5 NOISE
IMPACT
This chapter presents the findings of the noise assessment for the proposed CKR during both the construction and operational phases. Construction airborne noise associated with the use of Powered Mechanical Equipment (PME) has been conducted. With the implementation of practical mitigation measures, construction noise impacts at most of the neighboring noise sensitive uses would be controlled to acceptable levels. However, for some receivers that are very close to some of the works sites, adverse residual impacts exceeding the construction noise criterion are anticipated even after implementing all practicable mitigation measures. Construction groundborne noise associated with the use of PME has also been conducted at representative noise sensitive receivers along the tunnel and the construction groundborne noise impacts would comply with the noise criteria.
Operational noise impacts associated with road traffic noise and fixed noise sources have also been investigated. With the implementation of mitigation measures, potential noise impacts would comply with the statutory criteria.
Construction Noise during Non-restricted Hours
The Noise Control Ordinance (NCO) (Cap. 400)
provides the statutory framework for noise control in Hong Kong. Assessment procedures and standards are set
out in the respective Technical Memoranda (TM) promulgated under the NCO. The following TMs are applicable to the
assessment and control of construction noise.
·
TM on Noise from Construction Work other than
Percussive Piling (TM-GW);
·
TM on Noise from Percussive Piling (TM-PP); and
·
TM on Noise on Construction Work in Designated
Areas (TM-DA).
To ensure a better environment, the TM-EIAO
promulgated under the Environmental Impact Assessment Ordinance (EIAO) (Cap.
499) has imposed more stringent criteria.
For construction, there is no statutory limit on daytime construction
noise under the NCO and related TMs.
Nevertheless, the TM-EIAO stipulates noise standards of 65 – 75 dB(A)
for daytime construction activities, as shown in the table below.
Table 5.1:
Noise Standards for Construction Activities
Uses |
Noise Standards [1],
Leq (30 mins) dB(A) |
|
0700 to 1900 hours on any day not being a Sunday or general holiday |
1900 to 0700 hours or any time on Sundays or general holiday |
|
All domestic premises including temporary housing
accommodation |
75 |
(See Note 2) |
Hotels and hostels |
75 |
|
Educational institutions including
kindergartens, nurseries and all others where unaided voice communication is
required |
70 65 (During examinations) |
Notes:
[1] The above
standards apply to uses that rely on opened windows for ventilation.
[2] The
criteria laid down in the relevant technical memoranda under the NCO for
designated areas and construction works other than percussive piling may be
used for planning purpose. A
Construction Noise Permit (CNP) shall be required for the carrying out
construction work during the period.
Construction Noise during Restricted Hours
The NCO also provides statutory control on
general construction works during restricted hours (ie 1900 to 0700 hours (of
the next day) from Monday to Saturday and at any time on Sundays or public
holidays). The use of PME for
construction works during restricted hours would require a Construction Noise
Permit (CNP). The TM-GW details the
procedures adopted by EPD for assessing such application. The granting of a CNP is subject to
conditions stated in the CNP and it may be revoked at any time for failure to
comply with the permit conditions.
In addition to the general controls on the use
of PME during restricted hours, the use of Specified Powered Mechanical
Equipment (SPME) and the undertaking of Prescribed Construction Work (PCW)
during the restricted hours in a designated area are controlled by the
TM-DA. Construction plant or equipment
classified as SPME under the TM-DA includes hand-held breakers, bulldozers,
concrete mixer lorries, dump trucks and poker vibrators. The PCW includes the erection or dismantling
of formwork or scaffolding, hammering, handling of rubble, wooden boards, steel
bars, or scaffolding material, and the disposal of rubble through plastic
chutes.
The TM-DA details the procedures that should
generally be adopted by the Authority for assessing the use of SPME during
restricted hours and for determining whether a CNP would be issued.
Maximum noise levels from construction
activities during restricted hours at affected NSRs are controlled under the
TMs and shall not exceed the specified Acceptable Noise Levels (ANLs). These ANLs are stipulated in accordance with
the Area Sensitivity Ratings established for the NSRs. The ANLs for construction works in Designated
Areas are more stringent than those given in the GW-TM and summarized in the
table below.
