Contents

 

10              Landscape and Visual Impacts  1

10.1            Introduction  1

10.2            Environmental Legislation, Standards and Guidelines  2

10.3            Landscape Impact Assessment Methodology  3

10.4            Visual Impact Assessment Methodology  5

10.5            Identification of Potential Landscape and Visual Mitigation Measures  8

10.6            Residual Impact Assessment Methodology  8

10.7            Overall Result of the Landscape and Visual Impact Assessment 8

10.8            Review of Planning and Development Control  Framework  10

10.9            Baseline Study  14

10.10         Landscape and Visual Impact Assessment before Mitigation Measures  39

10.11         Minimisation of Landscape and Visual Impact 85

10.12         Landscape and Visual Mitigation Measures for Construction and Operation  88

10.13         Residual Impacts upon Mitigation  94

10.14         Cumulative Impact 123

10.15         Conclusions  124

 


 

Figures

 

Figure 10.1

Figure 10.1a

Figure 10.1b

Figure 10.1c

Figure 10.1d

Figure 10.2

Outline Zoning Plan

Outline Zoning Plan - Enlargement (Sheet 1 of 4)

Outline Zoning Plan - Enlargement (Sheet 2 of 4)

Outline Zoning Plan - Enlargement (Sheet 3 of 4)

Outline Zoning Plan - Enlargement (Sheet 4 of 4)

Recommended Outline Development Plan (RODP)

Figure 10.3

Aerial Photo of Yuen Long South Site

Figure 10.3a

Aerial Photo of Yuen Long South Site-Enlargement(Sheet 1 of 4)

Figure 10.3b

Aerial Photo of Yuen Long South Site-Enlargement(Sheet 2 of 4)

Figure 10.3c

Figure 10.3d

Figure 10.4

Figure 10.4a

Figure 10.4b

Figure 10.4c

Figure 10.4d

Figure 10.5a

Figure 10.5b

Figure 10.5c

Figure 10.6

Figure 10.6a

Figure 10.6b

Figure 10.6c

Figure 10.6d

Figure 10.7a

Figure 10.7b

Figure 10.7c

Figure 10.7d

Figure 10.7e

Figure 10.7f

Figure 10.7g

Figure 10.7h

Aerial Photo of Yuen Long South Site-Enlargement(Sheet 3 of 4)

Aerial Photo of Yuen Long South Site-Enlargement(Sheet 4 of 4)

Landscape Character Areas Plan 

Landscape Character Areas Plan -Enlargement Plan(Sheet 1 of 4) 

Landscape Character Areas Plan -Enlargement Plan(Sheet 2 of 4) 

Landscape Character Areas Plan -Enlargement Plan(Sheet 3 of 4) 

Landscape Character Areas Plan -Enlargement Plan(Sheet 4 of 4) 

Photographs of Landscape Character Areas(1 of 3)

Photographs of Landscape Character Areas(2 of 3)

Photographs of Landscape Character Areas(3 of 3)

Landscape Resources Plan

Landscape Resources Plan -Enlargement Plan(Sheet 1 of 4) 

Landscape Resources Plan -Enlargement Plan(Sheet 2 of 4) 

Landscape Resources Plan -Enlargement Plan(Sheet 3 of 4) 

Landscape Resources Plan -Enlargement Plan(Sheet 4 of 4) 

Photographs of Landscape Resources (1 of 8)

Photographs of Landscape Resources (2 of 8)

Photographs of Landscape Resources (3 of 8)

Photographs of Landscape Resources (4 of 8)

Photographs of Landscape Resources (5 of 8)

Photographs of Landscape Resources (6 of 8)

Photographs of Landscape Resources (7 of 8)

Photographs of Landscape Resources (8 of 8)

Figure 10.8

Figure 10.8a

 

Figure 10.8b

 

Figure 10.8c

 

Figure 10.8d

 

Figure 10.9

Landscape Character Area Plan with RODP Layout

Landscape Character Areas Plan with RODP Layout -Enlargement Plan (Sheet 1 of 4)

Landscape Character Areas Plan with RODP Layout -Enlargement Plan (Sheet 2 of 4)

Landscape Character Areas Plan with RODP Layout -Enlargement Plan (Sheet 3 of 4)

Landscape Character Areas Plan with RODP Layout -Enlargement Plan (Sheet 4 of 4)

Landscape Resources Plan with RODP Layout

Figure 10.9a

Landscape Resources Plan with RODP Layout -Enlargement Plan(Sheet 1 of 4) 

Figure 10.9b

Landscape Resources Plan with RODP Layout -Enlargement Plan(Sheet 2 of 4) 

Figure 10.9c

 

Figure 10.9d

 

Landscape Resources Plan with RODP Layout -Enlargement Plan(Sheet 3 of 4) 

Landscape Resources Plan with RODP Layout -Enlargement Plan(Sheet 4 of 4) 

Figure 10.10

Visual Sensitive Receiver Plan

Figure 10.11a

Figure 10.11b

Figure 10.11c

Figure 10.11d

Figure 10.11e

Figure 10.11f

Figure 10.11g

Figure 10.11h

Figure 10.11i

Figure 10.11j

Figure 10.11k

Figure 10.11l

Figure 10.11m

Figure 10.11n

Figure 10.11o

Figure 10.11p

Figure 10.11q

Figure 10.11r

Views of Visual Sensitive Receivers (1 of 18)

Views of Visual Sensitive Receivers (2 of 18)

Views of Visual Sensitive Receivers (3 of 18)

Views of Visual Sensitive Receivers (4 of 18)

Views of Visual Sensitive Receivers (5 of 18)

Views of Visual Sensitive Receivers (6 of 18)

Views of Visual Sensitive Receivers (7 of 18)

Views of Visual Sensitive Receivers (8 of 18)

Views of Visual Sensitive Receivers (9 of 18)

Views of Visual Sensitive Receivers (10 of 18)

Views of Visual Sensitive Receivers (11 of 18)

Views of Visual Sensitive Receivers (12 of 18)

Views of Visual Sensitive Receivers (13 of 18)

Views of Visual Sensitive Receivers (14 of 18)

Views of Visual Sensitive Receivers (15 of 18)

Views of Visual Sensitive Receivers (16 of 18)

Views of Visual Sensitive Receivers (17 of 18)

Views of Visual Sensitive Receivers (18 of 18)

Figure 10.12

Figure 10.12a

Figure 10.12b

Figure 10.12c

Overall Landscape Master Plan

Landscape Master Plan Area 1

Landscape Master Plan Area 2

Landscape Master Plan Area 3

Figure 10.13

Figure 10.13a

Figure 10.13b

Figure 10.13c

Mitigation Measures Plan

Mitigation Measures Plan -Enlargement Plan (Sheet 1 of 3)

Mitigation Measures Plan -Enlargement Plan (Sheet 2 of 3)

Mitigation Measures Plan -Enlargement Plan (Sheet 3 of 3)

Figure 10.14a

Figure 10.14b

Figure 10.14c

Figure 10.14d

Figure 10.14e

Figure 10.14f

Figure 10.14g

Figure 10.14h

Figure 10.14i

Figure 10.14j

Figure 10.14k

Figure 10.14l

Figure 10.14m

Figure 10.14n

Figure 10.14o

Figure 10.14p

Figure 10.14q

Figure 10.14r

Figure 10.14s

Figure 10.14t

Sample Photomontage VSR 1 Yuen Long Park tower (1 of 2)

Sample Photomontage VSR 1 Yuen Long Park tower (2 of 2)

Sample Photomontage VSR 5 Forefront Cyber Centre (1 of 2)

Sample Photomontage VSR 5 Forefront Cyber Centre (2 of 2)

Sample Photomontage VSR 13 Pathway near Muk Kiu Tau Tsuen (1 of 2)

Sample Photomontage VSR 13 Pathway near Muk Kiu Tau Tsuen (2 of 2)

Sample Photomontage VSR 15 One Hyde Park (1 of 2)

Sample Photomontage VSR 15 One Hyde Park (2 of 2)

Sample Photomontage VSR 16 Channel Pathway on Kung Um Road (1 of 2)

Sample Photomontage VSR 16  Channel Pathway on Kung Um Road (2 of 2)

Sample Photomontage VSR 18 Tai Lam Mountain1 Facing Northeast (1 of 2)

Sample Photomontage VSR 18 Tai Lam Mountain1 Facing Northeast (2 of 2)

Sample Photomontage VSR 23 Tai Lam Mountain6 Facing North  (1 of 2)

Sample Photomontage VSR 23 Tai Lam Mountain6 Facing North  (2 of 2)

Sample Photomontage VSR 29 Sham Chung Tsuen (1 of 2)

Sample Photomontage VSR 29 Sham Chung Tsuen (2 of 2)

Sample Photomontage VSR 31 Ho Hok Shan (1 of 2)

Sample Photomontage VSR 31 Ho Hok Shan (2 of 2)

Sample Photomontage VSR 44 Shap Pat Heung Road (1 of 2)

Sample Photomontage VSR 44 Shap Pat Heung Road (2 of 2)

Figure 10.15

Typical Detail of Grasscrete

Figure 10.16

Reference Images for Noise Barrier Designs

 

 

 

 

 

Appendix

 

Appendix 10.1

Broad Brush Tree Survey Report

Appendix 10.2

Predication of Visual Impact Based on Field of View

Appendix 10.3

Elevation of Enclosures Noise Barrier Design

Appendix 10.4

Noise Barriers and Enclosures



10                          Landscape and Visual Impacts

10.1                   Introduction

10.1.1.1            The following sections identify the potential landscape and visual impacts during the construction and operation of the PDA in YLS, in accordance with the Environmental Impact Assessment Ordinance. 

10.1.1.2            In accordance with the criteria as stated in Annexes 10 and 18 of the Technical Memorandum on EIAO-TM, the Landscape and Visual Impact Assessment (LVIA) for this project includes:

·                  a list of the relevant environmental legislation, standards and guidelines;

·                  a review of the relevant planning and development control framework;

·                  a landscape and visual impact assessment methodology;

·                  a landscape impact assessment section, including:

o      a landscape baseline study providing a comprehensive and accurate description of the baseline Landscape Resources (LRs) and Landscape Character Areas (LCAs) within the YLS assessment area;

o      identification of potential landscape impacts;

o      prediction of the nature of landscape impacts and the potential magnitude of change they will cause as well as the potential significance of  impacts before the implementation of mitigation measures;

o      recommendation of appropriate mitigation measures and associated implementation programmes;

o      prediction of the significance of residual landscape impacts after the implementation of the suggested mitigation measures;

·                  a visual impact assessment section, including:

o      a visual baseline study, providing comprehensive details of visual elements surrounding each PDA and their Visually Sensitive Receivers (VSRs);

o      identification of potential visual impacts;

o      prediction of the nature of visual impacts and the potential magnitude of change they will cause, as well as the potential significance of  impacts before the implementation of mitigation measures;

o      recommendation of appropriate mitigation measures and associated implementation programmes;

o      prediction of the significance of residual visual impacts after implementation of the suggested mitigation measures; and

·                  an assessment of the acceptability or otherwise of the predicted residual impacts, according to the five criteria set out in Annex 10 of the EIAO-TM, namely beneficial, acceptable, acceptable with mitigation measures, unacceptable or undetermined.

 

10.2                   Environmental Legislation, Standards and Guidelines

10.2.1.1            The following legislation, standards and guidelines are applicable to this LVIA associated with the construction and operation of the YLS PDA:

Legislation and Planning Standards

·                  Environmental Impact Assessment Ordinance (Cap. 499. S16) and the EIAO-TM Annexes 3, 10, 11, 18 and 20;

·                  Environmental Impact Assessment Ordinance Guidance Note 8/2010 (Preparation of Landscape and Visual Impact Assessment;

·                  Town Planning Ordinance (Cap131);

·                  Town Planning (Amendment) Ordinance, 2004;

·                  Hong Kong Planning Standards and Guidelines (HKPSG) Chapters 4, 10, 11 and 12;

·                  Forests and Countryside Ordinance (Cap.96); and

·                  Protection of Endangered Species of Animals and Plants Ordinance (Cap.586).

Technical Circulars/ Guidelines

·                  Development Bureau (DEVB) Technical Circular (Works) (TC(W)) No. 7/2015 – Tree Preservation;

·                  DEVB TC(W) No. 2/2012 – Allocation of Space for Quality Greening on Roads;

·                  DEVB TC(W) No. 3/2012 – Site Coverage of Greenery for Government Building Projects;

·                  DEVB TC(W) No. 2/2013 – Greening on Footbridges and Flyovers;

·                  DEVB TC(W) No. 6/2015 – Maintenance of Vegetation and Hard Landscape Features;

·                  Greening, Landscape and Tree Management (GLTM) Section of DEVB – Guidelines on Greening of Noise Barriers, April 2012;

·                  Environment, Transport and Works Bureau (ETWB) TC(W) No. 11/2004 – Cyber Manual for Greening;

·                  ETWB TC(W) No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for their Preservation;

·                  ETWB TC(W) No. 5/2005 – Protection of Natural Streams/ Rivers from Adverse Impacts Arising from Construction Works;Geotechnical Engineering Office (GEO) Publication No. 1/2011 – Technical Guidelines on Landscaping Treatment for Slopes;

·                  Highways Department (HyD) Guidelines No. HQ/GN/13 – Interim Guidelines for Tree Transplanting Works under Highways Department's Vegetation Maintenance Ambit;

·                  HyD Guidelines No. HQ/GN/15 – Guidelines for Greening Works along Highways; and

·                  Drainage Services Department (DSD) Practice Note (PN) No.1/2015 – Guidelines on Environmental and Ecological Considerations for River Channel Design.

Other Reference Information and Planning Studies

·                  Landscape Character Map of Hong Kong (2005 Edition);

·                  Urban Design Guidelines for Hong Kong issued by the Planning Department (2003); and

·                  Technical Report of “Study on Landscape Value Mapping of Hong Kong”by Planning Department.

10.3                   Landscape Impact Assessment Methodology

10.3.1             Identification of the Baseline LRs and LCAs within the Study Area

10.3.1.1            The landscape baseline study identifies all LRs and LCAs located within 500m of the Project Boundary using a combination of desktop study and site verification.

10.3.1.2            The Project Site has been divided into broad units of similar character based on a process of landscape characterisation which draws on the information gathered in the desktop study and site surveys. In addition, the Planning Department “Study of Landscape Value Mapping of Hong Kong” and “Map of Land Utilization in Hong Kong” are also considered. Typical elements which contribute to the landscape character include:

·                Local topography;

·                Woodland extent and type;

·                Other vegetation/ ground cover types;

·                Built form (including scale and appearance);

·                Patterns of settlement;

·                Wildness.

·                Land use;

·                Scenic spots;

·                Details of local materials, styles, streetscapes condition;

·                Prominent watercourses;

·                Cultural and religious features;

10.3.2             Broad Brush Tree Survey

10.3.2.1            For Landscape and Visual Impact Assessment purposes, the study carried out a broad-brush tree survey within the development boundary to estimate the numbers of existing trees, dominant species, maturity, rarity and any plant species of conservation interest (including Old and Valuable Trees (OVTs), Potentially Registrable OVT (POVT) or rare/ protected species) and areas for tree preservation and landscape restoration.

10.3.2.2            The detail tree survey methodology and tree survey record shall be referred to Appendix 10.1.

10.3.3             Sensitivity of LCAs and LRs

10.3.3.1            A qualitative description of LCAs and LRs has been provided and their extent quantified either by area or length. The sensitivity of the LCAs and LRs are evaluated and rated taking into account the following criteria:

·                  whether the landscape character/ resource is common or rare;

·                  whether it is considered to be of local, regional, national or global importance;

·                  whether there are any statutory or regulatory limitations/ requirements relating to the resource;

·                  the quality and condition of the resource;

·                  the maturity of the resource; and

·                  the capacity of the landscape character/ resource to accommodate change.

10.3.3.2            The sensitivity ratings are classified as below:

High

LR or LCA of high quality and value, which is sensitive to even relatively small changes.

Medium

LR or LCA of moderate quality and value, which is reasonably tolerant to change.

Low

LR or LCA with low quality and value, which is largely tolerant to change.

10.3.4             Magnitude of Change to LRs and LCAs

10.3.4.1            The assessment of “Magnitude of Change” for landscape impacts considers the following criteria: 

·                  the physical extent of the impact;

·                  the landscape context of the impact; and

·                  the time-scale of the impact - temporary (short, medium or long term) or a permanent reversible/ irreversible change.

10.3.4.2            The magnitude of change is considered separately for the construction phase and operational phase; the ratings are classified as below:

Large

LR or LCA will suffer a major change.

Intermediate

LR or LCA will suffer a moderate change.

Small

LR or LCA will suffer a barely perceptible change.

Negligible

LR or LCA will suffer no discernible change.

10.3.5             Impact Significance in Relation to LRs and LCAs

10.3.5.1            The assessment of the “Impact Significance Threshold before Mitigation” for landscape impacts is considered during the construction and operational phases by synthesizing the “Sensitivity” and “Magnitude of Change” for various LRs and LCAs according to Table 10.3.1. The degree of significance has been divided into four thresholds identified below:

Substantial

Adverse/ beneficial impact where the proposals will cause significant deterioration or improvement in existing landscape quality

Moderate

Adverse/ beneficial impact where the proposal will cause a noticeable deterioration or improvement in existing landscape quality

Slight

Adverse/ beneficial impact where the proposal will cause barely perceptible deterioration or improvement in existing landscape quality

Insubstantial

No discernible change in the existing landscape quality

Table 10.3.1  Relationship between sensitivity of LR/ LCA and magnitude of change in defining impact significance

 

Receptor Sensitivity (of LR/LCA)

Low

Medium

High

Magnitude

of Change

Negligible

Insubstantial

Insubstantial

Insubstantial

Small

Slight

Slight/ Moderate

Moderate

Intermediate

Slight/ Moderate

Moderate

Moderate/ Substantial

Large

Moderate

Moderate/ Substantial

Substantial

10.4                   Visual Impact Assessment Methodology

10.4.1             Identification and Plotting of the Visual Envelope (VE)

10.4.1.1            The assessment area for the visual impact assessment is defined by the VE which includes all the points from which the scheme proposals may be visible, comprising the viewshed formed by natural/ manmade features such as ridgelines, built form or areas of woodland/ large trees.  This area is identified through a combination of detailed field surveys, desktop study and review of aerial photography.

10.4.1.2            To ensure a comprehensive understanding of the visual setting and to demonstrate the potential impacts of the development from varying distances and scales, representative VSRs have been selected which cover the following VSR levels:

Strategic

This refers to a point in the landscape which provides a large scale overview of the site incorporating the adjacent districts within the wider landscape setting such as from very tall buildings, high ground and mountain peaks.

District

This refers to a point where a medium scale view covering the site and the immediate setting or district is possible such as from medium scale buildings or low hillsides.

Local

This refers to a point where a small scale view of part of the site is possible such as from the local streetscape or low rise buildings in the vicinity.

10.4.2             Sensitivity of VSRs

10.4.2.1            VSRs within the VE during the construction and operational phases of the development are identified.  Views from these points are recorded, described and the sensitivity assessed. 

10.4.2.2            The assessment of sensitivity is based on the quality and extent of the existing view.  The factors affecting the sensitivity of receivers for evaluation of visual impacts include the following:

·                  Value and quality of existing views;

·                  Availability and amenity of alternative views;

·                  Type and estimated number of receiver population;

·                  Duration or frequency of view; and

·                  Degree of visibility.

10.4.2.3            The VSRs and their sensitivity can be broadly categorised as follows:

High

The VSR is highly sensitive to any changes in the viewing experience - Residential properties where the principle view is of the development site, formalised public viewpoints or designed landscape vistas. 

Medium

The VSR is moderately sensitive to any changes in the viewing experience - Outdoor workers, office workers, recreational users, residential properties where the secondary view is of the development.

Low

The VSR is slightly sensitive to any changes in the viewing experience - People travelling though the landscape (by private/ public motorised transport).

10.4.3             Identification of Potential Sources of Visual Impact

10.4.3.1            These are the various elements of the construction works and operational procedures that could generate visual impacts. They will create varying levels of visual impact due to factors such as visual obstruction, degradation of the quality of existing views and incompatibility with the surrounding landscape setting.

10.4.4             Magnitude of Change to VSRs

10.4.4.1            Magnitude of change to an existing view can be determined by a number of interrelated factors, including:

·                  compatibility of the Project with the surrounding landscape;

·                  duration of impacts under construction and operation phases;

·                  scale of development;

·                  reversibility of change;

·                  viewing distance; and

·                  potential obstruction of view.

10.4.4.2            The visual impact of a development can be quantified by reference to the degree of influence on a person’s field of vision referencing the typical parameters of human vision based on anthropometric data. The prediction of visual impact based on the field of view can be referred to Appendix 10.2.

10.4.4.3            The duration of the impact during construction and operation is determined based on the following ratings:

Construction

 

Temporary

Construction works that will only be visible for a short duration of the overall construction period.

Permanent

Construction work will be visible throughout the whole construction period.

Operation

 

Temporary

Elements of the Project that will be open to the view for a short period of time but is likely disappear at an early stage in the operational phase with minimal intervention or mitigation, for example, further growth of existing tree screening.

Permanent

Views of the Project that will remain permanently open to the view.

10.4.4.4            The magnitude of changes at different stages of the construction and operational phases are considered separately, with ratings set out below:

Large

The VSRs would suffer a major change in their viewing experience.

Intermediate

The VSRs would suffer a moderate change in their viewing experience.

Small

The VSRs would suffer a small change in their viewing experience.

Negligible

The VSRs would suffer no discernible change in their viewing experience.

10.4.5             Impact Significance to VSRs

10.4.5.1            The impact significance to VSRs deals with the prediction of “Impact Significance Threshold before Mitigation” for visual impacts through combining the “Sensitivity to Change” and “Magnitude of Change” for various VSRs according to Table 10.4.1 below.

10.4.5.2            The degree of significance is divided into four thresholds:

Substantial

Adverse/ beneficial impact where the proposal would cause significant deterioration or improvement in existing visual quality

Moderate

Adverse/ beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing visual quality

Slight

Adverse/ beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in existing visual quality

Insubstantial

No discernible change in the existing visual quality

Table 10.4.1  Relationship between sensitivity of VSRs and magnitude of change in     
                       defining impact significance

 

Receptor Sensitivity (of VSR)

Low

Medium

High

Magnitude

of Change

Negligible

Insubstantial

Insubstantial

Insubstantial

Small

Slight

Slight/ Moderate

Moderate

Intermediate

Slight/Moderate

Moderate

Moderate/ Substantial

Large

Moderate

Moderate/ Substantial

Substantial

10.5                   Identification of Potential Landscape and Visual Mitigation Measures

10.5.1.1            Alternative design configurations, design and construction methodologies that will avoid or reduce landscape and visual impacts are considered before adopting other mitigation measures. The recommended mitigation measures are considered for both construction and operational phases to prevent or minimise unavoidable adverse impacts.

10.6                   Residual Impact Assessment Methodology

10.6.1             Identification of Residual Impact

10.6.1.1            This part of the assessment describes any unavoidable residual adverse landscape and visual impacts to LRs, LCAs and VSRs. Residual impacts are those which remain post implementation of mitigation measures after commissioning of the development (operation Day 1 & Year 10). According to the implementation programme (refer to Chapter 2), the whole Project is divided into four main stages and the construction period for these stages are overlapped. Operation phase will start at the first year of population intake for each stage listed as below:

                                                 ·          Stage One: Construction phase commences in Year 2020, Operation phase starts from Year 2029;

                                                 ·          Stage Two: Construction phase commences in Year 2022, Operation phase starts from Year 2033 ;

                                                 ·          Stage Three: Construction phase commences in Year 2031, Operation phase starts from Year 2038; and

                                                 ·          Stage Four: Construction phase commences in Year 2032, Operation phase starts from Year 2038.

10.6.1.2            The level of impact is derived from the magnitude of change which the development will cause to the LR, LCA or VSR taking into account its ability to tolerate change and effectiveness of mitigation measures.

10.7                   Overall Result of the Landscape and Visual Impact Assessment

10.7.1.1            An overall assessment is made on the development based on the identified landscape and visual impacts described in Table 10.7.1:

Table 10.7.1  Residual impact assessment methodology

Overall Result of LVIA Assessment

Description

Beneficial

The impact is beneficial if the Project will complement and enhance the landscape value and visual character of its setting, will follow the relevant planning objectives and will improve overall landscape and visual quality.

Acceptable

The impact is acceptable if the assessment indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the Project, or no interference with key views.

Acceptable with mitigation measures

The impact is acceptable with mitigation measures if there will be some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures.

Unacceptable

The impact is unacceptable if the adverse effects are considered too excessive and are unable to mitigate practically.

Undetermined

The impact is undetermined if significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study.  Further detailed study will be required for the specific effects in question.


 

10.8                   Review of Planning and Development Control  Framework

10.8.1             Review of Existing OZPs

10.8.1.1            A review of relevant statutory and departmental plans has been undertaken to identify areas of high landscape value, open space, amenity area, conservation area, green belt designations and existing and planned visually sensitive receivers. 

10.8.1.2            The PDA and works area of the proposed infrastructures (including road improvement works, service reservoir, nullah and road widening works)  have been superimposed onto existing OZPs and RODP (as shown on Figure 10.1 and 10.2) to determine the potential influence on the existing zonings. Their extent are covered by the following OZPs:

·                  Approved Tong Yan San Tsuen (TYST) OZP No. S/YL-TYST/10

·                  Approved Tai Tong (TT) OZP No. S/YL-TT/16

·                  Yuen Long OZP No. S/YL/23,

10.8.1.3            A breakdown of the land use zonings within the study area and site boundary is provided in Table 10.8.1 below.

Table 10.8.1  Review of RODP under the Existing OZPs

Item

Existing Zoning Type *

Proposed Development Works within OZP

Changes in RODP^

1

Green Belt (GB)

Preserved Agricultural Land,

Public Recreational Areas,

Open Storage Development,

Proposed Road Network,

Road Improvement Works,

Service Reservoir

(GB), GB(1), AGR, LO,  A, OU(OS), OU (SU)2,  (OU (SU)1, OU(Service Reservoir), Road

2

Industrial (I) (Group D)

Storage and Workshop,

Public Recreational Areas,

Proposed Road Network

OU(SU)1, OU (S+W), LO, DO, Road

3

Government/

Institution/

Community

(G/IC)

Government and Institution Development,

Residential Development,

Open Storage Development,

Public Recreational Areas,

Road Improvement Works

G/IC, OU(SU)1, LO (1), R5, Road

4

Residential (Group B) R(B))

Low-rise Residential Development,

Retained Existing Development Area,

Public Recreational Areas

R5, R5(EDA), LO (1), LO, DO

5

Residential (Group C) R(C)

Low-rise Residential Development,

Green Buffer Area

A, R5, GB

6

Residential (Group D)

R(D)

Retained Existing Development Area,

Low-rise Residential Development,

Government and Institutional Development,

Mixed Use Development,

Agricultural Land,

Public Recreational Areas

DO, OU(MU), G, E, R4, R5, GB, GB(1), AGR, LO, R6, R5(EDA), Road

7

Open Storage (OS)

Mixed Use Development,

Village Development,

Proposed Road Network

OU(MU), A, V, Road

8

Undetermined (U)

Retained Existing Development Area,

Residential Development,

Government and Institutional Development,

Mixed Use Development,

Public Recreational Areas,

Sewage Treatment Works,

Proposed Road Network,

Nullah Revitalisation Works

RSc, R1(SSF)c, R1c, R6, R(EDA), R2c, R3, R2(SSF)c, G, OU(MU), OU(STW), E, DO, LO, A, GB, GB(1), Road

9

Other Specified Uses (OU, Rural Use)

Retained Existing Development Area,

Middle-rise Residential Development,

Government and Institutional Development,

Public Recreational Areas,

Proposed Road Network

R3, R6, G, E, DO, LO, R5 (EDA), Road

10

Agriculture (AGR)

Agricultural Land,

Government and Institutional Development,

Public Recreational Areas,

Proposed Road Network

E, G, AGR, DO, LO, Road

11

Open Space (O)

Road Improvement Works

Road

Note: [*] Within 500m assessment area only. Zonings that are not affected are omitted.

          [^] Land Use Types of RODP. Refer to Figure 10.2.

10.8.1.4            In OZP No. S/YL-TYST/10, the proposed PDA of YLS would modify mainly the ‘Undetermined (U)’ which comprises previously developed in OZP No. S/YL-TYST/10 into a new comprehensive development, which includes residential, commercial, government, education, mixed use, open space and etc. It is considered that the proposed development would be broadly compatible and in some cases positive impacts may be generated where degraded and poor quality current landscapes are redeveloped.

10.8.1.5            In relation to ‘GB’ zoning which comprises the existing agricultural land near Shan Ha Tsuen, the RODP would retain most of these areas as ‘GB’ and ‘AGR’. The other parts would be changed into open space, amenity and some storage uses.

10.8.1.6            The ‘R(B)’, ‘R(C)’ and ‘R (D)’ which have undergone previous development and will be affected under the RODP would be redeveloped and differentiated into new zonings of residential development. It is considered that these landuses would generally be compatible with the propose development.

10.8.1.7            In addition, the landuses affected in OZP No. S/YL-TT/16 including relatively small areas of ‘OU (Rural use)’, ‘AGR’ and ‘O’ along Kung Um Road,  are proposed to be generated into various kinds of landuses within the PDA, such as residential, education and G/IC. The road improvement works of the RODP would also cover some small patches of ‘O’ and ‘G/ IC’ in OZP No. S/YL/23. 

