5.                   Water Quality

 

Introduction

5.1               Stage 1 of HATS, comprising the Stonecutters Island Sewage Treatment Works (SCISTW) and the deep tunnels, was commissioned in late 2001 to bring early improvement to the harbour water quality.  The deep tunnels collect sewage from Kwai Chung, Tsing Yi, Tseung Kwan O, parts of eastern Hong Kong Island and all of Kowloon and deliver it to SCISTW for chemically enhanced primary treatment (CEPT).  Stage 2 of HATS would be implemented in two phases, namely Stage 2A and Stage 2B.  Under Stage 2A, deep tunnels would be built to bring sewage from the northern and western areas of Hong Kong Island to SCISTW and the treatment works would be expanded to meet the demands of both existing and future developments.   Stage 2B of HATS involves the provision of biological treatment at the SCISTW to improve the effluent quality.

5.2               This Project involves the provision of disinfection facilities at the SCISTW. Based on the technical review of disinfection technologies and option evaluation as discussed in Section 2, the purchase of sodium hypochlorite solution for chlorination and sodium bisulphite for dechlorination was recommended as the disinfection technology for SCISTW.  The environmental acceptability of the proposed disinfection method would also be based on the technical assessment performed under this EIA Study.  Based on the current programme, construction of the chlorination plant would commence in March 2008 for commissioning the advance disinfection facilities (ADF) in September 2009. As for the dechlorination plant, construction would commence in September 2008 for completion in September 2009. The major construction activities for the Project are described in Sections 2.11 and 2.12.

5.3               During the ADF stage, use of the existing effluent culvert as the chlorine contact tank is proposed. At Stage 2A, the permanent disinfection facilities of SCISTW (including a new chlorine contact tank) will be available for the HATS effluent to increase the chlorine contact time so as to further improve the effectiveness of the chlorination and minimize the chlorine dosage.

5.4               This Section evaluates the potential water quality impacts that are likely to be generated during the construction and operation phase of the proposed disinfection facilities during Stage 1, Stage 2A and Stage 2B.  Appropriate mitigation measures were identified, where necessary, to mitigate the potential water quality impacts.

 

Key Water Quality Issues

5.5               The Project involves the provision of disinfection facilities at the existing SCISTW.  The key water quality issue of this Project would be the effect of sewage effluent discharged from the SCISTW after commissioning of the Project including:

·            the reduction of faecal bacteria in the effluent due to the proposed disinfection facilities

·            the potential generation of low-level total residual chlorine (TRC) and chlorination by-products (CBP) in the effluent due to chlorination of the sewage effluent

·            the potential impact of TRC in the event of dechlorination plant failure

·            the potential impact of faecal pollution in the event of chlorination plant failure

·            the potential minor oxygen depletion impact due to addition of dechlorination chemical

5.6               Therefore, the key parameters of concern would be:

·            E.coli

·            Dissolved oxygen (DO)

·            TRC and CBP

5.7               E.coli bacteria originate from human and animal faeces and are often used as indicator for faecal pollution.  TRC includes free chlorine residuals such as hypochlorous acid (HOCl) and dissolved hypochlorite ion (OCl-) after chlorine is added to water, plus combined chlorine residuals such as chloramines formed by the reaction of free residuals with ammonia.

5.8               CBP refer to chlorinated organic compounds (or total organic halogen) formed by the reaction of chlorine (mainly free chlorine residuals) with some specific organic compounds such as humic substances, which generally are not present in any large quantity in CEPT effluent. CBP consist of a whole range (hundreds) of halogenated organic compounds, and are generally considered of concern to human health. Examples of CBP formed during chlorination include trihalomethanes (THM) and haloacetic acids (HAA). THM are suspected as being carcinogens and are strictly monitored in drinking water.  CBP concentrations may vary in orders of magnitude during different chlorination processes.  Typical concentrations of THM and HAA in chlorinated drinking water are usually in the range 1-100 mg/l ([1]).  Range of concentrations in chlorinated sewage effluent for specific CBP compounds is identified under this EIA. The potential marine water quality impacts due to chlorination of the SCISTW effluent are quantitatively assessed and described in this Section. The potential toxicity of chlorinated sewage effluent is assessed and discussed under the Human Health and Ecological Risk Assessment in Section 6.

5.9               It is considered that the provision of disinfection facilities would not cause any adverse effects on the marine environment in terms of the changes in hydrology, flow regime, sediment erosion, sediment deposition pattern, sediment quality and salinity profile.  The effects of the Project on marine ecology are discussed under Section 8.  The effects of the Project on the water quality of Tsuen Wan beaches and the possibility of re-opening these beaches are discussed in this Section.

 

Water Sensitive Receivers

5.10            To evaluate the potential water quality impacts from the Project, the water sensitive receivers within the North Western, Western Buffer, Victoria Harbour, Eastern Buffer, Junk Bay and Southern Water Control Zones (WCZ) were considered.  Figure 5.1 shows the locations of identified water sensitive receivers.  Major water sensitive receivers include:

·            Cooling Water Intakes;

·            WSD Flushing Water Intakes;

·            Fish Culture Zones (FCZ);

·            Beaches;

·            Sites of Special Scientific Interest (SSSI);

·            Marine Parks and Marine Reserves;

·            Seagrass Beds;

·            Artificial Reefs;

·            Corals;

·            Chinese White Dolphins; and

·            Green Turtle Nesting Grounds

 

Water Quality Standards, Guidelines and Criteria in Hong Kong

5.11            The general criteria established in Hong Kong for evaluating water quality impacts are provided in Sections 5.12 to 5.24.  Specific criteria for this EIA are provided in Sections 5.25 to 5.29.

 

Environmental Impact Assessment Ordinance (EIAO)

5.12            The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) is issued by the Environmental Protection Department (EPD) under Section 16 of the EIAO.  It specifies the assessment method and criteria that need to be followed in the EIA.  Reference sections in the EIAO-TM provide the details of the assessment criteria and guidelines that are relevant to the water quality impact assessment, including:

·            Annex 6 Criteria for Evaluating Water Pollution

·            Annex 14 Guidelines for Assessment of Water Pollution.

 

Marine Water Quality Objectives under WPCO

5.13            The Water Pollution Control Ordinance (WPCO) provides the major statutory framework for the protection and control of water quality in Hong Kong.  According to the WPCO and its subsidiary legislation, Hong Kong waters are divided into ten Water Control Zones (WCZ).  Corresponding statements of Water Quality Objectives (WQO) are stipulated for different water regimes (marine waters, inland waters, bathing beaches subzones, secondary contact recreation subzones and fish culture subzones) in the WCZ based on their beneficial uses.  With reference to the EIA Study Brief, the study area for this water quality assessment shall cover the North Western, Western Buffer, Victoria Harbour, Eastern Buffer, Junk Bay and Southern WCZ (see Figure 5.2). Their corresponding WQO are listed in Table 5.1 to Table 5.6 respectively.

 

Table 5.1     Summary of Water Quality Objectives for North Western WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones, water gathering ground subzones and other inland waters

Not less than 4.0 mg/l for 90 % sample

Marine waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters excepting bathing beach subzones

To be in the range of 6.5 – 8.5

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

To be in the range of 6.0 –9.0

Other inland waters

To be in the range of 6.0 –9.0 for 95% samples

Bathing beach subzones

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by human activity

Marine waters

Change due to waste discharges not to exceed 20 mg/l of annual median

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 25 mg/l of annual median

Inland waters

Unionized ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionized form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.3 mg/l

Castle peak bay subzone

Annual mean depth-averaged inorganic nitrogen not to exceed 0.5 mg/l

Marine waters excepting castle peak bay subzone

E.coli Bacteria

Not exceed 610 per 100 ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary contact recreation subzones

Should be less than 1 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken between 7 and 21 days.

Tuen Mun (A) and Tuen Mun (B) subzones and water gathering ground subzones

Not exceed 1000 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken between 7 and 21 days

Tuen Mun (C) subzone and other inland waters

Not exceed 180 per 100 ml, calculated as the geometric mean of all samples collected from March to October inclusive.

Bathing beach subzones

Colour

Change due to waste discharges not to exceed 30 Hazen units

Tuen Mun (A) and Tuen Mun (B) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 50 Hazen units

Tuen Mun (C) subzone and other inland waters

5-Day biochemical oxygen demand (BOD5)

Change due to waste discharges not to exceed 3 mg/l

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 5 mg/l

Inland waters

Chemical oxygen demand (COD)

Change due to waste discharges not to exceed 15 mg/l

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water gathering ground subzones

Change due to waste discharges not to exceed 30 mg/l

Inland waters

Toxins

Should not cause a risk to any beneficial uses of the aquatic environment

Whole zone

Waste discharge shall not cause the toxins in water significant to produce toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

Phenol

Quantities shall not sufficient to produce a specific odour or more than 0.05 mg/l as C6 H5OH

Bathing beach subzones

 

Turbidity

Shall not reduce light transmission substantially from the normal level

Bathing beach subzones

Source:   Statement of Water Quality Objectives (North Western Water Control Zone).

 

Table 5.2     Summary of Water Quality Objectives for Western Buffer WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l for 90% of samples

Marine waters excepting fish culture subzones

Not less than 5.0 mg/l for 90% of samples

Fish culture subzones

Not less than 4.0 mg/l

Water gathering ground subzone and other Inland waters

5-Day biochemical oxygen demand (BOD5)

Change due to waste discharges not to exceed 3 mg/l

Water gathering ground subzones

Change due to waste discharges not to exceed 5 mg/l

Inland waters

Chemical oxygen demand (COD)

Change due to waste discharges not to exceed 15 mg/l

Water gathering ground subzones

Change due to waste discharges not to exceed 30 mg/l

Inland waters

pH

To be in the range of 6.5 – 8.5, change due to waste discharges not to exceed 0.2

Marine waters

To be in the range of 6.5 – 8.5

Water gathering ground subzones

To be in the range of 6.0 – 9.0

Inland waters

Salinity

Change due to waste discharges not to exceed 10% of ambient

Whole zone

Temperature

Change due to waste discharges not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by waste discharges and shall not affect aquatic communities

Marine waters

Change due to waste discharges not to exceed 20 mg/l of annual median

Water gathering ground subzones

Change due to waste discharges not to exceed 25 mg/l of annual median

Inland waters

Unionized ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionized form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg/l

Marine waters

Toxic substances

Should not attain such levels as to produce significant toxic effects in humans, fish or any other aquatic organisms

Whole zone

Waste discharges should not cause a risk to any beneficial use of the aquatic environment

Whole zone

E.coli Bacteria

Not exceed 610 per 100 ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary contact recreation subzones and fish culture subzones

Not exceed 180 per 100 ml, calculated as the geometric mean of all samples collected from March to October inclusive in 1 calendar year. Samples should be taken at least 3 times in 1 calendar month at intervals of between 3 and 14 days.

Bathing beach subzones




Less than 1 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days

Water gathering ground subzones

Not exceed 1000 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days

Inland waters

Colour

Change due to waste discharges not to exceed 30 Hazen units

Water gathering round

Change due to waste discharges not to exceed 50 Hazen units

Inland waters

Turbidity

Shall not reduce light transmission substantially from the normal level

Bathing beach subzones

 

Source:   Statement of Water Quality Objectives (Western Buffer Water Control Zone).

 

Table 5.3     Summary of Water Quality Objectives for Victoria Harbour WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l for 90% of samples

Marine waters

PH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by human activity

Marine waters

Unionised ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionised form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg/l

Marine waters

Toxic substances

Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

Human activity should not cause a risk to any beneficial use of the aquatic environment.

Whole zone

Source: Statement of Water Quality Objectives (Victoria Harbour (Phases One, Two and Three) Water Control Zone).

 

 

Table 5.4     Summary of Water Quality Objectives for Eastern Buffer WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l for 90% of samples

Marine waters excepting fish culture subzones

Not less than 5.0 mg/l for 90% of samples

Fish culture subzones

Not less than 4.0 mg/l

Water gathering ground subzone and other Inland waters

5-Bay biochemical oxygen demand (BOD5)

Change due to waste discharges not to exceed 3 mg/l

Water gathering ground subzones

Change due to waste discharges not to exceed 5 mg/l

Inland waters

Chemical oxygen demand (COD)

Change due to waste discharges not to exceed 15 mg/l

Water gathering ground subzones

Change due to waste discharges not to exceed 30 mg/l

Inland waters

PH

To be in the range of 6.5 – 8.5, change due to waste discharges not to exceed 0.2

Marine waters

To be in the range of 6.5 – 8.5

Water gathering ground subzones

To be in the range of 6.0 – 9.0

Inland waters

Salinity

Change due to waste discharges not to exceed 10% of ambient

Whole zone

Temperature

Change due to waste discharges not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by waste discharges and shall not affect aquatic communities

Marine waters

Change due to waste discharges not to exceed 20 mg/l of annual median

Water gathering ground subzones

Change due to waste discharges not to exceed 25 mg/l of annual median

Inland waters

Unionised ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionised form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg/l

Marine waters

Dangerous substances

Should not attain such levels as to produce significant toxic effects in humans, fish or any other aquatic organisms

Whole zone

Waste discharges should not cause a risk to any beneficial use of the aquatic environment

Whole zone

E.coli Bacteria

Not exceed 610 per 100 ml, calculated as the geometric mean of all samples collected in one calendar year

Fish culture subzones

Less than 1 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days

Water gathering ground subzones

Not exceed 1000 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days

Inland waters

Colour

Change due to waste discharges not to exceed 30 Hazen units

Water gathering ground

Change due to waste discharges not to exceed 50 Hazen units

Inland waters

Source:   Statement of Water Quality Objectives (Eastern Buffer Water Control Zone).

 

Table 5.5     Summary of Water Quality Objectives for Junk Bay WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l for 90% of samples

Marine waters excepting fish culture subzones

Not less than 5.0 mg/l for 90% of samples

Fish culture subzones

Not less than 4.0 mg/l

Inland waters

5-Bay biochemical oxygen demand (BOD5)

Change due to waste discharges not to exceed 5 mg/l

Inland waters

Chemical oxygen demand (COD)

Change due to waste discharges not to exceed 30 mg/l

Inland waters

pH

To be in the range of 6.5 - 8.5, change due to waste discharges not to exceed 0.2

Marine waters

To be in the range of 6.0 –9.0

Inland waters

Salinity

Change due to waste discharges not to exceed 10% of ambient

Whole zone

Temperature

Change due to waste discharges not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by waste discharges and shall not affect aquatic communities

Marine waters

Change due to waste discharges not to exceed 25 mg/l of annual median

Inland waters

Unionised ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionised form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.3 mg/l

Marine waters

Dangerous substances

Should not attain such levels as to produce significant toxic effects in humans, fish or any other aquatic organisms

Whole zone

Waste discharges should not cause a risk to any beneficial use of the aquatic environment

Whole zone

E.coli Bacteria

Not exceed 610 per 100 ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary contact recreation subzones and fish culture subzones

Not exceed 1000 per 100 ml, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days

Inland waters

Colour

Change due to waste discharges not to exceed 50 Hazen units

Inland waters

Source:   Statement of Water Quality Objectives (Junk Bay Water Control Zone).

 

Table 5.6     Summary of Water Quality Objectives for Southern WCZ

Parameters

Objectives

Sub-Zone

Offensive odour, tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/l for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/l for 90 % sample

Marine waters excepting fish culture subzones

Not less than 5.0 mg/l for 90% of samples

Fish culture subzones

Not less than 4.0 mg/l

Inland waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters excepting bathing beach subzones; Mui Wo (A), Mui Wo (B), Mui Wo (C), Mui Wo (E) and Mui Wo (F) subzones

To be in the range of 6.0 – 9.0

Mui Wo (D) sub-zone and other inland waters.

To be in the range of 6.0 –9.0 for 95% of samples, change due to human activity not to exceed 0.5

Bathing beach subzones

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by human activity

Marine waters

Change due to waste discharges not to exceed 20 mg/l of annual median

Mui Wo (A), Mui Wo (B), Mui Wo (C), Mui Wo (E) and Mui Wo (F) subzones

Change due to waste discharges not to exceed 25 mg/l of annual median

Mui Wo (D) subzone and other inland waters

Unionized ammonia (UIA)

Annual mean not to exceed 0.021 mg/l as unionized form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total inorganic nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.1 mg/l

Marine waters

E.coli Bacteria

Not exceed 610 per 100 ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary contact recreation subzones

and fish culture subzones

Not exceed 180 per 100 ml, calculated as the geometric mean of all samples collected from March to October inclusive in 1 calendar year. Samples should be taken at least 3 times in 1 calendar month at intervals of between 3 and 14 days.

Bathing beach subzones

5-Day biochemical oxygen demand (BOD5)

Change due to waste discharges not to exceed 5 mg/l

Inland waters

Chemical oxygen demand (COD)

Change due to waste discharges not to exceed 30 mg/l

Inland waters

Dangerous substances

Should not attain such levels as to produce significant toxic effects in humans, fish or any other aquatic organisms

Whole zone

Waste discharges should not cause a risk to any beneficial use of the aquatic environment

Whole zone

Source:   Statement of Water Quality Objectives (Southern Water Control Zone).

 

Technical Memorandum on Effluents Discharge Standard

5.14            Discharges of effluents are subject to control under the WPCO.  The Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) gives guidance on permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters). The limits control the physical, chemical and microbial quality of effluent.  Any sewage from the proposed construction and operation activities must comply with the standards for effluent discharged into the foul sewers, inshore waters and marine waters of the Victoria Harbour WCZ and Western Buffer WCZ, as given in the TM-DSS.

 

Water Supplies Department (WSD) Water Quality Criteria

5.15            Besides the WQO set under the WPCO, the WSD has specified a set of objectives for water quality at flushing water intakes as listed in Table 5.7

 

Table 5.7  WSD Standards at Flushing Water Intakes

Parameter (in mg/l unless otherwise stated)

WSD Target Limit

Colour (Hazen Unit)

< 20

Turbidity (NTU)

< 10

Threshold Odour Number (odour unit)

< 100

Ammoniacal Nitrogen

< 1

Suspended Solids

< 10

Dissolved Oxygen

> 2

Biochemical Oxygen Demand

< 10

Synthetic Detergents

< 5

E.coli (no. per 100 ml)

< 20000

 

Practice Note

5.16            A practice note for professional persons has been issued by the EPD to provide guidelines for handling and disposal of construction site discharges. The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with ten types of discharge from a construction site.  These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities.  Practices given in the ProPECC PN 1/94 should be followed as far as possible during construction to minimise the water quality impact due to construction site drainage.

 

EEFS Water Quality Criteria (WQC)

5.17            In addition to the statutory WQO stipulated under the WPCO, a set of water quality criteria (WQC) was established under the “Environmental and Engineering Feasibility Assessment Studies in relation to the Way Forward of the HATS (EEFS)”.

 

Background

5.18            The HATS is an overall sewage collection and treatment scheme for areas on both sides of Victoria Harbour. Stage 1 of HATS, fully commissioned in December 2001, collects sewage from the urban areas of Kowloon, Tsuen Wan, Kwai Tsing, Tseung Kwan O and the north-eastern part of Hong Kong Island and conveys it to SCISTW for CEPT treatment which has brought early water quality improvements especially in eastern Victoria Harbour, Eastern Buffer WCZ and Junk Bay WCZ.  As the population grows and with further development on both sides of the harbour, deterioration of water quality in Victoria Harbour may occur if the full HATS is not completed.

5.19            In 2004, the Government of the Hong Kong SAR completed trials and studies on environmental impacts and engineering feasibility to assist in deciding the best way forward for the remaining stages of HATS.  Detailed marine water quality, ecological and fisheries assessment was performed as part of the EEFS with the objective of assessing the potential impacts of different treatment and disposal scheme proposed for the remaining stages of HATS and the associated construction activities.  The recommended option for HATS Stage 2 is to convey all sewage from the harbour area to SCISTW for centralized treatment.  The EEFS recommended that biological treatment plus disinfection should be provided for the HATS on a long-term basis. The marine water quality, ecological and fisheries assessment conducted as part of the EEFS followed the guidelines set forth in the EIAO-TM.  The potential water quality impacts were quantitatively assessed using various WQC outlined for the EEFS with a further qualitative assessment based on the collective professional opinion of a team of local and international experts in marine sciences and water quality management.

5.20            Setting of WQC has been recognized from the start of the EEFS as a key to assessing the acceptability and performance of different HATS options.  In support of criteria setting, an extensive public consultation exercise on the proposed WQC for HATS was conducted in 2002 as part of the EEFS.  These WQC were based on the statutory WQO stipulated under the WPCO, originally developed in the late 1980’s, and further refined by the consultant of the EEFS using the results of the Environmental Impact Assessment of the Strategic Sewage Disposal Scheme (SSDS EIA) and other recently completed studies.  The set of HATS specific WQC, developed as a part of the EEFS, has integrated the concerns of various interested stakeholders and the general public through a presentation and briefing with the Advisory Council on the Environment and the Monitoring Group for HATS, public view-sharing workshops and receipt of public comments. 

5.21            The findings of this consultation exercise and a full set of the proposed final WQC are documented in the “Report on Community Consultation for the Proposed Water Quality Criteria (October 2002)” prepared under the EEFS.  

 

Water Quality Criteria (WQC)

5.22            The WQC of relevant parameters for far field and near field impact assessment are shown in Table 5.8a and Table 5.8b respectively. The far field water quality impact assessment and far field modelling to be performed under this EIA will cover the North Western, Western Buffer, Victoria Harbour, Eastern Buffer, Junk Bay and Southern WCZ as well as the adjacent outer water to take into account all the major pollution sources (including Pearl River) that may have a bearing on the environmental acceptability of the Project as required by the EIA Study Brief.  The near field impact assessment will also be conducted by mathematical modelling to simulate the characteristics of the sewage plume in the vicinity of the submarine outfall to determine the zone of initial dilution (ZID), plume dimensions, rise height, merging and trapping in various flow and ambient conditions.  Details of the near field modelling are provided in Appendix 5.1.

5.23            Relevant WQC were derived under the EEFS for Western Buffer, Eastern Buffer, Junk Bay, Southern and Victoria Harbour WCZ. Different WQC were provided for different zones or locations to protect marine resources and uses of the water bodies.  EEFS did not derive WQC for the North Western WCZ.  Various marine resources and water sensitive uses identified within the Study Area are shown in Figure 5.1. .

 

Table 5.8a    Reference Marine Water Quality Criteria at Edge of Mixing Zone (1) for Far Field Water Quality Assessment

Parameter

Value

Type / Period

Applicable Zones / Uses (2)

E.coli

≤ 180/100ml

Geometric mean

Bathing waters

≤ 610/100ml

Geometric mean

Secondary contact recreation zones and mariculture zones

≤ 20,000/100ml

90% of occasions

Sea water intakes for flushing and industrial use

Dissolved oxygen (DO)

≥ 4 mg/l (water column average)

90% of occasions

Western Buffer, Eastern Buffer, Junk Bay and Victoria Harbour WCZ (except mariculture zones and fish spawning ground) (Figure 5.1)

≥ 2  mg/l

at all times

All WCZ (except mariculture zones)

≥ 5 mg/l (water column average)

Monthly average

Southern WCZ and fish spawning ground (Figure 5.1)

≥ 5 mg/l (water column average)

90% of occasions

Mariculture zones only

≥ 2 mg/l (bottom DO within 2 m from the seabed)

90% of occasions

Mariculture zones only

Total residual chlorine (TRC)

≤ 0.008 mg/l

Daily maximum

All WCZ

Chronic toxicity

≤ one chronic toxicity unit (TUc), (derived from NOEC values based on whole effluent toxicity tests) (3)

4-day average chronic toxicity exposure

All WCZ

(Source: EEFS Report on Community Consultation for the Proposed Water Quality Criteria)

(1) A mixing zone is defined as an impact zone of an effluent discharge where water quality criteria can be exceeded as long as acute toxicity criteria are met.

(2) North Western WCZ (which is within the Study Area for this EIA) was not considered under the EEFS in deriving the WQC.

(3) USEPA Technical Support Document for Water Quality-Based Toxics Control (March 1991), from which one chronic Toxicity Unit (TUc) is defined TUc = 100/NOEC, where NOEC = % of effluent which gives no observed effect on the most sensitive of the range of species tested.

 

Table 5.8b Reference Marine Water Quality Criteria for Near Field Water Quality Assessment

Parameter

Value

Type / Period

Applicable Zones / Uses

Total residual chlorine (TRC)

≤ 0.013 mg/l

Daily Maximum

At edge of ZID (1)

Acute Toxicity

0.3 acute toxicity units (TUa) (derived from LC50 values based on whole effluent toxicity tests) (2)

One hour average condition not to exceed this value

At edge of ZID (1)

(Source: EEFS Report on Community Consultation for the Proposed Water Quality Criteria)

(1) For a surface plume, initial dilution is defined as the dilution obtained at the centre line of the plume when the sewage reaches the surface.  For a trapped plume, initial dilution is defined as the dilution obtained at the center line of the plume where the plume reaches the maximum rise height when the vertical momentum / buoyancy of the plume becomes zero.

(2) USEPA Technical Support Document for Water Quality-Based Toxics Control (March 1991), from which one acute Toxicity Unit (TUa) is defined as TUa = 100/LC50, where LC50 = % of effluent which gives 50% survival of the most sensitive of the range of species tested.

5.24            TRC has been recognised as potentially toxic to aquatic lives and is therefore considered for both near field and far field modelling, whereas E.coli, DO and CBP are considered in the far field modelling only.  The chronic and acute toxicity criteria were used to assess the toxicity of the sewage effluent with reference to the results of the whole effluent toxicity test (WETT).  Details of the WETT results are given in Sections 5.162 to 5.166.

Assessment Criteria for CBP

5.25            Based on a CBP selection exercise conducted under this EIA, 34 CBP compounds were identified for impact assessment.  The CBP selection process is described in Appendix 6.1.  Water quality criteria/standards of USA (federal and state level), United Kingdom, Canada, Australia and China were reviewed for the 34 selected CBP compounds.  Criteria/standards for 13 CBP were not found in this review.  For the CBP with available criteria/standards, the following rules were adopted to derive the water quality assessment criteria:

 

·   Rule 1: Criteria from Hong Kong are adopted when available and suitable

·   Rule 2: Criteria/standards for protection of marine water/saltwater biota are preferred to that of freshwater or that without clear specification (e.g. protection of aquatic environment)

·   Rule 3: Chronic criteria/standards specified with averaging time period are preferred and adopted whenever possible.   

·   Rule 4: National criteria/standards are preferred to local criteria/standards

·   Rule 5: If more than one criteria/standards for the same chemical of concern (COC) satisfy the above rules, then criterion/standard with the lower value would be adopted to provide conservatism

5.26            The relevant CBP criteria/standards reviewed are provided in Annex B.  A summary of the adopted values are given in Table 5.9a below.

