CONTENTS
2.6 Proposed Location of Access Tunnel and Tunnel Portal
2.7 Proposed Layout for the Project
2.8 Consideration of Construction Methodologies
2.9 Tackling Environmental Challenges and Options Considered
2.10 Environmental
Initiatives
2.11 Collating
and Addressing Public Views
2.14 Potential Environmental Impacts
Arising from Construction and Operation of the Project
TABLES
Table 2.1 Advantages and Disadvantages of Proposed Cavern
Options
Table 2.2 Advantages and
Disadvantages of Proposed Tunnel Options
Table 2.3 Consideration of Construction Methods for Tunnels and Caverns
Table 2.4
Summary of Public Views
Table 2.5
Potential Concurrent Project
Table 2.6 Indoor Air Quality Objectives for Office and
Public Places
a)
Construction of the relocated DHSRs and associated
pumping stations and water main laying works;
b)
Construction of tunnels, adits, ventilation
system and caverns for accommodating the relocated DHSRs and the associated
facilities;
c)
Terminating the operation of the existing
DHSRs and the associated facilities; and
d)
All other associated works that are
incidental to and necessary for the completion of the Project.
Table 2.1 Advantages and Disadvantages of
Proposed Cavern Options
Cavern Option |
Land Matter |
Environmental Considerations |
Other Considerations |
Cavern Option 1 - hillsides
north of Chuk Yuen North Estate |
In government land (“Green
Belt” zone between the Tsz Wan Shan, Diamond Hill & San Po Kong Outline
Zoning Plan No. S/K11/29 and the Wang Tau Hom & Tung Tau Outline Zoning
Plan No. S/K8/23) |
·
Noise and dust impacts during
open excavation but controllable when inside cavern ·
Relatively further away from
the Lion Rock Country Park (LRCP) compared to Options 2 and 3 |
·
The site is in close proximity
to the existing DHSRs, which allows the relocated DHSRs to be housed and
positioned at similar level as the invert levels of the existing DHFWSR and
DHSWSR ·
The geology of the proposed
relocation site, belonging to hard granite with no obvious weak zones and
faults, is most suitable for construction of large caverns ·
Great public concern on the
blasting impact on their private slopes due to its close proximity from the
proposed caverns |
Cavern Option 2 - hillside
north of Ma Chai Hang FWSR |
In government land (“Green
Belt” zone of the Wang Tau Hom & Tung Tau Outline Zoning Plan No.
S/K8/23) |
·
Noise and dust impacts during
open excavation but controllable when inside cavern ·
Closer to LRCP than Option 1 |
·
Relevant WTSDC members and
local public requested to further revise the cavern location in order to
maximise the distance between the proposed caverns and nearby housing estates |
Cavern Option 3 - hillside
northwest of Ma Chai Hang FWSR |
Same as Cavern Option 2 |
·
Noise and dust impacts during
open excavation but controllable when inside cavern, and less impact to nearby
residents is anticipated compared with Option 2 ·
Closer to LRCP than Option 2
but no encroachment |
·
Watermains laying works at Chui
Chuk Street will no longer be required |
Cavern Option 4 – hillside
north of Lion Rock Park |
Same as Cavern Option 2 |
·
Greatest distance from nearby
residential areas amongst all the four options ·
Closer to LRCP than Option 2
but no encroachment |
·
Potential impact to the structural
integrity of MTRC Shatin-Central Link (SCL) Tunnel due to proximity ·
Poor ground condition as revealed
by results from ground investigation |
Table 2.2 Advantages
and Disadvantages of Proposed Tunnel Options
Tunnel
Options |
EVA (Notes 1 & 2) |
Land Matters |
Environmental Considerations |
Other Considerations |
Tunnel
Option 1 – Shatin Pass Road near Fat Jong Temple |
Not
recommended due to constraint in Shatin Pass Road (i.e. gradient 1:5) |
Inside
Government land |
·
Comparatively
lesser air / noise sensitive receivers surrounding the proposed tunnel portal,
but will affect woodland and stream habitat ·
Relatively
short tunnel length among other options which will produce lesser excavated
material for disposal, dust and noise impact. ·
Low visual
and landscape impact generated from construction of tunnel portal |
·
Close to
existing water main network to Fung Wong Fresh and Salt Water Service
Reservoir ·
Could be
used as utility gallery for water mains to Fung Wong Fresh and Salt Water
Service Reservoir, also serve as emergency exit |
Tunnel
Option 2 – Shatin Pass Road near Ying Fuk Court |
Not
recommended due to inside private slope |
Inside
private slope |
·
Locating
on existing slope and opposite to Wong Tai Sin Hospital mainly which is
locating away from residential areas ·
Potential
noise and dust impact, longer tunnel length among Options 1-5, 6a & 6b leading
to more excavated materials requiring handling and disposal ·
Relatively
low visual and landscape impact generated from construction of tunnel portal
