7.             Land contamination

7.1         Introduction

This Section identifies and assesses the potential land contamination impacts due to historical and current land uses within the Project site.  The assessment was undertaken in accordance with the criteria set out in Annex 19 of the EIAO-TM.

As part of the land contamination assessment, a Contamination Assessment Plan (CAP) has been prepared to identify the presence of potential land contamination areas and investigate the associated land contamination impacts within the Project site due to past and present operations, and subsequently devise a sampling and testing plan.  The CAP was endorsed by EPD on 13 July 2021 and is provided in Appendix 7A.

7.2         Statutory Requirements and Evaluation Criteria

 The following EPD’s guiding documents are referenced for this land contamination assessment:

§  Annex 19 of the Technical Memorandum on Environmental Impact Assessment Process (Annex 19 of EIAO-TM);

§  Guidance Note for Contaminated Land Assessment and Remediation (the RBRGs Guidance Note);

§  Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (the RBRGs Guidance Manual); and

§  Practice Guide for Investigation and Remediation of Contaminated Land (the Practice Guide).

The following legislation, documents and guidelines may cover or have some bearing upon the assessment of contamination and the handling, treatment and disposal of contaminated materials for this Project:

§  Dangerous Goods Ordinance (Cap 295);

§  Water Pollution Control Ordinance (WPCO) (Cap 358);

§  Waste Disposal Ordinance (WDO) (Cap 354);

§  Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C); and

§  Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

7.3         Description of the Project

The existing GT2, GT3, GT4, GT57 and GT6 and its auxiliaries, including the transformers, generator coolers and aboveground lube oil tanks, will be demolished for the installation of new GT8, GT9, GT10 and GT11. The existing foundation piles and concrete structure will be reused to support the new units, therefore no corresponding excavation works will be required for the installation of new units.  As part of the Project, the lube oil tank adjacent to GT5, the existing BSGT at the northwest corner of the GT Compound and the miscellaneous storage shed immediate south of the BSGT will be demolished.  A new BSGT will be installed at the same location as the existing BSGT.

Upon retirement of GT57, the existing GTAB will be converted to a new 132kV Switching Station.  Existing equipment inside the GTAB (i.e. the main oil tank, chemical dosing pit, miscellaneous gas tanks, cooling water pumps, generator, generator coolers and lube oil coolers, etc) will be removed.  As part of the conversion to a new 132kV Switching Station, the existing Turbo Block structure inside the GTAB will be demolished for reconstruction works which will involve minor excavation down to 2.6m below ground level (bgl).  The construction of new 132kV cable trenches for the new units will also require minor excavation down to 1.8m bgl.  In addition, a New Staircase and Lift will be constructed at the immediate east of existing GTAB which is currently a Circulating Water Pipe Room to be demolished under the Project.  The construction of the New Staircase and Lift will require excavation down to 5m bgl and new piles will be installed to support the said New Staircase and Lift.  The existing stacks (80 m tall) serving the existing OCGTs and CCGT will be retained for the new units.  Other existing building structures and equipment, including the Gas Turbine 132kV Switching Station and Gas Turbine Equipment Building, will be retained.

In general, the demolition of abovementioned structures and installation of new OCGTs and BSGT will not involve earthworks, except minor excavation (down to about 1.8m bgl) required for the new cable trenches for the new units.  The work areas requiring structure removal/demolition and minor excavation are highlighted in Figure 7.1.

7.4         Assessment Methodology

The assessment of potential land contamination impact within the Project site was conducted by undertaking:

§  A desktop study to review the hydrogeology of the Site from previous SI conducted within/ at vicinity of the Project site;

§  A desktop study to review the current and historical land use information from Lands Department (LandsD) and publicly available information;

§  A site walkover to identify the current land uses;

§  A proposed SI programme, including soil and groundwater sampling and testing at proposed sampling locations; and

§  Review of potential contamination sources and possible remediation methods.

