CONTENTS
1.1 Background
1.2 Designated
Project
1.3 Purpose
of the EIA Study
1.4 Objectives
of the EIA Study
1.5 Structure
of this EIA Report
2.1 Introduction
2.2 Project
Objective
2.3 The
Need for the Project
2.4 Scope
of the Project
2.5 Proposed
Relocation Site
2.6 Proposed
Location of Access Tunnel and Tunnel Portal
2.7 Proposed
Layout for the Project
2.8 Consideration
of Construction Methodologies
2.9 Tackling
Environmental Challenges and Options Considered
2.10 Environmental
Initiatives
2.11 Collating
and Addressing Public Views
2.12 Project
Programme
2.13 Project
Interface
2.14 Potential
Environmental Impacts Arising from Construction and Operation of the ProjecT
3.1 Introduction
3.2 Relevant Legislation,
Standards and Guidelines
3.3 Baseline
Condition
3.4 Air Sensitive
Receivers
3.5 Identification
of Key Air Pollutants
3.6 Assessment
Methodology
3.7 Prediction and
Evaluation and Environmental Impacts
3.8 Mitigation
Measures
3.9 Residual
Impacts
3.10 Monitoring and
Audit Requirement
3.11 Conclusion
4. Noise Impact
4.1 Introduction
4.2 Relevant
Legislation, Standards and Guidelines
4.3 Baseline
Condition
4.4 Noise
Sensitive Receivers
4.5 Potential
Sources of Impact
4.6 Assessment
Approach and Methodology
4.7 Impact
Assessment
4.8 Mitigation
Measures
4.9 Cumulative
Impacts
4.10 Residual
Impacts
4.11 Monitoring
and Audit Requirement
4.12 Conclusion
4.13 References
5.1 Introduction
5.2 Relevant
Legislation, Standards and Guidelines
5.3 Water
Sensitive Receivers
5.4 Existing
Baseline Condition
5.5 Potential
Sources of Impacts
5.6 Assessment
Methodology
5.7 Impact
Assessment
5.8 Mitigation
Measures
5.9 Cumulative
Impacts
5.10 Residual
Impacts
5.11 Monitoring
and Audit Requirement
5.12 Conclusions
6. Waste Management IMPLICATIONS
6.1 Introduction
6.2 Relevant
Legislation, Policies, Standards and Criteria
6.3 Assessment
Methodology
6.4 Identification
of Potential Waste Sources
6.5 Impact
Assessment and Evaluation
6.6 Mitigation
Measures
6.7 Residual
Impacts
6.8 Monitoring
and Audit Requirement
6.9 Conclusions
7.1 Introduction
7.2 Relevant
Legislation, Policies, Standards and Criteria
7.3 Assessment
Methodology
7.4 Site
Appraisal
7.5 Mitigation
Measure
7.6 Residual
Impacts
7.7 Monitoring
and Audit Requirement
7.8 Conclusions
8 Ecological
Impact Assessment
8.1 Introduction
8.2 Requirement of
EIA under Study Brief
8.3 Relevant
Legislation, Standards and Guidelines
8.4 Assessment
Methodology
8.5 Field Survey
Methodology
8.6 Survey Result
8.7 Evaluation of
Habitats and Species of Ecological Importance
8.8 Impact
Identification and Evaluation
8.9 Mitigation
Measures
8.10 Cumulative
Impact
8.11 Residual Impact
8.12 Monitoring and
Audit Requirement
8.13 Conclusion
8.14 References
9.1 Project
Background
9.2 Key
Development Component
9.3 Relevant
Legislations, Standards & Guidelines
9.4 Landscape
Assessment Methodology
9.5 Visual
Assessment Methodology
9.6 Review
of Planning and Development Control Framework
9.7 Landscape
Baseline Condition
9.8 Visual
Baseline Condition
9.9 Broad
Brush Tree Survey Findings
9.10 Sources
of Landscape and Visual Impacts
9.11 Magnitude
of Change of Landscape Quality without Mitigation
9.12 Magnitude
of Change of Visual Quality without Mitigation
9.13 Significance
of Landscape Impacts without Mitigation
9.14 Significance
of Visual Impacts without Mitigation
9.15 Recommended
Landscape and Visual Mitigation Measures
9.16 Recommended
Photomontage Vantage Points
9.17 Significance
of Residual Landscape and Visual Impacts
9.18 Concurrent
Projects and Potential Cumulative Impacts
9.19 Environmental
and Monitoring Audit Requirement
9.20 Conclusion
10.1 Introduction
10.2 Relevant
Legislation, Standards and Guidelines
10.3 Hazard
