CONTENT
2.1 General Description of the
Project
4.4 Proposal of Use of
Portable Direct Reading Dust Meter
4.5 Laboratory Measurement/Analysis
5.2 Noise Monitoring
Parameters
5.11 Commissioning Test for
Fixed Plant Noise Sources
7 Waste
Management Implications
10 Landscape
and Visual Impacts
12.3 Choice of Construction
Method
13.2 Baseline Monitoring Report
13.3 Monthly Monitoring Report
13.4 Final EM&A Review
Reports
13.6 Interim Notifications of
Environmental Quality Limit Exceedances
TABLES
Table
4.1 Construction Dust Monitoring
Locations
Table 4.2 Summary of Construction Dust Monitoring
Programme
Table 4.3 Action and Limit Levels for Air Quality
(Dust)
Table 4.4 Event and Action Plan for Air Quality
(Dust)
Table 5.1 Proposed Construction Noise Monitoring
Locations
Table 5.2 Action and Limit Levels for Construction
Noise
Table 5.3 Event/Action Plan for Construction Noise
Table 10.1 Event and Action Plan for
Landscape and Visual
FIGURES
Project Layout |
|
Location of the
Representative Air and Noise Sensitive Receivers |
|
Location of Proposed
Air Quality Monitoring Station (Construction Phase) |
|
Locations of
Proposed Construction Noise Monitoring Stations |
APPENDICES
Tentative
Construction Programme Project Organization
for Environmental Works |
|
Sample Data Sheet
for TSP Monitoring |
|
Project
Implementation Schedule |
|
Noise Monitoring Field Record
Sheet |
|
Proactive Environmental
Protection Proforma |
|
Sample Template for Interim
Notification |
· Guide the set-up of an EM&A programme to ensure compliance with the EIA recommendations;
· Specify the requirements for monitoring equipment;
· Propose environmental monitoring points, monitoring frequency etc;
· Propose Action and Limit Levels; and
· Propose Event and Action Plans.
· Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET), and the Independent Environmental Checker (IEC) under the context of EM&A;
· Project organization for the EM&A works;
· The basis for, and description of the broad approach underlying the EM&A programme;
· Details of the methodologies to be adopted, including all laboratories and analytical procedures, and details on quality assurance and quality control programme;
· The rationale on which the environmental monitoring data will be evaluated and interpreted;
· Definition of Action and Limit Levels;
· Establishment of Event and Action Plans;
· Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints; and;
· Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures.
a)
Construction
of the relocated DHSRs and associated pumping stations and water main laying
works;
b)
Construction
of tunnels, adits, ventilation system and caverns for accommodating the
relocated DHSRs and the associated facilities;
c)
Terminating
the operation of the existing DHSRs and the associated facilities; and
d)
All other
associated works that are incidental to and necessary for the completion of the
Project.
The
Contractor
· Implement the EIA recommendations and requirements;
· Provide assistance to ET in carrying out monitoring and auditing;
· Submit proposals on mitigation measures in case of exceedances of Action and Limit Levels in accordance with the Event and Action Plans;
· Implement measures to reduce impact where Action and Limit Levels are exceeded; and
· Adhere to the agreed procedures for carrying out compliant investigation.
Environmental
Team
· Set up all the required environmental monitoring stations;
· Monitor various environmental parameters as required in the EM&A Manual;
· Analyse the environmental monitoring and audit data, review the success of EM&A programme, confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions, and to identify any adverse environmental impacts arising;
· Carry out site inspection to investigate and audit the Contractors’ site practice, equipment and work methodologies with respect to pollution control and environmental mitigation measures, and take proactive actions to pre-empt problems;
· Audit and prepare audit reports on the environmental monitoring data and site environmental conditions;
· Report on the environmental monitoring and audit results to the IEC, Contractor, the ER and EPD or its delegated representative;
· Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit Levels in accordance with the Event and Action Plans;
· Undertake regular on-site audits / inspections and report to the Contractor and the ER of any potential non-compliance;
· Follow up and close out non-compliance actions; and
· Adhere to the procedures for carrying out environmental complaint investigation.