10.8.2             Consideration of The Development Option

10.8.2.1            In general, the Project Proponent has been proactively conducting a series of community engagement (CE) exercise (including forums and workshops) to collect views and opinions from stakeholders, green groups and local communities etc. on the development proposals. Therefore, the Stage 1, 2 and 3 of CE will help to enhance the overall visual quality of the PDA through the displacement of brownfield sites.

10.8.2.2            PODP was formulated in 2014 which aimed to maximize the development potential for housing supply by introducing high to medium density zones at the northern part of PDA and Medium to Low Density zone at the southern part of the PDA. All proposed new development was directly adjacent to the existing villages.

10.8.2.3            Further to the public comments received in CE2, additional 20m wide “Local Open Space”, “Low Building Area” and “Non Building Area” were introduced on the draft RODP to further enhance the visual compatibility and permeability by respecting the surrounding development and natural environment.

10.8.2.4            The RODP has further optimized the green space network throughout the PDA by enlarging the district open space and separation between development sites. Apart from retaining the key view corridor, the secondary view corridors within the PDA have been further expanded to enhance the visual linkage between Yuen Long New Town and Tai Lam Country Park.

10.8.3             Key Development Parameters

10.8.3.1            The proposed development of YLS follows a tapering building height profile from the urban north to the Tai Lam Country Park in the south. With the intention to integrate the PDA with its surrounding context, plots within higher building height profile are situated to be located to the north near the existing Yuen Long New Town. The north of the PDA at Kung Um Road proposes housing development of 30-33 domestic storeys (approx. from 101m to 110m).

10.8.3.2            To the south, the RODP will have a much lower building height profile to provide a transition towards the rural setting of Tai Lam Country Park. Along the edges and towards the south of this planning area, housing development ranging from 11 to 27 storeys (approx. from 40m to 95m) is permitted.

10.8.3.3            For the low-rise development in TYST, building height of majority of the proposed developments will be 4-5 storeys (approx. from 13m to 16m). The proposed developments at “OU(MU)” zone located adjacent to the TYST Interchange is restricted to a maximum building height of 12 storeys (approx.. up to 68m).

10.8.4             Proposed Infrastructure Works

Road Improvement Works

10.8.4.1            Improving connectivity is one of the guiding principles and planning and urban design framework. The main objective of the proposed road network is to improve connectivity with Yuen Long New Town, the proposed Hung Shui Kiu (HSK) NDA, and provide a direct access and egress to Yuen Long Highway(YLH). Long Hon Road is proposed to be upgraded and extended to Kung Um Road to form a key corridor of the PDA (refer to Figure 10.2 and 10.12).

10.8.4.2            In terms of external connectivity to Yuen Long Highway, the improved TYST Interchange would be modified to cater for all traffic movements to and from YLH, Long Tin Road and Long Hon Road. In addition, a pair of slip roads running on both sides and parallel with YLH y from Kung Um Road eastward are proposed to provide connectivity to YLH via Shap Pat Heung Interchange.

10.8.4.3            A continuous cycle track designated as “Road” will be provided along proposed residential developments with the cycle track network along the road (refer to Figure 10.2 and 10.12).

Nullah Revitalisation

10.8.4.4            There are three existing drainage channels within the PDA, namely Yuen Long Nullah, Tin Tsuen Channel and Yuen Long West Nullah, and decking of these channels would be avoided as far as practicable. Through revitalisation, these channels would provide a landscaped and pleasure walking environment for the community (refer to Figure 10.2 and 10.12).

Service Reservoir

10.8.4.5            The zoning of OU located to the south of the PDA at TYST area is intended for a potential reclaimed water service reservoir. Considering the topography, the proposed location is recommended to minimise cut extent and hence visual impact. The zone is subject to a maximum building height of 1 storey (refer to Figure 10.2).

Retention Tank

10.8.4.6            An underground Retention Tank (RT) or a retention lake integrating with the open space design is proposed near TYST interchange to mitigate the impact of additional surface runoff generated from the proposed development. This facility will be constructed underground, and the upper would be designed with some landscape features to mitigate the potential impacts (refer to Figure 10.2).

Sewerage Alignment

10.8.4.7            A new sewerage alignment connecting Yuen Long South to the existing inert chamber of the NWNT effluent tunnel at San Tai for discharging to Urmston Road submarine outfall has also been proposed by the development. The alignment of the sewage mains are installed underground.


10.9                   Baseline Study

10.9.1             Landscape Baseline Conditions

10.9.1.1            The landscape baseline review comprises the identification of all existing LCAs and LRs within 500m assessment area.

10.9.1.2            The landscape character has been influenced by many different types and scales of human development set within a dramatic natural landscape of mountains, urban development landscape and coastal areas. This has formed a series of LCAs of varying landscape value and development sensitivity. The LCAs in the study area are classified into major categories as follows:

LCA1 – Miscellaneous Rural Fringe Landscape, this LCA is subcategorized as follows:

·         LCA1a – Miscellaneous Rural Fringe Landscape - Open Storage/ Rural Built Area

·         LCA1b – Miscellaneous Rural Fringe Landscape - Lowland Agricultural Land

LCA2 – Miscellaneous Urban Fringe Landscape

LCA3 – Upland and Hillside Landscape

LCA4 – Settled Valley Landscape

LCA5 – Park Urban Landscape

LCA6 – “Hui” Urban Landscape

LCA7 – Urban Peripheral Village Landscape

LCA8 – Transportation Corridor Landscape

10.9.1.3            There are important LRs with known landscape value in the area. The highest value and most sensitive LRs generally occur within the upland areas within the assessment area. Complex LRs can be classified into different major categories, as follows:

LR1 – Agricultural Land, this LR is subcategorized as follows:

·         LR1a – Active Agricultural Land 

·         LR1b – Abandoned Agricultural Land

·         LR1c – Orchard

LR2 – Lowland Mixed Trees, Shrubland and Grassland

LR3 – Hillside Shrubland and Grassland

LR4 – Secondary Woodland 

LR5 – Plantation

LR6 – Urban Park

LR7 – Road and Urban Infrastructure

LR8 – Major Transport Corridor

LR9 – Urbanised Development

LR10 – Village Type Development

LR11 – Open Storage/ Rural Built Area

LR12 – Disturbed Area

LR13 – Agricultural Pond

LR14 – Channelised Watercourse

LR15 – Watercourses of higher ecological value

LR16 – Reservoir

10.9.1.4            The landscape resources and landscape character areas within the assessment area are described in further detail in Section 10.9.3 together with their sensitivity.

10.9.2             Broad Brush Tree Survey Result

10.9.2.1            A broad-brush tree survey has been carried out within the development boundary that estimates that there are approximately 17,421 trees consisting of approx. 170 species. 35 trees were rare species (Aquilaria sinensis and Artocarpus hypargyreus) and 42 trees were POVT. The dominant tree species were Acacia confusa, Leucaena leucocephala, Ficus microcarpa, Macaranga tanarius var. tomentosa, and Bauhinia spp. While most of the trees surveyed belong to common tree species of variable qualities, some rare tree species and other trees of relatively outstanding quality were found occasionally. These are summarised with individual LR descriptions. Many trees are found in the foothills of the natural upland, as well as the rural fringe in between different villages and they are generally mature. The indicative locations of the tree groups as well as the identified rare/ protected specimens are marked on the Broad Brush Tree Survey Report in Appendix 10.1.

10.9.2.2            The area of identified Landscape Resources within the development boundary and estimated number of trees within each LR are presented in Table 10.9.1.

Table 10.9.1  Broad Estimated Number of Trees within each LR

ID

Landscape Resources

Area within PDA and Working Area for the Proposed Infrastructure (ha)

Within Tree Groups

Estimated Number of Trees within the LR

LR1a

Active Agricultural Land 

15.0

Group1,Group6,Group9,Group15,Group19

498

LR1b

Abandoned Agricultural Land

1.1

Group8, Group9,  Group15

52

LR1c

Orchard

2.7

Group4,Group10, Group11,Group15

811

LR2

Lowland Mixed Trees, Shrubland and Grassland

11.6

Group1,Group3,Group5, Group6,Group8,Group9,Group11,Group13, Group15, Group16, Group19

1926

LR3

Hillside Shrubland and Grassland

3.8

Group4,Group9, Group11, Group17

330

LR4

Secondary Woodland 

14.6

Group2, Group4, Group5, Group8, Group9, Group10, Group11,Group13

3704

LR5

Plantation

17.4

Group2, Group5, Group11, Group12, Group13, Group14

4798

LR6

Urban Park

0.2

Group5

74

LR7

Road and Urban Infrastructure

8.8

Group5,Group6, Group11,Group15

138

LR8

Major Transport Corridor

0

N/A

N/A

LR9

Urbanised Development

12.1

Group4,Group5, Group6, Group8

493

LR10

Village Type Development

10.2

Group3,Group5, Group6, Group8, Group9, Group11, Group15, Group16

730

LR11

Open Storage/ Rural Built Area

142.2

Group1, Group4, Group5, Group6,Group7, Group8, Group9, Group12,Group13, Group14, Group15, Group16, Group17, Group18, Group19

3670

LR12

Disturbed Area

2.9

Group5, Group6,Group8

197

LR13

Agricultural Pond

0.3

N/A

N/A

LR14

Channelised Watercourse

7.7km

N/A

N/A

LR15

Watercourses of higher ecological value

4.1km

N/A

N/A

LR16

Reservoir

0

N/A

N/A

 


 

10.9.3             Baseline Landscape Character Areas and Landscape Resources

10.9.3.1            The baseline LCAs and LRs of the 500m assessment area are detailed along with their sensitivity in Tables 10.9.2 and 10.9.3. The figures presenting this information are shown in Figure 10.4 to 10.6.

Table 10.9.2  LCAs in the Assessment Area and their Sensitivity

LCA 1a Miscellaneous Rural Fringe Landscape – Open Storage/ Rural Built Area (545.6ha)

LCA refers to previous agricultural landscape to the south of Yuen Long which has been colonised by open storage, horticulture, industrial estates as well as parking land uses which has fragmented the development pattern of the local landscape. In places, ad-hoc development appears to have followed traditional agricultural field boundary to generate an organic development pattern when viewed from elevated points around the site.  These developments are predominantly located in the southern portion of the Project area. Small pockets of woodland are scattered within the landscape helping to break up the monotonous roofline of temporary sheds and retain a sense of rural character. One built heritage, the Yeung Hau Temple at Tong Yan San Tsuen, is identified within this LCA (Detail information refer to Chapter 13). Major drainage nullahs which sit within Kung Um Road, Kiu Hing Road and Lam Tai West Road are high visible geometric features which sit awkwardly against the rural context and against the grain of sprawling development in the surrounding developed areas.

 

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

LCA 1b Miscellaneous Rural Fringe Landscape  - Lowland Agricultural Land (71.0ha)

LCA refers to existing agricultural landscape within the assessment area, which is found mainly in the village areas on the east of Kiu Hing Road, southeast of Shan Ha Tsuen and east of Tong Yan San Tsuen. Tree vegetation is generally sparse and restricted to field boundaries. These areas remain many of the rural characteristics to the local landscape, but are also undergoing significant changes in characters by the rural land use changes in recent decades.

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Medium

Sensitivity - Medium

LCA 2 Miscellaneous Urban Fringe Landscape (91.9ha)

LCA refers to landscape found on the periphery of Yuen Long between Castle Peak Road, YLH y and Long Hon Road forming the transition point from the dense urban core of Yuen Long New Town to the rural outskirts.  Locally the development pattern includes a mixture of industrial, village (Tong Yan San Tsuen), burial grounds, low to medium rise residential and GIC land uses.  This is set within pockets of mature woodland planting which cover a significant area although are very fragmented/ disconnected from each other.

Quality and Maturity – Medium

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

LCA 3 Upland and Hillside Landscape (161.8ha)

LCA refers to the large scale elevated upland landscape (generally between 40 to 300mPD) of Tai Lam Country Park.  The hillsides consist of rocky outcrops, exposed soils, scrub vegetation and pockets of woodland cover.  Numerous pylons cross this landscape detracting from the naturalness of the setting. Informal un-surfaced paths provide pedestrian access to the top of the hill, significant erosion has occurred as a result of use by motorcyclists which has spread beyond these access routes which has affected vegetation cover and visual amenity.  Due to lack of development, the character of this area is wild, and feels remote from the surrounding urban developments.  Numerous seasonal and permanence streams emanate from the hillside following the shallow ravines to the foot of the hillside.

Quality and Maturity – Medium

Rarity – Low

Ability to accommodate change – Low

Sensitivity - High

LCA 4 Settled Valley Landscape (11.6ha)

LCA refers to the valley landscape belonging to the Tai Lam Country Park.  This valley area is almost surrounding by other uplands of Tai Lam Mountains while a small area of countryside and villages in the north.  Several paths from the top of the hill provide the pedestrian access from the mountains to the local villages. With low development density, most part of this area covers with vegetation and plants, so the landscape character quality and value consider as high. The area has low tolerance to accept change and the sensitivity is high. 

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Low

Sensitivity - High

LCA 5 Park Urban Landscape (10.4ha)

LCA refers to Yuen Long Park, the major passive recreational park within Yuen Long New Town which falls partly within the study area.  The park consists of sports facilities, ornamental planting, lawns, pathways, sitting areas, water features, pavilions, an aviary/ viewing tower and park operation/ maintenance buildings.  The elevation of the landscape increases towards the centre which helps to evoke a more naturalistic appearance.  The landscape is a mixture of informal and formal landscape styles with a strong presence of soft landscape.   The park is surrounded by development which creates a distinct boundary or edge.

Quality and Maturity – High

Rarity – High

Ability to accommodate change – Low

Sensitivity - High

LCA 6 “Hui” Urban Landscape (34.9ha)

LCA refers to a very small portion of the core of the Yuen Long New Town which formed the centre of the town prior to the New Town development, which falls within the outer edge of study.  In this location, the LCA covers the Park Royale Development to the west of Yuen Long Park comprising medium rise residential development along Shan Ha Road.  Typically this landscape is distinguishable from the surrounding new town by the simple building character, older building stock, intimate scale, narrow streets and orthogonal street blocks.

Quality and Maturity – Low

Rarity – Medium

Ability to accommodate change – High

Sensitivity - Low

LCA 7 Urban Peripheral Village Landscape (238.8ha)

LCA refers to the medium scale village within the assessment area. The area consists of grouped village houses, which include traditional dwellings and temples as well as newer houses, all separated by narrow footpaths or lanes. A declared monument (Cheung Anchestral Hall) is found within this LCA (Detail information refer to Chapter 13). Part of the area has been changed to car park uses. Vegetation consists of scattered matured trees and peripheral woodland at the backside of the village.

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Medium

Sensitivity - Medium

LCA 8 Transportation Corridor Landscape (55.1ha)

LCA refers to the main transport corridor like YLH, which connecting different areas from Yuen Long to Tuen Mun. The YLH comprises a 4 lane highway delineated with vertical concrete barriers and boundary fencing. Vegetation cover is restricted to a narrow verges with grass, hedge and small tree planting.

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

10.9.3.2            In summary, LCAs of ‘High’ sensitivity include LCA3 ‘Upland and Hillside Landscape, LCA4 ‘Settled Valley Landscape’ and LCA5 ‘Park Urban Landscape’. This is as a result of the natural qualities or high amenity landscape features of these LCAs.

10.9.3.3            LCAs of ‘Medium’ sensitivity include LCA1b ‘Miscellaneous Rural Fringe Landscape – Lowland Agricultural Land’ and LCA7 ‘Urban Peripheral Village Landscape’.  In this case, these resource have undergone disturbance as a result of human activity or urban development, however, they retain some natural features and landscape amenity value.

10.9.3.4            The other LCAs are considered to have ‘Low’ sensitivity including LCA1a ‘Miscellaneous Rural Fringe Landscape – Open Storage/ Rural Built Area’, LCA2 ‘Miscellaneous Urban Fringe Landscape’, LCA6 ‘“Hui” Urban Landscape’ and LCA8 ‘Transportation Corridor Landscape’. In this case, these LCAs have undergone significant change as a result of urban development.

Table 10.9.3  LRs in the Assessment Area and their Sensitivity

LR 1a Active Agricultural Land (53.6ha)

LR refers to various scale active agricultural land holdings within the assessment area, including wet and dry agricultural lands under cultivation. They are mainly located within the village areas on the east of Kiu Hing Road (including those near Ma Tin Pok, Fraser Village and Tin Liu Tsuen, west of Shui Tsiu San Tsuen Road, and in Yeung Ka Tsuen), north of TYST Interchange, near Fui Shan Wai, southeast of Sha Tseng Tsuen, southwest of Shan Ha Tsuen and those scattered in Shap Pat Heung, Kong Tau Tsuen and Chuk San Tsuen. Among those, the agricultural land adjoining Shan Ha Tsuen is the largest agricultural land in the PDA and the Assessment Area.

The periphery of the land conatins numerous tree, typical species include Macaranga tanarius, Eucalyptus spp., Ficus spp. Fruit trees such as Artocarpus heterophyllus, Carica papaya, Clausena lansium, Dimocarpus longan, Litichi chinensis and Mangifera indica are also commonly planted in this LR type. These trees range from semi-mature and mature and are generally in fair to good condition.

Two (2) nos. of POVTs as Important Trees, T-0018 (Ficus elastica) and T-0026 (Celtis sinensis), are located within the extent of this LR. No trees of rare and protected species are found during the survey.

This resource is considered as ‘High’ for landscape quality. The overall sensitivity is considered to be ‘High’.

Quality and Maturity – High

Rarity – Medium

Ability to accommodate change – Low

Sensitivity - High

LR 1b Abandoned Agricultural Land (3.5ha)

LR refers to these inactive agricultural lands identified in the assessment area. These fallow fields were recorded outside the PDA in Yeung Ka Tsuen, Tai Kei Leung, Sheung Yau Tin Tsuen and in the village areas east of Kiu Hing Road, and within the PDA in the large agricultural land adjoining the southwest of Shan Ha Tsuen respectively.

These inactive agricultural fields are dominated by weedy trees and shrubs such as Leucaena leucocephala and Lantana camara. Tree age ranges between semi-mature and mature and general condition is fair.

No trees of POVT, rare and protected species are found during the survey.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Medium

Sensitivity - Medium

LR 1c Orchard (13.9ha)

LR refers to those orchards of varying sizes comprising common fruit trees dominated by Clausena lansium, Dimocarpus longan, Litchi chinensis and Mangifera indica. The resources are mainly located in Yeung Ka Tsuen, in the village areas to the west of Shui Tsui San Tsuen Road and in Fui Sha Wai, and the planting areas near the Tin Shui Wai West Interchange and existing Tan Kwai Tsuen Fresh Water Service Reservoir. These trees range from semi-mature and mature and are generally in fair to good condition.

In addition, there are two considerable sizes of Lychee orchards located at the junction between the mature secondary woodland and large agricultural lands in Shan Han Tsuen. These Lychee woodlands appeared to be abandoned orchards and comprise mature/ over-mature trees of Litchi chinensis and with very sparse understory and lack of native plant species.

Among these trees, two (2) nos. of POVTs as Important Trees, T-0015 (Litchi chinensis) and T-0016 (Celtis sinensis), are identified. No trees of rare and protected species are found during the survey.

This resource is considered as ‘High’ for landscape quality. The overall sensitivity is considered to be ‘High’, due to its important ecological function.

Quality and Maturity – High

Rarity – Medium

Ability to accommodate change – Low

Sensitivity - High

LR 2 Lowland Mixed Trees, Shrubland and Grassland (36.1ha)

LR refers the fringes of the developed area within the low lying plains, isolated undeveloped landscape between village areas, scattered open space within villages and settlements. In those areas,  a mixture vegetation cover of trees, shrubs and grasses has colonised the spaces. The density of trees’ coverage ranges from low to medium.

Typical species include Bauhinia blakeana, Acacia confusa, Chukrasia tabularis var. velutina, Delonix regia, Lagerstroemia speciosa, Ficus microcarpa, Bombax ceiba, Callistemon viminalis, Macaranga tanarius and Cinnamomum camphora. Tree ages range between semi-mature and mature and general condition is fair to good.

Five (5) nos. of POVTs as Important Trees, T-0013 (Ficus microcarpa), T-0023 (Bombax ceiba), T-0028 (Celtis sinensis), T-0033 (Ficus elastica) and T-0042 (Ficus elastica), are also identified within this LR. No trees of rare and protected species are found during the survey.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Medium

Sensitivity - Medium

LR 3 Hillside Shrubland and Grassland (151.2ha)

LR refers to mixture of shrubland and grassland located on the hillsides to the west and south of the PDA. Dense woodland filters out to shrubland and scattered trees further up the slope with a mixture of grassland at intervals. Erosion is a result of unmanaged access and use of motorcycles has damaged large areas of the hillside, exposed soils and impacted on vegetation to a certain extent.

This LR comprises native shrub species including Baeckea frutescens, Glochidion eriocarpum, Helicteres angustifolia, Melastoma dodecandrum, Melastoma sanguineum, Rhaphiolepis indica, and Rhodomyrtus tomentosa, and native grass species such as Arundinella nepalensis, Neyraudia reynaudiana, Paspalum conjugatum, Dicranopteris pedata, Imperata cylindrica var. major, Ischaemum barbatum, Miscanthus floridulus and Miscanthus sinensis.

In addition, three (3) nos. of rare and protected species as Important Trees, R-0001(Aquilaria sinensis), R-0002 (Aquilaria sinensis) and R-0003 (Aquilaria sinensis), are located on the slopes in the south of Long Hon Road. No POVTs are found during the survey.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Medium

Sensitivity - Medium

LR 4 Secondary Woodland (87.1ha)

LR refers to dense secondary woodlands within the Assessment Area, which are found both in the PDA and outside of the PDA. These secondary woodlands are established on the continuous upland adjoining the western boundary of PDA, adjoining south of Shan Ha Tsuen, in or near Tong Yan San Tsuen, near Lam Hau Tsuen and Lam Hau Wai Tsuen, under the pylon near Yeung Ka Tsuen, and some small woodlands scattered through the village or developed areas. 

Those woodlands comprise a varing diversity of mature trees of typical native woodland species including Acronychia pedunculata, Aporusa dioica, Bischofia javanica, Breynia fruticosa, Bridelia tomentosa, Celtis sinensis, Cinnamomum burmannii, Cinnamomum camphora, Ficus variegata, Litsea glutinosa, Litsea monopetela, Microcos nervosa, Rhus chinensis, Rhus succedanea, Sapium sebiferum and Schefflera heptaphylla. Exotic plantation species such as Acacia confusa are also scattered through some of these woodland areas. Tree age ranges between semi-mature and mature and general condition is fair to good.

Thirty-seven (37) nos. of Important Trees are found within the extent of this LR. Among these trees, thirty (30) nos. of rare and protected species were recorded in the hillside woodland area in the south of Tong Yan San Tsuen, including R-0004, R-0005, R-0006, R-0007, R-0008, R-0009, R-0010, R-0011, R-0012, R-0013, R-0014, R-0015, R-0016, R-0017, R-0018, R-0019, R-0020, R-0022, R-0023, R-0024, R-0025, R-0026, R-0027, R-0028, R-0029, R-0030, R-0031, R-0032, R-0033, R-0034. These trees all belong to Artocarpus hypargyreus. Seven (7) nos. of POVTs, T-0003 (Ficus virens var. sublanceolata), T-0005 (Ficus microcarpa), T-0006 (Celtis sinensis), T-0008 (Delonix regia), T-0010 (Ficus microcarpa), T-0012 (Bombax ceiba) and T-0014 (Celtis sinensis) are also identified during the survey.

This resource is considered as ‘High’ for landscape quality. The overall sensitivity is considered to be ‘High’.

Quality and Maturity – High

Rarity – High

Ability to accommodate change – Low

Sensitivity - High

LR 5 Plantation (37.9ha)

LR refers to dense plantation on modified slopes of Tai Lam Country Park, roadside plantings along YLH and planting of nursery. The LR is a mixture of secondary and man-made plantation woodland covering substantial areas and providing important landscape amenity.

Typical species include Macaranga tanarius, Bauhinia blakeana, Acacia confusa, Dimocarpus longan, Cinnamomum camphora, Eucalyptus spp. and Magnifera indica. Tree age ranges between semi-mature and mature and general condition is fair to good.

In addition, one (1) POVT as Important Trees, T-0031 (Ficus microcarpa), is found within this LR. No trees of rare and protected species are found during the survey.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Low

Ability to accommodate change – Medium

Sensitivity - Medium

LR 6 Urban Park (9.5ha)

LR refers to Yuen Long Park, the major passive recreational park within Yuen Long New Town and public playgrounds in Tong Yan Shan Tsuen, which partly are within the Assessment Area. The Yuen Long Park consists of sports facilities, ornamental planting, lawns, pathways, sitting areas, water features, pavilions, an aviary/ viewing tower and park operation/ maintenance buildings. The elevation of the landscape is a mixture of informal and formal landscape styles with a strong presence of soft landscape. The park is surrounded by development which creates a distinct boundary or edge.

Typical species include: Melaleuca leucadendron, Acacia confuse, Bauhinia blackeana, Aleurites moluccana, Roystonea regia, Bombax ceiba, Eucalyptus citriodora and Araucaria heterophylla. The trees range from semi-mature to mature and the feneral condition is good.

Two OVTs, ARCHSD YL/1 and ARCHSD YL/2 are located in the Yuen Long Park, with species of Dracontomelon duperreanum. No POVTs, trees of rare and protected species are found during the survey.

This resource is considered as ‘High’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – High

Rarity – Medium

Ability to accommodate change –Medium

Sensitivity - Medium

LR 7 Road and Urban Infrastructure (60.6ha)

LR refers to the distributor roads and other urban infrastructures like public parking areas, associated with the road plantings of tree avenues, verges and amenity landscaped areas throughout the urbanized areas. The roadside trees can soften the hard infrastructure surface.

Typical species include Bauhinia blackeana, Macaranga tanarius, Araucaria cunninghamia, Bombax ceiba, Dimocarpus longan and Melaleuca leucadendra. Generally those trees are in fair condition.

Moreover, four (4) nos. of POVTs as Important Trees, T-0011 (Eucalyptus robusta), T-0024 (Bombax ceiba), T-0036 (Ficus elastica) and T-0037 (Ficus elastica), are identified within this LR. No trees of rare and protected species are found during the survey.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Low

Ability to accommodate change – Medium

Sensitivity - Medium

LR 8 Major Transport Corridor (29.2ha)

LR refers to the major infrastructure corridor forming the YLH, which is the premiere road within the Assessment Area.  Generally this route does not comprise any vegetation cover and are predominantly formed of engineered structures/barriers, modified slopes & embankments.

No trees of POVT, rare and protected species are found during the survey.

This resource is considered as ‘Low’ for landscape quality. The overall sensitivity is considered to be ‘Low’.

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

LR 9 Urbanised Development (163.6ha)

LR refers to the developed area dominated by low-rise rural residential developments, and parts of commercial, educational and recreational development of Yuen Long New Town within the Assessment Area.

This LR comprises low diversity of planted exotic trees such as Bombax ceiba, Bauhinia variegata and wasteland vegetation type of low floristic diversity and ecological value. Other plantation consists of a mixture of municipal roadside tree and shrub planting and amenity planting in open spaces and around residential estate. Tree age ranges between semi-mature and mature and general condition is fair to good.

Moreover, one (1) nos. of rare and protected species and two (2) nos. of POVTs, R-0035 (Artocarpus hypargyreus), T-0002 (Delonix regia) and T-0020 (Eucalyptus citriodora), are found within this LR.

This resource is considered as ‘Low’ for landscape quality. The overall sensitivity is considered to be ‘Low’.

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

LR 10 Village Type Development (219.4ha)

LR refers to the rural village areas within the Assessment Area. This LR type is mainly located east of Kiu Hing Road adjoining the eastern boundary of the PDA, and between Area 2 and Area 3 of PDA.

This LR comprises diverse plant diversity of planted fruit trees including Citrus reticulata, Clausena lansium, Dimocarpus longan, Eriobotrya japonica, Litchi chinensis and a wide range of ornamental species. Mature trees and ornamental planting appear along roadsides and within garden areas, pockets of mature woodland and horticultural plots sit intertwined within the developed areas and on the periphery of the villages.  Typical tree species include Ficus microcarpa, Bauhinia blakeana, Bombax ceiba, Acacia confusa, Callistemon viminalis, Macaranga tanarius, Cinnamomum camphora and Lagerstroemia speciosa. The age of trees range from semi-mature to mature, generally the quality of planting is fair.

In addition, two (2) nos. of POVTs and one (1) nos. of rare and protected species, T-0004 (Ficus microcarpa), T0041 (Ficus microcarpa) and R-0021 (Aquilaria sinensis), are found within this LR.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Low

Ability to accommodate change – Medium

Sensitivity - Medium

LR 11 Open Storage/Rural Built Area (245.5ha)

LR refers to the areas composed of formal and informal industrial buildings (warehouses, sheds, offices, workshops) open/ un-surfaced ground, access roads/ parking (surfaced and un-surfaced) and open storage, which surrounding Tong Ya San Tsuen, along Kung Um Road and in isolated pockets to the north of the YLH. There is only a small portion of planting located on the periphery of the plots where space is limited; planting in this location is of poor quality. This LR also includes some roadside trees together with scattered planting within the plots.

