9                            Landscape & Visual Impact

9.1                       Introduction

9.1.1.1              This chapter presents the potential landscape and visual impacts due to the construction and operation of Trunk Road T2 (hereinafter referred to as “the Project”) in accordance with the Environmental Impact Assessment Ordinance (EIAO). The focus of the Landscape Impact Assessment (LIA) as stated within the April 2009 EIA Study Brief ESB-203/2009 shall include areas within 100 metres from the boundary of the project and proposed off-site work sites. The focus of the Visual Impact Assessment (VIA) is defined by the three visual envelopes of the project.  

9.1.1.2              Since the 31 July 2009 date for commencement, the original proposals and locations for the project, and the location of the Trunk Road T2 Eastern Ventilation Building have been relocated to the Lam Tin Interchange. The Trunk Road T2 Eastern Ventilation Building is outside the scope of this study and has been addressed by a separate consultancy.  For information regarding the Trunk Road T2 Eastern Ventilation Building within Lam Tin Interchange, please refer to Section 9 Appendix A for the relevant extracted text and supporting figures from AECOM’s October 2012, Agreement No. CE 42/2008 Tseung Kwan O - Lam Tin Tunnel and Associated Works – Investigation Report (TKO-LTT), which includes an in-depth section within their LVIA and supporting photomontages for the Trunk Road T2 Eastern Ventilation Building, located within the Lam Tin Interchange.  Please note the TKO-LTT EIA is awaiting approval.

9.1.1.3              Trunk Road T2 and associated buildings will be commissioned by the end of 2020 in coordination with both the CKR and TKO-LTT Route 6 projects. According to the approved March 2009 KTD EIA Report and the KTD Recommended Outline Development Plan, the Kai Tak development is proposed to be commissioned by the end of 2020.

9.1.1.4              This LVIA will focus on both the Cha Kwo Ling Eastern Works Area and the KTD South Apron Western Works Area in the construction phase and the Trunk Road T2 Western Ventilation and Tunnel Portal Buildings in the operation phase. All future developments planned within the Kai Tak Development (or any planned developments as appropriate) do not form part of the Project and are not intended for approval under this EIA Submission but are discussed in the section on Cumulative Landscape & Visual Impacts.

9.1.1.5              The scale of the Project will inevitably cause landscape and visual impacts, on both existing and future landscape resources and characteristics as well as visually sensitive receivers (VSRs).  Key issues on landscape and visual impacts during construction and operation stages are identified and assessed.  The scale and extent of the Project site is likely to alter the visual context of some VSRs in Kowloon Bay, Kowloon City and Kwun Tong.

 

9.1.1.6              Given that all underground activities and facilities will unlikely cause landscape and visual impacts, this report assesses potential landscape and visual impacts associated with surface construction activities, excavation, storage and above-ground structures (Tunnel Portal Building & Ventilation Building).

9.1.1.7              The LVIA follows the criteria and guidelines in Annexes 10 and 18 of the EIAO TM. Photographs showing baseline conditions, and photomontages and illustrative materials supporting conclusions are provided and the locations of key viewpoints are mapped. Photomontages provide comparisons between existing views, proposals on day 1 after completion without mitigation measures, on day 1 after completion with mitigation measures, and in year 10 after completion with mitigation measures in accordance with EIAO Guidance Note No. 8/2010.

9.2                       Environmental Legislation, Standards and Guidelines

9.2.1.1              The following legislation, standards and guidelines are applicable to landscape and visual impact assessment associated with the construction and operation of the Project:

·             EIAO  (Cap.499.S.16) and the TM on EIA Process, particularly Annexes 10 and 18;

·             EIAO Guidance Note 8/2010;

·             Protection of Endangered Species of Animals And Plants Ordinance (Cap 586);

·             Town Planning Ordinance (Cap 131);

·             Protection of the Harbour Ordinance (Cap 531);

·             Hong Kong Planning Standards and Guidelines (HKPSG);

·             Study on Landscape Value Mapping of Hong Kong;

·             Land Administration Office Instruction (LAOI) Section D-12 - Tree Preservation;

·             WBTC No. 25/92 - Allocation of Space for Urban Street Trees;

·             WBTC No. 7/2002 - Tree Planting in Public Works;

·             ETWB TC(W) No. 13/2003 - Guidelines and Procedures for Environmental Impact Assessment of Government Projects and Proposals;

·             ETWB TC(W) No. 13/2003A - Guidelines and Procedures for Environmental Impact Assessment of Government Projects and Proposals; Planning  for Provision of Noise Barriers;

·             ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features;

·             ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees (OVTs), and Guidelines for their Preservation;

·             ETWB TCW No. 8/2005 - Aesthetics Design of Ancillary Buildings in Engineering Projects;

·             ETWB No. 36/2004 - Advisory Committee on the Appearance of Bridges and Associated Structures (ACABAS);

·             ETWB TCW No. 3/2006 - Tree Preservation;

·             DEVB TCW No. 2/2012 - Allocation of Space for Quality Greening on Roads;

·             DEVB TCW No. 2/2013 - Greening on Footbridges And Flyovers;

·             DEVB TCW No. 3/2012- Site Coverage of Greenery for Government Building Projects

·             Highways Department - Structures Design Guidelines for Highways & Railways, Third Edition. Section 17.

9.2.1.2              As requested in the EIA Study Brief, relevant Outline Development Plans, Outline Zoning Plans, Layout Plans, Recommended Outline Development Plan for the Kai Tak Development, other planning briefs and studies, guidelines and reports on landscape strategies and landscape/urban frameworks will be reviewed to understand the future outlook of the area affected and to assess whether the project is compatible with its surroundings.

9.2.1.3              The following Statutory and Administrative Plans are relevant to this Study:

·             Draft Ngau Tau Kok and Kowloon Bay Outline Zoning Plan No. S/K13/27 gazetted on 14/10/2011;

·             Approved Kwun Tong (South) Outline Zoning Plan No. S/K14S/18 gazetted on 14/6/2013;

·             Approved Cha Kwo Ling, Yau Tong, Lei Yue Mun Outline Zoning Plan No. S/K15/19 gazetted on 17/06/2011;

·             Approved Kai Tak Outline Zoning Plan No. S/K22/4 gazetted on 14/09/2012; and

·             Recommended Outline Development Plan (RODP) for Kai Tak Development.

9.2.1.4              The following approved EIA Reports are referred to in this Study:

·             Kai Tak Airport North Apron Decommissioning EIA Report (EIAO Register No. AEIAR- 002/1998);

·             Comprehensive Feasibility Study for the Refined Scheme of South East Kowloon Development (EIAO Register No. AEIAR-044/2001);

·             Further Development of Tseung Kwun O Feasibility Study (EIAO Register No. AEIAR-092/2005);

·             Dredging Works for Proposed Cruise Terminal at Kai Tak (EIAO Register No. AEIAR-115/2007);

·             Decommissioning of the Former Kai Tak Airport Other than the North Apron (EIAO Register No. AEIAR-114/2007);

·             Kai Tak Development EIA (EIAO Register No. AEIAR-130/2009); and

·             Installation of Submarine Gas Pipelines and Associated Facilities from To Kwa Wan to North Point for Former Kai Tak Airport Development (EIAO Register No. AEIAR-153/2010).

9.2.1.5              The following previous Kai Tak Development studies and con-current works reports are considered for this LVIA:

·             CE 35/2006 (CE) – Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Preliminary Design Report and Design Memorandum of Trunk Road T2 (Final);

·             CE 35/2006 (CE) – Final Report on Planning, Landscape and Urban Design Study;

·             CE 35/2006 (CE) – Final Preliminary Design Report for Advance Works;

·             CE 35/2006 (CE) – Review Report;

·             CE 35/2006 (CE) – Kai Tak Development Environmental Impact Assessment Report;

·             CE 35/2006 (CE) – ACABAS Submission for Preliminary Design of Highway Structures in KTD; (Revision A)(6-7-09);

·             CE 58/2006 (HY) – Central Kowloon Route and Gascoigne Road Flyover Landscape and Visual Impact Assessment Report;

·             CE 42/2008 (CE) Tseung Kwan O - Lam Tin Tunnel and Associated Works – Investigation Report;

·             CE 43/2010 (HY) Central Kowloon Route - Design & Construction: Draft Landscape and Visual Impact Assessment – Baseline Study;

·             SCL-NEX/2206 EIA Study for Tai Wai to Hung Hom Station (MTR Corporation LTD);

·             CV/2009/06 - Greening Master Plan (GMP) for Kwun Tong District by CEDD; and

·             Recommended Outline Development Plan (RODP) for Kai Tak Development.

9.3                       Assessment Methodology

9.3.1                   General Methodology

9.3.1.1              Landscape and visual impacts have been assessed separately for the construction and operation phases.

9.3.1.2              The methodology will comply with the requirements of Annexes 10 and 18 of the EIAO TM, the EIA Study Brief ESB-203/2009 (issued in April 2009) and the EIAO Guidance Note No. 8/2010. The methodology consists of the following procedures:

·             Review of the planning and development control framework;

·             Landscape impact assessment;

·             Visual impact assessment;

·             Recommendation on landscape and visual mitigation measures;

·             Identification of residual impacts; and

·             Predication of acceptability of impacts.

9.3.2                   Review of the Planning and Development Control Framework

9.3.2.1              A review of the existing planning studies and documents for the Project is carried out to understand the planned role of the site and help determine if the Project fits into the wider landscape context.

9.3.2.2              The review will consider all areas zoned on the Outline Development Plans, Outline Zoning Plans, Layout Plans, and Recommended Outline Development Plan for Kai Tak Development which are physically affected by the Project including the area within the project boundary and temporary construction or works areas. The review considers the following aspects of planning designations:

·             Loss of zoning areas due to the implementation of the Project;

·             Degradation zoning areas which might affect the viability of its landscape planning designation;

·             The visual amenity enjoyed by future residents or users; and

·             The compatibility of the Project with this future landscape.

9.3.3                   Landscape Impact Assessment

9.3.3.1              The assessment of landscape impacts involves:

·             Baseline landscape review;

·             Assessment of the degree of sensitivity of the landscape resources and landscape character areas;

·             Identification of potential sources of landscape impacts;

·             Assessment of the magnitude of landscape impacts before and after mitigation measures: and

·             Prediction of significance of landscape impacts.

9.3.4                   Baseline Landscape Review

9.3.4.1              A baseline landscape review is achieved by site visits and desktop study of topographical maps, information databases and photographs to identify the baseline landscape resources (LRs) and landscape character areas (LCAs) within the study area. Landscape resources include vegetation, patterns of settlement, land use and water bodies.

9.3.5                   Assessment of the Degree of Sensitivity of the Landscape Resources and Landscape Character area

9.3.5.1              Sensitivity of LCAs and LRs identified in the baseline landscape review is assessed by the following factors:

·             Quality and maturity;

·             Importance or rarity;

·             Ability to accommodate change;

·             Significance of the change in local and regional context;

·             Overall size within the study area; and

·             Whether there are any statutory or regulatory limitations / requirements relating to the LCAs and LRs.

9.3.5.2              Sensitivity of each LCA and LR is classified as follows:

High:            Important landscape resources or landscape with particularly distinctive character or high importance, sensitive to small changes.

Medium:       Moderately important landscape resources or landscape with moderately valued landscape characteristics reasonably tolerant to changes.

Low:             Landscape resources of low value or relatively unimportant landscape characteristics highly tolerant to changes.

9.3.6                   Identification of Potential Sources of Landscape Impacts

9.3.6.1              These are various elements of construction and operational works which generate landscape impacts. Such impacts are described, measured and illustrated in this report.

9.3.7                   Assessment of the Magnitude of Landscape Impacts

9.3.7.1              The magnitude of the impact or magnitude of change depends on a number of factors including:

·             Scale of Project;

·             Location of Project;

·             Compatibility of Project with the surrounding landscape;

·             Duration of impacts under construction and operation phases;

·             The relative size of the change in comparison to the size of the LCAs and LRs; and

·             Reversibility of change (changes are residual or not residual after mitigation).

9.3.7.2              The magnitude of landscape impacts is classified as follows:

Large:                   The LCA or LR would experience major change.

Intermediate:       The LCA or LR would experience moderate change.

Small:                    The LCA or LR would experience slight or barely perceptible changes.

Negligible:            The LCA or LR would experience no discernible change.

9.3.8                   Prediction of Significance of Landscape Impacts

9.3.8.1              The degree of significance of landscape impact is derived from the magnitude of change which the Project will cause to the existing LRs & LCAs and ability to tolerate the change, i.e. their sensitivity. The landscape impacts during construction and operation are assessed by combining the sensitivity and the magnitude of change for LRs and LCAs according to Table 9.1. Any such impacts are further defined as beneficial or adverse.

Table 9.1             Matrix for Impact Significance Threshold

Magnitude of Change caused by the Project

Large

Moderate

Moderate / Substantial

Substantial

Intermediate

Slight / Moderate

Moderate

Moderate / Substantial

Small

Slight

Slight / Moderate

Moderate

Negligible

Insubstantial

Insubstantial

Insubstantial

 

Low

Medium

High

 

Sensitivity (LCAs, LRs or VSRs)

 

9.3.8.2    The Degree of Impact Significance Threshold is divided into four thresholds:

Substantial:       Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape.

Moderate:         Adverse / beneficial impact where the proposal would cause noticeable deterioration or improvement in existing landscape.

Slight:                Adverse / beneficial impact where the proposal would cause slight or barely perceptible deterioration or improvement in existing landscape.

Insubstantial:    No discernible change in the existing landscape.

9.3.9                   Visual Impact Assessment

9.3.9.1        The assessment of visual impacts has involved the followings procedures:

·               Identification of Zone of Visual Influence (ZVIs);

·               Identification of Visually Sensitive Receivers (VSRs) within the ZVIs;

·               Identification of relative numbers of VSRs;

·               Assessments of the degree of sensitivity of the VSRs;

·               Identification of potential sources of visual impacts;

·               Assessment of the magnitude of visual impacts; and

·               Predication of significance of visual impacts.

9.3.10               Identification of Zone of Visual Influence (ZVI)

9.3.10.1          This is achieved by site visits and desktop study of topographic maps and photographs, and preparation of cross-section to determine visibility of the Project from various locations. The ZVI for both construction and operational phases of the Project are identified.

9.3.11               Identification of Visually Sensitive Receivers (VSRs) within the ZVI

9.3.11.1          These are the people who would reside within, work within, play within, or travel through, the ZVI.

9.3.12               Identification of relative numbers of VSRs

9.3.12.1          The relative number of VSRs is expressed in terms of whether there are few, medium or many.

9.3.13               Assessments of the Degree of Sensitivity of the VSRs

9.3.13.1          The individual VSRs identified are assessed by the following factors that influence sensitivity:

·             The type of VSRs, which is classified as Residential User, Occupational User, Recreational User or Travelling User according to whether the person is at home, at work, at school, at play, or travelling;

·             Estimated number of receiver population;

·             Value and quality of existing views;

·             Availability and amenity of alternative views;

·             Duration or frequency of view; and

·             Degree of visibility.

9.3.13.2          The ratings for sensitivity of the VSRs are classified below:

High:                 The VSR is highly sensitive to any change in their viewing experience.

Medium:            The VSR is moderately sensitive to any change in their viewing experience.

Low:                  The VSR is slightly sensitive to any change in their viewing experience.

9.3.14               Identification of Potential Sources of Visual Impacts

9.3.14.1          These are the various elements of the construction works and physical aboveground structures of the Project that would generate visual impacts.

9.3.15               Assessment of Magnitude of Visual Impacts

9.3.15.1          Factors for considering the Potential Magnitude of Visual Impacts include:

·             Compatibility with the landscape and character of the surroundings;

·             Duration of impacts;

·             Scale of the project;

·             Reversibility of the change (changes are residual or not residual after mitigation);

·             Viewing distance; and

·             Potential blockage of views.

9.3.15.2          The rating for Magnitude of Change of the view of VSRs is classified as below:

Large:              The VSR would suffer major change in their viewing experience.

Intermediate:  The VSR would suffer moderate change in their viewing experience.

Small:               The VSR would suffer slight or barely perceptible changes.

Negligible:       The VSR would suffer no discernible change.

9.3.16               Predication of Significance of Visual Impacts

9.3.16.1          The significance threshold for visual impacts is rated in a similar fashion to the landscape impact, i.e. significant, moderate, slight and negligible. The visual impact during construction and operation is assessed by combining the sensitivity of change and the magnitude of change of various VSRs according to Table 9.1. The impacts may be beneficial or adverse.

9.3.16.2          The Degree of the Impact Significance is divided into four thresholds:

Substantial:      Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing visual quality.

Moderate:        Adverse / beneficial impact where the proposal would cause noticeable deterioration or improvement in existing visual quality.

Slight:               Adverse / beneficial impact where the proposal would cause slight or barely perceptible deterioration or improvement in existing visual quality.

Insubstantial:   No discernible change in the existing visual quality.

9.3.17               Recommendation on Landscape and Visual Mitigation Measures

9.3.17.1          The identification of the landscape and visual impacts will highlight those sources of conflict requiring design solutions or modifications to reduce the impacts, and, if possible, blend the development and associated activities with the surrounding landscape. Mitigation measures have considered factors including:

·             Adopting alternative design or revisions to the basic engineering or architectural design to prevent and / or minimize adverse impacts;

·             Mitigation measures such as colour, architectural and landscape treatment of physical, engineering and building features;

·             Compensatory measures such as the implementation of  landscape design measures such as creation of new amenity area to compensate for unavoidable adverse impacts and to attempt to generate potentially beneficial long-term impacts;

·             Compensatory tree planting to compensate for felled trees; and

·             Additional tree planting to screen the Trunk Road T2 and associated structures.

9.3.17.2          The mitigation measures will be included in the detail design, construction and operation phases of the Project and associated works to reduce impacts to acceptable levels. Responsible parties will be identified for the on-going management and maintenance of the proposed mitigation measures to ensure their effectiveness throughout the operation phase of the Project and associated works. The Funding Agency and Implementation Agency for the implementation of the recommended mitigation measures are presented in Tables 9.20 and 9.21.  This will follow ETWB TCW No.2/2004 Maintenance of Vegetation and Hard Landscape Features, and ETWB TCW No.3/2006 - Tree Preservation.

9.3.18               Identification of Residual Impacts

9.3.18.1          Residual impacts are those which remain after the proposed mitigation measures have been implemented. These are assessed both during the construction and operation periods, which are taken to be day 1 and 10 years after the Project has been operational.

9.3.18.2          During the operational period the soft landscape mitigation measures will reach a level of maturity that allows them to perform their original design objectives. The residual impacts in this instance will reduce over time as the vegetation becomes established and mature.

9.3.18.3          The significance threshold of residual impacts is derived from the matrices described separately above for the landscape and visual impacts. Both landscape and visual residual impacts are products of magnitude of change and sensitivity of the receiver.

9.3.19               Predication of Acceptability of Impacts

9.3.19.1          The acceptability of the Project is dependent upon the significance of the residual impacts in accordance with the five criteria set out in Annex 10 of the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM). The criteria are summarized below:

·             Beneficial. The project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improve the landscape and visual quality of the study area;

·             Acceptable. The assessment indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the project, or no interference with key views;

·             Acceptable With Mitigation Measures. There will be some adverse effects; these can be eliminated, reduced or offset to a large extent by specific measures;

·             Unacceptable. The adverse effects are considered too excessive and are unable to be mitigated practically; and

·             Undetermined. Significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question.

9.4                       Scope and Content of the Study

9.4.1                   Description of the Project

 

9.4.1.1              The nature, scope and implementation programme of the Project is described in Section 2 & 3 of this Report. In accordance with the Study Brief, this study will assess the landscape and visual impacts during the construction and operation phases of the Project.

9.4.1.2              Background: The Kai Tak (North) Outline Zoning Plan (OZP) and Kai Tak (South) OZP were gazetted in 1998 providing the statutory planning framework for the area. Following subsequent reviews and consultation processes, the OZP for the entire Kai Tak area was gazetted and subsequently amended under the Town Planning Ordinance between 2006 and 2012. It is noted that the land use proposals for Kai Tak would be refined in later stages.  This report also reflects the best available information from the latest Kai Tak OZP and CEDD’s draft Recommended Outline Development Plan (RODP) for Kai Tak Development at the time of preparing the report.

9.4.1.3              As a part of the strategic road network within the South East Kowloon Development, Route 6 forms an east west express link between West Kowloon and Tseung Kwan O. Route 6 comprises the Central Kowloon Route (CKR), Trunk Road T2 and Tseung Kwan O – Lam Tin Tunnel (TKO-LTT).

9.4.2                   Consideration of Alternatives and Development of a Preferred Option

 

9.4.2.1              Details of the comparison of various development options and how the preferred option is formulated and translated are summarized in Section 2 of this report.

9.4.3                   Scope and Content of the Study

 

9.4.3.1              The Project boundary covers the Kowloon Bay, Former Kai Tak South Apron, Kwun Tong and Cha Kwo Ling as shown in Figures 9.1 and 9.2.

9.4.3.2              According to EIA Study Brief No. ESB-203/2009, the study area for the landscape impact assessment shall include all areas within 100m extended from the Project boundary and the proposed off-site work sites.  The assessment area for the visual impact assessment shall be defined by the visual envelope of the Project (ZVI). The study area for the landscape impact assessment and ZVI are indicated in Figures 9.1 and 9.2.

9.5                       Review of Planning and Development Control Framework

9.5.1                   Review of Outline Development Plan and Outline Zoning Plans

 

9.5.1.1              The proposed Trunk Road T2 has been planned within limited land take and where possible is in tunnel. A review of the existing and planned development framework for the proposed works and for the surroundings is undertaken. It identifies issues for neighbouring planned land uses, identifying potential resources and sensitive receivers, and ensuring a high compatibility between the Project and the surroundings.

9.5.1.2              The study area is covered by:

·             Draft Ngau Tau Kok and Kowloon Bay Outline Zoning Plan No. S/K13/27 gazetted on 14/10/2011;

·             Approved Kwun Tong (South) Outline Zoning Plan No. S/K14S/18 gazetted on 14/6/2013;

·             Approved Cha Kwo Ling, Yau Tong, Lei Yue Mun Outline Zoning Plan No. S/K15/19 gazetted on 17/06/2011;

·             Approved Kai Tak Outline Zoning Plan No. S/K22/4 gazetted on 14/09/2012; and

·             Recommended Outline Development Plan (RODP) for Kai Tak Development (KTD).

9.5.1.3              The review of ODPs and OZPs has not only included a review of the plans, but also the “Notes” and “Explanatory Statements” which accompany, and form part of these plans.

9.5.1.4              The proposed alignment of the at-grade section of Trunk Road T2 at the south apron is located within the planned road corridor of the approved Kai Tak OZP as shown in Figures 9.5 and 9.5.1 to 9.5.8. However, some of the proposed works will cause a minor change of current land use in the area. The change comprises:

9.5.1.5              The proposed Ventilation Building at Kai Fuk Road located within areas zoned “Other Specific Uses (Tunnel Ventilation Shaft)” (“OU”) as shown in Figure 9.1. Since this zone is already reserved for tunnel ventilation shaft use, it is not considered to have potential conflicts with the planning intention of this OZP.

9.5.1.6              On completion of the approved design of the Trunk Road T2 and associated buildings, it is recommended that the OZP shall be amended to incorporate the changes arising from the Project.

9.5.1.7              Apart from the change in land use mentioned above, there will not be any impacts on guidelines on landscape strategies, landscape frameworks, urban design concept, building height profiles, special design areas, landmarks, designated view corridors, open space networks and landscape links of the area except for the RODP for KTD. Ongoing liaison between the proponent of this Project and KTD regarding the proposed zoning and road alignment will be carried out throughout the design development process to ensure the Project is compatible with the future context of the area.