Engineer
or Engineer’s Representative
· Supervise the Contractor’s activities and ensure that the requirements in the EM&A Manual are fully complied with;
· Inform the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;
· Assist the Project Proponent in employing an IEC to audit the results of the EM&A works carried out by the ET;
· Comply with the agreed Event Contingency Plan in the event of any exceedance;
· Adhere to the procedures for carrying out complaint investigations.
Independent
Environmental Checker
· Review the EM&A works performed by the ET (at not less than monthly intervals);
· Audit the monitoring activities and results (at not less than monthly intervals);
· Validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations, monitoring procedures and location of sensitive receivers;
· Report the audit results to the ER and EPD in parallel;
· Review the EM&A reports (monthly and quarterly summary reports) submitted by the ET;
· Review the proposal on mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;
· Check the mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;
· Check the mitigation measures that have been recommended in the EIA Report and this Manual, and ensure they are properly implemented in a timely manner, when necessary; and
· Report the findings of site inspections and other environmental performance reviews to ER and EPD.
· 0.6 - 1.7 m3 per minute (20 - 60 standard cubic feet per minute) adjustable flow range;
· equipped with a timing / control device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum exposed area of 406 cm2;
· flow control accuracy: ± 2.5% deviation over 24-hour sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hour period.
· The wind sensors should be installed at 10m above ground so that they are clear of obstructions or turbulence caused by buildings;
· The wind data should be captured by a data logger, the data shall be downloaded for analysis at least once a month;
· The wind data monitoring equipment should be re-calibrated at least once every six months; and
· Wind direction should be divided into 16 sectors of 22.5 degrees each.
Table 4.1 Construction Dust Monitoring Locations
ID |
ASR ID |
Description |
Impact
Monitoring Period [1] |
DM-1 |
ASR 2 |
Tennis Court near Tin Ma Court |
Year 2022-2026 |
DM-2 |
ASR 5 |
Chun Sing House, Tin Ma Court |
Year 2022-2026 |
DM-3 |
ASR 7 |
Grace Methodist Church Kindergarten |
Year 2022-2026 |
DM-4 |
ASR 9 |
Block 6, Tsui Chuk Garden |
Year 2022-2026 |
Note: [1] The monitoring period is
determined based on the tentative construction period of the nearest
worksites within the Project Site and will subject to adjustment based on the
actual construction programme of the relevant contracts in the
Construction Stage. |
i.
At the
site boundary or such locations close to the major dust emission source;
ii.
Close to
the air sensitive receivers as defined in the EIAO-TM;
iii.
Proper
position/ sitting and orientation of the monitoring equipment; and
iv.
Take into
account the prevailing meteorological conditions.
i.
a
horizontal platform with appropriate support to secure the samplers against
gusty wind shall be provided;
ii.
the distance
between the sampler and an obstacle, such as buildings, shall be at least twice
the height that the obstacle protrudes above the sampler;
iii.
a minimum
of 2 metres of separation from walls, parapets and penthouses is required for
rooftop samplers;
iv.
a minimum
of 2 metres of separation from any supporting structure, measured horizontally
is required;
v.
no
furnace or incinerator flue is nearby;
vi.
airflow
around the sampler is unrestricted;
vii.
the
sampler is more than 20 metres from the dripline;
viii.
any wire
fence and gate, to protect the sampler, shall not cause any obstruction during
monitoring;
ix.
permission
must be obtained to set up the samplers and to obtain access to the monitoring
stations;
x.
a secured
supply of electricity is needed to operate the samplers; and
xi.
no two
samplers should be placed less than 2 meters apart.