Identification
10.4 Monitoring
and Audit Requirement
10.5 Conclusion
11 Environmental Monitoring & Audit Requirements
11.1 Project
Organisation
11.2 EM&A
Manual
11.3 Project
Implementation Schedule
11.4 EM&A
Programme
12.1 Introduction
12.2 Environmentally
Friendly Options Considered and Incorporated to Avoid Environmental Impact
12.3 Environmental Designs Recommended to
Minimise and Mitigate Environmental Impacts
12.4 Summary of Key Environmental Problems
Avoided, Protection of Sensitive Areas and Provision of Compensatory Tree
Planting
12.5 Estimated Population Protected from
Various Environmental Impacts
12.6 Environmental Benefits of Environmental
Protection Measures Recommended
13 ConclusionS
13.1 General
13.2 Benefits
of Project
13.3 Air
Quality Impact
13.4 Noise
Impact
13.5 Water
Quality Impact
13.6 Waste
Management Implications
13.7 Land
Contamination
13.8 Ecological
Impact
13.9 Landscape
and Visual Impacts
13.10 Hazard
to Life
13.11 Overall
Conclusion
List of Tables
Table
2.1 Advantages and Disadvantages of
Proposed Cavern Options
Table 2.2 Advantages and Disadvantages
of Proposed Tunnel Options
Table
2.3 Consideration of Construction Methods for Tunnels and Caverns
Table
2.4 Summary of Public Views
Table
2.5 Potential Concurrent Project
Table
2.6 Indoor Air Quality Objectives for Office and
Public Places
Table 3.1 Hong Kong Air Quality Objectives
Table 3.2 5-year Averaged Annual Background Concentration of Air
Pollutants recorded at Sham Shui Po Station by EPD for the Period of 2015-2019
Table 3.3 Air Pollutants Concentrations at the Project Site
in 2020 Predicted from PATH-2016 Model
Table 3.4 Representative Air Sensitive Receivers
Table 3.5 Key Concurrent Projects for Construction Dust
Assessments
Table 3.6 Individual Construction Activities during Construction
Table 3.7 Emission Factor for Dust Emitting Construction Activity
Table 3.8 Preliminary Design of Ventilation System at the Portal
Table 3.9 Vehicular Classes in EMFAC-HK Model
Table 3.10 Summary of Cumulative Dust Emission Concentration
(Unmitigated Scenario)
Table 3.11 Summary of Dust Suppression Measures
Table 3.12 Summary of Cumulative Dust Emission Concentration
(Mitigated Scenario)
Table 4‑1 EIAO-TM Day-time Construction
Noise Standards
Table 4‑2 Area Sensitivity Ratings
Table 4‑3 Acceptable Noise Levels (ANLs)
for General Construction Works to be carried out during Restricted Hours
(GW-TM)
Table 4‑4 ANLs to be used as
Operational Noise Criteria
Table 4‑5 Measured Prevailing Noise
Levels
Table 4‑6 Representative Noise
Sensitive Receivers (NSRs)
Table 4‑7 Predicted Construction Noise
Levels (Without Mitigation Measures)
Table 4‑8 Fixed Plant Noise Design
Criteria
Table 4‑9 Predicted
Construction Noise Levels (Mitigated Scenario 1)
Table 4‑10 Predicted
Construction Noise Levels (Mitigated Scenario 2)
Table 4‑11 Predicted
Cumulative Construction Noise Levels
Table 4‑12 Predicted
Cumulative Fixed Plant Noise Levels
Table 5‑1 Summary
of Water Quality Objectives for Victoria Harbour (Phase 2) WCZ
Table 5‑2 Representative
Water Sensitive Receivers
Table 5‑3 Summary
of River Water Quality Monitoring Data collected by EPD for Stations in Kai Tak
River
Table 5‑4 Summary
of Marine Water Quality Monitoring Data collected by EPD for VM1, VM2, VT4 and
VT11
Table 6.1 Summary of Different Types of Waste Volumes Generated during Construction
Phase
Table 6.2 Programme of Disposal of C&D Materials
Table 6.3 Tentative Transportation Routings for Waste Disposal
Table 7.1 Review of Historical Aerial Photos
Table 8.1 Planned Schedule of Ecological
Surveys
Table 8.2 Estimated Size of the
Habitat Types within the Project Area and Study Area
Table 8.3 Ecological Evaluation of
Secondary Woodland