which is locating on existing slope |
·
Close to
Chuk Yuen North Estate, CLP’s pylons |
Tunnel
Option 3 – Wing Chuk Street |
Not
recommended due to inside private slope |
Inside
private slope |
·
Locating
on existing slope and opposite to Chuk Yuen North Estate ·
Potential
noise and dust impacts, generated excavated materials will be similar for
Options 3-5, 6a & 6b ·
Relatively
low visual and landscape impact generated from construction of tunnel portal
which is locating on existing slope |
·
Close to
Chuk Yuen North Estate |
Tunnel Option
4 – Junction between Wing Chuk Street & Chui Chuk Street |
Not
recommended due to inside private slope |
Inside
private slope |
·
Locating
on existing slope and opposite to Pang Ching Court ·
Potential
noise and dust impacts, generated excavated materials will be similar for
Options 3-5, 6a & 6b ·
Relatively
low visual and landscape impact generated from construction of tunnel portal
which is locating on existing slope |
·
Close to
Chuk Yuen North Estate and Pang Ching Court |
Tunnel
Option 5 – Chui Chuk Street |
Feasible,
significant traffic impact anticipated during construction stage |
Inside
Government land |
·
Locating
on existing slope and opposite to Pang Ching Court ·
Potential
noise and dust impact, generated excavated materials will be similar for Options
3-5, 6a & 6b ·
Relatively
low visual and landscape impact generated from construction of tunnel portal
which is locating on existing slope |
·
Close to
Chuk Yuen North Estate and Pang Ching Court ·
Impact on
Chui Chuk Street which is the sole access road for Tsui Chuk Garden ·
There is
constraint on laying water mains in Chui Chuk Street due to existing UUs ·
Could be considered as EVA / watermains laying to
existing network |
Tunnel
Option 6a & 6b – Ma Chai Hang Fresh Water Service Reservoir |
Feasible,
further liaison with FSD is required to upgrade the existing access road |
Inside
Government land |
·
Potential
generate larger noise and dust impacts to Tsui Chuk Garden due to close
proximity of the work site, direct loss of woodland habitat (Option 6a) for construction
of booster pumping station and widening of the existing access road ·
Relatively
short tunnel length which produce lesser excavated material for disposal ·
Visual and
landscape impact generated from construction of tunnel portal owing to the
close proximity to nearby housing estates (e.g. Tsui Chuk Garden which is
located to the south of the tunnel portal). |
·
Far away
from existing water main network, not suitable for laying water mains
·
The
existing substandard access road will need to be widened for use by emergency
vehicles, and the slopes along the access road need to be upgraded. ·
Larger
blasting impact to adjacent areas ·
WTSDC
member and the residents of Tsui Chuk Garden raised their great concern on
the tunnel portal location ·
Local
public had great concern about temporarily closure of the access road to Ma
Chai Hang FWSR during the construction |
Tunnel
Option 7 – Near the entrance of Lion Rock Park |
Separate EVA
not required as passage length not exceeding 750m |
Inside
Government land |
·
Relatively
longer tunnel length which produce larger quantity of excavated material for
disposal ·
Potential
dust and noise impacts to the nearby sensitive receivers are expected to be longer
due to longer construction programme when compare to Tunnel Options 6a &
6b ·
Direct
loss of woodland habitats due to construction ·
Potential
impact on existing flora species of conservation importance ·
Relatively
low visual and landscape impact generated from construction of tunnel
portal |
·
No
additional pumping station and widening of existing access road to Ma Chai
Hang FWSR would be required ·
Relatively
low blasting impact to adjacent areas ·
Relatively
less public concern |
Tunnel
Option 8 - Adjacent to the Lion Rock Park Transit Nursery Landscape Section |
Separate EVA
not required as passage length not exceeding 750m |
Inside
Government land |
·
Direct
loss of existing plantation habitats on slope
·
Relatively
longer tunnel length which produce larger quantity of excavated material for
disposal ·
Potential
dust and noise impacts to the nearby sensitive receivers are expected longer
due to longer construction programme when compare to Tunnel Options 6a &
6b ·
Relatively
low visual and landscape impact generated from construction of tunnel
portal |
·
No
additional pumping station and widening of existing access road to Ma Chai
Hang FWSR would be required ·
Relatively
low blasting impact to adjacent areas ·
Potential
effect to the hikers to the LRCP |
Notes:
1. According to the “Guide to Fire Safety
Design for Cavern” published by Building Department, an emergency vehicular
access (EVA) to caverns shall be provided for firefighting and rescue
purposes, except if the safe passage would not exceed 750m.
