conducted. The revitalization
works of YLN will involve smaller scale construction activities such as
breaking of concrete nullah bed, excavation, decommissioning of existing low
flow pumping station and inflatable dam, construction of hard landscapes
(concreting works) and installation of greenery (planting).
Habitat loss
7.6.5
The
proposed barrage scheme involves construction of a barrage in the lower section
of YLN (YLN Section 4), the proposed pumping stations and E&M control room
will be constructed beside the barrage on the Nullah as
well as adjacent plantation
(Figure
7.1). New and heightening of parapet walls will be constructed in
upper YLN (YLN Section 1) as well as Sham Chung River and Kam Tin River,
respectively.
7.6.6
Parapet walls ¡V The new and heightening of parapet walls will be of simple
structures, in linear shape, and situated above existing concrete parapet walls or replacing existing
hand rail. They will occupy limited area size on developed area
which are of very low ecological values, and will not change the
nature of the existing habitat after construction and thus is not expected to
cause habitat loss.
Although a tiny part of the heightened parapet in Kam Tin River is situated within the
WBA, all construction works for the heightened parapet walls will be confined to land areas to avoid direct impacts on
wetland (i.e. channelized watercourse). A night roost of ardeids was recorded
next to Kam Tin River which is just next to the proposed parapet wall. However,
the trees of the ardeids¡¦ night roost will not be encroached or
affected by the works.
Hence, the direct ecological impact due to the proposed parapet walls are minimal
and habitat loss is not
expected.
7.6.7
Proposed barrage ¡VThe construction
of the proposed
barrage, pumping stations and E&M control room will result in small direct loss of
habitats in plantation and channelized watercourse (YLN Section 4) which are of low and low
to middle ecological values, respectively and are located at
the fringe of WBA. A total
0.29ha of plantation will be encroached due to the area occupied by pumping
station (0.10ha) and E&M room (0.09ha), and the space released for channel
widening works (0.10ha). As the plantation was dominated by exotic plant
species and without any species of conservation importance recorded (different from the plantation in
NSW of which ecological value is comparatively higher (see Table 30 of Appendix 7.1), the direct impact due to
the loss of small area of plantation is considered minor. Compensatory
planting will be proposed under LVIA.
7.6.8
The affected channelized watercourse (YLN Section 4) is the northern end
of YLN. Similar with other
upstream sections, this section
still has concrete-lined banks and bottom, but the concrete channel bed has
been deposited with mud sediments originated from the Deep Bay area. YLN Section 4 up to the location of
existing inflatable dam currently receives brackish waters from Deep Bay. When the deposited sediments are exposed and
waterbirds may be present in the channel. There were records of wetland-dependent bird species in YLN Section 4 and some of them are
considered as species of conservation importance, but both bird diversity and
abundance were much lower than the nearby SPR and KTR. In fact, the construction
of the proposed barrage
system in YLN Section 4 will directly
encroach about 1.02ha of channelized watercourse (i.e. 0.26ha for the footprint
of tidal barrier and
pumping station which will constitute permanent loss; 0.76ha of the watercourse will be deepened and widened which will
constitute temporary loss), the direct encroachment of the
habitat (i.e. 1.02ha of watercourse during construction phase) will be very
limited. On the other hand,
the existing inflatable dam with an area of approximately 255m2 will
be decommissioned, so that some area (i.e. 255m2) of waterbody will
be re-provided. In addition, the operation of the future tidal barrier can still allow water from the
Deep Bay flushing in, and reach beyond the existing inflatable dam location
(when without the obstruction of the inflatable dam). It is estimated that about 50m stretch of YLN upstream of the inflatable dam can
provide additional ~0.26ha of wetland habitat, of similar size to
those occupied by the barrage, and achieve no net loss of wetland.
7.6.9
During
construction of the barrage, the proposed works will be conducted in phases and the channelized watercourse within
the footprint will be temporarily isolated for works part by part (possibly
finish the construction of one side and then the other side). The watercourse would not be blocked at any given time, and will allow brackish waters flushing into the YLN Section 4 outside the barrage
works areas. Hence, the
brackish water habitat (i.e. in between the existing inflatable dam and the
proposed barrage) will only be lost partially during construction, plus minor additional area of plantation and
watercourse which will be
lost temporarily due to the works space and the cofferdam. Due to the small area size (when compared to similar habitats
within Deep Bay) and nature (i.e. man-made structure) of wetland habitat, availability of
similar habitats nearby,
the direct impact of temporary habitat loss due to the construction of the proposed barrage is considered minor to moderate.
7.6.10 Revitalization ¡V The revitalization works in YLN aims for
improvement of the environment and enhancement of the ecological functions, and
might involve
demolition of the existing channel bed. Direct impacts
are expected. Although few bird species of conservation importance were
recorded in YLN Sections 1 to 3, the abundance were very low. Together with the
naturalness and environmental settings, the ecological values are ranked as
very low. Hence, the potential ecological impacts due to the revitalization
works for YLN Sections 1-3
are considered minor. For YLN Section 4, the existing concrete
nullah bed will be removed, deepened and filled with natural substrate. Currently the part
downstream to the existing inflatable dam within this section had records of a number of wetland-dependent bird
species and some of them are considered as species of conservation importance, while
the part upstream to the inflatable dam is mostly dry with the bare concrete
bed exposed, similar with YLN Sections 1-3. The revitalization works will be
conducted after the construction of the barrage. Similarly, the revitalization works will
also be conducted part by part, in particular within YLN Section
4, and the flow will be maintained at any given time. It is considered that the temporarily habitat
loss caused by the revitalization works in YLN Section
4 will be of similar magnitude with that due to the construction of the barrage discussed above, the potential ecological impacts on
YLN Section 4
are considered minor to moderate. It is expected that the ecological values will be increased due to the
revitalization, in particular YLN Section 4 with the theme of ecological enhancement. While the
decommissioning of existing low flow pumping station and inflatable dam will
release the land space as well as the channel area, turning developed
area habitats into channelized watercourse, and thus direct impacts to ecology is
minimal and no habitat loss is anticipated.
7.6.11 Estimated loss of area of each
habitat type is summarized in Table
7.3.
Table 7.3 ¡V Estimated Loss of Area of Each Habitat Type
Habitat |
Works |
Temporary
Loss (ha) |
Permanent
Loss (ha) |
Developed Area |
Revitalization |
6.94 |
0 |
Plantation |
Barrage scheme |
0.29 (channel widening works: 0.10;
pumping station: 0.10; E&M room: 0.09) |
0.29 |
Channelized watercourse (brackish water habitat) |
Barrage scheme |
1.02 (tidal barrier: 0.09; pumping
station: 0.17; channel deepening and widening: 0.76) |
0 (although 0.26ha of watercourse
due to tidal barrier and pumping station will be lost permanently, the
replacement of existing inflatable dam with the operation of tidal barrier
will allow waters from Deep Bay flush in 50m beyond the existing inflatable
dam to achieve no net loss of wetland) |
Revitalization |
13.64 |
0 |
|
|
Total |
21.89 |
0.29 |
Fragmentation
7.6.12
Fragmentation is the appearance of discontinuities in
habitat that render it less attractive to flora or fauna or isolate populations
of a species, potentially leading to reduced viability of a population. In the
current study, potential fragmentation impacts to major channelized
watercourses include additional barriers to the movement of aquatic life
especially the proposed barrage. The flight path of waterbirds might also be
affected by both the proposed parapet walls and barrage.
7.6.13
Water connectivity ¡V As YLN Section 4 receives brackish waters
from the Deep Bay during high tide, aquatic life follow tidal influence might
be blocked by the construction works of the proposed barrage. The ecological
value of YLN Section 4 is
considered low to middle with low diversity and abundance of aquatic fauna. The
ecological value of this section of channelized watercourse is mainly due to
the presence of waterbirds. Although the diversity and abundance of aquatic
fauna were low, a fish species of conservation importance Gobiopterus
macrolepis was found along channel margins at YLN Section 4. In an extreme case, fragmentation
impacts may result in the loss of populations of a species if the remaining
fragments are too small to support a viable population. Species mostly affected
by fragmentation impacts are usually habitat specialists, terrestrial species
and species with low mobility. In
order to maintain the connectivity during construction phase, the pumping
stations and tidal barriers will not be constructed simultaneously (i.e. will
be by 2 sections, one of the pumping station and half of the tidal barrier at a
time). Hence, the channelized
watercourse will not be completely blocked and allow brackish waters flush in
and out YLN Section 4 during high tide and low tide, respectively,
as in the existing situation. The water body between
the proposed tidal barrier and the existing inflatable dam will be maintained
except the ongoing works area for the
pumping station and tidal barrier. The completed part of the tidal barrier will be opened to allow water to flush in, and
another works area will be demarcated for construction of the remaining part of barrier. On the other hand, a cofferdam will be
constructed to divert the water from upstream to downstream of the channel. Hence, the ecological impact to
aquatic fauna due to fragmentation during construction phase is considered minor.
7.6.14
Flight-line of waterbirds ¡V
Flight-line impacts are another type of fragmentation impact that affect flying
fauna. Typical flight-lines involve routes followed between feeding and
roosting areas or between feeding and breeding areas. Development located on a
flight-line may result in a decrease in the suitability of a foraging, breeding
or roosting site by preventing movement between sites. In an extreme case, this
may lead to the total abandonment of one or both sites. There may also be an
increased risk of mortality by collision with structures constructed on or
close to a flight-line.
7.6.15
The proposed parapet walls and barrage might potentially have fragmentation
impact on flight-lines of ardeids or other waterbirds (e.g. Great Cormorant).
As there are existing parapet walls along Kam Tin River and only heightening of
~200mm is proposed (i.e. from existing 1m to 1.2m), and in accordance with ecological survey results, the recorded flight heights of waterbirds including
ardeids and Great Cormorant passing through the location of the proposed parapet walls in Kam Tin River were all
above 10m, potential impacts to waterbird flight-lines due to the heightening of parapet walls are not expected.
While additional concrete parapet walls will be constructed along YLN and Sham Chung River along sections that are vulnerable to flooding,
but those sections are already with metal railing (~1m high) which will be
replaced by concrete parapet wall of the same height. Besides, the areas are
surrounded by developed area and, the abundance and diversity of waterbirds
were very low, the potential impacts due to fragmentation of the proposed
parapet walls in YLN and Sham Chung
River are also not expected.
