Contents

 

                                                                                                                                                                        Page

2            PROJECT DESCRIPTION AND CONSIDERATION OF ALTERNATIVES  1

2.1           Need of the Project 1

2.2           Consideration of Scenario Without the Proposed Development 8

2.3           Consideration of Different Development Options  9

2.4           Summary of Recommended Outline Development Plan (RODP) 51

2.5           Consideration of Alternatives  78

2.6           Proposed Construction Methodologies for Land Uses and Design  93

2.7           Consideration of Alternatives for Construction Methodologies  103

2.8           Summary of Reclamation Area and Permanent Seabed Loss Area  133

2.9           Construction Programme  133

 

 

 

References

 

Tables

 

Figures

Figure 2.1a                Project Location Plan Presented in EIA Study Brief
(ESB-251/2012)

Figure 2.1b                Project Location Plan Presented in EIA Study Brief
(ESB-283/2014)

Figure 2.1c                 Project Location Plan Presented in EIA Study Brief
(ESB-285/2015)

Figure 2.2                  Revised Recommended Outline Development Plan - TCE

Figure 2.3                  Revised Recommended Outline Development Plan - TCW

Figure 2.4                  Site IDs of RODP (TCE)

Figure 2.5                  Site IDs of RODP (TCW)

Figure 2.6a                Locations of Residential Land Use in RODP (TCE)

Figure 2.6b                Locations of Residential Land Use in RODP (TCW)

Figure 2.7                  Locations of Village Development Area in RODP (TCW)

Figure 2.8a                Locations of Commercial Land Use in RODP (TCE)

Figure 2.8b                Locations of Commercial Land Use in RODP (TCW)

Figure 2.9a                Locations of Government Land Use in RODP (TCE)

Figure 2.9b                Locations of Government Land Use in RODP (TCW)

Figure 2.10                Locations of Education Land Use in RODP (TCE)

Figure 2.11                Locations of Institution and Community Land Use in RODP (TCW)

Figure 2.12a              Locations of Other Specified Uses Land Use in RODP (TCE)

Figure 2.12b              Locations of Other Specified Uses Land Use in RODP (TCW)

Figure 2.13                Locations of Conservation Area Land Use in RODP (TCW)

Figure 2.14                Locations of Coastal Protection Area Land Use in RODP (TCW)

Figure 2.15a              Locations of Open Space Land Use in RODP (TCE)

Figure 2.15b              Locations of Open Space Land Use in RODP (TCW)

Figure 2.16                Locations of Green Belt Land Use in RODP (TCW)

Figure 2.17                Locations of Agriculture Land Use in RODP (TCW)

Figure 2.18a              Locations of Road Land Use in RODP (TCE)

Figure 2.18b              Locations of Road Land Use in RODP (TCW)

Figure 2.19a              Locations of Public Transport Interchange in RODP (TCE)

Figure 2. 19b             Locations of Public Transport Interchange in RODP (TCW)

Figure 2.20a              Locations of Cycle Track Connections in RODP (TCE)

Figure 2.20b              Locations of Cycle Track Connections in RODP (TCW)

Figure 2.21                Locations of Cycling Park in RODP (TCE)

Figure 2.22                Locations of Infrastructure Outside RODP

Figure 2.23                Total Permanent Seabed Loss

Figure 2.24a              Locations of Development Phasing in TCE

Figure 2.24b              Locations of Development Phasing in TCW

 

Drawings

 

Pictures

 

Photographs

 

Attachments

 

Appendices

 

Appendix 2.1               Detailed Layout Plan of RODP for TCE and TCW

Appendix 2.2               Land Use Options in PODP considered for TCE and TCW

Appendix 2.3               Conceptual Drawings of the Sustainable Drainage System

Appendix 2.4               Schematic Cross Sections for Different Seawall Construction Options

Appendix 2.5               Schematic Cross Sections for Different Reclamation Options

Appendix 2.6               Connectivity Options for Road P1 (Tung Chung – Tai Ho Section)

Appendix 2.7               Construction Programme

 

 


2                                PROJECT DESCRIPTION AND CONSIDERATION OF ALTERNATIVES

2.1                         Need of the Project

2.1.1                  Territory-Wide Housing Issues

2.1.1.1           Housing has been long identified as an issue of great public concern.  According to the statistics in 2011, there are currently 2.6 million residential units in HK, accommodating 2.35 million households. Of those, 730,000 households live in Public Rental Housing (PRH) and 380,000 in self-owned units acquired with government subsidies. In other words, almost half of the households in HK are benefiting from some form of housing subsidy by the Government. Of the remaining 1.24 million households living in private properties, 870,000 are owner-occupants. Taken together, nearly 85% of households live in PRH units, subsidised home ownership scheme (HOS) flats or their own private properties.  Hence, housing has been one of the focus areas in the Policy Addresses for last few years.   

2.1.1.2           The 2011-2012 Policy Address had identified that maintaining PRH production, maintaining affordable price for private property and providing adequate land supply would be the key to tackle issues relating to housing. For PRH production in particular, the first challenge is the shortage of land and it is necessary to open up new sites and explore ways to appropriately increase the densities and plot ratios of PRH projects without compromising the living environment. The second challenge is the objection of some local communities to PRH development. In terms of land supply, the government set a target for an average of 20,000 private residential flats each year in the next decade in order to ensure the healthy and stable development of the property market. The 2011 – 2012 Policy Address had also stated that, according to the Public Housing Construction Programme of the Housing Authority (HA), about 75,000 PRH units will be completed in the next five years. 

2.1.1.3           In 2012 – 2013 Policy Address, the objectives for housing were to (i) assist grassroots families to secure public housing to meet their basic housing needs; (ii) assist the public to choose accommodation according to their affordability and personal circumstances, and encourage those who can afford it to buy their own homes; (iii) provide subsidised home ownership flats on top of PRH so as to build a progressive housing ladder; and (iv) maintain the healthy and steady development of the private property market, with priority to be given to meet HK permanent residents’ needs. A series of strategies has been identified to address the land supply issue in short, medium and long term. Of particular relevance is the development of Lantau Island. With the rapid development of the west bank of the Pearl River Delta, Qianhai, Nansha and Hengqin, coupled with the availability of the Hong Kong-Zhuhai-Macao Bridge and other infrastructure, the northwest of HK will become a focal point of development. Lantau Island, in particular Tung Chung, has a geographical advantage for the development of logistics, tourism and other industries, hence creating new employment opportunities for the local residents. In fact, the government commenced the Tung Chung New Town Extension Study in Year 2012 to explore the potential of developing the remaining Tung Chung into a new town with more comprehensive and better developed community facilities.

2.1.1.4           Policy Address 2014 also examined the housing issue and considered that the housing shortage problem had been serious. Apart from soaring property and rental prices, cramped living conditions trouble many HK people, the government identified a number of strategies to tackle these issues, from short, medium and long terms. This Policy Address also adopted the Long Term Housing Strategy Steering Committee’s recommendation that public housing should account for 60% of the 10-year housing supply target of 470,000 units. Among public housing, the supply of PRH should be 200,000 units while that of subsidised sale flats 80,000 units. In line with the annual roll-over approach, the Government would review and where necessary adjust these splits between public and private housing, and between PRH and subsidised sale flats to better respond to changing market situations and evolving needs of the community. Besides, extension of the Tung Chung New Town had also been highlighted again as one of the strategies to increase the long term land supply. Similar statement was also emphasised in the Policy Address 2015 on the need on the extension of Tung Chung New Town for supplying residential units and a commercial hub.

2.1.2                  The Development of Tung Chung New Town

2.1.2.1           The development of Tung Chung New Town started in the 1990s under the original goal of establishing a supporting community for Hong Kong’s new international airport. In 1990, the Government commissioned Consultants to carry out planning of the North Lantau New Town (NLNT) and detailed feasibility studies collectively known as the North Lantau Development Study (NLDS).  The NLDS was completed and a final report together with a Tung Chung and Tai Ho Recommended Outline Development Plan (RODP) was produced in 1992. The NLDS and the RODP was subsequently approved by the then Development Progress Committee (DPC) in 1992. According to the NLDS, the NLNT would be developed in five phases with population level at 120,000 by 2006 (upon completion of Phases 1, 2 and 3) and 210,000 by 2011 (upon completion of Phase 4) ,and there was also development potential for an ultimate population of 260,000 after 2011 (Phase 5 developments).

2.1.2.2           In mid 1996, the Government completed the Territorial Development Strategic Review (TDSR) which identified housing shortfall in the medium to long term. The TDSR also identified the NLNT as a strategic growth area, among other areas, to meet the territorial housing demand, with a revised population target of 320,000 by 2011.

2.1.2.3           In 1996, the Administration approved the Development Statement for Tung Chung and Tai Ho with a population target of 320,000 by year 2011. The then Territory Development Department (TDD) commissioned Consultants in 1997 to carry out a consultancy study – Remaining development in Tung Chung and Tai Ho – Comprehensive Feasibility Study (CFS).

2.1.2.4           In 1999, TDD completed the CFS which showed that it was feasible for NLNT to accommodate a population target of about 334,000 in anticipation of the projected territory-wide demand by 2011. The Islands District Council, professional institutions, Advisory Council on Environment (ACE) and green groups were consulted on the recommendations of the study.  Following consultation with the Town Planning Board of the RODP for Tung Chung and Tai Ho, the Administration briefed the Legislative Council Panel on Planning, Lands and Works in 2000 for funding approval to proceed with detailed design of engineering works. At the meeting, Members had reservation on the form of development at Tai Ho and requested the Administration to further consult the public. However, the RODP had been withheld due to subsequent changes in planning circumstances and bringing in the mega territorial infrastructure projects in North Lantau. These included the proposed logistics park in North Lantau as set out in the 2003 Policy Address and the Hong Kong-Zhuhai-Macao Bridge (HZMB) with a landing point at North West Lantau.

2.1.2.5           In 2004, the Administration endorsed a new concept plan for planning initiatives on Lantau which placed more emphasis on tourism, economic infrastructure and nature conservation on Lantau with a corresponding reduction in housing development. In  2004, the Lantau Development Task Force commenced a three-month public consultation on the Concept Plan for Lantau. According to the concept plan, part of NLNT development was replaced by the Lantau Logistics Park (LLP) at Siu Ho Wan and a possible theme park/major recreational uses in Tung Chung east subject to feasibility studies.  These were intended to enhance Hong Kong’s competitiveness in the logistics industry and to enhance the attraction of Lantau.  

2.1.2.6           In 2007, the Revised Concept Plan for Lantau was completed, featuring a greater emphasis on tourism, economic infrastructure and nature conservation in Lantau. It should be noted that the engineering works for Phases 1 and 2 developments, and reclamation for Phase 3A had been completed. The Phases 1 and 2 housing developments at NLNT have also been completed. The housing developments of Phases 1, 2 and 3A have a total capacity to accommodate about 108,000 people upon full occupation. Continuing development of the North Lantau New Town (NLNT) is necessary to provide for a more optimum scale of the new town to support the major community, commercial and transport facilities and services required by the residents. According to the Revised Concept Plan for Lantau, Tung Chung would be a comprehensively planned new town with a capacity to accommodate a total population of about 220,000. However, some of the proposals under the Revised Concept Plan for Lantau are still being reviewed and yet to be studied in details and implemented. According to the latest Population Census, the population in Tung Chung reached 78,400 in 2011. 

2.1.3                  Need for Suitable Scale of Development in Tung Chung

2.1.3.1           As mentioned in Section 2.1.2, after the completion of CFS in late 1990s, it was recommended that Tung Chung would be developed in 4 phases. Currently, Phases 1, 2 and 3a development have been completed where the Tung Chung New Town is currently located. The recommended Phase 4 development under the CFS involved reclamation of the entire Tung Chung Bay, as well as the development of the Tai Ho area (originally accommodating a total population of 334,000). With the change in subsequent planning circumstances, further development was not proceeded at that time.  The Tai Ho development area was excluded.  Subsequently in the 2007 Revised Concept Plan for Lantau the planned population was reduced to 220,000.

2.1.3.2           The intention for this Study is to review and re-start the remaining development of Tung Chung. Due to the latest planning circumstances, and public concerns on the environmental sensitivity of the Tung Chung Bay, the proposal for TCW reclamation is not pursued, while the focus of the RODP will concentrate on the development in the  reclamation in TCE and optimizing existing land in the TCW. Compared to the original Phase 4 development recommended under the CFS, the reclamation area is greatly reduced. (See Section 2.3.2 for more details on the comments from the PE exercises)

2.1.4                  Aspirations from Local Communities in Tung Chung

2.1.4.1           Since the commencement of this study in Year 2012, a three-stage Public Engagement (PE) exercise has been conducted to collate the views from various stakeholders, including but not limited to local communities, NGOs etc. The comments received cover a wide range of issues such as 1) Development scale and land uses; 2) Economic development; 3) Ecology and environment; 4) Provision of facilities, and housing; and 5) Transport and Infrastructures (see Section 2.3.2 for more details on the comments from the PE exercises).    

2.1.4.2           Though there is a broad consensus for further development in Tung Chung, the local communities in Tung Chung also demand the possibility to revitalise the local economy and to stimulate economic growth by offering more job opportunities from the development. There is a strong need calling for more diverse job opportunities in Tung Chung that can match the local skillsets. For instances, more local business such as small street shops, local retailing services and commercial facilities etc. should be provided so that more diverse kinds of job opportunities could be created. The local communities also ask for a multi-sports stadium, extension of cycling tracks, more GIC facilities such as wet markets, flea markets, religious facilities, childcare centres etc, and tertiary education institution.

2.1.4.3           Given the current urban context in Tung Chung, all the above aspirations would require extra land to achieve.  In fact, according to the latest proposal (see Section 2.4 for details on latest land use planning), once the PDAs in TCE and TCW are implemented, the RODP would provide a total floor area of 8.76ha for commercial areas.  Together with the commercial components in the planned Metro Core Area, these commercial areas, including retails, offices and hotel facilities would provide a total of around 40,000 permanent employments during the operational phase.  These employment opportunities would cover a wide spectrum of job nature such as retail services, office work, property management, hotel mangement, tourism services etc. Besides, the current planning within the PDA has also allowed the implementation of street shops and hence would satisfy the need raised by the local communities. Without the proposed development at TCE and TCW, all these aspirations from the local communities could not be materialised.

2.1.5                  Summary on the Need for Further Developments in Tung Chung

2.1.5.1           It can be seen from the above discussion in Section 2.1.1 to Section 2.1.4 that the territory-wide shortage of housing supply has caused a number of social issues in HK. Tung Chung has been identified by the recent Policy Addresses as one of the potential areas to contribute to the land supply and abate the circumstances. While Tung Chung New Town was first occupied decades ago, its current population is less than that originally envisioned. Throughout the PE process, the local communities have raised a number of views and aspirations such as development scale and landuses, economic development, ecology and environment, provision of facilities and housing, transport and infrastructures etc.  Given the current urban context in Tung Chung, extra land would be required to achieve many of these views and aspirations.  Hence, as mentioned in Section 2.1.4, development of the TCNTE, comprising new development areas in TCE and TCW, aims to provide land to meet the future housing, economic and social development needs of Hong Kong.

2.1.6                  Project Vision

2.1.6.1           Given the unique development history and geographical setting of Tung Chung, there are three key project visions in planning the development of TCNTE to suit the needs of the society and the aspirations from the local communities:

2.1.6.2           Optimising living environment: The first vision is to help address the territory-wide housing needs while enhancing the quality of living of residents by adopting sustainable urban design and providing balanced allocation of open space and community facilities.  Since the new town extension will extend the footprint of Tung Chung considerably, the land formed would offer a good opportunity to address many of the aspirations from the local communities such as sports ground, post-secondary institution, comprehensive network of cycling tracks and other GIC facilities etc. Together with development proposals in other parts of HK, it is envisioned that the current housing issues could be progressively alleviated and would be beneficial to the entire society. 

2.1.6.3           Treasuring natural resources: Tung Chung is enjoying a number of valuable natural resources including those from ecology, built heritage, natural coastline, etc.  Tung Chung Bay, Tung Chung Stream, mudflat, mangroves, Tai Ho Bay, country parks, future marine park are some of the examples of recognized ecologically sensitive areas.  Built heritages such as monuments and graded historical buildings in the vicinity have also reflected it’s richness in history.  The natural coastline in Tung Chung West also has its own characteristics that are coherent with the western part of Lantau.  All these natural resources in the vicinity of Tung Chung have therefore brought both constraints and opportunities for planning of TCNTE. 

2.1.6.4            In terms of achieving an environmentally considerate planning, lots of initiatives have been proactively incorporated to not just avoiding and minimizing environmental impacts, but also enhancing some of the environmental conditions. A summary of those initiatives is given below, and are discussed in more details in Section 14.

Avoidance of environmental impacts

·      No reclamation in TCW to avoid impact to Tung Chung Bay and Estuary

·      Avoidance of encroachment on Tung Chung Stream

·      Avoidance of emergency discharge from sewage pumping stations at both TCE and TCW

·      Avoidance of using fully dredged construction method in TCE reclamation

·      Avoidance of encroachment on natural resources with high ecological resources

·      Avoidance of encroachment on built heritage

Minimisation and mitigation of environmental impacts

·      Provision of sustainable drainage system for TCW

·      Utilisation of existing site formation for services reservoirs

·      Adoption of stepped heights for buildings

·      Provision of greening at TCE and TCW

·      Minimisation of encroachment on Fung Shui Woods

·      Adoption of transport oriented development principle, e.g. planning higher density developments near the new TCE and TCW railway stations to help reduce environmental impact arising from road traffic

·      Provision of Road P1 (Tung Chung – Tai Ho Section) connecting TCE and North Lantau Highway (NLH) at the Tai Ho Interchange to minimise road traffic at Tung Chung Town Centre

·      Provision of setback distance between residential developments and NLH and Tuen Mun – Chek Lap Kok Link

·      Provision of direct noise mitigation measures within TCE and TCW etc.

Environmental Enhancements

·      Proper zoning of Conservation Area, Coastal Protection Area and Green Belt within TCW

·      Revitalization of the existing channelised section of Tung Chung Stream

·      Provision of a River Park at portion of the eastern branch of Tung Chung Stream to promote eco-education

·      Provision of proper sewerage system for the existing villages in TCW

·      Extension of promenade for public enjoyment

·      Provision of cycling tracks to improve connectivity within Tung Chung

·      Provision of space to accommodate charging facilities for future generation of environmentally friendly buses

·      Planting of aquatic plants in biofiltration zone of attenuation and treatment ponds

·      Restoration and enhancement of degraded habitats inside buffer zone

·      Planting on the earth bunds of polders

2.1.6.5           Enhancing job opportunities: The third vision is in response to the public expectation of a wide variety of job opportunities for the residents of Tung Chung. With the introduction of different commercial development, including offices, retails, hotels and marina, TCNTE is expected to create various job opportunities.  Added with the nearby developments, the job opportunities in Tung Chung will be more diversified, ultimately encouraging employment within the district.

2.2                         Consideration of Scenario Without the Proposed Development

2.2.1.1           As discussed in Section 2.1.4, the 3 stages of PE exercises conducted for this study have provided an effective platform to exchange views and opinions between the stakeholders and the Project Proponent. The PE exercises have revealed a number of aspirations from the local communities that would require extra land for development and a summary of these aspirations is given below.


 

Table 2.1   Summary of aspirations for local communities

Aspirations

Benefits to the Local Communities

Qty[1]

Sport ground

Currently, there is a sports centre located at Man Tung Road.  A lot of public comments raise request for a sports ground in Tung Chung to address local demand for multi-sports facilities.  A sports ground which can accommodate more than 10,000 persons has been allowed for in TCE.

3ha

Post-secondary institution

The post-secondary institution in TCE could provide specific training for local people to meet job requirements and opportunities available in the area.

2.5ha

Comprehensive cycling network

The cycle track network can improve the connectivity and cater for the needs of local residents and tourists in Tung Chung.

12km

Other GIC such as wet market, flea market, cultural heritage items etc.

The wet markets will be provided within subsidised housing estate in future development run by Housing Authority while flea markets can be provided within the open space area on application to the Leisure and Cultural Services Department (LCSD). Existing temples and cultural heritage will be preserved in the extension area to pay respect to cultural heritage.

-

[1] Quantity as incorporated in latest RODP.

2.2.1.2           It can be seen from the above table that all the above public aspirations on sports ground, post-secondary institution and some Government, Institution or Community (GIC) facilities would require an extra total land of about 16.5ha in TCE, and a total of about 12km long cycle track (including 8.3km in TCE, 1.2km for Road P1 and 2.8km in TCW).  This extra land obviously cannot be made available for the benefits of the public without the proposed developments in TCE and TCW.  If the proposed development is not implemented, all these public aspirations, together with the needs for housing supply in HK, could not be addressed properly.

2.3                         Consideration of Different Development Options

2.3.1                  Applications for EIA Study Briefs

2.3.1.1           As discussed in Sections 1.1 and 1.3, a total of 3 Project Profiles have been submitted to EPD in July 2012, December 2014 and March 2015 respectively for application of EIA SBs. A summary table listing their respective details and key elements presented in the EIA SBs is shown in Table 2.2 and their respective locations are shown in Figure 2.1a to Figure 2.1c.


Table 2.2       Summary of EIA SB applications

No.

PP No

EIA SB No.

Date of Issue

Key Elements Described in the respective PP and EIA SB

1

PP-470/2012

ESB-251/2012

28 Aug 2012

·   A total development area of about 285 ha (110 ha for TCE PDA and 175 ha for TCW PDA);

·   A total reclamation area of about 160 ha (110 ha for TCE PDA and 50 ha for TCW PDA); and

·   A possible theme park/ major recreational uses of about 40 ha at TCE PDA

2

PP-519/2014

ESB-283/2014

28 Jan 2015

·   Reclamation of 120 hectare of land for formation of TCE;

·   Reclamation of 9 hectare of land for extension of Road P1 from Tung Chung to Tai Ho;

·   Construction of District Distributor roads and sewage pumping stations with capacity more than 2,000m3/day within PDAs (locations to be confirmed);

·   Upgrading of the existing Chung Mun Road sewage pumping station from the existing capacity of about 3,500 m3/day to a proposed capacity of over 4,500 m3/day and a few sections of the existing rising mains/sewers close to the PDA at TCW;

·   Construction of a marina with about 95 berths at the PDA at TCE;

·   Construction of an outdoor sporting facility with a capacity of over 10,000 persons;

·   Construction of two possible Mass Transit Railway stations, with one at TCE and the other one at TCW;

·   Construction of a petrol filling station with an area of about 800m2;

·   Construction of two service reservoirs, including one for fresh water and the other for flushing water, with capacities of 55,000 m3 and 11,000 m3 respectively;

·   Construction of about 4 km long of dual rising mains at TCE connecting a proposed sewage pumping station within the PDA at TCE to the existing Siu Ho Wan (SHW) Sewage Treatment Works (STW); while the upgrading works required for the existing SHW STW will not be undertaken in this Project;

·   Possible waterfront promenade at the coastal area of proposed Town Park;

·   De-channelization of the existing channelized section of Tung Chung Stream for amenity uses and environmental enhancement (e.g. river park); and

·   Possible amenity uses and environmental enhancement (e.g. river park) in the land adjacent to the immediate upstream of the channelized section of Tung Chung Stream to Shek Mun Kap.

3

PP-523/2015

ESB-285/2015

17 Apr 2015

·   Key elements as listed in ESB-283/2014 except the construction of two possible Mass Transit Railway stations, with one at TCE and the other one at TCW as it will be conducted by future railway operator

·   Construction of a comprehensive network of cycle track of 12km long along the proposed distributor roads, waterfront promenade, walkways and along future Road P1 from Tung Chung to Tai Ho;

·   Construction of a possible cycle park with an area of about 1.4ha to be surrounded by slip roads connecting the future Tai Ho Interchange to integrate with the cycle tracks in TCE;

·   Construction of a sustainable urban drainage system within TCW which may comprise polders, dual-purpose stormwater attenuation and treatment ponds (locations and extent to be confirmed);

·   Construction of a village sewerage system for the unsewered villages within TCW (location and extent of the sewerage to be confirmed); and

·   Space provision of facilities for suitable green initiatives such as regional energy efficiency system and environmentally friendly systems (such as electric buses, electric cars and bicycle sharing system).

 


2.3.1.2           However, as mentioned in Section 1.1, the Project Proponent has been proactively conducting a series of public engagement exercises (including forums and workshops) to collate views and opinions from stakeholders, green groups and local communities etc. In parallel to the PE exercises, the planning and engineering designs of the Project have also been progressing and evolving to address various constraints and development needs as well as the comments collated in public engagement exercises. Major environmental related public comments and corresponding solutions are summarised in subsequent sections.

2.3.2                  Consideration of Public Comments

2.3.2.1           As mentioned in Section 2.1.4, a total of 3 PE Stages have been conducted to collate the views from various stakeholders and the comments received cover a wide range of issues.  The following table summarises the dates and key objectives of the 3 stages of PE conducted.

Table 2.3    Key objectives of the 3 stages of PE conducted

Stage

Date

Key Objectives

Stage 1 PE

12 Jun 2012 to 12 Aug 2012

·       Outline the key constraints on environmental, planning and engineering aspects

·       Gather public views through discussions on issues, opportunities and constraints which form the basis for preparing the initial land use options formulated under Stage 2 PE for consultation

Stage 2 PE

21 May 2013 to 21 Jul 2013

·       Present the initial land use options for TCE and TCW for discussion after consideration of public views collected in Stage 1 PE

·       Gather views to formulate the draft RODP for further public consultation in PE3

Stage 3 PE

15 Aug 2014 to 31 Oct 2014

·       Present the draft RODP which has incorporated the comments on the initial land use options received during Stage 2 PE

Summary of Stage 1 PE

2.3.2.2           Roving exhibitions at four locations in Tung Chung, 7 numbers of briefing sessions with concern groups and advisory bodies, a public forum and a questionnaire survey had been conducted during the Stage 1 PE which commenced in June 2012 and completed in August 2012.  Over 2,300 written submissions were also received. The key purposes of the Stage 1 PE were to present the resources and constraints in further developing Tung Chung, and to invite stakeholders to offer their views on the further development of Tung Chung.  It was basically an envisioning process and no land use options were presented for discussion.  Key views collated during this Stage 1 PE are summarised in Table 2.4 below.


Table 2.4       Summary of key comments and approaches adopted to address comments collated in Stage 1 PE

Elements

Key Comments

Responses

Development Needs

·       It was generally agreed that there is a need and potential for further development in Tung Chung.

·       Transportation, community/ recreational facilities and job/ business opportunities were considered as high priorities than the other areas of development.

·       There were queries on the necessity and feasibility of achieving the target population.

·       Comments and suggestions on transportation, community/ recreational facilities, job/ business opportunities and the other development areas would be considered and take into account where appropriate in formulating various development themes and land use options.

·       Accommodation of the additional population in Tung Chung PDAs by considering the development opportunities and constraints would be further explored.

Planning Vision

·       There was broad consensus for a balanced development of Tung Chung in terms of development intensity, environmental protection and social needs.

·       There were views suggesting Tung Chung to be developed into a tourist and recreational hub.

·       Balanced, tourism and recreational developments would be incorporated in the development options for further discussion at Stage 2 PE where appropriate.

Land Supply and Demand

·       There was a general preference for developing fallow agricultural land over reclamation to increase land supply in Tung Chung West. Reclamation in Tung Chung West, particularly in Tung Chung Bay, was strongly opposed due to its high ecological, cultural and historical values. There was no major objection to reclamation in Tung Chung East.

·       Resumption of land for reselling to private developers was strongly opposed.

·       Development options with proposed reclamation extent would be formulated to address issues concerning development pressure, ecological conservation and cultural and historical preservation for further public consultation.

·       The need for land resumption will be carefully considered by relevant government departments.

Housing Supply and Mix

·       There was a general understanding that higher population and more housing developments in Tung Chung would lead to more community and recreational facilities, facilitate local economic development and consequently improve the living standard of the residents.

·       A balanced mix of public and private housing was demanded for community coherence.

·       Public preference on housing mix would be taken into account in formulating the development options for residential development in the PDAs to meet the public aspiration for a coherent and harmonious community.

Transportation Network

·       It was generally agreed to improve the external connectivity of Tung Chung with the other parts of Hong Kong and better internal connectivity of Tung Chug with TCE, TCW and the villages.

·       Additional MTR station in TCW to serve Yat Tung Estate and the future population was requested.

·       More transport types and services were suggested to reduce transportation cost and to support the population growth of Tung Chung.

·       Better connectivity of Tung Chung with the other parts of Hong Kong as well as within Tung Chung would be taken into consideration in planning vehicular and pedestrian links in various development options.

·       Provision of new MTR stations would be explored with relevant government departments and the MTR.

Community Facilities

·       More and fairer distribution of community and recreational facilities, particularly hospitals, medical care facilities, sports grounds and wet markets in TCE and TCW was requested.

·       It was suggested to develop resorts/ hotels/ villas and eco-tourist facilities such as ecological parks and organic farms.

·       The Tritons Triathlon Club requested on improvement and extension of the existing cycle tracks to Sunny Bay.

·       Suggestions on types and distribution of various community facilities would be carefully considered in formulating the development schemes for a balanced and sustainable community.

·       The feasibility of improving the existing cycle tracks within the vicinity of the Project would be examined.

Ecology and Environment

·       There were grave concerns about the possible adverse impacts of development on the ecology and the environment of Tung Chung Stream and Tung Chung Bay.

·       It was suggested to promote eco-tourism and environmental education in TCW.

·       There were concerns about traffic noise caused by roads, e.g. the North Lantau Highway and by transport facilities e.g. the Airport Express to the residents.

·       The possible impact on ecologically sensitive areas and on the environment such as on air quality and residential dwellings would be critically assessed and minimised in the EIA. Areas proven to be ecologically sensitive would be protected against undue influence/ disturbance.

Cultural Heritage

·       It was agreed to preserve the declared monuments, graded historical buildings and rural villages for their educational and tourism purposes.

·       Ma Wan Chung was proposed for preservation and revitalisation. The existing fishing village was proposed to be developed into a Fisherman’s Wharf.

·       Preservation of the Prajna Dhyana Temple at Shek Mun Kap was requested.

·       Prajna Dhyana Temple, other declared monuments and places of high cultural heritage values such as Ma Wan Chung Fishing Village would be preserved in the development options.

Economic Development

·       Theme park development is preferred to increase job and business opportunities for local residents.

·       Promotion of commercial and tourism uses with the development, e.g. hotel/ resort centres, water sports centres, flea markets, marina and fisherman’s wharf was suggested.

·       Provision of local employment and business opportunities and the possibility of tourism development would be examined in formulating the various development options.

 

 


 

2.3.2.3           Views and suggestions received in Stage 1 PE served as an important basis for formulating the initial land use options that were promulgated for public discussion and comments under the Stage 2 PE.

Summary of Stage 2 PE

2.3.2.4           All the comments collated during Stage 1 PE were duly considered and where appropriate incorporated into the development of initial land use options, which were put forward to consultation in Stage 2 PE.  Similar to the Stage 1 PE, a series of events of different types had been conducted. Roving exhibitions at four locations, a community workshop, a public forum, 17 numbers of focus group meetings, and meetings with statutory advisory bodies had been conducted during the Stage 2 PE which commenced in May 2013 and completed in July 2013.  A total of 3,099 submissions were received through various channels.  The key purposes of the Stage 2 PE were to present the initial land use options and to invite stakeholders to offer their specific views on them. Key views collated during this Stage 2 PE are summarised below. 