9.5.1.8              As a whole, it is considered that the Project would be in accordance with the planning intentions for the study areas, as set out in the OZPs and other planned development framework. 

9.6                       Baseline Study

9.6.1              Baseline Study

 

9.6.1.1              The study areas cover the South Apron of the former Kai Tak Airport, Kwun Tong, Cha Kwo Ling, and adjacent water bodies. The extent of works are illustrated in Figures 9.1 and 9.2.

9.6.1.2              The landscape baseline review comprises the identification of all existing Landscape Resources (LRs) and Landscape Character Areas (LCAs) within 100m from the works limit of the Project.

9.6.1.3              The visual baseline review comprises the identification of all Visually Sensitive Receivers (VSRs) within the Zones of Visual Influence (ZVIs) of the Project.

9.6.1.4              For ease of reference each LR, LCA and VSR is given an identity number, which is used in all relevant tables and figures in this report.

9.6.2             Landscape Resources

 

9.6.2.1              The baseline landscape resources that will be affected during the Construction and Operation Phases, together with their sensitivity, are described in Table 9.2. The locations of LRs are mapped in Figures 9.6.1 and 9.6.2. Photo views illustrating the LRs within the study area are illustrated in Figures 9.7.1 to 9.7.4.

9.6.2.2              In surveying and reviewing the Trunk Road T2 Works Area, no Old and Valuable Trees, important trees or wall trees are found within the site boundary or within the proximity of the works area. For all tree locations, refer to Figures 9.10.1 and 9.10.2.

Table 9.2         List of Landscape Resources and their Sensitivity

ID. No.

Landscape Resources

Sensitivity

(Low, Medium, High)

LR1

 

Roadside Planting (Kai Fuk Road)

There are approximately 40 trees of semi-mature size planted along the roadside. The area is approximately 6,430 square metres. No area will be required by the Project for either Construction or Operation phases. Trees in this area are 5-12 meters in height with low to medium amenity value. The species mainly include Acacia confusa, Albizia lebbeck, Aleurites moluccana, Caryota mitis and Melaleuca cajuputi subsp. cumingiana. Some tall shrubs such as Schefflera arboricola and Schefflera actinophylla are planted underneath. The sensitivity of this landscape resource is considered medium.

Medium

LR2

 

Derelict / Disturbed Land Proposed as Open Space (Kai Fuk Road)

There are approximately 78 trees of young to mature size planted along the road side and periphery of the amenity area. The size of the area is approximately 3,120 square metres. This area is currently used for storage of construction materials.  No area will be required by the Project for either Construction or Operation phases. Trees in this area are 3-9 meters in height with low to medium amenity value. The species mainly include Macaranga tanarius var. tomentosa, Leucaena leucocephala, Morus alba,  Thevetia peruviana and Aleurites moluccana.  The sensitivity of this landscape resource is considered medium.

Medium

LR3

 

Roadside Planting (Sheung Yee Road)

Small shrubs in columnar form such as Garcinia subelliptica and Podocarpus macrophyllus are planted along Sheung Tee Road. Some colourful and flowering shrubs such as Cordyline fruticosa, Duranta erecta, Osmanthus fragrans, Loropetalum chinensis f. rubrum and Ixora chinensis are planted underneath. The size of the area is approximately 2,560 square metres. No area will be required by the Project for either Construction or Operation phases.The sensitivity of this landscape resource is considered medium.

Medium

LR4

 

Car Park (GW Parking Lot at Sheung Yee Road)

There are approximately 28 trees of young to semi-mature size planted within Sheung Yee Road Parking Lot. The size of the area is approximately 4,710 square metres.  Trees in this area are 3-8 metres in height with low to medium amenity value. The dominant species include Albizia lebbeck, Aleurites moluccana, and Macaranga tanarius var. tomentosa. No area will be required by the Project for either Construction or Operation phases. The sensitivity of this landscape resource is considered low.

Low

LR5

 

Occupational Land (Kai Fuk Road Shell Garage)

There are approximate 11 trees of young to semi-mature size planted within amenity planters at Kai Fuk Road Shell Garage. The size of the area is approximately 1,590 square metres. Trees in this area are 5-8 metres in height with medium amenity value. The dominant species include Aleurites moluccana, Bombax ceiba and Delonix regia.  No area will be required by the Project for either Construction or Operation phases. The sensitivity of this landscape resource is considered medium.

Medium

LR6

 

Amenity Area (Kai Fuk Road / Kwun Tong By-pass)

This amenity area comprises a series of small sitting out areas and a footpath, in addition to planting under and next to the elevated Kuwn Tong Bypass. The size of the area is approximately 11,010 square metres. Within the site there are approximately 81 trees of young to semi-mature size planted along the amenity area next to Kwun Tong By-pass in the T2 area. Trees in this area are 5-12 mxeters in height with low to medium amenity value. The dominant species include Albizia lebbeck, Aleurites moluccana, Bauhinia variegata and Spathodea campanulata. The overall form and health of trees surveyed are fair to poor. A majority of them have broken and/or dead branches and are damaged. Some colourful and flowering shrubs such as Cordyline fruticosa, Duranta erecta, Excoecaria cochinchinensis and Ixora chinensis are planted underneath. The sensitivity of this landscape resource is considered medium.

Medium

LR7

 

Amenity Area (under Kwun Tong By-pass)

This is a small amenity area connecting the Kowloon Bay Industrial Area and the former Kai Tak South Apron. Parts of the area are under the Kai Fuk Road Flyover and Kwun Tong By-pass. The size of the area is Approximately 19,720 square metres.  There are approximately 100 semi-mature trees of 6 - 10 metres height with low to medium amenity value. Dominant species include Acacia confusa, Lagerstroemia speciosa, Caryota  mitis, Schima superba and Delonix regia. Some shrubs such as Cordyline fruticosa, Duranta erecta, Allamanda schottii and Spathiphyllum floribundum are planted around the planting area. No area will be required by the Project for either Construction or Operation phases. Given the relative small size of this open area and less prominent location, the sensitivity of this landscape resource is considered medium.

Medium

LR8

 

Derelict / Disturbed Land (KTD South Apron)

There are 46 trees recorded within the Project. The dominant species include Melia azedarach and Archontophoenix alexandrae. An exotic species of invasive weed tree is also abundant in the area near Cheung Yip Street, namely Leucaena leucocephala. There are two planters which combine to measure 159 square metres.

The size of the area is approximately 208,440 square metres. The temporary Western Works construction area will require approximately 75,300 square metres of LR8. The sensitivity of this landscape resource is considered low.

Low

LR9

 

Water Body (Kai Tak Approach Channel)

It is an artificial water body connecting the Kai Tak Nullah and Kwun Tong Typhoon Shelter. The size of the area is approximately 32,910 square metres. Both sides of the channel are linear man-made intertidal hard shore with some weeds scattered along it. It serves as a transition between a nullah and open water which is sensitive to reclamation. The sensitivity of this landscape resource is considered medium.

Medium

LR10

 

Artificial Shoreline (KTD South Apron)

The straight artificial shoreline along former Kai Tak South Apron comprises armour stone and concrete pavement. The size of the area is approximately 1,100 square metres. Some self-seeded trees, including the invasive weed tree Leucaena leucocephala, grow between the gaps along the artificial shoreline which are of low amenity value. It is currently bounded by the construction site which is not accessible to the public. The sensitivity of this landscape resource is considered low.

Low

LR11

 

Amenity Area (Public Works Central Laboratory)

There are approximately 25 trees of young to semi-mature size planted within the amenity areas in Public Works Central Laboratory. The size of the area is approximately 870 square metres. Trees in this area are 4-15 meters in height with low to medium amenity value. The dominant species include Aleurites moluccana, Bombax ceiba, Callistemon viminalis, Chrysalidocarpus lutescens and Spathodea campanulata. Some colourful and flowering shrubs such as Duranta erecta and Ixora chinensis are planted underneath.  No area will be required by the Project for either Construction or Operation phases. The sensitivity of this landscape resource is considered medium.

Medium

LR12

Water Body (Kwun Tong Typhoon Shelter)

It is a semi-enclosed water body bounded by the runway of former Kai Tak Airport, the man-made hard shore of Kwun Tong Public Cargo Working Area and the breakwater at southern end. The size of the area is approximately 315,320 square metres. The sensitivity of this landscape resource is considered medium.

Medium

LR13

Water Body (Victoria Harbour)

It is a recognised and distinctive feature of Hong Kong worldwide, both as a tourist attraction and working port. The size of the area is approximately 206,790 square metres. The area will be used for barging construction and demolition waste from the Western Works Area. No area will be required by the Project throughout the Operation phase. The Harbour forms an iconic centrepiece for Hong Kong, with the airport runway forming a unique coastline edge. The sensitivity of this landscape resource is considered high.

High

LR14

Roadside Planting (Cha Kwo Ling Road)

There are approximately 43 trees of young to semi-mature size planted along the Cha Kwo Ling Road. The size of the area is approximately 1,570 square metres. No area will be required by the Project for either Construction or Operation phases. Trees in this area are 5-12 meter in height with low to medium amenity value. The dominant species include Bischofia javanica, Melaleuca cajuputi subsp. cumingiana  and Spathodea campanulata.  The sensitivity of this landscape resource is considered medium.

Medium

LR15

Residential Landscape (Cha Kwo Ling Residential Area)

There are approximately 80 trees within the low rise area of Cha Kwo Ling Village. The size of the area is approximately 21,660 square metres. No area will be required by the Project for either Construction or Operation phases. Trees in this area are 5-14 meter in height with low to medium amenity value. The dominant species include Acacia spp., Eucalyptus spp., Ficus spp., Litsea glutinosa, Mallotus paniculatus, Sterculia lanceolata. The existing trees and shrubs occupy an area of 1ha.  The sensitivity of this landscape resource is considered medium.

Medium

LR16

Derelict / Disturbed Land Proposed as Cha Kwo Ling Promenade Park by Others (Cha Kwo Ling Former Public Cargo Working Area)

It is currently a fenced-off area inaccessible to the public of approximately 27,020 square metres. Some self-seeded weeds and one tree, Macaranga tanarius var. tomentosa, with low amenity value grow between the gaps in the concrete pavement. The sensitivity of this landscape resource is considered low.

Low

LR17

Derelict / Disturbed Land (Wai Lok Street Reclaimed Industrial Area)

The size of the area is approximately 7,370 square metres. No area will be required by the Project for either Construction or Operation phases. The area has some self-seeded weeds with low amenity value. There are no trees within the promenade area.  It is currently fenced-off and inaccessible to the public. A temporary holding nursery is beside Wai Lok Street Reclaimed Industrial Area. There are approximately 15 trees of young to semi-mature size within the area. Trees are 3-7 meters in height with low to medium amenity value. The dominant species include Delonix regia, Hibiscus tiliaceus and Senna siamea. The sensitivity of this landscape resource is considered low.

Low

LR18

Occupational Land (Wai Lok Street Garage)

There are approximately 30 trees of young to semi-mature size planted within Wai Lok Street Garage area. The size of the area is approximately 7,040 square metres. No area will be required by the Project for either Construction or Operation phases. The trees in this area are 4-11 metres in height with low to medium amenity value. The dominant species include Ficus elastica, Callistemon viminalis, Hibiscus tiliaceus and Macaranga tanarius var. tomentosa. An exotic species of invasive weed tree is abundant within the area, namely Leucaena leucocephala. The sensitivity of this landscape resource is considered low.

Low

LR19

Amenity Area and Access Road (Adjacent to Wai Lok Street Temporary Soccer Pitch)

There are approximately 18 trees of young to semi-mature size along the southern boundary of the area adjacent to the soccer pitch. The size of the area is approximately 900 square metres. No area will be required by the Project for either Construction or Operation phases. The trees in this area are 3-6 metres in height with medium amenity value. The dominant species includes Delonix regia. Some colourful and flowering shrubs such as Duranta erectaVariegata’, Allamanda cathartica and Wedelia trilobata are planted around the study area. A grass soccer pitch is adjacent to the southern boundary of the area. The sensitivity of this landscape resource is considered medium.

Medium

LR20

Derelict / Disturbed Land Proposed as Cha Kwo Ling Promenade Park by Others (Wai Yip Street / Cha Kwo Ling Road Reclaimed Industrial Area)

This derelict/disturbed land is approximately 11,240 square metres. No area will be required by the Project for either Construction or Operation phases. There are approximately 5 trees of young to semi-mature size within the area. Trees in this area are 5-11 metres in height with low to medium amenity value. The dominant species includes Casuarina equisetifolia and Ficus microcarpa. The sensitivity of this landscape resource is considered low.

Low

LR21

Occupational Land (Wai Yip Street Car Park)

This is a hard standing area with approximately 4 trees of young to semi-mature size. The size of the area is approximately 1,840 square metres. No area will be required by the Project for either Construction or Operation phases. Trees in this area are 3-5 metres in height with low amenity value. The dominant species include Macaranga tanarius var. tomentosa and the invasive exotic weed tree Leucaena leucocephala. The sensitivity of this landscape resource is considered low.

Low

9.6.3                   Landscape Character Areas

 

9.6.3.1              Landscape Character Areas have been identified within the Study Area in accordance with the Study on Landscape Value Mapping of Hong Kong. These are described in Table 9.3 and mapped in Figures 9.8.1 to 9.8.2. Photo views illustrating the LCAs within the study area are illustrated in Figures 9.9.1 and 9.9.2.

Table 9.3        List of Landscape Character Areas and their Sensitivity

ID. No.

Landscape Character Area

Sensitivity

(Low, Medium, High)

LCA1

Major On-Going Development Landscape 

This area comprises the former Kai Tak Airport which can be further sub-divided to the North Apron area, the South Apron corner and the Runway Precinct. The area is generally flat, open, primarily hard standing.  Currently the area is undergoing various demolition/site clearance, infrastructure and construction projects within both the South Apron and Runway Precinct areas. The area is comprised of the following Landscape Resources: LR8, LR10 & LR11. In total the landscape resources is approximately 210,410 square metres. 

As previously discussed, in the landscape resources section the temporary Western Works construction area is approximately 75,300 square metres. Given the area is already disturbed by ongoing construction work but includes 159 square metres of planting and 71 trees, the sensitivity of this area is considered low.

Low

LCA2

Kowloon Bay Industrial Urban Landscape

This is an area of industrial and commercial use.  This comprises medium to high -rise industrial buildings.  The streetscape is a mix of utilitarian with very little soft landscape treatment within the older Kowloon Bay industrial areas and upgraded streetscape of a mix of trees and planter beds around the new developments. The area is comprised of the following Landscape Resources: LR2, LR3 & LR4. In total the landscape resources is approximately 10,390 square metres which includes 106 trees.  Given the urbanized nature of the area the sensitivity of this area is considered medium.

Medium

LCA3

Transport Corridor

This area are comprises the Kwun Tong Bypass (elevated bypass expressway), Kai Fuk Road, Wai Yip Street and Cha Kwo Ling Road.  The area is comprised of the following Landscape Resources: LR1, LR5, LR6, LR7 & LR14. In total the landscape resources is approximately 40,320 square metres. 

Within the area a few amenity plantings of low to medium amenity value are found in the central medians on both sides of the corridors which include 275 trees. It is slightly sensitive to highway development. Given the urbanized nature of the area and the few amenity plantings, the sensitivity of this area is considered medium.

Medium

LCA4

Kwun Tong Typhoon Shelter Landscape

This is an area for typhoon shelter use in Kwun Tong.  It is substantially enclosed by coast and offshore breakwater. Though they consist primarily of water, other features in these landscapes include jetties, pontoons and navigational features resulting in a landscape that is a transitional one between land and sea. The area is comprised of the following Landscape Resources: LR12. In total the landscape resources is approximately 315,320 square metres. Given this area is comprised by mainly water body, the sensitivity of this area is considered medium.

Medium

LCA5

Kai Tak Typhoon Shelter Landscape

This is an area for typhoon shelter use in Kai Tak and Kowloon bay.  It is enclosed by an artificial coastline and offshore breakwater. The area is an unused large standing body of water.  It is comprised of the following Landscape Resource: LR9 and LR10. In total the landscape resources is approximately 34,010 square metres. Given this area is comprised by mainly man made artificial features the sensitivity of this area is considered medium.

Medium

LCA6

Cha Kwo Ling Miscellaneous Urban Fringe Landscape

This area is dominated by low rise residential development scattered along the hillside. There are patches of roadside tree planting of low to medium amenity value along the Cha Kwo Ling Road. Fruit trees have been planted by the villagers, in front of their homes. The area is sensitive to tunnel and highway development. The area is comprised of the following Landscape Resources: part of LR15. In total the landscape resources is approximately 21,660 square metres with approximately 80 trees. Given the urbanized nature of the area and the low to medium amenity value of tree planting, the sensitivity of this area is considered medium.

Medium

LCA7

Cha Kwo Ling Reclaimed Industrial Urban Landscape

This is a fenced-off area of mixed of reclaimed industrial areas, sewage treatment works, reclaimed open storage, cargo and dock. The study area is utilitarian and lack of amenity plantings. Most of the study area is hard standing or vacant with self-seeded weeds that are with low amenity value. The area is slightly sensitive to the highway development. The area is comprised of the following Landscape Resources: LR14, LR16 and LR17. In total the landscape resources is approximately 34,390 square metres with approximately 16 trees. Though LR14 is within the boundary of LCA7, the area coverage is included in LCA3. Given the urbanized nature of the area and lack of amenity plantings, the sensitivity of this area is considered low.

Low

LCA8

Wai Yip Street/Cha Kwo Miscellaneous Urban Fringe Landscape This is an area of mixed of a petrol station, car park, temporary soccer pitch and temporary tree nursery. Some amenity plantings with trees and shrubs of low to medium amenity value are found within the petrol station and temporary soccer pitch. The area is comprised of the following Landscape Resources: LR18, LR19, LR20, LR21 and a small portion of LR17.  In total the landscape resources is approximately 21,020 square metres which include 57 trees. Given the urbanized nature of the area and the low to medium amenity value of the planting, the sensitivity of this area is considered medium.

Medium

LCA9

Victoria Harbour Inshore Water Landscape

This area refers to costal water off Kowloon Bay and Kwun Tong. The extent of seascape is part of the open seascape locally. The area is comprised of the following Landscape Resources: LR13. In total the landscape resources is approximately 206,790 square metres. As the area is very sensitive to reclamation, the sensitivity of this area is considered high.

High

9.6.4                   Zones of Visual Influence

 

9.6.4.1              The Zones of Visual Influence for the Project vary between the Construction and Operation Phases. Both ZVIs for Construction and Operation Phases are mapped in Figures 9.14 to 9.14.7 and 9.15 to 9.15.6 respectively. VSRs within the study area are illustrated in Figures 9.16.1 to 9.16.13.

9.6.4.2              For the Construction Phase the ZVI has been divided into Western and Eastern Works Areas. The Western Works Area ZVI is quite extensive through the Construction Phase as there are potentially clear views on to the works area whilst the Kai Tak Development Runway Precinct and South Apron are under construction. The Eastern Works Area ZVI is not as extensive, though there are still open views onto the works area from the surrounding developments and across Kowloon Bay from Hung Hom.

9.6.4.3              In the Operation Phase only the Western Works Area ZVI is affected. The ZVI will be limited to the above-ground permanent structures including the road corridor, tunnel portal and ventilation buildings. Due to proposed developments, as per the Recommended Outline Development Plan (RODP) for Kai Tak, these buildings will be potentially screened by the adjacent buildings and elevated Kwun Tong By Pass.


9.6.5                   Visually Sensitive Receivers

 

9.6.5.1              Key VSRs found within the ZVI are described in Table 9.4. The assessments of the degree of sensitivity are listed in Tables 9.5, 9.6 and 9.7. VSRs are divided into Residential, Occupational, Recreational and Travelling.

            Table 9.4                    List of the Visually Sensitive Receivers – Construction Phase

VSR

ID. No.

Visually Sensitive Receivers

Type of VSRs

Status

O1

General Description

Newport Centre

The building is low rise, with eastern views across Kowloon Bay and KTD: The Runway Precinct on to the Western Works Area. Currently the site is undergoing various clearance, and infrastructure construction work with no major aesthetic appeal for the area. The building is planned for redevelopment. The value and quality of the existing view is fair.

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location have open eastern views of approximately 1150m min, onto the Western Works Area. Depending on the detailed design and construction of RE5, there could be glimpsed views of the site. The sensitivity of this VSR is considered low.

Operational Phase

 Eastern Works Area: N/A

Western Works Area: Refer to R1 For description.

O2

General Description

Kai Tak 1M: Comprehensive Development Area

A planned high rise building, on a reclaimed site within the KTD: North Apron Area. The Area is currently undergoing various regeneration and construction projects.

Occupational

Planned

(2016)

Construction Phase

Eastern Works Area: N/A

Western Works Area: Development is planned to be operational by 2016. VSRs in this location will have a glimpse south eastern view of approximately 1350m min towards the Western Works Area. The sensitivity of this VSR is considered low.

O2

Operational Phase

Eastern Works Area: N/A

Occupational

Planned

(2016)

Western Works Area: Depending on the detail design of GIC6, GIC7, GIC9 & GIC10, future VSRs in this location will have a glimpse southern view of approximately 1450m min towards the Trunk Road T2 Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

O3

General Description

Skyline Tower, Kowloon Bay

This VSR is one of the tallest commercial buildings in Kowloon Industrial Area. Viewers at medium to high levels in these buildings have open and panoramic south eastern views over the area and onto Victoria Harbour.

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have a partial south eastern view of approximately 700m min towards the Trunk Road T2 Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Due to South Apron Development being completed by 2021, the view will be screened by GIC9 and GIC10 depending on the detailed design and construction of the above buildings. VSRs in this location will have a partial southern view of approximately 650m min onto the Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

O4

General Description

Hong Kong International Trade and Exhibition Centre

Existing medium rise building. VSRs in this location will have partial views to the project area. Views are blocked by the elevated Kwun Tong By-pass, roadside trees and the Jordan Valley Box Culvert; desilting & pumping station house buildings, which are currently under construction. South eastern facing users will be affected.

Occupational

Existing

Construction

Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs in this location will have a partial south eastern view of approximately 400m min towards the Western Works Area. As the VSR is currently looking onto the derelict South Apron site, the sensitivity of this VSR is considered medium.

O4

Operational Phase

Eastern Works Area: N/A

Occupational

Existing

Western Works Area: Due to South Apron Development being completed by 2021, the view will be screened by GIC6, GIC9 & GIC10, depending on the detailed design and construction of the buildings. VSRs will have a partial southern view of approximately 500m min onto the Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

O5

General Description

Enterprise Square & Enterprise Square II, Industrial/Office development Kowloon Bay

Existing medium to high rise buildings with partial south and south-eastern views from the upper building levels onto the Trunk Road T2, area. The view to the project site is partially blocked by elevated Kwun Tong By-pass, roadside trees and the Jordan Valley Box Culvert; desilting & pumping station house buildings. South eastern facing users will be affected.

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs in this location will have a partial south eastern view of approximately 200m min towards the Western Works Area. As the VSR is currently looking onto the derelict South Apron site, the sensitivity of this VSR is considered medium.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Due to South Apron Development being completed by 2021, the view will be screened by GIC9 & GIC10, depending on the detailed design and construction of the buildings. VSRs will have a partial southern view of approximately 250m min towards upon the Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

 

 

O6

General Description

Kai Fuk Industrial Center, Hong Leong Industrial Complex & Billion Centre

Existing medium to high rise buildings. The view to the project site is partially blocked by elevated Kwun Tong By-pass, roadside trees and the Jordan Valley Box Culvert; desilting & pumping station house buildings.