7.6.16
On the other hand, the height of the proposed
barrage varies from 6 ¡V 19 mPD (tidal barrier: 0-6 mPD; link bridge: 7.2 mPD;
pumping station: 19 mPD; E&M building 13.6 mPD), and a portion of
waterbird¡¦s flight-lines (347
observations from 36 survey sessions (30min per session) during a 12-month period, approximately less than
10 birds per survey) flied along the YLN Section
4 across the proposed barrage location with the
height below 10m, among other waterbird flight-lines above 10m and even higher than
20m reported from the same surveys. This indicated that the flight behaviour of some
water birds currently flying along the YLN will be affected. Due to the artificial
nature and disturbance level in YLN, major feeding and roosting grounds in the
upstream of YLN (i.e. YLN Sections
1 to 3) are not anticipated. In fact, the abundance of waterbirds recorded in YLN Section
4 was much lower when compared with the abundance recorded in
Shan Pui River and Kam Tin River from the current
study, and also the abundance in Deep Bay Area according to the Monthly
Waterbird Monitoring conducted by Hong Kong Bird Watching Society (Table
7.4). Besides, various flight
heights of the ardeids as well as other waterbirds were observed including those fly over
infrastructures of certain height such as
highways. For example, the breeding ardeids in Tung Shing Lei Egretry flied
over Tsing Long Highway were all well over 10m in
height (the Highway is about 20m in height). And as mentioned above the recorded flight
heights of waterbirds passing through the location of the proposed parapet walls in Kam Tin River were also all above 10m. With the future barrage in place, the change of flight height of waterbirds would be limited as the tidal barrier and link bridge
will be around 6 and 7.2mPD, respectively. Hence, the potential fragmentation
impacts to ardeids and other waterbirds from the proposed barrage are
considered minor due to the low
abundance, manoeuvrability of waterbirds and the unlikely feeding and roosting
grounds in the upstream of YLN.
7.6.17
According to the ecological baseline survey, the
breeding ardeids at Tung Shing Lei egretry mainly flying a general northward direction
with occasional individuals landing at the ponds in front of the egretry or
flying western to Yuen Long Town direction. Hence, the potential impacts to the
flightpath of breeding ardeids at the egretry are not expected. Besides, a new
egretry at Shan Pui River (i.e. Shan Pui River Egretry) was newly found at and
near the Yuen Long Sewage Treatment Plant. Potential impacts to the breeding ardeids from the new egretry are not
expected, as no breeding ardeids were observed flying from that egretry towards
the Project Site. In addition, as it is over 1 km from the Project Site and
there are abundant suitable wetland habitats near the egretry, in particular to
the north of the egretry.
Table 7.4 Comparison
of Waterbirds¡¦ Abundance among the Assessment Area, Nam Sang Wai, Shan Pui
River and Deep Bay Area during the Ecological Survey Period
|
Current Study |
Monthly Waterbird Monitoring Conducted by HKBWS** |
|||
Shan Pui River |
YLN Section 4 |
Shan Pui River*** |
Nam Sang Wai |
Deep Bay Area |
|
Species no.* |
25 |
16 |
33 |
39 |
91 |
Total abundance
(during the monitoring period)* |
1,143 |
228 |
3,373 |
22,847 |
201,194 |
Average per month
(abundance) |
98 |
23 |
375 |
2,539 |
22,355 |
*Species no. and total
abundance of the monthly waterbird monitoring were from Jul 2019 to Mar 2020
(versus Jul 2019 to Jun 2020 from current study)
**Mai Po Inner Deep Bay
Ramsar Site Waterbird Monitoring Programme 2019-20 Biannual Report 1 (April to
September 2019) p.35-43; Mai Po Inner Deep Bay Ramsar Site Waterbird Monitoring
Programme 2019-20 Monthly Waterbird Monitoring Biannual Report 2 (October 2019
to March 2020) p.31-48
***Shan Pui River from
monthly waterbird monitoring refers to lower course of Shan Pui River where is
not overlapped with the surveyed section from current study
Construction Phase ¡V Indirect
Impacts
Water
quality
7.6.18
During
the construction phase, aquatic and the intertidal habitats (e.g. tidal marsh,
mangrove) near the proposed works including construction of
barrage, decommissioning
of existing low flow pumping station and inflatable dam and revitalization would be potentially
impacted by surface runoff, especially during rainstorm. The surface runoff
might be polluted by sedimentation from site surfaces; excavation and
backfilling works, wash water from dust suppression sprays and wheel washing
facilities, concrete spillage, and chemicals spillage such as fuel, oil,
solvents and lubricants from maintenance of construction machinery and
equipment.
7.6.19
Elevated
suspended solid levels caused by site runoff could increase the suspended
solids load in the water bodies, and could decrease dissolved oxygen levels. A
lower oxygen level would affect stationary species, whilst mobile species would
tend to temporarily avoid the area. The result could be a temporary reduction
in aquatic life abundance and/or change in distribution. Shan Pui River, tidal
marsh and mangrove are downstream to the proposed works, all with middle
ecological values, and supported a fish species of conservation importance
(i.e. Gobiopterus macrolepis). If without
control, the potential impact due to runoff to these habitats is considered moderate.
7.6.20
Guidelines
in DSD Practice Note No. 1/2015 and ETWB TCW No. 5/2005 set out for the
protection of natural rivers and streams from adverse impacts arising from
construction works should be followed.
7.6.21
Precast
structures or other similar approaches should be used to minimize construction
works inside the watercourse and thus reduce direct water quality impact to
Shan Pui River and Old Kam Tin River. Good site management as stipulated in
ProPECC PN1/94 should be fully implemented to avoid polluted liquid or solid
wastes from falling into the river waters. The potential of these impacts will
be greatly reduced to acceptable level.
7.6.22
Besides,
excavation works within the watercourse might release contaminants to the
aquatic habitats, which subsequently affecting aquatic life. According to Chapter
5, the use of containment structures and diversion channels is
recommended wherever practicable to facilitate a dry or at least confined
excavation within the nullah. Water within the contained area should be
discharged to the nullah before excavation commences to create a dry condition.
Besides, careful programming of the works to avoid excavation works during the
rainy season is recommended in Chapter 5 that can further minimize
the chance of releasing contaminants to aquatic habitats. Hence, the potential
ecological impacts to downstream to the works area including the confluence of
Shan Pui River and Kam Tin River, and Deep Bay area from the excavation works
are considered minor.
Construction
noise disturbance
7.6.23
The potential response of
waterbirds to noise disturbance varies from minor response like head turning
scanning to behavioural changes like taking flight, reducing feeding/roosting
time or increasing agonistic behaviour, depending on the sensitivity of the
waterbirds and the level of disturbance. In general, high level of disturbance
could cause deterioration of habitat quality and decrease of bird usage as well
as subsequent decrease in wildlife density of the sensitive wetland habitats in
the vicinity of the works area. Hence, the birds might move away to areas which
are less disturbed and within their noise tolerances or reduce the foraging
efficiency of birds that remain in the affected area. While the sensitivity of
waterbirds to the same level of noise disturbance varies among different
species, residents are typically more tolerant of disturbance than migrant
birds (Klein et al. 1995). As such, the noise disturbance from
construction activities of this Project on waterbirds that are present all year
round (e.g. resident ardeids) are expected to be less significant than the
disturbance impacts on migratory/overwintering waterbirds given the generally
higher tolerance of residents to disturbance. While in many instances higher level of stimuli
from construction works, e.g. construction noise, would cause greater level of
disturbance, waterbirds were found to be especially prone to the intrusion of
human activities into the wetland habitats and high level of irregular
construction noise (Cutts et al. 2008 & 2013).
7.6.24
Among
different noise source from various construction activities, noise from
foundation works would generate higher construction noise. Various
construction methods for foundation works, including the conventional percussive
piles, bored piles by reverse circulation drill, box rafts and shallow
foundation, have been explored for this Project. The foundation options are
highly subject to the ground conditions. While box rafts, bored piling
by reverse circulation drill and shallow foundation typically cause
less disturbances (including noise, vibration and dust etc.), the application
of these methods for this Project is comparatively limited, given the site and
engineering constraints, including deep bed rocks (over 150 m below ground) of
the Project Site, additional ground treatment (e.g. grouting) required for
foundation works and large excavation volume, that could cause other
environmental issues such as water pollution and adverse waste management
implication. Due to the ground conditions and programme
constraints, percussive piling works might be a more feasible
foundation method. It is noted that
alternative piling method will be considered as far as practicable during the
detail design. In the
case percussive piling is unavoidable, it will generate higher construction
noise levels as compared to other general construction activities of the
Project, including site clearance/formation, superstructure or other quieter
demolition/foundation methods. In general, construction noise of above
background noise level is likely to cause low to moderate level of disturbance
that would trigger some degree of responses, which could be readily habituated,
in waterbirds (Cutts et al. 2008 & 2013).
7.6.25
It
is noticed that there is no established criteria/threshold for construction
noise tolerance of waterbirds in Hong Kong or similar urbanized environment,
the unmitigated construction noise levels at most of the noise assessment
points are predicted to exceed relevant noise control standards for domestic
premises stipulated under the Annex 5 of EIAO-TM (see Chapter 4) during the
construction phase in the absence of mitigation measures. This degree of
construction noise levels could potentially cause moderate level of disturbance
to the waterbirds. Hence, mitigation measures for noise reduction will be
required and stated in Chapter 4.
7.6.26
It
is worth noting that during the wet season months, the key wetland habitats for
waterbirds, as well as the wetland habitats nearby the Project Site were
actually dominated by comparatively low abundance of disturbance-tolerant
resident waterbirds that are common and present all year round (mainly resident
ardeids). It should be noted that while wetland habitats comprise about 20% of
the 500m assessment area, and there are about 1,500 ha of wetland in the Ramsar
Site north to the 500m assessment area. Serious impacts to the waterbirds using
the wetland habitats near the Project Site is therefore unlikely given the
ability of birds to move away from sources of disturbance as well as the ample
of well-connected, continuing and extensive wetland habitats available within
and in the vicinity of the assessment area. Given the relatively higher
diversity and abundance of overwintering waterbirds recorded in the Shan Pui
River, the confluence of Shan Pui River and Kam Tin River, as well as Nam Sang
Wai and the high construction noise level, the impact from construction noise
disturbance is considered moderate
for migratory/overwintering waterbirds and minor to moderate for the more
tolerant waterbirds that are present all year if unmitigated.
Vibration
disturbance from piling works
7.6.27
Among the piling methods, percussive piling would
generate vibration disturbance. Apart from construction noise, ground-borne
vibration due to percussive piling
works at the Project Site could also disturb waterbirds foraging or resting in
wetland habitats nearby the site. Higher diversity and abundance were recorded
at lower Shan Pui River and at the confluence of Shan Pui River and Kam Tin
River, which are away from the proposed works area, so that the vibration
impacts to the waterbirds at those areas are not anticipated. While wetland
habitats located in close vicinity from the Project Site supported
significantly less diversity and abundance of waterbirds that were mostly
resident, the impact from the vibration due to percussive piling
works for migratory/overwintering waterbirds is therefore considered minor to moderate for
migratory/overwintering waterbirds and minor for more tolerant waterbirds that are present all year if
unmitigated.
Dust
and human activities
7.6.28
Dust
and human activities will increase during construction phase, and might
temporarily reduce the abundance and distribution of fauna in habitats adjacent
to the works area.
7.6.29
Apart from construction noise, disturbance to
waterbirds caused by construction and decommission activities could have been
largely attributed to the increased presence of people/visual stimuli
associated with such activities such as movement of plants or workers operating
outside of machinery (Cutts et al., 2008 & 2013). Due to
the alignment of Shan Pui River (i.e. curved towards northwest side after the
location of proposed barrage), waterbirds in the Shan Pui River away from the
proposed barrage would not be affected by the human activities during
construction phase, as the view is blocked by the eastern side of Yuen Long
Industrial Estate. Besides, the wetlands in Nam Sang Wai are also mostly
blocked by plantation. The impacts of disturbance due to increased human
activities to waterbirds in particular Shan Pui River as well as the confluence
of Shan Pui River and Kam Tin River and Nam Sang Wai are considered minor.
