CONTENTS
2. PROJECT DESCRIPTION 2-2
2.1 Project Objectives 2-2
2.2 Site History and Project
Location 2-2
2.3 Project Scope 2-3
2.4 Need for the Project 2-4
2.5 Benefits of the Project 2-5
2.6 Without Project Scenario 2-6
2.7 With Project Scenario 2-6
2.8 Design Considerations 2-7
2.9 Consideration of
Alternatives Location, Design and Layout 2-7
2.10 Construction Aspects of
the Project 2-14
2.11 Consideration of
Alternative Construction Methods 2-16
2.12 Consideration of
Alternative Construction Sequence 2-17
2.13 Implementation Programme 2-17
2.14 Concurrent Projects 2-18
2.15 Sustainability
Considerations 2-20
2.16 Continuous Public
Involvement 2-21
2.17 References 2-23
2.1.1
The objectives of the Project are
to enhance the flood protection level of the existing Yuen Long Nullah (YLN) and
Kam Tin River (KTR) and minimise the flooding risk in accordance with DSD¡¦s Stormwater
Drainage Manual (SDM), accounting for future development and climate change.
2.1.2
The proposed revitalisation
works under the Project would enhance the social connectivity of YLN and its
surroundings into an aesthetically-pleasing environment. The aim is to promote
water-friendliness, ecological enhancements, biodiversity and beautification of
YLN, taking into consideration of their effects on hydraulic performance.
2.2
Site History and Project Location
2.2.1
YLN is part of the oldest
drainage system in the territory and is located in the middle of Yuen Long town
centre. According to the DMP Review Study, YLN and KTR are within drainage
basin ¡§Basin 9¡¨, covering approximately 89 km2.
2.2.2
The surface runoff from the upstream
rural & urban areas of ¡§Basin 9¡¨ is mainly collected by the existing
natural watercourses / engineered open channels and urban drainage systems
prior to discharging via Shan Pui River (SPR) and KTR to Deep Bay. Furthermore,
two existing inflatable dams were constructed at the downstream of YLN near
Wang Chau and Yuen Long Bypass Floodway (YLBF) to prevent backwater from Deep
Bay to the town centre.
2.2.3
To meet the flood protection
standards as stipulated in the SDM, the Yuen Long Barrage Scheme (YLBS) was
developed under Agreement No. CE 24/2013(DS) ¡§Drainage Improvement Works in
Yuen Long, Stage 2 ¡V Investigation¡¨. With the proposed location of YLBS situated
at the most downstream part of YLN near the end of Shan Pui Ho East Road, the
anticipated traffic, environmental and public impacts are minimised over the
original stormwater storage scheme, situated near the town center and local
villages. This arrangement also maximises the extent of flood protection area
and enables shorter construction programmes with increased resilience to
climate change. A location plan of the Project is shown in Drawing No. 400171/B&V/LAY/001 in Appendix 1.1.
2.2.4
The YLBS comprises tidal
barrier, pumping station, E&M control room and a linkage bridge. While the tidal barrier serves to
separate the high tide from the low-lying area of Yuen Long, the pumping
station operates to convey upstream stormwater flows over the tidal barrier to
Deep Bay during rainstorm events.
2.2.5
The proposed Project site falls
within Government land, in which no land resumption is anticipated. The YLBS
does not encroach into the nearby Conservation Area (CA) zone and Nam Sang Wai.
2.3
Project Scope
2.3.1
The
scope of the Project includes the construction and operation of the flood
protection facilities. In retaining the technical
feasibility and resilience towards climate change, the flood protection scheme
also comprises revitalisation of the nullah in tandem with blue-green
infrastructures. The
proposed works are summarised in Table 2.1. The
proposed layout of the YLBS is provided in Drawing
No. 400171/B&V/ LAY/002 in Appendix
1.1.
2.3.2
The scope and description of
the proposed works are summarised in Table 2.1.
Table 2.1 - Summary of Project Scope
Proposed
Works
|
Description and Scale of Works
|
Construction and operation of Pumping
Stations
|
A pumping station,
housing in two structures, are located at the western and eastern banks of
the downstream YLN. With a total footprint of approx. 3,300 m2,
the pumping station is also equipped with low flow pumps to be operated during
dry season.
|
Construction and
operation of Tidal Barrier
|
The tidal barrier would
be divided into bays, whereby each segment can be opened at various angles at
the operator¡¦s discretion. Upon completion, the gates would span across YLN at
a width of approx. 50 m.
|
Construction and operation of E&M Control
Room
|
The E&M control
room, with a footprint of approx. 1,300 m2, houses all the E&M
apparatus & facilities for public enjoyment among other ground level open
areas.
|
Construction of Link
Bridge
|
The link bridge provides
an access for maintenance personnel between Wang Lok Street and Shan Pui Ho
East Road and utility crossings. With intermediate piers, the bridge would be
situated downstream of the pumping station, which spans approx. 110 m across
the nullah.
|
Local Widening
and Deepening of YLN
|
The proposed works at YLN
would widen the nullah by 10 m on each side and deepen its bottom to
facilitate flow intake to the pumping station. Inflow-guiding structures would
be constructed to direct flow towards the pumping station.
|
Construction & Modification
of Parapet Walls
|
An additional height of
approx. 200 mm at the top of the existing parapet walls along KTR and additional
parapet walls along YLN and Sham Chung River (SCR) would be constructed. The
extent of works is approx. 3,000 m in total for both banks of KTR and approx.
800 m in total for both banks at YLN & SCR.
|
Refinements to the
existing intersection of YLN & YLBF
|
The proposed works will
involve minor excavation and concreting works at the existing concrete
diversion structure, resulting in the diversion of additional flow to YLBF
for the barrage¡¦s operation at the downstream.
|
Revitalisation works of
YLN
|
Revitalisation works
within YLN by applying the concept of revitalising water bodies to enhance
the local environmental quality. Vegetation & landscape components would
be introduced to enhance the nullah¡¦s biodiversity and social connectivity.
|
Decommissioning of the
Existing
Low Flow Pumping Station (LFPS) & Inflatable Dam
|
The function of the
existing Kau Hui LFPS and the associated existing inflatable dam that spans
approx. 75 m across YLN would be replaced by the tidal barrier of the barrage,
thus would be decommissioned.
|
2.3.3
The modification of parapet
wall at YLBF had been taken up by Mainland North Division of DSD, which would
not be implemented under the YLBS.