Occupational

 

 

 

 

 

Existing

 

 

 

 

 

 

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs will have a full south eastern view of approximately 120m min towards the Western Works Area. As the VSR is currently looking onto the derelict South Apron site, the sensitivity of this VSR is considered medium.

 

 

Operational

Phase

Eastern Works Area: N/A

 

 

Western Works Area: Due to South Apron Development being completed by 2021, the area will be screened by the proposed buildings. VSRs will have a partial southern view of approximately 140m min towards upon the Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered medium.

 

 

O7

General Description

Mega Box/Enterprise Square V, Enterprise Square III, Exchange Tower, Manhattan Place & One Kowloon

VSRs in these locations are some of Kowloon’s industrial and commercial areas tallest buildings. The users in mid to upper levels will have panoramic views of the Victoria Harbour area, depending on the detail design of the completed Runway Precinct and South Apron Area.

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs in this location will have a full south eastern to south western view of approximately 70m min towards the Western Works Area. As the VSR is currently looking onto the derelict South Apron site, the sensitivity of this VSR is considered medium.

 

 

O7

Operational Phase

Eastern Works Area: N/A

Occupational

Existing

Western Works Area: Due to South Apron Development being completed by 2021, VSRs will have a partial western to southern view of approximately 70m min towards upon the Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered medium.

 

 

O8

General Description

Petrol Stations along Kai Fuk Road

VSRs in these locations are on separate sides of the Kai Fuk Road. The existing view is a typical road corridor comprised by elevated Kwun Tong By-pass, Kai Fuk Road and roadside amenity planting.

Occupational

 

 

 

 

 

 

 

Existing

 

 

 

 

 

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have a southern view of approximately 80m min to the Western Works Area has a glimpse view due to screening of the roadside amenity planting, the road corridor and the Jordan Valley Box Culvert; desilting & pumping station house buildings. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have a southern view of approximately 80m min to the Western Tunnel Portal & Ventilation Buildings are glimpsed due to the screening of roadside amenity planting, the road corridor, GIC9 & GIC10. The sensitivity of this VSR is considered low.

O9

General Description

Kai Tak Runway Precinct Hotel Belt

A row of medium-rise buildings are planned on the southern fringe for hotel development. 

Occupational/Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have glimpse of approximately 500m min  north and north-western views onto the project site. Though buildings close to the D4 road bridge will have direct northern views onto the Western Tunnel Portal Building, depending on the detail design and construction of GIC11A which is planned to be completed by 2016, and R5, RE8 & GIC11C, which are planned for completion in 2021. The sensitivity of this VSR is considered low.

O10

General Description

Kai Tak Cruise Terminal & Tourism Related Commercial Development 

A mixed use commercial development of low to high rise buildings is currently under construction and is planned for completion by 2014 and 2015.

Occupational/Recreational

Planned

(2014- 2015)

Construction Phase

Eastern Works Area: VSR’s in this location will have a partial south eastern view of approximately 1100m min onto the Eastern Works Area. Additional marine traffic for moving construction and demolition material between the Eastern and Western Works Areas will have an indirect impact onto this VSR. As the view onto the eastern site waterfront area is in context with adjacent redevelopment, the sensitivity of this VSR is considered low.

 

 

Western Works Area: VSRs in this location will have a partial north western view of approximately 500m min towards the Western Works Area. However this will be viewed within the context of adjacent major KTD redevelopment. The sensitivity of this VSR is considered medium.

 

 

 

 

 

O10

Operational

Phase

Eastern Works Area: N/A

Occupational/Recreational

Planned

(2014- 2015)

Western Works Area: Due to South Apron Development being completed by 2021, the area will be screened by O12 and GIC11A, which are planned to be completed by 2016, and R5, RE9 which are planned for completion in 2021. Depending on the detail design and construction of these developments, the future users within the upper floors will have glimpse north and north-western views of approximately 1200m min onto the project site onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered medium.

O11

General Description

Vacant Lot at southern end of former Kai Tak South Apron/3E1 Commercial Development

The Site is currently a bus parking area. Within the construction phase the site is planned to be used as a site works area.  As per the RODP, the Site is designated as a medium to high rise commercial development. At present, there is no re-development schedule available for review. (Exact details for demolition or redevelopment are not currently known).

Occupational

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Existing/Planned

 (2021)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: As this area is designated as a site works area within the Construction phase, it is not designated as a VSR.

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have a partial north western to northern view of approximately 320m min to the Western Tunnel Portal & Ventilation Buildings. As the completion of the buildings is proposed for completion in 2021, the sensitivity of this VSR is considered medium.

O12

General Description

Kai Tak South Apron: Gas Pigging Station

Within Appendix A – Development Schedule for Draft RODP [Ref: WP019-02] (August 2012) A Gas Pigging Station is proposed for a 2012 completion. There is a caveat, that the area could be rezoned for residential development.

Occupational

Planned

(2012-2015)

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have a view of approximately 5m min onto the Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: On completion of the 2021, South Apron Development the future users will have partial north-western views of approximately 350m min onto the project site onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered low.

O13

General Description

Pacific Trade Centre/ Proposed 3D2 Commercial Development

The site is currently the Pacific Trade Centre. As per the RODP the site is planned to be redeveloped into a medium to high rise commercial development. At present, there is no re-development schedule available for review (exact details for demolition or redevelopment are not currently known). 

Occupational

Existing/Planned

(2021)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs in this location will have south eastern partial views, obstructed by 014, R3 and R4, of approx 200m min onto the project area. The sensitivity of this VSR is considered low.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Future viewers in this VSR will have a partial north western to northern view of approximately 380m min to the Western Tunnel Portal & Ventilation Buildings. As the completion of the buildings is proposed for completion in 2021, the sensitivity of this VSR is considered medium.

O14

General Description

Octa Tower

Existing high-rise office development with 360 degree views on the Kowloon Bay/Kwun Tong Commercial Areas and of Victoria Harbour.

Occupational

Existing

Construction Phase

Eastern Works Area: VSRs in this location will have glimpse south eastern views of approximately 1800m min onto the Eastern Works Area. As the view is onto the waterfront area and Victoria Harbour, the sensitivity of this VSR is considered low.

Western Works Area: VSRs in this location will have full south western to north western views onto the Western Works Area of approximately 20m. The sensitivity of this VSR is considered medium.

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have a partial north western to northern view of approximately 320m min to the Western Tunnel Portal & Ventilation Buildings. As the buildings are proposed to be operational in 2021, the sensitivity of this VSR is considered medium.

O15

General Description

 Not Used

 

 

Construction Phase

Eastern Works Area: Not Used.

Western Works Area: Not Used.

Operational Phase

Eastern Works Area: Not Used.

Western Works Area: Not Used.

O16

General Description

Proposed Industrial/Office development at Kwun Tong Commercial Area

Planned high rise building. The view to the project site is partially blocked by elevated Kwun Tong By-pass.

Occupational\

Planned

(2015

 

Construction Phase

Eastern Works Area: There are glimpse views onto the Eastern Works Area, though additional marine traffic between the eastern and Western sites will have an indirect impact onto this VSR. As the view onto the waterfront area is dominated by additional marine traffic for construction and demolition material, the sensitivity of this VSR is considered low.

 

 

O16

Construction Phase

Western Works Area: South west and north west facing VSRs are affected whilst the Trunk Road T2 Western Works Area is under construction. VSRs in this location will have a partial south western to north western view of approximately 300m min to the Western Works Area. The sensitivity of this VSR is considered medium.

Occupational\

Planned

(2015

 

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: VSRs in this location will have a glimpse western view of approximately 650m min to the Western Tunnel Portal & Ventilation Buildings, depending on the detailed design and construction of R3, R4, O11, O13 and GIC11B. The sensitivity of these VSRs is considered low.

 

 

O17

General Description

Industrial/Office development at Kwun Tong Western commercial area

The existing view is of Kwun Tong Typhoon Shelter to the south west and a typical industrial area with medium to high-rise buildings within Kwun Tong’s commercial district.

Occupational

Existing

 Construction Phase

 

 

 

 

 

 

Eastern Works Area: At the north western end, there are no direct views onto the Eastern Works Area, though views of approximately 200m min to additional marine traffic for construction and demolition material between the eastern and western sites will have a partial indirect impact onto this VSR. The sensitivity of this VSR is considered low.

 

Western Works Area: The view to the project site is partially blocked by elevated Kwun Tong By-pass and cargo working areas. Only south west facing users are affected whilst the Western Works Area is under construction. Viewers in these VSR’s will have a partial south western – north western view of approximately 320m min to the Trunk Road T2 Western Works Area. The sensitivity of this VSR is considered low.

 

 

O17

Operational

Phase

Eastern Works Area: N/A

Occupational

Existing

Western Works Area: Viewers in these VSR’s will have a glimpse western view of approximately 650m min to the Western Tunnel Portal & Ventilation Buildings, depending on the detailed design and construction of R3, R4, O11 and O13 the completion of the buildings  which are proposed for completion in 2021, the sensitivity of this VSR is considered low.

O18

General Description

Industrial/Office development at Kwun Tong Eastern commercial area

The existing view is of Kwun Tong Typhoon Shelter & Kai Tak Cruise terminal to the south west. The area is a mix of medium-to- high-rise, new commercial and industrial buildings within Kwun Tong’s commercial district.

Occupational

Existing

Construction Phase

Eastern Works Area: At the south eastern end, the VSRs have glimpse south eastern views of approximately 360m min onto the project site. As the site is currently a decommissioned cargo works area the sensitivity of this VSR is considered low.

Western Works Area: The view to the project site is partially blocked by elevated Kwun Tong By-pass and a decommissioned cargo Works Area. Only south west facing users are affected whilst the Western Works Area is under construction. VSRs in this location will have a partial south western – north western view of approximately 750m min to the Trunk Road T2 Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: Not Used.

Western Works Area: Not Used.

O19

General Description

Kwun Tong Sewage Treatment Works/Kwun Tong Pumping Station /Planned Landscape Decked: Enclosed Sewage Works

The development is divided into two sites, separated by the Kwun Tong By-pass and Kwun Tong Nullah. The existing view is an open view of Victoria Harbour to the south west, typical industrial area with medium rise industrial buildings to the north and partially blocked views of Laguna City by elevated Kwun Tong By-pass to the north east. The area is proposed to be redeveloped and enclosed with landscaped deck.

Occupational

Existing/Planned (2021)

Construction Phase

Eastern Works Area. Additional marine traffic between the eastern and western sites will have an indirect impact onto this VSR. VSRs in this location will have partial south western views of approximately 160m min to the Eastern Works Area The sensitivity of this VSR is considered low.

Western Works Area: VSRs in this location will glimpse western views of approximately 1400m min to the Western Works Area. The views are blocked by the existing ferry piers and Kwun Tong Typhoon Shelter. Additional marine traffic between the eastern and western sites will have an indirect impact onto this VSR. As the views onto the waterfront area will be dominated by additional marine traffic for construction and demolition material, the sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

O20

General Description

Soccer Pitch, Car Park, Petrol Filling Station & Vacant Sites (Proposed Cha Kwo Ling Promenade Park)

This area comprises a soccer pitch, car park, petrol filling station & vacant sites. The area is planned to be redeveloped as part of the proposed Cha Kwo Ling Promenade Park.

Occupational/Recreational

Existing/ Planned (2021)

Construction Phase

Eastern Works Area: The VSR will have full south eastern views of approximately 5m min to the Eastern Works Area whilst the project is under construction. The sensitivity of this VSR is considered medium.

 

 

Western Works Area: N/A

 

 

O20

Operational Phase

Eastern Works Area: N/A

Occupational/Recreational

Existing/ Planned (2021)

Western Works Area: Refer to RE17: Cha Kwo Ling Park, N/A

O21

General Description

Proposed Cha Kwo Ling Promenade

The site is a decommissioned commercial cargo working area. The area is planned to be redeveloped as part of the proposed Cha Kwo Ling Promenade/Park.

Occupational/Recreational

Existing/ Planned (2021)

Construction Phase

Eastern Works Area: As this area is designated as a site works area within the construction phase, it is not designated as a VSR.

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

O22

General Description

Tin Hau Temple

This is a Tin Hau Temple with a vegetated hillside backdrop to the north.

Occupational

Existing

Construction Phase

Eastern Works Area: The view to the project site is partially screened by the roadside planting along the Cha Kwo Ling Road.

The VSR will have partial south western views of approximately 900m min to the Eastern Works Area. The sensitivity of this VSR is considered low.

Western Works Area: N/A

Operational

Eastern Works Area: N/A

Phase

Western Works Area: N/A

 

 

GIC1

General Description

EMSD Workshops, Sewage Pumping Station & Electricity Substation.

Existing government workshops are proposed to be redeveloped into a sewage pumping station and electricity substation by 2016. The buildings are low rise, with eastern views across Kowloon Bay and KTD: The Runway Precinct on to the Western Works Area. Currently the KTD site is undergoing various clearance, and infrastructure construction work with no major aesthetic appeal for the area.

Government /Institutional/

Community

Existing/Proposed

GIC1

Construction Phase

Eastern Works Area: N/A

Government /Institutional/

Community

Existing/Proposed

Western Works Area: Buildings are planned to be redeveloped by 2016. Depending on detail design of RE4 & RE5. VSRs in this location will have partial eastern views of approximately 1000m min, onto the Western Works Area. The value and quality of the existing view is fair and the sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on detail design of RE8, GIC7, GIC8 & GIC11C, VSRs in this location will glimpse eastern views of approximately 1200m min onto the Western Works Area The sensitivity of this VSR is considered low.

 

 

GIC2

General Description

Electricity Substation

Planned low rise building on open land adjacent to Kai Tak Tunnel and Kai Tak Nullah. Views into the site are screened due to existing and proposed CKR elevated roads, and proposed South Apron pedestrian bridge extensions.

Government /Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on detail design of GIC6, GIC7 & GIC11C. VSRs in this location will glimpse south eastern views of approximately 900m min, onto the Western Works Area. The sensitivity of this VSR is considered low.

GIC3

General Description

Tunnel Ventilation Shaft & Administration Building

Planned low rise to medium rise building, on open land adjacent to Kai Tak Tunnel and Kai Tak Nullah.

Government

/Institutional/

Community

Planned

(2016)

 

Construction

Eastern Works Area: N/A

 

 

Phase

Western Works Area: VSRs in this location will glimpse south eastern views of approximately 600m min, onto the Western Works Area. The sensitivity of this VSR is considered low.

 

 

GIC3

Operational Phase

Eastern Works Area: N/A

Government

/Institutional/

Community

Planned

(2016)

 

Western Works Area: Depending on detail design of GIC6, GIC7 & GIC11C, VSRs in this location will glimpse south eastern views of approximately 640m min, onto the onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered low.

GIC4

General Description

Tunnel Ventilation Shaft & Administration Building (Kai Tak Tunnel Entrance)

Existing low rise to medium rise buildings adjacent to the Kai Tak Nullah. Views into the site are screened by existing and proposed CKR elevated road, and proposed South Apron pedestrian bridge extensions.

Government

/Institutional/

Community

Existing

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will glimpse south eastern views of approximately 690m min, onto the Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on detail design of GIC6, GIC7 & GIC11C, VSRs in this location will glimpse south eastern views of approximately 800m min, onto the onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered low.

GIC5

General Description

DSD Desilting Compound

Planned low rise to medium rise building, on open land adjacent to Kai Tak Tunnel and Kai Tak Nullah. Views into the site are screened due to existing and proposed CKR elevated roads, and proposed South Apron pedestrian bridge extensions.

Government

/Institutional/

Community

Planned

(2016)

 

GIC5

Construction Phase

Eastern Works Area: N/A

Government

/Institutional/

Community

Planned

(2016)

 

Western Works Area: VSRs in this location will glimpse south eastern views of approximately 760m min, onto the Western Works Area. The sensitivity of this VSR is considered low.

GIC5

Operational Phase

Eastern Works Area: N/A

Government

/Institutional/

Community

Planned

(2016)

 

Western Works Area: Depending on detail design of GIC6, GIC7 & GIC11C, viewers within this VSR will have glimpse south eastern views of approximately 760m min, onto the onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered low.

GIC6

General Description

Northern Undesignated Government Site at former Kai Tak South Apron

Planned low rise to medium rise building. Depending on detail design of buildings.

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: Viewers within this VSR will have partial south eastern views of approximately 400m min, onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered medium.

GIC7

General Description

Southern  Undesignated Government Site at former Kai Tak South Apron

Planned low rise to medium rise building. Depending on detail design of buildings.

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have partial south eastern to eastern views of approximately 150m min, onto the Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered medium.

GIC8

General Description

Social Welfare Facilities

Planned low rise to medium rise building. Depending on detail design of building.

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

 

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have full south eastern to eastern views of approximately 140m min, onto the Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered medium.

GIC9

General Description

Animal Management Centre

Planned low rise building. Depending on detail design of buildings.

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have partial south eastern views of approximately 130m min, onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered low.

GIC10

General Description

Jordan Valley Box Culvert: DSD Desilting Building & Pumping Station

Existing low rise to medium rise building. Depending on detail design of building.

Government

/Institutional/

Community

Existing

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location will have full south eastern – eastern views of approximately 5m min onto the Western Tunnel Portal & Ventilation Buildings The sensitivity of this VSR is considered medium.

Operational Phase

As defined for the Construction Phase

Eastern Works Area: N/A

Western Works Area: medium

GIC11A

General Description

Hospital at Former Kai Tak South Apron

This planned VSR is proposed as one of three planned medium-rise hospital buildings.

Government

/Institutional/

Community

Planned

(2018)

 

Construction

Phase

Eastern Works Area: N/A

Western Works Area: The future users have an open view at varying levels of approximately 10m min. The Trunk Road T2 and associated work areas are located to the northwest and south east of the hospital site, with full views directly upon the construction of the T2 Ventilation, Tunnel Portal Building. As no existing buildings were previously within this part of the South Apron area, the sensitivity of this VSR is considered medium.

 

Operational Phase

Eastern Works Area: N/A

 

Western Works Area: The future users have a full northern view onto the project site at varying levels of approximately 10m min, but only those directly facing the project will be affected. However, they will have an alternative high amenity view to south of the future metro park. The sensitivity of this VSR is considered medium.

GIC11B

General Description

Electrical & Mechanical Services Department, Kowloon Bay Vehicle Servicing Station/ Proposed Hospital at former Kai Tak South Apron

At present the site is an Electrical & Mechanical Services Department, Kowloon Bay Vehicle Servicing Station. The current building is planned for demolition, as the future area is planned to house a medium-rise hospital building.

Government

/Institutional/

Community

 

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: Building is planned for demolition. Date of Demolition unknown. VSRs in this location will have full southern – north western views of 10m min from the Project in the construction phase. The sensitivity of this VSR is considered medium.

 

 

GIC11B

Operational Phase

Eastern Works Area: N/A

Government

/Institutional/

Community

 

Planned

(2021)

 

Western Works Area: The future users have a full view at varying levels of approximately 10m min onto the onto the Western Tunnel Portal & Ventilation Buildings, which are located to the northwest of the Hospital site, with full views directly upon the Ventilation, Tunnel Portal Buildings but only those directly facing the project will be affected. The sensitivity of this VSR is considered medium.

GIC11C

General Description

Derelict land and Proposed Hospital at former Kai Tak South Apron

Currently the site is being used as a waste holding area. The area has been designated as a T2 works area until 2019 as per the submitted CE38/2008 (HY) Land Requirement Plan. On release of the land, this visually sensitive receiver is proposed as one of three planned medium-rise hospital buildings, with direct northern and north-eastern views onto the project site.

Government

/Institutional/

Community

 

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: As this area is designated as a site works area within the Construction phase, it is not designated as a VSR.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The future users have a full view at varying levels of approximately 10m min onto the Western Tunnel Portal & Ventilation Buildings. Which are located to the northwest of the Hospital site, with full views directly upon the T2 Ventilation & Tunnel Portal Buildings but only those directly facing the project will be affected. However, they will have an alternative high amenity view to south of the future metro park. The sensitivity of this VSR is considered medium.

GIC12

General Description

Kwun Tong Public Transport Interchange and Kwun Tong Ferry Pier

The area is an existing transportation hub for buses, taxis and public ferries. The main transportation hub is set back from the water’s edge, and is partially blocked by existing mature trees and the elevated Kwun Tong By-pass. The ferry pier has open views onto Victoria Harbour and the surrounding area.

Government /Institutional/

Community

Existing

 

Construction Phase

Eastern Works Area: There are full views of approximately 450m min from the ferry pier onto the Eastern Works Area. The sensitivity of this VSR is considered low.

 

 

Western Works Area: Viewers within the Ferry Pier will glimpse views of approximately 1250m min to the Western Works Area due to obstruction by the existing breakwaters. The VRS’s will have full southern views views of approximately 80m min onto additional marine traffic for construction and demolition material within Victoria Harbour. The sensitivity of this VSR is considered low.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

R1

General Description

Comprehensive Development Area, Ma Tau Kok.

A planned medium to high rise building with eastern views across Kowloon Bay and KTD: The Runway Precinct on to the Western Works Area. The value and quality of the existing view is good.

Residential

Planned

(2021)

Construction

Eastern Works Area: N/A

Phase

Western Works Area: Refer to O1 for description.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: After the completion of Kai Tak Development, the view will be screened by the South Apron Development Government. The VSR would glimpse eastern views of approximately 1350m min, onto the Trunk Road T2 Western Ventilation Building, depending of detailed design and construction of RE5, RE8, GIC7, GIC8, & GIC11C. The sensitivity of this VSR is considered low.

R2

General Description

Kai Tak 2B: Comprehensive Development Area

A planned medium to high rise building, on a reclaimed site within the KTD: North Apron Area. The Area is currently undergoing various regeneration and construction projects. On completion South eastern facing users will be affected.

Residential

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of GIC6, GIC7, GIC9 & GIC10, VSRs in this location will have a glimpse southern view of approximately 1600m min towards the Trunk Road T2 Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

R3

General Description

S/K22/13 Commercial Development

Planned VSR on the western edge of the South Apron.

Residential

 

Planned

(2016)

Construction Phase

Eastern Works Area: The users within the upper floors will have partial south eastern views of approximately 1740m min onto the Eastern Works Area. The sensitivity of these VSR’s is considered medium.

Western Works Area: VSRs in this location will have partial north western – south eastern view of approximately 10m min to the Western Works Area. The sensitivity of this VSR is considered high.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of O11 & GIC11B, VSRs in this location will have a partial north western - northern view of approximately 500m min to the Western Tunnel Portal & Ventilation Buildings. As the completion of the buildings is proposed for completion in 2021. The sensitivity of this VSR is considered medium.

R4

General Description

S/K22/11 Comprehensive Development Area

Planned VSR on the western edge of the South Apron.

Residential

 

Planned

(2016)

Construction Phase

Eastern Works Area: The users within the upper floors will have partial south eastern views of approximately 1740m min onto the Eastern Works Area. The sensitivity of these VSR’s is considered medium.

 

 

Western Works Area: Future viewers in this VSR will have full western – eastern view of approximately 10m min to the Western Works Area. The sensitivity of this VSR is considered high.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Future viewers in this VSR will have a partial north western - northern view of approximately 500m min to the Western Tunnel Portal & Ventilation Buildings, depending on the detail design and construction of O11 & GIC11B. As the completion of the buildings is proposed for 2021, the sensitivity of this VSR is considered medium.