 

Assessment Criteria for this Water Quality Impact Assessment

5.27            As discussed in Sections 5.5 and 5.6, water quality parameters of concern include dissolved oxygen (DO), E.coli, TRC and toxicity.  It is considered that criteria from Hong Kong should be adopted when available and suitable. Statutory standards for DO and E.coli are available in Hong Kong under the WPCO. Relevant standards and guidelines for DO and E.coli are also available locally from the WSD and the EEFS.  The assessment criteria for DO and E.coli chosen for the current EIA are based on the review of the standards available from the WPCO, the WSD and the EEFS. For the parameter having more than one standard from the information reviewed, the most stringent standard would be adopted as the assessment criterion for conservative assessment.

5.28            For TRC and toxicity, no statutory requirement for marine water is available in Hong Kong.  The TRC and toxicity standards adopted in this EIA are the assessment criteria derived under the EEFS study. The TRC and toxicity criteria derived under the EEFS study are based on the collective professional opinion of a team of local and international experts in marine sciences and water quality management and were established via an extensive public consultation exercise and are therefore suitable for use in this EIA.

5.29            The assessment criteria for CBP are based on the literature search conducted under this EIA as described in Section 5.25.  The adopted marine water quality criteria for far field and near field modelling are shown in Table 5.9a and Table 5.9b respectively. Results of the near field modelling are given in Appendix 5-1.

 

Table 5.9a     Proposed Marine Water Quality Criteria for Far Field Water Quality Assessment

Parameter

Value

Type / Period

Applicable Zones / Uses

Source

E.coli

180 per 100 m1

Geometric mean for the period from March to October

Bathing beach subzones only

WPCO

610 per 100 ml

Annual geometric mean

Secondary contact recreation subzones and fish culture subzones only

WPCO

20000 per 100 ml

Maximum value

WSD flushing water intakes only

WSD criteria 1

Depth Averaged DO

4 mg/l

90 percentile

All WCZ of concern except Southern WCZ and fish spawning ground (shown in Figure 5.2) and fish culture subzones.

WPCO / EEFS

≥ 5 mg/l

90 percentile

Fish culture subzones

WPCO / EEFS

≥ 5 mg/l

Monthly average

Southern WCZ and Fish spawning ground (Figure 5.2)

EEFS

Bottom DO within 2 m from the seabed

≥ 2 mg/l

90 percentile

All WCZ of concern

WPCO / EEFS

DO at any depth

≥ 2 mg/l

Minimum concentrations

All WCZ of concern

EEFS

TRC

0.008 mg/l

Daily maximum

All WCZ of concern

EEFS

Chronic toxicity

1 chronic toxicity unit (TUc), (derived from NOEC values based on whole effluent toxicity tests) 2

4-day average chronic toxicity exposure

All WCZ of concern

EEFS

Chlorination By-products:

Four Specific Compounds of Trihalomethanes (THM):

Bromodichloromethane

22µg/L

Annual average

Marine water

See Note a

Bromoform

360µg/L

Annual average

Marine water

See Note a

Chloroform

12µg/L

Annual average

Marine water

See Note b

Dibromochloromethane

34µg/L

Annual average

Marine water

See Note a

Five Specific Compounds of Haloacetic Acids (HAA):

Bromoacetic acid

See Note 3

-

-

-

Chloroacetic acid

See Note 3

-

-

-

Dibromoacetic acid

See Note 3

-

-

-

Dichloroacetic acid

See Note 3

-

-

-

Trichloroacetic acid

See Note 3

-

-

-

Other CBP Compounds:

Methylene chloride

1580µg/L

Annual average

Marine water

See Note a

Carbon tetrachloride

12µg/L

Annual average

Marine water

See Note b

Chlorobenzene

25µg/L 

Not specified

Marine water

See Note c

1,1-dichloroethane

See Note 3

-

-

-

1,2-dichloroethane

10µg/L 

Annual average

Marine water

See Note b

1,1-dichloroethylene

3.2µg/L

Annual average

Marine water

See Note a

1,2-dichloropropane

See Note 3

-

-

-

Tetrachloroethylene

8.85µg/L 

Annual average

Marine water

See Note a

1,1,1-trichloroethane

100µg/L 

Annual average

Marine water

See Note b

1,1,2-trichloroethane

100µg/L 

Annual average

Marine water

See Note b

Trichloroethylene

10µg/L 

Annual average

Marine water

See Note b

2-chlorophenol

50µg/L 

Annual average

Marine water

See Note b

2,4-dichlorophenol

20µg/L

Annual average

Marine water

See Note b

p-chloro-m-cresol

40µg/L 

Annual average

Marine water

See Note b

Pentachlorophenol

7.9µg/L

4-day average

Marine water

See Note d

2,4,6-trichlorophenol

See Note 3

-

-

-

Bis(2-chloroethoxy)methane

See Note 3

-

-

-

1,4-dichlorobenzene

See Note 3

-

-

-

Hexachlorobenzene

0.03µg/L 

Annual average

Marine water

See Note b

Hexachlorocyclopentadiene

See Note 3

-

-

-

Hexachloroethane

See Note 3

-

-

-

1,2,4-trichlorobenzene

5.4µg/L

Not specified

Marine water

See Note c

Alpha-BHC

See Note 3

-

-

-

Beta-BHC

0.046µg/L

Annual average

Marine water

See Note a

Gamma-BHC

0.063µg/L 

Annual average

Marine water

See Note a

Notes:

1 The E.coli criterion set out by WSD for flushing water intakes is <20,000 per 100 ml at any time.  The E.coli criterion developed under the EEFS for flushing water intake is <20,000 per 100 ml for 90% of samples.  The more stringent WSD standard was used as the assessment criterion.

2   USEPA Technical Support Document for Water Quality-Based Toxics Control (March 1991), from which one chronic Toxicity Unit (TUc) is defined TUc = 100/NOEC, where NOEC = % of effluent which gives no observed effect on the most sensitive of the range of species tested.

3   No criteria/standard was found from literature review (refer to Section 5.25).

a USEPA. www.epa.gov/waterscience/standards/states

b Cole S., Codline I. D., Parr W. and Zabel T. (1999).  Guidelines for Managing Water Quality Impacts within UK European Marine Sites. Prepared by WRc Swindon Frankland Road Blagrove Swindon Wiltshire SN5 8YF for the UK Marine SCA Project

c The Canadian Council of Ministers of the Environment (2005).

d USEPA (2004).

 

Table 5.9b     Proposed Marine Water Quality Criteria for Near Field Water Quality Assessment

Parameter

Value

Type / Period

Applicable Zones / Uses

Source

TRC

<=0.013 mg/l

Daily maximum

At edge of initial dilution zones

EEFS

Acute Toxicity

0.3 acute toxicity units (TUa) (derived from LC50 values based on whole effluent toxicity tests) 1

One hour average condition not to exceed this value

At edge of initial dilution zones

EEFS

Notes:

1 USEPA Technical Support Document for Water Quality-Based Toxics Control (March 1991), from which one acute Toxicity Unit (TUa) is defined as TUa = 100/LC50, where LC50 = % of effluent which gives 50% survival of the most sensitive of the range of species tested.

Description of the Environment

 

EPD Marine Water Quality Monitoring Data

5.30            The marine water quality monitoring data routinely collected by EPD were used to establish the baseline conditions for E.coli and DO. A summary of water quality data for selected EPD monitoring stations is presented in Table 5.10 to Table 5.14 for North Western WCZ (NM1-NM3, NM5-NM6 and NM8), Western Buffer WCZ (WM2-WM4), Victoria Harbour WCZ (VM1 VM2, VM4-VM8, VM12, VM14, VM15), Eastern Buffer WCZ (EM1, EM2), Junk Bay WCZ (JM3, JM4) and Southern WCZ (SM7, SM9, SM10, SM11).  Locations of the monitoring stations are shown in Figure 5.1.  As the HATS Stage I was commissioned in late 2001, the data shown in Table 5.10 to Table 5.14 represent the situation after the commissioning of HATS Stage I.  The relevant WQO are also included in Table 5.10 to Table 5.14 for comparison.  WQO for E.coli is only applicable to stations SM10 and SM11 because only these two selected stations are located in secondary contact recreation subzones. Descriptions of the baseline conditions for individual WCZ provided in the subsequent sections are based on the information extracted from the EPD’s report “20 years of Marine Water Quality Monitoring in Hong Kong” which contains the latest information published by EPD on marine water quality at the moment of preparing the EIA report.

 

North Western WCZ

5.31            The mean E.coli counts in 2005 ranged from 60 per 100 ml at stations NM6 and NM8 (near Chek Lap Kok) to 1400 per 100 ml at station NM1 in Lantau North.  The mean DO levels were above 5 mg/l at all stations.  In 2005, stations NM3, NM5 and NM6 experienced an increase of E.coli bacteria, NM1,  NM2 and NM8 showed some decreases as compared to the 2004 condition. The increase in E.coli bacteria on the western side (NM3, NM5 and NM6) could be influenced by the sewage outfall at Black Point, which discharged increasing flows from the San Wai Sewage Treatment Works.  The water quality in the North Western WCZ is also heavily influenced by the Pearl River flow. All stations complied with the WQO for DO (Table 5.10).

 

Western Buffer WCZ

5.32            Full compliance with the WQO for DO was achieved in the Western Buffer WCZ in 2005.  The water quality in this WCZ in 2005 was largely stable as compared to that in 2004 except that there were some increases of E.coli at WM3.  The increase in the E.coli levels in the central area (WM3) may be related to the increased discharges from the SCISTW. The mean E.coli counts for stations WM2, WM3 and WM4 were 1500, 4500 and 1500 per 100 ml respectively. The mean DO values recorded in 2005 were 5.5 mg/l (Table 5.11).

 

Victoria Harbour WCZ

5.33            The marked improvements in eastern Victoria Harbour (VM1 and VM2) and moderate improvements in the mid harbour area (VM4 and VM5) and northern part of Rambler Channel (VM14) since HATS Stage 1 was commissioned were generally sustained in 2005. Full compliance with the WQO for DO was achieved in 2005. All the mean DO values recorded in 2004 were 5.3 mg/l.  The E.coli counts in the WCZ in 2004 were lower at the eastern end (VM1 and VM2) (ranging 640-1600 per 100 ml) and higher in the middle (VM5-VM7) and the western parts (VM12, VM14, VM15) of the harbour (5700-9100 per 100 ml and 2100-5400 per 100 ml respectively) (see Table 5.12).

 

Junk Bay WCZ

5.34            The water quality at Junk Bay was stable and improvements since HATS Stage 1 were sustained in 2005. A slight increase of E.coli (67 and 100 per 100 ml at stations JM3 and JM4 respectively) was observed as compared to the 2004 condition. All the mean DO values were 5.6 mg/l. Full compliance with the WQO for DO was achieved in 2005 (Table 5.13).

 

Eastern Buffer WCZ

5.35            The DO level in this WCZ in 2005 slightly decreased from that in 2004.  All the mean DO values recorded in 2005 were 5.7 mg/l.  The mean E.coli levels (130 and 36 per 100 ml at EM1 and EM2 respectively) were low. Full compliance with the WQO for DO was achieved in 2005 (Table 5.13). 

 

Southern WCZ

5.36            For Southern WCZ, only four stations (SM7, SM9, SM10 and SM11) closest to the SCISTW outfall were selected for presentation in Table 5.14. The mean DO level in 2005 was higher than than 5.9 mg/l. The level of sewage bacteria in 2005 was generally low, similar to that in 2004. The highest E.coli count (260 per 100 ml) was found at station SM9 close to the SCISTW outfall and was likely to be impacted by the discharge. Full compliance with the WQO for DO was achieved at all the selected stations.   The mean E.coli levels at stations SM10 and SM11 (located in the secondary contact subzone) also complied with the WQO in 2005.

 


Table 5.10      Baseline Water Quality Condition for North Western WCZ in 2005

Parameter

Lantau Island (North)

Pearl Island

Pillar Point

Urmston Road

Chek Lap Kok

WPCO WQO (in marine waters)

EEFS WQC (in marine waters)

NM1

NM2

NM3

NM5

NM6

NM8

Dissolved Oxygen  (DO)

(mg/l)

Depth average

5.9

(3.7 - 7.2)

6.4

(4.8 - 7.6)

6.2

(4.1 - 7.5)

6.1

(4.1 - 7.4)

6.7

(4.1 - 9.1)

6.9

(5.1 - 8.8)

Not less than 4 mg/l for 90% of the samples

Not available

Bottom

5.5

(2.3 - 7.2)

6.1

(4.0 - 7.3)

5.9

(3.2 - 7.2)

5.8

(3.3 - 7.3)

6.5

(3.3 - 8.6)

6.6

(3.6 - 8.5)

Not less than 2 mg/l for 90% of the samples

Not available

Dissolved Oxygen (DO) (% Saturation)

Depth average

81

(52 - 102)

88

(68 - 108)

86

(58 - 107)

84

(58 - 103)

92

(66 - 123)

94

(71 - 119)

Not available

Not available

Bottom

77

(33 - 99)

84

(57 - 109)

82

(46 - 107)

79

(47 - 101)

89

(47 - 117)

91

(51 - 116)

Not available

Not available

E.coli

(cfu per 100 ml)

700

(80 - 7200)

370

(98 - 1800)

460

(140 - 1400)

740

(380 - 1500)

55

(10 - 510)

2

(1 - 25)

Not available

Not available

Note:                   1. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2. Data presented are annual arithmetic means of depth-averaged results except for the E. coli values that are annual geometric means.

3. Data in brackets indicate the ranges.

 

Table 5.11      Baseline Water Quality Condition for Western Buffer WCZ in 2005

Parameter

Hong Kong Island (West)

Tsing Yi (South)

Tsing Yi (West)

WPCO WQO (in marine waters)

EEFS WQC (in marine waters)

WM2

WM3

WM4

Dissolved Oxygen (DO)

(mg/l)

Depth average

6.0

(4.8 - 7.3)

5.7

(3.9 - 6.9)

5.6

(3.1 - 6.8)

Not less than 4 mg/l for 90% of the samples

Not less than 4mg/l for 90% of the samples/

Not less than 2 mg/l at all times at any water depth

Bottom

5.9

(3.3 - 7.1)

5.7

(2.8 - 7.1)

5.5

(2.3 - 6.7)

Not less than 2 mg/l for 90% of the samples

Not less than 2 mg/l at all times at any water depth

Dissolved Oxygen (DO) (% Saturation)

Depth average

84

(68 - 108)

80

(55 - 104)

78

(43 - 100)

Not available

Not available

Bottom

82

(47 - 103)

79

(40 - 107)

76

(33 - 93)

Not available

Not available

E coli

(cfu per 100 ml)

1500

(170 - 9700)

4500

(450 - 23000)

1500

(360 - 6800)

Not available

Not available

Note:                   1. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2. Data presented are annual arithmetic means of depth-averaged results except for the E. coli values that are annual geometric means.

3. Data in brackets indicate the ranges.

 

 

 

Table 5.12      Baseline Water Quality Condition for Victoria Harbour WCZ in 2005

Parameter

Victoria Harbour East

Victoria Harbour Central

Victoria Harbour West

Stonecutters Island

Rambler Channel

WPCO WQO (in marine waters)

EEFS WQC (in marine waters)

VM1

VM2

VM4

VM5

VM6

VM7

VM8

VM15

VM12

VM14

Dissolved Oxygen (DO) (% Saturation)

Depth average

5.7

(4.2 - 6.9)

5.6

(4.4 - 6.8)

5.4

(4.4 - 6.6)

5.5

(4.7 - 6.6)

5.5

(4.8 - 6.5)

5.6

(4.9 - 6.6)

5.8

(4.3 - 7.1)

5.5

(4.5 - 7.0)

5.4

(3.8 - 6.4)

5.7

(4.8 - 6.9)

Not available

Not available

Bottom

5.6

(3.3 - 6.9)

5.6

(3.8 - 6.8)

5.3

(3.6 - 6.5)

5.3

(3.3 - 6.6)

5.3

(3.2 - 6.5)

5.4

(3.8 - 6.5)

5.6

(2.5 - 7.1)

5.3

(3.1 - 6.7)

5.3

(2.9 - 6.2)

5.6

(3.7 - 6.9)

Not available

Not available

Dissolved Oxygen (DO)

(mg/l)

Depth average

79

(59 - 94)

78

(66 - 92)

75

(63 - 88)

76

(68 - 99)

77

(68 - 96)

78

(72 - 99)

80

(61 - 108)

77

(64 - 105)

75

(54 - 94)

80

(68 - 105)

Not less than 4 mg/l for 90% of the samples

Not less than 4mg/l for 90% of the samples/

Not less than 2 mg/l at all times at any water depth

Bottom

78

(46 - 93)

77

(54 - 90)

74

(51 - 88)

74

(46 - 99)

73

(45 - 94)

75

(54 - 94)

78

(35 - 108)

74

(43 - 101)

74

(42 - 92)

79

(52 - 103)

Not less than 2 mg/l for 90% of the samples

Not less than 2 mg/l at all times at any water depth

E coli

(cfu per 100 ml)

640

(88 - 4500)

1600

(120 - 31000)

2400

(310 - 11000)

7700

(2500 - 23000)

5700

(1200 - 33000)

9100

(1200 - 35000)

4900

(790 - 40000)

5400

(490 - 22000)

4000

(1200 - 17000)

2100

(520 - 8700)

Not available

Not available

Note:                   1. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2. Data presented are annual arithmetic means of depth-averaged results except for the E. coli values that are annual geometric means.

3. Data in brackets indicate the ranges.

 

Table 5.13      Baseline Water Quality Condition for Junk Bay and Eastern Buffer WCZ in 2005

Parameter

Junk Bay WCZ

Eastern Buffer WCZ

JM3

JM4

WPCO WQO (in marine waters)

EEFS WQC (in marine waters)

EM1

EM2

WPCO WQO (in marine waters)

EEFS WQC (in marine waters)

Dissolved Oxygen (DO) (% Saturation)

Depth average

5.9

(3.7 - 7.0)

5.8

(4.0 - 7.2)

Not available

Not available

5.7

(4.3 - 6.8)

6.0

(4.7 - 7.2)

Not available

Not available

Bottom

5.7

(3.2 - 6.9)

5.6

(3.6 - 7.1)

Not available

Not available

5.7

(3.7 - 6.8)

5.9

(3.6 - 7.1)

Not available

Not available

Dissolved Oxygen (DO)

(mg/l)

Depth average

83

(53 - 101)

81

(56 - 95)

Not less than 4 mg/l for 90% of the samples

Not less than 4 mg/l for 90% of the samples

80

(64 - 97)

84

(68 - 109)

Not less than 4 mg/l for 90% of the samples

Not less than 4mg/l for 90% of the samples/

Not less than 2 mg/l at all times at any water depth

Bottom

79

(45 - 96)

78

(50 - 96)

Not less than 2 mg/l for 90% of the samples

Not less than 2 mg/l at all times

79

(51 - 98)

82

(51 - 101)

Not less than 2 mg/l for 90% of the samples

Not less than 2 mg/l at all times at any water depth

E coli

(cfu per 100 ml)

67

(15 - 7100)

100

(23 - 550)

Not available

Not available

130

(29 - 1300)

36

(2 - 1800)

Not available

Not available

Note:                   1. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2. Data presented are annual arithmetic means of depth-averaged results except for the E. coli values that are annual geometric means.

3. Data in brackets indicate the ranges.

 

Table 5.14              Baseline Water Quality Condition for Southern WCZ in 2005

Parameter

West Lamma Channel

Lantau Island (East)

WPCO WQO (in marine waters)

EEFS WQC (in marine waters)

SM7

SM9

SM10

SM11

Dissolved Oxygen (DO)

(mg/l)

Depth average

6.5

(4.7 - 8.6)

6.1

(4.3 - 7.3)

7.2

(5.5 - 9.1)

7.1

(4.5 - 9.7)

Not less than 4 mg/l for 90% of the samples

Not less than 5 mg/l for monthly average/

Not less than 2 mg/l at all times at any water depth

Bottom

6.3

(4.3 - 8.4)

5.9

(3.5 - 7.4)

7.1

(5.2 - 9.1)

6.7

(2.6 - 9.2)

Not less than 2 mg/l for 90% of the samples

Not less than 2 mg/l at all times at any water depth

Dissolved Oxygen (DO) (% Saturation)

Depth average

91

(67 - 118)

84

(60 - 101)

101

(78 - 129)

99

(65 - 137)

Not available

Not available

Bottom

88

(61 - 115)

82

(50 - 99)

98

(73 - 128)

92

(37 - 129)

Not available

Not available

E coli

(cfu per 100 ml)

69

(1 - 1200)

260

(3 - 3400)

9

(1 - 180)

10

(1 - 120)

Not more than 610 per 100 ml for annual geometric mean (applicable to SM10 and SM11 only)

Not available

Note:                   1. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2. Data presented are annual arithmetic means of depth-averaged results except for the E. coli values that are annual geometric means.

3. Data in brackets indicate the ranges.

 

.


Long Term Trends of E.coli Levels

5.37            The 20-year long term monitoring data showed that the level of E.coli in the Southern WCZ has remained low and stable.  For North Western WCZ, considerable long-term increases of E.coli were observed at NM1 and NM5 during 1988-2005.  The former may be related to pollution in Victoria Harbour and other discharges around Castle Peak Road, while the latter to effluents discharged from the San Wai Sewage Treatment Works and Pillar Point Sewage Treatment Works. Based on EPD’s long term monitoring data, the E.coli levels at NM1 appeared to increase after commissioning of HATS Stage 1 in 2001.

5.38            Increasing trends of E.coli levels were observed in the eastern and central Victoria Harbour before the implementation of HATS Stage 1 in late 2001.  After the implementation of HATS Stage 1 in late 2001, the increasing trends of E.coli formerly observed in the Victoria Harbour ceased.  The reduction of sewage related bacteria in the last few years was also evident in Eastern Buffer WCZ and Junk Bay WCZ after the implementation of HATS Stage 1 in late 2001.

5.39            For Western Buffer WCZ, considerable increases of sewage bacteria were observed in central and northern part of the WCZ (i.e. stations WM2, WM3 and WM4) since 2001.  The increases in the E.coli levels at WM2, WM3 and WM4 were probably caused by the effluent discharged from the SCISTW under HATS Stage 1 which was implemented in late 2001. 

 

HATS Survey Data

5.40            Two marine water sampling events were conducted under the Minor Works Contract ([2]) in December 2004 and May 2005 respectively to collect marine water samples for chemical analysis of nine CBP compounds (namely bromoform, chloroform, bromodichloromethane, dibromochloromethane, bromoacetic acid, chloroacetic acid, dibromoacetic acid, dichloroacetic acid and trichloroacetic acid). During each sampling event, replicate depth-integrated samples (composite of samples from near-surface, mid-depth and near-bottom) were collected at two marine stations, one near the existing outfall of SCISTW, namely SCI-1, and one at EPD’s monitoring station, namely SM18, in Southern WCZ. Locations of these monitoring stations are shown in Figure 5.1.

5.41            In February 2006, triplicate depth-integrated samples were collected at SCI-1 and SM18 under this EIA for laboratory analysis of TRC and the other 25 identified CBP compounds. 

5.42            Total (soluble plus insoluble) concentrations of CBP were measured in the marine water samples. Table 5.15 shows the maximum values measured in the samples.  All the maximum levels were below the detention limits except for methylene chloride where its maximum level measured at station SM18 was 55 mg/l. No reason can be offered to explain the detection of methylene chloride at Station SM18.  It should be noted that the chemical analysis was conducted by a HOKLAS accredited laboratory.  Also, methylene chloride was detected in all three water samples collected at SM18, with satisfactory QA/QC results. 

 

Table 5.15            Maximum Ambient Levels for TRC and CBP

Parameters

Station SCI-1 (mg/L)

Station SM18 (mg/L)

Total residual chlorine

<20

<20

Bromoform

<5

<5

Bromodichloromethane

<5

<5

Chloroform

<5

<5

Dibromochloromethane

<5

<5

Bromacetic acid

<2

<2

Chloroacetic acid

<2

<2

Dibromoacetic acid

<2

<2

Dichloroacetic acid

<2

<2

Trichlroacetic acid

<2

<2

Methylene chloride

<20

55

Carbon tetrachloride

<0.5

<0.5

Chlorobenzene

<0.5

<0.5

1,1-dichloroethane

<0.5

<0.5

1,2-dichloroethane

<0.5

<0.5

1,1-dichloroethylene

<0.5

<0.5

1,2-dichloropropane

<0.5

<0.5

Tetrachloroethylene

<0.5

<0.5

1,1,1-trichloroethane

<0.5

<0.5

1,1,2-trichloroethane

<0.5

<0.5

Trichloroethylene

<0.5

<0.5

2-chlorophenol

<0.5

<0.5

2,4-dichlorophenol

<0.5

<0.5

p-chloro-m-cresol

<0.5

<0.5

Pentachlorophenol

<2.5

<2.5

2,4,6-trichlorophenol

<0.5

<0.5

Bis(2-chloroethoxy)methane

<0.5

<0.5

1,4-dichlorobenzene

<0.5

<0.5

Hexachlorobenzene

<0.5

<0.5

Hexachlorocyclopentadiene

<2.5

<2.5

Hexachloroethane

<0.5

<0.5

1,2,4-trichlorobenzene

<0.5

<0.5

Alpha-BHC

<0.5

<0.5

Beta-BHC

<1

<1

Gamma-BHC

<1

<1

 

Beach Water Quality Monitoring Data

5.43            Although other bacteria may be present in the marine water, the WQO for bathing beaches focuses on E.coli bacteria because these have been proved to provide the best correlation with the illness rates associated with swimming (specifically skin and gastrointestinal illnesses). The E.coli data routinely collected by EPD were used to establish the baseline condition for the eight beaches in Tsuen Wan District. During the bathing/wet seasons (March to October), all gazetted beaches are monitored by EPD at least three times per month. The interval between the sampling occasions is maintained at 3 to 14 days. During non-bathing/dry seasons, gazetted beaches which remain open throughout the year are still monitored at least three times per month. During each beach monitoring visit, beach water samples are collected where the water depth is between thigh to waist depth i.e. about 0.6 to 1 metre depth for analysis of E. coli bacteria. The annual trends of geometric mean E.coli levels measured at the beaches provided in the EPD’s publication “20 years of Beach Water Quality Monitoring in Hong Kong” (which is the latest beach water quality report published by EPD at the time of the moment of preparing the EIA report) are presented in Table 5.16.  Locations of the beaches are shown in Figure 5.3. As the HATS Stage I was commissioned in late 2001, the data shown in Table 5.16 cover the periods both before and after the commissioning of HATS Stage I.