Table 2.5       Summary of key comments and approaches adopted to address comments collated in Stage 2 PE

Elements

Key Comments

Responses

Development Needs and Planning

·       It was generally agreed to proceed with the further development in Tung Chung to revitalise the local economy and to stimulate economic growth, despite firstly to address the existing problems in Tung Chung (e.g. lack of good connectivity, community facilities, job opportunities, etc.).

·       There were requests from the public for sustainable development of the Tung Chung expansion under a holistic approach, better integration of the East and West, capitalisation on the geographic bridgehead location of Tung Chung and reinvigoration of the economic vibrancy of Tung Chung.

·       Besides housing development, Tung Chung extension should also focus on commercial and tourism growth.

·       The public agreed on the need for a balanced housing mix.

·       The public urged for a better building design and avoidance of any possible “wall-effect” residential development especially along the coastal area. The key stepped building design, view corridor inclusions were largely supported and welcomed.

·       The population targets should be reviewed in order not to overload the carrying capacity of the existing infrastructure.

·       The public’s request for sustainable development matched with the planning and design principles for the Initial Options and the Preferred Option.

·       The draft RODP will maintain a strong and diversified commercial component and will take into account the opportunities brought by the bridgehead economy and complimentary development proposals around.

·       The draft RODP will ensure the provision and distributions of community facilities are well designed; with a housing ratio in-line with policy direction, and adopting a socially inclusive and human-scale design in the Preferred Option.

·       The proposed 14ha reclamation in Tung Chung West, has been abandoned; the ecologically-sensitive areas of Tung Chung Valley, Tung Chung Bay, Tai Ho etc. has been carefully planned and be the key areas of concern in the preparation of the Preferred Option.

·       To provide a balanced land use provision in the PDAs, less than 40% of the proposed land use will be for residential purpose. The remaining will be used for open space, conservation related use, G/IC use, commercial use, existing village, roads and utilities etc.

·       A total of about 853,000m2 commercial Gross Floor Area (GFA) has been proposed with office, retail and hotel component to ensure economic vibrancy and capture the opportunities with surrounding developments.

·       The draft RODP has taken into account the latest direction recommended by the Long Term Housing Strategy for a 60:40 housing mix for the PDAs to cater for the territorial need regarding the public to private housing mix.

·       Urban design principles raised by public are in-line with that for the draft RODP. Stepping height from inland towards waterfront will be maintained.

·       Reference has been made according to the latest Sustainable Building Design Guidelines and Urban Design Guidelines in the preparation of draft RODP to avoid “wall effect” developments along the coastal area as far as possible. Quality design would be pursued in order to achieve a pleasant townscape.

·       The future capacity of infrastructures has been reviewed and it would be able to support future population increase.

Tung Chung East

·       Majority of stakeholders support the proposed development on the Tung Chung East reclamation area, and the high-density development near the core area or around the transportation hubs.

·       Stakeholders’ concerns included environmental impact during construction, visual impact of the new development on reclaimed area, impact on ecology in Tai Ho Inlet, cumulative impact on marine ecology and Chinese White Dolphin, narrowing of the navigation channel, impact on water flow near Tai Ho Inlet, etc. There was also suggestions to reduce the extent of reclamation in Tung Chung East.

·       There are diverse views on the need, scale and location of the marina proposed. Most stakeholders believed that marina development would only benefit the affluent minority while others considered that marina could enhance the economy of Tung Chung and make Tung Chung a more interesting recreation and tourism destination.

·       The draft RODP would adopt a transit-oriented development approach for high-density development proposed to be within the catchment area of the TCE MTR Station to maximise convenience provided by public transport. A Public Transport Interchange is also proposed near the Station to further enhance the role as a transportation hub at the Metro Core.

·       The establishment of reclamation in TCE is supported by technical assessments, and has already taken into account various public concerns such as marine ecology, Chinese White Dolphin etc. Environmental concerns will be carefully assessed and countered with mitigation measures, if necessary, in the EIA process.

·       Visual impact will be avoided by designation of planning and design measures such as visual corridors and other special requirements for areas with interface with existing development in Tung Chung.

·       Given some public concern on the potential impact for the proposed marina to the Tai Ho Inlet, the marina is proposed to be relocated from the eastern-end of the TCE reclamation to the northern-tip of the reclamation. The scale of the marina has also been reduced from 350 boats to 95 boats.

·       It has been confirmed that the proposed location of marina on the draft RODP will not affect the navigation channel to the north of the TCE reclamation. The proposed marina and its clubhouse facilities would be incorporated into the design of the waterfront promenade and the waterfront park, as well as to synergise with the adjacent retail and hotel facilities to form a vibrant commercial hub at this northern part of TCE.

Tung Chung West

·       Majority of the public opposed the proposed reclamation in TCW.

·       The public were concerned about the adverse ecological impact on nearby Tung Chung Bay and the impact of water flow which would deteriorate the current odour problem near Ma Wan Chung by the proposed reclamation.

·       Private housing development near Tung Chung Town Park was objected.

·       The public generally supported the revitalisation of Ma Wan Chung village.

·       For the Tung Chung Valley, there are conflicting views towards its future development in that the local villagers and land owners would like to have more development opportunities whilst green groups, religious practitioner/operator and individual members of the public prefer to maintain the existing rural and countryside setting of the valley. Nevertheless, majority of the public generally agree on the need for a balanced housing mix in TCW.

·       Coral Ching Limited, villagers, Island District Council and some other stakeholders suggested the government to explore and develop all available fallow agricultural land instead of carrying out reclamation for more developable land.

·       There are mixed views on the future plot ratio for TCW development.

·       The Buddhist Navigation Vihara proposed to develop TCW into a new recreational tourist spots under the theme with Buddhism characteristics, and zone the area around Prajna Dhyana Temple as G/IC and to retain the existing view from the temple. They also had plans to provide community services such as elderly care and to promote organic farming.

·       Green Groups were concerned that the areas with high ecological values would be adversely affected by the human activities arising from nearby developments and urged for preservation of the important ecological assets including Tung Chung Stream, Tung Chung Bay etc.

·       The draft RODP abandoned the 14ha reclamation in TCW in response to the public objections.

·       Infrastructural support would be provided to facilitate Ma Wan Chung village revitalisation.

·       The detailed design of the draft RODP has taken into account of the villagers’ comments and the areas having potential for agricultural uses are proposed for designation as “Agriculture” zone.

·       Development in areas with conservation value, landscape value, agricultural potential, and existing village settlements are eliminated; and conservation of precious features would be taken into account when determining the proposed land use and development intensity in Tung Chung Valley.

·       Areas with development potentials in Tung Chung Valley has been further reviewed and has proposed two additional plots of land (total approx. 3ha) to the west of the TC Stream (to the north and south of Nim Yuen) for low-rise development.

·       For development intensity in Tung Chung Valley, development in the areas with conservation value, landscape value, agricultural potential and existing village settlements will be avoided. New developments will take into account the conservation of precious features in the valley.

·       PR6 and PR5 Public Housing Sites have been proposed along Tung Chung Road to maximise the efficiency of TCW MTR station.

·       A re-arrangement of land use around Prajna Dhyana Temple has been in response to comments on development around Prajna Dhyana Temple.

·       Based on the RODP, statutory plan(s) will be prepared to provide planning framework to guide the remaining development in Tung Chung.

Community Facility Provision

·       The public generally considered that the facilities were not evenly distributed in Tung Chung East and West, in particular, the locals pointed out that community facilities in Tung Chung West (e.g. Yat Tung Estate) were seriously lacking.

·       The public requested for a balanced community facilities provisions in both Tung Chung East and Tung Chung West for the youth, the elderly and the ethnic minorities, for more recreation, leisure, civic amenities and all levels of education land uses.

·       There were suggestions on the location of sports ground to be located between TCE and TCW.

·       Educational parties and groups advised additional conventional primary and secondary schools may lead to over-provision of classes. More tertiary education facilities, schools for other uses and school for special needs students could be considered.

·       The draft RODP has carefully examined and proposed an appropriate provision of G/IC facilities, recreation facilities and open space to serve the existing and planned population.

·       Sports centres are planned at centre of population and/or incorporated within the open space network in both TCE and TCW to ensure the highest accessibility for future users.

·       To improve connectivity, the connected waterfront promenade, cycling track and extension of Tung Chung Line could improve the mobility for residents in TCW to other community facilities in the PDAs.

·       Wet markets in Public Housing Sites would be considered / planned by Housing Authority where appropriate in the future development. Flea markets/ night market could be provided within the existing/ planned open space in PDAs on application to LCSD.

·       Land has been reserved for GIC facilities (one in TCE and one in TCW) such as social welfare facilities or other community / government facilities and services, if necessary.

·       Policy support from relevant bureaux would be required for the demand religious facilities. Other community facilities such as library, G/IC facilities for youth and elderly etc. have made reference to the Hong Kong Planning Standards and Guidelines (HKPSG) standards and confirmation with relevant government departments on the special requirement relative to Tung Chung’s context.

·       The draft RODP has paid particular attention to encourage local shops by careful planning and design.

·       Regarding education facilities, the provision of primary and secondary school facilities have been reviewed based on the latest information from the Education Bureau. Land for tertiary institutes and other school uses has also been reserved in the draft RODP.

Traffic and Transportation

·       There was acute need to upgrade the transportation and connectivity within the new town and to better connect with other parts of Hong Kong. The sole reliance on rail development would not be adequate.

·       Residents of the existing villages claimed that the existing road connection between the village areas and to Tung Chung town was generally insufficient, and strongly requested for well-planned local transportation system for better connectivity.

·       It was suggested to provide cycling path to connect all areas within Tung Chung.

·       The public were concerned about the existing rail and road capacity might not be sufficient to cope with the proposed population and requested for detailed capacity study before deciding the target population extension.

·       The Airport Authority Hong Kong (AAHK) recommended investigating the feasibility of a spur line allowing an airport shuttle train service to be run between Tung Chung East and Hong Kong International Airport Station via the existing Airport Express Line.

·       There were other public suggestions such as considering implementation of electrification of the transportation system and green-road infrastructures to connect to the tourist facilities to develop Tung Chung into a green city for sustainable living and transportation, making use of the seven existing piers, developing a monorail system to improve the connectivity between Tung Chung and other parts in Hong Kong, etc.

·       Traffic assessment has been conducted which indicates that the future rail and road capacity is sufficient to cope with the proposed increase in population.

·       The draft RODP has taken into account the public comments to provide rural roads to connect the various existing villages within TC Valley, to enhance the convenience and safety of local residents.

·       The draft RODP has proposed a comprehensive cycling network within whole Tung Chung.

·       Liaison with Airport Authority Hong Kong (AAHK) would be continued on their latest development proposal on the North Commercial District (NCD) on the airport island and the shuttle train service via the Airport Express Line would be considered by the relevant bureau/departments on its feasibility.

·       Various green initiatives, e.g. green linear park with cycling track connection, central park etc. has been considered in the development plan. The existing pier within Tung Chung will also be maintained.

·       To encourage the use of railway as the key development principle for transit-oriented development, the draft RODP has been formulated with high density clustered near to the proposed railway stations. Residents further away from railway station would be well-connected by linear parks extending from the metro-core area penetrating to the rest of the reclamation in TCE. The entire PDAs would be well-served by a well-planned public transport system (and PTIs) and cycle track to ensure mobility.

·       Monorail system is not proposed since it will take up much land space, impose possible noise nuisance and possibly sterilize land around the alignment for residential purpose, which violate the key intentions of the Project which is to optimize land for providing residential unit and commercial space to serve the development need in the territory.

Environment

·       The majority of the public agreed on the preservation of the natural environment and protection of the high ecological value areas in TCW.

·       The public urged for the conservation of Tung Chung Stream (including the channelized section) and Tung Chung Bay, as the areas are regarded by the public as sites of high ecological value.

·       The conservation boundary was commented as not large enough.

·       Majority of the public opposed the reclamation in TCW, since they were concerned about the reclamation and subsequent development would cause adverse impact on water and air quality.

·       Green Groups expressed their concern about the impact on Chinese White Dolphins due to reclamation works, especially the cumulative effects with the on-going reclamation works on the marine life and their habitats. The Conservancy Association demanded for a comprehensive report on the cumulative impacts on marine habitat by all concurrent projects.

·       The draft RODP has been refined with consideration on conservation of the natural environment and high ecological value features in TCW. Most of the conservation features, such as a Conservation Area (CA) zone along the river channel, Green Belt (GB) for more mature woodland areas would be retained.

·       Ecological surveys in the TCW has been updated throughout the Project in refining the important areas for conservation for refinement of the draft RODP, in particular, the proposed GB zone in the Fong Yuen area has been proposed to be enlarged southwards to protect the living habitat of the rare butterfly species. In addition, a comprehensive EIA Study has been conducted in parallel in confirming/ detailing the conservation boundaries for the PDAs and to ensure the impact of the development could satisfy the corresponding statutory criteria, such as air quality, noise, water quality, ecology, etc.

·       The 14ha reclamation in TCW has been removed having considered the green concern about the ecological sensitivity of coastal area and estuary of Tung Chung Stream.

·       Based on Agriculture, Fisheries and Conservation Department (AFCD) long-term monitoring data of CWD, the proposed reclamation area in Tung Chung was outside the habitat for CWD.

·       The government has commissioned a separate consultancy to assess the cumulative impact of several potential developments in western waters on various key aspects including the CWD

Cultural Heritage

·       It is strongly agreed that preservation of the local cultural heritage such as Hau Wong Temple, Tung Chung Fort, Tung Chung Battery and the local villages would be essential. There were suggestions on incorporation of these assets as part of a cultural tourism programme or within a wider tourism plan. In particular, revitalisation of Ma Wan Chung Village was suggested.

·       The initial land use options presented in PE2 were consistent with public aspirations towards preservation of local cultural heritage in Tung Chung. Future development would respect and would not affect existing heritage features such as Hau Wong Temple, Tung Chung Fort, Tung Chung Battery, as well as Fu Tei Wan Kiln, Tung Chung Game Board Carving on the town park hill etc. Consideration has been made to ensure compatibility of future development with these heritage features, e.g. view corridors would be retained in front of cultural heritages such as Hau Wong Temple, Tung Chung Battery, Shek Mun Kap Entrance Gate etc.

·       Development intensity of future development has been carefully considered to ensure harmony with the character of rural villages in the Tung Chung Valley.

·       The potential for enhancing connectivity of these heritage features, which is integral to the character of Tung Chung, and the integration with the proposed cycling network would be studied.

·       Infrastructural support would be proposed to facilitate Ma Wan Chung Village revitalisation.

Tourism Development

·       The public agreed that Tung Chung has great potential in developing tourism which could bring enormous economic benefits and create ample opportunities for both Tung Chung and Hong Kong. More facilities such as hotels, commercial premises and shopping malls would needed to facilitate tourism development.

·       Connectivity in Tung Chung should be enhanced to cope with the future visitors in the area.

·       The draft RODP would retain a major office node with retail components within the PDAs, which could complement the latest development proposals for hotel and retail developments in the North Commercial District on the Airport Island and potential retail facilities on the HKBCF. The proposed marina and adjacent commercial uses at the northern tip of the TCE reclamation would also create other tourism attractions and a vibrant hub for Tung Chung.

·       Opportunities for leisure tours/ eco-toursim has been considered in the draft RODP given the unique character of TCW area which possessed a rich and diversified natural/ scenic/ cultural assets.

·       Together with the intention for a comprehensive cycling network and generously designed linear open space network in Tung Chung, it is intended to link up these various tourism features within the PDAs with the exiting tourism facilities (such as Citygate Mall, the Ngong Ping Cable car) to further consolidate Tung Chung’s tourism role in North Lantau.

Job Opportunities and Local Economy

·       It has been suggested that Tung Chung has significant locational advantage due to close proximity to various future major infrastructure developments, and should be developed as a Bridgehead Economic Zone to capture this opportunity and improve local economy.

·       The public has opined that Tung Chung has great potential of developing into a business centre, the MICE market and this could be well integrated with the development of HZMB and HKIA.

·       Connectivity in Tung Chung should be enhanced so as to cope with the future HZMB and the exhibition visitors in the area.

·       The public pointed out that many Tung Chung residents were unemployed due to mis-match in the skillsets needed in the area. The public called for more diverse job opportunities in Tung Chung that could match the local skillsets.

·       Having reviewed the latest developments / proposals in Lantau, a diversified commercial provision in the PDAs has been maintained, which could respond to public comments regarding the provision of additional job opportunities in terms of quantity and diversity.

·       In the draft RODP, more focus would be put on the provision of office component to form a “major office node” in Tung Chung (500,000m2 GFA). A regional retail component (155,000m2 GFA) that is complimentary to surrounding retail proposals such as North Commercial District (NCD) and the potential retail development on the HKBCF island; as well as the same provision of a 1000-room hotel (50,000m2 GFA) in the PDAs would be maintained.  With the operation of the Third Runway of the HKIA, together with several other developments being constructed or planned in North Lantau, the job diversity in the wider area is anticipated to be increased.

·       Together with the provision of various local retail activities to serve the residents, future job provision from the PDAs is estimated to be more than 40,000.

·       Regarding the concerns on mis-match of skillsets, educational areas for territory institutes and other school uses have been proposed that could provide the opportunity for vocational / tertiary training that is specialised for the employment opportunities in the area.

 

 


2.3.2.6           The Study team analysed and evaluated all comments received during PE2 and formulated a draft RODP for the Project. The draft RODP had been promulgated for further discussion and comments under PE3.

Summary of Stage 3 PE

2.3.2.7           All the comments and opinions collated during Stage 2 PE were duly considered and where appropriate incorporated into the formulation of draft RODP which was put forward for consultant in Stage 3 PE. Roving exhibitions at seven locations, physical model displays at five locations, a public forum and 25 numbers of focus group meetings were held. Consultation with statutory advisory bodies including the Islands District Council, Town Planning Board, Planning Sub-Committee of the Land and Development Advisory Committee and Airport Authority Hong Kong were also held, and an information centre had been set up to provide information to the public during the Stage 3 PE which commenced in August 2014 and completed in October 2014. A total of 4,086 public submissions were received through various means, including individual submissions, standard submissions and signature campaigns. The key purposes of the Stage 3 PE were to present the draft RODP that had incorporated the comments collated from Stage 2 PE as appropriate, and invite further comments from the stakeholders. A summary of the key comments received and the approaches adopted to address those comments are summarised in Table 2.6.


 


Table 2.6       Summary of key comments and approaches adopted to address comments collated in Stage 3 PE

Elements

Key Comments

Approaches Adopted to Address Comments

Land Uses

General

·       The proposed land uses should balance the specific needs of the residents in each area, while avoiding conflicting land uses between daily living purposes and tourism development.

·       A stakeholder proposed an extension of the covered walkway linking Tung Chung Centre and Tung Chung North to other new development area.  They suggested that the waterfront area could be used for commercial, recreational, cultural and educational purposes, and that public access to waterfront events should be encouraged. The organisation also suggested having more diversified forms of open space.

·       During the PE3 Public Forum, the Expert Panel expressed their concerns of maintaining a balance between the development of different land uses and aspects of the community. They also expressed the importance of resolving conflicts between different land uses in the planning process.

·       Provision of open space and government, institution or community (GIC) facilities in the RODP has been designed in accordance with HKPSG and taking into account valuable comments received in PE3. The proposed waterfront promenade in the RODP concurs with some public comments requesting a linkage between the existing TCNT and the PNTEAs. In particular, some residential plots along the DO are required for street-facing shop fronts and certain area near waterfront (in both TCE and TCW) are provided with commercial facilities to encourage activities and vibrancy and allow the area to become a focal point for residential activities in the future.  

·       Pedestrian networks and linear parks have also been designed to encourage public access to the waterfront.

Tung Chung Town Centre

·       NGO/ local community groups suggested Area 1, 2, 3 should be used as transport terminals and parking areas for coaches, and Area 52 as public leisure space.

·       A stakeholder objected to the proposed change of land use from District Open Space and Education to Residential (Group A) site, and said Area 29 should be best used as a town park for public enjoyment. Both Lotlink Development Ltd. and Full Fame Development Limited opposed to the residential development on Area 29 due to its natural hilly terrain, and opined that since Area 23 was a suitable site for high-density development, therefore the change of land use to District Open Space and Education was not justified.

·       Comments relating to existing Tung Chung Town Centre have been conveyed to the relevant department for considerations.

·       Land use review on the draft RODP has been carried out with respect of public and relevant government departmental comments as well as planning and engineering considerations. Residential uses with various density and stepped building height have been have been incorporated.

Tung Chung East

·       NGO/ local community groups suggested having more leisure spaces with local characteristics in Tung Chung East and opined that the education land use should be more balanced within Tung Chung East, while suggesting a review on the location and scale of the proposed education land use and nearby road network. The organisation also opined that the underground area of Tung Chung East could be better utilised.

·       Stakeholders in general supported the RODP for Tung Chung East, which utilised the concept of transport-oriented development.

·       Provision of open space and design of the road network have been designated on the RODP in accordance with HKPSG, and taking into account valuable comments received in PE3. The RODP has also reviewed the provision of education land use with consultation of the Education Bureau, the provision of primary schools and secondary schools has been revised and six primary and two secondary schools are reserved in RODP.  Besides, in our RODP, we have also assumed an efficient use of underground area of TCE and TCW by assuming car-parks serving the residential and commercial uses of the PNTEAs to be placed at underground to reduce building bulk and enhance ventilation.

·       Regarding the possible overlapping issue with current OZP for part of the north-eastern area of Tung Chung, the Study Team has reviewed the overlapped area of the existing TC OZP and our revised RODP and proposed an appropriate zoning that meets the latest need.

Tung Chung West

·       Varied comments were received in regard to the land uses in Tung Chung West. The revised land uses near Prajna Dhyana Temple in Shek Mun Kap was generally appreciated. For the proposed land uses in Tung Chung West, most comments were related to the designation of areas for conservation, such as GB or CA zonings. 

·       In principle, the land uses (e.g. residential, GIC, CA, CPA, GB, etc.) in TCW in the RODP are proposed and taken into consideration of various factors, including urban planning, local demand for housing/infrastructure/facilities, existing sensitive natural environment, findings of ecological survey, environmental impact, comments received from various stages of public engagement activities, etc. The proposal aims to strike a balance between these various aspects.

·       NGO/ local community groups suggested zoning parts of Tung Chung west, (e.g. fung shui woods) as Conservation Area/ GB; suggested designating the two areas on the bank of the Tung Chung Stream near Fong Yuen and Shek Mun Kap as conservation area and GB to protect the natural environment and the habitats for butterflies.

·        However, NGO/ local community groups also objected to designating GB and Conservation Area zonings on the bank of Tung Chung Stream, especially for the village area in Tung Chung West around Lam Che and Nim Yuen. The Committee suggested changing the land use of the two places around Lam Che and Nim Yuen from GB and R4 site to “Government, Institution or Communities”. Some villagers requested that suitable compensation should be paid if private land was to be zoned for conservation purpose.

·       In principle, the land uses (e.g. residential, GIC, CA, CPA, GB, etc.) in TCW in the RODP are proposed and taken into consideration of various factors, including urban planning, local demand for housing/infrastructure/facilities, existing sensitive natural environment, findings of ecological survey, environmental impact, comments received the various stages of public engagement activities, etc. The proposal aims to strike a balance between these various aspects. Appropriate conservation and protection considerations have been included in the proposed zonings of the RODP (e.g. CA, CPA, GB etc). Some area north of Ngau Au Village, which was proposed as “GB” in the draft RODP will be revised to low-rise residential use (“R4” zone, PR1) to optimize land of comparatively lower ecological value for an acceptable degree of development in the Tung Chung Valley. This additional residential site in the TC Valley is proposed to maintain a low development intensity to maximize compatibility with the surrounding context.

·       The existing use of the land or the agricultural use would not be affected by the conservation related uses.

·       There were different opinions on whether the fung shui woods in Tung Chung west should be zoned as GB or Conservation Area, and NGO/ local community groups pointed out that there should be consistency in this regard. Concern was also raised about private land being zoned for conservation, and suggested designating it as a park managed by the Leisure and Cultural Services Department (LCSD) under the Pleasure Ground Ordinance and a park managed by the Agriculture, Fisheries and Conservation Department (AFCD) under the Country Park Ordinance, or as land swap or resumption with compensation.

·       NGO/ local community groups requested the designation of R3 site near Shek Mun Kap as Natural Park.

·       There was also opinion regarding emphasis on both village type development and environmental conservation in the development of Tung Chung West.

·       Specific comments on land uses were also received from different organisations and villages. In this regards, NGO/ local community groups considered that abandoned farmlands should be used as green spaces or for community and residential purposes.

·       For rural development, Wong Nai Uk village requested for expansion of the “Village Type Development” (“V”) zone to meet their future small house demand.

·       Mok Ka Village opposed to any development carried out in the village and suggested moving the R3 development near the village eastward, adding that the agricultural area should also be maintained. They criticised that the village boundary shown in the map was incorrect, and suggested extending the boundary for future rural development.

·       NGO/ local community groups expressed grave concern on the future use of the piece of land in front of Hau Wong Temple. They advised that the land should be used for traditional festival celebrations and/or religious functions. The organisation also suggested changing the land use of the two places around Lam Che and Nim Yuen from GB and R4 site to GIC land use.

·       A stakeholder suggested removing the non-building area in Tung Chung West, and rezoning the two plots of R4 land near the Tung Chung West MTR Station as R3 with an aim to maximising the development potential in Tung Chung Valley, and changing the proposed zoning of the western side of the estuary of Tung Chung Stream from GB to Government, Institution or Communities or recreational use.

·       A private sector opposed the proposal to designate the surrounding area of Nim Yuen Village as GB as it acted against the villagers’ will and development plans.

·       A private sector suggested a revised planning of the neighbourhood of Tung Chung West MTR Station, which involved the designation of an OU (Mixed use) zoning and a civic centre with the application of TOD to create a vibrant district centre.

·       Regarding the proposal of setting up a Nature Park on the proposed “R3” site north of Shek Mun Kap, it is considered that R3 site is an area with a relatively lower ecological value and it is one of the limited available flat land in Tung Chung West suitable for residential development, and therefore retaining it as “R3” is appropriate.

·       In response to the comments about the zoning for the fung shui wood, the zoning designated on the RODP is based on ecological survey results. Moreover, the proposed “GB” and “CA” zone along the TC Stream is based on the findings of ecological survey and consultation with the relevant Government department and is considered appropriate and therefore retained on the RODP.

·       Regarding the public comment to change the land use around Lam Che and Nim Yuen from “GB” and “R4” to G/IC uses, the “R4” site is one of the limited available land in Tung Chung West that is suitable for residential development and there are no other solid proposals for what type of G/IC facilities to be developed at the location, therefore it is considered appropriate to retain the proposed zoning as in the draft RODP. Area around Nim Yuen and Lam Che mainly consists of fung shui woods, shrubland and grassland, and therefore it is considered that the “GB” zone should be retained for conservation purpose.

·       Regarding the suggestion for a civic centre/ art venue near the TCW station along the waterfront, it is understood that a civic centre/ art venue/ town hall has already been planned in Tung Chung Area 1 (near the existing TC Station).  Nevertheless, in the RODP, with the removal of 1 sports centre near the TCW station (taking into account the planned IRC near Area 39), the area north of the “R3” Site west of Yat Tung will be converted to a larger “DO” with a view towards the Tung Chung Bay. It is intended that the design of the “DO” should include facilities such as an ampitheatre to create vibrancy and encourage the use of the “DO” for TCW residents.

·       The areas near proposed TCW railway station are carefully planned. By adopting TOD concept, higher density of residential sites and some local commercial uses are located near the proposed TCW railway station. On the other hand, low-density development is maintained nearby the Hau Wong Temple to maximize compatibility. Same as the draft RODP presented in the PE3, there will be no development in front of the Hau Wong Temple so as to maintain an open view and the “DO” area in front of the temple can accommodate the need for holding traditional functions.

·       Apart from the above, some minor refinement has been made to include the entire coastline above high water mark as CPA zone near the Sha Tsui Tau area.

Ecology and Environment

General

·       It was generally agreed that the biodiversity and natural environment of Tung Chung should be preserved. Many expressed the hope that its natural scenery, environment and wildlife habitats could be maintained when considering the proposed future development nearby.

·       NGO/ local community groups urged in their joint submission for a designated Sites of Special Scientific Interest in the areas that are ecologically valuable in Tung Chung West and also opined that the cumulative impact brought by surrounding large-scale infrastructure developments should not be underestimated. They also urged the Government to explain the measures dealing with cumulative environmental impacts arising from nearby projects and the standards of conservation zones proposed in the area.

·       NGO/ local community groups requested both in their respective submissions and the joint submission that Tung Chung West should be covered by Development Permission Area (DPA) Plan to control the human activities and possible environmental disturbance in the area.

·       NGO/ local community groups were concerned about the disturbance on the living environment of ecologically important species due to the development, and opined that valuable natural habitats should be protected.

·       Regarding Construction and Demolition (C&D) waste from future development, NGO/ local community groups opined that land transport of construction materials should be prioritised to minimise marine traffic and they suggested the collection and transportation of C&D wastes should be carried out in appropriate locations.

·       The Recommended Outline Development Plan (RODP) has been formulated based on urban design consideration and taken into account the findings of ecological survey. Appropriate conservation and protection considerations have been included in the proposed zonings of the RODP (e.g. CA, CPA, GB, etc.).

·       Regarding the concern about C&D waste and cumulative impact due to surrounding large-scale infrastructure developments, appropriate construction methods and necessary mitigation measures have been formulated and included in the EIA, which has taken into consideration of the on-going and committed projects to ensure the impacts will be acceptable.

·       Regarding Green Group’s request for a DPA plan, the request was studied and statutory plans would be prepared to provide the statutory framework to guide the remaining development in Tung Chung.

·       A new initiative to implement District Cooling System (DCS) in Tung Chung is being considered.  The way forward is yet to be confirmed.  Should the initiative is to be put forward in future, the DCS will be implemented under separate project subject to further study.

Tung Chung Stream, Tung Chung Bay and surrounding areas

·       There is a general support for the conservation of Tung Chung Stream and Tung Chung Bay, with impact of nearby development to be minimised as much as possible.

·       A group submission by NGO/ local community groups focused on the environmental and ecological impacts brought by the proposed development along Tung Chung Stream and Tung Chung Bay. They urged the Government to further protect the ecology, riverbanks, estuary and the water quality of the Tung Chung Stream and Tung Chung Bay from impacts from nearby residential development. Some suggested that education and scientific research could be conducted in Tung Chung West.

·       In the joint submission, NGO/ local community groups opined that to protect the natural environment of Tung Chung Stream and Tung Chung Stream system, it was necessary to avoid channelisation, civil engineering works and human activities that could pollute the courses and banks of Tung Chung Stream and estuary and the entire Tung Chung Bay. They also requested the de-channelisation/rehabilitation of the channelised parts of Tung Chung Stream, and a careful consideration on any proposed development in Tung Chung Valley in order to protect the habitat in Tung Chung Stream.

·       Proposal from the NGO/ local community groups urged for more refined measures for protecting Tung Chung Stream, particularly around the Sites of Special Scientific Interest along the River, Tung Chung Bay and Wong Lung Hang. De-channelisation/rehabilitation of the channelised parts of Tung Chung Stream was also called for.

·       NGO/ local community groups also suggested de-channelisation/rehabilitation of the channelised parts of Tung Chung Stream, and maintaining sufficient vegetation cover and proper land use planning. They also supported conducing education and scientific research in Tung Chung West.

·       On the measures that could be implemented to protect Tung Chung Stream and the surrounding areas, NGO/ local community groups suggested zoning Tung Chung Stream and the riparian zones as Conservation Area to protect the local ecology and also proposed zoning of an area near Ma Wan Chung (where no zoning was shown in the draft RODP) into CPA zone to protect the mangroves from incompatible development.

