CONTENTS
3.2 Relevant
Legislation, Standards and Guidelines
3.5 Identification
of Key Air Pollutants
3.7 Prediction
and Evaluation and Environmental Impacts
3.10 Monitoring
and Audit Requirement
TABLES
Table 3.1 Hong Kong Air
Quality Objectives
Table 3.3 Air Pollutants
Concentrations at the Project Site in 2020 Predicted from PATH-2016 Model
Table 3.4 Representative
Air Sensitive Receivers
Table 3.5 Key Concurrent
Projects for Construction Dust Assessments
Table 3.6 Individual Construction
Activities during Construction
Table 3.7 Emission Factor
for Dust Emitting Construction Activity
Table 3.8 Preliminary
Design of Ventilation System at the Portal
Table 3.9 Vehicular
Classes in EMFAC-HK Model
Table 3.10 Summary of
Cumulative Dust Emission Concentration (Unmitigated Scenario)
Table 3.11 Summary of Dust
Suppression Measures
Table 3.12 Summary of
Cumulative Dust Emission Concentration (Mitigated Scenario)
·
Air Pollution
Control Ordinance (APCO) (Cap 311);
·
Air Pollution
Control (Construction Dust) Regulation;
·
Air Pollution
Control (Non-road Mobile Machinery) (Emission) Regulation;
·
EIAO-TM Annex
4 and Annex 12; and
·
Technical
Circular (Works) No. 13/2020 of Development Bureau (DEVB TC(W) No. 13/2020)
Table 3.1 Hong Kong
Air Quality Objectives
Air
Pollutant |
Averaging Time |
Concentration (mgm-3)
(a) |
No. of Exceedances Allowed per Year |
Sulphur Dioxide (SO2) |
10 minutes |
500 |
3 |
|
24-hours |
125 |
3 |
Respirable Suspended Particulates
(RSP) (b) |
24-hours |
100 |
9 |
Annual |
50 |
- |
|
Fine Suspended Particulates (FSP) (c) |
24-hours |
75 |
9 |
Annual |
35 |
- |
|
Nitrogen Dioxide (NO2) |
1-hour |
200 |
18 |
|
Annual |
40 |
- |
Ozone (O3) |
8-hours |
160 |
9 |
Carbon Monoxide (CO) |
1-hour |
30,000 |
- |
|
8-hours |
10,000 |
- |
Lead |
Annual |
0.5 |
- |
Notes: (a) Measured at 298K and 101.325 kPa. (b) Suspended particles in air with a nominal aerodynamic diameter of
10 μm or less (c) Suspended particles in air with a nominal aerodynamic diameter of
2.5 μm or less |
Table
3.2 5-year
Averaged Annual Background Concentration of Air Pollutants recorded at Sham
Shui Po Station by EPD for the Period of 2015-2019
Air
Pollutant |
Averaging Time |
AQO (a) |
Data Description |
UNIT |
Year (b) (c) |
5-year mean |
||||
2015 |
2016 |
2017 |
2018 |
2019 |
||||||
Fine Suspended Particulates (FSP) (PM 2.5) |
24-hour |
75 (9) |
10th Max. |
μg
m-3 |
58 |
48 |
46 |
41 |
36 |
46 |
Annual |
35 |
- |
μg
m-3 |
25 |
23 |
21 |
21 |
18 |
22 |
|
Respirable
Suspended Particulates (RSP) (PM10) |
24-hour |
100
(9) |
10th
Max. |
μg m-3 |
80 |
77 |
72 |
59 |
65 |
71 |
Annual |
50 |
- |
μg m-3 |
38 |
35 |
33 |
33 |
33 |
34 |
|
Sulphur
Dioxide (SO2) |
10-minute |
500
(3) |
4th
Max. |
μg m-3 |
186 |
126 |
76 |
98 |
41 |
105 |
24-hour |
125
(3) |
4th Max. |
μg m-3 |
28 |
26 |
25 |
21 |
14 |
23 |
|
Nitrogen
Dioxide (NO2) |
1-hour |
200
(18) |
19th
Max. |
μg m-3 |
215 |
161 |
194 |
152 |
176 |
180 |
Annual |
40 |
- |
μg m-3 |
63 |
58 |
54 |
49 |
48 |
54 |
|
Ozone
(O3) |
8-hour |
160
(9) |
10th
Max. |
μg m-3 |
143 |
106 |
130 |
147 |
164 |
138 |
Notes: (a) Values in ( ) indicate the number of exceedances
allowed per year
(b) Data
extracted from EPD Website (http://www.aqhi.gov.hk/en/download/air-quality-reportse469.html?showall=&start=1)
(c) Bolded values
represent exceedances of the AQOs.