Table 5.2:
Acceptable Noise Levels for Construction during Restricted Hours
Time
Period |
Acceptable Noise Levels for Area Sensitivity Ratings, dB(A) |
||
A |
B |
C |
|
All weekdays during the evening (1900 to 2300 hours), and general
holidays (including Sundays) during the day and evening (0700 to 2300 hours) |
60 (45) |
65 (50) |
70 (55) |
All days during the night-time (2300 to 0700 hours) |
45 (30) |
50 (35) |
55 (40) |
Note: Figures in brackets are ANLs for SPME
construction work in designated areas
Area Sensitivity
Rating (ASR)
The appropriate ASR for the NSR shall consider under consideration from below table.
Any NSR shall, irrespective of Table 5.3, be assigned an ASR of "C" if it is within 100 m of a zone designated as "Industrial" or "Industrial Estate" on a statutory Outline Zoning Plan, or an ASR of "B" if it is between 100 m and 250 m from such a zone, except in cases where Table 5.3 indicates an ASR of "C".
Table 5.3
Area Sensitivity Ratings (ASRs)
Type of Area containing
NSR |
Degree to which NSR is
affected by IF |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
(i)
Rural area, including country parks or village type developments |
A |
B |
B |
(ii)
Low density residential area consisting of low-rise or isolated high-rise
developments |
A |
B |
C |
(iii)
Urban area |
B |
C |
C |
(iv)
Area other than those above |
B |
B |
C |
Note:
For the purpose of Table 5.3,
the following definitions apply:
"country park"
means an area that is designated as a country park pursuant to section 14 of
the Country Parks Ordinance;
"directly affected"
means that the NSR is at such a location that noise generated by the IF is
readily noticeable at the NSR and is a dominant feature of the noise climate of
the NSR;
"indirectly
affected" means that the NSR is at such a location that noise generated by
the IF, whilst noticeable at the NSR, is not a dominant feature of the noise
climate of the NSR;
"not affected"
means that the NSR is at such a location that noise generated by the IF is not
noticeable at the NSR; and
"urban area" means
an area of high density, diverse development including a mixture of such
elements as industrial activities, major trade or commercial activities and
residential premises.
Despite any description made in this EIA, there
is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a
well-justified CNP application, once filed, for construction works within
restricted hours as guided by the relevant TMs issued under the NCO. The Noise Control Authority will take into
account contemporary conditions / situations of adjoining land uses and any
previous complaints against construction activities at the site before making a
decision in granting a CNP. Nothing in
the EIA report shall bind the Noise Control Authority in making a
decision. If a CNP is to be issued, the
Noise Control Authority shall include in it any conditions demand. Failure to comply with any such conditions
will lead to cancellation of the CNP and prosecution under the NCO.
Percussive Piling
Under the TM-PP, CNPs are also required for
percussive piling involving the use of diesel, pneumatic and / or steam
hammer. This TM specifies the permitted
hours and other conditions for percussive piling. The table below lists the acceptable
percussive piling noise levels for various types of NSR.
Table 5.4:
Acceptable Noise Levels for Percussive Piling
NSR Window Type or Means of Ventilation |
ANL (dB(A)) |
(i) NSR (or part of NSR) with no window or
other opening |
100 |
(ii) NSR with central air conditioning system |
90 |
(iii) NSR with windows or other openings but without central air conditioning system |
85 |
Depending on the numbers and types of piling
machines and the separation from NSRs, percussive piling may be restricted to
12, 5 or 3 hours per day. For NSRs that
are particularly sensitive to noise, such as hospitals, medical clinics,
educational institutions and courts of law, a further reduction of 10 dB(A)
shall be applied to the above ANLs.
Blasting
The administrative and procedural control of
all blasting operations in Hong Kong is vested in the Mines Division of the
Civil Engineering and Development Department (CEDD). The Dangerous Goods (General) Regulations,
Chapter 295 also stipulates that no person shall carry out blasting unless he
possesses a valid mine blasting certificate to be issued by the Mines Division
of CEDD. The Superintendent of Mines
will review the application on a case-by-case basis before issuing the Mine
Blasting Certificate. Although there is
no statutory noise level for blasting, the noise associated with the removal of
debris and rocks are controlled under the TM-EIAO.
Construction Groundborne Noise
Noise arising from general construction works
during normal working hours is governed by the TM-EIAO under the EIAO. The Technical Memorandum for the Assessment
of Noise from Places other than Domestic Premises, Public Places or
Construction Sites (TM-IND) under the NCO stipulates that noise transmitted
primarily through the structural elements of building, or buildings, shall be
10 dB(A) less than the relevant ANLs.