2. The gradient of the EVA should not be
greater than 1:10 and it should allow for safe operation of a vehicle with
gross weight of 30 tons according to the Code of Practice for the Provision
of Means of Access for Firefighting and Rescue Purposes (MoA).
|
Table
2.3
Consideration of Construction Methods for
Tunnels and Caverns
Construction
Methods Options for Tunnels and Caverns |
Engineering
Consideration |
Environmental
Consideration |
Construction
Duration |
Other
Considerations |
Recommendation |
Drill and
break (for
tunnel) |
·
Commonly adopted in tunneling project |
·
Noise and dust impacts during open excavation but
controllable when inside cavern |
Slower production and longer construction
duration |
- |
Recommended |
Drill and
blast (for tunnel
and caverns construction) |
·
Commonly adopted in tunneling project |
·
Noise and dust impacts during open excavation but
controllable when inside cavern |
Moderate production and construction duration |
·
Potential hazard from the delivery, storage and
handling of explosives ·
Requires permit for use of explosives |
Recommended |
Cut and
Cover (initial
short section connecting to the portal) |
·
Suitable for the tunnel section where the rock
cover is less than half of tunnel span |
·
Noise and dust impacts but controllable when
noise barrier, dust screen and water spraying are implemented |
Shorter construction duration |
·
Require TTA and the ELS is needed to be erected in
stages (bay by bay) for the Lion Rock Road section. |
Recommended |
TBM (including
similar methods such as horizontal directional drilling and raised boring
machine) |
·
Suitable for small to medium size tunnel ·
Requires larger launching area for TBM and to
retrieve cutter head ·
Not suitable for abrupt bend |
·
Less noise and dust impact |
Shorter construction duration |
·
Limited works space in tunnel portal ·
High capital cost |
Not
recommended |
Use of
chemical expansion agent |
·
Quiet |
·
No noise and dust impact |
Very slow production and very long construction duration |
·
Drilling is still required ·
Not suitable for fractured and weak rock mass |
Not
recommended |
·
To accommodate the relocated DHSRs and DHPS closer
to the vehicle access portal and includes a “Mean of Escape” (MOE) separated
from the driveway side in the proposed access tunnel, thus, the construction of
another emergency exit tunnel and portal of the cavern at Shatin Pass Road could
be eliminated; and
·
to consider the alternative access tunnel
with tunnel portal located adjacent to the Lion Rock Park Transit Nursery
Landscape Section rather than near Ma Chai Hang FWSR.
Avoidance of the Encroachment of Woodland
Avoidance of the Direct Impacts on Species of Conservation Interest
Minimisation
of Construction Dust and Noise Impacts to Local Residents
Minimisation of the Excavation
Volume of C&D
Materials
·
to integrate the MOE inside the access tunnel
(i.e. emergency exit tunnel can be eliminated); and
·
to shorten the length of the access tunnel by
250 metre, where the length of tunnel is about 1,000m under original caverns
location and about 750m under preferred cavern location.