Table 3.3 Air Pollutants
Concentrations at the Project Site in 2020 Predicted from PATH-2016 Model
Air
Pollutant |
Averaging Time |
AQO |
Data Description |
UNIT |
Predicted Background Concentration in
Year 2020 [1] |
|
(41, 36) |
(42, 36) |
|||||
FSP [2] |
24-hour |
75 (9) |
10th Max. |
μg
m-3 |
53 |
52 |
Annual |
35 |
- |
μg
m-3 |
22 |
22 |
|
RSP [3] |
24-hour |
100
(9) |
10th
Max. |
μg m-3 |
70 |
71 |
Annual |
50 |
- |
μg m-3 |
31 |
31 |
|
NO2 |
24-hour |
200 |
19th
Max |
μg m-3 |
115 |
112 |
Annual |
40 |
- |
μg m-3 |
19 |
17 |
Notes:
1)
Extracted
from PATH grids (41, 36) and (42, 36) in which the Project site is located.
2)
With
reference to EPD’s Guidelines on the Estimation of PM2.5 for Air Quality
Assessment in Hong Kong, the following conservative formulae are adopted to
calculate background FSP concentration from the RSP concentration extracted
from the PATH model:
·
Annual
(µg/m³): FSP = 0.71 × RSP
·
Daily (µg/m³): FSP = 0.75 × RSP
3)
With
reference to the EPD’s Guidelines on Choice of Models and Model Parameters,
PATH-2016’s output of RSP concentration is adjusted as follows:
·
10th
highest daily RSP concentration: add 26.5 µg/m³
·
Annual
RSP concentration: add 15.6 µg/m³
Table 3.4 Representative
Air Sensitive Receivers
Description |
Types
of ASRs |
No.
of Floors |
Base
Elevation (mPD) |
Ass.
Height (mAG) |
Minimum
Distance (m) |
||||
Access
Tunnel Portal |
Water
Main |
Access
Tunnel & Cavern |
Works
Boundary |
||||||
ASR
1 |
Lion Rock Park |
Recreational |
- |
93.6 |
1.5 |
54 |
107 |
68 |
54 |
ASR
2 |
Tennis Court near Tin Ma Court |
Recreational |
- |
60.3 |
1.5 |
25 |
14 |
132 |
14 |
ASR
3 |
Block B, Peninsula Heights |
Residential |
14 |
67.0 |
1.5,
3.0, 6.1, 9.1, 12.2, 15.2, 18.2, 21.3. 24.3. 27.4, 30.4, 33.4, 36.5, 39.5. 42.6,
45.6 |
38 |
72 |
220 |
38 |
ASR
4 |
Block 1, Meridian Hill |
Residential |
9 |
62.5 |
1.5,
2.8, 5.5, 8.3, 11.1, 13.9, 16.6, 19.4, 22.2, 24.9, 27.7 |
38 |
25 |
210 |
25 |
ASR
5 |
Chun Sing House, Tin Ma Court |
Residential |
37 |
54.5 |
1.5,
2.7, 5.4, 8.1, 10.8, 13.5. 16.2, 18.9, 21.6, 24.3. 27.0, 29.7, 32.4, 35.1,
37.8, 40.5, 43.2, 45.9, 48.6, 51.3, 54.0, 56.7, 59.4, 62.1, 64.8, 67.5, 70.2,
72.9, 75.6, 78.3, 81.0, 83.7, 86.4, 89.1, 91.8, 94.5, 97.2, 99.9, 102.6 |
86 |
40 |
155 |
40 |
ASR
6 |
Chun Wai House, Tin Ma Court |
Residential |
37 |
54.5 |
1.5,
2.7, 5.3, 8.0, 10.6, 13.3, 15.9, 18.6, 21.2, 23.9, 26.5, 29.2, 31.8, 34.5, 37.1,
39.8, 42.4, 45.1, 47.7, 50.4, 53.1, 55.7, 58.4, 61.0, 63.7, 66.3, 69.0, 71.6,
74.3, 76.9, 79.6, 82.2, 84.9, 87.5, 90.2, 92.8, 95.5, 98.1, 100.8 |
83 |
27 |
146 |
27 |
ASR
7 |
Grace Methodist Church
Kindergarten |
Educational |
1 |
60.0
[*] |
1.5
[*] |
98 |
10 |
131 |
10 |
ASR
8 |
Wang King House, Tin Wang Court |
Residential |
21 |
54.1 |
1.5,
2.7, 5.4, 8.2, 10.9, 13.6, 16.3, 19.0, 21.7, 24.5, 27.2, 29.9, 32.6, 35.3,
38.1, 40.8, 43.5, 46.2, 48.9, 51.6, 54.4, 57.1, 59.8 |
202 |
10 |
235 |
10 |
ASR
9 |
Block 6, Tsui Chuk Garden |
Residential |
22 |
92.3 |
1.5,
2.8, 5.5, 8.3, 11.0, 13.8, 16.6, 19.3, 22.1,24.8, 27.6, 30.4, 33.1, 35.9, 38.7,
41.4, 44.2, 46.9, 49.7, 52.5, 55.2, 58.0, 60.7, 63.5 |
141 |
74 |
128 |
74 |
ASR
10 |
Ma Chai Hang Recreation Ground |
Recreational |
- |
45.7 |
1.5 |
358 |
104 |
381 |
104 |
ASR
11 |
Baptist Rainbow Primary School |
Educational |
7 |
45.6 |
1.5,
2.9, 5.7, 8.6, 11.4, 14.3, 17.1, 20.0, 24 |
447 |