 

Table 5.16            Annual Trend of E.coli Levels at Tsuen Wan Beaches

Beach

Pre-HATS Stage 1

 

Post-HATS Stage 1

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

Geometric Mean E.coli (per 100 ml)

WQO: 180

Anglers'

636

(8-6900)

691

(27-9100)

502

(26-6100)

442

(17-7000)

326

(15-4600)

621

(16-6000)

1169

(38-15000)

693

(23-8100)

619

(32-5100)

895

(55-6600)

Approach

1164

(130-9800)

1009

(50-9500)

435

(94-3100)

387

(52-3400)

316

(12-4700)

411

(55-3200)

696

(17-6100)

762

(61-6300)

470

(18-2400)

663

(68-8200)

Casam

483

(30-5000)

609

(53-15000)

239

(10-1800)

231

(10-7400)

209

(27-5500)

233

(10-1900)

741

(16-12000)

702

(26-4900)

594

(11-3600)

716

(17-4100)

Gemini

512

(30-7400)

458

(28-3500)

399

(10-8900)

350

(58-4200)

258

(17-3700)

323

(11-3300)

1155

(38-12000)

875

(80-6500)

1102

(23-9000)

1042

(27-19000)

Hoi Mei Wan

373

(67-2000)

471

(28-10000)

280

(14-1700)

109

(5-870)

177

(10-2900)

199

(9-1400)

547

(12-6900)

442

(11-3800)

287

(6-4700)

641

(54-5200)

Lido

537

(23-2700)

600

(71-8100)

262

(10-2300)

231

(15-5400)

181

(19-4400)

269

(24-1500)

683

(29-4400)

734

(28-6100)

523

(27-6000)

782

(30-15000)

Ma Wan

59

(4-630)

110

(1-1300)

92

(2-3300)

51

(1-560)

39

(1-840)

133

(6-1800)

201

(2-3200)

159

(4-5300)

101

(1-5200)

132

(1-5200)

Ting Kau

2096

(100-7900)

1583

(55-16000)

1045

(130-5500)

515

(40-3500)

593

(46-7300)

739

(76-7000)

742

(6-6700)

831

(40-6300)

412

(27-5700)

512

(35-4700)

Notes:

Shaded cell - the geometric mean value exceeded the WQO

Data in brackets indicate the ranges

5.44            Of the eight beaches in the Tsuen Wan District, seven did not meet the WQO for bathing beaches and remained closed in 2005.  The pollution at Tsuen Wan beaches was partly caused by the discharge of sewage from squatter areas and other developments lacking adequate sewage facilities in the rural areas of Sham Tseng as well as the influence from the polluted marine water from the Rambler Channel due to the expedient connections, misconnections and polluted surface runoff from the dense urban areas in Tsuen Wan, Kwai Chung and Tsing Yi Districts.  The extension of the public sewer and connection of unsewered villages along Castle Peak Road (behind many of the Tsuen Wan beaches) is still on-going.  Water quality problems along the Tsuen Wan coastline has been further affected by undisinfected effluent discharged from SCISTW since the commissinong of HATS Stage 1 in late 2001.  Although Stage 1 of the Harbour Area Treatment Scheme (HATS) has brought about substantial water quality improvements to the Victoria Harbour, it has also concentrated the discharge of 1.4 million m3 per day of un-disinfected effluent from previously (pre-HATS Stage 1) dispersed sources along the coasts of Kowloon and eastern Hong Kong Island to a single point, i.e., the Stonecutters Island Sewage Treatment Works (SCISTW) outfall.  Under the influence of prevailing tides and currents in the harbour, the net effect is increased E. coli levels at most of the bathing beaches along the Tsuen Wan coast.  Together with water pollution caused by local sources such as sewage from upland unsewered villages or squatter areas, the un-disinfected effluent from SCISTW has exacerbated the already unsatisfactory beach water quality in Tsuen Wan.. The beach monitoring data are graphically presented in the figure below.

 


Annual Trend of Geometric Mean E.coli Levels Measured at Tsuen Wan Beaches:

5.45            Before commissioning of HATS Stage 1, three beaches on the Tsuen Wan coast, namely Anglers’, Approach and Ting Kau, had been closed due to strong influence of local pollution sources as mentioned in Section 5.44.  In general, the E.coli levels measured at the beaches showed a decreasing trend during the pre-HATS period from 1996 to 2000 as a result of local sewerage improvement works but the E.coli levels still exceeded the WQO at six beaches, namely Anglers’, Approach, Casam, Gemini, Lido and Ting Kau, in year 2000 before commissioning of HATS Stage 1 (Table 5.16). After commissioning of HATS Stage 1 in late 2001, the beaches have been further affected by the undisinfected effluent from SCISTW.  The undisinfected effluent from HATS Stage 1 has caused four other beaches on the coast to close. They are, namely Lido, Casam, Hoi Mei Wan, and Gemini. Provision of the advance disinfection facilities (ADF) at the SCISTW is expected to help restore the water quality at Tsuen Wan coast to the pre-HATS Stage 1 status, thus giving the prospect for re-opening of the beaches at Lido, Casam, Hoi Mei, and Gemini.  However, the beaches on Tsuen Wan coast are also subject to influence of local pollution sources, and the more ideal water quality for swimming can only be achieved when these pollution problems are tackled through local sewerage improvement work.

 

Assessment Methodology

 

Construction Phase

5.46            Construction of the Project would not involve marine works such as dredging or filling. The construction works would be land-based and would be designed not to affect normal operation of the SCISTW and the sewage effluent quality. The major construction activities for the Project are described in Sections 2.11 and 2.12.  Construction phase water quality issues would include the impacts from site run-off, sewage from workforce, accidental spillage and discharges of wastewater from various construction activities. The potential impact from these activities was reviewed. Practical water pollution control measures / mitigation proposals were recommended to ensure that any effluent discharged from the construction site would comply with the criteria of WPCO.

 

Operational Phase

Far Field Modelling Tools

5.47            Computer modelling was used to assess the potential impacts on water quality in Victoria Harbour associated with the operation of the Project.  The Delft3D suite of models, namely Delft3D-FLOW and Delft3D-WAQ, developed by Delft Hydraulics, were used as the platforms for hydrodynamic and water quality modelling respectivelyDelft3D is a state-of-the-art computer program that simulates three-dimensional flow and water quality processes and is capable of handling the interactions between different processes.

5.48            Delft3D-FLOW is a 3-dimensional hydrodynamic simulation programme with applications for coastal, river and estuarine areas.  The model calculates non-steady flow and transport phenomena that result from tidal and meteorological forcing on a curvilinear, boundary fitted grid.

5.49            Delft3D-WAQ is a water quality model framework for numerical simulation of various physical, biological and chemical processes in 3 dimensions.  It solves the advection-diffusion-reaction equation for a predefined computational grid and for a wide range of model substances.

5.50            In the present study, the detailed HATS model developed using Delft3D-FLOW and Delft3D-WAQ was employed for simulation of the water quality changes due to the provision of disinfection facilities at the SCISTW.  The detailed HATS model was originally developed and applied under the EEFS to assess the potential water quality impacts of different treatment and disposal scheme proposed for the HATS and the associated construction activities.

5.51            The detailed HATS model covers the North Western, Western Buffer, Victoria Harbour, Junk Bay, Eastern Buffer and Southern WCZ.  The model was extensively calibrated by comparing computational results with field measurements collected from the measurement campaign developed under the EEFS, and accepted by the EPD.  Details of the modelling tools and model setup are provided in the Briefing Document “Tools for Water Quality Modelling” prepared under the EEFS. 

5.52            The performance of the detailed HATS model in terms of its E.coli predictions was further reviewed under this EIA.  Minor adjustment of the process coefficients for E.coli was made upon review of the monitoring data.  Details of the performance of the detailed HATS model and the proposed model adjustment are given in Appendix 5-3.  Set up of the detailed HATS model such as the meteorological forcing, flow aggregation, wind condition, initial and boundary conditions is based on the EEFS.  The model accuracy and limitations are discussed in Appendix 5-2a.

5.53            The detailed HATS Model is linked to the regional Update Model, which was constructed, calibrated and verified under the project “CE42/97 Update on Cumulative Water Quality and Hydrological Effect of Coastal Development and Upgrading of Assessment Tool” (Update Study).  Computations were first carried out using the Update Model to provide open boundary conditions to the detailed HATS Model.  The Update model covers the whole Hong Kong and the adjacent Mainland waters including discharges from the Pearl River.  The influence on hydrodynamics and water quality in these outer regions would be fully incorporated into the detailed HATS Model.

 

Simulation Periods

5.54            For each assessment scenario, the simulation period of the hydrodynamic model covered two 15-day full spring-neap cycles (excluding the spin-up period) for dry and wet seasons respectively.  The hydrodynamic results were used repeatedly to drive the water quality simulations for 30 days (excluding the spin-up period) for each of dry and wet seasons as specified in the EIA Study Brief.  A spin-up period of 8 days and 30 days was provided for hydrodynamic simulation and water quality simulation respectively.  In order to determine whether sufficient spin-up period is provided for the simulation, a test was conducted by repeating the model run for one more simulation period.  It was found that the results of the two successive model runs were consistent with each other, which indicated that the spin-up period was sufficient.

 

Model Setup for Discharges

5.55            The Pearl River estuary flows as well as the effluent flow from the SCISTW were incorporated in the hydrodynamic model. Flows from other storm and sewage outfalls within the whole Hong Kong waters are relatively small and would unlikely change the hydrodynamic regime in the area and were therefore not included in the hydrodynamic model.      

5.56            The diurnal flow variation of the Project effluent was incorporated in both the hydrodynamic and water quality model. The daily flow patterns measured at the SCISTW during August 2004 and January 2005 were reviewed.  The review indicated that there was no substantial change in the diurnal patterns between the dry and wet seasons. The typical diurnal flow pattern measured at the SCISTW as shown in Table 5.17 below was applied to the projected daily Project flow and load to derive the hourly diurnal flow and load for different year horizons as model inputs.  The same 24-hour diurnal flow pattern was used in the model throughout the simulation periods.  The exact vertical and horizontal grid cell(s) of the 3D far field model into which the Project flow and pollution loading were allocated were determined by the near field modelling as detailed in Appendix 5-1

 

Table 5.17            Typical Hourly Flow Pattern for the Project Effluent

Hour

% of Daily Flow

Hour

% of Daily Flow

Hour

% of Daily Flow

Hour

% of Daily Flow

0:00

4.45%

6:00

2.53%

12:00

5.03%

18:00

4.83%

1:00

3.70%

7:00

2.74%

13:00

4.94%

19:00

4.90%

2:00

3.48%

8:00

3.32%

14:00

4.81%

20:00

4.96%

3:00

3.17%

9:00

3.89%

15:00

4.27%

21:00

5.94%

4:00

2.90%

10:00

4.80%

16:00

4.29%

22:00

5.06%

5:00

2.66%

11:00

4.86%

17:00

4.40%

23:00

4.07%

5.57            Loading from the rest of the sewage outfalls was allocated in the bottom water layer. Pollution loads from storm outfalls and other point source discharges were specified in the middle layer of the water quality model. 

 

Chemical Dosages

5.58            Sodium hypochlorite and sodium bisulphite would be adopted as the chlorination agent and dechlorination agent respectively in the latest scheme of this Project. Bench-scale tests were conducted using CEPT effluent to estimate the chlorine demand and chlorine residual for meeting the geometric mean E.coli standards of 20,000 and 200,000 counts per 100 ml.  The tests were conducted by HOKLAS accredited laboratories appointed by DSD in 2002 and 2005.  Based on the data of the bench-scale chlorination studies, the recommended sodium hypochlorite and sodium bisulphite dosages for chlorination / dechlorination under different phases of HATS are summarized in Table 5.18

 

Table 5.18            Recommended Sodium Hypochlorite and Sodium Bisulphite Dosages for HATS

Description

Operational Range

Advance Disinfection Facilities (ADF) Stage to meet the E.coli standard of 200,000 counts per 100 ml

Minimum Chlorine Contact Time

6.6 minutes (under peak flow condition)

Sodium Hypochlorite Dosage (mgCl2/L)

11 - 15

Sodium Bisulphite Dosage(mgNaHSO3/l)

Automatic Mode

4 – 7

Manual Mode

8 – 11

Stage 2A Disinfection Facilities to meet the E.coli standard of 20,000 counts per 100 ml

Minimum Chlorine Contact Time

20 minutes (under peak flow condition)

Sodium Hypochlorite Dosage (mgCl2/L)

10 – 14

Sodium Bisulphite Dosage (mgNaHSO3/l)

2 – 4

Stage 2B Disinfection Facilities to meet the E.coli standard of 20,000 counts per 100 ml

Minimum Chlorine Contact Time

20 minutes (under peak flow condition)

Sodium Hypochlorite Dosage (mgCl2/L)

2 - 3

Sodium Bisulphite Dosage (mgNaHSO3/l)

1 - 2

 

5.59            Under the advance disinfection facilities (ADF) stage, two operation modes are developed for the control of chemical dosages – Manual Operation Mode and Automatic Operation Mode.  The difference between the two operation modes is the methods for measuring the TRC levels at the outlet of the chlorination system. Under Automatic Operation Mode, dosages of dechlorination agent (i.e. sodium bisulphite) are adjusted automatically following sewage flow rate and online TRC measurements at the outlet of the chlorination system. The TRC measurements are conducted continuously e.g. at 15-min intervals. Thus, dechlorination chemical can be adjusted based on the TRC data every 15 minutes. Under Manual Operation Mode, chemical dosages are adjusted based on sewage flow rate and manual TRC measurement. Practically, hourly TRC measurements are conducted during the Manual Operation Mode and dechlorination chemical is adjusted based on the TRC data every hour. A higher dechlorination chemical would be provided to ensure zero TRC in the discharge during the Manual Operation Mode and to allow sufficient safety margin to offset the potential fluctuation of TRC between the hourly measurements. Automatic Operation Mode would be the key control mode for SCISTW chlorination system, while Manual Operation Mode will be provided to allow operation flexibility and reliability in case of online TRC analyzer failure. As a conservative approach, the assessment of water quality impacts has been based on the chemical dosages under Manual Operation Mode.

5.60            At the ADF stage, provision of a new chlorine contact tank to increase the effectiveness of chlorination is not feasible. The existing effluent culvert system would be used for chlorine contact at the ADF stage and the chlorine contact times would be less than 10 minutes. At Stage 2A and Stage 2B, the effluent flow rates would be considerably larger than the ADF flow. A more stringent effluent E.coli standard of 20,000 counts per 100 ml was therefore proposed.  Under Stage 2A, a new chlorine contact tank would be built at the SCISTW to increase the chlorine contact time for the HATS effluent so as to effectively achieve the required disinfection level. Although the recommended dosage for ADF stage would be slightly higher than that for Stage 2A, the resulted disinfection level for ADF would be lower than that for Stage 2A due to the short contact time available under the ADF stage.

 

Effluent Characteristics

5.61            Laboratory pilot tests were conducted for the CEPT effluent from SCISTW and the secondary treated effluent from Tai Po Sewage Treatment Works (TPSTW) and Sha Tin Sewage Treatment Works (STSTW).  The pilot tests aimed to simulate the chlorination and dechlorination process for sewage effluent and to determine the chemical characteristics of the chlorinated/dechlorinated (C/D) effluents.  Table 5.19 summarizes the chemical analysis results.  Of the 34 CBP’s tested, only 8 were detected in the C/D CEPT effluent, the concentrations of 6 were less than 10 parts per billion while those for the remaining 2 were in the 10-50 parts per billion range.  However, 5 of these 8 CBPs were also detected in the raw CEPT effluent before chlorination and dechlorinationOf these 5, the concentrations of 3 were less than 10 parts per billion while the remaining two had concentrations in the 10-50 parts per billion range.  These results indicated that of the few CBP’s detected, the majority was already present in the raw CEPT effluent, and the chlorination and dechlorination process introduced 3 CBP’s all showing concentrations of less than 10 parts per billion.  The laboratory results also showed that the THM and HAA formed were in the parts per billion concentration range, well below USEPA’s drinking water standard for THM and HAA. The chemical analysis results are also discussed in Sections 7.16 and 7.17.  The laboratory results for C/D CEPT effluent were used to assess the water quality impacts due to the effluent discharged from SCISTW during HATS ADF stage and Stage 2A.  The results for C/D secondary treated effluent were used to assess the water quality impacts during HATS Stage 2B where the SCISTW would be upgraded to secondary treatment. The pilot tests were performed using a chlorine dosage of 15 and 20 mg/l for the CEPT effluent and 5 and 9 mg/l for the secondary treated effluent.  The chlorine dosages adopted in the pilot tests are larger than the recommended dosages as shown in Table 5.18, which would provide conservative assessment.

 

Table 5.19            Summary of Chemical Analysis Results

Parameters

Raw CEPT Effluent

C/D CEPT Effluent

Raw Secondary Treated Effluent

C/D Secondary Treated Effluent

Ammonia (mg/l)

18 - 30

(17.4 – 21.5)

1.27 – 1.41

(0.43 – 1.16)

Sulfite (mg/l)

<0.1 – 1.5

(<0.1 – 1.5)

<0.1

0.7

Total residual chlorine (mg/l)

<0.02

(0.02 - 0.1)

<0.02

<0.02

Bromoform (mg/L)

<5

<5

<5

(32 – 49)

Bromodichloromethane (mg/L)

<5

<5

<5

<5

Chloroform (mg/L)

<5 to 5

(<5 – 7)

<5

<5

Dibromochloromethane (mg/L)

<5

<5

<5

(<5 – 8)

Bromoacetic acid (mg/L)

<2

<2

<2

<2

Chloroacetic acid (mg/L)

<2

(<2 – 4)

<2

<2

Dibromoacetic acid (mg/L)

<2

(<2 – 4)

<2

(6 – 10)

Dichloroacetic acid (mg/L)

11 to 17.3

(20 - 45.9)

<2

<2 - 3

Trichlroacetic acid (mg/L)

4.7 to 10

(7.19 – 22)

<2 to 2

(4 – 7)

Methylene chloride (mg/L)

<20

<20

<20

<20

Carbon tetrachloride (mg/L)

<0.5

<0.5

<0.5

<0.5

Chlorobenzene (mg/L)

<0.5

<0.5

<0.5

<0.5

1,1-dichloroethane (mg/L)

<0.5

<0.5

<0.5

<0.5

1,2-dichloroethane (mg/L)

<0.5

<0.5

<0.5

<0.5

1,1-dichloroethylene (mg/L)

<0.5

<0.5

<0.5

<0.5

1,2-dichloropropane (mg/L)

<0.5

<0.5

<0.5

<0.5

Tetrachloroethylene (mg/L)

1.0 to 1.3

(0.5 - 1.3)

<0.5

<0.5

1,1,1-trichloroethane (mg/L)

<0.5

<0.5

<0.5

<0.5

1,1,2-trichloroethane (mg/L)

<0.5

<0.5

<0.5

<0.5

Trichloroethylene (mg/L)

1.5 to 1.9

(1.1 – 2)

<0.5

<0.5

2-chlorophenol (mg/L)

<0.5

<0.5

<0.5

<0.5

2,4-dichlorophenol (mg/L)

<0.5

<0.5

<0.5

<0.5

p-chloro-m-cresol (mg/L)

<0.5

<0.5

<0.5

<0.5

Pentachlorophenol (mg/L)

<2.5

<2.5

<2.5

<2.5

2,4,6-trichlorophenol (mg/L)

<0.5

(1 – 2)

<0.5

<0.5

Bis(2-chloroethoxy)methane (mg/L)

<0.5

<0.5

<0.5

<0.5

1,4-dichlorobenzene (mg/L)

<0.5

<0.5

<0.5

<0.5

Hexachlorobenzene (mg/L)

<0.5

<0.5

<0.5

<0.5

Hexachlorocyclopentadiene (mg/L)

<2.5

<2.5

<2.5

<2.5

Hexachloroethane (mg/L)

<0.5

<0.5

<0.5

<0.5

1,2,4-trichlorobenzene (mg/L)

<0.5

<0.5

<0.5

<0.5

Alpha-BHC (mg/L)

<0.5

<0.5

<0.5

<0.5

Beta-BHC (mg/L)

<1

<1

<1

<1

Gamma-BHC (mg/L)

<1

<1

<1

<1

Note:        Data in brackets indicate the ranges.

 

Whole Effluent Toxicity Test

5.62            Whole effluent toxicity test (WETT) was conducted to determine the whole effluent toxicity of C/D CEPT effluent from SCISTW and C/D secondary treated effluent from TPSTW and STSTW for the following five local marine species:

l    Amphipod (Melita longidactyla), with 48-hour survival test

l    Barnacle larvae (Balanus amphitrite), with 48-hour survival test

l    Fish (Lutjanus malabaricus), with 48-hour survival test

l    Shrimp (Metapenaeus ensis), with 48-hour survival test

l    Diatom (Skeletonema costatum), with 7-day growth inhibition test

5.63            The toxicity tests for amphipod, barnacle larvae, fish and shrimp were conducted to determine the acute toxicity of the effluents to the 4 animal species while the toxicity tests for diatom were to determine the chronic toxicity of the effluents to the plant species.  The species chosen and the testing protocols used for the WETT were developed by a previous study commissioned by Agriculture, Fisheries and Conservation Department (AFCD) and were accepted by EPD and AFCD.  It should be noted that the WETT results reflected the cumulative effects of all CBP species and other toxic contaminants (such as ammonia and heavy metals) that may be present in the raw CEPT effluent.  The WETT results are summarized in Sections 5.162 to 5.166.

 

Modelling Scenarios for Normal Operation

5.64            According to the Brief, construction of the Project (i.e. disinfection facilities) is tentatively scheduled to commence in 2007 for completion by 2009 (ADF stage).  HATS Stage 2 would be implemented in two phases, namely Stage 2A and Stage 2B.  For the purpose of water quality modelling, it is assumed that Stage 2A and Stage 2B would be implemented by 2014 and 2021 respectively. 

5.65            The time horizons for operational phase assessment and the assumed Project flow rates are shown in Table 5.20. The Project flow rates were estimated using the latest population and employment forecast (i.e. 2003-based Territorial Population and Employment Data Matrices) provided by Planning Department and the unit flow factors from the GESF ([3]).  Assumptions for calculating the Project flow rates are given in Appendix 5-2.  The Project flow rates were compiled using the latest information available at the time when the water quality model was set up for this EIA.  Based on the flow projection exercise being conducted under the on-going HATS Stage 2A EIA Study using the latest set of planning data obtained from Planning Department for the HATS catchment, the projected flows in the assessment years would likely be less than those shown in Table 5.20 and Table 5.21.   The Project flow rates adopted in this water quality modelling exercise are therefore considered conservative.

 


Table 5.20            Modelling Scenarios for Operational Phase Impact Assessment

Scenario

Year

Stage

Assumed Flow Rate (m3/day)

Assumed E.coli Counts – Geometric Mean (no. per 100 ml)

Required Chlorine Dosage (mg/l)

Assumed TRC Level - 95%ile value

(mg/l)

1b

2009

Early Commissioning of ADF

1576300

200,000 a

11-15

0.2

2b

2013

Late ADF Stage

1661100

200,000 a

11-15

0.2

2c (Sensitivity Test)

2013

Late ADF Stage

1661100

2,000,000

10-14

0.2

3b

2020

Late Stage 2A with disinfection

2341600

20,000 a

10-14

0.2

3c (Sensitivity Test)

2020

Late Stage 2A with disinfection

2341600

200,000 a

10-13

0.2

4b

Ultimate

Late Stage 2B with disinfection

2800000 b

20,000 a

2-3

0.2

Notes: a – Equivalent to 99% or above E. coli removal

b – The flow rate of 2.8M m3 per day was used in this EIA for conservative assessment.  The recent flow projection conducted under the on-going HATS Stage 2A EIA Study indicated that the ultimate flow rate should be less than 2.8M m3 per day

5.66            Two time horizons (2009 and 2013 respectively) were considered for the ADF stage as there would be changes in the coastline configurations and the background pollution discharges within the Study Area between these two years.  On the other hand, year 2021 was assumed to be the time horizon for implementation of Stage 2B for assessment purpose of this EIA Study. Thus, year 2020 would represent the late phase of Stage 2A just before the commissioning of Stage 2B.

5.67            It was assumed that CEPT with continuous disinfection would be provided for the Project effluent under ADF stage and Stage 2A.  In addition, secondary treatment with continuous disinfection would be provided under Stage 2B (for ultimate scenario).

5.68            An annual geometric mean value and a 95 percentile (%ile) value were specified for the E.coli discharge standards whereas a 95%ile value and a maximum discharge limit were specified for the TRC standards.  The geometric mean value and the 95%ile value were adopted as the effluent concentrations for E.coli and TRC respectively as shown in Table 5.20.

5.69            Scenario 1b, Scenario 2b, Scenario 3b and Scenario 4b as shown in Table 5.20 are the base case scenarios for water quality modelling. The proposed E.coli standards for these base case scenarios (i.e. 200,000 counts per 100 ml for ADF and 20,000 counts per 100 ml for Stage 2A and Stage 2B, both equivalent to 99% or above E. coli removal) were derived with reference to the findings of the previous EIA Study for SSDS Stage 1 and the HATS EEFS, as well as the finding of the water quality impact assessment carried out under this EIA Study.   These proposed effluent standards were only used in this EIA as the base case for water quality modelling.  Based on the results of the base case modelling, additional model runs (namely Scenario 2c and Scenario 3c as shown in Table 5.20) were performed by adjusting the disinfection level to determine the optimum chlorine dosage for the disinfection facilities.  The objective was to, on one hand, protect the beneficial uses of water sensitive receivers, and on the other hand, minimize the chlorine dose and thus the potential for generation of CBP.  The results of the base case modelling and the rationales for deriving the sensitivity tests (namely Scenario 2c and Scenario 3c and Scenario 4b) are detailed in Sections 5.125 to 5.149.

5.70            Based on the recommendation of EEFS, the TRC standards for HATS effluent were set at 0.2 mg/l (95%ile) and 0.4 mg/l (maximum).  The adequacy of the proposed TRC standards was assessed by means of water quality modelling.  The TRC levels in the receiving waters as predicted by the water quality model are compared against the ambient water quality objectives to evaluate the potential impacts.   The adequacy of the proposed TRC standards in terms of their human health and ecological risks are discussed in Section 6. 

5.71            The adverse assumption of using the 95%ile value (0.2 mg/l) as the initial HATS effluent concentration for continuous discharge was adopted for water quality modelling.  This model input is considered conservative, given that 95%ile of the TRC loads are usually about twice their mean values.  The pilot test data presented in Table 5.19 also showed a TRC range of 0.02 to 0.1 mg/l.  Thus, the water quality impacts simulated were likely to be higher than the real situation that would happen. 

5.72            In addition, four scenario runs (Scenario 1a, Scenario 2a, Scenario 3a and Scenario 4a) for the case without the Project were included to give the baseline conditions for the four selected time horizons (see Table 5.21). The baseline conditions assumed that no disinfection facility would be provided at the SCISTW. The purpose of performing the baseline scenarios was to quantify the E.coli impacts due to the undisinfected effluent from SCISTW to demonstrate the need for this Project.  The net impact due to continuous disinfection at the SCISTW could also be quantified by comparing the results of different assessment scenarios.