Table
4.2 Summary of Construction Dust Monitoring
Programme
Monitoring Period |
Duration |
Sampling Parameter |
Frequency |
Baseline
Monitoring |
Consecutive
days of at least 2 weeks before commencement of major construction works |
1-hour TSP |
3 times per
day |
Impact
Monitoring |
Throughout
the construction phase |
1-hour TSP |
Table
4.3 Action and Limit Levels for Air Quality
(Dust)
Parameter |
Action
Level |
Limit Level |
1-hour TSP level in µg/m3 |
For baseline level 384 µg/m3, action level =
(baseline level ´ 1.3 + limit level)/2 For baseline level > 384 µg/m3,
action level = limit level. |
500 µg/m3 |
Table
4.4 Event and Action Plan for Air Quality (Dust)
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action
level exceedance for one sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform IEC and
ER; 3. Repeat
measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check contractor’s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
Action
level exceedance for two or more consecutive samples |
1. Identify
source; 2. Inform IEC and
ER; 3. Advise the ER on
the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings; 5. Increase
monitoring frequency to daily; 6. Discuss with
IEC and Contractor on remedial actions required; 7. If exceedance
continues, arrange meeting with IEC and ER; 8. If exceedance
stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss with ET
and Contractor on possible remedial measures; 4. Advise the ET
on the effectiveness of the proposed remedial measures; 5. Supervise
Implementation of remedial measures. |
1. Confirm receipt of
notification of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures
properly implemented. |
1. Submit proposals for
remedial actions to ER within 3 working days of notification; 2. Implement the agreed
proposals; 3. Amend proposal if
appropriate. |
Limit
level exceedance for one sample |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Inform ER, Contractor and
EPD; 3. Repeat measurement to confirm
finding; 4. Increase monitoring frequency
to daily; 5. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. |
1. Check
monitoring data submitted by ET; 2. Check Contractor’s working
method; 3. Discuss with ET and
Contractor on possible remedial measures; 4. Advise the ER on the
effectiveness of the proposed remedial measures; 5. Supervise
implementation of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify Contractor; 3. Ensure remedial
measures properly implemented. |
1. Take immediate
action to avoid further exceedance 2. Submit proposals for remedial
actions to IEC within 3 working days of notification; 3. Implement the agreed
proposals; 4. Amend proposal
if appropriate. |
Limit level
exceedance for two or more consecutive samples |
1. Notify IEC, ER,
Contractor and EPD; 2. Identify
source; 3. Repeat
measurement to confirm findings; 4. Increase
monitoring frequency to daily; 5. Carry out
analysis of Contractor’s working procedures to determine possible mitigation
to be implemented; 6. Arrange meeting
with IEC and ER to discuss the remedial actions to be taken; 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; 8. If exceedance
stops, cease additional monitoring. |
1. Discuss amongst
ER, ET, and Contractor on the potential remedial actions; 2. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; 3. Supervise the
implementation of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. In consultation
with the IEC, agree with the Contractor on the remedial measures to be
implemented; 4. Ensure remedial
measures properly implemented; 5. If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance is abated. |
1. Take immediate
action to avoid further exceedance; 2. Submit
proposals for remedial actions to IEC within 3 working days of notification; 3. Implement the
agreed proposals; 4. Resubmit proposals
if problem still not under control; 5. Stop the
relevant portion of works as determined by the ER until the exceedance is
abated. |
Notes:
ET – Environmental
Team; IEC – Independent Environmental Checker; ER – Engineer’s Representative
Table 5.1
Proposed Construction Noise Monitoring Locations
ID |
NSR ID |
Description |
Impact
Monitoring Period[1] [2] |
NM-1 |
NSR 2 |
Block 1, Meridian Hill |
Year 2022 - 2026 |
NM-2 |
NSR 3 |
Chun Sing House, Tin Ma Court |
Year 2022 - 2026 |
NM-3 |
NSR 5 |
Grace Methodist Church Kindergarten
|
Year 2022 - 2026 |
NM-4 |
NSR 7 |
Block 6, Tsui Chuk Garden |
Year 2022 - 2026 |
Note:
[1] The monitoring period is
determined based on the tentative construction period of the nearest worksites
within the Project Site and will subject to adjustment based on the actual
construction programme of the relevant contracts in the Construction
Stage.
i.
Monitoring
at sensitive receivers close to the major site activities that are likely to
have noise impacts;
ii.
Monitoring
should close to or at the NSRs as defined in the EIAO-TM; and
iii.
Assurance
of minimal disturbance to the occupants during monitoring.
Table 5.2
Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) * |
Notes:
If works are to be carried out
during restricted hours, the conditions stipulated in the construction noise
permit issued by the Noise Control Authority have to be followed.
*
Reduce to 70 dB(A) for schools and 65 dB(A) during school examination
periods.