2.4.1
The topography of Yuen Long
town is generally flat with ground levels ranging between +4.0 mPD to +4.7 mPD.
With reference to the SDM, given the tide level under a 50-year return period
(with consideration of the mid-21st century climate change) is +4.32 mPD,
there exists a risk of flooding in Yuen Long town even with the absence of
rainfall event.
2.4.2
With reference to the tidal
level of previous Super Typhoons Hato (+4.71mPD) and Mangkhut (+4.28mPD) in
August 2017 and September 2018 respectively, Yuen Long is susceptible to
flooding.
2.4.3
In view of the public safety,
there is a need to provide a robust flood protection scheme that is both climate
resilient and cost effective.
Existing Drainage Conditions
2.4.4
According to the DMP Review
Study, low-lying areas in the Yuen Long District could not meet the required
flood protection level upon catering for future developments, sedimentation at
the downstream main channels, mangrove growth at river estuaries, updated
extreme sea level statistics at Tsim Bei Tsui and climate change.
2.4.5
The existing drainage network
is unable to cater for the design rainstorm and tidal scenarios. Flooding is anticipated covering a vast
area of Yuen Long town centre. A number of flooding incidents from previous wet
seasons corroborated with the findings of the Study.
Current and Predicted Flooding Susceptibility
2.4.6
On 23 August 2017, at the
hoisting of Typhoon Signal No. 10 during the passage of Typhoon Hato, the sea
level at Deep Bay hit a record high in Tsim Bei Tsui Tide Station and reached
+4.71mPD, flooding had been recorded with significant impacts to traffic and local
businesses across Yuen Long town.
2.4.7
The high magnitude of sea level
had wide impacts on coastal areas as well as inland areas in Yuen Long (e.g.
Wang Chau Tseung Tau Tsuen, Hong Lok Road near LRT station, Pau Cheung Square,
Tai Fung Street, Tai Cheung Street, Tung Tai Street, Shui Che Kwun Street, Shan
Pui Tsuen, Shui Pin Tsuen, Tung Shing Lei, Sha Po, Pak Wai Tsuen, Shui Tau,
Shui Mei, Kam Hing Wai, Tai Tseng Wai, Lut Chau).
2.4.8
As a result, the YLBS emerges
as the more pronounced solution among other options in mitigating the impacts
of extreme tidal level.
2.5
Benefits of the Project
2.5.1
The implementation of YLBS embodies
a comprehensive solution in providing adequate drainage performance & flood
resilience to Yuen Long.
2.5.2
The tidal barrier will be
operated in accordance with the real-time tidal level and the observed water
quality in Deep Bay, while the details of a 300mm x 300mm ecological trench will
be further explored in the detailed design stage to allow
free passage of water and aquatic organisms, even when the tidal barriers are
closed. This is to maintain
ecological connectivity and prevent sea water back flow to Yuen Long Town
Centre to resolve the long-standing odour issues. After the construction of
barrage, the tidal barrier and pumps will operate cohesively to replace the
existing inflatable dam, whereby the existing inflatable dam will be deflated
and removed as part of the revitalisation works.
2.5.3
Upon implementation of the
YLBS, the Kau Hui LFPS in YLN would no longer be necessary and its services
would be suspended / decommissioned to achieve energy efficiency. No demolition
works would be involved.
2.5.4
With reference to the 2019
Policy Address, the Chief Executive has proposed to develop and take forward
the concept of ¡§Rivers in the City¡¨, emphasising the aim enhance public
enjoyment of river facilities, experience the multiple values of water bodies,
treasure water bodies and create a better living environment.
2.5.5
The increased flood protection
provided by YLBS would facilitate the concept of ¡§Rivers in the City¡¨ via
nullah revitalisation and aesthetic enhancement works. Subsequently retaining
the ecological connectivity between Deep Bay and the YLN under non-critical
operations.
2.5.6
Vegetation & landscape
components would be introduced to enhance the nullah¡¦s biodiversity and social connectivity
for the revitalisation works within YLN.
2.5.7
In addition to proposed green
roofs and vertical greening, the use of solar panels will be adopted as far as
possible. The applicability and extent of solar energy on the building façade
or roof areas of the Pumping stations and E&M control room will be
evaluated during the detailed design stage.
2.5.8
The current parapet wall along
the existing KTR does not meet the standards for drainage & flood control
performance under the latest climate change parameters, e.g. wave run-ups and
safety margin requirements under DSD¡¦s Stormwater Drainage Manual. Hence,
upgrading works at KTR is necessary to ensure adequate protection against
extreme tides.
2.6
Without Project Scenario
2.6.1
Without the Project, the flood
risk would persist and extent of flooding would continue to increase in Yuen
Long town under extreme weather events and increasing sea-level due to climate
change.
2.6.2
In accordance with the SDM, a
vast area in Yuen Long town centre would be flooded with maximum flood depths
in excess of 1 m. The flood extent maps of ¡§Without Project Scenario¡¨ are
enclosed in Appendix 2.1. Moreover, the
existing concrete-lined YLN would be maintained to preserve the drainage
capacity, negating the opportunity of revitalising YLN.
2.7.1
With the Project, flooding extent
from rainfall & tidal events under 50-year return periods would be
significantly reduced in YL town with some remaining residual flooding (ranging
between 150-300mm depth) in local low-lying areas. Rainfall & tidal events
under 200-year return periods would also be capable of passing within the
banks. The flood extent maps of ¡§With Project Scenario¡¨ are provided in Appendix 2.2, and an increase in flood risk downstream (i.e.
the waterbody of Shan Pui River and Kam Tin River) of the YLBS is not
anticipated as a result of its construction and operation.
2.7.2
The proposed revitalisation
works along the existing concrete-lined YLN under the Project would provide an
opportunity to implement scenic public spaces for leisure activities and
enjoyment and reduces the heat island effect during hot climates. Thus,
showcasing the concept of ¡§Rivers in the City¡¨. The nullah is currently not
accessible by the public. However, the level of access into the nullah at
certain periods throughout the year, such as during the dry season, would be
explored during the detailed design stage, particularly for the section
immediately downstream of the Long Ping Station, but this would be subject to
the findings in the detailed design assessment, establishment of monitoring
system and flood warning system, public safety, evacuation system, etc. Photomontages
of the revitalised YLN are presented in Chapter 10 of this report.