32 |
453 |
32 |
ASR
12 |
Pang Ching Court |
Residential |
34 |
69.9 |
N/A |
532 |
25 |
417 |
25 |
ASR
13 |
Chung Yuen House, Chuk Yuen
North Estate |
Residential |
34 |
63.9 |
N/A |
657 |
14 |
473 |
14 |
ASR
14 |
Wah Yuen House, Chuk Yuen South
Estate |
Residential |
34 |
50.9 |
N/A |
632 |
13 |
529 |
13 |
ASR
15 |
Mui Yuen House, Chuk Yuen North
Estate |
Residential |
34 |
55.4 |
N/A |
1021 |
23 |
778 |
23 |
ASR
16 |
Our Lady of Maryknoll Hospital |
Care
Centre |
7 |
46.0 |
N/A |
1115 |
1 |
888 |
1 |
ASR
17 |
Our Lady's College |
Educational |
7 |
39.0 |
N/A |
1124 |
3 |
943 |
3 |
ASR
18 |
Evangel Children's Home |
Care
Centre |
6 |
58.2 |
N/A |
1137 |
6 |
811 |
6 |
ASR
19 |
Wing Shing House |
Residential |
6 |
43.8 |
N/A |
1292 |
5 |
982 |
5 |
ASR
20 |
Ying Fuk Court |
Residential |
37 |
55.5 |
N/A |
1043 |
54 |
698 |
54 |
ASR
21 |
Diamond Hill Kwong Yum Home for
the Aged |
Care
Centre |
7 |
62.5 |
N/A |
1144 |
12 |
810 |
12 |
ASR
22 |
St. Bonaventure College and
High School |
Educational |
8 |
46.7 |
N/A |
1202 |
3 |
942 |
3 |
ASR
23 |
Wu York Yu Health Centre |
Care
Centre |
4 |
55.0 |
N/A |
1276 |
6 |
928 |
6 |
ASR
24 |
Twghs Wong Tai Sin Hospital |
Hospital |
5 |
66.5 |
N/A |
1172 |
31 |
783 |
31 |
ASR
25 |
Ho Lap Primary School |
Educational |
7 |
60.9 |
N/A |
1349 |
23 |
962 |
23 |
ASR
26 |
Lok Shing House, Tsz Lok Estate |
Residential |
40 |
67.8 |
N/A |
1363 |
22 |
957 |
22 |
ASR
27 |
Fat Chong Temple |
Temple |
4 |
129.5 |
N/A |
1044 |
62 |
550 |
62 |
ASR
28 |
Wo Tin House |
Residential |
41 |
126.5 |
N/A |
1130 |
5 |
651 |
5 |
ASR
29 |
CCC Kei Tsz Primary School |
Educational |
9 |
131.0 |
N/A |
1297 |
24 |
772 |
24 |
ASR
P1 |
Proposed Departmental Quarters
for Customs & Excise Department |
Residential |
27 |
62.0 |
N/A |
1320 |
7 |
924 |
7 |
[*] The kindergarten is a
one floor building with the bottom being a car park. Base elevation has been
taken at the elevation of the kindergarten classrooms. The assessment height of
the car park and roof are not assessed.
·
Transportation Routes of Materials
Ø
The proposed disposal outlets of inert C&D materials and non-inert
C&D materials will be disposed to the public fill reception facility at TKO
Area 137 Fill Bank and SENT landfill by trucks respectively via Lung Cheung
Road, Kwun Tong Road, Tseung Kwan O Road and Wan Po Road. Chemical waste will
be collected by licensed collectors and dispose to Chemical Waste Treatment
Centre (CWTC) at Tsing Yi or licenced facility via Lung Cheung Road, Ching
Cheung Road, Tsing Kwai Highway, Kwai Tsing Road, Tsing Yi Road and/or waste
transfer/disposal facilities. The general refuse generated will be collected by
a waste collector and disposed of at waste transfer/disposal facilities and
then to designated landfill.
Ø
The relocated DHSRs are mainly for the storage and pumping of fresh
water and flushing water. The relocated DHSRs and the other ancillary
facilities will be unmanned during operation, only small amount of general
waste would be generated during regular inspection and maintenance. The general
refuse generated will be collected by a waste collector and disposed of at
waste transfer/disposal facilities and then to designated landfill. In
addition, small amount of chemical waste will be generated which will be
collected by licensed collector for the disposal of at licensed treatment facilities.