 

Table 5.21            Modelling Scenarios for Baseline Conditions (Without the Project)

Scenario

Description

Assumed Flow Rate (m3/day)

Assumed E.coli Level in the Undisinfected Effluent (no. per 100 ml)

1a

2009 with no ADF

1576300

1.0E+7 (a)

2a

2013 with no ADF

1661100

1.0E+7 (a)

3a

2020 Stage 2A with no disinfection

2341600

1.0E+7 (a)

4a

Ultimate Stage 2B with no disinfection

2800000 (c)

2.96E+5 (b)

Notes:

(a)       The assumed E.coli level in undisinfected CEPT was based on the bench-scale chlorination tests conducted by DSD in 2002 and 2005.

(b)       95%ile value measured in the effluent from Sha Tin STW (secondary treatment plant) in 2001 (derived under the EIA Study for Tai Po STW Stage 5).

(c)       The flow rate of 2.8M m3 per day was used in this EIA for conservative assessment.  The recent flow projection conducted under the on-going HATS Stage 2A EIA Study indicated that the ultimate flow rate should be less than 2.8M m3 per day

5.73            The E.coli level in the undisinfected effluent of HATS Stage 2B would depend on the type of biological treatment process to be selected for HATS.  The biological treatment process for HATS Stage 2B is however not yet decided.  The E.coli level assumed for the HATS Stage 2B effluent (without disinfection) under Scenario 4a was based on the 95%ile value (2.96E+5 counts per 100 ml) measured in the secondary treated effluent from Sha Tin STW as derived under the EIA Study for Tai Po STW Stage 5.  Based on “Wastewater Engineering Treatment Disposal Reuse, Metcalf & Eddy Third Edition”, the effluent E.coli level of a secondary process is in the range of 1E+5 to 1E+6 no. per 100 ml.  The 95%ile value measured at Sha Tin STW was within this range and therefore a reasonable assumption for modelling. Review of recent effluent quality data (2001– 2005) obtained for several existing secondary treatment plants including Sha Tin STW, Tai Po STW and Yuen Long STW also revealed that the adoption of the E.coli value of 2.96E+5 counts per 100 ml is a reasonable assumption. 

5.74            Under normal circumstances, the treated effluent would be discharged into the sea via the existing submarine outfalls of SCISTW.  The submarine outfalls of SCISTW are shown in Attachment 1 of Appendix 5-1. 

 

Sensitivity Test – Time Varying E.coli Loading

5.75            As mentioned above, the geometric mean E.coli effluent standards have been applied constantly throughout the simulation period for water quality modelling.  As E.coli levels normally exhibit large fluctuations, the geometric mean, which reflects an average condition, may not be representative of situations having high E.coli levels. To address this concern, a sensitivity model run was conducted using a time varying E.coli loading for model input under the 2009 scenario. The loading input for this sensitivity test was derived from the E.coli levels measured in the chlorinated CEPT effluent from the bench-scale chlorination studies conducted by DSD in 2002 and 2005.  Only those E.coli levels that were within the design range for meeting the effluent geometric mean standard of 200,000 no. per 100 ml were chosen for hourly model input which covered a simulation period of 22 days. The E.coli levels adopted for model input are given in Appendix 5-4a. The sensitivity test results are attached in Appendix 5-4b.  The sensitivity results are compared with the base case results for 2009 where a constant geometric mean E.coli level of 200,000 no. per 100 ml was applied throughout the simulation period.  The sensitivity results indicated that there is no significant difference in the geometric mean levels predicted at the Tsuen Wan beaches due to the use of time fluctuating loading for model input.  Therefore, the assumption of using a constant geometric mean loading for modelling is reasonable

Assumptions for TRC and CBP Modelling

5.76            The modelling scenarios have taken into account the discharge of TRC and CBP.  A tracer was defined at the discharge location of the Project to determine the dilution in the vicinity of the discharge point.  Tracers were also defined at other identified concurrent discharges for cumulative impact assessment.  The dilution information was used to determine the decreases in the concentrations and to evaluate the potential impacts. The modelling of TRC was conducted using a decay rate of 24 per day ([4]). An even more conservative assumption of zero decay rate was applied to the CBP discharges. 

5.77            Four major sewage effluent discharges were considered in the TRC and CBP modelling.  They were the effluent from SCISTW, Pillar Point Sewage Treatment Works (PPSTW), Tai Po Sewage Treatment Works (TPSTW) and Sha Tin Sewage Treatment Works (STSTW) respectively.  It should be noted that the effluent from TPSTW and STSTW would be discharged into the Victoria Harbour via the Kai Tak Nullah under the Tolo Harbour Effluent Export Scheme (THEES).  UV radiation would be used as the disinfection method for TPSTW and STSTW.  However, for the purpose of this water quality impact assessment and as a worst-case scenario study, chlorination and dechlorination were assumed to be the disinfection processes of the sewage effluent discharges from TPSTW and STSTW.  Effluent from Sham Tseng STW and Siu Ho Wan STW was not included in the TRC modelling as UV disinfection is currently adopted for these two treatment works.  Cumulative TRC and CBP impact from cooling water discharges within the Study Area was also incorporated into the model.  

5.78            The initial TRC levels assumed in the effluent from TPSTW and STSTW as well as in the cooling water discharges are based on the assumptions adopted in the approved “EIA Study for Tai Po Sewage Treatment Works Stage 5”.  The initial concentrations of CBP assumed in the TPSTW and STSTW effluents and the cooling water discharges are based on the maximum CBP levels measured in the C/D secondary treated effluent samples as shown in Table 5.19 above (please also refer to Sections 7.16 and 7.17).  As the SCISTW would eventually be upgraded to secondary treatment, the initial CBP levels in the SCISTW effluent under the ultimate stage during Stage 2B are also based on the maximum values measured in the C/D secondary treated effluent.  The initial CBP levels in the HATS effluent during ADF stage and Stage 2A are based on the maximum values measured in the C/D CEPT effluent samples collected from the SCISTW.  The initial TRC and CBP levels in the C/D CEPT effluent from PPSTW were assumed to be the same as those in the C/D CEPT effluent from the SCISTW.

5.79            Modelling of TRC and CBP was to evaluate whether the Project discharges would cause any cumulative water quality impact with other concurrent discharges and to determine the size of the mixing zone for these compounds.  The assumptions adopted for modelling of TRC and CBP represent the worst case scenarios for water quality impact assessment. Assessment of the acute and chronic toxicity of TRC and CBP was conducted under the Human Health and Ecological Risk Assessment in Sections 6 and 7.

 

Potential Oxygen Depletion Due to the Addition of Dechlorination Chemical

5.80            Sodium hypochlorite and sodium bisulphite would be adopted as the chlorination agent and dechlorination agent respectively.  The operational range of sodium bisulphite dosage was derived from the data obtained from the bench-scale tests as shown in Table 5.18. The upper limit of operational range for sodium bisulphite dosage is 11 mg/l, 4 mg/l and 2 mg/l for ADF, Stage 2A and Stage 2B respectively and these upper values were assumed as the sodium bisulphite concentration in the Project effluent for water quality modelling.  A conservative tracer (with zero decay rate) was defined in the far field model at the effluent discharge point to predict the sodium bisulphite concentrations in the marine water under normal operation.  This would be a very worst case in terms of the predicted sodium bisulphite level in the marine water as it is assumed that the chemical does not react and remains inert.  In reality, sodium bisulphite would not be inert as it would react with chlorine and other chemicals in the water. 

5.81            The sodium bisulphite concentrations predicted by the far field water quality model were used to estimate the oxygen depletion in the marine water.  For conservative assessment, it is assumed that all sodium bisulphite would undergo the following reaction with the oxygen in marine water:

 

2NaHSO3 (sodium bisulphite) + O2 (oxygen) à 2NaHSO4 (sodium bisulphate)

5.82            On a weight to weight basis, approximately 6.5 parts of sodium bisulphite would consume 1 part of oxygen.  The level of oxygen depletion was calculated by dividing the predicted sodium bisulphite concentration in the marine water with a factor of 6.5.  The level of oxygen depletion was then compared with the ambient DO levels predicted by the far field water quality model to determine the significance of the potential impact.  The assessment focused on areas in the vicinity of the Project discharge point.

 

Modelling Scenarios for Emergency Situations

 

Temporary Discharge of Undisinfected Effluent

5.83            Water quality modelling was carried out to address the impact from the discharge of undisinfected effluent under temporary failure of disinfection facilities due to the lack of power supply as well as other incidents such as pump or equipment failure.  The modelling also addressed the impacts from the discharge of undisinfected effluent in the event of temporary failure of dechlorination where the chlorination plant would need to be shutdown to avoid excessive discharge of TRC.

5.84            In the event of emergency situations when the disinfection facilities fail or are shutdown, treated (but undisinfected) effluent would be discharged into the sea via the submarine outfall of SCISTW.   The North West Kowloon outfall which conveys effluent to a disposal point between the Cargo Handling Wharf and the North Fairway, forms a bypass to the HATS Stage 1 outfall.  Sewage bypass is also available via other preliminary treatment works (PTW) within the HATS catcments.  The bypass would be discharged via the submarine outfalls of the PTW except for Kwai Chung PTW where its submarine outfall was decommissioned.  Emergency bypass at Kwai Chung PTW can only be discharged via the seawall bypass location.  However, such sewage bypass would only happen when malfunctioning of the SCISTW submarine outfall or failure of the pumping units at the main treatment facilities of the SCISTW occurs or when equipment failure or power supply failure at the screening plant occurs.  Only screened sewage would be discharged via these sewage bypass locations.  As such, emergency discharge of treated (but undisinfected) effluent due to the failure of the disinfection facilities would only occur at the submarine outfall of SCISTW. 

5.85            Modelling was carried out for six scenarios as shown in Table 5.22 to simulate the impact due to the shutdown of the disinfection facilities.

 

Table 5.22    Proposed Modelling Scenarios for Emergency Discharge of Undisinfected CEPT Effluent

Scenario

Year

Total Discharge Period (hours)

Assumed E.coli Concentration in Undisinfected CEPT Effluent (no. per 100 ml)

5a

Year 2009 – ADF

6

 

 

 

1.0E+7 (2)

5b

Year 2009 – ADF

24 (1)

6a

Year 2013 – ADF

6

6b

Year 2013 – ADF

24 (1)

7a

Year 2020 – Stage 2A

6

7b

Year 2020 – Stage 2A

24 (1)

Notes:

(1)       Past emergency discharge records available from various sewage treatment works indicated that the longest period of emergency discharge would be less than 6 hours.  Thus, emergency discharge for 24 hours is an extremely remote scenario for the purpose of worst-case assessment only.

(2)       The assumed E.coli level in undisinfected CEPT are based on the bench-scale chlorination tests conducted by DSD in 2002 and 2005.

5.86            Year 2020 represents the worst case in terms of the E.coli loading from the undisinfected CEPT effluent.  Year 2009 and Year 2013 are selected to address the effect during the ADF stage. Although the HATS flow under the ultimate scenario would be larger than that under Stage 2A, the E.coli concentration in the undisinfected secondary treated effluent would be much smaller than that in the undisinfected CEPT effluent.  The impact due to emergency discharge under the ultimate scenario was therefore not assessed.

5.87            According to the information provided by DSD, emergency discharge has never occurred at the existing SCISTW.  The historical records of emergency discharge at the PTW and STW in both HATS Stage 1 and HATS Stage 2 catchments were reviewed for the period from 2002 to 2005.  The recorded emergency bypasses were due to prolonged or very heavy rainfall or failure of pumping stations at the PTW or STW. The longest duration of emergency discharge was 5 hours 27 minutes recorded at Northwest Kowloon Pumping Station in 2005 due to prolonged rainfall.  Based on the historical records, emergency discharge due to power failure has not happened before at the Pillar Point PTW and San Wai PTW.

5.88            The proposed scenarios cover two different discharge period namely:

 

·                a 6-hour period (which is a reasonable assumption based on past emergency discharge records) and

·                a 24-hour period (which is a very adverse scenario as sensitivity test)

5.89            For the first scenario (namely Scenario 5a), four separate model runs were conducted using the far field model to simulate the impacts for four emergency discharge periods centred at namely neap tide high water, neap tide low water, spring tide mid-flood and spring tide mid-ebb respectively for both wet and dry seasons.  The model results were analyzed to determine the sensitivity of the water quality impacts under different discharge times.  The sensitivity results indicated that the water quality impact at the identified sensitive receivers would be relatively larger under the discharge periods centred at neap tide low water and spring tide mid-flood.  These two tide conditions were therefore selected and modelled for both dry season and wet season under the remaining five scenarios (i.e. Scenarios 5b, 6a, 6b, 7a and 7b).  Thus, four runs were performed for each scenario, i.e., two runs (neap low water and spring mid-flood respectively) for dry season and two runs (neap low water and spring mid-flood respectively) for wet season.

 

Temporary Discharge of Chlorinated Effluent

5.90            Failure of dechlorination could be caused by the malfunction of the pumping system or power failure at the dechlorination unit. It is considered that the plant operator would be notified immediately after any power failure or pump failure via the control system of the treatment plant.  It is also considered that the chlorination dosing process could be practically stopped within 30 minutes upon notification of the dechlorination plant failure.  It is therefore assumed in the modelling that when failure of dechlorination occurs, the reaction time to shut down the chlorination unit to avoid excessive discharge of TRC into the marine environment would be about 30 minutes.  During the period when the dechlorination unit is failed, a higher level of TRC would be present in the effluent.

5.91            Table 5.23 shows the proposed emergency discharge scenarios. Scenario 8a and Scenario 9a would cover an emergency discharge period of 40 minutes which takes into account the reaction time for DSD to shut down the chlorination plant (30 minutes) plus the assumed chlorine retention time of 10 minutes. Scenario 10a would cover an emergency discharge period of 60 minutes which takes into account the reaction time for DSD to shut down the chlorination plant (30 minutes) plus the assumed chlorine retention time of 30 minutes.  Stage 2B was not assessed as Stage 2A already represents the worst case in terms of the Project discharge.

 

Table 5.23   Proposed Modelling Scenarios for Emergency Discharge of TRC

Scenario

Year

Assumed Chlorine Retention Time (minute)

Reaction Time to Shut Down the Chlorination Plant (minutes)

Total  Discharge Period

Assumed Chlorine Residuals without Dechlorination (mg/l)

8a

Year 2009 – ADF

10

30

40 minutes

6.7

9a

Year 2013 – ADF

10

30

40 minutes

6.7

10a

Year 2020 – Stage 2A

30

30

60 minutes

5.5

5.92            Based on data from the bench-scale chlorination studies, the maximum chlorine residuals at the ADF stage and Stage 2A would be in the range of 4.8 - 6.3 mg/l and 4.3 – 5.3 mg/l respectively. The ranges identified from the bench-scale studies are based on the chlorine dosage of 15 and 20 mg/l. The chorine residuals assumed for the emergency scenarios as shown in Table 5.23 are 6.7 and 5.5 mg/l for ADF and Stage 2A respectively which are slightly higher than the ranges identified from the bench-scale studies. Based on the updated design information, the operational chlorine dosage would range from 11 to 15 mg/l to achieve geometric mean E.coli standard of 200,000 no. per 100ml for ADF and 10 to 14 mg/l to achieve the geometric mean standard of 20,000 no. per 100 ml for Stage 2A as shown in Table 5.18.  The TRC at the dechlorination point of SCISTW will be controlled within range of 1 to 4 mg/l during the operation. The maximum chlorine dosage of 20 mg/l adopted in the bench-scale studies and the chlorine residuals adopted under the emergency scenarios are therefore conservative assumptions. 

 

Coastline Configurations

5.93            The coastline configurations adopted for the 2009 and 2013 scenarios are shown in Figure 5.4 and Figure 5.5 respectively.  The assumed coastline configurations for 2020 and ultimate stage are shown in Figure 5.6The reclamations for South East Kowloon Development (SEKD), Wan Chai Development II (WDII) and Yau Tong Bay Reclamation (YTBR) were excluded as they were still subject to planning review when this EIA report was prepared. It should be noted that the reclamation for Central Reclamation Phase III (CRIII) has been incorporated into the existing coastline as shown in Figure 5.4 to Figure 5.6

5.94            Sensitivity test was conducted under this Study to investigate the effect of possible changes of coastline configurations in Victoria Harbour on the overall conclusion of the water quality impact assessment.  Additional sensitivity test modelling was undertaken for 2020 using an alternative coastline configuration for the Victoria Harbour as shown in Figure 5.7, namely Scenario 3fThe alternative coastline configurations have incorporated the reclamations for SEKD, WDII and YBTR.  The reclamation limits for these additional developments as shown in Figure 5.7 are based on the information provided in the latest approved EIA reports for these developments. Scenario 3e uses the maximum extent of reclamation as in previous approved EIA which already represents the worst case impact upon the hydrodynamic and water quality, as compared to the base case scenario (namely Scenario 3b) with no reclamation at all within the Victoria Harbour.  Additional model runs to consider the latest concept plans for SEKD and WDII which involve a lesser extent of reclamation are considered not necessary.

 

Pollution Loading

5.95            The pollution loading inventory for different assessment years was compiled using the latest planning data. Appendix 5-2 gives the detailed methodology for compiling the pollution loading. The inventory has incorporated all possible pollution sources within the Hong Kong waters including those from landfill sites, non-point source surface run-off and sewage from cross connections etc.  The inventory has also taken into account the removal of pollutants due to wastewater treatment facilities and the possible redistribution of pollution loads due to different sewage disposal plans and sewage export schemes. 

5.96            The key sewage effluent discharges included in the far field water quality model for cumulative assessment include the effluent flow from SCISTW, Pillar Point STW, Siu Ho Wan STW, NWNT outfall, Sham Tseng STW and THEES. Figure 5.8 shows the major sewage outfalls located in the assessment area.  The pollution loading inventory for these major sewage outfalls was considered separately based on the information from recent studies and actual measurements.  Appendix 5-4 gives the flow and effluent concentrations assumed for these major sewage outfalls under different assessment scenarios.

5.97            It should be noted that the water quality at the Tsuen Wan Coast including the eight beaches in Tsuen Wan District was greatly influenced by the local pollution sources as discussed in Section 5.44.  The future pollution loads from these background sources were estimated using the best information available at the time when this EIA report was prepared, and were included in the water quality model for cumulative impact assessment.  Based on the information obtained from DSD and EPD under this EIA, it is expected that the sewerage along the Castle Peak Road would be in place around the same time of commissioning of this ADF Project to serve unsewered villages and properties around Ting Kau, Sham Tseng and Tsing Lung Tau.  For the purpose of water quality modelling, it is assumed that the residual loading discharged to the Tsuen Wan coast from Sham Tseng, Tsuen Wan, Kwai Chung and Tsing Yi catchments in the future would be 10 percent of the total loading generated within these catchments which is a conservative assumption.  To enhance the model configuration, distribution of the pollution loading of the beach hinterlands is adjusted based on the updated information on the distribution of unsewered population in the respective areas.

 

Identification of Environmental Impacts

 

Construction Phase

 

General Construction Activities

5.98            The general construction activities would be primarily land-based as descried in Section 2.11.  Various types of construction activities may generate wastewater. These include general cleaning and polishing, wheel washing, dust suppression and utility installation.  These types of wastewater would contain high concentrations of suspended solids.  Impacts could also result from the accumulation of solid and liquid waste such as packaging and construction materials, and sewage effluent from the construction work force involved with the construction.  If uncontrolled, these could lead to deterioration in water quality. 

 

Construction Site Runoff

5.99            During a rainstorm, site runoff would wash away the soil particles. The runoff is generally characterised by high concentrations of suspended solids.  Uncontrolled release of site runoff would increase the SS levels and turbidity in the nearby water environment.

5.100        Increase in debris and SS arising from the construction site could also block the drainage channels and may result in local flooding when heavy rainfall occurs.  High concentrations of suspended degradable organic material in marine water could lead to reduction in DO levels in the water column.

5.101        Wind blown dust would be generated from exposed soil surface in the works areas.  It is possible that wind blown dust would fall directly onto the nearby water bodies when a strong wind occurs.  Dispersion of dust within the works areas may increase the SS levels in surface runoff causing a potential impact to the nearby sensitive receivers.

 

Accidental Spillage

5.102        A large variety of chemicals would be used during construction. These may include surplus adhesives, spent paints, petroleum products, lubrication oil, grease and mineral oil, spent acid and alkaline solutions/solvent and other chemicals. Accidental spillage of chemicals in the works areas may contaminate the surface soils. The contaminated soil particles may be washed away by construction site runoff or storm runoff causing water pollution.

Operation Phase

5.103        The Project involves the provision of disinfection facilities at the existing SCISTW.  The key operational phase water quality effects from this Project would be:

·           the reduction of faecal bacteria in the effluent due to the proposed disinfection facilities

·           the potential generation of low-level TRC and CBP in the effluent due to chlorination of the sewage effluent

·           the potential impact of TRC in the event of dechlorination plant failure

·           the potential impact of faecal pollution in the event of chlorination plant failure

·           the potential minor oxygen depletion impact due to addition of dechlorination chemical

 

Prediction and Evaluation of Environmental Impacts

 

Construction Phase

5.104        The Project would involve the following major construction activities:

·               Site formation & site establishment

·               Piling (presumably pre-bored H pile)

·               Excavation and backfilling

·               Erection of formwork and reinforcement

·               Concreting

·               Fabrication of steelwork & installation of E&M equipment

·               Testing and commissioning

 

General Construction Activities

5.105        The effects on water quality from general construction activities are likely to be minimal, provided that site drainage would be well maintained and good construction practices would be observed to ensure that litter, fuels, and solvents are managed, stored and handled properly.

5.106        Based on the Sewerage Manual, Part I, 1995 of the Drainage Services Department (DSD), the sewage production rate for construction workers is estimated at 0.35 m3 per worker per day. For every 50 construction workers working simultaneously at the construction site, about 17.5 m3 of sewage would be generated per day.  The sewage should not be allowed to discharge directly into the surrounding water body without treatment.  Sufficient chemical toilets should be provided for workers.  Existing toilets within the SCISTW could also be made available for use as necessary.

 

Construction Runoff and Drainage

5.107        Construction run-off and drainage may cause local water quality impacts.  It is important that proper site practice and good site management be followed to prevent run-off with high level of SS from entering the surrounding waters.  With the implementation of appropriate measures to control run-off and drainage from the construction site, disturbance of water bodies would be avoided and deterioration in water quality would be minimal. Thus, unacceptable impacts on the water quality are not expected, provided that the recommended measures described in Sections 5.212 to 5.220 are properly implemented.

 

Operation Phase

Normal Operation

Overall E.coli Impact

5.108        The contour plots of predicted depth-averaged E.coli for the whole Study Area are compared between different assessment scenarios in Figure 5.9 and Figure 5.10 for wet and dry seasons respectively.  Figure 5.11 and Figure 5.12 show the close up of the model output at Western Buffer WCZ and its adjacent waters. Appendix 5-5 to Appendix 5-8 tabulate the E.coli levels predicted at the bathing beaches, WSD flushing water intakes, fish culture zones (FCZ) and other ecological sensitive receivers identified within the Study Area. The results provided in Appendix 5-5 to Appendix 5-8 are depth-averaged results except for the seawater intakes where the results are presented for the mid-depth where the intake points are located.

5.109        To isolate the impact of the SCISTW effluent from other background discharges assumed in the model, additional model runs were performed by including the SCISTW effluent only for the four assessment years (i.e. 2009, 2013, 2020 and ultimate scenarios).  The results of these additional model runs showing the effluent plume from SCISTW alone are presented as contour plots in Figure 5.13 and Figure 5.14 for wet and dry seasons respectively.  The E.coli improvements due to the proposed disinfection are also presented in Figure 5.13 and Figure 5.14 for reference.

5.110        The contour plots indicated that the baseline water quality impact on Tsuen Wan and Tuen Mun waters would be smaller in 2013 (Scenario 2a) as compared to 2009 (Scenario 1a) which was mainly caused by the upgrading of Pillar Point STW which was scheduled to be implemented in 2011.  It can also be seen that the water quality in Victoria Harbour and areas to the southwest of Hong Kong Island would be improved after the implementation of HATS Stage 2A under Scenario 3a.  The HATS Stage 2A is scheduled for implementation in 2014 and the observed improvement in water quality would be seen thereafter.  However, the degree of local impact in areas close to the SCISTW outfall would be larger after implementation of HATS Stage 2A in 2014 (Figure 5.9 and Figure 5.10).

5.111        The comparison between the modelling results of baseline scenarios (without disinfection at SCISTW) and operation phase scenario (with disinfection at SCISTW) indicated that the provision of disinfection at SCISTW would significantly improve the water quality in Victoria Harbour and Western Buffer WCZ.  The model results showed that there was no obvious difference in the extent of water quality impact between the two scenarios in areas farther away such as Junk Bay WCZ, Eastern Buffer WCZ and Southern WCZ. 

5.112        The model prediction also showed that the influence from the SCISTW effluent would be relatively smaller along the eastern coast of Tsuen Wan inside the Rambler Channel as compared to the western coast of Tsuen Wan.  The SCISTW outfall is situated to the south of Tsuen Wan coast where the SCISTW effluent would be brought to the Tsuen Wan coast by the water current flowing from south to north during flood tides. Figure 5.15 shows the flow patterns in the Western Buffer WCZ under typical flood and ebb tide conditions.  Under the flood tide conditions, the SCISTW effluent flowing towards the Tsuen Wan coast would be blocked by the Tsing Yi Island and diverted around the Tsing Yi Island to the western coast of Tsuen Wan. Therefore, the eastern coast of Tsuen Wan inside the Rambler channel would be subject to a lesser extent of the influence from SCISTW effluent.

5.113        In ultimate year, the degree of E.coli improvement by disinfection would be substantially reduced due to the fact that the E.coli levels would be substantially lower from the secondary process under Stage 2B even without the provision of disinfection. However, there would still be water quality improvements in areas to the south of Tsing Yi Island in the central Western Buffer WCZ and western Victoria Harbour (Figure 5.13 and Figure 5.14)

5.114        Water quality objectives (WQO) for E.coli are available for the secondary contact subzones, fish culture zones (FCZ), WSD flushing water intakes and bathing beaches.  Figure 5.1 shows the boundaries of the secondary contact subzones as well as the locations of FCZ, WSD intakes and beaches identified within the Study Area.

5.115        As shown in Appendix 5-5 to Appendix 5-8, the geometric mean E.coli levels predicted at all the identified FCZ would comply with the WQO of 610 no. per 100 ml under all the baseline and assessment scenarios (i.e. both with and without disinfection). Impacts on the identified ecological receivers are addressed in detail under the ecological impact assessment in Section 7.

5.116        Appendix 5-5 to Appendix 5-8 show that the provision of disinfection facilities at SCISTW would significantly improve the situation (i.e. reduce the degree of WQO exceedances) at the Tsuen Wan beaches during the ADF Stage and Stage 2A.  The influence zone of the HATS effluent would not cover the area in farther field including the beaches in Tuen Mun, Lantau Island, southern Hong Kong Island and Cheung Chau.

