DP1, DP2, DP5, DP6, & DP12 ¡V ROADS & Associated infrastructure
TABLE OF CONTENTs
11A...... SCHEDULE 2 DP:
PACKAGE A ¡V LANDSCAPE AND VISUAL IMPACTS
11.2A Designated Projects
under Schedule 2 within NDA Project
11.4A Baseline Landscape
Conditions
11.5A Landscape Impact
Assessment
11.6A Landscape and
Visual Mitigation Measures in Construction and Operation Phases
11.7A Prediction of
Significance of Landscape Impacts
11.8A Visual Impact
Assessment
11.9A Cumulative Impacts
from Concurrent Projects
FIGURES
Figure 11.20 Landscape
Resources (LRs)
Figure 11.20a-j Landscape
Resource Enlargement Plans
Figure 11.21 Landscape
Character Areas
Figure 11.22 Landscape
Resource Impacts
Figure 11.22a-j Landscape
Resource Impacts Enlargement Plans
Figure 11.23 Landscape
Character Area Impacts
Figure 11.23a-j Landscape
Character Area Impacts Enlargement Plans
Figure 11.4 Mitigation
Measures
Figure 11.24a-j Mitigation
Measure Enlargement Plans
Figure 11.25a-c Mitigation
Measures Road Sections
Figure 11.26a-b Locations
of Viewpoints in Construction and Operation Phase
Figure 11.27a-b Residential VSRs in Construction and
Operation Phase
Figure 11.28a-b Recreational VSRs in Construction and Operation
Phase
Figure 11.29a-b Occupational VSRs in Construction and
Operation Phase
Figure 11.30a-b Travelling VSRs in Construction and
Operation Phase
Figure 11.31a-b Photomontage
01 ¡V View from Tin Shui Wai Estate Rooftop
Figure 11.32a-b Photomontage
02 ¡V View from Tung Tau Tsuen (Looking North)
Figure 11.33a-b Photomontage 03 ¡V View from Tung Tau Tsuen
(Looking West)
Figure 11.34a-b Photomontage 04 ¡V View from Ngau Hom Shek
Hiking Trail
Figure 11.35a-b Photomontage 05 ¡V View from Proposed Eco
Hiking Trail
Figure 11.36a-b Photomontage 06 ¡V View from Ling To Hiking
Trail
Figure 11.37a-b Photomontage 07 ¡V View from Kau Lee Uk
Tsuen
Figure 11.38a-b Photomontage 08 ¡V View from TSW River
Channel (South)
Figure 11.39a-b Photomontage 09 ¡V View from San Lee Uk
Tsuen Nullah
Figure 11.40a-b Photomontage 10 ¡V View from Yuen Tau Shan
Figure 11.41a-b Photomontage 11 ¡V View from San Sang San
Tsuen
Figure 11.42a-b Photomontage 12 ¡V View from Yick Yuen Road
Figure 11.43a-b Photomontage 13 ¡V View from Tsing Chuen Wai
Hiking Trail
Figure 11.44a-b Photomontage 14 ¡V View from Tsing Chuen Wai
Nullah
Figure 11.45 Broad
Brush Tree Survey
Figure 11.46 Tree Impact and Mitigation Plan
TABLES
Table 11.1 Schedule
2 DPs Associated with HSK NDA (DP1, DP2, DP5, DP6 and DP12)
Table 11.2 Broad
Brush Tree Survey (DP1, DP2, DP5, DP6 and DP12)
Table 11.3 Baseline Landscape Resources (DP1, DP2,
DP5, DP6 and DP12)
Table 11.4 Baseline Landscape Character Areas (DP1,
DP2, DP5, DP6 and DP12)
Table 11.5 Magnitude
of Landscape Change during the Construction and Operation Phases before
Mitigation (DP1, DP2, DP5, DP6 and DP12)
Table 11.6 Proposed Construction Phase Landscape and
Visual Mitigation Measures (DP1, DP2, DP5, DP6 and DP12)
Table 11.7 Proposed Operation Phase
Landscape and Visual Mitigation Measures (DP1, DP2, DP5, DP6 and DP12)
Table 11.8 Significance of Landscape Impacts in
Construction and Operation Phases (DP1, DP2, DP5, DP6 and DP12)
Table 11.9 Sensitivity
of VSRs (DP1, DP2, DP5, DP6 and DP12)
Table 11.10 Magnitude
of Visual Change during the Construction and Operation Phases before Mitigation (DP1, DP2, DP5, DP6 and DP12)
Table 11.11 Significance of Visual Impacts in the
Construction and Operation Phases (DP1, DP2, DP5, DP6 and DP12)
Construction of New Primary Distributor Road (Road P1) (DP1)
Primary Distributor Roads (Dual 2 Standard)
Construction of Eight New Distributor Roads (Roads D1 to D8) (DP2)
District Distributor Roads
Construction of Slip Roads between: Road D8 Junction and Existing Castle Peak Road; Junction of D8/P1 and Junction of D7/P1; and KSWH Connection to Road D3 (DP5)
Construction of Partly Depressed and Partly Decked-over Roads Located at Road D2, Road D4 and Road D6 (DP6)
Construction of Road P1 and Slip-Road from KSWH to Road D3 partly located within the ¡§Conservation Area¡¨ of Yuen Tau Shan (DP12)
Table 11.1A Schedule 2 DPs Associated
with HSK NDA (DP1, DP2, DP5, DP6 and DP12)
Designated Project Reference No. |
Schedule 2 Designated Project |
Work Component/ Reference in RODP |
|
DP1 1 |
Part I, A.1 |
A road which is an expressway, trunk road, primary distributor road or district distributor road including new roads, and major extensions or improvements to existing road |
Construction of new primary distributor road (Road P1) |
DP2 1 |
Part I, A.1 |
A road which is an expressway, trunk road, primary distributor road or district distributor road including new roads, and major extensions or improvements to existing road |
Construction of eight new distributor roads (Roads D1 to D8) |
DP5 1 |
Part I, A.8 |
A road or railway bridge more than 100 m in length between abutments |
Construction of slip roads between: Road D8 Junction and existing Castle Peak Road; Junction of D8/P1 and Junction of D7/P1; and KSWH connection to Road D3 |
DP6 1 |
Part I, A.9 |
A road fully enclosed by decking above and by structure on the sides for more than 100 m |
Construction of partly depressed and partly decked-over roads located at Road D2, Road D4, and Road D6 |
DP12 1 |
Part I, Q.1 |
All projects including new access roads, railways, sewers, sewage treatment facilities, earthworks, dredging works and other building works partly or wholly in an existing or gazetted proposed country park or special area, a conservation area, an existing or gazetted proposed marine park or marine reserve, a site of cultural heritage, and a site of special scientific interest. |
Construction of Road P1 and a slip-road from KSWH to Road D3 partly located within the¡§CA¡¨ of Yuen Tau Shan |
Note:
Outline Zoning Plans (OZPs)
Landscape Features
Landscape Resources
¡P trees of 100 years old or above;
¡P trees of cultural, historical or memorable significance e.g. Fung Shui tree, tree as landmark of monastery or heritage monument, and trees in memory of an important person or event;
¡P trees of precious or rare species;
¡P trees of outstanding form (taking account of overall tree size, shape and any special features) e.g. trees with curtain like aerial roots, trees growing in unusual habitat; or
¡P trees with trunk diameter equal or exceeding 1.0m (measured at 1.3m above ground level), or with height/canopy spread equal or exceeding 25 m.
Broad Brush Tree Survey
Table
11.2A Broad Brush Tree Survey (DP1,2,5,6, and 12) |
||||||||||
Tree no. |
Species |
Chinese Name |
Est. Tree Size
(m) |
Form |
Health |
Amenity Value |
Survival Rate after Transplanting |
Remarks |
||
Overall Height |
Trunk Diameter |
Crown Spread |
||||||||
155E-T1 |
Artocarpus
nitidus subsp. lingnanensis |
®Û¤ì |
7 |
0.30 |
8 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of precious or rare species. |
155E-T2 |
Artocarpus nitidus
subsp. lingnanensis |
®Û¤ì |
6 |
0.15 |
5 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of precious or rare species. |
278-T1 |
Bombax ceiba |
¤ì´Ö |
35 |
1.50 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
278-T2 |
Bombax ceiba |
¤ì´Ö |
20 |
1.00 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
278D-T1 |
Ficus
microcarpa |
²Ó¸º_ |
16 |
1.00 |
20 |
Good |
Fair |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
403-T1 |
Ficus microcarpa |
²Ó¸º_ |
12 |
1.00 |
12 |
Good |
Good |
High |
Med |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
407B-T1 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.00 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
407B-T2 |
Ficus elastica |
¦L«×¾ó¾ð |
12 |
1.00 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
743-T1 |
Bombax ceiba |
¤ì´Ö |
16 |
1.10 |
14 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
785A-T1 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
18 |
0.90 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T2 |
Eucalyptus citriodora |
ÂfÂcÑÛ |
18 |
0.80 |
12 |
Fair |
Fair |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T3 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
25 |
1.00 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T4 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
18 |
1.00 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
785A-T5 |
Eucalyptus
citriodora |
ÂfÂcÑÛ |
22 |
0.80 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
787A-T1 |
Ficus
microcarpa |
²Ó¸º_ |
8 |
1.56 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
949-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
11 |
1.50 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
978-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
20 |
3.00 |
20 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
995-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
13 |
1.50 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1071A-T1 |
Melaleuca
cajuputi subsp. Cumingiana |
¥Õ¤d¼h |
12 |
1.00 |
7 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
1077-T1 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.00 |
18 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size. |
1213A-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
15 |
1.50 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
A0017-T1 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.50 |
12 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1202-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
12 |
1.00 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
1202-T2 |
Ficus elastica |
¦L«×¾ó¾ð |
12 |
1.00 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
1203-T1 |
Ficus
microcarpa |
²Ó¸º_ |
14 |
1.00 |
15 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1213-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
15 |
1.50 |
17 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
1213-T2 |
Ficus elastica |
¦L«×¾ó¾ð |
16 |
3.00 |
25 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
201-T1 |
Ficus
microcarpa |
²Ó¸º_ |
13 |
2.00 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
202-T1 |
Ficus
microcarpa |
²Ó¸º_ |
14 |
1.20 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
203-T1 |
Ficus microcarpa |
²Ó¸º_ |
13 |
1.20 |
16 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
203-T2 |
Ficus
microcarpa |
²Ó¸º_ |
15 |
1.50 |
16 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
203-T3 |
Ficus
microcarpa |
²Ó¸º_ |
15 |
1.50 |
16 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
203-T4 |
Ficus
microcarpa |
²Ó¸º_ |
18 |
1.00 |
12 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
207-T1 |
Ficus
microcarpa |
²Ó¸º_ |
15 |
1.50 |
20 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
207-T2 |
Ficus
microcarpa |
²Ó¸º_ |
15 |
1.50 |
20 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
207-T3 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.20 |
15 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
34-T1 |
Ficus
microcarpa |
²Ó¸º_ |
14 |
1.50 |
20 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good
form and size among its own tree species. |
633-T1 |
Bombax ceiba |
¤ì´Ö |
20 |
1.00 |
14 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
633-T2 |
Ficus
microcarpa |
²Ó¸º_ |
12 |
1.20 |
16 |
Good |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size, this particular tree has very good form
and size among its own tree species. |
756-T1 |
Ficus benjamina |
««¸º_ |
16 |
1.00 |
18 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
962-T1 |
Ficus elastica |
¦L«×¾ó¾ð |
13 |
1.50 |
16 |
Fair |
Good |
High |
Low |
Potentially
registrable as OVT: tree of large size |
Table
11.2A Broad Brush Tree Survey (DP1,2,5,6, and 12) (cont.) |
||||||||||
Tree no. |
Species |
Chinese Name |
Est. Tree Size
(m) |
Form |
Health |
Amenity Value |
Survival Rate after Transplanting |
Remarks |
||
Overall Height |
Trunk Diameter |
Crown Spread |
||||||||
59D-T2 |
Aquilaria
sinensis |
¤g¨I» |
10 |
0.22 |
7 |
Fair |
Good |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
155E-T4 |
Aquilaria sinensis |
¤g¨I» |
5 |
0.15 |
3 |
Fair |
Good |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
237A-T1 |
Aquilaria
sinensis |
¤g¨I» |
5 |
0.15 |
3 |
Good |
Good |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
237A-T2 |
Aquilaria
sinensis |
¤g¨I» |
3 |
0.10 |
2 |
Good |
Good |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
456-T1 |
Aquilaria
sinensis |
¤g¨I» |
8 |
0.15 |
5 |
Fair |
Good |
Med |
Low |
The
tree species is protected under local legislation, the Protection of Endangered
Species of Animals and Plants Ordinance (Cap. 586). |
456-T2 |
Aquilaria
sinensis |
¤g¨I» |
10 |
0.20 |
6 |
Fair |
Good |
Med |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
456-T3 |
Aquilaria
sinensis |
¤g¨I» |
10 |
0.20 |
6 |
Fair |
Good |
Med |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
1212-T1 |
Aquilaria sinensis |
¤g¨I» |
8 |
0.25 |
3 |
Fair |
Good |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
1213-T3 |
Ailanthus
fordii |
±`ºñ¯äÝÏ |
10 |
0.16 |
3 |
Fair |
Good |
High |
Low |
The
tree species is scheduled under the Forests And Countryside Ordinance (Cap.
96). |
1213-T4 |
Ailanthus
fordii |
±`ºñ¯äÝÏ |
10 |
0.22 |
3 |
Fair |
Good |
High |
Low |
The
tree species is scheduled under the Forests And Countryside Ordinance (Cap.
96). |
34A-T1 |
Aquilaria
sinensis |
¤g¨I» |
8 |
0.25 |
3 |
Fair |
Fair |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
34A-T2 |
Aquilaria
sinensis |
¤g¨I» |
10 |
0.25 |
3 |
Fair |
Fair |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
34A-T3 |
Aquilaria
sinensis |
¤g¨I» |
10 |
0.25 |
3 |
Fair |
Poor |
Med |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
34A-T4 |
Aquilaria
sinensis |
¤g¨I» |
8 |
0.25 |
4 |
Fair |
Good |
High |
Low |
The
tree species is protected under local legislation, the Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586). |
Table 11.2A Broad
Brush Tree Survey (cont.)
Tree no. |
Species |
Chinese Name |
Est. Tree size (m) |
Form |
Health |
Amenity Value |
Survival Rate after Transplanting |
Remarks |
||
Overall Height |
Trunk Diameter |
Crown Spread |
||||||||
181-T1 |
Celtis sinensis |
¦µ¾ð |
12 |
0.70 |
10 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
224-T1 |
Bombax ceiba |
¤ì´Ö |
15 |
0.65 |
10 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
237C-T1 |
Cinnamomum
camphora |
¼Ì |
7 |
0.50 |
8 |
Good |
Good |
High |
Low |
This
particular tree has very good form. |
278D-T2 |
Bombax ceiba |
¤ì´Ö |
20 |
0.60 |
12 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
640A-T1 |
Bombax ceiba |
¤ì´Ö |
13 |
0.50 |
10 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
640A-T2 |
Bombax ceiba |
¤ì´Ö |
15 |
0.60 |
12 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
688D-T1 |
Michelia x alba |
¥ÕÄõ |
20 |
0.55 |
10 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
688D-T2 |
Michelia x alba |
¥ÕÄõ |
20 |
0.30 |
7 |
Fair |
Good |
High |
Low |
This
particular tree has very large size among its own tree species. |
688G-T1 |
Ficus religiosa |
µÐ´£¾ð |
12 |
0.80 |
10 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
914-T1 |
Homalium
hainanensis |
¬õªá¤Ñ®Æ¤ì |
13 |
0.45 |
8 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
914-T2 |
Homalium
hainanensis |
¬õªá¤Ñ®Æ¤ì |
12 |
0.35 |
6 |
Good |
Good |
High |
Low |
This
particular tree has very good form and size among its own tree species. |
Baseline Landscape and Visual Conditions
Southern Project Area
Western Project Area
Eastern Project Area
Sensitivity of LRs and LCAs
¡P Quality of the LRs;
¡P Maturity of the LRs;
¡P Rarity of special landscape elements;
¡P Importance of the Landscape Resource in local and regional context; and
¡P Ability of the landscape to accommodate change
Table 11.3 Baseline Landscape Resources (DP1, DP2,
DP5, DP6 and DP12)
Id. No. |
Landscape
Resource (LR) |
Baseline Area |
Description |
||||
Quality &
Maturity (High, Medium, Low) |
Rarity (High, Medium, Low) |
Importance (Local, Regional, National, Global) |
Ability to Accommodate Change (Low, Medium, High) |
Sensitivity (Low, Medium, High) |
|||
LR
2 ¡V Hillside Woodland |
146.8 ha |
|
|||||
2.2 |
Ngau Hom |
2.8 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises a large
wooded hillside rising to 46.9 m located to the north of Ngau Hom and Sha
Kong Wai villages and to the east of San Hing Tsuen village. Numerous graves are found scattered
about the hillside.
Vegetation is comprised of mature and semi-mature tree canopies of
various species forming a mostly interconnected tree canopy. Two Important
Trees, 34A-T1 and 34A-T4, are located in this LR. A total of approx. 130
trees have been identified within this LR; the dominant species includes Celtis sinensis, Macaranga tanarius var.
tomentosa, and Dimocarpus longan. |
|||||||
Zoning: The extent of the LR
lies within areas zoned as ¡§Green Belt¡¨ (GB) and ¡§Village Type Development¡¨
(V) under the Lau Fau Shan & Tsim Bei Tsui OZP S/YL-LFS/7 |
|||||||
2.3 |
Hang Hau Tsuen |
0.3 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises two
contiguous wooded hillsides rising to 38.6 m and 36.5 m located to the south
of Hang Hau Tsuen with a section
of Deep Bay Road cutting across the northern extents. Numerous graves are found scattered
about the hillsides.
Vegetation is comprised of mature and semi-mature tree canopies of
various species forming an interconnected tree canopy. One Important Tree, 59D-T2, is located
on the edge of the LR. Identified
as Aquilaria sinensis, the tree species
is protected under local legislation, the Protection of Endangered Species of
Animals and Plants Ordinance (Cap. 586). A total of approx. 12 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, and Celtis
sinensis. |
|||||||
Zoning: The majority of the LR
lies within area zoned as ¡§Residential (Group D)¡¨ (R(D)) under the Ha Tsuen
OZP S/YL-HT/10. The area of this
LR located to the north of Deep Bay Road is zoned CPA under the same OZP. |
|||||||
2.4 |
Ngau
Hom Shek |
26.3 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises the
contiguous wooded hillsides located to the east of the Shenzhen Bay Bridge
and KSWH that effectively form the northern green backdrop of the
Project. Numerous graves are
found scattered about the hillsides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy. Three
Important Trees, 181-T1, 237A-T1, and 237A-T2, are located in this LR. The identified tree species include Celtis sinensis and Aquilaria sinensis and have very good
form and size or are protected
under local legislation, the Protection of Endangered Species of Animals and
Plants Ordinance (Cap. 586). A total of approx. 1,468 trees have been identified
within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Lophostemon confertus, and
Celtis sinensis. |
|||||||
Zoning: The majority of the LR
lies within area zoned GB under the Ha Tsuen OZP S/YL-HT/10, with smaller patches
located at the base of the northerly and westerly slopes zoned ¡§Agriculture¡¨
(AGR). |
|||||||
2.6 |
Tung Tau Tsuen |
4.4 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises two
contiguous wooded hillsides rising to 28.3 m and 24.2 m located north of Hong
Mei Tsuen and Tung Tau Tsuen. The
hillsides lie immediately adjacent to Yeung Hau Temple, a Declared
Monument. Numerous graves are
found scattered about the hillsides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy.
Six Important Trees, 155E-T1, 155E-T2, 155E-T4, 203-T1, 203-T2, and
203-T3, are located within this LR.
The identified tree species include Artocarpus nitidus subsp. lingnanensis and Aquilaria sinensis and are protected
under local legislation, the Protection of Endangered Species of Animals and
Plants Ordinance (Cap. 586) or are potentially registrable as OVT due to
large size and good form and size among its own tree species. A total of
approx. 446 trees have been identified within this LR; the dominant species
includes Macaranga tanarius var.
tomentosa, Dimocarpus longan, Clausena lansium, Litchi chinensis, and
Artocarpus heterophyllus. |
|||||||
Zoning: The north facing
slopes of the hillsides are zoned ¡§Comprehensive Development Area¡¨ (CDA) and
the south-facing hillsides are zoned V, both under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
2.7 |
Ha Tsuen Road |
0.6 ha |
High |
Medium |
Local |
Medium |
High |
This LR comprises a lone,
isolated wooded hillside rising to 13.2 m located north of Ha Tsuen Road and
surrounded by open storage land-uses on all sides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy. A
total of 85 trees have been identified within this LR; the dominant species
includes Litchi chinensis. |
|||||||
Zoning: The hillside is zoned
GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.8 |
Ha Tsuen |
1.3 ha |
Medium |
Medium |
Local |
Low |
Medium |
This LR comprises a
lone, isolated wooded hillside rising to 35.9 m located north of the Sewage
Treatment Plant and disconnected from the northern wooded hillside ridgeline
of Ngau Hom Shek by open storage land-uses on all sides. The top of the hillside has been
de-vegetated and levelled to make room for industrial land uses. Vegetation is comprised of mature and
semi-mature tree canopies of various species forming an interconnected tree
canopy. A total of approx.108 trees have been identified within this LR. |
|||||||
Zoning: The hillside is zoned
GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.9 |
Yuen Tau Shan |
101.7 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises the
contiguous wooded hillsides located to the west of the Shenzhen Bay Bridge and
KSWH that effectively form the western ridgeline of the Project area. Numerous graves are found scattered
about the hillsides.
Vegetation is comprised of mature and semi-mature tree canopies of
various species forming an interconnected tree canopy. A total of approx.4,804 trees have been
identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Eucalyptus
sp., Acacia confusa,
Leucaena leucocephala, and Dimocarpus longan. |
|||||||
Zoning: The majority of the LR
lies within area zoned ¡§CA¡¨ under the Ha Tsuen OZP S/YL-HT/10, Ping Shan OZP S/YL-PS/16, &
Lam Tei & Yick Yuen OZP S/TM-LTYY/8.
Additional areas lie within areas zoned GB under the aforementioned
OZPs, and a small patch located at the foothills facing Deep Bay is zoned AGR
under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.11 |
Kau Lee Uk Tsuen |
5.5 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises of a
hillside area located to the west Kau Lee Uk Tsuen and rises 38.1 m in
elevation. Numerous graves are
found scattered about the hillsides. Vegetation is comprised of
mature and semi-mature tree canopies of various species forming an
interconnected tree canopy. Three
Important Trees, 456-T1, 456-T2, and 456-T3 are located within this LR. The identified tree species are Aquilaria sinensis and are protected under local legislation,
the Protection of Endangered Species of Animals and Plants Ordinance (Cap.
586). A total of approx. 264 trees have been identified within this LR; the
dominant species includes Litchi chinensis,
Macaranga tanarius var. tomentosa, Clausena lansium, Dimocarpus longan, and
Celtis sinensis. |
|||||||
Zoning: The hillside lie
within areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
2.12 |
San Sang Tsuen |
2.9 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises
three discontinuous hillside areas located to the west and northwest San Sang
Tsuen, rising to elevations of 18 m, 24.5 m, 28.3 m. Numerous graves are found
scattered about the hillsides.
Vegetation is comprised of mature and semi-mature tree canopies of
various species forming an interconnected tree canopy. One Important Tree,
633-T2, is located within the LR; it is identified as Ficus macrocarpa. A
total of approx. 156 trees have been identified within this LR; the dominant
species includes Macaranga
tanarius var. tomentosa and Aleurites moluccana. |
|||||||
Zoning: The easternmost
hillsides lies within area zoned G/IC, and the two westerly hillsides lie
within areas zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
LR 3 ¡V Hillside Shrub & Grassland |
51.0 ha |
||||||
3.1 |
Ngau Hom |
0.5 ha |
Medium |
Medium |
Local |
Low |
High |
This LR comprises a
large open hillside conjoined to LR2.2 - Ngau Hom Woodland. Here, nearly all trees have been removed
resulting in succession of herbaceous species and grassland. Numerous graves are found scattered
about the area. A total of approx. 8 trees have been identified within this
LR; the dominant species includes Celtis
sinensis, Macaranga tanarius var. tomentosa, and Dimocarpus longan. |
|||||||
Zoning: The extent of the LR
lies within areas zoned GB under the Lau Fau Shan & Tsim Bei Tsui OZP
S/YL-LFS/7. |
|||||||
3.3 |
Ngau Hom Shek |
16.7 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises various
hillside meadows located within the extents of LR2.3 - Ngau Hom Shek
Woodland. Here, there are few
trees and the dominant vegetation consists of successional herbaceous plants
and grassland species. Numerous
graves are found scattered about the areas. One Important Tree, 237C-T1 is
located within this LR. The
identified tree species is Cinnamomum
camphora and is identified as having very good form for trees of this
species. A total of approx. 389 trees have been identified within this LR;
the dominant species includes Lophostemon
confertus, Acacia auriculiformis, and Tetradium glabrifolium. |
|||||||
Zoning: The LR lies within
area zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
3.4 |
Yuen Tau Shan |
32.7 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises
various hillsides located scattered amongst the extents of LR2.9 ¡V Yuen Tau
Shan Woodland. These hillsides
comprise part of the western ridgeline of the Project area, and comprise
dense woodland stands and more open, hillside shrub land. In this LR, there are few trees and
the dominant vegetation consists of successional herbaceous plants and
grassland. Numerous graves are
found scattered about the various hillsides. A total of approx. 213 trees
have been identified within this LR; the dominant species includes Leucaena leucocephala and Macaranga tanarius
var. tomentosa. |
|||||||
Zoning: The majority of the LR
lies within area zoned CA under the Ha Tsuen OZP S/YL-HT/10, Ping Shan OZP S/YL-PS/16, &
Lam Tei & Yick Yuen OZP S/TM-LTYY/8.