·       NGO/ local community groups proposed a conservation along the Tung Chung Stream to protect the local ecosystem and also opined that the riparian zone of Tung Chung Stream could be protected by land resumption. They also pointed out the necessity of having an enhanced protection of the remaining marshes and agricultural areas in Tung Chung Valley, demolishing suspected illegal bridges and having more effective restoration plans and that zoning should be done on the part of the Tung Chung Stream near Shek Lau Po.

·       NGO/ local community groups opined that control of human activities should be exercised in addition to proper protection measures to avoid extinction of specific species.

·       The Recommended Outline Development Plan (RODP) has been formulated based on the findings of ecological survey. Appropriate conservation and protection considerations have been included in the proposed zonings of the development proposal (e.g. CA, CPA, GB, etc.). To further minimize the risk of polluting Tung Chung Stream by nearby human activities, appropriate drainage and sewage system have been designed and provided under the development.

·       The mangrove area near Tung Chung Bay has now been zoned as Coastal Protection Area (CPA) under the RODP.

·       De-channelisation/rehabilitation of the existing channelised sections of Tung Chung Stream is proposed and these sections will form part of the proposed River Park for environmental enhancement, eco-education and recreational use.

Reclamation

·       Deletion of the previously proposed reclamation in TCW during PE2 and preservation of the Tung Chung Stream and Tung Chung Bay were generally supported.

·       While there was no major objection to the proposed reclamation in TCE and Road P1, a private sector opined that the water body between the Airport Island and Tung Chung should be left open to tidal flushing.

·       Some concern groups expressed worries about the potential direct and indirect ecological impact due to reclamation (e.g. construction vessels using the water outside, etc.). In particular, NGO/ local community groups pointed out that the habitats of Chinese White Dolphins would likely be affected by the proposed marina on the reclamation area in Tung Chung East and also the nearby development projects.   

·       Regarding the necessity of reclamation, NGO/ local community groups urged the Government to better utilise the land resources available in the development so that future reclamation projects would not be needed.

·       NGO/ local community groups also strongly urged the Government to further study and explain the cumulative impacts of reclamation and nearby large-scale infrastructure to surrounding areas, such as the proposed Marine Park in the Brother Islands.

·       NGO/ local community groups mentioned in their joint submission that disturbance to Chinese White Dolphins inside the protected area of Brothers Islands Marine Park (BIMP) might be caused by the work barges and vessels from the proposed reclamation in Tung Chung East, reducing the effectiveness of the BIMP. They suggested that marine traffic could be minimised by exploring and prioritising land transport of construction materials.

·       Regarding the concerns such as water flow / water quality and direct / indirect impacts on marine ecology (including the habitats of Chinese White Dolphins) due to reclamation, preliminary environment assessments on the cumulative impact due to surrounding large-scale infrastructure developments, etc.,  have been carried out, which indicated that the impacts should be acceptable. Appropriate construction methods and necessary mitigation measures have been formulated and included in the EIA, which has taken into consideration of the on-going and committed projects to ensure the impacts will be acceptable.

 

Pollution

·       There were concerns on the cumulative impacts on the environment, in particular noise and air pollution, due to increased traffic generated by the proposed developments and large-scale infrastructure projects in the area. These concerns were raised by NGO/ local community groups, who also urged for measures to counter the aforementioned environmental impacts.

·       There were comments on the existing air quality in Tung Chung (in particular the O3 concentration) and that the proposed developments may further worsen the situation. NGO/ local community groups were concerned about the adverse impacts of air quality due to air pollution from the mainland and an excessive level of ozone.

·       NGO/ local community groups commented on the potential impact on air quality from cross-boundary vehicles and nearby infrastructure in the new town and were also concerned about the increased human activities (e.g. surface run-off and sewage from the existing villages) and their possible adverse impact on ecologically sensitive areas in Tung Chung West. 

·       In terms of water pollution, NGO/ local community groups was concerned about the impact from the proposed marina as well as the cumulative impact from nearby development projects, pointing out that the habitats for Chinese White Dolphins would likely be affected.

·       The statutory Environmental Impact Assessment (EIA) had been carried out for the RODP under the EIAO, and necessary mitigation measures had been proposed to ensure the impacts were acceptable. The statutory EIA included individual and cumulative impacts for all key environmental aspects, and had taken into consideration of the proposed construction methods and mitigation measures, on-going and committed projects, etc.

·       To minimize the risk of polluting Tung Chung Stream by nearby human activities, appropriate drainage and sewage system in the form of stormwater attenuation and treatment ponds and multi-stage sedimentation has been proposed under the development.

·       With regard to  the air pollution from mainland and excessive level of ozone, the governments of HKSAR and Guangdong Province had drawn up the Pearl River Delta (PRD) Regional Air Quality Management Plan (the “Management Plan”) in 2003, under which both sides have been pursuing emission reduction measures targeting power plants, motor vehicles and heavily polluting industrial processes. The Special Panel on PRD Air Quality Management and Monitoring was set up to follow up on the tasks under the Management Plan. In November 2012, the two governments endorsed an emission reduction plan for the Pearl River Delta region up to 2020 which includes emission reduction targets for four major air pollutants, namely sulphur dioxide (SO2), nitrogen oxides (NOX), respirable suspended particulates (RSP) and volatile organic compounds (VOC), for 2015 and 2020. Additional emission reduction measures are being implemented on this basis with a view to ensure continuous improvement to the regional air quality. Under the Management Plan, Hong Kong and Guangdong jointly set up the PRD Regional Air Quality Monitoring Network (the Network) in November 2005. Air monitoring results of the Network reflected that efforts of the two sides in implementing various emission reduction measures have been successful over the period from 2006 to 2013. It is anticipated that with the continuous implementation of emission reduction measures, the air pollution problem in the region will continue to be improved.

Drainage and flooding measures

·       NGO/ local community groups called for improvements on the sewerage and drainage in Tung Chung West, as well as improvements on district-level storm water and sewage drainage.

·       NGO/ local community groups suggested the government should formulate a long-term and innovative drainage strategy for Tung Chung West and the resumption of the nearby private lands in Tung Chung Stream Valley.

·       NGO/ local community groups called for the justification on the necessity and effectiveness of the polders for flood prevention, an exploration on alternative measures and a detailed ecological impact assessment. They also called for measures to deal with water pollution and sewage issues, such as discharge of effluents.

·       NGO/ local community groups were also concerned that the proposed polder scheme will block the ecological connectivity across Tung Chung Stream. They also mentioned that no pollution should be caused to Tung Chung Stream during the construction of the polders, and that environmentally and ecologically compatible design and materials should be used to keep the footprint of the polders to a minimum, allowing wildlife to migrate across Tung Chung Valley. 

·       NGO/ local community groups suggested other ways of preventing the effects of flooding, such as building bypass floodways, relocating housing away from the River and enforcement of laws to prevent illegal waste dumping and development. They also opined that the proposed treatment facilities for surface run-off should be carefully designed and managed, and that communal sewer connecting the village houses in Tung Chung West was necessary.

·       NGO/ local community groups opined that the environmental performance of polder system and stormwater attenuation and treatment ponds was yet to be proven. They also opined that Tung Chung Stream should be kept in its natural conditions and that concrete channelling should not be done.

·       NGO/ local community groups supported revitalising Ma Wan Chung by improving its sewage system.

·       The statutory Environmental Impact Assessment (EIA) had been carried out for the RODP under the EIAO, and necessary mitigation measures had been proposed to ensure the impacts were acceptable. The statutory EIA included individual and cumulative impacts for all key environmental aspects, and had taken into consideration of the proposed construction methods and mitigation measures, on-going and committed projects, etc.

·       The polder system and stormwater attenuation and treatment ponds were proposed to minimise the flooding risk and impact of polluted surface runoff on the Tung Chung Stream respectively. The required extent of the polder system were supported and substantiated by detailed modelling and design in the upcoming Design and Construction phase of the project. The drainage and sewage within the villages had been properly designed to ensure human activities would not cause an adverse impact on the ecologically sensitive areas in TCW. Innovative mitigation measures in the form of stormwater attenuation and treatment ponds and multi-stage sedimentation had been explored in detail. Such innovative idea has been implemented in other countries and has been proven to be a very efficient measure.

·       The Green Belt proposed in Tung Chung West can serve as ecological passageway across the river.

·       A proper sewerage system connecting to Ma Wan Chung has been proposed.

 

Technical assessments

·       NGO/ local community groups urged the Government to release more data regarding technical assessments on the environment and demographics in Tung Chung and proposed conducting more studies for the subsequent EIA, including site-specific water modelling study and a marine traffic impact assessment, study about the change in water quality, the impact of the proposed marina, as well as on-site fishery surveys and a Strategic Environment Assessment.

·       NGO/ local community groups suggested that technical assessments such as Marine Traffic Impact Assessment, Strategic Environmental Impact Assessment and assessment on the impacts of the marina on Chinese White Dolphins should be done.

·       NGO/ local community groups opined that, besides air quality impact, a Strategic Environmental Impact Assessment should be conducted to evaluate the cumulative impact brought by surrounding large-scale infrastructure developments in Lantau at earlier stages of decision-making process.

·       Environmental assessments undertaken suggested that the environmental impacts complied with the required standards. The statutory EIA under the EIAO was carried out with the consideration of Tung Chung remaining development as well as all nearby projects to confirm both individual and cumulative environmental impacts are acceptable.

Provision of Facilities

General

·       The public opined that more community facilities should be built in Tung Chung with a balance of provision between Tung Chung East and Tung Chung West. The provision of facilities should also be accessible and specific to the needs of various groups, including the youth, elderly and ethnic minorities. The public also urged for social inclusion and cultural diversity of the local community.

·       Sufficient and appropriate government and community facilities have been proposed in the RODP in accordance with the HKPSG, under consultation with relevant departments and stakeholders. The proposed distribution of these facilities have also taken into account of the existing distribution and targeted for the best accessibility to both future and existing residents of Tung Chung.

Community facilities

·       In general, the public asked for a balanced provision of community facilities for different age groups.

·       While supporting the idea of a balanced provision, the NGO/ local community groups also opted for more open spaces to enhance residents’ quality of life.

·       One private sector suggested that lands should be reserved for NGOs and charities and a municipal services building operated by the Government should be built for people in Tung Chung.

·       Requests from the public and community organisations were made on the development of a government-operated public markets and cooked food markets. There were also requests for specific community facilities, including a city hall, childcare and elderly centres, arts venue/theatre, clinics, and government offices.

·       Local community groups also suggested that the two management companies could operate the public facilities together.

·       More sports facilities were suggested by sports related association, such as a new rugby pitch near the proposed Tung Chung East MTR station and a multi-sports stadium. They opined that having more sports facilities could provide diverse recreational opportunities for the community and help develop Tung Chung into a sports hub.

·       There were suggestions for more facilities especially for ethnic minorities from the public and organisations. They also which recommended building a hostel and community centre operated by a charitable foundation. 

·       A private sector suggested reserving a place for installing plants for a town cooling system.

·       The public were cautioned against an uneven distribution, duplication and possible waste of resources. They expressed their concerns over the proposed clinic/healthcare centre in Tung Chung West, which would be located 500 meters away from North Lantau Hospital.

·       The public was also concerned on the effect of the R2 proposed development on the Tung Chung Community Services Complex in Wong Nai Uk village.  Local community groups suggested relocating the Tung Chung Community Services Complex to the sports centre proposed at the west of Yat Tung Estate before demolishing the current building. They also suggested relocating the non-government organisations in phases, so as not to affect the provision of services and job opportunities offered by the organisations.

·       Sufficient government and community facilities for various groups such as the youth, elderly, ethnic minorities, etc. have been proposed in accordance with the HKPSG, and with reference to the advices from relevant departments and the comments from the publics received during the 3 stage of the public engagement activities. For the facilities that require policy support such as wet market, flea market, religious facilities, etc., specific requests have been conveyed to relevant bureau/departments for consideration.

·       Adequate GFA has been provided for GIC facilities and services within the R2 sites.

·       A 3ha standard sports ground, which was repeatedly requested by Tung Chung residents, has been proposed at Tung Chung East, which can be used for different sports activities, including rugby and football.

·       After discussion with the relevant Government bureau/department, in view of an arts venue/theatre has already been proposed in Area 1 within the Tung Chung Town Centre, the Government site originally planned for sports centre in Tung Chung West has been changed to District Open Space, in which some facilities such as amphitheatre could be designed subject to future detailed design.

Religious facilities

·       Religious related organisations voiced their opinions on the effect of the proposed development on Tao Yan Church of the Evangelical Lutheran Church of Hong Kong, located in Wong Nai Uk Village in Tung Chung. They opined that Tao Yan Church should be remained at the current site to maintain its service.

·       Religious related organisations expressed its hope to slightly expand the existing zone of Prajna Dhyana Temple as I/C into two pieces of government lands. They also expressed the urgent need to have a Catholic church in Tung Chung to cater for the local Catholic community, adding that continuous negotiation had been done with the Government.

·       One private sector proposed that a joint venture project with Dzongsar Temple could be considered to establish a structure in Hong Kong to promote Tibetan Buddhism and other related arts and medicine. It also expressed interest to develop land at Nim Yuen, Lam Che and She Lau Po for “Institution or Communities” purposes, including religious use.

·       The religious organisations have been advised to consult the relevant bureau and obtain policy support for their proposal separately. Separate site search for a re-provisioning site will be carried out by the relevant Government department if policy support is received.

Education facilities

·       Educational related organisations raise grave concerns on the provision of primary and secondary schools in both TCE and TCW and requested a critical review taking into account the latest school plans allocation in Tung Chung.

·       There were requests for specific tertiary education facilities, including a university to provide training for local people. In this regard, suggestion to have an aviation-training centre in Tung Chung was received.

·       The Vocational Training Council proposed having a centre on vocation education and training, such as a Youth College, under Vocational Training Council in Tung Chung. The organisation proposed grouping several lots in Tung Chung East, with an approximate area of 19000m2, and reserving it for the Youth College at the east part of the Tung Chung Extension.

·       Mixed opinions were noted on development of international schools. Educational related organisations specifically objected to the provision of an international school in Tung Chung; however, the stakeholders supported the idea.

·       For the schools, as confirmed with the Education Bureau, the provision of primary schools and secondary schools has been revised to six numbers and two numbers respectively, while post-secondary education facilities and other school uses are retained in TCE. The sites released from the reduction of 4 school sites will either be used for residential purposes or other GIC uses serving the community.

Proposed marina in Tung Chung East

·       The public generally supported the idea that the marina can enhance the vibrancy of the area. Stakeholders opined that the capacity of proposed marina should be limited to 300 vessels.

·       Stakeholders suggested integrating the marina into the pedestrian walkway networks so that the promenade and scenic view of the water area and the Airport could be best utilised. They also suggested that the marina should be opened for public use instead of being a “members only” facility.

·       A private sector opposed to the development of a marina and regarded it as an exclusive club activity, but fully supported a sheltered water area provided by the Government for local vessels in the development proposals. 

·       NGO/ local community groups suggested that the need of the proposed marina should be carefully evaluated, especially regarding its impact on Chinese White Dolphins arising from an increase in marine traffic in Tung Chung and its surrounding waters.

·       The exact operation mode of the marina is being examined in detail with the relevant bureau and departments. Marine traffic impact arising from the implementation of the proposed marina has been assessed.

·       The proposed marina is intended to be opened for public access and integrated into the pedestrian walkway networks with the scenic view of the water area.

Transport and Infrastructures

General

·       In general, the public opined that the transport and infrastructure network and connectivity in Tung Chung could be further improved. Adequate provision of transport facilities would be needed in the future development of the new town, as suggested by local community groups.

·       NGO/ local community groups urged the Government to consider the existing capacity of local bus services.

·       Opinion was also noted on the burden to both the road networks and MTR services in Tung Chung from the proposed increase in the future population of the new town.

·       There were requests for improvements on the transportation by increasing the frequency and types of transport to improve the connectivity.

·       Environmentally friendly transport systems such as electric buses, electric cars and bicycle sharing system in Tung Chung were also suggested.

·       There was also opinion that the connectivity between rural villages and other parts of the new town could be improved. NGO/ local community groups suggested linking Tai Ho and Three Villages with the proposed developments in Tung Chung. They also supported revitalising Ma Wan Chung by improving its road and car park provision, etc.

·       Local community groups opined that the connectivity into Three Villages should be improved with better utilisation of the Tai Ho Interchange.

·       Assessments have been conducted which confirmed that the capacity of the road and railway is sufficient to cater for the additional population from Tung Chung new town extension and also from other nearby developments in Lantau.

·       A connection between Tung Chung East and Ma Wan Chung and the provision of car park near Ma Wan Chung were review and reflected in the RODP.

·       Access to the villages would be provided as far as possible.

·       The request for increasing the frequency and types of transport, and environmentally friendly transport systems, etc. have been conveyed to the relevant bureau and departments for consideration and further study. Space provision for charging facilities of electric buses within  new public transport interchange has been allowed.

·       The provision of connection from future Tai Ho Interchange to Tai Ho is considered.

·       Three Villages are outside the Tung Chung new town extension, and the request for improving the connectivity into Three Villages has been conveyed to relevant bureau and departments for further consideration.

Railway transport

·       The public urged for an evaluation on the capacity of the MTR Tung Chung line and strengthening of the current system for handling the increasing demand from Tung Chung residents and visitors. The public supported the two proposed MTR stations in Tung Chung East and West. In particular, stakeholder supported the proposed Tung Chung East MTR Station. Opinion varied on the development priority, detailed design and location of the proposed MTR stations. In this regard, NGO/ local community groups expressed their disagreement on the location of the proposed Tung Chung West MTR Station.

·       Extension of the current MTR service was also noted. Local community groups suggested that the existing Tung Chung Line could be extended northward to a new Siu Ho Wan Station.

·       Local community groups hoped the Government could explore viable options to link the Airport Express with Tung Chung and the Airport.

·       MTR Corporation suggested that a public transport interchange (PTI) should be planned as close as possible to the proposed MTR TCE station and within the Metro Core area, in order to encourage the use of railway and facilitate a seamless connection between railway and other modes of transport.

·       Technical assessments have been conducted which confirmed that the capacity of the railway network even at the critical section is still sufficient to cater for the additional population from Tung Chung New Town Extension and also from other nearby developments on Lantau.

·       The location of Tung Chung West railway station was proposed with consideration of various constraints such as alignment, available land, engineering feasibility, etc. Indeed, a TOD principle has been adopted around TCW station, which is surrounded by high-density subsidized housing development of the existing Yat Tung Estate and planned Area 39.   We have also proposed commercial uses adjacent to the station to serve as a focal point. Development intensity also gradually descends further away from the station.

·       The feasibility of extending existing Tung Chung Line to Siu Ho Wan Station will be studied under separate feasibility study for Siu Ho Wan development.

·       Suggestion of linking the Airport Express Link with Tung Chung and the Airport is now being reviewed under separate study for topside development at HKBCF island.

Road network

·       The proposed Tai Ho Interchange and Road P1 (Tung Chung – Tai Ho Section) to improve the connectivity of Tung Chung was supported by stakeholders. They suggested extending the road networks, including linking Cheung Tung Road to Tai Ho Interchange and the existing pedestrian and cycling underpass from Tai Ho access point to the shoreline of Tung Chung East for leisure activities.

·       Local community groups also opined that existing road networks could be further extended to Tai Ho Bay.

·       A private sector opined that the access road to Shek Lau Po should be extended to Chung Yat Street to facilitate traffic flow. There was also suggestions on the design of the road network, such as widening Cheung Tung Road into four lanes, linking and widening the coverage of local pedestrian path, building cycling paths and a promenade to link up different parts of Tung Chung.

·       A private sector also proposed a designated route linking different parts of Tung Chung West for visitors.

·       NGO/ local community groups called for attention on the construction of the proposed road linking Shek Mun Kap to Mok Ka Village aligned through an Ecological Important Stream recognised by the AFCD. They also mentioned that no road access to sensitive areas such as natural coastlines, riverbanks, fung shui woods and ecologically valuable sites should be provided to avoid pollution and illegal dumping in those areas. They also opined that traffic restrictions should be imposed in Tung Chung West to prevent adverse environmental impact to Tung Chung Valley.

·       Regarding road safety, local community groups suggested the adoption of the London mode to develop a road layout with important elements such as speed management, street design techniques and enhancement measures of safety to deal with possible at-grade crossings.

·       NGO/ local community groups suggested minimising the lands reserved for roads for greenery walkways and supported revitalising Ma Wan Chung by improving its road and car park provision.

·       A proper road connection network, cycling paths, a greenery walkway and waterfront promenade linking various parts of Tung Chung including villages in Tung Chung West have been proposed in the RODP. These measures will serve as a long-term improvement for the connectivity within the entire Tung Chung. Improvement of road connection and provision of cark parks near Ma Wan Chung are also proposed. Provision of connection from future Tai Ho Interchange to Cheung Tung Road is considered.

·       The proposed road alignment has taken into account of the findings of an ecological survey, and an EIA has been carried out to ensure the impact of road construction to Tung Chung Stream will be acceptable. A detailed design of the roads with consideration on road safety, etc. will be carried out in the Design and Construction phase of the project.

·       The requests for improving the existing roads, such as Chung Yat Street, Cheung Tung Road, local pedestrian path, etc. have been conveyed to relevant departments for consideration.

Cycling

·       There were requests on improving the cycle track network in Tung Chung to cater for the needs of local residents, tourists and professional/sports cyclists in the area.

·       For the existing cycle track network, local community groups opined that it should be linked together so that the use of bicycles could further be promoted.

·       There were suggestions on measures to avoid conflict of usage between drivers and cyclists on roads in the area, so that experienced cyclists would be able to share the road with other users in the future. It is proposed connecting cycling tracks in both Tung Chung West and Tung Chung East and adopting extensive traffic calming design features for cyclists.

·       Opinion was also sought from cycling clubs in Tung Chung. It is stressed that there should not be any restrictions for cyclists to use Cheung Tung Road and that strict speed limits should be set for all users for safety reason. Ancillary facilities for cycling, such as more cycle parking spaces and rental kiosks, were also suggested.

·       Suggestions on existing facilities, such as linking the existing cycle track, unrestricted use of Cheung Tung Road for cyclist, etc. are limited by many existing constraints. Nevertheless, such suggestions have been conveyed to the relevant department for consideration.

Any future cycle track network will need to be designed in compliance with relevant standards. The appropriate width and safety features will be further studied and enhanced. With regards to the proposed cycling lane (i.e., a cycle lane next to vehicular road with no physical barrier as currently used in some countries), discussions with the relevant department indicated that such idea is not yet applicable in Hong Kong at this stage due to different legislations, safety standards, and driving culture, etc.

Economic Development

General

·       The proposed economic development under the draft RODP taking into account the nearby developments in Lantau was generally appreciated.

·       There were comments that local job opportunities should be provided to match the skills of labour available in Tung Chung, with suggestions of industries, such as those related to technology and the environment, could be further developed in the new town.  

·       It was also pointed out that further economic development opportunities could be brought by nearby development projects in Lantau, such as the North Commercial District (NCD) of the Hong Kong international Airport, which should be considered in the overall planning of economic development in Tung Chung.

·       Relevant parties and organisations of nearby developments in Lantau have been consulted, and their valuable comments have been taken into account in formulating the economic development for the RODP of Tung Chung. Sufficient and diverse job opportunities with diverse skills have been proposed to ensure Tung Chung and nearby projects are complementing but not competing with each other.

Tourism

·       There was opinion on the further development of local tourism in Tung Chung.  In this regard, the NGO/ local community groups suggested that more efforts should be done to attract visitors to the area, especially by developing local tourism and preserving sites with historical and cultural values. They also urged for avoidance of possible conflicts between locals and tourists due to tourism development. Improvement on the natural shoreline in Tung Chung, such as better linkage to the waterfront promenade, was another suggestion to attract more visitors to the area.

·       Opinion on promoting eco-tourism by preservation of the natural scenery in Tung Chung was also suggested. The stakeholders suggested developing eco-tourism in the Tai Ho valley, which they suggested could be converted as an “Ecology and Heritage Park”.

·       The protection of sites with historic and cultural values is one of the key development principles of our RODP. Local tourism is also encouraged in the RODP, e.g. the revitalisation of the Ma Wan Chung village, and the connected waterfront promenade. The proposed River Park would also aim to promote eco-education.

 

Local economy

·       Development of local economy was urged for from the public and organisations which supported an increased commercial space and provision of waterfront retail and street shops.

·       The proposal of street shops and local retailing services providing a variety of affordable goods, rather than a large shopping mall with chained stores, was generally supported. There were also suggestions of additional local retail opportunities including public wet markets, flea markets, cooked food centres, etc. An underground shopping mall was also suggested by a local community group to better utilise the available space and widen the retail opportunities.

·       It was suggested that products incorporating the characteristics of the area could be sold at the aforementioned local retail opportunities while job opportunities could be offered to Tung Chung residents, which could help to diversify future job opportunities.

·       More diversified development in the local economy in addition to tourism development was also suggested. In this regard, the NGO/ local community groups proposed the development on local agriculture and flea markets to establish a diversified economy in Tung Chung.

·       In terms of agriculture, the NGO/ local community groups opined that farmland in Tung Chung West should not be used as low-density village type development, but should be purchased by the Government and leased to those who were eligible to apply for the Agricultural Land Rehabilitation Scheme.

·       Local community groups pointed out that more land for airplane and vessel maintenance, scientific research centres or other high value-added positions in Tung Chung could be included in the future development of the new town and thus help develop Hong Kong into a “knowledge economy”. It was also suggested that the waterfront area could be used for development of local economy.

·       MTR Corporation mentioned that retail elements in the proposed footbridges between the Metro Core and proposed TCE MTR station could be incorporated to create more commercial floor space and employment opportunities. Topside development was also suggested to maximise development potential and land resources offered by the proposed TCE MTR station.

·       The Study Team is fully aware of the need to match the jobs with the skills of the residents. The study team has been coordinating with project proponents of nearby developments for creating job opportunities of diverse nature. In the RODP, the positioning of Tung Chung has been steered towards a major office node of the region after taken into account the surrounding developments such as NCD and HKBCF, which are going towards retail/hotel uses. It is estimated with the variety of commercial uses (including office, retail, hotel, etc) in the future, it will definitely lead to a more diverse job nature for the benefit of existing and future residents. Moreover, our reserved site for post-secondary education institutions will provide opportunity for technical training courses in training up the suitable skillset for residents with the different type of jobs in Tung Chung and the surroundings.

·       We are fully aware of the community’s demand for both shopping malls and “local shops” or “street shops”, with a diversity of retail spaces not only convenient to the locals, but also providing local job opportunities and creating street vibrancy. Regarding the request for public wet markets, it is understood that these will be provided by HD in the upcoming PRH developments in Area 39 and Area 56. As for flea markets, the comments are noted and conveyed to the relevant Government departments. Nevertheless, in the proposed DO in our RODP, there are potential for flea markets on application to LCSD in future.

Development Scale

General

·       The public generally supported further development of Tung Chung New Town and urged for its earlier implementation. The public opined that an enhanced development plan for Tung Chung Town Centre, Yat Tung Estate and Ma Wan Chung Village should be formulated.

·       Local community groups pointed out that future development should focus on the entire Tung Chung rather than the extension areas only. There was support for advocating a stepped height profile and stringent building height restrictions near the waterfront in Tung Chung. Moreover, they also showed strong support for the strategic planning for Tung Chung reclamation area and suggested the benefits brought by surrounding transportation infrastructures should be better utilised.

·       Stakeholders in general supported the RODP for Tung Chung East, which utilised the concept of transport-oriented development.

·       The support on the draft RODP is noted. The Study has already taken the existing Tung Chung New Town into account.

Development density

·       There were no major comments on the proposed development scale for Tung Chung East. In terms of development in Tung Chung West, the proposed development was generally supported.

·       More specific comments were received which opined that the residential zone, with a low to medium development density, could be designated to preserve the natural coastal area and the view of Hau Wong Temple in Tung Chung West.

·       Moreover, stakeholders opined that the plot ratio for Tung Chung West should be increased to balance environmental protection and the local housing needs and they suggested developing Tung Chung West with a dual emphasis on the natural scenery of the Tung Chung Stream and local characteristics. Five areas could be designated for different purposes, focusing on cultural heritage, local ecology, agriculture, fishery and a central market.

·       During the PE3 Public Forum, the Expert Panel suggested the concept of harmonious community in development, and pointed out that the importance of local economy with regard to the planning, provision of community services and desired living environment.

·       The RODP has been reviewed. It is considered that the development intensity of TCE is appropriate taken into account various considerations including urban design, airport height restriction, environmental, air ventilation, traffic, sewage, drainage, etc.

·       The TCW RODP has been reviewed. Two additional plots have now been used for residential use (the “GB” site near Ngau Au and the additional primary school adjacent to TCV-6 site) and the development intensity of the R4 site has been slightly increased from Plot Ratio (PR) 0.75 to PR1.

Population

·       There were diverse views on the population. Some parties were worried about the increase in population; for example, NGO/ local community groups suggested that the proposed population in TCE should be reduced.

·       However there were also suggestions that the plot ratio in Tung Chung West should be increased, as mentioned by the Liberal party who opined that the estimated population for Tung Chung West had been very low compared with that of Tung Chung East.

·       There were also concerns that population increase would be inadequate to fill the future jobs provided in the area including the Airport. Opinion was noted in urging for a review on the proposed population growth in Tung Chung.

·       The proposed additional population in the RODP aims to strike a balance between various aspects including housing demand, environmental impact, impact on local community, capacity of infrastructure, etc.

Housing Development

General

·       A balanced provision of public and private housing was generally appreciated and there were different proposals on the types, distribution and locations of housing development.

·       A private sector opined that public and private housings should not be divided to obtain a balanced development on community facilities and a social impact assessment should be conducted and it suggested increasing the amount of private housing in Tung Chung West.

·       In regard to the natural environment in Tung Chung West, comments were received from the NGO/ local community groups, cautioning against excessive residential development in the area, which might bring adverse environmental and ecological impacts to Tung Chung Stream and Tung Chung Bay.

·       Wong Nai Uk village expressed their concern about the possible walled effect at Wong Nai Uk village as it would be surrounded by North Lantau Hospital, Yat Tung Estate and the proposed Residential 2 (R2) development, and suggested refining the design of R2 development to avoid the effect.

·       Local community groups supported revitalising Ma Wan Chung by conducting house enhancement works and advocated the concept of Green City in the development of Tung Chung with the provision of green spaces and green roofs in addition to a balanced housing development integrating with the surrounding environment.

·       The proposed mix of public and private housings has made reference to the recommendation given in the Long Term Housing Strategy.

·        A large part of the “R2” site adjoining the Town Park is already included as “R(A)” zone for high-density residential development in the existing Outline Zoning Plan. When compared to the existing R(A) zone, the development scale for the R2 site on the RODP has been reduced from PR5 to PR4, and the Building Height Restriction (BHR) of the “R2” site has been maintained as 75mPD which will not be higher than the peak of the Town Park. Air Ventilation Assessment, Landscape and Visual Impact Assessment and proper urban design have been conducted to ensure the impacts are acceptable.

Public housing

·       In the joint submission, NGO/ local community groups expressed their concerns about the residential development near Tung Chung Valley as it is incompatible with the physical and ecological setting of the area and violates the principles of the Convention on Biological Diversity.

·       Religious related organisations suggested relocating the nearby residential buildings to the other side of Tung Chung Stream in order to maintain an adequate distance with the Temple and alleviate the potential impacts on lighting and air ventilation. The opinion was echoed in the submission by local community groups, who proposed relocating the public housing blocks to the lands near Tung Chung West MTR Station.