Nonetheless, given the short separation distance between the Project Site and
Shan Pui River/Nam Sang Wai, implementation of good site practices would still
be recommended to further minimise the construction/visual disturbance on the
waterbirds using the Shan Pui River and Old Kam Tin River as much as possible.
7.6.30
Dust generated during the construction phase (e.g.
construction machinery, improper storage or dumping of construction materials)
could degrade the habitats adjacent to works area. Construction dust could
cover the leaves of plants in adjacent habitats and may affect photosynthesis,
respiration and transpiration of the plant and allow the penetration of
phytotoxic gaseous pollutants, thus changing the vegetation structure and/or
reducing the quality of habitat (Farmer, 1993). With the implementation of
mitigation measures and good site practices to minimise the potential dust
impact during the construction phase, no adverse air quality impact due to the proposed works
is anticipated. The impacts of construction dust disturbance on
terrestrial and wetland habitats, vegetation and other associated fauna are
therefore considered minor.
Artificial Lighting/Glare
7.6.31
Artificial lighting/glare could also affect light
sensitive wildlife including the endemic Bent-winged Firefly, the ardeid night
roost next to Kam Tin River, the Great Cormorant roosting on trees in Nam Sang
Wai and the mammal species of conservation importance. The artificial
lighting/glare could attract, disorient or disrupt the light-sensitive cycle of
the light sensitive/nocturnal species, subsequently affecting their migration,
foraging/predation and breeding success and causing the reduction of faunal
density in the area. However, given that the construction hours would be from
07:00 to 19:00 that no night-time construction works would be required under
this Project, working lights might only be turned on during evening time or
cloudy days with low light intensity. In any cases, there
will be no working lights after 19:00. Due to the sensitivity of nocturnal animals,
the impacts of construction lighting/glare disturbance are considered minor to moderate. In light of the
presence of light-sensitive fauna species of conservation importance in the
vicinity of the Project Site, implementation of good site practices would be
recommended to minimise the impacts of the artificial lighting/glare as much as
possible.
Disturbance to ardeid night roost
7.6.32
While there are no night-time works under this Project
and the impacts of construction lighting/glare disturbance are
considered minor for light-sensitive fauna species of
conservation importance in the vicinity of the Project Site, ardeids habitually
return to the night roost at every evening at around an hour before sunset and
the construction activities (construction hours: 07:00 to 19:00) would
potentially briefly interfere with the nigh roosts for up to around 2 hours and
cause disturbance impacts (mainly construction noise) on the ardeids night
roost beside
the proposed parapet wall at Kam Tin River. The roosting ardeid could
potentially relocate to another nearby location for roosting or other site
along Kam Tin River. Nonetheless, a change in night roosting site is unlikely
to trigger a decline in population as their breeding/nursery site are not
affected (MTRC, 2010). Furthermore, ardeid night roosts are known for their
highly changeable locations and roosting population that the roosting location
can be in temporal basis and even change from day to day on a small scale. It
has been observed in multiple cases in Hong Kong that the night roosting sites
were rather unstable and the change in their location could happen naturally.
The fluctuation of roosting population, abandonment or change in locations of
roosting site without major nearby environmental change has been observed in
roosts of various scale (from less than 100 to near 2,000 ardeids) and
locations in Hong Kong (HKJC, 2005; Lee et al., 2004; MTRC, 2010).
Given that ardeids are generally more tolerant to disturbances and short
interface of the construction hours and ardeids roosting hours, the unmitigated
impacts from the construction noise disturbance are expected to be minor to moderate on the ardeid
night roost given the short separation distance. Mitigation measures and
good site practices should also be implemented to minimise the impacts of
construction/visual disturbance on the ardeid night roost beside Kam Tin River
as much as possible.
Construction Phase ¡V Impacts on
recognized sites, important habitats and species of conservation importance
Recognized sites of
conservation importance and important habitats
7.6.33
Most of the recognized sites of conservation importance
were outside the Project Site, only part of the Project Site (mainly at the
last section of YLN where the barrage is proposed and the northern end of the
proposed parapet wall at Kam Tin River drainage channel) is within WBA. Other
recognized sites within the 500m assessment area include Wetland Conservation
Area, Conservation Area under OZP, Priority Sites for Enhanced Conservation and
Tung Shing Lei Egretry will not be affected directly. While Mai Po Inner Deep Bay Ramsar Site,
Mai Po Nature Reserve, and Mai Po Site of Special Scientific Interest are far
away from the 500m assessment area, potential impacts are not anticipated.
7.6.34
Part of the Project Site falls within the WBA (a
small area of channelized watercourse (YLN Section
4), plantation and developed area), while other recognized sites of
conservation importance (e.g. Mai Po Inner Deep Bay Ramsar Site, Wetland
Conservation Area, Mai Po Nature Reserve, SSSI, Conservation Area, Priority
Site and Tung Shing Lei Egretry), and important habitats such as
mudflat/mangrove at Kam Tin River and Shan Pui River will not be directly
affected.
7.6.35
However, the wetland habitats including the
mudflat/mangrove at Kam Tin River and Shan Pui River within the assessment area
in particular Deep Bay area serve as important feeding/roosting ground for
migratory and overwintering waterbirds, the indirect disturbance in particular
noise could cause the deterioration of habitat quality and decrease of bird
usage as well as subsequent decrease in wildlife density of the sensitive
wetland habitats within the recognized sites of conservation importance in the
vicinity of the works area. The sensitivity of the wetland habitats would
generally be considered higher during the peak visiting period of the migratory
and overwintering birds i.e. dry season given the greater number of species of
conservation importance affected.
7.6.36
Amongst the wetland habitats within the assessment
area, of particular note is the Shan Pui River and Nam Sang Wai located in the
close proximity of the Project Site. The wetland habitats in these two areas
supported a relatively greater diversity and abundance of migratory and
overwintering waterbirds observed within the assessment area. The impacts of construction disturbance
on the two areas are considered moderate
during dry season and minor to moderate
during wet season if unmitigated. Mitigation measures are detailed in the below
section. Only minor works (construction of parapet walls)
will be conducted in Kam Tin River, potential impacts to the wetland habitats
in Kam Tin River are considered minor.
Species of
conservation importance
7.6.37
As the plant species of conservation importance
i.e. Aquilaria sinensis and Phymatodes longissimi were recorded away from the Project Site, no
direct impacts to these two plant species are expected.
7.6.38
While the footprint of the tidal barrier
and the works area will encroach the habitat of the fish species of
conservation importance Gobiopterus macrolepis. However, the survey results of the present study
revealed that this species occurred in different locations in the area, and the abundance of Gobiopterus macrolepis in YLN Section 4 was
much lower than other
occurrence locations such as the reedbed in Nam Shan Wai.
However, due to the endemicity of Gobiopterus macrolepis, the ecological
impact on Gobiopterus macrolepis due to habitat loss is considered minor to moderate. Mitigation measures
for this species of conservation importance are required.
7.6.39
Bird species of conservation importance found
within the Project Site in particular YLN Section
4 included Northern Shoveler, Chinese Pond Heron, Grey Heron, Great Egret,
Little Egret, Great Cormorant, Black-winged Stilt, Pied Avocet, Little Ringed
Plover, Pheasant-tailed Jacana, Common Redshank, Marsh Sandpiper and Common
Greenshank. Besides, a regular high tide roost of Black-winged Stilt was found
in YLN Section 4. Like the night roost of ardeids
as discussed above, the
roosting Black-winged Stilt could potentially relocate to another nearby
location for roosting or other site along Shan Pui River. The roosting location
for Black-winged Stilt might be affected temporarily. However, a change in
night roosting site is unlikely to trigger a decline in population. To take a conservative approach, the
whole section of YLN Section 4 will be lost temporary during
construction phase, the ecological impacts are still considered minor to
moderate, taken consideration of the habitat size and quality (some with
concrete bed without sediment) as well as disturbance (regular maintenance
dredging of the sediment in that section) when compared with the Deep Bay area.
7.6.40
The Nam Sang Wai area is an important roosting site
for Great Cormorants. In winter, large roosting aggregations of Great
Cormorants on the gum trees in the Nam Sang Wai fishpond area were often seen
after feeding at Inner Deep Bay. No roosting Great Cormorant was recorded
within the proposed works area, so that no direct impacts to roosting habitat
of Great Cormorant are expected. While Black-faced Spoonbill was not recorded
within the proposed works area and no roosting of Black-faced Spoonbill was
also recorded within the 500m assessment area. Although Black-faced Spoonbill
might feed within YLN Section 4, the potential direct impacts to
this species are considered minor as the channel downstream to the YLN Section 4, i.e. Shan Pui River as well as the confluence of Shan Pui
River and Kam Tin River provides suitable habitats for Black-faced Spoonbill.
7.6.41
While the indirect disturbance impacts of the
construction activities (e.g. construction noise and increased in human
activities), if unmitigated, might consequently cause the waterbirds to avoid
using the habitats near the works area (including Black-faced Spoonbill and
roosting Great Cormorant at Nam Sang Wai). However, due to the distance from
the proposed works area to the confluence of Shan Pui River and Kam Tin River,
and Deep Bay area, potential impacts to the waterbirds roosting and/ or feeding
to that area are not expected.
7.6.42
No mammal species of conservation importance
including Eurasian Otter were recorded within the Project Site. Eurasian Otter
is a semi-aquatic mammal which forages in water and nest on land. Recent
records have only been found in the Mai Po Inner Deep Bay Ramsar Site and
nearby region. However, no Eurasian Otter was recorded within the 500m
assessment area throughout the present ecological survey and data from AFCD.
Wandering individual might be possible but the chance entering the Project Site
especially YLN Section 4 would be very low due to the
condition and disturbance of the channelized watercourse. As discussed, the
pumping stations and tidal barriers will not be constructed simultaneously, and
the completed part of tidal barrier will be kept open, hence, potential impacts
from habitat loss and fragmentation on Eurasian Otter are considered minor.
7.6.43
As there will be no night works during construction phase,
working lights might only be turned on during evening time or cloudy days with
low light intensity. The
working lights would be turned off after 19:00. Potential impacts of construction
lighting/glare disturbance to the light-sensitive fauna including the endemic
Bent-winged Firefly, the ardeid night roost next to Kam Tin River, the Great
Cormorant roosting in Nam Sang Wai and the mammal species of conservation
importance in the vicinity of the Project Site are considered minor to
moderate. In light of the presence of light-sensitive fauna species of
conservation importance, implementation of good site practices would be
recommended to minimise the impacts of the artificial lighting/glare as much as
possible.
7.6.44
The other species of conservation importance
including the butterfly, dragonfly, reptile and amphibian recorded away from
the Project Site will not be affected significantly.