Additional areas lie within areas zoned GB under the aforementioned
OZPs, and a small patch located at the foothills facing Deep Bay is zoned AGR
under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
3.5 |
Kau Lee Uk Tsuen |
1.1 ha |
Medium |
Medium |
Local |
Low |
High |
This LR comprises
hillside meadows located within the extents of LR2.10 - Hung Uk Tsuen
Woodland. Here, there are few
trees and the dominant vegetation consists of successional herbaceous plants
and grassland species. Numerous
graves are found scattered about the area. A total of approx. 24 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa and Celtis
sinensis. |
|||||||
Zoning: The hillsides lie within
areas zoned GB under the Ping Shan OZP S/YL-PS/16. |
|||||||
LR 4 ¡V Low-lying Woodland/Plantation |
22.2 ha |
||||||
4.1 |
Tin Ying Road &
Tin Wah Road |
3.8 ha |
High |
Medium |
Local |
Low |
High |
This LR primarily consists
of second-growth woodland with mature and semi-mature trees forming an
interlocking tree canopy. It
presently serves as a green buffer between TSW Promenade and the industrial
storage land uses west of the river.
It is located west of Tin Ying Road and south of Tin Wah Road. A total
of approx. 845 trees have been identified within this LR; the dominant
species includes Acacia
auriculiformis, Melia azedarach, Leucaena leucocephala, Eucalyptus
camaldulensis, Hibiscus tiliaceus, and Ficus benjamina. |
|||||||
Zoning: This LR resides within
area zoned CDA under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
4.3 |
Tin Ying Road &
Ping Ha Road |
1.6 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of tree
and scrubland vegetation adjacent to an existing nullah, and serves as a
green buffer between the nullah and open-air storage areas to the north and
south. The LR is bound to east
and west by Ping Ha Road and Tin Ying Road, respectively. A total of approx.
358 trees have been identified within this LR; the dominant species includes Acacia confusa, Eucalyptus sp., Acacia auriculiformis, and Hibiscus
tiliaceus. |
|||||||
Zoning: This LR falls on areas
that are zoned Open Space (O) on the north side of the nullah and
Undetermined (U) on the south side of the nullah. Both fall under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
4.8 |
San Sang San Tsuen |
15.8 ha |
High |
Medium |
Regional |
Low |
High |
This LR consists of
two extremely large, woodland and scrubland areas located adjacent to a
similar sized area of land used for agriculture. This LR is located between the Kong
Sam Western Highway and the WRL
alignment, and south of San Sang San Tsuen and San Sang Tsuen villages. It primarily consists of two
continuous, large areas. The
northern area is immediately south of the aforementioned village areas, and
consists of stands of mature and semi-mature trees and open scrubland and
grassland areas. All the
vegetation is of relatively high quality. The southern area is located south of
the large agricultural zone LR 6.9 and is bisected by a small drainage
channel. Vegetation here is similar
to the above. These two areas are
generally continuous, open, unspoiled, and generally of high quality. Five Important Trees, 688D-T1, 688-T2,
and 688G-T1, 914-T1 and 914-T2 are located within this LR. Identified as Michelia x alba, Ficus
religiosa, and Homalium hainanensis,
the tree species are recognised for their very good form and large size among
their own tree species A total of approx. 626 trees have been identified
within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, Leucaena leucocephala, and
Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The northern area of
this LR largely resides within areas zoned R(D), with a very small area
residing within area zoned V, both under the under the Ha Tsuen OZP
S/YL-HT/10. The majority of the
LR, both north and south areas, reside within areas zoned GB under the Ping
Shan OZP S/YL-PS/16. A small
portion of the southern LR area falls within land zoned U under the Ping Shan
OZP S/YL-PS/16. |
|||||||
4.11 |
Tin Sam |
0.6 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR primarily consists
of scrubland as well as a woodland stand adjacent to existing residential
developments in Tin Sam. This LR
is located to the west of the intersection of Tin Ha Road and Hung Leong
Road. The vegetation is generally
of good quality consisting of mature and semi-mature trees forming an
interlocking tree canopy and open area of scrubland with herbaceous and
grassland species. A total of approx. 34 trees have been identified within
this LR; the dominant species includes Dimocarpus longan. |
|||||||
Zoning: This LR resides within
three zoning designations under two OZPs. The northern area falls under land
zoned V and the middle area under R(C) under the Ping Shan OZP S/YL-PS/16,
and the southern area under land zoned R(B) under the Lam Tei & Yick Yuen
OZP S/TM-LTYY/8. |
|||||||
4.12 |
Powerline Pylon |
0.3 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of
the area surrounding an electrical transmission wire pylon. Vegetation has grown to include scrubland
and herbaceous species around the base of the pylon supports. It is located south of Yick Yuen Tsuen
and lies adjacent to a drainage nullah. A total of approx. 22 trees have been
identified within this LR; the dominant species includes Bauhinia purpurea and Leucaena leucocephala. |
|||||||
Zoning: This LR resides within
areas zoned R(C) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 5 ¡V Low-lying Shrub & Grassland |
37.0 ha |
||||||
5.2 |
Sha Kong Wai Tsai |
7.2 ha |
Low |
Low |
Local |
Medium |
Low |
This LR primarily
consists of scrubland with scattered carparks and open-air storage buildings
throughout. It is located west of
Tin Ying Road and north of Tin Wah Road, and forms a vegetative buffer
between the roadways and the rural housing found in Sha Kong Wai Tsai to the
west. A total of approx. 316 trees have been identified within this LR; the
dominant species includes Leucaena
leucocephala, Eucalyptus sp., Ficus microcarpa, Ficus virens, Hibiscus
tiliaceus, and Ficus benjamina. |
|||||||
Zoning: The majority of this
LR resides within either GB or Residential (Group C) (R(C)) zoning
designation under the Lau Fau Shan & Tsim Bei Tsui OZP S/YL-LFS/7. The southeastern corner of this LR
falls within G/IC zoning under the TSW OZP S/TSW/12. |
|||||||
5.3 |
Fung Kong Tsuen |
9.5 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR primarily
consists of scattered scrubland areas with open grassland or bare patches of
dirt interspersed between. It
presently serves as a transition between LR 2.4 - Ngau Hom Shek Woodland to
the west and large, contiguous industrial and open-air storage areas serviced
by Ping Ha Road to the east. Vegetation is generally of good quality and the
grassland forms the base of the hillside in this area. A total of approx. 197
trees have been identified within this LR; the dominant species includes Leucaena leucocephala and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This LR resides
primarily within areas zoned GB, but also within CDA, V, and Recreation (REC)
under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.5 |
San Wai |
1.6 ha |
High |
Medium |
Local |
Medium |
High |
This LR consists of
four grassland patches located within the vicinity of San Wai, Sik Kong
Tsuen, and Tseung Kong Wai villages.
Vegetation is generally of good quality and the grassland forms green
backdrops set against rural village housing. Three Important Trees, 278-T1,
278-T2 and 278D-T1 are located in this LR. The identified tree species include Bombax ceiba and Ficus microcarpa and are potentially registrable as OVTs due to
large tree size and very good form among trees of these species. A total of
approx. 68 trees have been identified within this LR; the dominant species
includes Dimocarpus longan,
Macaranga tanarius var. tomentosa, and
Clausena lansium. |
|||||||
Zoning: This LR resides within
areas zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.6 |
San Lee Uk Tsuen |
2.6 ha |
High |
Medium |
Local |
Low |
High |
This LR consists of a large
woodland stand and scrubland located south of Sha Chau Lei Road and the
nullah, and north of the WRL alignment.
The vegetation consists of mature and semi-mature trees forming an
interlocking tree canopy with dense understory, or more open areas of scrubland
with herbaceous and grassland species.
This LR is continuous, open, unspoiled, and generally of high quality.
A total of approx. 91 trees have been identified within this LR; the dominant
species includes Leucaena
leucocephala, Dimocarpus longan, Ficus microcarpa, and Celtis sinensis. |
|||||||
Zoning: This LR resides within
areas zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.7 |
San Sang Tsuen |
0.5 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of a small
grassland interspersed between rural residential developments in San Sang
Tsuen. As continual expansion of
village housing occurs, it is likely that this area will be subsumed by
development in short time. |
|||||||
Zoning: This LR resides within
areas zoned V and R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
5.8 |
Chung Uk Tsuen |
1.6 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR primarily
consists of an open area of scrubland vegetation and several stands of mature
woodlands and individual trees. The
LR is circumscribed on three sides by rural village housing and is bound to
the east by a nullah drainage channel.
This LR is located south of Castle Peak Road and south of Chung Uk
Tsuen. The character of
vegetation is generally of good quality in that the trees are mature and
semi-mature species. As continual
expansion of village housing occurs, it is likely that this area will be
subsumed by development. A total of approx. 115 trees have been identified
within this LR; the dominant species includes Leucaena leucocephala, Celtis sinensis, Artocarpus
heterophyllus, and Clausena lansium. |
|||||||
Zoning: This LR resides within
areas zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
5.9 |
Yick Yuen Tsuen |
12.4 ha |
High |
Medium |
Regional |
Medium |
High |
This LR consists of an
extremely large, woodland and scrubland area. This LR is located west of Yick Yuen
Tsuen and east of the Kong Sam Western Highway. It consists of continuous, large areas
vegetation including stands of mature and semi-mature trees and open
scrubland and grassland areas.
All the vegetation is of relatively high quality. This LR is generally continuous, open,
and of high quality. A total of approx. 503 trees have been identified within
this LR; the dominant species includes Leucaena leucocephala, Dimocarpus longan, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This LR resides within
areas zoned GB and R(D) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
5.10 |
Tuen Mun San Tsuen |
1.0 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of
scrubland and grassland vegetation patches circumscribed by development on
all sides. It is located east of
Castle Peak Road, immediately behind Lin Wah Hall, north of Lam Tei Main
Street, and adjacent to The Sherwood residential development as well as
numerous village housing settlements.
Two smaller grasslands are located to the south of Botania Villa and
east of Tuen Mun San Tsuen. As
continual expansion of village housing occurs, it is likely that these areas
will be subsumed by development in short time. A total of approx. 60 trees
have been identified within this LR; the dominant species includes Archontophoenix alexandrae, Dimocarpus
longan, Clausena lansium, and Leucaena leucocephala. |
|||||||
Zoning: This LR resides within
areas zoned V, GB, and CDA under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
5.11 |
Tsing Chuen Wai |
0.4 ha |
Low |
Low |
Local |
High |
Low |
This LR primarily
consists of low-quality scrubland interspersed between rural residential
developments and the KSWH. As continual
expansion of village housing occurs, it is likely that this area will be
subsumed by development in short time. A total of approx. 27 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala. |
|||||||
Zoning: This LR resides within
areas zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 6 ¡V Vegetation on Agricultural Land |
37.5 ha |
||||||
6.1 |
Sha Kong Wai |
1.2 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of numerous
small plots with stands of mature trees and buffer vegetation
throughout. It is located just
east of Sha Kong Wai village and surrounded by rural residential housing on
three sides. It is adjacent to LR
4.1 - Sha Kong Wai Tsai Low-lying Woodland and Scrubland. A total of approx.
86 trees have been identified within this LR; the dominant species includes Leucaena leucocephala, Ficus benjamina, and Ficus microcarpa. |
|||||||
Zoning: This LR resides within
two different zoning designations; land zoned V and GB under the Lau Fau Shan & Tsim Bei Tsui OZP
S/YL-LFS/7. |
|||||||
6.3 |
Ha Tsuen |
3.7 ha |
Low |
Low |
Local |
High |
Low |
This LR comprises five
individual, non-congruous plots of land actively being used in agricultural
production. They are located near
Tseung Kong Wai, Ski Kong Wai, San Wai, and Ha Tsuen Shi and generally are
bordered by rural village housing and vegetation. As this LR is essentially located in
leftover spots around village housing, as continual expansion of village
housing occurs it is likely that this area will be subsumed by development. A
total of approx. 66 trees have been identified within this LR; the dominant
species includes Eucalyptus
torelliana, Dimocarpus longan, and Melaleuca cajuputi subsp. cumingiana. |
|||||||
Zoning: This LR largely
resides within land zoned V under the Ha Tsuen OZP S/YL-HT/10, with very
small areas falling under REC or GB designation. |
|||||||
6.5 |
Shek Po Tsuen |
2.4 ha |
Low |
Low |
Local |
High |
Low |
This LR comprises five
individual, non-congruous plots of land actively used in agricultural
production. They are located in
the vicinity of Shek Po Tsuen to the north, west and south, as well as two
larger sized plots located to the west on either side of the WRL
alignment. The plots surrounding
Shek Po Tsuen occupy leftover spaces around village housing, and as continual
expansion of village housing occurs, it is likely that this area will be
subsumed by development. The two
plots located to the west are located adjacent to the large Low-lying
Woodland/Plantation LR4.12. A total of approx. 82 trees have been identified
within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, and Roystonea regia. |
|||||||
Zoning: This LR resides wholly
within land zoned V and R(D) under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
6.6 |
San Sang San Tsuen |
19.3 ha |
High |
Medium |
Local |
Low |
High |
This LR comprises
three individual, non-congruous plots of land actively used in agricultural
production. They are located to the
south of San Sang San Tsuen and are bounded by the KSWH to the west and the
WRL to the east. The north is
bound by LR4.13 ¡V San Sang San Tsuen Low-lying Scrub and Woodland, a
high-amenity scrubland. This LR
is the largest contiguous area of land being actively used for agriculture
within the Project area. It
consists of agricultural plots of various sizes growing a variety of crops,
numerous stands of trees varying in age, rural housing and buildings of varying
quality and functions, areas of woodland and scrubland between plots and
buildings. It is regarded to have
a high amenity value due to its intensive use and large size. Six Important Trees, 785A-T1, 785A-T2,
785A-T3, 785A-T4, 785A-T5, & 787A-T1 are located within this LR. The identified tree species include Eucalyptus citriodora and Ficus microcarpa and are potentially
registrable as OVTs due to tree of large size and good form. A total of
approx. 651 trees have been identified within this LR; the dominant species
includes Dimocarpus longan, Mangifera
indica, Artocarpus heterophyllus, and Macaranga tanarius var.
tomentosa. |
|||||||
Zoning: This LR resides mostly
within areas zoned GB under the Ping Shan OZP S/YL-PS/16. A small corner of the southeastern LR
falls within area zoned U under the Ping Shan OZP, and a very miniscule area
of the LR falls within land zoned R(D) under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
6.7 |
Ling To |
3.2 ha |
High |
Medium |
Regional |
Low |
High |
This LR comprises plots
of land actively used in agricultural production in the vicinity of Ling To
Tsz. This LR located primarily to
the west of the KSWH within a settled valley leading up to the temple, and
consequently is bound by hillsides of LR2.9 ¡V Yuen Tau Shan Woodland to the
south and LR3.4 ¡V Yuen Tau Shan Natural Hillside Scrub and Grassland to the
north. It consists of
agricultural plots of various sizes growing a variety of crops, numerous
stands of trees varying in age, areas of buffer woodland and scrubland between
plots and buildings. Due to the
contextual location and the character of the area leading up to the temple,
it is regarded to have a high amenity value. A total of approx. 180 trees
have been identified within this LR; the dominant species includes Ficus benjamina, Dimocarpus longan, and Roystonea regia. |
|||||||
Zoning: This LR resides wholly
within land zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
6.9 |
Wo Ping San Tsuen
& Nai Wai |
0.7 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR primarily consists
of two medium-sized agricultural plots, buffer vegetation, and several stands
of trees. The LR is circumscribed
on three sides by rural village housing and the easterly area is located
north of Shun Tat Street. The
character of vegetation is generally of good quality in that the trees are
mature and semi-mature species.
As continual expansion of village housing occurs, it is likely that
this area will be subsumed by development. The westerly LR is located east of Nai
Wai village and is completely circumscribed by village housing. Being that this LR is located in
leftover spots around village housing, as continual expansion of village
housing occurs it is likely that this area will be subsumed by development. A
total of approx. 24 trees have been identified within this LR; the dominant
species includes Leucaena
leucocephala, Celtis sinensis, Clausena lansium, Litchi chinensis, Artocarpus
heterophyllus, Macaranga tanarius var. tomentosa, Sterculia nobilis, Ficus benjamina, and Archontophoenix alexandrae. |
|||||||
Zoning: This LR resides within
areas zoned V, GB, and R(D) under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
6.10 |
Tin Sam |
4.5 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of continuous
agricultural plots located to the southwest of Tin Sam village. Interspersed throughout this
agricultural area are numerous trees as well as sheds and rural buildings of
varying functions. This LR is
located to the east of the WRL alignment across from a small drainage
channel. The vegetation is
generally of good quality. A total of approx. 472 trees have been identified
within this LR; the dominant species includes Dimocarpus longan and Clausena lansium. |
|||||||
Zoning: This LR resides within
area under R(C) under the Ping Shan OZP S/YL-PS/16. |
|||||||
6.11 |
Yick Yuen Tsuen |
2.1 ha |
Medium |
Low |
Local |
High |
Low |
This LR consists of
two small, non-congruous areas of agricultural land adjacent to LR4.19; a
large, open scrub and woodland area.
This LR is located west of Yick Yuen Tsuen and the WRL alignment, and
east of the Kong Sam Western Highway.
It also includes a small, marginalised area of agricultural land
adjacent to the KSWH located just north of Tsing Chuen Wai. Interspersed throughout these
agricultural areas are numerous trees as well as sheds and rural buildings of
varying functions. The vegetation
is generally of good quality. A total of approx. 82 trees have been
identified within this LR; the dominant species includes Dimocarpus longan, Litchi chinensis, and Clausena lansium. |
|||||||
Zoning: This LR resides within
areas zoned GB and R(D) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
6.12 |
Tsing Chuen Wai &
Tuen Tsz Wai |
1.0 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of a
small, isolated area of agricultural land located in the north of Tsing Chuen
Wai on the hillside. The LR is
bounded to the west by R2.9 ¡V Yuen Tau Shan Natural Hillside Woodland. Also within this LR is a small,
isolated area of agricultural land located in the vicinity of Tuen Tsz Wai
village. The area is
circumscribed on all sides by nullah, rail lines, and roads. Throughout this
agricultural area are stands of trees as well as sheds and rural buildings of
varying functions. The vegetation
is generally of good quality. A total of approx. 21 trees have been
identified within this LR; the dominant species includes Ficus microcarpa, Litchi chinensis, Leucaena
leucocephala, Clausena lansium, Bombax ceiba, Mangifera indica, and Dimocarpus longan. |
|||||||
Zoning: This LR resides within
areas zoned GB under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 7 ¡V Vegetation within Residential
Developments |
7.0 ha |
||||||
7.1 |
Developments in TSW |
5.7 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR encompasses all
residential developments within TSW located between Tin Sau Road to the north
and Tin Fuk Road to the south, and east of the TSW Promenade. Generally, developments consist of
high-rise buildings with amenity planting around buildings, sports fields, and
walkways. Vegetation is of
variable quality and consists of numerous trees, shrubs and groundcovers of
various native and exotic species. A total of approx. 737 trees have been
identified within this LR; the dominant species includes Cinnamomum burmannii, Ficus virens, Ficus microcarpa, Bauhinia x
blakeana, Archontophoenix alexandrae, Roystonea regia, Bauhinia sp., Ficus
benjamina, Livistona chinensis. |
|||||||
Zoning: This LR resides within
areas zoned R(A), R(B), and G/IC under the TSW OZP S/TSW/12. |
|||||||
7.5 |
The Sherwood |
1.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR comprises
amenity gardens and street plantings located within and around The Sherwood
and Botania Villa, both high-rise residential developments. Amenity
vegetation is located around larger gathering spaces and adjacent to
buildings and internal roads.
This LR is located east of Castle Peak Road and south of the
KSWH. The vegetation is generally
consisting of mature trees and good quality and provides garden and amenity
spaces for residents. A total of approx. 416 trees have been identified
within this LR; the dominant species includes Araucaria heterophylla, Aleurites moluccana, Ficus virens, and Archontophoenix alexandrae. |
|||||||
Zoning: This LR resides within
areas zoned CDA under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 8 ¡V Vegetation within Rural Village |
69.2 ha |
||||||
8.2 |
San Hing Tsuen/ Ngau
Hom / Sha Kong Wai |
7.9 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is scattered throughout
several villages north of Lau Fau Shan Road. These are San Hing Tsuen, Ngau
Hom and Sha Kong Wai. Vegetation is generally mixed planting of self-seeded
semi-mature trees. Three Important Trees, 34A-T1, 34A-T2 and 34-T1, are
located in this LR. Identified species include Aquilaria sinensiss. A
total of approx. 258 trees have been identified within this LR; the dominant
species includes Leucaena
leucocephala, Ficus microcarpa, Clausena lansium, and Ficus benjamina. |
|||||||
Zoning: This LR resides wholly
within land zoned V under the Lau Fau Shan & Tsim Bei Tsui OZP
S/YL-LFS/7. |
|||||||
8.5 |
Sik Kong Tsuen/ Hong
Mei Tsuen/ Tseung Kong Wai |
4.0 ha |
Medium |
Medium |
Local |
Medium |
Medium |
The LR is of multiple areas
in Sik Kong Tsuen, Hong Mei Tsuen and Tseung Kong Wai. The village areas are
along San Sik Road. The vegetation is within and around the rural housing and
the open storage areas. Four Important Trees, 201-T1, 202-T1, 207-T1 and
207-T2, are located in this LR. Identified species include Ficus macrocarpa. A total of approx.
220 trees have been identified within this LR; the dominant species includes Dimocarpus longan, Clausena lansium, Litchi
chinensis, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR resides in land
zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
8.6 |
Sik Kong Wai / San Uk
Tsuen / Ha Tsuen Shi |
4.4 ha |
Medium |
Medium |
Local |
Medium |
Medium |
The LR is part of the Sik Kong Wai, San Uk
Tsuen and Ha Tsuen Shi village housing areas. The village areas are north of
a large container yard across from Tin Ha Road. Vegetation is mixed and
self-seeded trees within and around the populated areas. A total of approx.
260 trees have been identified within this LR; the dominant species includes Melaleuca cajuputi subsp. cumingiana,
Eucalyptus torelliana, and
Acacia confusa. |
|||||||
Zoning: The LR resides in land
zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
8.8 |
Sha Chau Lei |
0.6 ha |
High |
Medium |
Local |
Low |
High |
The LR is east of container yard along Tin Ha
Road and west of Sha Chau Lei Road; area is adjacent the village of Sha Chau
Lei. Vegetation is of self-seeded mature and semi-mature trees with various
understorey and shrub planting.
Two numbers of Important Trees, 407B-T1 & 4017B-T2 are located
within this LR. The identified
tree species are Ficus microcarpa
and Ficus elastica and are
potentially registrable as an OVT due to their large size. A total of
approx.69 trees have been identified within this LR; the dominant species
includes Clausena lansium,
Mangifera indica, and Dimocarpus longan. |
|||||||
Zoning: The LR resides in land
zoned U under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
8.11 |
San Sang Tsuen |
3.4 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of two large medium-sized
areas trees scattered about village housing. It is located west of Tin
Ha Road. Vegetation is a mixture of self-seeded and cultivated trees within
and around the village area. One Important Tree, 633-T1, is located within
this LR. The identified species is Ficus
macrocarpa. A total of approx.191 trees have been identified within this
LR; the dominant species includes Dimocarpus
longan, Clausena lansium, Macaranga tanarius var. tomentosa, and Litchi chinensis. |
|||||||
Zoning: The majority of the LR
resides in land zoned V under the Ha Tsuen OZP S/YL-HT/10. A small portion of
the LR is under land zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. In addition,
a trivial area of the LR resides in land zoned U under the Ping Shan OZP
S/YL-PS/16. |
|||||||
8.12 |
San Lee Uk Tsuen / Tin
Sam |
2.5 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of several small, non-congruous
vegetation patches scattered about the San Lee Uk Tsuen Village area, and one
vegetation patch north of Tin Sam. The LR is located west of HSK Main Street. General
vegetation is of self-seeded semi-mature and mature trees. One Important Tree, 706-T1 is located
within this LR. A total of approx. 142 trees have been identified within this
LR; the dominant species includes Leucaena
leucocephala, Dimocarpus longan, Bauhinia purpurea, and Clausena lansium. |
|||||||
Zoning: The LR mostly resides
in land zoned V under the Ping Shan OZP S/YL-PS/16. Other areas are in land
zoned R(C) and G/IC also under the Ping Shan OZP S/YL-PS/16. |
|||||||
8.13 |
HSK |
1.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of three small sized village housing
areas located in the vicinity of HSK Tin Sam Road and Hung Kei Road. General vegetation is of
self-seeded semi-mature and mature trees. A total of approx. 81 trees have
been identified within this LR; the dominant species includes Dimocarpus longan, Clausena lansium,
Macaranga tanarius var. tomentosa, and Artocarpus heterophyllus. |
|||||||
Zoning: The LR resides in land
zoned R(B) under the Ping Shan OZP S/YL-PS/16. |
|||||||
8.14 |
Tin Sam |
10.5 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is located about the large village
housing area of Tin Sam; it is located south and west of Tin Ha Road along
Tin Sam. Area is west of residential developments Casa De Oro and Parkview
Garden. Vegetation is a mixture of self-seeded and cultivated trees within
and around the village area. A total of approx. 496 trees have been
identified within this LR; the dominant species includes Dimocarpus longan, Macaranga tanarius var.
tomentosa, and Clausena lansium. |
|||||||
Zoning: The LR resides in land
zoned V and R(C) under the Ping Shan OZP S/YL-PS/16. This LR also resides in
land zoned R(B)2 under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
8.17 |
Tan Kwai Tsuen |
1.0 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of a large
continuous canopy of trees and vegetation throughout Tan Kwei Tsuen. This LR
is located northeast and south of two residential developments, The Verdancy
and the Meadowlands. Vegetation within this LR primarily consists of
self-seeded and planted mature and semi-mature trees with various understory
and shrub planting. Two Important Trees, 1064-T1 & 1064-T2 are located
within this LR. A total of approx. 36 trees have been identified within this
LR; the dominant species includes Dimocarpus
longan, Bauhinia purpurea, Cinnamomum burmannii, and Ficus microcarpa. |
|||||||
Zoning: The majority of LR
resides in land zoned R(D) under the Tong Yan San Tsuen OZP S/YL/-TYST/10. A
smaller are of LR resides in land zoned R(B)3 under the Tong Yan San Tsuen
OZP S/YL/-TYST/10. |
|||||||
8.18 |
Wo Ping San Tsuen /
Cheung Uk Tsuen / Arkadia |
11.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of
two village housing areas; these are Wo Ping San Tsuen and Cheung Uk Tsuen. Southern
portion of area is a housing development Arkadia. The LR is located southeast
of Castle Peak Road HSK. Vegetation in the LR is generally self-seeded
semi-mature to mature trees. A total of approx. 215 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala, Clausena lansium, and Dimocarpus longan. |
|||||||
Zoning: The LR resides mostly
in land zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. A small
portion of LR resides in land zoned R(D) under the Lam Tei & Yick Yuen
OZP S/TM-LTYY/8. In addition, trivial areas of the LR reside in land zoned O
and R(B)2R(B)2 under the Lam Tei
& Yick Yuen OZP S/TM-LTYY/8. |
|||||||
8.19 |
Yick Yuen Tsuen |
11.9 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of one
village housing area, called Yick Yuen Tsuen. The site is adjacent to an open
air storage area to the north and woodland area to the west. There are
pockets of vegetation scattered around the village area between and around
the housing. Vegetation is generally self-seeded semi-mature to mature trees.
