

TABLE OF CONTENTS
1. INTRODUCTION.. 1
1.1 Background. 1
1.2 Project Objectives. 1
1.3 Nature of the Project 1
1.4 Purpose of EIA Study. 1
1.5 The Approach. 1
1.6 Mitigation Measures. 2
1.7 Reference to Relevant
Study. 2
1.8 Scope of Key Environmental
Issues. 2
2. description of the project.. 4
2.1 Location and Description
of the Project 4
2.2 Identification of the
Project Need. 4
2.3 Considerations for Design
Options. 5
2.4 Alternative Options for
Entrance and Subway Alignment 9
2.5 Considerations of Alternative
Construction Methods. 10
2.6 The Preferred Scheme. 10
2.7 Implementation and
Planning of the Proposed Project 13
3. construction air quality impact.. 14
3.1 Introduction. 14
3.2 Environmental
Legislation, Standards and Guidelines. 14
3.3 Description of the
Environment 15
3.4 Air Sensitive Receivers. 15
3.5 Identification of
Pollutant Sources. 16
3.6 Assessment Methodology. 17
3.7 TSP Daily Concentration. 19
3.8 Evaluation of Impacts. 19
3.9 Cumulative Impacts. 20
3.10 Mitigation of Adverse Environmental
Impacts. 20
3.11 Evaluation of Residual Impacts. 21
3.12 Environmental Monitoring and Audit 21
4. NOISE IMPACT.. 22
4.1 Introduction. 22
4.2 Environmental
Legislation, Policies, Plans, Standards and Criteria. 22
4.3 Construction Noise –
General Construction Works. 22
4.4 Fixed Noise in Operation
Phase. 24
4.5 Noise Sensitive Receivers. 24
4.6 Assessment Methodology. 26
4.7 Identification of
Environmental Impacts. 29
4.8 Prediction and Evaluation
of Environmental Impacts. 29
4.9 Mitigation of Adverse
Environmental Impacts. 31
4.10 Evaluation of Residual Impacts. 34
4.11 Environmental Monitoring and Audit 37
4.12 Conclusion. 37
5. construction water quality impact.. 39
5.1 General 39
5.2 Environmental Legislation
and Standards. 39
5.3 Environmental Impact
Assessment Ordinance (EIAO), Cap. 499, S.16. 39
5.4 Water Pollution Control
Ordinance (WPCO) 39
5.5 Technical Memorandum.. 40
5.6 Practice Notes. 41
5.7 Baseline Condition. 41
5.8 Assessment Methodology. 42
5.9 Identification of Water
Sensitive Receivers. 42
5.10 Potential Sources from Construction
Activities. 42
5.11 Evaluation of Potential Water Quality
Impacts. 43
5.12 General Construction Site Activities. 44
5.13 Mitigation Measures. 44
5.14 General Construction Site Activities. 46
5.15 Evaluation of Residual Impacts. 46
5.16 Environmental Monitoring and Audit 46
5.17 Conclusions. 46
6. waste management.. 47
6.1 Introduction. 47
6.2 Environmental Legislation
and Standards. 47
6.3 Waste Management 47
6.4 Construction and
Demolition (C&D) Materials. 48
6.5 Assessment Methodology. 48
6.6 Prediction and Evaluation
of Environmental Impacts. 48
6.7 Mitigation Measures. 51
6.8 Evaluation of Residual
Impacts. 52
6.9 Environmental Audit 53
6.10 Conclusion. 53
7. Landscape and Visual Impact assessment.. 54
7.1 Introduction. 54
7.2 Environmental
Legislation, Standards and Guidelines. 54
7.3 Assessment Methodology. 55
7.4 Scope and Content of the
Study. 59
7.5 Review of Planning and
Development Control Framework. 59
7.6 Baseline Study. 60
7.7 Landscape Impact
Assessment 64
7.8 Visual Impact Assessment 71
7.9 Conclusion. 77
8. BUILT HERITAGE IMPACT ASSESSMENT.. 78
8.1 Introduction. 78
8.2 Environmental Legislation
and Standards. 78
8.3 Assessment Methodology. 79
8.4 Results of the Desk Based
Study. 80
8.5 Results of the Field
Survey. 82
8.6 Prediction and
Identification of Impacts. 82
8.7 Evaluation of Impacts. 83
8.8 Mitigation
Recommendations. 85
8.9 Conclusions. 85
9. environmental monitoring and audit (EM&A)
Requirements.. 86
9.1 Introduction. 86
9.2 Construction Air Quality
Impact 86
9.3 Noise Impact 86
9.4 Construction Water
Quality Impact 87
9.5 Waste Management 87
9.6 Landscape and Visual
Impact 87
9.7 Built Heritage Impact 88
10. ConclUsions And rEcommendations.. 89
LIST OF TABLES
Table 2.1 Summary
of the Preferred Scheme
Table 2.2 Preliminary
Construction Programme
Table 3.1 Hong Kong Air Quality Objectives
Table 3.2 Annual
Average TSP Concentration in the Latest Five Years (Year 2002 – 2006) for Urban
Development
Table 3.3 Details
of Representative Air Sensitive Receivers
Table 3.4 Emission
Factors for Construction Activities
Table 3.5 Predicted
Maximum 1 - hour Average TSP Concentrations
Table 3.6 Predicted
Maximum 24 - hour Average TSP Concentrations
Table 4.1 Daytime
Construction Noise Criteria
Table 4.2 Acceptable
Noise Levels
Table 4.3 Acceptable
Noise Level for Fixed Plant Noise
Table 4.4 Summary
of Representative Noise Sensitive Receivers
Table 4.5 Construction
Tasks Involved
Table 4.6 Ventilation
Shafts for the Proposed Project
Table 4.7 Summary
of Unmitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours
Table 4.8 Summary
of Max SWL for Each Ventilation Shaft
Table 4.9 Summary
of Max SWL for Each Ventilation Shaft with Consideration of Cumulative Effect
Table 4.10 Quieter
PME Recommended for Adoption during Construction Phase
Table 4.11 Noise
Mitigation Measures for Certain PME during Construction Phase
Table 4.12 Mitigated
Construction Noise Levels
Table 4.13 Construction
Noise Residual Impacts
Table 4.14 Durations
of Construction Noise Residual Impacts
Table 4.15 Construction
Noise Residual Impacts at NSR N5
Table 5.1 Summary
of Water Quality Objectives for Victoria Harbour WCZ
Table 5.2 Marine
Water Quality of Victoria Harbour WCZ at
the Selected Monitoring Station in 2006
Table 6.1 Estimated
Quantities of C&D Materials
Table 7.1 Relationship
between Receptor Sensitivity and Impact Magnitude in Defining Impact
Significance
Table 7.2 List
of the Landscape Resources and Their Sensitivity to Change
Table 7.3 Visual
Sensitive Receivers (VSRs) and Their Sensitivity to Change
Table 7.4 Significant
Landscape Impacts of the Proposed Works during Construction Phase
Table 7.5 Proposed
Construction Phase Landscape Mitigation Measures
Table 7.6 Proposed
Operation Phase Landscape Mitigation Measures
Table 7.7 Significance
of Landscape Impacts in the Construction and Operation Phases
Table 7.8 Significance
of Visual Impacts in the Construction and Operation Phases
Table 8.1 Distance
of the Identified Resources in the Project Study Area from the Proposed Works
Table 10.1 Summary
of Key Environmental Outcomes
LIST OF FIGURES
Figure 1.1 Site
Layout Plan
Figure 1.2 Section
A-A
Figure 1.3 Section
B-B
Figure 1.4 Section
C-C
Figure 1.5 Study
Boundary for Air Quality, Noise and Water Quality Assessment
Figure 2.1 Construction
Sequence – Plant Basement
Figure 2.2 Construction
Sequence – Satellite Concourse
Figure 3.1 Locations
of Representative Air Sensitive Receivers
Figure 3.2 Contours
of Maximum 1-Hour Average TSP Concentration at 1.5m Above Ground
Figure 3.3 Contours
of Maximum 24-Hour Average TSP Concentration at 1.5m Above Ground
Figure 4.1 Locations
of Representative Noise Sensitive Receivers
Figure 4.2 Schematic
Diagram Showing Typical Site Arrangement
Figure 4.3 Schematic
Diagram Showing Typical Site Arrangement
Figure 4.4 Assumed
Worst Locations of Ventilation Shaft Openings
Figure 5.1 Locations
of Marine Water Quality Monitoring Stations in Victoria Harbour WCZ (VM5 &
VM6)
Figure 7.1 Landscape
and Visual Impact Study Area
Figure 7.2 Baseline
Landscape Resources
Figure 7.2.1 Baseline
Landscape Resources Photos
Figure 7.2.2 Baseline
Landscape Resources Photos
Figure 7.2.3 Baseline
Landscape Resources Photos
Figure 7.2A Aerial
Photograph Showing Baseline Landscape Characters and Resources
Figure 7.3 Key
VSRs and Zone of Visual Influence During Construction and Operation
Figure 7.3.1 Baseline
VSRs Photos
Figure 7.3.2 Baseline
VSRs Photos
Figure 7.4 Propose
Landscape Mitigation Measure
Figure 7.4.1 Photomontage
A
Figure 7.4.2 Photomontage
B
Figure 7.4.3 Photomontage
C
Figure 8.1 Enhanced
Entrance A1
Figure 8.2 Enhanced
Entrance A1 (View from NE Corner)
LIST OF APPENDICES
Appendix 3.1 Construction
Dust Emission Factors
Appendix 4.1 Photographs of Representative Noise Sensitive Receivers
Appendix
4.2 Plant
Inventory for Construction Noise Assessment (Unmitigated)
Appendix 4.3 Calculation
of Construction Noise Levels at Representative Noise Sensitive Receivers During
Normal Daytime Working Hours (Unmitigated Scenario)
Appendix 4.4 Plant
Inventory for Construction Noise Assessment (Mitigated)
Appendix 4.5 Calculation
of Construction Noise Levels at Representative Noise Sensitive Receivers During
Normal Daytime Working Hours (Mitigated Scenario)
Appendix 8.1 Figures
of Built Heritage Impact Assessment
Appendix 8.2 Catalogue
of the resources surveyed for the Project
Appendix 8.3 Photographs of the
existing environment
Appendix 10.1 Implementation
Schedule of the Proposed Mitigation Measures
Hayes, J 1966 Old
British Kowloon, Journal of the Hong Kong Royal Asiatic Society, Vol VI
pp.120-137
1.1.1
The title of this project is known as “Tsim Sha Tsui Station Northern Subway”
(TNS) (hereafter known as the Project). The Project Proponent is MTR Corporation
Limited (MTRCL). ENSR Asia (HK)
Limited has been commissioned to carry out an Environmental Impact Assessment
Study for the Project.