7.5         Historical and Current Land Uses

7.5.1    Historical Land Uses

A review of past land uses of the Concerned Areas were conducted by reviewing the aerial photographs in the years of 1978, 1985, 1991, 1995, 1999, 2002 and 2019.  The aerial photographs were obtained from the Surveys and Mapping Office of the Lands Department.   The historical land uses of the Project Site are presented in Table 7.1.

Table 7.1   Summary of Historical Land Uses of Project Site

Date Began/

Period

Description of Site History

1970s to 1980s

The land where the Project site is situated was previously the coastline of Lamma Island.

1985

Reclamation for LPS was completed between late 1970s and early 1980s. The Project site was vacant.

1991

Construction of six (6) OCGTs, i.e. GT2 to GT7, was completed and its operation commissioned in 1989.

2002 - present

Two (2) of the OCGTs, i.e. GT5 and GT7, were later converted into a CCGT, i.e. GT57, in 2002.  Reportedly, no historical spillage and leakage incidents occurred during the conversion works in 2002.  GTAB was constructed at the eastern boundary of the Project site in early 2000s with the purpose of housing the steam turbine and the auxiliaries. The operation of GT compound remained unchanged since 2002 until present.

7.5.2    Current Land Uses

Site walkover and site management interview were conducted on 5 January 2021 to observe the Project site conditions and identify signs of potential contamination.  Site observations and findings were summarised in Table 7.2.

Table 7.2   Summary of Current Land Uses of Project Site

Site

Description of Site Walkovers and Interviews Findings

GT Compound

General

The outdoor portions of whole Project site, including vehicle access roads and outdoor area, were concrete paved and in good condition.  No signs of oil stains or chemical stains were noted along the access roads as well as the proposed new cable trenches during the site walkover.

Reportedly by site management, no historical fuel/ chemical spillage were occurred in the Project site.

 

 

Six (6) GTs and its auxiliaries

 

Each GT was mounted on foundation pile and concrete structure with support from external steel reinforcement.  Each GT contained one (1) lube oil tank installed at about 3m aboveground.  No underground storage tank (UST) was installed.

 

Each GT’s auxiliaries, including transformer and generator cooler, were installed side by side to the GT.  Each transformer was constructed within a concrete containment bund filled with pebbles inside an isolated area.  No signs of oil stains were observed.  Reportedly, no historical leakage or spillage incidents were recorded.  Each generator cooler was supported by metal structure and mounted on concrete footings.  The operation of generator coolers did not require use of fuel and chemicals.

 

During the site walkover, no significant signs of oil stain and leakage or spillage marks were observed on the floor of each GT and its auxiliaries.  No signs of cracks were noted on the floor.  Lube oil pipes and fuel pipes connected to the GTs were observed in good conditions with no signs of seepage or corrosion. 

 

Six GT transformers were observed to be well maintained.  No significant signs of stains or odour were noted during the site walkover. Reportedly by the site management, the composition of transformer oil used was free of PCBs.

 

Reportedly by site management, no historical fuel/ chemical spillage or leakage were occurred at the six (6) GTs and its auxiliaries.

 

Lube Oil Tank area

 

A lube oil tank of about 30,000L capacity adjacent to GT5 was installed above two (2) concrete footings and placed within a concrete bund.  During the site walkover, minor black colour deposits (1m2) were noted at the bottom of the lube oil tank footings and under several pipe joints. The black deposits were in powder / granular form with no signs petroleum odour or colour.  Reportedly by the site management, no lube oil leakage incident was recorded in its operation history.  As a result, the black deposits were likely caused by the erosion of screws / steel bars in the concrete footings of the lube oil tank.

 

BSGT

 

The BSGT comprised one (1) diesel generator and three (3) air compressor units.  No onsite diesel tank was equipped with the BSGT.  Reportedly, diesel was supplied from an offsite source located 300m north of the Project site to the BSGT.