Based on the same principle for the ground-borne
noise criteria (i.e. ANL-10 dB(A) under the TM-IND), the construction
groundborne noise levels inside domestic premises and schools shall be limited
to 65 dB(A) and 60 dB(A) respectively when compared to the TM-EIAO. The
construction groundborne noise criteria has been summarized in Table 5.5.
For construction works conducted on general holidays, Sundays and weekdays during evening (1900-2300 hrs) and night time (2300-0700 hrs) the following day, the construction groundborne noise level shall be limited to 10 dB(A) below the respective ANLs for the ASR appropriate to those NSRs affected by the Project. A summary of these criteria is given in the table below.
Table 5.5: Construction Groundborne Noise Criteria (Leq
30min, dB(A))
NSR type |
Construction Groundborne
Noise Criteria, dB(A) |
||
Daytime (0700– 1900) except
general holidays and Sunday |
Daytime (0700-1900) during general
holidays and Sundays and all days during Evening (1900-2300 hrs) |
Night-time (2300 – 0700 hrs) |
|
All domestic premises including temporary housing accommodation |
65 |
50/55/60[1,2] |
35/40/45[1,2] |
Hotels and hostel |
|||
Educational institutions including kindergarten, nurseries and all
others where unaided voice communication is required |
60 55 (for during examination) |
N/A[3] |
N/A[3] |
Notes: [1] Based
on the Basic Noise Level for NSRs with Area Sensitivity Ratings of A, B, and
C detailed in the Technical Memorandum on Noise From Construction Work Other
Than Percussive Piling. [2] Construction Noise Permit is required for
works during this period. [3] No sensitive use in educational
institutions during evening and night-time
during normal period and on general holidays and Sunday is
assumed except specified. |
The relevant legislation and associated guidelines
applicable to the operational noise assessment includes:
·
EIAO (Cap. 499);
·
TM for the assessment of Noise from Places other
than Domestic Premises, Public Places or Construction Sites (TM-Places); and
·
Hong Kong Planning Standards and Guidelines (HKPSG).
Road Traffic Noise
The TM-EIAO has stipulated the noise standards
for various noise sources as shown in the following table.
Table 5.6:
Noise Standards for Operational Phase (Road Traffic Noise)
Common Uses |
Noise Standards [1] |
Road
Traffic Noise L10
(1hour) dB(A) |
|
All domestic premises
including temporary housing accommodation |
70 |
Hotels and hostels |
70 |
Offices |
70 |
Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required |
65 |
Places of public worship and
courts of law |
65 |
Hospitals, clinics,
convalescences and homes for the aged, diagnostic rooms, wards |
55 |
Notes:
[1] The above standards apply to uses that
rely on opened windows for ventilation.
Fixed Noise Sources
Operational noise from fixed noise sources is
controlled under the NCO’s Technical Memorandum on Noise from Places other than
Domestic Premises, Public Places or Construction Sites. To plan for a better environment, the TM-EIAO
has specified the following requirements.
·
5 dB(A) below the appropriate ANLs in the Technical
Memorandum on Noise from Places other than Domestic Premises, Public Places or
Construction Sites (TM-IND); or
·
the existing noise levels (For quiet areas with
level 5dB(A) below the ANL).
Table 5.7:
Noise Standards for Operational Phase (Fixed Noise Sources)
Common Uses |
Noise Standards [1] |
Fixed Noise Sources |
|
All domestic premises
including temporary housing accommodation |
(a) 5dB(A) below the appropriate Acceptable
Noise Levels (ANL) shown in Table 2 of the Technical Memorandum for the
Assessment of Noise from Places Other than Domestic Premises, Public Places
or Construction Sites, or (b) the prevailing background noise levels
(For quiet areas with level 5 dB(A) below the ANL) |
Hotels and hostels |
|
Offices |
|
Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required |
|
Places of public worship and
courts of law |
|
Hospitals, clinics,
convalescences and homes for the aged, diagnostic rooms, wards |
The ANLs for different ASR (refers to Table 5.3) during different periods are
summarized in the following table.