Typical tree species include Archontophoenix alexandrae, Dimocarpus longan, Eucalyptus spp., Ficus elastica, Ficus Microcarpa, Terminalia mantaly, Bauhinia blakeana, Bombax ceiba, Acacia confusa, Callistemon viminalis, Macaranga tanarius, Cinnamomum camphora and Lagerstroemia speciosa. Tree age ranges between semi-mature and mature, general condition is fair to good.

Moreover, fourteen (14) nos. of POVTs as Important Trees, T-0001 (Celtis sinensis), T-0007 (Bombax ceiba), T-0009 (Ficus microcarpa), T-0017 (Ficus microcarpa), T-0019 (Ficus microcarpa), T-0022 (Bombax ceiba), T-0027 (Celtis sinensis), T-0029 (Ficus microcarpa),  T-0032 (Ficus microcarpa), T-0034 (Ficus microcarpa), T-0035 (Ficus virens var. sublanceolata), T-0038 (Bombax ceiba), T-0039 (Melia azedarach) and T-0040 (Celtis sinensis),  are identified within this LR. No trees of rare and protected species are found during the survey.

This resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Low

Ability to accommodate change – Medium

Sensitivity - Medium

LR 12 Disturbed Area (56.5ha)

LR refers to the disturbed land and undeveloped lands within the Assessment Area, which are located in the fringes of the developed areas and scattered within the village areas. This LR is mainly derived from fallow cultivation and woodland clearance and has become overgrown with weedy vegetation after a long period of abandonment.

This resource comprising mainly pioneer herbaceous species such as Bidens alba, Cynodon dactylon, Ipomoea cairica, Mikania micrantha, Kyllinga polyphylla, and Pueraria lobata and is lack of tree stands.

In addition, one (1) nos. of POVT, T-0021 (Ficus microcarpa), is found within this LR. No trees of rare and protected species are found during the survey.

This resource is considered as ‘Low’ for landscape quality. The overall sensitivity is considered to be ‘Low’.

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

LR 13 Agricultural Pond (2.0ha)

LR refers to the scattered fish ponds within agricultural areas south of Fui Sha Wai, east of Tin Lung Yuen, south of Tai Tong Tsuen and within agricultural areas to the west of the PDA. Those ponds are man-made with soft bank edges and relatively geometric forms. They are fed by a series of irrigation channels linking to streams emanating from the local hillsides.

The two ponds located in Fui Sha Wai and Ying Lung Wai respectively, are both outside of the proposed PDA and surrounded with metal fences, common herbaceous vegetation and a few fruit trees including Morus alba and Mangifera indica were recorded along the pond bunds in Fui Sha Wai.  The Ying Lung Wai pond bund area was vegetated with ornamental species including the palm tree Archontophoenix alexandrae. In addition, there is one inactive fish pond located near Fui Sha Wai. Some fruit trees were found during the survey, including Artocarpus heterophyllus, Psidium guajava, and a few common native tree species such as Celtis sinensis, Listea glutinosa, were the most dominant species along the pond bund. Tree age ranges between semi-mature and mature and general condition is fair to good.

No trees of POVT, rare and protected species are found during the survey.

Since the varying quality of those ponds, this resource is considered as ‘Medium’ for landscape quality. The overall sensitivity is considered to be ‘Medium’.

Quality and Maturity – Medium

Rarity – Medium

Ability to accommodate change – Medium

Sensitivity - Medium

LR 14 Channelised Watercourse (19.4km)

LR refers to several large, trapezoidal and boxed concrete channels run through the Assessment Area, including the major drainage Nullah within Long Han Road, Lam Tai West Road and Kung Um Road. These are largely concrete lined with a dry weather flow channel at the base.  Part of the lower section of the main drainage channel (to the north of the As sessment Area) has been lined with grasscrete and there are areas of riparian vegetation.

Ficus hispida, Ficus microcarpa and Ficus subpisocarpa are the dominant tree species that had established along the narrow embankment of some channelized watercourses.

No trees of POVTs, rare and protected species are found during the survey.

Since those large scale trapezoidal concrete lined channels do not provide any landscape amenity, this resource is considered as ‘Low’ for landscape quality. The overall sensitivity is considered to be ‘Low’.

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

LR 15 Watercourses of higher ecological value (20.9km)

LR refers to watercourses of higher ecological value (permanent and seasonal) mainly concentrated within the natural hillsides to the west of the study area, where there has been little or no human impact to the channels or banks of these watercourses. These either enters into agricultural irrigation channels or Nullahs. Given the topography, particularly in the west, many of these watercourses are seasonal, with water restricted to pools or slow flow in the dry season.

Semi-natural shrubby grasslands are the dominant riparian vegetation of these seasonal watercourses in the upland. Most of the lowland watercourse sections are very exposed and with riparian vegetation, common native tree species such as Celtis sinensis, Ficus hispida, Macaranga tanarius var. tomentosa and Microcos nervosa were the most dominate species within this LR.

No trees of POVTs, rare and protectd species are found during the survey.

This resource is considered as ‘High’ for landscape quality. The overall sensitivity is considered to be ‘High’.

Quality and Maturity – High

Rarity – High

Ability to accommodate change – Low

Sensitivity - High

LR 16 Reservoir (1.7ha)

LR refers to the Tan Kwai Tsuen North fresh water service reservoir within the Assessment Area, which located along the western side of the site adjacent to the YLH but outside of the proposed PDA boundaries. The current status of the reservoir is labelled as abandoned. The surrounding vegetation consists of woodland and orchard planting. But there is a small portion of vegetation cover in this resource.

No trees of POVTs, rare and protectd species are found during the survey.

This resource is considered as ‘Low’ for landscape quality. The overall sensitivity is considered to be ‘Low’.

Quality and Maturity – Low

Rarity – Low

Ability to accommodate change – High

Sensitivity - Low

10.9.3.5            In summary LRs of ‘High’ sensitivity include LR1a ‘Active Agricultural Land’, LR1c ‘Orchard’, LR4 ‘Secondary Woodland’ and LR15 ‘Watercourses of higher ecological value’.  This is as a result of the natural qualities or high amenity landscape features of these LRs.

10.9.3.6            LRs of ‘Medium’ sensitivity include LR1b ‘Abandoned Agricultural Land’, LR2 ‘Lowland Mixed Trees, Shrubland and Grassland’, LR3 ‘Hillside Shrubland and Grassland’, LR5 ‘Plantation’, LR6 ‘Urban Park’, LR10 ‘Village Type Development’, LR11 ‘Open Storage/Rural Built Area’ and LR13 ‘Agricultural Pond’.  In this case these resource have undergone disturbance as a result of human activity or urban development however, they retain some natural features and landscape amenity value.

10.9.3.7            LRs considered to have a low sensitivity as a result of their heavily disturbed, low landscape amenity value or dominance of urban/ built form include LR7 ‘Road and Urban Infrastructure’, LR8 ‘Major Transport Corridor’, LR9 ‘Urbanised Development’, LR12 ‘Disturbed Area’, LR14 ‘Channelised Watercourse’ and LR16 ‘Reservoir’.

10.9.4             Identification of Existing Visual Resources

10.9.4.1            The YLS PDA is located to the south of Yuen Long Town and bounded by YLH, Kung Um Road and Tai Lam Country Park. Upon review of the existing visual condition, the PDA is largely dominated by the brownfield in Tai Tong, which include open storages, warehouses, rural workshops, industrial operations, agricultural land and unused land.

10.9.4.2            Another visually dominating resource is the Yuen Long Nullah along Kung Um Road and Kiu Hing Road. The nullah is currently channelised and lined with concrete, with narrow traffic roads on both sides and limited area for pedestrian passage.

10.9.4.3            For the low-rise residential developments within the PDA, include Pak Sha Tsuen, Tong Yan San Tsuen, Muk Kiu Tau Tsuen and Shan Ha Tsuen are located at the north of the PDA.

10.9.4.4            In addition, YLH is an elevated bypass expressway within the PDA. This present transport infrastructure will form a visual obstruction to the viewers within the PDA, which may partially block the views of the proposed developments from some VSRs.

10.9.4.5            For the natural visual resource within the PDA, the vegetated woodland hillsides are located at the foothill of Tai Lam Country Park and Ho Hok Shan. This extensive hillside forms a green and pleasant backdrop to the urban areas in Yuen Long Town, which enhances the visual experience of the public viewers.

10.9.5             Visual Envelope (VE)

10.9.5.1            The VE is generated by viewshed that confines to the south and east by the ridgeline of Tai Lam Country Park and Ho Hok Shan, to the north by the high-rise residential/ recreational buildings in Yuen Long New Town, and to the west by the village houses, public housing, plantation and viaduct of MTR West Line in HSK and Ping Shan. Within the VE the predominantly level landscape means that views from elevated positions can generally see very long distances whereas many ground level views are limited by intervening vegetation cover and built form.

10.9.6             Visually Sensitive Receivers (VSRs)

10.9.6.1            Elevated ground surrounding the study area to the south  provides the opportunity for uninterrupted long distance views over the study area from prominences in the local landscape, local landmarks such as Yuen Long Park viewing tower, existing high rise residential developments and from high points (including trails) in Tai Lam Country Park to the south.  Key visual receptors within the visual envelope include the settlements of Tong Yan San Tsuen, Lung Tin Tsuen, Tai Tong Tsuen, Shung Ching San Tsuen, Muk Kiu Tau Tsuen and residential estates on the southern fringe of Yuen Long.   In addition other key receptors include users of local pedestrian routes, transport infrastructure corridors such as the YLH, occupational receptors within local industrial estates, recreational views from tracks within Tai Lam Country Park and areas of open countryside to the south.

10.9.6.2            As part of the development works it is likely that landscape and visual impacts would arise from removal or disturbance of mature trees, vegetation and natural topography.  In addition impacts may arise from the visibility of construction operations, temporary works, changes in the existing landscape character, visibility of larger scale comprehensive development and changes in views from sensitive receivers.

10.9.6.3            The type of VSRs within the study area has been identified in Table 10.9.3, their sensitivity has assessed in Table 10.9.4. The location of viewpoints from these VSRs is presented on Figure 10.10 with representative photographic views taken from these points shown on Figure 10.11a to 10.11q.

Table 10.9.3 Identification of VSR Types

VSR Code

Visually Sensitive Receiver (VSR)

Type of VSRs

(Residential / Recreational / Occupational / Transportation/ Vehicular / Pedestrian)

VSR Category (Strategic/ District/ Local)

VSR 1

Yuen Long Park Tower

Recreational, Residential

District

VSR 2

Fui Sha Wai South Road

Transportation, Vehicular

Local

VSR 3

Tong Yan San Tsuen Track

Occupational

Local

VSR 4

Fui Sha Wai

Residential

District

VSR 5

Forefront Cyber Centre

Occupational, Transportation

District

VSR 6

Jasper Court and Long Tin Road

Residential, Pedestrian, Transportation

District

VSR 7

Park Side Villa

Residential, Occupational ,Pedestrian, Transportation

District

VSR 8

Tong Yan San Tsuen Interchange

Pedestrian, Transportation

District

VSR 9

Intersection of Kung Um Road and Shap Pat Heung Road

Residential, Pedestrian, Transportation

District

VSR 10

Intersection of Lam Hei Road and Kung Um Road

Pedestrian, Transportation

District

VSR 11

Tin Liu Tsuen

Residential, Pedestrian, Transportation

Local

VSR 12

Chun Fai Garden

Residential, Pedestrian, Transportation

Local

VSR 13

Pathway near Muk Kiu Tau Tsuen

Pedestrian, Transportation

Local

VSR 14

Kiu Hing Road near Pak Sha Tsuen

Residential, Pedestrian, Transportation

Local

VSR 15

One Hyde Park Bus Station

Residential, Pedestrian, Transportation

Local

VSR 16

Channel Pathway on Kung Um Road

Pedestrian, Transportation

Local

VSR 17

Pak Sha Tsuen Facing Southwest

Residential, Pedestrian, Transportation

Local

VSR 18

Tai Lam Mountain 1 Facing Northeast

Recreational

District

VSR 19

Tai Lam Mountain 2 Facing East 

Recreational

District

VSR 20

Tai Lam Mountain 3 Facing Southeast

Recreational

District

VSR 21

Tai Lam Mountain 4 Facing Northeast

Recreational

District

VSR 22

Tai Lam Mountain 5 Facing Northeast

Recreational

District

VSR 23

Tai Lam Mountain 6 Facing North

Recreational

District

VSR 24

Tai Lam Mountain 7 Facing Northeast

Recreational

District

VSR 25

Tai Lam Mountain 8 Facing Northeast

Recreational

District

VSR 26

Access Road off Tai Tong Shan Road

Recreational, Occupational, Transportation

Local

VSR 27

Shui Tsiu San Tsuen Road near Wong Nai Tun Tsuen

Residential, Pedestrian, Transportation

Local

VSR 28

Shui Tsui San Tsuen

Residential, Pedestrian, Transportation

Local

VSR 29

Sham Chung Tsuen

Residential, Pedestrian, Transportation

Local

VSR 30

Shan Ha Tsuen

Residential, Pedestrian, Transportation

Local

VSR 31

Ho Hok Shan 1 Facing Southwest

Recreational

District

VSR 32

Ton Yan San Tsuen

Residential, Occupational, Pedestrian, Transportation

Local

VSR 33

Tan Kwai Tsuen Road near Open Storage

Residential, Occupational, Pedestrian, Transportation

Local

VSR 34

Tan Kwai Tsuen Road near Osmanthus Arnold Garden

Residential, Occupational, Pedestrian, Transportation

Local

VSR 35

Cheung Ngau Shan Facing Northwest

Recreational

District

VSR 36

Near Yuen Long Government Primary School

Residential, Occupational, Pedestrian

Local

VSR 37

Pok Oi Hospital

Occupational, Pedestrian, Transportation

Local

VSR 38a

Yoho Town (Ground Level)

Occupational, Pedestrian, Transportation

Local

VSR 38b

Yoho Town (Upper Level)

Residential, Occupational, Pedestrian, Transportation

Local

VSR 39

Yau Tin West Road near Hoover Garden

Residential, Pedestrian, Transportation

Local

VSR 40

Intersection of Tai Tong Road

Residential, Pedestrian Transportation

Local

VSR 41

Tai Kei Leng Road

Pedestrian Transportation

Local

VSR 42

Tai Shu Ha Road East Facing Northwest

Residential, Pedestrian Transportation

Local

VSR 43

Hung Tin Road

Pedestrian Transportation

Local

VSR 44

Shap Pat Heung Road near La Grove

Pedestrian Transportation

Local

Table 10.9.4  VSRs and their sensitivity

VSR 1 Yuen Long Park Tower

VSR Type: Recreational, Residential

Number of VSRS: Many

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Long

Frequency of View: Frequent

Sensitivity: High

Description:

VSR represents recreational views from the park tower together with illustrating the typical view from residential receivers (including Long Bin Interim Housing, Park Royale, Parkside Villa, Scenic Gardens)  on the southern edge of Yuen Long looking south over the Study Area.  Give the level nature of the study area, elevated views from this point of Yuen gain a panoramic view across a significant area and the mountain backdrop.  The level landscape and low rise built form in the study area allow unobstructed views of the PDA.

VSR 2 Fui Sha Wai South Road

VSR Type: Transportation

Number of VSRS: Few

Quality of View: Poor

Availability of Alternative Views: No

Degree of Visibility: Glimpse

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Low

Description:

VSR represents vehicular views from Fui Sha Wa South Road which sits at the western point of PDA Area 1 adjacent to the YLH. Views from Fui Sha Wai South Road are limited by dense mature vegetation and existing noise barriers of YLH.

VSR 3 Tong Yan San Tsuen Track

VSR Type: Occupational

Number of VSRS: Few

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Glimpse

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents occupational views associated with the surrounding industrial area.  Medium distance views are limited by dense vegetation cover with some glimpse views available to local upland areas.  Industrial buildings, disturbed ground and poorly maintained vegetation cover lower the overall amenity of views.

VSR 4 Fui Sha Wai

VSR Type: Residential

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents residential views from Fui Sha Wau to the north of Area 1 across the YLH.  Vegetation cover in limited as a result of village house development and drainage works.  Visibility of road infrastructure and industrial development lowers the quality of the view.  Glimpse views to hillside to the south of Yuen Long are visible on the horizon.

VSR 5 Forefront Cyber Centre

VSR Type: Occupational, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents occupational and transportation views from the Forefront Cyber Centre with sits adjacent to the YLH with southerly views across the Study Area, with Area 1 in the foreground.  Views from the highway are possible as a result of the transparent noise barriers within this section.  The highway and industrial buildings are significant visual detractors in the view.  Scattered mature vegetation and views to the hillsides surrounding the Study Area provide important visual respite.  Longer distance views further to south over Area 3 are also possible.

VSR 6 Jasper Court and Long Tin Road

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Glimpse

Duration of View: short

Frequency of View: Occasional

Sensitivity: Low

Description:

VSR represents residential, pedestrian and transportation views from Jasper Court (low rise) and Long Tin Road.  Road infrastructure, including noise barriers dominates the views.  Medium to long distance views are generally restricted by intervening built form.  Local vegetation cover provides little visual amenity.

VSR 7 Park Side Villa

VSR Type: Residential, Occupational, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents residential, occupational, pedestrian and transportation views from medium-rise Parkside Villa development.  At present ground level views overlook an open storage area and YLH.  Views at higher elevation have an open and unobstructed vantage point over the study area and mountain landscape beyond.

VSR 8 Tong Yan San Tsuen Interchange

VSR Type: Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents ground level pedestrian and vehicular receivers from the TYST Interchange with the Shan Ha Road.  The roadscape, surrounding open storage and Nullah are dominant visual detractors.  Dense vegetation especially in the form of plantation associated with the YLH provides important visual respite.  The low level nature of development allows unobstructed views to the local hillside.  Ground level views over the study area are limited by mature vegetation, fencing and storage yards.

VSR 9 Intersection of Kung Um Road and Shap Pat Heung Road

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Glimpse

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents low level views from residential, pedestrian and vehicular receivers at the intersection of Kung Um Road and Shap Pat Heung Road at Lung Tin Tsuen.  Views are heavily dominated by the immediate roadscape and Nullah which heavily detract from the quality of the view.  Longer distance views along the road corridor are partially obscured by the YLH.  Some mature vegetation appears in between developed areas and open storage compounds.

VSR 10 Intersection of Lam Hei Rd and Kung Um Rd

VSR Type: Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents view further along the Kung Um Road as this passes beneath the YLH.  The raised structure of the YLH and surrounding plantation obstructs medium distance views.  The surrounding roadscape and Nullah dominate the foreground of the view.

VSR 11 Tin Liu Tsuen

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Glimpse

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents residential, pedestrian and vehicular receivers at Tin Liu Tsuen with westerly views over the Study Area and Area 2. At ground level the view is generally contained by local 3 storey village house development and vegetation cover.  Glimpse longer distance views are possible in between buildings.  The lack of vegetation cover, dominance of the road, open Nullah and low visual amenity of built form detract from the quality of the view.

VSR 12 Chun Fai Garden

VSR Type: Residential, Pedestrian, Vehicular

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: No

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents residential, pedestrian and vehicular views at Chun Fai Garden on Kiu Hing Road with westerly views over the Study Area and Area 2.  The roadscape, Nullah and open storage detract from the quality of the view.  The development pattern is more open at this point allowing greater visual connection with the hillsides to the west of the study area.  Ground level views towards the study area are obscured by vegetation cover.

VSR 13 Pathway near Muk Kiu Tau Tsuen

VSR Type: Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR 13 represents pedestrian and vehicular views at ground level at Muk Kiu Tau Tsuen towards Area 2.  At points along Kiu Hing Road small pedestrian foot bridges cross the wide Nullah.  The straight Nullah system and adjacent roads create a wide visual corridor to the south.  The lack of vegetation, uniform concrete surfaces and associated engineering create a very low quality visual setting.  The views of the hillsides within the country park to the south provide some visual respite.

VSR 14 Kiu Hing Road near Pak Sha Tsuen

VSR Type: Residential, Pedestrian Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents residential, pedestrian and vehicular views at Kiu Hing Road near Pak Sha Tsuen.  The presence of quality residential development including ornamental planting in the foreground of the view rather than open storage or low quality built form helps to improve the visual appearance of development in the foreground.  The existing road and Nullah system still detract heavily from the quality of the view.  Ground level views toward the study area are obstructed by intervening built form and vegetation cover.  Longer distance views towards local hillside beyond the study area are readily available.

VSR 15 One Hyde Park Bus Station

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR represents residential, pedestrian and vehicular views near the One Hyde Park Bus Station with views to the west and south west over the study area.  The presence of residential development including some ornamental planting in the foreground of the view rather than open storage or low quality built form helps to improve the visual quality.  In this location the density of new housing layout tends to form a low level wall of development alongside the road.  The existing road and Nullah system still detract heavily from the quality of the view.  Ground level views toward the study area are obstructed by intervening built form and vegetation cover.  Longer distance views towards local hillside beyond the study area are readily available.

VSR 16 Channel Pathway on Kung Um Road

VSR Type: Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents pedestrian and transportation receivers with northerly views along the Kiu Hing Road/ Kung Um Road over the Study Area and Area 3 from the vicinity of Pak Sha Tsuen.  The view demonstrates the openness of the view along the Nullah with the southern extent of Yuen Long visible in the distance.  The roadscape and Nullah are significant visual detractors in the view.  Pockets of mature planting along the roads provide some visual respite.  Ground level views towards the study area of blocked by intervening built form.

VSR 17 Pak Sha Tsuen Facing Southwest

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents residential, pedestrian and transportation views at ground level in the vicinity of Pak Sha Tsuen with south westerly over the Study Area and Area 3 at the convergence point of two major Nullah channels.  The open Nullah and adjacent roads allow view corridors through the local landscape at ground level towards the hillside landscape in the south.  Open storage functions in the foreground detract from the quality of the view.  Ground level views into the study area are blocked by intervening built form whereas long distance views of the hillsides beyond the Study Area are readily available.

 

VSR 18 Tai Lam Mountain 1 Facing Northeast

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape.  VSR provides an overview of Area 1 & 2 and vicinity of Tong Yan San Tsuen.  View illustrates a series of development patterns including the high density Yuen Long New Town, rural settlements, industrial areas, agricultural land and villages.  Woodland pockets throughout the landscape help to break up the visibility of uniform low scale development.   The elevation allows very long distance views to mountains in the background.  The existing development within the study appears fragmented with open storage and surface car parking areas detracting from the quality of the view.  The agricultural area south of TYST is a distinctive component of the view, which is the new location for the fresh water service reservoir as well.

VSR 19 Tai Lam Mountain 2 Facing East

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape.  VSR provides an overview of part of Area 1 and Area 2 & 3 along Kung Um Road.  Open storage functions at the foot of the hillside create an almost uniform carpet of development broken only by small and isolated tree pockets.  The view demonstrates the full extent of low scale sprawl which has taken place on the low level plains.  The high density built form of Yuen Long New Town forms a distinctive wall of development across the low scale development elsewhere in the landscape.  Mountain peaks and ridgelines are often visible in the background.

VSR 20 Tai Lam Mountain 3 Facing Southeast

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape.  VSR provides an overview of Area 2 & 3 along Kung Um Road.  Open storage functions at the foot of the hillside create an almost uniform carpet of development broken only by small and isolated tree pockets.  The view demonstrates the full extent of low scale sprawl which has taken place on the low level plains.  The high density built form of Yuen Long New Town forms a distinctive wall of development across the low scale development elsewhere in the landscape. Mountain peaks and ridgelines are often visible in the background.

VSR 21 Tai Lam Mountain 4 Facing Northeast

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape including the Country Park.  VSR provides an overview of Area 3 along Kung Um Road.  Open storage functions at the foot of the hillside create an almost uniform carpet of development broken only by small and isolated tree pockets.  The view demonstrates the full extent of low scale sprawl which has taken place on the low level plains.   Electricity pylons entre the hillside at this point and detract from the quality of the natural landscape.  Hillside erosion is more visible to the south of the study area. 

VSR 22 Tai Lam Mountain 5 Facing Northeast

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape.  VSR provides an overview of Area 1, 2 & 3.  The linear Nullah along Kung Um Road creates a highly visible open corridor through the landscape.  Open storage functions at the foot of the hillside create an almost uniform carpet of development broken only by small and isolated tree pockets.  The view demonstrates the full extent of low scale sprawl which has taken place on the low level plains.  Hillside erosion is more visible in the foreground of the view.  Electricity pylons also enter the hillside at the point.  The high density built form of Yuen Long New Town forms a distinctive wall of development across the low scale development elsewhere in the landscape.  Mountain peaks and ridgelines are omnipresent in the background.

VSR 23 Tai Lam Mountain 6 Facing North

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape.  VSR provides an overview of Area 1, 2 & 3.  The linear Nullah along Kung Um Road creates a highly visible open corridor through the landscape.  Open storage functions at the foot of the hillside create an almost uniform carpet of development broken only by small and isolated tree pockets.  The view demonstrates the full extent of low scale sprawl which has taken place on the low level plains.  Hillside erosion is more visible in the foreground of the view.  Electricity pylons also enter the hillside at the point.  The high density built form of Yuen Long New Town forms a distinctive wall of development across the low scale development elsewhere in the landscape.  Mountain peaks and ridgelines are often visible in the background.

VSR 24 Tai Lam Mountain 7 Facing Northeast

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR describes recreation views from surrounding mountainsides which form a horseshoe around the local landscape.  VSR provides an overview of Area 1, 2 & 3.  The linear Nullah along Kung Um Road creates a highly visible open corridor through the landscape.  Open storage functions at the foot of the hillside create an almost uniform carpet of development broken only by small and isolated tree pockets.  The view demonstrates the full extent of low scale sprawl which has taken place on the low level plains.  Hillside erosion is more visible in the foreground together with burial grounds.  Electricity pylons also enter the hillside at the point.  The high density built form of Yuen Long New Town forms a distinctive wall of development across the low scale development elsewhere in the landscape. Mountain peaks and ridgelines are often visible in the background.

VSR 25 Tai Lam Mountain 8 Facing Northeast

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

 

Description:

VSR describes recreational views from surrounding mountainsides which form a horseshoe around the local landscape. VSR provide an overview of Area 1. The view demonstrates the North of Area 1 and the new fresh water service reservoir, which is locate at the south of Tong Yan San Tsuen. The existing development within the study appears fragmented with open storage and surface car parking areas detracting from the quality of the view.

 

VSR 26 Access Road off Tai Tong Shan Road

VSR Type: Recreation, Occupational, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Medium

Frequency of View: Frequent

Sensitivity: Low

Description:

VSR represents recreation, occupational, transportation receivers from the south east of the Study Area off Tai Tong Shan Road.  Open storage function and road construction have heavily degraded the local landscape removing natural vegetation and altering natural terrain.  Glimpse views towards the Study Area towards Area 3 above the tree canopy and compound areas are possible.  The hillsides to the west of the study area have a strong visual presence on the skyline.

VSR 27 Shui Tsiu San Tsuen Road near Wong Nai Tun Tsuen

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Medium

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents typical views experienced at Shui Tsiu San Tsuen Road near Wang Nai Tun Tsuen, with westerly views over the Study Area, Area 2 and Area 3.  Views generally comprise village house development and development plots in the foreground and middle ground.  Vegetation cover is relatively sparse with individual mature trees are scattered throughout the village.  Ground level views towards the study area are limited by intervening built form and tree cover beyond the village.  The hillsides to the west of the study area are highly visible.

 

VSR 28 Shui Tsiu San Tsuen

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Medium

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents typical views experienced by residential, pedestrian and transportation receivers at Shui Tsiu San Tsuen with westerly views over the Study Area, Area 2 and 3.  The intervening landscape between the village and study area is less developed with lower scale built forms which blends into the vegetation cover.  Ground level views towards the study area are limited with views to the hillsides to the west of the study area being highly visible.

VSR 29 Sham Chung Tsuen

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Medium

Frequency of View: Frequent

Sensitivity: High

Description:

VSR represents typical views experienced by residential, pedestrian and transportation receivers at Sham Chung Tsuen with westerly views over the Study Area and Area 2.  Well-tended agricultural plots give the local landscape a higher amenity appearance.  Pockets of woodland planting are visible together with clusters of village houses.  Medium rise development on the southern edge of Yuen Long New Town is also visible.  Ground level views towards the study area are limited with views to the hillsides to the west of the study area being readily available.

VSR 30 Shan Ha Tsuen

VSR Type: Residential, Pedestrian, Transporation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Medium

Frequency of View: Frequent

Sensitivity: Medium

Description:

VSR represents typical views experienced by residential, pedestrian and transportation receivers at Sha Ha Tsuen with westerly views over the Study Area and Area 1.  The view comprises a mixture of village houses of varying ages. Pockets of woodland planting are visible together with dense clusters of village houses.  Ground level views towards the study area are limited with views to the hillsides to the west of the study area being highly visible above the existing development.

VSR 31 Ho Hok Shan and Facing Southwest

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Medium

Description:

VSR represents recreational views from the hillside at Ho Hok Shan located to the west of Yuen Long New Town.  The elevation at this point allows a long distance view towards the Study Area including Area 1, 2 and 3.  The landscape in the foreground appears relatively undeveloped.  The medium rise development on the southern edge of Yuen Long New Town is very conspicuous where this meets the small scale development to the south of the YLH.  Views to the hillside west of the Study Area form the back drop and contain the view.

VSR 32 Tong Yan San Tsuen

VSR Type: Residential, Occupational, Pedestrian, Transportation.