 

Minor fuel seepage from the diesel supply pipes was observed to be absorbed by pipe wrapping materials. No signs of oil leaks on ground were noted during the site walkover.  In addition, minor oil stain was observed in one of the air compressor units. The concrete slabs supporting the BSGT and air compressor units were intact.

 

GTAB

 

One (1) Main Oil Tank of about 30,000L was installed on the ground floor of this building in 2001 and was put into operation in 2003.  The Main Oil Tank was constructed within a concrete bund.  No signs of oil leakage or spillage stains were observed within the bunded area.  Oil pipes were also observed in good condition without signs of seepage or corrosion.  The main oil tank and its oil pipes have been maintained in good condition as they are located in an indoor environment and protected from extreme weather.  No signs of corrosion or cracks were noted during the site walkover.  Reportedly by site management, no historical fuel/ chemical spillage or leakage incidents were occurred at the Main Oil Tank.

 

One (1) Chemical Dosing Pit (Hydrazine Hydrate Tank), which is also a licensed Cat.4 DG storage, was also installed on the ground floor of this building and it is equipped with mechanical pump for dosing operation.  No signs of chemical leakage or spillage were observed during the site walkover. Reportedly by site management, no historical chemical spillage or leakage incidents were occurred.  However, the potential of mechanical pump oil leakage from the mechanical pump could not be ruled out.

 

Immediate east to the GTAB is the Circulating Water Pipe Room.  The emerging sections of two (2) circulating water pipes connected to the Condenser inside the GTAB were enclosed in this room.  No signs of ground contamination was observed.  No current and historical land contamination activities were noted. 

 

The rest of the ground floor was occupied by cooling water pumps and miscellaneous gas tanks.  No chemical storage or signs of contaminations were observed during the site walkover.

 

The generator, generator coolers, lube oil coolers were installed on 1/F and above floors.  No potential land contamination impacts were observed.

 

 

Miscellaneous Storage Shed

Approximately 20 empty chemical containers without secondary containers were placed in the vicinity of the Miscellaneous Storage Shed.  Several black stains of about 1m2 were observed on the ground of the shed’s entrance.

 

 

7.6         Review of Land Contamination Potential within the Project Site

The Project site are divided into different areas based on their types of structures and equipment installed to evaluate the likelihood and presence of potential land contamination hotspots, and the need of SI to assess potential land contamination impacts.

§  General

§  Six (6) GTs and its auxiliaries

§  Lube Oil Tank area

§  BSGT

§  Main Oil Tank area in GTAB

§  Chemical Dosing Pit (Hydrazine Hydrate Tank) in GTAB

§  Circulating Water Pipe Room

§  Miscellaneous Storage Shed

7.6.1    General

The demolition of abovementioned structures and installation of new OCGTs will not involve any forms of earthworks, such as ground breaking, trenching and excavation, except minor excavation required for associated new cable trenches for the new OCGTs (down to about 1.8m bgl).  Minor excavation will also be required for the construction of the New Staircase and Lift (down to about 5m bgl) and the reconstruction works within GTAB (down to about 2.6m bgl).

Based on the site walkover observation, the outdoor portions of whole Project site, including vehicle access roads and outdoor area, was concrete paved and in good condition.  No signs of oil stains or chemical stains were noted along the access roads as well as the alignment of proposed new cable trenches during the site walkover.

Although minor excavation works will be required for the construction of new 132kV cable trenches, the concrete paved surface of Project site was observed to be in good condition.  No historical land contaminations were identified.  Therefore, the land contamination potential of the outdoor portions of Project Site is unlikely in general and no sampling locations are required.

7.6.2    Six (6) GTs and its auxiliaries

No obvious signs of potential land contamination were noted at the six (6) GTs and its auxiliaries during the site walkover and review of its operation history.