A total of approx. 447 trees have been identified within this LR; the
dominant species includes Dimocarpus
longan and Litchi chinensis. |
|||||||
Zoning: The majority of LR
resides in land zoned R(C) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8.
A portion of LR resides in land zoned V under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
8.20 |
Tsing Cheun Wai / Tuen
Tsz Wai |
5.4 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is adjacent to
two village housing areas: Tsing Cheun Wai and Tuen Tsz Wai. Village area is
southwest of the KSWH and northwest of Castle Peak Road. The vegetation is
mostly scattered around housing areas; and are generally self-seeded
semi-mature to mature trees. One Important Tree, 1203-T1, is located within
this LR.
It is identified as Ficus macrocarpa. A total of approx. 159 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala, Dimocarpus longan, and Clausena lansium. |
|||||||
Zoning: The LR resides mostly
in land zoned V under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. Smaller
areas of LR reside in land zoned GB and CA under the Lam Tei & Yick Yuen
OZP S/TM-LTYY/8. |
|||||||
8.21 |
Lam Tei / Tuen Mun San
Tsuen |
5.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR comprises scattered stands of trees
and vegetation located amongst the village areas of Fuk Hang Tsuen, Lam Tei,
and Tuen Mun San Tsuen. This LR is located east of Castle Peak Road, near to the
residential developments, The Sherwood and Lingrade Garden. Vegetation is
generally self-seeded semi-mature to mature trees. A total of approx. 269
trees have been identified within this LR; the dominant species includes Dimocarpus longan, Leucaena leucocephala,
Clausena lansium, and Archontophoenix
alexandrae. |
|||||||
Zoning: The LR reside in land
zoned R(B), R(C), G/IC, CDA, O and V under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
LR 9 ¡V Vegetation within Industrial Land /
Open Storage |
56.7 ha |
||||||
9.2 |
Lau Fau Shan Road |
2.3 ha |
Low |
Low |
Local |
High |
Low |
LR is northeast of a
large container yard along Lau Fau Shan Road, also south of Ngau Hom Tsuen.
Vegetation is generally around the perimeter of the open space yards
providing a minor partition between the road and storage yard. Vegetation is
generally self-seeded semi-mature trees with understorey and shrub planting.
A total of approx. 86 trees have been identified within this LR; the dominant
species includes Ficus
microcarpa and Ficus benjamina. |
|||||||
Zoning: The LR resides in land
zoned V under the Lau Fau Shan & Tsim Bei Tsui OZP S/YL-LFS/7. In
addition, the LR resides in land zoned R(E) under the Lau Fau Shan & Tsim
Bei Tsui OZP S/YL-LFS/7.
Additionally, the LR also resides in land zoned V and CDA under the Ha
Tsuen OZP S/YL-HT/10. |
|||||||
9.3 |
Ping Ha Road |
2.9 ha |
Low |
Low |
Local |
High |
Low |
LR is scattered
amongst a large container yard and an open storage along Ping Ha Road.
Vegetation is generally around the perimeter of the open space yards
providing a minor partition between the road and storage yards. Vegetation is
generally self-seeded semi-mature trees with some understory and shrub
planting. A total of approx. 215 trees have been identified within this LR;
the dominant species includes Ficus
benjamina, Ficus microcarpa, and Macaranga tanarius var.
tomentosa. |
|||||||
Zoning: The LR resides in land
zoned CDA under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.4 |
Fung Kong Tsuen Road /
Deep Bay Road |
9.7 ha |
Low |
Low |
Local |
High |
Low |
LR consists of one
large container storage yard, located between Fung Kong Tsuen Road and Deep
Bay Road. Vegetation is found scattered around the open storages; and is generally
self-seeded semi-mature trees with various understory and shrub planting. A
total of approx. 402 trees have been identified within this LR; the dominant
species includes Ficus
benjamina, Ficus microcarpa, Macaranga tanarius var. tomentosa, and Dimocarpus longan. |
|||||||
Zoning: The LR is over
multiple zoned areas under the Ha Tsuen OZP S/YL-HT/10; zoned CDA, R(D) and
AGR. |
|||||||
9.6 |
Ping Ha Road / Tin Yip
Road |
0.9 ha |
Low |
Low |
Local |
High |
Low |
This LR consists of one
open storage yard and one parking lot. Area is located east of Ping Ha Road
and west of Tin Yip Road. Vegetation is found around the perimeters of the
open yard and parking lot. Vegetation is generally self-seeded semi-mature
trees with understory and shrubs plants. A total of approx. 81 trees have
been identified within this LR; the dominant species includes Ficus microcarpa and Ficus benjamina. |
|||||||
Zoning: The LR resides in land
zoned CDA under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.7 |
Tseung Kong Wai |
9.7 ha |
Low |
Low |
Local |
High |
Low |
The LR is south of an
open container yard and north of Tseung Kong Wai rural housing area.
Vegetation is within and around the boundary of the industrial buildings and
open-air yards. Vegetation is generally self-seeded semi-mature trees with
understory and shrubs plants. One Important Tree, 207-T3, is located in this
LR. A total of approx. 324 trees have been identified within this LR; the
dominant species includes Ficus
microcarpa, Macaranga tanarius var. tomentosa, and Ficus
virens. |
|||||||
Zoning: The LR is over
multiple zoned areas under the Ha Tsuen OZP S/YL-HT/10; zoned CDA,GB and REC. |
|||||||
9.8 |
Ping Ha Road / Tin Ha
Road |
5.1 ha |
Low |
Low |
Local |
High |
Low |
LR consists of one
large container yard and several smaller open space storages on southeast
Ping Ha Road and southeast Tin Ha Road. Vegetation is solely around the
perimeter of the open space yards providing a minor partition between the
road and storage yard. Vegetation is generally self-seeded semi-mature trees
with understory and shrub planting.
One identified Important Tree, 403-T1, is located within this LR
adjacent to Sha Chau Lei village.
The identified tree species is Ficus
microcarpa and is potentially registrable as an OVT due to its very good
form and size among trees of this species. A total of approx. 801 trees have
been identified within this LR; the dominant species includes Ficus microcarpa, Leucaena leucocephala,
Acacia auriculiformis, Macaranga tanarius var. tomentosa, Melia azedarach, and Ficus altissima. |
|||||||
Zoning: The LR resides in land
zoned U under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.9 |
Ha Tsuen Road |
9.3 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR consists of several
large open spaces used for container storage and parking lots. The area is
north of Ha Tsuen Road and a sewage treatment plant. Vegetation is generally
around the perimeter of the open space yards providing a minor partition
between the road and storage yard. Vegetation is mostly self-seeded
semi-mature trees with some wild understory planting. One Important Tree,
224-T1, is located in this LR. A total of approx. 453 trees have been
identified within this LR; the dominant species includes Ficus benjamina, Ficus microcarpa, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR resides mostly
in land zoned REC under the Ha Tsuen OZP S/YL-HT/10. Small areas of the LR
also reside in land zoned G/IC and GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.10 |
Hung Tin Road / Hung
Chi Road |
0.1 ha |
Medium |
Low |
Local |
Medium |
Medium |
The LR consists of a
large warehouse, open space storage area and a parking lot. The areas are
generally defined by the outline of the WRL and vegetation along boundaries
and roads. Vegetation is generally around the perimeter of the open space
yards providing a minor partition between the road and storage yard.
Vegetation is mostly self-seeded semi-mature trees with some wild understorey
planting. A total of approx. 6 trees have been identified within this LR; the
dominant species includes Ficus
microcarpa, Macaranga tanarius var. tomentosa, Bauhinia purpurea, and Eucalyptus urophylla. |
|||||||
Zoning: The LR resides mostly in
land zoned I(D) under the Ping Shan OZP S/YL-PS/16. Smaller areas of the LR
resides in land zoned I under the Ping Shan OZP S/YL-PS/16. In addition, the
LR resides in land zoned OS and O under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.11 |
Sik Kong Wai Road / Ha
Tsuen Road |
2.3 ha |
Low |
Low |
Local |
High |
Low |
LR is bordering a
large container yard and a smaller open-air storage area. Area is located
along Sik Kong Wai Road and north of Ha Tsuen Road. Vegetation is generally along
the perimeters of the sites flanking the roads. Vegetation is mostly self-seeded
semi-mature trees with some wild understory planting. A total of approx. 241
trees have been identified within this LR; the dominant species includes Ficus microcarpa, Ficus benjamina, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR is over
multiple zoned areas under the Ha Tsuen OZP S/YL-HT/10; zoned OS, REC, GB and
V. |
|||||||
9.12 |
San Wai Sewage
Treatment Works (SW STW) / Ha Tsuen Road |
0.4 ha |
Low |
Low |
Local |
High |
Low |
This LR is around the
perimeter of SW STW north of the KSWH. There are open space storages and
container yards to the northeast south of the site. Vegetation is at the
border of the sewage treatment plant mostly flanking the backroads Ha Tsuen
Road. Vegetation is mostly
self-seeded semi-mature trees with some wild understory planting. A total of
approx. 80 trees have been identified within this LR; the dominant species
includes Leucaena leucocephala and Acacia confusa. |
|||||||
Zoning: The LR resides in land
zoned G/IC under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
9.16 |
San Lee Uk Tsuen |
0.7 ha |
Low |
Low |
Local |
High |
Low |
The LR is northwest of San Lee Uk Tsuen, also
located along the southeast of the WRL and southeast of San Sang Tsuen.
Vegetation is mostly around the perimeter of the open storage yard. It is
generally self-seeded semi-mature trees with some wild understory planting. A
total of approx. 12 trees have been identified within this LR; the dominant
species includes Sterculia
nobilis, Macaranga tanarius var. tomentosa, Ficus benjamina, Clausena lansium, Morus alba,
Dimocarpus longan, and Ficus
microcarpa. |
|||||||
Zoning: The LR resides in land
zoned R(D) under the Ha Tsuen OZP S/YL-HT/10; and in land zoned V under the Ping
Shan OZP S/YL-PS/16. |
|||||||
9.17 |
Kau Lee Uk Tsuen / San
Sang Tsuen |
11.4 ha |
Low |
Low |
Local |
High |
Low |
The LR is located between Kau Lee Uk Tsuen and
San Sang Tsuen, and east of KSWH. General area consists of industrial
buildings and open storage yards with planting scattered throughout the
buildings and open storage yards. Vegetation is generally self-seeded
semi-mature to mature planting. Two identified Important Trees, 640A-T1 &
640A-T2, are located within this LR adjacent to Sha Chau Lei village. The identified tree species is Bombax ceiba and both have very good
form and size among trees of this species. A total of approx. 290 trees have
been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Clausena lansium, Litchi
chinensis, and Dimocarpus longan. |
|||||||
Zoning: Majority of LR resides
in land zoned R(D) under the Ha Tsuen OZP S/YL-HT/10. Other areas of LR are
in land zoned V, GB and OS(1) under the Ha Tsuen OZP S/YL-HT/10. In addition,
a small area of the LR resides in land zoned GB under the Ping Shan OZP
S/YL-PS/16. |
|||||||
9.18 |
Yick Yuen Road |
1.2 ha |
Low |
Low |
Local |
High |
Low |
The LR consists of one
large container storage area, located north of Yick Yuen Road and west of the
WRL. Vegetation is generally around the perimeter of the open space yards
providing a minor partition between the road and storage yards. Vegetation is
generally self-seeded semi-mature trees with some understory and shrub
planting. A total of approx. 102 trees have been identified within this LR;
the dominant species includes Leucaena
leucocephala, Ficus benjamina, and Macaranga tanarius var.
tomentosa. |
|||||||
Zoning: The LR resides mostly
in land zoned U under the Ping Shan OZP S/YL-PS/16. A small portion of LR is
in land zoned G/IC and R(B)2 under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
9.19 |
KSWH South |
1.0 ha |
Low |
Low |
Local |
High |
Low |
The LR consists of 2
separate open storage areas. Both are located along the KSWH: one at Yick Yuen
Road and other at Tsing Yick Road. Vegetation is generally at the perimeter
of the open space yards with self-seeded semi-mature trees with some
understorey and shrub planting. A total of approx. 75 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala, Eucalyptus
tereticornis, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The LR resides in land
zoned GB under both the Ping Shan OZP S/YL-PS/16 and the Lam Tei & Yick
Yuen OZP S/TM-LTYY/8. |
|||||||
LR 10 ¡V Water Course |
23.8 ha |
|
|||||
10.1 |
TSW River Channel |
15.3 ha |
Medium |
High |
Regional |
Low |
High |
TSW River Channel is a
concrete channel running through the whole TSW New Town and eventually draining
into inner Deep Bay. It has two major tributaries, namely the Shek Po Channel
and the Tin Sam Channel. It covers a catchment area of 16 km2,
with a total stretch of 27 km in length.
This area has an abundance of tree stands lining the river banks. A
total of approx. 410 trees have been identified within this LR; the dominant
species includes Sonneratia sp., Leucaena leucocephala, Acacia
auriculiformis. |
|||||||
Zoning: This
LR does not fall within any OZP. |
|||||||
10.2 |
Hang Hau Tsuen Nullah |
0.3 ha |
Medium |
Medium |
Regional |
Medium |
Medium |
Hang Hau Tsuen Nullah
is a concrete channel running through the north of the Project and eventually
draining into inner Deep Bay. It has one small tributary draining from San
Hing Tsuen village. The southern
extents of the nullah consists of a small drainage channel with vertical
walls whereas, after passing under Deep Bay Road, the channel widens to a
greater width and upon reaching Deep bay is a naturalised course set within
the manmade embankments. This
area has an abundance of tree stands lining the riverbanks. |
|||||||
Zoning: The
southern arm and small tributary of this LR resides within areas zoned CDA
under the Ha Tsuen OZP S/YL-HT/10, and as it flows into Deep Bay it resides
within areas zoned R(D) under the Lau Fau Shan & Tsim Bei Tsui OZP
S/YL-LFS/7. |
|||||||
10.3 |
Tung Tau Tsuen Nullah |
0.2 ha |
Low |
Low |
Local |
High |
Low |
This watercourse is a
small, concrete-lined vertical channel that for the most part is piped and
culverted and only briefly is open to the sky between Ping Ha Road and Tin
Ying Road before emptying into TSW River Channel. Despite its small
character, this LR has an abundance of tree stands lining the channel banks. |
|||||||
Zoning: The
LR resides within areas zoned CDA under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
10.4 |
Ping Ha Road Nullah |
0.8 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a
channelised watercourse with both vertical and sloping concrete banks running
north along the west side of Ping Ha Road and eventually turning northeast
and draining into TSW River Channel.
The southern extents of the nullah consists of a small drainage
channel with vertical walls whereas, after passing under Ping Ha Road, the
channel widens to a greater width and is set within manmade embankments. This area has an abundance of tree
stands lining the riverbanks. |
|||||||
Zoning: This
LR lies within areas zoned U and V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
10.5 |
Sik Kong Tsuen & Tseung
Kong Wai Nullah |
0.3 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a
channelised watercourse with vertical concrete banks running in west to east
direction eventually turning northeast and draining into LR10.4 - Ping Ha
Road Nullah. This LR stretches
from west of Tseung Kong Wai and passes through the village areas of San Wai
and Sik Kong Tsuen. This LR has
an abundance of tree stands lining the riverbanks in the vicinity of Sik Kong
Wai and gradually becomes more open and sparse of vegetation as one moves
upstream. One numbers of
identified Important Trees, 224-T1, islocated within this LR. The identified tree species is Bombax ceiba and has very good form
and size among trees of this species. |
|||||||
Zoning: This
LR lies within areas zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
10.6 |
Sik Kong Wai &
Ling To Nullah |
0.9 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a
channelised watercourse with vertical concrete banks running in a southwest to
northeast direction eventually joining LR10.5 and draining into Ping Ha Road
Nullah. This LR stretches from
Ling To where it passes under the KSWH, meanders between numerous industrial
and open storage yards, and, at flowing between Sik Kong Wai and Ha Tsuen
Shi, turns north to drain into LR10.4 ¡V Ping Ha Road Nullah. This LR has an abundance of tree
stands lining the riverbanks in the vicinity of the villages as well as
continuous tree cover as it meanders through the open storage areas. It gradually becomes more open in the
vicinity of Ling To Temple. A total of approx. 12 trees have been identified
within this LR; the dominant species includes Macaranga tanarius var. tomentosa and Acacia auriculiformis. |
|||||||
Zoning: This
LR lies within areas zoned V, GB, and ¡§Open Storage¡¨ (OS) under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
10.7 |
Yuen Tau Shan Streams
& Nullah |
0.1 ha (nulllah) |
Medium |
Medium |
Regional |
Medium |
Medium |
This LR consists of the
three natural watercourses that exist within the Project area. These three natural streams are all
located along the western ridgeline of the Project. The northernmost stream drains
northwards and eventually is channelised before emptying into Deep Bay. The other two streams are located
across the KSWH from LR6.6 - San
Sang San Tsuen. They both become
channelised and culverted before passing under the highway and eventually
emptying into LR10.11 ¡V Tin Sam Channel. A total of approx. 61 trees have been
identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Pinus massoniana, Leucaena
leucocephala, and Ficus hispida. |
|||||||
Zoning: The
northern stream lies within areas zoned GB and CA under the Ha Tsuen OZP
S/YL-HT/10. The two southern
streams lie within areas zoned GB and CA under the Ping Shan OZP S/YL-PS/16. |
|||||||
10.8 |
Hung Tin Road Nullah |
0.08 ha |
Low |
Low |
Local |
High |
Low |
This LR is a
channelised watercourse with vertical concrete banks running north along the east
side of Hung Tin Road. It extends
from Castle Peak Road to the south nearly to Kiu Fat Street in the
north. The northern extents has
an abundance of tree stands lining the vertical riverbanks, whereas the
majority of it has no vegetation. A total of approx. 12 trees have been
identified within this LR; the dominant species includes Hibiscus
tiliaceus, Ficus microcarpa and Casuarina equisetifolia. |
|||||||
Zoning: This
LR lies within areas zoned Industrial (Group D) (I(D)), Industrial (I), and U
under the Ping Shan OZP S/YL-PS/16. |
|||||||
10.10 |
Shek Po Channel |
1.1 ha |
High |
Medium |
Local |
Low |
High |
This LR is a concrete
channel running through the south of the Project and eventually draining into
LR10.1 TSW River Channel. It consists of a sloping concrete bank channel
north of Castle Peak Road and, south of Castle Peak Road, the concrete
sloping banks are lined with grasscrete for a short section before returning
to bare concrete banks. This LR
has an abundance of high quality tree stands lining the riverbanks for nearly
the entire length. |
|||||||
Zoning: The
extents of this LR north of Castle Peak Road does not fall within any OZP,
whereas the extents south of this road falls within area zoned R(D) under the
Tong Yan San Tsuen OZP
S/YL-TYST/10. |
|||||||
10.11 |
Tin Sam Channel |
2.6 ha |
High |
Medium |
Local |
Low |
High |
This LR is a concrete
channel running through the south of the Project and eventually draining into
LR10.1 TSW River Channel. It consists of a sloping concrete bank channel
north of Tin Ha Road and, south of Tin Ha Road, becomes a vertical bank
channel. This LR has an abundance
of high quality tree stands lining the riverbanks for nearly the entire length.
A total of approx. 2 trees have been identified within this LR; the dominant
species include Morus
alba. |
|||||||
Zoning: The
extents of this LR north of Tin Ha Road does not fall within any OZP, whereas
the extents south of this road falls within area zoned V and R(C) under the
Ping Shan OZP S/YL-PS/16 and GB under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
10.12 |
San Sang San Tsuen
Channel |
0.5 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR consists of three
very small tributaries traversing the area south of San Sang San Tsuen
through LR6.6 - San Sang San Tsuen Vegetation on Agricultural Land as well as
LR4.13 ¡V San Sang San Tsuen Low-lying Woodland/Plantation. These drainage channels consist of
vertical concrete embankments with an abundance of trees along their length. |
|||||||
Zoning: This
LR falls within numerous zoning designations under the GB, U, R(C) and R(D)
all under the Ping Shan OZP S/YL-PS/16. |
|||||||
10.13 |
Yick Yuen Tsuen & Tsing
Chuen Wai Nullah |
1.2 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR is a concrete
channel running through the south of the Project and eventually draining into
the Tuen Mun River. The main nullah consists of a sloping concrete bank
channel extending from Castle Peak Road and the KSWH and draining
southwest. A smaller tributary
drains from Yick Yuen Tsuen in a southwardly direction. This smaller tributary has an
abundance of tree stands along the riverbanks whereas the River Channel is
bare, concrete sloped embankment. A total of approx. 3 trees have been
identified within this LR; the dominant species includes Leucaena leucocephala, and Macaranga tanarius var. tomentosa. |
|||||||
Zoning: The
southern extents of this LR does not fall within any OZP, whereas the
northern extents fall within area zoned V and R(D) under the Ping Shan OZP
S/YL-PS/16 and GB under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 11 ¡V Vegetation in Urban Parks |
3.2 ha |
|
|||||
11.1 |
Parks in TSW |
1.3 ha |
High |
Medium |
Local |
Medium |
Medium |
The TSW Park, which
has a total area of 14.86 ha, is located at the heart of TSW New Town. It
consists of numerous spaces, activity areas, walking trails and planting
areas. Tree species located
within the park include; Archontophoenix
alexandrae, Bauhinia spp., Delonix regia, Ficus microcarpa and
Roystonea regia. Tin Shui Road Park is a linear park
linking TSW Park with the TSW Waterfront. It is divided into two halves, split
by the light rail line, Shui Wu Garden is a linear park located adjacent to
Tin Shui Wai Road Park and running parallel with the rail tracks, Locwood
Garden is a road park located adjacent to Tin Yiu Road and located in front
of Kingswood Villas and Locwood Court, and Tin Ho Road Playground is a road
park located adjacent to Tin Ho Road.
The vegetation within all these park sites consist of semi-mature
amenity trees and amenity planting. A total of approx. 327 trees have been
identified within this LR; the dominant species includes Archontophoenix alexandrae, Spathodea
campanulata, Ficus microcarpa, Lagerstroemia speciosa, Tabebuia argentea, and Livistona chinensis. |
|||||||
Zoning: This
LR falls within areas zoned O under the TSW S/TSW/12. |
|||||||
11.2 |
Ping Ha Road Garden |
0.2 ha |
High |
Medium |
Local |
Medium |
Medium |
The Ping Ha Road
Garden is a small open space adjacent to Lo Uk Tsuen. It primarily consists of a soccer
pitch with various amenity planting and paving around the pitch. The vegetation consists of semi-mature
amenity trees and shrub planting. A total of approx. 41 trees have been
identified within this LR; the dominant species includes Bauhinia sp., Leucaena leucocephala, and
Melaleuca cajuputi subsp.
Cumingiana. |
|||||||
Zoning: This
LR falls within areas zoned V under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
11.4 |
Tin Ha Road Playground |
0.1 ha |
High |
Medium |
Local |
Medium |
Medium |
The Tin Ha Road
Playground is a medium-sized open space adjacent to rural residential housing
and located along Castle Peak Road.