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

VSR represents the typical view experienced by residential, occupational, pedestrian and transportation receivers within the environs of TYST within Area 1.  Modern village house developments and more formalised streetscape create a slightly higher level of visual amenity although lack substantial vegetation cover.  Medium distance views are restricted by intervening built form and vegetation cover.  Glimpse views to the hillsides west of the study area are possible.

VSR 33 Tan Kwai Tsuen Road near Open Storage

VSR Type: Residential, Occupational, Pedestrian, Transportation

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Medium

Frequency of View: Frequent

Sensitivity: Low

 

Description:

VSR represents residential, occupational, pedestrian and transportation receivers at Tan Kwai Tsuen to the west of the Study Area and Area 1.  Locally the landscape comprises a mixture of development including village houses, open storage/compounds, workshop and public open space.  Ornamental and mature tree planting helps to provide visual amenity by breaking up the appearance of low quality development such as metal sheds.  Views towards the study area are limited at ground level by intervening development and vegetation cover.  Views towards the hillsides adjacent to the study area are possible.

 

VSR 34 Tan Kwai Tsuen Road near Osmanthus Arnold Garden

VSR Type: Residential, Occupational, Pedestrian, Transportation

Number of VSRS: Medium

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: High

 

Description:

VSR represents residential, occupational, pedestrian and transportation receivers at Tan Kwai Tsuen Road to the Tai Lam Mountain. It is situated on the shared road of vehicle and pedestrian walkway, and it is surrounded by the residential villa house, pockets of mature planting with vegetated hillsides is visible at the foreground of the view, which has provide some visual respite.

 

VSR 35 Cheung Ngau Shan Facing Northwest

VSR Type: Recreational

Number of VSRS: Few

Quality of View: Good

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: -Short

Frequency of View: Occasional

Sensitivity: Medium

 

Description:

VSR represents recreational views from the hillside at Cheung Ngau Shan located to the west of Yuen Long New Town. It is a long distance panoramic view on the top of the mountain of Cheung Ngau Shan facing to the Northwest of Development Area 2 and Yuen Long Town Centre. Electricity Pylons is visible at the foreground of the view. Views of YLH are obstructed by intervening built form and vegetation cover. Due to the low usage of hiking trial, the sensitivity of the receiver is considered as ‘’medium’’.

 

VSR 36 Near Yuen Long Government Primary School

VSR Type: Residential, Occupational, Pedestrian

Number of VSRS: Medium

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

 

Description:

VSR represents residential, occupational, pedestrian receivers at Yau Chuen Street to the north of Yuen Long New Town and PDA Area 2. The existing view towards north is characterized by low rise village buildings and scattered vegetation in a close view. The high rise buildings of Yuen Long New Town contain the view in a middle distance. View towards the study area are limited due to the far distance and blocked by intervening built form.

VSR 37 Pok Oi Hospital

VSR Type: Occupational, Pedestrian, Transportation

Number of VSRS: Medium

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

 

Description:

VSR represents occupational and transportation views from the Pok Oi Hospital which sits adjacent to the Castle Peak Road with southerly view across the high rise buildings of Yuen Long New Town. Views from the highway are possible as a result of scattered mature vegetation and Pok Oi Hospital buildings. Longer distance views further to south over Area 2 are also possible.

VSR 38a Yoho Town (Ground Level)

VSR Type: Occupational, Pedestrian, Transportation

Number of VSRS: Medium

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Low

 

Description:

For 38a, VSR represents views from pedestrian, occupational and transportation users along the Yuen Ching Road near Yoho Town. At present ground level views overlook an open storage area and Kwong Ming Ying Loi School. Short distances views to Major Road infrastructures on Yuen Ching Road are possible. Due to the short duration of views, the sensitivity of the receiver is considered as “Low”.

VSR 38b Yoho Town (Upper Level)

VSR Type: Residential

Number of VSRS: Many

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Long

Frequency of View: Frequent

Sensitivity: High

 

Description:

For 38b, VSR represents residential views at higher elevation which have an open and unobstructed views over the Castle Peak Road, YLH and mountain landscape beyond. Short distances views to Major Road infrastructures on Yuen Ching Road are possible. Due to the long duration of view for residential users, the sensitivity of the receiver is considered as “High”.

 

VSR 39 Yau Tin West Road near Hoover Garden

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Medium

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Long

Frequency of View: Frequent

Sensitivity: Medium

 

Description:

VSR represents residential, pedestrian and vehicular views from Hoover Garden. At points along Yau Tain West Road pedestrian foot bridges cross the wide Nullah. The lack of vegetation, uniform concrete surfaces and associated engineering create a very low quality visual setting. Longer distance views towards local hillside beyond the study area provide some visual respite.

VSR 40 Intersection of Tai Tong Road

VSR Type: Occupational, Pedestrian, Transportation

Number of VSRS: Many

Quality of View:  Fair

Availability of Alternative Views:  Yes

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Low

 

Description:

VSR represents occupational, pedestrian and transportation views at ground level at Tai Tong Road. The straight Nullah system and adjacent roads create a wide visual corridor to the south. The raised structure of the YLH and surrounding plantation obstructs medium distance views. Partial views to hillside to the south of Yuen Long are visible on the horizon.

 

VSR 41 Tai Kei Leng Road

VSR Type: Pedestrian, Transportation

Number of VSRS: Few

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Glimpse

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Low

 

Description:

VSR represent transportation and pedestrian views from Tai Kei Leng Road. Views from south east at Tai Kei Leng Road are limited by dense mature vegetation and existing noise barriers of YLH.

 

VSR 42 Tai Shu Ha Road East Facing Northwest

VSR Type: Residential, Pedestrian, Transportation

Number of VSRS: Medium

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Partial

Duration of View: Short

Frequency of View: Frequent

Sensitivity: Medium

 

Description:

VSR represent view further along Tai Shu Ha Road East as this passes beneath the YLH. The raised structure of the YLH and surrounding plantation obstructs medium distance views. The surrounding roadscape and Nullah dominate the foreground of the view and some residential villa houses are involved on the west.

VSR 43 Hung Tin Road

VSR Type: Pedestrian, Transportation

Number of VSRS: Few

Quality of View: Poor

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Low

 

Description:

VSR represent transportation and pedestrian views from Hung Tin Road. Short distances views to Utilities Construction on Hung Tin Road are possible. Due to the short duration of views, the sensitivity of the receiver is considered as “Low”.

VSR 44 Shap Pat Heung Road near La Grove

VSR Type: Pedestrian, Transportation

Number of VSRS: Few

Quality of View: Fair

Availability of Alternative Views: Yes

Degree of Visibility: Full

Duration of View: Short

Frequency of View: Occasional

Sensitivity: Low

 

Description:

VSR represents pedestrian and vehicular users along Shap Pat Heung Road near La Grove. A close distance views to the proposed noise enclosure in Kung Um Road and Kiu Hing Road are possible. Due to the short duration of views, the sensitivity of the receiver is considered as “Low”.

 

10.10              Landscape and Visual Impact Assessment before Mitigation Measures

10.10.1        Aims of Review

10.10.1.1        A review of the existing and planned development framework for the proposed development and context has been conducted to:

·                  Assist with identification of existing landscape resources and potentially sensitive receivers;

·                  Highlight potential issues for neighbouring planned land uses;

·                  Optimise the compatibility of the development with the surrounding land uses.

10.10.2        Sources of Landscape and Visual Impacts

10.10.2.1        The landscape impact assessment has been carried out taking into consideration the baseline LRs and LCAs described in Section 10.9 and potential impacts described in Section 10.7.5.

10.10.2.2        During the construction stage, potential landscape and visual impacts will generally result from the following:

·                  Site clearance including demolition of structures, tree removal/ transplantation and other vegetation removal would have a negative landscape and visual impact due to the appearance of construction activities and loss of vegetation cover.  Demolition of unsightly or temporary structures may generate positive impacts.

·                  Site formation works including cutting of slopes and filling of land e.g. filling of farmland, streams would generate negative impacts as a result of the loss of these features of high landscape value.

·                  Stockpiling of construction and demolition materials, including existing topsoil, storage of construction equipment and mechanical plant would generate negative visual impact as a result of these operations intruding into existing views.

·                  Construction of at-grade and above ground facilities including, bridges, viaducts, interchanges, roads and noise barriers are likely to generate negative visual impacts as a result of these operations intruding into existing views and the scale of the construction footprint.

·                  Construction of the sewage alignment connecting YLS to the existing inert chamber of the NWNT effluent tunnel at San Tai for discharging to Urmston Road submarine outfall may generate negative intruding into existing views.

·                  Temporary structures within the Project Site including site offices, boundary fencing/ hoarding and parking areas would generate negative visual impact due to generally low aesthetical value of these types of structures.

·                  Re-alignment of roads would generate negative landscape and visual impacts due to the visibility of construction operations and the scale of the construction footprint.

·                  Re-alignment, culverting and filling of streams and other watercourses would generate negative impacts due to the loss of visual amenity and natural value provided by these resources.

10.10.2.3        During the operation phase, potential impacts will result from the following:

·                  Construction of building structures would generate negative visual impacts due to the erection of new developments would be the visual intrusion to the existing view.

·                  Operation of new roads including intersections and viaducts would generate negative visual impacts due to the potential obstruction of existing views, visibility of new structures, and traffic movements. 

·                  Provisions of noise mitigation structures are likely to generate some negative visual impacts due to the appearance of new built form and potential to obstruct existing views.  This may be balanced where these barriers may provide screening from visual detractors.

·                  Residual impacts from loss of trees and vegetation during the construction phase would generate negative landscape and visual impacts in the short term until compensation planting has established and replaced these resources.

·                  Landscaping maintenance operations.

10.10.2.4        For the mitigation of the noise impact, due to site constraints at the concerned nullah (the roads locate right adjacent to the nullah) and the objective to achieve full noise compliance for all existing and planned NSRs according to EIAO-TM, it is inevitably to propose nullah feature/ barrier (3m to 5m high) to alleviate the road traffic noise impact. Please refer to Appendix 10.4 for the locations of noise mitigation measures.

10.10.2.5        Therefore, it is anticipated that the proposed temporary noise barrier is likely to generate visual blockage and visual intrusion to the surrounding sensitive receivers.

10.10.2.6        The visual impact of these temporary or movable noise barriers and noise enclosure proposed along the new road sections need to be mitigated through appropriate detailed design, including suitable transparent material, appropriate colour selection of panels and supporting structures, or provision of planting of trees, shrubs and/ or climbers camouflage to the barriers, as well as incorporate resistance to the effects of ultra-violet light on the plastic panels.

10.10.3        Prediction of Potential Impacts throughout the Development Stages

10.10.3.1        Refer to Section 2.5 and Figure 2.1 for Chapter 2, the overall Project is proposed to be implemented into four main stages to ensure a balanced and programmed development. The construction period of these stages are overlapped according to the implementation program. A review of main developments from each stage has been carried out to predict the potential impacts on existing landscape in YLS as follows:

Stage One (2020 – 2029)

10.10.3.2        The infrastructure works are the major development of this stage, including new road connection and road improvement works along the YLH and Kiu Hing Road. It is anticipated that these constructions of road works may cause disturbance on the roadside plantation and man-made channels. In addition, the proposed service reservoir has fallen into the woodland & plantation area on the hillside next to TYST. The initial residential developments are located in open storage sites across Lam Tai East Road. According to the proposed building footprint, estimated some of the existing trees within open storage are in direct conflict with the development.

10.10.3.3        The landscape character of the proposed residential site may change from rural industrial landscape into an urbanised setting. The character changes by other developments are temporary and reversible.

Stage Two (2022 – 2033)

10.10.3.4        Industrial settings as one of the major development are located near Tin Shui Wai West Interchange (TSW West Interchange), roadside plantation and a small plot of woodland in TYST are in direct conflict with the proposed building footprint. Another major development is the residential development within the open storage sites of Tai Fat Tsuen, which would lead to potential impacts on existing tree plots. In addition, educational facilities are proposed next to Muk Kiu Tau Tsuen may also affect the scattered plantings. Furthermore, infrastructure works including new slip road across Sha Ha Tsuen may have disturbance on agricultural land. The nullah revitalisation along Kung Um Road are proposed to enhance the landscape amenity of the man-made channels. Additional sewage treatment works in the south edge of Kung Um Road may generate direct impacts on existing trees in the rural built area.

10.10.3.5        The landscape character for residential and educational development sites next to Muk Kiu Tau Tsuen will be changed from the rural industrial setting into urbanised landscape. The existing industrial settings near TSW West Interchange are considered to experience reversible changes of landscape character.

Stage Three (2031 – 2038)

10.10.3.6        The development of this stage includes comprehensive development of residential, government buildings, open space and associated facilities. Potential impacts would be generated on the existing trees plots within open storage sites in the south-western of Kung Um Road.

10.10.3.7        After the above works, an urbanised landscape character would completely replace the existing industrial development.

Stage Four (2032-2038)

10.10.3.8        The major development of this final stage includes the residential buildings in TYST. Small scattered plots of woods, agricultural land, plantation and open storage sites would experience adverse impacts by the construction works. In addition, road improvement works for TSW West Interchange are needed, which may lead to the disturbance on the roadside plantation.

10.10.3.9        The landscape character in TYST is considered to be changed into urbanised character after the completion of these developments.

10.10.3.10    The detailed landscape impact assessment on each LRs and LCAs during construction and operation by the Project have been carried out in the following sections. The overall impacts on existing trees will be reviewed and discussed under the Tree Impact Assessment in Section 10.10.5.

10.10.4        Magnitude of Change of LCAs and LRs

10.10.4.1        Further details of the potential landscape impacts are provided for each below.  The magnitude of change on LRs and LCAs are presented in Tables 10.10.1 and 10.10.2 below.

10.10.4.2        Landscape Impacts on LCAs and LRs are mapped on Figure 10.8 and 10.9.

 


Table 10.10.1  Magnitude of Change on LCAs

LCA  Code

Name

 Land Use Type* Impacting LCA

Approx. Area of LCA within RODP

Physical extent of the impact  (Small/ Medium/ Large) ^

Compatibility with Surrounding Landscape
(Good/
Fair/ Poor)

Duration of Impact
(Temporary, Permanent)

Reversibility of Change
(Reversible/ Irreversible)

Magnitude of Change
(Large/ Intermediate/
Small/ Negligible)

CON

OP

CON

OP

CON

OP

CON

OP

LCA1a

Miscellaneous Rural Fringe Landscape – Open Storage/ Rural Built Area

(706.1 ha)

All Land Use Types

234.3 ha

 

Large

(33.2 %)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Large

Large

Description of Key Impacts during Construction and Operation

n   A large area (approx. 234.3ha) of this character area falls within the RODP scheme of overall developments throughout the four implementation stages, which is proposed with various land use such as agriculture, commercial, residential and open space, retrofitting the whole area with a miscellaneous urban landscape character.

n   During construction, site clearance works will require the demolition of buildings, structures, clearance of vegetation (including trees), breaking out hard surfaces, soil stripping and construction of new developments. These construction works would directly lead to changes of landscape quality on a large scale of character area within this LCA (33.2%). The compatibility during construction stage is considered to be poor.

n   In operation, the affected character area will be replaced with a newly urban layout together with a comprehensive road network, which represents a different type of landscape character, therefore the compatibility is considered to be poor during operational stage.

n   As a result of the large scale of construction footprint on this LCA, the magnitude of change is considered to be Large in both construction and operational stage.

 

LCA1b

Miscellaneous Rural Fringe Landscape – Lowland Agricultural Land

(92.7 ha)

AGR/OU (MU)/DO/G/GB/E/A/RSc/R1(SSF)/R2c

18.8 ha

(approx. 10ha preserved within AGR)

 

Medium

(9.5 %)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Key Impacts during Construction and Operation

n   Approximately 18.8ha of this character area falls within the RODP scheme of overall developments throughout the four implementation stages, which is proposed with various land use such as agriculture, commercial, residential and open space. However, one portion (approx. 10ha) of this character will be reserved as the future agricultural uses, which retain the rural character of this LCA.

n   During construction, site clearance works will require the clearance of vegetation (including trees), breaking out hard surfaces, soil stripping and construction of new developments. These construction works would directly lead to changes of landscape quality on a medium scale of character area within this LCA (9.5%). The compatibility during construction stage is considered to be poor.

n   In operation, the affected character area will be replaced with a newly urban layout, which represents a different type of landscape character, therefore the compatibility is considered to be poor during operational stage.

n   Given the above, the magnitude of change is considered to be Intermediate in both construction and operational stage.

LCA 2

Miscellaneous Urban Fringe Landscape

(218.4 ha)

Proposed Infrastructure (Road Improvement works)

2.8 ha

 

Small

(1.2 %)

Poor

Fair

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   A small area of this character (approx. 2.8ha) falls within the works area of proposed infrastructures development (road improvement works) in Stage One.

n   During construction, site formation and clearance will require the demolition of existing structures, clearance of vegetation (including trees), breaking out hard surfaces, soil stripping and earthworks. These construction works would lead to landscape changes on a small scale of the character area (1.2%).  The compatibility during construction stage is considered to be poor.

n   In operation, the affected character area will be replaced with the proposed road infrastructures and a public transport interchange, which are considered to be fair compatibility with the existing landscape character in place.

n   Due to the small proportion of the LCA within the 500m assessment area affected, the magnitude of change is considered to be Small.

LCA 3

Upland and Hillside Landscape

(188.1 ha)

OU(Service Reservoir)

3.8 ha

 

Small

(2.0%)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   A small area of this character area (approx. 3.8ha) will be in direct conflict with the footprint of the proposed development of service reservoir in Stage One.

n   During Construction, site clearance works would lead to a loss of small area of vegetation cover (2.0%) at the periphery of Area 1 west and alter the landscape quality of this LCA. The compatibility during construction stage is considered to be poor. 

n   In operation, these areas will be replaced with land use designated as open storage (OS) that is incompatible with the wider LCA, therefore the compatibility is considered to be poor in construction and operation.

n   As a result of the relatively small scale of the works within the wider LCA, the magnitude of change is considered to be Small during construction and operation.

LCA 4

Settled Valley Landscape

(11.6 ha)

N/A

0 ha

 

Nil

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Description of Key Impacts during Construction and Operation

n   This LCA falls outside the RODP and therefore the Project will have no impact on it.

LCA 5

Park Urban Landscape

(10.4 ha)

N/A

0 ha

 

Nil

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Description of Key Impacts during Construction and Operation

n   This LCA falls outside the RODP and therefore the Project will have no impact on it.

LCA 6

“Hui” Urban Landscape

(34.96 ha)

N/A

0 ha

 

Nil

Fair

Fair

N/A

N/A

N/A

N/A

N/A

N/A

Description of Key Impacts during Construction and Operation

n   This LCA falls outside the RODP and therefore the Project will have no impact on it.

 

LCA 7

Urban Peripheral Village Landscape

(224.4 ha)

OU(OS)/A/AGR/R5/R5(EDA)/R6/LO/DO

10.2ha

 

Small

(4.5 %)

Poor

Fair

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   A small area (approx. 10.2ha) of this character falls within the RODP scheme of major developments in Stage One, Two and Three , some of which is proposed with new land use such as agriculture, open space, residential and open storage.

n   During construction, site formation and new development will require the clearance of vegetation cover, soil stripping, demolition of buildings and structures, soil stripping and earthworks. These construction works would directly lead to changes of landscape quality on a small scale of character area within this LCA (4.5%). The compatibility during construction stage is considered to be poor. 

n   In operation, these areas will be replaced with new urban development that is fair compatible with the existing landscape character.

n   As a result of the relatively small scale of the works area within this LCA, the magnitude of change is considered to be Small during construction and operation.

LCA 8

Transportation Corridor Landscape

(55.1 ha)

Proposed Infrastructure (Road Improvement works)

13.05ha

 

Large

(24 %)

Fair

Good

Temporary

Permanent

Reversible

Reversible

Large

Small

Description of Key Impacts during Construction and Operation

n   A large area of this character (approx. 13.05ha) will be encroached by the works area of road improvement along YLH in Stage One.

n   During construction, the construction works will result in temporary impacts through the demolition of existing highway structures and clearance of some vegetation cover. Temporary traffic diversion will possibly be needed in the construction phase.

n   In operation, taking into account the majority of works sit within the existing LCA and the reversible impact, as the land use remain the same (road) before and after the development, it is considered that the compatibility will be good during operation.

n   Due to the large proportion of the LCA within the 500m assessment area affected, the magnitude of change is regarded to be Large during construction. As the new road will form part of this LCA in the future, the magnitude of change is considered to be Small during operation.

  Note: [^] Large physical extent of impact - >20% of total LR/ LCA area within 500m assessment area

                Medium physical extent of impact - 5 to 20 % of total LR/ LCA area within 500m assessment area

                Small physical extent of impact - <5 % of total LR/ LCA area within 500m assessment area

            [*] Land Use Types of RODP. Refer to Figure 10.2.


 

Table 10.10.2  Magnitude of Change on LRs

LR Code

Name

 Land Use Type* Impacting LR

Approx. Area of LR within RODP

Physical extent of the impact  (Small/ Medium/ Large)*

Compatibility with Surrounding Landscape
(Good/
Fair/ Poor)

Duration of Impact
(Temporary, Permanent)

Reversibility of Change
(Reversible/ Irreversible)

Magnitude of Change
(Large/ Intermediate/
Small/ Negligible)

CON

OP

CON

OP

CON

OP

CON

OP

LR1a

Active Agricultural Land

(65.6 ha)

AGR/OU (MU)/DO/G/GB/E/A/RSc/R1(SSF)/R2c

15.0ha

(approx.

9 ha preserved within AGR)

Medium

(9.1%)

Fair

Fair

Permanent

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Key Impacts during Construction and Operation

n   Approximately 15.0ha of this LR falls within the PDA boundaries. The large scale of active agricultural land near the Shan Ha Tsuen will be reserved for most areas (approx. 9ha) as the future agricultural uses. The potential impacts are generated from the new slip road works across Shan Ha Tsuen in Stage Two and residential development at TYST in Stage Four.

n   During construction, site formation will involve vegetation clearance, soil stripping and earthworks, and which leading to a permanent loss of approx. 6 ha (9.1%) of this resource within the RODP scheme. A total of approx. 139 nos, of trees including one potentially affected POVT (T-0026) within this LR are anticipated to be impacted.

n   In operation, these affected areas will be replaced with district open spaces, government uses and other mixed land use together with proposed road network in the west of Long Hon Road. Small scale of the agricultural plots next to Shan Ha Tsuen will be retained in existing development area as shown in the RODP. Three scattered plots in Area 2 will be reserved for residential and educational use that are incompatible with the existing landscape.

n   Apart from sites reserved for future agriculture use, a medium scale of this LR will be affected during construction and operation. Overall, the magnitude of change is considered as ‘Intermediate’ at both construction and operation.

LR1b

Abandoned Agricultural Land

(3.54 ha)

AGR

1.1ha

(approx. 1.0ha preserved within AGR)

 

Small

(3%)

Fair

Fair

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   Approximately 1.1ha of this LR falls within the PDA boundaries. Most areas of this LR (approx. 1.0ha) will be reserved as the future agricultural uses inside the large scale agricultural land near Shan Ha Tsuen. It is anticipated that the adverse impacts are mainly from the new slip road works across Shan Ha Tsuen in Stage Two and residential development at TYST in Stage Four.

n   During Construction, site formation will involve vegetation clearance, soil stripping and earthworks for road construction, and which leading to a permanent loss of a small scale of area (approx. 0.1 ha, 3%) within the RODP scheme. A total of approx. 5 nos. of trees within this LR are anticipated to be impacted.

n   In operation, the existing vegetation will be replaced with the new roads of the RODP scheme.

n   Apart from the areas reserved for future agriculture use, a small scale of this LR will be affected during construction and operation. Overall, the magnitude of change is considered as ‘Small’ at both construction and operation.

LR1c

Orchard

(20.8 ha)

OU(SU)2/A/R5

2.7 ha

 

Medium

(13.0%)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Key Impacts during Construction and Operation

n   Approximately 2.7ha of this LR falls within PDA boundaries, which are in direct conflict with the footprint of sites designated for storage uses, amenity uses, residential use at TYST in Stage Four and proposed road network near the Tin Shui Wai West Interchange in Stage Two.

n   During construction, site formation including vegetation clearance, soil stripping and earthworks will lead to a permanent loss of a medium scale area (13.0%) of this LR. A total of approx. 568 nos. of trees within this LR are estimated to be impacted.

n   In operation,  the affected areas of this LR will be totally replaced with a series of amenity landscape, infrastructures and buildings of the RODP scheme.

n   As a result of the relatively medium scale of this LR that will be affected, the magnitude of change is considered to be ‘Intermediate’ during construction and operation. 

 

LR2

Lowland Mixed Trees, Shrubland and Grassland

(42.9 ha)

LO/DO/OU(SU)2/OU(OS)/GB/R5/G/E/RSc/R1c/AGR/A

11.6 ha

 

Large

(27.0%)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Large

Large

Description of Key Impacts during Construction and Operation

n   Approximately 11.6ha of this LR falls within PDA boundaries. Those areas are designated as various land use such as residential uses, educational uses, amenity uses, government uses, storage uses, open spaces and the proposed roads for developments in Stage Two, Three and Four, which is incompatible with existing landscape. Other areas will be reserved for future agricultural uses and green belt which will be compatible with surroundings.

n   During construction, site formation will result in clearance of mature trees and vegetation, which will lead to a permanent loss of a large scale area (27.0%) of this LR. A total of approx. 1348 nos. of trees including five potentially affected POVTs (T-0013, T-0023, T-0028, T-0033 and T-0042) within this LR are estimated to be impacted. Therefore, the compatibility is considered to be poor.

n   In operation, the affected area will be replaced with a series of residential buildings, institutional buildings, industrial storages, amenity infrastructures and future agricultural lands of the RODP scheme.

n   In this case, due to a large scale of this LR will be affected, the magnitude of change is considered to be ‘Large’ during construction and operation.

 

LR3

Hillside Shrubland and Grassland

(162.1 ha)

OU(service reservoir)/OU/R2c/A/GB/LO/AGR

3.8 ha

 

Small

(2.3%)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   Approximately 3.8ha of this LR falls within the PDA boundaries, which is in direct conflict with the sites designated as future agricultural uses (in the southwest lower land areas of Tong Yan Shan Tsuen), residential uses, local open spaces and other land uses for development near TSW West Interchange in Stage Two.

n   Construction impacts will result in the clearance of vegetation and earthworks, which will lead a permanent loss of a small scale area (2.3%) of this LR. A total of approx. 231 nos. of trees including three potentially affected rare/ protected species (R-0001, R-0002 and R-0003) within the LR are estimated to be impacted.

n   In operation, the affected area will be replaced by residential buildings, amenity infrastructures, modified slopes of the proposed service reservoir and future agricultural land. The compatibility is considered as poor as well.

n   Given the above, the magnitude of change is considered to be ‘Small’ in construction and operation.

LR4

Secondary Woodland

(126.8 ha)

GB//GB(1)/A/R5/OU (services reservoir)/ OU/LO(1)

14.6 ha

(approx.

4.8 ha preserved within GB)

Medium

(7.7%)

Poor

Poor

Permanent

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Key Impacts during Construction and Operation

n   Approximately 14.6ha of this LR falls within PDA boundaries. The plots (approx. 4.8ha) in the south of Tong Yan Shan Tsuen will be reserved as green belts for purposes of conservation woodland. However, a small area of this LR closed to Tin Shui Wai West Interchange are designated as amenity uses in Stage Two. And other clusters of woodlands inside Tong Yan Shan Tsuen are designated as residential uses, local open spaces and parts of proposed road network in relation to the development in Stage Four. Furthermore, the proposed service reservoir in Stage One will also replace some areas of this LR.

n   Construction works will require vegetation clearance (including trees), soil stripping and excavation throughout the site.  Cut and fill works will be required to achieve the correct levels.  Those works will lead to a permanent loss of a medium scale area (7.7%) of this LR and significantly influence the integrity of the wider resource, therefore the compatibility would be poor. A total of approx. 1740 nos. of trees including two potentially affected POVT (T-0012 and T-0014) and two rare/ protected species (R-0007 and R-0008) within this LR are anticipated to be impacted.

n   In operation, these woodland areas will be replaced with residential buildings, infrastructures, utility facilities (proposed service reservoir), open spaces and roads that are conflict with the existing landscape. The compatibility is considered as poor as well.

n   Given the above, the magnitude of change is considered to be ‘Intermediate’ during construction and operation.

LR5

Plantation

(46.7 ha)

A/OU (service reservoir)/ OU(SU1)/ OU (S+W)/

Roads

17.4 ha

 

Large

(37.2%)

Fair

Fair

Temporary

Permanent

Reversible

Reversible

Large

Large

Description of Key Impacts during Construction and Operation

n   Approximately 17.4ha of this LR falls within PDA boundaries. Two relative small portions are designated as amenity uses near the Tin Shui Wai West Interchange and in the west of Tin Liu Tsuen for development in Stage Two. The proposed service reservoir on the hillside next to TYST in Stage One and its access road will replace some areas of this LR. Several plots of this LR along the YLH will be impacted by the formation of the proposed major road infrastructures in Stage One. 

n   Construction will require clearance of associated plantation for site formation of new developments, which will lead to a temporary loss of a large scale area (37.2%) of this LR. A total of approx. 3358 nos. of trees including one potentially affected POVT (T-0031) within this LR are anticipated to be impacted.  The area affected by the works will not influence the integrity of the wider resource, therefore the compatibility would be fair in construction and operation.

n   In operation, the affected area will be replaced by infrastructures for amenity uses, utility facilities (proposed service reservoir) and roads. The compatibility is considered to be fair.

n   As a result, given that large extent of the LR will be influence by various land uses, the magnitude of change is considered to be ‘Large’ during construction and operation.