Each GT was mounted on a concrete made foundation pile which provided a barrier to prevent any potential fuel leakage from entering the soil.  Each transformer was constructed within a concrete containment bund filled with pebbles inside an isolated area, which prevents contamination from entering the ground beneath of the transformer.  No signs of oil stains were observed.  The composition of transformer oil used was reportedly free of PCBs.  The generator coolers for GT did not require use of fuel and chemicals.  Based on the site walkover and interview with site management, no historical fuel / or chemical spillage or leakage were occurred at the six (6) GTs and its auxiliaries.

Review of historical information indicated the operation in this area remained unchanged since its operation started in 1989, except the conversion works for OCGT (GT5 and GT7) to CCGT (GT57) in 2002. Reportedly, no historical spillage and leakage incidents occurred during the conversion works in 2002.

In addition, no excavation works will be required during demolition of GT structures and installation of new OCGTs.  Therefore, the overall land contamination potential at the six (6) GTs and its auxiliaries is considered unlikely.  No sampling locations are required at the six (6) GTs and its auxiliaries.

7.6.3    Lube Oil Tank area

Based on the site observation and operation history of the lube oil tank, the black deposits were likely caused by erosion of screws / steel bars in the concrete footings of the lube oil tank and at the several pipe joints.  The lube oil tank structure and its piping are also exposed to ambient environment, thus it could be damaged under extreme weather conditions over the years.  Although no significant signs of potential land contamination were noted in the lube oil tank area, the potential land contamination risks as a result of long term usage and extreme weather impacts could not be ruled out.  Considering the lube oil tank was installed within a concrete bund to contain any potential oil leakage or spillage, the extent of potential contamination is likely localised.

Therefore, one (1) sampling location is proposed at the centre of Lube Oil Tank area based on hotspot sampling approach to represent the overall land condition. 

7.6.4    BSGT

Minor fuel seepage was noted from the diesel supply pipes.  Minor oil stains was also observed in one of the air compressor units.  The diesel supply pipes are also exposed to ambient environment, thus it could be damaged under extreme weather conditions over the years.  Due to its long operation history and its direct exposure without physical protection, potential land contamination caused by the fuel leakage could not be ruled out.  Since no significant oil stains were noted on the ground of the BSGT, the extent of potential contamination is likely localised.

Therefore, two (2) sampling locations are proposed at BSGT, i.e. the bottom of diesel generator and the bottom of an air compressor unit, based on the hotspot sampling approach to investigate the potential contamination.

7.6.5    Main Oil Tank area in GTAB

No signs of potential land contamination, including oil stain or colour stain, were observed at the main oil tank area during the site walkover. According to the information provided by HK Electric, the Main Oil Tank was fabricated in 2001 and put into operation in 2003.  The Main Oil Tank and its oil pipes have been maintained in good condition as they are located in an indoor environment.  In addition, the concrete bund that contains the Main Oil Tank and its oil pipes prevents contamination from entering the ground beneath.  No signs of corrosion or damages were noted at the tank structure and its oil pipes during the site walkover. 

Therefore, the good condition of tank structure and oil pipes and the concrete bund indicated that there’s a remote chance of historical oil leakage or spillage at the Main Oil Tank area.  In addition, no excavation works will be required during demolition of main oil tank. 

Hence, the land contamination potential is considered unlikely.  No sampling locations are required at the Main Oil Tank Area.

7.6.6    Chemical Dosing Pit (Hydrazine Hydrate Tank) in GTAB

Minor excavation down to 1.8m bgl will be required for the construction of new cable trenches for the new OCGTs under the existing chemical dosing pit (hydrazine hydrate tank) at GTAB after demolition. 

Based on site walkover observation and interview with site management, the Chemical Dosing Pit (Hydrazine Hydrate Tank) appeared to be well maintained. No signs of chemical leakage or spillage were observed.  Moreover, the concrete containment bund surrounding the Chemical Dosing Pit (Hydrazine Hydrate Tank) prevents contamination from entering the ground beneath.  Reportedly by site management, no historical chemical spillage or leakage incidents were occurred.  The risk of hydrazine hydrate being released into the soil is very low.  However, potential mechanical pump oil leakage as a result of long term usage of the mechanical pump of the dosing pit could not be ruled out.  Due to the small footprint of mechanical pump, the extent of potential contamination is likely localised.