It primarily consists of a soccer pitch and smaller sports pitch, with
various amenity planting and paved activity spaces around the pitch. The vegetation consists of semi-mature
amenity trees and shrub planting. A total of approx. 6 trees have been
identified within this LR; the dominant species includes Callistemon viminalis and Eucalyptus torelliana. |
|||||||
Zoning: This
LR falls within areas zoned O under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
11.5 |
Nai Wai Soccer Pitch /
Fuk Hang Tsuen Road Garden |
1.5 ha |
High |
Medium |
Local |
Medium |
Medium |
Nai Wai Soccer Pitch
is a small open space adjacent to Nai Wai. It primarily consists of a soccer
pitch with various amenity planting and paving around the pitch. The vegetation consists of semi-mature
amenity trees and shrub planting.
The Fuk Hang Tsuen Road Garden is a medium-sized open space adjacent
to residential units in The Sherwood, and located off Castle Peak Road behind
the Miu Fat Buddhist Monastery. It
primarily consists of numerous spaces, activity areas, walking trails and
planting areas. The vegetation
consists of semi-mature amenity trees and shrub planting. There is also a large paved square on
top of a carpark entrance located to the south off Lam Tei Main Street. One
Important Tree, 1213-T2, is located in this LR. A total of approx. 134 trees
have been identified within this LR; the dominant species includes Araucaria heterophylla, Aleurites moluccana,
Ficus virens, Leucaena leucocephala, and Archontophoenix alexandrae. |
|||||||
Zoning: This
LR falls within areas zoned O under the Lam Tei & Yick Yuen OZP
S/TM-LTYY/8. |
|||||||
LR 12 ¡V Vegetation on Modified Slopes |
4.6 ha |
|
|||||
12.1 |
Hang Hau Tsuen |
0.4 ha |
Medium |
Low |
Local |
High |
Low |
This LR comprises
several modified slopes along Deep Bay Road and Fung Kong Tsuen Road near
LR6.2 - Hang Hau Tsuen Nullah, in the north of the Project area. It also includes several vegetated
slopes circumscribing a large open storage yard in the vicinity of LR2.2 ¡V
Ngau Hom Hillside Woodland. These
slopes comprise hillsides with semi-mature vegetation and with various
scattered, self-seeded shrubs and trees growing on slopes. A total of approx.
79 trees have been identified within this LR; the dominant species includes Macaranga tanarius var. tomentosa, Celtis sinensis, Dimocarpus
longan, Ficus benjamina, Melia azedarach. |
|||||||
Zoning: This
LR falls within areas zoned CDA, V, and CPA under Ha Tsuen OZP S/YL-HT/10,
areas zoned R(D), R(E), and GB under Lau Fau Shan & Tsim Bei Tsui OZP
S/YL-LFS/7. |
|||||||
12.2 |
Ha Tsuen |
3.1 ha |
Medium |
Low |
Local |
High |
Low |
This LR comprises
numerous modified slopes in the vicinity of KSWH where it crosses the
northern hills and connects to Deep Bay Bridge. It also includes several small slopes
in the vicinity of the SW STW and Ha Tsuen Road. A total of approx. 421 trees
have been identified within this LR; the dominant species includes Leucaena leucocephala, Acacia auriculiformis,
Ficus microcarpa, Eucalyptus sp., Macaranga tanarius var. tomentosa, and Acacia confusa. |
|||||||
Zoning: This LR falls within
areas zoned AGR, GB, G/IC, and OS Ha Tsuen OZP S/YL-HT/10. |
|||||||
12.3 |
Yick Yuen Tsuen |
1.2 ha |
Medium |
Low |
Local |
High |
Low |
This LR comprises several
modified slopes in the vicinity of KSWH to the west of Yick Yuen Tsuen. The slopes cut into the
hillsides to make way for the highway and smaller roads branching off. A
total of approx. 125 trees have been identified within this LR; the dominant species
includes Leucaena leucocephala,
Eucalyptus citriodora and
Macaranga tanarius var. tomentosa. |
|||||||
Zoning: This
LR falls within areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
LR 13 ¡V Vegetation Along TSW Promenade |
4.4 ha |
||||||
13.0 |
Vegetation along TSW
Promenade |
4.4 ha |
High |
High |
Regional |
Medium |
Medium |
This LR runs along the
TSW Promenade and Main Channel for approximately 2 km. Vegetation along TSW
Promenade consists of amenity tree and shrub planting and is generally of mature
or semi-mature status. A total of approx. 894 trees have been identified
within this LR; the dominant species includes Cinnamomum burmannii, Bauhinia sp., Ficus microcarpa, Ficus virens, and
Livistona chinensis. |
|||||||
Zoning: This
LR does not fall within any OZP. |
|||||||
LR 14 ¡V Roadside Vegetation |
23.6 ha |
||||||
14.2 |
Tin Shui Road |
1.3 ha |
High |
Medium |
Local |
Low |
Medium |
This LR comprises
intermittent stands of trees located along Tin Shui Road, Tin Wah Road, Tin
Wu Road, and Tin Fuk Road. While
not continuous along the entire roadway, this LR extends from the north of
TSW area to the south at TSW Station.
Vegetation consists of mature and semi-mature trees of various
species, predominantly planted as amenity roadside planting. A total of
approx. 240 trees have been identified within this LR; the dominant species
includes Roystonea regia, Crateva
unilocularis, Bauhinia x blakeana, Syagrus romanzoffiana, Archontophoenix
alexandrae, and Cinnamomum burmannii. |
|||||||
Zoning: This
LR falls within areas zoned R(A) and G/IC under the TSW OZP S/TSW/12. |
|||||||
14.3 |
Tin Ying Road |
12.1 ha |
Medium |
Medium |
Local |
Low |
Medium |
This LR comprises
intermittent stands of trees located along Tin Ying Road. While not continuous along the entire
roadway, this LR extends along the TSW River Channel from Lau Fau Shan in the
northeast to Ping Ha Road in the south.
Several locations comprise of large, broad areas with stands of
trees. Vegetation consists of
mature and semi-mature trees of various species, some planted and others
naturally colonised. A total of approx. 3,915 trees have been identified
within this LR; the dominant species includes Acacia confusa, Acacia auriculiformis, Eucalyptus sp., Leucaena leucocephala, Albizia lebbeck,
and Ficus microcarpa. |
|||||||
Zoning: This
LR falls within areas zoned O, R(A), and OU under the TSW OZP S/TSW/12, and
areas zoned GB, G/IC, R(C), V, CDA, O, and U under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
14.4 |
Lau Fau Shan Road |
0.4 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR comprises
intermittent stands of trees located along Lau Fau Shan Road. While not continuous along the entire
roadway, this LR extends from Deep Bay Road to the northwest to Tin Wah Road
towards the southeast. Vegetation
consists of mature and semi-mature trees of various species, some planted and
others naturally colonised. A total of approx. 42 trees have been identified
within this LR; the dominant species includes Ficus
benjamina, Ficus microcarpa, and Bauhinia x blakeana. |
|||||||
Zoning: This LR falls within
areas zoned V and Commercial/Residential (C/R) under the Lau Fau Shan &
Tsim Bei Tsui OZP S/YL-LFS/7, and areas zoned CDA under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
14.6 |
Ping Ha Road |
3.1 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises intermittent stands of trees
located along Ping Ha Road. While
not continuous along the entire roadway, this LR extends from Tin Wah Road in
the north to TSW Station in the south.
Vegetation consists of mature and semi-mature trees of various
species, some planted and others naturally colonised. A total of approx. 416
trees have been identified within this LR; the dominant species includes Ficus microcarpa, Ficus benjamina, Leucaena
leucocephala, Melaleuca cajuputi subsp. cumingiana, and Hibiscus
tiliaceus. |
|||||||
Zoning: This LR falls within areas zoned R(A) and OU under the TSW OZP
S/TSW/12; areas zoned U under the Ping Shan OZP S/YL-PS/16; and areas zoned
V, U, G/IC, O, and CDA under the
Ha Tsuen OZP S/YL-HT/10. |
|||||||
14.7 |
Hung Tin Road |
0.1 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises intermittent stands of trees
located along Hung Tin Road.
While not continuous along the entire roadway, this LR extends from
Ping Ha Road to the north to Castle Peak Road to the south. Vegetation consists of mature and
semi-mature trees of various species, some planted and others naturally
colonised. A total of approx. 24 trees have been identified within this LR;
the dominant species includes Ficus
microcarpa, Hibiscus tiliaceus, Casuarina equisetifolia, and Leucaena leucocephala. |
|||||||
Zoning: This LR falls within areas zoned I(D) and I under the Ping Shan
OZP S/YL-PS/16. |
|||||||
14.8 |
Tin Ha Road |
1.2 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
intermittent stands of trees located along Tin Ha Road. While not continuous along the entire
roadway, this LR extends from Ping Ha Road to the north to Castle Peak Road
to the south. Vegetation consists
of mature and semi-mature trees of various species, some planted and others
naturally colonised. A total of approx. 135 trees have been identified within
this LR; the dominant species includes Ficus microcarpa, Macaranga tanarius var. tomentosa, Khaya senegalensis, and Dimocarpus longan. |
|||||||
Zoning: This
LR falls within areas zoned V and U under the Ha Tsuen OZP S/YL-HT/10; and
areas zoned V and R(C) under the Ping Shan OZP S/YL-PS/16. |
|||||||
14.9 |
Ha Tsuen Road |
0.9 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises intermittent
stands of trees located along Tin Ha Road. While not continuous along the entire
roadway, this LR extends from Tin Ha Road to the east to KSWH to the
west. Vegetation consists of
mature and semi-mature trees of various species, some planted and others
naturally colonised. A total of approx. 149 trees have been identified within
this LR; the dominant species includes Bauhinia
x blakeana, Leucaena leucocephala, Delonix regia, Ficus benjamina, Macaranga
tanarius var. tomentosa, and Bauhinia variegata. |
|||||||
Zoning: This
LR falls within areas zoned under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
14.10 |
Castle Peak Road |
2.2 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises
intermittent stands of trees located along Castle Peak Road. While not continuous along the entire
roadway, this LR extends from Ping Shan to the east to Lam Tei to the
west. Vegetation consists of
mature and semi-mature trees of various species, some planted and others naturally
colonised. Five identified
Important Trees, 1077-T1, 962-T1, 1202-T1, 1202-T2 & 1213A-T1, are
located within this LR adjacent to Castle Peak Road. The identified tree species are Ficus microcarpa, Melaleuca cajuputi subsp. Cumingiana,
& Ficus elastica and all have
very good form and large size among trees of this species. Two
additional Important Trees,
1202-T1, 1202-T2, are located within this LR. A total of approx. 315 trees
have been identified within this LR; the dominant species includes Celtis
sinensis, Melaleuca cajuputi subsp. cumingiana, Ficus microcarpa, Dimocarpus
longan, Albizia lebbeck, Leucaena leucocephala, Cinnamomum camphora |
|||||||
Zoning: This
LR falls within areas zoned V, R(A), R(B), GB, CDA, and I under the Ping Shan OZP
S/YL-PS/16; areas zoned I, V, and G/IC under the Tong Yan San Tsuen OZP
S/YL-TYST/10; and areas zoned V, G/IC, and R(C) under the Lam Tei & Yick
Yuen OZP S/TM-LTYY/8. |
|||||||
14.12 |
HSK Tin Sam Road /
Hung Yuen Road / |
0.4 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises intermittent
stands of trees located along HSK Tin Sam Road, Hung Chi Road, Hung Kei Road,
Hung Tai Road, and Hung Yuen Road.
While not continuous along the roadways, this LR covers roadways in
the general San Lee Uk Tsuen area and extends towards Castle Peak Road to the
south. Vegetation consists of
mature and semi-mature trees of various species, some planted and others
naturally colonised. A total of approx. 97 trees have been identified within
this LR; the dominant species includes Livistona chinensis, Bauhinia purpurea, and Spathodea campanulata. |
|||||||
Zoning: This LR falls within
areas zoned V, R(A), R(B), and CDA under the Ping Shan OZP S/YL-PS/16. |
|||||||
14.13 |
Yick Yuen Road |
0.2 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises three
intermittent stands of trees located along Yick Yuen Road. While not continuous along the
roadway, this LR extends from Castle Peak Road to the east to the WRL
alignment to the west. Vegetation
consists of mature and semi-mature trees of various species, some planted and
others naturally colonised. A total of approx. 19 trees have been identified
within this LR; the dominant species includes Ficus benjamina. |
|||||||
Zoning: This
LR falls within areas zoned U under the Ping Shan OZP S/YL-PS/16; and areas
zoned G/IC, R(C), and R(D) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
14.14 |
KSWH |
1.9 ha |
Medium |
Low |
Local |
Medium |
Medium |
This LR comprises stands
of trees located along KSWH and centred around the traffic islands around the
interchange with the Yuen Long Highway.
While not continuous along the entire roadway, this LR comprises
several significant stands of trees located along the roadway. Vegetation consists of mature and
semi-mature trees of various species, some planted and others naturally
colonised. One number of Important Trees, 1213-T1, is located in this LR. A
total of approx. 47 trees have been identified within this LR; the dominant
species includes Leucaena leucocephala,
Archontophoenix alexandrae, Clausena lansium, Bauhinia sp. |
|||||||
Zoning: This
LR falls within areas zoned GB, V, G/IC, and R(C) under the Lam Tei &
Yick Yuen OZP S/TM-LTYY/8. |
|||||||
LR 15 ¡V Water Bodies |
2.6 ha |
||||||
15.2 |
Sha Kong Tsuen |
0.6 ha |
Medium |
Medium |
Local |
Medium |
Medium |
This LR comprises a
fishpond and a recreational pond of 0.2 and 0.4ha, respectively. The recreational pond is used for
paddle boating by nearby residents and visitors and has heavy vegetation
surrounding it. The fishpond has
little vegetation and is bounded by rural village housing on two sides. |
|||||||
Zoning: This
LR lies within area zoned as CPA under the Lau Fau Shan & Tsim Bei Tsui
OZP S/YL-LFS/7. |
|||||||
15.5 |
Sik Kong Tsuen |
0.9 ha |
High |
High |
Local |
Low |
High |
This LR comprises four
stormwater ponds located in the vicinity of Sik Kong Wai, Sik Kong Tsuen, and
Lo Uk Tsuen villages. The ponds
are located along the proposed heritage trail that runs through numerous villages
in San Wai and therefore have strong cultural ties to the villagers. Vegetation lines the banks and
primarily comprises shrubs and grasses and numerous stands of mature and
semi-mature trees. |
|||||||
Zoning: This
LR falls within areas zoned V under the Ha Tsuen OZP S/YL-HT/10 |
|||||||
15.6 |
Tseung Kong Wai |
0.2 ha |
Low |
Medium |
Local |
High |
Low |
This LR comprises one
fishpond located amongst various industrial storage/open air storage land
uses at the base of the northern hills of the Project. It is situated north of Ha Tsuen Road
and has limited vegetation around the perimeter. |
|||||||
Zoning: This
LR falls within areas zoned GB under the Ha Tsuen OZP S/YL-HT/10. |
|||||||
15.10 |
Ling To |
0.6 ha |
Medium |
Medium |
Local |
Low |
High |
This LR is comprised
of four mitigation ponds located adjacent to the KSWH near Ling To Tsz Temple
constructed under the DBL project to compensate the loss of moderate value
fishponds. Two of the mitigation
ponds are located on the western side of the highway and two are located on
the eastern side. The water
bodies have dense vegetation around their edges consisting of semi-mature
trees and shrubs. |
|||||||
Zoning: This
LR resides wholly within land zoned GB under the Ha Tsuen OZP
S/YL-HT/10. |
|||||||
15.11 |
Tuen Tsz Wai |
0.3 ha |
Low |
Medium |
Local |
High |
Low |
This LR comprises two
manmade fishponds located in the vicinity of Fui Sha Wai Village and amongst
agricultural land LR6.4 ¡V Fui Sha Wai.
They are located north of Yuen Long Highway and south of Castle Peak
Road. The fishponds have
vegetation around their borders consisting of semi-mature trees and shrubs. |
|||||||
Zoning: This LR resides within
areas zoned R(B) under the Lam Tei & Yick Yuen OZP S/TM-LTYY/8. |
|||||||
15.12 |
San Sang San Tsuen |
0.32 ha |
Low |
Medium |
Local |
High |
Low |
This LR comprises of
one inactive fish pond located in the vicinity of San Sang San Tsuen and
amongst low-lying woodland/plantation land LR4.8 ¡V San Sang San Tsuen. It is
located west of Tin Ha Road and Tin Sam Channel. The fishpond is overgrown
with herbaceous species of vegetation. |
|||||||
Zoning: |
|||||||
This LR resides within
areas zoned GB under the Ping Shan OZP S/YL-PS/16 |
|||||||
LR 17 ¡V Marsh |
0.6 ha |
|
|||||
17.2 |
Fung Kong Tsuen |
0.6 ha |
High |
High |
Regional |
Low |
High |
This LR comprises a
moderate-sized marsh located adjacent LR5.3-Fung Kong Tsuen Low-lying Shrub
and Grassland. The marsh is
heavily influenced by development and likely evolved from abandoned
agriculture. A
total of approx. 26 nos. of trees have
been identified within this LR; the dominant species includes Dimocarpus longan, Litchi chinensis,
Macaranga tanarius var. tomentosa. |
|||||||
Zoning: |
|||||||
This LR resides
primarily within areas zoned GB under the Ha Tsuen OZP S/YL-HT/10 |
|||||||
LR 18 ¡V Important Trees |
N/A |
|
|||||
18 |
|
|
High |
High |
Regional |
Low |
High |
There
are approximately 66 trees that are classified as ¡§Important Trees¡¨. Species
include Ficus microcarpa, Ficus
elastic, Bombax ceiba, and Artocarpus
nitidus subsp. Lingnanensis,
among others. Important trees are located throughout the Project assessment
area and identified within the corresponding LR¡¦s above, contributing to the
sensitivity rating of each LR where present. Due to the ¡§Important Trees¡¨
quality and natural status, its regional importance, and low tolerance to
change, the sensitivity given is High. |
¡P Scattered villages: predominately concentrated along the major traffic corridors (e.g. Castle Peak Road and Yuen Long Highway) at the south of the assessment area, consisting largely of low-rise buildings.
¡P Agricultural land: of approximately 50.57 ha within the Assessment area. This land is intended for the retention of fallow arable land with potential for rehabilitation for cultivation and other agricultural purposes. The agricultural land is located in the north of the assessment area directly south of Deep Bay Road, and in the south-southeast located between KSWH and Castle Peak Road.
¡P Open storage plots: are one of the largest current constituent land uses within the Project planning area. Open storage is predominantly located in the northern portion of the Project and it is estimated that over 200 ha of land is committed to this category of land use. The existence of open storage uses has significant implications for the assessment area as they contribute to the degradation of the rural living environment of the assessment area and its surrounding environs and creates is a general sense of transience and change about the landscape even though the traditional rural character predominates.
Table 11.4 Baseline Landscape Character Areas (DP1,
DP2, DP5, DP6 and DP12)
Landscape Character Area |
Description |
Sensitivity |
Baseline Area |
||||
Quality &
Maturity (High, Medium, Low) |
Rarity (High, Medium,
Low) |
Importance (Local, Regional,
National, Global) |
Ability to
Accommodate Change (Low, Medium, High) |
||||
LCA1 |
Miscellaneous Rural Fringe Landscape |
Medium |
512.5 ha |
||||
Medium |
Medium |
Local |
Medium |
||||
LCA2 |
Miscellaneous Urban Fringe Landscape |
Medium |
97.7 ha |
||||
Medium |
Low |
Local |
Medium |
||||
LCA3 |
Residential Urban Landscape |
Medium |
74.6 ha |
||||
Medium |
Low |
Local |
Medium |
||||
LCA4 |
Upland and Hillside Landscape |
High |
205.3 ha |
||||
High |
Medium |
Regional |
Low |
||||
LCA5 |
Settled Valley Landscape |
Medium |
8.4 ha |
||||
Medium |
Medium |
Local |
Medium |
||||
LCA6 |
Rural Coastal Plain Landscape |
High |
32.7 ha |
||||
Medium |
High |
Regional |
Low |
||||
Potential Sources of Landscape and Visual Impacts
¡P Site clearance works involving the removal of the existing Storage Containers and recreational facilities, as well as the removal of existing trees and shrub planting;
¡P Site formation works including cutting and filling
¡P Excavation works and haulage off-site of excavated materials;
¡P Storage of existing topsoil for reinstatement works;
¡P Importation and storage of construction equipment and plant;
¡P Materials stockpiling;
¡P Construction of site access;
¡P Temporary Traffic Management activities;
¡P Removal of existing Tin Ying Road, upgrading of a present tertiary Road ¡V Ping Ha Road and the laying down of utilities including water, drainage, power and waste;
¡P Construction of the temporary parking areas, on-site accommodation offices & structures and working areas, importation and storage of equipment and materials;
¡P Construction of the Roads P1 and Roads D1 ¡V D7 and associated internal industrial and residential roads;
¡P Re-alignment of roads;
¡P Re-alignment of streams and watercourses
¡P Dust and construction debris;
¡P The laying down of utilities, including water, drainage and power; and
¡P Night lighting.