 

LR6

Urban Park

(10.6 ha)

LO

0.2 ha

(preserved in LO)

Small

(1.8%)

Good

Good

Temporary

Permanent

Reversible

Reversible

Negligible

Negligible

Description of Key Impacts during Construction and Operation

n   Approximately 0.2ha of this LR falls within PDA boundaries. A small scale area (1.8%) of this LR, which belongs to the TYST Garden, will be reserved for local open space within the Draft RODP.

n   Since the area of this LR within the Draft RODP will be retained for future open space use, the magnitude of change is considered to be ‘Negligible’ during construction and operation.

 

 

LR7

Road and Urban Infrastructure

(90.1 ha)

OU/LO

8.8 ha

 

Medium

(9.7%)

Fair

Good

Temporary

Permanent

Reversible

Reversible

Intermediate

Small

Description of Key Impacts during Construction and Operation

n   Approximately 8.8ha of this LR falls within the PDA boundaries. A part of section of Lam Tai West Road are designated as local open space and other land use, and the alignment will be amended according to the RODP for development in Stage Two.

n   During construction, site formation will require clearance of associated plantation for building new infrastructures. Breaking hard surface, loss of amenity trees, amending layout of the existing channels (along Lam Tai West Road),cut and fill works achieve the correct levels will directly affect a medium scale area of the LR (9.7%). A total of approx. 96 nos. of trees including three potentially affected POVT (T-0011, T-0036 and T-0037) within this LR are estimated to be impacted.

n   In operation, the affected area will be replaced with open space and sites of other land uses. However, the new proposed road network by the RODP shceme will compensate for the loss of this LR in operation. Therefore the compatibility would be good in operation.

n   Given the above, the magnitude of change is considered to be ‘Intermediate’ during construction and ‘Small’ during operation.

 

 

LR8

Major Transport Corridor

(29.2 ha)

N/A

0ha

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Description of Key Impacts during Construction and Operation

n   The existing major transport corridor, the YLH falls outside of the PDA boundaries and the works area of the proposed major road infrastructures, which will not be impacted by the Project.

 

 

 

 

LR9

Urbanised Development

(188.6 ha)

R5(EDA)/ LO/R5

12.1 ha

 

Medium

(6.4%)

Fair

Good

Temporary

Permanent

Reversible

Reversible

Intermediate

Small

Description of Key Impacts during Construction and Operation

n   Most of the areas within the PDA boundaries are the existing buildings which will be reserved for the residential uses in Tong Yan San Tsuen. According to the development at TYST in Stage Four, approximately 12.7ha of this LR falls within the footprint of the designated local open space in the south of TYST Road and the proposed road network of RODP scheme.

n   Construction impacts will include vegetation clearance, soil stripping and excavation, which lead to a temporary loss of a medium scale area (6.4%) of this LR. A total of approx. 345 nos. of trees including two potentially affected POVT (T-0002 and T-0020) and one rare/ protected species (R-0035) within this LR are anticipated to be impacted.

n   In operation, most of the affected areas will be replaced with new residential buildings, which would not change the nature of this LR. Therefore, the compatibility would be good in operation as the proposed land uses can be integrated within the surroundings.

n   As a result, taking into account that most of this LR will be retained and the limited extent affected by the project, the magnitude of change is considered to be ‘Intermediate’ in construction and ‘Small’ in operation.

LR10

Village Type Development

(265.8 ha)

OU(OS)/A/AGR/R5/R6/LO/DO

10.2 ha

 

Small

(3.8%)

Fair

Fair

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   Although some village areas will be preserved as existing development area within the PDA boundaries, approximately 10.2ha of this LR is still affected by sites designated for residential uses, local & district open spaces uses and proposed road network at TYST in Stage Four, amenity uses and open storage uses near the Tin Shui Wai Interchange for development in Stage Two, and future agricultural land uses in the existing areas next to Shan Ha Tsuen in Stage Four.

n   Construction will require demolition of the existing interim road, structures, clearance of vegetation (including trees), and earthworks to achieve the correct levels. A small scale (3.8%) of village areas will be lost. A total of approx. 511 nos. of trees including one potentially affected POVT (T-0004) within this LR are anticipated to be impacted.

n   In operation, the affected village areas will be replaced by new residential buildings, infrastructures, open spaces, future agricultural lands and roads. Since the proposed open space uses and road network can incorporate with this rural character area and introduce more formalised roads into the village environment during operation, the compatibility is considered to be fair. However, the impacts from the loss of village areas are still experienced.

n   Given the above, the magnitude of change is considered to be ‘Small’ during construction and operation. 

LR11

Open Storage/ Rural Built Area

(405.1 ha)

OU(S+W)/OU(SU1)/ LO/LO1/ DO/R5/R4/E/OU(MU)/RSc/R1c/R2c/R3/G/ GB/C

142.2 ha

 

Large

(35.1%)

Fair

Fair

Permanent

Permanent

Reversible

Irreversible

Large 

Large 

Description of Key Impacts during Construction and Operation

n   Approximately 142.2ha of this LR falls within the footprint of the RODP scheme and are mainly affected by various land uses for the further developments throughout Stage Two, Three and Four.

n   Construction will require demolition of the existing interim road, storages, rural industrial buildings, structures, clearance of vegetation, breaking out hard surface and earthworks. These works will lead a permanent loss of large scale areas (35.1%) of the LR. A total of approx. 2570 nos. of trees including eleven potentially affected POVT (T-0001, T-0007, T-0009, T-0017, T-0022, T-0027, T-0032, T-0034, T-0035, T-0038 and T-0040) within this LR are anticipated to be impacted.

n   In operation, these large affected areas will be totally replaced with a series of new buildings and infrastructures in accordance with the RODP. Since landscape enhancement works such as open spaces, revitalisation of nullahs and reedbed enhancement have been proposed, the development will be fairly compatible with the existing and partially enhance it.

n   As a result of the relatively large scale of this LR that will be affected, the magnitude of change is considered to be ‘Large’ during both construction and operation.

LR12

Disturbed Area

(58.8 ha)

R5/DO/G/R2c/R3/GB

2.9 ha

 

Small

(4.9%)

Fair

Fair

Permanent

Permanent

Irreversible

Irreversible

Small

Small

Description of Key Impacts during Construction and Operation

n   Approximately 2.9ha of this LR falls within RODP scheme for developments in Stage Two, Three and Four. Those areas are mainly in direct conflict with designated sites for residential uses, government uses, district open spaces and green belt in Tong Yan San Tsuen. In addition, some other plots will be covered by the proposed road networks.

n   During construction, site formation works will result in vegetation clearance, demolition of temporary structures and earthworks throughout this LR area. These works will lead to a loss of a small scale area (4.9%) of this LR. A total of approx. 138 nos. of trees within this LR are anticipated to be impacted.

n   In operation, the affected areas will be replaced with a series of residential buildings, government infrastructures, amenity landscape and road systems. The adverse impacts due to the replacement are still experienced. While some areas will also be reserved for open space and green belt uses. Therefore the compatibility with the surroundings is considered to be fair.

n   Given the above, the magnitude of change is considered to be ‘Small’ during both construction and operation.

LR13

 

Agricultural Pond

(4.3 ha)

DO/OU (MU)

0.3 ha

 

Medium

(6.9%)

Fair

Fair

Temporary

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Key Impacts during Construction and Operation

n   The existing ponds are mainly used for agricultural irrigation and water collection. Approximately 0.3ha of this LR within PDA is designated for district open space and mixed land use near the TYST Interchange for development in Stage Four.

n   During construction, site formation works will result in filling the existing ponds, which will lead a permanent loss of a medium scale area (6.9%) of this LR.

n   In operation, the affected ponds will be totally placed with infrastructures and facilities for amenity use. The adverse impact from the loss of this resource are still experienced.

n   As a result, the magnitude of change is considered to be ‘Intermediate’ in construction and operation.

LR14

Channelised Watercourse

(22.2 km)

OU(SU)1/AGR/R6 /R5/OU (MU)

7.7 km

 

Large

(34.6%)

Fair

Fair

Temporary

Permanent

Irreversible

Irreversible

Large

Small

Description of Key Impacts during Construction and Operation

n   Approximately 7.7km of this LR flows throughout the PDA boundaries. Most of these man-made channels and drainages fall into the working area for nullah decking and revitalisation works in Stage One and Two. They need to be upgraded and beautified with amenity vegetation together with road improvement works in various sections, including areas within the channel or along the ridgeline of embankment. Specially, part of the nullahs along Kung Um Road and Lam Tai West Road will be decked over for carriageway subject to the proposed road network. Other small parts of this LR will be filled for sites designated as storage uses and mixed uses.

n   Construction works will result in breaking concrete embankment and earthworks to achieve the planting requirement, and filling of some channels. These works will lead to temporary disturbance on a large scale area (34.6%) of this LR. 

n   In operation, the landscape quality of most channels will be improved in operation. The adverse impacts are anticpated for the loss of some sections that are filled for other land uses.

n   Due to the large scale extent of construction works,  the magnitude of change is considered to be ‘Large’ in construction but ‘Small’ in operation when the revitalisation works of these nullahs are completed.

LR15

Watercourses of higher ecological value (21.8km)

GB/OU/LO/R5

4.1km

(approx. 2.1km preserved in GB)

Medium

(9.1%)

Fair

Fair

Temporary

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Key Impacts during Construction and Operation

n   Approximately 4.1km of this LR flow through the PDA boundaries, some sections (approx. 2.1km) will be preserved to minimise the impacts by offsetting 15m green buffer on either side of the watercourses. And for the section near the Lam Tai West Road, it will be designated as the area for hillside river corridor with scenic cycle track for development in Stage Three. However, some sections of watercourses of higher ecological value will still be affected by the development at TYST in Stage Four.

n   During construction, slope formation and vegetation planting will be required to create natural buffers to the existing watercourses but this will have no impacts to this resource. Construction works for the affected sections will require partly filling of the watercourses, breaking the embankment and earthworks. These works will lead to a permanent loss of a medium scale area (9.1%) of this LR.

n   In operation, the affected sections will be replaced with a series of buildings and infrastructures. The adverse impacts from the loss of this resource are still experienced.

n   Given the above, the magnitude of change is considered to be ‘Intermediate’ during construction and operation.

LR16

Reservoir

(1.76 ha)

N/A

0 ha

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Description of Key Impacts during Construction and Operation

n   The extent of the reservoir and its associated planting falls within the 500m offset buffer range but does not fall within the PDA boundary. It is therefore considered the proposed development to have no impact physically upon the reservoir.

Note: [^] Large physical extent of impact - >20% of total LR/ LCA area within 500m assessment area

                Medium physical extent of impact - 5 to 20 % of total LR/ LCA area within 500m assessment area

                Small physical extent of impact - <5 % of total LR/ LCA area within 500m assessment area

          [*] Land Use Types of RODP. Refer to Figure 10.2.


10.10.5        Impact on Existing Trees

10.10.5.1     According to the latest RODP, it is predicted that about 63 % of trees may be affected by the proposed development. A detailed Tree Felling Application process will be carried out at a later detailed design stage, to finalise tree treatment and allocate compensatory planting areas including available open space, parks and streetscape. There are three (3) OVTs found in the assessment area, but outside the PDA; however there are seventy-seven (77) numbers of identified Important Trees (including POVT and rare/ protected species) as per LAO PN No. 7/2007. It is anticipated that thirty-four (34) numbers of them are in direct conflict with the proposed development as listed in Table 10.10.3. All the important tree locations are illustrated in Figures 10.6.

 


Table 10.10.3 Affected Important Trees within PDA

Item

Tree ID

Species

Chinese Name

Estimate Tree Size

Health

(Good / Fair / Poor)

Form (Good / Fair / Poor)

Survival Rate after

Transplanting (High/ Medium/ Low)

Remarks

Trunk Diameter

(mm)

Overall Height (m)

Crown Spread

(m)

1

T-0001

Celtis sinensis

朴樹

1120

11.0

6.0

Fair

Fair

Low

POVT *

2

T-0002

Delonix regia

鳳凰木

1010

14.0

11.0

Fair

Fair

Low

POVT

3

T-0004

Ficus microcarpa

細葉榕

1580

14.0

17.0

Fair

Fair

Low

POVT

4

T-0007

Bombax ceiba

木棉

1045

16.0

11.0

Fair

Fair

Low

POVT

5

T-0009

Ficus microcarpa

細葉榕

1000

14.0

14.0

Fair

Fair

Low

POVT

6

T-0011

Eucalyptus robusta

大葉桉

1200

12.0

10.0

Fair

Fair

Low

POVT

7

T-0012

Bombax ceiba

木棉

1300

16.0

12.0

Fair

Fair

Low

POVT

8

T-0013

Ficus microcarpa

細葉榕

1050

20.0

20.0

Fair

Fair

Low

POVT

9

T-0014

Celtis sinensis

朴樹

1100

16.0

14.0

Fair

Fair

Low

POVT

10

T-0017

Ficus microcarpa

細葉榕

1200

13.0

12.0

Fair

Fair

Low

POVT

11

T-0020

Eucalyptus citriodora

檸檬桉

1000

18.0

10.0

Fair

Fair

Low

POVT

12

T-0022

Bombax ceiba

木棉

1100

20.0

10.0

Fair

Fair

Low

POVT

13

T-0023

Bombax ceiba

木棉

1700

25.0

15.0

Fair

Fair

Low

POVT

14

T-0025

Celtis sinensis

朴樹

1000

10.0

10.0

Fair

Fair

Low

POVT

15

T-0026

Celtis sinensis

朴樹

1020

16.0

13.0

Fair

Fair

Low

POVT

16

T-0027

Celtis sinensis

朴樹

1050

12.0

6.0

Fair

Fair

Low

POVT

17

T-0028

Celtis sinensis

朴樹

1007

12.0

10.0

Fair

Fair

Low

POVT

18

T-0030

Ficus microcarpa

細葉榕

1925

16.0

20.0

Fair

Fair

Low

POVT

19

T-0031

Ficus microcarpa

細葉榕

1260

16.0

10.0

Fair

Fair

Low

POVT

20

T-0032

Ficus microcarpa

細葉榕

1200

12.0

18.0

Fair

Fair

Low

POVT

21

T-0033

Ficus elastica

印度榕

1200

10.0

12.0

Fair

Fair

Low

POVT

22

T-0034

Ficus microcarpa

細葉榕

1100

10.0

13.0

Fair

Fair

Low

POVT

23

T-0035

Ficus virens var. sublanceolata

大葉榕

1050

10.0

10.0

Fair

Fair

Low

POVT

24

T-0036

Ficus elastica

印度榕

1500

13.0

10.0

Fair

Fair

Low

POVT

25

T-0037

Ficus elastica

印度榕

1700

13.0

10.0

Fair

Fair

Low

POVT

26

T-0038

Bombax ceiba

木棉

1600

17.0

10.0

Fair

Fair

Low

POVT

27

T-0040

Celtis sinensis

朴樹

1100

10.0

11.0

Fair

Fair

Low

POVT

28

T-0042

Ficus elastica

印度榕

1200

10.0

10.0

Fair

Fair

Low

POVT

29

R-0001

Aquilaria sinensis

土沉香

162

7.0

4.0

Fair

Fair

Low

Tree of rare/ protected species

30

R-0002

Aquilaria sinensis

土沉香

126

6.0

3.0

Fair

Fair

Low

Tree of rare/ protected species

31

R-0003

Aquilaria sinensis

土沉香

108

6.0

2.0

Fair

Fair

Low

Tree of rare/ protected species

32

R-0007

Artocarpus hypargyreus

白桂木

499

12.0

7.0

Fair

Fair

Low

Tree of rare/ protected species

33

R-0008

Artocarpus hypargyreus

白桂木

576

12.0

8.0

Fair

Fair

Low

Tree of rare/ protected species

34

R-0035

Artocarpus hypargyreus

白桂木

400

11.0

7.0

Fair

Fair

Low

Tree of rare/ protected species

Note: [*] POVT = Potentially registrable Old and Valuable Trees.

10.10.5.2        The recommendation treatment for the Affected Important Trees are subject to detailed design at a later stage. For these rare/ protected species, retained on site should be explored as far as possible. As part of the detailed Urban Design Framework, many of these Important Trees are proposed to be circumscribed in Open Space areas in order to be retained and protected. In other instances where this is not practical, implementation of the proposed mitigation measures calls for the trees to be transplanted if impacts on them cannot be avoided.


10.10.6        Significance of Landscape Impacts Before Mitigation

10.10.6.1        The potential significance of landscape impacts during the construction and operational phases, before mitigation, is provided in Tables 10.10.4 and 10.10.5 below.  The assessment follows the methodology proposed in Section 10.3.5 and the matrix provided in Table 10.3.1.  

10.10.6.2        Landscape Impacts are mapped on Figures 10.8a to 10.8d and Figures 10.9a to 10.9d.

Table 10.10.4  Significance of Impacts on LCAs

LCA Code

Name

LR Sensitivity (High/ Medium/ Low)

Magnitude of Change (Large/ Intermediate/ Small/ Negligible

Impact Significance Before Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

CON

OP

CON

OP

LCA1a

Miscellaneous Rural Fringe Landscape – Open Storage/ Rural Built Area

Low

Large

Large

Moderate

Moderate

LCA1b

Miscellaneous Rural Fringe Landscape – Lowland Agricultural Land

Medium

Intermediate

Intermediate

Moderate

Moderate

LCA2

Miscellaneous Urban Fringe Landscape

Low

Small

Small

Slight

Slight

LCA3

Upland and Hillside Landscape

High

Small

Small

Moderate

Moderate

LCA4

Settled Valley Landscape

High

N/A

N/A

N/A

N/A

LCA5

Park Urban Landscape

High

N/A

N/A

N/A

N/A

LCA6

“Hui” Urban Landscape

Low

N/A

N/A

N/A

N/A

LCA7

Urban Peripheral Village Landscape

Medium

Small

Small

Slight

Slight

LCA8

Transportation Corridor Landscape

Low

Large

Small

Moderate

Slight

 


 

Table 10.10.5  Significance of landscape impacts on LRs

LR Code

Name

LR Sensitivity (High/ Medium/ Low)

Magnitude of Change (Large/ Intermediate/ Small/ Negligible

Impact Significance  Before Mitigation       (Substantial/ Moderate/ Slight/ Insignificant)

CON

OP

CON

OP

LR1a

Active Agricultural Land

High

Intermediate

Intermediate

Moderate

Moderate

LR1b

Abandoned Agricultural Land

Medium

Small

Small

Slight

Slight

LR1c

Orchard

High

Intermediate

Intermediate

Moderate

Moderate

LR2

Lowland Mixed Trees, Shrubland and Grassland

Medium

Large

Large

Moderate

Moderate

LR3

Hillside Shrubland and Grassland

Medium

Small

Small

Slight

Slight

LR4

Secondary Woodland

High

Intermediate

Intermediate

Moderate

Moderate

LR5

Plantation

Medium

Large

Large

Moderate

Moderate

LR6

Urban Park

Medium

Negligible

Negligible

Insignificant

Insignificant

LR7

Road and Urban Infrastructure

Medium

Intermediate

Small

Moderate

Slight

LR8

Major Transport Corridor

Low

N/A

N/A

N/A

N/A

LR9

Urbanised Development

Low

Intermediate

Small

Slight

Slight

LR10

Village Type Development

Medium

Small

Small

Slight

Slight

LR11

Open Storage/Rural Built Area

Medium

Large

Large

Substantial

Substantial

LR12

Disturbed Area

Low

Small

Small

Slight

Slight

LR13

Agricultural Pond

Medium

Intermeidate

Intermediate

Moderate

Moderate

LR14

Channelised Watercourse

Low

Large

Small

Moderate

Slight

LR15

Watercourses of higher ecological value

High

Intermediate

Intermediate

Moderate

Moderate

LR16

Reservoir

Low

N/A

N/A

N/A

N/A

 

 

10.10.7        Change of Existing Visual Resources

10.10.7.1        The existing brownfield sites are likely to experience significant changes by the proposed developments, which will transform the existing brownfield site to an urbanised area. A part of the existing industrial factories which located at the west of the PDA will be removed and change to a residential area. For the existing low-rise residential area which located at the south of the PDA, the erection of proposed high-rise residential buildings will make a significant change to the existing view. Besides, the existing Yuen Long Nullah will be developed by the proposed works, the northern section of nullah will be partially decked to provide adequate road space.

10.10.7.2        Further details of the magnitude of visual change are provided as below. 

10.10.8        Magnitude of Visual Change

10.10.8.1        The potential sources of visual impact due to the Project are described in Section 10.10.2.  They will create varying levels of visual impact during the construction and operation phases due to factors such as visual obstruction, degradation of the quality of existing views and incompatibility with the surrounding landscape setting.

10.10.8.2        The magnitude of visual change is largely dependent on a number of factors as outlined in the methodology.

10.10.8.3        Detailed engineering design of built elements is ongoing at this stage. Therefore, the structures shown in the photomontages (refer to Figure 10.14a to 10.14r) may change as detailed design is refined. 

10.10.8.4        Table 10.10.6 details the magnitude of change in relation to RODP.


Table 10.10.6  Magnitude of visual change for VSRs

VSR Code

Name

Key Designated Projects (DPs)/ Sites with Structures causing Visual Impact (Land Use Type) *

Blockage of View (Full/ Partial/ Nil)

Approx. Closest Viewing Distance to PDA (m)

Scale of Development (Large/ Medium/ Small)

Compatibility with Surrounding Landscape

(Good/ Fair/ Poor)

Duration of Impact

(Temporary, Permanent)

Reversibility of Change

(Reversible/ Irreversible)

 

 

 

Magnitude of Change (Large/ Intermediate/ Small/ Negligible)

CON

OP

CON

OP

CON

OP

CON

OP

VSR1

Yuen Long Park Tower

OU(MU)/OU(RCP&SPS)/A/V/R5(EDA)/R6/ DO/G/IC/LO

Partial

540

Large

Poor

Fair

Temporary

Permanent

Irreversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

The elevated level from this VSR can provide a broad view to the development area even though partial views are blocked by the high-rise residential buildings in Yuen Long New Town. During the construction, the ancillary structures such as site offices, construction facilities, and erection of structures as well as loss of trees are considered to be significant sources of visual impact. In the night time, the lighting requirements for these developments would generate night-time glare. In operation, high rise residential buildings will obstruct views towards hillside landscape in the backdrop. Due to the extensive visual extent affected by the Project, the magnitude of change is considered to be large both in construction and operation.

VSR2

Fui Sha Wai South Road

OU(SU)2/A/LO/R5(EDA)/IC

Partial

0

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During the construction stage, construction works require clearance of the existing trees and shrubs, which will degrade visual quality of the view. The erection of high-rise building blocks will be significant source of visual impact, while lighting from construction facilities would detract the nightscape. Control of night-time lighting by shrouding all lights, using directional lights and through minimisation of night working periods will be considered.  Avoid use of reflective surfaces on buildings or other structures. During operation, even though roadside tree can reduce the blockage of new industrial buildings, degree of visibility from this VSR is still glimpse. Therefore, the magnitude of change is considered as intermediate both in construction and operation.

VSR3

Tong Yan San Tsuen Track

OU(S+W)/

OU(SU)1/DO/

LO(1)

Partial

0

Medium

Poor

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During construction, vegetation clearance, earthworks and erection of building structures will degrade the existing visual quality. The proposed developments, especially industrial buildings form ing detracting elements, would also block view to the hillside landscape. Night-time glare by the construction facilities is also noticeable. In operation, facade of the proposed industrial buildings would detract the existing visual quality and block most of the view. Therefore, the magnitude of change is considered to be intermediate during construction and operation.

VSR4

Fui Sha Wai

OU(S+W)/

OU(SU)1/A/

LO(1)

Partial

230

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During the construction stage, the clearance of vegetation and trees would degrade the existing landscape. The erection of high-rise building blocks will be significant source of visual impact. As the existing environment mainly consist of low-rise buildings, whereas the proposed industrial developments are up to 70 to 90mPD, thus the compatibility of the development is considered to be poor during construction and operation. Given the above, the magnitude of change during construction and operation is considered to be intermediate.

VSR5

Forefront Cyber Centre

OU(S+W)/

OU(SU)1/A/LO/LO(1)/DO/R5 (EDA)

Partial

140

Medium

Poor

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Small

Description of Impacts during Construction and Operation

During construction, the demolition of buildings and structures, clearance of vegetation and trees would degrade the existing landscape. Night time glare from construction facilities would detract the nightscape. Control of night-time lighting by shrouding all lights, using directional lights and through minimisation of night working periods and avoidance of reflective surface on buildings or other structures will be considered during construction. In operation, loss of mature trees and erection of industrial buildings would be the significant source of visual impact. Roadside tree planting next to new developments would introduce more natural elements to the view thus reduce adverse impacts. Therefore, the magnitude of change is considered to be small in operation.”

VSR6

Jasper Court and Long Tin Road

OU(RCP&SPS)/OU(MU)/A/V/R6

 

Partial

260

Small

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

From the ground level of this VSR, views towards the proposed developments are restricted by the YLH and associated roadside plants. Since only  small scale of development will be visible in  a distance, the magnitude of change is considered to be small during construction and operation stage.

VSR7

Parkside Villa

OU(RCP&SPS)/OU(MU)/A/V/R6

 

Partial

280

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During construction, construction works such as clearance of vegetation, demolition of structures and site earthworks will degrade the visual quality, especially from the elevated level, where a broad view to the site is possible. At ground level, the adverse impacts can be reduced due to the blockage from the YLH, open storage and associated trees. Night time glare from the construction facilities is also considered as significant sources of visual impacts. In operation, major visual impact would generate by the erection of high-rise buildings, which would obstruct views towards natural hillside landscape in the backdrop. The magnitude of change is considered intermediate both in construction and operation.

VSR8

Tong Yan San Tsuen Interchange

OU(MU)/R5(EDA)/DO

 

Partial

0

Small

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During construction, construction works such as clearance of mature roadside vegetation and erection of the high-rise buildings are considered as the significant sources of visual impact. Night-time glare from construction facilities will become significant sources of visual impact and detract the nightscape. Control of night-time lighting by shrouding all lights, using directional lights and through minimisation of night working periods and avoidance of reflective surface on buildings or other structures will be considered during construction. In operation, even though mitigation plants would be implemented on site, the erection of commercial and residential buildings would be the intrusion to rural landscape view. The magnitude of change is considered intermediate in construction and operation.

VSR9

Intersection of Kung Um Road and Shap Pat Heung Road

R5(EDA)

Enclosure Noise Barrier

Partial

290

Large

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

Given the existing buildings and vegetation would be a blockage to the proposed development, only a small scale of residential buildings will be partially visible from this VSR. Besides, a 6m high semi-enclosure would be constructed next to Kung Um Road and Kiu Hing Road, which will be considered as significant sources of visual impacts (Refer to the section AA - North of Kung Um Road & Kiu Hing Road in Appendix 10.3). Therefore the magnitude of change is considered as large level during construction and operation.

VSR 10

Intersection of Lam Hei Rd and Kung Um Rd

R5(EDA)/

OU(RCP&SPS)

 

Partial

35

Medium

Fair

Fair

Temporary

Permanent

Irreversible

Irreversible

Intermediate

Small

Description of Impacts during Construction and Operation

View from this VSR is restricted by the existing roadside plantation. In construction, main source of visual impact come from the erection of high-rise buildings as well as lighting from construction facilities. In operation, the Project comprised of more urbanised elements can integrate with wider visual extent. Due to the blockage of YLH, the magnitude of change is considered to be intermediate in construction but small in operation given mitigation plants would link the proposed developments with wider landscape.

VSR 11

Tin Liu Tsuen

R5(EDA)/

OU(RCP&SPS)/LO

Partial

210

Large

Fair

Fair

Temporary

Permanent

Irreversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During construction, road improvement works including the provision of footpath, cycle track, amenity plants, as well as coverage of the existing nullah, would be the significant sources of visual quality. The erection of high-rise residential buildings and night-time lighting from construction facilities are also considered. In operation, a more urbanised road system with amenity plants would enhance the visual quality and the magnitude of change is considered to be intermediate in operation.

VSR 12

Chun Fai Garden

OU(ESS)/RSc/LO

 

Partial

35

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

During construction, construction works including the demolition of temporary structures, vegetation clearance, road improvement, would be the significant sources of visual quality. The erection of high-rise residential buildings and night-time glare from construction facilities will further detract the view and generate unpleasant visual impacts. Control of night-time lighting by shrouding all lights, using directional lights and through minimisation of night working periods and avoidance of reflective surface on buildings or other structures will be considered during construction. In operation, amenity plants from the PRN and DO would enhance the visual quality and thus the magnitude of change is considered to be intermediate in operation.

 

VSR 13

Pathway near Muk Kiu Tau Tsuen

DO/R1(SSF)c/ LO/G

Partial

15

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

From this sensitive receiver, the proposed developments can be seen along both sides of the Kung Um Road. Construction works include the demolition of temporary structures, vegetation clearance as well as road improvement. Night-time glare is also considered as source of visual impact. The monotonous appearance of the artificial channel would be decked over as a formalised urban road system comprised of amenity plants, pedestrian and outdoor furniture, forming a more attracting urban fabric. Given the GIC/Residential buildings sitting along the roadside will obstruct part of views towards the hillside landscape, the compatibility of the developments is considered to be poor during construction and operation. Therefore, the magnitude of change is considered to be large in construction and operation.

