CONTENTS

 

7          Land Contamination.. 7-1

7.1             Introduction.. 7-1

7.2             Relevant Legislation, Policies, Standards and Criteria.. 7-1

7.3             Assessment Methodology.. 7-1

7.4             Site Appraisal.. 7-1

7.5             Mitigation Measure.. 7-3

7.6             Residual Impacts. 7-3

7.7             Monitoring and Audit Requirement.. 7-3

7.8             Conclusions. 7-4

 

TABLES

Table 7.1       Review of Historical Aerial Photos. 7-2

 

 


7                             Land Contamination

7.1                       Introduction

7.1.1                  This Section presents the potential implications of land contamination associated with the Project.

7.2                       Relevant Legislation, Policies, Standards and Criteria

7.2.1                  The following requirements and guidelines are relevant to assessment of land contamination.

·         Section 3.1 of Annex 19 of EIAO-TM under the EIAO;

·         Guidance Note for Contaminated Land Assessment and Remediation (August 2007);

·         Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land Management (December 2007); and

·         Practice Guide for Investigation and Remediation of Contaminated Land (August 2011).

7.3                       Assessment Methodology

7.3.1                  According to the Practice Guide, site appraisal shall precede to determine the need for site investigation, and to provide the information to support a contamination assessment, which the findings will subsequently determine if site remediation is required. The assessment area for land contamination assessment is defined as the Project Area and is presented in Figure 7.1.

7.3.2                  The site appraisal consists of the following:

·         desk-top review of existing and historical survey maps;

·         interpretation of existing and historical aerial photographs;

·         review of land use record, permitted uses of existing private lots; and

·         site walkover to verify the collected information.

7.3.3                  The site walkover was undertaken to identify any physical clues of contamination, such as presence of industrial related building structures, chemical drums, chemical or oil stains, unnatural colours / odours and abandoned piping / mechanical components.

7.4                       Site Appraisal

Review of Historical Aerial Photos and Past Land Uses

7.4.1                  A review of historical aerial photos (from 1963 – 2018) was undertaken to identify the past land uses within the project areas (Appendix 7A).  Based on the historic photos, the land uses in the areas were formerly hilly terrain, slope, agricultural lands, resettlement area, village areas, squatters, roads, vacant lands and Lion Rock Park Transit Nursery. Review of historical aerial photos is summarized in Table 7.1.

Table 7.1   Review of Historical Aerial Photos

Aerial Photo Reference

Year

Observed Land Use

Cavern and Access Tunnel Area

Works Area for Tunnel Portal & Ancillary Building

Storage Area

Works Area for Water Mainlaying

Appendix 7A_1

1963

Most area of the site was hilly terrain covered by vegetation.

Bare slope and vacant land;

Northern part of the area was part of the construction site of Lion Rock Park

Vacant land temporarily occupied by construction materials

Agricultural lands, resettlement area, village areas, vacant lands and road

Appendix 7A_2

1973

Slope covered with vegetation and vacant land

Vacant land

Agricultural lands, resettlement area, village areas, vacant lands and road

Appendix 7A_3

1982

Most area of the site was hilly terrain covered by vegetation. Part of the proposed area for access tunnel was occupied by squatters

Slope covered with vegetation and Lion Rock Park Transit Nursery

Vacant land covered with vegetation

Mainly vacant lands and roads

Under redevelopment in Chuk Yuen area

Appendix 7A_4

1993

Most area of the site was hilly terrain covered by vegetation.

Roads (including Chuk Yuen Road, Shatin Pass Road, Lung Fung Street, Sheung Fung Street and Tsz Wan Shan Road)

Appendix 7A_5

2003

Appendix 7A_6

2012

Appendix 7A_7

2018

 

Site Walkover and Present Land Uses

7.4.2                  Site walkover was undertaken in March 2020 and June 2020 to verify existing land uses and to identify potential sources and signs of contamination, such as presence of industrial activities, chemicals, oil and hazardous waste handling and storage locations, bulk storage tanks, sumps, pipelines, staining, decolouration, abnormal odours, distressed vegetation, etc.

7.4.3                  The walkover confirmed the area for tunnel portal and ancillary buildings is slopes covered with vegetation and Lion Rock Park Transit Nursery Landscape Section while the proposed storage area is currently a vacant land covered with vegetation. Most of the proposed areas for the cavern and access tunnel is hilly terrain covered by vegetation and part of the southern end of the access tunnel area is access road. For water mainlaying, the proposed works areas are mainly existing roads including Chuk Yuen Road, Shatin Pass Road, Lung Fung Street, Sheung Fung Street and Tsz Wan Shan Road. No polluting activities / sources were observed within the project site areas during the walkover. The proposed works do not encroach upon any petrol filling stations, car repair / dismantling workshops, industrial premises or other major polluting areas. Representative photos showing the existing site conditions are presented in Appendix 7B.

7.4.4                  Site inspection was conducted to examine the current conditions of the existing Lion Rock Park Transit Nursery operated by Leisure and Cultural Services Department (LCSD). The site is used for temporary storage of nursery trees/plants and with about 1,100 m2. During the site inspection, no chemical storage, generator/transformer and other potential sources and signs of contamination were identified. The floors of both building and open area of the Transit Nursery were paved and generally clean, and there was no sign of any chemical spillage/leakage. Photos 3-6 of Appendix 7B show the existing site conditions and observations for the existing Lion Rock Park Transit Nursery.  A site walkover checklist is provided in Appendix 7C. According to the findings of site walkover survey, there was no chemical/oil storage in the store room. Therefore, it is considered that the stain found on the paved floor is not chemical/oil stain (Photo 5). In fact, the store room of the nursery will be retained and will not be affected during the construction works. Thus, no associated land contamination issue would be expected.

Review of Government Records

7.4.5                  Fire Services Department (FSD) and Environmental Protection Department (EPD) have been enquired on any dangerous goods license and possible incident on spillage, leakage of chemicals or dangerous goods at the Project Area. Reply from FSD and EPD indicate that there has been no dangerous goods license, records of any incidents of spillage/leakage of chemical waste or dangerous goods with the Project Area. The relevant correspondences are provided in Appendix 7D.

7.4.6                  The EPD’s Chemical Waste Producer Register was inspected in June 2020 and no record of chemical producer was identified within the Project Area.

Summary of Findings

7.4.7                  The proposed works will be constructed on existing hilly terrain, roads, vacant lands and Lion Rock Park Transit Nursery.  No signs of suspected land contamination due to past and present land uses were identified from review of historical aerial photos and during site walkover. Based on the site appraisal results, no potentially contaminating land use / activities were identified in the Site.  Therefore, no land contamination impact associated with present and past land uses/activities is anticipated.

7.5                       Mitigation Measure

7.5.1                  As no potential land contamination issue has been identified for the Project, specific mitigation measure is considered as not necessary.

7.6                       Residual Impacts

7.6.1                  Based on the desktop appraisal and site walkover, no land contamination issue is identified. No residual impact is expected.

7.7                       Monitoring and Audit Requirement

7.7.1                  Considering no potential land contamination issue is identified, no specific monitoring is required.

7.8                       Conclusions

7.8.1                  A review of past and present land uses of the project site was conducted. Based on desk-top review and site walkover, the presence of contaminated land is not expected.

 

END OF TEXT