2.7.3
The revitalisation schemes are subject
to further development in the Design Stage. Nonetheless, investigation is being
conducted to retain the existing habitat downstream of the existing inflatable
dam, as much as possible. Meanwhile, the feasibility of new habitats along YLN
would be explored to enhance the existing ecology. Further information can be
found in Chapter 7 of this report.
2.7.4
Given the preliminary design
and site investigation works are ongoing at the time of preparation of this
report, the location and layout of the YLBS may subject to further slight
adjustment upstream to surpass site constraints. Within the indicated boundary
of the pumping station and tidal barrier (in yellow) as shown in Drawing No. 400171/B&V/LAY/001 in Appendix 1.1, all Chapters in
this EIA report has taken into account the most conservative case for
assessment.
2.8
Design Considerations
Design Performance and Climate
Change
2.8.1
The Project is designed in
accordance with DSD¡¦s SDM with a climate change projects of mid-21st century
(2041-2060). The barrage system necessitates a total pumping capacity of 300 m3/s
and a tidal barrier that can withstand a maximum tide level of +5.0 mPD. The adopted
climate change parameters in rainfall and sea level increments are summarised
in Table
2.2.
Table
2.2 - Rainfall Increase and Sea
Level Rise due to Climate Change
Scenario
|
Rainfall Increase
|
Sea Level Rise
|
Mid 21st
century (2041-2060)
|
10.4%
|
0.23m
|
2.8.2
The design has considered
information from the Intergovernmental Panel on Climate Change (IPCC) regarding
the Fifth Assessment Report (AR5) and other relevant data such as the
historical and projected climate data from Hong Kong Observatory (HKO), study
findings of other departments/projects, and research papers from the academia
on global and local climate change. Appropriate AR5¡¦s climate change scenario
has been adopted for hydraulic analysis of the Project.
2.8.3
Given the pioneering nature of
this Project, reference has been made to overseas projects in Japan and USA such
as the 17th Street Canal Pumping Station of the Permanent Canal
Closure & Pumps (PCCP) in New Orleans. These said pumping stations resemble
a similar pump rate of 50 m3/s per pump and the ability to allow
upstream flows to be discharged downstream. Other overseas examples include the
Gulf Intracoastal Waterway West Closure Complex (GIWW) in New Orleans, the
Seabrook Floodgate in New Orleans and the Able Pumping Station in Dallas.
2.8.4
To synergise with the planned beautification
works in the area, a holistic approach to promote water-friendly cultures and
ecological enhancements such as green roofs, solar panels and planting of
vegetation within YLN would be adopted where applicable.
2.9
Consideration of Alternatives Location, Design and Layout
Development Option
2.9.1
To bring the flood protection level to the
standards as stipulated in the SDM, the DMP Review Study has
proposed drainage improvement works in a number of areas in Yuen Long District.
For the Yuen Long town centre, the DMP Review Study recommended
the construction of two underground storage tanks with pumping stations and
associated interception drains and parapet wall (collectively known as the
flood storage scheme [Option A]). The
construction of diversion drains to convey the stormwater into the storage
tanks in Yuen Long town centre would pose significant traffic impact and public
nuisance to the nearby sensitive receivers.
2.9.2
DSD commissioned an Investigation Consultancy Agreement No. CE 24/2013
(DS) ¡§Drainage Improvement Works in Yuen Long, Stage 2 ¡V Investigation¡¨ (the YL
Stage 2 Investigation) in March 2014 to develop a drainage improvement scheme
that would be both hydraulically and technically feasible with public support
for implementation. The YL Stage 2 Investigation recommended a flood resilient scheme
(Barrage Scheme, Option B) comprising a barrage cum pumping station to be built
at the downstream end of Yuen Long Nullah together with modification of the
existing flow diversion structure at the intersection of Yuen Long Nullah and
YLBF and installation of parapet walls.
2.9.3
A comparison on the
environmental factors is shown in Table 2.3:
Table 2.3 ¡V Comparison Summary of
Options A and B
|
Option A ¡V
Storage Tank Scheme
|
Option B ¡V
Yuen Long Barrage Scheme (Selected)
|
Environmental Benefit
|
¡P Current habitat near
inflatable dam remain unchanged
|
¡P Revitalises the existing
concrete-lined nullah
¡P Creates new beneficial
habitats
¡P Mitigates backflow of odorous
seawater from Deep Bay
|
Environmental Disbenefit
|
¡P
Generates large quantities of C&D materials
¡P
Air quality deteriorates from substantial excavation
¡P
Ingress of odorous seawater during high tides remain unchanged
¡P
This option cannot sufficiently reduce the flooding risk and there is
still risk of excess flooding damages to existing habitats
¡P
Further expansion works is required to cater for future climate change
|
¡P
Change in habitat downstream of the existing inflatable dam
¡P
Potential visual impact from YLBS
|
Alternative Location of Barrage Scheme
2.9.4
An assessment on alternative
location of the YLBS was carried out between the most downstream location of
YLN as compared with the location near the existing inflatable dam under
Agreement No. CE 24/2013 (DS).
¡P
Effective mitigation of odour complaints from local
villages;
¡P
Fulfils latest SDM standards while optimising flood
protection extent;
¡P
Maximizes revitalisation extent;
¡P
Less public nuisance; and
¡P
Minimises
land requirement with no land acquisition.
General Arrangement of Pumping Station
2.9.6
A total of 6 nos. of layouts
were proposed, where after examination, Layouts 4A/4B were selected based on
the following evaluations & environmental factors. Meanwhile, Layout 2
would serve as a fall-back option considering the complicated geological
conditions in Yuen Long (i.e. Scheduled Area No. 2) and the potential
geological constraints that may encounter.:
¡P
Hydraulics & Flood
Resilience:
The
chosen layouts (Layout 4A/B) exhibit enhanced pump performance in response to
various upstream water levels (WL) and ability for gravity flow without
operation of pumps. This increases flood resilience for YLN and allows for
optimisation at the forebay structures under the design scenarios of the latest
SDM. Thus, benefiting the environment through increased flexibility in which
the revitalisation schemes are designed with integral wetland compensation.