VSR 14

Kiu Hing Road near Pak Sha Tsuen

R2C/R2(SSF)c/LO

Partial

655

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

The main source of visual impact during the construction includes the road improvement works and erection of high-rise residential buildings. Night-time glare from construction facilities is also considered. Even though a more attracting streetscape can enhance the visual quality in operation, the visual extent and elements would be changed significantly. Therefore, the magnitude of change is considered to be intermediate in operation and construction.

VSR 15

One Hyde Park Bus Station

R2(SSF)c/LO

Partial

300

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

The main source of visual impact during the construction includes the road improvement works and erection of high-rise residential buildings. Night-time glare from construction facilities is also considered. During operation, trees and vegetation would become mature and form various green spaces along the roadside and parkland area. Providing the visual extent and elements would be changed significantly. Thus, the compatibility of the development is considered to be poor during construction and operation. Given the above, the magnitude of change during construction and operation is considered to be large.

 

VSR 16

Channel Pathway on Kung Um Road

R5(EDA)/E/A/LO/OU(MU)/G

Partial

0

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

The main source of visual impact during the construction includes the road improvement works and erection of high-rise residential buildings on either side of Kung Um Road. Night-time glare from construction facilities is also considered. Even though a more attracting streetscape can enhance the visual quality in operation, the scale and composition of visual elements would be changed significantly. Therefore, the compatibility of the development is considered to be poor during construction and operation. Given the above, the magnitude of change during construction and operation is considered to be large.

VSR 17

Pak Sha Tsuen Facing Southwest

C/R2(SSF)c/LO

Partial

50

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

During construction, road improvement works include clearance of the existing vegetation, demolition of temporary structures, earthworks as well as the construction of footpath, cycle track and amenity planting. Together with the erection of high-rise residential buildings, these would be the intrusion elements to the existing view. In operation, providing softscape fully implemented, part of the adverse impacts can be reduced. The coverage of the existing nullah would change the existing view significantly. In addition, the erection of public houses at the foothill area would partially block the natural views. Therefore, the compatibility of the development is considered to be poor during both construction and operation. Given the above, the magnitude of change during construction and operation is considered to be large.

VSR 18

Tai Lam Mountain 1 Facing Northeast

R4/R5/R6/ R5(EDA)/GB/ AGR/GB(1)/LO/IC/DO/LO(1)/OU(SU)1/

OU(S+W)/

OU(MU)/E/G/A/V

Nil

1220

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

This sensitive receiver is located on the high level area of the Tai Lam Mountain, which offers a broad view of the proposed developments. In the construction, works will require the demolition of existing buildings, clearance of vegetation and earthworks to achieve the correct roads levels throughout the PDA. The erection of building structures, loss of mixed woodland and agricultural land will be the significant sources of visual impact. Due to the long distance and high level of the view, there will be no blockage of the existing view. In operation, a more urbanised landscape would characterized the view connecting with the Yuen Long New Town to the north. Considering the extent and land use types affected, the magnitude of change is considered to be large in construction and operation.

VSR 19

Tai Lam Mountain 2 Facing East

A/OU/G/LO/C/E/RSc/R2c/

R2(SSF)c/ R5(EDA)/R3/ DO/GB(1)/

OU(STW)/

OU(MU)

Partial

665

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

High level of this VSR offers a broad view towards the overall development area.  In the construction, works will require the demolition of existing buildings, clearance of vegetation and earthworks to achieve the correct roads levels throughout the PDA. The erection of building structures, loss of mixed woodland and agricultural land will be the significant sources of visual impact.  Partial views have been blocked by ridgeline of the hillside mountain. In operation, a more urbanised landscape will dominate the view connecting with the Yuen Long New Town to the north. Due to the large scale of the Project, the magnitude of change is considered to be large in construction and operation.

VSR 20

Tai Lam Mountain 3 Facing Southeast

AGR/A/V/OU/G/LO/C/E/RSc/

R2c/R2(SSF)c/ R5(EDA)/R3/ DO/GB(1)/

OU(STW)/

OU(MU)

Partial

760

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

An overall view throughout the site is possible due to the elevated level of this VSR.  In the construction, works will require the demolition of existing buildings, clearance of vegetation and earthworks to achieve the correct roads levels throughout the PDA. The erection of building structures, loss of mixed woodland and agricultural land will be the significant sources of visual impact.  Partial views have been blocked by ridgeline of the hillside mountain. In operation, residential building blocks would replace the existing industrial buildings, which can enhance the visual quality. The magnitude of change is considered to be large in construction and operation. as a result of  extensive perspective towards the whole site.

VSR 21

Tai Lam Mountain 4 Facing Northeast

AGR/A/OU/G/LO/C/E/RSc/

R2c/R2(SSF)c/ R5(EDA)/R3/ DO/GB(1)/

OU(STW)/

OU(MU)

Nil

1335

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

High level of this VSR offers a broad view towards the overall development area.  In the construction, works will require the demolition of existing buildings, clearance of vegetation and earthworks to achieve the correct roads levels throughout the PDA. The erection of building structures, loss of mixed woodland and agricultural land will be the significant sources of visual impact.  Partial views have been blocked by ridgeline of the hillside mountain. In operation, residential building blocks would replace the existing industrial buildings, which can enhance the visual quality. Due to the large extent of the Project, the magnitude of change is considered to be large in construction and operation.

VSR 22

Tai Lam Mountain 5 Facing Northeast

AGR/A/V/OU/G/LO/C/E/RSc/

R2c/R2(SSF)c/ R5(EDA)/R3/ DO/GB(1)/

OU(STW)/

OU(MU)

Nil

615

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

A broad view throughout the site is possible due to the elevated hillside level.  In the construction, works will require the demolition of existing buildings, clearance of vegetation and earthworks to achieve the correct roads levels throughout the PDA. The erection of building structures, loss of mixed woodland and agricultural land will be the significant sources of visual impact.  Partial views have been blocked by ridgeline of the hillside mountain and woodland at the foothill area. In operation, residential building blocks would replace the existing industrial buildings, which can enhance the visual quality. Due to the large scale of the Project, the magnitude of change is considered to be large in construction and operation.

 

 

VSR 23

Tai Lam Mountain 6 Facing North

AGR/A/V/OU/G/LO/C/E/RSc/

R2c/R2(SSF)c/ R5(EDA)/R3/ R6/DO/GB(1)/

OU(STW)/

OU(MU)

Nil

780

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

From an elevated level of this VSR, an overall view is possible throughout the site.  In the construction, the demolition of existing buildings, clearance of vegetation and earthworks would become the significant sources of visual impacts. The erection of building structures, loss of mixed woodland and agricultural land is also considered. Partial views have been blocked by ridgeline of the hillside mountain and woodland along the foothill side. In operation, high-rise residential building blocks would replace the existing industrial buildings, which can enhance the visual quality. Due to the large scale of visual impacts, the magnitude of change is considered to be large in construction and operation.

 

 

VSR 24

Tai Lam Mountain 7 Facing Northeast

AGR/A/V/G/ LO/C/E/R2c/

R2(SSF)c/ R5(EDA)/R3/ DO/GB(1)/

OU(STW)

Partial

220

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

View from this VSR is restricted by the hillside woodland and burial ground. In the construction, the demolition of existing buildings, clearance of vegetation and earthworks would become the significant sources of visual impacts. The erection of building structures, loss of mixed woodland and agricultural land is also considered. In operation, residential building blocks would replace the existing industrial buildings, which would result in blockage view towards the northwest of the PDA. Therefore, the compatibility of the development is considered to be poor during both construction and operation. Given the above, the magnitude of change during construction and operation is considered to be large.

 

 

VSR 25

Tai Lam Mountain 8 Facing Northeast

R4/R5/

R5(EDA)/GB/AGR/GB(1)/LO/IC/DO/LO(1)/

OU(SU)/ OU(SU)1/

OU(SU)2/

OU(S+W)/

OU(MU)/E/G/A

Full

542

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

High level of this VSR offers a broad view towards the Area 1. In the construction, works will require the demolition of existing buildings, clearance of vegetation and earthworks to achieve the correct roads levels throughout the PDA. The erection of building structures, loss of mixed woodland and agricultural land will be significant sources of visual impact. Due to the long distance and high level of the view, there will be no blockage of the existing view. In operation, a more urbanised landscape would characterized the view connecting with Area 1. Due to the large scale of the Project, the magnitude of change is considered to be large in construction and operation.

 

 

VSR 26

Access Road off Tai Tong Shan Road

DO/V/E/R3/R2(SSF)c/LO

Nil

1000

Small

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

This sensitive receiver is located on one access way to Tai Tong Tsuen, from which a natural landscape of Tai Tam Country Park is visible. Due the relative long distance and blockage by the mixed trees and shurbland, the construction works on the ground level will not be noticed in this view. Building construction works such as erection of structures together with the facilities in the site and night-time glare will be the significant source of the visual impact. In operation, the erection of high-rise buildings would have small impact on the quality of natural view as a result of small extent visible from this VSR.

VSR 27

Shui Tsiu San Tsuen Road near Wong Nai Tun Tsuen

R3/R2(SSF)c/ LO

Partial

365

Medium

Fair

Good

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

The proposed developments will be noticed behind the existing village houses of Wong Nai Tun Tsuen. During construction, works including demolition of structures and buildings, clearance of vegetation will be the source of visual impact. The erection of high-rise buildings will be more significant impact on the view. Due to long distance and blockage of existing residential blocks, the views towards the proposed developments are of limited extent. The magnitude of change is considered as small both in construction and operation.

VSR 28

Shui Tsiu San Tsuen

A/E/LO/

R5(EDA)

 

Partial

312

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

The natural skyline at the ground level from this VSR will be affected by the erection of high-rise residential building and generate significant blockage to the hillside landscape. The clearance of vegetation and trees, site formation, and demolition of the existing structures would degrade the visual quality during construction. In operation, due the blockage of views towards hillside landscape, the magnitude of change is considered to be intermediate.

 

VSR 29

Sham Chung Tsuen

DO/R5(EDA)/ LO/RSc/DO

 

Partial

208

Medium

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

The proposed developments will be noticed from Sham Chung Tsuen to the west of the PDA. Construction works will require the demolition of structures and buildings, clearance of vegetation. Due to the low density developed area, the erection of high-rise buildings will be the significant impact on the view. The night-time glare will also be considered as the source of visual impact. In operation, the high-rise buildings of public housing or private housing will be the blockage of the landscape view to the Tai Lam Country Park. Given the compatibility of the development is considered to be poor during both construction and operation, the magnitude of change is considered to be large.

VSR 30

Shan Ha Tsuen

R6

Partial

217

Medium

Poor

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

From the VSR, view is restricted by the low-rise village houses. Visual impacts mainly come from the construction and erection of high rise residential buildings within the existing secondary woodland area. During construction, works including clearance of vegetation and trees will degrade the visual quality. Night-time glare will also be considered. In operation, the erection of high-rise buildings will partially blocked the view towards the natural landscape from the backdrop. Due the limited visual extent being affected, the magnitude of change is considered to be intermediate.

 

VSR 31

Ho Hok Shan Facing Southwest

R5(EDA)/DO/LO/RSc/G/A

 

Partial

2804

Large

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

Facing the southwest, this VSR represents the high level areas of Ho Hok Shan in Au Tau, where a broad view to the proposed developments is possible. In the construction, works such as the demolition of existing buildings, clearance of vegetation and earthworks would not have significant visual impact due to the long distance. However, the erection of building structures and the ancillary structures, facilities on the site will be the significant sources of visual impact in operation. While the site will be replaced with urban landscape, the skyline linking the natural landscape and Yuen Long New Town would be affected.  Considering the long distance and blockage to the hillside from the backdrop, the magnitude of change is considered to be small during construction and operation stage.

VSR 32

Tong Yan San Tsuen

R5(EDA)/R5

 

Partial

0

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

Partial view to the natural landscape will be blocked by the Residential building proposed within the existing woodland area. Construction works mainly include site formation of the PRN, clearance of vegetation, breaking the hard surface as well demolition of ancillary structures, which would degrade the visual quality.  The erection of high-rise buildings will have more significant impacts on the view due to the close distance. The night-time glare will also be considered as the source of visual impact. During operation, the high-rise buildings of public housing or private housing will partially obstructed the natural view towards Tai Lam Country Park.

 

 

 

VSR 33

Tan Kwai Tsuen Road  near Open Storage

OU(OS)/OU(SU)2

Partial

391

Small

Fair

Good

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

View from this VSR is restricted by the exiting temporary structures and roadside plantings. From the ground level, the distance of view and blockage of existing buildings and structures will reduce the impact. However, from the elevated level, visual quality would be degraded due to the construction of open storage buildings which require the clearance of existing vegetation and trees near Tin Shui Wai West Interchange.  During operation, the erection of new development in Area 1 would block part of views towards the hillside area. Given that there are a long distance and limited views to PDA, the magnitude of change is considered to be small in construction and operation.

 

 

 

VSR 34

Tan Kwai Tsuen Road near Osmanthus Arnold Garden

OU(OS)

Partial

600

Small

Fair

Good

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

From the VSR, view is restricted by the low rise buildings and mature vegetation. During construction, works including clearance of vegetation and trees will degrade the visual quality. Control of night time lighting by shrouding all lights, using directional lights and through minimisation of night working periods will be considered. During Operation, major visual impact would generate by the erection of high rise buildings in Area 1, which would obstruct part of views towards natural hillside landscape in the backdrop. Due to the relatively long distance and limited visual angle to PDA, the magnitude of change is considered to be small in construction and operation.

VSR 35

Cheung Ngau Shan Facing Northwest

R5(EDA)/DO/ LO/RSc

Nil

1224

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Negligible

Negligible

Description of Impacts during Construction and Operation

Given the proposed developments will be compatible with the surroundings, also the road infrastructures will not be significant due to the blockage of existing vegetation, thus the magnitude of change is considered to be negligible during construction and operation stage.

VSR 36

Near Yuen Long Government Primary School

RSc / Proposed Road Infrastructures

 

Nil

440

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Negligible

Negligible

Description of Impacts during Construction and Operation

The proposed developments and road infrastructures will not be visible due to the blockage of the existing village buildings and the mature vegetation, the magnitude of change is considered to be negligible in both stage.

VSR 37

Pok Oi Hospital

Proposed Public Transport Interchange

Nil

235

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Negligible

Negligible

Description of Impacts during Construction and Operation

Similar as above. The proposed development and road infrastructures will not be visible due to the blockage of the mature vegetation and the viaduct of YLH, thus the magnitude of change is considered to be negligible in both stage.

 

VSR 38a

Yoho Town (Ground Level)

Proposed Public Transport Interchange/ Proposed Road Infrastructures

Partial

230

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

The elevated level from this VSR can provide a broad view to the YLH and other main road infrastructures. The main source of visual impact during the construction includes the road improvement works. Night time glare from construction facilities is also considered. During operation, trees and vegetation would become mature and form various green spaces along the roadside. Providing the visual extent and elements would be changed significantly. The magnitude of change is considered as large in construction and operation.

VSR 38b

Yoho Town (Upper Level)

Proposed Public Transport Interchange/ Proposed Road Infrastructures

Partial

230

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Large

Large

Description of Impacts during Construction and Operation

The elevated level from this VSR can provide a broad view to the YLH and other main road infrastructures. The main source of visual impact during the construction includes the road improvement works. Night time glare from construction facilities is also considered. During operation, trees and vegetation would become mature and form various green spaces along the roadside. Providing the visual extent and elements would be changed significantly. The magnitude of change is considered as large in construction and operation.

 

VSR 39

Yau Tin West Road near Hoover Garden

Proposed Road Infrastructures

Nil

270

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Negligible

Negligible

Description of Impacts during Construction and Operation

Given the blockage of the existing planation, the visual impacts produced by the Project would be insignificant. Therefore, the magnitude of change is considered to be negligible in construction and operation.

VSR 40

Intersection of Tai Tong Road

Proposed Road Infrastructures

Partial

487

Small

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Small

Small

Description of Impacts during Construction and Operation

Since only small scale of development will be visible in a distance, and the proposed road infrastructures will be compatible with the existing surroundings, the magnitude of change is considered to be small in construction and operation stage.

VSR 41

Tai Kei Leng Road

Proposed Road Infrastructures

Nil

253

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Negligible

Negligible

Description of Impacts during Construction and Operation

The proposed road infrastructures would not be significant due to the blockage of the roadside plantation. Therefore, the magnitude of change is considered to be negligible in construction and operation.

VSR 42

Tai Shu Ha Road East Facing Northwest

Proposed Road Infrastructures

Partial

153

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

View from this VSR is limited by the existing roadside planation. Construction work include the demolition of temporary structures, vegetation clearance as well as road improvement. Night time glare is considered as source of visual impact. Even though a more attracting streetscape can enhance the visual quality in operation, the scale and composition of visual elements would be changed significantly. Therefore, the magnitude of change is considered to be intermediate in operation and construction.

VSR 43

Hung Tin Road

Utilities Construction

Nil

0

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Negligible

Description of Impacts during Construction and Operation

The main source of visual impact during the construction includes site clearance, earthworks, movement of construction vehicles and temporary structures within the Project site. Night-time glare from construction facilities is also considered. Due to the significance of the construction activities, the magnitude of change is considered to be intermediate in the construction stage. In operation, as the utilities are installed underground, the change will be insignificant. Therefore, the magnitude of change is considered to be negligible in operation.

VSR 44

Shap Pat Heung Road near La Grove

Proposed Noise Enclosure

Partial

Medium

Fair

Fair

Temporary

Permanent

Reversible

Irreversible

Intermediate

Intermediate

Description of Impacts during Construction and Operation

The proposed noise enclosure would be the main source of visual impact. As the construction works include vegetation clearance and earthworks would degrade the existing visual quality.  Besides, the erection of noise enclosure would be significant in a short distance. Therefore, the magnitude of change is considered to be intermediate during construction and operation stage.

Remarks: The approximate closest viewing distance to the PDA is measured from the edge of the VSR group to the closest built structure proposed within the VE.

*Refer to code for Land Use Types in Section 10.8.2


10.10.9        Significance of Visual Impacts Before Mitigation

10.10.9.1        The potential significance of visual impacts during the construction and operational phases, before mitigation, is provided in Tables 10.10.7 below.  The assessment follows the methodology proposed in Section 10.4.5 and the matrix provided in Table 10.3.2.

Table 10.10.7 Significance of impacts on VSRs before mitigation

VSR Code

Name

VSR Sensitivity (High/ Medium/ Low)

Magnitude of Change (Large/ Intermediate/ Small/ Negligible

Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Con

Op

Con

Op

VSR 1

Yuen Long Park Tower

High

Large

Large

Substantial

Substantial

VSR 2

Fui Sha Wai South Road

Low

Intermediate

Intermediate

Moderate

Moderate

VSR 3

Tong Yan San Tsuen Track

Low

Intermediate

Intermediate

Moderate

Moderate

VSR 4

Fui Sha Wai

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR 5

Forefront Cyber Centre

Low

Intermediate

Small

Moderate

Slight

VSR 6

Jasper Court and Long Tin Road

Low

Small

Small

Slight

Slight

VSR 7

Parkside Villa

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR 8

Tong Yan San Tsuen Interchange

Low

Intermediate

Intermediate

Moderate

Moderate

VSR 9

Intersection of Kung Um Road and Shap Pat Heung Road

Low

Large

Large

Substantial

Moderate

VSR 10

Intersection of Lam Hei Rd and Kung Um Rd

Low

Intermediate

Small

Slight

Slight

VSR 11

Tin Liu Tsuen

Low

Intermediate

Intermediate

Moderate

Moderate

VSR 12

Chun Fai Garden

Low

Intermediate

Intermediate

Moderate

Moderate

VSR13

Pathway near Muk Kiu Tau Tsuen

Low

Large

Large

Moderate

Moderate

VSR14

Kiu Hing Road near Pak Sha Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR15

One Hyde Park Bus Station

Medium

Large

Large

Substantial

Substantial

VSR16

Channel Pathway on Kung Um Road

Low

Large

Large

Moderate

Moderate

VSR17

Pak Sha Tsuen Facing Southwest

High

Large

Large

Substantial

Substantial

VSR18

Tai Lam Mountain1 Facing Northeast

Medium

Large

Large

Substantial

Substantial

VSR19

Tai Lam Mountain2 Facing East

Medium

Large

Large

Substantial

Substantial

VSR20

Tai Lam Mountain3 Facing Southeast

Medium

Large

Large

Substantial

Substantial

VSR21

Tai Lam Mountain4 Facing Northeast

Medium

Large

Large

Substantial

Substantial

VSR22

Tai Lam Mountain5 Facing Northeast

Medium

Large

Large

Substantial

Substantial

VSR23

Tai Lam Mountain6 Facing North

Medium

Large

Large

Substantial

Substantial

VSR24

Tai Lam Mountain7 Facing Northeast

Medium

Large

Large

Substantial

Substantial

VSR25

Tai Lam Mountain 8 Facing Northeast

Medium

Large

Large

Substantial

Substantial

VSR26

 

 

 

 

 

Access Road off Tai Tong Shan Road

Low

Small

Small

Slight

Slight

VSR27

Shui Tsiu San Tsuen Road near Wong Nai Tun Tsuen

Medium

Small

Small

Moderate

Slight

VSR28

Shui Tsiu San Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR29

Sham Chung Tsuen

High

Large

Large

Substantial

Substantial

VSR30

Shan Ha Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR31

Ho Hok Shan 1 and Facing Southwest

Medium

Small

Small

Slight

Slight

VSR32

Tong Yan San Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR33

Tan Kwai Tsuen Road near Open Storage

Low

Small

Small

Slight

Slight

VSR34

Tan Kwai Tsuen Road near Osmanthus Arnold Garden

High

Small

Small

Moderate

Moderate

VSR35

Cheung Ngau Shan and Facing Northwest

Medium

Negligible

Negligible

Insignificant

Insignificant

VSR36

Near Yuen Long Government Primary School

Medium

Negligible

Negligible

Insignificant

Insignificant

VSR37

Pok Oi Hospital

Medium

Negligible

Negligible

Insignificant

Insignificant

VSR38a

Yoho Town (Ground Level)

Low

Large

Large

Moderate

Moderate

VSR38b

Yoho Town (Upper Level)

High

Large

Large

Substantial

Substantial

VSR39

Yau Tin West Road near Hoover Garden

Medium

Negligible

Negligible

Insignificant

Insignificant

VSR40

Intersection of Tai Tong Road

Low

Small

Small

Slight

Slight

VSR41

Tai Kei Leng Road

Low

Negligible

Negligible

Insignificant

Insignificant

VSR42

Tai Shu Ha Road East Facing Northwest

Medium

Intermediate

Intermediate

Moderate

Moderate

VSR43

Hung Tin Road

Low

Intermediate

Negligible

Moderate

Insignificant

VSR44

Shap Pat Heung Road near La Grove

Low

Intermediate

Intermediate

Moderate

Moderate

10.10.9.2        Proposal to construct additional sewage alignment connecting YLS to the existing inert chamber of the NWNT effluent tunnel at San Tai for discharging to Urmston Road submarine outfall would require breaking hard surface and earthworks. Since this utility is constructed underground, with the blockage of roadside plantation, the magnitude change of view would be small, only slight visual impact would be anticipated during construction and no adverse impact during operation.


 

10.11                 Minimisation of Landscape and Visual Impact

10.11.1        Avoidance of Potential Impacts

10.11.1.1        At the Project planning stage, many factors have been considered in the RODP to avoid, reduce and/ or help compensate for the potential landscape and visual impacts of the DPs, with highest priority given to avoidance of impacts.

Preservation of Areas with High Landscape Value

10.11.1.2        The woodland with landscape value, “GB” and “Conservation Area” (“CA”) in the foothill areas, Tai Lam Country Park, and the ecologically important features including the watercourses of higher ecological value and egretries are areas of conservation importance within the assessment area. These natural landscapes possess value which should be well protected and preserved, avoiding any negative impacts arising from the proposed developments. The RODP has preserved approx. 4.8ha of secondary woodland and about 2,060m of watercourses of higher ecological value in the PDA.

10.11.2        Enhancement in Landscape and Visual Aspect

Creating Open Space and Green Network

10.11.2.1        The landscape network reflects the rural history of the area and creates a new focal point by connecting the residential communities of which will, in effect, enhance the existing rural character context of the region and provide a focal point connecting the residential communities of the PDA. Additionally, a buffer is proposed between the existing low-rise villages and the new high-rise public and private developments to address grave concerns on the local villages on the possible wall effect. This buffer consists of a 20m green strip, zoned as “Local Open Space” (“LO”) and a 10m low building area (LBA) along the development lots.

Revitalisation of Nullahs

10.11.2.2        In line with the recent advocate of integrated green infrastructure system and aspiration to improve aesthetics and ecological value of the land, a green and eco-hydraulics approach will be applied. A key consideration is to improve aesthetic whilst maintain and compensate for the hydraulic performance of about 2.5km of Yuen Long Nullah along Kung Um Road / Kiu Hing Road. Some of green and eco-hydraulics approaches are considered are:

·                  Using grasscreting and extensive vegetation embankment, e.g. Nullahs in Jordan Valley and Tsui Ping;

·                  Using gabions and geo-fabric reinforced grass lining, e.g. Yuen Long Bypass Floodway;

·                  Using unlined channel beds such as rip-rap base and retaining meanders, e.g. Kam Tin River, Shan Pui River & Ng Tung River; and

·                  Creating shallow ponds, wetland habitats and reed beds, e.g. Yuen Long Bypass Floodway & San Tin.

Reedbed Enhancemnt Opportunities

10.11.2.3        A reedbed with an area of about 4ha is proposed to be built at the south of Area 3. Such a treatment system can provide dual roles i.e. as a clean-up reedbed and providing significant ecological and landscape enhancement to the area. Further development and design of the reedbed at a later stage will be required to optimise clean-up capabilities and also provision of ecological function.

Building Height Respecting the Surroundings to Keep View Corridors

10.11.2.4        Through the tapering of development intensities and building heights, YLS will integrate with its settings by high density developments in the north near Yuen Long New Town and transitioning to medium and low-density development in the south to blend in with the rural setting and the Tai Lam Country Park.

10.11.2.5        The key viewing platforms from the Yuen Long Park Aviary Pagoda to the north of YLS has been incorporated in the urban design framework as the key view corridor. The gradation of development intensity and building heights from north to south optimizes views to the mountainous backdrop of the Tai Lam Country Park.

General Planting Design Principle

10.11.2.6        Corresponding to the landscape and environment improvement framework and the understanding of the open spaces and greening networks in YLS, the spatial design component in YLS has been divided into six categories, namely Open Space & Primary Amenity Areas, Greenbelt & Secondary Amenity Areas, Residential Areas, Roadside & Major Corridors, Scenic Routes and Reedbed/ Retention Ponds. Figure 10.12 refers.

·                  Open Space & Primary Amenity Areas: Includes all the proposed new or renovated green spaces within the Study Area, generally referred to as Public Parks. Integrated with the comprehensive recreational facilities, each public park adopts a set of general principles and is further customized to fit in its context and meet its purpose.

·                  Greenbelt & Secondary Amenity Areas: As their nature is rather different from the general planting spaces, thus it treated as separate category. Two main typologies are identified; (a) Conservation Woodland which located within the proposed development and (b) Green Buffers between the proposed buildings and Country Park.

·                  Residential Areas: Includes all the proposed new local open space within the Study Area, generally referred to as Small Community Parks within residential development.

·                  Roadside & Major Corridors: Includes all roads and streets within the Study Area and is comprised out of the following types; (a) Major Traffic Corridor, (b) Major Pedestrian Corridor, (c) Neighbourhood Connection; Primary & Secondary Streets.

·                  Scenic Routes: This category is comprised with inlier recreational space, including hillside river corridor and scenic cycling tracks.

·                  Reedbed/ Retention Ponds: This category works as an enhancement measure to support breeding nearby birds. Planting of stands of bamboo and sizeable trees as potential nesting substrates are proposed around Reedbed and Retention Ponds.

10.11.2.7        The above categories will act as the basis for the formulation of urban planning and landscape design guidelines as a manual in defining the basic design elements (i.e. parklands and streetscapes) in YLS, and to enhance the planting design.

10.11.2.8        As mentioned above, the proposed improvement schemes comprises new planting space to visually soften the surrounding environment, referring to the six categories spatial system as above, thematic planting has been carried out and implemented into the greening proposal as part of the mitigation measures for both landscape and visual aspects, species proposed for the Study Area are chosen regarding to their ecological function for the biodiversity maintenance within project sites, and their attractive foliage, lush colours, and varied shapes in order to create an impressive visual impact.