1.2.1
The
objectives of this Project are to
provide passengers with a direct and accessible safe pedestrian subway in
addition to the existing entrances and to relieve the existing busy northern
concourse and platform areas of Tsim Sha Tsui (TST) Station by providing a new
direct high-capacity corridor for effective passenger access. The location of the proposed Project is shown in Figure 1.1. Three cross sections of the Project are
shown in Figures 1.2 to 1.4.
1.3.1
The Project is classified as a
Designated Project under Category A.2 (A railway and its associated stations)
of Part 1, Schedule 2 of the EIAO.
1.3.2
The Project involves construction and operation of (i) An
underground pedestrian subway link that connects the north end of the TST
Station platform with integrated entrances in the basements of the Tung Ying Building Redevelopment, Miramar Hotel and
Miramar Shopping Centre; (ii) An underground satellite concourse underneath
Nathan Road located adjacent to Tung Ying
Building and the Miramar Hotel; and (iii) A new plant basement near existing
Entrance A1 to house the station equipment relocated from the north end of TST
Station for accommodating the TNS connection.
1.4
Purpose of EIA Study
1.4.1
The purpose of this EIA Study
is to provide information on the nature and extent of environmental impacts
arising from the construction and operation of the proposed subway works, and
to contribute to decisions on the overall acceptability of the Project, after
the implementation of proposed mitigation measures.
1.5.1
The EIA study has been prepared
in accordance to the EIA Study Brief (No. ESB-168/2007) and the guidelines
provided in Annex 11 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM) for the report contents and Annexes 12 to 19 for
the impact assessments of various environmental issues. The general approaches and methodologies
adopted for this EIA study are described below.
Existing
Environment Condition
1.5.2
The characteristics of the
existing environment were reviewed for identification and prediction of
environmental impacts. The baseline
conditions of the key issues as identified in the EIA Study Brief including
landscape & visual, noise, construction air and water quality and built
heritage are described in the assessment.
Impacts
Prediction
1.5.3
The EIA Study was undertaken in
accordance with the guidelines on assessment methodologies given in Annexes 12
to 19 of the EIAO-TM.
1.5.4
Quantitative approach was adopted
for assessing the construction noise impacts. The predictions were conducted
based on well-proven, internationally accepted methods.
1.5.5
The applied methodologies for
the Project had previously been adopted in other EIA studies. They have been generally accepted for
use in predicting environmental impacts and for comparison of assessment
results with the EIAO-TM requirements.
Limitations are however envisaged of these methodologies. The accuracy
of the prediction result will be affected by uncertainty in input data such as
sound power levels of construction plants to be used on-site. The most realistic data have been used
in the prediction in order to provide a result with the lowest practicable
quantitative uncertainty.
1.6.1
Mitigation measures are
proposed to alleviate the potential impacts predicted. The proposed mitigation
measures have previously been adopted in other environmental assessment studies
with similar construction works. An
Environmental Monitoring and Audit programme is recommended to ensure that the
recommended mitigation measures can effectively mitigate the impacts so as to
comply with the corresponding criteria.
1.7.1
The EIA Study was made
reference to the approved relevant EIA Study Modifications to MTRCL Tsim Sha Tsui Station, Mass Transit Railway Corporation Limited
(EIAO Register No.: AEIAR-043/2001).
1.8.1
The identified key
environmental issues regarding the construction of the proposed Project are
listed as below:
·
potential construction dust impacts to nearby
sensitive receivers from the Project;
·
potential construction and operation noise impacts
to nearby sensitive receivers from the Project;
·
potential construction water quality impacts to
nearby sensitive receivers, as well as waste management implications, from the
Project;
·
potential landscape and visual impacts to nearby
sensitive receivers from the Project during its construction and operation
stages;
·
potential impacts to nearby identified heritage resources from the Project during its construction and
operation stages; and
·
potential cumulative impacts to nearby sensitive
receivers for the above key issues, taking into account the existing
construction works is discussed in Section 2.
1.8.2
The assessments of these key
environmental issues are to be discussed in the following chapters of this
Report. The study boundaries of construction air quality, noise and
construction water quality impacts are shown in Figure 1.5.
1.8.3
The Project is within a developed urban area,
there are no ecological sensitive receivers, such as
Sites of Special Scientific Interest (SSSIs), Fish Culture Zones and Marine Parks
and/or Reserves and other areas of ecological importance or conservation
interest, within or in the immediate vicinity of the site area. Ecological impacts are, therefore, not
expected during the construction and operation phases of the proposed
Project. Accordingly ecological impact assessment is not required
in this EIA Study.
2.1.1
The Project is located in Tsim
Sha Tsui district which is an urban area with mixture of commercial and
residential developments. The
proposed works lie along Nathan
Road from Cameron Road junction to Miramar Shopping
Centre near Kimberley Road. The proposed new plant basement will be
located under the existing Entrance A1 of the TST Station.
2.1.2
The project includes the
following:
·
A
subway (Subway TST) from the north end of TST Station, running approximate 85m
under Nathan Road
to a Satellite Concourse;
·
A
satellite concourse (45m approx) underneath Nathan Road located adjacent to Tung Ying
Building and the Miramar
Hotel;
·
A
subway (Subway MSC) from the north end of the Satellite Concourse, running
approximate 80m under Nathan Road
to the Miramar Shopping Centre (MSC).
2.2
Identification of the
Project Need
2.2.1
The passenger forecast study
has established that the north of TST Station is under the most pressure and is
now already approaching capacity.
This is because the station catchment areas of the northern section are
relatively more developed and will have more re-development. The northern section of the station is
already and is expected to continue to be overloaded, especially at the
vertical links between concourse and street at Entrances A1 (to Nathan Road and Haiphong Road), B1
and B2 (to Nathan Road
and Cameron Road). Without any modification works, the
north end of the station concourse will become significantly overloaded in the
next few years.
2.2.2
The proposed subway will
provide a direct link for passengers between the platform at the north end of
the TST Station to a satellite concourse with access to street level via subway
connections to the Tung Ying
Building Redevelopment, Miramar Hotel, and Miramar Shopping Centre. Passengers
can access the development areas north-east of TST, thus avoiding congestion
and a number of signalled pedestrian crossings at street level.
2.2.3
TNS will provide an attractive
route for existing and future passengers as it will enhance the walking
quality, and provide a fast, safe, air-conditioned and weather proof route
between the station and the catchment north of Tsim Sha Tsui avoiding Entrances
A1, B1 and B2 of TST Station and traffic and pedestrian congestion at street
level.
2.2.4
In the absence of the project,
in the longer term the TST Station would remain busy and its congested sections
would remain saturated. This
strongly implies that the station is in need of a significant operational
relief in its northern section, despite the launching of the Kowloon Southern
Link (KSL) in year 2009, and the passenger diversion that it may cause.
2.2.5
The TNS scheme is also
complementary with a number of pedestrian schemes and traffic calming measures
implemented by the Government of the HKSAR in the area west of Nathan Road to
improve the whole pedestrian environment.
These include Haiphong Road,
Canton Road, Peking Road, Hankow Road, Lock Road and Ashley Road modification schemes. As these schemes have been well received
by the public, further schemes are in progress to implement even more
comprehensive measures to regulate both vehicular and pedestrian traffic to
achieve a better environment in the whole Tsim Sha Tsui area.
·
Those
projects include:
·
Greening
Master Plan (GMP) for TST Area by Civil Engineering Development Department
(CEDD); and
·
Area
Improvement Plan (AIP) for TST Area by Transport Department (TD).
2.2.6
Since the opening of East Tsim
Sha Tsui (ETS) Station and the new pedestrian connections to TST Station, it
has provided rail and non rail users a direct and convenient interchange
to/from MTR stations, relieving congestion at the busy street level and
enhancing the walking environment in Tsim Sha Tsui. In the next few years, this subway
network is to be expanded to include the Middle Road Subway Extension to Peking Road
extending the railway catchment to the south west of Tsim Sha Tsui. With both the ETS related pedestrian
links in TST south and the TNS scheme in TST north completed, the TST District
can be comprehensively served with good pedestrian connectivity and
accessibility along both sides of Nathan
Road.
