TABLE OF
CONTENTS
12 Impact
on Cultural heritage
12.2 Environmental
Legislation, Standards and Guidelines
12.3 Assessment Scope and Methodology
12.5 Built
Heritage Impact Assessment
12.6 Archaeological
Impact Assessment
List of tables
Table 12.1......... Built Heritage and Other Identified Items within the Assessment Area
LIST OF FIGURES
Figure
12.1 Project
Site Boundary and Assessment Area for Cultural Heritage Impact Assessment
Figure
12.2 Geological
Map of Assessment Area
Figure
12.3 1963
Aerial Photo
Figure
12.4 1982
Aerial Photo
Figure
12.5 Previous
Archaeological Works Conducted within Assessment Area (Key Plan)
Figure
12.5.1
Previous Archaeological Works Conducted within Assessment Area (Sheet 1
of 4)
Figure
12.5.2
Previous Archaeological Works Conducted within Assessment Area (Sheet 2
of 4)
Figure
12.5.3
Previous Archaeological Works Conducted within Assessment Area (Sheet 3
of 4)
Figure
12.5.4
Previous Archaeological Works Conducted within Assessment Area (Sheet 4
of 4)
Figure
12.6.1 Assessed
Archaeological Potential Area Prior to This Study (1)
Figure
12.6.2 Assessed
Archaeological Potential Area Prior to This Study (2)
Figure
12.6.3 Assessed
Archaeological Potential Area Prior to This Study (3)
Figure
12.6.4 Assessed
Archaeological Potential Area Prior to This Study (4)
Figure
12.7 Locations
of Built Heritage and Other Identified Items (Key Plan)
Figure
12.7.1 Locations of
Built Heritage and Other Identified Items
(Sheet 1 of 12)
Figure
12.7.2 Locations of
Built Heritage and Other Identified Items
(Sheet 2 of 12)
Figure
12.7.3 Locations of
Built Heritage and Other Identified Items
(Sheet 3 of 12)
Figure
12.7.4 Locations of
Built Heritage and Other Identified Items
(Sheet 4 of 12)
Figure
12.7.5 Locations of
Built Heritage and Other Identified Items
(Sheet 5 of 12)
Figure
12.7.6 Locations of
Built Heritage and Other Identified Items
(Sheet 6 of 12)
Figure
12.7.7 Locations of
Built Heritage and Other Identified Items
(Sheet 7 of 12)
Figure
12.7.8 Locations of
Built Heritage and Other Identified Items
(Sheet 8 of 12)
Figure
12.7.9 Locations of
Built Heritage and Other Identified Items
(Sheet 9 of 12)
Figure
12.7.10 Locations of Built
Heritage and Other Identified Items
(Sheet 10 of 12)
Figure
12.7.11 Locations of Built
Heritage and Other Identified Items
(Sheet 11 of 12)
Figure
12.7.12 Locations of Built
Heritage and Other Identified Items
(Sheet 12 of 12)
Figure
12.8 Locations
of Other Identified Items in Relations to RODP
Figure
12.9 Further
Review of Past Disturbance that Affect Archaeological Potential Assessment
Figure
12.10 Overall
Evaluated Archaeological Potential of Assessment Area
Figure
12.11 Mitigation
Measures for Archaeological Heritage
Figure
12.12 Geology
Map Overlay with Moderate-Low and High Archaeological Potential Areas within
Project Site Requiring Mitigation Measures
LIST OF APPENDICES
|
Built Heritage and
Other Identified Items Recording Sheets |
|
|
Notable Visual
References |
|
|
Site Visit Photos |
Related
to EIA Study
· Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499);
· Annexes
10 and 19 of EIAO-TM; and
Others
· Antiquities
and Monuments Ordinance (A&MO) (Cap. 53).
·
List of declared and proposed monuments[1];
·
List of graded historic buildings[2];
·
List of new items for grading assessment[3];
·
Government historic sites identified by AMO[4];
·
Previous related EIA studies, publications and
monographs on relevant historical and geographical issues;
·
Unpublished
archival papers and records, and collection and
libraries of tertiary institutions; and
·
Geological and historical maps, aerial photos and
relevant visual archives.
·
List of proposed and declared monuments[5];
·
List of Sites of Archaeological Interest[6] identified by the AMO;
·
Previous related EIA studies and archaeological reports;
·
Related publications and monographs on relevant
archaeological, historical and geographical issues;
·
Unpublished archival papers and records, and
collection and libraries of tertiary institutions; and
·
Geological and historical maps, aerial photos and
relevant visual archives.
i.
declared monuments under A&MO: the concerned place, building, site or structure which is declared to
be a monument, historical building or archaeological or palaeontological site
or structure under section 3 of the A&MO (Cap. 53); and included in the
latest list of Declared Monuments in Hong Kong.
ii.
proposed monuments under A&MO: the concerned place, building, site or structure which is declared to
be a proposed monument, proposed historical building, or proposed
archaeological or palaeontological site or structure under section 2A of the
A&MO (Cap. 53).
iii.
grade 1 historic buildings assessed by the Antiquities Advisory Board (AAB): as defined by the AAB, they are
buildings of outstanding merit, which every effort should be made to preserve
if possible.
iv.
grade 2 historic buildings assessed by the AAB: as defined by the AAB, they are buildings of special merit; efforts
should be made to selectively preserve.
v.
grade 3 historic buildings assessed by the AAB: as defined by the AAB, they are buildings of some merit; preservation
in some form would be desirable and alternative means should be considered if
preservation is not practicable.
vi.
new items pending for grading assessment by the
AAB: currently under the latest list of new items for grading
assessment with grading results pending for grading assessment by the AAB,
and yet to be grading accorded.
vii.
government historic site identified by the AMO: under the list of government historic site maintained by the AMO.