5.117        With the provision of disinfection facilities at SCISTW, full compliance with the WSD standard of 20000 no. per 100 ml would be achieved at all the identified flushing water intakes within the Study Area except that the maximum values predicted for the intakes at North Point and Sheung Wan (during ADF Stage) and Cheung Sha Wan (during ADF stage, Stage 2A and Stage 2B) would exceed the WQO as shown in Appendix 5-5 to Appendix 5-8.  The residual exceedances predicted at North Point during ADF stage were essentially due to the pollutants discharged from the nearby North Point PTW before the implementation of HATS Stage 2A. These exceedances were shown to cease after the implementation of HATS Stage 2A when effluent from North Point PTW would be intercepted to the SCISTW by the HATS Stage 2A sewage conveyance system. The residual exceedances at Cheung Sha Wan were caused by the pollutants discharged from the nearby storm drains as the same levels of exceedances were predicted under both baseline (with no disinfection at SCISTW) and operational phase (with disinfection at SCISTW). It is therefore considered that the residual exceedances predicted at North Point and Cheung Sha Wan (after the Project commissioned) are not related to the effluent discharged from SCISTW.  It is expected that the residual exceedances predicted at Sheung Wan (located in the western Victoria Harbour) during ADF stage was caused by the sewage discharged from the nearby Central PTW.  As indicated in Appendix 5-5 to Appendix 5-7, the provision of disinfection at the SCISTW would improve the WQO compliances at the WSD flushing water intakes located in the western Victoria Harbour, namely Central Water Front, Sheung Wan and Kennedy Town, under ADF stage and Stage 2A.

5.118        Non-compliance with the WQO (of 610 no. per 100 ml for geometric mean) was predicted within the secondary contact subzones in the coastal areas of Tuen Mun and Tsuen Wan as shown in Figure 5.9 and Figure 5.10.  It was found that the degree of exceedances in the Tuen Mun and Tsuen Wan coast would be improved after the provision of disinfection facilities at the SCISTW during ADF stage and Stage 2A. 

5.119        Non-compliance with the WQO was also predicted at some of the secondary contact subzones outside the Tuen Mun and Tsuen Wan Districts. These exceedances were however not related to the HATS discharge as the same levels of exceedances were predicted under the baseline scenarios (without disinfection at SCISTW) and the operational phase scenarios (with disinfection at SCISTW).  These exceedances were due to the discharges from the local sources assumed in the modelling for the purpose of cumulative assessment.

5.120        Based on the water quality modelling results, it was found that the undisinfected effluent from SCISTW would contribute WQO exceedances at the WSD flushing water intakes in western Victoria Harbour, the beaches in Tsuen Wan District as well as the secondary contact subzones in Tsuen Mun and Tsuen Wan coast.  Thus, more detailed analysis on these potential impacts was conducted to determine the optimum disinfection level for protecting the beneficial uses of these sensitive receivers.  Detailed analysis of these potential impacts is provided in subsequent sections.

 

Impacts on Water Sensitive Receivers

5.121        Three WSD flushing water intakes in western Victoria Harbour, namely Central Water Front (WSD18), Sheung Wan (WSD19) and Kennedy Town (WSD20) respectively would be affected by the HATS effluent. Figure 5.1 shows the locations of these flushing water intakes. Appendix 5-5 to Appendix 5-8 tabulate the geometric mean and maximum E.coli levels predicted at the WSD flushing water intakes for both the operational scenarios (with disinfection at SCISTW) and the baseline scenarios (without disinfection at SCISTW)  

5.122        There are eight beaches in Tsuen Wan District, namely Anglers’ (B7), Gemini (B8), Ho Mei Wan (B9), Casam (B10), Lido (B11), Ting Kau (B12), Approach (B13) and Ma Wan (B14) respectively, which would be affected by the HATS effluent. Figure 5.3 shows the locations of these Tsuen Wan beaches. Figure 5.16 and Figure 5.17 show the predicted E.coli levels at the Tsuen Wan beaches. Results for both the operational scenarios (with disinfection at SCISTW) and the baseline scenarios (without disinfection at SCISTW) are included in Figure 5.16 and Figure 5.17 for comparison. The geometric mean and maximum values predicted at the beaches are also tabulated in Appendix 5-5 to Appendix 5-8.  To isolate the impact of the SCISTW effluent from other background discharges assumed in the model, additional model runs were performed by including the SCISTW effluent only for the four assessment years.  These additional model runs aimed to provide an indication of the impact contributed from the SCISTW effluent alone at the water sensitive receivers. 

5.123        Model results provided for flushing water intakes represent the E.coli values predicted at the mid-depth where the intake points are located. These model results are compared with the WSD standard ( 20000 no. per 100 ml at all times) to evaluate the potential impacts upon the flushing water intakes.  The impact assessment on the bathing beaches was made based on depth-averaged E.coli results because the WQO (180 no. per 100 ml, geometric mean for bathing season) is applicable to the whole bathing water body.  As the water depth at the bathing beaches is considered small, it is not expected that there would be any significant difference in the depth averaged and the surface E.coli levels.

5.124        The bathing (or wet) season is defined as the period from March to October based on the WQO set out under the WPCO. Thus, November to February would represent the dry season.  The model simulation was however performed for a 30-day period under typical wet season condition covering the period from late July to late August and typical dry season condition covering the period from late January to late February. As the meteorological forcing, wind condition, daily pollution load discharges and all process coefficients adopted in the water quality model set-up are constant throughout the simulations and each model simulation covered at least a full tidal cycle (including both large amplitude spring tides and small amplitude neap tides) in wet season, it is considered acceptable to compare the mean model output from the 30-day simulations with the WQO to evaluate the beach water quality impacts.  Moreover, the model simulations were separately performed for the dry season (non-bathing season) scenarios.  The dry season model results are also compared with the beach WQO under this EIA to assess the potential water quality impacts in the non-bathing seasons for reference. It should however be noted that there is no statutory requirement on the beach water quality during the non-bathing seasons in Hong Kong.

Bathing Beaches

5.125        Major factors that influencing the predicted E.coli levels at Tsuen Wan beaches include:

 

·         Change of HATS effluent loading

·         Change of local pollution loading from the polluted storm water discharged from the rural areas of Sham Tseng and the dense urban areas in Tsuen Wan, Kwai Chung and Tsing Yi Districts

·         Upgrading the treatment process of Pillar Point STW from preliminary treatment to CEPT plus disinfection which is scheduled for commissioning by 2011/12.

2009 (Early HATS ADF Stage)

5.126        Table 5.24 and Table 5.25 show the E.coli levels predicted at the beaches in 2009 during early commissioning of the Project for wet season and dry season respectively. Figure 5.16 and Figure 5.17 present the results graphically as contour plots.  The E.coli levels predicted at the beaches in Table 5.24 and Table 5.25 are broken down by two different components (namely the SCISTW effluent alone and other background discharges respectively).

5.127        It should be highlighted that it is not possible to isolate the impact of the SCISTW discharge mathematically as the E.coli levels are reported as geometric mean. The HATS contributions shown in the tables below only represent an indication of the impact from SCISTW discharge alone. To isolate the impact of the SCISTW effluent from other background discharges assumed in the model, sensitivity model runs were performed by including the SCISTW effluent only.  The background contributions shown in tables below were estimated by subtracting the geometric mean level predicted under the sensitivity run from the geometric mean levels resulted from the base case scenarios with both the SCISTW and background discharges.

 

 Table 5.24    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2009 - Wet (or Bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 1a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 1E+7 per 100 ml)

SCISTW effluent (w/o disinfection)

683

761

733

221

194

145

295

486

Other background sources **             

259

283

191

304

282

313

238

130

Total

942

1044

924

525

476

458

533

616

Scenario 1b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+5 per 100 ml)

SCISTW effluent (with disinfection)

14

15

15

4

4

3

6

10

Other background sources **

259

283

191

304

282

313

238

130

Total

273

298

206

308

286

316

244

140

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

Table 5.25    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2009 - Dry (or Non-bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 1a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 1E+7 per 100 ml)

SCISTW effluent (w/o disinfection)

476

539

547

168

164

112

150

204

Other background sources **

152

147

114

122

103

194

439

17

Total

628

686

661

290

267

306

589

221

Scenario 1b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+5 per 100 ml)

SCISTW effluent (with disinfection)

10

11

11

3

3

2

3

4

Other background sources **

152

147

114

122

103

194

439

17

Total

162

158

125

125

106

196

442

21

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

5.128        The predicted E.coli levels would exceed the WQO at all the Tsuen Wan beaches in 2009 under the baseline scenarios (i.e. without disinfection at SCISTW). The model results however showed that provision of disinfection at SCISTW (with the proposed geometric mean effluent E.coli standard of 200,000 no. per 100 ml) would significantly reduce the E.coli levels at Tsuen Wan beaches (with the HATS contribution almost eliminated). Except for Ma Wan Beach, the quality of these beaches may still be affected by the local discharges unrelated to HATS. 

5.129        The beach water quality after ADF commissioning at 2009 is predicted to be impacted partly by:

 

·               Rural areas of Sham Tseng

·               Polluted waters in Rambler Channel due to the expedient connections, misconnections and surface runoff from the dense urban areas in Tsuen Wan, Kwai Chung and Tsing Yi Districts

·               Discharges from other sewage and storm outfalls within the modelled areas 

5.130        Table 5.24 and Table 5.25 also indicated that, without the provision of disinfection facilities at SCISTW, the E.coli impacts from the SCISTW effluent would be significant, which demonstrated the need of disinfection to improve the beach water quality.  With the provision of disinfection at SCISTW, the E.coli contributions from SCISTW would be substantially reduced.  The mean E.coli levels contributed by the disinfected effluent from SCISTW alone as predicted by the model were less than 20 no. per 100 ml.

 

2013 (Late HATS ADF Stage)

5.131        Table 5.26 and Table 5.27 show the E.coli results for year 2013 at the late ADF stage before commissioning of HATS Stage 2A.  Similar to the 2009 case, the model predicted that the provision of disinfection at SCISTW at late ADF stage (with the proposed geometric mean effluent E.coli standard of 200,000 no. per 100 ml) would significantly reduce the E.coli levels at the beaches.  It was found that the E.coli impacts from the background sources were improved by 2013 as compared to the 2009 case.  This was caused by the local improvement works as well as the upgrading of PPSTW, which is scheduled for commissioning in 2011/12.  It was predicted that the beach water quality would comply with the WQO in 2013 at all the beaches, except the Approach Beach in dry season, with the provision of disinfection facilities at SCISTW.  The contributions from the disinfected effluent from SCISTW ranged from 2 to 12 E.coli per 100 ml only. The residual impact predicted at the beaches was caused by other background pollution sources as mentioned in Section 5.129.

 

Table 5.26    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2013 – Wet (or Bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 2a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 1E+7 per 100 ml)

SCISTW effluent (w/o disinfection)

525

591

565

144

125

88

203

336

Other background sources **

97

137

73

147

118

159

90

52

Total

622

728

638

291

243

247

293

388

Scenario 2b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+5 per 100 ml)

SCISTW effluent (with disinfection)

11

12

11

3

3

2

4

7

Other background sources **

97

137

73

147

118

159

90

52

Total

108

149

84

150

121

161

94

59

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

Table 5.27    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2013 - Dry (or Non-bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 2a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 1E+7 per 100 ml)

SCISTW effluent (w/o disinfection)

432

491

496

144

140

94

127

180

Other background sources **

101

103

78

99

76

167

360

9

Total

533

594

574

243

216

261

487

189

Scenario 2b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+5 per 100 ml)

SCISTW effluent (with disinfection)

9

10

10

3

3

2

3

4

Other background sources **

101

103

78

99

76

167

360

9

Total

110

113

88

102

79

169

363

13

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

 

2020 (Late Phase of HATS Stage 2A)

5.132        Table 5.28 and Table 5.29 show the E.coli results for year 2020 at late phase of HATS Stage 2A.  With disinfection at SCISTW, the E.coli levels predicted at the beaches would be significantly reduced.  Table 5.28 and Table 5.29 show that the absolute contribution from the undisinfected effluent of SCISTW in Stage 2A was larger than that in ADF stage (2009 and 2013). This was due to the fact that more sewage flow would be intercepted to the SCISTW under HATS Stage 2A and hence the effluent E.coli loading in the undisinfected effluent would be increased. The absolute contribution from the disinfected effluent of SCISTW during the late phase of HATS Stage 2A was smaller than that in ADF stage, as the proposed disinfection level for Stage 2A (with a geometric mean effluent E.coli standard of 20,000 no. per 100 ml) was higher than that for ADF stage (with a geometric mean effluent E.coli standard of 20,000 no. per 100 ml).  At the ADF stage, the existing effluent culvert system would be used for chlorine contact whilst at Stage 2A, a new chlorine contact tank would be built for the HATS effluent to enhance the disinfection performance. Although the recommended dosage for ADF stage would be the similar as that for Stage 2A, the resulted disinfection level for Stage 2A would be higher than that for ADF stage due to the longer contact time available under the Stage 2A.

 

Table 5.28    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2020 – Wet (or Bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 3a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 1E+7 per 100 ml)

SCISTW effluent (w/o disinfection)

727

817

778

199

171

122

280

479

Other background sources **

72

86

45

149

116

166

80

38

Total

799

903

823

348

287

288

360

517

Scenario 3b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+4 per 100 ml)

SCISTW effluent (with disinfection)

2

2

2

1

1

1

1

1

Other background sources **

72

86

45

149

116

166

80

38

Total

74

88

47

150

117

167

81

39

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

Table 5.29   Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2020 - Dry (or Non-bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 3a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 1E+7 per 100 ml)

SCISTW effluent (w/o disinfection)

611

693

694

202

197

131

179

271

Other background sources **

80

69

56

97

70

171

343

3

Total

691

762

750

299

267

302

522

274

Scenario 3b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+4 per 100 ml)

SCISTW effluent (with disinfection)

2

2

2

1

1

1

1

1

Other background sources **

80

69

56

97

70

171

343

3

Total

82

71

58

98

71

172

344

4

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

5.133        It was predicted that the beach water quality would comply with the WQO during Stage 2A at all the beaches, except the Approach Beach in dry season, with the provision of disinfection facilities at SCISTW. The contribution from the disinfected effluent from SCISTW was negligible under Stage 2A (ranged from 1 to 2 E.coli per 100 ml only). The residual impact predicted by the model was caused by other background pollution sources.

Ultimate Year (Late Phase of HATS Stage 2B)

5.134        Table 5.30 and Table 5.31 show that similar to the HATS Stage 2A case, the contribution from the disinfected effluent from SCISTW was negligible in the ultimate year under Scenario 4b. The residual impacts predicted by the model were caused by other background pollution sources.

5.135        The model results showed that the contribution from the undisinfected effluent from HATS Stage 2B under Scenario 4a (with an effluent E.coli value of 2.96E+5 no. per 100 ml) would be significantly greater than the case with disinfection at SCISTW. The HATS contributions ranged from 4 to 24 no. per 100 ml which however did not contribute any new WQO exceedance at the beaches.  However, it is important to note that modelling cannot fully predict the high variability of some factors (e.g. salinity, natural ultra violet radiation, and wind) that affect the density of E. coli in the receiving waters. Therefore, planning for disinfection in Stage 2B is recommended, though this provision may be reviewed in the light of actual water quality monitoring results after commissioning of the ADF.

 

Table 5.30    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for Ultimate Year - Wet (or Bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 4a–without disinfection at SCISTW (base case scenario using an effluent E.coli value of 2.96E+5 per 100 ml)

SCISTW effluent (w/o disinfection)

24

27

26

7

6

4

9

16

Other background sources **

84

99

51

183

140

204

92

38

Total

108

126

77

190

146

208

101

54

Scenario 4b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+4 per 100 ml)

SCISTW effluent (with disinfection)

2

2

2

1

1

1

1

2

Other background sources **

84

99

51

183

140

204

92

38

Total

86

101

53

184

141

205

93

40

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

Table 5.31    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for Ultimate Year - Dry (or Non-bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 4a–without disinfection at SCISTW (base case scenario using an effluent E.coli value of 2.96E+5 per 100 ml)

SCISTW effluent (w/o disinfection)

21

24

24

7

7

5

6

10

Other background sources **

95

78

63

115

81

201

385

3

Total

116

102

87

122

88

206

391

13

Scenario 4b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+4 per 100 ml)

SCISTW effluent (with disinfection)

2

2

2

1

1

1

1

1

Other background sources **

95

78

63

115

81

201

385

3

Total

97

80

65

116

82

202

386

4

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

5.136        The high background E.coli levels predicted at Ting Kau and Casam are due to the nearby storm pollution loading assumed in the model.  It is believed that the continuous efforts by the government to improve the sewerage system and implement water pollution control measures and enforcement in these catchments will eliminate the residual local water quality problems at the Ting Kau and Casam beaches in the long term.

 

Discussions on the Modelling Results for Bathing Beaches

5.137        The model predicted that the E.coli levels in wet seasons are in general higher than that in dry seasons at all the beaches except for Approach Beach.  This could be explained by the differences in the flow regime between dry and wet seasons. In wet seasons, the coastal currents are in general from southwest to northeast and the Pearl river discharges would flow on the surface to the west which brings more HATS effluent from the south and other background sources from the east to the Tsuen Wan coast.  In dry seasons, the coastal currents are generally from east to west and the Pearl river discharges flow to the southwest.  Thus, during dry seasons, Approach Beach would be subject to the largest influence from the polluted marine water at the inner Rambler Channel due to the direction of coastal currents (Figure 5.17).  Other beaches are however located in more embayed areas (as compared to Approach beach) and are therefore sheltered from the effect in dry seasons.

5.138        For the case “with disinfection at SCISTW” in 2013 (late ADF stage), 2020 (late phase of Stage 2A) and ultimate year (late phase of Stage 2B) as shown in Table 5.26 to Table 5.31, the differences in the model results between the dry season case and the wet season case are substantially smaller as compared to the 2009 case (early ADF stage) at Anglers’, Gemini, Hoi Mei Wan, Casam, Lido and Ting Kau.  As pointed out before, these beaches should be subject to a larger impact from the HATS effluent in the south and other background sources in the east under the wet season scenarios as compared to the dry season scenarios because of the coastal currents.  These pollution sources would be, however, mostly eliminated in 2013 (late ADF stage) due to the provision of disinfection facilities at SCISTW in 2009 and Pillar Point STW in 2011/12 which thus diminishes the potential impacts in the wet seasons.

5.139        The model results indicated that the residual E.coli levels predicted at Approach Beach would likely breach the WQO in dry season and this situation would remain the same in the ultimate year.  The residual impact predicted at Approach Beach was caused by the polluted storm discharges from the Tsuen Wan, Kwai Chung and Tsing Yi Districts.  To address the uncertainties on the programme for implementing sewerage improvement and water pollution control measures in the Tsuen Wan and Kwai Tsing catchments, it is assumed in this modelling exercise that 10% of the total load generated in these catchments would be lost to the marine waters and no further reduction on these storm discharges would be achieved in the future for conservative assessment.  This is a worst case assumption and would provide an indication on the maximum extent of the potential water quality impacts.  It is believed that the continuous efforts by the government to improve the sewerage system and implement water pollution control measures and enforcement in these catchments will eliminate the residual local water quality problems at Approach beach in the long term.

5.140        For the case “with disinfection at SCISTW” as shown in Table 5.28 to Table 5.31, the predicted impacts at the beaches are slightly worsened under the ultimate scenario as compared to the 2020 case.  This was caused by the increase in the background storm loading assumed in the model due to the projected population growth between 2020 and the ultimate year given that a constant sewage interception rate of 90% was assumed for both 2020 and ultimate year. 

 

Consideration of Lower Disinfection Level

5.141        Additional model runs were performed for 2013 (ADF stage) and 2020 (Stage 2A) using a lower disinfection level as sensitivity tests, namely Scenario 2c and Scenario 3c respectively.  The objective was to determine the minimum chlorine dosage required for protecting the beneficial use of Tsuen Wan beaches and thus minimizing the potential generation of CBP.  The ultimate scenario (Stage 2B) was not tested because the differences in the HATS contributions at the beaches were small between the Stage 2A case and the Stage 2B case under the “with disinfection” scenario (see Table 5.28 to Table 5.31).  The sensitivity test results for Stage 2A, namely Scenario 3c, would be used as reference for determining the optimum effluent standard for Stage 2B. An E.coli level of 2,000,000 no. per 100 ml and 200,000 no. per 100 ml was assumed under Scenario 2c and Scenario 3c respectively.  Table 5.32 to Table 5.35 show the results of these sensitivity tests. Figure 5.20 and Figure 5.21 show the contour plots for these sensitivity tests. The model results for the case using the original disinfection level (Scenario 2b and Scenario 3b) are also included in Table 5.32 - Table 5.35 and Figure 5.20Figure 5.21 for comparison.

 

Table 5.32    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2013 – Sensitivity Test – Wet (or Bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 2c – with disinfection at SCISTW (effluent E.coli level: 2,000,000 per 100 ml)

SCISTW effluent (w/o disinfection)

95

129

102

25

22

15

35

59

Other background sources **

97

137

73

147

118

159

90

52

Total

192

266

175

172

140

174

125

111

Scenario 2b – with disinfection at SCISTW (effluent E.coli level: 200,000 per 100 ml)

SCISTW effluent (with disinfection)

11

12

11

3

3

2

4

7

Other background sources **

97

137

73

147

118

159

90

52

Total

108

149

84

150

121

161

94

59

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

Table 5.33    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2013 – Sensitivity Test - Dry (or Non-bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 2c – with disinfection at SCISTW (effluent E.coli level: 2,000,000 per 100 ml)

SCISTW effluent (w/o disinfection)

103

133

112

36

34

24

72

37

Other background sources **

101

103

78

99

76

167

360

9

Total

204

236

190

135

110

191

432

46

Scenario 2b – with disinfection at SCISTW (effluent E.coli level: 200,000 per 100 ml)

SCISTW effluent (with disinfection)

9

10

10

3

3

2

3

4

Other background sources **

101

103

78

99

76

167

360

9

Total

110

113

88

102

79

169

363

13

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

Table 5.34    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2020 – Sensitivity Test - Wet (or Bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 3c – with disinfection at SCISTW (effluent E.coli level: 200,000 per 100 ml)

SCISTW effluent (w/o disinfection)

16

31

17

5

4

3

6

10

Other background sources **

72

86

45

149

116

166

80

38

Total

88

117

62

154

120

169

86

48

Scenario 3b – with disinfection at SCISTW (effluent E.coli level: 20,000 per 100 ml)

SCISTW effluent (with disinfection)

2

2

2

1

1

1

1

1

Other background sources **

72

86

45

149

116

166

80

38

Total

74

88

47

150

117

167

81

39

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

 

Table 5.35    Predicted Geometric Mean E.coli Levels at Tsuen Wan Beaches for 2020 – Sensitivity Test - Dry (or Non-bathing) Season

Pollution Source

 

Anglers'

Gemini

Hoi Mei Wan

Casam

Lido

Ting Kau

Approach

Ma Wan

Geometric Mean * (no. per 100 ml)

WQO:

180

Scenario 3c – with disinfection at SCISTW (effluent E.coli level: 200,000 per 100 ml)

SCISTW effluent (w/o disinfection)

18

30

20

6

6

4

13

6

Other background sources **

80

69

56

97

70

171

343

3

Total

98

99

76

103

76

175

356

9

Scenario 3b – with disinfection at SCISTW (effluent E.coli level: 20,000 per 100 ml)

SCISTW effluent (with disinfection)

2

2

2

1

1

1

1

1

Other background sources **

80

69

56

97

70

171

343

3

Total

82

71

58

98

71

172

344

4

Shaded cell – exceedance of beach water quality objective.

The model results are subject to uncertainties and limitations as discussed in Appendix 5.2a.

*    See Section 5.124.

**   The major background sources are described in Section 5.129.

 

5.142        It should be noted that the required operational range of chlorine dosage could be reduced from 11 - 15 mg/l respectively to 10 - 14 mg/l due to the change of effluent E.coli value from 200,000 no. per 100 ml to 2,000,000 no. per 100 ml during ADF stage. The model results as shown in Table 5.32 and Table 5.33 indicated that the reduction of disinfection level during ADF stage would reduce the WQO compliances at the beaches. The contributions from SCISTW effluent predicted at the ADF stage under the sensitivity test (with an effluent E.coli value of 2,000,000 no. per 100 ml) would range from 15 up to 133 E.coli per 100 ml which at the upper end of the range is a large proportion of the WQO of 180 no. per 100 ml.  The effluent E.coli levels between 200,000 no. per 100 ml to 2,000,000 no. per 100 ml were not considered further because the reduction of chlorine dosage due to such change would be insignificant. 

5.143        The sensitivity test results for 2020 (Stage 2A) showed that the degree of WQO compliance would be similar between the two selected effluent E.coli levels (i.e. 20,000 no. per 100 ml and 200,000 no. per 100 ml) but the HATS contribution would increase to a level up to 31 no. per 100 ml at Gemini if the lower standard of 200,000 no. per 100 ml is used.  Given the same effluent standard of 200,000 no. per 100 ml, the HATS contribution at Gemini for Stage 2A (31 no. per 100 ml) is greater than that for ADF stage (2 – 15 no. per 100 ml) because more sewage flow would be intercepted to the SCISTW under Stage 2A and hence more effluent loading would be discharged from the plant.  It is considered that the operational range of chlorine dosage could be reduced from 10 - 14 mg/l to 10 - 13 mg/l due to the change of geometric mean effluent E.coli value from 20,000 no. per 100 ml to 200,000 no. per 100 ml under Stage 2A.  Optimisation of the dosage would be conducted during the commissioning and operation.

 

Impact Summary

5.144        Water quality modelling was performed to estimate the optimum disinfection level for the proposed disinfection facilities, on one hand, to protect the health of the bathing beach users and, on the other hand, to minimize the chlorine dose and thus the generation of CBP.  Modelling was also performed in a way that the impact of the HATS effluent was separated from the impact from other background pollution discharges within the Study Area.

5.145        The model results indicated that the levels of E.coli would exceed the WQO at the beaches if no disinfection is provided at SCISTW during both Stage 1 and Stage 2A.  The mean E.coli levels contributed from the undisinfected HATS effluent at the beaches could range from 88 to 817 no. per 100 ml during Stage 1 and Stage 2A as compared to the WQO of 180 no. per 100 ml.  The model results also indicated that provision of disinfection facilities at SCISTW would significantly improve the WQO compliances at the beaches, based on the geometric mean E.coli effluent standards of 200000 and 20000 no. per 100 ml for ADF stage and Stage 2A respectively.  The mean E.coli levels contributed from the disinfected HATS effluent at the beaches would range from 2 to 15 no. per 100 ml during ADF stage and 1 to 2 no. per 100 ml during Stage 2A.  These contributions were low as compared to the WQO of 180 no. per 100 ml.  From this perspective, it is affirmative that provision of disinfection facilities at SCISTW could facilitate the reopening of those closed beaches at Tsuen Wan and minimize the human health risk to the current beach users.