2.2.7
To conclude, this station
improvement scheme would provide much-needed relief to the currently congested
Entrances A1 (to Haiphong Road)
and B1 & B2 (to Cameron Road). Without such relief, these two northern
entrances would continue to suffer from heavy operational pressure, especially
with the continuous TST catchment growth following the airport relocation and
the subsequent relaxation of building height/massing constraints in south Kowloon.
2.3
Considerations for Design Options
2.3.1
In 2006, MTRCL commenced the
planning of a new capacity enhancement scheme to relieve the northern section
of the TST Station. This is known
as the Tsim Sha Tsui Station Northern Subway (TNS) and is the subject of this
submission. This scheme consists of
an underground pedestrian subway link (TNS) that connects the northern end of
the TST Station platform, via the modified concourse plant room area, with
integrated entrances in the basements of Tung Ying
Building Redevelopment, Miramar Hotel and the Miramar Shopping Centre together
with an underground satellite concourse (the Satellite Concourse) in the middle
of the subway.
Considerations
for TNS Subway Alignment
2.3.2
The two prime objectives to be
achieved in the planning of the TNS subway include:
·
to
provide a direct pedestrian subway link between the TST Station and the Tung Ying Building Redevelopment, Hotel Miramar and
Miramar Shopping Centre;
·
to
accommodate the existing plant rooms displaced from the TST Station by the TNS
subway link.
2.3.3
The key objective is to
minimise the walking distance as far as practicable. Obviously, if the
alignment of the pedestrian subway is not attractive to the passengers, the
purpose of building it will be defeated.
In planning the subway alignment, there are several key considerations
for its layout and the form that it might take. The major constraints on the design and
construction of the proposed subway identified are as follows:
·
Clearance
requirements to the Tsuen Wan Line (TWL) Tunnels and structures;
·
Minimum disturbances to the existing water mains,
utilities and drainage systems;
·
Interface with the redevelopment works of Tung Ying Building (TYB);
·
Interfaces with Hotel Miramar (HM) and Miramar
Shopping Centre (MSC), both in use during construction;
·
Interface with MTR TST Station and the need to
minimise any impacts on the functionality of key public and plant room areas;
·
Limited works area and construction access;
·
Land availability and projections from buildings;
·
Vehicular and Pedestrian Traffic Management during
construction;
·
Landscape and visual impacts for any above ground
structures;
·
Minimal disturbance to Old and Valuable Trees
(OVTs) and trees of landscape value; and
·
Minimum noise and dust nuisance to the public and
residents during construction.
TNS
Subway Alignment
2.3.4
In identifying the above
constraints, the preferred alignment of the subway has been developed to
provide:
·
a shallow and broad subway;
·
a vertical alignment that is as flat as possible,
the ideal conditions for pedestrians comfort and convenience;
·
Travelators to further enhance passenger convenience.
2.3.5
As the vertical alignment of
the subway is controlled by the need to connect into the TST Station and the
basement of Tung Ying Building
Redevelopment, Miramar Hotel and Miramar Shopping Centre, there is limited
flexibility in adjusting the vertical alignment.
2.3.6
The subway connects into the
section north end wall at approximately 1m above existing concourse level to provide
sufficient cover to the existing MTR running tunnels underneath. To overcome any artificial obstructions,
in the form of left-in-place temporary piles and grout injection tubes, a
Connection Chamber is located here to be built by cut-and-cover method. The Connection Chamber is a buried
underground structure with no permanent impacts at ground or above-ground
level.
2.3.7
The north end of the existing
TST Station is to be modified to accommodate the passageway to Subway TST (the
southern section of the subway between the Satellite Concourse and TST
Station).
New
Plant Basement Options
2.3.8
The connection between the
Subway MSC (the northern section of the subway between Satellite Concourse and
the Miramar Shopping Centre) and TST Station requires that the existing station
E&M equipment from north-end plant rooms be re-located to provide a clear
passageway to the platform. There
is no space in the existing station for the relocated E&M equipment. By inspection of the surrounding area,
the only vacant space near the station in which to construct a new Plant
Basement to contain the displaced equipment from TST Station is in the vicinity
of Entrance A1.
2.3.9
In physical terms, the new
plant basement is contained within a zone around Entrance A1 with the following
structures and features surrounding it:
·
Heritage building, known as the Health Education
Exhibition and Resource Centre (HEER) located north;
·
the old retaining wall at Haiphong Road;
·
existing TST Station Entrance A1 Adit and
Ventilation Shaft Z located east;
·
the western wall of the TST Station and Nathan Road to the
west; and
·
existing Entrance A2 Adit and Haiphong Road to the south.
2.3.10
The dimensions of the Plant
Basement are constrained by the site environs (see above). Options have been considered for both
single-level and two-level basements.
The single level basement extended beyond the footpath of Haiphong Road was
rejected based on unacceptable impacts to the existing structures nearby and
the traffic on Haiphong Road. A two-level basement was preferred as
the layout was more compact and minimised impacts to the surrounding vehicular
traffic and the existing structures including the heritage building nearby.
2.3.11
The plant basement will be
ventilated through to the existing exhaust stack in Vent Shaft ‘Z’, in
preference to constructing new ventilation shafts which would cause operational
noise, visual and landscape impacts.
Entrance
Options
General
2.3.12
In general, the above-ground
entrances have the most potential impacts on noise, dust, visual and landscape
to the public. The entrance options
discussed in the following section have different impacts on the immediate
surrounding areas as follows:
Entrances Q1, Q2 and Q3
2.3.13
The three integrated entrances
to the east of the satellite concourse (namely, Entrances Q1, Q2 and Q3) will
have no permanent environmental impacts at ground and above-ground levels, with
the only impacts being the underground connections to the basement levels of
the adjoining buildings, namely, Tung Ying
Building Redevelopment and the two existing Miramar Developments, Miramar Hotel
and Miramar Shopping Centre.
2.3.14
As far as these buildings and
their integrated MTR entrances are concerned, appropriate interior layout will
be arranged such that any pedestrians can be fed to/from the respective
buildings, and any by-passing passengers can walk effectively through these
buildings for:
·
comfort of weather proof environment; and
·
convenient and direct access to the station’s
platform avoiding the congested northern section at the station’s concourse
level.
Entrances Q4 and Q5 on Park Lane Shopper’s Boulevard
2.3.15
To comply with statutory
requirements for the emergency escape requirements from the subway. It has been established that one
emergency exit is required at the Satellite Concourse, the mid-point between
the two subways. A second emergency
exit is required at the end of Subway MSC.
As emergency escapes routes can be upgraded to form entrances, a review
of entrance options was undertaken on the western footpath of Nathan Road. These entrances are all located in order
to:
·
facilitate public accessibility to the station, the
Kowloon Park or as a means of crossing Nathan Road; and
·
assist in evacuation from the underground subway.
2.3.16
The environmental
considerations include the need to:
·
minimise noise and dust impacts during
construction;
·
minimise the visual and landscape impacts during
construction and operation;
·
minimise the nuisance to pedestrians during
construction; and
·
avoid the large OVTs, and the assumed extent of
their tree roots and tree canopies.
2.3.17
The entrance locations
identified on the western footpath of Nathan
Road include:
a)
An entrance located at the Kowloon Park
entrance between the north and south blocks of Park Lane Shopper’s Boulevard;
b)
An entrance opposite the Miramar Shopping Centre;
and
c)
An entrance opposite the proposed Satellite
Concourse.
No further entrance options were identified, given the constraints found
on the footpaths of Nathan Road.
2.3.18
The entrance scheme at Kowloon Park
was not considered further due to construction impacts on the existing Kowloon Park stair structure where the electric
equipment supporting the Park Lane Boulevard shops could not be temporarily
re-provided during construction.
2.3.19
Substantial discussions had been
held with Leisure and Cultural Services Department (LCSD) regarding the
entrance options proposed on the footpath of Park Lane Boulevard opposite the
Miramar Shopping Centre and the proposed Satellite Concourse. Though due considerations have been given
in the design and construction methodology of the entrances, it is concluded
that the two entrance options on the footpath of Park Lane Boulevard were
inappropriate in view of the potential impacts to the OVTs on the west side of
Nathan Road and were not further pursued.
2.3.20
The ventilation shaft
originally proposed to be integrated with one of the entrance on the footpath
of Park Lane Boulevard will be incorporated with the Tung Ying Redevelopment and Hotel Miramar.
Emergency Exits
2.3.21
As mentioned earlier, two
emergency exit points are required for the scheme, and as no entrances would be
provided to street, the proposed emergency exits are dedicated escape routes
only and not for public access. Two
locations identified are at the satellite concourse and at the end of the
Subway MSC.
Emergency Exit at the Satellite Concourse
2.3.22
The emergency exit at the
Satellite Concourse exits via the Tung Ying
Building Redevelopment in a dedicated emergency corridor to street level. The exit location to street is under
study by the Tung
Ying
Building developer.
Emergency Exit at Subway MSC
2.3.23
The emergency exit is situated
in the east footpath and planter of Nathan
Road. It was placed well away from the OVT in the
roadside planter in front of the Miramar Shopping Centre. The footprint of the emergency exit was
minimized to fit into the space at present occupied by young Ficus microcarpa (non-OVTs). No other feasible locations have been
identified due to the sever constraints found in the area. To minimise any sight line problems and
visual impacts, the above-ground structure is level with the existing planter
and finished with materials to the adjacent planter to provide total
integration.
