1.2Purpose and Objectives of the EIA
1.4Key Environmental Issues and Study Approach
1.5Structure of the EIA Report
2.2Considerations on Siting of New Crematorium
Option 1: Building additional new cremators at existing crematoria
Option 2: Building a new crematorium at a new site
Option 3: Reprovisioning of the cremators at the Existing Crematorium site at Diamond Hill
Proposed Project Site
2.3Considerations on Layout of New Crematorium
2.4Considerations on Selection of Cremation and Pollution Control Technologies
Cremation Technology
Pollution Control Technology
2.5Description of the Existing and New Crematorium
Existing Crematorium
New Crematorium
2.6Construction and Demolition Programme
Phase I
Phase II
2.7Construction and Demolition Methodology
Phase I
Demolition Works
Construction Works
Phase II
Demolition Works
Construction Works
2.9Interactions with Other Projects
2.10Scenarios with and without the Project
3ENVIRONMENTAL LEGISLATION, POLICIES, PLANS, STANDARDS AND CRITERIA
3.1Environmental Impact Assessment
Construction Noise Criteria
General Construction Works
Operation Noise Criteria
Waste Disposal (Chemical Waste) (General) Regulation
Construction and Demolition (C&D) Materials
4AIR QUALITY IMPACT ASSESSMENT
Background of the Project
Description of the Proposed Project
4.3Introduction to Cremation and Air Pollution Control Technology
Introduction to Cremation Technology
Flat-bed Cremator
Free-falling Cremator
Introduction to the Available Air Pollution Control Technology
Wet Scrubbing
Carbon Injection
Neutralization with Chemical
Electrostatic Precipitation
Bag Filters
Quenching
Air Pollution Control Technology to be Adopted by the New Crematorium
4.4Description of the Nearby Environment
Geographic Conditions of the Site
Background Ambient Air Quality
Air Sensitive Receivers
Existing and Future Construction Projects Near the Site
Diamond Hill No. 2 Freshwater Service Reservoir
KCRC Shatin to Central Link
4.5Methodology of the Air Quality Assessment
Background Information of the Construction Works of the Project
Construction Works of Phase I
Commissioning and Operation of New Crematorium
Concerned Air Pollutants
Air Quality Acceptable Criteria
Design of the Cremators
Air Quality Impact Assessment
Decommissioning of the Existing Crematorium and Phase II Building Works
4.6Results of the Air Quality Impact Assessment
Construction Works of Phase I
Maximum Impact to the Air Quality Due to the Phase I Construction Works
Cumulative Impact Including Background due to the Nearby Projects
Testing and Commissioning of the New Crematorium
Operation of the New Crematorium
Air Quality Impact Assessment Results
Air Quality Assessment for the Operation of Joss Paper Burners
Demolition of the Existing Crematorium and Phase II Building Works
Maximum Impact to the Air Quality Due to Phase II Construction Works
Fugitive Emission of Dioxin Contaminated Dust during Decommissioning of the Existing Crematorium
Demolition and Removal of Asbestos Containing Material
4.7Mitigation Measures to Reduce Adverse Environmental Impacts
Construction Works of Phase I
Commissioning of New Crematorium
Operation of New Crematorium
Demolition of the Existing Crematorium and Phase II Construction Work
4.8Evaluation of Residual Impacts
Construction and Demolition Phase
Operation Phase
Description of the Noise Environment
Determination of Assessment Area
Identification of Representative Noise Sensitive Receivers
5.3Construction and Demolition Noise Assessment
Methodology of Assessment and Assumptions
Potential Sources of Impact and Emission Inventory
Assessment Results
Proposed Construction/Demolition Noise Mitigation Measures
Residual Impacts
Methodology of Assessment and Assumptions
Potential Fixed-noise Sources
Assessment Results
Transitional Impacts (Testing and Commissioning of New Cremators)