Table 5.8:
Acceptable Noise Levels for Fixed Noise Sources
Time Period |
ANL, dB(A) |
ANL-5, dB(A) |
||||
ASR A |
ASR B |
ASR C |
ASR A |
ASR B |
ASR C |
|
Day (0700 to 1900 hours) |
60 |
65 |
70 |
55 |
60 |
65 |
Evening (1900 to 2300 hours) |
60 |
65 |
70 |
55 |
60 |
65 |
Night (2300 to 0700 hours) |
50 |
55 |
60 |
45 |
50 |
55 |
Note: ASR –
Area Sensitivity Rating
Noise from Public Transport Interchange
There are no noise level standards
stipulated for the noise from the operation of public transport interchange
(PTI). Chapter 9 of Hong Kong Planning
Standards and Guidelines (HKPSG) provides considerations for the Project
Proponent to determine the location and layout of a PTI during planning
stage.
Representative NSRs within a distance of 300m from the either side of
the project boundary have been identified.
The first layer of NSRs has been identified and selected for
assessment. These NSRs will cover all
existing sensitive developments (including those occupied before completion of
the construction) for construction noise assessment, and both the existing and
planned developments for operational noise assessment.
Existing Receivers
The existing NSRs are identified by means of topographic maps, aerial photos, land status plans and several site surveys.
Planned/Committed Receivers
Planned/committed NSRs are identified by making reference to relevant
Outline Zoning Plans (OZP), Outline Development Plans, Layout Plans and other
published plans in the vicinity of the alignment, including:
·
South West Kowloon (KPA 20) Outline Zoning Plan
(No. S/K20/27);
·
Tsim Sha Tsui (KPA 1) Outline Zoning Plan (No.
S/K1/26);
·
Yau Ma Tei (KPA 2) Outline Zoning Plan (No.
S/K2/21);
·
Ho Man Tin (KPA 6 & 7) Outline Zoning Plan (No.
S/K7/22);
·
Hung Hom (KPA 9) Outline Zoning Plan (No. S/K9/24);
·
Ma Tau Kok (KPA 10) Outline Zoning Plan (No.
S/K10/20);
·
Kai Tak (KPA 22) Outline Zoning Plan (No. S/K22/4);
and
·
Ngau Tau Kok & Kowloon Bay (KPA 13 & 17)
Outline Zoning Plan (No. S/K13/27)
A list of planned/ committed noise sensitive receivers was identified and summarized below.
West Portion
There are several areas zoned as Governmental, Institution and Community (G/IC) in West Portion. Planning use of these G/IC zone has been requested from Planning Department and a letter from Planning Department showing the potential uses of G/IC sites in West Kowloon latest OZP No. S/K20/27 is shown in Appendix 5.1A. Some of the G/IC uses are identified as noise sensitive receivers including Refuse Collection Point and Street Sleepers’ Shelters, Primary School and Hindu Temple for assessment.
According to the information provided by the respective project
proponents of Street Sleepers’ Shelters and Hindu Temple, the Street Sleepers’
Shelters will be a 4-storey building with sensitive facades facing Ferry Street
and Hau Cheung Street, the Hindu Temple will be a 10-storey building with
sensitive facade facing West Kowloon Highway.
However, there are no confirmed information on the layout of the planned
school, referenced has been made to the existing schools in surrounding. It has therefore been assumed the school is
8-storey. The Coronation is a
residential premises located at OZP No. S/K20/27, which is zoned as R(A)1. The latest layout and number of storey have
been adopted in this assessment, which has already confirmed by site
inspection. There
are no confirmed intake programme of Hindu Temple and Primary School, hence,
these two receivers are not included as construction noise impact assessment.
Central Portion
According to the latest OZP No. S/K7/21, there is a R(B)2 zone next to the planned Project site office which is under construction. However, as no confirmed building layout is available during the preparation of this EIA study, assessments point at the boundary has been selected for airborne construction noise impact assessment.
East Portion
All selected planned / committed receivers at East portion were based on latest Kai Tak Outline Zoning Plan (No. S/K22/4) gazetted on 14 Sept 2012. As no confirmed building layout is available during the preparation of this EIA study, assessment locations have been selected at this area including residential uses, comprehensive development area, planned hospital and planned school. The building height restriction and the population intake of these planned receivers is based on the latest Kai Tak Outline Zoning Plan.
For the planned school, the school layout has assumed as typical school layout and sensitive facades surrounding the building layout are selected for assessment.
