Problems & Solutions

Shatin Transfer Station

Image of Sha Tin Transfer Station

General Information

Location:Sha Tin, New Territories
Contractor:Grandblue Canvest - Pekko Joint Venture
Contractor Facility Office Tel:2649 0213
Initial Capital Cost:$200 million
Throughput:about 1,800 tonnes per day
Commissioning Date:October 1994
Opening Hours:07:30 to 23:30
Waste Delivered to:North East New Territories Landfill
Major Plant / Equipment:Compactors, Yard Tractors, Highway Tractors, Trailers, Containers, Trailer Tippers, Bucket Loader, Bobcat Loader, Road Washing Vehicle
Other Facilities:Computerized Weighbridge System, Exhaust Ventilation System with Odour Removal Units, Waste Water Treatment Plant, Vehicle Wash System

 

Back to topBack