Table 5.3
Event/Action Plan for Construction Noise
Event |
Action |
|||
|
ET |
IEC |
ER |
Contractor |
Action Level Exceedance |
1. Notify IEC, ER and
Contractor; 2. Carry out investigation; 3. Report the results of investigation
to the IEC, ER and Contractor; 4. Discuss with the Contractor
and formulate remedial measures; 5. Increase monitoring
frequency to check mitigation effectiveness. |
1. Review the analysed results
submitted by the ET; 2. Review the proposed remedial
measures by the Contractor and advise the ER accordingly; 3. Supervise the implementation
of remedial measures. |
1. Confirm receipt of
notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to
propose remedial measures for the analysed noise problem; 4. Ensure remedial measures are
properly implemented. |
1. Submit noise mitigation
proposals to IEC and ER; 2. Implement noise mitigation
proposals. |
Limit Level Exceedance |
1. Identify source; 2. Inform IEC, ER, EPD and
Contractor; 3. Repeat measurements to
confirm findings; 4. Increase monitoring
frequency; 5. Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6. Inform IEC, ER and EPD the causes and actions
taken for the exceedances; 7. Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional
monitoring. |
1. Discuss amongst ER, ET, and
Contractor on the potential remedial
actions; 2. Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of remedial
measures. |
1. Confirm receipt of
notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to propose remedial measures
for the analysed noise problem; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1. Take immediate action to
avoid further exceedance; 2. Submit proposals for remedial actions to the IEC
within three working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under
control; 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
Notes:
ET –
Environmental Team; IEC – Independent Environmental Checker; ER – Engineer’s
Representative
· investigate the problems and the causes;
· issue action notes to the Contractor which is responsible for the works;
· implement remedial and corrective actions immediately;
· re-inspect the site conditions upon completion of the remedial and corrective actions; and
· record the event and discuss with the Contractor for preventive actions.
Table 10.1 Event
and Action Plan for Landscape and Visual
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Non-conformity on one occasion |
1. Inform the IEC, ER and the Contractor; 2. Discuss remedial actions with IEC, ER and Contractor;
and 3. Monitor remedial actions until rectification
has been completed. |
1. Check inspection report; 2. Check Contractor’s working method; 3. Discuss with ET, ER and Contractor on possible remedial measures; 4. Advise ER on effective of proposed remedial measures; and 5. Check implementation of remedial measures. |
1. Confirm receipt of notification of
non-conformity in writing; 2. Review and agree on the remedial measures
proposed by the Contractor; and 3. Ensure remedial measures are properly
implemented. |
1. Identify source and investigate the non-conformity; 2. Amend working methods agreed with
ER as appropriate; and 3. Rectify damage and undertake any
necessary replacement. |
Repeated Non-conformity |
1. Identify sources; 2. Inform the Contractor, IEC and ER; 3. Discuss inspection frequency; 4. Discuss remedial actions with IEC, ER and
Contractor; 5. Monitor remedial actions until rectification
has been completed; and 6. If non-conformity stops, cease additional
monitoring. |
1. Check inspection report; 2. Check Contractor’s working method; 3. Discuss with ET, ER and Contractor on possible
remedial measures; and 4. Advise ER on effectiveness of proposed
remedial measures. |
1. Notify the Contractor; 2. in consultation with the ET and IEC, agree
with the Contractor on the remedial measures to be implemented; and 3. Supervise implementation of remedial measures. |
1. Identify source and investigate the
non-conformity; 2. implement remedial measures; 3. Amend working methods agreed with
ER as appropriate; 4. Rectify damage and undertake any
necessary replacement. Stop relevant portion of works as determined by ER
until the non-conformity is abated. |
a)
EIA
Report recommendations on environmental protection and pollution control
mitigation measures;
b)
works
progress and programme;
c)
individual
works methodology proposals (which shall include the proposal on associated
pollution control measures);
d)
contract
specifications on environmental protection;
e)
relevant
environmental protection and pollution control legislations; and
f)
previous
site inspection results.