5.146        Sensitivity tests were carried out to investigate the water quality impacts due to the reduction of effluent E.coli level from 200,000 no. per 100 ml to 2,000,000 no. per 100 ml for ADF stage.  The required range of chlorine dosage could be reduced from 11 - 15 mg/l to 10 - 14 mg/l due to the change of effluent E.coli level from 200,000 no. per 100 ml to 2,000,000 no. per 100 ml. The sensitivity results showed that the reduction of disinfection level would reduce the WQO compliances at the beaches.  The HATS effluent contributions at the Tsuen Wan beaches would range from 15 to 133 E.coli per 100 ml after reducing the disinfection level.  At the upper end of the range, these contributions are a large proportion of the WQO of 180 no. per 100 ml.  It is therefore not recommended to reduce the disinfection level from 200,000 no. per 100 ml to 2,000,000 no. per 100 ml for ADF stage. The effluent E.coli levels between 200,000 no. per 100 ml and 2,000,000 no. per 100 ml were not further considered because the reduction of chlorine dosage due to such change would be insignificant. 

5.147        As pointed out in Section 5.3, at the ADF stage, the existing effluent culvert system would be used for chlorine contact and the corresponding chlorine contact times would be less than 10 minutes.  Due to the short contact time, the more stringent E.coli standard of 20,000 no. per 100 ml would not be effectively achieved at the ADF stage and is therefore not further considered for sensitivity analysis.  Balancing the limitations and environmental impacts during the ADF stage, the geometric mean effluent E.coli standard of 200,000 no. per 100 ml is recommended as the optimum disinfection level for the ADF, and it is confirmed by the WQ modelling that this optimum disinfection level can effectively remove the HATS contribution to the impact on the Tsuen Wan beaches.

5.148        Sensitivity tests were also carried out to investigate the water quality effect due to the reduction of effluent E.coli level from 20,000 no. per 100 ml to 200,000 no. per 100 ml for HATS Stage 2A.  The required range of chlorine dosage could be reduced from 10 - 14 mg/l to 10 - 13 mg/l due to the change of effluent E.coli level from 20,000 no. per 100 ml to 200,000 no. per 100 ml. Given the same geometric mean effluent standard of 200,000 no. per 100 ml, the HATS contribution at the beaches for Stage 2A (ranged from 3 to 31 no. per 100 ml) is greater than that for ADF stage (ranged from 2 to 15 no. per 100 ml) as a result of flow build-up at HATS Stage 2A due to the collection of additional flows from northern and western areas of HK Island. Considering that the E.coli levels normally exhibit large fluctuations at the beaches based on past monitoring data (Table 5.16) and in view of the flow build-up at HATS Stage 2A, the safer standard of 20,000 no. per 100ml is recommended to minimize the human health risk to the future beach users during HATS Stage 2A.  The level of 20,000 no. per 100ml is considered a reasonably safe standard to provide adequate protection for the beach users and this standard can be effectively achieved at HATS Stage 2A (without the need for excessive chlorine dosage) due to the provision of a new chlorine contact tank to increase the chlorine contact time at the SCISTW by 2014.

5.149        Based on the model result, the E.coli contribution of undisinfected effluent from HATS Stage 2B at the beaches could vary from 4 to 27 no. per 100 ml.  As modelling cannot fully predict the high variability of some factors (e.g. salinity, natural ultra violet radiation, and wind) that affect the density of E. coli in the receiving waters and there is still uncertainty in the biological process to be adopted, it is therefore recommended that planning for disinfection for HATS Stage 2B should be considered to minimize the potential human health risk to future beach users and to comply with the existing Government policy of providing disinfection to all large discharges of sewage effluent and to ensure consistent compliance with the regulatory standards at sensitive receivers. The contribution from the disinfected effluent from HATS Stage 2B would be small (ranged from 1 to 2 E.coli per 100 ml only) based on the proposed effluent standard of 20,000 no. per 100 ml.  Based on the same effluent standard of 20,000 no. per 100 ml, the required chlorine dosage for HATS Stage 2B (2 – 3 mg/l) would be significantly smaller than that for Stage 2A (10 - 14 mg/l) due to the substantial reduction in E.coli loading from the secondary treatment process. Based on the same considerations for Stage 2A discussed in Section 5.148, it is not recommended to adopt the lower effluent E.coli standard of 200,000 no. per 100 ml in view that the effluent flow of Stage 2B would be even larger than that for Stage 2A.  The recommended effluent standard for Stage 2B would be 20,000 no. per 100 ml. A post-project monitoring should be implemented to confirm the predictions of water quality made in this EIA report at relevant stages of the HATS. The need of disinfection at Stage 2B will be subject to the prevailing environmental conditions at the time before commissioning of Stage 2B.

 

WSD Flushing Water Intakes

5.150        The water quality impacts upon the WSD flushing water intakes are assessed in subsequent sections based on the optimum disinfection levels recommended for protection of the Tsuen Wan beaches.

5.151        Table 5.36 and Table 5.37 tabulate the maximum E.coli levels predicted at the three WSD flushing water intakes for ADF stage (2009 and 2013) and late phase of Stage 2A (2020) assuming that the effluent E.coli value would be 200,000 no. per 100 ml (for ADF stage) and 20,000 no. per 100 ml (for Stage 2A and Stage 2B).  Results for both the operational scenarios (with disinfection at SCISTW) and the baseline scenarios (without disinfection at SCISTW) for ADF stage and Stage 2A are included in Table 5.36 and Table 5.37 for comparison.

 

Table 5.36   Predicted Maximum E.coli Levels at WSD Flushing Water Intakes - Wet Season

 

2009 (ADF Stage)

2013 (ADF Stage)

2020 (Stage 2A)

Pollution Source

 

WSD18

WSD19

WSD20

WSD18

WSD19

WSD20

WSD18

WSD19

WSD20

Maximum Level (no. per 100 ml)

WSD Standard:

<20000 at any time

Without disinfection at SCISTW

SCISTW effluent (w/o disinfection)

19653

23805

13373

18470

22528

13099

25984

31665

19090

Other background sources **

8412

22120

2888

7193

21298

2611

2213

1291

2522

Total

28065

45925

16261

25663

43826

15710

28197

32956

21612

With disinfection at SCISTW

SCISTW effluent (with disinfection)

393

476

267

369

451

262

52

63

38

Other background sources **

8412

22120

2888

7193

21298

2611

2213

1291

2522

Total

8805

22596

3155

7562

21749

2873

2265

1354

2560

Shaded cell – exceedance of WSD standard.

**   The major background sources are described in Section 5.129.

 

Table 5.37   Predicted Maximum E.coli Levels at WSD Flushing Water Intakes - Dry Season

 

2009 (ADF Stage)

2013 (ADF Stage)

2020 (Stage 2A)

Pollution Source

 

WSD18

WSD19

WSD20

WSD18

WSD19

WSD20

WSD18

WSD19

WSD20

Maximum Level (no. per 100 ml)

WSD Standard:

<20000 at any time

Without disinfection at SCISTW

SCISTW effluent (w/o disinfection)

17136

18730

25741

17034

18574

26020

25567

26213

38875

Other background sources **

6864

9826

2721

6615

9864

2697

3224

4633

3024

Total

24000

28556

28462

23649

28438

28717

28791

30846

41899

With disinfection at SCISTW

SCISTW effluent (with disinfection)

343

375

515

341

371

520

51

52

78

Other background sources **

6864

9826

2721

6615

9864

2697

3224

4633

3024

Total

7207

10201

3236

6956

10235

3217

3275

4685

3102

Shaded cell – exceedance of WSD standard.

**   The major background sources are described in Section 5.129.

 

5.152        The maximum E.coli levels predicted at all the three WSD flushing water intakes in western Victoria Harbour would exceed the WSD standard of 20000 no. per 100 ml under the baseline scenarios (i.e. without disinfection at SCISTW) for ADF stage (2009 and 2013) and Stage 2A (2020). The model results showed that the provision of disinfection at SCISTW would significantly reduce the E.coli levels at the intake point but the predicted maximum values would still breach the WSD standard at Sheung Wan during ADF stage (2009 and 2013) because of the contribution from the background source. 

5.153        The residual impact predicted at Sheung Wan (with the Project commissioned) during ADF stage was mainly contributed by the sewage effluent discharged from the Central PTW outfall which is situated in close proximity of the intake point. The absolute levels contributed from the disinfected effluent from SCISTW at Sheung Wan ranged from 371 to 451 no. per 100 ml only which were low as compared to the background levels of 9864 to 21298 no. per 100 ml and the WSD standard of 20000 no. per 100 ml.  It can be seen that the background values predicted at Sheung Wan were substantially smaller under Stage 2A when effluent from Central PTW is intercepted to the SCISTW by the HATS Stage 2A sewage conveyance system. HATS Stage 2A is scheduled for implementation in 2014 and the improvement at Sheung Wan intake is expected to be seen thereafter.  The model results as shown in the table above indicated that full compliance with the WSD standard would be achieved at Sheung Wan in 2020 at the late stage of HATS 2A with the provision of disinfection facilities at SCISTW. 

5.154        Table 5.38 and Table 5.39 tabulate the maximum E.coli levels predicted at the three WSD flushing water intakes for Stage 2B (ultimate scenario). To address the uncertainty of the biological treatment process for HATS Stage 2B, sensitivity analysis was carried out using both the effluent E.coli value of 2.95+E5 no. per 100 ml and a more adverse E.coli level of 1E+6 no. per 100 ml for the undisinfected effluent. The model results indicated that full compliance with the WSD standard would be achieved at Stage 2B under both the “with disinfection at SCISTW” case and the “without disinfection at SCISTW” case.

 

 

Table 5.38     Predicted Maximum E.coli Levels at WSD Flushing Water Intakes for Stage 2B - Wet Season

Pollution Source

 

WSD18

WSD19

WSD20

Maximum Level (no. per 100 ml)

WQO:

<20000 at any time

Scenario 4a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 2.96E+5 per 100ml)

SCISTW effluent (w/o disinfection)

858

1033

626

Other background sources**

2893

1466

2913

Total

3751

2499

3539

Scenario 4b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+4 per 100ml)

SCISTW effluent (with disinfection)

58

70

42

Other background sources**

2893

1466

2913

Total

2951

1536

2956

Shaded cell – exceedance of WSD standard.

**   The major background sources are described in Section 5.129.

 

Table 5.93     Predicted Maximum E.coli Levels at WSD Flushing Water Intakes for Stage 2B - Dry Season

Pollution Source

 

WSD18

WSD19

WSD20

Maximum Level (no. per 100 ml)

WQO:

<20000 at any time

Scenario 4a – without disinfection at SCISTW (base case scenario using an effluent E.coli value of 2.96E+5 per 100ml)

SCISTW effluent (w/o disinfection)

915

925

1398

Other background sources**

3769

5274

3422

Total

4684

6199

4820

Scenario 4b – with disinfection at SCISTW (base case scenario using an effluent E.coli value of 2E+4 per 100ml)

SCISTW effluent (with disinfection)

62

63

95

Other background sources**

3769

5274

3422

Total

3831

5337

3516

Shaded cell – exceedance of WSD standard.

**   The major background sources are described in Section 5.129.

5.155        The model results indicated that the recommended disinfection level for SCISTW would be adequate to protect the flushing water intakes in western Harbour.

Secondary Contact Recreation Subzones

5.156        The water quality impacts upon the secondary contact recreation subzones are assessed in subsequent sections based on the optimum effluent E.coli standards recommended for protection of the Tsuen Wan beaches (i.e. 200,000 no. per 100 ml for ADF stage and 20,000 no. per 100 ml for Stage 2A and Stage 2B).

5.157        Figure 5.9 and Figure 5.10 show that, without disinfection at SCISTW, the E.coli levels predicted at the secondary contact subzones along the Tsuen Wan and Tuen Mun coast would exceed the WQO of 610 no. per 100 ml in 2009.  For 2013 and 2020, the exceedances were only predicted at the Tsuen Wan coast due to the reduction in the background pollution loading in North Western WCZ. 

5.158        With the provision of disinfection facilities at SCISTW, full compliance with the WQO was predicted at the secondary contact subzones along the Tsuen Wan coast for ADF stage (2009 and 2013) and Stage 2A (2020).

5.159        Some residual impacts were however predicted at the secondary contact subzones along Tuen Mun coast which were shown to be the result of other background pollution sources in the modelling area and were not related to the SCISTW effluent.  Figure 5.13 and Figure 5.14 indicated that the influence zone of the disinfected HATS effluent plume would be very localized in close proximity of the SCISTW outfall, and would not contribute to any impact on the secondary contact recreation zones.

5.160        The model results indicated that the recommended disinfection level for SCISTW would be adequate to protect the beneficial uses of the secondary contact recreation subzones.

 

Sensitivity Analysis to the Schedule of Stage 2B Implementation

5.161        For this water quality modelling and assessment, it is assumed in the base case scenarios that Stage 2B would be implemented by 2021.  In fact, the schedule of Stage 2B implementation would be subject to the review on population / flow build-ups and water quality conditions to be conducted in 2010/2011.  Based on the assessment results, the same effluent E.coli standards of 20,000 no. per 100 ml would be maintained for both Stage 2A and Stage 2B.  It is therefore considered that the possible change to the schedule of Stage 2B implementation would not be an issue of concern with regard the potential E.coli impacts upon the receiving marine waters and water sensitive receivers. It should be noted that the effluent from Stage 2B would have a greater effect on the receiving water as compared to the Stage 2A conditions as the effluent flow rate for Stage 2B would be higher.  The model predicted that the effluent from Stage 2B under the ultimate flow condition with the recommended E.coli standard of 20,000 no. per 100 ml would not cause any unacceptable impacts to the identified sensitive receivers as discussed in previous sections.

 

Whole Effluent Toxicity Test

 

5.162        Whole effluent toxicity test (WETT) was conducted to determine the whole effluent toxicity of C/D CEPT effluent from SCISTW and C/D secondary treated effluent from Tai Po Sewage Treatment Works (TPSTW) and Sha Tin Sewage Treatment Works (STSTW) for the following five local marine species:

l    Amphipod (Melita longidactyla), with 48-hour survival test

l    Barnacle larvae (Balanus amphitrite), with 48-hour survival test

l    Fish (Lutjanus malabaricus), with 48-hour survival test

l    Shrimp (Metapenaeus ensis), with 48-hour survival test

l    Diatom (Skeletonema costatum), with 7-day growth inhibition test

5.163        The toxicity tests for amphipod, barnacle larvae, fish and shrimp were conducted to determine the acute toxicity of the effluents to the 4 animal species while the toxicity tests for diatom were to determine the chronic toxicity of the effluents to plants.  Table 5.40a and Table 5.40b summarize the results obtained in the WETT for CEPT effluent whilst Table 5.41a and Table 5.41b give the results for secondary treated effluent.

 

Table 5.40a          Summary of WETT Result for CEPT Effluent (Acute Toxicity) 

Test Species

Composite CEPT Effluent

Chlorinated/Dechlorinated CEPT Effluent

48-hr LC50a

NOEC b

48-hr LC50a

NOEC b

Amphipod

N.D

>85.0%

N.D

>85.0%

Barnacle Larvae

44.9%

26.6%

40.2%

26.6%

Fish

N.D

30.8%

N.D

>81.9%

Shrimp

N.D

>81.0%

N.D

>81.0%

Note:     a48-hr LC50, the lethal concentration of effluent to 50% of test animals after 48 hours of exposure. 

b No-Observable-Effect-Concentration, the highest concentration of effluent producing effects not significantly different from responses to controls

N.D = Not Determined, less than 50% mortality was recorded when animal species were exposed to the highest concentration of effluent

 

Table 5.40b          Summary of WETT Result for CEPT Effluent (Chronic Toxicity) 

Test Species

Composite CEPT Effluent

Chlorinated/Dechlorinated CEPT Effluent

7-day IC50a

NOEC b

7-day IC50a

NOEC b

Diatom

34.9%

27.2%

39.7%

27.2%

Note:     a7-day IC50, the inhibition concentration to 50% of organisms after 7 days of exposure.

b No-Observable-Effect-Concentration, the highest concentration of effluent producing effects not significantly different from responses to controls

 

Table 5.41a          Summary of WETT Result for Secondary Treated Effluent (Acute Toxicity) 

Test Species

Composite Secondary Treated Effluent

Chlorinated/Dechlorinated Secondary Treated  Effluent

48-hr LC50

NOEC

48-hr LC50

NOEC

Amphipod

N.D1

N.D2

N.D1

N.D2

Barnacle Larvae

N.D1

N.D2

N.D1

N.D2

Fish

N.D1

N.D2

N.D1

N.D2

Shrimp

N.D1

N.D2

N.D1

N.D2

Diatom

N.D1

N.D2

N.D1

N.D2

N.D = Not Determined,

1 LC50 could not be determined - less than 50% mortality was recorded when animal species were exposed to the highest concentration of effluent

2 NOEC could not be determined - the highest concentration of effluent did not produce effects significantly different from controls

 

Table 5.41b          Summary of WETT Result for Secondary Treated Effluent (Chronic Toxicity)

Test Species

Composite Secondary Treated Effluent

Chlorinated/Dechlorinated Secondary Treated  Effluent

7-day IC50

NOEC

7-day IC50

NOEC

Diatom

N.D1

N.D2

N.D1

N.D2

N.D = Not Determined,

1 IC50 could not be determined - less than 50% growth inhibition was recorded when plant species were exposed to the highest concentration of effluent

2 NOEC could not be determined - the highest concentration of effluent did not produce effects significantly different from controls

 

5.164        The WETT results indicated that both raw CEPT effluent and C/D CEPT effluent generally do not exert acute toxicity effect to amphipod, fish and shrimp as no 48-hr LC50 was determined (Table 5.40a).  However, LC50 and IC50 were observed for barnacle larvae and diatom respectively which implied that some degree of acute toxicity and chronic toxicity effect was exerted on barnacle larvae and diatom respectively from both the raw CEPT effluent and C/D CEPT effluent. 

5.165        Statistical analysis was conducted for the toxicity test data of barnacle larvae and diatom to determine whether C/D process induced additional toxicity in the CEPT effluent. Two-way analysis of variance (ANOVA) test using software SigmaStat was conducted, which compares the difference between the toxicity data of composite CEPT effluent and C/D CEPT effluent with consideration of the effects of difference in effluent concentrations.  The analysis showed that the C/D process did not induce statistically significant difference to the toxic effect in CEPT effluent to barnacle larvae and diatom, i.e. the C/D process did not induce additional toxicity.

5.166        Based on the WETT test conducted for the effluent from TPSTW and STSTW, no LC50 values could be derived for fish, shrimp, amphipod and barnacle larvae due to the low mortality (Table 5.41a).  Also, no IC50 value could be calculated as the maximum growth inhibition for diatoms was low.  Based on the statistical tests, no significant differences were found between the seawater control and various strengths (up to 100%) of raw and C/D secondary treated effluent samples.  Hence, it was concluded that the C/D secondary treated effluent samples would not pose any acute or chronic toxicity to the test organisms. 

 

 

Far Field Modelling Results for TRC and CBP

5.167        Far field water quality modelling was conducted for TRC and 34 CBP compounds as listed in Table 5.9a. The model results have taken into account other concurrent discharges such as Pillar Point STW, Sha Tin STW and Tai Po STW where chlorination and dechlorination were assumed to be their disinfection method for worst-case assessment.  Possible discharges of TRC and CBP from spent cooling water were also included in the model for cumulative assessment.  The initial CBP levels assumed in the effluent discharges and other concurrent discharges are based on the laboratory CBP testing in the C/D effluent samples as discussed in Section 5.78

5.168        The contour plots for TRC are shown in Figure 5.22 and Figure 5.23.  These contour plots present the maximum values predicted over the whole model simulation period.  The model results showed that the predicted maximum values at and near the SCISTW outfall complied well the assessment criterion of 0.008 mg/l.  The contour plots indicated some localized TRC exceedances along the coastlines.  These localized exceedances were contributed from the background sources and were not related to the HATS discharges.  

5.169        The predicted maximum values for all the identified CBP compounds complied well with their corresponding ambient water objectives as shown in Table 5.9a. The model results are presented as contour plots for selected CBP compounds including dichloroacetic acid, trichloroacetic acid, dibromoacetic acid and bromoform in Figure 5.24 to Figure 5.31. The contour plots showed that the predicted maximum levels of dichloroacetic acid were higher than the measured ambient levels near the outfall location under ADF stage and Stage 2A during both dry and wet season.  The predicted maximum levels of trichloroacidic acid were also higher than the measured ambient levels during ADF stage and Stage 2A under the wet season scenarios. The predicted maximum levels for bromoform and dibromoacetic acid exceeded the measured ambient levels near the outfall location during Stage 2B under the wet season scenarios.  The predicted maximum values for all the remaining CBP compounds were within the measured ambient levels.  

5.170        Amongst all the 34 CBP compounds, the mixing zones of dichloroacetic acid (during ADF stage and Stage 2A) and bromoform (during Stage 2B) were predicted to be the largest.  Table 5.42 shows the maximum dimensions of their mixing zones. These mixing zones would however be limited in areas close to the SCISTW submarine outfall to the south of Tsing Yi Island.  The approximate location and extent of the mixing zone with respect to the SCISTW outfall are given in Figure 5.31a.  It should be hightlighted that the mixing zone dimensions provided in this EIA represent a conservative estimation as they were established based on the maximum values predicted over the entire simulation period.

 

Table 5.42   Maximum Dimensions of Mixing Zones for CBP See Notes 1 and 2

Scenarios

Chemical

Maximum Dimension of Mixing Zone (m2)

Minimum Dilution at the Edge of Mixing Zone

Figure Reference

Wet Season

Dry Season

2009 - ADF Stage

Dichloroacetic acid Note 1

1385 x 1105

1110 x 460

62

5.24 and 5.25

2013 - ADF Stage

Dichloroacetic acid Note 1

1400 x 1505

1110 x 460

60

5.24 and 5.25

2020 – Stage 2A

Dichloroacetic acid Note 1

1685 x 2450

1400 x 1505

50

5.24 and 5.25

Ultimate - Stage 2B

Bromoform Note 2

1385 x 925

See Note 3

43

5.28 and 5.29

Notes:

1.                    No water quality standard is available for dichloroacetic acid.  The maximum mixing zone provided in this table was determined by applying the measured ambient level in Table 5.15.  As the ambient levels for dichloroacetic acid were below the detection limit, the detection limit of dechloroacetic acid was applied as the criterion to determine the size of mixing zone.

2.                    Water quality standard is available for bromoform as shown in Table 5.9a.  Based on the established water quality standard for bromoform, no mixing zone can be identified as all the predicted maximum bromoform values complied well with the standard.  The maximum mixing zone provided in this table was determined by applying the measured ambient level in Table 5.15. As the ambient levels for bromoform were below the detection limit, the detection limit of bromoform was applied as the criterion to determine the size of mixing zone.

3.                    The predicted maximum levels of bromoform were all below the detection limit under the dry season (see Figure 5.29)..

5.171        Table 5.19 indicated that the maximum dichloroacetic acid level measured in the C/D CEPT effluent was 45.9 µg/l and the maximum bromoform level measured in the C/D secondary treated effluent was 49 µg/l.  Based on the dilution rates of 62, 60 and 50 for ADF stage (2009 and 2013) and late Stage 2A (2020) as shown in Table 5.42, the predicted concentration of dichloroacetic acid at the edge of mixing zone would be around 1 µg/l only. Based on the dilution rate of 43 for ultimate year as shown in Table 5.42, the predicted concentration of bromoform at the edge of mixing zone would also be about 1 µg/L only which complied well with the water quality standard for bromoform of 360µg/l (refer to Table 5.9a). There is no existing available marine water quality standard for dichloroacetic acid.

5.172        Based on the minimum dilution at the edge of mixing zone as shown in Table 5.42, the chronic toxicity unit (TUc) ([5]) at the edge of the mixing zone was calculated for the CEPT effluent and the results are summarized in Table 5.43.

 

Table 5.43            Summary of Chronic Toxicity Unit (TUc) at Edge of Mixing Zone

Scenario

Minimum Dilution Factor

NOEC Detected for Diatom in the WETT 1

TUc at Effluent 2

Predicted TUc at Edge of Mixing Zone 3

Criterion

(mg/l) 4

% of Criterion

2009 - ADF Stage

62

27.2%

3.68

0.059

1

6%

2013 - ADF Stage

60

0.061

6%

2020 - Stage 2A

50

0.074

7%

Note:

1.                    NOEC of 27.2% was detected in C/D CEPT effluent for diatom (see Section 5.162 to Section 5.166)

2.                    TUc = 100/NOEC

3.                    TUc at edge of mixing zone = TUc at effluent / minimum dilution

4.                    Toxicity criterion for far field modelling (see Table 5.9a)

5.173        As shown in Table 5.43, the predicted TUc at the edge of mixing zone for the 2009, 2013 and 2020 scenarios would be 0.059, 0.061 and 0.074 respectively which are well below the criterion of 1.

5.174        As discussed in Section 5.166, the C/D secondary treated effluent samples would not pose any chronic toxicity to the diatom. Therefore, no TUc was determined for the C/D secondary treated effluent.

5.175        It is noted that the TRC and CBP results in Figure 5.22 to Figure 5.31 indicate a sizable mixing zone for a number of background cooling water discharges.  It should be highlighted that the TRC and CBP results for these background sources are based on some very conservative assumptions. The peak discharge flow rates of the cooling water systems were applied to the model continuously (that is, 24 hours daily). For cooling water where no information on the residual chlorine level is available, the maximum chlorine dose rates were directly applied to calculate the TRC loading for model input which, again, represents a very adverse scenario. In reality, the peak flow rates would occur during a short period of time within a day and the chlorine would be decayed within the cooling water systems.  Therefore, the actual chlorine contents in the cooling water discharges should be significantly smaller than that assumed in the model.  In addition, the mixing zone dimensions provided in this EIA represent a conservative estimation as they were established based on the maximum values predicted over the entire simulation period. The background cooling water discharges are included in the model only for the purpose of addressing the possible worst-case cumulative impact with the HATS effluent.  The model results indicated that the C/D HATS effluent would not cause any cumulative TRC and CBP impact with all other concurrent discharges assumed in the model.

 

Near Field Modelling Results for TRC and Acute Toxicity

5.176        TRC concentrations at the edge of the zone of initial dilution (ZID) were calculated based on the near field modelling results as given in Appendix 5-1.  The TRC standard of 0.2 mg/l (at 95%ile) was assumed as the TRC concentration in the C/D HATS effluent for the purpose of near field modelling.

5.177        Based on the HATS survey data, the measured ambient TRC levels in the marine water were all under the detection limit. Given the fact that TRC would undergo decay in marine water, it is anticipated that the ambient TRC concentration, if any, would be minimal.  Thus, for the purpose of calculation, the ambient TRC concentration was assumed to be negligible.