Minimisation
of Visual Impact
Provision
of Landscape Area/Compensatory Planting
·
Preservation of watercourse, woodland and
other ecological resources and sensitive area;
·
Reuse of granitic rocks (i.e. other projects or
public fill reception facility) from access tunnel excavation;
·
Minimise the footprint of the relocated DHSRs;
and
·
Providing reliable water supply system in Upper
Wong Tai Sin district (Fresh Water) and in Central Kowloon (Salt Water).
Stakeholders
|
Major Concern
|
Responses
|
FS Stage
|
||
Residents of Housing Estates nearby
|
Potential environment impact during construction, such as dust and
noise
|
·
Generally, dust suppression
measures, including watering once per hour, will be incorporated in
accordance with the requirements of the Air Pollution Control (Construction
Dust) Regulation in the construction site. (See Section 3.8.1)
·
For the construction of cavern
and tunnel, blast nets / canvas covers will be installed inside the tunnel
and portal door will also be installed and closed before and during blasting
(See Section 3.8.6). A dust filter will also be installed at the ventilation
shaft of the tunnel portal to filter all emissions emitted inside cavern.
(See Table 3.11)
·
To mitigate the noise impact from
the construction of tunnel & cavern, noise enclosure lined with
absorptive materials shall be provided at the tunnel portal. The acoustic
doors shall remain closed throughout the construction period. (See Section
4.8.3)
·
With the implementation of the
recommended mitigation measures, adverse dust and noise impact are not
anticipated. (See Sections 3.8. & 4.8)
|
WTSDC Members
|
Tunnel portal at Ma Chai Hang Fresh Water Service Reservoir is located
in close proximity to nearby housing estates
|
·
Alternative tunnel portal
locations (Options 7-8) are reviewed in investigation stage. (See Table 2.2)
·
Tunnel portal next to Lion Rock
Park Transit Nursery is recommended (Tunnel Option 8) to minimise impact of
construction. (See Section 2.7)
|
Investigation Stage
|
||
Residents of nearby Housing Estates and DC Members
|
Cavern is located near nearby housing estates
|
·
Cavern locations (Options 2-4)
reviewed in investigation stage. (See Table 2.1)
·
Cavern located hillside north to
Ma Chai Hang Fresh Water Service Reservoir (Cavern Option 3) is recommended
to maximise clearance from nearby housing estate. (See Section 2.7)
|
Green Group
|
·
Cavern and tunnel excavation may
result in groundwater infiltration, which will cause the potential
groundwater table drawdown.
·
The construction of cavern and
tunnel will generate large quantity of the C&D materials.
·
Aboveground ventilation
facilities may impose environmental impacts such as air quality and visual
impacts.
|
·
Groundwater control measures will
be implemented during the construction of cavern and tunnel. The mitigation
measures include: undertake rigorous probing of the ground ahead of
excavation works to identify zones of significant water inflow. Pre-grouting
will be applied to reduce the water inflow, waterproof lining will be
installed after formation of the tunnels and cavern, etc. (Section 5.8)
·
C&D materials will be reuse
on site as far as practical, Rest of the inert C&D materials will be disposed
of at TKO Area 137 Fill Bank for reuse in other construction projects.
(Section 6.5)
·
Aboveground ventilation facilities are not
required under the latest design of cavern and tunnel to avoid any adverse
impacts to the environment. (Sections 2.9.7 & 2.9.18)
|
Table
2.5 Potential Concurrent Project
Project Name |
Target Work Commencement
Date |
Target Work Completion
Date |
CE 28/2017 (HY) - Pedestrian Link near Chuk Yuen North Estate – Design
and Construction |
Mid 2023 |
Mid 2029 |
CE 48/2018 (HY) - Improvement of Lion Rock Tunnel |
Mid 2024 |
[1] |
[1] Project details is not available for
consideration at time of reporting. |
Health Impact on Radon
Indoor Air Quality Objectives for Office and
Public Places
Table
2.6
Indoor Air Quality Objectives for Office and
Public Places
Parameter |
Unit |
8-hour average |
|
Excellent Class |
Good Class |
||
Radon (Rn) |
Bq/m3 |
< 150 |
< 200 |
ProPECC PN 1/99 Control of Radon Concentration in New Buildings
WHO Recommendation
Cultural
Heritage
END OF TEXT