While the backup option (Layout 2) is slightly inferior to Layout 4A/B in term
of pump intake conditions, it retained a wider width in YLN which provides a
good ability for gravity flow without operation of pumps. It also increases
flood resilience for YLN and allows flexibility in the design of revitalisation
schemes.
¡P
Discharge Performance:
Layout
4A/B distribute the discharge evenly under extreme scenarios and has
versatility to implement devices such as a submerged discharge to minimise
surface turbulence that can be harmful to nearby aquatic ecology. The discharge
of Layout 2 assembles in the western bank of YLN (Yuen Long Industrial Estate
(YLIE) side), which is further away from the CA zone. With the implementation
of devices such as submerged discharge, surface turbulence can be controlled to
minimize the implications.
¡P
Erosion &
Sedimentation:
Layout
4A/B can effectively incorporate energy dissipators that work in conjunction
with submerged discharges to further minimise the energy from the pumps,
despite having a lower resultant peak flow under extreme weather. This enhances
erosion control and better preserves the habitat downstream of the YLBS against
scouring. The discharge of Layout 2 assembles in the western bank of YLN (Yuen
Long Industrial Estate (YLIE) side), which is further away from the CA zone.
With incorporation of energy dissipators in conjunction with submerged
discharges, energy from the pumps can be minimised and preserves the habitat
downstream of the YLBS in vicinity of the CA zone.
¡P
Construction Aspects:
With Layout 4A/B, site accessibility for workers
and plant is greatly enhanced as the pumping stations can be constructed
independently from existing land. This increases safety and flexibility of
construction staging and allows for phased commissioning of the YLBS. Subject
to detailed design and the Contractor¡¦s proposal, a shorter construction
duration may be achieved to minimise the potential environmental impacts
incurred by the construction works. The modular nature of the layout also
provides versatility for future pump upgrading over its lifecycle, thus an ease
of expansion works. Regarding Layout 2, with the majority of the pumping
station footprint is on land, site accessibility is enhanced which would ease
the construction difficulties and facilitate future maintenance procedures. The
backup option also allows flexibility for future expansion works. Besides, due
to the minimized river occupancy, there will be less flow obstruction during
construction which is beneficial in hydraulic and safety perspective.
¡P
Ecological & Visual
Aspects:
Layout 4A/B exhibit smaller sized pumping stations
and an equidistant arrangement from the downstream. This enables more effective
visual mitigation and minimises the impact to the flightpaths of low-flying
species & avifauna whilst reserving a greater potential for ecological
connectivity. Layout 2 retains a wider width in YLN, which allows a spacious
and open view in downstream of YLN. With visual mitigation measures adopted,
implications to the low-flying species & avifauna will be minimised and
potential for ecological connectivity will be maintained.
Further benefits of Layout 4A/4B are elaborated in Appendix 2.3.
2.9.7
As an outcome of the options
evaluation, the ¡§split pumping station on both banks of YLN¡¨, shown in Drawing No. 400171/B&V/LAY/002 in Appendix 1.1, is
adopted in this EIA as it serves to be the most conservative assessment case
for stormwater pumping from upstream to downstream of the tidal barrier. The other
feasible layouts listed under Appendix 2.3
are also under investigation to delineate the most practicable design with consideration
on optimal hydraulic performance, geotechnical constraints and the associated
foundation design scheme.
Tidal Barrier
2.9.8
The proposed tidal barrier will
be constructed with a total span of approx. 49 m and 6 m in height. To maximise
operational flexibility, the proposed barrier will be divided into 3 bays to
allow independent operation. The various types of tidal control structures
investigated are as shown below:
¡P
Inflatable Dam;
¡P
Penstocks;
¡P
Flap Gates;
¡P
Segment Gates; and
¡P
Sector Gates.
2.9.9
In view of the environmentally
sensitive Nam Sang Wai, priority has been placed on height obstructions and ease
of flow control when not in use. Hence, flap gates and sector gates were
shortlisted for their low visual impact and height that would not obstruct the
potential flight path of migratory birds. The application of these barrier is
being investigated with potential suppliers to delineate the least
environmentally and hydraulically obstructing arrangement.
Pumping System
2.9.11
As the Project requires large
design flows with relatively low head, the feasible pump types are shortlisted
to kinetics pumps, namely Axial Flow Pumps and Mixed Flow Pumps with separately
coupled end suction. Further liaison with potential suppliers would be kept
obtaining the intake structure specifications.
2.9.12
Fish-friendly pumps would be
adopted as much as practicable in case any fish enters through the intake
screen into the pumping station.
Power Supply
2.9.13
Based on factors such as power
ratings, reliability, capital & recurrent cost, required footprint and
environmental impact, the following power supply arrangements were weighed:
¡P
Dual Power Supply;
¡P
Single Power Supply with
supporting Generator Sets (Hybrid); and
¡P
All-Generator Powered.
2.9.14
In light of its reliability
from dual sources and minimal emissions on-site, a dual power supply is adopted
in the design. Through continuous liaisons with CLP, it has been noted that a
dual power supply can be supplied through a single source with dual feeds or
from two standalone sources.
Discharge Outlet, Arrangement and Flow
2.9.16
With reference to overseas
examples in New Orleans (USA) such as the Bonnabel Pump Station and 17th
Street Pump Station under the Permanent Canal Closure & Pumps (PCCP), a
submerged discharge is being considered to minimise surface disruptions and to
be further developed in the Design Stage of the Project.
Operation Modes & Maintenance
2.9.17 The conceptual operational scenarios of the proposed tidal barrier
and ancillary pumping station are simplified for easy understanding in Table
2.4.
Table 2.4 - Conceptual Operational
Scenarios for the Barrage Scheme
Mode
|
Tidal
Condition
|
Precipitation
|
Flow Condition
|
Barrier Status
|
Pump Status
|
1
|
Low
|
No
|
Dry Weather
|
Opened
|
Off
|
2
|
High
|
Closed
|
On
|
3
|
Low
|
Heavy
|
High
|
Closed
|
On
|
4
|
High
|
Closed
|
On
|
A visual illustration of the
conceptual operation modes of the YLBS is enclosed in Appendix 2.4.
2.9.18
As the tidal barrier is
intended to withstand the odourous tidal backflow from Deep Bay, operation of
the gates would be optimised with a flexibility of opening and closing at designated
times of the day through flow sensors and Supervisory Control and Data
Acquisition (SCADA) systems.