5.178        Based on the minimum initial dilutions predicted by the near field model, the TRC concentration at the edge of the ZID was calculated and the results are summarized in Table 5.44

 

Table 5.44            Summary of TRC Levels at Edge of ZID

Scenario

Minimum Initial

Dilution

TRC concentration at Effluent (mg/l)1

Predicted Concentration at Edge of ZID (mg/l) 2

Criterion

(mg/l) 3

% of Criterion

2009

47

0.2

0.0043

<0.013

33%

2013

48

0.0042

32%

2020

36

0.0056

43%

Ultimate

34

0.0059

45%

Note:

1.                    TRC standard at 95%ile

2.                    TRC at edge of ZID = TRC at effluent / minimum initial dilution

3.                    TRC criterion for near field modelling (see Table 5.9b)

5.179        As shown in Table 5.44, with TRC concentration at effluent as 0.2 mg/l, the predicted TRC concentrations at the edge of ZID for the 2009, 2013, 2020 and ultimate scenarios would be 0.0043, 0.0042, 0.0056 and 0.0059 mg/l respectively which are well below the criterion of 0.013 mg/l.

5.180        As indicated in Appendix 5-1, the average dimension of the ZID would be about 1220 x100 m2.  It should be noted that the length of ZID (1220m) has taken into account the outfall diffuser length of 1200m. Thus, the predicted effluent plume width from the diffuser is only about 10m.  The main flow direction would be perpendicular to the diffuser length where the predicted downstream distance of the effluent plume from the diffuser is only about 50m. The edge of the ZID is therefore within 100m away from the outfall diffuser. The approximate location and extent of the ZID with respect to the SCISTW outfall are given in Figure 5.31a.

5.181        Based on the minimum initial dilutions predicted by the near field model, the acute toxicity unit (TUa) ([6]) at the edge of the ZID was calculated and the results are summarized in Table 5.45.

Table 5.45            Summary of Acute Toxicity Unit (TUa) at Edge of ZID

Scenario

Minimum Initial Dilution

LC50 Detected for Barnacle Larvae in the WETT 1

TUa at Effluent 2

Predicted TUa at Edge of ZID (mg/l) 3

Criterion 4

% of Criterion

2009 - ADF Stage

47

40.2%

2.49

0.053

<0.3

18%

2013 - ADF Stage

48

0.052

17%

2020 - Stage 2A

36

0.069

23%

Note:

1.                    Lowest LC50 of 40.2% was detected in C/D CEPT effluent for barnacle larva (see Section 5.162 to Section 5.166)

2.                    TUa = 100/LC50

3.                    TUa at edge of ZID = TUa at effluent / minimum initial dilution

4.                    Toxicity criterion for near field modelling (see Table 5.9b)

5.182        As shown in Table 5.45, the predicted TUa at the edge of ZID for the 2009, 2013 and 2020 scenarios would be 0.053, 0.052 and 0.069 respectively which are well below the criterion of 0.3. Details of the near field model results and the dimensions of the ZID are given in Appendix 5-1

5.183        As discussed in Section 5.166, the C/D secondary treated effluent samples would not pose any acute toxicity to the test organisms. Therefore, no TUa was determined for the C/D secondary treated effluent.

5.184        It should be noted that the TRC levels measured in the C/D CEPT effluent used for the WETT tests ranged from 0.02 to 0.1 mg/l (see Table 5.19) which are lower than the proposed TRC discharge standards (0.2 mg/l at 95%ile and 0.4 mg/l at maximum) for the HATS effluent. It is however expected that the TRC discharged from the Project would easily be dispersed by the fast moving tidal currents at the submarine outfall and would be diluted many times in close proximity of the outfall. Based on the tracer dilution modelling results, the effluent would be diluted more than 10 times at the immediate vicinity of the SCISTW outfall.  Moreover, as shown in Table 5.45, there is a great safety margin of over 75% between the predicted TUa and the assessment criterion.  It is therefore unlikely that the Project would induce any acute toxicity on the marine environment.  More detailed discussion on the acute and chronic toxicity of the Project effluent is provided under the human health and ecological risk assessment in Section 6.

 

Impact Due to Possible Change of Coastline Configurations

5.185        A sensitivity test, namely Scenario 3e, was conducted under this Study to investigate the effect of possible change in coastline configurations in Victoria Harbour on the overall conclusion of the water quality assessment. Modelling was undertaken for Scenario 3b (Table 5.20) using an alternate coastline configuration.  The alternate coastline configurations have included three additional reclamations (i.e. SEKD, WDII and YTBR respectively) as shown in Figure 5.7.

5.186        The E.coli contour plots for this sensitivity test are shown in Figure 5.32.   Appendix 5-7 tabulates the sensitivity results for E.coli at the water sensitive receivers.  The results for Scenario 3b (using the original coastline as shown in Figure 5.6) are also presented in Figure 5.32 and Appendix 5-7 for comparison. The model results indicated that no significant change in the degree of E.coli impact was observed due to the change of coastline configurations. 

5.187        Figure 5.33 shows TRC results for this sensitivity test.  The results showed that there was no obvious change in the TRC concentration pattern due to change of coastline in Victoria Harbour.

5.188        Based on the model results, the change of coastlines from Scenario 3b (no reclamation at all) to Scenario 3e (maximum extent of reclamations as in previous approved EIA) would not cause significant difference in the model results.  It is therefore not expected that the latest concept plans for WDII and SEKD which involve a lesser extent of reclamation would cause any significant difference in the model results. It is considered that the possible change of coastline in Victoria Harbour would unlikely affect the overall conclusion of the impact assessment.

 

Potential Effect on Red Tide Formation

5.189        The WETT results indicated that some degree of chronic toxicity effect was exerted on diatom from the raw CEPT effluent and C/D CEPT effluent.  Reduced diatom population in the marine water may favour the growth of other plant species and hence the species composition may be changed by the Project effluent, which could result in promoting the formation of harmful algal bloom.   From the WETT test results, NOEC to diatom was 27.2% effluent, which implied that there would be no effect to the diatom if the effluent is diluted 5 times or more.  Based on the tracer dilution modelling results, the effluent would be diluted more than 10 times at the immediate vicinity of the SCISTW outfall. As shown in Table 5.42, the effluent would be diluted at least 34 times at the edge of ZID.  It is therefore considered that the Project would unlikely induce any chronic effect on the algal populations in the receiving water.

 

Potential Oxygen Depletion Due to the Addition of Dechlorination Chemical

5.190        The upper limits of the operational range for sodium bisulphite dosage of 11 mg/l, 4 mg/l and 2 mg/l for ADF, Stage 2A and Stage 2B respectively were assumed as the sodium bisulphite concentration in the C/D HATS effluent for water quality modelling which is a conservative approach.

5.191        The average and maximum levels of oxygen depletion predicted at the Project discharge point are given in Table 5.46.  The mean ambient oxygen levels predicted under the baseline scenarios (without the Project) at different year horizons are graphically presented in Figure 5.34 and Figure 5.35 for wet and dry seasons respectively. Based on the EPD routine monitoring data, the mean ambient oxygen levels measured near the Project discharge point were 5.8 and 5.9 mg/l at stations WM3 and VM8 respectively in 2004 which accorded with the values predicted by the model as shown in Figure 5.34 and Figure 5.35.  It should be noted that the oxygen depletion as shown in Table 5.46 is based on the values extracted from the grid cell in which the SCISTW outfall was located. The size of the grid cells at or near the SCISTW outfall is approximately 140 m x 120 m. The oxygen depletion at the grid cell immediately adjacent to the outfall grid cells was at least 2 times smaller.  The predicted oxygen depletions are considered insignificant.

 

Table 5.46            Predicted Oxygen Depletion at the SCISTW Outfall Location

Scenario

Dry Season

Wet Season

Average

Maximum

Average

Maximum

Value (mg/l)

% Decrease

Value (mg/l)

% Decrease

Value (mg/l)

% Decrease

Value (mg/l)

% Decrease

2009 – ADF Stage

0.021

0.36%

0.042

0.72%

0.028

0.48%

0.077

1.33%

2013 – ADF Stage

0.021

0.36%

0.042

0.72%

0.028

0.48%

0.077

1.33%

2020 – Stage 2A

0.013

0.23%

0.021

0.37%

0.013

0.23%

0.037

0.64%

Ultimate Year – Stage 2B

0.007

0.11%

0.012

0.21%

0.012

0.21%

0.028

0.48%

Note:        The % decrease was calculated using the mean ambient oxygen levels measured near the SCISTW outfall at EPD station WM3 in 2004.

5.192        The oxygen depletions shown in Table 5.46 represent a very worse condition as the maximum chemical dosage was assumed to be the effluent concentrations.  In reality, the chemical would react with chlorine and consumed within the dechlorination facilities and the diffuser systems. The actual concentration of the dechlorination chemical in the effluent should be much smaller than the dosage value. Thus, it is expected that the oxygen depletion caused by the Project would be negligible. 

 

Emergency Situations

 

Temporary Failure of Chlorination Plant

5.193        This section addresses the potential impact on the beaches in Tsuen Wan District and the WSD flushing water intakes in western Victoria Harbour during emergency situations.  Impacts on Ma Wan FCZ under the emergency situations are not presented because the model predicted that the water quality at Ma Wan FCZ would comply with the WQO of 610 no. per 100 ml under the “without Project” scenarios as shown in Appendix 5-5 to Appendix 5-8. Year 2009, 2013 and 2020 scenarios were selected for modelling.  For each assessment year, modelling was carried out for two emergency discharge periods of 6 hours and 24 hours respectively.  It should be highlighted that the past emergency discharge records available from various sewage treatment works indicated that the longest period of emergency discharge would be less than 6 hours.  Thus, the scenario of emergency discharge for 24 hours is an extremely remote case for the purpose of worst-case assessment only.

5.194        For each of the scenarios, two separate model runs were conducted for the discharge periods centred at neap tide low water and spring tide mid-flood respectively for both wet and dry seasons. Figure 5.36 to Figure 5.41 contain the contour plots showing the maximum E.coli values predicted under the emergency situations for reference.  The maximum values predicted under the normal operation scenario are also included in Figure 5.36 to Figure 5.41 for comparison.

5.195        It should be noted that E.coli levels based on geometric means were used to depict the existing and normal operation scenarios as given in Figure 5.9 to Figure 5.21, whereas the predicted peak E.coli levels were used to assess the impacts due to emergency discharge of undisinfected effluent as given in Figure 5.36 to Figure 5.41.  The E.coli values presented for “normal operation” scenarios are geometric means over the entire 30-day simulation period which cannot reflect the short term impacts of the emergency discharge for over a 6-hour or 24-hour period.  Description of the elevation / trend of E.coli levels during and after the emergency discharge period (as compared to the normal condition with disinfection at SCISTW) is provided in the subsequent sections to indicate the impact from emergency discharge.

5.196        The model results for 2009 are presented as time series plots for E.coli covering the periods before, during and after the emergency discharges in Appendix 5-9 to Appendix 5-12.  The predicted results for the normal operation scenarios are also included in these time series plots for comparison. The indicator points selected for presentation include eight Tsuen Wan beaches (namely B7, B8, B9, B10, B11, B12, B13 and B14) and three WSD flushing water intakes (namely WSD18, WSD19 and WSD20). The results provided for the Tsuen Wan beaches are depth-average values whereas those for the WSD flushing water intakes represent the middle water layer.  Figure 5.1 shows these indicator points.   

5.197        During the emergency discharge period, it is likely that the water quality at the Tsuen Wan beaches would be affected.  Appendix 5-9 to Appendix 5-12 showed that elevations of E.coli levels are predicted immediately after the start of emergency discharge.  The trends of E.coli levels shown in the appendices indicated that the E.coli levels would sharply increase after the emergency discharge. The peak levels would last for only several hours and the levels would then significantly drop. The normal water quality conditions (i.e. the conditions under normal operation of the disinfection facilities) are predicted to recover within 2 days from the start of the emergency period under various discharge scenarios.  The time series plots for 2013 and 2020 are similar to that for 2009 and are therefore not presented. During the emergency discharge periods, the magnitudes of impacts predicted at Anglers’, Gemini and Hoi Mei Wan are considered high. The elevations predicted at Casam, Lido, Ting Kau, Approach and Ma Wan are relatively smaller. It was found that, in dry seasons, the predicted E.coli elevations at Approach are negligible under all the emergency discharge scenarios.  The likely range of E.coli levels predicted at the beaches under normal operation scenarios is also shown in Appendix 5-9 to Appendix 5-12 for comparison.

5.198        Scenario 5b, Scenario 6b and Scenario 7b represent a very worst case of emergency discharge for 24 hours.  Relatively less impact on the sensitive receivers was predicted for the discharge of undisinfected effluent for 6 hours

5.199        The worst impacts from emergency discharge would occur at the late phase of Stage 2A before commissioning of Stage 2B.  The impacts for 2009 and 2013 scenarios are expected to be smaller.  The predicted impacts in 2013 are generally smaller than that in 2009 due to the reduction of background pollution sources in 2013 as discussed in Section 5.131. 

5.200        Table 5.47 below shows the geometric mean E.coli values predicted at the beaches under the emergency situations for comparison with the WQO. The values shown in Table 5.47 are the average values predicted over the 30-day simulation periods. The geometric mean values predicted under the normal operation scenarios are also included in Table 5.47 for comparison.  As previously mentioned, geometric means over the 30-day simulation period cannot reflect the short term impacts of the emergency discharge for over a 6-hour or 24-hour period. The geometric mean E.coli values in Table 5.47 below are presented for reference and comparison with the WQO which is also a geometric mean.

 

Table 5.47            Predicted Geometric Mean E.coli Levels under Emergency Situations

Discharge Scenario

Geometric Mean Depth-averaged E.coli level (no. per 100 ml) See Note 1

Anglers’

Gemini

Hoi Mei Wan

Casam

 Lido

Ting Kau

Approach

 Ma Wan

WQO:

180

Year 2009 – HATS ADF Stage - Wet Season

Scenario 5a - Emergency discharge at Neap Tide for 6 hours

281

307

213

312

289

318

248

146

Scenario 5a -Emergency discharge at Spring Tide for 6 hours

278

305

210

310

288

318

246

144

Scenario 1b - Normal Operation

273

298

205

308

286

316

244

140

Year 2009 – HATS ADF Stage - Wet Season (Sensitivity Test) See Note 2

Scenario 5b - Emergency discharge at Neap Tide for 24 hours

288

315

220

315

291

320

252

152

Scenario 5b -Emergency discharge at Spring Tide for 24 hours

286

314

216

314

292

321

250

149

Scenario 1b - Normal Operation

273

298

205

308

286

316

244

140

Year 2009 – HATS ADF Stage - Dry Season

Scenario 5a - Emergency discharge at Neap Tide for 6 hours

167

165

131

127

109

199

448

23

Scenario 5a -Emergency discharge at Spring Tide for 6 hours

166

163

128

128

108

199

447

22

Scenario 1b - Normal Operation

161

158

124

126

106

197

443

21

Year 2009 – HATS ADF Stage - Dry Season (Sensitivity Test) See Note 2

Scenario 5b - Emergency discharge at Neap Tide for 24 hours

173

172

136

129

111

201

452

24

Scenario 5b -Emergency discharge at Spring Tide for 24 hours

171

168

133

130

110

200

451

23

Scenario 1b - Normal Operation

161

158

124

126

106

197

443

21

Year 2013 – HATS ADF Stage - Wet Season

Scenario 6a - Emergency discharge at Neap Tide for 6 hours

112

153

88

152

122

162

96

61

Scenario 6a -Emergency discharge at Spring Tide for 6 hours

111

153

87

151

122

162

95

60

Scenario 2b - Normal Operation

108

149

84

150

121

161

94

58

Year 2013 – HATS ADF Stage - Wet Season (Sensitivity Test) See Note 2

Scenario 6b - Emergency discharge at Neap Tide for 24 hours

115

158

91

153

123

163

97

64

Scenario 6b -Emergency discharge at Spring Tide for 24 hours

115

159

90

153

124

164

97

62

Scenario 2b - Normal Operation

108

149

84

150

121

161

94

58

Year 2013 – HATS ADF Stage – Dry Season

Scenario 6a - Emergency discharge at Neap Tide for 6 hours

114

118

92

103

80

171

367

14

Scenario 6a -Emergency discharge at Spring Tide for 6 hours

113

116

91

104

80

171

367

13

Scenario 2b - Normal Operation

110

113

88

102

79

169

363

13

Year 2013 – HATS ADF Stage – Dry Season (Sensitivity Test) See Note 2

Scenario 6b - Emergency discharge at Neap Tide for 24 hours

117

122

97

104

82

172

371

14

Scenario 6b -Emergency discharge at Spring Tide for 24 hours

117

120

95

106

82

172

371

14

Scenario 2b - Normal Operation

110

113

88

102

79

169

363

13

Year 2020 – HATS Stage 2A – Wet Season

Scenario 7a - Emergency discharge at Neap Tide for 6 hours

78

92

50

152

118

168

83

42

Scenario 7a -Emergency discharge at Spring Tide for 6 hours

78

92

49

152

118

168

83

41

Scenario 3b - Normal Operation

74

88

47

150

117

167

81

39

Year 2020 – HATS Stage 2A - Wet Season (Sensitivity Test) See Note 2

Scenario 7b - Emergency discharge at Neap Tide for 6 hours

81

96

53

154

119

169

85

44

Scenario 7b -Emergency discharge at Spring Tide for 6 hours

82

98

52

154

121

170

86

43

Scenario 3b - Normal Operation

74

88

47

150

117

167

81

39

Year 2020 – HATS Stage 2A – Dry Season

Scenario 7a - Emergency discharge at Neap Tide for 6 hours

86

76

62

99

73

174

349

5

Scenario 7a -Emergency discharge at Spring Tide for 6 hours

86

75

61

100

73

174

350

5

Scenario 3b - Normal Operation

82

71

58

98

71

172

344

4

Year 2020 – HATS Stage 2A – Dry Season (Sensitivity Test) See Note 2

Scenario 7b - Emergency discharge at Neap Tide for 6 hours

90

80

65

100

75

176

354

5

Scenario 7b -Emergency discharge at Spring Tide for 6 hours

91

79

64

103

75

176

355

5

Scenario 3b - Normal Operation

82

71

58

98

71

170

344

4

Shaded cell – exceedance of beach water quality objective.

Notes:  

1.            Values shown in the above table represent the geometric mean model output for a 30-day simulation period.

2.            Past emergency discharge records available from various sewage treatment works indicated that the longest period of emergency discharge would be less than 6 hours.  Thus, the scenario of emergency discharge for 24 hours is an extremely remote case for the purpose of worst-case assessment only.

5.201        Table 5.48 tabulates the peak E.coli values predicted at three WSD intakes in western Victoria Harbour that could be potentially affected by the undisinfected effluent from HATS during the emergency discharge period. 

 

Table 5.48            Predicted Peak E.coli Levels During Emergency Discharge Period

Tide

Peak Depth-averaged E.coli level (no. per 100 ml) During Emergency Discharge Period

WSD18 – Central Water Front

 

 

 

 

 

 

WSD18

WSD19 - Sheung Sha Wan

WSD20 - Kennedy Town

F5

WQO:

20000 at any time

Scenario 5a - Year 2009 – HATS ADF Stage - Emergency Discharge for 6 Hours – Wet Season

Neap Tide

NEG

 

 

 

 

NEG

NEG

NEG

 

Spring Tide

8142

 

 

10788

6876

 

Scenario 5b – Year 2009 – HATS ADF Stage - Emergency Discharge for 24 Hours – Wet Season (Sensitivity Test)

Neap Tide

7854

21370

2331

 

Spring Tide

15607

17789

13517

 

Scenario 5a - Year 2009 – HATS ADF Stage - Emergency Discharge for 6 Hours – Dry Season

Neap Tide

NEG

NEG

13571

 

Spring Tide

5508

7854

3540

 

Scenario 5b - Year 2009 – HATS ADF Stage – Emergency Discharge for 24 Hours – Dry Season (Sensitivity Test)

Neap Tide

7151

8921

21531

 

Spring Tide

10289

13578

23397

 

Scenario 6a - Year 2013 – HATS ADF Stage - Emergency Discharge for 6 Hours – Wet Season

Neap Tide

NEG

NEG

NEG

 

Spring Tide

6643

2446

NEG

NEG

3672

NEG

NEG

6643

9955

5331

 

Scenario 6b - Year 2013 – HATS ADF Stage - Emergency Discharge for 24 Hours – Wet Season (Sensitivity Test)

Neap Tide

6341

 

 

 

 

 

 

 

20676

1698

 

Spring Tide

12596

 

 

 

 

 

 

 

15624

11225

 

Scenario 6a - Year 2013 – HATS ADF Stage - Emergency Discharge for 6 Hours – Dry Season

Neap Tide

NEG

 

 

 

 

 

 

 

NEG

13947

 

Spring Tide

NEG

 

 

 

 

 

 

 

7718

3644

 

Scenario 6b - Year 2013 – HATS ADF Stage - Emergency Discharge for 24 Hours – Dry Season (Sensitivity Test)

Neap Tide

NEG

 

 

 

 

 

 

 

8887

21573

 

Spring Tide

10176

 

 

 

 

 

 

 

13579

23541

 

Scenario 7a - Year 2020 – HATS Stage 2A - Emergency Discharge for 6 Hours – Wet Season

Neap Tide 

NEG

 

 

 

 

 

 

 

NEG

NEG

 

Spring Tide

4907

 

 

 

 

 

 

 

4933

6548

 

Scenario 7b - Year 2020 – HATS Stage 2A - Emergency Discharge for 24 Hours – Wet Season (Sensitivity Test)

Neap Tide

3180

 

 

 

 

 

 

 

5357

2190

 

Spring Tide

16887

 

 

 

 

 

 

 

18957

14481

 

Scenario 7a - Year 2020 – HATS Stage 2A - Emergency Discharge for 6 Hours – Dry Season

Neap Tide

3735

 

 

 

 

 

 

 

5209

20461

 

Spring Tide

2966

 

 

 

 

 

 

 

4066

3845

 

Scenario 7b - Year 2020 – HATS Stage 2A - Emergency Discharge for 24 Hours – Dry Season (Sensitivity Test)

Neap Tide 

6756

 

 

 

 

 

 

 

7574

31843

 

Spring Tide

13150

 

 

 

 

 

 

 

17790

33578

 

Notes:

NEG – The observed elevations are negligible.

Shaded cell – exceedance of WSD standard.

5.202        Under each scenario, modelling was carried out for two emergency discharge cases at the large amplitude spring tide and the small amplitude neap tide respectively. The model runs aimed to capture the extreme conditions in spring tides where the pollutants could be brought to the farther field and in neap tides where there may be larger impacts in the near field.  Significant differences in the model results are thus observed between the neap tide case and the spring tide case as shown in Table 5.48.

5.203        The model predicted that the peak E.coli levels at Sheung Wan (WSD19) and Kennedy Town (WSD20) in the western Victoria Harbour would breach the WSD standard of 20000 no. per 100 ml during the emergency discharge under some discharge scenarios.  It should be noted that almost all WQO exceedances predicted at WSD19 and WSD20 occurred under the very adverse case of 24-hour discharge of undisinfected effluent with a total discharge volume of over 1.5, 1.6 and 2.3 million m3 for 2009, 2013 and 2020 respectively.  Based on past record, the longest period of emergency discharge of untreated effluent at various PTW and STW in Hong Kong would be less than 6 hours.  The chance of emergency discharge for more than 6 hours is therefore expected to be very remote.  The peak levels predicted at the Kennedy Town (WSD20) would exceed the WSD standard under the emergency discharge of 6 hours.  However, it should be highlighted that this predicted peak level only marginally exceeded the standard and the exceedance occurred only at one instant during the emergency discharge period.  The predicted impacts on the WSD intakes due to the emergency discharge are therefore considered acceptable.

 

Temporary Failure of Dechlorination Plant

5.204        The predicted TRC levels under the emergency situation are presented as maximum instantaneous values in Figure 5.42 to Figure 5.47.  The contour plots for normal operation scenarios are also included in these figures for comparison.  It was found that, during the emergency discharge periods, the predicted maximum TRC values in the receiving water would exceed the assessment criterion of 0.008 mg/l.  However, the mixing zones of TRC (within which the maximum TRC values would exceed the assessment criterion) would be limited in areas close to the SCISTW submarine outfall to the south of Tsing Yi Island as shown in Figure 5.42 to Figure 5.47.  The sizes of the maximum mixing zones of TRC predicted under different emergency discharge scenarios are given in Table 5.49.  It should be hightlighted that the mixing zone dimensions provided in this EIA represent a conservative estimation as they were established based on the maximum values predicted over the entire simulation period.

 

Table 5.49   Maximum Dimensions of Mixing Zones for TRC under Emergency Situations

Stage

Emergency Discharge Scenarios

Approximate Dimension of Mixing Zone (m2)

Figure Reference

Dry Season

Wet Season

2009 – ADF Stage

8a – Discharge at spring tide for 40 minutes

1410 x 1880

1410 x 1720

5.42 and 5.43

2009 – ADF Stage

8a – Discharge at neap tide for 40 minutes

1830 x 1200

1490 x 1550

5.42 and 5.43

2013 – ADF Stage

9a – Discharge at spring tide for 40 minutes

1430 x 1910

1400 x 1780

5.44 and 5.45

2013 – ADF Stage

9a – Discharge at neap tide for 40 minutes

1830 x 1300

1500 x 1670

5.44 and 5.45

2020 – Stage 2A

10a – Discharge at spring tide for 60 minutes

1460 x 1920

1420 x 1810

5.46 and 5.47

2020 – Stage 2A

10a – Discharge at neap tide for 60 minutes

1860 x 1400

1500 x 1680

5.46 and 5.47

5.205        Based on the chlorine residual of 6.7 mg/l for ADF stage and 5.5 mg/l for Stage 2A and the minimum dilution predicted in Table 5.45, it is calculated that the chlorine concentrations at the edge of ZID would range from 0.14 to 0.15 mg/l which exceeded the TRC criterion of 0.013 mg/l under the emergency situations.  However, as shown in Figure 5.42 to Figure 5.47, no observable impact was predicted in the areas farther away from the outfall outside the mixing zones.  The maximum values predicted at all the identified sensitive receivers including the Tsuen Wan beaches and Ma Wan FCZ were well below the assessment criterion of 0.008 mg/l under all the emergency situations.  The model results indicated that the emergency discharge would not cause any cumulative TRC impact with other concurrent discharges.

5.206        The influence zones of the emergency TRC discharges are predicted to cover only the areas close to the submarine outfall of SCISTW and no observable impact was predicted at all the identified water sensitive receivers.  The time series plots of TRC for the periods before, during and after the emergency discharge are presented at two selected indicator points near the SCISTW outfall, in Appendix 5-13 to Appendix 5-16 for 2009. Both indicator points are EPD stations, namely WM3 and VM8 respectively, as shown in Figure 5.1. The predicted results for normal operation are also included in the time series plots for comparison. The time series plots for 2013 and 2020 are similar to that for 2009 and are therefore not presented.