Overall
The locations of the representative NSRs for noise impact assessment
during both construction and operation of the project are illustrated in
Figures 5.1.1 to 5.3.2, and are summarized in the table
below. Groundborne noise sensitive
receivers have been selected at both portal end and central portion given that
separation distance between these selected noise sensitive receivers to the
rock head level would be minimum along the alignment. Figure 2.3
shows the longitudinal profile of CKR. A
summary of noise sensitive receivers is tabulated in Appendix 5.1. Photos showing existing noise sensitive
receivers are given in Appendix 5.2.
Table 5.9: Representative NSRs for Noise
Impact Assessment
NSR ID |
Description |
Landuse [1] |
No. of Storey |
Construction Phase |
Operational Phase |
||
Airborne |
Groundborne |
Road Traffic Noise |
Fixed Plant Noise |
||||
West
Portion |
|||||||
W-N1A |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) |
E |
8 |
√ |
X |
√ |
√ |
W-N1B |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) |
E |
8 |
X |
X |
√ |
X |
W-N2 |
Charming Garden Block 12 |
R |
23 |
√ |
X |
√ |
√ |
W-N3 |
Yau Ma Tei Catholic Primary School (Tung Kun Street) |
E |
7 |
√ |
X |
√ |
X |
W-N6 |
Man Cheong Building |
R |
18 |
X |
X |
√ |
X |
W-N6A |
Man Wai Building |
R |
18 |
X |
X |
√ |
X |
W-N7 |
Kum Lam Building |
R |
12 |
√ |
X |
√ |
X |
W-N8 |
Dickson Building |
R |
18 |
√ |
X |
√ |
X |
W-N8A |
Tak Cheong Building |
R |
18 |
√ |
X |
√ |
X |
W-N9A |
Yau Ma Tei Jockey Club Polyclinic |
H |
10 |
X |
X |
√ |
X |
W-N9B |
Yau Ma Tei Jockey Club Polyclinic |
H |
10 |
X |
X |
√ |
X |
W-N10A |
Alhambra Building (West façade) |
R |
15 |
√ |
√ |
√ |
X |
W-N10B |
Alhambra Building (West façade) |
R |
15 |
√ |
X |
X |
X |
W-N10C |
Alhambra Building (North façade) |
R |
15 |
X |
X |
√ |
X |
W-N11 |
Hong Kong Community College (HKCC) of the HK [1] |
E |
19 |
√ |
X |
√ |
X |
W-N14 |
Charming Garden Block 1 |
R |
22 |
X |
X |
√ |
√ |
W-N15 |
HKMA David Li Kwok Po College |
E |
8 |
√ |
X |
√ |
X |
W-N18 |
Hydan Place |
R |
17 |
√ |
X |
√ |
X |
W-N19 |
Methodist College |
E |
6 |
√ |
√ |
√ |
X |
W-N20 |
Tang’s Mansion |
R |
15 |
X |
X |
√ |
X |
W-N21 |
Temple Street No. 56 |
R |
7 |
√ |
X |
√ |
X |
W-N22 |
Kamly Court |
R |
10 |
√ |
X |
√ |
X |
W-N23 |
Hang Wan House |
R |
23 |
√ |
X |
√ |
X |
W-N24 |
Prosperous Garden Block 5 |
R |
27 |
√ |
X |
√ |
X |
W-N25A |
Prosperous Garden Block 1 |
R |
28 |
√ |
X |
√ |
X |
W-N25B |
Prosperous Garden Block 1 |
R |
28 |
X |
X |
√ |
X |
W-N26A |
Prosperous Garden Block 2 |
R |
28 |
X |
X |
√ |
X |
W-N26B |
Prosperous Garden Block 2 |
R |
28 |
X |
X |
√ |
X |
W-N27 |
Prosperous Garden Block 3 |
R |
28 |
X |
X |
√ |
X |
W-N28 |
Wah
Tak Building |
R |
17 |
X |
X |
√ |
X |
W-N29 |
Tin Hau Temple |
W |
1 |
X |
X |
√ |
X |
W-N30 |
The Sorrento |
R |
50 |
X |
X |
√ |