Construction and Demolition Noise
Operation Noise
6LAND CONTAMINATION ASSESSMENT
6.2Geology, Hydrogeology and Hydrology
6.10Proposed Remediation Action Plan
6.11Potential for Future Land Contamination
7WASTE MANAGEMENT IMPLICATIONS
7.3Identification of Potential Environmental Impacts During Construction and Demolition Phase
Phase I
Phase II
7.4Identification of Potential Environmental Impacts During Operation Phase
7.5Prediction and Evaluation of Environmental Impacts for Construction and Demolition Phase
Excavated Materials
Construction and Demolition Materials
Contaminated Materials
Asbestos Containing Materials (ACM)
Dioxin Containing Materials (DCM) / Heavy Metal Containing Materials (HMCM) / Polyaromatic Hydrocarbon Containing Materials (PAHCM) from Demolition of the Existing Crematorium
Dioxin Containing Materials (DCM) / Heavy Metal Containing Materials (HMCM) / Polyaromatic Hydrocarbon Containing Materials (PAHCM) / Total Petroleum Hydrocarbon Containing Materials (TPHCM) / Polychlorinated Biphenyls Containing Materials (PCBCM) from Soil Remediation at the Project Site
Potential Hazards of ACM, DCM, HMCM, Hydrocarbon Containing Materials and PCBCM
Chemical Wastes
General Refuse
Cumulative Impacts
7.6Prediction and Evaluation of Environmental Impacts for Operation Phase
Ash and Non-combustible Residues
Chemical Waste
General Refuse
7.7Mitigation of Adverse Environmental Impacts for Construction and Demolition Phase
General - Good Site Practice and Waste Reduction Measures
Excavated Material
Construction and Demolition Material
Contaminated Materials
Further Contamination Investigation
Asbestos Containing Materials (ACM)
Dioxin Containing Materials (DCM) / Heavy Metal Containing Materials (HMCM) / Polyaromatic Hydrocarbon Containing Materials (PAHCM) from Demolition of the Existing Crematorium
Dioxin Containing Materials (DCM) / Heavy Metal Containing Materials (HMCM) / Polyaromatic Hydrocarbon Containing Materials (PAHCM) / Total Petroleum Hydrocarbon Containing Materials (TPHCM) / Polychlorinated Biphenyls Containing Materials (PCBCM) from Soil Remediation at the Project Site
Chemical Waste
General Refuse
7.8Mitigation of Adverse Environmental Impacts for Operation Phase
Ash and Non-combustible Residues
Chemical Waste
General Refuse
8LANDSCAPE AND VISUAL IMPACT ASSESSMENT
Landscape Impact Assessment Methodology
Visual Impact Assessment Methodology
Mitigation Measures
Residual Impacts
Funding, Implementation, Management and Maintenance
Photomontage Illustration
Review of Planning Development Control Framework
Existing Landscape and Visual Context
Landscape Impacts
Landscape Resources – Tree Survey
Visual Impacts
Recommended Mitigation Measures During Construction/Operation
Photomontages
Funding, Implementation and Management
Cumulative Impacts
Conclusion and Summary of Landscape and Visual Impacts
9WATER QUALITY IMPACT ASSESSMENT
Existing Water Quality
Water Sensitive Receivers
9.4Potential Sources of Impacts
Construction and Demolition Phase
Operation Phase
9.5Prediction and Evaluation of Environmental Impacts
Construction and Demolition Phase
Operation Phase
9.6Mitigation of Adverse Environmental Impacts
Construction and Demolition Phase
Operation Phase
10.2Potential Hazard of the Project
10.3Recommended Safety Measures
Fuel Tanks Design
Fuel Storage and Transportation
DG Storage
11ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS
11.2EM&A Requirements for Construction and Demolition Phases I & II
Air Quality
Noise
Land Contamination
Waste Management
Air Quality
Landscape and Visual
11.4Summary for All Monitoring Parameters
11.5Environmental Management Plan
12SUMMARY OF ENVIRONMENTAL OUTCOMES
12.3Key Environmental Outcomes
14IMPLEMENTATION SCHEDULE OF MITIGATION MEASURES
LIST OF TABLES (VOLUME 1 OF 2)
Table 3.1 Hong Kong Air Quality Objectives