Table 12.1 Built
Heritage and Other Identified Items within the Assessment Area
|
Name |
Status |
Approx.
Distance to Project Site |
Details and
Photographic Record |
Relevant
Figure No. |
|
|
Yau Tam Mei Tsuen |
|||||
|
HB1219 |
Wai Cheung Ancestral Hall |
AAB discussed in 2010 and confirmed as no grading |
Within Project Site |
Appendix 12.1, Built Heritage and Other Identified Items
Recording Sheet YTMT (Yau Tam Mei Tsuen) |
12.7.4 |
|
YTMT01 |
DD104 Lot 4186 S.E (Residence) |
No Status |
Within Project Site |
12.7.9 |
|
|
YTMT02 |
DD104 Lot 4187 S.B (Watchtower) |
No Status |
Within Project Site |
12.7.9 |
|
|
YTMT03 |
Remnants of Nam Shan Monastery |
No Status |
Within Project Site |
12.7.9 |
|
|
YTMT04 |
Subsidiary Station of San Yau Vegetable
Marketing Co-operative Society, Ltd. |
No Status |
Within Project Site |
12.7.10 |
|
|
YTMT05 |
San Yau Vegetable Marketing Co-operative
Society, Ltd. |
No Status |
6 m |
12.7.5 |
|
|
YTMT06 |
Former Yau Tam Mei Primary School |
No Status |
Within Project Site |
12.7.10 |
|
|
YTMT07 |
Lee’s Boundary Stone |
No Status |
Within Project Site |
12.7.9 |
|
|
Wai Tsai Tsuen |
|||||
|
DD104 Lot 2729 (Residence) |
No Status |
25 m |
Appendix 12.1, Built Heritage and Other
Identified Items Recording Sheet WTT (Wai Tsai Tsuen) |
12.7.1 & 12.7.2 |
|
|
WTT02 |
Nos. 9-11, Wai Tsai Tsuen |
No Status |
82 m |
12.7.2 |
|
|
WTT03 |
Nos. 13-15, Wai Tsai Tsuen |
No Status |
93 m |
12.7.2 |
|
|
WTT04 |
No. 44, Wai Tsai Tsuen |
No Status |
99 m |
12.7.2 |
|
|
No. 47, Wai Tsai Tsuen |
No Status |
107 m |
12.7.2 |
||
|
WTT06 |
No. 51, Wai Tsai Tsuen |
No Status |
107 m |
12.7.2 |
|
|
WTT07 |
No. 54, Wai Tsai Tsuen |
No Status |
111 m |
12.7.2 |
|
|
WTT08 |
Former Kai Tak School |
No Status |
97 m |
12.7.2 |
|
|
Chuk Yuen |
|||||
|
HB1383 |
Kong Ha Tong, No. 34, Sheung Chuk Yuen |
AAB discussed in 2010 and confirmed as no grading |
149 m |
Appendix 12.1, Built Heritage and Other Identified Items
Recording Sheet CY (Chuk Yuen) |
12.7.5 |
|
Kong Ha Tong, No. 35, Sheung Chuk
Yuen |
AAB discussed in 2010 and
confirmed as no grading |
152 m |
12.7.5 |
||
|
CY01 |
No. 3, Sheung Chuk Yuen |
No Status |
83 m |
12.7.5 |
|
|
No. 37, Sheung Chuk Yuen |
No Status |
168 m |
12.7.5 |
||
|
No. 35, Chuk Yuen Tsuen |
No Status |
93 m |
12.7.3 |
||
|
No. 72, Chuk Yuen Tsuen |
No Status |
128 m |
12.7.3 |
||
|
CY05 |
Nos. 74-75, Chuk Yuen Tsuen |
No Status |
136 m |
12.7.3 |
|
|
CY06 |
Temple, Chuk Yuen Tsuen |
No Status |
168 m |
12.7.3 |
|
|
CY07 |
Chuk Hing Public School |
No Status |
115 m |
12.7.3 |
|
|
San Wai |
|||||
|
No. 57, San Wai Tsuen |
Grade 2 Historic Building |
195 m |
Appendix 12.1, Built Heritage and Other
Identified Items Recording Sheet SW (San Wai) |
12.7.5 & 12.7.7 |
|
|
HB613 |
No. 50, San Wai Tsuen |
Grade 3 Historic Building |
212 m |
12.7.5 & 12.7.7 |
|
|
HB628 |
No. 51, San Wai Tsuen |
Grade 3 Historic Building |
218 m |
12.7.5 & 12.7.7 |
|
|
HB658 |
No. 35, San Wai Tsuen |
Grade 3 Historic Building |
57 m |
12.7.6 |
|
|
HB659 |
No. 36, San Wai Tsuen |
Grade 3 Historic Building |
58 m |
12.7.6 |
|
|
HB784 |
No. 71, San Wai Tsuen |
Grade 3 Historic Building |
251 m |
12.7.7 |
|
|
HB785 |
No. 87, San Wai Tsuen |
Grade 3 Historic Building |
62 m |
12.7.6 |
|
|
HB858 |
No. 70, San Wai Tsuen |
Grade 3 Historic Building |
209 m |
12.7.7 |
|
|
HB1016 |
Hon Lo, No. 61, San Wai Tsuen |
Grade 3 Historic Building |
163 m |
12.7.7 |
|
|
HB1032 |
No. 62, San Wai Tsuen |
Grade 3 Historic Building |
175 m |
12.7.7 |
|
|
SW01 |
No. 3, San Wai Tsuen |
No Status |
64 m |
12.7.6 |
|
|
SW02 |
No. 10, San Wai Tsuen |
No Status |
52 m |
12.7.6 |
|
|
SW03 |
Nos. 16-17, San Wai Tsuen |
No Status |
48 m |
12.7.6 |
|
|
SW04 |
No. 25A, San Wai Tsuen |
No Status |
20 m |
12.7.6 |
|
|
Nos. 39-40, San Wai Tsuen |
No Status |
177 m |
12.7.5 |
||
|
SW06 |
Nos. 46-47, San Wai Tsuen |
No Status |
183 m |
12.7.5 |
|
|
SW07 |
No. 54, San Wai Tsuen |
No Status |
172 m |
12.7.5 & 12.7.7 |
|
|
SW08 |
No. 59, San Wai Tsuen |
No Status |
217 m |
12.7.5 & 12.7.7 |
|
|
SW09 |
No. 67 and Sin Lo, San Wai Tsuen |
No Status |
216 m |
12.7.7 |
|
|
Long Ha |
|||||
|
Chan Ming Yam Tong |
No Status |
209 m |
Appendix 12.1, Built Heritage and Other
Identified Items Recording Sheet LH (Long Ha) |
12.7.8 |
|
|
General (NTM Area) |
|||||
|
Grave of
Mrs Man Ng |
No Status |
63 m |
Appendix 12.1, Built Heritage and Other
Identified Items Recording Sheet NB (General (NTM Area)) |
12.7.11 |
|
|
Mailbox
No. 35 |
No Status |
13 m |
12.7.6 |
||
|
Mailbox No.
