|
Island West Transfer Station
General Information
|
Location
|
:
|
Mount Davis, Kennedy Town (underground inside cavern)
|
|
Contractor
|
:
|
China Harbour Engineering Company LTD
|
| Contractor Facility Office Tel |
: |
2818 2896 |
|
Initial Capital Cost
|
:
|
$654 million
|
|
Throughput
|
:
|
about 1, 100 tonnes per day
|
|
Commissioning Date
|
:
|
May 1997
|
|
Opening Hours
|
:
|
07:30 to 23:30
|
|
Waste Delivered to
|
:
|
West New Territories Landfill
|
|
Major Plant / Equipment
|
:
|
Container Vessels, "Live Floor" System & Compactors, Yard Tractors, Landfill Tractors, Container Handling Units, Road Washing Vehicle, Containers
|
|
Other Facilities
|
:
|
Computerized Weighbridge System, Exhaust Ventilation System with Odour Removal Unit, Waste Water Treatment Plant, Vehicle Wash System
|
|