Operational Phase ¡V
Direct Impacts
Habitat loss
7.6.45
Without the proposed barrage, the brackish water from
Inner Deep Bay flushes into YLN Section 4 up to the existing inflatable dam
during high tide period. The brackish water flushed from the Inner Deep Bay
also brings sediment to YLN Section 4, that created an intertidal mudflat-liked
habitat which attracts waterbirds to roost and feed during low tide. The fish
species of conservation importance Gobiopterus macrolepis was also
recorded in YLN Section 4, but the abundance was much lower than the reedbed in Nam Sang Wai.
7.6.46
According to Chapter 2, the operation of tidal
barrier will be closed during high tide above 0.5mPD and will be opened below
0.5mPD (Appendix 2.5). Currently water from Deep Bay starts flushing in at about ~0.2mPD during flooding tide.
Hence, the water with sediment from Deep Bay can still be flushed into YLN
Section 4 from ~0.2-0.5mPD during flooding tide
before closure of tidal barriers. As the whole section of YLN Section 4 will be
deepened (either for barrage or for revitalization), a certain amount of the water from Deep Bay can be kept within the YLN Section 4 and will be maintained at a certain depth even the tidal barriers are closed. After the
tidal barrier is closed, the waters from the Deep Bay can still be flushed into
the YLN Section 4 during high tide through the proposed 300mm x 300mm
ecological trench. Besides, the low flow pump can be operated when necessary to adjust a desired water level inside the YLN Section
4, and maintain water exchange even during
closure of tidal barriers. The
tidal barriers will then open again during the ebbing tide when the tidal level
goes down to about 0.5 mPD, and the water kept within YLN Section 4 will go out to Deep Bay with the ebbing tide. The water in YLN Section 4 will thus be exchanged regularly, and the water depth within
Section 4 will fluctuate between the level of about 0.5 mPD (when the tidal
barrier is closed) and the depth of the deepening channel bed (when the water
has gone with the ebbing tide). In
practice, the water level in YLN Section 4 will be
kept in a level which could facilitate the utilization of waterbirds for a longer time
than its current condition.
7.6.47
The operation of the tidal barrier can still allow
brackish waters with the sediment flush in and store in Section 4, so that the
waterbirds can still utilize the Section 4 for roosting and feeding with a longer utilization time, and the Gobiopterus macrolepis can
follow tidal influence and inhabit in YLN Section 4. Detailed operation
of the tidal barrier and the low flow pump with the
consideration of ecology (including the area size to be flooded by water, the water
level and allowing sediment to enter YLN Section 4) will be confirmed in the Detailed Design Stage. The feasibility of
flexible trigger levels and an adaptive management approach to extend the
durations in partial opening of tidal barriers and operation of the low flow
pumps could also be further explored. Extension of opening time of the gates will be considered if the water
quality in Deep Bay has improved and there is no further odour concern for Yuen
Long Town Centre and adjacent villages. For the footprint of tidal barrier and pumping station
(0.26ha of watercourse) that will be lost permanently, the direct encroachment of the habitat as well as the feeding/roosting
ground for waterbirds will be very limited. As discussed in the construction
phase, the existing inflatable dam with an area of approximately 255m2
will be decommissioned, so that some area (i.e. 255m2) of waterbody
will be re-provided. Besides, the operation of the tidal barrier will allow water from the Deep Bay
flushing in beyond the existing inflatable dam. It is estimated that about 50m
stretch of YLN upstream of
the inflatable dam can provide additional ~0.26ha of wetland habitat during
operational phase, and hence achieve no net
loss of wetland.
Fragmentation
7.6.48
The connectivity between YLN Section 4 and Shan Pui River might
be blocked by the proposed barrage. As same as the construction phase, aquatic
life and the fish species of conservation importance Gobiopterus macrolepis
might be affected. With the operation of the tidal barrier and the 300mm x
300mm ecological trench that allow brackish waters flush into YLN Section 4 during high tide, the
potential impacts to aquatic fauna as well as the Gobiopterus macrolepis
are considered minor, while the existing inflatable dam
will be decommissioned to re-provide connectivity to further upstream
sections.
7.6.49
On the other hand, as discussed in the construction
phase impact, the height of the proposed barrage varies from 6 mPD to 19 mPD. Only low
numbers of waterbirds (about less than 10 birds per
survey) flied along the YLN Section 4 with observed flight height below 10m.
7.6.50
Potential impacts to the flight-lines might occur.
As discussed in the construction phase impact, the flight height of the
waterbirds can be adjusted to fly over infrastructures such as highways.
Besides, due to the artificial nature and disturbance level in YLN, major
feeding and roosting grounds in the upstream of YLN (i.e. YLN Sections
1 to 3) are not anticipated. The abundance of ardeids and other waterbirds were
very small compared to the abundance in Deep Bay Area (see Table 7.4). Hence, the potential fragmentation
impacts to ardeids (including the breeding ardeids from Tung Shing Lei egretry and
the new egretry at and near the Yuen Long Sewage Treatment Works) and other
waterbirds from the proposed barrage are considered minor due to the low abundance, manoeuvrability of waterbirds and
the unlikely feeding and roosting grounds in the upstream of YLN.
7.6.51
As the proposed parapet walls will be built mostly on
existing concrete structures or developed area with limited height (~1m or
1.2m), there will be no direct ecological impacts deduced from the proposed
parapet walls during operational phase.
Operational Phase ¡V
Indirect Impacts
Water quality
7.6.52
Although the operation of the tidal barrier allows
brackish waters flush into YLN Section 4, the salinity upstream to the barrage
might be lowered as the time of brackish water entering the barrage will be
decreased. Drastic changes of salinity would affect the composition of benthic
organisms which eventually affects the food source of waterbirds. Since the
operation of tidal barrier allows brackish waters enter the upstream of
barrage, change of salinity that eventually affect the benthic composition will
not be significant. In fact, due to the influence of the discharge from the
Pearl River, the Inner Deep Bay area experiences fluctuating salinity which
could range from 3.2 to 29.2 ppt. Shan Pui River nearby the Project Site would
therefore be exposed to varying salinity of a range similar to the existing
condition under the tidal influence that no adverse impacts on the aquatic
communities or the associated waterbirds are anticipated. On the other hand,
freshwater habitats also provide roosting and feeding habitats for waterbirds
(e.g. egrets), drastic changes of waterbird community are not likely. When
compare with the size of similar habitat in Deep Bay area, and the abundance of
waterbirds as well as the bird species of conservation importance, the
potential ecological impacts due to the change of salinity of the YLN Section 4
is considered insignificant.
7.6.53
On the other hand, as the freshwater from upstream of YLN will be intercepted by the proposed barrage, salinity in Shan Pui River
might be increased. However, the freshwater will not be diverted away from the
barrage, and the gates of the tidal barrier will be opened or the upstream
waters will be pumped out just after the tidal barrier to maintain the water
connectivity. Hence, the potential ecological impacts are similar to above
paragraph and considered insignificant.
7.6.54
In fact, the water quality in YLN will be improved as the
dry weather flow will be collected and diverted to Yuen Long Effluent Polishing
Plant according to the EIA study of Improvement of Yuen Long Town Nullah (AEIAR
223/2020), so that the water quality of YLN Section as well as Shan Pui River
will further be improved. Therefore, the quality of the habitats for waterbirds
will be further enhanced.
Change of hydrodynamics
7.6.55
According to Chapter 2, the tidal level in Old Kam Tin River will not be
changed significantly, due to the large waterbody of Deep Bay, as compared with
the existing concrete-lined section (to be regulated by YLBS), no significant
increase is anticipated to the design tide levels at the Old Kam Tin River as
well as Shan Pui River from the implementation of tidal barriers. Hence, the
periods of low tides and high tides would be similar to the existing
conditions. Waterbirds rely on the exposed mudflat in Old Kam Tin River and
Shan Pui River as well as the confluence of Shan Pui River and Kam Tin River,
and Deep Bay area during low tides would not be affected. The potential impacts
due to change of hydrodynamics are considered insignificant.
Sedimentation
7.6.56
Shan Pui River is a drainage channel, its channel bed is composed of
soft muddy sediments deposited through tidal movement. The exposed sediments in
Shan Pui River in particular the confluence of Shan Pui River and Kam Tin River
during low tide form a tidal mudflat for waterbirds to feed and roost, as
benthic community which is a major food source for waterbirds, can be
established in the accumulated sediments/tidal mudflat. Hence, Shan Pui River
in particular the lower course as well as the confluence of Shan Pui River and
Kam Tin River are favourite feeding grounds of waterbirds during low tide
periods. During the operational phase of the barrage scheme, the discharge of
water might flush away the sediments on the channel bed, which might affect the
area of sediment exposure for waterbirds. However, the volume of water being
discharge would not be different with the proposed barrage, only the force and
the pattern of water discharge will be different. Hence, the potential impacts
from the discharge on the sedimentation pattern/tidal mudflat are considered
low to moderate at the location just outside the proposed barrage. The detailed
design should consider the orientation of the outlet and angle of discharge, to
minimize significant changes to the existing sedimentation pattern / mudflats
in Shan Pui River and Old Kam Tin River. While the impacts to the confluence of
Shan Pui River and Kam Tin River, and Deep Bay area are considered
insignificant due to the distance (>1.5km) from the proposed barrage.
7.6.57
The barrage will also reduce the tidal flushing at the
downstream area. However, considered the long distance (~3km) from the estuary
to the proposed barrage, the tidal movement at the barrage will be weak.
Therefore, increase in sedimentation is expected to be minimal at the
downstream of the proposed barrage. Potential ecological impacts such as change
in feeding and/or roosting habitats/areas in particular the confluence of Shan
Pui River and Kam Tin River for waterbirds are not expected.
Bird collision
7.6.58
Only opaque instead of
transparent glass panels will be used for the parapet walls, potential risk of
bird collision on the parapet walls is considered insignificant.
7.6.59
The use of large areas of
reflective material on the outer surfaces of the buildings (i.e. pumping
stations, E&M control room) would be avoided to minimize the risk of aerial
collisions from birds. Hence, the ecological impacts arising from bird
collision is considered minor. However, given the close proximity of Shan Pui
River with relatively higher abundance and diversity of birds, environmental
friendly design of the buildings would still be recommended to minimize the
potential impacts as much as possible.
Artificial Lighting/Glare
7.6.60
The behavior and
distribution of nocturnal wildlife may be affected by artificial
lightings. Lighting sources (e.g.,
village houses, buildings of Yuen Long Industrial Estate) are already present
within and near the Project Site.
Fauna inhabiting in habitats near the Project Site have probably
habituated to lightings. Sensitive
species might not be present in these areas.
7.6.61
During operation
phase, only security light with minimum light intensity will be turned on at
night, no flush light will be required. Hence, no significant adverse impact to nocturnal fauna in nearby areas is anticipated.
Potential impacts to fauna from this source are considered minor. As an enhancement measure, further minimize
the impacts on nocturnal fauna will be considered during Detailed Design Stage.