¡P Operation of Ping Ha Road, Roads P1 and Roads D1 ¡V D7;
¡P Operation of the Proposed HSK WRL Station, as well as the, proposed Residential, Commercial, Industrial and Mixed Use Developments;
¡P Operation and maintenance of proposed open space;
¡P Provision of any noise mitigation structures; and
¡P Residual impacts from loss of trees and vegetation during the construction phase;
Nature and Magnitude of Landscape change Before Mitigation in Construction Phase
Nature and Magnitude of Landscape change Before Mitigation in Operation Phase
Table 11.5 Magnitude of Landscape Change during the
Construction and Operation Phases before Mitigation (DP1, DP2, DP5, DP6 and
DP12)
ID No. |
Landscape Resources/ Landscape Character Areas |
Source of Impact |
Description of Impacts |
Compatibility of the Project with the
Surrounding Landscape (High, Medium, Low) |
Duration of Impact (None, Temporary (Short,
Medium, Long-term); Permanent, Reversible; Permanent, Irreversible) |
Magnitude of Change (None, Negligible, Small, Intermediate, Large) |
LR2 Hillside Woodland |
||||||
LR2.2 |
Ngau
Hom |
None |
None -
Baseline vegetation
coverage is approx. 2.8 ha |
N/A |
None |
None |
LR2.3 |
Hang
Hau Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.3 ha |
N/A |
None |
None |
LR2.4 |
Ngau
Hom Shek |
Construction -
Site clearance works -
Construction of the temporary
structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.04 ha -
Baseline vegetation
coverage is approx. 26.3 ha -
A total of approx. 2
trees are impacted |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR2.6 |
Tung
Tau Tsuen |
None |
None -
Baseline vegetation coverage
is approx. 4.4 ha |
N/A |
None |
None |
LR2.7 |
Ha
Tsuen Road |
None |
None -
Baseline vegetation
coverage is approx. 0.6 ha |
N/A |
None |
None |
LR2.8 |
Ha
Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 1.3 ha |
N/A |
None |
None |
LR2.9 |
Yuen
Tau Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.2 ha -
Baseline vegetation
coverage is approx. 101.7 ha -
A total of approx. 9 trees
are impacted |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of existing
vegetation, and replacement with roads and infrastructure |
|||||
LR2.11 |
Kau
Lee Uk Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.1 ha -
Baseline vegetation
coverage is approx.5.5 ha -
A total of approx. 5
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR2.12 |
San
Sang Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 2.9 ha |
N/A |
None |
None |
LR3 Hillside Shrub & Grassland |
||||||
LR3.1 |
Ngau
Hom |
None |
None -
Baseline vegetation
coverage is approx. 0.5 ha |
N/A |
None |
None |
LR3.3 |
Ngau
Hom Shek |
None |
None -
Baseline vegetation coverage
is approx. 16.7 ha |
N/A |
None |
None |
LR3.4 |
Yuen
Tau Shan |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.02 ha -
Baseline vegetation
coverage is approx.32.7 ha |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and infrastructure |
|||||
LR3.5 |
Kau
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 1.1 ha |
N/A |
None |
None |
LR4 Low-lying Woodland/Plantation |
||||||
LR4.1 |
Ting
Ying Road & Tin Wah Road |
None |
None -
Baseline vegetation
coverage is approx. 3.8 ha |
N/A |
None |
None |
LR4.3 |
Ting
Ying Road & Ping Ha Road |
None |
None -
Baseline vegetation
coverage is approx. 1.6 ha |
N/A |
None |
None |
LR4.8 |
San
Sang San |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 2.1 ha -
Baseline vegetation
coverage is approx.15.8 ha -
Four Important Trees
are affected (688D-T1, 688D-T2, 785A-T1, 785A-T2) -
A total of approx. 83
trees are impacted |
Low |
Permanent, Irreversible |
Intermediate |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR4.11 |
Tin
Sam |
None |
None -
Baseline vegetation coverage
is approx. 0.6 ha |
N/A |
None |
None |
LR4.12 |
Powerline
Pylon |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.01 ha -
Baseline vegetation
coverage is approx.0.3 ha -
A total of approx. 1
tree is impacted |
Low |
Permanent, Irreversible |
Negligible |
Operation New road network replacing existing vegetation |
Operation -
Residual impacts from loss
of trees and vegetation due to the replacement with roads and infrastructure |
|||||
LR5 Low-lying Shrub & Grassland |
||||||
LR5.2 |
Sha
Kong Wai Tsai |
None |
None -
Baseline vegetation
coverage is approx. 7.2 ha |
N/A |
None |
None |
LR5.3 |
Fung
Kong Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 1.5 ha -
Baseline vegetation
coverage is approx.9.5 ha -
A total of approx. 31
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR5.5 |
San
Wai |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.5 ha -
Three Important Trees
are affected (278-T1, 278-T2,
& 278D-T1) -
Baseline vegetation
coverage is approx.1.6 ha -
A total of approx. 21
trees are impacted |
Low |
Permanent, Irreversible |
Large |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure Transplantation of three nos. of Important Trees |
|||||
LR5.6 |
San
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 2.6 ha |
N/A |
None |
None |
LR5.7 |
San
Sang Tsuen |
None |
None -
Baseline vegetation coverage
is approx. 0.5 ha |
N/A |
None |
None |
LR5.8 |
Chung
Uk |
None |
None -
Baseline vegetation
coverage is approx.1.6 ha |
N/A |
None |
None |
LR5.9 |
Yick
Yuen Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 2.0 ha -
Baseline vegetation
coverage is approx.12.4 ha -
A total of approx. 81
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network replacing
existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR5.10 |
Tuen
Mun San Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 1.0 ha |
N/A |
None |
None |
LR5.11 |
Tsing
Chuen Wai |
None |
None -
Baseline vegetation
coverage is approx.0.4 ha |
N/A |
None |
None |
LR6 Vegetation on Agricultural Land |
||||||
LR6.1 |
Sha
Kong Wai |
None |
None -
Baseline vegetation
coverage is approx. 1.2 ha |
N/A |
None |
None |
LR6.3 |
Ha
Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 3.7 ha |
N/A |
None |
None |
LR6.5 |
Shek
Po Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 2.4 ha |
N/A |
None |
None |
LR6.6 |
San
Sang San Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 1.3 ha -
Baseline vegetation
coverage is approx.19.3 ha -
A total of approx. 44
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR6.7 |
Ling
To |
Construction -
Site clearance works -
Construction of the temporary
structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.02 ha -
Baseline vegetation
coverage is approx.3.2 ha -
A total of approx. 1
tree is impacted |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR6.9 |
Wo
Ping San Tsuen & Nai Wai |
None |
None -
Baseline vegetation coverage
is approx. 0.7 ha |
N/A |
None |
None |
LR6.10 |
Tin
Sam |
None |
None -
Baseline vegetation
coverage is approx. 4.5 ha |
N/A |
None |
None |
LR6.11 |
Yick
Yuen Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.2 ha -
Baseline vegetation
coverage is approx.2.1 ha -
A total of approx. 8
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR6.12 |
KSWH
South |
None |
None -
Baseline vegetation
coverage is approx. 1.0 ha |
N/A |
None |
None |
LR7 Vegetation within Residential Developments |
||||||
LR7.1 |
Developments
in TSW |
None |
None -
Baseline vegetation
coverage is approx. 5.7 ha |
N/A |
None |
None |
LR7.5 |
The
Sherwood |
None |
None -
Baseline vegetation
coverage is approx. 1.3 ha |
N/A |
None |
None |
LR8 Vegetation within Rural Villages |
||||||
LR8.2 |
San
Hing Tsuen / Ngau Hom / Sha Kong Wai |
None |
None -
Baseline vegetation
coverage is approx. 7.9 ha |
N/A |
None |
None |
LR8.5 |
Sik
Kong Tsuen / Hong Mei Tsuen /
Tsueng Kong Wai |
None |
None -
Baseline vegetation coverage
is approx. 4.0 ha |
N/A |
None |
None |
LR8.6 |
Sik
Kong Wai / San Uk Tsuen / Ha Tsuen Shi |
None |
None -
Baseline vegetation
coverage is approx. 4.4 ha |
N/A |
None |
None |
LR8.8 |
Sha
Chau Lei |
None |
None -
Baseline vegetation
coverage is approx. 0.6 ha |
N/A |
None |
None |
LR8.11 |
San
Sang Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.0 5ha -
Baseline vegetation coverage
is approx.3.4 ha -
A total of approx. 3
trees are impacted |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR8.12 |
San
Lee Uk Tsuen / Tim Sam |
None |
None -
Baseline vegetation
coverage is approx.2.5 ha |
N/A |
None |
None |
LR8.13 |
HSK |
None |
None -
Baseline vegetation
coverage is approx. 1.1 ha |
N/A |
None |
None |
LR8.14 |
Tim
Sam |
None |
None -
Baseline vegetation
coverage is approx. 10.5 ha |
N/A |
None |
None |
LR8.17 |
Tan
Kwei Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 1.0 ha |
N/A |
None |
None |
LR8.18 |
Wo
Ping San Tsuen / Cheung Uk Tsuen / Arkadia |
None |
None -
Baseline vegetation
coverage is approx. 11.3 ha |
N/A |
None |
None |
LR8.19 |
Yick
Yuen Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 1.1 ha -
Baseline vegetation
coverage is approx. 11.9 ha -
A total of approx. 41
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR8.20 |
Tsing
Chuen Wai / Tuen Tsz Wai |
None |
None -
Baseline vegetation
coverage is approx. 5.4 ha |
N/A |
None |
None |
LR8.21 |
Lam
Tei / Tuen Mun San Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 5.3 ha |
N/A |
None |
None |
LR9 Vegetation within Industrial Land / Open
Storage |
||||||
LR9.2 |
Lau
Fau Shan Road |
None |
None -
Baseline vegetation
coverage is approx. 2.3 ha |
N/A |
None |
None |
LR9.3 |
Ping
Ha Road |
Construction -
Site clearance works -
Construction of the temporary
structures and working areas -
Construction of Road
DP2 |
Construction -
Loss of vegetation of
approx. 0.1 ha -
Baseline vegetation
coverage is approx. 2.9 ha -
A total of approx. 7
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.4 |
Fung
Kwong Tsuen Road / Deep Bay Road |
None |
None -
Baseline vegetation
coverage is approx. 9.7 ha |
N/A |
None |
None |
LR9.6 |
Ping
Ha Road / Tin Yip Road |
None |
None -
Baseline vegetation
coverage is approx. 0.9 ha |
N/A |
None |
None |
LR9.7 |
Tseung
Kong Wai |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 1.2 ha -
Baseline vegetation
coverage is approx. 9.7 ha -
A total of approx. 40
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network replacing
existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.8 |
Ping
Ha Road / Tin Ha Road |
None |
None -
Baseline vegetation
coverage is approx. 5.1 ha |
N/A |
None |
None |
LR9.9 |
Ha Tsuen
Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 1.3 ha -
Baseline vegetation
coverage is approx. 9.3 ha -
One Important Tree is
affected (224-T1) -
A total of approx. 63
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.10 |
Hung
Tin Road / Hung Chi Road |
None |
None -
Baseline vegetation
coverage is approx. 0.1 ha |
N/A |
None |
None |
LR9.11 |
Sik
Kong Wai Road / Ha Tsuen Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.1 ha -
Baseline vegetation
coverage is approx. 2.3 ha -
A total of approx. 10
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.12 |
SW
STW Ha Tsuen Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.06 ha -
Baseline vegetation
coverage is approx. 0.4 ha -
A total of approx. 12
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.16 |
San
Lee Uk Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.7 ha |
N/A |
None |
None |
LR9.17 |
Kau
Lee Uk Tsuen / San Sang Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.1 ha -
Baseline vegetation
coverage is approx. 11.4 ha -
A total of approx. 3
trees are impacted |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.18 |
Yick
Yuen Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the Roads
P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.2 ha -
Baseline vegetation
coverage is approx. 1.2 ha -
A total of approx. 17
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR9.19 |
KSWH
South |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the Roads
P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.3 ha -
Baseline vegetation
coverage is approx. 1.0 ha -
A total of approx. 23
trees are impacted |
Low |
Permanent, Irreversible |
Intermediate |
Operation -
New road network replacing
existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LR10 Water Course |
||||||
LR10.1 |
TSW
River Channel |
None |
None -
Baseline nullah area is
approx. 15.3 ha |
N/A |
None |
None |
LR10.2 |
Hang
Hau Tsuen Nullah |
None |
None -
Baseline nullah area is
approx. 0.3 ha |
N/A |
None |
None |
LR10.3 |
Tung
Tau Tsuen Nullah |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of nullah of
approx. 0.02 ha -
Baseline nullah area is
approx. 0.2 ha |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of nullah and
vegetation -
Residual impacts from
loss of water and vegetation due
to the replacement with roads and infrastructure |
|||||
LR10.4 |
Ping
Ha Road Nullah |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the Roads
P1 and Roads D1 ¡V D7 |
Construction -
Loss of nullah of
approx. 0.02 ha -
Baseline nullah area is
approx. 0.8 ha |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of nullah and
vegetation -
Residual impacts from
loss of water and vegetation due
to the replacement with roads and infrastructure |
|||||
LR10.5 |
Sik
Kong Tsuen / Tsueng Kong Wai Nullah |
None |
None -
Baseline nullah area is
approx. 0.3 ha |
N/A |
None |
None |
LR10.6 |
Sik
Kong Wai / Ling To Nullah |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of nullah of
approx. -
Baseline nullah area is
approx. 0.9 ha -
A total of approx. 1
tree is impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of nullah and
vegetation -
Residual impacts from
loss of water and vegetation due
to the replacement with roads and infrastructure |
|||||
LR10.7 |
Yuen
Tau Shan Streams |
None |
None -
Baseline nullah area is
approx. 0.1 ha |
N/A |
None |
None |
LR10.8 |
Hung
Tin Road Nullah |
None |
None -
Baseline nullah area is
approx. 0.08 ha |
N/A |
None |
None |
LR10.10 |
Shek
Po Channel |
None |
None -
Baseline nullah area is
approx. 1.1 ha |
N/A |
None |
None |
LR10.11 |
Shek
Po Channel |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of nullah of
approx. 0.01 ha -
Baseline nullah area is
approx. 2.6 ha |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of nullah and
vegetation -
Residual impacts from
loss of water and vegetation due
to the replacement with roads and infrastructure |
|||||
LR10.12 |
San
Sang San Tsuen Channel |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of nullah of
approx. -
Baseline nullah area is
approx. 0.5 ha |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of nullah and
vegetation -
Residual impacts from
loss of water and vegetation due
to the replacement with roads and infrastructure |
|||||
LR10.13 |
Yick
Yuen Tsuen / Tsign Chuen Wai Nullah |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of nullah of
approx. -
Baseline nullah area is
approx. 1.2 ha |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of nullah and
vegetation -
Residual impacts from
loss of water and vegetation due
to the replacement with roads and infrastructure |
|||||
LR11 Vegetation within Urban Park |
||||||
LR11.1 |
Parks
in TSW |
None |
None -
Baseline vegetation
area is approx. 1.3 ha |
N/A |
None |
None |
LR11.2 |
Ping
Ha Road Garden |
None |
None -
Baseline vegetation
area is approx. 0.2 ha |
N/A |
None |
None |
LR11.4 |
Tin
Ha Road Playground |
None |
None -
Baseline vegetation
area is approx. 0.1 ha |
N/A |
None |
None |
LR11.5 |
Nai Wai
Soccer Pitch / Fuk Hang Tsuen Road Garden |
None |
None -
Baseline vegetation
area is approx. 1.5 ha |
N/A |
None |
None |
LR12 Vegetation on Modified Slopes |
||||||
LR12.1 |
Hang
Hau Tsuen |
None |
None -
Baseline vegetation
area is approx. 0.4 ha |
N/A |
None |
None |
LR12.2 |
Ha Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Slope upgrading works |
Construction -
Loss of vegetation of
approx. 0.2 ha -
Baseline vegetation
area is approx. 3.1 ha -
A total of approx. 27
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the replacement
with roads and infrastructure |
|||||
LR12.3 |
Yick
Yuen Tsuen |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Slope upgrading works |
Construction -
Loss of vegetation of
approx. 0.3 ha -
Baseline vegetation
area is approx. 1.2 ha -
A total of approx. 31
trees are impacted |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the
replacement with roads and infrastructure |
|||||
LR13 Vegetation along TSW Promenade |
||||||
LR13.0 |
Vegetation
along TSW Promenade |
None |
None -
Baseline vegetation
coverage is approx.4.4 ha |
N/A |
None |
None |
LR14 Roadside Vegetation |
||||||
LR14.2 |
Tin
Shui Road |
None |
None -
Baseline vegetation
coverage is approx. 1.3 ha |
N/A |
None |
None |
LR14.3 |
Tin
Ying Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Construction of noise
barriers/enclosures |
Construction -
Loss of vegetation of
approx. 0.6 ha -
Baseline vegetation
area is approx. 12.1 ha -
A total of approx. 194
trees are impacted |
High |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the
replacement with roads and infrastructure |
|||||
LR14.4 |
Lau
Fau Shan Road |
None |
None -
Baseline vegetation coverage
is approx. 0.4 ha |
N/A |
None |
None |
LR14.6 |
Ping
Ha Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Construction of noise
barrier/enclosure |
Construction -
Loss of vegetation of
approx. 0.9 ha -
Baseline vegetation
area is approx. 3.1 ha -
A total of approx. 121
trees are impacted |
High |
Permanent, Irreversible |
Intermediate |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the
replacement with roads and infrastructure |
|||||
LR14.7 |
Hung
Tin Road |
None |
None -
Baseline vegetation
coverage is approx. 0.1 ha |
N/A |
None |
None |
LR14.8 |
Tin
Ha Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.05 ha -
Baseline vegetation
area is approx. 1.2 ha -
A total of approx. 6
trees are impacted |
High |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the
replacement with roads and infrastructure |
|||||
LR14.9 |
Ha
Tsuen Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.7 ha -
Baseline vegetation
area is approx. 0.9 ha -
A total of approx. 116 trees
are impacted |
High |
Permanent, Irreversible |
Large |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the
replacement with roads and infrastructure |
|||||
LR14.10 |
Castle
Peak Road |
None |
None -
Baseline vegetation
coverage is approx. 2.2 ha |
N/A |
None |
None |
LR14.12 |
HSK
Tin Sam Road / Hung Yuen Road |
None |
None -
Baseline vegetation
coverage is approx. 0.4 ha |
N/A |
None |
None |
LR14.13 |
Yick
Yuen Road |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of vegetation of
approx. 0.02 ha -
Baseline vegetation
area is approx. 0.2 ha -
A total of approx. 2
trees are impacted |
High |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Loss of vegetation -
Residual impacts from
loss of vegetation due to the
replacement with roads and infrastructure |
|||||
LR14.14 |
KSWH |
None |
None -
Baseline vegetation
coverage is approx. 1.9 ha |
N/A |
None |
None |
LR15 Water Bodies |
||||||
LR15.2 |
Sha
Kong Tsuen |
None |
None -
Baseline area is
approx. |
N/A |
None |
None |
LR15.5 |
Sik
Kong Tsuen |
None |
None -
Baseline area is
approx. |
N/A |
None |
None |
LR15.6 |
Tseung
Kong Wai |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 |
Construction -
Loss of area of approx.
0.1 ha -
Baseline area is
approx. |
Low |
Permanent, Irreversible |
Large |
Operation -
New road network
replacing existing water and vegetation |
Operation -
Loss of water body and
vegetation -
Replacement of existing
water and vegetation with roads and infrastructure |
|||||
LR15.10 |
Ling
To |
Construction -
Site clearance works -
Construction of the
temporary structures and working areas -
Construction of Roads
DP1, 5 and 12 |
Construction -
Baseline area coverage
is approx. 0.6 ha |
Low |
Temporary (Medium term) |
Small |
Operation -
New road network replacing
existing vegetation |
Operation -
Reduced abundance of
vegetation caused by the shadowing effect from Road DP1 |
|||||
LR15.11 |
Tuen
Tsz Wai |
None |
None -
Baseline area coverage
is approx. 0.3 ha |
N/A |
None |
None |
LR 15.12 |
San
Sang San Tsuen |
None |
None -
Baseline area coverage
is approx. 0.3 ha |
N/A |
None |
None |
LR17 Marsh |
||||||
LR17.2 |
Fung
Kong Tsuen |
None |
None -
Baseline vegetation
coverage is approx. 0.6 ha |
N/A |
None |
None |
Landscape Character Areas |
||||||
LCA1 |
Miscellaneous Rural Fringe Landscape |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Night lighting |
Construction -
Loss of vegetation of
approx. 41.4 ha -
Baseline vegetation
coverage is approx. 512.5 ha -
Change of landscape
quality |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from loss
of trees and vegetation due to the replacement with roads and infrastructure |
|||||
LCA2 |
Miscellaneous
Urban Fringe Landscape |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Night lighting |
Construction -
Loss of vegetation of
approx. 7.0 ha -
Baseline vegetation
coverage is approx. 97.7 ha -
Change of landscape
quality |
Medium |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and
infrastructure |
|||||
LCA3 |
Residential
Urban Landscape |
None |
None -
Baseline vegetation
coverage is approx. 74.6 ha |
N/A |
None |
None |
LCA4 |
Upland and Hillside Landscape |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.5 ha -
Baseline vegetation
coverage is approx. 205.3 ha -
Change of landscape
quality |
Low |
Permanent, Irreversible |
Small |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from loss
of trees and vegetation due to the replacement with roads and infrastructure |
|||||
LCA5 |
Settled
Valley Landscape |
None |
None -
Baseline vegetation
coverage is approx. 8.4 ha |
N/A |
None |
None |
LCA6 |
Rural
Coastal Plane Landscape |
Construction -
Site clearance works -
Presence of
construction equipment -
Construction of the
temporary structures and working areas -
Construction of the
Roads P1 and Roads D1 ¡V D7 -
Night lighting |
Construction -
Loss of vegetation of
approx. 0.5 ha -
Baseline vegetation
coverage is approx. 32.7 ha -
Change of landscape
quality |
Low |
Permanent, Irreversible |
Negligible |
Operation -
New road network
replacing existing vegetation |
Operation -
Residual impacts from
loss of trees and vegetation due to the replacement with roads and infrastructure |
Table 11.6 Proposed
Construction Phase Landscape and Visual Mitigation Measures (DP1, DP2, DP5, DP6
and DP12)
ID No. |
Landscape and Visual Mitigation Measures |
Capital Funding Agency |
Implementation Agency** |
CM1 |
Minimised
construction area and contractor¡¦s temporary works areas The
construction area and contractor¡¦s temporary works areas should be minimised. General Good Practice Measures - For areas unavoidably disturbed by the Project on a short-term basis e.g. works areas, the general principle to try and restore these to their former state to suit future land use, should be adhered to. |
CEDD |
Government (via Contractor) |
CM2 |
Stripping
and storing of topsoil Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where practical. The Contract Specification shall include storage and reuse of topsoil as appropriate. On potentially contaminated sites (as per Section 8) where investigation results indicate soil contamination is present, the use of contaminated soils for planting is to be avoided where appropriate. |
CEDD |
Government (via Contractor) |
CM3 |
Protection
of existing trees Tree
Protection & Preservation ¡V Existing trees to be retained within the
Project Site should be carefully protected during construction. Detailed Tree
Protection Specification shall be provided in the Contract Specification.
Under this specification, the Contractor shall be required to submit, for
approval, a detailed working method statement for the protection of trees
prior to undertaking any works adjacent to all retained trees, including
trees in Contractor¡¦s works areas. A detailed tree survey will be carried out for the Tree Removal Application (TRA) process which will be carried out at the later detailed design stage of the Project. The detailed tree survey will propose which trees should be retained, transplanted or felled and will include details of tree protection measures for those trees to be retained. |
CEDD |
Government (via Contractor) |
CM4 |
Transplantation
of existing trees where practical Trees unavoidably affected by the Project works should be transplanted where practical. Trees should be transplanted straight to their final receptor site and not held in a temporary nursery as far as possible. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, where applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the Project programme. A detailed
transplanting proposal will be submitted to relevant Government departments
for approval in accordance with DEVB TCW Nos 6/2015 and 7/2015 and final
locations of transplanted trees should be agreed prior to commencement of the
work. For trees associated with highways e.g. roadside planting along highways, that are unavoidably affected and should be transplanted, HyD HQ/GN/13 ¡¥Interim Guidelines for Tree Transplanting Works under Highways Department's Vegetation Maintenance Ambit¡¦ should be referred to. |
CEDD |
Government (via Contractor) |
CM5 |
Control of night-time lighting Control of night-time lighting and glare by hooding all lights. Construction day and night time lighting should be controlled to
minimise glare impact to adjacent VSRs during the construction phase. |
CEDD |
Government (via Contractor) |
CM6 |
Construction of decorative hoarding around construction works Erection of decorative mesh screens or construction hoardings around
works areas in visually unobtrusive colours. Screen hoarding shall be erected along areas of the construction works
site boundary where the works site borders publically accessible routes
and/or is close to visually sensitive receivers (VSRs). It is proposed that
the screening be compatible with the surrounding environment and where
possible, non-reflective, recessive colours be used. |
CEDD |
Government (via Contractor) |
CM7 |
Reduction of construction period to practical minimum Options to reduce the construction period to practical minimum to be
provided. |
CEDD |
Government (via Contractor) |
CM8 |
Prevention of run-off Limitation of / Ensuring no run-off into surrounding landscape and prohibit
run-off from entering adjacent water bodies and waterways |
CEDD |
Government (via Contractor) |
CM9 |
Phasing of construction stage Phasing of the construction stage to reduce visual impacts. |
CEDD |
Government (via Contractor) |
CM10 |
Advance screen planting Advance screen planting of fast growing tree and shrub species to
noise barriers and hoardings. Trees shall be capable of reaching a height
>10m within 10 years. |
CEDD |
Government (via Contractor) |
CM11 |
Minimise disturbance footprints To minimise landscape and visual impacts, the footprint and elevation
of such elements should be optimised to reduce topographical/ landform
changes, as well as reduce land take and interference with natural terrain.
Where there is a need to significantly cut into the existing landform,
retaining walls should be considered as well as cut slopes, to minimise
landform changes and land resumption, while also considering visual amenity.
Earthworks and engineered slopes should be designed to be a visually
interesting landform, compatible with the surrounding landscape and to mimic
the natural contouring and terrain e.g. introduction and continuation of
natural features such as spurs and ridges where appropriate, to support
assimilation with the hillside setting. |
CEDD |
Government (via Contractor) |
CM12 |
Protection of existing water courses For all the natural rivers and streams inside the development area,
consideration of protection measures should be made to minimise any impacts
from the construction works. Avoid affecting watercourses ¡V In the detailed design, consideration
should be made of watercourses, to minimise any impacts e.g. at new bridge
crossings, viaducts, road alignment etc. Guidelines stated should be
followed. Bridges and box culverts should also be used to minimise the necessity
of watercourse modification and protect the watercourses where necessary. |
CEDD |
HyD/CEDD |
CM13 |
Hydroseeding on modified slopes Hydroseeding of modified slopes should be done as soon as grading
works are completed to prevent erosion and subsequent loss of landscape
resources and character. Woodland tree seedlings and/ or shrubs should be
planted where slope gradient and site conditions allow. In addition, landscape planting should be provided for the retaining
structures associated with modified slopes where conditions allow. All slope landscaping works should comply with GEO Publication No.
1/2011-Technical Guidelines on Landscape Treatment for Slopes. |
CEDD |
HyD/CEDD |
CM14 |
Integrate Open Space Network with existing nullah conditions For watercourses affected during construction, measures should be
sought to minimise the impact with respect to the existing nullah conditions,
existing shrubs and trees along the banks. |
CEDD |
HyD/CEDD |
*Management and Maintenance Agencies are identified as per DEVB TCW No. 6/2015
**CEDD will only be responsible for construction of the site formation and
essential infrastructure
Table 11.7 Proposed
Operation Phase Landscape and Visual Mitigation Measures (DP1, DP2, DP5, DP6
and DP12)
ID No. |
Landscape and Visual Mitigation Measures |
Capital Funding Agency |
Implementation Agency** |
Management Agency* |
Maintenance Agency* |
OM1 |
Compensatory tree planting where practical Compensatory Planting ¡V Compensatory tree planting for felled trees shall
be provided to the satisfaction of relevant Government departments. Required
numbers and locations of compensatory trees shall be determined and agreed
separately with Government during the Tree Removal Application process under
ETWBTC 7/2015. Compensatory planting is proposed at the potential open areas such as
open spaces, amenity areas, open areas of the streetscapes, as well as the
open areas within development lots. Tree compensation within the HSK NDA will be provided at a 1:1 ratio.
This means that for every tree that is removed, a new one will be planted.
Furthermore, trees affected by DPs will be compensated within their
respective DP areas. |
CEDD |
CEDD/HyD |
HyD/ LCSD |
HyD/ LCSD |
OM3 |
Sensitive design of hardscape elements along
roadsides Streetscape elements along new and existing roads (e.g. paving, signage, street furniture, lighting etc.) shall be sensitively designed in a manner that responds to the existing and planned urban context. |
CEDD |
CEDD/HyD |
HyD |
HyD |
OM4 |
Reinstatement of streetscape elements All streetscape areas and hard and soft landscape areas disturbed during construction shall be reinstated to equal or better quality, to the satisfaction of the relevant Government departments. |
CEDD |
CEDD/HyD |
HyD/ LCSD |
HyD/ LCSD |
OM6 |
Quality greening along roadside amenity strips Shade trees, ornamental tree / shrub / climber planting should be provided along roadside amenity strips to enhance the townscape quality. Provision of utlitiy free planting strips for quality planting shall be adopted according to DEVB TCW 2/2012. |
CEDD |
CEDD/HyD |
HyD/ LCSD |
HyD/ LCSD |
OM7 |
Design
of street lighting Appropriate design of street lighting to avoid glare and light pollution to surrounding areas. |
CEDD |
CEDD/HyD |
HyD |
HyD |
OM10 |
Sensitive design of noise barriers and enclosures The visual impact of noise barriers & enclosures will be mitigated by appropriate detailed design, including suitable combination of transparent and sound absorbent materials, appropriate colour selection of panels and supporting structures, or provision of at-grade planting of trees, shrubs and/or climbers camouflage to the barriers, as well as design of supporting structures to incorporate a high level of quality and aesthetics. A combination of transparent panels at top and solid panels at bottom would lighten the visual impact, and at the same time maintain the attractiveness by using colourful panels. (refer Figure 11.64) |
CEDD |
CEDD/HyD |
HyD |
HyD |
OM14 |
Greening of viaduct structures and noise barriers Aesthetic improvement of viaduct structures and noise barriers through greening of structure where feasible and appropriate to mitigate visual impact of viaduct/noise barrier form. |
CEDD |
CEDD/HyD |
HyD/LCSD |
HyD/LCSD |
*Management and Maintenance Agencies are identified as per DEVB TCW No. 6/2015. Agreement from individual agent shall be sought at
detailed design stage.