Table 3.2 Air Quality Criteria for non-AQO Pollutants
Table 3.3 Health Risk Guidelines for Exposure to Air Toxics
Table 3.4 EIA-TM Noise Standard for Daytime Construction Activities
Table 3.5 Acceptable Noise Levels for Fixed Noise Sources
Table 4.2 Background Air Pollutant Levels Adopted for Air Quality Assessment
Table 4.4 Tentative Work Schedule of the Project
Table 4.6 Acceptable Air Quality Criteria of the Air Quality Impact Assessment
Table 4.7 Calculation of Emission Rates of Air Pollutants
Table 4.8 Calculation of Emission Rates of Odour
Table 4.9 Data Input for ISCST Analysis – Phase I Construction Work
Table 4.11 Data Input for ISCST3 Modelling Work
Table 4.12 Maximum Air Quality Impact at the 24 ASRs
Table 4.13 Increased Risk to Lifetime Exposureof 70 years to Dioxins
Table 4.14 Data Input for ISCST3 Modelling Work for Odour Assessment
Table 4.15 Results of the Odour Assessment at Different Atmospheric Stability Classes
Table 4.16 Maximum 5-second Odour Exposure at ASRs Under Stability Class E,F
Table 4.17 Comparison of Existing and New Cremators
Table 4.18 Data Input for ISCST3 Analysis – Phase II Construction Work
Table 4.19 Fugitive Dust Impact to the ASRs at 1.5 mA.G. due to Phase II Construction Work
Table 5.1 Details of the Representative Noise Sensitive Receivers
Table 5.2 Predicted (Unmitigated) Noise Levels of Phase I and II Construction Works
Table 5.3 Examples of Quiet PME
Table 5.4 Predicted (Mitigated) Noise Levels of Phase I Works
Table 5.5 Predicted (Mitigated) Noise Levels of Phase II Works
Table 5.6 Prevailing Daytime Noise Levels and ASR of the Representative NSRs
Table 5.7 Predicted Noise Impacts Contributed from the Operation of the Crematorium
Table 6.2 Summary of Soil Testing Results
Table 6.3 Results of TCLP Tests for Parameters Exceeding Assessment Criteria
Table 7.1 Level and Volume of Contaminated Ash Waste in KCIP and TSKH Clinical Waste Incinerator
Table 7.2 Further Contamination Investigation Requirements
Table 7.3 Proposed Contamination Classification for Ash Waste with DCM/HMCM
Table 7.5 Demolition, Handling, Treatment and Disposal of Severely Contaminated DCM
Table 8.1 Matrix for Analysis of the Significance Threshold for the Landscape and Visual Impact
Table 8.2 Overall Impact for the Proposed Crematorium Scheme
Table 8.3 Summary of the key anticipated landscape impacts
Table 8.4 Summary of the key anticipated visual impacts
Table 8.5 Summary of mitigation measures and residual landscape impacts
Table 8.6 Summary of mitigation measures and residual visual impacts
Table 9.1 Summary of Water Quality Monitoring Data for Kai Tak Nullah Monitoring Station KN7 in 2001
Table 11.1 Limit Levels of TSP Monitoring
Table 11.2 Location of TSP Monitoring
Table 11.3 Location of Noise Monitoring
Table 11.4 Limit Levels of Noise Monitoring
Table 11.5 Supplementary and Confirmatory Site Investigations Locations, Timing and Parameters
Table 11.6 Supplementary Site Investigations Locations, Timing and Parameters
Table 11.8 Summary for All Monitoring Parameters
Table 12.1 Summary of Key Environmental Impacts
Table 14.1 Implementation Schedule for Reprovisioning of Diamond Hill Crematorium
APPENDICES (VOLUME 1 OF 2)
APPENDIX A |
AIR QUALITY MODELING INFORMATION |
|
|
Predicted Noise Levels of Construction and Demolition Works (Unmitigated and Mitigated) |
|
Calculation of Fixed-Noise Source – Operation Noise Assessment |
|
|
|
LIST OF FIGURES (VOLUME 2 OF 2)
Figure 2.1 Existing Crematorium and Project Site Boundary
Figure 2.2 Lower Ground Floor Plan
Figure 2.6 Construction and Demolition Phase Boundary
Figure 2.7 Proposed Project Programme
Figure 2.8 Locations of Co-current Projects
Figure 4.1 Locations of Air Sensitive Receivers
Figure 4.2 Maximum Level of Fugitive Dust During Phase I Construction at 1.5 mA.G. (worst hit level as well, 1-hour average) (unmitigated)