Operational Phase ¡V Impacts on
recognized sites, important habitats and species of conservation importance
Recognized
sites of conservation importance and important habitats
7.6.62
The Project Site is located
within WBA and is near the WCA/Conservation Area. However, the proposed barrage
will not affect the ecological integrity of the wetlands within
WCA/Conservation Area or cause direct habitat loss in WCA/Conservation Area,
only small area within WBA will be lost permanently and is considered insignificant. While the wetland habitats in WCA are
separated by a channelized watercourse from the Project Site. The potential
impacts to the recognized sites of conservation importance as well as the
important habitats such as mudflat/mangrove at Kam Tin River and Shan Pui
River, and the habitats in Nam Sang Wai are considered insignificant as
the operational phase disturbance (e.g. noise, human disturbance) will be very
limited.
Species
of conservation importance
7.6.63
No significant increase of
human activities is expected during the operational phase of the barrage. Human
activities will mainly be occurred inside the pumping stations and the E&M
control room. On the other hand, the external lighting system required for the
barrage, pumping stations and the E&M control room is expected to be low
and would not affect nearby wildlife and species of conservation importance,
particular the night roost of Great Cormorant at Nam Sang Wai (though no night
roost of Great Cormorant was identified within the 500m assessment area),
light-sensitive endemic Bent-winged Firefly and the nocturnal mammal species of
conservation importance. As lighting system is not necessary for the parapet
walls, the ardeid night roost beside Kam Tin River will not be affected. The
glare would be further minimized through landscape design and control of
lighting system. Hence, disturbance impacts from the operation of the barrage,
including human activities and lighting/glare to the ecological value of the
nearby habitats and wildlife, particularly waterbirds and light-sensitive
wildlife, as well as recognized sites of conservation importance, are
considered minor. In light of the presence of light-sensitive fauna species of
conservation importance in the vicinity of the Project Site, implementation of
good site practices would still be recommended to further minimize the impacts
of the artificial lighting/glare from the light system required at night as
much as possible.
7.6.64
According to Chapter 2, approximately 2-12 hours of
opening per day could be catered but subject to other parameters. Hence, the
watercourse would not be blocked and allow semi-aquatic fauna such as Eurasian
Otter to access the YLN Section 4. As mentioned in the construction phase, no
Eurasian Otter was recorded in the assessment area by present study and AFCD,
potential impacts to Eurasian Otter are considered minor. In order to cater
wandering individual entering the Project Site, provision of a corridor should be considered to provide an access for
Eurasian Otter between Shan Pui River and YLN Section 4.
7.6.65
After revitalization of YLN, in particular YLN Section
4, the ecological value will be enhanced. The enhanced habitat can provide more
microhabitats for the waterbirds and the fish species of conservation
importance i.e. Gobiopterus
macrolepis. In
addition, as the bank of YLN Section 4 provided a high tide roost for Black-winged Stilt, the bank
will be kept or with limited enhancement. Hence, the high tide roost of
Black-winged Stilt will be maintained/enhanced for the species. As the existing
YLN Section 4 would be covered by waters during high tide, which is not a
favourable roosting location for waterbirds. However, with the operation of the
tidal barrier and the revitalization measures, the YLN Section 4 will provide a
high tide roost for other waterbirds.
7.7.1
In order
to assess the cumulative impacts, a review of best available information at the
time of preparing this EcoIA to identify a number of other projects that are
undergoing planning, design, construction and/or operation within the
construction and /or operation period for this Study has been conducted. The
potential occurrence of cumulative impacts would be mostly determined by the
nature of the projects, the project scales, and the distance between the
projects. The cumulative impacts were assessed based on Section 4.3.3 of the
EIAO-TM.
7.7.2
According
to the preliminary construction programme of the Project (Chapter 2), the construction works is anticipated to
commence in Q4 of 2022 for completion by Q2 of 2027, with concurrent
construction and modification of the parapet walls. Upon completion of the
barrage, the revitalization works along YLN and
decommissioning of the existing inflatable dam would take place unit Q3 of
2029.
7.7.3
Five
concurrent projects are identified in the vicinity the Project Site as discussed
in Chapter 2, including the ¡§Improvement of Yuen Long Town Nullah (Town
Centre Section) ¡V Stage 1 Improvement Works ¡V Design and Construction¡¨, ¡§Elevated Pedestrian Corridor in Yuen Long Town
Connecting with Long Ping Station ¡V Investigation, Design and Construction¡¨,
¡§Yuen Long Effluent Polishing Plant ¡V Investigation, Design and Construction¡¨,
¡§Yuen Long South Development ¡V Stage 1 ¡V Design and Construction¡¨, and ¡§Hung
Shui Kiu Effluent Polishing plant and Yuen Long South Effluent Polishing Plant
¡V Investigation¡¨. Table 7.5 summarizes the relevancy
of the concurrent projects.
Table
7.5 Potential Cumulative
Ecological Impact from Concurrent Projects
Concurrent
Projects |
Project Proponent |
Construction Programme |
Potential Cumulative Impacts |
|
Construction Phase |
Operational Phase |
|||
Present
Project |
DSD |
Q4 2022 to
Q2 2027 |
N/A |
N/A |
Improvement
of Yuen Long Town Nullah |
DSD |
Q2 2021 to
2026 |
Part of the
proposed works area falls within the WBA, cumulative impacts from the works
of rising mains are expected. As the
construction works will be scheduled outside dry season, significant
cumulative impacts to ecology and waterbirds are not expected. |
Potential
cumulative ecological impacts are not expected as there will be no high
disturbance to the environment. On the other hand, the water quality in YLN as well as
Shan Pui River will be enhanced. |
Elevated
Pedestrian Corridor in Yuen Long Town Connecting with Long Ping Station |
HyD |
2020 to 2025 |
No
cumulative impacts are expected as the works are away from the present
Project. |
No
cumulative impacts are expected as the works are away from the present
Project. |
Yuen Long
Effluent Polishing Plant |
DSD |
2020 to 2030 |
Potential
cumulative disturbance impacts to ecology and waterbirds are anticipated, as percussive piling works will be conducted for both Projects. However, the
noise impacts to waterbirds will be mitigated, and percussive piling works will be scheduled outside the peak
season of waterbirds. |
Potential
cumulative ecological impacts are not expected as there will be no high
disturbance to the environment. On the other hand, the water quality in Yuen
Long Nullah as well as Shan Pui River will be enhanced. |
Yuen Long
South Development |
CEDD |
2020 to 2038 |
No
cumulative impacts are expected as the works are away from the present
Project. |
No cumulative
impacts are expected as the works are away from the present Project. |
Hung Shui
Kiu Effluent Polishing plant and Yuen Long South Effluent Polishing Plant |
DSD |
Q1 2028 to
Q4 2032 |
No
cumulative impacts are expected as the works are away from the present
Project. |
No
cumulative impacts are expected as the works are away from the present
Project. On the other hand, the water quality in Deep Bay area will be
enhanced. |
7.7.4
Only the concurrent
projects ¡§Improvement
of Yuen Long Town Nullah¡¨ and ¡§Yuen
Long Effluent Polishing Plant¡¨ will contribute to cumulative impacts on ecology during construction
phase. As the most disturbance works of both projects will avoid the peak
season of waterbirds, potential cumulative impacts to waterbirds as well as
ecology are considered minor. While during operational phase, the combined
effects of the projects will further enhance the water quality in the YLN as
well as Deep Bay area. No adverse cumulative impacts on ecology are expected
during operational phase.
General
7.8.1
According
to the EIAO-TM Annex 16 and EIAO Guidance Note 3/2010, ecological impacts on
important habitats and the associated wildlife caused by the proposed Project
should be mitigated, in order of priority, avoidance, minimization, and
compensation approaches to the maximum practical extent.
Consideration of avoidance
7.8.2
While
the Project Site of the proposed barrage is situated within the WBA, the site
and construction works are designed to be mainly confined to the YLN (i.e. man-made channelized watercourse with concrete bed) that direct
impacts on all other recognized sites of conservation importance including
Ramsar Site, Priority Site, WCA, SSSI and Conservation Area would be avoided.
Consideration of minimization
7.8.3
Consideration of alternative construction
methods ¡V Demolition using concrete crusher is quieter
than demolition using breakers mounted on excavators that its construction
noise level is comparable to other general construction activities. Concrete
crusher also generates less vibration and dust than breakers during demolition
works. However, concrete crusher is less efficient than breaker
(approximate 50% slower) and its demolition rate would be more
unreliable. In view of the tight programme, concrete crusher would be
used for demolition works to be undertaken during dry season months and
demolition using breakers mounted on excavators should only be undertaken
during wet season when the wetland habitats nearby the Project Site are less
sensitive outside the peak overwintering. Other
quieter demolition methods including non-explosive demolition agent and the use
of thermal lance and/or high-pressure water jets have also been considered but
their demolition rate is also unreliable as well and thus not viable for the
Project.
7.8.4
Due to the ground conditions and programme
constraints, percussive piling works might be a more feasible
foundation method. It is noted that
alternative piling method will be considered as far as practicable during the
detail design. In considering the construction noise, ecological impact and
other engineering constraints, other quieter foundation methods, including
bored piling by reverse circulation drill, raft foundation and shallow
foundation, would be considered as far as possible.
7.8.5
Avoidance of percussive piling during winter - According to the ecological survey data from the present study, Shan
Pui River recorded a relatively higher abundance of waterbirds in dry season,
the potential impacts from noise disturbance to overwintering waterbirds are
considered moderate (if percussive piling is adopted). In order to minimize the
construction noise disturbance on the nearby wetland habitats and the
associated disturbance-sensitive overwintering/migratory waterbirds, which are
most abundant during the dry season months, the comparatively disturbing
construction works i.e. percussive piling works and demolition using breakers
mounted on excavators, would therefore be scheduled outside the dry season
(i.e. November to March, which is the peak overwintering period of waterbirds).
7.8.6
Careful phasing of construction activities ¡V The programme and phasing of the
construction activities have been carefully planned to localise the
construction disturbance within and to reduce the duration of high level of
disturbances on sensitive wetland habitats and associated waterbirds. The
proposed works will be conducted in 3 primary phases stated in Chapter
2. For example, excavation works within watercourse will be conducted
in dry season to minimize the impacts to water quality and release of
contaminants to aquatic habitats. Besides, all works for the
barrage (the two pumping stations and tidal barriers) will not be constructed simultaneously, but
will be constructed by 2 sections (one pumping station and half of tidal
barriers at a time), to maintain the ecological connectivity, and to allow
brackish water from Deep Bay entering YLN Section 4 that can provide wetland
habitat for utilization of waterbirds.
7.8.7
Use of quality powered mechanical equipment ¡V The Quality Powered Mechanical Equipment (QPME)
system was developed by EPD to benchmark construction equipment items that are
new, notably quieter, more environmentally friendly and efficient by QPME
Labels. The contractor should source QPMEs for construction as far as
practicable to further minimise the overall construction noise and other
disturbance to the nearby wetland habitats and associated waterbirds to the
maximum practical extent.