Entrance A1 Upgrade
2.3.24
The existing canopy structure
for Entrance A1 is approximately twenty-six years old.
2.3.25
The existing Entrance A1 canopy
will be demolished during construction of the Plant Basement. It will be replaced with an iconic
transparent glass box, a distinctive station entrance that reinforces the
Corporate image in Tsim Sha Tsui District.
The new Entrance A1 will improve access to the station with a disabled
lift serving the Kowloon
Park entrance, street
level and the TST concourse level, a staircase and escalators from street level
to the existing Entrance A1/A2 adit.
2.3.26
The transparent structure is
intended to allow the new structure to blend in with the surrounding
environment and minimise any landscape and visual impacts.
2.4.1
Alternative entrance locations
and subway alignment are studied under the following constraints placed on this
Project:
a)
Location of large OVTs and their assumed extend of
root system near the project boundary;
b)
Requirement of an emergency escape/exit at the
subway northern end;
c)
Requirement of an emergency escape/exit located at
the mid-point between the existing TST station box and the northern end of the
subway extension; and
d)
With the objective to minimise the walking distance
as much as practicable; hence the shortest construction duration and the
minimal environmental impacts.
2.4.2
Alternative location for
Entrance Q3 (proposed at the footpath of Park Lane Boulevard) has been
reviewed. Nevertheless, in view of
the potential impacts to the OVTs on the west side of Nathan Road, it is
concluded that lesser degree of environmental impact cannot be provided from
any alternative due to the location constraint and thus not pursued further.
2.4.3
For the subway alignment, the
current alignment provides the shortest and the most direct connection between
the existing TST Station & Satellite Concourse and between Satellite
Concourse and the Miramar Shopping Centre, such that the environmental impact will
be minimised.
Other alignment alternatives have been considered but all present
additional environmental burdens from noise and dust due to longer or deeper
subway alignment hence were not further pursued.
2.5.1
The construction of the TNS
subway and associated structures is expected to be difficult, given the obvious
need to minimise any environmental disturbance and impacts on the OVTs, traffic
and pedestrian, residents, existing MTRCL Tsuen Wan Line (TWL) tunnels, TST Station and the nearby building
structures. Tunneling by mining
method and cut-and-cover method are the available techniques to select from. Based on the study, large proportion of
the works under this project are to be constructed using tunneling by mining
method, in which environmental impact will be minimised, only small proportion
of works, where above ground construction works are inevitable are to be
constructed by cut-and-cover method.
2.5.2
In order to minimise the
environmental impacts and disturbance to the existing utilities and traffic
along Nathan Road,
the subway tunnels, which comprise a large proportion of the project, are to be
constructed by using tunneling
by mining method.
The alignment of the tunnels and ground conditions found in the project
area are considered suitable for using tunneling by mining method based on the
geological information provided by the geotechnical investigation carried out
for this Project.
2.5.3
For the small remaining
proportion of works of this project, where above ground construction works are
inevitable (such as area with limited soil cover and the need for access point
for the works), the cut-and-cover method are to be adopted. Nevertheless, cut-and-cover elements of
the work have been limited as far as practicable to the Satellite Concourse,
Connection Chamber, Plant Basement and the Emergency Exit stair.
2.5.4
Whenever cut-and-cover method is adopted,
majority of construction works will be decked to reduce
airborne noise, dust, visual and minimise traffic
impacts which allow traffic to be diverted back over the excavation on Nathan Road.
2.5.5
Other alternative construction
method including open-cut excavation method has been reviewed. Nevertheless, in view of large
environmental impact will be created as compare with tunneling by mining method
and cut-and-cover method, it is not recommended and thus not further pursued.
2.6.1
The site constraints,
environmental factors and options available for the selection of the preferred
scheme have been discussed in the above sections and are summarised below in Table
2.1:
Table 2.1 Summary of the Preferred
Scheme
TNS Component
|
Scheme and Environmental Factors Considered
|
Subway Tunnels
-
Subway TST
-
Subway MSC
|
·
The TNS subway is the most direct and shortest link to the proposed
entrances, i.e. minimise the extent of the construction works area and limit
the works area to the section of Nathan
Road that are mostly surrounded by hotels and
commercial buildings provided with central air conditioning systems and do
not rely upon openable windows for ventilation.
·
The subway tunnels which form of a large proportion of the project are
to be constructed using tunneling by mining method. The environmental benefits include:
- minimal
airborne noise and dust impacts on nearby sensitive receivers;
- minimal
impact on the traffic and pedestrians at street level during construction to
reduce the chance noise generated from possible traffic back up.
·
The subway alignment shifts towards the east side of Nathan Road away
from the row of OVTs on west footpath of Nathan Road.
|
Cut-and-Cover Components –
Satellite Concourse, Connection
Chamber, Plant Basement and Emergency Exit
|
·
Above ground
construction work are inevitable.
Nevertheless, they are limited as far as practicable to:
- Satellite
Concourse;
- Plant
Basement;
- Connection
Chamber; and
- Emergency
Exit Stair.
Moreover, cut and cover
method is adopted, i.e. majority of construction works would be carried out
under road deck. Dust and airborne noise emission
during construction, would be screened off by the road deck from the nearby
receivers.
|
Plant Basement and Entrance A1 Upgrade
|
·
The two-level plant
basement located near Entrance A1 is compact to minimise environmental impacts during the construction phase.
Comparing to the single-level scheme, the works area would be largely
reduced, the associated impacts, particularly construction noise and fugitive
dust impacts are substantially reduced.
·
Relocation of the
plant basement near Entrance A1 provides an opportunity to upgrade the
entrance. The old entrance is over 26 years
old.
The new entrance with use of transparent glass would reduce bulk
effect and be in compatible with the adjacent urban setting. The new facilities for the entrance
include a disabled lift serving the station, street level and Kowloon Park. The accessibility/connectivity
of Kowloon Park,
a recreational/ leisure resource in urban Hong Kong,
is effectively enhanced with the Entrance A1 upgrade in place as it
significantly improves the pedestrian and disabled access to the park from
the station with insubstantial level of visual impact.
·
Ventilation at the
plant basement utilises the existing exhaust shaft that could avoid
environmental impacts arising from construction of a new vent shaft.
|
Emergency Exit
|
·
The emergency exits are a statutory requirement for the TNS
scheme. The emergency exits are
located at the Satellite Concourse and at the end of Subway MSC.
·
The emergency exit at the Satellite Concourse is routed via the Tung Ying Building Redevelopment in a dedicated route
to street level.
·
The emergency exit at Subway MSC is situated in the planter along the east footpath at Nathan Road. The above ground structure is level with the
existing planter and finished with materials similar to the
adjacent planter to provide total integration. Moreover it is well
away from the OVT. As such visual and landscape impacts
are minimised.
|
2.6.2
Following review of the scheme
options, construction methods and environmental factors, the preferred scheme
for the Tsim Sha Tsui Station Northern Subway consist of :
a)
A subway (Subway TST) from the
north end of TST Station, running approximate 85m under Nathan Road to a Satellite Concourse;
b)
A satellite concourse (the
Satellite Concourse) approximate 45m underneath Nathan Road, containing ticket gates
(reversible type), ticket issuing machines (TIMs), self service points,
help-lines, etc. It has direct
underground connections to the basements of the Miramar Hotel and of the
development on the site of the former Tung Ying Building - these integrated entrances
are designated Q2 and Q1 respectively.
A mezzanine level in the Satellite Concourse contains electrical and
ventilation plantrooms for the subway;
c)
A subway (Subway MSC) from the
north end of the Satellite Concourse, running approximate 80m under Nathan Road to the
Miramar Shopping Centre (MSC), where an underground link connects to its
basement. This integrated entrance
is designated Q3;
d)
An Emergency Exit situated in
the east footpath and planter of Nathan
Road, outside the Miramar Shopping Centre;
e)
The fresh, ventilation and smoke exhaust ducts for
TNS are integrated with the Tung Ying
Redevelopment and Hotel Miramar;
f)
A two-level plant basement (Plant Basement) located
below and in front of Entrance A1 to house the displaced E&M equipment from
the north end of TST Station; and
g)
Entrance A1 upgrade to replace the existing
concrete structure with a new transparent box reconstructed on the same site
with a improved access to the station with new disabled lift serving TST
concourse level, street and Kowloon Park; and escalators serving street and the
existing Entrance A1 Adit.
2.7
Implementation and Planning
of the Proposed Project
2.7.1
The proposed works are
scheduled to commence in June 2009 with duration of approximately 35 months.
The entire project is scheduled to be completed in May 2012. The preliminary
construction programme for the Project is shown in Table 2.2.
Table 2.2 Preliminary
Construction Programme
Activity
|
Time
period
|
Site clearance and set up
|
Jun
2009 to Jul 2009
|
Tree Protection
|
Jun
2009 to Jan 2012
|
Plant Basement and
Entrance A1 construction
|
Jul
2009 to Dec 2010 and Nov 2010 to Nov 2011
|
Satellite
Concourse and Entrances Q1 and Q2 construction
|
Nov
2009 to Jan 2012
|
Subway to TST
Station
|
Mar
2011 to Dec 2011
|
Subway to Miramar
Shopping Centre and Entrance Q3 construction
|
Feb
2011 to Dec 2011
|
Emergency Exit at Miramar Shopping Centre
|
Jul 2009
to Aug 2009, Nov 2011 to Feb 2012
|
TST Connection Chamber
|
Jul
2009 to Mar 2010
|
TST North End modification
|
Jun
2011 to Mar 2012
|
Landscaping works
|
Oct
2011 to Jan 2012
|
Site reinstatement works
|
Jan
2012 to May 2012
|
2.7.2
The construction of the
proposed Plant Basement and Satellite Concourse are divided into six stages to
adopt temporary pedestrian flow and traffic diversion. The construction
sequence of the Plant Basement and Satellite Concourse are shown in Figures
2.1 and 2.2 respectively.