·
Dust Control Measures
Ø
Vehicles would be required to pass through the wheel washing facilities
provided at site exit. No earth, mud, debris, dust and the like shall be
deposited on public roads. Watering will be provided once per hour and vehicles
leaving a site loaded with dusty materials should be covered by tarpaulin or
other impervious sheeting (please refers to Section 3.8 of EIA). With the
implementation of the dust control measures, dust generated from the
transportation activities would not cause significant emission. Regular site
inspections and audit is recommended to ensure the effectiveness of the
proposed mitigation measures. No dust and odour impact are anticipated during
the operation of the Project.
·
Construction Methods: The design of the Project has undergone a detailed
evaluation of different arrangements to arrive at the optimum planning,
engineering and environmental solutions which fit together in a coherent manner
(please refers to Section 2.6 of the EIA). The location of the cavern and the
alignment of the access tunnel have been carefully planned to avoid
encroachment into the Lion Rock Country Park (LRCP) and nearby sensitive receivers.
With further reduction of tunnel length and emergency exit tunnel near Shatin
Pass Road, the potential dust quality impact to Tsz Wan Shan portal area (of
emergency exit) and generation of construction & demolition material can be
greatly minimised. For the construction methods of tunnel and caverns, it is
proposed to adopt drill and break/drill and blast method for the tunnel/ cavern
excavation. Other construction method such as tunnel boring machine (TBM) has
also been considered but they are not recommended due to the site constraint
and project nature (please refers to Section 2.8 of the EIA).
·
Means of Transportation for Construction Materials: The construction materials will be transported by trucks to the
construction site. The inert and non-inert C&D materials generated from the
Project will be disposed to the public fill reception facility, recycling
companies and/or landfill by trucks. Chemical waste will be collected by
licensed collector and dispose to licenced facility and waste transfer/disposal
facilities to Chemical Waste Treatment Centre (CWTC) at Tsing Yi by truck.
Other means of transportation are considered not applicable due to site
location and constraints.
·
Phasing Programmes: The access tunnels would be excavated first from the
tunnel portal area towards to the cavern area. This would be followed by
excavation of the caverns. The excavated tunnels would be used as construction
access for transportation of materials by trucks and plants ingress and egress
of the construction site. Ancillary building will be constructed adjacent to
the tunnel portal afterwards. For water mains laying at carriageways/footpath,
their extent of excavation, unloading/loading of spoils, material handling, and
site area exposed to wind erosion are very limited. In addition, they will be
constructed by section to minimise the potential traffic and environmental
impacts. As there is only single route to cavern, there is not much room to
divide the construction programme in phases/packages.
·
Operation Mode of Relocated DHSRs: The relocated DHSRs only involve routine inspection
and maintenance of ventilation system, pumping system, electrical system,
detection/ alarm system, pipeworks and civil structures. No special alternative
operation mode is required.
Table 3.5 Key
Concurrent Projects for Construction Dust Assessments
Project Name |
Project
Scope |
Remarks |
HyD’s
Improvement of Lion Rock Tunnel |
The
scope of the Project comprises the construction of a new tunnel tube to
facilitate the subsequent rehabilitation/reconstruction of the two existing
tunnel tubes, widening of the connecting roads and the associated works. |
Project
details is not available for consideration at time of reporting. |
CE 28/2017 (HY) - Pedestrian Link near Chuk Yuen
North Estate – Design and Construction |
The
scope of the Project comprises the main construction of covered pedestrian
link, pedestrian subway and covered walkway. The project also includes road
realignment and other associated works, which include provision of barrier
free facilities. |
Works
area of tunnel portal and ancillary building is away from this concurrent
project, only the small scale watermain laying shall be considered relevant. |
a.
Site formation for Portal Enclosure, Auxiliary Buildings and
Infrastructure Works for Watermain Laying
·
Excavation and material handling within the construction site; and
·
Wind erosion of open active area.
b.
Drill & Blast / Drill & Break for Caverns and Access Tunnel
·
Drill & Blast operations
·
Excavation and material handling within the construction;
·
Wind erosion of open active area;
·
Rock crusher with loading, crushing and screening;
·
Materials handling of excavated material; and
·
Vehicle movements on unpaved site roads.
c.
Stockpiling of Excavated Material
·
Stockpiling and material handling within the construction site; and
·
Wind erosion of open active area.