2.9.19
The barrier would operate to
combat both high tides and sub-standard water quality. Hence, subject to
further developments in detailed design, the default is for the tidal barrier
to remain closed during adverse weather conditions. The details of a 300mm x
300mm ecological trench will be further explored in the detailed design stage
to allow free passage of water and aquatic organisms, even when the tidal
barriers are closed. Indicative details of this scheme is provided in Appendix 2.4.
2.9.20
In accordance to a preliminary
analysis of historical tidal data, approximately 2-12 hours of opening per day
could be catered but subject to other parameters such as existing / predicted
weather condition, water quality and water level upstream of the YLBS. In the
case where water quality in Deep Bay has improved and there is no further odour
concern for Yuen Long Town Centre and adjacent villages, opening of the gates
can be considered to further maximise the amount of water upstream of the YLBS
in the intertidal zone.
2.9.21
To balance the rate of water
ingress at the tidal barrier and maintain the allowable water depth upstream,
the YLBS would utilise low-flow pumps under normal conditions and be subjected
to further studying for the opening/closing of the tidal barrier. Nonetheless,
the ingress of water would require carefully designing to avoid posing flooding
risk to Yuen Long Town. With further design optimisations required in detailed
design, the dedicated high-capacity pumps of the YLBS would begin to operate
accordingly when the upstream water level reaches +1.2mPD tentatively.
2.9.22
Given the proven reliability
from CLP¡¦s dual power supply, no alternative power supply arrangements would be
fitted to the large capacity pumps. Nonetheless, fail-safe provisions would be
incorporated to ensure the tidal barrier can be disengaged without a primary power
source. An access for maintenance personnel would be provided across the tidal barrier
to facilitate regular inspections and maintenance works.
Revitalisation of YLN
2.9.23
After implementation of YLBS, the
hydraulic performance of YLN is enhanced. The proposed revitalisation works
along the existing concrete-lined YLN under the Project would provide an
opportunity to implement scenic public spaces for leisure activities and
enjoyment and reduces the heat island effect during hot climates. This promotes
water-friendliness, ecological enhancements, biodiversity and beautification along
the existing concrete-lined YLN. At nullah sections that are technically
feasible (e.g. geotechnical, hydraulics, etc.), scope of revitalisation works
may include: removal of sections of concrete nullah, provision of natural
substrates and planting and provision of designated viewing points.
2.9.25
The sparse numbers of public
amenities downstream of the Long Ping West Rail Line Station can limit the ease
of access and degree of public enjoyment. To enhance the social connectivity of
the revitalisation scheme, the potential public attractions to be developed
under YLBS would be explored in synergy with the architectural designs under
Agreement No. CE 3/2015 (DS) Yuen Long Effluent Polishing Plant.
2.9.26
For the downstream section
between the existing inflatable dam and YLBS which has adequate width, the
revitalisation will aim for a more ¡¥nature¡¦ approach. This could include
removing parts of the existing concrete beds, providing natural substrates,
planting of suitable vegetation and provision of viewing platforms.
2.9.27
The preliminary architectural
designs, feasible co-use schemes and revitalisation theme would be further
developed throughout the progression of the Project and to be evaluated under
the Landscape and Visual Impact Assessment (LVIA) of this report. The details of revitalisation would be subject to further stakeholder engagement,
engineering studies, hydraulic assessments & optimisations.
2.9.28
As part of the nullah revitalisation,
measures are being explored to retain the habitat between the existing
inflatable dam and the proposed tidal barrier as far as practicable. Apart from
periodic opening of the tidal gates and provision of ecological trench as
mentioned above, the proposed nullah deepening works for the pump intakes can
also be deepened at a gradient to further enhance ecological connectivity. In
combination with the proposed 300mm x 300mm ecological trench, with details to
be explored in the detailed design stage, this would facilitate an exchange of
water and provide a similar environment to the existing tidal fluctuations.
2.9.29 With consideration of the gradual deepening, the water level to be
maintained upstream of the YLBS is approximately +1.0mPD with a water depth
range of between 0m to 2m. To cater for potential loss of watercourse habitat,
the design could allow tidal water to flush 50m further upstream of the current
inflatable dam. This would create a watercourse habitat area similar to
existing conditions and be further enhanced by the revitalisation works. The details
would be subject to further engineering studies, hydraulic assessments & optimisations.
2.9.30
The design and construction of
the nullah revitalisation under the YLBS, would comply with the management of
construction site drainage as provided in ProPECC
PN 1/94. The Contractor would be instructed to be compliant with the Water
Pollution Control Ordinance and its subsidiary regulations and obtain a
discharge license under the Ordinance. The management of construction and
demolition (C&D) materials, including the generation and reuse of surplus
inert materials, and other mitigation measures including perimeter drainage
channels, sand/silt removal facilities and suitable containment structures for
nullah works would be adopted as far as possible. Please refer to Chapter
5 of this Report for further details.
Construction Method ¡V Barrage Scheme
2.10.1
To mitigate the potential
adverse impacts incurred to the nullah¡¦s hydraulic performance, the environment
and nearby stakeholders, the proposed works comprises a phased construction
method with interim flow diversion schemes by cofferdams. Furthermore, piling
works would be suspended during the dry seasons to minimise potential impact on
migratory birds in Nam Sang Wai. The Contractor would be required to design and
coordinate the corresponding temporary works and flow diversion schemes with
DSD prior to Construction. An overview of the 3 primary phases are presented
below in Table 2.5:
Table 2.5 - Key Construction Phases
& Description
Phase 1 ¡V Local Widening and Deepening of
YLN
|
¡P
Cofferdam for Temporary Diversion
¡P
Excavation Works by Open Cut
¡P
Slope Stabilising (Concreting Works)
|
|
Phase 2 ¡V Construction of Pumping Stations, E&M Control Room &
Link Bridge
|
¡P
Cofferdam for Temporary Diversion
¡P
Foundation Works (Piling / Concreting Works)
¡P
Superstructure & E&M Installation Works
|
|
Phase 3 ¡V Construction of Tidal Barrier
|
¡P
Cofferdam for Temporary Diversion
¡P
Flow Optimising Walls in YLN
¡P
Superstructure & E&M Installation Works
|
|
Upon Barrage Completion:
Revitalisation of YLN
|
¡P
Excavation Works by Open Cut
¡P
Decommissioning of the Existing LFPS & Inflatable Dam
¡P
Construction of Hard Landscapes (Concreting Works)
¡P
Installation of Greenery (Planting)
|
|
Non-critical Path Works:
Parapet Walls & Public Enjoyment Facilities
|
¡P
Construction & Modification of Parapet Walls (Concreting Works)
¡P
Refinements to the Existing Intersection of YLN & YLBF
¡P
Installation of Pre-fabricated Opaque Panels & Public Space
Amenities
|
|
Phase 1 ¡V Channel Deepening, Widening and
Stabilisation Works
2.10.2
Channel deepening and widening
works would be carried out one bank at a time to preserve the drainage
performance of YLN as well as the impact on existing ecology. The cross
sections of deepened forebay is shown in Drawing
No. 400171/B&V/ LAY/003 & 004 in Appendix
1.1.