169 |
No Status |
37 m |
12.7.1 |
||
|
Mailbox
No. 299 |
No Status |
Within Project Site |
12.7.3 |
||
|
NB05 |
Man’s
Boundary Stone |
No Status |
40 m |
12.7.11 |
|
|
NB06 |
Castle Peak Road Milestone |
No Status |
52 m |
12.7.3 |
|
|
NB07 |
Tam Mei Barracks |
No Status |
Immediately outside the Project Site |
12.7 |
|
|
NB08 |
Chun Chi Education Park |
No Status |
33 m |
12.7.1 |
|
|
NB09 |
Grave of Mr. Man Chiu Pak and His Wife |
No Status |
Within Project Site |
12.7.10 |
|
i. Wai Cheung Ancestral Hall (HB1219);
ii. DD104 Lot 4186 S.E (Residence) (YTMT01);
iii. DD104 Lot 4187 S.B (Watchtower) (YTMT02);
iv. Remnants of Nam Shan Monastery (YTMT03);
v. Subsidiary Station of San Yau Vegetable Marketing Co-operative Society Ltd. (YTMT04);
vi. Former Yau Tam Mei Primary School (YTMT06);
vii. Lee’s Boundary Stone (YTMT07);
viii. Mailbox No. 299 (NB04); and
ix. Grave of Mr. Man Chiu Pak and His Wife (NB09).
i. San Yau Vegetable Marketing Co-operative Society, Ltd. (YTMT05);
ii. DD104 Lot 2729 (Residence) (WTT01);
iii. Nos. 16-17, San Wai Tsuen (SW03);
iv. No. 25A, San Wai Tsuen (SW04);
v. Mailbox No. 35 (NB02);
vi. Mailbox No. 169 (NB03); and
vii. Chun Chi Education Park (NB08).
Table 12.2 Summary
of Potential Impact and the Proposed Mitigation Measures on Other Identified Items
|
Ref. No. |
Name |
Status |
Approx. Distance to Project Site |
Potential Impact |
Mitigation Measures |
|
|
Construction Phase |
Operational Phase |
|||||
|
Yau Tam Mei Tsuen |
||||||
|
HB1219 |
Wai Cheung Ancestral Hall |
AAB discussed in 2010 and
confirmed as no grading |
Within Project Site |
Potential indirect impacts of
ground-borne vibration, tilting and ground settlement and dust nuisance are
anticipated due to construction works in proximity. |
If it will be preserved in situ and would be utilised as part of its
proposed land use, direct impact would be anticipated. |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including condition
surveys both before and after all construction works and monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
A buffer zone should be reserved by the
project proponent or its contractor(s) according to the results of condition
survey in the design layout of the Project. No piling works should be allowed
within the buffer zone during the construction phase. (iii)
Physical barriers should be provided by the contractor(s) during construction
activities in proximity to avoid potential damages through direct contact
with construction machineries. (iv) Air Pollution
Control (Construction Dust) Regulation
shall be followed. Dust suppression measures and good site practice should be adopted by the contractor(s). (v)
A safe access route should be maintained by the contractor(s) for conducting
mitigation measures during the construction phase. Operational Phase (vi)
Any revitalisation proposed for the building
in subsequent stages should be further reviewed by the future project proponent(s) or
subsequent developer(s). |
|
YTMT01 |
DD104 Lot 4186 S.E (Residence) |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by
record via cartographic and photographic record, and other documentation
means (including 3D scanning), should be conducted by the contractor(s) prior
to the commencement of construction works at the respective location. |
|
YTMT02 |
DD104 Lot 4187 S.B (Watchtower) |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location. |
|
YTMT03 |
Remnants of Nam Shan Monastery |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location. |
|
YTMT04 |
Subsidiary Station of San Yau Vegetable Marketing Co-operative Society,
Ltd. |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location. |
|
YTMT05 |
San Yau Vegetable Marketing Co-operative Society, Ltd. |
No Status |
6 m |
Potential indirect impacts of
ground-borne vibration, tilting and ground settlement and dust
nuisance are anticipated due to construction
works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii) Air Pollution
Control (Construction Dust) Regulation shall be
followed. Dust suppression measures and good site practice should be adopted by the contractor(s). (iii)
A safe access route should be maintained by the contractor(s) for conducting
mitigation measures during the construction phase. (iv)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should
be deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
YTMT06 |
Former Yau Tam Mei Primary School |
No Status |
Within Project Site |
Subject to the detailed design in
subsequent stages, if the
school would be preserved in situ, potential indirect impacts of ground-borne
vibration, tilting and ground settlement and dust nuisance are anticipated
due to construction works in proximity. |
If it will be preserved in situ and would be utilised as part of its
proposed land use, direct impact would be anticipated. |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including condition
surveys both before and after all construction works and monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
A buffer zone should be reserved by the
project proponent or its contractor(s) according to the results of condition
survey in the design layout of the Project. No piling works should be allowed
within the buffer zone during the construction phase. (iii)
Physical barriers should be provided by the contractor(s) during
construction activities in proximity to avoid potential damages through
direct contact with construction machineries. (iv) Air Pollution
Control (Construction Dust) Regulation shall be
followed. Dust suppression measures and good site practice should be adopted by the contractor(s). (v)