7.8.8
Other
noise mitigation measures ¡V Chapter 4 discusses only
the noise mitigation measures required to fulfil relevant noise control standards
stipulated under Annex 5 of EIAO-TM and recommends good construction site
practice, use of quiet Powered Mechanical Equipment (PME), adoption of movable
noise barriers and scheduling of PME/construction activities. In view of the
presence of sensitive wetland habitats and the abundance of waterbirds
(particularly migratory/overwintering ones) within the assessment area, other
practicable effective mitigation measures on planning and construction of the
Project have been fully explored and exhausted under this Project as described
below to further abate the ecological impacts arising from construction noise
disturbance on nearby wetland habitats and associated waterbirds, including
careful phasing of construction activities, consideration of alternative
construction methods, use of noise barriers and use of Quality Powered
Mechanical Equipment (QPME).
7.8.9
Operation
of tidal barrier to allow brackish waters flushing in ¡V In
order to mitigate the impacts of fragmentation in particular the water
connectivity between the YLN Section 4 and Shan Pui River, as well as the
loss of brackish water habitat at YLN
Section 4, measures are being explored to retain the habitat between the
existing inflatable dam and the proposed barrage as far as practicable. The operation of tidal barrier will be closed
during high tide above 0.5mPD and will be opened below 0.5mPD (Appendix 2.5). The situation now is the waters from Deep
Bay start flushing in above ~0.2mPD during high tide. Hence, the waters with
sediment from Deep Bay can still be flushed into YLN Section 4 from ~0.2-0.5mPD
during high tide before closure of tidal barriers The
operation would facilitate an exchange of water, similar to the existing
conditions, according to tidal fluctuations and enhance ecological connectivity
through periodic opening of the tidal barriers. Additionally, the details of
the proposed 300mm x 300mm ecological trench underneath the soffit of the tidal
barriers is being investigated to serve a similar purpose when the barriers are
closed. The necessary operation modes would be further explored in the Detailed
Design Stage.
7.8.10
Discharge
design to minimize the scouring effect to tidal mudflat ¡V
The performance of the discharge system would be assessed against the YLBS¡¦
maximum discharge (i.e. under 200-year rainstorm event) and the configuration
of the pumping stations is being optimised. Apart from under design weather
events, no significant increase in discharge is anticipated as a result of the
barrage. The orientation of the outlet and angle of discharge will be designed
to prevent localized turbulent flows which could lead to scouring of the river
bed and bank, thereby minimising significant changes to the existing
sedimentation pattern / mudflats in Shan Pui River and Old Kam Tin River.
Energy dissipators could be designed at the outlet to protect the downstream
Shan Pui River from erosion by further reducing the flow velocity.
7.8.11
Reducing glare/lighting ¡V No night-time construction works would be
required under this Project (construction hours: 07:00 ¡V 19:00) while the
operations of the pumping stations and E&M room will be unmanned, only
safety light will be turned on. Noting the Bent-winged Firefly is most active
right after dusk, to avoid the potential disturbance impact on the firefly, any
outdoor lighting associated with the construction works of the barrage after
18:00 should be avoided during May to September. In light of the presence of
light sensitive mammal species of conservation importance, Great Cormorants
that roost on trees at Nam Sang Wai and Bent-winged Firefly, the overall
reduction of glare during both construction and operation phases should also be
considered. A balance between lighting for safety, and avoiding excessive
lighting can be achieved through the use of directional lighting to avoid light
spill into sensitive areas, and control/timing of lighting periods of some
facilities. Major construction site lighting should point inward and downward
to minimize glare disturbance to wildlife at night. The intensity of light
should also be controlled to the lowest possible level.
Consideration of mitigation
7.8.12
Translocation of Gobiopterus macrolepis ¡V Within YLN Section 4 of the Project Site, fish species of conservation importance
i.e. Gobiopterus macrolepis was
recorded. Direct impact to this species is likely in the works area of the
tidal barrier during construction phase, and mitigation measures are
recommended. Capture-and-translocation of this fish species will be implemented
in the works area of the tidal barrier and pumping station prior to
construction works to minimize the impacts on this species of conservation
importance.
7.8.13
Capture-and-translocation
exercises for fish species of conservation importance were recommended in other
EIA studies, and conducted in Hong Kong. For example, in the EIA study Drainage
Improvements in Southern Lantau (AEIAR-093/2005), the proposed works at Pak
Ngan Heung had the potential impacts to two fish species of conservation
importance i.e. Flagtail Kuhlia marginata and Predaceous Chub Parazacco
spilurus, and hence capture-and-translocation for the two species was
proposed. Furthermore, in the course of preparing the Environmental
Study Report of PWP Item No. 112CD (i.e. a drainage improvement works), a species
of rare fish species Acrossocheilus parallens was found at the Kau Lung
Hang Stream. The population of the species within the works area was captured
and temporary kept in a set of fish tanks made of concrete beside the stream.
The fish in the temporary fish tanks were then translocated back to the stream
after the drainage improvement works. Although no precedent case of
translocation of Gobiopterus macrolepis, a
relative of this species from the same genus G. chuno is an ornamental
fish and available on ornamental fish market. Potential translocation of Gobiopterus macrolepis is considered feasible.
7.8.14
The
capture-and-translocation exercise should be undertaken by ecologists with
relevant experience. Besides the primary target of Gobiopterus macrolepis,
other aquatic species of conservation importance should also be translocated if
encountered during the capture exercise. Captured individuals will be released
to suitable habitats with records of the species during the exercises. As the works area of the tidal barrier
subjects to tidal influence, it is recommended the capture exercise should be
conducted after the
works area boundary is encircled by cofferdam and the water is drained. It is
preferred that the final cofferdam will be installed during low tide, allowing most fish or other aquatic fauna to evacuate with the ebbing tide, and the works area will further drain down
by pump to facilitate the capture. Cofferdam
should be maintained and kept intact to prevent recolonization of aquatic fauna in the works area after the capture survey.
7.8.15
Gobiopterus macrolepis were recorded along the Shan Pui River, Kam Tin River, the confluence
of Shan Pui River and Kam Tin River, and the reedbed in Nam Sang Wai, all these
locations can be considered as potential receptor sites for fish translocation.
7.8.16
The
detailed fish translocation plan and ecologists involved in the translocation
should be submitted to relevant authorities including AFCD for approval prior
to commencement of the fish translocation. The plan should include brief
description on pre-translocation fish survey, translocation methodology,
identification of fish receptor site, post-translocation monitoring
methodology, and measures to prevent recolonization of aquatic fauna in the
works area of the tidal barrier.
7.8.17
With
the implementation of the fish translocation programme, the direct encroachment
impact on Gobiopterus macrolepis within the works area of the tidal
barrier can be reduced to minor.
7.8.18
Use of noise barriers/acoustic screens ¡V In order to further minimise the overall
impacts on the nearby wetland habitats and associated waterbirds, particularly
to the wetland habitats adjacent to the Project Site, noise barriers with
absorptive materials of about 2-3m high will be erected along the sensitive
sides of the Project Site, throughout the construction phase. The purpose is to
screen the construction noise and human disturbance from the waterbirds during
construction phase.
7.8.19
Adequate noise barriers should also be provided for
the demolition using breakers mounted on excavators and percussive piling
works, to further minimise the construction noise disturbance from these
construction activities. Movable noise barriers should be provided to breakers
mounted on excavator used for demolition works and acoustic mat should be
provided to the piling plants around the rig. The contractor should
provide enclosure for construction equipment, especially static plants (e.g.
generator), as appropriate to minimise the noise disturbance as far as
practicable.
7.8.20
As
ardeid night roost was recorded beside the Project Site of Kam Tin River, noise
barriers with absorptive materials of about 2-3m high should be erected along
the side close to the night roost location, that would screen human disturbance
and noise disturbance to the night roost. As night roost may change from time
to time, a pre-construction survey is recommended for areas within 100m from
the Project boundary to confirm the location and status of the night roost. No
construction works should be undertaken within 100m of any night roost
confirmed by the pre-construction survey after 17:00 from February to September
and 16:30 from October to January to avoid disturbance.
Enhancement opportunities
7.8.21
Revitalization ¡V Upon operation of the Project, opportunities would be provided to
revitalize the existing YLN. One of the revitalization components under the barrage scheme aims to
enhance the ecology and biodiversity of the nullah. The targets should be
focused on providing habitats to waterbirds as well as the aquatic fauna in
particular Gobiopterus macrolepis. The nullah bed will be replaced with
natural substrates and vegetation will be provided, to provide more
microhabitats for aquatic life as well as waterbirds. It is expected YLN Section 4 will be enhanced that attracts more waterbirds for feeding
and roosting after revitalization. Together with the operation of the tidal
barrier, a high tide roost for waterbirds can be provided. Besides, the
ecological connection would be another component for the revitalization. For
example, there should not be continuous curb at the fringe between the tidal
barrier and the watercourse that affects the aquatic fauna to-and-fro between
Shan Pui River and YLN. Provision of a corridor should be considered to provide
an access for semi-aquatic organisms such as Eurasian Otter.
7.8.22
Green opportunities ¡V Greening opportunities, including green roofs
and vertical greening on building structures, would be explored in the Project
to further promote the ecological value of the Project Site. Further details of
the relevant greening opportunities are discussed in Chapter 10 ¡V Landscape
and Visual Impact Assessment.
7.8.23
With the abovementioned mitigation measures, no secondary/induced/additional/synergistic
impacts are anticipated. A summary of the impacts in construction and
operational phases, with sources, receivers, nature, significance and
mitigation required, are provided in Table 7.6.