2.7.3
Based on the tentative
construction programme, the Project will be carried out concurrently with the
adjacent Tung Ying Building
Redevelopment, which is under construction. It is expected that the foundation and
infrastructure works of the Tung Ying
Building Redevelopment will be completed at the time of the commencement of
this Project. Consequently,
cumulative environmental impacts from the Tung Ying
Building Redevelopment are envisaged to be insignificant.
3.
construction air quality impact
3.1.1
This section presents air
quality impact assessment during construction phases of the Tsim Sha Tsui
Station Northern Subway (TNS) Project.
Representative Air Sensitive Receivers (ASRs) and the potential air quality
impact on these receivers associated with the Project has been identified and
assessed. Appropriate mitigation
measures would be proposed if necessary.
3.2.1
The criteria for evaluating air
quality impacts and the guidelines for air quality assessment are set out in
Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
Air Quality Objective &
EIAO-TM
3.2.2
The Air Pollution Control
Ordinance (APCO) provides the statutory authority for controlling air
pollutants from a variety of sources.
The Hong Kong Air Quality Objectives (AQOs), which must be satisfied,
stipulate the maximum allowable concentrations of certain pollutants over
specific periods. The relevant AQOs
are listed in Table 3.1.
Table 3.1 Hong Kong Air Quality Objectives
|
Maximum Concentration (µg m-3) (1)
|
Pollutant
|
Averaging Time
|
|
1 hour (2)
|
8 hour (3)
|
24 hour (3)
|
Annual (4)
|
Total Suspended Particulates (TSP)
|
-
|
-
|
260
|
80
|
Respirable Suspended Particulates
(RSP) (5)
|
-
|
-
|
180
|
55
|
Sulphur Dioxide (SO2)
|
800
|
-
|
350
|
80
|
Nitrogen Dioxide (NO2)
|
300
|
-
|
150
|
80
|
Carbon Monoxide (CO)
|
30,000
|
10,000
|
-
|
-
|
Photochemical Oxidants
(as Ozone, O3) (6)
|
240
|
-
|
-
|
-
|
Notes:
(1)
Measured at 298 K and
101.325 kPa.
(2)
Not to be exceeded more than
three times per year.
(3)
Not to be exceeded more than
once per year.
(4)
Arithmetic mean.
(5)
Suspended particulates in
air with a nominal aerodynamic diameter of 10 mm or smaller.
(6)
Photochemical oxidants are
determined by measurement of ozone only.
Air Pollution Control
(Construction Dust) Regulation
3.2.4
Notifiable and regulatory works
are under the control of the Air Pollution Control (Construction Dust)
Regulation. Notifiable works are
site formation, reclamation, demolition, foundation and superstructure construction
for buildings and road construction.
Regulatory works are building renovation, road opening and resurfacing
slope stabilisation, and other activities including stockpiling, dusty material
handling, excavation, concrete production etc. This Project is expected to include both
notifiable and regulatory works.
Contractors and site agents are required to inform the Environmental
Protection Department (EPD) on carrying out construction works and to adopt
dust reduction measures to reduce dust emission to the acceptable level.
3.3.1
The Project is located in Tsim
Sha Tsui district which is an urban area with mixture of commercial and
residential developments. The
proposed works lie along Nathan
Road from Cameron Road junction to Miramar Shopping
Centre near Kimberley Road. The proposed new plant basement is
located under the existing Entrance A1 of the TST Station.
3.3.2
There is no EPD air quality
monitoring station at Tsim Sha Tsui.
The background pollutant values adopted for assessment are based on the
EPD “Guideline on Assessing the ‘TOTAL’ Air Quality Impacts”. In the categorisation of monitoring air
quality data, Tsim Sha Tsui is categorised as urban development. The latest five years (2002-2006)
average monitoring data for urban development would be adopted as the background
concentrations. These urban
monitoring stations considered in this assessment include: Central/Western,
Kwun Tong and Sham Shui Po. Table
3.2 summarizes the annual average TSP concentrations adopted as background
concentrations for this air impact assessment.
Table 3.2 Annual
Average TSP Concentration in the Latest Five Years (Year 2002 - 2006) for Urban
Development
Pollutant
|
Annual Average Concentration in the Latest Five Years (mg m-3)
|
TSP
|
78
|
3.4.1
In accordance with the Annex 12
of the EIAO-TM, any domestic premises, hotel, hostel, hospital, clinic,
nursery, school, educational institution, office, factory, shop, shopping
centre, place of public worship, library, court of law, sports stadium or
performing arts centre are considered to be an ASR. Any other place with which, in terms of
duration or number of people affected, has a similar sensitivity to the air
pollutants as the aforelisted places are also be considered to be a sensitive
receiver, for example, playground, sitting area of parks/promenade.
3.4.2
No planned ASRs are located in
vicinity of the Project. The
identified representative ASRs are listed in Table 3.3 and the
corresponding locations are shown in Figure 3.1.
Table 3.3 Details of Representative Air Sensitive
Receivers
ASR
|
Description
|
*Current
Use
|
Distance
from nearest emission sources (m)
|
A1
|
Parmanand House
|
Commercial
|
40
|
A2
|
Hai Phong
Mansion
|
Residential and commercial
|
20
|
A3
|
Health Education Exhibition and Resource
Centre
|
G/IC
|
35
|
A4
|
Health Education Exhibition and Resource
Centre
|
G/IC
|
5
|
A5
|
Kowloon Mosque and Islamic Centre
|
Religionary
|
25
|
A6
|
Park
Lane Shopper's Boulevard
|
Shop
|
20
|
A7
|
Park
Lane Shopper's Boulevard
|
Shop
|
30
|
A8
|
Park
Lane Shopper's Boulevard
|
Shop
|
25
|
A9
|
Park
Lane Shopper's Boulevard
|
Shop
|
30
|
A10
|
Park
Lane Shopper's Boulevard
|
Shop
|
55
|
A11
|
Cheong Hing
Building
|
Residential and commercial
|
35
|
A12
|
Manson House
|
Service Apartment
|
25
|
A13
|
Majestic House
|
Residential and commercial
|
30
|
A14
|
Comfort Building
|
Residential and commercial
|
10
|
A15
|
Burlington Arcade
|
Residential and commercial
|
35
|
A16
|
Milton Mansion
|
Commercial
|
20
|
A17
|
Hotel Miramar
|
Hotel and Shop
|
10
|
A18
|
Miramar Shopping Centre
|
Commercial and Shop
|
5
|
A19
|
Antiquities & Monuments Office Antiquities
Advisory Board Secretariat
|
G/IC
|
60
|
Note: (*) G/IC: Government, institution or community
use. The permitted uses of the
premise A16 are both residential and commercial
3.4.3
As the construction activities
are to be undertaken at and
below ground level, the worst dust impact on the ASRs
will be at the ground floor of the ASRs.
The height of 1.5m
above ground, which is the breathing level of human, was adopted for the
construction dust impact assessment.
In addition, 5m and 10m above local ground level were also
selected to show the vertical variation of the pollutant concentrations.
3.5.1
The plant basement and modification
works at the existing entrance A1, connection chamber, satellite concourse, two
subways and emergency exit are to be constructed at
five works areas. The
construction period for the TNS Project is tentatively scheduled from June 2009
to early 2012. According to the
construction programme, the major dusty construction activities at the five works areas will
not be overlapped. However, the
construction works at different areas are assumed to be undertaken simultaneously in the
assessment as the worst case scenario.
3.5.2
Cut-and-cover method would be
adopted for the construction of the plant basement, connection chamber,
satellite concourse and emergency exit.
Construction would be conducted initially above ground for installation
of traffic deck. Once the decking
is completed, majority of the construction activities would be underground
below the deck. Aboveground
construction works including excavation, material handling, loading and
unloading of fill materials may pose potential dust impacts to ASRs in the
vicinity of the site area of the proposed Project.
3.5.3
For the construction of the
subways connecting the new entrances and concourses, tunneling by mining method
would be considered. With the works
conducted underground, no dust impact is expected.
3.5.4
Based on the tentative
construction programme, the proposed Project will be carried out concurrently
with the Tung Ying Building
Redevelopment adjacent to TNS Project Site, which is under construction. However, it is expected that the
foundation and infrastructure works of the Tung Ying
Building Redevelopment will be complete at the time of the commencement of this
Project i.e. June 2009 Cumulative
environmental impacts from the Tung Ying
Building Redevelopment are thus envisaged to be insignificant.
3.6.1
The principal source of air
pollution during the construction phase will be dust from the dusty activities
as mentioned in Section 3.5.2. The impact of fugitive dust sources on
air quality depends upon the quantity as well as the drift potential of the
dust particles emitted into the atmosphere. Large dust particles (i.e. over 100 mm in diameter) will settle out near the source and particles that
are between 30 and 100 mm in diameter are likely to undergo
impeded settling. The main dust
impacts are likely to arise from particles less than 30 mm in diameter, which have a greater potential to disperse over
greater distances.