R5

General Description

Kai Tak Runway Precinct Housing Development

A row of medium rise residential developments are planned on the northern fringe of the KTD Runway Precinct.

Residential

 

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: depending on the detail design and construction of GIC11A which is planned to be completed by 2016, and R5, RE8, GIC11C and the D4 Road Bridge, which are planned for completion in 2021, the future VSRs will glimpse north and north-western views of approximately 400m min onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered medium.

R6

General Description

Laguna City

The existing view is an open view of Victoria Harbour to the south west, typical industrial area with medium rise industrial buildings to the north west and typical urban residential area to the north east. Only south and south west facing users are affected.

Residential

Existing

Construction Phase

Eastern Works Area: The residents at mid to upper level of this visual sensitive receiver have a full south eastern sea view to the Eastern Works Area of approximately 160m min. The sensitivity of this VSR is considered high.

 

 

Western Works Area: The residents at mid to upper levels of this residential development have an glimpse western to north western s sea view to the Western Works Area of approximately 1600m min. The sensitivity of this VSR is considered low.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

R7

General Description

Residential development at Cha Kwo Ling Road

The existing view is of the decommissioned open storage and cargo working area with a backdrop of Victoria Harbour to the west and vegetated hillsides to the east. Only west facing users are affected.

Residential

Existing

Construction Phase

Eastern Works Area: VSR’s will have a full view to the Eastern Works Area of approximately 50m min. Only east facing users are affected within the construction stage of the project. The sensitivity of this VSR is considered high.

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

R8

General Description

Cha Kwo Ling Tsuen

This visual sensitive receiver shares similar existing views with R3 but Victoria Harbour is highly blocked by the decommissioned cargo working area and roadside planting in front as the residential complex is close to the ground level.

Residential

Existing

Construction Phase

Eastern Works Area: The VSRs have a full view of approximately 20m min to the Eastern Works Area The sensitivity of this VSR is considered high.

Western Works Area: N/A

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: N/A

 

 

R9

General Description

Grand Waterfront, To Kwa Wan

Existing high rise building. The existing view is a panorama view across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD. The residents of this visual sensitive receiver have a full view to the Western Works area, but only those facing east to north east are affected. However, they have views south to south east of Victoria Harbour and the planned Metro Park.

Residential

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs will have a glimpse view of approximately 1150m min to the Western Works Area, depending on the detailed design of RE4 & RE5. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of RE4, RE5, RE8, GIC7, GIC8 & GIC11C, the VSRs would have a glimpse eastern view of approximately 1400m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

R10

General Description

Wyler Gardens, To Kwa Wan

Existing medium to high rise building. The existing view is a panorama view across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

Residential

Existing

Construction

Eastern Works Area: N/A

 

 

Phase

Western Works Area: VSRs in this location will have a glimpse view of approximately 1250m min to the Western Works Area, depending on detailed design of RE4 & RE5. The sensitivity of this VSR is considered low.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of RE4, RE5, RE8, GIC7, GIC8 & GIC11, the VSRs would glimpse eastern views of approximately 1500m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

R11

General Description

Sky Tower, Kowloon City

This is one of the tallest residential building blocks in Ma Tau Kok and residents in mid and upper levels currently enjoy a high quality panoramic view of the surroundings. The existing view is a panorama view across To Kwa Wan, Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

These VSRs are medium to high rise buildings and residents in the mid to upper levels will have a direct view to the Project Site.

Residential

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: VSRs in this location have a glimpse eastern to south eastern view of approximately 1550m min to the Western Works Area, depending of detailed design of RE4 & RE5. The sensitivity of this VSR is considered low.

 

 

R11

Operational Phase

Eastern Works Area: N/A

Residential

Existing

Western Works Area: Depending on the detail design of RE4, RE5, RE8, GIC7 & GIC11C, the VSR would glimpse eastern to south eastern views of approximately 1900m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

 

 

R12

General Description

Sunrise Villas, To Kwa Wan

Existing medium to high rise building. The existing view is a panorama view across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

These VSRs are medium to high rise buildings and residents in the mid to upper levels will have a direct view to the Project Site.

Residential

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: VSRs in this location have an eastern glimpse view of approximately 1600m min to the Western Works Area, depending on detailed design of RE4 & RE5. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of RE5, RE8, GIC7, GIC8 & GIC11C VSRs would glimpse eastern views of approximately 2000m min onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

 

 

R13

General Description

Laguna Verde Complex, Hung Hom

Existing medium to high rise building. The existing view is a panorama view across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

Residential

Existing

Construction Phase

Eastern Works Area: There are glimpse views of approximately 3800m min onto the Eastern Works Area, though these views will be obstructed by operation of the Kai Tak Cruise Terminal. Although additional marine traffic between the Eastern and Western sites will have an indirect impact onto this VSR. As the view onto the waterfront is currently dominated by the cruise terminal and associated marine traffic, the sensitivity of this VSR is considered low.

Western Works Area: VSRs in this location have glimpse eastern views of approximately 1620m min to the Western Works Area, depending on the detail design and construction of RE5 and GIC11A. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: depending on the detail design and construction of O9, R5, RE6, RE8 & GIC11C, which are planned for completion in 2021, this VSR, would have a glimpse eastern view of approximately 1840m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

R14

General Description

Harbourfront Landmark & Harbour Grand, Kowloon,  Hung Hom

These buildings are the furthest away from the Project. The developments house a high number of residents. This existing VSR’s view is a panorama across Victoria Harbour, Kowloon Bay and over the Kai Tak development and a direct view of the Kai Tak Cruise Terminal.

Residential

Existing

Construction Phase

Eastern Works Area:

The VSR’s will have a glimpse eastern view of approximately 3200m min view via the Kai Tak Cruise Terminal onto the Eastern Works Area. Though additional marine traffic between the Eastern and Western sites will have an indirect impact onto this VSR. As the view is currently dominated by the cruise terminal and associated marine traffic, the sensitivity of this VSR is considered low.

Western Works Area: Depending on the detail design of RE5, & GIC11A the VSR would glimpse a north eastern view of approximately 2110m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: Depending on the detail design of O9, R5, RE6, RE8, GIC7 & GIC11C the VSR would glimpse north eastern views of approximately 2000m min onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

 

 

R15

General Description

Kai Tak 2B Housing Development

A planned medium to high rise building, on a reclaimed site within the KTD: North Apron Area. The Area is currently undergoing various regeneration and construction projects. On completion South eastern facing users will be affected.

Residential

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

R15

Operational Phase

Eastern Works Area: N/A

Residential

Planned

(2021)

Western Works Area: Depending on the detail design of GIC6, GIC7, GIC9 & GIC10, future viewers in this VSR will have a glimpse southern view of approximately 1550mm min towards the Trunk Road T2 Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

R16

General Description

Kai Tak 1L & 1K Housing Development

Planned medium to high rise building. South eastern facing users will be affected.

Residential

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of GIC6, GIC9 & GIC10, VSRs in this location will have a partial southern view of approximately 1060m min towards the Trunk Road T2 Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

R17

General Description

Kai Tak 1H & 1I Housing Development

Planned medium to high rise building. South eastern facing users will be affected. Views of Western Works Area are obscured by the Kowloon Bay commercial area.

Residential

Planned

(2016)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The Development is planned to be operational by 2016. VSRs in this location will have a partial south eastern view of approximately 1050m min towards the Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of GIC6, GIC9 & GIC10, VSRs in this location will glimpse south eastern views of approximately 1100m min towards the Trunk Road T2 Western Tunnel Portal & Ventilation Building. The sensitivity of this VSR is considered low.

R18

General Description

Hing Yan Street Residential Block

Existing medium rise building. South eastern facing VSRs will be affected. Views of the Western Works Area are obscured by the Kowloon Bay commercial area.

Residential

Existing

 

 

Construction

Eastern Works Area: N/A

 

 

Phase

Western Works Area: VSRs in this location will have an east to north east glimpse view of approximately 1200m min to the Western Works Area, depending of detailed design of RE5. The sensitivity of this VSR is considered low.

 

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Refer to R1 For details

R19

General Description

Yau Tong Bay Development

Planned medium to high rise building mixed use waterfront development.

Residential/

Occupational

Planned

(2018)

Construction Phase

Eastern Works Area: VSRs in this location will have a partial view of approximately 300m min to the Eastern Works area The sensitivity of this VSR is considered high.

Western Works Area: N/A

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: N/A

 

 

E1

General Description

Ma Tau Kok: Regional Open Space

At present, proposed development is being used as a Wilson Car park. The existing view is a panorama at pedestrian level across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

Recreational

Planned

(2014)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of RE4 & RE5, Pedestrians at ground level within this VSR will glimpse eastern to north eastern views of approximately 1800m min, onto the Western Works Area The sensitivity of this VSR is considered low.

 

 

E1

Operational Phase

Eastern Works Area: N/A

Recreational

Planned

(2014)

Western Works Area: Depending on the detail design of RE8, & GIC11C, pedestrians at ground level within this VSR will glimpse eastern to north eastern views of approximately 1650m min onto the Western Works Area. The sensitivity of this VSR is considered low.

RE2

General Description

Hoi Sham Park, Ma Tau Kok

Existing public waterfront park.  At pedestrian level there are good panoramic views across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

Recreational

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of RE4 & RE5, pedestrians at ground level within this VSR will glimpse eastern to north eastern views of approximately 1500m min, onto the Western Works Area The sensitivity of this VSR is considered low.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of RE8 & GIC11C Pedestrians at ground level within this VSR will have a glimpse eastern to north eastern view of approximately 1600m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

RE3

General Description

Current & Future Waterfront Promenade, Ma Tau Kok

Existing waterfront park with good open south eastern to north western views onto Victoria Harbour and KTD. Promenade will later be extended and connected to the Kia Tak Development.

Recreational

Existing/ Planned

(2021)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: Depending on the detail design of RE4 & RE5, Pedestrians at ground level within this VSR will glimpse south eastern to north western views of approximately 1200m min onto the Western Works Area. The sensitivity of this VSR is considered low.

 

 

RE3

Operational Phase

Eastern Works Area: N/A

Recreational

Existing/ Planned

(2021)

Western Works Area: Depending on the detail design of RE8, GIC7, GIC8 & GIC11C Pedestrians at ground level within this VSR will glimpse south eastern to north western views of approximately 1300m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

RE4

General Description

Planned Multi-Purpose Stadium Complex –

Park

Viewers in this future VSRs will mainly be focused inside the stadium complex and their views to the proposed Trunk Road T2 Site could be potentially screened by landscaping or other structures.

Recreational

Planned

(2016-2020)

Construction Phase

Eastern Works Area: N/A

Western Works Area: Pedestrians at ground level within this VSR will have partial south eastern views of approximately 1000m min onto the Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of RE8, GIC7, GIC8 & GIC11C. Pedestrian VSRs will glimpse eastern to south eastern views of approximately 1000m min onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered low.

RE5

General Description

Kai Tak Runway Precinct: Metro Park

Proposed waterfront public park. This visual sensitive receiver has north eastern and eastern views into the site via the L18 Road.   As per the RODP the date of completion is under review.

Recreational

Planned

(2017)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: Pedestrians at ground level within this VSR will have partial eastern to south eastern views of approximately 300m min to the Western Works Area. The sensitivity of this VSR is considered medium.

 

 

RE5

Operational Phase

Eastern Works Area: N/A

Recreational

Planned

(2017)

Western Works Area: Depending on the detail design of RE8, GIC7, GIC8 & GIC11C Pedestrians at ground level within this VSR will have a glimpse of eastern to south eastern views of approximately 400m min, onto the Trunk Road T2 Western Ventilation Building. The sensitivity of this VSR is considered medium.

RE6

General Description

Kai Tak Runway Precinct Northern Promenade

Proposed waterfront public promenade.

Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational

Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of RE8, GIC7, GIC8 & GIC11C and the D4 road bridge, pedestrian VSRs at ground level will have partial south eastern, north and north-western views of approximately 330m min onto the Western Tunnel Portal Building. The sensitivity of this VSR is considered medium.

RE7

General Description

Kai Tak Runway Park

Proposed waterfront public park.   The park is built in 2 phases:

1st phase, planned 2013

2nd phase is under review.  Details unknown.

Recreational

Planned

(2013)

Construction Phase

Eastern Works Area: Pedestrians VSRs at ground level will have full south eastern views of approximately 700m min.  Additional marine traffic for construction and demolition material will have an indirect impact onto this VSR. The sensitivity of this VSR is considered medium.

Western Works Area: Pedestrian VSRs will have a full northern view of approximately 350m min to the Trunk Road T2 Works Area. The sensitivity of this VSR is considered medium.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

RE8

General Description

Kai Tak South Apron: Southern Promenade

Proposed waterfront public promenade.

Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

 

Western Works Area: N/A

 

Operational Phase

Eastern Works Area: N/A

 

Western Works Area: Depending on the detail design of RE8, GIC7, GIC11A & GIC11C and the D4 road bridge, pedestrian VSRs will have partial north and north eastern views of approximately 100m min onto the Western Ventilation Building and the Tunnel Portal Building. The sensitivity of this VSR is considered medium.

 

RE9

General Description

Kai Tak South Apron: Kowloon Bay Square

Planned Public Waterfront Park with proposed MTR/Light Rail Station (station details to be finalised).  As per the RODP of KTD, the planned park is currently under review, details unknown.

Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of O11, O12, GIC11A & GIC11C, future VSRs will have partial northern and north western of approximately 450m min to the Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered medium.

RE10

General Description

Kai Tak South Apron: Amenity Area

Undesignated Amenity Area, adjacent to the Western Tunnel Portal & Ventilation Buildings.

Recreational

Planned

(2021)

Construction

Eastern Works Area: N/A

 

 

Phase

Western Works Area: Area is designated to be within site boundary area - N/A.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Pedestrian VSRs would have full north western views of approximately 5m min, onto the Trunk Road T2 Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered medium.

RE11

General Description

Enterprise Square: CIC Zero Carbon Building

Existing Public Park. This VSR has slight south western views towards the project site. Views are screened mostly by the elevated Kwun Tong By-pass, Kai Fuk Road and roadside amenity planting.

Recreational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of GIC10, pedestrian VSRs would glimpse southern views of approximately 150m min onto the Trunk Road T2 Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Depending on the detail design of GIC10, pedestrian VSRs would glimpse southern views of approximately 150m min onto the Trunk Road T2 Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered low.

RE12

General Description

Hoi Bun Road Park

Existing Public Park. Views of the Project to this VSR will be partially blocked by the elevated Kwun Tong By-pass and existing trees inside the park.

Recreational

Existing

Construction Phase

 

Eastern Works Area: There are no views onto the Eastern Works Area, though VSRs may glimpse views of approximately 300m min to additional marine traffic for construction and demolition material between the eastern and western sites. This may have an indirect impact. The sensitivity of this VSR is considered low.

Western Works Area: The view to the Project is partially blocked by the elevated Kwun Tong By-pass. Only south west facing VSRs are affected. VSRs will glimpse south western to north western views of approximately 350m min to the Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

RE13

General Description

Kwun Tong Promenade (Existing )

Existing Public Waterfront Promenade Park with north western views onto the project site.

Recreational

Existing

Construction Phase

Eastern Works Area: There are no views onto the Eastern Works Area, though VSRs will have full views of approximately 200m to additional marine traffic for construction and demolition material between the eastern and western sites. This will have an indirect impact. The sensitivity of this VSR is considered low.

Western Works Area: Pedestrian VSRs would have full north western to western views of approximately 750m min onto the Western Works Area. VSRs will have full views of approximately 200m to additional marine traffic for construction and demolition material between the eastern and western sites. This will have an indirect impact. The sensitivity of this VSR is considered medium.

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: N/A

 

 

RE14

General Description

Kwun Tong Promenade (Planned)

This is a linear strip of decommissioned land on the Kwun Tong Waterfront awaiting redevelopment. This area will shortly become a construction site for the new promenade, hence VSRs are considered to be occupational but will become recreational in 2021.

Occupational/Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: There are no views onto the Eastern Works Area, VSRs will have full views of approximately 200m min to additional marine traffic for construction and demolition material between the eastern and western site. This is considered an indirect impact. The sensitivity of this VSR is considered low.

Western Works Area: Viewers within this VSR will have full south western to north western views of approximately 200m min to the Western Works Area. The sensitivity of this VSR is considered low.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A.

RE15

General Description

Laguna Park

Existing Public Park. Views of the Project in this location are partially blocked by the elevated Kwun Tong By-pass, Kwun Tong Nullah and existing trees inside the park.

Recreational

Existing

Construction Phase

Eastern Works Area: Pedestrian VSRs would glimpse south eastern views of approximately 300m min onto the Eastern Works Area. The sensitivity of this VSR is considered low.

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A.

T1

General Description

Kwun Tong By-pass and Kai Fuk Road

These are elevated and at-grade roads. The existing views are of the former Kai Tak South Apron, Kwun Tong Typhoon Shelter, Victoria Harbour to the west and typical industrial area to the east. VSRs travelling on these roads will have direct sea views to the Project which in part are blocked by roadside trees, shrub planting and noise barriers.

Travelling

Existing

 

Construction Phase

Eastern Works Area: VSRs travelling on these roads will have a glimpse south eastern and eastern view of the Eastern Works Area. The sensitivity of this VSR is considered medium.

 

 

Western Works Area: VSRs travelling on these roads will have a full open view of approximately 5m min to the Western Works Area. The sensitivity of this VSR is considered medium.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The travellers of this visual sensitive receiver have a full view of approximately 5m onto the Trunk Road T2 Western Tunnel Portal & Ventilation Buildings. The sensitivity of this VSR is considered medium.

T2

General Description

Cha Kwo Ling Road

This is a road with existing views of the former open storage and cargo working area to the west and low rise residential buildings with a vegetated hillside backdrop to the east.

Travelling

Existing

 

Construction Phase

Eastern Works Area: VSRs on this road will have full views of the Project which in parts will be blocked by roadside planting, fences, walls, and the former cargo working area. The sensitivity of this VSR is considered medium.

 

 

Western Works Area: N/A

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

T3

General Description

Harbour Traffic at Victoria Harbour

VSRs in harbour traffic include cruise liners, ferries and commercial boats, and will have open sea views of the Project. The existing view is of a water body with development as a back drop.

Travelling

Existing

 

Construction Phase

Eastern Works Area: VSRs will have full open views to the Eastern Works Area. The sensitivity of this VSR is considered medium.

Western Works Area: VSRs will have full open views of approximately 5m min to the Western Works Area. The sensitivity of this VSR is considered medium.

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: VSRs will have glimpse views of approximately 100m onto the Project due to the proposed O11, O12, GIC11A GIC11C, R3, R4, RE8 & RE9 developments. The sensitivity of this VSR is considered medium.

 

 

 

Table 9.5        Assessments of the Degree of Sensitivity: Construction Phase (Eastern Works Area)

VSR

ID. No.

 

Number of VSRs

(Many/

Medium/

Few)

Quality of Existing View

(Good/

Fair/ Poor)

Availability and Amenity Value of Alternative View

(High/

Medium/

Low)

Minimum Distance between VSRs and Impact Sources (m)

Duration or Frequency of View

(Long/

Medium/

Short)

Degree of Visibility

(Full/

Partial/

Glimpse/(M))*

Sensitivity (Low, Medium, High)

O10

Many

Fair

Medium

1100

Medium

Partial

Low

O14

Medium

Fair

Medium

1800

Medium

Glimpse

Low

O16

Medium

Fair

Medium

1800

Medium

Glimpse

Low

O17

Medium

Fair

Medium

200

Medium

Partial (M)

Low

O18

Many

Fair

Medium

360

Medium

Glimpse

Low

O19

Few

Fair

Medium

160

Medium

Partial

Low

O20

Medium

Fair

Medium

5

Medium

Full

Medium

O22

Few

Fair

Low

900

Medium

Partial

Low

GIC12

Medium

Fair

Medium

450

Medium

Full (M)

Low

R3

Many

Fair

Medium

1740

Long

Partial

Medium

R4

Many

Fair

Medium

1740

Long

Partial

Medium

R6

Many

Fair

Medium

160

Long

Full

 High

R7

Many

Fair

Medium

50

Long

Full

High

R8

Many

Fair

Medium

20

Long

Full

High

R13

Many

Fair

High

3800

Long

Glimpse

Low

R14

Many

Fair

High

3200

Long

Glimpse

Low

R19

Many

Fair

Medium

300

Long

Partial

High

RE7

Medium

Fair

High

700

Medium

Full

Medium

RE12

Medium

Poor

Medium

300

Medium

Glimpse (M)

Low

RE13

Medium

Poor

High

200

Medium

Full

(M)

Low

RE14

Medium

Poor

High

200

Medium

Full (M)

Low

RE15

Medium

Fair

Medium

300

Medium

Glimpse

Low

T1

Many

Fair

Medium

5

Short

Glimpse

Medium

T2

Many

Fair

Medium

5

Short

Full

Medium

T3

Many

Fair

Medium

5

Short

Full

Medium

Note: *Degree of Visibility (M) denotes:- No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials

Table 9.6        Assessments of the Degree of Sensitivity: Construction Phase (Western Works      Area)

VSR

ID. No.

Number of VSRs

(Many/

Medium/

Few)

Quality of Existing View

(Good/

Fair/ Poor)

Availability and Amenity Value of Alternative View

(High/

Medium/

Low)

Minimum Distance between VSRs and Impact Sources (m)

Duration or Frequency of View

(Long/

Medium/

Short)

Degree of Visibility

(Full/

Partial/

Glimpse/(M))*

Sensitivity (Low, Medium, High)

O1

Medium

Fair

High

1150

Medium

Glimpse

Low

O2

Medium

Fair

High

1350

Medium

Glimpse

Low

O3

Medium

Fair

Medium

700

Medium

Partial

Low

O4

Medium

Fair

Medium

400

Medium

Partial

Medium

O5

Many

Fair

Medium

200

Medium

Partial

Medium

O6

Medium

Fair

Medium

120

Medium

Full

Medium

O7

Many

Fair

Medium

70

Medium

Full

Medium

O8

Few

Fair

Low

80

Medium

Glimpse

Low

O10

Many

Fair

High

500

Medium

Partial

Medium

O12

Few

Fair

Low

5

Medium

Full

Low

O13

Medium

Fair

Medium

200

Medium

Partial

Low

O14

Medium

Fair

Medium

20

Medium

Full

Medium

O16

Medium

Fair

Medium

300

Medium

Partial

Medium

O17

Many

Fair

Medium

320

Medium

Partial

Low

O18

Many

Fair

Medium

750

Medium

Partial

Low

O19

Few

Fair

Medium

1400

Medium

Glimpse

Low

GIC1

Few

Fair

High

1000

Medium

Partial

Low

GIC3

Few

Poor

Medium

600

Medium

Glimpse

Low

GIC4

Few

Poor

Medium

690

Medium

Glimpse

Low

GIC5

Few

Poor

Medium

760

Medium

Glimpse

Low

GIC10

Few

Fair

Low

5

Medium

Full

Medium

GIC11A

Medium

Fair

Low

10

Medium

Full

Medium

GIC11B

Few

Fair

Low

10

Medium

Full

Medium

GIC12

Medium

Fair

Medium

1250

Medium

Glimpse

Low

R3

Medium

Fair

Medium

10

Long

Partial

High

R4

Medium

Fair

Medium

10

Long

Full

High

R6

Medium

Fair

Medium

1600

Long

Glimpse

Low

R9

Medium

Fair

High

1150

Long

Glimpse

Low

R10

Medium

Fair

High

1250

Long

Glimpse

Low

R11

Medium

Fair

Medium

1550

Long

Glimpse

Low

R12

Medium

Fair

High

1600

Long

Glimpse

Low

R13

Many

Fair

High

1620

Long

Glimpse

Low

R14

Many

Fair

High

2110

Long

Glimpse

Low

R17

Many

Fair

Medium

1050

Long

Partial

Low

R18

Medium

Fair

Medium

1200

Long

Glimpse

Low

RE1

Medium

Fair

High

1800

Medium

Glimpse

Low

RE2

Medium

Fair

High

1500

Medium

Glimpse

Low

RE3

Medium

Fair

High

1200

Medium

Glimpse

Low

RE4

Medium

Fair

High

1000

Medium

Partial

Low

RE5

Medium

Fair

High

300

Medium

Partial

Medium

RE7

Medium

Fair

High

350

Medium

Full

Medium

RE11

Medium

Fair

Low

150

Medium

Glimpse

Low

RE12

Medium

Fair

Medium

350

Medium

Glimpse (M)

Low

RE13

Medium

Fair

High

750

Medium

Full

Medium

RE14

Medium

Fair

Medium

200

Medium

Full

Low

T1

Many

Fair

Medium

5

Short

Full

Medium

T3

Many

Fair

Medium

5

Short

Full

Medium

Note: *Degree of Visibility (M) denotes:- No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials

Table 9.7        Assessments of the Degree of Sensitivity: Operation Phase (Western Works Area) 

VSR

ID. No.