X |
W-N31 |
Shanghai Street No. 217-225 |
R |
5 |
√ |
X |
X |
X |
W-N32 |
Sing On Building |
R |
5 |
√ |
X |
X |
X |
W-P6A, C |
Refuse Collection Point and Street Sleepers’ shelters (Planned) |
GIC |
4 |
√ |
X |
√ |
X |
W-P7A-G |
Primary School (Planned) |
E |
8 |
X |
X |
√ |
X |
W-P8 |
Hindu Temple (Planned) [2] |
W |
10 |
X |
X |
√ |
√ |
W-P9 |
The Coronation |
R |
30 |
√ |
X |
√ |
X |
W-P10 |
The Coronation |
R |
30 |
X |
X |
√ |
X |
W-P11 |
The Coronation |
R |
30 |
√ |
X |
√ |
X |
W-P12 |
The Coronation |
R |
30 |
√ |
X |
√ |
X |
W-P13 |
The Coronation |
R |
30 |
X |
X |
√ |
X |
W-P14 |
The Coronation |
R |
30 |
X |
X |
√ |
X |
Central
Portion |
|||||||
M-N1 |
Kar Man House, Oi Man Estate |
R |
6 |
√ |
√ |
X |
√ |
M-N2 |
Carmel on the Hill |
R |
25 |
√ |
X |
X |
√ |
M-N3 |
SKH Tsoi Kung Po Secondary School |
E |
8 |
√ |
√ |
X |
√ |
M-N4 |
Man Fuk House Block A |
R |
15 |
√ |
X |
X |
√ |
M-N5 |
Cascades Block A |
R |
18 |
√ |
X |
X |
X |
M-N6 |
Ko Fai House, Kwun Fai Court |
R |
9 |
√ |
√ |
X |
√ |
M-P2 |
Planned Residential Area B (Planned) |
R |
- |
√ |
X |
X |
√ |
M-P3 |
Planned Residential Area B (Planned) |
R |
- |
√ |
X |
X |
√ |
East
Portion |
|||||||
E-N6 |
Grand Waterfront Tower 5 |
R |
51 |
√ |
X |
X |
X |
E-N11 |
Holy Carpenter Primary School |
E |
6 |
√ |
X |
X |
X |
E-N12 |
Grand Waterfront Tower 3 |
R |
51 |
√ |
√ |
X |
X |
E-N13 |
Grand Waterfront Tower 1 |
R |
51 |
√ |
X |
X |
X |
E-N14 |
Chong Chien Court Block J |
R |
13 |
√ |
√ |
X |
X |
E-N15 |
Hang Chien Court Block I |
R |
13 |
√ |
X |
X |
X |
E-N19 |
Buddhist Chi King Primary School |
E |
8 |
√ |
X |
√ |
X |
E-N20 |
Hing Yan Street No. 29 |
R |
7 |
√ |
X |
X |
X |
E-N21 |
Hang Chien Court Block J |
R |
13 |
√ |
X |
X |
X |
E-N22 |
Hang Chien Court Block H |
R |
13 |
√ |
X |
X |
X |
E-P1 |
Site 1L2 (Planned) |
R |
32 |
X |
X |
√ |
X |
E-P6 |
Site 5A4a (Planned) |
CDA |
20 |
X |
X |
√ |
X |
E-P7 |
Site 5A4b (Planned) |
CDA |
35 |
X |
X |
√ |
X |
E-P8 |
Site 1L3 (Planned) |
R |
15 |
X |
X |
√ |
√ |
E-P13A-B |
Site 3C1 – Hospital (Planned) |
H |
14 |
X |
X |
√ |
X |
E-P14A-G |
Site 3B1- Secondary School
(Planned) |
E |
10 |
X |
X |
√ |
√ |
E-P16 |
Site 1L3 (Planned) |
R |
32 |
X |
X |
√ |
X |
E-P20 |
Site 1I3 (Planned) |
R |
32 |
√ |
X |
√ |
X |
Barging Point |
|||||||
B-N1 |
Grand Horizons |
R |
36 |
√ |
X |
X |
X |
Notes:
R – residential; E –
educational; H – clinic/ home for the aged/hospital; W – worship; GIC –
government, institution and community; CDA – Comprehensive Development Area
√ – Include for assessment; X – Not included for assessment. Selected NSRs would better represent the
impacts already.
[1]
Central air-conditioning is provided.
[2]
According to the information provided by the respective project proponent, this
planned temple would have 10 storey high. The tentative layout has also
been adopted in this EIA.