·       Stakeholders considered the infrastructure and connectivity of Area 56 as inadequate for the proposed public housing development, and opined that the development might cause heavy road traffic and increase of traveling costs to residents.

·       The proposed residential use in Tung Chung Valley was based on urban planning consideration as well as the findings of ecological survey. Statutory EIA under the EIAO has been carried out to confirm that the physical and ecological setting of the area are acceptable and the principles of the Convention on Biological Diversity not violated.

·       The RS site near Prajna Dhyana Temple in Shek Mun Kap is considered suitable for development and will be remained on the RODP. Possible noise nuisance from temple activities will be mitigated by appropriate building design/orientation in the detailed design stage.

·       The type of subsidised housing (i.e. PRH or HOS) will be further examined and determined at a later stage in consultation with Housing Department.

·       The concern on infrastructure and connectivity of Area 56 within existing town centre has been conveyed to the relevant department for consideration.

Other Comments

·       NGO/ local community groups expressed its opinion on the arrangement of the Public Forum held on 11 October 2014, and suggested holding more Public Forums at different venues. The group also recommended that more exercises should be done in Stage 3 Public Engagement, with more information such as the demographic data of Tung Chung and technical data related to the environment of the new town provided.

·       There are comments about the high living cost, transport fares, etc. in Tung Chung. Local community groups opted for cancelling the Tsing Ma Control Area and the fees for North Lantau Highway to lower the cost of travelling and attract visitors to the area.

·       There are requests from villages outside the proposed new town expansion area (e.g. villages of San Tau and Tai Ho) that TCNT extension should include proposals to address their needs such as providing road connectivity and village sewerage.

·       During the two and a half month period of PE3, extensive engagement activities involving series of meetings with a wide range of stakeholders with different background were carried out, during which a large amount of valuable comments and suggestions were received. These comments and suggestions provide an extremely useful basis for the refinement of the development plans and the associated technical assessments, which will take considerable time. To facilitate an earlier implementation of the proposed development in response to the demand from the public, an analysis of PE3 views, finalization of development plans and technical assessments have been commenced immediately after the end of PE3. The relevant assessment data will be made available at an appropriate stage when the assessments are substantially completed.

·       Other comments such as living cost, transport fares, etc. have been conveyed to other departments for consideration.

·       The requests from villages outside Tung Chung New Town Extension area have been conveyed to relevant departments for consideration as well.

 


 


2.3.2.8           To summarise, a total of 3 stages of public consultation exercises had been conducted and during which liaison meetings had been conducted to collate the views from various stakeholders, local community and NGOs etc. Comments/ suggestions received cover a wide range of issues including but not limited to environmental, planning, facilities, economic etc. All these concerns have been properly addressed during the formulation of RODP and are briefly explained in this EIA Report. The key environmental aspects of concern are summarised below.

Key Environmental Aspects of Concern

Approaches to Address Comments

1.     Impact on Chinese White Dolphins due to reclamation works at TCE shall be minimised

1.     Reclamation site at TCE has been optimized to minimise impacts on Chinese White Dolphins and water quality during construction of reclamation shall be duly minimized by adopting non-dredged reclamation methodology

2.     Reclamation at TCW not preferred

2.     Reclamation at TCW has been avoided to allay public concern

3.     Tung Chung Stream and other ecologically sensitive areas in TCW shall be conserved

3.     CA, CPA, GB zoning has been assigned to provide buffer zone for all ecological sensitive areas

4.     Declared monuments, graded historic buildings with high cultural value in TCW shall be avoided

4.     Development has avoided nearby declared monuments, graded historic buildings

5.     The existing channelized section of Tung Chung Stream in TCW shall be revitalised

5.     The channelized section of Tung Chung Stream has been revitalised to enhance its ecological function

6.     Concern on air quality in Tung Chung

6.     Setback distance between NLH and TM-CLKL and planned residential development has been provided and space provision for railway system has been considered so that more future residents can enjoy the environmental friendly transport system

 


 

2.4                         Summary of Recommended Outline Development Plan (RODP)

2.4.1                  Overview

Key Design Principles

2.4.1.1           Urban design of the Project is driven by a series of design concepts that were developed during the course of the study and embody the opportunities for increasing pedestrian connectivity between TCE, TCW and the existing Tung Chung New Town, capitalizing on the location of the proposed new railway stations and integration with the surrounding context. The key design concepts are listed below.

1)   Transport Oriented Development

2.4.1.2           In order to capitalize on the development opportunities presented by major new public transport links to the territory but also within Tung Chung itself, the concept of Transport-Oriented Development is utilized to create highly concentrated hubs of activity and residential areas in close proximity to the proposed railway stations.

2.4.1.3           The increased development intensity around the proposed railway stations is seen as an opportunity to create a new, highly visible centrality that is emblematic of the New Town and its aspirations to become the home of a new generation of residents.

2.4.1.4           As such, residential land uses such as Residential Special (PR 5 – 6.5), Residential 1 (PR 6.5) and Comprehensive Development Area (domestic PR 6 + non-domestic PR 2.76/2.78) are assigned near the proposed railway station at TCE and the proposed railway station at TCW is assigned near Yat Tung Estate in which most of the local residents can be benefited. (See Section 2.4.1 Part A for details). However, the design, construction and operation of these railway stations will be carried out by the railway operator and will not be included under this Study.

2)   Connectivity

2.4.1.5           Convenient physical mobility between residential areas and key activity nodes is crucial to creating an open and accessible spatial setting within which can inspire a feeling of belonging to the place for new residents.

2.4.1.6           Planning for enhanced connectivity is one of the major underlying themes of the layout in the Project, with particular attention paid to the linkages between the Tung Chung Town Centre and TCW via the Town Park as well as the connections between TCE and Tung Chung Town Centre. The goal is to create a mobility system that considers the entire Tung Chung as a unified town composed of distinct districts.

2.4.1.7           As such, approximately 49.11ha of open space area as well as 36.96ha of road networks including primary, district and local distributors are allowed in the RODP. Details of the design can be referred to Section 2.4.1 Part J and Section 2.4.1 Part N respectively.

3)   Integration

2.4.1.8           As an extension to the existing Tung Chung, new development seeks to maximize integration with the existing built form and to balance the need for new residential development with the natural features of the site. In order to create a unified urban form that respects the existing layout and minimizes adverse impacts on the natural environment integration strategies are employed throughout the Projects.

2.4.1.9           As such, approximately 10.42ha of Conservation Area (CA) and 4.94ha of Coastal Protection Area (CPA) are reserved for protection of Tung Chung Stream and the coastline of Tung Chung Bay which have high ecological and landscape resources in the RODP. Details of the design can be referred to Section 2.4.1 Part H and Section 2.4.1 Part I respectively.

4)   Stepped Height Profile

2.4.1.10      In order to achieve an integration between natural topography and existing built form, stepped height profile has been adopted in this Project. The height and density of the buildings at TCE are designed to descend towards the waterfront while the rural residential area at TCW near the estuary of Tung Chung Stream will adopt lower PRs in order to preserve the rural environment.

Overall Land Use Budgets in RODP

2.4.1.11      The overall land use budget for new developments in the PDAs at TCE and TCW (including the Road P1(Tung Chung – Tai Ho Section)) are as follows:

                         Table 2.7   Land use budget for Tung Chung New Town Extension

Major Land Uses

Area in ha

TCE at PDA

TCW at PDA

Road P1

Total Area

Commercial

7.64

1.12

-

8.76

CDA (metro core)

7.65

-

-

7.65

Residential

43.95

27.95

-

71.90

·       Special Residential

23.99

5.01

-

29

·       Residential Zone 1

2.72

-

-

2.72

·       Residential Zone 2

1.02

1.82

-

2.84

·       Residential Zone 3

16.22

8.03

-

24.25

·       Residential Zone 4

-

13.09

-

13.09

Village Type Development

-

14.00

-

14

Government

7.44

4.72

-

12.16

Institution or Community

-

0.30

-

0.3

Education

9.11

-

-

9.11

Other Specified Uses

1.92

5.11

-

7.03

Open Space

21.48

24.70

2.93

49.11

·       Regional Open Space

10.74

1.76

2.93

15.43

·       District Open Space

10. 74

22.94

-

22.94

·       Local Open Space

Within Residential Zones

Agriculture

-

4.97

-

4.97

Green Belt

-

13.24

-

13.24

Conservation Area

-

10.42

-

10.42

Coastal Protection Area

-

4.94

-

4.94

Road

23.19

7.88

5.89

36.96

TOTAL

122.38

119.35

8.82

250.55

Remarks: Zoning boundaries in the RODP are to illustrate the broad development areas within the PDA, or based on the ecological survey conducted for this EIA only, and may be subject to detailed survey and layout in future.

 

2.4.1.12      The proposed land use zonings of the RODP for PDAs at TCE and TCW are shown in Figure 2.2 and Figure 2.3 respectively and their relevant site IDs are illustrated in Figure 2.4 and Figure 2.5. Detailed layout plan with building layout of the RODP for PDAs at TCE and TCW are shown in Appendix 2.1.

A.  Comprehensive Development Area (CDA) (Figure 2.6a and Figure 2.6b)

TCE

2.4.1.13      This zone is intended for comprehensive residential, retail and office development as a “Metro Core Area” in the RODP connecting to the proposed TCE railway station. The Metro Core Area is intended to function as the key centre for the entire TCE development.

2.4.1.14      Within the RODP, “A1-1” and “A1-2”, with areas of 3.90ha and 3.75ha respectively are proposed for the zoning. The rationale for this zoning is 1) to provide a means for achieving coordinated development along NLH as buffer/screen where subject to environmental constraints; 2) to ensure adequate and timely provision of G/IC facilities, public transport facilities, transport connections and open space serving the entire TCE area and 3) to ensure the relevant authority to have an appropriate control on the overall scale and design of development at this location with high centrality and gateway of the entire TCE reclamation area. The layout should be designed carefully by future developers through Master Layout Plan (MLP).

2.4.1.15      Given the connectivity with the proposed TCE railway station and its emblematic centrality, higher development intensity will be appropriate for this Metro Core Area. “A1-1” and “A1-2” are subject to a total PR of about 8.8, including PR6.0 for domestic use and PR2.76/2.78 for non-domestic use. The high development intensity would allow the Metro Core Area to be distinguished from a distance from the surrounding buildings and its role as the development core of the RODP will be emphasized. A maximum building height (BH) restriction  is ranging from 105mPD to 195mPD as stipulated on the Plan.

B.  Residential Developments (Figure 2.6a and Figure 2.6b)

1)   Special Residential (RS)

2.4.1.16      This zone is intended for high-density residential development for subsidized housing. Thirteen sites are proposed for Residential Special (RS) zoning for high density subsidised residential development in the RODP.

TCE

2.4.1.17      Within the PDA at TCE, 11 sites are proposed for “RS” zoning. They include “A2-1”, “A2-4”, “B0-4”, “B1-2”, “C1-1”, “C2-1”, “C2-2”, “D2-3”, “D2-4”, “E1-1” and “E1-5”. These sites are mostly within the 500m catchment around the proposed TCE railway station to allow convenient access to public transport. Development within these sites is subject to a maximum domestic PR ranging from 5 to 6.5 (with non-domestic PR ranging from 0.4 or 0.5) and a maximum building height restriction ranging from 95mPD to 140mPD as stipulated on the Plan. Stepped building height considerations have been taken into account the surrounding planned developments.


 

TCW

2.4.1.18      Within the PDA at TCW, 2 sites are proposed for “RS” zoning. They include “TCV-6” & “TCV-7” along Tung Chung Road. These 2 sites are located south of the planned Public Rental Housing in Area 39, and are along the western side of the Tung Chung Road. Development within TCV-6 is subject to a maximum domestic PR of 6 (with non-domestic PR of 0.4) and a maximum building height restriction of 130mPD as stipulated on the plan, which results in a stepped BH profile with the planned Area 39 Public Rental Housing to its immediate north. “TCV-7” is located at the southern end of the Tung Chung Valley. Development within this site is subject to a maximum PR of 5 (with non-domestic PR of 0.4) and a maximum building height of 140mPD as stipulated on the Plan.

2)   Residential Zone 1 (R1)

2.4.1.19      This zone is intended for high-density residential developments.

TCE

2.4.1.20      Two sites are proposed for “R1” zoning (“A2-2” & “A2-3”) intended for high-density private residential development in the PDA.

2.4.1.21      Both “R1” sites are located to the immediate north of the Metro Core Area CDA. These two “R1” sites are subject to a maximum domestic PR of 6.5. The maximum BH of 105mPD.

3)   Residential Zone 2 (R2)

2.4.1.22      This zone is intended for medium-density residential developments.

TCE

2.4.1.23      Two sites, i.e. “E1-2” and “E1-3” are proposed for “R2” zoning intended for medium density residential development in the RODP.

2.4.1.24      Both “R2” sites are subject to a maximum domestic PR of 5 and a maximum BH restriction of 90mPD. Non-domestic PR of about 0.4 is proposed for local commercial uses. It is recommended that both “R2” sites are to reserve the area fronting the DO and the Central Green to be developed into an area for ‘Shop & Services’ and ‘Eating Place’ uses in buildings not exceeding two storeys above ground as retail frontage within these “R2” sites. The intention is to encourage “street-life” and retail shops serving the locals and promotion of lively streetscapes and activities along the key pedestrian corridors.


 

TCW

2.4.1.25      One site, i.e. “TCW-2” located at the south-eastern edge of the future Town Park is proposed for “R2” zoning for medium density residential development in the RODP.

2.4.1.26      “TCW-2” lies along Chung Yan Road, with a lower development intensity to adhere to the setting against the backdrop of the Town Park which the tallest point is about 75mPD. Therefore, development within this site is subject to a maximum domestic PR of 4 (with non-domestic PR of 0.1), with a maximum BH of 75mPD as stipulated on the Plan.

4)   Residential Zone 3 (R3)

2.4.1.27      This zone is intended for low-density residential developments.

TCE

2.4.1.28      Within the RODP, 11 sites are proposed for “R3” zoning. They include “D1-1”, “D1-2”, “D2-1”, “D2-2”, “E1-4”, “E3-1”, “E3-2”, “F1-1”, “F1-2”, “F2-1” & “F2-2”. All these sites are located along or near the waterfront. For sites in the north-western part of the RODP, i.e. “D1-1”, “D1-2” & “D2-1”, development within these sites are subject to a maximum domestic PR of 3.5 and a maximum BH of 70mPD. For sites “D2-2” & E3-1”, development are subject to a maximum domestic PR of 3.5 and a non-domestic PR of 0.3 and 0.4 and a maximum BH of 70mPD.

2.4.1.29      For sites in the north-eastern part of the RODP, i.e. “E1-4”, “E3-2”, “F1-1”, “F1-2”, “F2-1” & “F2-2”, development within these sites is subject to a maximum domestic PR of 2.5 to 3, and a maximum non-domestic PR of 0.3 and 0.4, if any, and a maximum BH ranging from 45mPD to 70mPD. The maximum BH descends towards the northeast.

TCW

2.4.1.30      Within the RODP, 4 sites are proposed for “R3” zoning. They include “TCW-1”, “TCW-3”, “TCV-5a” & “TCV-5b”.

2.4.1.31      “TCW-3” is located between the “TCW-2” R2 Site and Ma Wan Chung. Given its elongated site layout and proximity to the low-rise Ma Wan Chung village, it is subject to a domestic PR of 2 and maximum BH of 55mPD as stipulated on the Plan. “TCW-1”is located to the west of the existing Yat Tung Estate. Development within this site is subject to a maximum domestic PR of 3.5 and a maximum BH of 70mPD as stipulated on the Plan.

2.4.1.32      “TCV-5a” & “TCV-5b” are located in the inner part of the Tung Chung Valley, to the north of the Shek Mun Kap Road and in between the Tung Chung Steam. The 2 sites are separated by a proposed 7.3m road connecting Shek Mun Kap Road to Mok Ka Village. Development within these two sites are subject to a maximum domestic PR of 1.5 and a maximum BH of 45mPD as stipulated on the Plan. The development intensity is to adhere to the rural context and the low-rise village environment of the adjoining Shek Lau Po, Shek Mun Kap and Mok Ka villages.

5)   Residential Zone 4 (R4)

2.4.1.33      This zone is intended for low-density rural residential developments.

TCW

2.4.1.34      Within the RODP, 5 sites within Tung Chung Valley are proposed for the “R4” zoning. They include “TCV-1”, “TCV-2”, “TCV-3”, “TCV-4” and “TCV-8”. All 5 sites are located in the central part of Tung Chung Valley and along the environmentally-sensitive Tung Chung Steam. In order to achieve an integration with the existing naturalistic and rural settlement character of Tung Chung Valley and avoid disturbance to the adjacent woodland habitats and natural stream courses during operational phase, a lower development intensity is proposed.

2.4.1.35      The “R4” Sites are subject to a maximum domestic PR of 1 and a maximum BH ranging from 20mPD to 55mPD as stipulated on the Plan. This BH range is to ensure a stepped BH profile from Tung Chung Estuary to the inner part of Tung Chung Valley, where the topography is relatively higher, in particular for “TCV-4” that will be developed on a formed slope south of Nim Yuen village.

Planned Flat Provision and Population

2.4.1.36      As discussed in Chapter 1, in order to cope with the territorial need on housing, the residential development potential of the Project are explored and the land resources should be optimized, while maintaining a suitable environment and opportunities for commercial development that is compatible with the regional developments and recreational facilities.

2.4.1.37      Taking into account the local context, public views collected during the Public Engagement activities as well as territorial aspirations, the land use proposal of the RODP is to provide a total of about 49,400 flats, with an additional population of around 144,400.

2.4.1.38      The following Table 2.8 shows the proposed flat provision and anticipated population of the RODP and in comparison with the existing Tung Chung New Town.

                         Table 2.8   Flat provision and anticipated population

Existing and Planned [1]

 

Population

Flat No.

Existing

78,400

28,800

Existing + Planned

124,000

44,200

Additional Population in RODP

 

Population

Flat No.

TCE

118,900

40,800

TCW

25,500

8,600

Sub-total

144,400

49,400

Overall Population Upon Full Development (Existing + Planned [1] + Additional Population in RODP)

 

Population

Flat No.

Total

268,400

93,600

Note:

[1] Planned population includes residential developments in Area 27, Area 39, Area 54, Area 55a, Area 55b and Area 56

Housing Mix

2.4.1.39      In response to the recommendations of the Long Term Housing Strategy in 2014, and subsequently requested by the Housing Department in Jan 2014, the public to private housing ratio for newly proposed development in the Project will be at least 60:40 and the breakdown of flat numbers allowed in the  RODP are summarized in Table 2.9 below.    

Table 2.9     Public: Private Housing Ratio

Existing & Planned [1]

TCE

TCW

TCE + TCW

Public

11,100

16,900

28,000

Private

16,200

0

16,200

Total

 27,300

16,900

44,200

% of Public  Flat

41%

100%

63%

% of Private  Flat

59%

0%

37%

Additional Housing in RODP

TCE

TCW

TCE + TCW

Public

25,700

5,200

30,900

Private

15,100

3,400

18,500

Total

40,800

8,600

49,400

% of Public  Flat

63%

60%

63%

% of Private  Flat

37%

40%

37%

Overall Flat Upon Full Development (Existing + Planned [1] + Additional Housing in RODP)

TCE

TCW

TCE + TCW

Public

36,800

22,100

58,900

Private

31,300

3,400

34,700

Total

68,100

25,500

93,600

% of Public  Flat

54%

87%

63%

% of Private  Flat

46%

13%

37%

Note:

[1] Planned population includes residential developments in Area 27, Area 39, Area 54, Area 55a, Area 55b and Area 56

C.  Village Type Development  (Figure 2.7)

2.4.1.40      This zone is to reflect existing recognized and other villages, and to reserve land suitable for future village expansion. Land within this zone is reserved for development of small houses by indigenous villagers.

TCW

2.4.1.41      Within the PDA, 8 sites are proposed for the “V” zoning. These include Wong Nai Uk, Ma Wan Chung, Ngau Au, Nim Yuen, Lam Che, Shek Lau Po, Mok Ka and Shek Mun Kap villages. The boundaries of the “V” zones are intended to concentrate village type development within this zone,  within the established Village Environs, and taken into account the existing village cluster, projected small houses demands (outstanding and 10-year forecast), as well as other factors such as local topography, natural characteristics and existing site conditions etc. Area of difficult terrain, dense vegetation, burial grounds, ecological sensitive areas and streamcourses have been avoided where possible.

2.4.1.42      Development within the “V” zones are subject to a maximum BH of 3 storeys (8.23m). The approximate sizes of each village zone are summarised in Table 2.10.              

Table 2.10  Size of village zone

Village Name

Area in ha (Approximate)

Ma Wan Chung

3.26

Wong Nei Uk

0.23

Shek Lau Po

3.37

Shek Mun Kap

2.75

Mok Ka

2.06

Nim Yuen

0.15

Lam Che

0.41

Ngau Au

1.77

Total

14.0

D.  Commercial Uses (Figure 2.8a and Figure 2.8b)

2.4.1.43      This zone is intended for commercial uses to serve the local community as well as the regional demand for commercial facilities.

TCE

2.4.1.44      The total area of the “C” zone is approximately 7.64ha. A Retail and Office Belt along NLH, consists of 3 sites, i.e. “COM-1”, “COM-2” & “COM-3”, is intended as an extension to the Metro Core Area. These “C” Sites, designated with a PR from 9 to 9.5 are intended to form part of the “Major Office Node” along the NLH with retail facilities on lower floors. In order to enhance the pedestrian connectivity of the 3 “C” sites with the Metro Core Area, pedestrian footbridges/ connections with 24-hour public access should be provided between the “CDA” sites and the “C” sites.

2.4.1.45      The other 2 “C” Sites, i.e. “COM-4” and “COM-5” are located at the northern tip of the RODP, around the proposed 95-berths marina. “COM-5” is intended to be developed into a low-rise marina clubhouse with retail and catering activities to create a vibrant waterfront and is subject to a maximum PR of 3 and a maximum BH of 45mPD, and urban design consideration of being along the waterfront. The design of this “C” Site should also synergize with the proposed waterfront park to its immediate north to form a vibrant activity node.

2.4.1.46      “COM-4” is intended to be developed into a hotel with supporting retail and dining activities, and is subject to a maximum PR of 3 and a maximum BH of 45mPD, and urban design consideration of being along the waterfront.

TCW

2.4.1.47      Within the PDA, three sites are proposed for the “C” zoning, clustered around the proposed TCW railway station and to the south of the Hau Wong Temple, i.e. “COM-1”, “COM-2”, “COM-3”. These “C” Sites, designated with a PR of 2 to 3 is intended to serve as a central hub of retail activities serving the future population in the RODP, as well as population in Yat Tung Estate and future population in the Area 39 PRH.

2.4.1.48      The three “C” Sites are restricted to a maximum BH from +20mPD to +30mPD as stipulated on the Plan to ensure a generally low-rise development south of the Hau Wong Temple.

E.  Government (Figure 2.9a and Figure 2.9b)

2.4.1.49      Areas zoned as Government (G) land uses include 1) Sports Ground; 2) Sports Centres; 3) Fire Station; 4) District Police Station & Married Police Quarters ; 5) General Clinic; 6) Salt Water Pumping Station; 7) Sewage Pumping Stations; 8) Government Reserve and 9) Attenuation Ponds and they are described in details as follows.

1)   Sports Ground

TCE

2.4.1.50      “G0-1” is reserved for a standard sports ground. It is intended to accommodate a seating capacity of about 10,000 spectators, and to provide a 400m track (all weather), a grass infield for athletics, and a 11-a-side football pitch for high graded soccer matches. This “G” Site is located at the eastern side of the RODP and is well-connected via the waterfront promenade. This “G” Site is subject to a maximum BH of 3 storeys as indicated on Plan.

2)   Sports Centres 

TCE

2.4.1.51      “D0-2” and “F0-1” are reserved for sports centres.  It is intended that the sports centres will provide a range of sports facilities such as badminton, squash, basketball, table tennis, fitness, dance and gymnastics. These “G” Sites are located along the major DO networks and is intended for integrated recreational, leisure and cultural development. The two “G” Sites are subject to a maximum BH of 5 storeys as indicated on Plan.

3)   Fire Station 

TCE

2.4.1.52      “G0-3” is reserved for a standard divisional fire station at the eastern side of the RODP. This “G” Site is subject to a maximum BH of 9 storeys as indicated on Plan.


 

4)   District Police Station & Married Police Quarters

TCE

2.4.1.53      C0-2” and “C0-3” are reserved for district police station and married police quarters respectively at the eastern side of the RODP. The “G” Sites are subject to a maximum BH of 16 storeys for the district police station and +90mPD for the married police quarters.

5)   General Clinic

TCE

2.4.1.54      B0-3” is reserved for a general clinic at the south-western side of the RODP, adjoining the existing Area 56. This “G” Site allows flexibility to be developed into a joint-user complex with other social welfare facilities when future need arises, subject to the agreement of the Food and Health Bureau and Social Welfare Department. This “G” Site is subject to a maximum BH of 5 storeys as indicated on Plan.

TCW

2.4.1.55      SiteTCV-i” is reserved for a general clinic to the south of Hau Wong Temple. This “G” Site allows the flexibility to be developed into a joint-user complex with other social welfare facilities when future need arises, subject to the agreement of the Food and Health Bureau and Social Welfare Department. This “G” Site is subject to a maximum BH of 4 storeys as indicated on plan.

6)   Salt Water Pumping Station

TCE

2.4.1.56      D0-1” is reserved for a salt water pumping station at the western waterfront of the RODP. The “G” Site is subject to a maximum BH of 1 storey. The design of the salt water pumping station should include adequate greening and to be integrated with the overall design of the waterfront promenade.

7)   Sewage Pumping Stations

TCE

2.4.1.57      “B0-4” and “C0-4” are reserved for sewage pumping stations at the southern part of the RODP. The “G” Sites are subject to a maximum BH of 1 storey.


 

TCW

2.4.1.58      “TCW-b” located along Chung Yan Road (opposite to the Wong Nei Uk village) is zoned as “G” to reflect the existing use of the Site as the Chung Yan Road Sewage Pumping Station.

2.4.1.59      “TCV-b”, “TCV-d” and “TCV-f” located within Tung Chung Valley are reserved for new sewage pumping stations to serve the future population of the RODP. Development within these 3 “G” zones is subject to a maximum BH of 1 storey.

8)   Government Reserve

TCE

2.4.1.60       E0-4”, with a size of about 7,000m2 is reserved for a government reserve to allow land use flexibility when future need arises. This “G” Site is subject to a maximum BH of 8 storeys as indicated on the Plan.

TCW

2.4.1.61      TCW-a” and “TCW-c”, both located along the Chung Yan Road are reserved for government reserves to allow land use flexibility when future need arises. There is an intention to provide car-parking space in support of the revitalization of the Ma Wan Chung village within Site “TCW-a” subject to detailed design.

9)        Attenuation Ponds

TCW

2.4.1.62      5 Sites, namely “TCV-c”, “TCV-e”, “TCV-g”, “TCV-k” and “TCV-n”, are reserved for stormwater attenuation and treatment ponds. They are located immediately adjacent to each residential development plot within Tung Chung Valley. The intention is to ensure each development area within the sensitive Tung Chung Valley will be fitted with stormwater attenuation and treatment ponds to minimize the water quality issues due to surface runoff generated within new urban development before discharging to Tung Chung Stream and to mitigate flood risk.

F.  Education (Figure 2.10)

TCE

2.4.1.63      This zone is intended primarily for the provision of education facilities to serve the needs of the population and complementing provisions. Ten “E” zones are designated within the PDA.

2.4.1.64      Eight “E” sites for six 30-classroom primary schools and two 30-classroom secondary schools for local and district needs are reserved in the RODP and are subject to a maximum BH of 8 storeys as indicated on Plan.

2.4.1.65      Two “E” sites are located on the eastern edge of the RODP is intended for a Post-Secondary Institution and Other School Use.  The two “E” sites are subject to a maximum BH of 50mPD.

G.  Institution and Community (Figure 2.11)

TCW

2.4.1.66      Two “IC” sites are planned with the RODP to reflect their existing uses, including Hau Wong Temple (“TCV-h”) near Tung Chung Estuary and Prajna Dhyana Temple (“TCV-m”) in Tung Chung Valley. Development within these “IC” sites is subject to a maximum BH of their existing number of storeys as stipulated on the Plan.

 

H.  Other Specified Uses (Figure 2.12a and Figure 2.12b)

2.4.1.67      This zone covers land allocated for the following specified uses:

1)   Electricity Sub-Station

TCE

2.4.1.68      B0-2” is reserved for an Electricity Sub-Station at the southeastern side of the RODP. This “OU” Site is subject to a maximum BH of 3 storeys as indicated on the Plan.

2)   Petrol Filling Station

TCE

2.4.1.69       B0-5” is reserved for a Petrol Filling Station at the southeastern side of the RODP, on the other side of the Road P1 (Tung Chung – Tai Ho Section). This “OU” Site is subject to a maximum BH of 1 storey as indicated on the Plan.

3)   Boatyard and Maintenance Area

TCE

2.4.1.70       F0-5” is reserved for the development of a Boatyard and Maintenance Area at the northern part of the RODP, immediately adjacent to and should be developed together with the proposed marina. This “OU” Site is subject to a maximum GFA of 4,000m2 and a maximum BH of 2 storeys as indicated on the Plan. An unobstructed landscape area should be provided on the waterfront park to connect the planned road junction to the “OU” site.

4)   Railway Station

TCE

2.4.1.71      The proposed TCE railway station is a new station on the Tung Chung Line situated next to the TCE development between Sunny Bay Station and Tung Chung Station. The proposed railway station would mainly serve the planned population in the PDA. This “OU” Site is subject to a maximum BH of 3 storeys as indicated on plan.

5)   Telephone Exchange

TCW

2.4.1.72       TCV-j”, locating to the south of the “COM-1” Site is reserved as the relocation site for a Telephone Exchange (which was used to be located in Area 39). This “OU” Site is subject to a maximum BH of 11mPD as indicated on the Plan.

6)   River Park

TCW

2.4.1.73      On the eastern tributary of Tung Chung Stream, from the YMCA of Hong Kong Christian College to Shek Mun Kap Road, will be developed into a “River Park” on both sides of the Tung Chung Stream for public recreational use and managed by the Drainage Services Department. Existing vegetation and trees shall be retained as much as practical.

2.4.1.74      As highlighted in 2015 Policy Address, the Government is promoting the concept of revitalising water bodies in large-scale drainage improvement works and planning drainage works. It is proposed to de-channelize an existing channelized section of Tung Chung Stream and develop together with the immediate upstream natural section into a River Park for environmental enhancement, eco-education and recreational uses. The proposed River Park aims to promote eco-education by setting up viewing decks/ boardwalk, passive recreation zone for appreciation of natural environment. The tentative schematic layout is presented in Appendix 2.1 and further developments and refinements would evolve during subsequent detailed design stage.


 

7)   Polder

TCW

2.4.1.75      Elongated strips of land mainly along the western tributaries of the Tung Chung Steam are reserved for polder scheme within Tung Chung Valley. The intention of the polder scheme is to mitigate flood risk due to anticipated high water level of Tung Chung Steam during extreme rain events.