Number of VSRs

(Many/

Medium/

Few)

Quality of Existing View

(Good/

Fair/ Poor)

Availability and Amenity Value of Alternative View

(High/

Medium/

Low)

Minimum Distance between VSRs and Impact Sources (m)

Duration or Frequency of View

(Long/

Medium/

Short)

Degree of Visibility

(Full/

Partial/

Glimpse/M=V)

Sensitivity(Low, Medium, High)

O2

Many

Fair

Medium

1450

Medium

Glimpse

Low

O3

Medium

Fair

Medium

650

Medium

Partial

Low

O4

Medium

Fair

High

500

Medium

Partial

Low

O5

Medium

Fair

High

250

Medium

Partial

Low

O6

Medium

Fair

High

140

Medium

Partial

Medium

O7

Many

Fair

High

70

Medium

Partial

Medium

O8

Few

Fair

Low

80

Medium

Glimpse

Low

O9

Medium

Fair

High

500

Medium

Glimpse

Low

O10

Many

Fair

High

1200

Medium

Glimpse

Medium

O11

Medium

Fair

Medium

320

Medium

Partial

Medium

O12

Few

Fair

Medium

350

Medium

Partial

Low

O13

Medium

Fair

High

380

Medium

Partial

Medium

O14

Medium

Fair

High

320

Medium

Partial

Medium

O16

Medium

Fair

Medium

650

Medium

Glimpse

Low

O17

Medium

Fair

Medium

650

Medium

Glimpse

Low

GIC1

Few

Fair

Medium

1200

Medium

Glimpse

Low

GIC2

Few

Fair

Medium

900

Medium

Glimpse

Low

GIC3

Few

Fair

Medium

640

Medium

Glimpse

Low

GIC4

Few

Fair

Medium

800

Medium

Glimpse

Low

GIC5

Few

Fair

Medium

760

Medium

Glimpse

Low

GIC6

Medium

Fair

Medium

400

Medium

Partial

Medium

GIC7

Medium

Fair

Medium

150

Medium

Partial

Medium

GIC8

Medium

Fair

Medium

140

Medium

Full

Medium

GIC9

Few

Fair

Medium

130

Medium

Partial

Low

GIC10

Few

Good

Medium

5

Medium

Full

Medium

GIC11A

Medium

Good

Medium

10

Medium

Full

Medium

GIC11B

Medium

Good

Medium

10

Medium

Full

Medium

GIC11C

Medium

Good

Medium

10

Medium

Full

Medium

R1

Medium

Good

High

1350

Long

Glimpse

Low

R2

Medium

Fair

Medium

1600

Long

Glimpse

Low

R3

Medium

Fair

High

500

Long

Partial

Medium

R4

Medium

Fair

High

500

Long

Partial

Medium

R5

Many

Fair

Medium

400

Long

Glimpse

Medium

R9

Medium

Fair

High

1400

Long

Glimpse

Low

R10

Medium

Fair

High

1500

Long

Glimpse

Low

R11

Medium

Fair

Medium

1900

Long

Glimpse

Low

R12

Medium

Fair

Medium

2000

Long

Glimpse

Low

R13

Many

Fair

High

1840

Long

Glimpse

Low

R14

Many

Fair

High

2000

Long

Glimpse

Low

R15

Many

Fair

Medium

1550

Long

Glimpse

Low

R16

Many

Fair

Medium

1060

Long

Partial

Low

R17

Many

Fair

Medium

1100

Long

Glimpse

Low

RE1

Medium

Fair

High

1650

Medium

Glimpse

Low

RE2

Medium

Fair

High

1600

Medium

Glimpse

Low

RE3

Medium

Fair

High

1300

Medium

Glimpse

Low

RE4

Medium

Fair

High

1000

Medium

Glimpse

Low

RE5

Medium

Fair

High

400

Medium

 Glimpse

Medium

RE6

Medium

Fair

High

330

Medium

Partial

Medium

RE8

Medium

Fair

High

100

Medium

Partial

Medium

RE9

Medium

Fair

High

450

Medium

Partial

Medium

RE10

Medium

Fair

Medium

5

Medium

Full

Medium

RE11

Medium

Fair

Low

150

Medium

Glimpse

Low

T1

Many

Fair

Medium

5

Short

Full

Medium

T3

Many

Fair

Medium

100

Short

Glimpse

Medium

 

9.7                       Landscape Impact Assessment

9.7.1                   Potential Sources of Impacts

 

9.7.1.1              The nature and scope of works are described in detail in Section 3. Sources of impacts of Trunk Road T2 during the construction phase would include:

9.7.2                   Construction Works (Direct Impacts)

·             Construction of a dual two-lane trunk road approximately 0.3km long at grade section and about 2.7 km in the form of a tunnel and Tunnel Portal building;

·             Construction of Ventilation building, administration buildings and a traffic control and surveillance system; and

·             Construction of associated civil, electrical, mechanical, landscape and environmental protection and mitigation works.

9.7.3                   Construction Site Operation (Indirect Impacts)

·             Stockpiling of excavated and building materials and storage of construction equipment;

·             Minor demolition of existing facilities;

·             Temporary noise mitigation measures (e.g. barriers and enclosures);

·             Contractor’s temporary works areas, including site offices temporary barging point, haulage between T2 sites, and parking areas.

9.7.4                   Sources of Impacts in the Operation Phase

·             Dual two-lane trunk road of approximately 0.3km long at grade and 2.7km in the form of a tunnel;

·             The completed ventilation and administration buildings; and

·             The completed associated civil, electrical, mechanical, landscape and environmental protection and mitigation works.

9.7.5                   Impact on Existing Trees

 

9.7.5.1              Within the 100m works boundary area, there are an approximately 605 trees.

9.7.5.2              128 trees are recorded within Trunk Road T2 area and 10m offset buffer zone from the works limit. No registered Old and Valuable Tree, protected or endangered species are recorded. 30 trees will be protected from the impact of the proposed T2 development, 31 trees are recommended for transplantation, and 67 trees unsuitable for transplanting are recommended for felling. In total 152 new trees of minimum 75mm DBH are proposed to compensate the loss of trees in T2 area. Refer to Figures 9.10.1 and 9.10.2.

9.7.5.3              Compensatory tree planting will be incorporated along all roadside amenity areas affected by the construction works. The required numbers and locations of compensatory trees shall be determined and agreed with the Government during the Tree Removal Application under ETWB TCW No. 3/2006.

Table 9.8         Summary of Proposed Treatment of Trees (Trunk Road T2 Works Area)

Proposed Treatment

Quantity

Total tree quantity

128

Retain

30

Transplant

31

Fell

67

Accumulated loss of DBH (m)

114.00

 

9.7.5.4              Table 9.8 summarise the number of trees affected by the whole Trunk road T2 works and Table 9.9 summaries the affected trees with respect to the Western and Eastern Works Areas.

Table 9.9         Summary of Proposed Treatment of Trees (Individual Works Areas)

Proposed Treatment

Western Works Area

Eastern Works Area

Total

Total tree quantity

127

1

128

Retain  

30

0

30

Transplant

31

0

31

Fell

66

1

67

Accumulated loss of DBH(m)

113.865

0.135

114

 

9.7.6                   Impact on Existing Passive Amenity Areas

9.7.6.1              The only area affected by construction of the Trunk Road T2 and associated buildings is the amenity area next to Kwun Tong By-pass.

9.7.7                   Degree of Compatibility of the Project and Associated Works

9.7.7.1              The Trunk Road T2, ventilation and tunnel portal buildings are scheduled to be commissioned in 2020 and operational by 2021 within the Kai Tak South Apron Development. Currently the land is mainly derelict with areas allocated for temporary storage and on-going infrastructure projects. The proposed construction within the Kai Tak Development covers 3 main areas: The North Apron, South Apron and Runway Precinct. As per the KTD RODP, Trunk Road T2 will be operational at approximately the same time as the surrounding South Apron. The KTD agency has provided a landscape masterplan document for future Kai Tak Development to adhere to. As the area is intended to have a cohesive design approach, Trunk Road T2 and associated works will be designed in harmony with the surrounding context.

9.7.7.2              With the completion of Trunk Road T2 and associated works, the area of T2 will be reinstated into a Kai Tak South: Amenity Area, with provision of street trees, shrubs and ground cover planting. A green design approach is provided for the ventilation building, tunnel portal and refuge collection buildings, including green walls and stepped planted berms, which will minimise the visual impact and blend the development into the design of the proposed surrounding landscape.

9.7.7.3              Tables 9.10 and 9.11 present the impacts on landscape resources and character areas respectively. Magnitude of change is considered to be small to negligible at the operation phase.

9.7.8                   Nature and Magnitude of Unmitigated Landscape Impacts in Construction and Operation Phases

9.7.8.1              The magnitude of impacts, before mitigation measures, on LRs and LCA’s  in the construction and operation phases are described below and tabulated in Tables 9.10 to 9.11.


Table 9.10      Impacts on Landscape Resources of the Proposed Works and their Magnitude of Change

LR

ID No.

Landscape Resources

Size of LR (m2)

Description of Impacts

Sources of impact

Reversibility

Scale of Development

Compatibility with Surrounding Landscape

Duration of impact (Low, Medium, High)

Magnitude of Change (Negligible, Small, Intermediate, Large)

Construction

Operation

Construction

Operation

LR6

Amenity Area (Kai Fuk Road / Kwun Tong By-pass)

11,010

Within the portion of LR6 where impact is expected, of the 81 nos. trees, 18 trees will be retained and protected, 21 trees will be transplanted and 42 trees will be felled. Approximately 3,620 square metres of planting area would be lost by construction of building and temporary works and associated impacts.

 

Approximately 1,250 square metres of planting area will be permanently lost by the construction of the Ventilation Building.

Construction of ventilation building, Temporary storage and stockpiling area.

 

No

 

Large

 

Low

 

Medium

 

High

 

Large

 

Large

 

LR8

Derelict / Disturbed Land (KTD South Apron)

208,440

The T2 Western Works Area is currently an area of approximately 75,300 square metres of hard standing which will be temporarily lost in the   construction phase.

 

8,500 square metres of hard standing will be lost by the construction of the Tunnel Portal & Ventilation Buildings.

 

Approximately 46 nos. trees are recorded. 10 nos. of trees will be transplanted and 24 nos. trees unsuitable for transplanting are recommended to be felled. The remaining 12 nos. trees will be protected on site. In addition, two planting areas containing 159 square meters will be lost.

 

Impacts due  to the construction of cut and cover tunnel, underwater tunnel, minor demolition works of existing facilities, temporary traffic arrangement, temporary Storage and stock piling, temporary barging point and associated impacts.

Temporary Storage area and site office, work site for proposed temporary traffic arrangement, temporary storage and stock piling area, temporary barging point.

 

Construction of Ventilation Building, Tunnel Portal Buildings, construction of depressed road, construction of cut and cover tunnel, construction of underwater tunnel, minor demolition works of existing facilities.

No

 

Large

 

Medium

 

Medium

 

High

 

 

Large

 

 

Large

 

 

LR12

Water Body (Kwun Tong Typhoon Shelter)

315,320

Barges operating between 07.00 and 19.00.

Impacts due to the construction of underwater tunnel and, temporary barging point.

The temporary barging point has a vertical seawall face and no temporary facilities would be needed to be constructed above the sea.  It will be consist of a one vehicle unloading ramp and a fully enclosed conveyor belt unloading chute from LR8

Yes

Large

Low

Medium

 

N/A

Small

Negligible

LR16

Derelict / Disturbed Land Proposed as Cha Kwo Ling Promenade Park by Others (Cha Kwo Ling Former Public Cargo Working Area)

27,020

1 tree to be felled.

Impacts due to the additional construction works traffic in area and views onto Trunk Road T2 Western Works Area.

 

An approximate area of 21,500 square metres of hard standing will be temporary lost for the Eastern Works Area site offices.

Temporary Storage area and site office, Temporary vehicular haulage from Trunk Road T2 Eastern Works Area to T2 Western Works Area.

 

Yes

 

Large

 

High

 

Medium

 

N/A

 

 

Intermediate

 

Negligible

 

 

Notes:      The duration of impacts will be from 2016 to 2020 for both Construction Stages of the Eastern and Western areas. 

                  Only Landscape Resources that are impacted are discussed.

 

Table 9.11      Impacts on Landscape Character Areas of the Proposed Works and their Magnitude of Change

LCA

ID No.

Landscape Resources within the LCA

Size of LR (m2)

Description of Impacts

Sources of Impact

Reversibility

Scale of development

Compatibility with Surrounding Landscape

Duration of impact

Magnitude of Change (Negligible, Small, Intermediate, Large)

Construction

Operation

Construction

Operation

LCA1

LR8, LR10 & LR11

210,410

The Western Works Area site boundary is approximately 75,300 square metres of hard standing. This area will be temporarily lost throughout the construction phase.

 

8,500 square metres of hard will be lost by the construction of the Tunnel Portal & Ventilation Buildings.

 

Within LR8 and LR11, approximately 71 nos. trees are recorded.

 

Within the portion of LR8 where impact is expected, approximately 46 nos. trees are recorded. 10 nos. of trees will be transplanted and 24 nos. trees unsuitable for transplanting are recommended to be felled. The remaining 12 nos. trees will be protected on site. In addition, two planting areas containing 159 square meters will be lost.

 

Impacts due  to the construction of cut and cover tunnel, underwater tunnel, minor demolition works of existing facilities, temporary traffic arrangement, temporary Storage and stock piling,   temporary barging point and associated impacts.

Temporary storage area and site office, work site for proposed temporary traffic arrangement, temporary storage and stock piling area, temporary barging point.

 

Construction of Ventilation and Tunnel Portal Buildings, construction of depressed road, construction of cut and cover tunnel, construction of underwater tunnel, minor demolition works of existing facilities.

No

 

Large

 

Medium

 

Medium

 

High

 

 

Large

 

 

Large

 

 

LCA3

LR1, LR5, LR6, LR7 & LR14

40,320

Within LR1, LR5, LR6, LR7 & LR14, approximately 275 nos. trees are recorded.

 

Within the portion of LR6 where impact is expected, 18 trees will be retained and protected, 21 trees will be transplanted and 42 trees will be felled.  Approximately 3,620 square metres of planting area would be lost by construction of building and temporary works and associated impacts.

 

Approximately 1,250 square metres of planting area will be permanently lost by the construction of Ventilation Building.

Construction of ventilation building, temporary storage and stockpiling area.

 

Temporary vehicular haulage from Trunk Road T2 Eastern Works Area to Western Works Area.

No

Large

Low

Medium

 

High

 

Large

 

Large

 


 

ID No.

Landscape Resources

Size of LR (m2)

Description of Impacts

Sources of Impact

Reversibility

Scale of Development

Compatibility with Surrounding Landscape

Duration of impact

Magnitude of Change (Negligible, Small, Intermediate, Large)

Construction

Operation

Construction

Operation

LCA4

LR12

315,320

Impacts due to the construction of underwater tunnel and temporary barging point.

Impacts due to the construction of underwater tunnel and, temporary barging point. The temporary barging point has a vertical seawall face and no temporary facilities would be needed to be constructed above the sea.  It will be consist of a one vehicle unloading ramp and a fully enclosed conveyor belt unloading chute from LCA1 (LR8).

Yes

Large

Low

Medium

 

N/A

Small

Negligible

 

LCA7

LR14& LR16

34,390

Impacts due to the additional construction works traffic in the area, temporary excavation works, site offices, structures and heavy machinery and 1 tree to be felled.

 

An approximate area of 21,500 square metres of hard standing will be temporary lost for the Eastern Works Area site offices.

Temporary storage area and site office, temporary vehicular haulage from Trunk Road T2 Eastern Works Area to Trunk Road T2 Western Works Area.

 

Temporary vehicular haulage from Trunk Road T2 Eastern Works Area to Trunk Road T2 Western Works Area.

1 tree to be felled.

 

 

Yes

 

 

 

Large

 

 

 

High

 

 

 

Medium

 

N/A

 

 

Intermediate

 

 

Negligible

 

 

Notes:      The duration of impacts will be from 2016 to 2020 for both Construction Stages of the Eastern and Western areas. 

                  Only Landscape Resources that are impacted are discussed.


9.7.9                   Assessment of Significance of Landscape Impacts

 

9.7.9.1              The significance threshold of landscape impacts are tabulated in Tables 9.12 and 9.13.  All impacts are adverse unless otherwise stated.

Table 9.12       Significance Threshold of Landscape Resources before Mitigation

ID. No.

Sensitivity (Low, Medium, High)

Magnitude of Change

(Negligible, Small, Intermediate, Large)

Significance Threshold Before Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

LR6

Medium

Large

Large

Moderate

Moderate

 

LR8

Low

Large

Large

Moderate

Moderate

LR12

Medium

Small

Negligible

Slight

 

Insubstantial 

LR16

Low

Intermediate

Negligible

Slight

 

Insubstantial 

Note: Only Landscape Resources that are impacted are discussed.

 

Table 9.13       Significance Threshold of Landscape Character Areas before Mitigation

ID. No.

Sensitivity (Low, Medium, High)

Magnitude of Change

(Negligible, Small, Intermediate, Large)

Significance Threshold Before Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

LCA1

Low

Large

Large

Moderate

Moderate

LCA3

Medium

Large

Large

Moderate

 

Moderate

 

LCA4

Medium

Small

Negligible

Slight

 

Insubstantial 

LCA7

Low

Intermediate

Negligible

Slight

 

Insubstantial 

Note: Only Landscape Resources that are impacted are discussed.

 

LR6 – Amenity Area (Kai Fuk Road / Kwun Tong By-pass)

9.7.9.2              The significance threshold before mitigation for LR6 within the construction phase of the Ventilation Building and Western Works Area is considered as moderate, due to the loss of an amenity area, which includes sitting out areas, a footpath and a planting area of 3,620 square metres. 18 of the trees at this location will be retained and protected, 21 trees will be transplanted and 42 trees unsuitable for transplanting will be felled. The significance threshold before mitigation for LR6 within the operation phase is considered as moderate as, on completion of the Project a planting area of 1,250 square metres will be lost due to Trunk Road T2 and Ventilation Building.

LR8 - Derelict / Disturbed Land (KTD South Apron)

9.7.9.3              Since this is an area of derelict / disturbed land measuring 75,300 square metres and a planting area of 159 square metres, where 12 trees will be protected, 10 trees are recommended for transplanting, and 24 trees which are not suitable for transplanting will be felled. The significance threshold before mitigation for LR8 within the construction phase of the Ventilation and Tunnel Portal Buildings and Western Works Area is considered as moderate. On completion of the Project, an area of 8,500 square meters will be permanently lost to the Trunk Road T2, Ventilation and Tunnel Portal Buildings.

LCA1 – Major On-Going Development Landscape

9.7.9.4              Since this is an area of derelict / disturbed land measuring 75,300 square metres and a planting area of 159 square metres, where 12 trees will be protected, 10 trees are recommended for transplanting, and 24 trees which are not suitable for transplanting will be felled. The significance threshold before mitigation for LCA1 within the construction phase of the Ventilation and Tunnel Portal Buildings and Western Works Area is considered as moderate. On completion of the Project, an area of 8,500 square meters will be permanently lost to the Trunk Road T2, Ventilation and Tunnel Portal Buildings.

LCA3 – Transport Corridor

9.7.9.5              The significance threshold before mitigation for LCA3 within the construction phase of the Ventilation Building and Western Works Area is considered as moderate, due to the loss of an amenity area, which includes sitting out areas, a footpath and a planting area of 3,620 square metres. 18 of the trees at this location will be retained and protected, 21 trees will be transplanted and 42 trees unsuitable for transplanting will be felled. The significance threshold before mitigation for LCA3 within the operation phase is considered as moderate as, on completion of the Project a planting area of 1,250 square metres will be lost due to Trunk Road T2 and Ventilation Building.

9.8                       Visual Impact Assessment

9.8.1                   Potential Sources of Visual Impacts

9.8.1.1              The sources of impacts due to the Project would create varying levels of visual impact during the construction and operation phases.  Potential visual impacts would result from the elements stated in Sections 9.7.1 to 9.7.4.  Compatibility of the Project within its visual context is described in Section 9.7.7.

9.8.2                   Assessment of Magnitude to Change and Significance of Visual Impacts before Mitigation

9.8.2.1              The sensitivity and magnitude of change to VSRs is presented in Table 9.14 and the magnitude of change to VSRs before mitigation in the construction and operation phases is then summarised in Tables 9.15 to 9.17 below.  The significance of visual impacts before mitigation is presented in Tables 9.18 and 9.19.

Table 9.14       Sensitivity and Magnitude of Change for Visual Sensitive Receivers

VSR

ID. No.

Sensitivity and Magnitude of Change for VSRs

Type of VSRs

Status

O1

General Description

Newport Centre

This low rise commercial building is planned for redevelopment. Please refer to R1 for description.

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1150 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Operational Phase

 Eastern Works Area: N/A

Western Works Area: Refer to R1 For description.

O2

General Description

Kai Tak 1M: Comprehensive Development Area

The description and evaluation of impacts on the both the residents and workers are discussed below:

Occupational

Planned

(2016)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1350 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

 

 

O2

Operational Phase

Eastern Works Area: N/A

Occupational

Planned

(2016)

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1450 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7, GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered negligible.

O3

General Description

Skyline Tower, Kowloon Bay

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 700 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

O3

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 650 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered small.

O4

General Description

Hong Kong International Trade and Exhibition Centre

The description and evaluation of impacts on the both the visitors and  workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 400 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

O4

Operational Phase

Eastern Works Area: N/A

Occupational

Existing

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 500 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered small.

O5

General Description

Enterprise Square & Enterprise Square II, Industrial/Office development Kowloon Bay

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

 

 

O5

Operational Phase

Eastern Works Area: N/A

Occupational

Existing

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 250 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered small.

 

 

O6

General Description

Kai Fuk Industrial Center, Hong Leong Industrial Complex & Billion Centre

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 120 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Operational

Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 140 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

O7

General Description

Mega Box/Enterprise Square V, Enterprise Square III, Exchange Tower, Manhattan Place & One Kowloon

The description and evaluation of impacts on both the visitors and workers are discussed below.

Occupational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 70 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Operational Phase

Eastern Works Area: N/A.

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 70 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

O8

General Description

Petrol Stations along Kai Fuk Road

The description and evaluation of impacts on the both the visitors and  workers are discussed below:

Occupational

 

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 80 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 80 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered small.