Table 3.6 Individual
Construction Activities during Construction
Activity |
Description |
Details |
Blasting |
Area and the depth of
each blasting |
For drill and break per event, depth is
assumed to be 1.5m; For drill and blast per event, depth is
assumed to be 3m; Approximate area is
assumed to be 14.7m x 11.2m = 165m2 |
Number of blasting per
day |
1 time |
|
Planned time for
blasting in each working day |
Blasting could have
happened anytime between 7am to 7pm – Monday to Saturday (subject to
condition) |
|
Procedures |
1)
Before blasting, blast nets / canvas will be installed at the blasting
area inside the tunnel/cavern. 2)
Blast door will be installed near to the blasting area and keep closed
which can withstand the air pressure generated inside the tunnel/cavern and
minimise the dust emission during blasting. Ventilation system will be turned
off before blasting. All other construction activities inside tunnel/cavern
(e.g. rock crushing, wet drilling, material handling, vehicle movement) will
be ceased. 3)
After blasting, all dust emitted will be confined with the
tunnel/cavern. 4)
Blast door will be opened. Water spraying will be provided to
facilitate initial dust settlement after blasting. Ventilation system will be
turned on to remove the dust emitted. |
|
Bulldozing |
Any bulldozing activity |
No bulldozing activity
is anticipated |
Material Handling |
Working hours per day |
24 hours in tunnel |
Handling rate per hour |
21 m3/hr |
|
Material moisture
content in percent |
0.7% for crushed
limestone |
|
Density of material |
Ranging between
2500kg/m3 and 2700kg/m3 (subject to lab test report) |
|
Wind speed inside
cavern |
0.1m/s |
|
Tertiary Crushing |
Crushing Rate |
3.9 ton/hr |
Truck Unloading |
Loading Rate |
3.9 ton/hr |
Vehicle
Movements on Unpaved Site Roads |
The net weight and the
gross weight of each truck |
10 tonnes |
Truck flow in each
direction |
The truck flow in one way is 3.5 truck per hour |
|
The weight of the
materials to be carried by each truck |
20 tonnes |
|
Average one-way travel
distance within site |
750m is a conservative
estimation |
|
Surface material slit
content |
8.5% |
|
Wet
Drilling |
Handling rate per hour |
21 m3/hr |
Table 3.7 Emission Factor
for Dust Emitting Construction Activity
Activity |
Emission Factor |
Remarks |
Location |
Heavy Construction Activities and ii) Water mains
laying works |
E = 2.69 Mg/hectare/month of activity (TSP)
TSP-to-FSP factor = 0.072 E = 2.0756E-04
g/s (TSP) E = 9.8177E-05
g/s (PM10) E = 1.4944E-05
g/s (PM2.5) |
USEPA AP-42, Section 13.2.3, 1/95 ed. USEPA AP-42, 5th ed. 11/06 ed. S13.2.4 Assumed
total area of 7889.15m2 |
Outside Cavern |
Wind Erosion |
E = 0.85
Mg/hectare/year (TSP) TSP-to-RSP factor = 0.473 TSP-to-FSP factor = 0.072 E = 2.6953E-06
g/s (TSP) E = 1.2749E-06
g/s (PM10) E
= 1.9406E-07 g/s (PM2.5) |
USEPA AP-42, 5th ed., Table 11.9.4 USEPA AP-42, 5th ed. 11/06 ed. S13.2.4 USEPA AP-42, 5th ed. 11/06 ed. S13.2.4 Assumed total area of 7889.15m2 |
Outside Cavern |
Blasting |
E = 1.3203E-01 g/s (TSP) E = 6.8654E-02 g/s (PM10) E = 3.9608E-03 g/s (PM2.5) |
USEPA
AP-42, Section 11.9, Table 11.9-1 |
Inside
Cavern |
Loading Point of Rock Crusher within Portal Enclosure |
E = 8.0000E-06 kg/Mg (PM10) TSP-to-RSP factor = 2.1[1] E = 1.6405E-05 g/s
(TSP) E = 7.8119E-06 g/s (PM10) E = 7.8119E-06g/s (PM2.5) |
USEPA AP-42, 5th ed. 8/04 ed., Section 11.19.2, Table 11.19.2-1 100% actively operating AP-42 Section 11.19.2 |
Inside
Cavern |
Tertiary Crushing by Rock Crusher within Portal Enclosure |
E = 2.6365E-03 g/s (TSP) E = 1.1718E-03 g/s (PM10) E = 1.1718E-03 g/s (PM2.5) |