2.4.1.76      To mitigate flood risk due to anticipated high water level of Tung Chung Stream during extreme rain events, a total area of about 1.6ha is reserved along Tung Chung Stream in the PDA at TCW for approximately 1.5m high embankments. Although part of the polders near Mok Ka village and Shek Mun Kap village will inevitably encroach onto the Fung Shui Woods with high ecological value (approximately 0.16 ha), these concerned areas will still maintain as OU with the consideration of safety concern of local communities. Ecological impacts due to the erection of polder will be separately discussed in Section 9.5.

I.     Conservation Area (CA) (Figure 2.13)

2.4.1.77      This zoning is intended to protect and retain the ecological features within Tung Chung Valley from the adverse effects of development.  It consists of two main clusters. There is a general presumption against development in this zone. In general, only developments that are needed to support the conservation of the existing natural landscape or scenic quality of the area or are essential infrastructure projects may be permitted.

TCW

2.4.1.78      The first cluster refers to the linear zones along the natural sections of the 2 main tributaries of Tung Chung Steam as well as the concourse near the outlet. Tung Chung Stream is recognized as an Ecologically Important Stream (EIS) by AFCD, and also houses the second most diverse stream fish communities in Hong Kong (only lower than Tai Ho Stream). This “CA” zone is to serve as an about 20-30m buffer (at certain intervals 10m-wide polder is included) separating the future development and the sensitive Tung Chung Stream. Next to Mok Ka Village existing built structures are in close proximity to the stream, therefore the buffer zone is limited to an approximate 15m. According to latest ecological survey, fish species of conservation importance, such as Beijiang Thick-lipped Barb which is only recorded in very limited locations in Hong Kong, are found in Tung Chung Stream. The proposed buffer zones (zoned as CA) would thus protect the riparian vegetation which are an integrated part of the stream ecosystem.

2.4.1.79      The second main cluster being the area surrounding Ngau Au Village. Buffer zones is planned on the northern and eastern edge of the Ngau Au Village for the protection of Tung Chung Steam. To the southwestern side of the Ngau Au Village, it is currently colonized by a woodland habitat. This woodland habitat is part of a large extent of woodland habitat extending from the western side of Ngau Au to San Tau, and thus should be preserved in the form of “CA”.

2.4.1.80      The third cluster refers to the area to the north of Shek Mun Kap village where Fung Shui Woods are identified. Due to the nature of Fung Shui Woods and the potential linkage between terrestrial fauna and natural environment, this area located adjacent to Shek Mun Kap Road should also be preserved as “CA”.  

J.    Coastal Protection Area (CPA) (Figure 2.14)

2.4.1.81      This zoning is intended to conserve, protect and retain the sensitive coastal natural environment of Tung Chung Bay. There is a general presumption against development within the “CPA” zone. In general, only developments that are needed to support the intention above or are essential infrastructure projects with overriding public interest may be permitted.

TCW

2.4.1.82      Species of conservation importance including horseshoe crab juveniles, seagrass beds, pipe fish, seahorse, etc. have been reported at Tung Chung Bay. The “CPA” north of Hau Wong Temple is intended to act as a buffer for the mudflat habitat in Tung Chung Bay which is of high ecological value. One part of the “CPA” zone is narrower to the NW of Hau Wong Temple since it is already occupied by an existing football pitch (Tung Chung Playground). There is also an existing camp site of Hong Kong Playground Association.

K.  Open Space (Figure 2.15a and Figure 2.15b)

2.4.1.83      Areas reserved as Open Space include 1) Regional Open Space; 2) District Open Space and 3) Local Open Space and they are described in details as follows.

1)   Regional Open Space

2.4.1.84      This zone is intended for the provision of outdoor public space for active and/or passive recreational uses. It mainly comprises the waterfront promenade along the northern edge of the PDA, connecting with the existing waterfront promenade in Tung Chung Town Centre.

TCE

2.4.1.85      Waterfront parks at northern and eastern edge of the waterfront promenade is intended to serve as a focal point for activities. Besides, a cycle park with an area of about 1.4ha is also proposed at Road P1 (Tung Chung – Tai Ho Section) intended to connect with the proposed cycle tracks within the PDA. 

2.4.1.86      The RO provides facilities including pedestrian corridor, plazas, passive open spaces as well as various outdoor recreational activities required under the HKPSG.

TCW

2.4.1.87      The “RO” along the northern part of the future Town Park is planned as a pedestrian walkway to connect PDA with the existing waterfront promenade in the Tung Chung Town Centre Area. This pedestrian walkway is to be provided along the coastal area above high water mark to avoid reclamation in Tung Chung Bay. Consideration may also be given during detailed design stage to provide cycle track along this walkway (about 6m-7m) subject to further assessment on visual and environmental aspects.   It should be noted that part of the “RO” locating south of the “R3” site will include a structure required for railway reserve.

2.4.1.88      The “RO” in the RODP mainly provides facilities including pedestrian corridor, plazas, passive open spaces in serving the population.

2)   District Open Space

2.4.1.89      This zone is intended for the provision of outdoor public space for active and/or passive recreational uses serving the needs of the district population, distributed within the PDA along networks of Linear Parks. The DO network creates a livable pedestrian environment for the PDA, providing facilities including pedestrian corridor, plazas, passive open spaces as well as various outdoor recreational activities required under the HKPSG.

TCE

2.4.1.90      Three major north-south Linear Parks with landscaped facilities in the PDA are proposed, connecting the proposed TCE railway station towards the waterfront promenade. The Linear Park system in particular is envisioned as a multifunctional series of activity corridors that enhance pedestrian connectivity by linking together residential neighbourhoods, distribute open space throughout the development and provide an identifiable open space network with activity nodes tailor-made for the PDA.  Moreover, there is another east-west Linear Park through the PDA connecting to the existing linear LO network at the existing Tung Chung New Town.

2.4.1.91      In addition of the Linear Park system, pocket parks with seating and sports activities are also provided. In the heart of the PDA, a Central Green forms a shared meeting place for people from all neighbourhoods. The space is flanked by retail activities on ground level adding vibrancy to the area. Moreover, to enable smooth pedestrian access to the waterfront from the proposed TCE railway station, the district distributor bisecting the PDA from east to west is sunken along the Central Green to allow the creation of a pedestrian platform over its entire width. This platform, which will form part of the continuous open space network in the PDA, will enable pedestrians to walk uninterrupted northwards utilizing the open space system as a safe and comfortable walking environment.

2.4.1.92      Shop fronts are concentrated along the Linear Parks and the Central Park area of the pedestrian spines to create a unique activity node that would otherwise be diffused with additional commercial frontage along the entire length.

TCW

2.4.1.93      The existing vegetated knoll is planned to be a Town Park serving both the planned population of the RODP, as well as serving a direct landscape connection from Tung Chung New Town to TCW. Due to the topography constraints, the planned Town Park should be designed mainly for passive recreational uses such as landscaped pedestrian corridors, viewing deck, sitting-out area etc, and the design should pay attention to avoid impact on and ensure compatibility with the historic features on the hill, including the Tung Chung Battery, Tung Chung Game Board Carving and Fu Tei Wan Kiln etc. There are some existing village houses, stilted waterfront features and waterfront activities at this waterfront of this “DO”. To enhance its attractiveness for visitors, commercial and dining facilities including gift-shop, area for alfresco dining maybe permitted along this public open spaces. The unique character that symbolizes the character of the Ma Wan Chung village should be preserved in the future design.

2.4.1.94      Another “DO” is located to the north of the Yat Tung Estate, and immediately west of the Ma Wan Chung Village. This “DO” site is intended to serve as a waterfront park with the spectacular view towards Tung Chung Bay and the airport island.  Being highly accessible to residents and easily accessed by the proposed TCW railway station, numerous active outdoor recreational facilities are proposed at this location. Moreover, an outdoor performance venue is intended to be provided within this “DO” to encourage activities and vibrancy of this area and in response to public comments during the PE3.

2.4.1.95      A “DO” is located around Hau Wong Temple along the waterfront of the Tung Chung Bay. This “DO” includes an existing 7-a-side football pitch and the Tung Chung Area Recreation Centre to west of the Hau Wong Temple. This “DO” to the eastern side of the Hau Wong Temple will function as a passive open space, and provide an outdoor performance venue for the temple or other local festive activities.

3)   Local Open Space

TCE

2.4.1.96      Local Open Spaces to serve the local residents is required within individual residential sites to provide activity spaces and enhance the living environment requirement for local open space provision under the HKPSG. Since they are to be provided within individual residential sites, and they are not shown on the Plan.

L.   Green Belt (GB) (Figure 2.16)

2.4.1.97      This zone is mainly distributed within the Tung Chung Valley, intended to preserve the existing topography and natural vegetation as well as to provide a buffer between the urban development and the countryside to its west. There is a general presumption against development in the “GB” zone.

TCW

2.4.1.98      The GB zone along Tung Chung Road near Fong Yuen (in between “TCV-6” and “TCV-7” Sites) is intended to maintain the integrity of the hydrological linkage from the natural slopes to the wet abandoned agricultural land and finally to Tung Chung Stream, which would in turn help the preservation of the current core habitat of the rare butterfly.

2.4.1.99      Patches of Fung Shui Woods are scattered throughout Tung Chung Valley. They are mostly situated close to the existing village-type development and have both environmental and culture importance. To prevent these areas from being developed in the future, they are zoned as GB and excluded from the formulation of “V” boundaries.

M. Agriculture (AGR) (Figure 2.17)

2.4.1.100 This zone covers land intended for agricultural uses at areas in between “V” zones and low-rise residential developments in the Tung Chung Valley.

2.4.1.101 The AGR zones are mainly located around the existing villages and intended to retain active and fallow arable land with good potential for rehabilitation for cultivation, and to allow continuation of existing farming practices.

N.  Roads (Figure 2.18a and Figure 2.18b)

2.4.1.102 About 23.19ha of land in TCE and 7.88ha in TCW are reserved for “RD”, which comprises vehicular lanes, footpaths/ trails, road-side amenity areas and major transport facilities including bus lay-bys, as well as amenity strips alongside roads to enhance the amenity and to serve as visual buffers.

TCE

2.4.1.103 The road network in PDA at TCE will consist of primary, district and local distributors. In general, the road configuration for primary and district distributors will be either dual 2-lane or single 4-lane carriageway, while local distributor will be single 2-lane road. The primary distributor will connect to the North Lantau Highway through Tung Chung Eastern Interchange and the proposed Tai Ho Interchange.

2.4.1.104 The primary distributor in TCE includes Tung Chung Waterfront Road, Ying Hei Road and a new road named Road P1 (Tung Chung - Tai Ho Section) which will serve as the primary east-west connection to and from North Lantau Highway. The Road P1 (Tung Chung - Tai Ho Section) is proposed to be mainly an at-grade road on reclamation.  Grade separated interchange, namely Tai Ho Interchange, in the form of elevated bridge structures is proposed for connection to the North Lanatu Highway. 

2.4.1.105 Connected to Road P1 in PDA at TCE are the district distributors: D1, D2, D3 and D4. D1 together with D4 provide a link to the west of the PDA at TCE, whereas D2 provides connection to the east. D3 is located in between D1 and D2 which provides a north-south link from Road P1 to the north of the development.  The remaining roads (L1-L10) in the TCE development are local distributors that provide links to specific land parcels within the development. All local distributors are assumed to have one lane per direction. Modification to the road junctions at roads L3 and L16 are required to tie-with the proposed road network.

TCW

2.4.1.106 The road network in PDA at TCW will consist of district and local distributors. In general, the road configuration for district distributor Chung Mun Road will be a single 4-lane carriageway, while local distributors will be single 2-lane road. The district distributor will connect to Yu Tung Road, which connect further to North Lantau Highway via Tung Chung Eastern Interchange.

2.4.1.107 In terms of existing roads in the vicinity of the PDA at TCW, Tung Chung Road will be maintained as a two-lane (one lane each direction) rural road, while Yu Tung Road (district distributor) and Chung Yan Road (local distributor) will be two lanes per direction. Shek Mun Kap Road, which connects to Tung Chung Road, is proposed to be widened from a single lane access track to a single 2-lane carriageway.

2.4.1.108 PDA at TCW is located immediately south-west of Tung Chung. Chung Mun Road will be extended to serve as the district distributor in the development with two lanes per direction. Chung Mun Road will connect the northern part of the development to Yu Tung Road. There will be two local distributors (L30 and the improved Shek Mun Kap Road) connecting the middle and southern part of the development to Tung Chung Road respectively. A new local distributor (L29) connecting Chung Mun Road and the improved Shek Mun Kap Road will form a corridor to connect other local distributors (L24 – L28) to the external road network via Chung Mun Road, L30 and Shek Mun Kap Road. The local distributors are also extended to connect to existing villages including Ngau Au, Lam Che, Nim Yuen and Mok Ka. Although a few sections of these local distributors (in a form of bridge deck) will have to span over Tung Chung Stream and its tributaries, only the footings of the bridge deck, which are considerably small in size, will be located within the area above high water mark of the CA zone. Considered that there is only relatively limited works for the footing construction and the area affected would likely be the area above high water mark with relatively less disturbance on ecological habitat, adverse impact is thus not anticipated.

2.4.1.109 Regarding the northern portion of the development, Tung Chung Road North, L21 and L31 will be local distributors while L31 will involve formation of a new left-in-left-out vehicular access on Yu Tung Road.

2.4.1.110 In order to cater for the increased population within Tung Chung Valley, Shek Mun Kap Road has to be widened from the existing one-way configuration to two-way configuration to allow for the associated traffic demand. Given there are already existing village houses erected at the southern side of Shek Mun Kap Road, the proposed widening can only be made towards the northern side of the road which will inevitably touch the existing Fung Shui Woods. Although ecological constraints from natural habitat have been taken into account in the design of road connection network in TCW, a minor encroachment onto the Fung Shui Woods with approximately 0.04 ha in size is still inevitable due to limited separation distance away from existing village houses. Ecological impacts due to the road connection networks will be separately discussed in Chapter 9. Table 2.11 summarizes the lengths and number of lanes of distributor roads involved in TCE and TCW.

Table 2.11   Summary table of distributor roads involved in TCE and TCW

Internal Road

Number of Lane

Length (m)

TCE

Road D1

4

930

Road D2

4

790

Road D3

4

840

Road D4

4

220

Road L1

2

390

Road L2

2

730

Road L3

2

720

Road L4

2

460

Road L5

2

360

Road L6

2

300

Road L7

2

430

Road L8

2

110

Road L9

2

110

Road L10

2

80

Tung Chung Road North

2

360

Chung Mun Road

4

310

TCW

Shek Mun Kap Road

2

210

Road L22

2

120

Road L24

2

620

Road L25

2

350

Road L26

2

230

Road L28

2

320

Road L29

2

500

Road L30

2

290

Road L31

2

420

O.  Public Transport Interchanges (PTIs) (Figure 2.19a and Figure 2.19b)

TCE

2.4.1.111 Three PTIs are proposed in TCE. In support of the transport strategy to promote the use of public transport facilities, three public transport interchanges (PTIs) are proposed with one located at the “CDA” Sites of the Metro Core Area, next to the proposed TCE railway station and the other two located at the “RS” Sites of “B1-1” and “C2-2” at the eastern and western parts of the RODP. The size of the PTI will be able to accommodate all public transport traffic demands of the planning proposal. Sky bridges at both sides of the PTI at the “CDA” Sites at the Metro Core Area are proposed to enhance the connectivity between the development area and public transportation as well as the proposed TCE railway station.

TCW

2.4.1.112 In TCW, there are 2 PTIs proposed with one located at the edge of the development and next to the proposed TCW railway station and the other is an on-street bus terminus located along Shek Mun Kap Road.

2.4.1.113 It is expected that majority of the residents would rely on the road-based public transport services, either as the ultimate mode of transport bringing them to their final destinations or just as feeder service. Hence, sufficient road-based public transport facilities would have to be provided to serve the development needs. Implementation of electric buses (e-buses) will be promoted and space provision for charging facilities within the new PTI has been reserved.

P.   Cycle Track Connections (Figures 2.20a and Figure 2.20b)

TCE

2.4.1.114 Cycling connectivity throughout the Project is one of the key urban design concepts driving the configuration of the spatial framework. Primarily the key cycling routes are located in parallel to the open space area and within the Waterfront Promenade connecting directly to the mass-transport facilities in TCE. It is considered that the cycling facilities will create a pleasant, shaded environment that will enhance and encourage the use of non-motorized transportation within the new development areas.

TCW

2.4.1.115 In TCW, cycling routes are strategically located either along the proposed waterfront promenade at Rocky Lion Hill or in parallel to the road system. The consideration is to create opportunities for residents living in Tung Chung valley to access the proposed TCW Railway Station via walking and cycling. In addition, cycle tracks are provided along Tung Chung Stream for leisure purposes and enjoyment of the scenic character of TCW.

Table 2.12 Summary of table of cycle tracks

Cycle Track Alignment

Cycle Track(km)

Tung Chung East

Along proposed road networks

5.3

Along promenade

3

Road P1(Tung Chung to Tai Ho Section)

Along proposed road networks

1.2

Tung Chung West

Along proposed road networks

2.8

Total:

12.3

 

 

Q.  Cycle Park (Figure 2.21)

2.4.1.116 In order to facilitate the alignment of Road P1 (Tung Chung – Tai Ho Section), approximately 9ha of reclamation to the east of PDA at TCE will be required to cater for the loop shape of the alignment. The inner space within the loop will be utilized and constructed in a form of cycling park with an area of approximately 1.4ha. The cycle park is intended to connect with the existing cycle tracks within Tung Chung to form a comprehensive cycle track network.

R.  Infrastructure Outside RODP (Figure 2.22)

2.4.1.117 As mentioned in Chapter 1, a number of associated infrastructures, which are located outside the boundary of the RODP, would be required to support the development. They include:

·         An independent sewer network discharging directly inside the inlet chamber of the existing Tung Chung Sewage Pumping Station (TCSPS) / Siu Ho Wan Sewage Treatment Works (SHWSTW) without any connection and interference to the existing sewers;

·         Two service reservoirs, including one for fresh water and the other for flushing water, with capacities of 55,000 m3 and 11,000 m3 respectively; and

·         Associated modification to road junctions to tie-in with proposed road network.

2.4.1.118 Relevant environmental impact assessment for construction and operation of the above associated infrastructures have been conducted under this EIA.

2.4.2                  Summary of Environmental Considerations of RODP

2.4.2.1           A comparison of the development scale between that in the original EIA SB (i.e. ESB-251/2012) and the RODP is given in the table below.

                         Table 2.13  Comparison of development scale between original EIA SB and RODP

 

Area in ha (Approximate)

ESB-251/2012

RODP [1]

PDA at TCE

110

125

PDA at TCW

175

120

Others

 

 

·       Road P1 (Tung Chung – Tai Ho Section)

-

9 [2]

Total:

285

254

Remark:       

[1] The PDA boundaries of TCE and TCW as shown in RODP are identical to those presented in EIA SB (i.e. ESB-283/2014)

[2] A reclamation of 8.6 ha in size is required for Road P1 (Tung Chung – Tai Ho Section)

2.4.2.2           To conclude, as far as the reclaimed area is concerned, there is a large reduction in the reclaimed area as a result of 1) the deletion of 50ha reclamation in TCW to address public comments during PE process while 2) there is a need for the 9ha reclamation of Road P1 (Tung Chung – Tai Ho Section), and 3) the reclamation in TCE would be increased by 15ha. Taken into account the difference of land area between ESB-252/2012 and RODP, and the area occupied by the associated infrastructure outside PDA (~9 ha), the total development area has been reduced from 285ha to 254ha, with a reduction of approximately 31ha.

2.4.2.3           In fact, through the 3 stages of PE exercises, there have been lot of comments from different stakeholders. All of the comments have been duly considered and where appropriately addressed in the RODP as explained in Tables 2.4 to 2.6. A number of environmental considerations have been incorporated into the RODP to avoid and reduce environmental impacts at the outset. These environmental considerations include the following:

·         All reclamation in TCW has been deleted;

·         Mudflats, mangrove area, Country Park, SSSI have been avoided;

·         All graded historic buildings and built heritages have been avoided;

·         Conservation Area of about 10.42ha has been zoned along the natural section of Tung Chung Stream and Coastal Protection Area of about 4.94ha has been zoned along the coastline near Tung Chung Bay;

·         A River Park of about 3.3ha will be implemented to promote eco-education by setting up viewing decks/ boardwalk, passive recreation zone for appreciation of natural environment;

·         The existing engineered channel section in Tung Chung Stream would be revitalised to connect the natural section of Tung Chung Stream to Tung Chung Bay;

·         The marina has been located as far away from both Tung Chung Bay and Tai Ho Bay and its scale has been reduced;

·         Certain setback distance has been allowed for residential developments from NLH;

·         Noise tolerant buildings have been located between residential buildings and NLH as well as existing railway;

·         Central Park of about 4.8ha has been included in the plan in PDA at TCE.

2.4.2.4           However, despite all the efforts to avoid and minimise environmental impacts, the proposed development would still inevitably impact on some environmental resources. For example, road works and the polder system in TCW would inevitably encroach onto some Fung Shui Woods that are in close proximity (approx. 0.16ha due to polder and 0.04ha due to road works). Another example is that the proposed development would also cause loss in secondary woodland. 

2.4.2.5           Section 3 to Section 12 of the EIA Report have identified all the environmental impacts such as air quality, noise, water quality, sewage and sewerage treatment implications, waste managements, land contamination, ecology, fisheries, landscape and visual, and cultural heritage, for both the construction and operational phases of the Project.  Where necessary, all practicable and necessary mitigation measures are proposed for timely implementation.

2.5                         Consideration of Alternatives

2.5.1                  Background

2.5.1.1           Tung Chung New Town Extension is situated in a unique position within the landscape of Lantau Island. The Project is divided into two distinct zones with different character and development potential based on their topographic context, visibility from surrounding areas and accessibility.

2.5.1.2           TCE is situated across the sea from HKIA, the Hong Kong Boundary Crossing Facilities (HKBCF) and the new TMCLK link that are being constructed. Comprised entirely of reclaimed land, development in TCE will be the natural continuation of the existing Tung Chung New Town, framed against the vegetated backdrop of the North Lantau (Extension) Country Park.

2.5.1.3           Development in TCW balances the sensitive ecological character of Tung Chung Bay, Tung Chung Stream and the rural topography of Tung Chung Valley with more intensive development in the vicinity of the proposed TCW railway station. Residential clusters nested within the valley are carefully located as distinct micro-settlements integrated with the verdant vegetation and existing rural village-type development.

2.5.1.4           Throughout the design process of developing the RODP, extensive efforts have been paid to consider alternatives for various design concept/ elements so as to achieve a well-balanced and yet environmentally acceptable options. A summary of those design concept elements is given below:

·         Marina in TCE;

·         Land use themes in TCE;

·         Reclamation in TCW;

·         Revitalising the existing drainage channel along Tung Chung Stream in TCW;

·         Polder scheme and stormwater attenuation and treatment ponds in TCW;

·         Providing drainage system for TCW;

·         Providing sewerage connection for villages in TCW;

·         Land use zonings along Tung Chung Stream in TCW;

·         Land use zoning along coastline of TCW;

·         Optimizing building heights in TCE and TCW; and

·         Sites for services reservoirs at off-site area.

2.5.1.5           Obviously, there are many other design elements in both TCE and TCW such as sport centres, sewage pumping stations, a central park etc. as described in Section 2.4. All these have been designed and located according to their initiated functions and catchment as appropriate. Hence, design elements are not discussed item by item in terms of consideration of alternatives.

2.5.2                  Consideration of Alternatives for Marina

2.5.2.1           As discussed in Section 2.1.2.5, the northern part of TCE was designated as a potential theme park development when the CFS was first envisioned in 1997.  That potential theme park development had an area of 40ha and remained the same until the Stage 1 PE (Note: The first EIA SB (EIA SB No. ESB-251/2012) has considered this potential theme park development). 

2.5.2.2           During the Stage 1 PE, there were opinions that the needs for the potential theme park should be revisited.  One of the options considered would be to include a marina of appropriate size.  The other alternative considered was to use that for residential development.  A comparison of the benefits and dis-benefits for those alternatives including theme park, marina, open space / GIC and residential developments is given below.

Table 2.14     Comparison of benefits and dis-benefits for alternatives

Options

Benefits

Dis-benefits

Possible Theme Park development

·       Attract lot of tourists which would further improve the economic vibrancy of Tung Chung

·       Serve as an iconic location in Tung Chung New Town

·       Generate large number of employment opportunities

·       A large area of 40ha would be occupied.

·       The traffic such as coaches and private cars induced by the theme park would inevitably generate some concerns from or nuisance to any residents in the vicinity (eg noise, traffic etc), especially during evening periods and holidays during which the local communities may prefer a quieter environment.

Marina

·       Allow a seamless and coherent integration with the water front promenade

·       Serve as an iconic location in Tung Chung New Town

 

·       There are potential issues on the travelling vessels which would inevitably closer to the Chinese White Dolphin’s habitat (see Section 9.7 which has demonstrated that the impacts are acceptable)

Open Space / GIC

·       Allow a seamless and coherent integration with the water front promenade

·       Depends on the actual uses, could serve as an iconic location in Tung Chung New Town

·       Less economic vibrancy as compared to marina and theme park, and hence less employment opportunities

Residential development

·       Additional area for residential development

·       Less economic vibrancy as compared to marina and theme park, and hence less employment opportunities

·       May not serve as an iconic location in Tung Chung New Town

·       Only limited integration with the waterfront promenade

2.5.2.3           It can therefore been seen from the above table that having a marina at the northern part of TCE would have the advantages of generating higher economic vibrancy in that location and hence would provide higher potential for employment opportunities. Although the employment opportunities would be much less than that generated by a theme park, it would have removed any potential concerns on the environmental issues that may be experienced by the residential communities in close proximity.   As compared to open space / GIC and residential development, the proposed marina could provide better and more coherent integration with the water front promenade and therefore generate better economic vibrancy.  Hence, after considering all the pros and cons, a marina would be the preferred option among the alternatives considered. Under the RODP, the number of berthing spaces to be provided would be reduced to about 95 berths to allow space for public waterfront activities.

2.5.3                  Consideration of Alternatives for Land Use Themes

2.5.3.1           There have been altogether 3 stages of PE exercises conducted during the formulation of RODP to solicit public views on the Project throughout the Study. Apart from the original design which has been presented in previous EIA SB (ESB No: ESB-251/2012), 2 themes, i.e. Theme 1: Livable Town and Theme 2: Economic Vibrancy, have been considered as land use options in Tung Chung East. Details of these 2 themes are summarised below.

Theme 1: Livable Town

2.5.3.2           The theme of Livable Town is formulated based on the need of housing supply. Domestic Plot Ratio 6 is adopted at certain focal areas to the southern part near the proposed new railway station where accessibility is higher. The estimated population for this theme would be 110,000, and it would be acceptable in terms of infrastructural capacity, having taken into account the existing developments and all the committed projects.

Theme 2: Economic Vibrancy

2.5.3.3           The aim of this theme is to create a regional commercial hub in TCE alongside housing supply. Apart from the provision of local commercial space, land is also reserved for regional office and retail uses including waterfront retail and dining areas, hotels, shopping malls and a marina.

2.5.3.4           A summary of the key development parameters for the 2 themes is given in the following table. Appendix 2.2 shows the PODP for these 2 themes which had been presented during the PE.

                         Table 2.15  Summary of key development parameters between 2 themes of TCE

Key development parameters

Theme 1: Livable Town

Theme 2: Economic Vibrancy

Estimated Population

110,000

95,000

Estimated No. of Flats

38,000

33,000

Domestic Plot Ratios

3, 4, 5, 6

3, 4, 5

Non-Domestic Plot Ratios

1, 3

2.5, 3

Major Land Uses (approx. ha)

Residential

75

70

Government, Institution or Community Facilities

14

13

Open Space

19

17

Commercial

7

15

Road and Other Uses

5

5

2.5.3.5           Throughout the PE process, there has been no major objection to the proposed reclamation in TCE. Although some green groups expressed concerns on the potential impacts on Tai Ho Wan and dolphin habitats, and the potential impacts that may be caused by the Marina. (Note: the marina at that time can accommodate 350 berths) (see Table 2.4-2.6 for more details on public comments). There is support for both “Theme 1 – Livable Town” and “Theme 2 – Economic Vibrancy” in that population increase should be supported by corresponding economic and job opportunities. A hybrid development of Themes 1 and 2 has therefore been suggested and there is no major objection to the proposed development scale for TCE although there are views that adequate urban design components (e.g. visual corridor / air ventilation etc.) should be incorporated as appropriate. Table 2.16 compares the benefits and dis-benefits for land use themes in TCW.   

                         Table 2.16  Comparison of benefits and dis-benefits for landuse themes in TCW

Option

Benefits

Dis-benefits

Theme 1

(Livable Town)

·         Supply more land to fulfill the social need for residential uses

·         Requires reclamation in TCE

·         Potential for less local employment opportunities and hence less traffic commuting with other parts of HK for daily works

Theme 2

(Economic Vibrancy)

·         Potential for more local employment opportunities and hence less traffic commuting with other parts of HK for daily works

·         Requires reclamation in TCE

·         Supply less land to fulfill the social need for residential uses

Hybrid of Theme 1 and Theme 2 [1]

·         Potential for optimal local employment opportunities and hence optimal traffic commuting with other parts of HK for daily works

·         Requires reclamation in TCE

Remark:       

[1] represents the recommended option.

2.5.4                  Consideration of Alternatives for Reclamations in TCW

2.5.4.1           For the land use option in TCW, there has been strong objections from local communities on the originally proposed reclamation (~50 ha as presented in the Stage 1 PE) as it would encroach onto Tung Chung Bay with rich ecological resources. As such, an option having limited reclamation of 14ha to the north eastern part of the Tung Chung Bay with relatively lower ecological value was incorporated into the draft RODP presented in the Stage 2 PE activities. Areas of higher ecological importance including coastal areas of Tung Chung Bay and along the Tung Chung Stream had already been preserved at that time.

2.5.4.2           However, there were still strong objections from the stakeholders against the proposed 14 ha reclamation in TCW due to concerns on ecological, landscape, visual and environmental.  The 14 ha reclamation in TCW was subsequently removed from the revised RODP presented in the Stage 3 PE.  Hence, it can be seen that the options of having different scale of reclamation, including no reclamation in TCW have been fully considered throughout the process. A latest summary of the key development parameters of TCW is given in Table 2.17. A comparison of benefits and dis-benefits for reclamation in TCW is summarized in Table 2.18.              

                         Table 2.17  Summary of key development parameters of TCW

Key development parameters

TCW

Estimated Population

25,500

Estimated No. of Flats

8,600

Domestic Plot Ratios

1, 1.5, 3, 5, 6

Non-Domestic Plot Ratios

2 - 3

Major Land Uses (approx. ha)

Residential

27.95

Government, Institution or Community Facilities

5.02

Open Space

24.7

Commercial

1.12

Conservation Related Uses

28.6

Village and Others

31.96

 

                         Table 2.18  Comparison of benefits and dis-benefits for reclamation in TCW

Option

Benefits

Dis-benefits

With a 50ha reclamation

·         Supply more land to fulfill the social need for residential uses

·         Direct impacts on the coastal area and estuary of Tung Chung Stream

With a 14ha reclamation

·         Supply less land to fulfill the social need for residential uses

·         Direct impacts on the coastal area and estuary of Tung Chung Stream

Without any reclamation [1]

·         No direct impacts on the coastal area and estuary of Tung Chung Stream

·         Supply least land to fulfill the social need for residential uses

Remark:       

[1] represents the recommended option.

2.5.5                  Consideration of Alternatives for Revitalising the Existing Drainage Channel along Tung Chung Stream

2.5.5.1           As discussed in Section 1.8, a section of approximately 0.5km long of the original Tung Chung Stream had been channelized in 2004 for flood control purposes.  While this channelized section serves as a mitigation measures to protect the local communities from flood risk, it has broken up the ecological connection between the natural section of Tung Chung Stream upstream and Tung Chung Bay downstream. 