Table 7.6 Summary
of Construction Phase and Operational Phase Impacts
Impact |
Sources |
Receivers |
Nature of
impacts |
Significance
of ecological impact |
Mitigation
required |
|||||
Habitat quality |
Species
affected |
Size /
abundance |
Duration |
Reversibility |
Magnitude |
|||||
Construction Phase
¡V Direct Impacts |
||||||||||
Habitat loss |
Parapet walls |
Developed area |
Very low ecological value |
Very low diversity and abundance of waterbirds and
aquatic fauna |
Negligible size of developed area (heightening part
will be on top of the existing parapet wall, new parapet wall will replace
the existing railing) |
Permanent |
Reversible |
Very small |
No as it is not considered as a habitat loss |
No |
Proposed barrage (tidal barrier, pumping stations,
E&M room, channel widening and deepening works) |
Plantation and YLN Section 4 |
Low ecological value for plantation; low to middle
for YLN Section 4 |
Plantation: low diversity and abundance of flora and
fauna; YLN Section 4: low to moderate diversity and
abundance of waterbirds including those bird species of conservation
importance, and Gobiopterus macrolepis |
Tidal barrier: 0.09ha of channelized watercourse; Pumping stations: 0.17ha of channelized watercourse and
0.10ha of plantation; E&M room: 0.09ha of plantation; Channel widening and deepening works: 0.76ha of
channelized watercourse and 0.10ha of plantation |
Mostly permanent, but channel deepening works will
be temporary |
Not reversible |
Plantation: very small; YLN Section 4: small |
Plantation: minor; YLN Section 4/waterbirds
including bird species of conservation importance and Gobiopterus macrolepis:
minor to moderate; impact to Black-faced Spoonbill is considered minor |
No specific mitigation measure for plantation loss
under ecology, only compensatory planting under LVIA; translocation of Gobiopterus macrolepis; careful phasing of
construction activities to maintain the water source in YLN Section 4 for
waterbirds |
|
Revitalization |
YLN Sections 1-4 |
Very low ecological value for Section 1-3; low to
middle for Section 4 |
YLN Sections 1-3: very low diversity and abundance
of waterbirds and aquatic fauna; Section 4: ditto |
13.64ha |
Temporary |
Not reversible |
Small |
Not anticipated |
It is an enhancement measure |
|
Fragmentation (water connectivity) |
Construction of tidal barrier and pumping station at
YLN Section 4 |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River: middle ecological value |
Aquatic fauna including Gobiopterus macrolepis and
semi-aquatic fauna including otter |
Relatively low number of Gobiopterus macrolepis |
Permanent |
Not reversible |
Small |
Minor |
Pumping stations and tidal barriers shall not be
constructed simultaneously, to maintain the water connectivity |
Fragmentation (flight path of waterbirds) |
Construction of tidal barrier and pumping station at
YLN Section 4, construction of parapet walls at Kam Tin River |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River and Kam Tin River: middle ecological
value |
Waterbirds |
Low numbers of waterbirds compared to Shan Pui
River, Nam Sang Wai and Deep Bay area |
Permanent |
Not reversible |
Small for the barrage, very small for the parapet
walls |
Minor for the barrage; not expected for the parapet
walls |
No |
Construction
Phase ¡V Indirect Impact |
||||||||||
Water quality |
All proposed construction works |
Channelized watercourse including YLN, Shan Pui
River and Kam Tin River |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River and Kam Tin River: middle ecological
value |
Aquatic fauna and waterbirds |
Vary |
Transient |
Reversible |
Small |
Moderate |
Follow water quality mitigation measures |
Construction noise disturbance |
Construction noise in particular piling |
Sensitive habitats near the works area |
Very low ecological value for Section 1-3; low to
middle for Section 4; plantation in NSW: middle ecological value |
Mostly waterbirds |
Vary |
Transient |
Reversible |
Moderate during piling process |
Moderate |
Follow noise mitigation measures, consider
alternative piling method, and avoid percussive piling during dry season (if
piling is unavoidable); no construction works should be undertaken within 100m of any night
roost after 17:00 from Feb to Sep and 16:30 from Oct to Jan |
Vibration disturbance |
Due to piling |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River: middle ecological value |
Mostly waterbirds |
Vary |
Transient |
Reversible |
Low |
Minor to moderate during dry season; minor during
wet season |
Consider alternative piling method, Avoid percussive piling during dry season (if
percussive piling is unavoidable) |
Dust and human activities |
Construction activities |
Sensitive habitats near the works area |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River, tidal marsh, mangrove, plantation in
NSW: middle ecological value; Reedbed: middle to high ecological value |
Wildlife in the vicinity |
Vary |
Transient |
Reversible |
Low |
Minor |
Good site practice |
Artificial lighting/glare |
Works area |
Sensitive habitats near the works area |
Shan Pui River, tidal marsh, mangrove, plantation in
NSW, the abandoned ponds within NSW, mitigation wetland: middle ecological
value; Reedbed: middle to high |
Nocturnal fauna including Bent-winged Firefly,
ardeids night roost, the Great Cormorant roosting in NSW and the mammal
species of conservation importance |
Vary |
Temporary |
Reversible |
Low |
Minor to moderate |
Night works will
be avoided; Outdoor lighting
associated with the construction works of the barrage after 18:00 should be
avoided during May to September; Good site
practice, reduction of glare/lighting |
Construction disturbance to recognized sites,
important habitats and species of conservation importance |
Construction activities in particular noise |
Wetland habitats in Shan Pui River and Nam Sang Wai |
Shan Pui River, tidal marsh, mangrove, the abandoned
ponds within NSW and semi-natural watercourse: middle ecological value; Reedbed: middle to high ecological value |
Mostly waterbirds |
Vary |
Temporary |
Reversible |
Moderate during piling process |
Moderate during dry season, minor to moderate during
wet season |
Follow noise mitigation measures, and avoid
percussive piling during dry season; no construction works should be undertaken within
100m of any night roost after 17:00 from Feb to Sep and 16:30 from Oct to Jan |
Operational
Phase ¡V Direct Impact |
||||||||||
Habitat loss |
Due to the presence of pumping station and E&M
room |
Plantation, WBA (YLN S4) |
Plantation: low ecological value; YLN S4: low to middle ecological value |
Low diversity and abundance of flora and fauna |
0.29ha |
Permanent |
Not reversible |
Low |
Plantation: Minor; WBA: insignificant |
No specific mitigation measure for plantation loss
under ecology, only compensatory planting under LVIA; No net loss of wetland will be achieved by operation
of tidal barrier to allow waters from Deep Bay flush in 50m beyond existing
inflatable dam |
Fragmentation (water connectivity) |
Due to the presence of the proposed barrage |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River: middle ecological value |
Aquatic fauna includes Gobiopterus macrolepis
and semi-aquatic fauna includes otter |
Relatively low number of Gobiopterus macrolepis |
Permanent |
Not reversible |
Low |
Minor |
Operation of tidal barrier to allow waters from Deep
Bay flush in and provision of ecological trench to maintain water
connectivity |
Fragmentation (flight path of waterbirds) |
Due to the presence of the proposed barrage |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River and Kam Tin River: middle ecological
value |
Waterbirds |
Low numbers of waterbirds compared to Shan Pui
River, Nam Sang Wai and Deep Bay area |
Permanent |
Not reversible |
Low |
Minor |
No |
Operational
Phase ¡V Indirect Impact |
||||||||||
Water quality (change of salinity) |
With the tidal barrier blocking the exchange of
waters |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River: middle ecological value |
Food source of waterbirds and aquatic fauna |
Vary |
Permanent |
Not reversible |
Low |
Insignificant |
No |
Change of hydrodynamics and sedimentation |
Water discharge during operation of barrage |
Channelized watercourse |
Very low ecological value for Section 1-3; low to
middle for Section 4; Shan Pui River: middle ecological value |
Waterbirds and aquatic fauna |
Vary |
Permanent |
Not reversible |
Low |
Insignificant |
Discharge design to minimize scouring effect |
Bird collision |
Parapet walls, buildings |
N/A |
N/A |
Birds |
Vary |
Permanent |
Not reversible |
Low |
Minor |
Environmental friendly design |
Artificial lighting/glare |
Pumping stations and E&M room |
Sensitive habitats in the vicinity |
Shan Pui River, tidal marsh, mangrove, plantation in
NSW, the abandoned ponds within NSW, mitigation wetland: middle ecological
value; Reedbed: middle to high |
Nocturnal fauna including Bent-winged Firefly,
nocturnal mammal, Great Cormorant and ardeids night roost |
Vary |
Temporary |
Reversible |
Low |
Minor |
Environmental friendly design |
General disturbance to recognized sites, important
habitats and species of conservation importance |
Noise and human disturbance |
Wetland habitats in Shan Pui River (WBA) and Nam
Sang Wai (WCA) |
Shan Pui River, semi-natural watercourse, tidal
marsh, mangrove and abandoned ponds within NSW: middle ecological value; Reedbed: middle to high ecological value |
Mostly waterbirds |
Vary |
Temporary |
Reversible |
Very low |
Insignificant |
No |
7.9.1
Where possible, suitable type of the
future low flow pump for the barrage should be selected, which should be fish
friendly to avoid injury or mortality of aquatic fauna caused by the operation
of the low flow pump.
7.10.1
Only 0.29ha of plantation
of low ecological value will be lost permanently, while no net loss of wetland
will occur due to the decommissioning of the existing inflatable dam to release
some space and the operation of tidal barrier can allow waters from Deep Bay
flush in 50m beyond the existing inflatable dam to offset the wetland loss
(0.26ha watercourse) due to the permanent structures at the channelized
watercourse.
7.10.2
The unmitigated construction noise disturbances on
migratory/overwintering waterbirds and their associated wetland habitats
(particularly the key wetland habitats for the waterbirds and the wetland
habitats adjacent to the Project Site) during dry season as well as on resident
waterbirds that are present all year round and the key wetland habitats for
those species during wet season would be a key issue of the Project. Further to
the provision of noise barriers for the hydraulic breakers mounted on
excavators used in demolition works proposed, all other practicable effective
mitigation measures have been fully explored and exhausted in order to further
reduce the noise impact arising from the construction to the wetland habitats
and associated waterbirds, particular migratory/overwintering ones. Noise
mitigation measures proposed to reduce the overall all construction disturbance
from the Project Site include erection of noise barriers with absorptive
materials of about 2-3m high along the works area, provision of noise
barrier/acoustic mat to piling plant and breakers, provision of noise enclosure
for construction equipment and use of QPME. Furthermore, in light of the
presence of migratory/overwintering waterbirds within the assessment area, all percussive piling works and
demolition works using breaker mounted on excavator will only be conducted
during wet season when the area is utilized mainly by more-disturbance-tolerant
resident waterbirds.
Residual impacts to wetland habitats immediately
adjacent to the Project Site and associated migratory/overwintering waterbirds
during dry season
7.10.3
While some affected habitats are located immediately
adjacent to the Project Site (YLN Section 4, Shan Pui River, Nam Sang Wai),
they supported generally lower number of avifauna species of conservation
importance when compared to the Deep Bay area. With the avoidance of demolition
using breakers mounted on excavators and percussive piling, as well as
the implementation of the abovementioned noise mitigation measures proposed to
reduce the overall all construction disturbance from the Project Site, it is
considered that there would be no significant noise disturbance on the wetland
habitats adjacent to the Project Site. Furthermore, the key wetland habitats
are well-connected to the wetland habitats adjacent to the Project Site and
there are ample of continuing and extensive wetland habitats in the vicinity of
the assessment area (including about 1,500 ha of wetland in the Ramsar Site
north to the assessment area), given the ability of birds to move away from
sources of disturbance, no unacceptable residual adverse ecological impacts on
the migratory/overwintering waterbirds at the wetland habitats adjacent to the
Project Site are anticipated.
Residual impacts to wetland habitats further from the
Project Site and associated migratory/overwintering waterbirds during dry
season
7.10.4
Other affected wetland habitats within the assessment
area and the key wetland habitats that supported the greatest numbers of
overwintering/migratory waterbirds during dry seasons are located further from
the Project Site and the magnitude of construction noise disturbance experience
by waterbirds is expected to be further reduced. Additional noise mitigation
measures have been proposed to avoid percussive piling and demolition using
breakers mounted on excavators during dry season and to lower the overall construction
noise levels of the construction activities, no unacceptable residual adverse
ecological impacts on these wetland habitats and the associated
migratory/overwintering waterbirds are anticipated.
7.10.5
Reference has been made to other EIA studies that were
also nearby sensitive wetland habitats on the acceptability of the noise
impacts from non-percussive construction activities on waterbirds. For
instance, the works boundary of a ventilation building of Express Rail Link
(XRL) (MTRC 2009) was located only around 15m from fishponds in WCA. While no
percussive piling works were required, the construction tasks of the building
required were quite similar to general construction activities required under this
Project (e.g. superstructure). Ecological monitoring of avifauna community was
conducted in wetland habitats nearby works area in fishponds within WCA in Mai
Po and drainage channel upstream of Kam Tin River at Tai Kong Po during the
construction from 2010 to 2017 (MTRC 2009; MTRC 2018). Throughout the monthly
ecological monitoring, while fluctuations of avifauna population were
encountered, no adverse impacts from the construction works on the population
or composition of avifauna communities had been identified with the proper
implementation of appropriate mitigation measures (MTRC 2018).