USEPA AP-42, 5th ed. 8/04 ed., Section 11.19.2, Table 11.19.2-1 100% actively operating USEPA AP-42, 5th ed. 8/04 ed., Section11.19.2, Table 11.19.2-1 Adopt PM10 Emission Factor as upper bound |
Inside
Cavern |
Fine Screening by Rock Crusher (controlled with wet suppression) within
Portal Enclosure |
E
= 1.7577E-03 g/s (TSP) E
= 1.0741E-03 g/s (PM10) E = 1.0741E-03 g/s (PM2.5) |
100%
actively operating USEPA AP-42, 5th ed. 8/04 ed.,
Section11.19.2, Table 11.19.2-1 USEPA AP-42, 5th ed. 8/04 ed.,
Section11.19.2, Table 11.19.2-1 PM2.5 Emission
Factor Adopt PM10
Emission Factor as upper bound |
Inside
Cavern |
Materials Handling |
RSP-TSP factor = 0.52 FSP-TSP factor = 0.03 E = 1.4581E-03 g/s (TSP) E = 6.8964E-04 g/s (PM10) E = 1.0443E-04 g/s (PM2.5) |
USEPA AP-42, Section 11.9, Table 11.9-1 USEPA AP-42, 5th ed, Section 13.2.4.1 |
Inside
Cavern |
Vehicle movements on unpaved site roads (with loading) |
E = 2.3298E+00 g/s (TSP) E = 6.6568E-01 g/s (PM10) E = 6.6568E-02 g/s (PM2.5) |
USEPA AP-42, 5th ed, Section 13.2.2.2 |
Inside
Cavern |
Vehicle movements on unpaved site roads (without loading) |
E = 1.4211E+00 g/s (TSP) E = 4.0603E-01 g/s (PM10) E = 4.0603E-02 g/s (PM2.5) |
USEPA AP-42, 5th ed, Section 13.2.2.2 |
Inside
Cavern |
Wet Drilling |
E = 6.3000E-03 g/s (TSP) E = 6.3000E-04 g/s (PM10) E = 6.3000E-04 g/s (PM2.5) |
USEPA
AP-42,
Section 11.19.2, Table 11.19.2-1 |
Inside
Cavern |
Table
3.8 Preliminary
Design of Ventilation System at the Portal
Design |
Emission Type |
Coordinates |
Design Dimension |
Temp |
Emission velocity (m/s) |
Building Height (m) |
|||
X |
Y |
Length (m) |
Width (m) |
Height (m) |
|||||
Roof
monitor structure |
POINT (CAPPED) |
837094.8 |
822795.8 |
1.5 |
1.5 |
0.5 |
Ambient |
3 |
14.5m
above ground (ground
level: 75.7 mPD) |
Vehicular
Emission within the Quantitative Assessment Area
Determination
of Worst Assessment Year
Table
3.9 Vehicular Classes in EMFAC-HK Model
Vehicle Class |
Description |
Fuel |
Gross
Vehicle Weight |
PC |
Private Cars |
ALL |
ALL |
TAXI |
Taxi |
ALL |
ALL |
LGV3 |
Light Goods
Vehicles (≤2.5t) |
ALL |
≤2.5t |
LGV4 |
Light Goods
Vehicles (2.5-3.5t) |
ALL |
>2.5-3.5t |
LGV6 |
Light Goods
Vehicles (3.5-5.5t) |
ALL |
>3.5-5.5t |
HGV7 |
Medium &
Heavy Goods Vehicles (5.5-15t) |
ALL |
>5.5-15t |
HGV8 |
Medium &
Heavy Goods Vehicles (≥15t) |
ALL |
>15t |
PLB |
Public Light
Buses |
ALL |
ALL |
PV4 |
Private Light
Buses (≤3.5t) |
ALL |
≤3.5t |
PV5 |
Private Light
Buses (>3.5t) |
ALL |
>3.5t |
NFB6 |
Non-franchised
Buses (<6.4t) |
ALL |
≤6.36t |
NFB7 |
Non-franchised
Buses (6.4-15t) |
ALL |
>6.36-15t |
NFB8 |
Non-franchised
Buses (15-24t) |
ALL |
>15t |
FBSD |
Single Deck
Franchised Buses |
ALL |
ALL |
FBDD |
Double Deck
Franchised Buses |
ALL |
ALL |
MC |
Motor Cycles |
ALL |
ALL |
·
Minimum temperature extracted from Wong Tai Sin weather station = 9.9
deg.C
·
Minimum relative humidity extracted from King's Park weather station = 18%
Other
Dust Emission Sources within the Quantitative Assessment Area
·
Fu Shan Crematorium
·
Diamond Hill Crematorium
Concurrent
Project – HyD’s Improvement of Lion Rock Tunnel (LRT)
·
A road tunnel will be constructed in between the two existing tunnels,
approximately 1.4 km long;
·
Tunnel Boring Machine (TBM) will be adopted as the road tunnel construction
method;
·
Tunnel excavation will commence from Shatin side to Kowloon side;
·
Most of the excavated material will dispose offsite at Shatin side
portal; and
·
Tentative TBM excavation programme will commence from 2024 at Shatin
side and expect to reach the Kowloon side by 2027 or later.
Air
Dispersion Model and Meteorological Data
·
10th
highest daily RSP concentration: add 26.5 μg/m3.