2.5.5.2           A total of 3 development options has been considered for this channelized section, including 1) No change to the current channelized section; 2) dechannelize this section without any specific uses; and 3) dechannelize this section and revitalise it to become a river park.

2.5.5.3           Obviously, Option 1 would not help improve the ecological resources of Tung Chung Stream although it would not cause any impacts to Tung Chung Stream as well.  Option 2 would restore the ecological connection between the upstream Tung Chung Stream and the Tung Chung Bay.  This would definitely be a major ecological improvement although the flood risk could be managed by the installation of polder systems as explained in Section 2.4.  Option 3 further enhances the performance of Option 2 by introducing elements of eco-education such as viewing decks/ boardwalk and passive recreation zone for appreciation of natural environment into the design and turn it into a river park.  Option 3 would have obvious advantages over the other 2 options considered and hence has been selected as the preferred option. A summary of comparison of benefits and dis-benefits for revitalizing the existing drainage channel along Tung Chung Stream is given below.

                         Table 2.19   Comparison of benefits and dis-benefits for revitalizing the existing drainage channel along Tung Chung Stream

Option

Benefits

Dis-benefits

As per existing arrangement

·         No impacts to Tung Chung Stream

·         No improvements to ecological resources of Tung Chung Stream

Revitalise existing drainage channel without specific uses

·         Restore the ecological connection between the upstream Tung Chung Stream and Tung Chung Bay

·         Some minor construction works would be inevitable

·         No opportunities to promote eco-education

Revitalise existing drainage channel as part of River Park [1]

·         Restore the ecological connection between the upstream Tung Chung Stream and Tung Chung Bay

·         Introduce opportunities to promote eco-education

·         Some minor construction works would be inevitable

Remark:       

[1] represents the recommended option.

2.5.6                  Consideration of Alternatives for Polder Scheme and Stormwater Attenuation and Treatment Ponds in TCW

2.5.6.1           The PDA at TCW falls within the catchment of Tung Chung Stream in Tung Chung Valley. According to the requirements as stipulated in the DSD Storm Drainage Manual, flood impact assessment has to be carried out to assess the potential flood risk of Tung Chung Stream adjacent to the proposed new extension area under this project. Based on the flood impact assessment, a number of locations along Tung Chung Stream including Shek Lau Po, Mok Ka, Shek Mun Kap etc. have been identified to have potential flooding risk under different return periods. Mitigation measures are hence required to reduce the flood risk of the proposed development area and existing villages to acceptance level. Though approximately 0.16ha of Fung Shui Woods would inevitably be encroached inside Tung Chung Valley under the current RODP (see Section 2.4.1.76), shifting of polder alignment and location to avoid the Fung Shui Woods is considered not feasible as both sides of the polder are bounded by village boundaries and CA zone. Further shifting towards Tung Chung Stream will result in further encroachment on CA zone which is not preferable from environmental point of view.

2.5.6.2           In general, a consideration of strategies including 1) river training, 2) diversion of water, 3) provision of flood detention scheme and 4) rising land platform for the development would be adopted to mitigate against flooding in Hong Kong. However, the unique characteristic of Tung Chung Stream and TCW have limited the application of the most these solutions as described below:

Option 1 - River Training

2.5.6.3           River training always includes excavation to increase the width and depth of the river or straighten local section of the river to enhance its flow capacity. However, as discussed in Section 9.3, Tung Chung Stream is well-known as one of the rivers in Hong Kong with high ecological value and it has been recommended to keep as intact as possible. Any works within the Stream bed such as excavation works for river training would lead to significant impact to its existing condition and ecology. In addition, it is also planned to zone an about 30m buffer from the stream as Conservation Area against any development and impact to the stream. River training is hence considered inapplicable for Tung Chung Stream except a short part of channelized section.

Option 2 - Diversion of Water

2.5.6.4           As mentioned above, Tung Chung Stream is well-known with high ecological and landscape value in Hong Kong. Diversion of significant portion of water from Tung Chung Stream may change the water environment of the Stream that will lead to significant impact to the established ecological system and landscape characteristics along the stream and the area within close proximity. Diversion of the water from Tung Chung is hence considered inapplicable for Tung Chung Stream as flood mitigation measures.

Option 3 – Provision of Flood Detention Scheme

2.5.6.5           The provision of the detention ponds to store excess stormwater temporarily in the detention pond for reducing the peak flow severe rainfall events can help to relieve part of the flooding concerns. However, unless large areas of land around the river is used for the pond, which will involve consideration scale of the earthworks near the river and sterilize a large amount of land originally planned for development, sole provision of flood detention pond would not be able to mitigate all the identified flood risk along Tung Chung Stream.

Option 4 - Rising Land Platform

2.5.6.6           Site formation works including the rise of the land platform of the proposed new extension area is usually the most practicable way to mitigate the flooding concern. In Tung Chung Valley, most of the land around the Stream is owned by individual private owners. Given the need to minimize land resumption as much as possible, it is necessary to allow individuals to initialize the development of their land lots after the rezoning. This arrangement limits the feasibility of the large scale site formation works to rise the entire area of concern to avoid flooding. In addition, with the presence of the adjacent existing villages, solely rise of the land platform for the new development would worsen the possible flooding risk of the adjacent developed village areas where site formation works is infeasible. Hence, it is considered that the large scale site formation works in term of rising land platform is not applicable in Tung Chung Valley.

Recommendations

2.5.6.7           With the consideration of the above-mentioned constraints, a polder scheme, which includes the construction of a perimeter (earth) bund to prevent ingress of flood water into the low-lying area and a pumping station to discharge the flood water within the bund to the nearby river, is hence proposed to the concerned areas with flood risk based on this stage of assessment. The estimated maximum height of the bund as part of the polder scheme will be up to 1.5m subject to the existing topography of the concerned areas. More details of the polder system will be further developed during the detailed design stage. A summary of comparison of benefits and dis-benefits for polder scheme and stormwater attenuation and treatment ponds in TCW is given below.

                         Table 2.20   Comparison of benefits and dis-benefits for polder scheme and stormwater attenuation and treatment ponds in TCW

Option

Benefits

Dis-benefits

Option 1

(River Training)

·         Effective means to alleviate flood risk

·         Requires extensive excavation and hence adverse impacts on ecology and landscape resources

Option 2

(Diversion of Water)

·         Effective means to alleviate flood risk

·         Results in significant change in water environment and hence adverse impacts on ecology and landscape resources

Option 3

(Provision of Flood Detention Scheme)

·         Effective means to alleviate flood risk

·         Large area is required for the flood detention ponds

·         Construction of flood detention ponds would have certain impacts on ecology and landscape resources

Option 4

(Rising Land Platform)

·         Effective means to alleviate flood risk

·         Site formation would have certain impacts on ecology and landscape resources

Combination of Options 2, 3 & 4 [1]

·         Effective means to alleviate flood risk

·         Still some minimal residual impacts on ecology and landscape resources

Remark:       

[1]  represents the recommended option.

2.5.7                  Consideration of Alternatives for Providing Drainage System for TCW

2.5.7.1           New developments would inevitably bring additional surface runoff.  For the proposed development in TCW in particular, the issue of additional runoff discharged into Tung Chung Stream has been cautiously considered from environmental perspective.  

2.5.7.2           The existing catchment at TCW has an area of about 11km2.  It includes the upstream vegetated catchment of the North and South Lantau Country Park with scattered villages and the downstream urban catchment of Tung Chung New Town. Tung Chung Stream is the main river network serving the catchment areas and it discharges downstream to Tung Chung Bay. According to the location of DSD flooding blackspots as at March 2015 available from DSD website, there is no DSD flooding blackspot within the vicinity of the Project.

2.5.7.3           Unlike the conventional drainage system in which surface runoff would pass through gullies to filter off dirt and debris and then discharged into the receiving water bodies, the proposed Sustainable Urban Drainage System (SUDS) within TCW includes a number of new and innovative features to address the concerns of possible impacts on the ecology of Tung Chung Stream and the downstream estuary (See Section 9 for more details). According to the latest design, the new system would include the provision of a series of regional stormwater attenuation and treatment ponds. During rainfall events, flows will be directed into the stormwater attenuation and treatment ponds which are capable of managing peak flows and removing pollutants.  Runoff from the proposed development areas will be directed towards onsite stormwater attenuation and treatment ponds. The ponds will have a vegetated wetland zone and permanent pool, which will create valuable open space amenity and increase biodiversity. The water in the stormwater attenuation and treatment ponds will drain by gravity during small rain events and via high flow pumping stations during heavy rainfall events. The capacity of those stormwater attenuation and treatment ponds would vary from 3,000 – 5,000m3, depending on the catchments to be served.

2.5.7.4           Runoff from roadways, parcels, and existing villages will be diverted via dedicated pipe network and discharged to a primary sedimentation zone. Runoff will be slowed down to allow sediment to settle out. Retaining sediment at the forebay rather than in the larger detention zone will allow for easier removal, thus minimize maintenance costs.

2.5.7.5           At the opposite end of the sedimentation zone, runoff will enter a wide and shallow biofiltration wetland zone. Treatment action will occur as stormwater travels slowly through dense, climate-appropriate landscaping, removing floating debris and encouraging the uptake of nutrients by the plants. Following the biofiltration wetland zone, treated flows will be discharged into the permanent pool or attenuation zone.

2.5.7.6           During large rainfall events, high flows will bypass the sedimentation zone and biofiltration wetland zone and be directed into the attenuation zone. This zone will contain high- and low-flow weirs to mitigate peak flows due to the planned development, keeping the rate of discharge to the Tung Chung Stream at or below the existing condition

2.5.7.7           A total of 2 options have been considered, including the conventional approach and the sustainable drainage systems comprising of a series of regional stormwater attenuation and treatment ponds.

2.5.7.8           As compared to the conventional approach, the sustainable drainage system would offer more advantages to filter as much as pollutant in the surface runoff.  It is therefore considered more favourable to adopt the sustainable drainage system in TCW. The conceptual drawings of the sustainable urban drainage system are shown in Appendix 2.3. The comparison of benefits and dis-benefits for providing drainage system in TCW is summarized below.              

Table 2.21     Comparison of benefits and dis-benefits for providing drainage system in TCW

Option

Benefits

Dis-benefits

Conventional approach with surface runoff discharged to Tung Chung Stream

·         Require less land area for implementation

·         Require less land area for implementation

·         Pollutants in surface run-off will not be filtered

Sustainable urban drainage system to filter Surface runoff before discharged to Tung Chung Stream [1]

·         Pollutants in surface run-off will be filtered as much as practicable and hence impacts on Tung Chung Stream will be minimized as much as practicable

·         Require more land area for implementation

·         Require more maintenance to ensure effectiveness

Remark:       

[1] represents the recommended option.

2.5.8                  Consideration of Alternatives for Providing Sewerage Connection for Villages in TCW

2.5.8.1           The proposed sewerage system comprises construction of SPSs, separate sewerage connections in the form of gravity sewer which runs along Tung Chung Road, Yu Tung Road and future development roads connecting to existing SPSs.  For each of the villages at Shek Mun Kap, Ma Wan Chung, Wong Nai Uk, Mok Ka, Nim Yuen, Lam Che, Ngau Au and Shek Lau Po, a proper village sewerage system would be provided to facilitate the villagers for the connection to the public sewer as appropriate. With the implementation of proper separate sewerage system, it is anticipated that the existing conditions of Tung Chung Stream could be significantly improved. As compared to the option of maintaining the existing systems, the current option would provide an opportunity to improve the water quality in Tung Chung Stream. Table 2.22 summarizes a comparison of benefits and dis-benefits for providing sewerage connection for villages in TCW.

Table 2.22      Comparison of benefits and dis-benefits for providing sewerage connection for villages in TCW

Option

Benefits

Dis-benefits

As per existing arrangement

·         Require no construction works in the vicinity of the villages

·         Any existing sewage from villages may, if not properly discharged  to  Tung  Chung  Stream,  affect  water quality

Provide sewerage connection [1]

·         Sewage from villages could be connected to the new sewer system and hence reduce the pollution loading discharged to Tung Chung Stream

·         Require minor construction works in the vicinity of the villages  

Remark:       

[1]  represents the recommended option.

2.5.9                  Consideration of Alternatives for Land use Zonings Along Tung Chung Stream

2.5.9.1           Tung Chung Stream has been known for its biodiversity and ecological values, and landscape resources.  The ecological surveys conducted under this study has also confirmed its importance (see Section 9 for more details of the ecological surveys).

2.5.9.2           In terms of landuse zoning for conservation, there are 2 possible zonings, including Green Belt (GB) and Conservation Area (CA). The planning intention of GB zone is primarily for defining limits of urban and sub-urban development areas by natural features and to provide passive recreational outlets. In comparison, CA would require a more stringent planning intention which aims to protect and retain the ecological features of important items from adverse effect of development.

2.5.9.3           CA would provide a better planning protection of Tung Chung Stream and hence has been adopted as the zoning for the area along the Tung Chung Stream except for the section of engineered channel which would be revitalized and the River Park). The total area of CA along Tung Chung Stream is approximately 10ha. A summary of comparison of benefits and dis-benefits for land use zonings along Tung Chung Stream is given below.

                         Table 2.23        Comparison of benefits and dis-benefits for land use zonings along Tung Chung Stream

Option

Benefits

Dis-benefits

Zoned as GB

·         Provide certain planning protection of Tung Chung Stream

·         Relatively less protection for Tung Chung Stream

Zone as CA (except for the engineered channel which would be revitalized) [1]

·         Provide better planning protection of Tung Chung Stream

·         Less development scope for area zoned as CA

 

Remark:       

[1] represents the recommended option.

2.5.10             Consideration of Alternatives for Land Use Zonings Along Coastline of TCW

2.5.10.1      Similar to Tung Chung Stream, the natural coastline of TCW has been identified to have high rich ecological and landscape resources such as mangroves and mudflats. The development has avoided physical encroachment onto these mangroves and mudflats. A total of 3 possible land use zoning options including GB, CA and Coastal Protection Area (CPA) have been considered.

2.5.10.2      The planning intention of GB and CA zone has been described in Section 2.5.5, while CPA is intended to conserve, protect and retain the natural coastline and the sensitive coastal natural environment.

2.5.10.3      For the coastline to the west of Wong Lung Hang Nullah, ecological surveys have confirmed that the conditions of the mangroves and mudflats are more intact and thus a CPA zoning is therefore proposed to separate the proposed development from habitats with high ecological value.  For the natural coastline to the east of Wong Lung Hang Nullah, however, the size of the patch of mangroves is smaller with close distance with the existing urbanised land. Though RO zone is proposed to the east with encroachment onto the small patch of mangroves, the importance of mangroves have been put into consideration and the actual pathway lying within the RO zone is designed to totally avoid the mangrove footprint. A summary of comparison of benefits and dis-benefits for land use zonings along coastline is given below.

                         Table 2.24        Comparison of benefits and dis-benefits for land use zonings along coastline

Option

Benefits

Dis-benefits

No special zoning

·         More development scope for coastal area

 

·         No planning protection to suit the habitats along the coastline

Combination of GB, CA, CPA and RO [1]

·         Provide an optimal planning protection to suit the habitats along the coastline

·         Less development scope for coastal area

 

Remark:       

[1]  represents the recommended option.

2.5.11             Consideration of Alternatives for Optimising Building Height

2.5.11.1      Urban design principles raised by the public are also incorporated into the planning and design principle for the RODP in which stepped building height from inland towards the waterfront will be maintained. In TCE, the building heights near the coastline are approximately 40m and the building heights will increase to 195m towards the proposed railway station. Similarly, for TCW, the building heights near the proposed railway station are 70m and the height would decrease to 25m especially in the vicinity of existing villages. As compared to the options of having more uniform building height, the current option of having stepped building height would avoid “wall effect” developments along the coastal area as far as possible. A summary of comparison of benefits and dis-benefits for optimising building height is given below.

                         Table 2.25  Comparison of benefits and dis-benefits for optimising building height

Option

Benefits

Dis-benefits

More uniform building height across different land lots

·         Nil

·          “Wall effect” developments along the coast line as far as possible

Stepped building height from inland towards the waterfront [1]

·         Avoid and minimize “wall effect” developments along the coast line as far as possible

·         Nil

Remark:       

[1]  represents the recommended option.

2.5.12             Consideration of Alternatives for Sites for Service Reservoirs

2.5.12.1      As discussed in Section 2.4, the RODP would introduce an additional population of approximate 144,400 to Tung Chung New Town.  This additional population and associated employment would definitely require additional supply of both fresh water and flush water.  According to the current findings of engineering studies, it is essential to have new services reservoirs, including one for fresh water and one for flush water.

2.5.12.2      The proposed locations for these services reservoirs are in the vicinity of the existing reservoirs along Wong Lung Hang Road.  The advantages of this option is that the existing access road would be utilised and there is no need to construct another access road which would inevitably require extensive site formation work and hence cause additional habitat loss.  Besides, some of the site formation works at that location have been constructed decades ago during the construction of the existing reservoirs and hence the additional amount of spoil and trees to be removed would be less.  It should also be noted that the service reservoirs were originally proposed at Tai Ho area in the CFS conducted in 1997. However, considering the rich ecological resources in Tai Ho area, alternative location within the North Lantau (Extension) Country Park was considered as the service reservoir has to be built on hillsides to provide sufficient elevation difference for water flow. However, in order to address the public concerns on works within country parks, the service reservoirs are now proposed to locate next to the existing service reservoirs in which some of the site formation work has been previously constructed. This would definitely reduce the disturbance to the natural habitat around that area. A summary of comparison of benefits and dis-benefits for service reservoirs is given below.

                         Table 2.26  Comparison of benefits and dis-benefits for service reservoirs

Option

Benefits

Dis-benefits

Away from the existing services reservoirs

·         Nil

·         Need for another access road and more construction works

·         More C&D material generated

·         More habitat loss

In the vicinity of the existing services reservoirs [1]

·         No need for another access road and hence less construction works

·         Less C&D material generated

·         Less habitat loss

·         Nil

Remark:       

[1] represents the recommended option.

2.6                         Proposed Construction Methodologies for Land Uses and Design

2.6.1.1           Section 2.4 has presented the key elements for the RODP. The construction methodologies for these key elements have been duly examined to take into account of many considerations including environmental consideration, practicability etc. The recommended construction methodology of different key construction works are summarized below. Section 2.7 summarises the consideration of alternatives for these construction methodologies.

2.6.2                  Reclamation

2.6.2.1           As discussed in Section 2.3, the reclamation in TCW has been deleted. However, there would still be a reclamation above high water mark of 120.5ha for TCE and 8.6 ha for the Road P1 (Tung Chung – Tai Ho Section). For the reclamation in TCE, a non-dredged approach has been recommended to minimise environmental impacts. However, while dredging work has been preferably avoided, filling work would be inevitable. The actual construction sequences and processes of main reclamation filling shall be further developed by the contractor but the envisaged construction processes of the adopted drained reclamation summarised below:

1.        Installation of the silt curtain;

2.        Laying of geotextile and sand blanket over the marine sediment (i.e. over the existing seabed) prior to reclamation filling;

3.        Installation of band drains by marine based method to accelerate the consolidation of marine sediment;

4.        Construction of seawall to allow at least 200m leading edge before reclamation filling;

5.        Underwater filling from sand blanket to +2.50mPD;

6.        Land filling from +2.50mPD to formation level; and

7.        Surcharging (including construction and removal)

2.6.2.2           The above major processes are described in more details as below:

1.      Installation of the Silt Curtain;

2.6.2.3           A perimeter silt curtain enclosing the reclamation site will be installed during the whole construction period. A second layer of silt curtain will be installed near the active stone column installation. At the marine assess, staggered layers of silt curtain will be provided to reduce sediment loss migrating across the silt curtain system.

2.       Laying of Geotextile and Sand Blanket

2.6.2.4           Laying of geotextile and sand blanket over the marine sediment over the existing seabed shall be carried out prior to reclamation filling as one of the measures to prevent mud wave.

2.6.2.5           In order to prevent the mud wave, deposition of the sand blanket shall be carried out in layers not exceeding 0.5m thick, with a leading edge between consecutive layers. The minimum length of the leading edge required would usually in the order of 5-10m and would be subject to further development during the detailed design stage, taking into account various seabed material strength parameters.

2.6.2.6           In laying of geotextile, tight connection must be ensured between geotextile sheetings (usually by sewing or stapling for woven geotextile, and thermal bonding for non-woven geotextile) to form geotextile panels up to the limit that can be handled by marine craft. The overlapping between geotextile panels must also be adequate (typical 1-2m).

3.       Installation of Band Drain

2.6.2.7           Band drains will be installed by barges equipped with installation equipment. The drains are instated by pushing a rectangular hollow steel mandrel into the seabed statically by the weight of the installation unit. If hard material is encountered, penetration will be assisted with vibration by hydraulic vibrator. Rising of the mandrel will only be permitted after completion of a drain installation.

4.      Construction of Seawall to allow at least 200m Leading Edge before Reclamation Filling

2.6.2.8           Detailed construction sequence for seawall refers to Section 2.6.3 below.

5.      Underwater Filling (up to +2.50mPD);

2.6.2.9           Underwater filling will be carried out by various methods such as derrick barge and tug boat depending on the availability of working space, water depth and types of fill materials. Public fill, sand fill or a mix of sand fill and public fill will be adopted as the underwater filling materials subject to the availability of these materials. Public fill (if available) will be used as far as possible as one of the key fill materials for reclamation filling. Leading edge seawall of at least 200m long shall be allowed before the commencement of the underwater filling.

2.6.2.10      To prevent occurrence of mud wave, underwater reclamation fill will need to be deposited in thin layer with adequate leading edge between consecutive layers; (commonly in one-meter thick for each layer and 10 to 15 metres for the minimum leading edge subject to the design).

6.      Above water filling from +2.50mPD to formation level;

2.6.2.11      Deposition of fill materials for land filling will be carried out by various methods such as dump truck, derrick barge, pelican barge, bulldozer and excavator depending on the availability of access, working space, water depth and types of fill materials. Public fill, sand fill or a mix of sand fill and public fill will be adopted as the above water filling materials subject to the availability of these materials. Public fill (if available) will be used as far as possible as one of the key fill materials for reclamation filling. Vibratory rollers will be used to compact the fill after filling to the required degree of compaction.

7.      Surcharging

2.6.2.12      Surcharge will be built up similar to those of above water filling. Public fill (if available) will be used as the surcharge materials. Surplus surcharge materials at the completion of the project shall be disposed off site. During each stage of land formation, surcharge removed from a completed works area will be reused as fill material in other active works areas, thereby minimising the amount of surplus surcharge material that needs to be disposed of offsite after completion of all land formation.

 

2.6.3                  Seawall Construction

2.6.3.1           The details of construction sequences and processes of seawalls shall be further developed by the contractor but the envisaged construction processes of the adopted seawall options are summarized below. To minimize the water quality impact during the construction stage, the reclamation work would normally only be commenced after the adjacent seawalls (~200m in length) are completed.

2.6.3.2           The envisaged construction processes for non-dredged seawall with pipe pile structure supported by ground improvement - stone column are listed as follows:

1.        Installation of the silt curtain (if not in-place);

2.        Lay geotextile and deposit rock fill (gravel) blanket;

3.        Install stone columns by marine based plant;

4.        Install pipe pile structures;

5.        Fill inside pipe pile structures;

6.        Install corrosion protection system (if necessary) and construct capping beam/ connecting tie;

7.        Construct sloping berm in front of pipe pile structure (if necessary).

2.6.3.3           The sectional details of the seawall are designed in accordance with different climate wave conditions and seabed level. In some local area with shallow water depth, the pipe pile structure may not be required and the seawall can be mainly supported by ground improvement - stone column. The envisaged construction processes of sloping seawall and vertical seawall are listed as follows.

Sloping Seawall supported by Stone Column

Vertical Seawall supported by Stone Column

1.    Installation of the silt curtain (if not in-place);

2.     Lay geotextile and deposit rock fill (gravel) blanket;

3.    Install stone columns by marine based plant;

4.     Deposit rock fill core material on top of the rockfill layer;

5.     Place the underlayers;

6.     Place the armour rock;

7.     Install the bermstones; &

8.     Construct the coping

1.     Installation of the silt curtain (if not in-place);

2.     Lay geotextile and deposit rock fill (gravel) blanket;

3.     Install stone columns by marine based plant;

4.     Place the leveling stones;

5.     Place the pre-fabricated concrete blockwork elements;

6.     Deposit filter layers at the back of concrete blocks; &

7.     Construct the coping

2.6.3.4           The key construction processes for typical seawall are described in more details below:

1.      Installation of the Silt Curtain;

2.6.3.5           A perimeter silt curtain enclosing the reclamation site will be installed during the whole construction period. A second layer of silt curtain will be installed near the active stone column installation. At the marine access, staggered layers of silt curtain will be provided to reduce sediment loss migrating across the silt curtain system.

2.      Lay geotextile and deposit rock fill (gravel) blanket;

2.6.3.6           A layer of geotextile and stone blanket of approximate 2m thick shall be installed on the existing seabed prior to installation of stone columns. The stone blanket serves the purpose of preventing the bulging of the top part of stone columns.

3.      Installation of Stone Columns

2.6.3.7           Stone columns are generally installed to facilitate the consolidation of marine sediment and improve the strength of the marine sediment layer. The sizes and the details of the stone columns shall be determined during detailed design.

4.      Installation of Pipe Pile Structure

2.6.3.8           For pipe pile structure, the pipe pile could be pre-fabricated off-site and then toward to the installation point for installation using vibrators. It is envisaged the pre-fabricated process will be conducted outside HK and the pile structure will be transported by barges to site. When delivered to site, temporary guide frames may be installed on site in advance to secure the alignment of the pipe pile as necessary.

5.      Deposition of Fill Materials

2.6.3.9           A geotextile and sand blanket layer will be deposited on top of the seabed acting as filter and buffer between the founding stratum and the rock core, as well as for the control of mud wave.  A leading length of approximately 200m is allowed for seawall construction. 

2.6.3.10      After the fill has been formed at around –2.5mPD, a bottom-split barge would no longer be applicable in depositing the fill material.  A derrick barge would be employed to continue the rock filling works and subsequently the underlayer as well as the protective armour rock layer.  The derrick barge would also assist in depositing the filter layer at the back of the seawall before depositing the sand fill in the reclamation areas.

6.      Installation of Seawall Underlayers & Rock Armour

2.6.3.11      The seawall rock armour and underlayers should be placed from the bottom to the top of each section with the aid of derrick barges.  This could ensure that individual rock pieces interlock with each other and do not segregate and the interstices are kept free of small rock fragments.  These requirements are particularly important as they relate directly to the design assumptions covering stability against wave attack and wave run-up. 

2.6.3.12      Armour is the most important layer for the stability of the rubble mound.  The armour layer should be placed as soon as possible following the placement of the underlayer to avoid damage to these layers.   Each armour should be inspected to ensure its integrity before it is placed onto its designated location.

2.6.3.13      In addition to survey checking on the slope profile after completion of deposition works, visual inspections shall also be carried out regularly on the sloping seawall structure whenever possible from the seaside.  Diver inspections shall also be carried out after the deposition work is completed and a final inspection shall be carried out after the whole length of seawall is completed.  If any significant holes or areas with infilled interstices are identified, rectification works shall be promptly carried out. 

7.      Installation of Bermstones

2.6.3.14      Bermstone is the key element that should be installed as soon as practicable to its designated position in protecting the toe of the seawall structure from being affected by scouring due to waves and currents. The early deposition of bermstones would enhance the overall integrity and protect the overall structure from environmental attack.  

2.6.3.15      The bermstones will be installed with the aid of a derrick barge.  They will be deposited underwater onto the seabed carefully by grabs.  Diver inspection shall be carried out after installation to ensure that the bermstones have been placed properly in accordance with the design requirements and any gaps between bermstones are kept to a minimum.

8.      Placement of Concrete Blocks

2.6.3.16      Precast concrete blocks are to be placed for vertical seawall in accordance with the designed sectional configuration and corner details for each layer of blocks.  Placement of concrete blocks is carried out following the deposition of a layer of leveling stones to ensure the vertical alignment of the seawall blocks.  Diver inspection will be undertaken to confirm the positions of leveling stones and bottom layer(s) of concrete blocks.  Derrick barge with loading cables/wires is normally employed to correctly position the seawall blockworks.  Regular survey checks will be undertaken to further review the horizontal and vertical alignment.

9.      Construction of Coping

2.6.3.17      The last step in seawall construction is the casting of in-situ concrete copings.  This activity should be carried out as late as possible to eliminate any additional settlement on the soil stratum after being surcharged by the seawall structure and possible damage by frequent loading/unloading of construction materials and heavy machineries.  It is recommended that the seawall coping will only be cast at the end of the superstructure construction rather than at the reclamation completion stage.

2.6.4                  Site Formation

2.6.4.1           The site formation to be carried out mainly in Tung Chung Valley (TCV-6 and TCV-7) along Tung Chung Road, Tung Chung West (TCW-2) at the west of the town park and the proposed service reservoirs next to the existing one. Surplus inert Construction & Demolition (C&D) material generated in the site formation would be reused in the concurrent projects especially for the reclamation filling works in Tung Chung East.

2.6.5                  Road Works and Utilities

2.6.5.1           The proposed road works and utilities include road networks, drainage systems, sewerage networks, water supply networks and utility construction to support the development in the new development area in TCE and TCW.

2.6.5.2           Except for the construction of the viaduct of Road P1 (Tung Chung – Tai Ho Section), typical construction method at-grade road construction would be adopted. The works involve earthworks, utilities laying, laying of sub-base materials and laying of bituminous or concrete surfacing layers.

2.6.6                  Viaduct of Road P1 (including Tai Ho Interchange)

2.6.6.1           The substructures of the viaduct at Road P1 (Tung Chung – Tai Ho Section) including Tai Ho Interchange (THI) will take the form of reinforced concrete (RC) columns & pile caps founded on RC bored piles. It is envisaged that the superstructures of the Road P1 Viaduct, for accommodating the dual-2 carriageway, will be constructed by one of the following methods:

2.6.6.2           Precast segmental method: With the bridge deck constructed as precast segments (each a few metres long) which are lifted into position and then stitched & prestressed together. This method was adopted extensively for numerous bridgework projects in Hong Kong in recent years (e.g. Shenzhen Bay Bridge, Deep Bay Link, Route 8);

2.6.6.3           In-situ balanced-cantilever method: With the bridge deck constructed as in-situ segments by a travelling formwork (each segment was concreted in-situ and then prestressed onto the preceding segment). This method was adopted in some of the projects in Hong Kong (e.g. Castle Peak Road Improvement Siu Lam Viaduct.

2.6.6.4           The above methods do not differ significantly in terms of environmental impacts. The selection of method is, rather, driven by consideration on engineering constraints and the individual contractors’ available equipment/resources in-hand. It should be noted that although the precast segmental method does not require mega lifting equipment as that for the precast spans method, the length of spans that the precast segmental method can sustain is usually limited to about 80 m (due to limitation on the capacity of the launching girder for such a method). For the purpose of this assessment, it is appropriate to assume that the length of spans for precast segmental method should be limited to 75 m.

2.6.7                  Underpass at Road D1 in Tung Chung East

2.6.7.1           Cut-and-Cover method would be adopted for the underpass at Road D1 in Tung Chung East, which involving trench-excavation (i.e. open-cut) followed by in-situ construction of the tunnel structures.