5.207        The time series plots in Appendix 5-13 to Appendix 5-16 showed that the emergency discharge would cause a short-term elevation of TRC.  Table 5.50 shows the peak TRC values predicted during the emergency discharge periods at stations WM3 and VM8 under various discharge scenarios.  The model results indicated that the baseline water quality conditions would quickly recover (within 2 hours) after the termination of the discharge under all the emergency scenarios.  The peak TRC values predicted at the two EPD stations complied well with the assessment criterion.

 

Table 5.50    Predicted Maximum TRC Levels During the Emergency Discharge Periods at Stations VM8 and WM3

Stage

Emergency Discharge Scenarios

Peak TRC Value (mg/l)

Station VM8

Station WM3

Wet Season

Dry Season

Wet Season

Dry Season

Assessment Criterion:

0.008

2009 – ADF Stage

8a – Discharge at spring tide for 40 minutes

NEG

NEG

0.0013

0.001

2009 – ADF Stage

8a – Discharge at neap tide for 40 minutes

0.0001

0.0003

0.0005

NEG

2013 – ADF Stage

9a – Discharge at spring tide for 40 minutes

NEG

NEG

0.0014

0.001

2013 – ADF Stage

9a – Discharge at neap tide for 40 minutes

0.0001

0.0004

0.0005

NEG

2020 – Stage 2A

10a – Discharge at spring tide for 60 minutes

NEG

NEG

0.0015

0.0012

2020 – Stage 2A

10a – Discharge at neap tide for 60 minutes

0.0001

0.0005

0.0005

NEG

Note:

NEG – The observed elevations are negligible.

5.208        It is considered that the chlorination process could be practically stopped within 30 minutes upon the occurrence of any dechlorination plant failure.  The model results indicated that the TRC level would exceed the assessment criterion at the edge of the ZID in the near field. The average size of ZID is given in Section 5.180. It is however expected that the impact on the marine ecology due to the emergency discharge should be limited given that the TRC exceedance would be only localized and temporary (within a few hours). The peak TRC levels predicted at all the identified water sensitive receivers would well comply with the assessment criterion of 0.008 mg/l under various emergency scenarios.  

 

Disinfection Period

5.209        The model results indicated that the gazetted beaches in Tsuen Wan District would be adversely affected by the undisinfected effluent from SCISTW under both bathing and non-bathing seasons.    However, the WQO of 180 per 100 ml for bathing beaches is a geometric mean for the bathing season (March to October) only.  Therefore, disinfection at SCISTW would only be needed during the bathing seasons to meet the statutory requirement with respect to the WQO for bathing beaches. 

5.210        The WQO of 610 E.coli per 100 ml for secondary contact recreation subzones, on the other hand, is an annual geometric mean which covers the periods in both bathing and non-bathing seasons.   In addition, the WSD standard of 20,000 E.coli per 100 ml for flushing water intakes is a criterion that should be met at all times during the year. The model predicted that the beneficial uses of the secondary contact recreation subzones in Tsuen Wan coast and the WSD flushing water intakes in western Victoria Harbour would be adversely affected by the undisinfected SCISTW effluent under both bathing and non-bathing seasons.  It is therefore recommended that year-round disinfection should be provided for the SCISTW effluent to protect the secondardy contact recreation subzones and the WSD flushing water intakes.  Year-round disinfection would also be required to minimize the human health risk if the Tsuen Wan beaches are to be opened at all times during the year.

5.211        The SCISTW outfall is situated between the Tsuen Wan coast and the western HK Island.  Under the flood conditions, the undisinfected SCISTW effluent would be brought to the Tsuen Wan coast by the water current flowing from south to north affecting the Tsuen Wan beaches. During the ebb tides, the SCISTW effluent would be brought towards the coast of western HK Island influencing the nearby WSD flushing water intakes.  Temporary discharge of undisinfected effluent from SCISTW for 6 hours and 24 hours was modelled under different seasonal and tidal conditions as shown in Appendix 5-9 to Appendix 5-12. The model predicted that the E.coli levels at the Tsuen Wan beaches and the WSD flushing water intakes would be sensitive to the temporary discharge of undisinfected effluent from SCISTW. Appendix 5-9 to Appendix 5-12 showed that, depends on the tide status when the temperary discharge starts, the E.coli levels at some sensitive receivers under some situations would be elevated quite significantly immediately (within a hour) after the start of the temporary discharge.  Temporary discharge of undisinfected HATS effluent for less than 6 hours was not further considered. It is suggested that continuous disinfection throughout the year would be needed to protect the sensitive receivers and minimize the human health risk to the beach users. Intermittent disinfection is therefore not recommended.

 

Mitigation of Adverse Environmental Impacts

 

Construction Phase

Construction Site Runoff and General Construction Activities

5.212        To minimise the potential water quality impacts from construction site runoff and various construction activities, the practices outlined in ProPECC PN 1/94 Construction Site Drainage should be adopted. A copy of the ProPECC PN 1/94 is attached in Appendix 5-17 for reference. It is recommended to install perimeter channels in the works areas to intercept runoff at site boundary prior to the commencement of any earthwork. To prevent storm runoff from washing across exposed soil surfaces, intercepting channels should be provided. Drainage channels are also required to convey site runoff to sand/silt traps and oil interceptors. Provision of regular cleaning and maintenance can ensure the normal operation of these facilities throughout the construction period.  Any practical options for the diversion and re-alignment of drainage should comply with both engineering and environmental requirements in order to ensure adequate hydraulic capacity of all drains.

5.213        There is a need to apply to EPD for a discharge licence under the WPCO for discharging effluent from the construction site. The discharge quality is required to meet the requirements specified in the discharge licence. All the runoff and wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS.  The beneficial uses of the treated effluent for other on-site activities such as dust suppression, wheel washing and general cleaning etc., can minimise water consumption and reduce the effluent discharge volume. It is anticipated that the wastewater generated from the works areas would be of small quantity. If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring should be carried out in accordance with the WPCO license which is under the ambit of regional office (RO) of EPD.   

5.214        The construction programme should be properly planned to minimise soil excavation, if any, in rainy seasons.  This prevents soil erosion from exposed soil surfaces.  Any exposed soil surfaces should also be properly protected to minimise dust emission.  In areas where a large amount of exposed soils exist, earth bunds or sand bags should be provided.  Exposed stockpiles should be covered with tarpaulin or impervious sheets at all times.  The stockpiles of materials should be placed at locations away from any stream courses so as to avoid releasing materials into the water bodies.  Final surfaces of earthworks should be compacted and protected by permanent work.  It is suggested that haul roads should be paved with concrete and the temporary access roads protected using crushed stone or gravel, wherever practicable.  Wheel washing facilities should be provided at all site exits to ensure that earth, mud and debris would not be carried out of the works areas by vehicles.

5.215        Good site practices should be adopted to clean up / collect the rubbish and litter on the construction sites so as to prevent the rubbish and litter from spreading from the site area.  It is recommended to clean the construction sites on a regular basis.

Sewage from Workforce

5.216        The presence of construction workers generates sewage.  It is recommended to provide sufficient chemical toilets in the works areas.  The toilet facilities should be more than 30 m from any watercourse.  A licensed waste collector should be deployed to clean the chemical toilets on a regular basis.  The construction workers can also make use of the existing toilet facilities within the SCISTW as necessary.

5.217        Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment during the construction phase of the project.  Regular environmental audit on the construction site can provide an effective control of any malpractices and can achieve continual improvement of environmental performance on site.  It is anticipated that sewage generation during the construction phase of the project would not cause water pollution problem after undertaking all required measures.

Accidental Spillage of Chemicals

5.218        Contractors must register as a chemical waste producer if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes.

5.219        Any service shop and maintenance facilities should be located on hard standings within a bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

5.220        Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:

 

·            Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

·            Chemical waste containers should be suitably labeled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

·            Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.

 

Operation Phase

5.221        An operational phase environmental monitoring programme would be recommended in the EM&A Manual to confirm the predictions of the environmental impacts made in the EIA report. Effluent quality from the SCISTW will be governed by the Water Pollution Control Ordinance and the associated discharge licence conditions. The dosing system is designed to allow adjustment for compliance of the effluent standards as well as minimization of the chlorine dosage, thus, the potential generation of chlorination by-products.

5.222        The modelling results indicated that the residual E.coli predicted at the Tsuen Wan beaches (after the Project is commissioned at 2009) would be partly caused by the local pollution sources in the rural areas of Sham Tseng, and the polluted waters in Rambler Channel due to the expedient connections, misconnections and polluted surface runoff from the dense urban areas in Tsuen Wan, Kwai Chung and Tsing Yi Districts.  It is noted that Government has also put in place local sewerage improvement projects, in conjunction with the provision of disinfection facilities at SCISTW, to tackle the local pollution problems in Sham Tseng, Tsuen Wan, Kwai Chung, and Tsing Yi District so as to rectify these local problems.

5.223        In case of power outage, the uninterruptible power supply (UPS) system will switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent.  With proper implementation of these mitigation measures, the occurrence of discharge of non-dechlorinated effluent  would be very remote.  In case that the dechlorination process fails, the chlorination process could be practically stopped within 30 minutes to avoid discharge of TRC into the marine water.  The E.coli impact due to no chlorination for a short period of time would be temporary and acceptable as supported by the water quality impact assessment results.

5.224        The bacterial levels at the beaches, the Ma Wan FCZ and the secondary contact recreation subzones in Tsuen Wan District, as well as the WSD flushing water intakes in western Victoria Harbour could be elevated in the event of temporary discharge of undisinfected effluent from SCISTW during chlorination plant failure or when the chlorination plant is closed in the event of dechlorination plant failure. Under the emergency discharge, the beaches and the secondary contact subzones in Tsuen Wan District should be closed. It is recommended that relevant government departments including EPD and LCSD should be informed by DSD as soon as possible of any emergency discharge so that appropriate actions can be taken. A list of address, email address, phone and fax number of key persons in relevant departments responsible for action should be made available to the plant operators.  Water quality monitoring should be carried out at such a time to quantify the water quality impacts and to determine when the baseline water quality conditions are restored.

5.225        To provide a mechanism to minimise the impact of emergency discharges, a framework of the emergency response procedures in case of chlorination / dechlorination plant failure has been formulated and are given in a standalone EM&A Manual.

 

Evaluation of Residual Impact

 

Construction Phase

5.226        The construction phase water quality impact, if any, would generally be temporary and localised during construction.  No unacceptable residual water quality impacts would be expected during the construction phase of the Project, provided that all the recommended mitigation measures are properly implemented.

 

Operation Phase

5.227        The Project would result in beneficial effect as the E.coli Levels in the receiving water bodies would be significantly reduced due to the provision of disinfection facilities at SCISTW.  The model results indicated that adverse water quality impact due to the discharge of TRC and CBP associated with chlorination of the Project effluent is not expected.  The model predicted that the water quality impact in terms of the TRC and CBP levels at all the identified water sensitive receivers would be acceptable after commissioning of the Project. 

5.228        The water quality impact due to the emergency discharges is expected to be short-term. In case of dechlorination plant failure, the TRC level would exceed the assessment criterion at the edge of the ZID in the near field based on the model results. It is however expected that the associated impact on marine ecology should be limited given that the TRC exceedance would be only localized and temporary (within a few hours). In case of power outage, the uninterruptible power supply (UPS) system will switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent.   Also, a framework of the emergency response procedures has been formulated to minimise the impact of emergency discharges.  No insurmountable water quality impact is expected from these temporary discharges provided that all the recommended mitigation measures are properly implemented.

 

Environmental Monitoring and Audit

5.229        Effluent quality from the SCISTW will be governed by the Water Pollution Control Ordinance and the associated discharge licence conditions. An operational phase environmental monitoring programme is recommended for the ADF stage to confirm the predictions of the environmental impacts made in the EIA report. Marine water quality monitoring is also recommended during and after any emergency discharge of undisinfected HATS effluent under the ADF stage. Details are given in the separate EM&A Manual as part of the EIA study. Detailed monitoring programme for HATS Stage 2A will be developed under a separate EIA study.

 

Conclusions

 

Construction Phase Impact

5.230        Minor water quality impact, if any, would be associated with land-based construction. Impacts may result from the surface runoff and sewage from on-site construction workers.  Impacts could be controlled to comply with the Water Pollution Control Ordinance (WPCO) standards by implementing the recommended mitigation measures. Unacceptable residual impacts on water quality would not be expected.

 

Operation Phase Impact

5.231        Chlorination is proposed as the disinfection technology for the Stonecutters Island Sewage Treatment Works (SCISTW) which would however generate total residual chlorine (TRC) and chlorination by-products (CBP) in the Project effluent.  Dechlorination will be applied to eliminate the discharge of TRC into the marine environment.  An assessment of water quality impact due to the operation of the Project was made using the Delft3D model.  Impacts were assessed over a series of 30-day simulation periods.

Normal Operation

Proposed Effluent Standards

5.232        The model results indicated that the provision of disinfection facilities at SCISTW would be needed to satisfy the requirement for protection of the identified water sensitive receivers and help to improve water quality in the Western Buffer water control zone (WCZ) and western Victoria Harbour. 

5.233        Sensitivity model runs were performed to estimate the optimum disinfection levels and durations for the disinfection facilities, on one hand, to safeguard the beneficial uses of nearby water sensitive receivers and, on the other hand, to minimize the chlorine dose and thus the potential generation of CBP.  

5.234        The model results indicated that the gazetted beaches in Tsuen Wan District would be adversely affected by the undisinfected effluent from SCISTW under both bathing and non-bathing seasons.    However, the WQO of 180 per 100 ml for bathing beaches is a geometric mean for the bathing season (March to October) only.  Therefore, disinfection at SCISTW would only be needed during the bathing seasons to meet the statutory requirement with respect to the WQO for bathing beaches. 

5.235        The WQO of 610 E.coli per 100 ml for secondary contact recreation subzones, on the other hand, is an annual geometric mean which covers the periods in both bathing and non-bathing seasons.   In addition, the WSD standard of 20,000 E.coli per 100 ml for flushing water intakes is a criterion that should be met at all times during the year. The model predicted that the beneficial uses of the secondary contact recreation subzones in Tsuen Wan coast and the WSD flushing water intakes in western Victoria Harbour would be adversely affected by the undisinfected SCISTW effluent under both bathing and non-bathing seasons.  It is therefore recommended that year-round disinfection should be provided for the SCISTW effluent to protect the secondardy contact recreation subzones and the WSD flushing water intakes.  Year-round disinfection would also be required to minimize the human health risk if the Tsuen Wan beaches are to be opened at all times during the year.

5.236        Based on the water quality modelling results, discharge standards are recommended for the SCISTW effluent after the Project commissioned as shown in Table 5.51.  The advance disinfection facilities (ADF) and the permanent disinfection facilities under Stage 2A would be designed to cater for the recommended disinfection levels.  Allowances would be provided in the design with capacities higher than those required for the recommended operational range. An operation plan has been developed for the chemical dosing. The dosing system would be designed to allow adjustment for compliance with the effluent standards. Monitoring of effluent quality is recommended for operational stage and under the perspective of the WPCO.

 

Table 5.51   Recommended Effluent Standards for the HATS

Stage

Operation Range of Chlorine Dosage (mg/l)

E.coli (no. per 100 ml)

TRC (mg/l)

Geometric Mean

95 Percentile

95 Percentile

Maximum

HATS – ADF Stage

11-15

200,000

3,000,000

0.2

0.4

HATS – Stage 2A

10-14

20,000

300,000

0.2

0.4

HATS – Stage 2B

2-3

20,000

300,000

0.2

0.4

 

5.237        The water quality model results showed that, with the adoption of effluent standards (which are equivalent to 99% or above E. coli removal) recommended in Table 5.51, the discharge of HATS effluent after chlorination and dechlorination would be unlikely to cause adverse water quality impact.  Although the model input parameters were conservative, the model predicted that the disinfected HATS effluent would not cause any non-compliance with the marine water quality criteria as shown in Table 5.52

 

Table 5.52   Marine Water Quality Criteria Adopted in the Water Quality Impact Assessment

Parameter

Assessment Criteria

Applicable Zones / Uses

E.coli

180 per 100 ml

Geometric mean for the period from March to October

Bathing beach subzones only

610 per 100 ml

Annual geometric mean

Secondary contact recreation subzones and fish culture subzones only

20000 per 100 ml

Maximum value

WSD flushing water intakes only

Total residual chlorine (TRC)

0.008 mg/l

Daily maximum

All WCZ of concern

0.013 mg/l

Daily maximum

At edge of initial dilution zones

 

Environmental Benefits of the Project

Marine Water Quality  

5.238        The Project would result in beneficial effect as the bacteria levels in the receiving marine water bodies would be significantly reduced due to the provision of disinfection facilities at SCISTW.  The Project would bring significant water quality improvements at the water sensitive receivers identified within the Study Area including the beaches, the fish culture zones (FCZ) and the secondary contact recreation subzones in Tsuen Wan coast as well as the seawater intakes in western Victoria Harbour.  The model predicted that the bacteria levels in the Western Buffer WCZ, western Victoria Harbour and eastern part of the North Western WCZ would be significantly reduced upon commissioning of the Project.

Beach Water Quality

5.239        The model results revealed that considering the contribution from the undisinfected HATS effluent alone, the mean E.coli levels predicted at the bathing beaches in Tsuen Wan District could range from 88 to 817 no. per 100 ml during Stage 1 and Stage 2A as compared to the water quality objective (WQO) of 180 no. per 100 ml.  The proposed disinfection facilities (including the ADF) at SCISTW are found to be capable of almost eliminating the HATS E.coli loading to the beaches.   The geometric mean HATS contributions predicted at the bathing beaches would be reduced to 15 count per 100mL after provision of the ADF. These contributions are considered small when compared to the WQO of 180 E.coli per 100mL.  From this perspective, the Project could facilitate the reopening of those closed beaches at Tsuen Wan and minimize the human health risk to the beach users.

Re-opening of Tsuen Wan Beaches

5.240        The Leisure and Cultural Services Department (LCSD) is currently the “beach management authority”, responsible for determining the opening and closing of gazetted beaches.  The decision is made with reference to the advice provided by EPD on the suitability of beach water quality for bathing purposes and the consideration of all other factors.  Generally, a beach will be closed if it is ranked "Very Poor" repeatedly.  Beaches having annual geometric mean E.coli densities greater than 610 per 100mL are ranked "Very Poor”.

5.241        The procedures for re-opening a beach will involve the following key steps:

1.1        

·         EPD informs LCSD of continued water quality improvement at the concerned beach and that the beach is suitable for swimming.  In making this advice, EPD normally refers to beach water quality monitoring results that it has collected over a sufficiently long period (typically at least one year).  

·         LCSD then clarifies the actual situation with EPD, and decides whether and when to re-open the affected beach.

·         Once a decision on beach re-opening is made, LCSD will issue a press release and inform the relevant District Council.

5.242        The monitoring data shows that both the HATS Stage 1 un-disinfected effluent discharge and local pollution sources are contributing to the poor or very poor beach water quality at the seven Tsuen Wan beaches.  Before the beach management authority may consider re-opening any of these beaches, it is necessary to improve beach water quality to a level consistent with the present policy on beach management and community aspirations.

5.243        The ADF, together with reduction of localised un-treated wastewater discharges being implemented under the regional sewerage schemes, will be essential to improving the Tsuen Wan beach water quality and, consequently, re-opening of the beaches.  From the historic records as shown in Exhibit 2.2, three beaches, namely Anglers’, Ting Kau and Approach, on the Tsuen Wan coast had been closed due to strong influence of local pollution sources before the commissioning of HATS Stage 1.  On top of the already poor water quality, un-disinfected effluent from HATS Stage 1 commissioned in late 2001 has caused four other beaches on the coast to close.  They are, namely Lido, Casam, Hoi Mei Wan, and Gemini.

5.244        Based on the water quality modelling results, provision of disinfection facilities at SCISTW after implementation of ADF will keep the influence of the HATS effluent at the Tsuen Wan Beaches to a very low level (≤ 15 E. coli per 100 ml).  With regard to the background (i.e., non-HATS) pollution sources, the government has been implementing the local sewerage works along Castle Peak Road for completion by 2009 in conjunction with the ADF to serve the unsewered villages and properties around Ting Kau, Sham Tseng and Tsing Lung Tau.  As the outfalls of Kwai Chung, Tsing Yi and Northwest Kowloon PTWs (which should have an influence on the water quality of Tsuen Wan beaches at the pre-HATS stage) have been decommissioned since the commissioning of HATS Stage 1 in 2001, it is expected that the beach water quality after the operation of the ADF would be improved to a level that is better than the pre-HATS Stage 1 condition to facilitate early re-opening of the Tsuen Wan beaches.

5.245        Without disinfecting the HATS Stage 1 effluent, the Tsuen Wan beach water quality cannot be restored even with the completion of local sewerage works which can only arrest the local pollution problems.  The proposed ADF, in conjunction with the local sewerage works being implemented, will bring about the necessary water quality improvements needed for the re-opening of Tsuen Wan beaches at the earliest possible moment.  If the ADF were not implemented, the Tsuen Wan beach water quality would remain jeopardised by the un-disinfected HATS Stage 1 effluent, until the permanent disinfection facilities proposed under Stage 2A are commissioned.  The current timetable for HATS Stage 2A is for substantial completion to be achieved by end 2014.  This is about five years behind the target commissioning date of end 2009 for completing the ADF.

5.246        In conclusion, the provision of the proposed ADF is an integral part of the sewerage programme to restore the water quality of the Tsuen Wan beaches at the earliest possible moment.  The E. coli levels at the Tsuen Wan beaches during the ADF stage have been quantified by using mathematical model. As the model input data such as the HATS flow rates and the background pollution loading tended to be conservative to provide a margin of tolerance (refer to Section 5.65 and Appendix 5.2), it is likely that the actual E. coli levels at the beaches could be lower than that predicted in this EIA.  This will be ascertained by monitoring of the actual beach water quality.  Once the actual monitoring results confirm that the beach water quality has returned to an acceptable level for swimming, arrangements to re-open the beaches for public enjoyment will be instigated.

Provision of Disinfection for HATS Stage 2B

5.247        Regarding Stage 2B, the EIA water quality modelling results showed that with the implementation of biological treatment, compliance with the relevant WQO at most of the beaches without the provision of disinfection should be achievable.  However, it is important to note that modelling cannot fully predict the high variability of some factors (e.g. salinity, natural ultra violet radiation, and wind) that affect the density of E. coli in the receiving waters.  Therefore, planning for disinfection in Stage 2B is recommended, though this provision may be reviewed in the light of actual water quality monitoring results after commissioning of the ADF.

Chlorination By-products (CBP) and Effluent Toxicity

5.248        Chlorination would generate total residual chlorine (TRC) and chlorination by-products (CBPs) in the effluent.  Dechlorination would eliminate the discharge of TRC into the marine environment.  As for CBPs, laboratory tests were carried out on 34 CBP’s (including trihalomethane (THM) and haloacetic acid (HAA)) in the CEPT effluent before and after chlorination/dechlorination.  Of these 34 CBP’s, only 8 were detected in the CEPT after chlorination and dechlorination, the concentrations of 6 were less than 10 parts per billion while those for the remaining 2 were in the 10-50 parts per billion range.  However, 5 of these 8 CBPs were also detected in the raw CEPT effluent before chlorination and dechlorination.  Of these 5, the concentrations of 3 were less than 10 parts per billion while the remaining two had concentrations in the 10-50 parts per billion range.  These results indicated that of the few CBP’s detected, the majority was already present in the raw CEPT effluent, and the chlorination and dechlorination process introduced 3 CBP’s all showing concentrations of less than 10 parts per billion.  The laboratory results also showed that the THM and HAA formed were in the parts per billion concentration range, well below USEPA’s drinking water standard for THM and HAA.

5.249        Water quality modelling results showed that the discharge of effluent after chlorination and dechlorination would not cause adverse water quality impact.  Although the model input parameters were conservative, water quality modelling results suggested that the maximum TRC and CBPs levels in the receiving waters would comply well with the assessment criteria during normal operation of the SCISTW after commissioning of the Project.

5.250        Results of whole effluent toxicity test on C/D HATS effluent were used to determine whether the C/D effluent would induce adverse effects to marine life.  It was found that the established toxicity criteria were complied at both edge of zone of initial dilution (ZID) and edge of mixing zone under all the assessment scenarios.  Therefore, the potential toxicity impacts from the Project effluent on marine life were expected to be acceptable. 

 

Emergency Situations

5.251        The discharge of chlorinated effluent (without dechlorination) under the event of dechlorination plant failure has been modelled for various discharge durations and scenarios.  The model predicted that, during the emergency discharge periods, the TRC levels near the SCISTW outfall would be elevated and the TRC levels would exceed the assessment criterion in the near field during the emergency discharge period.  Since the impact zones for the emergency TRC discharge are predicted to be localized (close to the SCISTW outfall) and temporary (within a few hours), the associated water quality and ecological impacts should be limited. The model results indicated that the maximum TRC levels predicted at all the identified water and ecological sensitive receivers would comply well with the assessment criterion under the emergency situations. 

5.252        In case of power outage, the uninterruptible power supply (UPS) system will switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent.      

5.253        The model predicted that the bacteria levels at the gazetted beaches, the (FCZ and the secondary contact recreation subzones in Tsuen Wan coastal waters, and the WSD flushing water intakes in western Victoria Harbour would be elevated due to the emergency release of undisinfected effluent at the SCISTW outfall during ADF stage and Stage 2A, but impacts are expected to be short-term.    In the event of emergency discharge of undisinfected effluent, the Plant operators of SCISTW should inform EPD and LCSD as soon as possible so that appropriate actions can be taken.    A list of address, email address, phone and fax number of key persons in relevant departments responsible for action should be made available to the plant operators.  Water quality monitoring should be carried out to quantify the water quality impacts and to determine when the normal water quality conditions are recovered. In view of the temporary nature of the emergency discharge, no insurmountable water quality impact is expected, provided that all the recommended mitigation measures are properly implemented.

 



([1]) Rehan Sadiq, Manuel J. Rodriguez (2003). Disinfection By-products (DBPs) in Drinking Water and Predictive Models for their Occurrence: A Review.

([2]) Tender Ref 2004T140 Testing of Chlorination / Dechlorination CEPT Effluent from SCISTW

([3])   Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning (Version 1.0), EPD, March 2005

([4] )   A.M. Shams El Din, Rasheed A. Arain, A.A. Hammoud (2000).  “On the chlorination of seawater”, Desalination 129, page 53-62, www.elsevier.com.

 

([5]) Chronic Toxicity Unit (TUc) is defined as: TUc = 100/NOEC, where NOEC = % of effluent which gives no observed effect on the diatom examined under the 7-day growth inhibition test as discussed in Sections 5.166 to 5.170.

([6]) Acute Toxicity Unit (TUa) is defined as TUa = 100/LC50, where LC50 = % of effluent which gives 50% survival of the most sensitive of the range of species examined under the 48-hour survival tests as discussed in Sections 5.166 to 5.170.