A safe access route should be maintained by the contractor(s) conducting
mitigation measures during the construction phase. Operational Phase (vi)
Opportunity for potential revitalisation
should be explored and mitigation measures will be
proposed as appropriate by the future project proponent(s) or
subsequent developer(s) in the detailed
design stage. |
|
Subject to the detailed design in subsequent stages, if the
school would not be preserved, direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location. |
||||
|
YTMT07 |
Lee’s Boundary Stone |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location. |
|
Wai Tsai Tsuen |
||||||
|
WTT01 |
DD104 Lot 2729 (Residence) |
No Status |
25 m |
Potential indirect impacts of
ground-borne vibration, tilting and ground settlement are anticipated due to
construction works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should
be deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
San Wai |
||||||
|
SW03 |
Nos.
16-17, San Wai Tsuen |
No Status |
48 m |
Potential indirect impacts of
ground-borne vibration, tilting and ground settlement are anticipated due to
construction works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should
be deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
SW04 |
No. 25A,
San Wai Tsuen |
No Status |
20 m |
Potential indirect impacts of ground-borne
vibration, tilting and ground settlement are anticipated due to construction
works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should
be deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
General (NTM Area) |
||||||
|
NB02 |
Mailbox No. 35 |
No Status |
13 m |
Potential indirect impacts of ground-borne
vibration, tilting and ground settlement are anticipated due to construction
works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and
settlement should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should
be deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
NB03 |
Mailbox No. 169 |
No Status |
37 m |
Potential indirect impacts of
ground-borne vibration, tilting and ground settlement are anticipated due to
construction works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and settlement
should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should be
deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
NB04 |
Mailbox No. 299 |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location. |
|
NB05 |
Man’s Boundary Stone |
No Status |
40 m |
No impact |
No impact |
Construction Phase To ensure no direct disturbance would be
caused to its physical fabrics, management measures should be deployed by the contractor(s), such as briefing to site staff before
commencement of construction works and posting notices at site office(s). |
|
NB08 |
Chun Chi Education Park |
No Status |
33 m |
Potential indirect impacts of
ground-borne vibration, tilting and ground settlement are anticipated due to
construction works in proximity. |
No impact |
Construction Phase (i)
Standard control measures on ground-borne vibration, tilting and settlement
should be conducted by the contractor(s), including monitoring of ground-borne
vibration, tilting and ground settlement when there are construction works
nearby. (ii)
To ensure no direct disturbance would be
caused to its physical fabrics, management measures should
be deployed by the contractor(s), such as
briefing to site staff before commencement of construction works and posting
notices at site office(s). |
|
NB09 |
Grave of Mr. Man Chiu Pak and His Wife |
No Status |
Within Project Site |
Direct impact is anticipated. |
No impact |
Construction Phase Preservation by record via cartographic and photographic record, and
other documentation means (including 3D scanning), should be conducted by the
contractor(s) prior to the commencement of construction works at the respective
location.
Implementation details would be subject to
discussion between project proponent(s) and stakeholders. |
·
SAI in Hong Kong: under the List of Sites of
Archaeological Interest in Hong Kong maintained by the AMO; and
·
Area of archaeological potential identified in
previous studies and / or this Project, but not
included in the item above.
· Former
offshore area;
· Past
and current watercourses and water bodies, such as natural streams and ponds; and
· Disturbed
or developed areas, such as cut slopes and areas of development(s) where site
formation works had been carried out.
·
Previous
Archaeological Surveys
·
Previous
Archaeological Assessment
·
Previous
Archaeological Assessment
· Previous Archaeological Assessment
· Previous Archaeological Assessment
· Previous Archaeological Assessment
Construction Phase
Operational Phase
Table 12.3 Summary of Potential Impact and the Proposed Mitigation Measures on Archaeological
Heritage in the Vicinity of the Project Site
|
Area of
Concern |
Impact
Assessment |
Impact Level |
Mitigation
Measures |
|
Ngau Tam Mei SAI |
As assessed in previous archaeological investigations, Ngau Tam Mei SAI is confirmed to have high archaeological potential during the prehistoric and historical
period. Land uses of Government (UniTown) (G.11) and
Road D1 as planned in the RODP encroached into the Ngau Tam Mei SAI. Direct impact to
archaeological deposits (if any) would be anticipated for this area. |
Direct Impact |
Archaeological excavation is necessary to be conducted at the Project Site within Ngau Tam Mei SAI to obtain adequate archaeological information of the area, and
retrieve the archaeological data, if any, before commencement of works involving soil disturbance at the respective area.