Figure 4.3 Maximum Level of Fugitive Dust During Phase I Construction Work at 1.5 mA.G. (worst hit level as well, 1-hour average) (mitigated)
Figure 4.4 Maximum Level of Fugitive Dust During Phase I Construction Work at 1.5 mA.G. (worst hit level as well, 24-hour average) (unmitigated)
Figure 4.5 Maximum Level of Fugitive Dust During Phase I Construction Work at 1.5 mA.G. (worst hit level as well, 24-hour average) (mitigated)
Figure 4.6 Maximum Level of Fugitive Dust During Phase II Construction Work at 1.5 mA.G. (worst hit level as well, 1-hour average) (unmitigated)
Figure 4.7 Maximum Level of Fugitive Dust During Phase II Construction Work at 1.5 mA.G. (worst hit level as well, 1-hour average) (mitigated)
Figure 4.8 Maximum Level of Fugitive Dust During Phase II Construction Work at 1.5 mA.G. (worst hit level as well, 24-hour average) (unmitigated)
Figure 4.9 Maximum Level of Fugitive Dust During Phase II Construction Work at 1.5 mA.G. (worst hit level as well, 24-hour average) (mitigated)
Figure 4.10 Maximum Level of RSP During Operation at 1.5 mA.G. (24-hour average)
Figure 4.11 Maximum Level of RSP During Operation at 58.5 mA.G. (worst hit level, 24-hour average)
Figure 4.12 Maximum Level of CO During Operation at 1.5 mA.G. (1-hour average)
Figure 4.13 Maximum Level of CO During Operation at 61.5 mA.G. (worst hit level, 1-hour average)
Figure 4.14 Maximum Level of CO During Operation at 1.5 mA.G. (8-hour average)
Figure 4.15 Maximum Level of CO During Operation at 61.5 mA.G. (worst hit level, 8-hour average)
Figure 4.16 Maximum Level of NO2 During Operation at 1.5 mA.G. (1-hour average)
Figure 4.17 Maximum Level of NO2 During Operation at 61.5 mA.G. (worst hit level, 1-hour average)
Figure 4.18 Maximum Level of NO2 During Operation at 1.5 mA.G. (24-hour average)
Figure 4.19 Maximum Level of NO2 During Operation at 58.5 mA.G. (worst hit level, 24-hour average)
Figure 4.20 Maximum Level of SO2 During Operation at 1.5 mA.G. (1-hour average)
Figure 4.21 Maximum Level of SO2 During Operation at 61.5 mA.G. (worst hit level, 1-hour average)
Figure 4.22 Maximum Level of SO2 During Operation at 1.5 mA.G. (24-hour average)
Figure 4.23 Maximum Level of SO2 During Operation at 58.5 mA.G. (worst hit level, 24-hour average)
Figure 4.24 Maximum Level of HCl During Operation at 1.5 mA.G. (1-hour average)
Figure 4.25 Maximum Level of HCl During Operation at 61.5 mA.G. (worst hit level, 1-hour average)
Figure 4.26 Maximum Level of Mercury During Operation at 1.5 mA.G. (1-hour average)
Figure 4.27 Maximum Level of Mercury During Operation at 61.5 mA.G. (worst hit level, 1-hour average)
Figure 4.28 Maximum Level of Excess Cancer Risk During Operation at 1.5 mA.G. (worst hit level as well)
Figure 4.29 Maximum Level of Odour (5-second average) During Operation at 1.5 mA.G.
Figure 4.30 Maximum Level of Odour (5-second average) During Operation at 61.5 mA.G. (worst hit level)
Figure 5.1 Location Plan of Representative Noise Sensitive Receivers
Figure 6.1 Potential Sources of Contamination
Figure 6.2 Location of Exploratory Holes
Figure 6.3 Summary of the Remediation Works
Figure 8.1 Planning Context (Scale 1:5,000)
Figure 8.2 Diamond Hill Crematorium Landscape Impact Assessment Survey Plan (Scale 1:5,000)
Figure 8.3 Master Landscape Plan
Figure 8.4 Longitudinal and Transverse Sections of the New Crematorium
Figure 8.5 Diamond Hill Crematorium Visual Impact Assessment Survey Plan (Scale 1:5,000)
Figure 8.6 Diamond Hill Crematorium Visual Impact Assessment - Key Viewpoints (Refer survey plan for locations)
Figure 8.7 New Crematorium View A (from Diamond Hill Um Cemetery)
Figure 8.8 New Crematorium View B (from Po Kong Village Road)
Figure 8.9 New Crematorium View C (from Po Kong Village Road)
Figure 8.10 New Crematorium View D (from New School Village)