Table 8.4 Ecological Evaluation of
Plantation
Table 8.5 Ecological Evaluation of
Shrubland
Table 8.6 Ecological Evaluation of
Watercourse
Table 8.7 Ecological Evaluation of
Developed Area
Table 8.8 Ecological Evaluation of
Floral Species of Conservation Interest
Table 8.9 Ecological Evaluation of
Faunal Species of Conservation Interest
Table 8.10 Summary of Habitat Loss
Table 8.11 Length of Proposed Fresh
Water and Salt Water Mains
Table
9.1 Description
of Key Development Components
Table
9.2 Matrix of Significance of Landscape
and Visual Impacts
Table
9.3 Review of Existing Planning and
Development Framework within the 500m Study Area
Table
9.4 Baseline Conditions of Landscape
Resources
Table
9.5 Summary of Sensitivity of Landscape
Resources
Table
9.6 Baseline Conditions of Landscape
Character Areas
Table
9.7 Summary of Sensitivity of Landscape
Character Areas
Table
9.8 Baseline VSRs and their Sensitivity
Table
9.9 Summary of Broad Brush Tree Survey Results
Table
9.10 Sources of Landscape and Visual
Impacts
Table
9.11 Magnitude of Change of Landscape Quality without Mitigation
Table
9.12 Magnitude of Change of Visual Quality without Mitigation
Table
9.13 Recommended Landscape and Visual Mitigation Measures for Construction
Phase
Table
9.14 Recommended Landscape and Visual Mitigation Measures for Operation Phase
Table
9.15 Significance of Residual Landscape Impacts
Table
9.16 Significance of Residual Visual Impacts
Table 12.1 Key Environmental
Problems Avoided and Sensitive Areas Protected
Table 12.2 Key Recommended
Mitigation Measures and Associated Benefits
List of Figures
Figure 1.1 Project Layout
Figure 2.1 General Layout
of Proposed Cavern Options
Figure 2.2 General Layout
of Proposed Access Tunnel Options – Feasibility Stage (Option 1-6)
Figure 2.3 General Layout
of Proposed Access Tunnel Options – Investigation Stage (Option 6-8)
Figure 2.4 Proposed Project
Site Location
Figure 2.5 Location of
Concurrent Project
Figure 3.1 Location
of Air Sensitive Receivers (Within 500m Quantitative Assessment Area)
Figure 3.2 Location
of Air Sensitive Receivers (Quantitative and Qualitative Assessment)
Figure 3.3 Surrounding
Environment and Concurrent Project
Figure 3.4 Segment
Configuration
Figure 3.5 Contours
of Cumulative Unmitigated Maximum Hourly TSP Concentration at 1.5 mAG (60.3 mPD
Base Elevation)
Figure 3.6 Contours
of Cumulative Unmitigated Annual RSP Concentration at 1.5 mAG (60.3 mPD Base Elevation)
Figure 3.7 Contours
of Cumulative Unmitigated 10th Highest Daily RSP Concentration at 1.5 mAG (60.3
mPD Base Elevation)
Figure 3.8 Contours
of Cumulative Unmitigated Annual FSP Concentration at 1.5 mAG (60.3 mPD Base
Elevation)
Figure 3.9 Contours
of Cumulative Unmitigated 10th Highest Daily FSP Concentration at 1.5 mAG (60.3
mPD Base Elevation)
Figure 3.10 Contours of
Cumulative Mitigated Maximum Hourly TSP Concentration at 1.5 mAG (60.3 mPD Base
Elevation)
Figure 3.11 Contours of
Cumulative Mitigated Annual RSP Concentration at 1.5 mAG (60.3 mPD Base
Elevation)
Figure 3.12 Contours of
Cumulative Mitigated 10th Highest Daily RSP Concentration at 1.5 mAG (60.3 mPD
Base Elevation)
Figure 3.13 Contours of
Cumulative Mitigated Annual FSP Concentration at 1.5 mAG (60.3 mPD Base
Elevation )
Figure 3.14 Contours of
Cumulative Mitigated 10th Highest Daily FSP Concentration at 1.5 mAG (60.3 mPD
Base Elevation)
Figure 4.1 All Noise
Sensitive Receivers within Assessment Area
Figure 4.2 Represetative
Noise Senstive Receivers during Construction Phase
Figure 4.3 Represetative
Noise Senstive Receivers during Operation Phase
Figure 5.1 Represetative
Water Senstive Receivers
Figure 5.2 Location
of EPD’s Water Quality Monitoring Stations
Figure 6.1 Location