10.11.2.9        Sample plant materials and criteria is provided as follows:

Table 10.11.1.  Tree Selection Criteria with Examples

Spatial Categories

Proposed Species*

Flowering Colour

Criteria

Botanical Name

Chinese Name

Open Space & Primary Amenity Areas:

Bischofia Javanica

秋楓

Green

·       Non-poisonous and non-thorny

·       Non aggressive root-systems to minimise impact on adjacent paving

·       Bird, Bat and Butterfly attracting species

·       Colorful flowering species

·       Varying tree canopy levels

Sterculia lanceolata 

Pink

Magnolia grandiflora

荷花玉蘭

White

Morus alba

白蘭

White

Greenbelt & Secondary Amenity Areas

Liquidambar formosana

楓香

Green

·       Low-maintenance species

·       Shade-tolerant species

·       Seasonal variety to allow year-round attractiveness

·       The species selected is complementary with the existing vegetation

Bridelia tomentosa

土蜜樹

Yellow

Morus alba

白蘭

White

Ailanthus fordii

福氏臭樁

Yellow

Residential Areas

Sterculia lanceolata 

Pink

·       Non aggressive root-systems to minimise impact on adjacent paving

·       Relatively high shading capacity (non-continuous)

·       Varying color and tree canopy level

·       Extensive maintenance

Hibiscus tiliaceus

黄槿

Bright Yellow

Bauhinia variegata

宮粉羊蹄甲

Lavender and Pink

Peltophorum pterocarpum

盾柱木

Yellow

Roadside & Major Corridors

Melaleuca leucadendron

白千層

Brush White

·       Continuous tree canopy providing shade for footpaths and roads

·       Evergreen trees with minimal loss of flowers or seedpods to avoid drainage cluttering

·       Pollution tolerant species

·       Sufficient crown height and

·       Long-living tree species

Cinnamomum burmannii

陰香

White and Yellow

Chukrasia tabularis

Green

Terminalia mantaly

細葉

Green

Scenic Routes

Koelreuteria bipinnata

羽葉欒樹

Yellow and Seeds Red

·       Season specific features, with flowering/color change in late spring and autumn

·       Bird, Bat and Butterfly attracting species

·       Non-poisonous and non-thorny

·       Relatively high shading capacity (non-continuous)

Tabebuia impetiginosa

紫花風鈴木

Pink

Bombax malabaricum

木棉

Orange/ Red

Liquidambar formosana

楓香

Inconspicuous (leaves turn red in Autumn)

Spathodea campanulata

火焰木

Bright Orange/ Red

Reedbed/ Retention Ponds

Ficus Microcarpa

榕樹

Inconspicious

·       Suitable breeding ground for nearby Egrets

·       Water-tolerant species

·       Attract birds

Celtis Sinensis

Inconspicious

Lagerstroemia speciosa

大花紫薇

Purple/ Pink

Hibiscus tiliaceus

槿

Bright Yellow

Note: [*] = The proposed list of planting species are not definitive and subject to change in the later detailed design stage; The proposed species will follow the principles of ‘Right Tree, Right Place’ in accordance with GLTM, DEVB, ‘Handbook on Tree Management’, April 2016.

10.12              Landscape and Visual Mitigation Measures for Construction and Operation

10.12.1.1        The proposed mitigation measures for the Project are described in the following section and summarised in Table 10.12.1 below. The construction measures focus on the methods of preservation or minimisation of potential impacts from working extent, which effectiveness will take effect during the construction stage. Compensatory measures (OM1 and OM2) and soft landscape mitigation measures (OM4 and OM5) will be considered during detailed design, most likely be implemented during construction, and their full effect are often appreciated by the year 10 of operation. Equally, detailed design measures (OM6, OM7 and OM8) such as design of buildings and structures will also take effect during operational stage. Considering their effectiveness period is operational stage, these measures are classified as operation measures.

10.12.1.2        Table 10.12.2 lists the agents responsible for the capital funding, the implementation and the maintenance of the suggested measures. 

Table 10.12.1   Mitigation Measures for Construction and Operation Phase

Mitigation Measure Code

Summary Description

Mitigate Landscape Impacts

Mitigate Visual Impacts

Construction Phase

CM1

Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction

CM2

Minimise Topographical Changes

CM3

Tree Protection and Preservation

 

CM4

Transplanting of Existing Trees

 

CM5

Screen Hording

 

CM6

Watercourses of higher ecological value/ Channels Protection

 

CM7

Construction Light Control

 

CM8

Woodland Conservation

 

Operational Phase

OM1

Compensatory Planting

 

OM2

Woodland Compensation

 

OM3

Operation Light Control

 

OM4

Screen Planting

OM5

Road Side Planting

OM6

Aesthetic Design of Built Development

 

OM7

Maximise Greening on Engineering Structures and Surfaces

OM8

Noise Barrier Design

 

OM9

Man-made Channel Improvements

OM10

Slope Landscaping

 

Table 10.12.2  Responsibility Matrix

Mitigation Measure Code

Summary Description

Capital Funding Agency

Implementation Agency**

Post-Construction Management Agency*

Post-Construction Maintenance Agency*

CM1

Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction

CEDD

CEDD (via Contractor)

N/A

N/A

CM2

Minimise Topographical Changes

CEDD

CEDD (via Contractor)

N/A

N/A

CM3

Tree Protection and Preservation

CEDD

CEDD (via Contractor)

N/A

N/A

CM4

Transplanting of Existing Trees

CEDD

CEDD (via Contractor)

N/A

N/A

CM5

Screen Hoarding

CEDD

CEDD (via Contractor)

N/A

N/A

CM6

Watercourses of higher ecological value/ Channels Protection

CEDD

CEDD (via Contractor)

N/A

N/A

CM7

Construction Light Control

CEDD

CEDD (via Contractor)

N/A

N/A

CM8

Woodland Conservation

CEDD

CEDD (via Contractor)

N/A

N/A

OM1

Compensatory Planting

CEDD

CEDD (via Contractor)

LCSD

LCSD

OM2

Woodland Compensation

CEDD

CEDD/ AFCD

AFCD

AFCD

OM3

Operation Light Control

ArchSD/ Housing Department/ Private Sector

ArchSD/ Housing Department/ Private Sector

ArchSD/ Housing Department/ Private Sector

ArchSD/ Housing Department/ Private Sector

OM4

Screen Planting

CEDD

CEDD (via Contractor)

HyD/ LCSD

HyD/ LCSD

OM5

Road Side Planting

CEDD

CEDD (via Contractor)

HyD (within boundary of expressways)/ LCSD (along non-expressways public roads outside country park)

HyD (within boundary of expressways)/ LCSD (along non-expressways public roads outside country park)

OM6

Aesthetic Design of Built Development

ArchSD/ Housing Department/ Private Sector

ArchSD/ Housing Department/ Private Sector

ArchSD/ Housing Department/ Private Sector

ArchSD/ Housing Department/ Private Sector

OM7

Maximise Greening on Engineering Structures and Surfaces

 

Initiating Government Department (relevant user department)/ Private Sector

Initiating Government Department (relevant user department)/ Private Sector

Initiating Government Department (relevant user department)/ Private Sector

Initiating Government Department (relevant user department)/ Private Sector

OM8

Noise Barrier Design

CEDD

CEDD (via Contractor)

HyD

HyD

OM9

Man-made Channel Improvements

CEDD

DSD

DSD

DSD

OM10

Slope Landscaping

CEDD

CEDD (via Contractor)

HyD/ LCSD/ LandsD

HyD/ LCSD/ LandsD

Note: {*} Management and Maintenance Agencies are identified as per DEVB TCW No. 6/2015. Agreement from individual agent shall be    sought at the detailed design stage before commencement of the contract.

          {**} CEDD will only be responsible for construction of the site formation and essential infrastructure

Note: The Contractor shall be responsible for the maintenance of the landscape works during the establishment period at operation phase. The Project Proponent shall then be responsible for the management and maintenance of the implemented Landscape Mitigation Measures until such time those are successfully handed over to the designated agent/department.

10.12.1.3        Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1) - Construction areas’ control shall be enforced, where possible, to ensure that the landscape and visual impacts arising from the construction activities are minimised.  It includes reduction of the extent of working areas and temporary works areas, management on storing and using the construction equipment and materials, and consideration of detailed schedules to shorten the construction period. Temporary landscape treatments are considered to be adopted such as applying hydro-seeding on temporary stockpiles and reclamation areas to alleviate the potential impacts.

10.12.1.4        Minimise Topographical Changes (CM2) - To minimise landscape and visual impacts, the vertical and horizontal alignment of the at-grade road construction works should be optimised to reduce topographical/ landform changes, as well as reduce land take and interference with natural terrain and reduce overall earth movements. Where there is a need to significantly cut into the existing landform, retaining walls should be considered as well as cut slopes, to minimise landform changes and land resumption, whilst also considering visual amenity. Earthworks and engineered slopes should be designed to provide a structurally stable and visually interesting landform, which is compatible with surrounding landscape and mimics the natural contouring and terrain (e.g. introduction and continuation of natural features such as spurs and ridges where appropriate) to support landscape and visual assimilation with the surrounding terrain.

10.12.1.5        Tree Protection & Preservation (CM3) - Existing trees to be retained within the Project Site should be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas.

10.12.1.6        A detailed tree survey will be carried out for the Tree Removal Application (TRA) process which will be carried out at the later detailed design stage of the Project.  The detailed tree survey will propose which trees should be retained, transplanted or felled and will include details of tree protection measures for those trees to be retained.

10.12.1.7        Transplanting of Existing Trees (CM4) - Trees unavoidably affected by the Project works should be transplanted where practical. Trees should be transplanted straight to their final receptor site and not held in a temporary nursery as far as possible.

10.12.1.8        A detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with DEVB TCW No.6/2015 and DEVB TCW 7/2015 and final locations of transplanted trees should be agreed prior to commencement of the work. 

10.12.1.9        For trees associated with highways e.g. roadside planting along highways, that are unavoidably affected and should be transplanted, following HyD Guidelines  HQ/GN/13 ‘Interim Guidelines for Tree Transplanting Works under Highways Department's Vegetation Maintenance Ambit’.

10.12.1.10    Screen Hoarding (CM5) - Screen hoarding shall be erected along areas of the construction boundary where the works site borders with publicly accessible routes and/or is close to visually sensitive receivers (VSRs), to screen undesirable views of the works site. It is proposed that the screening be compatible with the surrounding environment in terms of material choice and colour. 

10.12.1.11    Watercourses of higher ecological value/ Channels Protection (CM6) - For all the watercourses of higher ecological value inside the development area, in accordance with ETWB TCW 5/2005, consideration of protection measures should be made to minimise any impacts from the construction works. Precast structures or other similar approaches will be used to prevent any construction works in river and thus to avoid any direct water quality impact. Good site management as stipulated in ProPECC PN1/94 will be fully implemented to avoid polluted liquid or solid wastes from falling into the river waters.

10.12.1.12    Construction Light Control (CM7) - All security floodlights for construction sites should be carefully controlled to minimise light pollution and night-time glare to nearby users.

10.12.1.13    Woodland Conservation (CM8) - Woodland conservation is proposed to avoid large scale of potential loss of the existing secondary woodland within the PDA.

10.12.1.14    Compensatory Planting (OM1) - Compensatory tree planting for felled trees shall be provided to the satisfaction of relevant Government departments. The required numbers and locations of compensatory trees shall be determined and agreed separately with Government during the Tree Removal Application process under DEVB TCW No.7/2015.  Compensatory planting is proposed at the potential open areas such as open spaces, amenity areas, open areas of the streetscapes, as well as the open areas within development lots.  The provision of space for compensatory planting takes into accounts the subsequent schedules.

10.12.1.15    The location of compensatory planting includes the roadside areas, street tree planting, central medians and any soft landscape areas affected by the works area. 

10.12.1.16    Woodland Compensation (OM2) - Specific Woodland compensatory planting is proposed for any areas of woodland that are unavoidably affected. The compensatory woodland planting will principally be within the LRs of lower value such as (LR3 Hillside Shrubland and Grassland), where integrity of the wider woodland resource is possible. Plant species should be selected to include a mix of species with pioneering characteristics (fast-growing/ light-tolerant/ drought-tolerant/ wind-tolerant, etc.) and native species and complementary species to the local area. The list of recommended species for the proposed woodland compensation planting are displayed in Table 8.68 in Chapter 8 of Ecological Impact. Given the limited space within the Draft RODP, on site woodland compensation is considered not practicable. The location for off-site woodland compensation has been shown in Figure 10.9.

10.12.1.17    This provision would take some time for the compensatory planting to achieve the landscape and ecological function and value of the area to be lost. In addition, it allows for the fact that not all of the areas identified for planting will be viable, by virtue of topography and ground conditions and, especially the areas, because though the areas identified are largely grassland it is inevitable that these areas will already support some patches of trees and shrubs which would be inappropriate for further planting. The intention of the compensatory woodland will be to recreate areas of quality woodland, not necessarily to compensate for loss of trees on a like for like basis. 

10.12.1.18    Operation Light Control (OM3) – Night time lighting should be controlled during operation to minimise glare and light spill from the potential development/ infrastructure. Street and night time lighting shall also be controlled to minimise glare impact to adjacent VSRs during the operation phase.

10.12.1.19    Screen Planting (OM4) - Tall screen/buffer trees and shrubs should be planted to assist in screening proposed road corridors and associated above ground structures such as elevated road sections and engineered embankments. This measure may additionally form part of the compensatory planting and will improve compatibility with the surrounding environment and create a pleasant pedestrian environment.

10.12.1.20    Road Side Planting (OM5) - For LRs that would require road upgrading or realignment should be provided to soften the hard, straight edges, such as (LR7), (LR8) and the new roads within PDA. Shade tolerant plants should be planted, where light is insufficient, to improve aesthetic value of areas under viaducts.  The guideline of DEVB TC(W) No.2/2012 – Allocation of Space for Quality Greening on Roads should be followed.

10.12.1.21    Aesthetic Design of Built Development (OM6) - Compatible design, construction materials and surface finishes of the proposed structure should match with the nearby existing external appearance of the proposed buildings for achieving visual uniformity. Finishing materials shall have due consideration to form, light earthy tone colours treatments, micro- and macro-texture, and reflectivity/ light absorbance to avoid glare.

10.12.1.22    Maximise Greening on Engineering Structures and Surfaces (OM7) - Where space and appropriate planting conditions allow (i.e. where suitable depth of planting medium is possible, maintenance access available and enough light penetration to ground level), climbing plants should be considered to grow up vertical surfaces such as greening facade of building blocks, viaduct piers or noise barriers.

10.12.1.23    The planting once established will assist in breaking up the appearance of uniform engineered structures and surfaces. Tree planting and care that integrate with wider streetscape elements such as hardscape paving, outdoor furniture as well as lighting poles should be considered to create a pedestrian-friendly network.  Streetscape design, including integrity with the building space at ground floor, keeping a suitable distance between trees and buildings should follow the Greening, Landscape and Tree Management Section (GLTM) of the Development Bureau's Guidelines on Greening of Noise Barriers (April 2012). 

10.12.1.24    At-grade road planting should be considered along central median planters and on the road island (Roadside planting is considered part of OM5), DEVB TC(W) No.2/2012 should be referred to. Furthermore, HQ/GN/15 - Guidelines for Greening Works along Highways should be referred to for greening of highways specifically, DEVB TCW No. 2/2013 - Greening on Footbridges and Flyovers for footbridges and flyovers. The above mitigation measures would only be implemented for public developments/projects.

10.12.1.25    Noise Barrier Design (OM8) - The visual impact of noise mitigation measures will be mitigated by appropriate detailed design to reduce visual bulkiness and incorporate aesthetically pleasing surface treatments to promote visual amenity, including suitable combination of transparent and sound absorbent materials, appropriate colour selection of panels and supporting structures, or provision of at-grade planting of trees, shrubs and/or climbers camouflage to the barriers, as well as design of supporting structures to incorporate a high level of quality and aesthetics. A combination of transparent panels at top and solid panels at bottom would lighten the visual impact, and at the same time maintain the attractiveness by using colourful panels. (Noise barrier design has been included in Appendix 10.3 for the section of enclosures noise barrier design, Figure 10.14e to 10.14f and Figure 10.14s to 10.14t for the photomontage of selected VSRs and Figure 10.16 for the reference images of noise barrier design.) The noise barriers would be implemented for District Distributor Roads and Local Distributor Roads. Relevant technical documents DEVB (GLTM) No. 2/2012 - Allocation of Space for Quality Greening on Roads, DEVB (GLTM) No. 3/2012 – Site Coverage of Greenery for Government Building Projects, and Guidelines on Design of Noise Barriers by HyD and EPD in 2003 shall be reference.

10.12.1.26    Man-made Channel Improvements (OM9) - Artificial and man-made watercourse channels within the site will be affected by the works; whilst these are considered to have a low current value there is an opportunity to better integrate these features in to the urban and landscape design.  Proposals to integrate these features in to public areas can include creating more natural watercourse with soft banks and ornamental ponds would generate positive impacts.

10.12.1.27    Slope Landscaping (OM10) - Site formation has been reduced as far as possible to avoid substantial slope cutting. Hydroseeding of modified slopes should be done as soon as grading works are completed to prevent erosion and subsequent loss of landscape resources and character. Complementary woodland tree seedlings and/ or shrubs should be planted where the slope gradient and site conditions allow.  In addition, landscape planting should be provided for the retaining structures associated with modified slopes, where conditions allow.  All slope landscaping works should comply with GEO Publication No. 1/2011-Technical Guidelines on Landscape Treatment for Slopes.  In summary, it is considered that these measures implemented during construction and operational phases will assist in avoiding potential adverse impacts in relation to LRs, LCAs and VSRs.

10.13              Residual Impacts upon Mitigation

10.13.1        Residual Landscape Impacts

10.13.1.1        The proposed landscape and visual mitigation measures, as described in Section 10.12 have been applied to the various impacts and used to identify potential residual impacts. 

10.13.1.2        The potential significance of residual landscape impacts during the construction and operational phases, before and after mitigation at day 1 and year 10, are provided in Tables 10.13.1 and 10.13.2.  The tables assume that the appropriate mitigation measures have been applied and that the full effect of the soft landscape mitigation measures would be fully realised and established after 10 years. As stated in Section 10.6, the Day 1 of Operation for the Project will start at the year of first population intake for each development stage, and the Year 10 of operation are defined 10 years later after that time.

10.13.1.3        Where insignificant impacts have been identified prior to mitigation, mitigation measures are still shown in the table as these would be applied as best practice in the construction and operational stages as part of a consistent design and construction approach.

 


Table 10.13.1  Residual Landscape Impact on Implementation of Mitigation Measures for LCAs

LCA Code

Name

Sensitivity (High/ Medium/ Low)

 

Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Recommended Mitigation Measures (MM)

Residual Impact Significance UPON Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Construction

Operation

Construction

Operation

Construction

Operation

Day 1

Operation

Year 10

LCA1a

Miscellaneous Rural Fringe Landscape – Open Storage/ Rural Built Area

Low

Moderate

Moderate

CM1, CM2, CM3, CM4, CM6, CM8

OM1, OM2, OM4, OM5, OM9, OM10

Moderate

Moderate

Slight

LCA1b

Miscellaneous Rural Fringe Landscape – Lowland Agricultural Land

Medium

Moderate

Moderate

CM1, CM3, CM4

OM1, OM4, OM5

Moderate

Moderate

Slight

LCA2

Miscellaneous Urban Fringe Landscape

Low

Slight

Slight

CM1, CM2, CM3, CM4

OM1, OM4, OM5, OM10

Slight

Insignificant

Insignificant

LCA3

Upland and Hillside Landscape

High

Moderate

Moderate

CM1, CM2, CM3, CM4, CM8

OM1, OM2, OM4, OM5, OM10

Moderate

Moderate

Slight

LCA7

Urban Peripheral Village Landscape

Medium

Small

Small

CM1, CM3, CM4, CM8

OM1, OM2, OM4, OM5

Slight

Slight

Slight

LCA8

Transportation Corridor Landscape

Low

Moderate

Slight

CM1, CM2, CM3, CM4

OM1, OM4, OM5, OM10

Slight

Insignificant

Insignificant

Note:        The LCA not affected by the Project is not shown in the above table


 

Table 10.13.2  Residual Landscape Impact on Implementation of Mitigation Measures for LRs

LR Code

Name

Sensitivity (High/ Medium/ Low)

 

Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Recommended Mitigation Measures (MM)

Residual Impact Significance UPON Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Construction

Operation

Construction

Operation

Construction

Operation

Day 1

Operation

Year 10

LR1a

Active Agricultural Land

High

Moderate

Moderate

CM1, CM3, CM4

OM1, OM4, OM5

Moderate

Moderate

Moderate

LR1b

Abandoned Agricultural Land

Medium

Slight

Slight

CM1, CM3, CM4

OM1, OM4, OM5

Slight

Slight

Slight

LR1c

Orchard

High

Moderate

Moderate

CM1, CM3, CM4, CM8

OM1, OM2, OM4, OM5, OM10

Moderate

Slight

Slight

LR2

Lowland Mixed Trees, Shrubland and Grassland

Medium

Moderate

Moderate

CM1, CM3, CM4, CM8

OM1, OM4, OM5, OM10

Moderate

Moderate

Slight

LR3

Hillside Shrubland and Grassland

Medium

Slight

Slight

CM1, CM2, CM3, CM4, CM6

OM1, OM4, OM5, OM10

Slight

Slight

Slight

LR4

Secondary Woodland

High

Moderate

Moderate

CM1, CM2, CM3, CM4, CM6, CM8

OM1, OM2, OM4, OM5, OM10

Moderate

Moderate

Slight

LR5

Plantation

Medium

Moderate

Moderate

CM1, CM2, CM3, CM4, CM8

OM1, OM2, OM4,  OM5, OM10

Moderate

Moderate

Slight

LR6

Urban Park

Medium

Insignificant

Insignificant

N/A

N/A

Insignificant

Insignificant

Insignificant

LR7

Road and Urban Infrastructure

Medium

Moderate

Slight

CM1, CM4

OM1, OM4, OM5, OM6, OM7, OM10

Slight

Slight

Insignificant

LR9

Urbanised Development

Low

Slight

Slight

CM1, CM3, CM4

OM1, OM4, OM5, OM6, OM7, OM10

Slight

Slight

Insignificant

LR10

Village Type Development

Medium

Slight

Slight

CM1, CM3, CM4

OM1, OM4, OM5, OM6, OM7, OM10

Slight

Slight

Slight

LR11

Open Storage/Rural Built Area

Medium

Substantial

Substantial

CM1, CM2, CM3, CM4

OM1, OM4, OM5, OM6, OM7, OM10

Substantial

Moderate

Moderate

LR12

Disturbed Area

Low

Slight

Slight

CM1, CM3, CM4

OM1, OM4,  OM5

Slight

Insignificant

Insignificant

LR13

Agricultural  Pond

Medium

Moderate

Moderate

CM1, CM6

OM1

Moderate

Moderate

Slight

LR14

Channelised Watercourse

Low

Moderate

Slight

CM1, CM2

OM5, OM9, OM10

Moderate

Slight

Slight

LR15

Watercourses of higher ecological value

High

Moderate

Moderate

CM1, CM6

N/A

Moderate

Moderate

Moderate

Note:        The LR not affected by the Project is not shown in the above tab

 



10.13.2        Residual Visual Impacts

10.13.2.1        The proposed landscape and visual mitigation measures, as described in Section 10.12, have been applied to the various impacts and used to identify potential residual impacts. 

10.13.2.2        The potential significance of residual visual impacts during the construction and operational phases, before and after mitigation at day 1 and year 10, are provided in Tables 10.13.3.  The tables assume that the appropriate mitigation measures have been applied and that the full effect of the soft landscape mitigation measures would be fully realised and established after 10 years. 

10.13.3        Photomontages

10.13.3.1        This EIA Study is an investigation to examine the future land use, optimise the development potential impacts and ascertain the feasibility for public and private housing development in the YLS PDA. However, the current building layouts are considered to be a conceptual design based on the strategic urban planning proposal. Therefore, it should be noted that the photomontages intend to demonstrate only the scale and massing of the proposed development and effect of the proposed mitigation measures. The architectural design, finishes or any other related detailed design components are subject to refinement and changes at the detailed design stage. Thus, the photomontage(s) for Year 10 scenario cannot illustrate effectively the visual outlook of such scenario.

10.13.3.2        And hence, the photomontages have been used to assess the effectiveness of the various landscape and visual mitigation measures described from the previous sections, a series of images are prepared showing the existing conditions, the development without mitigation upon completion, with mitigation upon completion and after 10 years of operation. The location of the selected VSRs for photomontage has been demonstrated in Figure 10.10.


10.13.4        The Selection of Views for Photomontages

10.13.4.1         Refer to Figure 10.14a to 10.14r, VSR1, VSR5, VSR13, VSR15, VSR16, VSR18, VSR23, VSR29, VSR31 and VSR 44 are intended to demonstrate the range of anticipated visual impacts from different locations throughout the VE. These views accurately reflect potential local concerns, and these visual receptors could potentially have views (short to long distances) of some or all of the proposed development. Specific considerations on each VSR are described below:

§  VSR1 represents the recreational users from the north, and with a broad viewing angle to the development site. Regarding to its high sensitivity, it is necessary to provide demonstration to the visual changes;

§  VSR5 represents the views from the north-west, and with similar viewing angles and viewing distance with VSR3 and VSR4;

§  VSR13 represents the residential users from the villages nearby, viewing towards the nullah which is proposed to be modified under the future development, it is predicted to have a similar magnitude of visual changes as VSR11 and VSR12;

§  VSR15 is similar as above, it is predicted to have a similar magnitude of visual changes as VSR14 and VSR17;

§  VSR16 represents a close distance view from the south towards the development site;

§  VSR18 represents a medium distance elevated view from the south towards the Proposed Service Reservoir, and with similar viewing angles and viewing distance with VSR25;

§  VSR23 represents a medium distance elevated view from the south towards the development site, and with similar viewing angles and viewing distance with VSR21, VSR22 and VSR24;

§  VSR29 represents the residential users from the villages nearby, viewing towards the proposed high-rise development in a short distance. Regarding to its high sensitivity, it is necessary to provide demonstration to the visual changes;

§  VSR31 represents a long distance elevated view from the east towards the development site, and with similar viewing distance with VSR35; and

§  VSR44 represents a close distance view from the north towards the noise enclosure.

 

 


Table 10.13.3  Significance of visual impacts

VSR Code

Name

Sensitivity (High/ Medium/ Low)

Magnitude of Change (Large/ Intermediate/ Small/ Negligible)

Impact Significance Before Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Recommended Mitigation Measures

Residual Impact Significance UPON Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

CON

OP

CON

OP

CON

OP

CON

OP Day 1

OP Year 10

VSR1

Yuen Long Park Tower

High

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6,

Moderate

Moderate

Moderate

Description:

During the construction stage, the ancillary structures such as site offices, construction facilities, and erection of structures as well as loss of trees would generate substantial impacts on this VSR. However, with mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction, the adverse impacts from the construction works can be reduced to a lower level. Refer to Figure 10.14b, although the change of this visual character cannot be completely mitigated, the proposed high-rise developments will be compatible with the existing surroundings during the operational stage, also with the implementation of mitigation measure such as Aesthetic Design of Built Development (OM6), the use of light earthy tone colours with the buildings will help to reduce the visibility of the development components, therefore the adverse impacts can be reduced to moderate level eventually. However, given the large scale of the Project, the change of the visual character would be inevitably large, therefore the visual impact cannot be completely mitigated, the residual impact will stay at moderate level at Year 10 of operation stage.

 

 

VSR2

Fui Sha Wai South Road

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM6,

Slight

Slight

Slight

Description:

Given the blockage of the existing vegetation, the proposed low-rise storage site will not be significant, therefore the residual impact would reduce to slight level during construction and operation stage.

 

 

 

 

VSR3

Tong Yan San Tsuen Track

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM6

Moderate

Moderate

Slight

Description:

As the change of the existing visual character would be large, the proposed mitigation measures may not be able to alleviate the impact, therefore the residual impact during construction will remain at moderate level. However, the proposed low-rise storage development will not be visible due to the blockage of existing mature vegetation, therefore the residual impacts will reduce as slight at operation stage in Year 10.

 

 

 

VSR4

Fui Sha Wai

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM6

Moderate

Moderate

Moderate

Description:

Since the existing low-rise residential area will change to an industrial development site, the proposed mitigation measures may not be able to fully alleviate the impact, therefore the residual impact will remain at moderate level during construction and operation phase.

 

 

VSR5

Forefront Cyber Centre

Low

Intermediate

Small

Moderate

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7

Moderate

Slight

Slight

Description:

During the construction stage, the demolition of structures, vegetation removal and erection of building structures would generate moderate impact, the proposed mitigation measures may not be able to alleviate the impact, therefore the residual impact during construction will remain at moderate level. Refer to Figure 10.14d, since the proposed developments would preserve views to the mountain backdrop, also the existing industrial factories have been transformed to a low-rise industrial development site, which will be more compatible with the surrounding context. However, consider with the large changes to the existing visual character, the residual impacts will stay as slight during operation.

VSR6

Jasper Court and Long Tin Road

Low

Small

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM6, OM7, OM8

Slight

Slight

Slight

Description:

Given the existing low-rise residential environment will change to mid-rise development area, the proposed mitigation measures may not be able to fully alleviate the impact, therefore the residual impact will remain at slight level during construction and operation phase.

VSR7

Parkside Villa

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Slight

Description:

The construction works for the proposed developments would lead to clearance of vegetation, earthworks and demolition of structures, which would generate moderate impacts on this VSR. With the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction to minimise the visual impacts, the adverse impacts from the construction works can be reduced to a slight level. During the operational stage, since the major visual impact would generate by the erection of high-rise buildings, which would obstruct views towards natural hillside landscape and the existing open sky view, with the implementation of mitigation measure such as Aesthetic Design of Built Development (OM6), the use of light earthy tone colours with the buildings will help to reduce the visibility of the development components and improve the visual amenity, the adverse impacts can be reduced to slight level eventually.

VSR8

Tong Yan San Tsuen Interchange

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Slight

Description:

Construction of the proposed developments would require clearance of mature roadside vegetation and erection of the high-rise buildings would generate moderate impacts on this VSR. With the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction, the adverse impacts from the construction works can be reduced to a lower level. During the operational stage, since the proposed commercial and residential buildings would not obstruct views towards natural hillside landscape in the backdrop, the adverse impacts can be reduced to slight level eventually.