Figure 8.11 New Crematorium View E (from Fung Tak Estate)
Figure 8.12 New Crematorium View F (from Fu Shan Estate)
Figure 8.13 Existing and New Crematoria View A (from Diamond Hill Um Cemetery)
Figure 8.14 Existing and New Crematoria View B (from Po Kong Village Road)
Figure 8.15 Existing and New Crematoria View C (from Po Kong Village Road)
Figure 8.16 Existing and New Crematoria View D (from New School Village)
Figure 8.17 Existing and New Crematoria View E (from Fung Tak Estate)
Figure 8.18 Existing and New Crematoria View F (from Fu Shan Estate)
Figure 9.1 River Water Quality Monitoring Stations in Kai Tak Nullah
Figure 9.2 Water Sensitive Receivers Nearby the Project Site
AAP |
Asbestos Abatement Plan |
ACM |
Asbestos Containing Materials |
AIR |
Asbestos Investigation Report |
AMP |
Asbestos Management Plan |
ANL |
Acceptable Noise Level |
AQMS |
Air Quality Monitoring Station |
AQO |
Air Quality Objectives |
Arch SD |
Architectural Services Department |
ASR |
Area Sensitivity Rating |
ASRs |
Air Sensitive Receivers |
BOD |
Biochemical Oxygen Demand |
BPM |
Best Practicable Means |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CARB |
Air Resources Board, California |
CLP |
China Light and Power |
CNL |
Corrected Noise Level |
CNP |
Construction Noise Permit |
CO |
Carbon monoxide |
COD |
Chemical Oxygen Demand |
COP |
Code of Practice |
CWTC |
Chemical Waste Treatment Centre |
DA-TM |
Technical Memorandum on Noise from Construction Work in Designated Areas |
DCM |
Dioxin Containing Materials |
EIAO |
Environmental Impact Assessment Ordinance |
EIAO-TM |
Technical Memorandum on Environmental Impact Assessment Process |
EM&A |
Environmental Monitoring and Audit |
EMSD |
Electrical and Mechanical Services Department |
EPD |
Environmental Protection Department |
ETWBTC(W) |
Environment, Transport and Works Bureau Technical Circular (Works) |
FEHD |
Food and Environmental Hygiene Department |
GFA |
Gross Floor Area |
GW-TM |
Technical Memorandum on Noise from Construction Work other than Percussive Piling |
HCl |
Hydrogen chloride |
HEPA |
High Efficiency Particulate Air |
Hg |
Mercury |
HMCM |
Heavy Metal Containing Materials |
IND-TM |
Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites |
ISCST |
Industrial Source Complex Short Tem (Air dispersion modelling) |
KCIP |
Kwai Chung Incineration Plant |
KCRC |
Kowloon-Canton Railway Corporation |
LD |
Labour Department |
NCO |
Noise Control Ordinance |
NO2/NOx |
Nitrogen Dioxide / Nitrogen oxides |
NSR |
Noise Sensitive Receiver |
OEHHA |
Office of Environmental Health Hazard Assessment, California |
OU |
Odour Unit |
PAH |
Polyaromatic Hydrocarbons |
PAHCM |
Polyaromatic Hydrocarbons Containing Materials |
PCB |
Polyclorinated Biphenyls |
PCBCM |
Polyclorinated Biphenyls Containing Materials |
PCW |
Prescribed Construction Works |
PME |
Powered Mechanical Equipment |
PNL |
Predicted Noise Level |
PP-TM |
Technical Memorandum on Noise from Percussive Piling |
ProPECC |
Practice Note for Professional Persons |
RAP |
Remediation Action Plan |
RNSR |
Representative Noise Sensitive Receiver |
RSP |
Respirable Suspended Particulates |
SO2 |
Sulphur Dioxide |
SPME |
Specified Powered Mechanical Equipment |
SWL |
Sound Power Level |
TAP |
Toxic air pollutant |
TCDD |
Tetrachloro-p-Dibenzo Dioxin |
TCLP |
Toxicity Characteristic Leaching Procedure |
TEQ |
Toxicity equivalent (for dioxin species) |
TOC |
Total Organic Carbon |
TPH |
Total Petroleum Hydrocarbons |
TPHCM |
Total Petroleum Hydrocarbons Containing Materials |
TSKH |
Ting Siu Kin Hospital |
TSP |
Total Suspended Particulates |
USEPA |
United States Environmental Protection Agency |
WBTC |
Works Branch Technical Circular |
WHO |
World Health Organization |
WPCO |
Water Pollution Control Ordinance |
WQO |
Water Quality Objectives |