of Proposed Stockpiling Area
Figure 7.1 Assessment
Area of the Land Contamination Assessment
Figure 8.1 Habitat
Map and Species of Conservation Interest (Preferred Option) (Key Plan)
Figure 8.1a Habitat Map
and Species of Conservation Interest (Preferred Option) (Sheet 1 of 4)
Figure 8.1b Habitat Map
and Species of Conservation Interest (Preferred Option) (Sheet 2 of 4)
Figure 8.1c Habitat Map
and Species of Conservation Interest (Preferred Option) (Sheet 3 of 4)
Figure 8.1d Habitat Map
and Species of Conservation Interest (Preferred Option) (Sheet 4 of 4)
Figure 8.2 Habitat
Loss within Project Site (Key Plan)
Figure 8.2a Habitat Loss
within Project Site (Sheet 1 of 4)
Figure 8.2b Habitat Loss
within Project Site (Sheet 2 of 4)
Figure 8.2c Habitat Loss
within Project Site (Sheet 3 of 4)
Figure 8.2d Habitat Loss
within Project Site (Sheet 4 of 4)
Figure 9.1a Review of
Planning and Development Framework
Figure 9.1b Review of
Planning and Development Frameworks (Blow-up)
Figure 9.2a Landscape
Resources
Figure 9.2b Landscape
Resources (Blow-up)
Figure 9.3a Photographs
of Landscape Resources (1 of 7)
Figure 9.3b Photographs
of Landscape Resources (2 of 7)
Figure 9.3c Photographs
of Landscape Resources (3 of 7)
Figure 9.3d Photographs
of Landscape Resources (4 of 7)
Figure 9.3e Photographs
of Landscape Resources (5 of 7)
Figure 9.3f Photographs
of Landscape Resources (6 of 7)
Figure 9.3g Photographs
of Landscape Resources (7 of 7)
Figure 9.4a Landscape
Character Areas
Figure 9.4b Landscape
Character Areas (Blow-up)
Figure 9.5 Photography
of Landscape Character Areas
Figure 9.6a Visual
Envelope and Visually Sensitive Receivers During Construction Phase
Figure 9.6b Visual
Envelope and Visually Sensitive Receivers During Operation Phase
Figure 9.7a Photographs
of Visually Sensitive Receivers (VSR) (1 of 2)
Figure 9.7b Photographs
of Visually Sensitive Receivers (VSR) (2 of 2)
Figure 9.8a Photomontage
VP1
Figure 9.8b Photomontage
VP2
Figure 9.8c Photomontage
VP3
Figure 9.9 Compensatory
Planting Locations
Figure 9.10a Landscape and
Visual Mitigation Plan (Sheet 1 of 2)
Figure 9.10b Landscape and
Visual Mitigation Plan (Sheet 2 of 2)
Figure 9.11 Conceptual
Section
List of Appendices
Appendix 2A Construction Programme
Appendix 3A Calculation
of Emission Factor (Unmitigated Scenario)
Appendix 3B Not
Used
Appendix 3C EMFAC
Traffic Emission Factor
Appendix 3D Calculation
of Vehicular Emission
Appendix 3E Calculation
of Lion Rock Tunnel Portal Emission Factor
Appendix 3F Emission
Inventory
Appendix 3G Details of
Surface Characteristics
Appendix 3H Result of
Cumulative Dust Emission Concentration (Unmitigated Scenario)
Appendix 3I Calculation
of Emission Factor (Mitigated Scenario)
Appendix 3J Result
of Cumulative Dust Emission Concentration (Mitigated Scenario)
Appendix 4A All Noise
Sensitive Receivers within Assessment Area and Photos of Existing
Representative Noise Sensitive Receivers
Appendix 4B Not
Used
Appendix 4C Construction
Noise Calculation for Unmitigated Scenario
Appendix 4D Determination
of Maximum Permissible SWL for Fixed Plant Noise
Appendix 4E Construction
Noise Calculation for Mitigated Scenarios 1 and 2
Appendix 4F Cumulative
Construction Noise Impact
Appendix 4G Cumulative
Operation Noise Impact
Appendix 7A Historical
Aerial Photo
Appendix 7B Representative
Photos of Existing Site Condition
Appendix 7C Site
Walkover Checklist
Appendix 7D Correspondences
with Government Departments
Appendix 8A Representative
Survey Photo and Survey Data
Appendix 9A Broad
Brush Tree Survey Schedule
Appendix 11A Project
Implementation Schedule
Appendix 13A Summary of
Environmental Impact
Appendix 13B Key
Assessment and Limitation of Assessment Methodologies