It should be subject to future land
resumption status and discussion with AMO in later stages. |
|
Ngau Tam Mei ASA and Ngau Tam Mei (North) ASA |
Ngau Tam Mei and Ngau Tam Mei (North) ASA are assessed to have high archaeological potential located within the Project Site. According to the RODP, land uses of Private and Public Residential (R.1, R.2,
R.3, R.4 and RSc.1), Education (E.2), Government, Institution or Community
(G.3, G.4, G.7, G.8 and G.13),
Government (UniTown) (G.6, G.10 and G.12), Open
Space (O.2, O.3, O.4 and O.7), Green Belt (GB.2), Ngau Tam Mei Road, Road L1, L2, L3 and D1 are located within both Ngau Tam Mei Archaeological Potential Area and Ngau Tam Mei (North) Archaeological Potential Area. Direct impact to the
archaeological deposits (if any) would be anticipated during the construction
phase. |
Direct Impact |
This CHIA has conducted a comprehensive review based on all available
information at this stage, in order to safeguard any
archaeological resources that might have existed within the Project Site. Considering the potential direct impact to both Ngau Tam Mei ASA and Ngau Tam Mei (North) ASA where have high archaeological potential,
archaeological survey-cum-excavation should be conducted. The aim is to obtain adequate
archaeological information of these areas for verifying its archaeological
potential, and retrieve the archaeological data, if any, before commencement
of works involving soil disturbance at the respective area. It should be subject to future land
resumption status and discussion with AMO in later stages. In principle, archaeological survey-cum-excavation should be conducted
with an aim to locate the precise horizontal extent and nature of the
archaeological deposits. Should
key archaeological findings occurred, excavation works should be applied to
retrieve archaeological data completely before commencement of works
involving soil disturbance at the respective area. |
|
Moderate-Low Archaeological Potential Area |
The low-lying agricultural fields and hilly
landscape within the Project Site are considered to have moderate-low archaeological potential. These moderate-low archaeological
potential areas encroach on land uses of Government, Institution or Community
(G.7, G.8 and G.9), Government (UniTown) (G.11 and
G.12), Road L3 and Road D1.
Direct impact to the archaeological deposits (if any) would be
anticipated during construction phase. |
Direct Impact |
Considering the potential direct impact to both
the low-lying agricultural fields and hilly landscape where have moderate-low
archaeological potential, archaeological survey should be conducted. The aim is to obtain adequate
archaeological information of these areas for verifying its archaeological
potential, and retrieve the archaeological data, if any, before commencement
of works involving soil disturbance at the respective area. It should be subject to future land
resumption status and discussion with AMO in later stages. |
|
Low Archaeological Potential Area |
For the low archaeological potential areas identified
in the NOL Main Line and STLMC DN EIA Reports within Project Site, direct
impact to the potential archaeological remains (if any) is anticipated. However, the impact on archaeology is
considered minimal and acceptable. |
Acceptable Impact |
As
a precautionary measure and pursuant to the A&MO (Cap. 53), the project proponent is
required to inform the AMO immediately in case of discovery of antiquities or
supposed antiquities in the course of works, so that appropriate mitigation
measures, if needed, can be timely formulated and implemented in agreement
with and to the satisfaction of AMO. |
|
No Archaeological Potential Area |
Desktop study has revealed that the Project Site has undergone extensive modern disturbance,
primarily driven by infrastructure projects.
Additionally, the construction of property developments, cut slopes and fishponds have contributed
to the disturbance. These modern
construction activities had involved significant soil disturbance, resulting
in the disturbance of the natural soil (and hence any potential
archaeological deposits). As a
result, the developed or disturbed areas within the Project Site are considered to have no archaeological potential. |
No Impact |
As
a precautionary measure and pursuant to the A&MO
(Cap. 53), the project proponent is required to inform the AMO immediately in
case of discovery of antiquities or supposed antiquities in the course of
works, so that appropriate mitigation measures, if needed, can be timely
formulated and implemented in agreement with and to the satisfaction of AMO. |
Bibliography
Fyfe, J. A et al. (2000). The Quaternary
Geology of Hong Kong. Hong Kong: Civil Engineering Department.
Johnson, E. (2000). Recording a rich heritage: research on Hong Kong's
"New Territories". Hong Kong: Leisure & Cultural Services
Department.
Internet
Civil
Engineering and Development Department and Planning Department. (2023). First
Phase Development of the New Territories North – San Tin / Lok Ma Chau
Development Node – Investigation (Agreement No. CE 20/2021). Section 12 Impact
on Cultural Heritage. Retrieved from
https://www.epd.gov.hk/eia/files/applications/en/pp_340/eia_1994/progress/action_157674/eia_3022023/EIA/CE20_EIA_S12.htm#_Toc154070604
Hong Kong Government.
(1964). Laws of Hong Kong. Appendix IV A Selection of Constitutional
Documents, Conventions and Treaties. Retrieved from https://oelawhk.lib.hku.hk/archive/files/87f64e08aedf20f07b7d8ac2132030c1.pdf.
Topographic Map
Lands Department. (1966).
1:1,200. 75-SW-C [topographic map]. Lands Department.
Lands Department. (1966).
1:1,200. 75-SW-D [topographic map]. Lands Department.
Lands Department. (1966). 1:1,200. 92-NW-A
[topographic map]. Lands Department.
Lands Department. (1966). 1:1,200. 92-NW-B
[topographic map]. Lands Department.
Lands Department. (1969).
1:1,200. 75-SW-C [topographic map]. Lands Department.
Lands Department. (1969).
1:1,200. 75-SW-D [topographic map]. Lands Department.
Lands Department. (1969). 1:1,200. 92-NW-A
[topographic map]. Lands Department.