· The Contractor to log complaint and date of receipt onto the complaint database and inform the ER, ET and IEC immediately;
· The Contractor to investigate, with the ER and ET, the complaint to determine its validity, and assess whether the source of the problem is due to construction works of the Project with the support of additional monitoring frequency and stations, if necessary;
· The Contractor to identify remedial measures in consultation with the IEC, ET and ER if a complaint is valid and due to the construction works of the Project;
· The Contractor to implement the remedial measures as required by the ER and to agree with the ET and IEC any additional monitoring frequency and stations, where necessary, for checking the effectiveness of the remedial measures;
· The ER, ET and IEC to review the effectiveness of the Contractor's remedial measures and the updated situation;
· The ET to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstances leading to the complaint do not recur;
· If the complaint is referred by the EPD, the Contractor to prepare interim report on the status of the complaint investigation and follow-up actions stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, for submission to EPD within the time frame assigned by the EPD; and
· The ET to record the details of the complaint, results of the investigation, subsequent actions taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.
i.
Up to
half a page executive summary;
ii.
brief
project background information;
iii.
drawings
showing locations of the baseline monitoring stations;
iv.
monitoring
results (in both hard and diskette copies) together with the following
information:
· monitoring methodology;
· name of laboratory and types of equipment used and calibration details;
· parameters monitored;
· monitoring locations;
· monitoring date, time, frequency and duration; and
· quality assurance (QA)/quality control (QC) results and detection limits;
v.
details
of influencing factors, including;
· major activities, if any, being carried out on the site during the period;
· weather conditions during the period; and
· other factors which might affect monitoring results;
vi.
determination
of the Action and Limit Levels for each monitoring parameter and statistical
analysis of the baseline data;
vii.
revisions
for inclusion in the EM&A Manual; and
viii.
comments,
recommendations and conclusions.
First
Monthly EM&A Report
i.
Executive
summary (1-2 pages);
· breaches of Action and Limit levels;
· complaint log;
· notifications of any summons and successful prosecutions;
· reporting changes; and
· future key issues.
ii.
Basic
project information:
· project organization including key personnel contact names and telephone numbers;
· programme;
· management structure; and
· works undertaken during the month.
iii.
Environmental
status
· advice on the status of statutory environmental compliance such as the status of compliance with the environmental permit (EP) conditions under the EIA Ordinance, submission status under the EP and implementation status of mitigation measures;
· works undertaken during the month with illustrations (such as location of works, daily excavation rate, etc.); and
· drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations (with co-ordinates of the monitoring locations).
iv.
A brief
summary of EM&A requirements including;
· all monitoring parameters;
· environmental quality performance limits (Action and Limit levels);
· Event-Action Plans;
· environmental mitigation measures, as recommended in the project EIA Study final report; and
· environmental requirements in contract documents.
v.
Implementation
status
· advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report.
vi.
Monitoring
result (in both hard and diskette copies) together with the following
information:
· monitoring methodology;
· name of laboratory and types of equipment used and calibration details;
· monitoring parameters;
· monitoring locations;
· monitoring date, time, frequency, and duration;
· weather conditions during the period;
· any other factors which might affect the monitoring results; and
· QA / QC results and detection limits.
vii.
Reporting
on non-compliance, complaints, and notifications of summons and successful
prosecutions:
· record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
· record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
viii.
Others
· an account of the future key issues as reviewed from the works programme and work method statements;
· advice on the solid and liquid waste management status;
· record of any project changes from the originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc.); and
· comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for examples, any improvement in the EM&A programme) and conclusions.
Subsequent monthly EM&A Report
i.
Executive
summary (1-2 pages);
· breaches of Action and Limit levels;
· complaint log;
· notifications of any summons and successful prosecutions;
· reporting changes; and
· future key issues.
ii.
Basic
project information:
· project organization including key personnel contact names and telephone numbers;
· programme;
· management structure;
· works undertaken during the month; and
· any updates as needed to the scope of works and construction methodologies.
iii.
Environmental
status
· advice on the status of statutory environmental compliance such as the status of compliance with the environmental permit (EP) conditions under the EIA Ordinance, submission status under the EP and implementation status of mitigation measures;
· works undertaken during the month with illustrations (such as location of works, daily excavation rate, etc.); and
· drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.
iv.
Implementation
status
· advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA Report.
v.
Monitoring
result (in both hard and diskette copies) together with the following information:
· monitoring methodology;
· name of laboratory and types of equipment used and calibration details;
· monitoring parameters;
· monitoring locations;
· monitoring date, time, frequency, and duration;
· weather conditions during the period;
· any other factors which might affect the monitoring results; and
· QA / QC results and detection limits.
vi.
