[English Version] [Traditional Chinese Version] [Simplified Chinese Version] [Graphical Version] [Content Us] [Site Map] [EIAO Website]


Public Works Engineers

Preliminary Project Appraisal

Once the need for a project is established, to gain a formal status in the Public Works Programme (PWP), the respective Bureau Secretary is required to sign off a Project Definition Statement (PDS) for the capital works project. Based on the PDS, the works department prepares the Technical Feasibility Study (TFS) to ascertain viability, identify development / environmental constraints, formulate implementation strategy and estimate cost. Thereafter, inclusion of the project in Category C of the PWP.

Completion of a Project Definition Statement (PDS) for inclusion into the PWP

The PDS explains the rationale for a project and the commitment to it. According to the Handbook, the PDS should determine that:

a. the need for a project has been identified and justified;
b.

the proposed project will meet the need in full and part.

c.

The proposed project will not duplicate or be in conflict with any other existing or planned projects, and

d.

The proposed project is in line with approved policy and approved plans.

Tips:

As a good practice, a project proponent is advised to review and follow up recommendations of strategic planning studies, if available. Then, the project proponent should anticipate and avoid environmental problems as early as possible.

Please click here for Chapter 3 to learn more about "How to use information in strategic Environmental Assessment or Planning Studies?"

Completion of Technical Feasibility Study (TFS) for inclusion into Category C of the PWP
The Handbook requests preliminary considerations in TFS should be given to:

(a) The scope of the project
(b)

Land requirements

(c)

Development constraints

(d)

Environmental consideration including whether a project is a Designated Project and application of avoidance-minimization-mitigation principle

(e) Project Programme
(f) Capital Cost Estimate

Environmental Considerations during TFS stage

With a more defined project scope, a project proponent should seek advice from EPD on whether the work is a Designated Project. Click here for Chapter 3 - "Know whether a project is a Designated Project".

Tips:

project proponent should plan the project programme to avoid putting environmental assessment in the critical path; might decide whether to commence EIA or gather background and baseline information at this stage.

For non-designated projects, the works departments' undertaking should be included to either provide the mitigation measures to implement standard pollution control measures during construction or to carry out a Preliminary Environmental Review of the project, as appropriate.

[Back to top]

 

Last Updated : 2004/03/01

End of Page


[Introduction] [Project Conception] [Preliminary Project Appraisal] [Feasibility Study and PWP Stage] [Implementation] [Monitoring and Evaluation]


[Home] [Myths about EIA] [Learning the Fundamentals] [Getting an EIA Process Started] [Getting to Know your EIA Report] [Improving the EIA Process] [Better Environmental Outcomes] [Useful Resources and Guidelines] [Public Works Engineers]


Copyright 2004 Environmental Protection Department. The Government of the Hong Kong SAR. All rights reserved. Disclaimer