Phase 2 ¡V Construction of Pumping Stations, E&M Control Room &
Link Bridge
2.10.3
To minimise the impact on
over-wintering birds in Nam Sang Wai, no piling works would be conducted during
the dry season. Sufficient time would be scheduled to allow for Testing and
Commissioning (T&C) prior to the partial operation of the pumping station.
The preliminary designs of Pumping Stations A & B, E&M Control Room and
Link Bridge are shown in Drawing
No. 400171/B&V/LAY/102, 202, 402 & 601 in Appendix 1.1 respectively.
Phase 3 ¡V Tidal Barrier Assembly & Installation
2.10.4
Upon completion of Phase 2, a
cofferdam would be constructed between the pumping stations for subsequent
construction of the tidal barrier and forebay optimisations. Through operating
the pumps, it is anticipated to compensate for the loss of flow area during the
tidal barrier¡¦s construction and its T&C. The preliminary design of tidal
barrier is shown in Drawing Nos.
400171/B&V/LAY/ 003 in Appendix
1.1.
Revitalisation Works along Yuen Long
Nullah and Decommissioning of Existing LFPS & Inflatable Dam
2.10.5
Subject to the selected design
theme, it is anticipated for the revitalisation works to comprise hard
landscape features and vegetation. The works would be carried out in sections
along the length of YLN through temporary flow diversion with stacks of sand
bags. The accumulated sediment downstream of the existing inflatable dam would
be removed prior to works and the typical cross sections of the revitalisation
extent is shown in Drawing No.
400171/B&V/LAY/501 & 502 in Appendix
1.1.
Construction & Modification of Parapet Walls
2.10.6
Additional concrete parapet
walls would be constructed along YLN and SCR along sections that are vulnerable
to flooding. The existing parapet walls along KTR would be heightened through metal-framed,
opaque panels to minimise visual impact.
2.10.7
Ardeid night roost was recorded
at a site along Kam Tin River. To avoid / minimise the disturbance to the ardeid
night roost, no construction works should be undertaken within 100m from any
night roost confirmed by the pre-construction survey after 17:00 from February
to September and 16:30 from October to January.
Summary of Key Construction Activities
2.10.8
Construction of the barrage
generally involves common civil engineering construction activities such as
site clearance, excavation, formwork, substructure and superstructure
construction, concreting, landscaping and E&M installation. Revitalisation
of YLN involves smaller scale construction activities such as breaking of
nullah bed, excavation and landscaping.
2.11
Consideration of Alternative Construction Methods
Barrage Scheme
2.11.1
Potential alternative
construction method includes offsite precast structures or modular integrated
construction (MiC) for the pumping stations and tidal barrier. The
environmental benefit of offsite construction is that there will be less
construction waste, shortened construction period, and less environmental
disturbance and nuisance to nearby sensitive receivers. The applicability of
adopting MiC would be explored.
2.11.2
To allow for flexibility in
design and facilitate the installation of large sized pumps / gates, it is more
practicable to construct the structures in-situ.
The associated environmental impacts anticipated are generally temporary, localized
and can be mitigated through appropriate pollution control measures.
Revitalisation of YLN
2.11.3
The revitalisation would
generally be small scale and localized construction and landscaping works.
Alternative construction methods will be limited. Nonetheless, the removal of
the concrete bed of YLN should explore saw and lift method instead of
traditional surface breaking using breakers. The concrete slab could be
beneficially reused as flow deflector, stepping stones or sitting area in the
revitalised channel enhancing the overall sustainability concept of the
Project.
2.12
Consideration of Alternative Construction Sequence
2.12.1
Ardeid night roost was recorded
at a site along Kam Tin River. To avoid / minimise the disturbance to the
ardeid night roost, no construction works should be undertaken within 100m from
any night roost confirmed by the pre-construction survey after 17:00 from
February to September and 16:30 from October to January.
2.12.2
To reduce disturbance and
nuisance to nearby sensitive receivers and to maintain adequate flood
protection capacity in YLN, the pumping stations and tidal barrier will not be
constructed simultaneously and the revitalisation works shall only commence
upon completion and operation of the barrage. To further reduce the potential
water quality impacts, excavation works in the YLN will only be undertaken in
dry condition.
2.12.3
The design and construction of
YLBS is anticipated to adopt an Early Contractor Involvement (ECI) under NEC4
Engineering and Construction Contract (ECC). The selected Contractor would be
engaged early in the project lifecycle to collaborate with design groups and
project owners on the constructability and cost control. The programme and
methods of construction would be further developed subject to coordination with
the ECI Contractor later in the Design Stage.
2.13
Implementation Programme
2.13.1
The construction works of the
pumping stations and tidal barrier is anticipated to commence in Q4 of 2022 for
completion by Q3 of 2027, with concurrent construction & modification of
the parapet walls along Kung Um Road, Kiu Hing Road and KTR. Upon completion of
the barrage, the LFPS would be decommissioned, and the existing inflatable dam would
be removed from YLN. The revitalisation works along YLN would take place until
Q3 of 2029. A tentative construction programme is shown in Chapter 4 for assessment
purposes. Subject to detailed design and the Contractor¡¦s proposal, a shorter
construction duration may be achieved such that general nuisance and potential environmental
impacts are minimised.
2.14.1
Based on best available information,
the following projects to be undertaken concurrently in the vicinity of the
Project Site are identified as potential concurrent projects. The potential
cumulative construction / operation impacts due to these projects to be
addressed in this EIA Study are presented in Table 2.6.