O9

General Description

Kai Tak Runway Precinct Hotel Belt

The description and evaluation of impacts on both the visitors and workers are discussed below:

Occupational/Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 500 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by R5, RE8, GIC11A & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

O10

General Description

Kai Tak Cruise Terminal & Tourism Related Commercial Development 

The description and evaluation of impacts on both the visitors and workers are discussed below:

Occupational/Recreational

Planned

(2014- 2015)

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial and the distance of the view is approximately 1100 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

O10

Construciton Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 500 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Occupational/Recreational

Planned

(2014- 2015)

Operational

Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by O12, GIC11A, R5 & RE9 GIC6 within the operation phase, the magnitude of impact for this VSR is considered negligible.

 

 

O11

General Description

Vacant Lot at southern end of former Kai Tak South Apron/3E1 Commercial Development

The description and evaluation of impacts on workers are discussed below:

Occupational

 

Existing/Planned

 (2021)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: The site is designated as a construction works area. 

 

 

O11

Operational Phase

Eastern Works Area: N/A

Occupational

 

Existing/Planned

 (2021)

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 320 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

O12

General Description

Kai Tak South Apron: Gas Pigging Station

The description and evaluation of impacts on the visitors and  workers are discussed below:

Occupational

Planned

(2012-2015)

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 350 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

 

 

O13

General Description

Pacific Trade Centre/ Proposed 3D2 Commercial Development

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing/Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 200 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 380 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

O14

General Description

Octa Tower

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 1800 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

O14

Construction Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 20 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Occupational

Existing

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 320 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

 

 

O15

General Description

 Not Used

 

 

Construction Phase

Eastern Works Area: Not Used.

Western Works Area: Not Used.

Operational Phase

Eastern Works Area: Not Used.

Western Works Area: Not Used.

O16

General Description

Proposed Industrial/Office development at Kwun Tong Commercial Area

The description and evaluation of impacts on the workers are discussed below:

Occupational

Planned

(2015)

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 1800 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 300 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 650 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by R3, R4, O11, O13 and GIC11B within the operation phase, the magnitude of impact for this VSR is considered negligible.

 

 

O17

General Description

Industrial/Office development at Kwun Tong Western commercial area

The description and evaluation of impacts on the workers are discussed below:

Occupational

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial and the distance of the view is approximately 320 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 650 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by R3, R4, O11 and O13 within the operation phase, the magnitude of impact for this VSR is considered negligible.

 

 

O18

General Description

Industrial/Office development at Kwun Tong Eastern commercial area

The description and evaluation of impacts on the workers are discussed below

Occupational

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 360 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 750 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Operational Phase

Eastern Works Area: Not Used.

Western Works Area: Not Used.

O19

General Description

Kwun Tong Sewage Treatment Works/Kwun Tong Pumping Station /Planned Landscape Decked: Enclosed Sewage Works

The description and evaluation of impacts on the workers are discussed below

Occupational

Existing/Planned (2021)

Construction Phase

Eastern Works Area The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 160 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1400 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

O20

General Description

Soccer Pitch, Car Park, Petrol Filling Station & Vacant Sites (Proposed Cha Kwo Ling Promenade Park)

The description and evaluation of impacts on the users and workers are discussed below.

Occupational/Recreational

Existing/ Planned (2021)

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the construction phase.

 

 

Western Works Area: N/A

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Refer to RE17: Cha Kwo Ling Park, N/A

 

 

O21

General Description

Proposed Cha Kwo Ling Promenade

The description and evaluation of impacts on the workers are discussed below

Occupational/Recreational

Existing/ Planned (2021)

Construction Phase

Eastern Works Area: The site is designated as a construction works area. 

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

O22

General Description

Tin Hau Temple

The description and evaluation of impacts on the users are discussed below

Occupational

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 900 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

Western Works Area: N/A

 

 

O22

Operational

Phase

Eastern Works Area: N/A

Occupational

Existing

Western Works Area: N/A

 

 

GIC1

General Description

EMSD Workshops, Sewage Pumping Station & Electricity Substation.

The description and evaluation of impacts on the workers are discussed below

Government /Institutional/

Community

Existing/Proposed

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 1000 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4 & RE5 within the construction phase, the magnitude of impact for this VSR is considered small.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, GIC7, GIC8 & GIC11C, within the operation phase, the magnitude of impact for this VSR is considered negligible.

GIC2

General Description

Electricity Substation

The description and evaluation of impacts on the workers are discussed below

Government /Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 900 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7 & GIC11C. within the operation phase, the magnitude of impact for this VSR is considered negligible.

GIC3

General Description

Tunnel Ventilation Shaft & Administration Building

The description and evaluation of impacts on the workers are discussed below

Government

/Institutional/

Community

Planned

(2016)

 

Construction

Eastern Works Area: N/A

Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 600 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

GIC3

Operational Phase

Eastern Works Area: N/A

Government

/Institutional/

Community

Planned

(2016)

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 640 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7, & GIC10 within the operation phase, the magnitude of impact for this VSR is considered small.

GIC4

General Description

Tunnel Ventilation Shaft & Administration Building (Kia Tak Tunnel Entrance)

The description and evaluation of impacts on the workers are discussed below

Government

/Institutional/

Community

Existing

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 690 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 800 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7 & GIC11C, within the operation phase, the magnitude of impact for this VSR is considered small.

GIC5

General Description

DSD Desilting Compound

The description and evaluation of impacts on the workers are discussed below

Government

/Institutional/

Community

Planned

(2016)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 760 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 760 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7 & GIC11C, within the operation phase, the magnitude of impact for this VSR is considered small.

GIC6

General Description

Northern Undesignated Government Site at former Kai Tak South Apron

The description and evaluation of impacts on the workers are discussed below

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 400 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

GIC7

General Description

Southern  Undesignated Government Site at former Kai Tak South Apron

The description and evaluation of impacts on the workers are discussed below

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 150 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the operation phase.

GIC8

General Description

Social Welfare Facilities

The description and evaluation of impacts on the workers are discussed below.

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 140 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the operation phase.

GIC9

General Description

Animal Management Centre

The description and evaluation of impacts on the workers are discussed below

Government

/Institutional/

Community

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 130 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the operation phase.

GIC10

General Description

Jordan Valley Box Culvert: DSD Desilting Building & Pumping Station

The description and evaluation of impacts on the workers are discussed below.

Government

/Institutional/

Community

Existing

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: Same as Construction Phase

GIC11A

General Description

Hospital at Former Kai Tak South Apron

The description and evaluation of impacts on the visitors and workers are discussed below

Government

/Institutional/

Community

Planned

(2018)

 

Construction

Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the construction phase.

 

 

GIC11A

Operational Phase

Eastern Works Area: N/A

Government

/Institutional/

Community

Planned

(2018)

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the operation phase.

GIC11B

General Description

Electrical & Mechanical Services Department, Kowloon Bay Vehicle Servicing Station/ Proposed Hospital at former Kai Tak South Apron

The description and evaluation of impacts on the visitors and workers are discussed below

Government

/Institutional/

Community

 

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the operation phase.

GIC11C

General Description

Derelict land and Proposed Hospital at former Kai Tak South Apron

The description and evaluation of impacts on the visitors and workers are discussed below

Government

/Institutional/

Community

 

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

Western Works Area: The site is designated as a construction works area.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the operation phase.

GIC12

General Description

Kwun Tong Public Transport Interchange and Kwun Tong Ferry Pier

The description and evaluation of impacts on the users and workers are discussed below

Government /Institutional/

Community

Existing

 

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be full, and the distance of the view is approximately 450 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

 

 

GIC12

Construction Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1250 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Government /Institutional/

Community

Existing

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

R1

General Description

Comprehensive Development Area, Ma Tau Kok.

The description and evaluation of impacts on the residents are discussed below

Residential

 

 

 

 

Planned

(2021)

Construction

Eastern Works Area: N/A

Phase

Western Works Area: Refer to O1 for description.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1350 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE5, RE8, GIC7, GIC8, & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

R2

General Description

Kai Tak 2B: Comprehensive Development Area

The description and evaluation of impacts on the residents and workers are discussed below

Residential

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1600 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7, GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered negligible.

R3

General Description

S/K22/13 Commercial Development

The description and evaluation of impacts on the residents and workers are discussed below

Residential

 

Planned

(2016)

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 1740 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

R3

Construction Phase

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered high. The degree of visibility to the Project will be partial, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Residential

 

Planned

(2016)

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 500 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by O11 & GIC11B within the operation phase, the magnitude of impact for this VSR is considered small.

 

 

R4

General Description

S/K22/11 Comprehensive Development Area

The description and evaluation of impacts on the residents and workers are discussed below

Residential

 

Planned

(2016)

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 1740 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

R4

Construction Phase

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered high. The degree of visibility to the Project will be full, and the distance of the view is approximately 10 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Residential

 

Planned

(2016)

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 500 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by O11 & GIC11B. within the operation phase, the magnitude of impact for this VSR is considered small.

 

 

R5

 

General Description

Kai Tak Runway Precinct Housing Development

The description and evaluation of impacts on the residents are discussed below

Residential

 

Planned

(2021)

 

Construction Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

R5

Operational Phase

Eastern Works Area: N/A

Residential

 

Planned

(2021)

 

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 400 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, GIC11A, GIC 11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

R6

General Description

Laguna City

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered high. The degree of visibility to the Project will be full, and the distance of the view is approximately 160 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered large during the construction phase.

 

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1600 meters min.

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

R7

General Description

Residential development at Cha Kwo Ling Road

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered high. The degree of visibility to the Project will be full, and the distance of the view is approximately 50 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

R8

General Description

Cha Kwo Ling Tsuen

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered high. The degree of visibility to the Project will be full, and the distance of the view is approximately 20 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered large during the construction phase.

Western Works Area: N/A

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: N/A

 

 

R9

General Description

Grand Waterfront, To Kwa Wan

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1150 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1400 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4, RE5, RE8, GIC7, GIC8 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

R10

General Description

Wyler Gardens, To Kwa Wan

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction

Eastern Works Area: N/A

 

 

Phase

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1250 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4 & RE5 within the construction phase, the magnitude of impact for this VSR is considered small.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1500 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4, RE5, RE8, GIC7, GIC8 & GIC11 within the operation phase, the magnitude of impact for this VSR is considered negligible.

R11

General Description

Sky Tower, Kowloon City

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1550 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4 & RE5, within the construction phase, the magnitude of impact for this VSR is considered small.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1900 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4, RE5, RE8, GIC7, & GIC11 within the operation phase, the magnitude of impact for this VSR is considered negligible.

R12

General Description

Sunrise Villas, To Kwa Wan

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1600 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4 and, RE5, within the construction phase, the magnitude of impact for this VSR is considered small.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 2000 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE5, RE8, GIC7, GIC8 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

R13

General Description

Laguna Verde Complex, Hung Hom

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 3800 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1620 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE5, & GIC11A within the construction phase, the magnitude of impact for this VSR is considered small.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1840 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by O9, R5, RE6, RE8 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

R14

General Description

Harbourfront Landmark & Harbour Grand,  Kowloon,  Hung Hom

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction Phase

Eastern Works Area:

The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 3200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 2110 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE5, & GIC11A within the operation phase, the magnitude of impact for this VSR is considered small.

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 2000 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by O9, R5, RE6, RE8, GIC7 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

 

 

R15

General Description

Kai Tak 2B Housing Development

The description and evaluation of impacts on the residents are discussed below

Residential

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1550 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC7, GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered negligible.

R16

General Description

Kai Tak 1L & 1K Housing Development

The description and evaluation of impacts on the residents are discussed below

Residential

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 1060 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC9 & GIC10, within the operation phase, the magnitude of impact for this VSR is considered small.

R17

General Description

Kai Tak 1H & 1I Housing Development

The description and evaluation of impacts on the residents are discussed below

Residential

Planned

(2016)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 1050 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1100 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC6, GIC9 & GIC10 within the operation phase, the magnitude of impact for this VSR is considered negligible.

R18

General Description

Hing Yan Street Residential Block

The description and evaluation of impacts on the residents are discussed below

Residential

Existing

Construction

Eastern Works Area: N/A

Phase

Western Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: Refer to R1 for details

R19

General Description

Yau Tong Bay Development

The description and evaluation of impacts on the residents are discussed below

Residential/

Occupational

Planned

(2018)

Construction Phase

Eastern Works Area: The frequency and duration of views would be long. Sensitivity for this VSR is considered high. The degree of visibility to the Project will be partial, and the distance of the view is approximately 300 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Western Works Area: N/A

Operational

Eastern Works Area: N/A

Phase

Western Works Area: N/A

 

 

RE1

General Description

Ma Tau Kok: Regional Open Space

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Planned

(2014)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1800 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction of RE4 & RE5 within the operation phase, the magnitude of impact for this VSR is considered small

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1650 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

RE2

General Description

Hoi Sham Park, Ma Tau Kok

Existing public waterfront park.  At pedestrian level there are good panoramic views across Kowloon Bay and over the Kai Tak development, which is currently undergoing various demolition/site clearance, infrastructure and construction projects throughout the KTD.

Recreational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1500 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction of RE4 & RE5 within the operation phase, the magnitude of impact for this VSR is considered small

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1600 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

RE3

General Description

Current & Future Waterfront Promenade, Ma Tau Kok

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Existing/ Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE4 & RE5 within the construction phase, the magnitude of impact for this VSR is considered small during the phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1300 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, GIC7, GIC8 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

RE4

General Description

Planned Multi-Purpose Stadium Complex –

Park

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Planned

(2016-2020)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be partial, and the distance of the view is approximately 1000 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 1000 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, GIC7, GIC8 & GIC11C, within the operation phase, the magnitude of impact for this VSR is considered negligible.

RE5

General Description

Kai Tak Runway Precinct: Metro Park

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Planned

(2017)

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 300 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 400 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered high.

 

Due to obstruction by RE8, GIC7, GIC8 & GIC11C within the operation phase, the magnitude of impact for this VSR is considered negligible.

RE6

General Description

Kai Tak Runway Precinct Northern Promenade

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational

Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 330 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, GIC7, GIC8 & GIC11C, within the operation phase, the magnitude of impact for this VSR is considered intermediate.

RE7

General Description

Kai Tak Runway Park

The description and evaluation of impacts on the recreational users are discussed below:.

Recreational

Planned

(2013)

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 700 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

 

 

RE7

Construction Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 350 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Recreational

Planned

(2013)

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: N/A

 

 

RE8

General Description

Kai Tak South Apron: Southern Promenade

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 100 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by RE8, GIC7, GIC11A & GIC11C within the operation phase, the magnitude of impact for this VSR is considered intermediate.

RE9

General Description

Kai Tak South Apron: Kowloon Bay Square

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: N/A

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be partial, and the distance of the view is approximately 450 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by O11, O12, GIC11A & GIC11C, within the operation phase, the magnitude of impact for this VSR is considered intermediate.

RE10

General Description

Kai Tak South Apron: Amenity Area

The description and evaluation of impacts on the recreational users are discussed below:.

Recreational

Planned

(2021)

Construction

Eastern Works Area: N/A

Phase

Western Works Area: Area is designated to be within site boundary area - N/A.

 

 

Operational Phase

Eastern Works Area: N/A

 

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered large. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered large during the operation phase.

RE11

General Description

Enterprise Square: CIC Zero Carbon Building

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Existing

Construction Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 150 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 150 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

 

Due to obstruction by GIC10, within the operation phase, the magnitude of impact for this VSR is considered negligible.

RE12

General Description

Hoi Bun Road Park

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Existing

Construction Phase

 

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 300 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be glimpse (M), and the distance of the view is approximately 350 meters min.

 

The scale of the development is considered medium. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the operation phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A

RE13

General Description

Kwun Tong Promenade (Existing )

The description and evaluation of impacts on the recreational users are discussed below:.

Recreational

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be full, and the distance of the view is approximately 200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

R13

Construction Phase

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 750 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Recreational

Existing

Operational

Eastern Works Area: N/A

 

 

Phase

Western Works Area: N/A

 

 

RE14

General Description

Kwun Tong Promenade (Planned)

The description and evaluation of impacts on the recreational users are discussed below:

Occupational/Recreational

Planned

(2021)

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be full, and the distance of the view is approximately 200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered high. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

 

Western Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be full, and the distance of the view is approximately 200 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A.

RE15

General Description

Laguna Park

The description and evaluation of impacts on the recreational users are discussed below:

Recreational

Existing

Construction Phase

Eastern Works Area: The frequency and duration of views would be medium. Sensitivity for this VSR is considered low. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 300 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered low. Overall the magnitude of impact for this VSR is considered negligible during the construction phase.

Western Works Area: N/A

Operational Phase

Eastern Works Area: N/A

Western Works Area: N/A.

T1

General Description

Kwun Tong By-pass and Kai Fuk Road

The description and evaluation of impacts on the travellers are discussed below:

Travelling

Existing

 

Construction Phase

Eastern Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be a glimpse, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered small during the construction phase.

 

 

 

T1

Construction Phase

Western Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Travelling

Existing

 

 

Operational Phase

Eastern Works Area: N/A

 

 

 

Western Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the operation phase.

 

 

 

T2

General Description

Cha Kwo Ling Road

The description and evaluation of impacts on the travellers are discussed below:

Travelling

Existing

 

 

Construction Phase

Eastern Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

 

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

 

Western Works Area: N/A

 

Operational Phase

Eastern Works Area: N/A

 

Western Works Area: N/A

 

T3

General Description

Harbour Traffic at Victoria Harbour

The description and evaluation of impacts on the travellers are discussed below:

Travelling

 

Existing

 

 

Construction Phase

Eastern Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

Western Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be full, and the distance of the view is approximately 5 meters min.

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium. Overall the magnitude of impact for this VSR is considered intermediate during the construction phase.

 

Operational

Eastern Works Area: N/A

 

 

 

Phase

Western Works Area: The frequency and duration of views would be short. Sensitivity for this VSR is considered medium. The degree of visibility to the Project will be glimpse, and the distance of the view is approximately 100 meters min.

The scale of the development is considered small. Compatibility within the surrounding visual context is considered medium.

Due to obstruction by O11, O12, GIC11A GIC11C, R3, R4, RE8 & RE9 within the operation phase, the magnitude of impact for this VSR is considered negligible.

 

 

 

Note:- “N/A” denotes – No views of Project or construction traffic


 

Table 9.15      Magnitude of Change to Visually Sensitive Receivers:  Eastern Works Area - Construction Phase

VSR

ID. No.

Compatibility with surrounding

(High/ Medium/ Low)

Duration of Impacts under Construction Phase

(Long/ Medium/ Short)

Scale of the

Construction

Project

(Large/ Medium/ Small)

Reversibility

(Yes/No)

Degree of Visibility under Construction

(Full/Partial/

Glimpse/None)

(M)*

Magnitude of Change under Construction

(Negligible, Small, Intermediate, Large)

 

O10

Medium

Medium

Small

No

Partial

Small

O14

Medium

Medium

Small

No

Glimpse

Small

O16

Medium

Medium

Small

No

Glimpse

Negligible

O17

Medium

Medium

Small

No

Partial (M)

Small

O18

Medium

Medium

Medium

No

Glimpse

Small

O19

Medium

Medium

Large

No

Partial

Intermediate

O20

Medium

Medium

Large

No

Full

Large

O22

Medium

Medium

Medium

No

Partial

Small

GIC12

Medium

Medium

Medium

No

Full (M)

Negligible

R3

Medium

Medium

Small

No

Partial

Small

R4

Medium

Medium

Small

No

Partial

Small

R6

Low

Medium

Large

No

Full

Large

R7

Low

Medium

Large

No

Full

Large

R8

Low

Medium

Large

No

Full

Large

R13

Medium

Medium

Small

No

Glimpse

Negligible

R14

Medium

Medium

Small

No

Glimpse

Negligible

R19

Low

Medium

Small

No

Partial

Intermediate

RE7

Low

Medium

Small

No

Full

Intermediate

RE12

Medium

Medium

Small

No

Glimpse (M)

Negligible

RE13

Medium

Medium

Small

No

Full (M)

Small

RE14

High

Medium

Small

No

Full (M)

Negligible

RE15

Low

Medium

Small

No

Glimpse

Negligible

T1

Medium

Short

Small

No

Glimpse

Small

T2

Medium

Short

Small

No

Full

Intermediate

T3

Medium

Short

Small

No

Full

Intermediate

Notes:      Compatibility: The visual context within which the Project is located.

                  Scale of Construction: Based on distance from Project and compatibility with surrounding redevelopment

                  * Degree of Visibility (M): No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials

 

Table 9.16      Magnitude of Change to Visually Sensitive Receivers:  Western Works Area - Construction Phase

VSR

ID. No.

Compatibility with surrounding

(High/ Medium/ Low)

Duration of Impacts under Construction Phase

(Long/ Medium/ Short)

Scale of the

Construction

Project

(Large/ Medium/ Small)

Reversibility

(Yes/No)

Degree of Visibility under Construction

(Full/Partial/

Glimpse/None) (M)*

Magnitude of Change under Construction

(Negligible, Small, Intermediate, Large)

 

O1

Medium

Medium

Small

No

Glimpse

Negligible

O2

Medium

Medium

Small

No

Glimpse

Negligible

O3

Medium

Medium

Small

No

Partial

Small

O4

Medium

Medium

Small

No

Partial

Small

O5

Medium

Medium

Small

No

Partial

Intermediate

O6

Medium

Medium

Large

No

Full

Intermediate

O7

Medium

Medium

Large

No

Full

Intermediate

O8

Medium

Medium

Large

No

Glimpse

Small

O10

Low

Medium

Small

No

Partial

Intermediate

O12

Medium

Medium

Large

No

Full

Intermediate

O13

Medium

Medium

Medium

No

Partial

Small

O14

Medium

Medium

Large

No

Full

Large

O16

Medium

Medium

Medium

No

Partial

Small

O17

Medium

Medium

Small

No

Partial

Small

O18

Medium

Medium

Small

No

Partial

Intermediate

O19

Medium

Medium

Small

No

Glimpse

Negligible

GIC1

Medium

Medium

Small

No

Partial

Small

GIC3

Medium

Medium

Small

No

Glimpse

Small

GIC4

Medium

Medium

Small

No

Glimpse

Small

GIC5

Medium

Medium

Small

No

Glimpse

Small

GIC10

Medium

Medium

Large

No

Full

Large

GIC11A

Medium

Medium

Large

No

Full

Large

GIC11B

Medium

Medium

Large

No

Full

Large

GIC12

Medium

Medium

Small

No

Glimpse

Negligible

R3

Low

Long

Large

No

Partial

Large

R4

Low

Long

Large

No

Full

Large

R6

Medium

Long

Small

No

Glimpse

Small

R9

Medium

Long

Small

No

Glimpse

Small

R10

Medium

Long

Small

No

Glimpse

Small

R11

Medium

Long

Small

No

Glimpse

Small

R12

Medium

Long

Small

No

Glimpse

Small

R13

Medium

Long

Small

No

Glimpse

Small

R14

Medium

Long

Small

No

Glimpse

Small

R17

Medium

Long

Small

No

Partial

Small

R18

Medium

Long

Small

No

Glimpse

Small

RE1

Medium

Medium

Small

No

Glimpse

Small

RE2

Medium

Medium

Small

No

Glimpse

Small

RE3

Medium

Medium

Small

No

Glimpse

Small

RE4

Medium

Medium

Medium

No

Partial

Small

RE5

Medium

Medium

Medium

No

Partial

Small

RE7

Medium

Medium

Medium

No

Full

Intermediate

RE11

Medium

Medium

Small

No

Glimpse

Small

RE12

Medium

Medium

Medium

No

Glimpse (M)

Small

RE13

Medium

Medium

Small

No

Full

Intermediate

RE14

Medium

Medium

Small

No

Full

Small

T1

Medium

Short

Small

No

Full

Intermediate

T3

Medium

Short

Small

No

Full

Intermediate

Notes:      Compatibility: The visual context within which the Project is located.