VSR9

Intersection of Kung Um Road and Shap Pat Heung Road

Low

Large

Large

Substantial

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8

Substantial

Moderate

Moderate

Description:

Given the noise enclosure is a 6m high structure which considered to be compatible with the existing environments. With the implementation of mitigation measure such as Noise Barrier Design (OM8), the visual impact of noise mitigation measures will be mitigated by appropriate detailed design, such as suitable combination of transparent and sound absorbent materials, or provision of at-grade planting of trees, shrubs and/or climbers to reduce visual bulkiness and incorporate aesthetically pleasing surface treatments to promote visual amenity. Therefore, the adverse impacts can be reduced to moderate level eventually during operation.

VSR10

Intersection of Lam Hei Rd and Kung Um Rd

Low

Intermediate

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Slight

Description:

Since the proposed development would be blocked by the YLH and existing vegetation, besides the proposed development will comprise of more urbanised elements which can integrate with wider visual extent. Therefore the residual of impact would be stay at slight level during construction and operation stage.

VSR11

Tin Liu Tsuen

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

As the proposed developments will change the existing low-rise village environment to a high-rise residential area,  the recommended mitigation measures may not be able to alleviate the impacts, therefore the residual impacts will stay as moderate during construction and operation stage.

VSR12

Chun Fai Garden

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Similar as above. Since the existing village environment will transform to a mid-rise development, the recommended mitigation measures may not be able to fully alleviate the impacts, thus the residual impacts will stay as moderate during construction and operation stage.

VSR13

Pathway near Muk Kiu Tau Tsuen

Low

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM8, OM9

Moderate

Moderate

Moderate

Description:

The construction works for the proposed developments would require clearance of vegetation and erection of building structures, which would generate substantial impacts on this VSR. In addition, a small portion of noise barrier along Kiu Hing Road will be visible from this viewpoint. With the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction, the adverse impacts from the construction works can be reduced to a lower level. Refer to Figure 10.14f, during operation phase, although the change of this visual character cannot be completely mitigated, the existing nullah will be revitalise and apply natural building materials such as timber on the footpath to improve the aesthetic value of the nullah, also with the Aesthetic Design of Built Development (OM6), the use of light earthy tone colours with the buildings will help to reduce the visibility of the development components and improve the visual amenity. For the noise barrier, with the implementation of mitigation measure such as Noise Barrier Design (OM8), the noise barrier will be mitigated by appropriate detailed design to promote visual amenity, also with the proposed measures including Screen Planting (OM4) and Roadside Tree Planting (OM5) will introduce more natural elements to the view and reduce the visual bulkiness of the noise barrier, thus the adverse impacts can be reduced to moderate level eventually. Since the proposed development will change the existing village environment to a high-rise residential area, the visual impact cannot be completely mitigated by the proposed mitigation measures, therefore the residual impact will stay at moderate level at Year 10 of operation stage.

 

VSR14

Kiu Hing Road near Pak Sha Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM9

Moderate

Moderate

Moderate

Description:

Given the proposed development will result in large changes to the existing visual character, the recommended mitigation measures may not be able to alleviate the impacts, therefore the residual impacts will stay as moderate during construction and operation stage.

 

 

VSR15

One Hyde Park Bus Station

Medium

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM9

Moderate

Moderate

Moderate

Description:

During the construction stage, visual intrusion and degraded visual amenity caused by the road improvement works and erection of building structures would generate substantial impacts on this VSR. With the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction, the adverse impacts from the construction works can be reduced to a lower level. Refer to Figure 10.14g, during the operational stage, although the change of this visual character cannot be completely mitigated, the existing nullah will be revitalise and apply natural building materials such as timber on the footpath to improve the visual amenity. Besides, with the implementation of mitigation measure such as Aesthetic Design of Built Development (OM6), the use of light earthy tone colours with the buildings will help to reduce the visibility of the development components and improve the visual amenity, the adverse impacts can be reduced to moderate level eventually. However, the proposed development will change the existing village environment to a high-rise residential area, the proposed mitigation measures may not be able to fully alleviate the impact, therefore the residual impact will stay at moderate level at Year 10 of operation stage.

 

 

VSR16

Channel Pathway on Kung Um Road

Low

Large

Large

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Slight

Description:

The construction works for the proposed developments and infrastructures would require clearance of vegetation, earthworks and erection of building structures, which would generate moderate impacts on this VSR, the proposed mitigation measures may not be able to alleviate the impact, therefore the residual impact will stay as moderate during construction stage. Refer to Figure 10.14j, during the operational stage, the erection of high-rise residential buildings would be the visual intrusion to the existing view, with mitigation measures such as Screen Planting (OM4) and Roadside Tree Planting (OM5) which will introduce more natural elements to the view, also the revitalised nuallah will provide a landscaped and pleasure walking environment for the community, it will enhance the visual amenity of the surroundings. Therefore, the adverse impacts can be alleviated to slight eventually.

 

 

 

VSR17

Pak Sha Tsuen Facing Southwest

High

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM9

Moderate

Moderate

Moderate

Description:

Similar as VSR 15, given the proposed development will result in large changes to the existing visual character, although the recommended mitigation measures may not be able to fully alleviate the impacts, the existing nullah will be revitalise to improve the visual amenity. Besides, with the implementation of mitigation measure such as Aesthetic Design of Built Development (OM6), the use of light earthy tone colours with the buildings will help to reduce the visibility of the development components and improve the visual amenity, the adverse impacts can be reduced to moderate level eventually. However, the proposed development will change the existing village environment to a high-rise residential area, the proposed mitigation measures may not be able to fully alleviate the impact, therefore the residual impacts will stay as moderate during construction and operation stage.

 

 

 

 

VSR18

Tai Lam Mountain1 Facing Northeast

Medium

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Construction of the proposed infrastructures would require the demolition of existing buildings, clearance of vegetation, loss of mixed woodland and the erection of building structures would generate substantial impacts on this VSR., with the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7), the adverse impacts from the construction works can be reduced. Refer to Figure 10.14l, during the operational stage, a more urbanised landscape would characterised the view connecting with the Yuen Long New Town to the north, also the thematic greening proposal will introduce more natural elements to the view, and comprises new planting spaces to alleviate the visual impacts. Besides, with mitigation measures such as Screen Planting (OM4), Road Side Planting (OM5), Aesthetic Design of Built Development (OM6), Maximise Greening on Engineering Structures and Surfaces (OM7) and Man-made Channel Improvements (OM9), the proposed developments would be more compatible with the surrounding context, the residual impacts can be alleviated eventually. However, due to the large scale of the Project, the change of the visual character would be inevitably large, therefore the visual impact cannot be completely mitigated by the proposed mitigation measures, thus the residual impacts would be remain at moderate level at year 10 of operation.

 

VSR19

Tai Lam Mountain2 Facing East

Medium

Large

Large

Substantial

Substantial

CM1, CM2, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Similar as above. Since the large scale of construction activities will be visible even in a far viewing distance, consider with the proposed landscape and visual enhancement works, such as revitalisation of nullah and thematic greening proposal will help to create a pleasant environment for the community, thus the proposed development would be more compatible with the surrounding landscape, and the adverse impacts can be reduced to moderate level eventually.

 

 

VSR20

Tai Lam Mountain3 Facing Southeast

Medium

Large

Large

Substantial

Substantial

CM1, CM2, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Similar as above. Also consider with the proposed development would be compatible with the surroundings, the adverse impacts can be reduced to moderate level eventually.

 

VSR21

Tai Lam Mountain4 Facing Northeast

Medium

Large

Large

Substantial

Substantial

CM1, CM2, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Similar as above. As the far viewing distance and the proposed development will be compatible with the existing environment, the adverse impacts can be reduced to moderate level eventually.

 

VSR22

Tai Lam Mountain5 Facing Northeast

Medium

Large

Large

Substantial

Substantial

CM1, CM2, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Similar as above. The adverse impacts can be reduced to moderate level eventually.

VSR23

Tai Lam Mountain6 Facing North

Medium

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Due to the far viewing distance of this VSR, the construction works of the development may not be visible. With the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction, the adverse impacts from the construction works can be reduced to a lower level. Refer to Figure 10.14n, the proposed development will change from the existing brownfield site to a planned new town, besides the thematic greening proposal and revitalised nullah will introduce more nature elements to the site, the proposed development will be more compatible with the surroundings.  Therefore, the adverse impacts can be reduced to moderate level eventually.

 

 

 

VSR24

Tai Lam Mountain7 Facing Northeast

Medium

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9

Moderate

Moderate

Moderate

Description:

Similar as above. As the proposed development will be compatible with the surroundings, the adverse impacts can be reduced to moderate level eventually.

 

 

 

 

 

VSR25

Tai Lam Mountain 8 Facing Northeast

Medium

Large

Large

Substantial

Substantial

CM1, CM2, CM5, CM7

OM3, OM4, OM5, OM6, OM7, OM8, OM9, OM10

Moderate

Moderate

Moderate

Description:

As the proposed developments will change from the brownfield site to a planned new town, which will be compatible with the existing landscape. Besides, the thematic greening proposal and revitalised nullah will introduce more nature elements to the site, thus the adverse impacts can be reduced to moderate level eventually.

VSR26

Access Road off Tai Tong Shan Road

Low

Small

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

Since the change of the existing visual character would be large, the proposed mitigation measures may not be able to fully reduce the impact, the residual impact will remain at slight level during construction and operation stage.

VSR27

Shui Tsiu San Tsuen Road near Wong Nai Tun Tsuen

Medium

Small

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

Similar as above. The residual impacts will stay at slight during construction and operation stage.

VSR28

Shui Tsiu San Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Moderate

Moderate

Moderate

Description:

Given the change of the visual character would be inevitably large, the proposed mitigation measures will not able to adequately compensate the visual impact, the residual impact would remain at moderate during construction and operation stage.

VSR29

Sham Chung Tsuen

High

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Substantial

Substantial

Substantial

Description:

Refer to Figure 10.14p, since the existing village environment will be change to high-rise residential area, the change of the visual character would be inevitably large, the proposed mitigation measures may not be able to fully alleviate the impact, therefore the residual impact will remain at substantial level during construction and operation stage.

VSR30

Shan Ha Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Moderate

Moderate

Moderate

Description:

Since the existing village environment will be change to a high-rise residential area, the proposed mitigation measures will not able to adequately compensate the visual impact, the residual impact would remain at moderate during construction and operation stage.

VSR31

Ho Hok Shan 1 and Facing Southwest

Medium

Small

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

 Refer to Figure 10.14r, as the change of the existing visual character would be large, the proposed mitigation measures may not be able to fully alleviate the impact, the residual impact will remain at slight level during construction and operation stage.

VSR32

Tong Yan San Tsuen

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Moderate

Moderate

Moderate

Description:

Similar as above. Given the change of the visual character would be inevitably large, the residual impact would stay at moderate level during construction and operation stage.

 

VSR33

Tan Kwai Tsuen Road near Open Storage

Low

Small

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

Similar as above. The residual impact would stay at slight during construction and operation stage.

VSR34

Tan Kwai Tsuen Road near Osmanthus Arnold Garden

High

Small

Small

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

As the proposed developments will change from the village environment to a high rise residential area, the proposed mitigation measures may not be able to fully alleviate the impact. However, due to the blockage of the existing village buildings and the proposed developments would not obstruct the views to natural hillside landscape in the backdrop, therefore the residual impact would reduce to slight level at construction and operation stage.

VSR35

Cheung Ngau Shan and Facing Northwest

Medium

Negligible

Negligible

Insignificant

Insignificant

-

-

Insignificant

Insignificant

Insignificant

Description:

Given the proposed development would be compatible with the existing surroundings, and the proposed road infrastructures would not be visible due to the blockage of vegetation, the residual impact would stay at slight during construction and operation stage.

 

VSR36

Near Yuen Long Government Primary School

Medium

Negligible

Negligible

Insignificant

Insignificant

-

-

Insignificant

Insignificant

Insignificant

Description:

Since the proposed development and road infrastructures would not be visible due to the blockage of vegetation and village buildings, the residual impacts will be insignificant during construction and operation stage.

VSR37

Pok Oi Hospital

Medium

Negligible

Negligible

Insignificant

Insignificant

-

-

Insignificant

Insignificant

Insignificant

Description:

Similar as above. Due to the blockage of existing vegetation, the proposed development would not be significant, the residual impacts will be insignificant in both stage.

VSR38a

Yoho Town (Ground Level)

Low

Large

Large

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

As the proposed road infrastructures will be compatible with the existing landscape, also with the implementation of mitigation measures such as Screen Planting (OM4) and Roadside Tree Planting (OM5), which will introduce more natural elements to the view, thus the adverse impacts can be reduced to slight level eventually.

VSR38b

Yoho Town (Upper Level)

High

Large

Large

Substantial

Substantial

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Moderate

Moderate

Moderate

Description:

Similar as above. Due to the proposed road infrastructures will be compatible with the existing landscape, also with the implementation of mitigation measures such as Screen Planting (OM4) and Roadside Tree Planting (OM5), which will introduce more natural elements to the view, thus the adverse impacts can be reduced to moderate level eventually.

VSR39

Yau Tin West Road near Hoover Garden

Medium

Negligible

Negligible

Insignificant

Insignificant

-

-

Insignificant

Insignificant

Insignificant

Description:

The proposed road infrastructures would not be visible due to the blockage of existing vegetation, therefore the residual impacts will be insignificant in both stage.

VSR40

Intersection of Tai Tong Road

Low

Small

Small

Slight

Slight

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

Since the proposed road infrastructures will be compatible with the existing surroundings, the residual impact will be remain as slight during construction and operation stage.

VSR41

Tai Kei Leng Road

Low

Negligible

Negligible

Insignificant

Insignificant

-

-

Insignificant

Insignificant

Insignificant

Description:

As the proposed road infrastructures would not be visible due to the blockage of the mature vegetation, the residual impacts will be insignificant in both stage.

VSR42

Tai Shu Ha Road East Facing Northwest

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM4, OM5, OM6

Slight

Slight

Slight

Description:

Given the proposed road infrastructures would not have a significant change to the existing visual character, also with the implementation of mitigation measures such as Screen Planting (OM4) and Roadside Tree Planting (OM5), which will introduce more natural elements to the view, thus the adverse impacts can be reduced to slight level eventually.

VSR43

Hung Tin Road

Low

Intermediate

Negligible

Moderate

Insignificant

CM1, CM5, CM7

OM3

Slight

Insignificant

Insignificant

Description:

During construction stage, the proposed utilities construction would include the breaking out hard surfaces and earthworks, which would generate moderate impacts on this VSR. With the implementation of mitigation measures as Optimisation of Construction Areas and Providing Temporary Landscape on Temporary Construction (CM1), Screen Hording (CM5) and Construction Light Control (CM7) during construction, the adverse impacts from the construction works can be reduced to a lower level. As the utilities are installed underground, the residual impacts during operation will be insignificant.

 

VSR44

Shap Pat Heung Road near La Grove

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM5, CM7

OM3, OM5, OM8

Slight

Slight

Slight

Description:

As the proposed noise enclosure is a low-rise structure which will not block the natural hillside view in the background, also with the implementation of mitigation measure such as Noise Barrier Design (OM8), the visual impact of noise mitigation measures will be mitigated by appropriate detailed design, such as suitable combination of transparent and sound absorbent materials, or provision of at-grade planting of trees, shrubs and/or climbers to reduce visual bulkiness and incorporate aesthetically pleasing surface treatments to promote visual amenity. The adverse impacts can be reduced to slight level eventually during operation stage.

 


Summary of Residual Landscape Impacts on LCAs

10.13.4.2        The main LCA affected by the Project is the LCA 1a ‘Miscellaneous Rural Fringe Landscape – Open Storage/ Rural Built Area’ and LCA1b ‘Miscellaneous Rural Fringe Landscape – Lowland Agricultural Land’.  This rural landscape character is impacted, in part, by the construction and operation of Public Housing Building, and in part by the proposed road network (including the beautification of existing nullahs and renovation of the Kung Um Road and Long Han Road), introducing the a more urbanized landscape character into the rural context.

10.13.4.3        This rural character is predicted to experience moderate adverse residual impacts at the construction stage considering the design measures which have been adopted and recommended construction and operation mitigation measures including tree protection, preservation and transplantation; compensatory planting, compensatory woodland planting, road greening and general good site practice.  It is anticipated that the impact significance would reduce to slight at year 10 when the landscape character has been changed into urban type development, and compensatory planting achieves its full potential.

10.13.4.4        Moderate adverse impacts are predicted for LCA 3 ‘Upland and Hillside Landscape’ prior to mitigation due to the interference of natural topography and vegetation as a result of embankment construction and road verges.  Given the limited extent of the works on the fringes of the LCA, which is relaitvely small areas with the wider LCA, it is considered careful design of the proposed engineered slopes, protection of vegetation and replanting of slopes can reduce the impact gradually.  By year 10 establishments of slope planting measures would have reduced the impact to slight.

10.13.4.5        Moderate impacts are predicted for LCA8 ‘Transportation Corridor Landscape’ due to the major infrastructure works on the YLH during the construction. Given the limited extent of the works and considering the new road infrastructures belong to the same landscape character in the operation, the impact will reduce to slight level after the works’ completion. In addition, Slight impacts are also predicted to LCA 2 ‘Miscellaneous Urban Fringe Landscape’ due to this major infrastructure works. It is considered that with mitigation measures such as roadside planting and slope landscaping, can help to enhance the landscape character and reduce the impacts for these two LCAs to insignificant by year 10.

10.13.4.6        Slight impacts are predicted for LCA7 ‘Urban Peripheral Village Landscape’ due to a small proportion falls within the major infrastructure works and proposed zonings of storage use. The potential impact is considered as irreversible and cannot be fully mitigated with proposed mitigation measures. However, with landscape enhancement measures by the RODP, this slight impact can be alleviated in place eventually.

10.13.4.7        There is no impact on LCA 4 ‘Settled Valley Landscape’, LCA 5 ‘Park Urban Landscape’ and LCA 6 “Hui” Urban Landscape’ for the LCA locations outside the proposed development.

Summary of Residual Landscape Impacts on LRs

10.13.4.8        Approximately 63% of existing trees within the development boundary are predicted to be potentially impacted by the proposed development. Most of these trees which may be affected can be found in the areas of LR2 ‘Lowland Mixed Trees, Shrubland and Grassland’, LR4 ‘Secondary Woodland’, LR5 ‘Plantation’ and LR11 ‘Open Storage/ Rural Built Area’. In order to avoid or minimise the potential impacts, the urban design framework of the RODP has introduced areas of Green Belt and Open Space to retain and protect these trees as far as practical. In addition, these open areas together with greening along development lots can create opportunities for mitigation measures such as tree transplanting and compensatory plantings in-situ if retained on site is not practical. Tree compensation will be provided in accordance with DEVB TCW No.7/2015 to meet a ratio of 1:1 in terms of number. Further tree compensation proposal will refer to the Tree Removal Application at detailed design stage.

10.13.4.9        Taking into the nature of the Project, adverse impacts are anticipated for those high sensitivity and landscape value resources including LR1a ‘Active Agricultural Land’, LR4 ‘Secondary Woodland’ and LR15 ‘Watercourses of higher ecological value’. Since these resources contribute to the rural character of the existing Project area largely, mitigation measures cannot fully compensate for these adverse impacts from the permanent loss of these resources. Moderate residual impacts are still predicted for LR1a and LR15. However, since the area of woodland compensation are proposed (a minimum 5ha of compensation woodland in the proposed planting site of 12ha), it is considered that the residual impacts on LR4 can be reduced to a lower level when these compensatory plantings matured.

10.13.4.10    For, LR1c ‘Orchard', LR2 ‘Lowland Mixed Trees, Shrubland and Grassland’, LR3 ‘Hillside Shrubland and Grassland’,  LR5 ‘Plantation’ and LR13 ‘Agricultural Pond’,  any loss of these LRs also influences the rural character of the landscape; directly compensating for the loss of this resource is limited by local land availability, demand and suitability. In this case the mitigation measures ensure, as far as possible, that tree cover is compensated at an appropriate level, agricultural features such as ponds are replaced, and the overall incorporation of soft landscape works and provision of public open space are maximised within the RODP. As a result it is considered the residual impact, post mitigation, can be reduced to slight to moderate adverse levels by operation day 1 and slight by year 10 when mitigation measures have matured and taken effect.

10.13.4.11    For LR11 Open Storage/Rural Built Area, most areas of this LR are under the footprint of the RODP which means the magnitude of change are predicted to be large. The existing trees and vegetation coverage including 14 nos. of important trees (POVTs) would be potentially affected by the proposed development. The landscape impacts on this LR are anticipated to be substantial. However, in the long-term, the new land use types and landscape proposal will introduce more open space and green network to the existing areas, these important trees are proposed to be circumscribed in these landscape areas in order to be retained and protected. In addition, with implementation of mitigation measures, most trees and vegetation would be replaced with much higher quality planting with amenity value, the landscape quality of these affected areas within this LR are considered to be enhanced, the residual impacts by year 10 of operation can therefore be reduced to moderate.

10.13.4.12    For LR14 ‘Channelised Watercourse’, which flows throughout the PDA, as well as Kung Um Road within the Study Area. All of this LR needs to be upgraded and beautified with amenity vegetation together with road improvement works in various sections. Specially, part of the Kung Um Road and Lam Tai West Road will be decked over for carriageway subject to the proposed road network. Thus, during construction, the potential impact is considered to be moderate. When the construction works complete, the enhanced watercourse features will raise the landscape value of this LR. With mitigation measures, the residual impacts can be reduced to insignificant by year 10 of operation.

10.13.4.13    Before mitigation, slight adverse impacts are predicted in construction for LR1b ‘Abandoned Agricultural Land’, LR7 ‘Road and Urban Infrastructure’, LR9 ‘Urbanised Development’, LR10 ‘Village Type Development’ and LR12 ‘Disturbed Area’ due to large scale construction footprint of the proposed development. This would involve extensive excavation, ground works, reconfiguration works and felling of plantation trees including which is inside industrial areas, villages and residential open spaces and currently line the roads and channels (both sides would be affected). During construction, measures to protect the planting resources, transplant trees where feasible together with provision of compensatory planting are considered to have the capacity to address these impacts.  Following application of mitigation, this impact can be reduced to insignificant by year 10 when various landscape mitigation are introduced and taken effect.

10.13.4.14    No impact is predicted on LR8 ‘Major Transport Corridor’ and LR16 ‘Reservoir’ as the sites are located outside the areas of those LRs.

Significance of Residual Visual Impacts on VSRs

10.13.4.15    In summary for VSRs, it is considered the most sensitive views are those which currently experience a direct and broad connection with the wider undeveloped landscape setting, in particular those residential VSRs overlooking of the proposed development in Yuen Long South, such as VSR 1 Yuen Long Park Tower, VSR15 One Hyde Park Bus Station, VSR 17 Pat Sha Tsuen Facing SW, VSR29 Sham Chung Tsuen, VSR 34 Tan Kwai Tsuen Road near Osmanthus Arnold Garden and VSR 38 Yoho Town. Otherwise, those recreational VSRs such as VSR 18, VSR 19, VSR 20, VSR 21, VSR 22, VSR 23, VSR 24 and VSR 25 on Tai Lam Mountain would experience substantial impacts due to substantial loss of visual element and large magnitude of visual change. Other views of the site element and large magnitude of visual change. Other views of the site within the visual envelope including public footpaths, trails, local open spaces, municipal parks, high rise buildings, major infrastructure routes and so on, would experience slight to moderate visual impacts depending on the visible proportion of the PDA development, magnitude of visual change and their visual sensitivity.

10.13.4.16    Following the implementation of mitigation measures, VSR29 Sham Chung Tsuen will be remain as substantial residual impacts, as the change of the visual character would be inevitably large. For the other residential and recreational VSRs, the residual impacts would be reduced from substantial to moderate levels eventually. Mitigation works in development areas during the construction stage rely heavily on the optimisation of the extent of the works areas, proving temporary landscape on temporary construction, avoidance of significant topographical changes together with the retention, protection and compensatory planting of trees/ vegetation. Greening measures such as use of climbing plants and verge planting, can help to break up the uniformity of new road formation and associated structures. When used in combination with measures such as sensitive design of infrastructure, facade treatment and colour scheme, those measures would have the capacity to reduce the level of visual impacts in the early operational stage.

10.13.4.17    In terms of effectiveness of mitigation measures, it is considered that for visual amenity purpose, improving the appearance of new urban infrastructures together with landscape planting or screening measures, and lighting control would help to alleviate the adverse visual impacts from the new urban development and enhance the compatibility with the existing Yuen long Town development. Although the recommend mitigation measures may not be able to compensate the large change in character adequately. However, the overall change that is to occur as a result of development of the Project will ultimately bring about positive change.


 

10.14              Cumulative Impact

10.14.1        General

10.14.1.1        The key concurrent project which may generate cumulative landscape and visual impacts during construction and operation phases in the vicinity are assessed from below. Other concurrent projects as described in Chapter 1 and illustrated on Figure 1.3.

10.14.2        HSK NDA Planning and Engineering Study – Investigation (EIA – 248/2016 )

10.14.2.1        The overall objective of the HSK Study is to formulate a feasible landuse framework for the HSK NDA to meet the long-term housing and other land-use needs of Hong Kong, and to formulate an outline development plan, layout plans for the NDA. Technical assessments are conducted to confirm the feasibility and environmental accepatability of the development proposals. The construction programme of HSK NDA shall commence in 2020 and be completed by 2024 according to the current construction programme (refer Section 1.8 and Table 1.3). The Study Site, covering an area of about 714 ha, is bounded by Tin Ying Road and Kiu Hung Road to the east; Castle Peak Road to the south; Lau Fau Shan Road and Deep Bay Road to the north; and Kong Sham Western Highway (KSWH) to the west.

10.14.2.2        According to the HSK NDA EIA exhibited by public inspection (EIA – 248/2016), major landscape impacts are generated from the loss of vegetation, fragmentation of some resources and the fundamental change in character of brownfield sites. Given the adverse landscape impacts from YLS development is predicted to be similar, thus, no additional landscape impacts are predicted with the implementation of mitigation measures (such as compensatory plantings and sensitive design of landscape areas) in place at this stage.

10.14.2.3        The TYST area in YLS development is the closest to the HSK NDA (approx. 450m away from the Project boundary near Hung Fuk Estate). Given that the proposed development intensity of HSK NDA near Hung Fuk Estate is planned to be a high-density residential development with a plot ratio of 2.5 to 5.0, the potential cumulative visual impact will be generated for those sensitive receivers near Hung Fuk Estate. It is considered that the residual impacts would not be fully addressed by mitigation measures due to the fundamental changes of existing visual character. However, the adverse residual impacts are not considered in a substantial level since both of the proposed developments would create certain degree of visual amenity enhancement to the local community, such as creating open space and thematic greening proposals. As a result, the visual receptors are likely to experience a moderate level of cumulative visual impacts during both construction and operational phases.

 

 


 

10.15              Conclusions

10.15.1.1        The Project will inevitably result in some landscape and visual impacts during construction and operational phases. The existing rural character in YLS would be transformed into a more urbanized landscape setting after commissioning of the Project. It is not possible to fully mitigate all landscape impacts in relation to loss of active agriculture land, mature woodland or tree planting for affected LRs and LCAs in the construction period and early operational stage, mainly as long periods of time are required to sufficiently compensate for the associated impacts. In addition, approximately 63% of exiting trees within the development boundary will be potentially affected. Urban design framework has proposed open spaces and greening along development lots for tree preserved or transplanting. Compensatory planting will be required in terms of 1:1 by quantity. Tree planting to achieve the compensatory ratio of 1:1 by aggregated DBH, i.e. the total DBH of planted trees to have the same total DBH of felled trees should be undertaken as far as practicable. After compensatory measures are applied, in combination with landscape enhancement proposed by the RODP, the residual impacts to LRs and LCAs can be reduced to slight to moderate levels eventually.

10.15.1.2        The overall visual character in Yuen Long South area would be changed by the proposed development after the construction, the recommended mitigation measures are not able to adequately compensate for such a large magnitude of visual character change. However, the overall change that is to occur as a result of development of the Project will eventually bring about positive change. The proposed developments will change the existing brownfield site into a planned new town, also with the enhancement proposals go further by defining the basic design elements, such as parklands and streetscape in YLS. The transformation will result in strong visual interest and character and improved visual outlook for the majority of VSRs, the overall change would enhance the compatibility with the existing visual character of Yuen Long Town.  Besides, the enhanced planting design and revitalised nullah will help to improve aesthetics and create a green, quality and liveable community for housing supply and improving the existing brownfield environment.

10.15.1.3        Cumulative landscape and visual impact during construction and operation phases are predicted to be generated from other concurrent projects which mainly include the HSK NDA. Given the adverse landscape impacts (such as loss of vegetation, fragmentation of some resources and the fundamental change in character of brownfield sites) are predicted to be similar to the YLS development, no additional landscape impacts are predicted with the implementation of mitigation measures. The adverse visual impacts will not be substantial since both of the proposed developments would create certain degree of visual amenity enhancement to the local community.

10.15.1.4        On review of the likely residual impacts and possibility to alleviate the impact by operation in year 10 when the mitigation measures are matured and the enhancement proposals are well established, the overall residual landscape and visual impacts would be acceptable with mitigation measures during the construction and operational phases.