·
Annual RSP
concentration: add 15.6 μg/m3
Table 3.10 Summary of Cumulative Dust
Emission Concentration (Unmitigated Scenario)
ASR ID |
Description |
TSP |
RSP |
FSP |
Comply
with AQO or EIAO-TM (Y/N) |
||||
Hourly
(Max) |
Daily
(10th Highest) |
No.
of Daily exceedance |
Annual |
Daily
(10th Highest) |
No.
of Daily exceedance |
Annual |
|||
(µg/m3) |
(µg/m3) |
(µg/m3) |
(µg/m3) |
(µg/m3) |
|||||
ASR1 |
Lion
Rock Park |
2421 |
187 |
111 |
74 |
57 |
2 |
28 |
N |
ASR2 |
Tennis
Court near Tin Ma Court |
3732 |
238 |
148 |
92 |
68 |
5 |
30 |
N |
ASR3 |
Block
B, Peninsula Heights |
3469 |
139 |
49 |
55 |
58 |
2 |
26 |
N |
ASR4 |
Block
1, Meridian Hill |
3631 |
144 |
72 |
59 |
60 |
2 |
26 |
N |
ASR5 |
Chun
Sing House, Tin Ma Court |
4542 |
125 |
28 |
51 |
57 |
2 |
25 |
N |
ASR6 |
Chun
Wai House, Tin Ma Court |
4738 |
119 |
27 |
49 |
57 |
2 |
25 |
N |
ASR7 |
Grace
Methodist Church Kindergarten |
3548 |
133 |
27 |
52 |
56 |
2 |
25 |
N |
ASR8 |
Wang
King House, Tin Wang Court |
2492 |
106 |
16 |
47 |
57 |
2 |
25 |
N |
ASR9 |
Block
6, Tsui Chuk Garden |
2672 |
100 |
9 |
43 |
55 |
2 |
24 |
N |
ASR10 |
Ma
Chai Hang Recreation Ground |
1188 |
82 |
2 |
36 |
53 |
1 |
23 |
N |
ASR11 |
Baptist
Rainbow Primary School |
1255 |
79 |
2 |
36 |
54 |
1 |
23 |
N |
Notes: [1]
Bolded value represents non-compliance to AQO or EIAO-TM criteria. |
Table 3.11 Summary of Dust Suppression Measures
Process |
Description |
Dust Control Measure |
Remarks |
Site Formation |
Heavy construction |
·
Watering will
be provided once per hour. Assume dust removal efficiency at 91.7%. |
USEPA’s Control of Open Fugitive Dust Sources, s3.3.3, equation 3-2 |
Rock Crusher |
Truck unloading, tertiary crushing, fines screening |
·
The rock
crushing plant is configured as an enclosed system with dust collector. ·
Dust
collector will be provided at the exhaust of the rock crusher during rock
crushing. Assume typical dust removal efficiency at 95%[1]. |
USEPA’s Control Techniques for Particulate Emission from Stationary
Sources Vol.2, S9.7.1.2.2 |
Blasting |
- |
Before blasting, blast nets / canvas will be installed at the blasting
area inside the tunnel/cavern. Blast door will be installed near to the
blasting area and keep closed during blasting. The tunnel ventilation system
will be provided with built-in filters for dust removal. |
- |
Trucks |
Material handling, vehicle leaving the works area |
·
Vehicles
would be required to pass through the wheel washing facilities provided at
site exit. ·
Watering will
be provided once per hour. Assume dust removal efficiency at 91.7%. |
USEPA’s Control of Open Fugitive Dust Sources, s3.3.3, equation 3-2 |
Overall Emission inside Cavern |
|||
Dust filter in ventilation system |
All emissions inside cavern |
·
A dust filter
is installed at the ventilation shaft of the tunnel portal to filter all
emissions emitted inside cavern. ·
Assume
typical dust removal efficiency at 80%[2]. |
- |
Remarks: [1] The USEPA’s Control
Techniques for Particulate Emission from Stationary Sources Vol.2, S9.7.1.2.2
indicates typical fabric filter, regardless of the type are greater than 99%.
However, the efficiency is conservatively reduced to 95% in the construction
phase assessment, which is suggested in the same document to be the
suppression efficiency of other common dust suppression methods. [2] Blasting shall not
reduce the performance of the dust filter, as the ventilation system will be
shut down during the blasting process, and blast door will be installed
during the blasting process to ensure the change in air pressure during
blasting would not affect the dust filter efficiency. |
Table 3.12 Summary of Cumulative Dust Emission Concentration
(Mitigated Scenario)
ASR ID |
Description |
TSP |
RSP |
FSP |
Comply
with AQO or EIAO-TM (Y/N) |
||||
Hourly (Max) |
Daily
(10th Highest) |
No.
of Daily exceedance |
Annual |
Daily
(10th Highest) |
No.