Lands Department. (1973). 1:1,200. 92-NW-B
[topographic map]. Lands Department.
Lands Department. (1974).
1:1,200. 75-SW-D [topographic map]. Lands Department.
Lands Department. (1975).
1:1,200. 75-SW-C [topographic map]. Lands Department.
Lands Department. (1975). 1:1,200. 92-NW-A
[topographic map]. Lands Department.
Lands Department. (1975). 1:1,200. 92-NW-B
[topographic map]. Lands Department.
Lands Department. (1978).
1:1,200. 75-SW-C [topographic map]. Lands Department.
Lands Department. (1978).
1:1,200. 75-SW-D [topographic map]. Lands Department.
Lands Department. (1978). 1:1,200. 92-NW-A
[topographic map]. Lands Department.
Lands Department. (2006). 1:5 000, 2-SE-C (Ed
2006-08) [topographic map]. Lands Department.
Aerial Photo
Lands Department. (1924). 1:13800, 11500ft.,
H8-0005 [aerial photo]. Retrieved from https://www.hkmapservice.gov.hk/OneStopSystem/map-search.
Lands Department. (1924). 1:14332, ---ft.,
H32-0013 [aerial photo]. Retrieved from https://www.hkmapservice.gov.hk/OneStopSystem/map-search.
Lands Department. (1945). 1:12000, 20000ft.,
681_4-4138 [aerial photo]. Retrieved from
https://www.hkmapservice.gov.hk/OneStopSystem/map-search.
Lands Department. (1956). 1:10020, 16700 ft.
F22_560-0205 [aerial photo]. Lands Department.
Lands Department. (1963). 1:27000, 13500 ft.,
V81A_857-0013R [aerial photo]. Lands Department.
Lands Department. (1964). 1:25000, 12500 ft.,
1964-2790R [aerial photo]. Lands Department.
Lands Department. (1974). 1:4800, 2400 ft., 09416
[aerial photo]. Lands Department.
Lands Department. (1975). 1:25000, 12500ft, 11882R [aerial photo].
Lands Department.
[1] Antiquities
and Monuments Office. List of Declared
Monuments and Proposed Monuments (as at 10 October 2024). Retrieved from https://www.amo.gov.hk/filemanager/amo/common/form/DM_Mon_List.pdf.
[2] Antiquities and Monuments Office. List of Graded Historic
Buildings (as at 26.6.2025). Retrieved from https://www.amo.gov.hk/filemanager/amo/common/form/List%20of%20Graded%20Historic%20Buildings.pdf.
[3] Antiquities Advisory Board. List of New Items for Grading
Assessment with Assessment Results (as at 3 September 2025). Retrieved from https://www.aab.gov.hk/filemanager/aab/en/content_29/list_new_items_assessed.pdf.
[4] Antiquities and Monuments Office. Government Historic Sites
Identified by AMO (as at May 2022). Retrieved from https://www.amo.gov.hk/filemanager/amo/common/form/build_hia_government_historic_sites.pdf.
[5] Antiquities
and Monuments Office. List of Declared
Monuments and Proposed Monuments (as at 10 October 2024). Retrieved from https://www.amo.gov.hk/filemanager/amo/common/form/DM_Mon_List.pdf.
[6] Antiquities
and Monuments Office. List of
Sites of Archaeological Interest in Hong Kong (as at Nov 2012). Retrieved from https://www.amo.gov.hk/filemanager/amo/common/form/list_archaeolog_site_eng.pdf.
[7] 500 m
assessment area refers to the area extending 500 m from the Project Boundary of STLMC DN and Proposed At-Grade Works Site and Works Area of NOL Main Line.
[8] Section
12.3.1.1 of the approved STLMC DN EIA report stated
that “the AIA is to assess the possible impact on any archaeological
resources fall within the Project area”. Archaeological
fieldworks and subsequent detailed analysis for both
AIA studies under the STLMC DN and NOL Main Line EIA reports were only
conducted within their project areas .
[9] Geotechnical Control
Office. (1989). Hong Kong Geological Survey Sheet 2. Government of Hong
Kong.
[10] Fyfe, J. A et al. (2000). The Quaternary Geology of Hong Kong.
Hong Kong: Civil Engineering Department.
[11] 司馬遷 (c.a. 91BC)。史記 卷一百一十三 南越列傳 第五十三。北京:中華書局
(1959) 。
[12]
Although the
boundary between Boluo (博羅) County and Panyu (番禺) County during Han
to East Jin period is unclear, it is generally suggested that Hong Kong
region belonged to Boluo County at that time, according to Xinan
Gazetteer (1819), Social Change in Hong Kong Before and After the Early
Qing Clearance (1986), and Brief History of Ancient Shenzhen (1997). However, Professor Jao Tsung-I (2005) discussed that the area
belonged to Panyu based on the inscriptions on bricks of Lei Cheng Uk
Han Tomb.
[13] 劉智鵬、劉蜀永 (編) (2020) 。《方志中的古代香港-
《新安縣志》香港史料選》。香港:三聯書店(香港)有限公司。
[14]
Ibid.
[15] 蕭國健 (1986) 。《清初遷界前後香港之社會變遷》。台北:台灣商務印書館。
[16] Hong Kong Government.
(1964). Laws of Hong Kong. Appendix IV A Selection of Constitutional
Documents, Conventions and Treaties. Retrieved from https://oelawhk.lib.hku.hk/archive/files/87f64e08aedf20f07b7d8ac2132030c1.pdf.
[17] Ibid.
[18] Ibid.
[19]Lands Department. (1924). 1:14332, ---ft., H32-0013 [aerial photo]. Retrieved from https://www.hkmapservice.gov.hk/OneStopSystem/map-search.