Therefore, one (1) sampling location is proposed at the bottom of the mechanical pump of Chemical Dosing Pit (Hydrazine Hydrate Tank) based on hotspot sampling approach to investigate the potential land contamination.  Due to shallow excavation depth required for the new cable trenches, trial pit is recommended as site investigation (SI) method.

7.6.7    Other Facilities in GTAB

No signs of potential land contamination, including oil stain or colour stain, and no chemical storage were observed at the Turbo Block structure, miscellaneous gas tanks and cooling water pumps on G/F during the site walkover.  No potential land contamination impacts were observed at the generator, generator coolers and lube oil coolers that were installed on 1/F and above floors.

Although minor excavation works down to 2.6m bgl will be undertaken for the demolition and reconstruction works at the Turbo Block structure, the chances of encountering contaminated materials under the Turbo Block structure is very low.  Hence, no sampling location is required at the other facilities in GTAB.

7.6.8    Circulating Water Pipe Room

The Circulating Water Pipe Room only served to enclose the emerging section of two (2) circulating water pipes connected to the Condenser inside the GTAB.  No current and historical land contamination activities were noted.  Although deep excavation works down to 5m bgl will be undertaken for the construction of New Staircase and Lift, the chances of encountering contaminated materials under the Circulating Water Pipe Room during the construction phase is very low.  Therefore, no sampling location is proposed at the Circulating Water Pipe Room. 

7.6.9    Miscellaneous Storage Shed

Based on the observation during the site walkover, approximately 20 empty chemical containers without secondary containers were placed in the vicinity of the Miscellaneous Storage Shed.  The area of Miscellaneous Storage Shed is about 40 m2.  In addition, two black stains of about 1m2 in total were observed on the ground of the shed’s entrance.  The potential land contamination from fuel or chemical leakage is likely. Considering the small footprint of black stains observed onsite, the extent of potential contamination is likely localised.

Therefore, one (1) sampling location is proposed at the shed entrance based on hotspot sampling approach to investigate the potential contamination at the black stains.

7.7         Site Investigation Programme

A SI plan was proposed in the CAP provided in Appendix 7A to assess the potential contamination in the hotspots locations of Project site. 

Details of the proposed SI plan are summarised in Table 7.3.  The proposed sampling locations are presented in Figure 7.2.  Since the Project site area is still in use at the time of preparing this EIA, the proposed sampling locations are not accessible at the moment.  SI and sampling shall be carried out when the proposed sampling locations are available after the demolition stage.

During the demolition stage, a Land Contamination Specialist shall oversee the removal / demolition process and record any new visual signs of potential contamination such as oil leakage or oil stains. The Land Contamination Specialist shall also review the need of additional sampling to capture potential contamination observed during the demolition stage.

 


Table 7.3     Summary of SI Plan

Potentially Contaminated Area

Sampling Location ID

Proposed Coordinates (a)

RBRGs Land Use Scenario

Proposed Testing Parameters

Soil Sampling

Groundwater

Depths (m bgl)

Sampling Depths (m bgl)

Lube Oil Tank area

BH1

E: 828818.021

N: 808678.132

Industrial

Metals (b),

PCRs (c),

VOCs (d),

SVOCs (e)

Manual excavation of Inspection Pit (0-1.5m bgl):

n To collect disturbed sample at 0.5m bgl

 

Rotary Drilling of boreholes

(1.5-7.0m bgl):

n Continuous drilling and retrieving of soil materials for visual inspection at every 1m from the bottom of inspection pit to a maximum depth of 7 m bgl or 2m below static groundwater level, whichever shallower.

To collect undisturbed soil samples at 3.0 m and 6.0 m bgl

 

Collect one (1) groundwater sample at static groundwater level, if groundwater is encountered before end of borehole.