of Daily exceedance |
Annual |
|||
(µg/m3) |
(µg/m3) |
(µg/m3) |
(µg/m3) |
(µg/m3) |
|||||
ASR1 |
Lion
Rock Park |
254 |
71 |
2 |
35 |
53 |
2 |
23 |
Y |
ASR2 |
Tennis
Court near Tin Ma Court |
361 |
77 |
2 |
36 |
54 |
2 |
24 |
Y |
ASR3 |
Block
B, Peninsula Heights |
232 |
74 |
2 |
34 |
54 |
2 |
24 |
Y |
ASR4 |
Block
1, Meridian Hill |
276 |
75 |
2 |
34 |
55 |
2 |
24 |
Y |
ASR5 |
Chun
Sing House, Tin Ma Court |
223 |
72 |
2 |
33 |
53 |
2 |
23 |
Y |
ASR6 |
Chun
Wai House, Tin Ma Court |
229 |
72 |
2 |
33 |
53 |
2 |
23 |
Y |
ASR7 |
Grace
Methodist Church Kindergarten |
274 |
73 |
2 |
33 |
54 |
2 |
23 |
Y |
ASR8 |
Wang
King House, Tin Wang Court |
198 |
73 |
2 |
33 |
54 |
2 |
23 |
Y |
ASR9 |
Block
6, Tsui Chuk Garden |
197 |
71 |
2 |
32 |
53 |
2 |
23 |
Y |
ASR10 |
Ma
Chai Hang Recreation Ground |
199 |
71 |
1 |
32 |
53 |
1 |
22 |
Y |
ASR11 |
Baptist
Rainbow Primary School |
199 |
71 |
1 |
32 |
53 |
1 |
22 |
Y |
·
The
contractor shall observe and comply with Air Pollution Control (Construction
Dust) Regulation and implement all the required mitigation measures;
·
The
contractor shall undertake precautions at all times to prevent dust nuisance
and smoke as a result of his activities;
·
The
contractor shall ensure a highly efficient dust filter (at least 80%
efficiency) to be installed at the ventilation exhaust to treat the exhausting
air from cavern;
·
The
contractor shall frequently clean and water the site to minimise fugitive dust
emissions;
·
The
contractor shall ensure that there will be adequate water supply/storage for
dust suppression;
·
The
working area of any pavement breaking, excavation or earth moving operation
should be sprayed with water immediately before, during and after the operation
to avoid dust generation;
·
Any
stockpile of dusty material should be properly covered by tarpaulin or other
impervious sheeting;
·
Vehicles
leaving a site loaded with dusty materials should be covered by tarpaulin or
other impervious sheeting;
·
Wheel
washing facilities shall be installed and used by all vehicles leaving the
site. No earth, mud, debris, dust and the like shall be deposited on public
roads. Water in the wheel cleaning facility shall be changed at frequent
intervals and sediments shall be removed regularly. The contractor shall submit
details of proposals for the wheel cleaning facility. Such wheel washing
facilities shall be usable prior to any earthworks excavating activity on the
site. The Contractor shall also provide a hard-surfaced road between any
washing facility and the public road;
·
Any
materials dropped on paved roads shall be cleaned up immediately to prevent
dust nuisance;
·
The
contractor shall devise, arrange methods of working and carrying out the works
in such a manner so as to minimise dust impacts on the surrounding environment,
and shall provide experienced personnel with suitable training to ensure that
these methods are implemented; and
·
The
contractor shall plan that the works areas of the close proximity water mainlaying
sections will not overlap with the works are of Pedestrian Link near Chuk Yuen
North Estate” project as far as practical. The WSD’s contractor shall further liaise
with HyD’s contractor on the interfacing issue during construction is required.
·
The
contractor shall avoid the use of diesel power machines and generators as far
as practicable;
·
The
contractor shall avoid the use of non-road mobile machineries which exempt by
the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation,
and seek the ones with proper label issued by EPD; and
·
The
contractor shall observe the requirement of DEVB TC(W) No. 13/2020, to apply
a temporary electricity and water supply with a target that the necessary
cables/water mains laying works could be completed before the commencement of
the works contract.
[1] The conversion factor has
also been included in the following EIA reports:
·
Sha
Tin Cavern Sewage Treatment Works (Register No.: AEIAR-202/2016) https://www.epd.gov.hk/eia/register/report/eiareport/eia_2402016/01_EIA/Appendix/Appendices/Appendix%203.02c.pdf
·
West
Island Line (Register No.: AEIAR-126/2008)
https://www.epd.gov.hk/eia/register/report/eiareport/eia_1532008/EIA-pdf/Appendix/app%2011.1.pdf
[2] From USEPA AP-42, 5th
ed. 11/06 ed, Section 1.5 Liquefied
Petroleum Gas Combustion, s2.3
https://www.epa.gov/sites/production/files/2020-09/documents/1.5_liquefied_petroleum_gas_combustion.pdf
[3] Chai Wan Government Complex and Vehicle Depot
(Reigster No.: AEIAR-(AEIAR-191/2015)
https://www.epd.gov.hk/eia/register/report/eiareport/eia_2302015/Web/HTML/Ch%2010%20Hazard.htm
[4]
From
University of Connecticut Department of Plant Science and Landscape
Architecture, Approximate Heating Value of Common Fuels
http://ipm.uconn.edu/documents/raw2/Approximate%20Heating%20Value%20of%20Common%20Fuels/Approximate%20Heating%20Value%20of%20Common%20Fuels.php?aid=230
[5] Kai Tak Multi-purpose
Sports Complex EIA Report (Register No.: AEIAR-204/2017)
https://www.epd.gov.hk/eia/register/report/eiareport/eia_2472016/html/EIA/Appendix/Appendix_3.5.pdf