2.6.8                  Landscaping Works at Open Spaces, Amenity Areas and Slopes

2.6.8.1           Landscaping works at open space, amenity areas and slopes will be provided after site formation works and slope works. As these will mainly involve planting and minor pedestrian facilities, environmental impact is not anticipated.

2.6.9                  Polder Scheme and Stormwater Attenuation and Treatment Ponds in Tung Chung West

2.6.9.1           The polder scheme proposed in TCW as part of the flood protection measures will be generally in form of an earth berm less than approximate 1.5m in height while the stormwater attenuation and treatment ponds will be in form of normal water pond with various depth and planting for sedimentation and water treatment purpose. The works involve earthwork, laying of lining and some water pipe laying works. Suitable landscaping works would also be implemented for the polders and stormwater attenuation and treatment ponds.

2.6.10             Rising Main connecting Siu Ho Wan Sewage Treatment Works

2.6.10.1      Rising main connecting Siu Ho Wan Sewage Treatment Works will be carried out after the completion of the reclamation for Road P1. Cut-and-cover method would be adopted as far as possible for the rising main, which involves trench-excavation (i.e. open-cut) followed by in-situ construction of the rising main. For those portion across the North Lantau Highway, trenchless method such as pipe jacking will be adopted.

2.6.11             Salt Water and Fresh Water Service Reservoirs

2.6.11.1      The major construction works will include typical earthwork, concrete works for service reservoir structures, pipeworks and modification work to existing access road. Both cut-and-fill slopes shall be formed for the formation of platform for the service reservoirs construction and for the modification work to existing access road.

2.6.12             Proposed New Railway Stations in Tung Chung East and Tung Chung West

2.6.12.1      Proposed railway stations and its associated railway system in TCE and TCW will be conducted under separate study subject to the implementation programme by the Government. For the purpose of assessing the cumulative construction phase impacts, a cut-&-cover methodology is assumed for the new station in TCW and at-grade construction for the new station in TCE.

2.6.12.2      Tunnel Boring Method (TBM) is proposed for the construction of part of the tunnel since the current alignment is proposed to pass underneath the existing Man Wan Chung bay area and also underneath the hill crests to the northeast of Ma Wan Chung which has a height up to +50mPD. A minimum of 1.0d, where d is the tunnel diameter, clearance has been allowed from the seabed level or ground level to the top of the tunnel during the design of the vertical alignment of the tunnel. The depth of the track level ranges from roughly -5mPD at the existing Tung Chung Station to -18.25mPD at the proposed TCW station.

2.6.13             Buildings

2.6.13.1      As discussed in Section 2.9, the first batch of population intake will commence around Year 2023 and would last for 7 years progressively until Year 2030 for the last batch. The building construction will therefore align with the population intake programme. In TCE, Phase 1 Buildings will be mainly the western part of the proposed development area on newly reclaimed in TCE, site TCV-6 and TCV-7 in Tung Chung Valley along Tung Chung Road and site TCW-2) in TCW at the west of the town park. Apart from several educational sites (site DO-03, DO-04) in TCE, operation of Phase 1 Building will also include a salt water pumping station, a sewage pumping station and electricity substation. Phase 2 Building will be mainly the north-western part of the proposed development area on newly reclaimed in TCE (site D1-1, D1-2, D2-1, D2-2, D2-3 and D2-4) while Phase 3 Building will be located at the centre of the proposed development area in TCE (site A1-1, A1-2, A2-1, A2-2, A2-3 and A2-4). The remaining development area in TCE will be included in the last phase of the development for population intake. In TCW, after the Phase 1 development along the Tung Chung Road, the remaining areas will be developed gradually from the downstream of Tung Chung Stream up to Shek Mun Kap area together with all the necessary supporting infrastructure. Full population intake of all new development under this project is expected to be by around 2030.

2.6.13.2      Construction activities would include concrete foundation works, formworks and superstructures.

2.6.14             Others

2.6.14.1      The existing Pak Mong Pier, a solid jetty, will be affected by the proposed reclamation works. Hence, re-provision of the facilities in a form of landing steps along the waterfront promenade at the TCE will form as part of the reclamation works.

2.7                         Consideration of Alternatives for Construction Methodologies

2.7.1                  Alternative Methodology for Seawall Construction

2.7.1.1           As discussed in Section 1.2, approximately 120 ha of water at the north of the existing Tung Chung new town is proposed to be reclaimed to form land for TCE and 9 ha for Road P1 (Tung Chung – Tai Ho Section). Seawall with a length of approximately 3,400m is hence required to support the proposed reclamation and protect it against wave and current action. In general, seawall is a retaining structure to protect the reclaimed fill. Therefore, the design of seawall should achieve a minimum Factor of Safety to ensure the stability against the slip failure and provide adequate bearing capacity to support the seawall without significant settlement. In accordance with Clause 4.3 of Port Works Design Manual (2002), Part 4, the global factor of safety against soil shear failure along critical slip surface will be checked to ensure the stability of the proposed seawall structure.

2.7.1.2           Considering seawall is always founded on seabed comprised of marine sediment which is generally soft in nature, various options of the seawall design have been adopted in Hong Kong or overseas reclamation projects to achieve the necessary stability requirements of the seawall. A discussion of these options is presented below.

Option 1 - Fully Dredged Seawall

2.7.1.3           Fully dredged seawall is widely adopted in Hong Kong for the past decades as the preferred seawall scheme in reclamation projects. It involves removal of the marine sediment in existing seabed for forming the seawall base so as to ensure the stability of the seawall and minimize the settlement of the seawall. A fully dredged trench will be required to form and fill by sandfill / rockfill or rockfill only, followed by laying of seawall core then the armour layers on the sloping seawall surface as shown in the typical section in Appendix 2.4. Technically feasibility of this method is well-recognized in the long list of its track records in past reclamation projects in Hong Kong including West Kowloon Reclamation, Penny Bay’s Reclamation, Chek Lap Kok Reclamation for new airport etc and its construction works is generally familiar with local marine works contractor.

2.7.1.4           The adoption of fully dredged seawall will involve large amount of dredging for the formation of dredged trench which will lead to significant impact to the water quality especially while the proposed reclamation is in close proximity to Tai Ho Inlet and Tung Chung Bay where is well known ecological resources. In addition, a large amount of sand / rock fill materials to be used to backfill the dredged trench for the foundation of the seawall will also contribute some adverse impact to the water quality. In view of the lack of the mud pits in Hong Kong, necessary disposal of the dredged marine sediment is another key concern of the adoption of the fully dredged option and may impose constraint to the use of the fully dredged option, especially if some of the underlying marine sediment is contaminated.

2.7.1.5           Furthermore, in order to transport the dredged marine sediment to designated location for disposal and bring sufficient amount of the sand/rock fill materials to backfill the dredged trench, it may require marine barges which will lead to possible increase of the marine traffic issues. The noise and emission from this marine vessels will also contribute to the noise impact and air pollution impact of the adjacent areas and marine ecology.

Option 2 - Partial Dredged Seawall

2.7.1.6           Partial dredged seawall is similar to Option 1: Fully dredged seawall although not all the soft marine sediment underneath seawall will be removed and replaced by sand/rock fill to form the foundation of seawall. The marine sediment will only be removed to an certain extent such that sufficient level of the stability of the seawall can be achieved. Compared to Option 1, the amount of dredged marine sediment to be disposal and fill materials to be required for filling up of the dredged trench can be reduced to certain extent. However, those concerns similar to fully dredged seawall including need of the disposal site for dredged materials, water quality impact due to dredging, need of large amount of filling materials for dredged trench and induced marine traffic can only be relieved to certain extent but still cannot be eliminated.

Option 3 - Non-dredged Seawall with Ground Improvement

Option 3a - Non-dredged Seawall with Band Drains and Surcharge

2.7.1.7           The method of band drains and surcharge has good performance and track records in Hong Kong on the control of long term residual settlement. Apart from settlement control, the design of seawall should achieve a minimum factor of safety to ensure stability against slip failure as required in Clause 4.3 of Port Works Design Manual, Part 4.  The stability of seawall mainly depends upon the shear strength capacity of the underlying soil stratum including marine sediment and alluvium.  In TCE, the marine sediment is generally soft in nature with thickness from about 9m to 15m.

2.7.1.8           Although the method of band drains and surcharge could accelerate the consolidation settlement, improvement to the shear strength capacity of marine sediment is indispensable.  Improvement of the shear strength of marine sediment by this method is relatively less effective compared to other ground improvement methods such as stone column and deep cement mixing etc, and is highly depending localised ground condition and its performance need to be carefully verified by considerable amount of in-situ monitoring and field testing. If necessary, a very long surcharge period will be required to ensure sufficient degree of consolidation as well as gain in shear strength is achieved which will always lead to high uncertainty to the stability and the construction programme.

2.7.1.9           Based on the current assessment of seawall stability for the non-dredged method where the soft marine sediment is left in-place, the use of band drains and surcharge (with nominal surcharge height and a reasonable surcharging period of around 6 to 8 months) fail to achieve the required seawall stability against slip failure. Therefore, the use of band drains and surcharge is considered inadequate to be used for the non-dredged method of seawalls.  

Option 3b - Non-dredged Seawall with Stone Columns 

2.7.1.10      Stone Columns are typically used in soft soil applications to facilitate consolidation of the compressible soils for the drained reclamation and increase the shear strength of the soil when dealing with stability issues associated with the seawall and breakwater structures. It is achieved by the use of vibro-displacement or vibro-replacement method. These techniques involve the installation of gravel compacted piles commonly referred to as “stone columns” into the soil compressible soils.

2.7.1.11      Stone columns are achieved by the use of the vibro-displacement/vibro-replacement method – vibro-flotation under either land-based or marine based operation. The penetration of the vibro-flot in soils produces a cavity that is subsequently filled with gravel, either feed from the top of the hole or using a bottom feed system. The compaction of loose soils or uncompacted fills can be achieved at depth by using the process of vibro-flotation. The vibro-flot is then reintroduced into the gravel and the procedure repeated until adequate stone compaction and column size has been achieved. Each vibro-compaction phase is carried out in 300 to 500 mm steps, proceeding from the bottom to the top so as to create a "stone column" with load bearing properties and vertical drainage effects. No spoil is generally required to be disposed for the use of stone column method but a considerable amount of the gravel is required which is generally required to be inputted from Mainland China. The application of stone columns is not extensive as band drains and surcharge system in Hong Kong and its cost is relatively expensive. 

2.7.1.12      In recent HKBCF reclamation project, stone column has been largely adopted in different types of non-dredged seawalls for the proposed around 140 hectares reclamation. It has been solely adopted in some portions of the seawall to improve the underneath soft marine sediment to form a firm foundation for the seawall while in some other portion stone column and steel cellular structure are jointly applied as another type of non-dredged seawall system.

2.7.1.13      Stone column as ground treatment for non-dredged seawall design is adopted in HKBCF reclamation project. It is also identified that solely use of stone column to support the seawall will generally require a large amount of the stone column especially while the thickness of marine sediment is large and the water is deep. It may sometimes lead to constraint on provision of the large amount of plant, supply of gravel and marine traffic. Combination of stone column and other non-dredged seawall method such as pipe-pile and steel cellular structure can help to relieve the over dependence of single component of works which is always considered to be inappropriate for large scale project.

2.7.1.14      In view of the above, the use of the non-dredged seawall with stone column is still considered to be one of the feasible option for the proposed TCE and Road P1 (Tung Chung – Tai Ho Section) reclamation especially for those portion with relative shallow water and thinner marine sediment . The schematic cross section is shown in Appendix 2.4.

Option 4 - Pipe-pile wall

2.7.1.15      Apart from the ground improvement methods discussed above, pipe pile wall is considered to be the alternative option to support the proposed seawall structures without dredging the marine sediment.  The seawall will be supported by a row of contiguous pipe pile wall in connection with another row of contiguous pipe pile as shown in Appendix 2.4. All the pipe piles will be penetrated through the whole depth of marine sediment and soft alluvial clay and founded on either stiff alluvium or weathered rock stratum. In order to provide sufficient structural capacity under the aggressive sea condition over the whole design life, the pipe pile would be filled with structural concrete with reinforcement cage from top of the pile down to approximately 5m below seabed. 

2.7.1.16      The pipe pile wall is not uncommon in the marine structures.  However, measures should be provided to prevent loss of fine materials from reclamation through the contiguous pipe piles.  These include the tight control on the construction tolerance of the piles, use of anchor system between consecutive pipes behind the piles. In addition, the installation of pipe piles is through the vibratory/press-in method.

2.7.1.17      One of the concerns for adopting pipe pile wall is that the pile pipes are visually intrusive. This problem can be resolved by lowering the crest level of the pipe pipes. The level should be designed to be just above high water level such that the capping of the structure can be installed in dry environment. A sloping berm topped with rock armours can also be proposed in front of the structure, except for sections where vertical seawalls are required for berthing.  The rock armours on the sloping berm would be designed against wave action in the same way as a sloping seawall, and at the same time provide substrates for fish spawning ground, coral growth, etc as in traditional seawall. The area within the pipe pile structure and that below the sloping berm can be coupled with other ground improvement measures where necessary. A layer of rock armours or artificial units could be placed for the topping of the completed pipe pile structure. 

2.7.1.18      When compared to other ground improvement methods, relatively high cost and long construction period are expected for the construction and associated testing of the piles.  The implications to the overall cost and programme may cause this option less favourable than other ground improvement methods.  In addition, the maintenance of pipe pile wall against corrosion under the aggressive sea condition is an important issue that need to be addressed.  However, there is an option that the pipe-pile method is jointly adopted with the other ground treatment method. With this arrangement, the concerns on the necessary large amount of plant and gravel for stone column (as mentioned in previous section) and relatively high construction cost for pipe pile wall can be relieved. In view of the above, the combined use of stone column and pipe pile wall is considered as one of the feasible option for the proposed TCE reclamation.

Option 5 - Steel Cellular Structure

2.7.1.19      Steel Cellular Structure can be proposed as non-dredged seawall. The steel cellular structure consists of large diameter circular cells of about 30m diameter formed by interlocking of a large number of approximately 500mm wide steel sheet piles.  The cells are then linked together by arc sections to form a continuous seawall structure.  The cellular structure, once driven into alluvium layer and backfilled up its top level, will become a massive gravity retaining structure which can retain the reclamation fill. The schematic cross-sections and isometric view are shown in Appendix 2.4 respectively.

2.7.1.20      Though this non-dredged seawall scheme is only firstly adopted in HKBCF reclamation and has not been widely adopted in Hong Kong, they are widely used for maritime structures in South Korea, Japan, Singapore, Greece, Denmark, Chile, France, Canada, US, etc. Steel sheet pile cellular structures have also been adopted for port developments in India, Indonesia and Egypt.  In particular, this seawall scheme has been adopted for land reclamation in Jurong Island, Singapore where the average seawater temperature is at times similar to and at other time higher than that in Hong Kong waters. 

2.7.1.21      Similar to pipe pile wall scheme, one of the concerns for adopting steel cellular structure is that the steel sheet piles are visually intrusive. This problem can be resolved by lowering the crest level of the steel cellular structure. The level should be designed to be just above high water level such that the capping of the cellular structure can be installed in dry environment. A sloping berm topped with rock armours can also be proposed in front of the structure, except for sections where vertical seawalls are required for berthing.  The rock armours on the sloping berm would be designed against wave action in the same way as a sloping seawall, and at the same time provide substrates for fish spawning ground, coral growth, etc as in traditional seawall. The area within the steel cellular structure and that below the sloping berm can be coupled with other ground improvement measures where necessary. A layer of rock armours or artificial units could be placed for the topping of the completed cells. 

2.7.1.22      With the provision of a sloping berm in front of the seawall cells and due consideration of a gain in shear strength of the marine sediment  during consolidation process with adoption of some ground treatment method such as stone column, the steel sheet pile cellular structures can be designed to be omitted in the long run based on seawall stability assessment.  In this regard, the long-term corrosion protection measures for the steel sheet pile cells could be omitted as well.

2.7.1.23      Based on the experience from HKBCF, the adoption of the steel cellular structure will generally require relatively higher level of construction technology, marine vessels with very large lifting capacity, considerable size of on-site and off-site pre-fabrication yard and larger working space but it has its advantage of relative large stiffness to cope with the situation with great water depth and thick soft marine sediment  underneath so as to provide a more robust seawall design.

2.7.1.24      In the area of proposed TCE reclamation, the water level is not as deep as HKBCF while the marine sediment is generally thinner than HKBCF. In addition, available working space is relative tight along the existing seafront. The use of the steel cellular is limited and less effective in view of the above and hence not considered.

Recommendations of Construction Methodology for Seawall

2.7.1.25      The above sections have described a total of 5 options for the construction for seawall. The following table summarises the benefits and dis-benefits identified.

Table 2.27                      Comparison of seawall design options

Options

Benefits

Dis-benefits

Option 1 –

Fully Dredged Seawall

·       Well proven technology in Hong Kong.

·       Relatively fast if dumping site for marine sediment is available and fill source is sufficient.

·       Familiar by most of the local contractors.

·       Better control of the stability and settlement as all the compressible soft sediment underneath the seawall are removed.

·       Large amount of dredged marine sediment (up to approximate 4.4Mm3 (in-situ volume)) to be disposed.

·       Large amount of the fill materials (up to 4.4Mm3 (in-situ volume)) to be required to fill the dredged trench as the foundation to support the seawall on top.

·       Increase of the marine vessels trips (up to around 8,800 trips assuming 1,000m3 vessels) for the transportation of the relatively large amount of dredged marine sediment and fill materials.

·       Increased marine vessels trips will lead to increased impact to noise and air.

·       Increased marine vessels trips will lead to increased disturbance to the China White Dolphin.

·       It is currently lack of dumping site for marine sediment in Hong Kong, the necessity disposal of up to 4.4Mm3 marine sediment will impose a large pressure to the remaining capacity of existing mud disposal grounds in Hong Kong.

·       Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent.

·       In general, less environmentally friendly.

Option 2 - Partial Dredged Seawall

·       Well proven technology in Hong Kong.

·       Relatively fast if dumping site for marine sediment is available and fill source is sufficient.

·       Familiar by most of the local contractors.

·       Relative less marine sediment to be disposal compared to fully dredged seawall.

·       Relative less fill materials to be required compared to fully dredged seawall.     

·       Even though less than fully dredged seawall, relative large amount of dredged marine sediment (up to approximate more than 2.0Mm3 (in-situ volume)) is still required to be disposed.

·       Even though less than fully dredged seawall, large amount of the fill materials (up tomore than approximate 2.0Mm3 (in-situ volume)) is still required to fill the dredged trench as the foundation to support the seawall on top.

·       Even though less than fully dredged seawall, increase of the marine vessels trips (up to around 4,000 trips assuming 1,000m3 vessels) for the transportation of the relatively large amount of dredged marine sediment and fill materials.

·       Even though less than fully dredged seawall, increased marine vessels trips will lead to increased impact to noise and air.

·       Even though less than fully dredged seawall, increased marine vessels trips will lead to increased disturbance to the China White Dolphin.

·       It is currently lack of dumping site for marine sediment in Hong Kong, the necessity disposal of up to 3.7Mm3 marine sediment will impose a large pressure to the remaining capacity of existing mud pits in Hong Kong.

·       Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent.

·       Relative higher risk of settlement and instability compared to fully dredged seawall.

Option 3 –

Non-dredged Seawall with Ground Improvement

·       Minimal or even no marine sediment are required to be disposed.

·       Significantly reduced demand of fill materials for filling of the dredged trench compared to fully dredged / partial dredged seawall.

·       Significantly reduced marine vessels trips are required for transportation of dredged marine sediment and fill materials compared to fully / partial dredged seawall.

·       In general, more environmentally friendly.

·       Less familiar by local contractors.

·       Relative longer construction period (if band drain and surcharge method is adopted) may be required compared to fully dredged seawall.

·       Some ground improvement technique (such as band drain and surcharge) may not be applicable for seawall from the technical consideration.

·       Relative longer mobilisation time from overseas may be required for some of ground improvement techniques.

·       Relative higher cost compared to fully dredged / partial dredged seawall.

Option 4 –

Pipe-pile wall

·       Minimal or even no marine sediment are required to be disposed.

·       Significantly reduced demand of fill materials for filling of the dredged trench compared to fully dredged / partial dredged seawall.

·       Significantly reduced marine vessels trips are required for transportation of dredged marine sediment and fill materials compared to fully / partial dredged seawall.

·       Relatively lower requirements of construction technology compared to Option 5 including marine vessels with very large lifting capacity, considerable size of on-site and off-site pre-fabrication yard and larger working space…etc.

·       Jointly use of pipe-pile wall with Option 3 - ground improvement method (stone column) to relieve over dependence of single component of works which is considered inappropriate for large scale project.

·       In general, more environmentally friendly.

·       Less familiar by local contractor.

·       Relative longer construction period may be required compared to fully dredged seawall.

·       Some ground treatment (despite much less than those required for Option 3) will still be required to strengthen the ground to support the pipe-pile wall.

·       Measures should be provided to prevent loss of fine materials from reclamation through the contiguous pipe piles. 

·       Relative higher cost compared to fully dredged / partial dredged seawall.

·       Maintenance of pipe pile wall against corrosion under aggressive sea condition via different corrosion protection measures is one of the concern.

Option 5 –

Steel Cellular Structure

·       Minimal or even no marine sediment are required to be disposed.

·       Significantly reduced demand of fill materials for filling of the dredged trench compared to fully dredged / partial dredged seawall.

·       Significantly reduced marine vessels trips are required for transportation of dredged marine sediment and fill materials compared to fully / partial dredged seawall.

·       Long term corrosion protection measures for steel sheet pile cells (as required by Option 3 – Pipe pile wall scheme) could be omitted if a sloping berm in front of the seawall cells is provided.

·       Relative larger stiffness to cope with the situation with great water depth and soft marine sediment.

·       Jointly use of steel cellular structure with Option 3 - ground improvement method (stone column) to relieve over dependence of single component of works which is considered inappropriate for large scale project.

·       In general, more environmentally friendly.

·       Less familiar by local contractor.

·       Require relatively higher level of construction technology, marine vessels with very large lifting capacity.

·       Relative longer construction period may be required compared to fully dredged seawall.

·       Some ground treatment (despite much less than those required for Option 3) will still be required to strengthen the ground to support the steel cellular structure.

·       Relative higher cost compared to fully dredged / partial dredged seawall.

·       Relative larger working space is required for construction works.

·       Considerable size of on-site and off-site pre-fabrication yards are required.

 

2.7.1.26      It can therefore be seen that Option 3 (ground improvement by stone column) or combined use of Option 3 and Option 4 (pipe-pile wall) have  the biggest environmental benefits in terms of minimisation of the dredging, reduced amount of marine sediment to be disposed, reduced amount of required fill materials and reduction of the marine vessels movement with their correlated air and noise impact. On this basis, Option 3 or combined use of Option 3 and Option 4 have been selected as the preferred option for implementation.

2.7.2                  Alternative Construction Methodology for Reclamation

2.7.2.1           As discussed in Section 1.1, apart from the approximately 3,400m seawall, the main reclamation above high water mark of 120.5ha of land for TCE and 8.6ha of land for Road P1 Tung Chung – Tai Ho Section) is another key component of the land formation for the proposed new town extension in TCE. In general, the reclamation methodology may be summarised as (1) Fully dredged, (2) Partially dredged and (3) Non-dredged (Drained) reclamation. 

Option 1 - Fully-dredged Reclamation

2.7.2.2           Under this form of reclamation, the layer of marine sediment is fully dredged.  Dredging will be carried out down to a firm stratum, commonly the alluvial layer. Typical arrangement is presented in Appendix 2.5 for reference. This serves to eliminate post-reclamation settlement due to consolidation of soft marine sediment layer. On some particular projects, surcharging is carried out even if fully-dredged reclamation is adopted due to the presence of soft alluvial clay in the underlying alluvial layer.  The required surcharge period is nonetheless much shorter than the case of non-dredged reclamation.

2.7.2.3           After the dredging works, reclamation fill will then be deposited onto the dredged seabed, using either sandfill, or public fill, or a combination thereof. Priority will be given to consider the use of public fill as it is the government policy to make beneficial use of public fill generated by the construction industry as far as possible.  However, it should be noted that reclamation with sandfill is generally more expeditious than using public fill. 

2.7.2.4           The fully dredged reclamation method could achieve substantial programming advantage, not only because its surcharge period (if any) will be much shorter than that in the case of non-dredged reclamation, but also because reclamation filling could proceed more expeditiously.

2.7.2.5           The disadvantage of fully-dredged reclamation is that the dredged marine sediment will need to be disposed, thus consuming the space of mud-pits in Hong Kong which is already tight or cross boundary. Furthermore, the volume of reclamation filing in fully-dredged reclamation will be larger than the case of non-dredged reclamation, thus involving higher construction cost for the reclamation and increased marine traffic and adhere risk.

2.7.2.6           With the consideration of latest government policy as stated in Environment, Transport and Works Bureau (ETWB) TCW No. 34/2002 of keeping the marine sediment in place, the use of fully dredged method will not be considered under this Project.

2.7.2.7           If fully dredged method is adopted, it is estimated approximately 15.5Mm3 (in-situ) of marine sediment is required to be dredged and disposed. In addition, similar of fill materials will be imported to fill the dredged trench to form the foundation of the seawall.

Option 2 - Partially-dredged Reclamation

2.7.2.8           Partially dredged reclamation method is similar to those of fully-dredged method while not all the underlying soft marine sediment are to be removed. Typical arrangement is presented in Appendix 2.5 for reference. Partial removal of marine or alluvial deposits, leaving the lower, stiffer or stronger deposits in place reduces the dredging and fill quantities compared to the fully dredged method. However, it should be noted that better control is required than for full removal for the final trimming in dredging and for initial fill placement, to avoid future differential settlement. The remaining layer of marine or alluvial deposits will consolidate by vertical drainage upward through the fill and downward, if the layer beneath the soil is sufficiently permeable. The construction programme must still allow time for this consolidation and band drains with preloading may still be required if the available time is short. The extent of marine or alluvial deposits to be left in place must be decided after investigation and is subject to detailed design. It will depend on the amount of settlement predicted to occur after the completion of the reclamation compared to the magnitude of differential settlement which can be tolerated in the particular situation.

2.7.2.9           Similar to fully-dredged reclamation, partially-dredged still leads to concern on the necessary disposal of marine sediment, import of large amount of the fill materials for the dredged trench and increased amount of marine traffic, although the concern is relatively less than the fully-dredged method.

2.7.2.10      If partially dredged method is adopted, it is estimated approximately 8.0Mm3 (in-situ) of marine sediment is required to be dredged and disposed. In addition, similar of fill materials will be imported to fill the dredged trench to form the foundation of the seawall.

Option 3 - Non-dredged (Drained) Reclamation

2.7.2.11      Instead of dredging the marine sediment, drained (non-dredged) method is one of the commonly adopted reclamation method in Hong Kong. The non-dredged reclamation method will leave the marine sediment in place, but will add measures to prevent the occurrence of mud wave, and adopt band drain and surcharge system to accelerate consolidation of the marine sediment and alluvial clay so as to mitigate the risk of post-reclamation settlement. 

Band Drains and Surcharge

2.7.2.12      During reclamation, the dissipation of excess pore water pressure in the soft compressible soils during primary consolidation would take place with drainage paths in the vertical direction which relates to the thickness of the marine mud and soft alluvial clay. The consolidation period can be shortened significantly by reducing the drainage path. This is achieved by the installation of band drains through the highly compressible layers such as marine mud/alluvial clay layer, at typically 1.2m spacing in triangular pattern in plan. The presence of band drains provide additional shortened drainage path in the horizontal direction for the pore water in the soil matrix. It enables the pore water to drain horizontally to the conduits, and then vertically through the conduits to the free drainage layer provided on top of the marine sediment. In this way, the flow path is reduced considerably and hence the consolidation process greatly accelerated.

2.7.2.13      The consolidation process of marine sediment and soft alluvial clay can be further accelerated by the use of surcharge (or pre-loading). The objective of surcharging is to induce settlement greater than that predicted under the service loading. 

2.7.2.14      Band drains can be installed by both marine and land method subject to site constraints, type of fill materials, water depth and design. Normally, the marine-based method always has programme advantage due to early start of the consolidation in early stage of the reclamation filling. Band drain and surcharge method is a proven technique in Hong Kong and a lot of previous site data are available to demonstrate its performance to accelerate the consolidation settlement. Typical arrangement is shown in Appendix 2.5 for reference.

Prevention of Mud Wave

2.7.2.15      As the soft marine sediment is still in place (and have not been treated) at the time of reclamation filling, mud wave is one of the key concerns for non-dredged reclamation method and a series of methods have been well developed in previous completed projects as listed below to prevent the occurrence of mud wave during reclamation filling.

·         Tight connection must be ensured between geotextile sheetings (usually by sewing or stapling for woven geotextile, and thermal bonding for non-woven geotextile) to form geotextile panels up to the limit that can be handled by marine craft. The overlapping between geotextile panels must also be adequate (commonly specified as 1 to 2 metres).

·         Deposition of the sand blanket shall be carried out in layers not exceeding 0.5m thick, with a leading edge between consecutive layers.  .

·         Deposition of the reclamation fill shall be carried out in layers of limited thickness and with a leading edge between consecutive layers.  .

·         Close monitoring of the reclamation shall be carried out, including regular underwater survey.

2.7.2.16      If non-dredged method is adopted for the reclamation, no or minimal marine sediment is expected to be dredged and disposal.

Recommendations of Construction Methodology for Reclamation

2.7.2.17      Different from fully-dredged or partially dredged method, no marine sediment is required to be disposed for the non-dredged reclamation method and hence concern on the limited availability of the mud pit for disposal can be eliminated. In addition, the required large amount of fill material for the filling of the dredged trench is no longer required for the non-dredged method. Both of them can greatly reduce the marine traffic for the transportation of the dredged marine sediment and fill materials which will have beneficial effect to the air and noise impact (due to marine vessels movement) as well as the marine traffic risk. Furthermore, band drain and surcharge is well-developed method in Hong Kong as adopted in many previous reclamation projects and is generally with a relative low cost compared to fully/partially dredged method. The following table summarises the benefits and dis-benefits  identified.


 

Table 2.28     Comparison of reclamation design options

Options

Benefits

Dis-benefits

Option 1 –

Fully Dredged Reclamation

·       Well proven technology in Hong Kong.

·       Relatively fast if dumping site for marine sediment is available and fill source is sufficient.

·       Familiar by most of the local contractors.

·       Better control of the stability and settlement as all the compressible soft marine sediment underneath the seawall are removed.

·       Large amount of the fill materials (up to 15.5Mm3 (in-situ volume)) to be required to fill the dredged trench as the foundation to support the seawall on top.

·       Increase of the marine vessels trips (up to around 30,000 trips assuming 1,000m3 vessels) for the transportation of the relatively large amount of dredged marine sediment and fill materials.

·       Increased marine vessels trips will lead to increased impact to noise and air.

·       Increased marine vessels trips will lead to increased disturbance to the China White Dolphin.

·       It is currently lack of dumping site for marine sediment in Hong Kong, the necessity disposal of up to 15.5Mm3 marine sediment will impose a large pressure to the remaining capacity of existing mud disposal grounds in Hong Kong.

·       Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent.

·       Sand is generally adopted for the backfilling of the dredged trench. There is constraints or difficulty nowadays to import large amount of sand from Mainland China under the current policy.

·       In general, less environmentally friendly.

Option 2 –

Partially-dredged Reclamation

 

·       Well proven technology in Hong Kong.

·       Relatively fast if dumping site for marine sediment is available and fill source is sufficient.

·       Familiar by most of the local contractors.