BSGT

 

BH2

E:828699.830

N:808748.382

Industrial

Metals (b)

PCRs (c),

VOCs (d) ,

SVOCs (e)

BH3

E:828702.277

N:808740.643

Industrial

Metals (b)

PCRs (c),

VOCs (d) ,

SVOCs (e)

Miscellaneous Storage Shed Entrance

BH4

E:828699.301

N:808729.200

Industrial

Metals (b)

PCRs (c),

VOCs (d),

SVOCs (e)

Mechanical Pump of Chemical Dosing Pit (Hydrazine Hydrate Tank)

TP1

E: 828922.015

N: 808675.576

Industrial

Metals (b)

PCRs (c),

VOCs (d),

SVOCs (e)

Manual excavation of trial pit (0-2.0m bgl):

n To collect disturbed sample at 0.5m, 1.0m and 2.0m bgl

 

No groundwater sampling is required as the excavation depth of trial pit is shallower than the anticipated groundwater table at 3.85m bgl.

Notes:

m bgl = meter below ground level.

(a)     By experience, the exact sampling locations will be determined by on-site Land Contamination Specialist and subject to adjustment due to site-specific conditions/ constraints (e.g. presence of underground utilities, foundations, insufficient headroom, spaces occupied by vehicles, etc) during the actual SI.

(b)     Metals: For soil: Antimony, Arsenic, Barium, Cadmium, Cobalt, Copper, Lead, Manganese, Molybdenum, Nickel, Tin, Zinc, Mercury, Chromium (III) and Chromium (VI); For groundwater: Mercury

(c)      PCRs: C6 – C8, C9 – C16 and C17 – C35

(d)     VOCs: For soil and groundwater: Acetone, Benzene, Bromodichloromethane, 2-Butanone, Chloroform, Ethylbenzene, Methyl tert-Butyl Ether, Methylene Chloride, Styrene, Tetrachloroethene, Toluene, Trichloroethene and Xylenes (Total)

(e)     SVOCs: For soil: Acenaphthylene, Acenaphthene, Anthracene, Benzo(a)anthracene, Benzo(a)pyrene, Benzo(b)fluoranthene, Benzo(k)fluoranthene, Benzo(g,h,i)perylene, Bis-(2- ethylhexyl)phthalate, Chrysene, Dibenz(a,h)anthracene, Fluoranthene, Fluorene, Hexachlorobenzene, Indeno(1,2,3cd)pyrene, Naphthalene, Phenanthrene, Phenol and Pyrene.
For groundwater: Acenaphthylene, Acenaphthene, Anthracene, Benzo(b)fluoranthene, Chrysene, Fluoranthene, Fluorene, Hexachlorobenzene, Naphthalene, Phenanthrene and Pyrene.


7.8           Impact Evaluation

Based on the site appraisal findings, only four (4) areas, i.e. Lube Oil Tank area, BSGT, Miscellaneous Storage Shed Entrance, and Mechanical Pump of Chemical Dosing Pit (Hydrazine Hydrate Tank) were identified as potential land contamination hotspots.  The land contamination issues are considered surmountable due to the following reasons as discussed below.

(1)   Localised contamination in the identified hotspots:

Based on the site appraisal, these potential contamination hotspots have small footprint in general. These areas are typically affected by potential contaminating activities such as small scale of fuel or chemical storage.  Therefore, it is anticipated that the extent of land contamination, if any, would be localised.

(2)   Chemical of Concerns (COCs) identified are treatable with existing remediation techniques:

Based on the site appraisal, the identified COCs include metals, VOCs, SVOCs and PCRs.  Remediation methods that have demonstrated to effectively treat the aforementioned soil and groundwater contaminants include biological treatment and physical / chemical treatment.