3.6.2
According to the USEPA AP-42,
construction dust particles may be grouped into nine particle size
classes. Their size ranges are 0 - 1 mm, 1 - 2 mm, 2 - 2.5 mm, 2.5 - 3 mm, 3 - 4 mm, 4 - 5 mm, 5 - 6 mm, 6 - 10 mm and 10 - 30 mm, and the percentage of particles in each class was estimated to be
4%, 7%, 4%, 3%, 7%, 5%, 4%, 17% and 49%, respectively.
3.6.3
The emission rates adopted in
the TNS project assessment for different construction activities are based on
the USEPA Compilation of Air Pollutant Emission Factors (AP-42), 5th
edition. The four major
construction sources including:
·
Plant Basement;
·
TST Connection Chamber;
·
Satellite Concourse; and
·
Emergency Stair at MSC.
3.6.4
Table 3.4 gives the relevant clauses for emission factors used in this
assessment in AP-42. Detailed
calculation of emission rate is presented in Appendix 3.1.
Table 3.4 Emission Factors for Construction
Activities
Emission Sources
|
Construction
Activities
|
Emission
Rate [2,3](g/m2/s)
|
Remark
[1]
|
Plant Basement
|
Heavy Construction Activities
|
E = 7.394E-05
|
- 47.5%
work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
TST Connection Chamber
|
Heavy Construction Activities
|
E = 2.179E-05
|
- 14.0% work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
Satellite Concourse
|
Heavy Construction Activities
|
E = 4.76354E-05
|
- 30.6% work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
Emergency Stair at MSC
|
Heavy Construction Activities
|
E = 6.6005E-05
|
- 42.4% work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
All Emission Sources
|
Wind Erosion
|
E = 2.6953E-06
|
- USEPA AP-42 5th ED., S.11.9, Table 11.9.4
|
Note:
-
[1] The percentage area under active operation has
reconfirmed with Engineer. The
percentage active area is estimated based on the actual construction programme
and the availability of plant equipment
-
[2] Only unit conversion has been conducted in the
emission factors in accordance with AP-42.
-
[3] Assume 30 working days per month and 8 working hours
per day.
3.6.5
The Air Pollution Control
(Construction Dust) Regulation specifies that dust suppression measures such as
watering shall be applied for the construction site. Dust emission from the site will be
reduced by 50% if watering with complete coverage of active construction area
twice a day. This assumption was
considered in the construction dust impact assessment.
3.6.6
Fugitive Dust Model (FDM) (1993
version) was used to assess potential dust impact from the construction
works. The worst case meteorological
data was used to predict the 1-hour and 24-hour average TSP concentrations at
representative discrete ASRs close to the construction works. As mentioned in Section 3.4.3,
assessment level at 1.5m,
5m and 10m are included in the assessment.
3.6.7
The meteorological data used in
the model are:
·
Wind
speed: 1 m/s
·
Wind
direction: 360
wind direction
·
Stability
class: D (daytime) & F (night time)
·
Surface
roughness: 1m
·
Mixing
height: 500 m
3.7.1
Daily TSP concentrations were
calculated as follows:
Daily TSP concentration =
(working hour)/24 ´ (1-hour average maximum TSP concentration during working hours) +
(non-working hour)/24 ´ (1-hour average maximum TSP concentration during non-working hours)
+ Background.
3.7.2
As mentioned in Section 3.3.2, the background TSP of 78 mg/m3 was adopted as an indication of the future TSP
background concentration.
3.8
Evaluation of Impacts
3.8.1
The predicted maximum 1-hour
and 24-hour average TSP during construction are shown in Tables 3.5 and
3.6, respectively.
Table 3.5
Predicted Maximum 1-hour Average TSP Concentrations
ASR
|
1.5m above ground
|
5m above ground
|
10m above ground
|
A1
|
186
|
147
|
95
|
A2
|
350
|
161
|
90
|
A3
|
203
|
152
|
93
|
A4
|
484
|
118
|
89
|
A5
|
247
|
160
|
93
|
A6
|
145
|
129
|
99
|
A7
|
182
|
137
|
94
|
A8
|
202
|
125
|
89
|
A9
|
108
|
105
|
96
|
A10
|
99
|
97
|
92
|
A11
|
206
|
153
|
93
|
A12
|
268
|
160
|
89
|
A13
|
224
|
156
|
91
|
A14
|
149
|
131
|
98
|
A15
|
163
|
136
|
97
|
A16
|
260
|
154
|
94
|
A17
|
365
|
158
|
94
|
A18
|
168
|
112
|
100
|
A19
|
103
|
100
|
93
|
Notes: (1) Background concentration is
included.
(2) 1-hour TSP criterion of 500mg/m3 is stipulated in the EIAO-TM.
Table 3.6 Predicted
Maximum 24-hour Average TSP Concentrations
ASR
|
1.5m above ground
|
5m above ground
|
10m above ground
|
A1
|
120
|
102
|
84
|
A2
|
179
|
107
|
82
|
A3
|
126
|
104
|
83
|
A4
|
223
|
92
|
82
|
A5
|
142
|
107
|
83
|
A6
|
105
|
97
|
85
|
A7
|
120
|
99
|
84
|
A8
|
126
|
94
|
82
|
A9
|
91
|
89
|
84
|
A10
|
87
|
86
|
83
|
A11
|
127
|
104
|
83
|
A12
|
150
|
107
|
82
|
A13
|
134
|
106
|
83
|
A14
|
106
|
98
|
85
|
A15
|
115
|
99
|
84
|
A16
|
153
|
105
|
84
|
A17
|
191
|
106
|
84
|
A18
|
112
|
92
|
86
|
A19
|
89
|
87
|
84
|
Notes: (1) Background concentration is
included.
(2) 24-hour TSP criterion of
260mg/m3 is stipulated in the EIAO-TM.
3.8.2
Based on the above prediction,
no exceedance of 1-hour and 24-hour average TSP objective will occur at any
representative ASR in the Study Area.
From the results, it is found that the maximum 1-hour and 24-hour
average TSP concentrations will occur at 1.5m above ground (484mg/m3
and 223mg/m3,
respectively). Contours of the maximum predicted 1-hour and 24-hour average TSP
concentrations at 1.5m above
ground are shown in Figures 3.2 and 3.3 respectively.
3.9.1
As mentioned in Section 3.5.4, it is expected that
the foundation and infrastructure works of the Tung Ying
Building Redevelopment would be completed at the time of the commencement of
this Project. Another new commercial development (iSquare) is found at 63 Nathan Road
(ex-Hyatt Regency Hong Kong Hotel at the
junction of Peking Road
and Nathan Road)
which is about 95m to the south of the new plant basement works area of the
Project. The commercial development
is scheduled to open in 2009 and all infrastructure construction works are
expected to be completed by July 2009 when this Project start. Thus, cumulative environmental impacts
would not be expected.
3.10.1
To ensure compliance with the
relevant standards, dust mitigation measures stipulated in the Air Pollution
Control (Construction Dust) Regulation and good site practices shall be
incorporated in the contract document to control potential dust emission from
the site. The major dust
suppression measures include:
watering of active construction works area twice a
day.
skip hoist for material
transport shall be totally enclosed by impervious sheeting.
every vehicle shall be
washed to remove any dusty materials from its body and wheels before leaving a
construction site.
the area where vehicle
washing takes place and the section of the road between the washing facilities
and the exit point shall be paved with concrete, bituminous materials or
hardcores.
where a site boundary
adjoins a road, streets or other accessible to the public, hoarding of not less
than 2.4m high
from ground level shall be provided along the entire length except for a site
entrance or exit.
every stack of more than 20
bags of cement shall be covered entirely by impervious sheeting places in an
area sheltered on the top and the 3 sides.
all dusty materials shall
be sprayed with water prior to any loading, unloading or transfer operation so
as to maintain the dusty materials wet.
the height from which
excavated materials are dropped shall be controlled to a minimum practical
height to limit fugitive dust generation from unloading.
stockpile of excavated or
dusty materials shall be covered entirely by clean impervious sheeting.
the load of dusty materials
carried by vehicle leaving a construction site shall be covered entirely by
clean impervious sheeting to ensure dust materials do not leak from the
vehicle.
instigation of an
environmental monitoring and auditing program to monitor the construction
process in order to enforce controls and modify method of work if dusty
conditions arise.
3.11
Evaluation of Residual Impacts
3.11.1
With the implementation of dust
suppression measures stipulated in Air Pollution control (Construction Dust)
Regulation and
watering of active construction works area twice a day during
construction, no exceedance of AQO within the Study Area is predicted. Therefore, no adverse residual dust
impact is expected.
3.12.1
With the implementation of the
proposed dust suppression measures, good site practices and dust monitoring and
audit programme, acceptable dust impact are expected at the ASRs. Details of the monitoring requirements
such as monitoring locations, frequency of baseline and impact monitoring are
presented in the stand-alone EM&A Manual.
4.
NOISE IMPACT
4.1.1
This section presents the
potential noise impacts arising from the proposed Project during construction
and operation phases. It is
expected that construction and operation noise impact will arise from the
proposed Project. Potential construction and operation noise impacts are
evaluated in this study.