Improvement of Yuen Long Town Nullah (Town Centre Section) ¡V Stage 1
Improvement Works (1)
2.14.2
The project mainly comprises
provision of a dry weather flow (DWF) interception system, including
construction of DWF interceptors along the Town Centre Section of YLN and a new
pumping station. The DWF interception
system will convey the first 18,000 m3 of DWF being intercepted each
day to the YLEPP for treatment.
2.14.3
The project will divert the polluted DWF and effectively eliminate the
main source of odour nuisance at YLN. It will also provide favourable condition
to allow the revitalisation of YLN to be implemented in this Project. Based on
current information, the DWF interception system will need to be in operation
before revitalisation works could begin. As such, concurrent construction work
is not envisaged. Nonetheless, the locations of the DWF interceptors and
associated nullah wall construction works is anticipated to interface with the
proposed revitalisation design works under this Project.
Elevated Pedestrian Corridor in Yuen Long Town Connecting with Long Ping
Station (2)
2.14.4
In the project (EPC), an
elevated pedestrian corridor, in form of a footbridge, along YLN from West Rail
Long Ping Station to the south of the Kau Yuk Road will be constructed. The
proposed elevated pedestrian corridor will be connected to at-grade footpath
via pedestrian interchanges located along the nullah. According to the latest
best information provided by HyD, the project was tentatively scheduled to
commence in first quarter of 2020 for completion in first quarter of 2025
¡Vsubject to the funding approval by LegCo.
2.14.5
Given the latest implementation
challenges faced by this project in Yuen Long, further liaison and monitoring
would be conducted to gauge the level of interface with YLBS. Therefore, the
cumulative impact to YLN due to the footbridge would be further reviewed and
incorporated in the hydraulic analysis of YLBS. To be conservative, the EPC
project is assumed to be conducted concurrently with the Project.
Yuen Long Effluent Polishing Plant (YLEPP) (3)
2.14.6
The existing Yuen Long Sewage
Treatment Works (YLSTW) will be upgraded into YLEPP in order to cater for
future needs in the catchment and improve the water quality of Deep Bay. The
capacity of the YLEPP will be increased from 70,000 m3/day (for
existing YLSTW) to 150,000 m3/day (Phase 1: 100,000 m3/day;
Phase 2: 150,000 m3/day) with upgrading the treatment level from
secondary to tertiary. The treatment capacity of YLEPP would be reduced to
35,000 m3/day during the upgrading period in Phase 1 (i.e. Year 2020
¡V Year 2027). According to the EIA Report of the YLEPP, the construction works
are tentatively scheduled to commence in third quarter of 2020 for completion
in second quarter of 2027 for Phase 1 and 2030 for Phase 2 the earliest.
2.14.7
The project boundary of the
YLEPP is outside the 500m study area of the Project. However, given that both
projects are in close proximity to the contiguous wetland habitats of Shan Pui
River and Nam Sang Wai, the likely cumulative impact on ecology will be
addressed in this EIA Study.
Yuen Long South Development ¡V Stage 1 (4)
2.14.8
The Revised Recommended Outline
Development Plan (RODP) of the ¡§Planning and Engineering Study for Housing
Sites in Yuen Long South (YLS) ¡V Investigation¡¨ was promulgated in May 2020. Under the Revised RODP, the YLS
Development will provide about 32,850 new flats with a total population of
about 101,200. The development
covers approximately 223.5 ha and is located to the south of Yuen Long New
Town. Other than housing development within the PDA, there are also some other
supporting infrastructure works (such as public transport interchange, road
construction / improvement works, main laying, partial nullah decking and
reclaimed water service reservoir) outside the PDA. This study included proposed river revitalisation and partial
decking at the upstream of Yuen Long Main Nullah and adjacent branches. The
proposed river revitalisation works would collect and divert the drainage from
the nearby existing village and low-rise residential area into Yuen Long West
Nullah, Tin Tsuen Channel and upstream portions of YLN.
2.14.10The Stage 1 project is to design and carry out site formation and
infrastructure works to support the YLS Development. Part of the road
improvement works include partial decking of YLN and providing nullah/river
channel revitalisation works. The Stage 1 works also includes modification of
drainage structure at junction of YLN and YLBF. Further liaisons with the
responsible project team would be made to ascertain their extent of works and
degree of interface with this Project. In particular, the proposed revitalisation
of YLN shall be compatible with the revitalisation works to be carried out
under the YLS Development.
River Revitalisation and Flood Resilience Planning in Yuen Long South
2.14.11This feasibility study is to investigate and develop a smart, green,
resilient and sustainable drainage system for the YLS Development. Further
liaisons with the responsible project team would be made to ascertain their
extent of works and degree of interface with this Project.
2.14.12 A summary of the potential interfaces are shown below in Table
2.6:
Table
2.6 - Potential Concurrent
Projects
Project
|
Project Proponent
|
Programme
|
Location of Potential Interface
|
Considered in this EIA
|
Start
|
Complete
|
Construction Phase
|
Operation Phase
|
CE 37/2012 (DS)
Improvement of Yuen Long Town Nullah (Town Centre Section) ¡V Stage 1
Improvement Works ¡V Design and Construction
|
DSD
|
Q2
2021
|
2026
|
Yuen
Long Nullah
|
ü
|
ü
|
CE 32/2014 (HY)
Elevated Pedestrian Corridor in Yuen Long Town Connecting with Long Ping
Station ¡V Investigation, Design and Construction
|
HyD
|
2020*
|
2025
|
Yuen
Long Town
|
ü
|
ü
|
CE 3/2015 (DS)
Yuen Long Effluent Polishing Plant ¡V Investigation, Design and Construction
|
DSD
|
2020
|
2030
|
Shan
Pui River
|
ü
|
ü
|
CE 32/2017 (CE)
Yuen Long South Development ¡V Stage 1 ¡V Design and Construction
|
CEDD
|
2020
|
2038
|
Intersection
of YLN and YLBF
|
ü
|
ü
|
*The commencement of construction of footbridge is
subject to the funding approval by LegCo.
Blue Green Infrastructure
2.15.1
Blue-green drainage
infrastructure is a form of development aiming to improve the sustainability
and resilience of the drainage system. It facilitates the infiltration of
rainfall and the process of natural filtering to reduce the quantity and
improve the quality of stormwater runoff.