                  Scale of Construction: Based on distance from Project and compatibility with surrounding redevelopment

                  * Degree of Visibility (M): No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials

 

Table 9.17      Magnitude of Change to Visually Sensitive Receivers:  Western Works Area - Operation Phase

VSR

ID. No.

Compatibility with surrounding

(High/ Medium/ Low)

Duration of Impacts Operation Phase

(Long/ Medium/ Short)

Scale of the

Operation

Project

(Large/ Medium/ Small)

Reversibility

(Yes/No)

Degree of Visibility in Operation Phase

(Full/Partial/

Glimpse/None)

(M)*

Magnitude of Change Operation Phase

(Negligible, Small, Intermediate, Large)

 

O2

Medium

Medium

Small

No

Glimpse

Negligible

O3

Medium

Medium

Small

No

Partial

Small

O4

Medium

Medium

Small

No

Partial

Small

O5

Medium

Medium

Small

No

Partial

Small

O6

Medium

Medium

Medium

No

Partial

Small

O7

Medium

Medium

Medium

No

Partial

Small

O8

Medium

Medium

Medium

No

Glimpse

Small

O9

Medium

Medium

Small

No

Glimpse

Negligible

O10

Medium

Medium

Small

No

Glimpse

Negligible

O11

Medium

Medium

Medium

No

Partial

Small

O12

Medium

Medium

Medium

No

Partial

Small

O13

Medium

Medium

Medium

No

Partial

Small

O14

Medium

Medium

Medium

No

Partial

Small

O16

Medium

Medium

Small

No

Glimpse

Negligible

O17

Medium

Medium

Small

No

Glimpse

Negligible

GIC1

Medium

Medium

Small

No

Glimpse

Negligible

GIC2

Medium

Medium

Small

No

Glimpse

Negligible

GIC3

Medium

Medium

Small

No

Glimpse

Small

GIC4

Medium

Medium

Small

No

Glimpse

Small

GIC5

Medium

Medium

Small

No

Glimpse

Small

GIC6

Medium

Medium

Small

No

Partial

Small

GIC7

Medium

Medium

Large

No

Partial

Intermediate

GIC8

Medium

Medium

Large

No

Full

Intermediate

GIC9

Medium

Medium

Large

No

Partial

Intermediate

GIC10

Medium

Medium

Large

No

Full

Large

GIC11A

Medium

Medium

Large

No

Full

Large

GIC11B

Medium

Medium

Large

No

Full

Large

GIC11C

Medium

Medium

Large

No

Full

Large

R1

Medium

Long

Small

No

Glimpse

Negligible

R2

Medium

Long

Small

No

Glimpse

Negligible

R3

Medium

Long

Medium

No

Partial

Small

R4

Medium

Long

Medium

No

Partial

Small

R5

Medium

Long

Medium

No

Glimpse

Negligible

R9

Medium

Long

Small

No

Glimpse

Negligible

R10

Medium

Long

Small

No

Glimpse

Negligible

R11

Medium

Long

Small

No

Glimpse

Negligible

R12

Medium

Long

Small

No

Glimpse

Negligible

R13

Medium

Long

Small

No

Glimpse

Negligible

R14

Medium

Long

Small

No

Glimpse

Negligible

R15

Medium

Long

Small

No

Glimpse

Negligible

R16

Medium

Long

Small

No

Partial

Small

R17

Medium

Long

Small

No

Glimpse

Negligible

RE1

Medium

Medium

Small

No

Glimpse

Negligible

RE2

Medium

Medium

Small

No

Glimpse

Negligible

RE3

Medium

Medium

Small

No

Glimpse

Negligible

RE4

Medium

Medium

Medium

No

Glimpse

Negligible

RE5

High

Medium

Medium

No

Glimpse

Negligible

RE6

Medium

Medium

Medium

No

Partial

Intermediate

RE8

Medium

Medium

Medium

No

Partial

Intermediate

RE9

Medium

Medium

Medium

No

Partial

Intermediate

RE10

Medium

Medium

Large

No

Full

Large

RE11

Medium

Medium

Small

No

Glimpse

Negligible

T1

Medium

Short

Small

No

Full

Intermediate

T3

Medium

Short

Small

No

Glimpse

Negligible

Notes:      Compatibility: The visual context within which the Project is located.

                  Scale of Construction: Based on distance from Project and compatibility with surrounding redevelopment

                  * Degree of Visibility (M): No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials


Table 9.18      Significance of Visual Impacts before Mitigation (Eastern Works Area)

VSR

ID. No.

Sensitivity

(Low, Medium, High)

Magnitude of Change

(Negligible, Small,

Intermediate, Large)

Significance Threshold

Before Mitigation (Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

O10

Low

N/A

Small

N/A

Slight

N/A

O14

Low

N/A

Small

N/A

Slight

N/A

O16

Low

N/A

Negligible

N/A

Insubstantial

N/A

O17

Low

N/A

Small

N/A

Slight

N/A

O18

Low

N/A

Small

N/A

Slight

N/A

O19

Low

N/A

Intermediate

N/A

Slight/Moderate

N/A

O20

Medium

N/A

Large

N/A

Moderate/Substantial

N/A

O22

Low

N/A

Small

N/A

Slight

N/A

GIC12

Low

N/A

Negligible

N/A

Insubstantial

N/A

R3

Medium

N/A

Small

N/A

Slight/Moderate

N/A

R4

Medium

N/A

Small

N/A

Slight/Moderate

N/A

R6

High

N/A

Large

N/A

Substantial

N/A

R7

High

N/A

Large

N/A

Substantial

N/A

R8

High

N/A

Large

N/A

Substantial

N/A

R13

Low

N/A

Negligible

N/A

Insubstantial

N/A

R14

Low

N/A

Negligible

N/A

Insubstantial

N/A

R19

High

N/A

Intermediate

N/A

Moderate/Substantial

N/A

RE7

Medium

N/A

Intermediate

N/A

Moderate

N/A

RE12

Low

N/A

Negligible

N/A

Insubstantial

N/A

RE13

Low

N/A

Small

N/A

Slight

N/A

RE14

Low

N/A

Small

N/A

Slight

N/A

RE15

Low

N/A

Negligible

N/A

Insubstantial

N/A

T1

Medium

N/A

Small

N/A

Slight/Moderate

N/A

T2

Medium

N/A

Intermediate

N/A

Moderate

N/A

T3

Medium

N/A

Intermediate

N/A

Moderate

N/A

 

Table 9.19      Significance of Visual Impacts before Mitigation (Western Works Area)

VSR

ID. No.

Sensitivity

(Low, Medium, High)

Magnitude of Change

(Negligible, Small,

Intermediate, Large)

Significance Threshold

Before Mitigation (Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

O1

Low

N/A

Negligible

Negligible

Insubstantial

N/A

O2

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

O3

Low

Low

Small

Small

Slight

Slight

O4

Medium

Low

Small

Small

Slight/Moderate

Slight

O5

Medium

Low

Intermediate

Small

Moderate

Slight

O6

Medium

Medium

Intermediate

Small

Moderate

Slight/Moderate

O7

Medium

Medium

Intermediate

Small

Moderate

Slight/Moderate

O8

Low

Low

Small

Small

Slight

Slight

O9

N/A

Low

N/A

Negligible

N/A

Insubstantial

O10

Medium

Medium

Intermediate

Negligible

Moderate

Insubstantial

O11

N/A

Medium

N/A

Small

N/A

Slight/Moderate

O12

Low

Low

Intermediate

Small

Slight/Moderate

Slight

O13

Low

Medium

Small

Small

Slight

Slight/Moderate

O14

Medium

Medium

Large

Small

Moderate/Substantial

Slight/Moderate

O16

Medium

Low

Small

Negligible

Slight/Moderate

Insubstantial

O17

Low

Low

Small

Negligible

Slight

Insubstantial

O18

Low

N/A

Intermediate

N/A

Slight/Moderate

N/A

O19

Low

N/A

Negligible

N/A

Insubstantial

N/A

GIC1

Low

Low

Small

Negligible

Slight

Insubstantial

GIC2

N/A

Low

N/A

Negligible

N/A

Insubstantial

GIC3

Low

Low

Small

Small

Slight

Slight

GIC4

Low

Low

Small

Small

Slight

Slight

GIC5

Low

Low

Small

Small

Slight

Slight

GIC6

N/A

Medium

N/A

Small

N/A

Slight/Moderate

GIC7

N/A

Medium

N/A

Intermediate

N/A

Moderate

GIC8

N/A

Medium

N/A

Intermediate

N/A

Moderate

GIC9

N/A

Low

N/A

Intermediate

N/A

Slight/ Moderate

GIC10

Medium

Medium

Large

Large

Moderate/Substantial

Moderate/Substantial

GIC11A

Medium

Medium

Large

Large

Moderate/Substantial

Moderate/Substantial

GIC11B

Medium

Medium

Large

Large

Moderate/Substantial

Moderate/Substantial

GIC11C

N/A

Medium

N/A

Large

N/A

Moderate/Substantial

GIC12

Low

N/A

Negligible

N/A

Insubstantial

N/A

R1

N/A

Low

N/A

Negligible

N/A

Insubstantial

R2

N/A

Low

N/A

Negligible

N/A

Insubstantial

R3

High

Medium

Large

Small

Substantial

Slight/ Moderate

R4

High

Medium

Large

Small

Substantial

Slight/ Moderate

R5

N/A

Medium

N/A

Negligible

N/A

Insubstantial

R6

Low

N/A

Small

N/A

Slight

N/A

R9

Low

Low

Small

Negligible

Slight

Insubstantial

R10

Low

Low

Small

Negligible

Slight

Insubstantial

R11

Low

Low

Small

Negligible

Slight

Insubstantial

R12

Low

Low

Small

Negligible

Slight

Insubstantial

R13

Low

Low

Small

Negligible

Slight

Insubstantial

R14

Low

Low

Small

Negligible

Slight

Insubstantial

R15

N/A

Low

N/A

Negligible

N/A

Insubstantial

R16

N/A

Low

N/A

Small

N/A

Slight

R17

Low

Low

Small

Negligible

Slight

Insubstantial

R18

Low

N/A

Small

N/A

Slight

N/A

RE1

Low

Low

Small

Negligible

Slight

Insubstantial

RE2

Low

Low

Small

Negligible

Slight

Insubstantial

RE3

Low

Low

Small

Negligible

Slight

Insubstantial

RE4

Low

Low

Small

Negligible

Slight

Insubstantial

RE5

Medium

Medium

Small

Negligible

Slight/Moderate

Insubstantial

RE6

N/A

Medium

N/A

Intermediate

N/A

Moderate

RE7

Medium

N/A

Intermediate

N/A

Moderate

N/A

RE8

N/A

Medium

N/A

Intermediate

N/A

Moderate

RE9

N/A

Medium

N/A

Intermediate

N/A

Moderate

RE10

N/A

Medium

N/A

Large

N/A

Moderate/Substantial

RE11

Low

Low

Small

Negligible

Slight

Insubstantial

RE12

Low

N/A

Small

N/A

Slight

N/A

RE13

Medium

N/A

Intermediate

N/A

Moderate

N/A

RE14

Low

N/A

Small

N/A

Slight

N/A

T1

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

T3

Medium

Medium

Intermediate

Negligible

Moderate

Insubstantial


9.9                       Mitigation Measures

9.9.1                   Tables 9.20 and 9.21 describe a series of mitigation measures to be used within the construction and operational phases to potentially reduce any landscape or visual impacts that have previously been identified within other sections of this report. The landscape and visual mitigation measures are illustrated in Figure 9.11.2.

 

Table 9.20            Construction Phase Mitigation Measures

ID No.

Landscape and Visual Mitigation Measure

Funding Agency

Implementation Agency

CM1

All works shall be carefully designed to minimize impacts on existing landscape resources and visually sensitive receivers. Existing trees within works area shall be retained and protected.

CEDD

CEDD’s Contractor

CM2

Existing trees of good quality and condition that are unavoidably affected by the works should be transplanted.

CEDD

CEDD’s Contractor

CM3

Not used

Not used

Not used

CM4

Not used.

Not used.

Not used.

CM5

Large temporary stockpiles of excavated material shall be covered with unobtrusive sheeting to prevent dust and dirt spreading to adjacent landscape areas and vegetation, and to create a neat and tidy visual appearance.

CEDD

CEDD’s Contractor

CM6

Construction plant and building material shall be orderly and carefully stored in order to create a neat and tidy visual appearance.

CEDD

CEDD’s Contractor

CM7

Erection of decorative screen hoarding should be designed to be compatible with the existing urban context.

CEDD

CEDD’s Contractor

CM8

All lighting in construction site shall be carefully controlled to minimize light pollution and night-time glare to nearby residences and GIC user. The contractor shall consider other security measures, which shall minimize the visual impacts.

CEDD

CEDD’s Contractor

 

Table 9.21            Operation Phase Mitigation Measures

ID No.

Landscape and Visual Mitigation Measure

Funding Agency

Implementation Agency

Maintenance/Management Agency

OM1

Compensatory tree planting shall be incorporated along roadside amenity areas affected by the construction works. The required numbers of compensatory trees shall follow the requirements of  ETWB TCW No. 3/2006.

CEDD

CEDD’s Contractor

LCSD

OM2

Compensatory tree planting shall be incorporated by the Project. The required numbers of compensatory trees shall follow the requirements of ETWB TCW No. 3/2006. Loss of amenity area adjacent to the Kwun Tong By-pass and planting areas in KTD South Apron will be mitigated by the creation of the Kai Tak South Apron: Amenity Area, which will be equal to or larger than the current provision.

CEDD

CEDD’s Contractor

LCSD

OM3

Trees, shrubs and climbers shall be planted to soften and screen proposed roads, central medians and associated structures, and to enhance streetscape greening.

CEDD

CEDD’s Contractor

LCSD

OM4

All works areas, excavated areas and disturbed areas for tunnel construction and temporary road diversion or any other proposed works shall be reinstated to former conditions or better, with landscape treatment and to the satisfaction of the relevant Government departments.

CEDD

CEDD’s Contractor

Relevant Government Departments

 

OM5

Tunnel portals and all above ground structures shall be sensitively designed to ensure the element with colour, texture and tonal quality being compatible to the existing urban context. Trees and shrub planting to minimize the potential adverse landscape and visual impacts shall be included where space permits. Roof top greening and vertical greening shall also be provided.

CEDD

CEDD’s Contractor

LCSD/ HyD

 

9.10                   Environmental Monitoring & Audit Requirement

9.10.1               Construction Phase

9.10.1.1          It is recommended that professionally qualified (i.e. LARB) Resident Site Landscape Staff (SRLA/RLA) supervise and monitor the construction phase landscape and visual mitigation measures.  This is necessary, to ensure that topsoil is saved, to ensure that existing trees earmarked for retention on site or transplanting are protected and to monitor advance screen planting works, including procurement of plants, and the effectiveness of temporary screen hoardings.  Regular site inspections should be undertaken to closely monitor all these aspects of the work.

9.10.2               Operation Phase

9.10.2.1          During the operation phase, landscape and visual mitigation measures should be monitored by the Environmental Team and Independent Environmental Checker – during the first 10 years to check that the intended mitigation effects are realised.  Regular monitoring should be undertaken to ensure that the landscape and visual mitigation measures have been implemented, are effective and are being managed and maintained.  The compensatory tree planting required to offset the loss of existing trees should be checked, and the additional planting works for screening and amenity purposes.  Planting must be established and sustainable and provide long term landscape and visual mitigation.  Hardworks elements that have been provided as part of the new works or as the reinstatement of impacted works should also be monitored and checked that they are being maintained and are achieving their mitigation function.

9.11                   Residual Impacts

9.11.1               Illustrations of Residual Impacts

9.11.1.1          Figures 9.17.1 to 9.17.4 provide photomontages of Trunk Road T2 and associated buildings and adjacent developments, showing the outline massing of the proposed developments, as per the KTD Recommended Outline Development Plan.

9.11.1.2          Landscape and visual impacts, at both construction and operation phases, which remain after all mitigation measures have been assessed, are provided in Tables 9.22 to 9.25.

9.11.2               Illustrations of Residual Visual Impacts (Refer to Figures 9.17 and 9.17.1 to 9.17.4)

9.11.2.1          In reviewing the location and context of the T2 Project in both the construction and operation phases, it is considered that on completion the only above ground structures that may impact the immediate and surrounding areas are within the Western Works Area. The views from Hung Hum, To Kwa Wan, Kwun Tong and Cha Kwo Ling would be significantly screened by the proposed KTD Runway Precinct and South Apron Development. As the maximum proposed height of the Ventilation and Tunnel Portal building is +17m PD, the following views were proposed to show context and detail of the T2 Works Area and associated buildings:

9.11.2.2          Figure 9.17.1: Viewpoint No 1. - 16th Floor of Mega Box. Mega Box is part of the Enterprise Square V complex. Upper floors of these buildings have a direct view onto the site from the Kowloon Bay Commercial Area. The views looking onto the Western Works Area and the proposed T2 Buildings are partially screened by Kowloon Bay/Kwun Tong By-Pass on lower floors of the buildings. The photomontages show the existing and proposed operational phase in scale and context, both with and without mitigation measures as per the latest Recommended Outline Development Plan (RODP) for Kai Tak Development. With the proposed mitigation measures and greening initiatives, the T2 Ventilation and Tunnel Portal Buildings complement the proposed KTD considering the current existing conditions.

9.11.2.3          Figure 9.17.2: Viewpoint No 2. – Trunk Road T2 & Road 18. The photomontages are based upon a pedestrian view at ground level and show the Tunnel Portal and the descending T2 Road.  On Day 1, the view shows the Tunnel Portal and Ventilation Buildings with vertical greening and planting. The trees are planted at semi mature size to help screen the buildings on Day 1. Within 10 years, the trees will soften and mask the top and sides of the tunnel portal from views at both pedestrian level and from the surrounding buildings.

9.11.2.4          Figure 9.17.3: Viewpoint No 3. – Trunk Road T2, refuse collection building & Road D4. The photomontages are based on a pedestrian view at ground level to provide a scale perspective of the Refuse Collection & Ventilation Building, both in size and context with the existing Kwun Tong By-pass, Kowloon Bay Commercial Area and the proposed KTD: South Apron Developments. It is anticipated that the refuse collection building will have vertical greening and planting. The greening measures will soften the hard concrete structure, and blend into the context of the regenerated surrounding area. Trees are planted on either side of the building so that their canopies, within 10 years, will help to screen the structures from surrounding roads and buildings.

9.11.2.5          Figure 9.17.4: Viewpoint No 4. – Top Floor Proposed Residential Block at R3 Runway Precinct Housing Development. The photomontages are based on a resident’s view within the Runway Precinct Housing Development. The photomontages illustrate the size and scale of the Tunnel Portal and refuse collection buildings against the back drop of the Kwun Tong By-pass with proposed mitigation measures. The refuse collection building on Day 1 fits in with the proposed soft landscape. In 10 years the building is screened by trees along the D6 bridge, and merges into the back drop of the trees along the edge of the Kwun Tong By-pass.

9.11.3               Concurrent Projects

9.11.3.1          Trunk Road T2 is to be constructed in conjunction with two other Route 6 Projects;  the CKR in the western South Apron area and the Tseung Kwan O - Lam Tin Tunnel Interchange at the eastern end, forming a major transportation route within the Kowloon Peninsula.  The Kai Tak South Apron Development has a series of residential, commercial and government buildings proposed adjacent to the Trunk Road T2, Ventilation & Tunnel Portal Buildings. The various developments are scheduled to be completed and operational by 2021.

9.11.3.2          As per the KTD Recommended Outline Development Plan the North Apron and Runway precinct areas will also be constructed and operational by 2021.

9.11.4               Assessment of the Significance of Residual Landscape Impacts

9.11.4.1          On completion of the Project, at the eastern end of Trunk Road T2 and associated works, within Cha Kwo Ling Road area, the residual landscape impacts are considered to be insubstantial.

9.11.4.2          On Day 1 of completion of the Project, at the western end of Trunk Road T2 and associated buildings, the residual landscape impacts are considered slight to insubstantial as the project will adhere to the mitigation measures shown in Tables 9.22 and 9.23, and illustrated in Figure 9.11.2 and Figures 9.12.1 to 9.12.4.  At Year 10 the impacts are slight to insubstantial, though are considered beneficial to the Project.

9.11.4.3          Residual landscape impacts on Landscape Resources & Landscape Character Areas at Day 1 and Year10 are summarised in Tables 9.22 and 9.23 respectively. Impacts on Landscape Resources by the Project are described as follows:

·             LR6 – Amenity Area (Kai Fuk Road / Kwun Tong By-pass): An amenity area including sitting out areas along a footpath and a planting area of 3,620 square metres will be lost by the construction of the Ventilation Building and Western Works Area. On completion of the Project a planting area of 1,250 square metres will be lost due to Trunk Road T2 and Ventilation Building. This will be compensated by a planting area to the immediate east of approximately 4,900 square metres (refer to Figure 9.11.2). Within the Western Works Area, 18 trees will be retained and protected, 21 trees will be transplanted and 42 trees unsuitable for transplanting will be felled. 63 trees will be provided as compensation in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2).

 

·             LR8 – Derelict / Disturbed Land (KTD South Apron): An area of derelict / disturbed land measuring 75,300 square metres and a planting area of 159 square metres will be lost due to the Western Works Area. On completion of the Project, an area of 8,500 square meters will be permanently lost to the Trunk Road T2, Ventilation and Tunnel Portal Buildings. This will be compensated by a planting area of approximately 15,740 square metres. 12 trees will be protected from impact by the Project, 10 trees are recommended for transplanting, and 24 trees which are not suitable for transplanting will be felled.  89 trees will be provided as compensation in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2).

 

·             LR12 – Water Body (Kwun Tong Typhoon Shelter):     A temporary barging point will be located at the south eastern corner of the South Apron LR8 during the construction phase only.  The barging point will not damage any parts of the seabed and is situated on the existing seawall.  Residual impacts will be the operation of barges between 07.00 & 19.00 in the construction phase only. The sea wall will be reinstated following completion of the Project.

 

·             LR16 – Derelict / Disturbed Land Proposed as Cha Kwo Ling Promenade Park by Others (Cha Kwo Ling Former Public Cargo Working Area): An approximate area of 21,500 square metres of hard standing will be lost for the Eastern Works Area site offices. One tree, Macaranga tanarius, which is not considered suitable for transplanting is recommended to be felled. Mitigation for the felled tree has been included within the compensatory trees for the Western Works Area in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2). The site will be reinstated and handed over for future development of Cha Kwo Ling Promenade Park under a separate project.

 

9.11.4.4          Impacts on Landscape Character Areas affected by the Project are described as follows:

·             LCA1 – Major On-Going Development Landscape: An area of derelict / disturbed land measuring an area of 75,300 square metres and a planting area of 159 square metres will be lost to the Western Works Area.  On completion of the Project an area of 8,500 square meters will be lost to the Trunk Road T2, Ventilation and Tunnel Portal Buildings. A planting area of 15,740 square metres will be provided to compensate the loss of this area. 12 trees will be protected from the impact of the proposed T2 development, 10 trees are recommended for transplanting, and 24 trees which are not suitable for transplanting will be felled.  89 trees will be provided as compensation in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2).