Prevailing Noise Levels
According to the latest design, there are three
ventilation buildings, one near the western portal, one near the eastern portal
and the central ventilation building will locate at the central portion near Ho
Man Tin West Service Reservoir. Noise
measurements have been conducted to establish the prevailing noise levels in
the vicinity of the proposed ventilation buildings where fixed noise sources
are anticipated. Appendix 5.3 shows the measurement locations for prevailing noise levels. A summary of the results is given in the
table below.
Table 5.10:
Measurements of Prevailing Noise Levels
Measurement Location |
Prevailing Noise Levels [1],
dB(A) L eq |
|
Day & Evening [2] |
Night [2] |
|
West Portion (Location A) |
64-68 |
60-61 |
West Portion (Location B) |
65-66 |
55-56 |
Central Portion (Location C) |
73-75 |
70-71 |
Central Portion (Location D) |
73-74 |
69-70 |
East Portion (Location E) |
69-71 |
66-69 |
Note:
[1] Measurements conducted in
November 2011
[2] Day: 0700 to 1900 hours, Evening:
1900 to 2300 hours, Night: 2300 to 0700 hours
Area Sensitivity Rating
The table above shows the NSRs which close to the
ventilation buildings may have potential fixed plant noise impact and these
NSRs have been selected for fixed plant noise assessment. The ASR of NSRs identified for the fixed
plant noise is summarized in the table below.
Table 5.11:
ASR of Representative NSRs for Fixed Plant Noise Assessment
NSR ID |
Landuse [1] |
Type of Area |
Influence Factor (IF) |
Degree to which NSR is
affected by IF |
ASR |
W-N1A |
E |
Urban |
N/A |
N/A |
B |
W-N2 |
R |
Urban |
N/A |
N/A |
B |
W-N14 |
R |
Urban |
West Kowloon Expressway [2] |
Directly |
C |
W-P8 |
W |
Urban |
West Kowloon Expressway [2] |
Directly |
C |
M-N1 |
R |
Urban |
N/A |
N/A |
B |
M-N2 |
R |
Urban |
N/A |
N/A |
B |
M-N3 |
E |
Urban |
N/A |
N/A |
B |
M-N4 |
R |
Urban |
N/A |
N/A |
B |
M-N6 |
R |
Urban |
N/A |
N/A |
B |
M-P2 |
R |
Urban |
N/A |
N/A |
B |
M-P3 |
R |
Urban |
N/A |
N/A |
B |
E-P8 |
R |
Urban |
Kai Fuk Road [3] |
Directly |
C |
E-P14A |
E |
Urban |
Kai Fuk Road [3] |
Directly |
C |
Notes:
[1] R– residential; E – educational; W – Place of public worship
[2] The AADT of West Kowloon Expressway (Station no. 3707) is greater
than 30,000 according to AADT 2011
[3] The AADT of Kai Fuk Road (Station no. 3206) is greater than 30,000
according to AADT 2011
Noise Criteria
A summary of the noise criteria at
representative NSRs which would be subject to the impact of fixed plant noise
is given in the following table. The
prevailing noise level at each NSR would be determined based on measurement results
at the nearest location as shown in the table below.
Table
5.12: Summary of Noise Criteria at NSRs
for Fixed Noise Sources
Location |
NSR |
Time Period [1] |
Prevailing Noise Levels, dB(A) [2] |
ASR |
ANL-5 dB(A) [3] |
Criteria dB(A) [4] |
West Portion (Location A) |
W-N1A, W-N2 |
Day & evening |
64 |
B |
60 |
60 |
Night |
60 |
B |
50 |
50 |
||
West Portion (Location A) |
W-N14 |
Day & evening |
64 |
C |
65 |
64 |
Night |
60 |
C |
55 |
55 |
||
West Portion (Location B) |
WP-8 |
Day & evening |
65 |
C |
65 |
65 |
Night |
55 |
C |
55 |
55 |
||
Central Portion (Location C) |
M-N2, M-N3, M-N4 |
Day & evening |
73 |
B |
60 |
60 |
Night |
70 |
B |
50 |
50 |
||
Central Portion (Location D) |
M-N1, M-N6, M-P2, M-P3 |
Day & evening |
73 |
B |
60 |
60 |
Night |
69 |
B |
50 |
50 |
||
East Portion (Location E) |
E-P8, E-P14A |
Day & evening |
69 |
C |
65 |
65 |
Night |
66 |
C |
55 |
55 |
Note:
[1] Day: 0700 to 1900 hours, Evening: 1900 to 2300
hours, Night: 2300 to 0700 hours.