·       Relative less marine sediment to be disposal compared to fully dredged reclamation.

·       Relative less fill materials to be required compared to fully dredged reclamation.

 

·       Even though less than fully dredged reclamation, relative large amount of dredged marine sediment (up to approximate more than 8.0Mm3 (in-situ volume)) is still required to be disposed.

·       Even though less than fully dredged reclamation, large amount of the fill materials (up to more than approximate 8.0Mm3 (in-situ volume)) is still required to fill the dredged trench as the foundation to support the reclamation on top.

·       Even though less than fully dredged seawall, increase of the marine vessels trips (up to around 16,000 trips assuming 1,000m3 vessels) for the transportation of the relatively large amount of dredged marine sediment and fill materials.

·       Even though less than fully dredged reclamation, increased marine vessels trips will lead to increased impact to noise and air.

·       Even though less than fully dredged reclamation, increased marine vessels trips will lead to increased disturbance to the China White Dolphin.

·       It is currently lack of dumping site for marine sediment in Hong Kong, the necessity disposal of up to 8.0Mm3 marine sediment will impose a large pressure to the remaining capacity of existing mud pits in Hong Kong.

·       Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent.

·       Relative higher risk of settlement and instability compared to fully dredged reclamation.

Option 3 –

Non-dredged (Drained) Reclamation

·       No marine sediment are required to be disposed.

·       Well proven technology adopted in many reclamation projects in recent years.

·       Significantly reduced demand of fill materials for filling of the dredged trench compared to fully dredged / partial dredged reclamation.

·       Significantly reduced marine vessels trips are required for transportation of dredged marine sediment and fill materials compared to fully / partial dredged reclamation.

·       In general, more environmentally friendly

·       Considerable amount of instrumentation should be installed to monitor the trend of settlement during surcharging period to ensure the residual settlement criteria is met.

·       Relative longer construction period may be required for surcharging compared to fully dredged method (if disposal site for marine sediment and fill source is sufficient).

·       Extension of the surcharging period may be required during construction phase if the settlement performance is out of the expectation which will eventually lead to extension of the overall programme. Considerable amount of the ground investigation and laboratory testing will be required during detailed design stage to provide sufficient data for better estimation of settlement behaviour.

 

 

2.7.2.18      It can therefore be seen that Option 3 has the biggest environmental benefits in terms of no dredging of marine sediment, reduced amount of fill materials, reduction of marine vessel trips for transportation with correlated air and noise impact, on this basis, Option 3 has been selected as the preferred option for implementation.

2.7.2.19      In view of the above, the use of the non-dredged reclamation with band drain and surcharge is preferable than other reclamation methods taking account of the cost and most importantly environmental concerns. Therefore, non-dredged reclamation with band drain and surcharge is assumed to be adopted in the proposed reclamation in Tung Chung East.

2.7.3                  Alternative Construction Methodologies for Road P1 (Tung Chung – Tai Ho Section)

2.7.3.1           As discussed in Section 1.1, the Road P1 (Tung Chung – Tai Ho Section) will serve as a primary distributor parallel to the NLH and connects the districts of Tung Chung, Siu Ho Wan and Sunny Bay. Its configuration, routing and interchange arrangement are hence strategically related to the planning of the whole North Lantau.

2.7.3.2           As identified by the traffic analysis in the Traffic Impact Assessment (TIA) report, the Road P1 (Tung Chung – Tai Ho Section) connecting existing Ying Hei Road to the proposed THI will be a major external highway connection for TCE.  The Road P1 (Tung Chung – Tai Ho Section) has the below key functions:

·         To relieve the future traffic over-capacity of Tung Chung East Interchange;

·         To divert the air and noise impact of through traffic away from the existing Tung Chung town centre;

·         To serve as an alternative access to TCE in case of traffic accidents in Tung Chung East Interchange and Yi Tung Road.

2.7.3.3           Two possible structural options have been conducted for the Road P1 (Tung Chung – Tai Ho Section), including viaduct option (Option 1) and the reclamation option (Option 2) which are shown in Appendix 2.5. The typical cross sections are shown in Appendix 2.5. Key summaries of these 2 options are listed as below.

Construction Option 1 – Viaduct Option

·         Road P1 (Tung Chung – Tai Ho Section) is constructed in the form of elevated viaduct adjacent to the existing seawall.

·         The soffit of the structure needs to be higher than the wave crest and hence the road level is at about +8.0mPD.

·         The viaduct is aligned to avoid conflict with the TM-CLKL piers and to minimise impact to the existing seawall armour rock.

·         The length of the viaduct structure is approximately 1,200m and might not be cost-effective for setting up a precast segment yard.   In-situ balanced cantilever by form traveller can be one of the possible construction methods.  Since the water depth is shallow in the area, temporary deck might be required in this option for the construction of the bridge foundation.

·         The viaduct is outside the “built up” area stipulated in the ETWB TC 02/2013 Greening on Footbridges and Flyovers and therefore is not covered by the circular.  Greening planter is not recommended on the viaduct due to the maintenance difficulties of planters on primary distributor viaduct.

·         As stipulated in the Highways Department (HyD) Structures Design Manual (SDM), utility is not usually allowed on viaduct structure.  As such the Road P1 (Tung Chung – Tai Ho Section) will not serve as a trunk utility corridor in this option.

·         In this viaduct option, the view from / to the shoreline is unavoidably blocked by the viaduct structure. The region-wide cycle track along Northern Lantau can be modified from the existing seawall maintenance access track. Technically, a  long cycle and footbridge can be  constructed along the northern

·         The viaduct foundation is close to the ecological sensitive area of Tai Ho Wan and hence water pollution control measures are required during construction.

·         The long-term maintenance cost for viaduct is generally higher than the at-grade road.

Construction Option 2 – Reclamation Option

·         In the reclamation option (Option 2), the Road P1 (Tung Chung – Tai Ho Section) is constructed on a strip of newly reclaimed land north of MTR rail line at Tai Ho.

·         The formation level is at about +6.0mPD above the wave crest level and tie-in with the adjacent ground.

·         The at-grade carriageway is aligned to avoid conflict with the TM-CLKL piers.

·         ETWB TC 02/2012 Allocation of Space for Quality Greening on Roads is followed.  In the technical circular, a 2.5m wide amenity strip, excluding profile barrier, at the central reserve is required.  Adding space for profile barrier, the total width is 3.3m.  On roadside, HKPSG and TPDM recommend 3m wide for large tree planting on major roads.

·         In this option, an at-grade promenade and region-wide cycle track can be constructed along the shoreline of the newly reclaimed land, offering higher leisure value.  A 6m promenade and 4m standard 2-way cycle track are assumed.  This promenade has a potential to link up the promenade in Tung Chung East Development in the west to form a region-wide promenade along North Lantau.  Screening might be considered at the amenity to screen off air and noise impact from Road P1 (Tung Chung – Tai Ho Section) to the promenade.

·         If necessary, the at-grade Road P1 (Tung Chung – Tai Ho Section) and the footpath/ trail might in the future serve as utility corridor for trunk utility.

·         The total width of the Road P1 (Tung Chung – Tai Ho Section) corridor is approximately 40m and a significant width is for greening following the guidance and for promenade.

·         The reclamation is close to the ecological sensitive area of Tai Ho Wan and hence water pollution control measures are required during construction. Elevated deck structure is proposed across the important Tai Ho outlet. The other box culvert connecting Tai Ho Wan to Tung Chung Bay needs to be extended.

·         The long-term maintenance cost for at-grade road is generally lower than the viaduct.

Recommendations for Construction Methodology for Road P1 (Tung Chung – Tai Ho Section)

2.7.3.4           To conclude, both options are technically feasible in term of engineering. However, as the reclamation option (Option 2) is recommended as it offers a continuous promenade and shoreline to the public which suits the planning of the North Lantau, and the visual impact of the reclamation option is also relatively lower. The pros and cons are summarised in the Table 2.29.

 

Table 2.29     Comparison of Viaduct and Reclamation Options (Options 1 & 2) for Road P1 (Tung Chung – Tai Ho Section)

Criteria

Option 1 – Viaduct

Option 2 - Reclamation

Planning & Land Use

·   Shoreline is blocked by elevated viaduct.

·   Continuous promenade on North Lantau offers high leisure value.

Traffic

·   Same

·   Same

Environment

·   Less disturbance to seabed

·   High visual impact

·   More disturbance to seabed

·   Lower visual impact

Impact to Locals

·   Unattractive elevated structure

·   Offer more regional open space

Engineering

·   Feasible

·   Feasible.

·   Negative skin friction allowed in TM-CLKL piers.

Programme

·   Similar

·   Similar

Cost

·   Higher maintenance cost for structure

·   Lower maintenance cost for at-grade roadwork

2.7.3.5           The Road P1 is not only serving the TCE but its connectivity is closely related to other development on Northern Lantau, in particular the nearby Siu Ho Wan Development. During the course of the Study, it is understood that the Siu Ho Wan Development is still under review and the land use type and development parameters are not yet available. There are high uncertainties on the development scale as well as its traffic infrastructure. Several options of connecting TCE to THI (Options A to F) are explored and shown in Appendix 2.6. The pros and cons among these options are listed below and are summarised in the Table 2.30.

Connectivity Option A

·         Road P1 (Tung Chung – Tai Ho Section) is designed to suit mainly the needs arisen from TCE. The Road P1 (Tung Chung – Tai Ho Section) from Tung Chung East side is connected directly to THI. A structural provision is reserved for future extension of the Road P1 to the Siu Ho Wan direction.

·         The scheme has the advantage of no junction in-between Tung Chung East and Tai Ho Interchange. This offers the highest traffic speed in-between Tung Chung East and the Tai Ho Interchange and hence is more convenient to the Tung Chung East road users.  The THI is mainly constructed to serve Tung Chung area in this scheme.

·         The key drawback of this option is that there is no interchange with the Siu Ho Wan development.  The potential traffic from Siu Ho Wan side cannot enter the Tai Ho Interchange. This arrangement limits the external connectivity of the potential Siu Ho Wan development and can in term limits the development potential of the Siu Ho Wan development.

·         Due to the restraint to the future external connectivity of Siu Ho Wan development, this option is not pursed.

·         The option serves as a fallback option if it is confirmed in the future that there will be no development in Siu Ho Wan and no interchange between Siu Ho Wan side and Tai Ho Interchange is required.

Connectivity Option B

·         Road P1 (Tung Chung – Tai Ho Section) is designed with an aim to serve both the TCE and the Siu Ho Wan Development. A large-capacity grade separated roundabout interchange was proposed at the Siu Ho Wan reclamation area. The interchange collects / distributes all the local traffic from Tung Chung and Siu Ho Wan and then joins together to the THI for expressway access. The relatively long separation between THI and the at-grade roundabout not only provides the gradient for the level difference, but also provides length for traffic to weave to the appropriate entry lanes.

·         The advantage of the option is that the design provides a high traffic reservation for future development in Siu Ho Wan. The scheme has a higher traffic capacity comparing to the other schemes.

·         The at-grade interchange collects / distributes all the local traffic from Tung Chung and Siu Ho Wan and hence can reduce the overall junction number along Road P1 (Tung Chung – Tai Ho Section).

·         The disadvantage is that the scheme involves extensive reclamation and cannot be justified under the TCE alone. In fact the scope is outside the EIA Study Boundary of the Tung Chung Remaining Development project. It is difficult to be implemented under the EIA and funding process of Tung Chung Remaining Development alone.

·         The implementation and programme of this highway scheme is therefore tied in with the Siu Ho Wan development.  Since there is still high uncertainty on the feasibility and programme of Siu Ho Wan development, there is higher risk on the implementation programme of this scheme.

·         The scheme requires land in the Siu Ho Wan development planning boundary.  This can be a constraint for the land use in the Siu Ho Wan planning.

·         Although the initial reclamation area of this scheme seems large, the reclamation is in fact within the Siu Ho Wan planning area.  This option can reduce the extra reclamation directly north of Tai Ho Wan as in Options D to F.

·         Since this option will affect the planning of the Siu Ho Wan development, the option is not pursed.

Connectivity Option C

·         Road P1 is designed with traffic connectivity in-between Options A & B. An elevated diamond interchange is proposed north of the THI to collect / distribute all the local traffic from both Tung Chung and Siu Ho Wan.  The option provides the connectivity of THI to both directions of Road P1 (Tung Chung – Tai Ho Section).

·         The diamond interchange with traffic signal is one of the possible junction arrangements. A variation is to adopt an elevated roundabout forming a double roundabout with the Tai Ho Interchange.  The junction spacing is similar the above 2 variations and the pros and cons are similar.

·         The key advantage of this option is that the land requirement footprint is the smallest among all the options.  The disturbance to the seabed, the visual impact and the cost is therefore the lowest among all the options.

·         The interchange can be partly within the scope of Tung Chung Remaining Development and partly within the Siu Ho Wan Development. Structural provision can be allowed on the elevated interchange for future ramps to the Siu Ho Wan side.

·         However, a major disadvantage is that the elevated diamond interchange and THI has relatively small junction separation at about 120m. (Transport Planning and Design Manual (TPDM) recommends 300m junction separation for primary distributor level.)  The close junction separation can highly reduce the traffic capacity of the junction groups and hence reduce the development scale that the interchange can support.  Especially since the connection is between the primary distributor and an expressway, the relatively short junction spacing might not be preferable for new interchange design.

·         Given the potential adverse impact to the traffic performance due to relatively short junction spacing, this option is nor preferable in traffic planning.

Connectivity Option D

·         This option explores the “mirroring” of Option B to the Tung Chung side to offer a longer junction spacing whilst avoiding the planning impact to Siu Ho Wan development.

·         In this scheme, the at-grade roundabout collects / distributes all the local traffic from Tung Chung and Siu Ho Wan and then joins together through a connecting viaduct.  No grade separation for Road P1 (Tung Chung – Tai Ho Section) bypassing the junction is provided.

·         The location of the at-grade roundabout is carefully selected to have a balance between junction spacing / ramp gradient and the reclamation limit. If the roundabout is put further west, the reclamation extent will be enlarged.  If the roundabout is put further east, it will not provide sufficient junction separation / length for climbing up to the Tai Ho Interchange.

·         The geometry of the connecting viaduct between the at-grade roundabout and the Tai Ho Interchange is restrained by the desirable minimum radius of curvature and the entry arm deflection at the at-grade roundabout.  Due to these constraints, there is a land in-between the roadwork available for future use if desirable.  The local road access to the site can be provided from the Siu Ho Wan side beneath the connecting viaduct.

·         The scheme is within the study boundary of Tung Chung and allows future connectivity between Siu Ho Wan and Tai Ho Interchange.

·         Compared to Options E & F, the scope of work is less in this scheme and hence has relatively low cost and visual impact.

·         The major problem in this arrangement is that the through traffic along Road P1 (Tung Chung – Tai Ho Section) will also enter the at-grade roundabout. The lack of grade separation increases the traffic burden to the at-grade roundabout. It is assessed that the capacity of the at-grade roundabout is marginal in this scheme and has small reserved traffic capacity in response to any increase in development.

·         Given the marginal insufficient traffic performance, Options E & F with grade separations are further explored.

Connectivity Option E

·         This option has similar connection arrangement to Option D, but a grade separation is provided along Road P1 (Tung Chung – Tai Ho Section).

·         The grade separation significantly enhances the traffic performance of the roundabout and hence resolves the traffic problem in Option D.

·         In this scheme, the roundabout is elevated whereas the Road P1 (Tung Chung – Tai Ho Section) through traffic is at-grade. This arrangement has two benefits in term of traffic. Firstly, a speed limit of 80kph can be maintained along Road P1 for through traffic offering faster running speed.  Secondly, the gradient of the ramps connecting to the roundabout will assist the acceleration and deceleration of the traffic entering and existing from Road P1 (Tung Chung – Tai Ho Section) and hence improves the traffic safety.

·         Underpass is not considered as it will be in conflict with the box culvert extension from Tai Ho Wan. The road levels of TM-CLKL viaducts are at +30mPD and hence provides sufficient headroom for 3-level of road.  The pier of the ramp should be arranged such that the piling work would not be obstructed by the TM-CLKL viaducts abovehead.

·         The drawback is that the scheme is presuming that there will be a future extension of Road P1 (Tung Chung – Tai Ho Section) to the Siu Ho Wan direction (no matter it is connecting to development or as a bypass). Since the roundabout is in elevated structure, it is more costly and less flexible for future design modification in case there is significant planning assumption change.

·         Comparing all the options, Option E is among the options which have the best traffic performance. It provides a reasonable provision for future connection to the Siu Ho Wan side and does not restraint the planning flexibility of the Siu Ho Wan side. As such it is recommended as the option to be pursed forward for further study.

Connectivity Option F

·         This option is very similar to Option E, except the Road P1 (Tung Chung – Tai Ho Section) is elevated and the roundabout is at-grade.

·         Since the roundabout is at-grade and the elevated Road P1 (Tung Chung – Tai Ho Section) above the junction is to be constructed by others, it offers slightly higher flexibility for future design modification in case there is significant planning assumption change.

·         The highway design requires a much longer length of parabolic transition curve for design speed of 80kph.  The length of the crest curve is to provide sufficient forward visibility to the traffic and therefore is related to traffic safety.  On the east side of the at-grade roundabout, there is not sufficient length for a Road P1 (Tung Chung – Tai Ho Section) with design speed of 80kph to get down and run beneath the connecting viaduct to Tai Ho Interchange.  Road P1 (Tung Chung – Tai Ho Section) with 80kph is not technically feasible in this arrangement. Therefore in this option Road P1 (Tung Chung – Tai Ho Section) can only be designed as 50kph.

·         The reduced traffic speed has 2 disadvantages. Firstly it increases the traffic time of the through traffic. Secondly and more importantly, although the speed limit is set as 50kph, the relatively straight configuration of Road P1 (Tung Chung – Tai Ho Section) and without junction for through traffic encourages running speed above 50kph in practice and is relatively less safe than Option F.

Recommendations for Connectivity of Road P1 (Tung Chung – Tai Ho Section)

2.7.3.6           Based on the current available information, it is reasonably presumed that a provision needs to be reserved for potential connection between Road P1 and Tai Ho Interchange. Option A not fulfilling this requirement is therefore not pursed.

2.7.3.7           Options C & D provides the required connectivity but the traffic performance is marginal.  The reserved traffic capacity for potential new land use and increase in development density is small. These options are therefore not preferred.

2.7.3.8           Option B is good in traffic performance but encroaches into the potential Siu Ho Wan development area.  Due to the impact to the flexibility of Siu Ho Wan development, this option is therefore not pursed. Among Options E & F, Option E is slightly better in term of traffic safety and traffic speed. Hence Option E is recommended as the conforming option for this study.


Table 2.30     Comparison of Connectivity Options (Options A to F) for Road P1 (Tung Chung – Tai Ho Section)

Criteria

Option A

Option B

Option C

Option D

Option E

Option F

Reclamation Area#

~8ha

~10ha

~6ha

~8ha

~9ha

~9ha

Planning & Land Use

·   Severe constraint to development potential of Siu Ho Wan Area in connectivity

·   Interchange is within the planning boundary of Siu Ho Wan development

·   Mild constraint to development potential of Siu Ho Wan Area in connectivity

·   Interchange is outside the planning boundary of Siu Ho Wan development

·   Interchange is outside the planning boundary of Siu Ho Wan development

·   Interchange is outside the planning boundary of Siu Ho Wan development

Traffic

·   Direct connection to Tai Ho Interchange from Tung Chung

·   Only traffic along Road P1 to and from Tung Chung is served

·   No connection between Siu Ho Wan and Tai Ho Interchange

·   Provision of additional roundabout for all traffic movements on Road P1

·   Future possible  traffic connection to Siu Ho Wan Development

·   Sufficient junction separation to accommodate queuing traffic

·   Provision of  additional diamond-type signalised junction for all traffic movements on Road P1

·   Future possible  traffic connection to Siu Ho Wan Development

·   Small junction separation (120m) may reduce the traffic capacity of the junction groups

 

·   Provision of additional roundabout for traffic movements on Road P1

·   Future possible  traffic connection to Siu Ho Wan Development

·   Sufficient junction separation to accommodate queuing traffic

·   Without provision of bypass for the through traffic along Road P1, all traffic would enter the roundabout causing heavy manoeuvring which deteriorates its performance

·   Provision of additional roundabout for all traffic movements on Road P1

·   Future possible  traffic connection to Siu Ho Wan Development

·   Sufficient junction separation to accommodate queuing traffic

·   The elevated slip road could facilitate deceleration of entry traffic to the additional roundabout

·   Provision of additional roundabout for all traffic movements on Road P1

·   Future possible  traffic connection to Siu Ho Wan Development

·   Sufficient junction separation to accommodate queuing traffic

·   The elevated bypass could only operate at 50kph given that the gradient is constrained by the surrounding structures

Environment

·  Relatively moderate disturbance to seabed due to moderate reclamation in size

·  Relatively more visual impact as it involves a longer viaduct section

·  Relatively more disturbance to seabed due to largest reclamation in size

·  Relatively more visual impact as it involves a longer viaduct section and a roundabout near MTR Siu Ho Wan Depot

·  Relatively least disturbance to seabed due to smallest reclamation in size

·  Relatively least visual impact as the reclamation lies along the coastline and a shorter viaduct section

·  Relatively moderate disturbance to seabed due to moderate reclamation in size

·  Relatively less visual impact as it involves a shorter viaduct section and an at-grade roundabout to the east of TM-CLKL Southern Connection

·  Relatively more disturbance to seabed due to larger reclamation in size

·  Relatively more visual impact as it involves a longer viaduct section and an elevated roundabout to the east of TM-CLKL Southern Connection

·  Relatively more disturbance to seabed due to larger reclamation in size

·  Relatively less visual impact as it involves a shorter viaduct section and an at-grade roundabout to the east of TM-CLKL Southern Connection

Impact to Locals

·  Promenade is reserved

·  Promenade is reserved

·  Promenade is reserved

·  Promenade is reserved

·  Promenade is reserved

·  Promenade is reserved

Engineering

·  Feasible

·  Feasible

·  Feasible

·  Structural provision allowed in elevated interchange

·  Feasible

·  Feasible

·  Structural provision allowed in elevated interchange

·  Feasible

Programme

·  Road P1 can be implemented in phase to suit needs for Tung Chung first. 

·  Programme and implementation inter-dependent on the Siu Ho Wan development

·  Road P1 can be implemented in phase to suit needs for Tung Chung first. 

·  Road P1 can be implemented in phase to suit needs for Tung Chung first. 

·  Road P1 can be implemented in phase to suit needs for Tung Chung first. 

·  Road P1 can be implemented in phase to suit needs for Tung Chung first. 

Cost

Moderate

Relatively high

Relatively low

Moderate

Relatively high

Moderate

# The reclamation area stated here is measured from copeline to copeline.  The area is approximate subject to detailed reclamation design.


2.8                         Summary of Reclamation Area and Permanent Seabed Loss Area

2.8.1.1           As mentioned in Section 1.2, the Project mainly comprises 129.1 ha reclamation (above high water mark) in which 120.5 ha is reclaimed for TCE and 8.6 ha is reclaimed for Road P1 (Tung Chung – Tai Ho Section). It should be noted that the reclamation area is estimated based on the extent of proposed land formation by reclamation above high water mark while the extent of the development area adopted for this EIA report is based on the RODP boundary covering all the development land in TCE and Road P1 (including some of the existing land and the proposed newly reclaimed land) at development level of approximately +5.5mPD. In addition, the inclined seawall, with berms and sloping face with gradient of approximately 1:2, will also take up part of the seabed below high water mark level. Considering the proposed ground level at TCE and Road P1 (Tung Chung – Tai Ho Section) after reclamation is +5.5mPD and the seabed level within the vicinity is approximately -2 to -5 mPD, the total permanent seabed loss would be approximately 145 ha. The summary of the RODP area, reclamation area and total permanent seabed loss is tabulated in Table 2.31 below and is shown in Figure 2.23.

                        Table 2.31    Summary of the area of RODP, proposed reclamation and total Permanent seabed loss (For Tung Chung East and Road P1 (Tung Chung – Tai Ho Section))

Project Elements

Area (ha)

RODP[1]

Reclamation

(above HWM[2])

Total Permanent Seabed Loss

TCE

122.4

(4 ha in urbanised area at +5.5mPD)

120.5

132

Road P1 (Tung Chung – Tai Ho Section)

8.8

(0.5 ha in urbanised area at +5.5mPD)

8.6

13.0

Total

131.2

129.1

145.0

Notes:

[1] RODP boundary covers all the development land in TCE and Road P1 (including some of the existing land and the proposed newly reclaimed land) at development level of approximately +5.5mPD.

[2] HWM denotes high water mark

2.9                         Construction Programme

2.9.1.1           According to the current information, the Tung Chung New Town Extension will be commissioned in phases with first population intake in Year 2023. The construction major work is targeted to commence in Year 2017 and completed by Year 2030 for full population intake. The construction programme is shown in Appendix 2.7.

2.9.1.2           Summary of construction period of the Key Construction Works is summarized in the following table.

Table 2.32     Summary of key construction works

Stages

Key Construction Works

Construction Period

Advanced Works

Advance Works

·   Ma Wan Chung Improvement Works

·   Tung Chung Road North

·   Access Road to RO

·   Early 2017 to Mid 2017

Reclamation Works

Reclamation Works

·   Tung Chung East Reclamation

·   Box Culvert Extension

·   Road P1 (Tung Chung – Tai Ho Section) Reclamation

·   Late 2017 to Late 2023

Tung Chung East

Phase 1 Infrastructures

·   Road Networks and Cycle Tracks in TCE Phase 1

·   Fresh Water Supply w/ pipelines in TCE Phase 1

·   Salt Water Supply w/ pipelines in TCE Phase 1

·   Saltwater In-take Pumping Station (by others)

·   Drainage w/ pipelines in TCE Phase 1

·   Sewerage w/ pipelines in TCE Phase 1

·   New Sewage Pumping Station - TCE West SPS

·   Waterfront Promenade - Phase 1 (by others)

·   Early 2020 to Mid/Late 2023

·   Refuse Collection Point (by others)

·   General Clinic / Health Centre (by others)

·   Petrol Filling Station (by others)

·   Early 2020 to Late 2023

Phase 2 Infrastructures

·   Road Networks and Cycle Tracks in TCE Phase 2

·   Fresh Water Supply w/ pipelines in TCE Phase 2

·   Salt Water Supply w/ pipelines in TCE Phase 2

·   Drainage w/ pipelines in TCE Phase 2

·   Sewerage w/ pipelines in TCE Phase 2

·   Water Front Promenade - Phase 2 (by others)

·   Late 2020 to Late 2024

Phase 3 Infrastructures

·   Road Networks and Cycle Tracks in TCE Phase 3

·   Salt Water Supply w/ pipelines in TCE Phase 3

·   Fresh Water Supply w/ pipelines in TCE Phase 3

·   Drainage w/ pipelines in TCE Phase 3

·   Sewerage w/ pipelines in TCE Phase 3

·   Water Front Promenade - Phase 3 (by others)

·   Late 2022 to Late 2027

Phase 4 Infrastructures

·   Road Networks and Cycle Tracks in TCE Phase 4

·   Drainage w/ pipelines in TCE Phase 4

·   Salt Water Supply w/ pipelines in TCE Phase 4

·   Fresh Water Supply w/ pipelines in TCE Phase 4

·   Sewerage w/ pipelines in TCE Phase 4

·   New Sewage Pumping Station - TCE East SPS

·   Water Front Promenade - Phase 4 (by others)

·   Police Married Quarters (C0-2) (by others)

·   District Police Station (C0-3) (by others)

·   Secondary School (E-01) (by others)

·   Primary School (E-02) (by others)

·   Primary School (E-03) (by others)

·   Undesignated GIC (E-04)

·   Sports Ground / Sports Centre (F-01) (by others)

·   Primary School (F-02) (by others)

·   Primary School (F-03) (by others)

·   Secondary School (F-04) (by others)

·   Boatyard and Maintenance Area (F-05) (by others)

·   Sports Ground / Sports Centre (G-01) (by others)

·   Post Secondary Institution (G-02) (by others)

·   Fire Station (G-03) (by others)

·   Early 2024 to Early 2030

Tung Chung West

Phase 1 Infrastructures

·   Road Networks and Cycle Track in TCW Phase 1

·   Fresh Water Supply w/ pipelines in TCW Phase 1

·   Salt Water Supply w/ pipelines in TCW Phase 1

·   Drainage w/ pipelines in TCW Phase 1

·   Attenuation ponds and pumping stations for Tung Chung West in TCW Phase 1

·   De-channalisation of channelised portion of Tung Chung Stream

·   Sewerage w/ pipelines in TCW Phase 1

·   New Sewage Pumping Station  - TCV East SPS

·   Early 2019 to Late 2023

Phase 2 Infrastructures

·   Road Networks and Cycle Track in TCW Phase 2

·   Bridges in Tung Chung West

·   Fresh Water Supply w/ pipelines in TCW Phase 2

·   Salt Water Supply w/ pipelines in TCW Phase 2

·   Drainage w/ pipelines in TCW Phase 2

·   Attenuation ponds and pumping stations for Tung Chung West Phase 2

·   Polder Scheme for Tung Chung West

·   Sewerage w/ pipelines in TCW Phase 2

·   New Sewage Pumping Station

·   Upgrading Existing Sewage Pumping Station - Tung Chung West - CMRSPS

·   Water Front Promenade (by others)

·   Early 2022 to Late 2030

·   General Clinic / Health Centre (by others)

·   Telephone Exchange (by others)

·   Early 2022 to Late 2030

·   Sports Ground / Sports Centre (by others)

·   Primary School (by others)

·   Late 2020 to Late 2024

Others

Service Reservoirs

·   Site Formation Works for Freshwater Service Reservoir

·   Freshwater Service Reservoir

·   Fresh Water Supply w/ pipelines at Service Reservoir

·   Site Formation Works for Saltwater Service Reservoir

·   Saltwater Service Reservoir

·   Salt Water Supply w/ pipelines at Service Reservoir

·   Mid 2018 to Mid 2022

Road P1 (Tung Chung – Tai Ho Section)

·   Road P1 (Tung Chung – Tai Ho Section) roadworks, Slip Roads and Tai Ho Interchange

·   Cycle Track at Road P1 (Tung Chung – Tai Ho Section)

·   Early 2021 to Early 2024

Infrastructure Works (by others)

Phase 1 Infrastructure (by others)

·   CLP sub-station (by others)

·   Late 2020 to Late 2023

·   Upgrading Works of Siu Ho Wan Water Treatment Works (by others)

·   Mid 2018 to Mid 2021

·   Fitting-out works of Siu Ho Wan Sewage Treatment Works (by others)

·   Mid 2021 to End 2024

 

2.9.1.3           Population for the proposed new development area in Tung Chung East and Tung Chung West will be intake in phase together with the supporting infrastructures. Based on the implementation of the supporting infrastructures, the proposed new development will be available for the population intake as listed in the summary of the schedule of the population intake in the following table. It is the prediction based on the early availability of land and phase completion of the supporting infrastructure to support the population and will still be subjected to change according to the latest implementation programme and government policy. Locations of development phasing in TCE and TCW are illustrated in Figures 2.24a and 2.24b.

                         Table 2.33  Population intake summary

Phase

Year of Population Intake

Population Intake (Approximate)

Cumulative Population Intake (Approximate)

Tung Chung East

Phase 1

2023

23,900

23,900

Phase 2

2025

13,700

37,600

Phase 3

2027

37,000

74,600

Phase 4

2029 - 2030

44,300

118,900

Tung Chung West

Phase 1

2023

19,200

19,200

Phase 2

2026 to 2030

6,300

25,500