General
4.2.1
Noise impacts generated by the
construction of this Project have been assessed in accordance with the criteria
and methodology given in the Technical Memoranda (TMs) under the Noise Control
Ordinance (NCO), and the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
4.2.2
The NCO and EIAO provide the
statutory framework for noise control.
Applicable assessment procedures and standards are set out in three TMs
listed below:
·
EIAO-TM
·
TM
on Noise from Construction Work other than Percussive Piling (GW-TM)
·
TM
on Noise from Construction Work in Designated Areas (DA-TM)
·
TM
on Noise from Places other than Domestic Premises, Public Places or
Construction Sites (IND-TM)
4.3.1
The NCO provides the statutory
framework for noise control of construction work, other than percussive piling,
using powered mechanical equipment (PME) between the hours of 1900 and 0700
hours or at any time on Sundays and general holiday (that is, restricted
hours). Noise control on
construction activities taking place at other times is subject to the Criteria
for Evaluating Noise Impact stated
in Table 1B of Annex 5 in the
EIAO-TM. The noise limit is Leq
(30 minutes) 75 dB(A) at the façades of dwellings and 70 dB(A) at the
façade of schools (65 dB(A) during examinations). The EIAO-TM construction noise criteria
are summarised in Table 4.1.
4.3.2
Table 4.1 Daytime Construction Noise Criteria
|
Noise Level in Leq(30-minutes), dB(A)
|
Domestic premises
|
75
|
Educational Institution
|
70
|
|
65
|
Note: The above standards apply to uses which rely on opened windows for
ventilation
4.3.3
Between 1900 and 0700 hours and
all day on Sundays and public holidays, activities involving the use of PME for
the purpose of carrying out construction work is prohibited unless a
construction noise permit (CNP) has been obtained. A CNP may be granted provided that the
Acceptable Noise Level (ANL) for the noise sensitive receivers can be complied
with. ANLs are assigned depending
upon the area sensitive rating (ASR).
The corresponding ANLs for evening and night time periods are given in Table
4.2.
Table 4.2 Acceptable
Noise Levels
|
Acceptable Noise Level in Leq(5-minutes), dB(A)
|
|
ASR B
|
ASR C
|
Evening (1900 to 2300 hours)
(1)
|
60
|
65
|
70
|
|
45
|
50
|
55
|
Note: (1) Includes Sundays and Public Holidays during daytime
and evening
4.3.4
Despite any description or
assessment made in this EIA Report on construction noise aspects, there is no
guarantee that a Construction Noise Permit (CNP) will be issued for the project
construction. The Noise Control
Authority will consider a well-justified CNP application, once filed, for
construction works within restricted hours as guided by the relevant Technical
Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take
into account of contemporary conditions / situations of adjoining land uses and
any previous complaints against construction activities at the site before
making his decision in granting a CNP.
Nothing in this EIA Report shall bind the Noise Control Authority in
making his decision. Failure to
comply with any such conditions will lead to cancellation of the CNP and
prosecution action under the NCO.
4.3.5
Under the DA-TM, the use of
five types of Specified Powered Mechanical Equipment (SPME) and three types of
Prescribed Construction Work (PCW) within a designated area during restricted
hours would require a valid CNP.
The SPME includes hand-held breaker, bulldozer, concrete lorry mixer,
dump truck and hand-held vibratory poker.
The PCW are:
·
erecting
or dismantling of formwork or scaffolding
·
loading,
unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding
material
·
hammering
4.3.6
As defined in the Noise Control
Designated Area Plan, all the works areas of the proposed Project are within
the Designated Area.
4.3.7
In general, it should not be
presumed that a CNP will be granted for carrying out PCW within a designated
area during the restricted hours.
The CNP may be granted for the execution of construction works during restricted
hours involving the use of PME and/or SPME if the relevant Acceptable Noise
Levels and criteria stipulated in the GW-TM and DA-TM can be met.
4.3.8
According to the construction
programme, most of the proposed construction works will be carried out during
non-restricted hours, except for underground tunneling work and some
construction activities in order to avoid local traffic impact. In case of any construction activities
during restricted hours, it is the Contractor’s responsibility to ensure compliance
with the NCO and the relevant TMs.
The Contractor will be required to submit CNP application to the Noise
Control Authority and abide by any conditions stated in the CNP, should one be
issued.
4.4.1
The major fixed plant
noise sources identified are ventilation shafts of the proposed Project which
would generate potential noise impact during operation. Fixed noise source such
as ventilation noise is controlled by the NCO and IND-TM. The appropriate Acceptable Noise Levels (ANL)
generated by fixed plant at neighbouring NSRs are provided in the IND-TM. The representative NSRs in the vicinity
of ventilation shafts are located in urban area and are fronting the busy
Nathan Road with an annual average daily traffic flow in excess of 30,000 in that road section
according to Annual Traffic Census 2006 published by Transport Department. Most of the NSRs will be directly
affected by traffic noise. In this connection, the Area Sensitivity Rating
(ASR) for these NSRs has been assumed as ‘C’. The ANLs for an ASR of ‘C’ under the IND-TM
are shown in
Table 4.3. The EIAO-TM recommends
that noise standard for fixed noise source are (a) 5 dB(A) below the
appropriate ANL, or (b) the prevailing background noise levels (For quiet areas
with level 5 dB(A) below the ANL). The existing background noise level
dominated by busy traffic along Nathan Road and community noise is expected to
be higher than ANL – 5dB(A), therefore, the noise criteria of ANL – 5dB(A) i.e.
65/55 dB(A) (daytime and night-time) have been adopted for the assessment.
Table 4.3 Acceptable
Noise Level for Fixed Plant Noise
Time Period
|
NCO criteria
Leq (30-min),
dB(A)
|
EIAO-TM
Leq (30-min),
dB(A)
|
ASR ‘C’
|
ASR ‘C’
|
Daytime
and Evening (0700-2300 hours)
|
70
|
65
|
Night-time
(2300-0700 hours)
|
60
|
55
|
4.4.2
In any event, the Area
Sensitivity Rating assumed in this EIA Report is for indicative
assessment. It should be noted that
the fixed noise sources are controlled under section 13 of the NCO. At the time of investigation, the Noise
Control Authority shall determine noise impact from concerned fixed noise
sources on the basis of prevailing legislation and practices being in force,
and taking account of contemporary conditions/situations of adjoining land
uses. Nothing in this EIA Report shall bind the Noise Control Authority in the
context of law enforcement against all the fixed noise sources being assessed.
4.5.1
In order to evaluate the
construction and operation noise impacts from the proposed Project,
representative existing noise sensitive receivers (NSRs) within the Study Area
are identified for assessment. Only
the first layer of NSRs has been identified for assessment because it provides
acoustic shielding to those receivers at further distance behind. As the centrally air-conditioned
buildings do not rely on opened windows for ventilation, the noise standard as
stipulated in Tables 1A and 1B of
Annex 5 of EIAO-TM would not be applicable, and hence these buildings have not
been identified for noise impact assessment. Table 4.4 shows the
representative NSRs for this noise impact assessment.
Table 4.4 Summary of
Representative Noise Sensitive Receivers
NSR
ID
|
Location
|
Permitted
Land Use
|
Number
of floors
|
Horizontal
Separation from Closest Works Area Boundary (m)
|
N1
|
Hai Phong Mansion (53-55 Haiphong Road)
|
Residential and commercial
|
15 domestic floors above 3 commercial use floors
|
17
|
N2
|
Majestic House (80 Nathan Road)
|
Residential and commercial
|
13 domestic floors above 3 commercial use floors
|
30
|
N3
|
Comfort Building (86-88 Nathan Road)
|
Residential and commercial
|
11 domestic floors above 3 commercial use floors
|
9
|
N4
|
Burlington Arcade (90-94C
Nathan Road)
|
Residential and commercial
|
14 domestic floors above 2 commercial use floors
|
29
|
*N5
|
Milton Mansion (96 Nathan Road)
|
Residential and commercial
|
12 floors
|
19
|
N6
|
Pacific Mansion (172-174 Nathan Road)
|
Residential and commercial
|
10 domestic floors above 4 commercial use floors
|
165
|
N7
|
Kowloon Mosque and Islamic
Centre (105 Nathan Road)
|
Religionary
|
3
|
24 (East façade N7a),
7 (South façade N7b)
|
Remark: (*) Refer to Section 4.5.2
for the nature of this NSR
4.5.2
According to the occupation
permit of Milton Mansion (N5) issued by Building Department, the allowed uses
are both commercial and residential.
Although it is identified as commercial use during the site survey, it
is selected as a representative sensitive receiver in the assessment to study
the impact level at this NSR should residential use be happened during the
construction period of the Project.
4.5.3
Two construction sites within
the study area are found along Nathan
Road i.e. 63 Nathan Road (iSquare) and 98 Nathan Road
(Tung Ying Building Redevelopment).
Both are commercial use. The
construction of the Urban Redevelopment Authority (URA) development at Mody Road (hotel
and service apartment use) is almost complete. According to the latest Outline Zoning
Plan, most of the land uses within the study area are commercial use with a few
G/IC, Open Space, Other Specified Uses and a few residential uses along Austin Road. No
planned/committed noise sensitive receiver is identified within the study area
during a site visit conducted on 9-Oct-2007.
4.5.4
In the absence of the programme
of planned/committed noise sensitive developments, construction and fixed noise
impact assessment will only focus on existing NSRs. The representative NSRs selected for
assessments of construction noise and fixed noise have been shown in Figure
4.1. The photographs of the
representative NSRs are shown in Appendix 4.1. Prior agreement with Environmental
Protection Department has been sought on the selected representative assessment
points for quantitative noise assessment.