Reporting
on non-compliance, complaints, and notifications of summons and successful
prosecutions:
· record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
· record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
vii.
Others
· an account of the future key issues as reviewed from the works programme and work method statements;
· advice on the solid and liquid waste management status;
· record of any project changes from the originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc.); and
· comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for examples, any improvement in the EM&A programme) and conclusions.
viii.
Appendices
· Action and Limit levels;
· graphical plots of trends of the monitoring parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:
a) major activities being carried out on site
during the period;
b) weather conditions during the period; and
c) any other factors that might affect the
monitoring results.
· monitoring schedule for the present and next reporting period;
· cumulative statistics on complaints, notifications of summons and successful prosecutions; and
· outstanding issues and deficiencies.
General
Final EM&A Review Report for Construction Stage
i.
Executive
summary (1-2 pages):
ii.
Drawings
showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations;
iii.
Basic
project information including a synopsis of the project organization, contacts
of key management, and a synopsis of work undertaken during the course of the
project or past twelve months;
iv.
A brief
summary of EM&A requirements including:
· environmental mitigation measures for construction stage, as recommended in the project EIA Report;
· environmental impact hypotheses tested;
· environmental quality performance limits (Action and Limit levels);
· all monitoring parameters;
· Event and Action Plans;
v.
A summary
of the implementation status of environmental protection and pollution
control/mitigation measures for construction stage, as recommended in the
project EIA Report and summarised in the updated implementation schedule;
vi.
Graphical
plots and the statistical analysis of the trends of monitoring parameters over
the course of the project, including:
· the major activities being carried out on site during the period;
· weather conditions during the period; and
· any other factors which might affect the monitoring results;
vii.
A summary
of non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
viii.
A review
of the reasons for and the implications of non-compliance including review of
pollution sources and working procedures as appropriate;
ix.
A
description of the actions taken in the event of non-compliance;
x.
A summary
record of all complaints received (written or verbal) for each media, liaison
and consultation undertaken, actions and follow-up actions taken and results;
xi.
A review
of the validity of EIA predictions for construction stage and identification of
shortcomings in EIA recommendations;
xii.
Comments
(for example, a review of the effectiveness and efficiency of the mitigation
measures and of the performance of the environmental management system, that
is, of the overall EM&A programme for construction stage); and
xiii.
Recommendations
and conclusions (for example, a review of success of the overall EM&A
programme for construction stage to cost-effectively identify deterioration and
to initiate prompt effective mitigatory action when necessary).
Final EM&A Review Report for Construction Stage
i.
Executive
summary (1-2 pages):
ii.
Drawings
showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations;
iii.
Basic
project information including a synopsis of the project organization, contacts
of key management, and a synopsis of work undertaken during the course of the
project or past twelve months;
iv.
A brief
summary of EM&A requirements including:
· environmental mitigation measures for construction stage, as recommended in the project EIA Report;
· environmental impact hypotheses tested;
· environmental quality performance limits (Action and Limit levels);
· all monitoring parameters;
· Event and Action Plans;
v.
A summary
of the implementation status of environmental protection and pollution
control/mitigation measures for operation stage, as recommended in the project
EIA Report and summarised in the updated implementation schedule;
vi.
Graphical
plots and the statistical analysis of the trends of monitoring parameters over
the course of the project, including:
· the major activities being carried out on site during the period;
· weather conditions during the period; and
· any other factors which might affect the monitoring results;
vii.
A summary
of non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
viii.
A review
of the reasons for and the implications of non-compliance including review of
pollution sources and working procedures as appropriate;
ix.
A
description of the actions taken in the event of non-compliance;
x.
A summary
record of all complaints received (written or verbal) for each media, liaison
and consultation undertaken, actions and follow-up actions taken and results;
xi.
A review
of the validity of EIA predictions for operation stage and identification of
shortcomings in EIA recommendations;
xii.
Comments
(for example, a review of the effectiveness and efficiency of the mitigation
measures and of the performance of the environmental management system, that
is, of the overall EM&A programme for operation stage); and
xiii.
Recommendations
and conclusions (for example, a review of success of the overall EM&A
programme for operational stage to cost-effectively identify deterioration and
to initiate prompt effective mitigatory action when necessary).
END OF TEXT