2.15.2
The concept of blue-green infrastructure is advocated to be
incorporated in the future development, maximising amenity and biodiversity
opportunities while minimising the impacts from climate change.
2.15.3
Various ecological features
would be adopted in the proposed revitalisation works to provide habitats for aquatic
life, thus promoting conservation of biodiversity and sustainable use of
biological resources. Blue-green components, embracing Sustainable Drainage
Systems (SuDS) such as green roofs, solar panels, porous pavements and
rainwater harvesting facilities, would be subjected to further feasibility study
in detailed design. While exterior elements such as vertical greening, porous
pavements & green roofs are incorporated as far as practicable within the
project site, internal elements such as the use of harvested rainwater for
toilet flushing purposes would also be explored in detailed design. Hence,
achieving a value-adding design to the proposed works and YLN.
Potential Water Sources
2.15.4
Based on a previous flow
survey, a dry weather flow of 13,000 m3/day was observed to contribute
from upstream Kung Um Road, which would serve as an environmental flow during
dry season.
2.15.5
It is noted that the works
under CE 6/2019 (DS) Project, for the construction and operation of Yuen Long
South Effluent Polishing Plant (YLSEPP), aims to provide sewage treatment for
YLS and other developments in North West New Territories for subsequent
discharge into YLN. In accordance with the Project Profile issued in January
2019, the maximum Average Dry Weather Flow (ADWF) treatment is at 65,000 m3/day.
In synergising with this, the feasibility of utilising the treated discharge
for benefit of the revitalised YLN in the form of an ecological flow would be explored
in the Design Stage of this Project. Further interfaces would be coordinated as
necessary.
2.15.7
However, as a contingency, the
two potential water sources (e.g. YLSEPP and Wong Nai Tung Irrigation
Reservoir, etc.) are situated upstream of the Yuen Long catchment for supplying
water to YLN by gravity without the need of pumping to achieve cost and energy
efficiency.
Green Building Certification
2.15.8 The Project will aim to obtain BEAM Plus Gold or higher
accreditation, as far as practicable for the existing and new
buildings/structures. Where applicable,
renewable energy sources such as photovoltaic panels would be incorporated.
Public Comments during Project
Profile
2.16.1
A public inspection of the
project profile was conducted under Agreement No. CE 24/2013 (DS) and public
comments were received. The main concerns and ways to address are outlined
below and an overview of these comments concerning the proposed works location,
existing ecology, drainage performance, sedimentation, construction methods and
public aspiration is enclosed in Appendix 2.5.
Main Concerns / Ways to Address
¡P
Ecologically
Sensitive Area in the vicinity of the proposed Barrage
A full-scale Ecological Impact Assessment
has been conducted and would contribute towards the corresponding Sections
under the Environmental Impact Assessment (EIA).
¡P
Cumulative
Impact from Construction Activities
We acknowledge the project interfaces in
the vicinity and would assess the cumulative effects to the environment as a
result of the concurrent works in the EIA Report.
¡P
Environmental
Impacts to Nam Sang Wai
The anticipated works area and footprint
for constructing YLBS does not include the use of Nam Sang Wai and would be
confined to the south of Kam Tin River old channel to avoid corresponding
environmental and ecological impacts.
2.16.2
With these preliminary comments
and responses, further public engagements by means of ¡§Design
Thinking Approach¡¨ commenced in mid-2020 to obtain in-depth aspirations from
local stakeholders & advisory bodies.
Green Groups Liaison Meeting
2.16.3
The Project maintained a
continuous communication with Green Groups and their views were obtained during
meetings and site visit as listed below:
¡P
22 September 2016 ¡V Green
Groups Liaison Meeting No. 13
¡P
1 February 2018 ¡V Green
Groups Liaison Meeting No. 18
¡P
28 October 2019 ¡V Site
meeting at the Proposed Location of YLBS
¡P
27 July 2020 ¡V Online
Presentation of YLBS
¡P
5 & 6 November 2020 -
Site meeting at the Proposed Location of YLBS
¡P
11 January 2021 ¡V Online
Meeting with Green Groups
Main
Concerns / Ways to Address
¡P
Ecological
Connectivity
In promoting ecological connectivity, the
Project has proposed a 300mm x 300mm ecological trench and optmisation of the
operation of tidal barriers to allow tidal flow coming-in for further
investigation, as detailed in Chapter 7.
¡P
Revitalisation
Ideas
Different
themes will be developed for the revitalisation works under different section
of YLN, with details further developed in the detailed design, as detailed in Chapters
7 & 10.
Consultation with District Council,
Rural Committee and Village Representative
2.16.4
The Project also engaged with
corresponding community stakeholders to obtain their views during meetings and
site visits as listed below:
¡P
Working Group on Footbridge
Planning and Improvement of Nullah of YLDC ¡V 29 October 2020
¡P
Site visit with District
Council (DC) members and Rural Committee (RC) members on 20, 22 & 28
October 2020
¡P
Environment, Climate
Change, Agriculture and Fisheries Committee of YLDC ¡V 9 November 2020 (followed
by site visit with Rural Committees)
Main
Concerns / Ways to Address
¡P
Odour
Nuisance
The existing
inflatable dam at YLN, near Wang Chau (along with the existing low-flow pump
station), as detailed in this Chapter 2, would be decommissioned upon
completion of the Project. Thus, the build-up of debris & odours could be
alleviated. Coupled with the dry weather flow intercepting system to be
constructed under PWP No. 4161CD ¡V Improvement of Yuen Long Town Nullah (Town
Centre Section), the quality of the local environment could be improved.
¡P
Revitalisation
Ideas
Different
themes will be developed for the revitalisation works under different section
of YLN, with details further developed in the detailed design, as detailed in Chapters 7 & 10
2.17
References
(1)
DSD (2020) ¡V EIA Report
for ¡§Improvement of Yuen Long Town Nullah (Town Centre Section)¡¨ (AEIAR-223/2020).
(2)
HyD (2014) ¡V EIA Report
for ¡§Elevated Pedestrian Corridor in Yuen Long Town Connecting with Long Ping
Station¡¨ (AEIAR-200/2016).
(3)
DSD (2019) ¡V EIA Report
for ¡§Yuen Long Effluent Polishing Plant¡¨ (AEIAR-220/2019).
(4)
CEDD (2017) ¡V EIA Report
for ¡§Housing Sites in Yuen Long South¡¨ (AEIAR-215/201