**CEDD will only be responsible for construction of the site formation and
essential infrastructure
Note: The Contractor shall
be responsible for the maintenance of the soft landscape works during the
establishment period at operation phase. The project proponent shall then be responsible
for the management and maintenance of the soft landscape work until such time
those are successfully handed over to the designated agent/department.
Programme of Implementation of Landscape and Visual Mitigation Measures
Table 11.8
Significance of Landscape Impacts in Construction and Operation Phases (DP1,
DP2, DP5, DP6 and DP12)
ID No. |
Landscape
Resources / Landscape Character |
Sensitivity (Low, Medium, High) |
Magnitude of Change (None,
Negligible, Small, Intermediate, Large)* |
Impact Significance BEFORE Mitigation (None,
Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual
Impact Significance AFTER
Mitigation (None,
Insubstantial, Slight, Moderate, Substantial) |
||||||||||||
|
Construction |
Operation |
||||||||||||||||
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
|||||||||||||
LR2
Hillside Woodland |
||||||||||||||||||
2.2 |
Ngau
Hom |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
2.3 |
Hang
Hau Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
2.4 |
Ngau
Hom Shek |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
2.6 |
Tung
Tau Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
2.7 |
Ha
Tsuen Road |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
2.8 |
Ha
Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
2.9 |
Yuen
Tau Tsuen |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4, 8,
9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
2.11 |
Kau
Lee Uk Tsuen |
High |
Small |
Small |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
2.12 |
San
Sang Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR3
Hillside Shrub & Grassland |
||||||||||||||||||
3.1 |
Ngau
Hom |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
3.3 |
Ngau
Hom Shek |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
3.4 |
Yuen
Tau Shan |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
3.5 |
Kau
Lee Uk Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR4
Low-lying Woodland/Plantation |
||||||||||||||||||
4.1 |
Ting
Ying Road & Tin Wah Road |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
4.3 |
Ting
Ying Road & Ping Ha Road |
Negligible |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
4.8 |
San
Sang San |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
4.11 |
Tin
Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
4.12 |
Powerline
Pylon |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
LR5
Grassland |
||||||||||||||||||
5.2 |
Sha
Kong Wai Tsai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
5.3 |
Fung
Kong Tsuen |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
5.5 |
San
Wai |
High |
Large |
Large |
Substantial |
Substantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Substantial |
Substantial |
Substantial |
||||||||
5.6 |
San
Lee Uk Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
5.7 |
San
Sang Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
5.8 |
Chung
Uk |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
5.9 |
Yick
Yuen Tsuen |
High |
Small |
Small |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
5.10 |
Tuen
Mun San Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
5.11 |
Tsing
Chuen Wai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR6
Vegetation on Agricultural Land |
||||||||||||||||||
6.1 |
Sha
Kong Wai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
6.3 |
Ha
Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
6.5 |
Shek
Po Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
6.6 |
San
Sang San Tsuen |
High |
Small |
Small |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
6.7 |
Ling
To |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
6.9 |
Chung
Uk Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
6.10 |
Tin
Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
6.11 |
Yick
Yuen Tsuen |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
6.12 |
KSWH
South |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR7
Vegetation within Residential Developments |
||||||||||||||||||
7.1 |
Developments
in TSW |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
7.5 |
The
Sherwood |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR8
Vegetation within Rural Village |
||||||||||||||||||
8.2 |
San
Hing Tsuen/ Ngau Hom / Sha Kong Wai |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.5 |
Sik
Kong Tsuen/ Hong Mei Tsuen/ Tseung Kong Wai |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.6 |
Sik
Kong Wai / San Uk Tsuen / Ha Tsuen Shi |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.8 |
Sha
Chau Lei |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.11 |
San
Sang Tsuen |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
8.12 |
San
Lee Uk Tsuen / Tim Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.13 |
HSK |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.14 |
Tim
Sam |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.17 |
Tan
Kwei Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.18 |
Wo
Ping San Tsuen / Cheung Uk Tsuen / Arkadia |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.19 |
Yick
Yuen Tsuen |
Medium |
Small |
Small |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
8.20 |
Tsing
Cheun Wai / Tuen Tsz Wai |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
8.21 |
Fuk
Hang Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR9
Vegetation within Industrial Land / Open Storage |
||||||||||||||||||
9.2 |
Lau
Fau Shan Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
9.3 |
Ping
Ha Road |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
9.4 |
Fung
Kwong Tsuen Road / Deep Bay Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
9.6 |
Ping
Ha Road / Tin Yip Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
9.7 |
Tseung
Kong Wai |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
9.8 |
Ping
Ha Road / Tin Ha Road |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
9.9 |
Ha
Tsuen Road |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
9.10 |
Hung
Tin Road / Hung Chi Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
9.11 |
Sik
Kong Wai Road / Ha Tsuen Road |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
9.12 |
SW
STW / Ha Tsuen Road |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
9.16 |
San
Lee Uk Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
9.17 |
Kau
Lee Uk Tsuen / San Sang Tsuen |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
9.18 |
Yick
Yuen Road |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
9.19 |
KSWH
South |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
LR10
Water Course |
||||||||||||||||||
10.1 |
TSW
River Channel |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
10.2 |
Hang
Hau Tsuen Nullah |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
10.3 |
Tung
Tau Tsuen Nullah |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
10.4 |
Ping
Ha Road Nullah |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
10.5 |
Sik
Kong Tsuen / Tsueng Kong Wai Nullah |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
10.6 |
Sik
Kong Wai / Ling To Nullah |
Medium |
Small |
Small |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
10.7 |
Yuen
Tau Shan Streams |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
10.8 |
Hung
Tin Road Nullah |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
10.10 |
Shek
Po Channel |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
10.11 |
Tin
Sam Channel |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
10.12 |
San
Sang San Tsuen Channel |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
10.13 |
Yick
Yuen Tsuen / Tsing Chuen Wai Nullah |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
LR11
Vegetation within Urban Park |
||||||||||||||||||
11.1 |
Parks
in TSW |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
11.2 |
Ping
Ha Road Garden |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
11.4 |
Tin
Ha Road Playground |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
11.5 |
Nai
Wai Soccer Pitch / Fuk Hang Tsuen Road Garden |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR12
Vegetation on Modified Slopes |
||||||||||||||||||
12.1 |
Hang
Hau Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
12.2 |
Ha
Tsuen |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
12.3 |
Yick
Yuen Tsuen |
Low |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
LR13
Vegetation along TSW Promenade |
||||||||||||||||||
13.0 |
Vegetation
along TSW Promenade |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR14
Roadside Vegetation |
||||||||||||||||||
14.2 |
Tin
Shui Road |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
14.3 |
Tin
Ying Road |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
14.4 |
Lau
Fau Shan Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
14.6 |
Ping
Ha road |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
14.7 |
Hung
Tin Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
14.8 |
Tin
Ha Road |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
14.9 |
Ha
Tsuen Road |
Medium |
Large |
Large |
Substantial |
Substantial |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Substantial |
Substantial |
Moderate |
||||||||
14.10 |
Castle
Peak Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
14.12 |
HSK
Tin Sam Road / Hung Yuen Road |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
14.13 |
Yick
Yuen Road |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
14.14 |
KSWH |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR15
Water Bodies |
||||||||||||||||||
15.2 |
Sha
Kong Tsuen |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
15.5 |
Sik
Kong Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
15.6 |
Tseung
Kong Wai |
Low |
Large |
Large |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
15.10 |
Ling
To |
High |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Slight |
||||||||
15.11 |
Tuen
Tsz Wai |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
15.12 |
San Sang San Tsuen |
Low |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR17
Marsh |
||||||||||||||||||
17.2 |
Fung
Kong Tsuen |
High |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LR18
Important Trees |
||||||||||||||||||
18 |
|
High |
|
|
|
|
|
|
|
|
||||||||
Landscape
Character Areas |
||||||||||||||||||
LCA1 |
Miscellaneous
Rural Fringe Landscape |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
LCA2 |
Miscellaneous
Urban Fringe Landscape |
Medium |
Small |
Small |
Slight |
Slight |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Slight |
Slight |
Insubstantial |
||||||||
LCA3 |
Residential
Urban Landscape |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LCA4 |
Upland
and Hillside Landscape |
High |
Small |
Small |
Moderate |
Moderate |
CM1, 2, 3, 4,
8, 9, 10, 11,12, 13, 14, OM1, 4, 6, 13, 14 |
Moderate |
Moderate |
Slight |
||||||||
LCA5 |
Settled
Valley Landscape |
Medium |
None |
None |
None |
None |
Not Required |
None |
None |
None |
||||||||
LCA6 |
Rural
Coastal Plane Landscape |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
Not required |
Insubstantial |
Insubstantial |
Insubstantial |
||||||||
Zone of Visual Influence (ZVI)
Key Positive Visual Elements
¡P TSW River Channel, Tim Sam Channel, and Shek Po Channel
¡P Ridgelines of Yuen Tau Shan, along the northern boundary of the Project, and to the south of the Project area
¡P Several scattered vegetated woodland hillsides rising above the valley bottom
¡P TSW Promenade and associated vegetation
¡P Vegetation associated with rural agriculture and village areas
¡P Ling To Temple and nearby valley environment
Key Negative Visual Elements
¡P Scattered, haphazard areas of light industrial sheds, buildings, and storage yards
¡P Haphazard placement of port back up storage yards
¡P Presence of and traffic along the KSWH, Yuen Long Highway, and Castle Peak Road
Visually Sensitive Receivers (VSRs)
¡P Type of VSR. VSRs are categorised according to whether the viewer is at home, at work or school, at play or leisure, or travelling. (Ranked by the major VSR types, as described below)
- Residential VSRs ¡V These VSRs are people living in the area and who view the proposed Project from their homes. They are considered the most sensitive VSRs due to the character of the view from their homes having a substantial effect on their perception of quality and acceptability of their home environment and general quality of life.
- Occupational VSRs ¡V These VSRs are people working or in education in the area, who view the proposed Project from their workplace or education centre. Visual amenity is in general not considered a top priority within the average workplace and these VSRs are considered to be relatively less sensitive than residential VSRs as their view will have a less important, although still material, effect on their perception of quality of life. The degree to which this applies to workers depends on whether their location is industrial, retail or commercial. The VSRs in industrial areas, such as factories, are generally considered to be the least sensitive, due to the relatively low quality of their existing view in an industrial area.
- Recreational VSRs ¡V These VSRs are people engaging in recreational activities such as hikers on established trails and footpaths, people participating in team sports at recreation grounds or at leisure. Sensitivity of these VSRs depends on duration of stay, nature of the activity and how enclosed the location is.
- Travelling VSRs ¡V These VSRs are people travelling on public roads and railways, both in public and private vehicles and on foot. They have varying sensitivity depending on the speed, nature and frequency of travel, but are generally considered to be transitory to the area with less regard for the surrounding views and with low sensitivity.
¡P Number of individuals (Ranked as very many, many, few or very few)
- Higher number of individuals within a VSR contributes to an increase in the level of sensitivity for that VSR
¡P Quality of existing view (Ranked as good, fair or poor)
- Good quality existing views contribute to an increase in the levels of sensitivity for that VSR, while poor quality views contribute to a decrease
¡P Availability of alternative views (Ranked as yes or no)
- The absence of alternative views contributes to an increase in sensitivity for the respective VSR as the importance of the existing view is heightened
¡P Degree of visibility / distance between VSR & nearest source(s) of impact (Ranked as full, partial or obscured)
- VSRs with full views have a greater exposure than partial and obscured views, and this contributes to an increased level of sensitivity, as does the VSR¡¦s proximity to the nearest source of impact
¡P Duration of view (Ranked temporary or permanent)
- VSRs with permanent duration of views have a longer exposure than those with a temporary duration, contributing to an increased level of sensitivity
¡P Frequency of view (Ranked intermittent or continuous)
- VSRs with a continuous frequency of views have a higher awareness than those with an intermittent duration, contributing to an increased level of sensitivity
High: The VSR is highly sensitive to any change in the viewing experience
(e.g. residential, recreational and travelling VSRs where the principle view is
of the development site, formalised public viewpoints or the landscape);
Medium: The VSR is moderately sensitive to any change in the viewing experience
(e.g. residential, recreational, occupational and travelling VSRs where the
secondary view is of the development); and
Table 11.9 Sensitivity
of VSRs (DP1, DP2, DP5, DP6 and DP12)
VSR ID |
Key VSR |
Number of Individuals (Very Few, Few, Many, Very Many) |
Quality of Existing View (Good,
Fair, Poor) |
Availability of
Alternative Views (Yes / No) |
Duration and Frequency of Views to Source(s) of
Impact (Temporary/Permanent
& Intermittent/Continuous) |
Degree of Visibility of Source(s) of Visual Impact (Full, Partial,
Obscured) & Distance
Between VSR & Nearest Source(s) of Impact |
Sensitivity of the VSR (High/
Medium/Low) |
||
Construction |
Operation |
Construction |
Operation |
||||||
RES-1 |
Residents in West TSW (Tin Yan Estate, Tin Wah Estate, Tin Shui
Estate, Tin Oi Court, Locwood Court, Tin Shing Court, Tin Yiu Estate, Tin Tsz
Estate, Sherwood Court) |
Very Many |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Full, 50-300 m |
Partial, 50-300 m |
High |
RES-3 |
Residents in Fung Kong Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 50 m |
Partial, 50 m |
Medium |
RES-4 |
Residents in Lo Uk Tsuen, Hong Mei Tsuen, San Wai, Sik Kong Tsuen, and
Tung Tau Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 50 m |
Partial, 50 m |
High |
RES-9 |
Residents in Sun Fung Wai |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 100 m |
Obscured, 100 m |
Medium |
RES-10 |
Residents in HSK |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 150 m |
Obscured, 100 m |
High |
RES-12 |
Residents in San Sang Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 250 m |
Obscured, 250 m |
High |
RES-24 |
Residents in Tuen Tsz Wai |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 150 m |
Obscured, 150 m |
High |
RES-46 |
Future Residents in HOS near TSW Station (Site 5-6) |
Many |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 750 m |
Obscured, 750 m |
High |
RES-47 |
Residents in Sunny Villas, Tseung Kong Wai, Sik Kong Wai, Ha Tsuen Shi, and San Uk Tsuen |
Many |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 0 m |
Partial, 0 m |
High |
RES-50 |
Residents in Grandeur Terrace Tin Chak Estate, Tin Heng Estate, and
Tin Yat Estate |
Many |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 300 m |
Obscured, 300 m |
High |
RES-51 |
Residents in Tin Fu Court, Tin Yuet Estate, Tin Ching Estate |
Many |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 300 m |
Obscured, 300 m |
High |
RES-52 |
Residents in Tin Chung Court, Chestwood Court, Central Park Towers,
Kingswood Ginza |
Many |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 650 m |
Obscured, 650 m |
High |
REC-1 |
Hikers along Castle Peak Trails |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, ~0-6150 m |
Partial, ~00-6150 m |
High |
REC-5 |
Users of TSW Promenade |
Many |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 250 m |
Partial, 250 m |
High |
REC-8 |
Hikers along the Hillside north of the Project |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 200 m |
Obscured, 200 m |
Medium |
REC-10 |
Users of Ping Ha Road Garden |
Few |
Poor |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 75 m |
Partial, 75 m |
Medium |
REC-11 |
Users of Sik Kong Tsuen Playground and Ha Tsuen Football Field |
Few |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 50 m |
Partial, 50 m |
Medium |
T-1 |
Motorists along KSWH |
Many |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Full, 0 m |
Full, 0 m |
Medium |
T-2 |
Users of the MTR between TSW and Siu Hong Station |
Many |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Full, 0 m |
Full, 0 m |
Medium |
T-4 |
Motorists along Hung Tin Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 0 m |
Obscured, 0 m |
Medium |
T-5 |
Motorists along Castle Peak Road |
Many |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 0 m |
Partial, 0 m |
Medium |
T-6 |
Motorists along Ping Ha Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Full, 0 m |
Full, 0 m |
Low |
T-7 |
Motorists along Tin Ha Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured, 0 m |
Partial, 0 m |
Medium |
T-8 |
Motorists along Shek Po Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured, 200 m |
Obscured, 200 m |
Low |
T-11 |
Motorists along Sha Chau Lei Road |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured, 200 m |
Obscured, 200 m |
Medium |
T-13 |
Motorists along Lan Fau Shan Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 0 m |
Partial, 0 m |
Medium |
T-16 |
Passengers on Light Rail System |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 0 m |
Partial, 0 m |
Medium |
T-17 |
Cyclists along Castle Peak Road |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 0 m |
Partial, 0 m |
High |
T-18 |
Cyclists along Tin Ha Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured, 0 m |
Partial, 0 m |
High |
T-19 |
Cyclists along Shek Po Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured, 200 m |
Obscured, 200 m |
Medium |
T-20 |
Cyclists along Ping Ha Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Full, 0 m |
Full, 0 m |
Medium |
T-23 |
Cyclists along Tin Ying Road and Hung Tin Road |
Few |
Good |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 450 m |
Obscured, 450 m |
High |
T-30 |
Motorists on Tin Wah Road |
Many |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Partial, 0 m |
Partial, 0 m |
Medium |
T-31 |
Motorists on Fuk Hang Tsuen Road |
Few |
Fair |
Yes |
Permanent, Intermittent |
Permanent, Intermittent |
Obscured, 0 m |
Obscured, 0 m |
Medium |
O-6 |
Teachers and students at WF Joseph Lee Primary School, Heung Tao
Middle School, and Pansy Ho Activity Centre |
Few |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 400 m |
Obscured, 400 m |
Low |
O-10 |
Teachers and students at VTC Youth College, Yan Chai Hospital Nina
Lam Kindergarten, and Pui Shing Catholic Secondary School |
Few |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Obscured, 500 m |
Obscured, 500 m |
Medium |
O-11 |
Teachers and students at Caritas Lok Kan School, and Twgh Leo Tung-hai Lee Primary
School |
Few |
Good |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 400 m |
Obscured, 400 m |
Medium |
O-22 |
Workers in Industrial Area of Ha Tsuen |
Few |
Fair |
Yes |
Permanent, Continuous |
Permanent, Continuous |
Partial, 200 m |
Partial, 200 m |
Low |
Potential Sources of Visual Impacts
¡P Compatibility of the Project with the Visual Backdrop: A ranking of High, Medium or Low is assigned according to the compatibility of the Project with the Visual Backdrop. Compatibility is determined by the visual consistency, proportion, scale, colour, texture, form of the Project in relation to what is presently available in forming the Visual Backdrop for the VSR. The Visual Backdrop may be made up of the surrounding landscape, geological features, waterways, and urban skyline that is viewable from the VSR;
¡P Duration and Frequency of Impact: A ranking of Temporary or Permanent define the duration of impact, while Intermittent and Continuous define the frequency. These are assigned according to the amount of time during which the VSR experiences the impact of the project;
Temporary: The impacts of the Project on the VSR are experienced for a finite duration; the Project will not always be visible;
Permanent: The impacts of the Project on the VSR are to remain constant; the Project will always be visible;
Intermittent: The impacts of the Project on the VSR are interrupted at times, occurring within discreet events; the Project will not be continually visible;
Continuous: The impacts of the Project on the VSR are experienced over an ongoing frequency; the Project will be continually visible.
¡P Scale of Development: A ranking of Large, Medium or Small is assigned according to the relative size, height and span of the Project;
¡P Reversibility of Change: A ranking of Yes or No is assigned according to whether the Project is Permanent or Temporary;
¡P Degree of Visibility of Sources of Visual Impact: A ranking of Full, Partial or Obscured is assigned according to the visibility of the Project, as a function of distance from the VSR and/or the absence/presence of any obstructions, such as existing structures or landscape elements, which may inhibit visibility. (For example, the Project may be located immediately adjacent to a VSR, but its visibility may be inhibited by the presence of existing tall buildings located between the VSR and the Project.):
Full:
The Project is fully visible to the VSR as a function of distance and/or
the absence of any obstructions;
Partial:
The Project is only partially visible to the VSR as a function of distance
and/or the presence of obstructions;
Obscured:
The Project is mostly hidden or concealed from the VSR as a function of
distance and/or the presence of obstructions.
¡P Distance Between VSR & Nearest Sources of Impact: The approximate distance between the VSR and the nearest source of impact as part of the Project (for example, a building or noise barrier) is indicated in metres;
¡P
Potential Blockage of Existing View: A
ranking of Full, Partial, Slight, Negligible or None is assigned in an effort
to anticipate the impact of the Project on the VSR¡¦s existing view, as a
function of changes to existing views or view corridors resulting from
construction of the new built form.
¡P
Full: The existing view is fully blocked
by the Project as a function of an increase or decrease in the blockage;
Partial: The existing view is partially blocked by the Project as a function of an increase or decrease in the blockage;
Slight:
The existing view is only slightly blocked by the Project as a function of an
increase or decrease in the blockage;
Negligible: The blockage of the existing view by the Project is negligible as a function of an increase or decrease in the blockage;
None:
The existing view is not blocked as a result of the Project.
Large: |
The VSRs would suffer a major change in their viewing experience; |
Intermediate: |
The VSRs would suffer a moderate change in their viewing experience; |
Small: |
The VSRs would suffer a small change in their viewing experience; |
Negligible: |
The VSRs would suffer no discernible change in their viewing experience. |
None |
The VSRs would suffer no change in their viewing |
Landscape and Visual Mitigation Measures
Table 11.10 Magnitude
of Visual Change during the Construction and Operation Phases before Mitigation (DP1, DP2, DP5, DP6, and DP12)
VSR
ID |
Key
VSR |
Compatibility
of the Project with the Visual Backdrop (High/Medium/Low) |
Duration
and Frequency of Impacts (Temporary/Permanent & Intermittent/Continuous) |
Scale of Development (Large/Medium/Small) & Reversibility of Change (Yes/No) |
Degree of Visibility
of Source(s) of Visual Impact (Full, Partial, Obscured) & Distance Between VSR & Nearest Source(s) of Impact |
Potential Blockage of
Existing View (Full/Partial/Slight/Negligible/None) |
Magnitude of Visual
Change BEFORE Mitigation (None,
Negligible, Small, Intermediate, Large) |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
||||
Residential VSRs |
|||||||||||
RES-1 |
Residents in West TSW (Tin Yan Estate, Tin Wah Estate, Tin Shui
Estate, Tin Oi Court, Locwood Court, Tin Shing Court, Tin Yiu Estate, Tin Tsz
Estate, Sherwood Court) |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Full, 50-300 m |
Partial, 50-300 m |
Partial |
Slight |
Large |
Intermediate |
This VSR would mainly experience views to the west towards the
Project. Due to close proximity, full views of the Road DP 2 and distant
views of DPs 1, 5 and 12 would be permanent and continuous during construction,
with partial views during operation as the buildings associated with the
Project would partially block views of the Road DPs. Existing views,
including views to the west of the HSK valley and Lau Fau Shan behind it,
would be partially obstructed during construction and reduce to slight during
operation. In terms of the source of visual impacts, views during
construction may include site clearance, site formation and development of
new road network, while views during operation may include the new road
network and associate infrastructure. Due to the large scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction is considered to
be ¡§Large¡¨ and at operation is considered to be ¡§Intermediate¡¨. Refer to
Figures 11.34a and 11.34b for an example of how views may be impacted on Day
1 and Year 10 of the operation phase. |
|||||||||||
RES-3 |
Residents in Fung Kong
Tsuen |
Low |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 50 m |
Partial, 50 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would mainly experience views to the south and east towards
the Project. Due to close proximity, partial views of the Project would be permanent
and continuous. Any existing views, including distant views of Yuen Tau Shan
to the southwest and Lam Tei to the southeast, would largely remain, with
partial obstruction to near and mid-ground views into the adjacent valley. In
terms of the source of visual impacts, views during construction may include
site clearance, site formation and development of new road network, while
views during operation may include new road network and associate
infrastructure. Residents of this VSR may be able to see two 5 m high
vertical noise barriers as shown in Figures 11.24a and 11.24c. Due to the
large scale of the development in the view combined with a ¡§Low¡¨
compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
RES-4 |
Residents in Lo Uk
Tsuen, Hong Mei Tsuen, San Wai, Sik Kong Tsuen, and Tung Tau Tsuen |
Low |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 50 m |
Partial, 50 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views in all directions towards the Project.
Due to close proximity, partial views of the Project would be permanent and
continuous. Any existing views of Lau Fau Shan and Yuen Tau Shan to the west
may be partially blocked by the DP5 and 12. In terms of the source of visual
impacts, partial views during construction may include site clearance, site
formation and development of new road network, while partial views during
operation may include new road network and associate infrastructure.