In addition, the soil contaminated with the abovementioned COCs had successfully been remediated in Hong Kong using proven remediation techniques.  Notable local remediation projects include the following:

§  Decommissioning of Kai Tak Airport North Apron;

§  Decontamination works at the Cheoy Lee Shipyard;

§  Reclamation works at North Tsing Yi Shipyard site;

§  Decommissioning of Kwai Chung Incinerator; and

§  Isolated sites in the Deep Bay Link project.

Provided that the soil and groundwater contamination identified during the SI, if any, are properly treated using the appropriate remediation techniques in accordance with the approved Remediation Action Plan (RAP), adverse land contamination impacts associated with the Project is not expected. 

7.9         Mitigation Measures

As adverse land contamination impacts associated with the Project is not expected, no mitigation measures specific to the Project are recommended. 

However, a number of recommendations as discussed in the following sub-sections should be followed during the demolition and construction phases of the Project in order to minimise the risk of land contamination.

7.9.1    Handling and Disposal Arrangement of Removed Diesel / Petroleum Products and Spill Prevention during Demolition

Prior to commencement of demolition works in the Project site, the leftover diesel or other petroleum products in the equipment to be demolished shall be removed as much as possible. The removed diesel and other petroleum products are considered as chemical waste and are controlled under the Waste Disposal (Chemical Waste)(General) Regulation.  The demolition contractor who will generate the chemical waste or cause it to be produced should register with the EPD as a chemical waste producer.  Removed diesel and petroleum products shall be labelled and stored in accordance with the requirement stipulated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes issued by EPD.  The removed petrol and petroleum products are required to be collected by licensed chemical waste collector for disposal.  Trip tickets system shall be implemented during the collection and disposal of removed petrol and diesel.

7.9.2    Good Housekeeping Practices

During demolition and construction phases, the following good housekeeping practices shall be implemented to ensure that risk of ground contamination as a result of oil spills or leaks is kept to a practical minimum:

§  Regular visual inspections to detect any early signs of fuel leakage prior to demolition;

§  Provision of impermeable lining or absorbent materials to contain leaks;

§  Minimise the chemical stock within the Project site, only store the amount of chemicals needed;

§  Designated chemical/ chemical waste storage shall be established on concrete paved ground as far as practicable;

§  Provision of secondary containment for the temporary storage of removed diesel or petroleum products, demolished structures and pipes;

§  Provision of spill control materials and equipment;

§  Conduct regular maintenance and inspection on plants and equipment, particularly those involve the use of fuel, hydraulic oil or any sort of chemicals; and

§  Divert rainfall and surface run-off around construction areas.

7.10      Environmental Monitoring and Audit

To ensure the recommendations discussed in Section 7.9 are properly implemented, regular site inspections should be carried out during the demolition and construction phases of the Project.

7.11      Conclusion

Based on the site appraisal findings, Lube Oil Tank area, BSGT, Chemical Dosing Pit (Hydrazine Hydrate Tank) and Miscellaneous Storage Shed are considered as the potential land contamination hotspots within the Project site.  Five (5) sampling locations (BH 1 to BH4 and TP1) are proposed for SI to collect soil and groundwater samples for laboratory testing.

Since the Project site is still under active operation at the time of preparing this EIA, the proposed sampling locations are not accessible at the moment.  SI and sampling shall be carried out when the proposed sampling locations are available after the demolition stage.

During the demolition stage, a Land Contamination Specialist shall oversee the removal / demolition process and record any new visual signs of potential contamination such as oil leakage or oil stains. The Land Contamination Specialist shall also review the need of additional sampling to capture potential contamination observed during the demolition stage. 

Provided that the soil and groundwater contamination identified during the SI, if any, are properly treated using the appropriate remediation techniques in accordance with the approved Remediation Action Plan (RAP), adverse land contamination impacts associated with the Project is not expected. 

Upon completion of the remediation works (if necessary), a Remediation Report (RR) will be prepared and submitted to EPD for approval.    No construction works within the contaminated area should be carried out prior to the approval of the RR by EPD.