Lands Department. (1924). 1:13800, 11500ft., H8-0005 [aerial
photo]. Retrieved from https://www.hkmapservice.gov.hk/OneStopSystem/map-search.
Lands Department. (1945). 1:12000, 20000ft., 681_4-4138 [aerial
photo]. Retrieved from https://www.hkmapservice.gov.hk/OneStopSystem/map-search.
[20] History in Data Project website (Accessed on 11 March 2022) Hong Kong
1941. Retrieved from
https://digital.lib.hkbu.edu.hk/1941hkbattle/en/research-team.php.
[21] Johnson, E. (2000). Recording
a rich heritage: research on Hong Kong's "New Territories". Hong
Kong: Leisure & Cultural Services Department.
[22] Lands
Department. (1956). 1:10020, 16700 ft. F22_560-0205 [aerial photo].
Lands Department.
[23] Lands
Department. (1963). 1:27000, 13500 ft., V81A_857-0013R [aerial photo].
Lands Department.
[24] Lands
Department. (1975). 1:25000, 12500ft, 11882R [aerial photo]. Lands
Department.
[25]
Lands Department.
(1964). 1:25000, 12500 ft., 1964-2790R [aerial photo]. Lands
Department.
[26] Lands
Department. (2006). 1:5 000, 2-SE-C (Ed 2006-08) [topographic map]. Lands
Department.
[27] Water
Services Department. Ngau Tam Mei Water Treatment Works. Retrieved from https://www.wsd.gov.hk/filemanager/en/share/pdf/NgauTamMeiTW-e.pdf.
[28] Antiquities and Monuments Office. List of Sites of Archaeological
Interest in Hong Kong (as of Nov 2012). Retrieved from https://www.amo.gov.hk/filemanager/amo/common/form/list_archaeolog_site_eng.pdf.
[29] 古物古蹟辦事處 (1997) 。《全港文物普查1997第一地區(元朗區)工作報告》。香港:古物古蹟辦事處檔案。
[30] Ibid.
[31] 古物古蹟辦事處 (1999) 。《元朗牛潭尾主渠道第二期工程考古調查工作報告》。香港:古物古蹟辦事處檔案。
[32] Ibid.
[33] Drainage Services Department. (2013). EIA and TIA Studies for the
Stage 2 of PWP Item No. 215DS – Yuen Long and Kan Tin Sewerage and Sewage
Disposal (Agreement No. CE 66/2001). Section 15
Cultural Heritage Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_82/eia_1578/progress/action_3229/eia_report.pdf.
[34] MTR
Corporation Limited. (2023). Environmental
Impact Assessment Study for Northern Link (Agreement No. C1603). Section 13 Cultural Heritage Impact Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_346/eia_1992/progress/action_1365/eia_3012023/HTML/EIA%20Report/S13%20CHIA.htm.
[35] Civil
Engineering and Development Department and Planning Department. (2023). First
Phase Development of the New Territories North – San Tin / Lok Ma Chau
Development Node – Investigation (Agreement No. CE 20/2021). Section 12 Impact on Cultural
Heritage. Retrieved from
https://www.epd.gov.hk/eia/files/applications/en/pp_340/eia_1994/progress/action_157674/eia_3022023/EIA/CE20_EIA_S12.htm#_Toc154070604.
[36] Water Supplies
Department. (2024). Ngau Tam Mei Water Treatment Works
Extension – Environmental Impact Assessment Report (282551-REP-080-05). Section 11 Impact on Cultural
Heritage. Retrieved from
https://www.epd.gov.hk/eia/register/study/latest/esb-333.pdf.
[37] Australia International Council and Monuments and Sites (ICOMOS).
(2013). The
Burra Charter: the Australia ICOMOS Charter
for Place of Cultural Significance. Retrieved
from https://australia.icomos.org/wp-content/uploads/The-Burra-Charter-2013-Adopted-31.10.2013.pdf.
[38] Buildings Department. (2024). Code of Practice for
Foundations 2017 (2024 Edition). Retrieved from https://www.bd.gov.hk/doc/en/resources/codes-and-references/code-and-design-manuals/FoundationCode2017.pdf.
[39] Buildings Department. (2024). Practice Note for
Authorised Person, Registered Structural Engineers and Registered Geotechnical
Engineers (PNAP) – Ground-borne Vibration and Ground Settlement arising from
Pile Foundation and Excavation and Lateral Support Work (APP-137).
Retrieved from https://www.bd.gov.hk/doc/en/resources/codes-and-references/practice-notes-and-circular-letters/pnap/APP/APP137.pdf.
[40] 商志𩡝 、吳偉鴻 (2010) 。《香港考古學叙研》。北京:文物出版社。
[41] 古物古蹟辦事處 (1999) 。《元朗牛潭尾主渠道第二期工程考古調查工作報告》。香港:古物古蹟辦事處檔案。
[42] Drainage Services Department. (2013). EIA and TIA Studies for the
Stage 2 of PWP Item No. 215DS – Yuen Long and Kan Tin Sewerage and Sewage
Disposal (Agreement No. CE 66/2001). Section 15
Cultural Heritage Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_82/eia_1578/progress/action_3229/eia_report.pdf.
[43] MTR
Corporation Limited. (2023). Environmental
Impact Assessment Study for Northern Link (Agreement No. C1603). Section 13 Cultural Heritage Impact Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_346/eia_1992/progress/action_1365/eia_3012023/HTML/EIA%20Report/S13%20CHIA.htm.