Residents of this VSR may be able to see two vertical noise barriers ranging
in height from 4 m to 6 m as shown in Figure 11.24c. Due to the large scale
of the development in the view combined with a ¡§Low¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Intermediate¡¨. Refer to Figures 11.33a and 11.33b as
representative examples of possible visual impacts. |
|||||||||||
RES-9 |
Residents in Sun Fung
Wai |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 100 m |
Obscured, 100 m |
Slight |
Slight |
Small |
Small |
This VSR would experience views to the north and west towards the
Project. The duration and frequency of impacts can be characterised as
permanent and continuous. Any
existing distant views of Lau Fau Shan and Yuen Tau Shan to the
west/northwest would largely remain, with impacts concentrated to views in
the near distance. In terms of the source of visual impacts, views during
construction may include site clearance, site formation and development of
new road networks, while views during operation would include new road
network and associate infrastructure, however it is anticipated these views
will be obscured. Due to the scale of the development in the view combined
with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude of change
during construction and operation is considered to be ¡§Small¡¨. |
|||||||||||
RES-10 |
Residents in HSK |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 150 m |
Obscured, 100 m |
Slight |
Slight |
Small |
Small |
This VSR would experience views to the west and south towards the
Project. The duration and frequency of impacts can be characterised as
permanent and continuous. Any existing
distant views of Lau Fau Shan and Yuen Tau Shan to the west/northwest and Lam
Tei to the east would largely remain, with impacts concentrated to views in
the near distance. In terms of the source of visual impacts, views during
construction may include site clearance, site formation and development of
new road networks, while views during operation would include new road
network and associate infrastructure. Due to the scale of the development in
the view combined with a ¡§High¡¨ compatibility with the visual backdrop, the
magnitude of change during construction and operation is considered to be
¡§Small¡¨. |
|||||||||||
RES-12 |
Residents in San Sang
Tsuen |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 250 m |
Obscured, 250 m |
Slight |
Slight |
Small |
Small |
This VSR would experience views to the west and south towards the
Project. The duration and frequency of impacts can be characterised as
permanent and continuous. Any
existing distant views of Lau Fau Shan and Yuen Tau Shan to the west/northwest
and Lam Tei to the east would largely remain, with impacts concentrated to
views in the near distance. In terms of the source of visual impacts, views
during construction may include site clearance, site formation and
development of new road networks, while views during operation would include
new road network and associate infrastructure. Due to the scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Small¡¨. Refer
to Figures 11.37a and 11.37b as representative examples of possible visual
impacts. |
|||||||||||
RES-24 |
Residents in Tuen Tsz
Wai |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 150 m |
Obscured, 150 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would experience views to the northeast towards the Project.
Despite this VSR¡¦s distance from the Project, obscured views of the Project
for some residences to the eastern edge of this group would be permanent and
continuous. The impact of the Road DPs on existing views would be negligible.
In terms of the source of visual impacts, obscured views during construction
may include site clearance, site formation and development of new road network,
while negligible views during operation would include new road network and
associate infrastructure. Residents of this VSR may be able to see two 3 m
high vertical noise barriers as shown in Figure 11.24i. Due to the scale of
the development in the view combined with a ¡§High¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
RES-46 |
Future Residents in HOS
near TSW Station (Site 5-6) |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 750 m |
Obscured, 750 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would experience views to the west towards the Project.
Despite this VSR¡¦s distance from the Project, obscured views of the Project
for some residences to the western edge of this group would be permanent and
continuous. The impact of the Road DPs on existing views would be negligible
and any existing distant views of Lau Fau Shan and Yuen Tau Shan to the west
would largely remain. In terms of the source of visual impacts, obscured
views during construction may include site clearance, site formation and
development of new road network, while negligible views during operation
would include new road network and associate infrastructure. Due to the scale
of the development in the view combined with a ¡§High¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
RES-47 |
Residents in Sunny Villas, Tseung Kong Wai, Sik Kong Wai, Ha Tsuen Shi, and San Uk Tsuen |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 0 m |
Partial, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views in all directions towards the Project.
Due to immediate adjacency, views of the Project would be permanent and
continuous. Any existing views of Lau Fau Shan and Yuen Tau Shan to the west
and Lam Tei to the southeast would be partially blocked by the Project. In
terms of the source of visual impacts, partial views during construction may
include site clearance, site formation and development of new road network,
while partial views during operation may include new road network and
associate infrastructure. Residents of this VSR may be able to see vertical
noise barriers ranging in height from 4 m to 5 m as shown in Figures 11.24c
and 11.24f. Due to the large scale of the development in the view combined
with a ¡§Medium¡¨ compatibility with the visual backdrop, the magnitude of
change during construction and operation is considered to be ¡§Intermediate¡¨.
Refer to Figures 11.32a and 11.32b, and Figures 11.33a and 11.33b, as
representative examples of possible visual impacts. |
|||||||||||
RES-50 |
Residents in Grandeur Terrace Tin Chak Estate, Tin Heng Estate, and
Tin Yat Estate |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 300 m |
Obscured, 300 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would experience views to the west and southwest towards the
Project. Despite this VSR¡¦s distance from the Project, obscured views of the
Project for some residences to the southwest edge of this group would be
permanent and continuous. The impact of the Road DPs on existing views would
be negligible. In terms of the source of visual impacts, partial views during
construction may include site clearance, site formation and development of
new roads, while partial views during operation may include the new road
network and associate infrastructure. Due to the scale of the development in
the view combined with a ¡§High¡¨ compatibility with the visual backdrop, the
magnitude of change during construction and operation is considered to be
¡§Negligible¡¨. |
|||||||||||
RES-51 |
Residents in Tin Fu Court, Tin Yuet Estate, Tin Ching Estate |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 300 m |
Obscured, 300 m |
Negligible |
None |
Negligible |
None |
This VSR would experience views to the west and southwest towards the
Project. Despite this VSR¡¦s distance from the Project, obscured views of the
Project would be visible to residences to the western edge of this group
during construction and be permanent and continuous, while views during
operation would be blocked by the new buildings and structures associated
with the Project development. The impact of the Project on existing views
would therefore be negligible during construction. In terms of the source of
visual impacts, obscured views during construction may include site
clearance, site formation and development of new road network, while views of
the Road DPs during operation would be blocked as mentioned. Due to the scale
of the development in the view combined with a ¡§High¡¨ compatibility with the
visual backdrop, the magnitude of change during construction is considered to
be ¡§Negligible¡¨ and at operation is considered to be ¡§None¡¨. |
|||||||||||
RES-52 |
Residents in Tin Chung Court, Chestwood Court, Central Park Towers,
Kingswood Ginza |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 650 m |
Obscured, 650 m |
Negligible |
None |
Negligible |
None |
This VSR would experience views to the west towards the Project.
Despite this VSR¡¦s distance from the Project, obscured views of the Project
would be visible to residences to the western edge of this group during
construction and be permanent and continuous, while views during operation
would be blocked by the new buildings and structures associated with the
Project development. The impact of the Project on existing views would
therefore be negligible during construction. In terms of the source of visual
impacts, obscured views during construction may include site clearance, site
formation and development of new road network, while views of the Road DPs
during operation would be blocked as mentioned. Due to the scale of the
development in the view combined with a ¡§High¡¨ compatibility with the visual
backdrop, the magnitude of change during construction is considered to be
¡§Negligible¡¨ and at operation is considered to be ¡§None¡¨. |
|||||||||||
Recreational VSRs |
|||||||||||
REC-1 |
Hikers along Castle
Peak Trails |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, ~0-6150 m |
Partial, ~00-6150 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views to the northeast and east towards the
Project. The duration and frequency of impacts can be characterised as
permanent and intermittent due to the changing nature of conditions along the
trail. According to a hiker¡¦s position along the trail, the Project would be
in partial view during construction and operation. In terms of the source of
visual impacts, views of the Project during construction may include site
clearance, site formation and development of new road network, while views
during operation would include the new road network and associate
infrastructure. Hikers along the trail would be able to see the Road DPs 1, 5
and 12, albeit from a distance. Likewise, this VSR may be able to discern the
presence of a 3 m vertical noise barrier, as well as a 5.5 + 2.5 m cantilever
noise barrier along KSWH. Hikers along the trail may Due to the large scale
of the development in the view combined with a ¡§Medium¡¨ compatibility with
the visual backdrop, the magnitude of change during construction and
operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
REC-5 |
Users of TSW Promenade |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 250 m |
Partial, 250 m |
Slight |
Slight |
Small |
Small |
This VSR would experience views to the west towards the Project. The
duration and frequency of impacts can be characterised as permanent and
continuous. According to the user¡¦s position along the promenade, the
Road-related DP 2 would be in partial view during construction and operation.
In terms of the source of visual impacts, views of the Project during
construction may include site clearance, site formation and development of
new road network, while views during operation would include the new road
network and associate infrastructure. Existing views from the promenade would
be slightly blocked by the Road-related DP2. Due to the large scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Small¡¨. |
|||||||||||
REC-8 |
Hikers along the
Hillside north of the Project |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 200 m |
Obscured, 200 m |
Partial |
Slight |
Intermediate |
Small |
This VSR would experience views to the east and south towards the
Project. The duration and frequency of impacts can be characterised as permanent
and intermittent. According to a hiker¡¦s position along the hillside, the
Road-related DPs would be partially visible during construction and obscured
during operation as the new buildings and structures associated with the
Project development block views of the Road-related DPs. In terms of the
source of visual impacts, views of the Project during construction may
include site clearance, site formation and development of new road network,
while views during operation would include the new road network and associate
infrastructure. Existing views from the hillside would be partially blocked
by the Road-related DPs during construction, and slightly blocked in
operation. Due to the large scale of the development in the view combined
with a ¡§Medium¡¨ compatibility with the visual backdrop, the magnitude of
change during construction is considered to be ¡§Intermediate¡¨ and in
operation is considered to be ¡§Small¡¨. |
|||||||||||
REC-10 |
Users of Ping Ha Road
Garden |
Low |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 75 m |
Partial, 75 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views along the north-south alignment of
Road-related DP2 works. The duration and frequency of impacts can be characterised
as permanent and continuous. The Project would be partially visible during
construction and operation. In terms of the source of visual impacts, views
of the Project during construction may include site clearance, site formation
and development of new road network, while views during operation would
include the new road network and associate infrastructure. Existing views
from Ping Ha Road Garden would be partially blocked by the Road-related DP2
works and vertical noise barriers. Users of this VSR may be able to see
vertical noise barriers ranging in height from 4 m to 5 m, and a 6 + 4.2 m
high cantilever noise barrier as shown in Figure 11.24c. Due to the large
scale of the development in the view combined with a ¡§Low¡¨ compatibility with
the visual backdrop, the magnitude of change during construction and
operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
REC-11 |
Users of Sik Kong Tsuen
Playground and Ha Tsuen Football Field |
Low |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 50 m |
Partial, 50 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views along the north-south alignment of
Road-related DP2 works. The duration and frequency of impacts can be
characterised as permanent and continuous. The Project would be partially
visible during construction and operation. In terms of the source of visual
impacts, views of the Project during construction may include site clearance,
site formation and development of new road network, while views during operation
would include the new road network and associate infrastructure. Existing
views from Sik Kong Tsuen Playground and Ha Tsuen Football Field would be
partially blocked by the Road-related DP2 works and vertical noise barriers.
Users of this VSR may be able to see vertical noise barriers ranging in
height from 4 m to 5 m, and a 6 + 4.2 m high cantilever noise barrier as
shown in Figure 11.24c. Due to the large scale of the development in the view
combined with a ¡§Low¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be
¡§Intermediate¡¨. |
|||||||||||
Travelling VSRs |
|||||||||||
T-1 |
Motorists along KSWH |
Low |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Full, 0 m |
Full, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would mainly experience direct views of DP1, 2, 5 and 12
(including the associated noise barriers) while travelling north-south along
the roadway. Due to the immediate proximity (travelling on the roads associated
with the works), full views of DP1, 2, 5 and 12 would be permanent and
intermittent as this VSR is in motion. Existing views to the north, east and
south would be partially blocked during construction by the associated site
clearance, site formation and traffic control measures, while views during
operation would be partially blocked by the provision of vertical noise
barriers and associated road infrastructure. Motorists along this route will
encounter a number of vertical noise barriers ranging in height from 3 m to 5
m. Due to the large scale of the
development in the view combined with a ¡§Low¡¨ compatibility with the visual
backdrop, the magnitude of change during construction and operation is
considered to be ¡§Intermediate¡¨. |
|||||||||||
T-2 |
Users of the MTR
between TSW and Siu Hong Station |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Full, 0 m |
Full, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views to the north, south and west toward
the Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. Due to immediate
adjacency as this VSR intersects Road-related DPs, the Project would be fully
visible during construction and operation. In terms of the source of visual
impacts, views of the Project during construction may include site clearance,
site formation and traffic control measures, while views during operation
would include the new road network and associate infrastructure. Existing
views experienced by MTR users would be partially blocked by the provision of
vertical noise barriers and associated road infrastructure. Due to the large
scale of the development in the view combined with a ¡§Medium¡¨ compatibility
with the visual backdrop, the magnitude of change during construction and
operation is considered to be ¡§Intermediate¡¨. Refer to Figures 11.44a and
11.44b as representative examples of possible visual impacts. |
|||||||||||
T-4 |
Motorists along Hung
Tin Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 0 m |
Obscured, 0 m |
Slight |
Negligible |
Small |
Negligible |
This VSR would experience views primarily to the west toward the
Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. Due to close proximity
as this VSR approaches Road-related DPs, the Project would be partially
visible during construction and obscured operation due to the blockage of
views by new buildings and structures associated with the Project
development. In terms of the source of visual impacts, views of the Project
during construction may include site clearance, site formation and
development of new roads, while views during operation would include the new
road network and associate infrastructure. Existing views along Hung Tin Road
would be partially blocked by Road-related DPs during construction and
obscured in operation. Due to the large scale of the development in the view
combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction is considered to be ¡§Small¡¨ and in operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
T-5 |
Motorists along Castle
Peak Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 0 m |
Partial, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would predominantly experience views to the northwest toward
the Project. The duration and frequency of impacts can be characterised as permanent
and intermittent as this VSR is in motion. Due to close proximity as this VSR
approaches Road-related DPs, the Project would be partially visible during
construction and operation. In terms of the source of visual impacts, views
of the Project during construction may include site clearance, site formation
and development of new roads, while views during operation would include the
new road network and associate infrastructure. Due to the large scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction is considered to
be ¡§Partial¡¨ and during operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
T-6 |
Motorists along Ping Ha
Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Full, 0 m |
Full, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would mainly experience direct views of DP2 and DP6
(including the associated noise barriers) while travelling north-south along
the roadways. Due to the immediate proximity (travelling on the roads
associated with the works), full views of DP2 and DP6 would be permanent and
intermittent as this VSR is in motion. Existing views to the east and west
would be partially blocked during construction by the associated site
clearance, site formation and traffic control measures, while views during
operation would be partially blocked by the provision of vertical noise
barriers and associated road infrastructure. Motorists along this route will
see numerous vertical noise barriers ranging in height from 3 m to 7 m, along
their way, including a 6 + 4.2m cantilever noise barrier. Due to the large scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Intermediate¡¨. |
|||||||||||
T-7 |
Motorists along Tin Ha
Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Obscured, 0 m |
Partial, 0 m |
Slight |
Slight |
Small |
Small |
This VSR would experience views to the north, west and south toward
the Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. In terms of the source
of visual impacts, views of the Project during construction would be slightly
blocked during construction by the associated site clearance, site formation
and traffic control measures, while views during operation would be slightly
blocked by the provision of vertical noise barriers and associated road
infrastructure. Motorists along this route may be able to see a 5m vertical
noise barrier on proposed Road L1. Due to the large scale of the development
in the view combined with a ¡§High¡¨ compatibility with the visual backdrop,
the magnitude of change during construction and operation is considered to be
¡§Small¡¨. Refer to Figures 11.39a and 11.39b as representative examples of
possible visual impacts. |
|||||||||||
T-8 |
Motorists along Shek Po
Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Obscured, 200 m |
Obscured, 200 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would generally experience views to the west toward the
Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. Due to the distance from
the Project, the Road-related DPs would be obscured during construction and
operation. In terms of the source of visual impacts, views of the Project
during construction may include site clearance, site formation and
development of new roads, while views during operation would include the new
road network and associate infrastructure. Any blockage of existing views
along Shek Po Road would be negligible. Due to the large scale of the
development in the view combined with a ¡§High¡¨ compatibility with the visual
backdrop, the magnitude of change during construction and operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
T-11 |
Motorists along Sha
Chau Lei Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Obscured, 200 m |
Obscured, 200 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would experience views in all directions toward the Project.
The duration and frequency of impacts can be characterised as permanent and intermittent
as this VSR is in motion. Due to the distance from the Project, the
Road-related DPs would be obscured during construction and operation. In
terms of the source of visual impacts, views of the Project during
construction may include site clearance, site formation and development of
new roads, while views during operation would include the new road network
and associate infrastructure. Any blockage of existing views along Sha Chau
Lei Road would be negligible. Due to the large scale of the development in
the view combined with a ¡§High¡¨ compatibility with the visual backdrop, the
magnitude of change during construction and operation is considered to be
¡§Negligible¡¨. |
|||||||||||
T-13 |
Motorists along Lan Fau
Shan Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 0 m |
Partial, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would generally experience views to the south and west toward
the Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. Due to close proximity
as this VSR approaches Road-related DPs, the Project would be partially
visible during construction and operation. In terms of the source of visual
impacts, partial views of the Project during construction may include site
clearance, site formation and development of new roads, while partial views
during operation would include the new road network and associate
infrastructure. Existing views along Lan Fau Shan Road would be partially blocked
by the project. Users of this VSR may be able to see a 3 m high boundary wall
as shown in Figure 11.24a. Due to the large scale of the development in the
view combined with a ¡§Medium¡¨ compatibility with the visual backdrop, the
magnitude of change during construction and operation is considered to be
¡§Intermediate¡¨. |
|||||||||||
T-16 |
Passengers on Light
Rail System |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 0 m |
Partial, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views to the northwest toward the Project.
The duration and frequency of impacts can be characterised as permanent and
intermittent as this VSR is in motion. Due to close proximity as this VSR
approaches Road-related DPs, the Project would be partially visible during
construction and operation. In terms of the source of visual impacts, slight
views of the Project during construction may include site clearance, site
formation and development of new roads, while partial views during operation
would include the new road network and associate infrastructure. Potential
blockage of existing views would increase from slight during construction to
partial in operation due to the alignment of new buildings associated with
the development of the Project. Due to the large scale of the development in
the view combined with a ¡§Medium¡¨ compatibility with the visual backdrop, the
magnitude of change during construction is considered to be ¡§Partial¡¨ and
during operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
T-17 |
Cyclists along Castle
Peak Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 0 m |
Partial, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would predominantly experience views to the northwest toward
the Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. Due to close proximity
as this VSR approaches Road-related DPs, the Project would be partially
visible during construction and operation. In terms of the source of visual
impacts, partial views of the Project during construction may include site
clearance, site formation and development of new roads, while partial views
during operation would include the new road network and associate
infrastructure. Due to the large scale of the development in the view
combined with a ¡§Medium¡¨ compatibility with the visual backdrop, the
magnitude of change during construction is considered to be ¡§Partial¡¨ and
during operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
T-18 |
Cyclists along Tin Ha
Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Obscured, 0 m |
Partial, 0 m |
Slight |
Slight |
Small |
Small |
This VSR would experience views to the north, west and south toward
the Project. The duration and frequency of impacts can be characterised as
permanent and intermittent as this VSR is in motion. This VSR experiences
views at a slower pace than motorists along the same road. Due to close
proximity as this VSR approaches Road-related DPs, the Project would be
obscured during construction and partially visible in operation as the
development associated with the Project would increase views toward the
Road-related DPs. In terms of the source of visual impacts, views of the
Project during construction would be slightly blocked during construction by
the associated site clearance, site formation and traffic control measures,
while views during operation would be slightly blocked by the provision of
vertical noise barriers and associated road infrastructure. Cyclists along
this route may be able to see a 5m vertical noise barrier on proposed Road
L1. Due to the large scale of the development in the view combined with a
¡§High¡¨ compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Small¡¨. Refer to Figures
11.39a and 11.39b as representative examples of possible visual impacts. |
|||||||||||
T-19 |
Cyclists along Shek Po
Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Obscured, 200 m |
Obscured, 200 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would generally experience views to the west toward the Project.
The duration and frequency of impacts can be characterised as permanent and
intermittent as this VSR is in motion. This VSR experiences views at a slower
pace than motorists along the same road. Due to the distance from the
Project, the Road-related DPs would be obscured during construction and
operation. In terms of the source of visual impacts, views of the Project
during construction may include site clearance, site formation and
development of new roads, while views during operation would include the new
road network and associate infrastructure. Any blockage of existing views
along Shek Po Road would be negligible. Due to the large scale of the
development in the view combined with a ¡§High¡¨ compatibility with the visual
backdrop, the magnitude of change during construction and operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
T-20 |
Cyclists along Ping Ha
Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Full, 0 m |
Full, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would mainly experience direct views of DP2 and DP6
(including the associated noise barriers) while travelling north-south along
the roadways. This VSR experiences views at a slower pace than motorists
along the same road. Due to the immediate proximity (travelling on the roads
associated with the works), full views of DP2 and DP6 would be permanent and
intermittent as this VSR is in motion. Existing views to the east and west
would be partially blocked during construction by the associated site clearance,
site formation and traffic control measures, while partial views during
operation would be partially blocked by the provision of vertical noise
barriers and associated road infrastructure. Cyclists along this route will
see numerous vertical noise barriers ranging in height from 3 m to 7 m, along
their way, including a 6 + 4.2m cantilever noise barrier. Due to the large
scale of the development in the view combined with a ¡§Medium¡¨ compatibility
with the visual backdrop, the magnitude of change during construction and
operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
T-23 |
Cyclists along Tin Ying
Road and Hung Tin Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 450 m |
Obscured, 450 m |
Slight |
Negligible |
Small |
Negligible |
This VSR would experience views to the west toward the Project. The
duration and frequency of impacts can be characterised as permanent and
intermittent as this VSR is in motion. This VSR experiences views at a slower
pace than motorists along the same road. Due to the distance from the
Project, the Road-related DPs would be partially visible during construction
and reduce to obscured in operation as the new buildings and structures
associated with the Project obstruct views of these DPs. In terms of the
source of visual impacts, views of the Project during construction may
include site clearance, site formation and development of new roads, while
views during operation would include the new road network and associate
infrastructure. Existing views along Tin Ying Road and Hung Tin Road would be
slightly blocked by the Road-related DPs during construction and have a
negligible impact during operation. Due to the large scale of the development
in the view combined with a ¡§Medium¡¨ compatibility with the visual backdrop,
the magnitude of change during construction is considered to be ¡§Small¡¨ and
in operation is considered to be ¡§Negligible¡¨. |
|||||||||||
T-30 |
Motorists on Tin Wah
Road |
Medium |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Partial, 0 m |
Partial, 0 m |
Partial |
Partial |
Intermediate |
Intermediate |
This VSR would experience views westward toward the Project. The
duration and frequency of impacts can be characterised as permanent and intermittent
as this VSR is in motion. Despite being in close proximity, the Project would
be partially visible during construction and operation due to some
obstructions in the foreground. In terms of the source of visual impacts,
views of the Project during construction may include site clearance, site
formation and development of new roads, while views during operation would
include the new road network and associate infrastructure. Existing views
along Tin Wah Road would be partially blocked by the Road-related DPs. Due to
the large scale of the development in the view combined with a ¡§Medium¡¨
compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Intermediate¡¨. |
|||||||||||
T-31 |
Motorists on Fuk Hang
Tsuen Road |
High |
Permanent, Intermittent |
Permanent, Intermittent |
Large, No |
Obscured, 0 m |
Obscured, 0 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would experience views northward toward the Project. The duration
and frequency of impacts can be characterised as permanent and intermittent
as this VSR is in motion. Despite being in close proximity, the Project would
be osbcured during construction and operation due to existing buildings /
structures and landscape elements in the foreground. In terms of the source
of visual impacts, views of the Project during construction may include site
clearance, site formation and development of new Road-related DP 1 and 5
works, while views during operation would include the new road network and
associate infrastructure. Any blockage of existing views along Fuk Hang Tsuen
Road would be negligible. Due to the large scale of the development in the
view combined with a ¡§High¡¨ compatibility with the visual backdrop, the magnitude
of change during construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
Occupational VSRs |
|||||||||||
O-6 |
Teachers and students
at Wf Joseph Lee Primary School, Heung Tao Middle School, and Pansy Ho
Activity Centre |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 400 m |
Obscured, 400 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the south and southwest
towards the Project. The duration and frequency of impacts can be characterised
as permanent and continuous. Due to the Project¡¦s distance from the schools
and activity centre, the Road-related DPs would be obscured during
construction and operation. Any blockage of existing views by the
Road-related DPS would be negligible. In terms of the source of visual
impacts, views during construction may include site clearance, site formation
and development of new roads, while views during operation may include new
road network and associate infrastructure. Due to the large scale of the
development in the view combined with a ¡§High¡¨ compatibility with the visual
backdrop, the magnitude of change during construction and operation is
considered to be ¡§Negligible¡¨. |
|||||||||||
O-10 |
Teachers and students
at VTC Youth College, Yan Chai Hospital Nina
Lam Kindergarten, and Pui Shing Catholic Secondary School |
High |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Obscured, 500 m |
Obscured, 500 m |
Negligible |
Negligible |
Negligible |
Negligible |
This VSR would mainly experience views to the west towards the
Project. The duration and frequency of impacts can be characterised as
permanent and continuous. Due to the Project¡¦s distance from the schools, the
Road-related DPs would be obscured during construction and operation. Any
blockage of existing views by the Road-related DPS would be negligible. In
terms of the source of visual impacts, views during construction may include
site clearance, site formation and development of new roads, while views during
operation may include new road network and associate infrastructure. Due to
the large scale of the development in the view combined with a ¡§High¡¨
compatibility with the visual backdrop, the magnitude of change during
construction and operation is considered to be ¡§Negligible¡¨. |
|||||||||||
O-11 |
Teachers and students
at Caritas Lok Kan School, and
Twgh Leo Tung-hai Lee Primary School |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 400 m |
Obscured, 400 m |
Slight |
Negligible |
Small |
Negligible |
This VSR would mainly experience views to the south and west towards
the Project. The duration and frequency of impacts can be characterised as
permanent and continuous. Due to the Project¡¦s distance from the schools, the
Road-related DPs would be partially visible during construction and become
obscured operation due to new buildings associated with the Project
development. Any blockage of existing views by the Road-related DPs would be
slight during construction and negligible during operation. In terms of the
source of visual impacts, views during construction may include site
clearance, site formation and development of new roads, while views during
operation may include new road network and associate infrastructure. Due to
the large scale of the development in the view combined with a ¡§Medium¡¨
compatibility with the visual backdrop, the magnitude of change during
construction is considered to be ¡§Small¡¨ and in operation is considered to be
¡§Negligible¡¨. |
|||||||||||
O-22 |
Workers in Industrial Area
of Ha Tsuen |
Medium |
Permanent, Continuous |
Permanent, Continuous |
Large, No |
Partial, 200 m |
Partial, 200 m |
Negligible |
Negligible |
Small |
Small |
This VSR would mainly experience views to the north and east towards the
Project. The duration and frequency of impacts can be characterised as
permanent and continuous. Due to the obstruction of views by existing
buildings and landscape features, the Road-related DPs would be partially
visible during construction and operation. Any blockage of existing views by
the Road-related DPs would be negligible. In terms of the source of visual
impacts, views during construction may include site clearance, site formation
and development of new roads, while views during operation may include new
road network and associate infrastructure. Due to the large scale of the
development in the view combined with a ¡§Medium¡¨ compatibility with the
visual backdrop, the magnitude of change during construction and operation is
considered to be ¡§Small¡¨. Refer to Figures 11.32a and 11.32b as
representative examples of possible visual impacts. |
|||||||||||
Note: (1) 0* denotes
VSR within Project Site Boundary |
(3) ¡¥Permanent¡¦
duration measurement refers to entire construction/operational phase
Prediction of Significance of Visual Impacts
Impacts during the Construction and Operational Phase before Mitigation
Residential VSRs
¡P RES1: This VSR will have permanent and continuous full views towards the source of visual impact at distances ranging from 50 m to 300 m. In the construction phase, the resultant magnitude of visual change is Intermediate, and this combined with their High sensitivity results in an impact considered to be of Substantial significance. In the operation phase, the predicted impact significance is anticipated to remain the same as in the construction phase, as the unmitigated development would render similar impacts as the construction phase.