 

·             LCA3 – Transport Corridor:  An approximate planting area of 3,620 square metres will be lost as a result of the Western Works Area. On completion of the Project a planting area of 1,250 square metres will be lost by the Western Ventilation Building. This will be compensated by approximately 4,900 square metres of amenity area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area. Within the works area, 18 trees will be retained and protected, 21 trees are recommended for transplanting and 42 trees which are not suitable for transplanting will be felled. 63 trees will be provided as compensation in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2).

·             LCA4 – Kwun Tong Typhoon Shelter Landscape: A temporary barging will be located at the south eastern corner of the South Apron (LCA1) within the construction phase. For mitigation measures please refer to LR12 above.

 

·             LCA7 – Cha Kwo Ling Reclaimed Industrial Urban Landscape: Within the Eastern Works Area, no planting areas will be lost as the site is currently hard standing. An approximate area of 21,500 square metres of hard standing will be lost for the Eastern Works Area site offices. One tree, a Macaranga tanarius which is not considered suitable for transplanting is recommended to be felled. Mitigation for the felled tree has been included within the compensatory trees for the Western Works Area in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2). The site will be reinstated and handed over for future development of Cha Kwo Ling Promenade Park under a separate project.

 

9.11.4.5          The following Table 9.22 refers to the Landscape Resources impacted by the Project and Table 9.23 refers to the Landscape Character Areas impacted by the Project.


Table 9.22         Residual Impacts on Landscape Resources after Mitigation

ID. No.

Landscape resources

Significance Threshold Before Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Residual Impact After Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Adverse or Beneficial

Construction

Operation

Construction

Operation

Construction

Operation Day1

Operation Year 10

LR6

Amenity Area (Kai Fuk Road / Kwun Tong By-pass)

Moderate

 

Moderate

CM1 to CM2

OM1 to OM5

Moderate

Adverse

Slight

Beneficial

Slight

Beneficial

LR8

Derelict / Disturbed Land (KTD South Apron)

Moderate

Moderate 

CM1 to CM2

OM1 to OM5

Moderate

Adverse

Slight

Beneficial

Slight

Beneficial

LR12

Water Body (Kwun Tong Typhoon Shelter)

Slight

Insubstantial

CM1

OM4

Slight

Adverse

Insubstantial

Insubstantial

LR16

Derelict / Disturbed Land Proposed as Cha Kwo Ling Promenade Park by Others (Cha Kwo Ling Former Public Cargo Working Area)

Slight

 

Insubstantial 

CM1 to CM2

OM4

Slight

Adverse

Insubstantial

Insubstantial

 

Table 9.23         Residual Impacts on Landscape Character Areas after Mitigation

ID. No.

Landscape Character Areas

Significance Threshold Before Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Residual Impact After Mitigation

(Insubstantial, Slight, Moderate, Substantial)

               Adverse or Beneficial

Construction

Operation

Construction

Operation

Construction

Operation Day 1

Operation Year 10

LCA1

LR8, LR10 and LR11

Moderate

Moderate 

CM1 to CM2

OM1 to OM5

Moderate

Adverse

Slight

Beneficial

Slight

Beneficial

LCA3

LR1, LR6 and LR14

Moderate

 

Moderate

CM1 to CM2

OM1 to OM5

Moderate

Adverse

Slight

Beneficial

Slight

Beneficial

LCA4

LR12

Slight

Insubstantial

CM1

OM4

Slight

Adverse

Insubstantial

Insubstantial

LCA7

LR14 and LR16

Slight

 

Insubstantial 

CM1 to CM2

OM4

Slight

Adverse

Insubstantial

Insubstantial

Note:                        The impacts on Landscape Resources and Landscape Character Areas are considered to reduce after 10 years of operation due to the maturity of tree and plant growth.

                  The impacts are considered beneficial.


9.11.5               Assessment of the Significance of Residual Impacts on Visually Sensitive Receivers

9.11.5.1          Residual landscape impacts on Visually Sensitive Receivers are summarised in Tables 9.24 and 9.25 respectively. Impacts on Visually Sensitive Receivers by the Project are described as follows:


Table 9.24      Residual Impacts on Visually Sensitive Receivers after Mitigation (Eastern Works Area)

VSR

ID. No.

Significance Threshold Before Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Residual Impact After Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

Day 1

Operation Year 10

O10

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

O14

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

O16

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

O17

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

O18

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

O19

Slight/ Moderate

N/A

CM1, CM5 to CM8

N/A

Slight

Adverse

N/A

NA

O20

Moderate/

Substantial

N/A

CM1, CM5 to CM8

N/A

Moderate

Adverse

N/A

NA

O22

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

GIC12

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

R3

Slight/ Moderate

N/A

CM1, CM5 to CM8

N/A

Slight

Adverse

N/A

NA

R4

Slight/ Moderate

N/A

CM1, CM5 to CM8

N/A

Slight

Adverse

N/A

NA

R6

Substantial

N/A

CM1, CM5 to CM8

N/A

Moderate/ Substantial

Adverse

N/A

NA

R7

Substantial

N/A

CM1, CM5 to CM8

N/A

Moderate/ Substantial

Adverse

N/A

NA

R8

Substantial

N/A

CM1, CM5 to CM8

N/A

Moderate/ Substantial

Adverse

N/A

NA

R13

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

R14

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

R19

Moderate/

Substantial

N/A

CM1, CM5 to CM8

N/A

Moderate

Adverse 

N/A

NA

RE7

Moderate

N/A

CM1, CM5 to CM8

N/A

Slight/ Moderate

Adverse 

N/A

NA

RE12

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

RE13

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

RE14

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

RE15

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

NA

T1

Slight/

Moderate

N/A

CM1, CM5 to CM8

N/A

Slight

Adverse

N/A

NA

T2

Moderate

N/A

CM1, CM5 to CM8

N/A

Slight/

Moderate

Adverse

N/A

NA

T3

Moderate

N/A

CM1, CM5 to CM8

N/A

Slight/

Moderate
Adverse

N/A

NA

 

Table 9.25      Residual Impacts on Visually Sensitive Receivers after Mitigation:(Western Works Area)

VSR

ID. No.

Significance Threshold Before Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Residual Impact After Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation Day 1

Operation Year 10

O1

Insubstantial

N/A

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

N/A

N/A

O2

Insubstantial

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

O3

Slight

Slight

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

O4

Slight/

Moderate

Slight

CM1, CM5 to CM8

OM1 to  OM5

Slight

Adverse

Insubstantial

Insubstantial

O5

Moderate

Slight

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

Insubstantial

Insubstantial

O6

Moderate

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

Slight

Beneficial

 

Insubstantial

O7

Moderate

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

Slight

Beneficial

 

Insubstantial

O8

Slight

Slight

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

O9

N/A

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

O10

Moderate

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

Insubstantial

Insubstantial

O11

N/A

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight

Beneficial

Insubstantial

O12

Slight/

Moderate

Slight

CM1, CM5 to CM8

OM1 to  OM5

Slight

Adverse

Insubstantial

Insubstantial

O13

Slight

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Slight

Beneficial

Insubstantial

O14

Moderate/

Substantial

Slight/ Moderate

CM1, CM5 to CM8

OM1 to  OM5

Moderate

Adverse

Slight

Beneficial

Insubstantial

O16

Slight/

Moderate

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Slight

Adverse

Insubstantial

Insubstantial

O17

Slight

 

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

O18

Slight/

Moderate

N/A

CM1, CM5 to CM8

N/A

Slight

Adverse

N/A

Insubstantial

O19

Insubstantial

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

Insubstantial

GIC1

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

GIC2

N/A

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

GIC3

Slight

Slight

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

GIC4

Slight

Slight

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

GIC5

Slight

Slight

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

GIC6

N/A

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight

Beneficial

Insubstantial

GIC7

N/A

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight/

Moderate

Beneficial

Slight

Beneficial

GIC8

N/A

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight/

Moderate

Beneficial

Slight

Beneficial

GIC9

N/A

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight

Beneficial

Insubstantial

GIC10

Moderate/

Substantial

Moderate/

Substantial

CM1, CM5 to CM8

OM1 to  OM5

Moderate

Adverse

Moderate

Beneficial

Slight/Moderate

Beneficial

GIC11A

Moderate/

Substantial

Moderate/

Substantial

CM1, CM5 to CM8

OM1 to  OM5

Moderate

Adverse

Moderate

Beneficial

Slight/Moderate

Beneficial

GIC11B

Moderate/

Substantial

Moderate/

Substantial

CM1, CM5 to CM8

OM1 to  OM5

Moderate

Adverse

Moderate

Beneficial

Slight/Moderate

Beneficial

GIC11C

N/A

Moderate/

Substantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Moderate

Beneficial

Slight/Moderate

Beneficial

GIC12

Insubstantial

N/A

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

N/A

N/A

R1

N/A

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

R2

N/A

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

R3

Substantial

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

Moderate/

Substantial

Adverse

Slight

Beneficial

Insubstantial

R4

Substantial

Slight/

Moderate

CM1, CM5 to CM8

OM1 to  OM5

Moderate/

Substantial

Adverse

Slight

Beneficial

Insubstantial

R5

N/A

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

R6

Slight

 

N/A

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

N/A

N/A

R9

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R10

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R11

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R12

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R13

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R14

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R15

N/A

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

R16

N/A

Slight

CM1, CM5 to CM8

OM1 to  OM5

N/A

Insubstantial

Insubstantial

R17

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

R18

Slight

N/A

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

N/A

N/A

RE1

Slight

Slight

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

RE2

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

RE3

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

RE4

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

RE5

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Slight

Adverse

Insubstantial

Insubstantial

RE6

N/A

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight/

Moderate

Beneficial

Slight

Beneficial

RE7

Moderate

N/A

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

N/A

N/A

RE8

N/A

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight/

Moderate

Beneficial

Slight

Beneficial

RE9

N/A

Moderate

CM1, CM5 to CM8

OM1 to  OM5

N/A

Slight/

Moderate

Beneficial

Slight

Beneficial

RE10

N/A

Moderate/

Substantial

CM1, CM5 to CM8

OM1 to  OM5

N/A

Moderate

Beneficial

Slight/Moderate

Beneficial

RE11

Slight

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Insubstantial

Insubstantial

Insubstantial

RE12

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

N/A

RE13

Moderate

N/A

CM1, CM5 to CM8

N/A

Slight/

Moderate

Adverse

N/A

N/A

RE14

Slight

N/A

CM1, CM5 to CM8

N/A

Insubstantial

N/A

N/A

T1

Moderate

Moderate

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

Slight/

Moderate

Beneficial

Slight

Beneficial

T3

Moderate

Insubstantial

CM1, CM5 to CM8

OM1 to  OM5

Slight/

Moderate

Adverse

Insubstantial

Insubstantial


9.11.6               Summary of Residual Impacts on Landscape Resources and Landscape Character Areas

9.11.6.1      Residual Impacts on Landscape Resources and Landscape Character Areas are described in Tables 9.22 and 9.23 respectively.  

9.11.6.2      LR6, amenity area, will experience moderate adverse residual impacts during the construction phase, due to the felling of trees and loss of amenity area to accommodate the Western Works Area and Ventilation Building.  Within the operation phase, impacts are slight and are considered beneficial, due to compensatory roadside tree and shrub planting and construction of approximately 4,900 square metres of amenity area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to Figure 9.11.2). In addition, there will be comprehensive greening to roofs and associated structures of the Tunnel Portal and Ventilation Buildings which help blend the Project into the surrounding landscape (refer to Figures 9.12.1 to 9.12.4). By Year 10 of operation, residual landscape impacts are considered slight and beneficial in nature.

9.11.6.3      LR8, derelict / disturbed land, will experience moderate adverse residual impacts during the construction phase, due to the loss of hard standing to accommodate the Western Works Area.  Within the operation phase, impacts are slight and are considered beneficial, due to compensation by approximately 4,900 square metres of amenity area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to Figure 9.11.2). By Year 10 of operation, residual landscape impacts are considered slight and beneficial in nature.

 

9.11.6.4      LR12, water body, will experience slight adverse residual impacts during the construction phase, due to the barges carrying materials to and from a temporary barging point located on the sea wall.  Within the operation phase the barging point will be removed and impacts on Day 1 and Year 10 are considered insubstantial.

 

9.11.6.5      LR16, derelict / disturbed land in the Eastern Works Area, will experience slight adverse residual impacts during the construction phase, due to loss of one tree, a Macaranga tanarius, and hard standing to accommodate the Eastern Works Area. The tree will be mitigated by trees, shrubs and amenity space created in the Western Works Area by the Project (refer to Figure 9.11.2). Within the operation phase the impacts on Day 1 and Year 10 are considered insubstantial. The site will be reinstated and handed over for future development of Cha Kwo Ling Promenade Park under a separate project.

9.11.7               Impacts on Landscape Character Areas

9.11.7.1      LCA1, derelict / disturbed land, will experience moderate adverse residual impacts during the construction phase, due to the loss of hard standing to accommodate the Western Works Area.  Within the operation phase, impacts are slight and are considered beneficial, due to compensatory roadside tree and shrub planting and compensation by approximately 4,900 square metres of amenity area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to Figure 9.11.2). By Year 10 of operation, residual landscape impacts are considered slight and beneficial in nature.

LCA3, amenity area, will experience moderate adverse residual impacts during the construction phase, due to the felling of trees and loss of amenity area to accommodate the Western Works Area and Ventilation Building.  Within the operation phase, impacts are slight and are considered beneficial, due to compensatory roadside tree and shrub planting and construction of approximately 4,900 square metres of amenity area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to Figure 9.11.2). In addition, there will be comprehensive greening to roofs and associated structures of the Tunnel Portal and Ventilation Building which help blend the Project into the surrounding landscape (refer to Figures 9.12.1 to 9.12.4). By Year 10 of operation, residual landscape impacts are considered slight and beneficial in nature.

9.11.7.2      LCA4, water body, will experience slight adverse residual impacts during the construction phase, due to the barges carrying materials to and from a temporary barging point located on the sea wall.  Within the operation phase the barging point will be removed and impacts on Day 1 and Year 10 are considered insubstantial.

9.11.7.3      LCA7, derelict / disturbed land in the Eastern Works Area, will experience slight adverse  residual impacts during the construction phase, due to loss of one tree, a Macaranga tanarius, and hard standing to accommodate the Eastern Works Area. The tree will be mitigated by trees, shrubs and amenity space created in the Western Works Area by the Project (refer to Figure 9.11.2). Within the operation phase the impacts on Day 1 and Year 10 are considered insubstantial. The site will be reinstated and handed over for future development of Cha Kwo Ling Promenade Park under a separate project.

 

9.11.8               Impacts on Visually Sensitive Receivers

9.11.8.1      At the Eastern Works Area, upon implementation of mitigation measures, VSRs with moderate to substantial residual impacts in the construction phase are R6, R7, R8, R19, and O20. They have close and direct views onto the construction site and are also impacted by additional barges within Victoria Harbour.  There will be no impacts onto the Eastern Works Area after completion of the construction phase, as after the operational stage the site will be handed back to CEDD, where the site is planned to be developed into the Cha Kwo Ling Promenade and Park. VSRs with slight to moderate residual impacts in the construction phase are O19, R3, R4, RE7, T1, T2 and T3 and the remaining VSRs will experience visual impacts of insubstantial significance.

 

9.11.8.2      Upon implementation of mitigation measures, within the Western Works Area in the construction phase, VSRs O14, GIC10, GIC11A, GIC11B, R3 & R4 will experience moderate to substantial residual impacts. This is due to the T2 works area being adjacent to the VSRs in the construction phase. VSRs with slight to moderate residual impacts in the construction phase is O4. O5, O6, O7, O10, O12, O16, O18, RE5, RE7, RE13, T1 and T3 and the remaining VSRs will experience visual impacts of insubstantial significance. As a large area of the KTD Runway Precinct and South Apron will also be under construction at the same time, the residual impacts within the western area are not viewed as adverse and cumulative impacts are not considered to be unacceptable within such a context.

9.11.8.3      Residual visual impacts to a majority of VSRs in the Western Works Area in the operation phase will be of slight to insubstantial significance, except for the VSRs GIC10, GIC11A, GIC11B, GIC11C, and RE10 which will experience moderate visual impacts and VSRs O6, O7, O11, O13, O14, GIC6, GIC7, GIC8, GIC9, R3, R4, RE6, RE8, RE9, and T1 that will experience visual impacts of slight to moderate significance. Despite the presence of physical above ground structures the residual visual impacts could be considered to be positive, since the structures are sensitively designed and extensive greening and tree planting will be in place to improve the overall visual experience of the structures and the surrounding area.

 

9.12                   Cumulative Landscape & Visual Impacts

9.12.1               Concurrent Projects

9.12.1.1      The landscape and visual impacts generated by the Project are assessed in the context of associated impacts of concurrent projects.

9.12.1.2          Previously the Kai Tak Development (KTD) was a disused airport runway. On regenerating the area into a high-end mixed use development, the KTD will create a multifunctional mixed use area, providing various government, occupational, residential and recreational facilities for the Kowloon Bay and Hong Kong areas as a whole.

9.12.1.3          Trunk Road T2 is to be constructed in conjunction with two other Route 6 Projects;  the CKR Route (Western Kowloon – Kai Tak) in the western South Apron area and the Tseung Kwan O - Lam Tin Tunnel Interchange at the eastern end, forming a major transportation route within the Kowloon Peninsula. For the CKR & TKO-LTT Route 6 projects that interface with the Project, separate EIAs have been carried out. The CKR and the Trunk Road T2 connect at the South Apron area running north west to south east directly through the site, while the Trunk Road T2 & TKO LTT will join at the Lam Tin Interchange.

9.12.1.4          The Project and associated buildings will be viewed from the north by the Kowloon Bay commercial area, comprised of newly built high rise commercial developments. From the south and south eastern areas, a cruise terminal, hotels, residential developments, a government hospital, and other related medical centers would be either in construction or are planned. Due to the increase in developments within the area, the Trunk Road T2 will play a vital role in providing public access for the growing urban population and linking the Kai Tak Development to both the immediate local areas and Hong Kong as a whole.

9.12.1.5          The Trunk Road T2 and associated buildings have insubstantial impacts to the area and are in keeping with the contemporary character of the proposed KTD. Trunk Road T2 and associated buildings will be commissioned by the end of 2020, in coordination with both the CKR and TKO-LTT Route 6 projects.

9.12.2               Impacts on Landscape Resources and Character Areas

9.12.2.1          Impacts on existing Landscape Resources and Character Areas will be mitigated in the construction and operation phases.

9.12.2.2          The cumulative impacts of the Project on Landscape Resources and Character Areas in the Western and Eastern Works Areas are listed below:

·             Western Works Area, temporary loss of 75,300 square metres and a permanent loss of 8500 square meters of hard standing, 5029 square meters of planting areas and loss of 66 trees. This will be mitigated by 15,740 square meters of planting areas and 4,900 square meters of Amenity Area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area. Extensive compensatory planting will include 152 trees in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2). Within the operation phase, impacts are slight and are considered beneficial.

 

·             Eastern Works Area: no planting areas will be lost as the site is currently hard standing. An approximate area of 21,500 square metres of hard standing will be lost for the Eastern Works Area site offices. One tree, a Macaranga tanarius which is not considered suitable for transplanting is recommended to be felled. Mitigation for the felled tree has been included within the compensatory trees for the Western Works Area in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2). The site will be reinstated and handed over for future development of Cha Kwo Ling Promenade Park under a separate project. 

 

9.12.2.3          If the Trunk Road T2 and associated buildings were the only developments in the area, the discussed landscape and visual impacts would appear more significant. As the Project is scheduled to be constructed at the same time as many KTD proposed developments, it would appear to blend into the South Apron Development with landscape mitigation measures. As a large area of the KTD Runway Precinct and South Apron will also be under construction at the same time, the residual impacts within the western area are not viewed as adverse and cumulative impacts are not considered to be unacceptable within such a context.

9.12.2.4          On assessing the Project within the context of the CKR & TKO LTT Route 6 Projects and the KTD RODP plan for other proposed developments, and reviewing the cumulative impacts generated by the Trunk Road T2 and associated buildings, it is considered compatible with the surrounding proposed landscape. Mitigation measures will include extensive compensatory tree and shrub planting, sensitive design and architectural detailing, and finishing of built structures and provision of new public amenity area.

9.13         Summary and Conclusions

9.13.1         For the construction phase of the Trunk Road T2 within the Eastern Works Area, there are anticipated to be only very limited impacts, due to the relatively small amount of construction works to be carried out in the Eastern Works Area.  Upon implementation of mitigation measures, VSRs R6, R7, R8 and R19 will be affected due to their being adjacent to the works area throughout the construction phase. However, they will only be affected by excavation of the receiving shaft early in the Project, and later the extraction and removal off-site of the tunnel boring machine. There will be no visual impacts by the Project in the Operation Phase.

9.13.2         For the construction phase of Trunk road T2 within the Western Works Area, upon implementation of mitigation measures, VSRs O14, GIC10, GIC11A, GIC11B, R3 & R4 will experience moderate to substantial residual impacts. This is due to the T2 works area being adjacent to the VSR’s in the developments through the construction phase. VSR’s with slight to moderate residual impacts in the construction phase are O4. O5, O6, O7, O10, O12, O16, O18, RE5, RE7, RE13, T1 and T3 and the remaining VSR’s experience visual impacts of insubstantial significance. As a large area of the KTD Runway Precinct and South Apron will also be under construction at the same time, the residual impacts within the western area are not viewed as adverse and cumulative impacts are not considered to be unacceptable within such a context.

9.13.3         On completion of the Project, the majority of Trunk Road T2 is underground, except for the low rise (+17mPD) Ventilation Building, Tunnel Portal Building and refuse collection building. In the Western Works Area, there will be a temporary loss of 75,300 square metres and a permanent loss of 8500 square meters of hard standing and, 5029 square meters of planting areas will be permanently lost. This will be mitigated by 15,740 square meters of planting areas and 4,900 square meters of Amenity Area as referred to in the report as RE10 Kai Tak South Apron: Amenity Area.  98 trees will be impacted upon. 67 trees are recommended to be felled and 31 are proposed to be transplanted to a location that will be identified at a later stage of the project. Extensive compensatory planting will include 152 trees in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2). In the Eastern Works Area one tree and an approximate area of 21,500 square metres of hard standing will be lost. Mitigation for the felled tree has been included within the compensatory trees for the Western Works Area. The site will be reinstated and handed over for future development of Cha Kwo Ling Promenade Park under a separate project. Details of the landscape proposals for the Western Works Area will be reviewed within the detail design stage. It is considered there will be no substantial adverse landscape and visual impacts by the Project during the operation phase.

9.13.4         For VSRs in the Kowloon Bay area having southern views towards the development, Trunk Road T2 and associated buildings are considered to be in context with the future developments in the South Apron and KTD.

9.13.5         The tunnel portal and refuse collection building would be sensitively designed and proposed to be no higher than 17mPD (Figures 9.12.1 – 9.12.4).  Mitigation measures including vertical greening and tree planting are proposed to be provided.  The overall visual impacts on the surrounding VSRs would not be significant and could be considered positive to a certain extent. 

9.13.6         Due to the intended 2021 completion dates of the Kai Tak Development including the Metro Park, Runway Residential and Hotel Precinct, the Cruise Terminal and Tourism and Leisure Hub, three hospital sites and other government buildings, views from the Victoria Harbour and Southern Kowloon areas will be screened and covered.  Substantial adverse visual impacts are not expected.

9.13.7         Overall, it is considered that the residual landscape and visual impacts of the Project are acceptable with mitigation measures during construction and operation phases.