[44] Civil
Engineering and Development Department and Planning Department. (2023). First
Phase Development of the New Territories North – San Tin / Lok Ma Chau
Development Node – Investigation (Agreement No. CE 20/2021). Section 12 Impact on Cultural
Heritage. Retrieved from
https://www.epd.gov.hk/eia/files/applications/en/pp_340/eia_1994/progress/action_157674/eia_3022023/EIA/CE20_EIA_S12.htm#_Toc154070604.
[45] Water Supplies
Department. (2024). Ngau Tam Mei Water Treatment Works
Extension – Environmental Impact Assessment Report (282551-REP-080-05). Section 11 Impact on Cultural
Heritage. Retrieved from
https://www.epd.gov.hk/eia/register/study/latest/esb-333.pdf.
[46] 古物古蹟辦事處 (1999) 。《元朗牛潭尾主渠道第二期工程考古調查工作報告》。香港:古物古蹟辦事處檔案。
[47] A11 is located within the said drainage
works area.
[48] MTR
Corporation Limited. (2023). Environmental
Impact Assessment Study for Northern Link (Agreement No. C1603). Section 13 Cultural Heritage Impact Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_346/eia_1992/progress/action_1365/eia_3012023/HTML/EIA%20Report/S13%20CHIA.htm.
[49] Geotechnical Control Office. (1989). Hong
Kong Geological Survey Sheet 2. Government of Hong Kong.
[50] Ibid.
[51] Housing
Bureau. Transitional Housing Project at Ngau Tam Mei South (Chun Shin Road),
Yuen Long. Retrieved from https://www.hb.gov.hk/eng/policy/housing/policy/transitionalhousing/details_70.html.
[52] MTR
Corporation Limited. (2023). Environmental
Impact Assessment Study for Northern Link (Agreement No. C1603). Section 13 Cultural Heritage Impact Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_346/eia_1992/progress/action_1365/eia_3012023/HTML/EIA%20Report/S13%20CHIA.htm.
[53] Civil
Engineering and Development Department and Planning Department. (2023). First
Phase Development of the New Territories North – San Tin / Lok Ma Chau
Development Node – Investigation (Agreement No. CE 20/2021). Section 12 Impact on Cultural
Heritage. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_340/eia_1994/progress/action_157674/eia_3022023/EIA/CE20_EIA_S12.htm#_Toc154070604.
[54] 古物古蹟辦事處 (1999)。 《元朗牛潭尾主渠道第二期工程考古調查工作報告》。香港:古物古蹟辦事處檔案。
[55] Lands
Department. (1966). 1:1,200. 75-SW-C [topographic map]. Lands
Department.
Lands
Department. (1969). 1:1,200. 75-SW-C [topographic map]. Lands
Department.
Lands
Department. (1975). 1:1,200. 75-SW-C [topographic map]. Lands
Department.
Lands
Department. (1978). 1:1,200. 75-SW-C [topographic map]. Lands
Department.
Lands
Department. (1966). 1:1,200. 75-SW-D [topographic map]. Lands
Department.
Lands
Department. (1969). 1:1,200. 75-SW-D [topographic map]. Lands
Department.
Lands
Department. (1974). 1:1,200. 75-SW-D [topographic map]. Lands
Department.
Lands
Department. (1978). 1:1,200. 75-SW-D [topographic map]. Lands
Department.
Lands
Department. (1966). 1:1,200. 92-NW-A [topographic map]. Lands
Department.
Lands
Department. (1969). 1:1,200. 92-NW-A [topographic map]. Lands
Department.
Lands
Department. (1975). 1:1,200. 92-NW-A [topographic map]. Lands
Department.
Lands
Department. (1978). 1:1,200. 92-NW-A [topographic map]. Lands
Department.
Lands
Department. (1966). 1:1,200. 92-NW-B [topographic map]. Lands
Department.
Lands
Department. (1973). 1:1,200. 92-NW-B [topographic map]. Lands
Department.
Lands
Department. (1975). 1:1,200. 92-NW-B [topographic map]. Lands
Department.
[56] Antiquities and Monuments Office. Geographical
Information System on Hong Kong Heritage. Retrieved from https://gish.amo.gov.hk/internet/index.html?lang=en-us.
[57] MTR
Corporation Limited. (2023). Environmental
Impact Assessment Study for Northern Link (Agreement No. C1603). Section 13 Cultural Heritage Impact Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_346/eia_1992/progress/action_1365/eia_3012023/HTML/EIA%20Report/S13%20CHIA.htm.
[58] Hong Kong Observatory. (2025). Yearly Extract. Climate Information
Service. Retrieved from https://www.hko.gov.hk/en/cis/yearlyExtract.htm.
[59] Fyfe, J. A et al. (2000). The Quaternary Geology of Hong Kong,
p.26. Hong Kong: Civil Engineering Department.
[60] 古物古蹟辦事處 (1997) 。《全港文物普查1997第一地區(元朗區)工作報告》。香港:古物古蹟辦事處檔案。
[61] 古物古蹟辦事處 (1999) 。《元朗牛潭尾主渠道第二期工程考古調查工作報告》。香港:古物古蹟辦事處檔案。
[62] 香港考古學會(2009)。《元朗七星崗考古調查工作報告》。香港:古物古蹟辦事處檔案。
[63] Lands Department. (1974). 1:4800, 2400 ft., 09416
[aerial photo]. Lands Department.
[64] Lands Department. (1975). 1:1 200 75-SW-C (Ed 1975-07)
[topographic map]. Lands Department.
[65] MTR Corporation Limited. (2023). Environmental Impact Assessment Study for Northern Link (Agreement
No. C1603). Section 13 Cultural Heritage Impact Assessment. Retrieved from https://www.epd.gov.hk/eia/files/applications/en/pp_346/eia_1992/progress/action_1365/eia_3012023/HTML/EIA%20Report/S13%20CHIA.htm.
[66] Ibid.