[2] Prevailing
noise level determined based on the measurement result recorded at the
representative location nearest to the respective NSR.
[3] A 5 dB(A) has been deducted from ANL as specified
in requirement of TM-EIAO.
[4] The Minimum of [2] & [3] is adopted.
5.4 Construction Noise Impact Assessment
5.4.1
Construction
Airborne Noise
Noise Sources
The latest construction methodology is
described in Chapter 3. Based on the construction
methodologies, the major construction works would include the following
activities:
·
Site clearance and formation activities;
·
Structure dismantling;
·
Tunnel construction (including non-blasting
tunneling, drill-and-blast tunneling, underwater tunnel and cut-and-cover);
·
Rock crushing inside the tunnel shaft of West,
Central and East Portions;
·
Construction of approach roads;
·
Portal construction;
·
Diversion of utilities;
·
Spoils removal from underground works &
stockpiling;
·
Backfilling and reinstatement works; and
·
Barging activities.
These construction activities would be carried out with the use of PME including breakers, excavators, lorries, mobile cranes, concrete pumps, concrete mixers, pokers, road rollers, etc. Sound Power Level (SWL) for each PME would be established according to TM-GW and other relevant information as appropriate.
All the works associated with the tunnel works (e.g. holes drilling and rock excavation etc) would be conducted deep inside the tunnel. For the operation of rock crushers in particular, they would be located typically at about 20 to 30m from the portals inside the tunnel. The approximate location of rock crushers are shown in Appendix 5.4C. Although the horizontal distance between the mucking out points and the sensitive receivers of West, Central and East Portions are within 50m, the rock crusher in the Central Portion will however be located over 100m vertically from the mucking out. Hence, only operations of rock crushers at West Portion and East Portion have been assessed.
Assessment Methodology
Construction airborne noise assessment has been
conducted based on the following procedures:
·
Determine the assessment area, and identify
representative NSRs that may be affected by the works;
·
Obtain the construction method and work sequence
for the construction period;
·
Obtain the plant items for each corresponding
construction work sequence;
·
Determine the sound power levels of the plant items
according to the information stated in the TM-GW or other recognized sources of
reference, where appropriate;
·
Calculate the correction factors based on the
distance between the NSRs and the notional noise source positions of the work
sites;
·
Apply corrections for façade, distance, barrier
attenuation, acoustic reflection where applicable;
·
Quantify the level of impact at the NSRs in
accordance with TM-GW;
·
Predict the cumulative noise impacts by any
concurrent construction works in the vicinity; and
·
For any exceedance of noise criteria, all practical
mitigation measures such as alternative construction methodology, quiet plant,
silencer, enclosure, etc, shall be examined to alleviate the predicted noise
impacts as much as practicable.
Utilization Rates and SWLs of Powered Mechanical Equipment
Practically, the PMEs will not be
operating for all times within a work site.
The utilization rates would depend on the construction sequences, work
fronts scale and construction nature. In
this assessment, the utilization rates for each work front during different
periods have been reviewed by the engineer and have been concluded to be
practicable for the purpose of this EIA.
Appendix 5.4A summarizes the adopted
utilization rates and the associated SWL for different construction
sequences.
Noise Assessment Tool
An in-house program has been used
for construction noise calculations.
Initially, the program runs were conducted without any mitigation
measures (i.e. the “Unmitigated Scenario”).
Where noise level exceedance was identified, further runs would be made
assuming different combinations of mitigation measures to be incorporated (i.e.
the “Mitigated Scenario”).
Assessment Results - Unmitigated Scenario
According to the latest engineering design, the construction works would mainly comprise of the activities as described in Section 3.5. The corresponding Sound Power Levels (SWLs) of these activities have been estimated according to the PME’s SWLs and the assessment methodology in the GW-TM. Appendices 5.5A to 5.8A present the PME inventory adopted in each construction works area, including west portion, central portion and east portion. Appendices 5.5B to 5.8B present the distance between the notional sources and the NSRs, screening effects due to terrains etc.