Construction Noise
4.6.1
The
Project is scheduled to commence in June 2009 and to be completed in 2012. According to the
construction programme, there are seven major construction tasks. Some
individual tasks have different stages.
Table 4.5 summarises the different tasks and the construction
periods. Most of the construction
tasks are planned to be carried out during unrestricted hours. In case of any construction activities
during restricted hours, it is the Contractor’s responsibility to ensure
compliance with the NCO and the relevant TMs. The Contractor will be required to
submit CNP application to the Noise Control Authority and abide by any
conditions stated in the CNP, should one be issued.
Table 4.5 Construction
Tasks Involved
Tasks
|
Description
|
*Construction Period
|
1
|
Plant Building
|
July 2009 to December
2010
|
2
|
Entrance A1
|
November 2010 to November
2011
|
3
|
TST Connection Chamber
|
July 2009 to March 2010
|
4
|
Satellite Concourse
|
November 2009 to January
2012
|
5
|
Subway to TST Station
|
March 2011 to December
2011
|
6
|
Subway to Miramar
Shopping Centre
|
February 2011 to December
2011
|
7
|
Emergency Stair at Miramar Shopping Centre
|
July to August 2009 and
November 2011 to February 2012
|
Note: (*)
Construction period involving use of powered mechanical
equipment only.
4.6.2
The construction noise
assessment has been carried out on a weekly basis from the commencement of the
Project. The construction tasks of
the Project taking place concurrently within 300m of a given NSR are considered to contribute to
the cumulative impact at that NSR.
Noise sources from the areas greater than this distance have been
excluded from the assessment.
4.6.3
In accordance with the EIAO,
the methodology outlined in the GW-TM has been used for the assessment of construction
noise (excluding percussive piling) and reference has been to the EIAO Guidance
Note No.9/2004 on preparing the assessment.
Sound Power Levels (SWLs) of the equipment were taken from Table 3 of this
TM. Where no SWL was supplied in
the GW-TM, reference was made to BS 5228, previous similar studies or from
measurements taken at other sites in Hong Kong.
4.6.4
Schedule of powered mechanical
equipment (PME) for the different construction tasks during normal daytime working
hours is presented in Appendix 4.2.
The proposed plant inventory and utilization rate adopted in the
assessment are considered practical and adequate in achieving the construction
programme. The plant inventory has
been provided as an option and the contractor may propose alternative plant
schedule should it be considered necessary and appropriate.
4.6.5
The assessment is based on the
cumulative SWL of PME likely to be used for each location, taking into account
the construction period in the vicinity of the receiver location. To predict the noise level, PME was
divided into groups required for each discrete construction task. The objective was to identify the worst
case scenario representing those items of PME that would be in use concurrently
at any given time. The sound
pressure level of each construction task was calculated, depending on the
number of plant and distance from receivers. The noise levels at NSRs were then
predicted by adding up the SWLs of all concurrent construction tasks.
4.6.6
Much of the excavation areas
will be decked and this will shield the noise from construction plant operating
below the deck. For example, the
rock drill used for excavation has noise emission but would be totally enclosed
as it will be operated underground below the deck. Considerations will also be
given to the location and the orientation of the temporary fixed noise sources
required for the ventilation of the works area underneath the decked area. If
exhaust above ground is required, it shall be located away from the existing
residential building and facing towards the Kowloon Park
(transient use). If required, silencer will be provided. It is anticipated that
a metal sheet cover with surface density of 10kg/m2 or more covering the excavation
areas would result in at least 20 dB(A) noise reduction. Therefore, a noise reduction of 20 dB(A)
was applied for the activities carried out underground. Schematic diagrams
showing the typical site arrangement of underground works are shown in Figures
4.2 and 4.3.
4.6.7
A positive 3 dB(A) façade
correction was added to the predicted noise levels in order to account for the
facade effect at each NSR.
Fixed Noise in Operation Phase
4.6.8
In the proposed Project two
ventilation shafts, one for exhaust extraction and one for smoke extraction,
would be integrated with the Tung Ying
Building Redevelopment and Hotel Miramar.
4.6.9
Potential noise impacts arising
from the operation of ventilation fans is expected at the sensitive receivers,
and this fixed plant noise impact has been assessed in accordance with the
IND-TM.
4.6.10
Table 4.6 summarises the ventilation shafts would be constructed for the
proposed Project.
Table 4.6 Ventilation
Shafts for the proposed Project
Location
|
Use
|
Tung Ying Building
|
*Exhaust/ Smoke extraction
|
Hotel Miramar
|
*Exhaust/ Smoke extraction
|
Note: (*) The use is either for exhaust or smoke extraction which is still not
finalised in the design.
4.6.11
The ventilation fans for the
smoke extraction and exhaust are all located underground inside the mezzanine
level of the satellite concourse.
4.6.12
The ventilation fans of the
smoke extraction shaft are operated for emergency only, however routine test of
those ventilation fans would be carried out during day time. The potential
impact from the concurrent operation of this shaft during day time period is
assessed in the study.
4.6.13
The assessment assumes that all
duty ventilation fans are operated for each ventilation shaft. Screening corrections from other
buildings / structures and directivity have also been excluded in the assessment. All ventilation fans provided for each
ventilation shaft will be installed with silencers.
4.6.14
In the absence of any detailed
information and noise specification of the proposed fixed plant, the maximum
permissible noise emission levels were determined for future detailed design of
the fixed plant.
4.6.15
For the assessment of noise
from the fixed plant, the maximum permissible sound power levels (Max SWLs) of
the identified fixed noise sources were determined by adopting standard
acoustics principles. The following
formula was used for calculating the Max SWLs of the fixed plant.
SPL = Max SWL – DC + FC
where
·
Sound
Pressure Level, SPL in dB(A)
·
Maximum
Permissible Sound Power Level, Max SWL in dB(A)
·
Distance
Attenuation, DC in dB(A) = 20 log D + 8 [where D is the distance in metres]
·
Façade
Correction, FC in dB(A) = 3 dB(A)
4.6.16
A positive 3 dB(A) was added to
predicted noise levels at the NSRs due to the façade effect.
4.6.17
No corrections have been
applied for tonality, intermittency or impulsiveness. If the noise exhibits any of these
characteristics during the operation of the plant, the noise limit should be
reduced in accordance with the recommendation given in Section 3.3 of IND-TM.
Construction Phase
4.7.1
The scope of this Project includes
modification to the existing Entrance A1 and construction of the plant basement
below; construction of a satellite concourse with integrated entrances to Tung Ying Building
and Hotel Miramar; construction of subways connecting TST station and Miramar
Shopping Centre with an integrated entrance and an emergency exit at Miramar
Shopping Centre. Potential construction impacts of the Project may arise from
the following activities:
·
Demolition
of existing structure of Entrance A1 and construction of the plant basement
below
·
Excavation
at Entrance A1
·
Excavation
at the existing Nathan Road
southbound carriageway and footpath for satellite concourse, connection chamber
and emergency exit
·
Construction
of two subways by mined excavation
·
Road
and pavement reinstatement and earthworks
4.7.2
Driven piling and blast method
would not be adopted for the construction works. The subway would be built
using tunneling by mining method and no tunnel boring machine would be used.
4.7.3
The Tung Ying
Building Redevelopment located nearby the proposed works area of this Project
would be carried out concurrently.
It is expected that the foundation and infrastructure works of the Tung Ying Building Redevelopment will be completed at the
time of the commencement of this Project in June 2009. Consequently, cumulative environmental
impacts contributed from the Tung Ying
Building Redevelopment are envisaged to be insignificant.
4.7.4
Another new commercial
development (iSquare) is found at 63
Nathan Road (ex-Hyatt Regency Hong
Kong Hotel at the junction of Peking Road and Nathan Road) which is about 95m to the south of the new plant basement
works area of the Project. The
commercial development is scheduled to open in 2009 and all infrastructure
construction works are expected to be completed by July 2009 when this Project
start. Hence cumulative
environmental impacts generated from this commercial development are not
anticipated.
Operation Phase
4.7.5
Ventilation noise affecting
sensitive receivers in the study area may arise from the proposed ventilation
shafts under the Project.
Construction Phase
4.8.1
For normal daytime working
hours, exceedences of the construction noise criteria i.e. Leq (30 minutes)
75 dB(A) for residential uses are predicted at representative NSRs in the
absence of mitigation measures.
4.8.2
Details of construction noise
calculations and results are presented in Appendix 4.3. A summary of the unmitigated
construction noise levels of the representative NSRs during normal daytime
working hours within the construction period of the Project is listed in Table
4.7.
Table 4.7 Summary of Unmitigated Construction
Noise Levels at Representative NSRs During Normal
Daytime Working Hours
NSR
ID
|
Predicted
Noise Levels, dB(A)
|
Daytime
Construction Noise Criteria, dB(A)
|
N1
|
56 – 87
|
75
|
N2
|
57 – 81
|
75
|
N3
|
60 - 89
|
75
|
N4
|
62 – 83
|
75
|
*N5
|
62 – 85
|
*75
|
N6
|
46 – 66
|
75
|
N7a
|
55 – 83
|
75
|
N7b
|
46 – 85
|
75
|
Note: (*)
Noise criteria would be applied only if residential use exist in NSR N5 during the period of construction.
4.8.3