Residual impacts to wetland habitats and associated
resident waterbirds during wet season
7.10.6
While percussive piling works and demolition using
breakers mounted on excavators would be conducted during wet season, the
magnitude of the percussive piling
works and demolition using breakers mounted on excavators during wet season is
expected to be effectively controlled with the implementation of additional
mitigation measures proposed, including erection of noise barriers with
absorptive materials of about 2-3m high, provision of noise barrier/acoustic
mat to piling machines and breakers, provision of noise enclosure for
construction equipment and use of QPME. It is also worth noting that the 500m
assessment area is utilized mainly by low number of disturbance-tolerant
resident waterbirds in wet season that would be a lot less affected than the
migratory/overwintering waterbirds. No unacceptable residual adverse ecological
impacts on wetland habitats within the assessment area and the associated
resident waterbirds during wet season are anticipated.
7.11.1
Mitigation
measures have been proposed under this Project to control any potential
indirect impacts to the nearby sensitive wetland habitats and associated
wildlife, particularly waterbirds. Implementation of the recommended mitigation
measures described above (e.g. avoidance of recognized sites of
conservation importance, avoidance of percussive piling and demolition using
breakers mounted on excavators during dry season, provision of noise barriers
along existing fence of Project Site, provision of movable noise barriers/acoustic
mat on breakers and piling plants, use of enclosure for construction plant, use
of QPME, restriction of construction hours of construction activities with PME,
implementation of all good site practices etc.) should be monitored and audited
weekly throughout the construction phase to ensure proper implementation of the
proposed mitigation measures. In case of non-compliance, the contractor should
be informed to strengthen the proposed mitigation measures accordingly.
7.11.2
Monthly
ecological monitoring in both wet and dry seasons, focusing on avifauna species
of conservation importance and overwintering waterbirds utilizing wetland
habitats within 500m of the Project Site, should be conducted during
construction phase to monitor the effectiveness of proposed mitigation measures
and detect any unpredicted indirect ecological impacts arising from the
proposed Project. Remedial actions can then be recommended, where appropriate,
based on the impact monitoring results.
7.11.3
Monthly
monitoring of the area within 100m from the Project boundary to check the
location and status of any active night roost should be conducted during the
construction phase to monitor the effectiveness of proposed mitigation measures
and detect any unpredicted indirect ecological impacts arising from the
proposed Project. Remedial actions can then be recommended, where appropriate,
based on the impact monitoring results.
7.11.4
Details
of environmental monitoring and audit (EM&A) requirements are discussed in
the separate EM&A Manual.
7.12.1
A literature review and ecological field surveys have
been conducted. A total of 14 habitat types, including channelized watercourse,
semi-natural watercourse, pond, abandoned wet agricultural land/freshwater
marsh, tidal marsh, mangrove, reedbed, mitigation wetland, shrubland,
agricultural land, mixed woodland, plantation and wasteland and developed area,
were recorded within the 500m assessment area, with channelized watercourse,
plantation and developed area being the habitats recorded within the Project
Site. The ecological values of the wetland associated habitats including
channelized watercourse (only YLN
Section 4, SPR, KTR), semi-natural watercourse, pond, abandoned wet
agricultural land/freshwater marsh, tidal marsh, mangrove, reedbed and
mitigation wetland are at least low to middle, middle or middle to high. The
other habitats, except shrubland, plantation in NSW, which are of low to middle
ecological value, are considered of low or very low ecological value. Species
of conservation importance recorded within the 500m assessment area included 2
flora, 3 mammals, 51 avifauna, 5 herpetofauna, 9 butterflies, 3 odonates, 1
aquatic fauna and the endemic Bent-winged Firefly. Only 14 avifauna of very low
abundance and 1 fish species of conservation importance were recorded within
the Project Site.
7.12.2
Potential direct impacts on
natural habitats and recognized sites of conservation importance within the
assessment area except WBA inside Project Site have been avoided through
confinement of construction works within the proposed works area. Only 0.29ha
of plantation of low ecological value will be lost permanently, while net
wetland loss will not occur due to the decommissioning of the existing
inflatable dam to release some space and the deepening of the bed of the watercourse together with the operation of tidal
barrier can allow waters from Deep Bay flush in 50m beyond the location of the existing inflatable dam to
offset the wetland loss (i.e. 0.26ha watercourse) due
to the permanent structures at the channelized watercourse.
7.12.3
Major indirect impacts due
to construction noise disturbances from demolition using breakers mounted on
excavators and piling works on key wetland habitats within the assessment area
and in close proximity to the Project Site as well as migratory/overwintering
waterbirds have been avoided through scheduling of percussive piling works and demolition using breakers mounted on excavators
outside dry season (i.e. November to March, which is the peak overwintering
period of waterbirds).
7.12.4
As the YLN Section 4 will be enhanced ecologically,
with the design of the tidal barrier to allow brackish waters flushing in the YLN, no negative ecological impacts due to habitat loss are predicted. On
the other hand, the flight-line of waterbirds to-and-fro the YLN Section 4 and
Shan Pui River were limited, with the manoeuvrability of waterbirds and the
unlikely feeding and roosting grounds in the upstream of YLN,
potential impacts to flight-line of waterbirds due to the barrage is considered
minor.
7.12.5
Hydrodynamics at the Old Kam Tin River as well as Shan
Pui River will not be changed significantly due to the large waterbody
of Deep Bay. While the scouring effects to the exposed mudflat during low tide
can be minimized by good discharging design. As there will be no strong
artificial lighting, with the proposed mitigation measure in place, potential
impacts from light to nocturnal life including Bent-winged Firefly are
considered minor.
7.12.6
Mitigation measures have been
proposed during construction stage. According to the ecological survey data
from present study, Shan Pui River recorded a relatively higher abundance of
waterbirds in dry season. In order to minimize the construction noise
disturbance on the nearby wetland habitats and the associated
disturbance-sensitive overwintering/migratory waterbirds, which are most
abundant during the dry season months, the comparatively disturbing
construction works i.e. percussive piling works and demolition using breakers
mounted on excavators, would therefore be scheduled outside the dry season
(i.e. November to March, which is the peak overwintering period of waterbirds).
In addition, a pre-construction survey is recommended for areas within 100m
from the Project boundary to confirm the location and status of the night
roost. Ardeid
night roost was recorded at a site along Kam Tin River. No construction works should be undertaken within 100m from any night
roost confirmed by the pre-construction survey after 17:00
from February to September and 16:30 from October to
January to avoid disturbance to ardeid night
roost. Within YLN Section 4 of the Project Site, fish species of conservation
importance i.e. Gobiopterus macrolepis
was recorded. Direct impact to this species is likely in the works area of the
tidal arrier during construction phase, and translocation of this species is
recommended. Capture-and-translocation of this fish species will be implemented
in the works area of the tidal barrier and pumping station prior to
construction works to minimize the impacts on this species of conservation
importance.
7.12.7
With the implementation of the recommended mitigation measures
(e.g. avoidance of percussive piling and demolition using breakers mounted on
excavators and use of alternative quieter construction method during peak
overwintering period within dry season; provision of noise barriers around
Project Sit, provision of movable noise barrier/acoustic mat for piling plants
and breaker; use of enclosure for construction plant, use of QPME; restriction
of construction activities within specified months, etc.), no unacceptable
adverse residual impacts would be expected during construction or operational
phase.
7.12.8
Ecological monitoring should be conducted during
construction phase to monitor the effectiveness of proposed mitigation measures
and detect any unpredicted indirect ecological impacts arising from the
proposed Project and the implementation of mitigation measures would be subject
to regular audit as part of the EM&A programme.
(1) Corlett,
R. T., Xing, F., Ng, S. C., Chau, L. K. C., & Wong, L. M. Y. (2000). Hong
Kong vascular plants: distribution and
status. Memoirs of the Hong Kong Natural History Society, 23: 1-157.
(2) Cutts, N., Hemingway, K. and Spencer, J. 2013. Waterbird Disturbance Mitigation Toolkit Informing Estuarine Planning & Construction Projects. Produced by Institute of Estuarine & Coastal Studies (IECS). University of Hull.
(3) Cutts, N., Phelps, A. and Burdon, D. 2008. Construction and Waterfowl: Defining Sensitivity, Response, impacts and Guidance. Institute of Estuarine and Coastal Studies (IECS). University of Hull.
(4) Farmer, A.M., 1993. The effects of dust on
vegetation - a review. Environmental pollution, 79(1): 63-75.
(5) Fellowes, J.R., Lau, M.W.N., Dudgeon, D., Reels, G.T., Ades, G.W.J., Carey, G.J., Chan, B.P.L, Kendrick, R.C., Lee, K.S., Leven, M.R., Wilson, K.D.P. and Yu, Y.T. 2002. Wild animals to watch: terrestrial and freshwater fauna of conservation concern in Hong Kong. Memoirs of the Hong Kong Natural History Society 25: 123-159.
(6) Hong Kong Jockey Club (HKJC). 2005. Proposed
Extension of Public Golf Course at Kau Sai Chau Island, Sai Kung. Environmental
Impact Assessment Report. Prepared by Binnie Black & Veatch Hong Kong Ltd for the Hong
Kong Jockey Club.
(7) Hong Kong Observatory (HKO), 2020. https://www.hko.gov.hk/en/index.html
(8) Klein, M.L., Humphrey, S.R. and Percival, H.F. 1995. Effects of ecotourism on distribution of waterbirds in a wildlife refuge. Conservation Biology 9: 1454-1465
(9) Lee, W.H., Liu, E., Choi, I.C., Tsim, S.T.
(2004). Summer Breeding and Winter Night Roosting Sites of Egrets in Hong Kong 2003. Hong
Kong Biodiversity (Agriculture, Fisheries and Conservation Department
newsletter) (6): 10-12
(10) MTR Corporation Ltd (MTRC). 2009. Express
Rail Link. Environmental Impact Assessment Report. Prepared by AECOM Asia Co
Ltd for MTR Corporation Ltd.
(11) MTR Corporation Ltd (MTRC). 2010. South
Island Line (East). Environmental Impact Assessment Report. Prepared by AECOM Asia Co Ltd for MTR
corporation Ltd.
(12) MTR Corporation Ltd (MTRC). 2018. Archive of
Environmental Monitoring and Audit Reports for Express Rail Link.
https://x.dantemanager.net/monitor/EnvPerformance!listEMA.action
(13) Qin et al., 2017. Threatened Species List of China¡¦s Higher Plants. Biodiversity Science 2017,
Vol. 25,
Issue (7):
696-744.
(14) Yip, J. K., Yip, J. K. L., Liu, E. K. Y., Ngar, Y. N., & Lai, P. C. C. (2010). A floristic survey of marshes in Hong Kong. Hong Kong Biodiversity 19: 7-16.