¡P RES3, RES4, and RES47: These VSRs will have permanent and continuous partial views towards the source of visual impact at distances ranging from 0 m to 50 m. In the construction phase, the resultant magnitude of visual change is Intermediate, and this combined with their Medium sensitivity results in an impact considered to be of Substantial significance. In the operation phase, the predicted impact significance is anticipated to remain the same as in the construction phase, as the unmitigated development would render similar impacts as the construction phase.
¡P RES10: These VSRs will have permanent and continuous obscured views towards the source of visual impact at a distance of 150 m. In the construction phase, the resultant magnitude of visual change is Small, and this combined with their High sensitivity results in an impact considered to be of Slight significance. In the operation phase, the VSRs will have permanent and continuous slight views with the predicted impact significance anticipated to change to Slight.
¡P RES12: This VSR will have permanent and continuous obscured views towards the source of visual impact during construction, and obscured views during operation at distances of 250 m. In the construction phase, the resultant magnitude of visual change is Small, and this combined with the High sensitivity results in an impact considered to be of Slight significance. In the operation phase, the VSRs will have permanent and continuous obscured views with the predicted impact significance anticipated to be Slight.
¡P
RES24, RES46, and RES50: These VSRs will
have permanent and continuous obscured views towards the source of visual
impact at distances ranging from
150 m to 750 m. In the construction phase, the resultant magnitude of visual
change is Negligible, and this combined with their High sensitivity results in
an impact considered to be of Insubstantial significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P RES9: These VSRs will have permanent and continuous obscured views towards the source of visual impact at a distance of 100 m. In the construction phase, the resultant magnitude of visual change is Small, and this combined with their Medium sensitivity results in an impact considered to be of Insubstantial significance. In the operation phase, the VSRs will have permanent and continuous slight views with the predicted impact significance anticipated to be Insubstantial.
¡P
RES51, and RES52: These VSRs will have
permanent and continuous obscured views towards the source of visual impact at
distances ranging from 300 m to
650 m. In the construction phase, the resultant magnitude of visual change is
Negligible, and this combined with their High sensitivity results in an impact
considered to be of Insubstantial significance. In the operation phase, the VSRs will
have permanent and continuous no views as a result of the adjacent
developments, with the predicted impact significance anticipated to change to None.
Recreational VSRs
¡P
REC1: This VSR will have permanent and
intermittent partial views towards the source of visual impact at distances
ranging from 0 m of 6,150 m. In the construction phase, the resultant magnitude
of visual change is Intermediate, and this combined with their High sensitivity
results in an impact considered to be of Substantial significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P REC5: This VSR will have permanent and continuous partial views towards the source of visual impact at a distance of 250 m. In the construction phase, the resultant magnitude of visual change is Small, and this combined with their High sensitivity results in an impact considered to be of Moderate significance. In the operation phase, the predicted impact significance is anticipated to remain the same as in the construction phase, as the unmitigated development would render similar impacts as the construction phase.
¡P REC8: This VSR will have permanent and intermittent partial views towards the source of visual impact during construction, and obscured views during operation at a distances of 200 m. In the construction phase, the resultant magnitude of visual change is Intermediate, and this combined with their Medium sensitivity results in an impact considered to be of Substantial significance. In the operation phase, the VSRs will have permanent and intermittent obscured views as a result of the adjacent developments, with the predicted impact significance anticipated to change to Moderate.
¡P REC10: This VSR will have permanent and continuous partial views towards the source of visual impact at a distance of 75 m. In the construction phase, the resultant magnitude of visual change is Intermediate, and this combined with their High sensitivity results in an impact considered to be of Substantial significance. In the operation phase, the predicted impact significance is anticipated to remain the same as in the construction phase, as the unmitigated development would render similar impacts as the construction phase.
¡P REC11: This VSR will have permanent and continuous partial views towards the source of visual impact at a distance of 50 m. In the construction phase, the resultant magnitude of visual change is Intermediate, and this combined with their Medium sensitivity results in an impact considered to be of Moderate significance. In the operation phase, the predicted impact significance is anticipated to remain the same as in the construction phase, as the unmitigated development would render similar impacts as the construction phase.
Traveling VSRs
¡P
T1, T2: These VSRs will have permanent
and intermittent full views towards the source of visual impact at a distance
of 0 m, as these VSRs intersect with the Project area. In the construction
Phase, the resultant magnitude of visual change is Intermediate, and this
combined with their Medium sensitivity results in an impact considered to be of
Moderate significance. In
the operation phase, the predicted impact significance is anticipated to remain
the same as in the construction phase, as the unmitigated development would
render similar impacts as the construction phase.
¡P
T6: This VSR will have permanent and
intermittent full views towards the source of visual impact at a distance of 0
m, as this VSR intersects with the Project area. In the construction phase, the
resultant magnitude of visual change is Intermediate, and this combined with
their Low sensitivity results in an impact considered to be of Moderate
significance. In the operation phase, the predicted impact significance is
anticipated to remain the same as in the construction phase, as the unmitigated
development would render similar impacts as the construction phase.
¡P
T4: This VSR will have permanent and
intermittent partial views towards the source of visual impact during
construction, and obscured views during operation at a distance of 0 m, as this
VSR intersects with the Project area. In the construction phase, the resultant
magnitude of visual change is Small, and this combined with their Medium
sensitivity results in an impact considered to be of Moderate
significance. In the operation
phase, the VSRs will have permanent and intermittent obscured views as a result
of the adjacent developments, with the predicted impact significance
anticipated to change to Insubstantial.
¡P
T5 and T16: These VSRs will have
permanent and intermittent partial views towards the source of visual impact at
a distance of 0 m, as this VSR intersects with the Project area. In the
construction phase, the resultant magnitude of visual change is Intermediate,
and this combined with the Medium sensitivity results in an impact considered
to be of Moderate significance.
In the operation phase, the predicted impact significance is anticipated
to remain the same as in the construction phase, as the unmitigated development
would render similar impacts as the construction phase.
¡P
T7: This VSR will have permanent and
intermittent obscured views towards the source of visual impact during
construction, and partial views during operation at a distance of 0 m, as this
VSR intersects with the Project area. In the construction phase, the resultant
magnitude of visual change is Small, and this combined with their Medium
sensitivity results in an impact considered to be of Slight
significance. In the operation
phase, the VSRs will have permanent and intermittent partial views as a result
of the adjacent developments, with the predicted impact significance
anticipated to change to Insubstantial.
¡P
T8: This VSR will have permanent and
intermittent obscured views towards the source of visual impact at a distance
of 180 m. In the construction phase, the resultant magnitude of visual change
is Negligible, and this combined with their Low sensitivity results in an
impact considered to be of Insubstantial significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P
T11 and T31: These VSRs will have
permanent and intermittent obscured views towards the source of visual impact
at a distances from of 0 m to 200 m. In the construction phase, the resultant
magnitude of visual change is Negligible, and this combined with their Medium
sensitivity results in an impact considered to be of Insubstantial
significance. In the operation
phase, the predicted impact significance is anticipated to remain the same as
in the construction phase, as the unmitigated development would render similar
impacts as the construction phase.
¡P
T13: This VSR will have permanent and
intermittent partial views towards the source of visual impact at a distance
from of 0 m, as this VSR intersects with the Project area. In the construction
phase, the resultant magnitude of visual change is Intermediate, and this
combined with their Medium sensitivity results in an impact considered to be of
Moderate significance. In
the operation phase, the predicted impact significance is anticipated to remain
the same as in the construction phase, as the unmitigated development would
render similar impacts as the construction phase.
¡P
T17: This VSR will have permanent and
intermittent partial views towards the source of visual impact at a distance
from of 0 m, as this VSR intersects with the Project area. In the construction
phase, the resultant magnitude of visual change is Intermediate, and this
combined with their High sensitivity results in an impact considered to be of Moderate
significance. In the operation
phase, the predicted magnitude of visual change is anticipated to be
Intermediate, with the predicted impact significance anticipated to change to Moderate.
¡P
T18: This VSR will have permanent and
intermittent obscured views towards the source of visual impact during
construction, and partial views during operation at a distance from of 0 m, as
this VSR intersects with the Project area. In the construction phase, the
resultant magnitude of visual change is Small, and this combined with their
High sensitivity results in an impact considered to be of Slight
significance. In the operation
phase, the predicted magnitude of visual change is anticipated to change to
Small as a result of the adjacent developments, with the predicted impact
significance anticipated to change to Insubstantial.
¡P
T19: This VSR will have permanent and
intermittent obscured views towards the source of visual at a distance of 200
m. In the construction phase, the resultant magnitude of visual change is
Negligible, and this combined with their Medium sensitivity results in an
impact considered to be of Insubstantial significance. In the operation phase, the predicted
impact significance is anticipated to remain the same as in the construction
phase, as the unmitigated development would render similar impacts as the
construction phase.
¡P
T20: This VSR will have permanent and
intermittent full views towards the source of visual at a distance from of 0 m,
as this VSR intersects with the Project area. In the construction phase, the
resultant magnitude of visual change is Intermediate, and this combined with
their Medium sensitivity results in an impact considered to be of Substantial
significance. In the operation
phase, the predicted impact significance is anticipated to remain the same as
in the construction phase, as the unmitigated development would render similar
impacts as the construction phase.
¡P
T23: This VSR will have permanent and
intermittent partial views towards the source of visual impact during
construction, and obscured views during operation at a distance from of 450 m.
In the construction phase, the resultant magnitude of visual change is Small,
and this combined with their High sensitivity results in an impact considered
to be of Slight significance.
In the operation phase, the predicted magnitude of visual change is
anticipated to change to Negligible as a result of the adjacent developments,
with the predicted impact significance anticipated to change to Insubstantial.
¡P
T30: This VSR will have permanent and
intermittent partial views towards the source of visual at a distance from of 0
m, as this VSR intersects with the Project area. In the construction phase, the
resultant magnitude of visual change is Intermediate, and this combined with
their Medium sensitivity results in an impact considered to be of Moderate
significance. In the operation
phase, the predicted impact significance is anticipated to remain the same as
in the construction phase, as the unmitigated development would render similar
impacts as the construction phase.
Occupational VSRs
¡P
O6 and O10: These VSRs will have
permanent and continuous obscured views towards the source of visual impact at
distances ranging from 400 m to 500 m. In the construction phase, the resultant
magnitude of visual change is negligible, and this combined with their Low
sensitivity results in an impact considered to be of Insubstantial
significance. In the operation phase, the predicted impact significance is
anticipated to remain the same as in the construction phase, as the unmitigated
development would render similar impacts as the construction phase.
¡P
O11: This VSR will have permanent and
continuous partial views towards the source of visual impact during
construction, and obscured views during operation at a distance of 400 m. In
the construction phase, the resultant magnitude of visual change is Small, and
this combined with their Low sensitivity results in an impact considered to be
of Slight significance. In the operation phase, the predicted magnitude
of visual change is anticipated to change to Negligible as a result of the
adjacent developments, with the predicted impact significance anticipated to
change to Insubstantial.
¡P
O22: This VSR will have permanent and
continuous partial views towards the source of visual impact at a distance of
200 m. In the construction phase, the resultant magnitude of visual change is
Small, and this combined with their Low sensitivity results in an impact
considered to be of Slight significance. In the operation phase, the
predicted impact significance is anticipated to remain the same as in the
construction phase, as the unmitigated development would render similar impacts
as the construction phase
Residual Impacts during the Construction & Operational Phases after Mitigation
Preliminary Land Use Study for Lam Tei Quarry and the Adjoining Areas
¡P
This is a preliminary land use
study to identify and examine the development potential and suitable types of
possible future land uses of the Lam Tei Quarry (LTQ) and its adjoining areas,
including two proposed Strategic Cavern Areas (SCVAs) identified under the
Feasibility Study on Long Term Strategy for Cavern Development. Although no
cumulative impacts are predicted with the implementation of mitigation measures
at this stage, it is advised that a coordinated approach be undertaken between
these projects.
Tuen Mun Western Bypass
¡P
TMWB together with the Tuen
Mun ¡V Chek Lap Kok Link, will provide a north-south highway corridor linking
the NWNT with the Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing
Facilities, the Hong Kong International Airport and North Lautau. Although no
cumulative impacts are predicted with the implementation of mitigation measures
at this stage, it is advised that a coordinated approach be undertaken between
these projects to reduce potential impacts in terms of both magnitude and the
period of disturbance during construction.
Proposed Development Under the Study on the Enhancement of the Lau Fau Shan Rural Township and Surrounding Areas
¡P
The objective of the study is
to realise the tourism and recreational potential of Lau Fau Shan and its surrounding
areas. The assessment area with a
total site area of about 565 ha, mainly covers Lan Fau Shan and the coastal
areas of Deep Bay, stretching from the KSWH in the south to Tsim Bei Tsui in
the north. Although no cumulative impacts are predicted with the implementation
of mitigation measures at this stage, it is advised that a coordinated approach
be undertaken between these projects to reduce potential impacts in terms of
both magnitude and the period of disturbance during construction.
Proposed Development Under the Study on the Enhancement of Yuen Long South
¡P
The overall objective of the
Study is to examine and optimise the development potential of the degraded
brownfield land in Yuen Long South for housing purpose and other uses with supporting
infrastructure and community facilities, and to improve the existing
environment. Although no cumulative impacts are predicted with the
implementation of mitigation measures at this stage, it is advised that a
coordinated approach be undertaken between these projects to reduce potential
impacts.
Table 11.11 Significance
of Visual Impacts in the Construction and Operation Phases (DP1, DP2, DP5, DP6
and DP12)
VSR ID. |
Key
Visually Sensitive Receiver (VSR) |
Magnitude of
Change before Mitigation (None, Negligible, Small, Intermediate, Large) |
Receptor
Sensitivity & Number
(Low, Medium, High) (Very Few, Few, Many, Very
Many) |
Impact
Significance BEFORE Mitigation (None, Insubstantial, Slight, Moderate, Substantial) |
Recommended
Mitigation Measures |
Residual
Impact Significance AFTER
Mitigation (None,
Insubstantial, Slight, Moderate, Substantial) |
|||||
Construction |
Operation |
||||||||||
|
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
|
DAY
1 |
YEAR
10 |
|
RES-1 |
Residents in West TSW (Tin Yan Estate, Tin Wah Estate, Tin Shui
Estate, Tin Oi Court, Locwood Court, Tin Shing Court, Tin Yiu Estate, tin Tsz
Estate, Sherwood Court) |
Large |
Intermediate |
High, Very Many |
High, Very Many |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
RES-3 |
Residents in Fung Kong Tsuen |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
RES-4 |
Residents in Lo Uk Tsuen, Hong Mei Tsuen, San Wai, Sik Kong Tsuen, and
Tung Tau Tsuen |
Intermediate |
Intermediate |
High, Many |
High, Many |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
RES-9 |
Residents in Sun Fung Wai |
Small |
Small |
Medium, Many |
Medium, Many |
Slight |
Slight |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Insubstantial |
Insubstantial |
RES-10 |
Residents in HSK |
Small |
Small |
High, Many |
High, Many |
Slight |
Slight |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Insubstantial |
Insubstantial |
RES-12 |
Residents in San Sang Tsuen |
Small |
Small |
High, Many |
High, Many |
Slight |
Slight |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Insubstantial |
Insubstantial |
RES-24 |
Residents in Tuen Tsz Wai |
Negligible |
Negligible |
High, Many |
High, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-46 |
Future Residents in HOS near TSW Station (Site 5-6) |
Negligible |
Negligible |
High, Many |
High, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-47 |
Residents in Sunny Villas, Tseung Kong Wai, Sik Kong Wai, Ha Tsuen Shi, and San Uk Tsuen |
Intermediate |
Intermediate |
High, Many |
High, Many |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
RES-50 |
Residents in Grandeur Terrace, Tin Chak Estate, Tin Heng Estate, and
Tin Yat Estate |
Negligible |
Negligible |
High, Many |
High, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
RES-51 |
Residents in Tin Fu Court, Tin Yuet Estate, Tin Ching Estate |
Negligible |
None |
High, Many |
High, Many |
Insubstantial |
None |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
None |
None |
RES-52 |
Residents in Tin Chung Court, Chestwood Court, Central Park Towers,
Kingswood Ginza |
Negligible |
None |
High, Many |
High, Many |
Insubstantial |
None |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
None |
None |
REC-1 |
Hikers along Castle Peak Trails |
Intermediate |
Intermediate |
High, Few |
High, Few |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
REC-5 |
Users of TSW Promenade |
Small |
Small |
High, Many |
High, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
REC-8 |
Hikers along the Hillside north of the Project area |
Intermediate |
Small |
Medium, Few |
Medium, Few |
Substantial |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Slight |
Insubstantial |
REC-10 |
Users of Ping Ha Road Garden |
Intermediate |
Intermediate |
High, Few |
High, Many |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
REC-11 |
Users of Sik Kong Tsuen Playground and Ha Tsuen Football Field |
Intermediate |
Intermediate |
Medium, Few |
Medium, Few |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-1 |
Motorists along KSWH |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-2 |
Users of the MTR between TSW and Siu Hong Station |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-4 |
Motorists along Hung Tin Road |
Small |
Negligible |
Medium, Many |
Medium, Many |
Moderate |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Insubstantial |
Insubstantial |
T-5 |
Motorists along Castle Peak Road |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-6 |
Motorists along Ping Ha Road |
Intermediate |
Intermediate |
Low, Many |
Low, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-7 |
Motorists along Tin Ha Road |
Small |
Small |
Medium, Many |
Medium, Many |
Slight |
Slight |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
T-8 |
Motorists along Shek Po Road |
Negligible |
Negligible |
Low, Many |
Low, Many |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
T-11 |
Motorists along Sha Chau Lei Road |
Negligible |
Negligible |
Medium, Few |
Medium, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
T-13 |
Motorists along Lan Fau Shan Road |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-16 |
Passengers on Light Rail System |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-17 |
Cyclists along Castle Peak Road |
Intermediate |
Intermediate |
High, Few |
High, Few |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
T-18 |
Cyclists along Tin Ha Road |
Small |
Small |
High, Few |
High, Few |
Slight |
Slight |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
T-19 |
Cyclists along Shek Po Road |
Negligible |
Negligible |
Medium, Few |
Medium, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
T-20 |
Cyclists along Ping Ha Road |
Intermediate |
Intermediate |
Medium, Few |
Medium, Few |
Substantial |
Substantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Moderate |
Moderate |
Slight |
T-23 |
Cyclists along Tin Ying Road and Hung Tin Road |
Small |
Negligible |
High, Few |
High, Few |
Slight |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
T-30 |
Motorists on Tin Wah Road |
Intermediate |
Intermediate |
Medium, Many |
Medium, Many |
Moderate |
Moderate |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Slight |
Slight |
Insubstantial |
T-31 |
Motorists on Fuk Hang Tsuen Road |
Negligible |
Negligible |
Medium, Few |
Medium, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
O-6 |
Teachers and students at Wf Joseph Lee Primary School, Heung Tao
Middle School, and Pansy Ho Activity Centre |
Negligible |
Negligible |
Low, Few |
Low, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
O-10 |
Teachers and students at VTC Youth College, Yan Chai Hospital Nina Lam Kindergarten, and Pui Shing Catholic
Secondary School |
Negligible |
Negligible |
Low, Few |
Low, Few |
Insubstantial |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
O-11 |
Teachers and students at Caritas Lok Kan School, and Twgh Leo Tung-hai Lee Primary
School |
Small |
Negligible |
Low, Few |
Low, Few |
Slight |
Insubstantial |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
O-22 |
Workers in Industrial Area of Ha Tsuen |
Small |
Small |
Low, Few |
Low, Few |
Slight |
Slight |
CM1, 3, 4, 5, 6, 7, 9, 10,
11, 13, 14, OM1, 3, 4, 6, 7, 10, 13, 14 |
Insubstantial |
Insubstantial |
Insubstantial |
Note: VSRs with impact significance of ¡§None¡¨ or
¡§Insubstantial¡¨ do not require mitigation measures
¡P Existing Baseline Conditions in March 2016 ¡V This photo illustrates the ¡¥before scenario¡¦ - the existing landscape conditions before construction of the proposed HSK development (including DP¡¦s 1, 2, 5, 6 and 12) for the purpose to assess the magnitude of visual change.
¡P
Proposed HSK development without mitigation
at Day 1 (Operational Phase) ¡V This photomontage illustrates the proposed
HSK development at Day 1 (including DP¡¦s 1, 2, 5, 6 and 12) without mitigation
(i.e. no screen planting, no chromatic treatment to the buildings, no landscape
greening etc.). This photomontage is used to demonstrate impacts / changes
caused by the DP¡¦s 1, 2, 5, 6 and 12 and assess the effectiveness of
implementing mitigation measures in reducing the landscape and visual impacts.
¡P Proposed HSK development with mitigation at Day 1 (Operational Phase) ¡V This photomontage illustrates the proposed HSK development at Day 1 (including DP¡¦s 1, 2, 5, 6 and 12) with mitigation (i.e. with screen planting, with chromatic treatment to the buildings, with landscape greening etc.). This photomontage is used to illustrate the implementation of mitigation measures at Day 1 and reduction of the landscape and visual impacts imposed by the proposed DP¡¦s listed above at Day 1.
¡P Proposed HSK development with mitigation at Year 10 (Operational Phase) - This photomontage illustrates the proposed HSK development at Year 10 (including DP¡¦s 1, 2, 5, 6 and 12) with mitigation (i.e. with screen planting, with chromatic treatment to the buildings, with landscape greening etc.). This photomontage is used to illustrate the implementation of mitigation measures matured at Year 10 further reducing the landscape and visual impacts imposed by the proposed DP¡¦s listed above.
Summary of Landscape and Visual Mitigation Measures
¡P CM1 - Minimised construction area and contractor¡¦s temporary works areas
¡P CM2 - Stripping and storing of top soil
¡P CM3 - Protection of existing trees
¡P CM4 - Transplantation of existing trees where practical
¡P CM5 - Control of night time lighting
¡P CM6 - Construction of decorative hoarding around construction works
¡P CM7 - Reduction of construction period to a practical minimum
¡P CM8 - Prevention of run-off
¡P CM9 - Phasing of construction stage
¡P CM10 - Advanced screen planting
¡P CM11 - Minimise disturbance footprints
¡P CM12 - Protection of existing water courses
¡P CM13 - Hydroseeding on modified slopes
¡P CM14 - Integrate Open Space Framework with existing nullah conditions
¡P OM1 - Compensatory tree planting where practical
¡P OM3 - Sensitive design of hardscape elements along roadsides
¡P OM4 - Reinstatement of streetscape elements
¡P OM6 - Quality greening along roadside amenity strips
¡P OM7 - Design of street lighting
¡P OM10 - Sensitive design of noise barriers and enclosures
¡P OM14 - Greening of viaduct structures and noise barriers
Summary of Proposed Planning and Urban Design Considerations
Breezeways
Roadside Planting
Summary of Predicted Visual Impacts in the Construction & Operation Phase
Overall Conclusion